R I C H M O N D
|
|
- Marybeth Carson
- 5 years ago
- Views:
Transcription
1 R I C H M O N D I C H M O N D P I P E L I N E Planning No Project No. UI105 Project Status Design (as at January 2011) Project Description In 2005 the Richmond Municipality requested that Umgeni Water consider supplying potable water to the town of Richmond as the existing water supply systems were proving problematic and unsustainable. Umgeni Water has thus proposed the construction of a pipeline from its 61 Pipeline system to serve the town. The project will serve the potable water demands of the greater Richmond area (initially 8.3Ml/day and ultimately 14 Ml/day) and will also tie into Umgeni Water s existing Thornville sub-system (Section 5.2.1), which is currently served from the Thornville Pump Station situated on the 61 Pipeline between ED2 and Umlaas Road. The project will be fed off the 61 Pipeline downstream of the ED4 take-off. A new pump station is required to lift the water to a new reservoir (Liliefontein Reservoir) sited near Thornville. The proposed Richmond Pipeline will run along the R56 main road to Richmond (Figure 7.14). The existing Thornville Pump Station will be decommissioned and the rising main with revert to a back feed gravity main once the Richmond Pipeline is in operation. The pipeline will terminate at the municipal reservoir that serves Richmond. Key information on this project is summarised in Table Table 7.15 Project information: Richmond Pipeline. Project Components: Capacity: m long section of 450 mm diameter pipeline and a new booster pump station. 27 Ml/day. Institutional Arrangements nts Umgeni Water will own, operate and maintain the Richmond Pipeline infrastructure and will sell potable water from this system to The Msunduzi Municipality and Umgungundlovu District Municipality as per existing bulk water supply agreements. Beneficiaries ies The consumers in The Msunduzi Municipal area and in the Richmond Municipality will benefit from this project. Implementation The construction duration of this project is anticipated to be two years. The total cost is anticipated to be R 181 million at 2010 prices. 366
2 Figure 7.14 General layout of the Richmond Pipeline. 367
3 U M L A A S M L A A S R O A D R E S E R V O I R U P G R A D E Planning No Project No. Project Status Design (as at January 2011) Project Description Umlaas Road Reservoir initially served as balancing storage for the Umlaas Road WTP. The WTP was decommissioned in 2002 as sufficient potable water could be transferred to the Umlaas Road demand node via the 61 Pipeline. The reservoir complex was retained and currently serves the Outer Western areas of ethekwini Municipality via the 57 Pipeline and the Eston/Umbumbulu and Lion Park pipelines. The reservoir site is situated to the east of the N3 National Road, just north of the N3-R603 interchange (Figure 7.15). The reservoir complex consists of two separate reservoirs, viz. the original 9 Ml reservoir and a later 45 Ml reservoir. The reservoir complex currently serves as both a break pressure and balancing storage facility and can be supplied from Midmar WTP via the 61 Pipeline and from D.V. Harris WTP via the recommissioned 53 Pipeline. It is necessary to provide at least 15 hours of balancing storage at Umlaas Road in order to cope with the peak demands placed on the supply system by the downstream consumers. It is therefore recommended that an additional 45 Ml reservoir be constructed in advance of the commencement of the proposed Western Aqueduct load transfer in This will ensure that there is sufficient storage in place to accommodate the load transfer until at least 2022, by which time the Western Aqueduct demand should have been transferred across to the Mkomazi Water Project (Section 7.2.1). Key information on this project is summarised in Table Table 7.16 Project information: Umlaas Road Reservoir Upgrade. Project Components: Capacity: New 45 Ml reservoir. 45 Ml. Institutional Arrangements Umgeni Water will build, own, operate and maintain all water supply infrastructure pertaining to this project. Beneficiaries The upgrade to the Umlaas Road Reservoir Complex will benefit all consumers downstream of the reservoir. These beneficiaries are primarily the ethekwini Municipality, but also include consumers within the Mkhambathini Municipal areas of Umgungundlovu District Municipality. Implementation The construction duration of this project is anticipated to be one year. The total cost is estimated to be R 81 million at 2010 prices. 368
4 Figure 7.15 General layout of the Umlaas Road Reservoir Upgrade. 369
5 G R E A T E R R E A T E R E S T O N B U L K W A T E R S U P P L Y S C H E M E Planning No Project No. Project Status Design (as at January 2011) Project Description The Greater Eston area falls within Wards 4 to 7 in the Mkhambathini Local Municipality and Ward 5 and 7 of the Richmond Local Municipality. These local municipalities fall within the jurisdiction of the umgungundlovu District Municipality (UMDM). The bulk water supply to the Greater Eston area as depicted in Figure 7.16 requires three off-takes on the Eston-Umbumbulu Pipeline. The first off-take will supply the umacalagwala area. The second off-take will supply the following areas: Esigodini/Gulube Ismont Mpangisa Embuthweni Inhlazuka Ukhalo The third off-take will supply the Ogagwini area. Key information on this project is summarised in Table Table 7.17 Project information: Greater Greater Eston BWSS. Project Components: Capacity: 19km of 350mm diameter pipe 16km of 200mm diameter pipe 19km of 160mm diameter pipe 14km of 110mm diameter pipe 1 Break Pressure Tank 3.5 Ml Reservoir 2 Pump Stations Scheme to accommodate ultimate demand of 4.4 Ml/day Institutional Arrangements The scheme is jointly funded by DWA, Umgeni Water and Umgungundlovu District Municipality through its MIG allocation. The proposed scheme will be operated and maintained by Umgeni Water. Bulk water contracts will be entered into with Umgungundlovu District Municipality. 370
6 Figure 7.16 Greater Eston Bulk Water Supply 371
7 Beneficiaries The beneficiaries of this scheme are shown in Table Table 7.18 Beneficiaries for the Proposed Greater Eston BWSS. Area Current Population WARD 4 - Mkhambathini 1,544 WARD 5 - Mkhambathini 5,912 WARD 6 - Mkhambathini 7,400 WARD 7 - Mkhambathini 9,448 WARD 5 & 7 - Richmond 16,936 TOTAL 41,240 Using an allocation of 60 l/c/day, with a population growth of 0.5% to 2.5% over the 30-year planning horizon, the long term demand is estimated to be 4.4 Ml/day. Implementation The project is currently at design and tender stage. Construction is expected to begin in the first quarter of It is envisaged that the project will take 3 to 4 years to implement. 372
M A N Y A V U
7. 4. 1 2 M A N Y A V U A N Y A V U P I P E L I N E Planning No. 105.25 Project No. Project Status Construction (as at January 2011) Project Description The rural community of Manyavu is situated in the
More informationI P E L I N E : M I D M A R I D M A R D A M T O M I D M A R
7. 4 M G E N I G E N I S Y S T E M 7. 4. 1 2 5 1 R A W A W W A T E R P I P E L I N E Planning No. 105.0 Project No. Project Status Design (as at January 2011) I P E L I N E : M I D M A R I D M A R W T
More informationTime (hours) TOTAL STORAGE REQUIREMENT 6.99
7 Ml (Table 5.28) of storage is required at Wartburg Reservoir to accommodate demands in 2020. Table 5.28 Storage Requirement at Wartburg Reservoir. Reservoir Function 2020 Demand (Ml/day) Time (hours)
More information5.2.1 Upper Mgeni System
5.2.1 Upper Mgeni System Description The Upper Mgeni System currently serves urban, peri-urban and rural settlements within the Umgungundlovu, Msunduzi and ethekweni (Outer West) municipal areas (Figure
More informationThe Mgeni System is an integrated water resources and potable bulk water distribution system comprising of two major sub-systems, viz.
5. 2 M G E N I G E N I S Y S T E M The Mgeni System is an integrated water resources and potable bulk water distribution system comprising of two major sub-systems, viz. The Upper Mgeni System (also referred
More informationTable 7.25 Project information: South Coast Augmentation Booster Pump Station. New in-line booster pump station. 120 Ml/day.
7. 6 S O U T H 7. 6. 1 S O U T H O U T H C O A S T S Y S T E M O U T H C O A S T A U G M E N T A T I O N B O O S T E R P U M P S T A T I O N Planning No. 305.6 Project No. Project Status Construction (as
More informationS T A T U S. Figure 5.60 Water demand from Hazelmere WTP. Average Daily Sales (Ml/day) Month. Dec-07. Oct-05. Jan-09. Apr-12. Mar-11.
5. 5. 2 S T A T U S T A T U S Q U O A N D L I M I T A T I O N S Figures 5.56 and 5.64 (schematically) illustrate the North Coast System in its current configuration and the current demands being placed
More information5.2.2 Lower Mgeni System
5.2.2 Lower Mgeni System Description The Lower Mgeni System (Figure 5.7 and Figure 5.8) serves the greater ethekwini Municipal area from lower Pinetown/KwaDabeka in the west, to Phoenix/Inanda/Verulam
More informationMEMORANDUM Managing Water for Life Date: 15 September 2016
MEMORANDUM Managing Water for Life Date: 15 September 2016 Subject: WARTBURG TO BRUYNSHILL PIPELINE INFORMATION 1. BACKGROUND Umgeni Water is a Bulk Water Provider to Umgungundlovu District Municipality
More information6.2 Umgeni Water Owned Wastewater Works
6. WASTEWATER 6.1 Overview Umgeni Water owns and operates the Darvill and Ixopo Wastewater Works (WWW), but manages a number of other WWW on behalf of Municipalities. Management contracts are in place
More informationThis section documents Umgeni Water s water demand forecast review that was completed in September This process:
3. DEMAND FORECASTS This section documents Umgeni Water s water demand forecast review that was completed in September 2016. This process: Reviewed the figures for the financial year ending in June 2016
More information9. CREATING VALUE ANNUAL REPORT 2011/
9. CREATING VALUE ANNUAL REPORT 211/212 61 9. CREATING VALUE CONTINUED... 9.1 9.1 PRODUCT QUALITY Management Approach Umgeni Water views the quality of potable water as paramount to its business sustainability
More information7.5 Lower Mgeni System
7.5 Lower Mgeni System 7.5.1 emaphephetheni WTP Upgrade Planning No. 106.0 Project No. UI49A Project Status Construction phase (as of January 2012) Project Description The emaphephetheni Water Treatment
More informationTable 5.51 Reservoirs to be supplied off the South Coast Pipeline Phase 1.
Lower South Coast Sub-Region The Lower South Coast sub-region is supplied with bulk treated water from the Bhobhoyi WTP (54 Ml/day), located 8 km inland of Port Shepstone and from the Mtamvuma WTP (20
More informationCreating Value PRODUCT QUALITY MANAGEMENT APPROACH POTABLE WATER QUALITY PERFORMANCE
62 UMGENI WATER AMANZI ANNUAL 2014/2015 PG 04-05 2.0 ORGANISATIONAL PG 06-15 3.0 CHAIRPERSON S PG 16-23 4.0 CHIEF EXECUTIVE S PG 24-31 5.0 CORPORATE GOVERNANCE PG 32-47 6.0 STAKEHOLDER UNDERSTANDING AND
More information8.O CREATING VALUE 54 UMGENI WATER AMANZI
8.O CREATING VALUE 54 UMGENI WATER AMANZI 8.1 PRODUCT QUALITY MANAGEMENT APPROACH The most signifi cant impact of Umgeni Water s business is provision of water that does not impact negatively on consumer
More information6. WASTEWATER. 6.1 Overview. 6.2 Darvill Wastewater Works
6. WASTEWATER 6.1 Overview Umgeni Water currently owns and operates the Darvill and Ixopo Wastewater Works (WWW). The Howick and Lynnfield Park WWW are operated for umgungundlovu District Municipality
More information6 WASTEWATER. 6.1 Overview. 6.2 Darvill Wastewater Works
6 WASTEWATER 6.1 Overview Umgeni Water currently owns and operates the Darvill and Ixopo Wastewater Works (WWWs). It also operates the Howick WWW for umgungundlovu District Municipality under a management
More informationPerformance Scorecards for 2009/2010
Scorecards for Creating Value for Customers Outcome Exceed Customer Product Expectations Quality Growth / Increase Customer Base Resiliency Optimisation Customer Satisfaction Infrastructure Stability The
More information5.5 North Coast System
5.5 North Coast System 5.5.1 Description The North Coast System comprises of the Mdloti System, the Lower Mvoti System and the Lower Thukela System (Figure 5.57). These systems have been grouped together
More informationSOCIO-ECONOMIC GROWTH AND SERVICE DELIVERY TOWARDS RURAL DEVELOPMENT. Umgeni Water s Activities in Support of DWAF Strategies
SOCIO-ECONOMIC GROWTH AND SERVICE DELIVERY TOWARDS RURAL DEVELOPMENT Umgeni Water s Activities in Support of DWAF Strategies Presentation to Portfolio Committee on Water Affairs and Forestry Strategic
More informationB A C K G R O U N P R O P O S E D P R O J E C T
4. 5 W A S T E W A T E R A S T E W A T E R R E U S E 4. 5. 1 B A C K G R O U N A C K G R O U N D A N D E X I S T I N G I N F R A S T R U C T U R E The reuse or reclamation of wastewater not only improves
More informationDHI 2016 ANNUAL CONFERENCE
DHI 2016 ANNUAL CONFERENCE Managing Drought The Umgeni Water Experience 18 April 2016 Percy Sithole Water Resources Planning Population Density Current Water Resources Mearns Weir Spring Grove Dam Albert
More informationHamilton City Water Distribution System Strategic Planning
Hamilton City Water Distribution System Strategic Planning Weijun Zhang Hamilton City Council, Private Bay 3010, Hamilton, New Zealand zhangw@dhicn.com, www.hcc.govt.nz ABSTRACT Hamilton s present water
More information7. WASTEWATER. 7.1 Overview. 7.2 Umgeni Water Owned Wastewater Works Darvill Wastewater Works
7. WASTEWATER 7.1 Overview Figure 7.1 illustrates the location of the wastewater works Umgeni Water operates in relation to the existing water system configurations discussed in Section 6. Umgeni Water
More information5.5 North Coast System
5.5 North Coast System 5.5.1 Description The North Coast System comprises of the Mdloti System, the Lower Mvoti System and the Lower Thukela System (Figure 5.57). These systems have been grouped together
More informationSINAYO SECURITIES UBS WATER SUMMIT WATER INFRASTRUCTURE DEVELOPMENT. Protea Hotel Breakwater Lodge 25 February 2016
SINAYO SECURITIES UBS WATER SUMMIT WATER INFRASTRUCTURE DEVELOPMENT Protea Hotel Breakwater Lodge 25 February 2016 2 Agenda 1 2 3 4 Section 1 Section 2 Section 3 Section 4 WATER SECTOR VALUE CHAIN GROUP
More informationOrganisational LEGISLATIVE MANDATE UMGENI WATER 2.2 ACTIVITIES OF
2.0 Organisational Pro le 2.1 LEGISLATIVE MANDATE Umgeni Water is a public entity established in 1974 to provide water services - water supply and sanitation services - to other water services institutions
More information4.4.4 Mooi/Mgeni Region
4.4.4 Mooi/Mgeni Region The Mooi/Mgeni region comprises of the two tertiary catchments of U20 (umngeni River) and V20 (Mooi River) (Figure 4.22). The major urban centres of Durban and Pietermaritzburg
More informationBroken Hill Water Supply. Hendrik Van Rhijn
Broken Hill Water Supply Hendrik Van Rhijn Public Works Advisory Who are we? We are the NSW Government s key advisor for large water infrastructure projects and complex water programs and portfolios. We
More informationPROPOSED CAPACITY UPGRADES TO THE N3 FROM LYNNFIELD PARK (KM 30.6) TO GLADYS MANZI (FORMERLY MURRAY) ROAD (KM 6.1) (DEA REF NO: 14/12/16/3/3/1/1966)
23 October 2018 Ms Zama Hadebe For Attention Thulani Mbokdo Department of and Sanitation (Licensing) PO Box 1018 Durban 4000 Dear Ms Hadebe, PROPOSED CAPACITY UPGRADES TO THE N3 FROM LYNNFIELD PARK (KM
More informationSchedule B Municipal Class Environmental Assessment Potable Water Storage
Schedule B Municipal Class Environmental Assessment Potable Water Storage Town Meeting: Phase 2 Status Update J.L. Richards & Associates Limited Sarah Gore, P.Eng., Project Manager Date: May 22, 2018 JLR
More informationHydropower from pressurized conduits Energy generation from distribution systems Research project
Energy generation from distribution systems Research project P1-1 Layout of the presentation Introduction Project team and collaborating organisations Study aims Deliverables/products Budget Bloemwater
More informationENVIRONMENTAL IMPACT ASSESSMENT (BASIC ASSESSMENT) PROCESS: PROPOSED REVERSE OSMOSIS PLANT, IRON ORE HANDLING FACILITY, PORT OF SALDANHA
ENVIRONMENTAL IMPACT ASSESSMENT (BASIC ASSESSMENT) PROCESS: PROPOSED REVERSE OSMOSIS PLANT, IRON ORE HANDLING FACILITY, PORT OF SALDANHA BACKGROUND INFORMATION DOCUMENT SRK Project 364470/42G June 2007
More informationMayfield West Phase Two Secondary Plan Water and Wastewater Servicing Study Part A Report Town of Caledon
Water and Wastewater Servicing Study Part A Report Town of Caledon Prepared by 170 Steelwell Road Suite 200 Brampton ON L6T 5T3 Canada File No: MTB 15608 The material in this report reflects best judgement
More informationCommunity Sustainability
Community Sustainability R ural Development Umgeni Water has firmly committed to government s strategic priorities through providing sustainable water services that would reduce backlogs in local municipalities
More informationSection 5 - Planning Criteria. Section 5
Section 5 - Planning Criteria Section 5 SECTION 5 PLANNING CRITERIA This section presents the design criteria and methodologies for analysis used to evaluate the existing distribution system and its facilities
More informationStorage and pumping capacity analysis using hydraulic modeling
Storage and pumping capacity analysis using hydraulic modeling G. MacPherson City of Chilliwack, B.C., Canada W. de Schaetzen & S. Cripps GeoAdvice Inc., Vancouver, B.C., Canada ABSTRACT: This paper summarizes
More informationDUBAI ELECTRICITY AND WATER AUTHORITY GUIDELINES FOR NEW DEVELOPMENT PROJECTS UPDATE
DUBAI ELECTRICITY AND WATER AUTHORITY GUIDELINES FOR NEW DEVELOPMENT PROJECTS UPDATE - 2010 POWER & WATER PLANNING (WATER TRANSMISSION PLANNING) DUBAI ELECTRICITY AND WATER AUTHORITY WATER TRANSMISSION
More information2. ORGANISATIONAL PROFILE AND GOVERNANCE
2. ORGANISATIONAL PROFILE AND GOVERNANCE 2.1 LEGISLATIVE MANDATE Umgeni Water is a public entity established in 1974 to provide water services - water supply and sanitation services - to other water services
More informationMontara Water and Sanitary District 2011 New Customer CIP and Water Capacity Charge. Presentation to Board April 21, 2011
Montara Water and Sanitary District 2011 New Customer CIP and Water Capacity Charge Presentation to Board April 21, 2011 PRESENTATION OUTLINE Master Plan Overview Purpose and Approach Supply and Demand
More informationBloemwater Conduit Hydropower Plant launched
Bloemwater Conduit Hydropower Plant launched Marco van Dijk Department of Civil Engineering University of Pretoria marco.vandijk@up.ac.za On 31 March 2015 the Minister of Water and Sanitation, Nomvula
More informationOUTLINE SERVICES SCHEME REPORT (WATER AND SEWER)
OUTLINE SCHEME REPORT (WATER AND SEWER) 327043 HOLDING 263, WILLOWGLEN AGRICULTURAL HOLDINGS Issue 1 SHELL SUMMIT ROAD PROPOSED FILLING STATION ON THE REMAINING EXTENT OF PORTION 123 (A PORTION OF PORTION
More informationTHE USE OF HYDRAULIC TRANSIENT MODELLING IN THE DESIGN OF RESILIENT PIPELINES
THE USE OF HYDRAULIC TRANSIENT MODELLING IN THE DESIGN OF RESILIENT PIPELINES Alistair Hancox, Grant Pedersen Harrison Grierson Consultants Limited ABSTRACT Pressure surges during the start up, shut down,
More informationYorkton Rona Commercial and Industrial development. Concept Plan and Serviceability Report
Yorkton Rona Commercial and Industrial development Concept Plan and Serviceability Report Prepared for: 101242326 Sask Ltd. Box Ft Quappelle, SK Canada S0G 1S0 Prepared by: Stantec Consulting Ltd. 302-1345
More informationTHE GREAT DROUGHT OF 1895
THE GREAT DROUGHT OF 1895 VISION; To be a provider of sustainable, universally competitive water and sanitation solutions for Africa MISSION; To deliver and supply world class affordable, reliable and
More informationBARRABA WATER SUPPLY. Construction of Split Rock Dam Pipeline and Ancillary Works
BARRABA WATER SUPPLY Construction of Split Rock Dam Pipeline and Ancillary Works Long history of unreliable water supply Water restrictions in place 50% of time over 10 years to 2012 Various studies looked
More informationGeorgetown Water Storage Class Environmental Assessment Study
Georgetown Water Storage Class Environmental Assessment Study Public Information Centre Cedarvale Community Centre 181-185 Main Street South Thursday, September 4th, 2008 6:30 p.m. 8:30 p.m. Why are we
More informationINNISFIL WATER AND WASTEWATER MASTER SERVICING PLAN UPDATE
INNISFIL WATER AND WASTEWATER MASTER SERVICING PLAN UPDATE Water and Wastewater Servicing Alternatives Public Information Meeting No. 2 March 20, 2018 1 MSP Update Objectives Develop water and wastewater
More informationSTAKEHOLDER UNDERSTANDING AND SUPPORT
7.0 INTERACTION One of the key Strategic Objectives of Umgeni Water is to increase customer and stakeholder value. In pursuance of this, customer and stakeholder interaction is a vital component. As a
More informationEl Margarita Development Analysis
303 Second Street, Suite 300 South San Francisco, California 94107 415-243-2150 FAX: 415-896-0999 El Margarita Development Analysis 28 January 2015 Prepared for City of Yuba City 1201 Civic Center Boulevard
More informationEWS Planning of Water and Sanitation
EWS Planning of Water and Sanitation 13/02/2015 Strategic Objectives Legislation driving the business plan Time horizon Long term, medium term and short term plan in terms in terms of legislated submission
More informationInfrastructure Master Plan / /2048 Volume 1. Improving Quality of Life and Enhancing Sustainable Economic Development
Infrastructure Master Plan 2017 2017/2018 2047/2048 Volume 1 Planning Services, Engineering and Scientific Services Division, Umgeni Water PO Box 9, Pietermaritzburg, 3200, KwaZulu-Natal, South Africa
More informationWATER MAIN EXTENSION DESIGN REQUIREMENTS
This guideline provides minimum requirements for the design of new water main extensions. This guide is not to be used as a substitution for the detailed design of the water system. The Developer s Engineer
More informationAfrican Utility Week Reducing Non-Revenue Water in the Durban Central Business District
African Utility Week Reducing Non-Revenue Water in the Durban Central Business District Mark Shepherd PrEng JOAT Consulting Background to Programme: Durban home to approximately 3,5 million 12 000km of
More informationPROPOSED LIBODE & NGQELENI BULK WATER SUPPLY CONVEYANCE CORRIDORS OR TAMBO DISTRICT MUNICIPALITY, EASTERN CAPE
PROPOSED LIBODE & NGQELENI BULK WATER SUPPLY CONVEYANCE CORRIDORS OR TAMBO DISTRICT MUNICIPALITY, EASTERN CAPE Background Information Document DEDEA Ref No s: EC 155/ORT/LN1&LN2/M/13 34 EC 157/ORT/LN1&LN3/M/13
More information4 PROJECT ALTERNATIVES
4 PROJECT ALTERNATIVES 4.1 Introduction In terms of the EIA Regulations published in Government Notice R543 of 2 August 2010 in terms of Section 24 of the National Environmental Management Act (Act No.
More informationBURKE WATER STATION TREATMENT, PUMPING AND STORAGE CLASS ENVIRONMENTAL ASSESSMENT
Welcome to the City of Guelph BURKE WATER STATION TREATMENT, PUMPING AND STORAGE CLASS ENVIRONMENTAL ASSESSMENT PUBLIC INFORMATION CENTRE NO. 1 Wednesday, November 7, 2012 from 6:30 PM to 8:30 PM Please
More information2.0 STAKEHOLDER UNDERSTANDING AND SUPPORT PG REPORT PROFILE ORGANISATIONAL PROFILE ORGANISATIONAL PROFILE PG 8-17 PG
8 ANNUAL PG 6-7 1.0 MINISTER S FOREWORD PG 18-21 3.0 CHAIRPERSON S PG 22-27 4.0 CHIEF EXECUTIVE S PG 28-35 5.0 CORPORATE GOVERNANCE PG 36-51 6.0 AND SUPPORT PG 52-57 7.0 Organisational Profile 2.1 LEGISLATIVE
More informationSUMMIT PRESENTATION. Presented by: MS B. MSANE. Date: 26 MAY Presented by: Name Surname Directorate. Date
MUNICIPAL PRESENTATION INFRASTRUCTURE TITLE SUMMIT PRESENTATION Presented by: Name Surname Directorate Date Presented by: MS B. MSANE Date: 26 MAY 2016 Contents 1. INTRODUCTION 2. MTEF ALLOCATIONS 3. REGIONAL
More informationEFFLUENT REUSE AT EAST LISMORE WASTEWATER TREATMENT WORKS
EFFLUENT REUSE AT EAST LISMORE WASTEWATER TREATMENT WORKS Jeremy Silk Project Engineer, Lismore Water, NSW Janaka Weeraratne A/Manager, Lismore Water, NSW Summary The East Lismore Wastewater Treatment
More informationThe West East Link Main is a 125 million pipeline project that will carry water across the North West of England
West East Link Main 55km pipeline, carrying 100 million litres, is one of the largest ever undertaken by a water company by Jon Higham The West East Link Main is a 125 million pipeline project that will
More informationWELL, WELL, WELL DRIFT WELL RECOMISSIONING, AN OPERATORS PERSPECTIVE. Adrian Cameron. Tamworth Regional Council
WELL, WELL, WELL DRIFT WELL RECOMISSIONING, AN OPERATORS PERSPECTIVE Paper Presented by: Adrian Cameron Author: Adrian Cameron, Team Leader Water Headworks, Tamworth Regional Council 3 rd Annual WIOA NSW
More informationYES WE CAN! Volume 2. Presented By: Joe Taranto
Volume 2 Presented By: Joe Taranto Universal Water Recycling 37 Moon Mountain Drive Mount View NSW 2325 universalwaterrecycling@hotmail.com www.uwr.com.au Option One Option Two Tillegra Dam Desalination
More informationRethinking wastewater treatment A new type of wastewater treatment plant is gaining a foothold in South Africa, Dominic Uys finds out more.
Rethinking wastewater treatment A new type of wastewater treatment plant is gaining a foothold in South Africa, Dominic Uys finds out more. MUNICIPAL VISIT At the new Wemmmershoek wastwater treatment plant
More informationPIGGING OF THE O SHANNASSY OUTLET MAINS. Paul Balassone. Melbourne Water
PIGGING OF THE O SHANNASSY OUTLET MAINS Paper Presented by : Paul Balassone Authors: Paul Balassone, Senior Asset Engineer, Infrastructure Ian Smith, Technical Specialist, Water Supply Operations, Melbourne
More informationUsing Hydraulic Modeling to Determine Viable Emergency Water Supply Options for the City Of San Francisco s Largest Reservoir and Pressure Zone
Using Hydraulic Modeling to Determine Viable Emergency Water Supply Options for the City Of San Francisco s Largest Reservoir and Pressure Zone October 28, 2015 Presented by: Brian Barry, SFPUC Karen Chu,
More informationTown of New Tecumseth. Water Distribution and Storage Master Plan April 2007
Town of New Tecumseth Water Distribution and Storage Master Plan April 2007 Town of New Tecumseth Water Distribution and Storage Master Plan Executive Summary The Water Distribution and Storage Master
More informationWashburn Booster Pumping Station Expansion and Upgrades Project Update November 2012
Washburn Booster Pumping Station Expansion and Upgrades Project Update November 2012 Project Background The Washburn Booster Pumping Station serves as a central water distribution facility and provides
More informationTOWN OF AURORA DRINKING WATER QUALITY ANNUAL REPORT
TOWN OF AURORA DRINKING WATER QUALITY ANNUAL REPORT JANUARY 1 TO DECEMBER 31, 2009 New Regulations Amendments to Ontario Regulation 170/03 came into effect on June 5, 2006. The provincially mandated amendments
More informationA Report on Reduction of Non Revenue Water in Kundapura Municipal Water Supply
A Report on Reduction of Non Revenue Water in Kundapura Municipal Water Supply Town Municipal Council Kundapura Udupi (Dist) Ph: 08245-230410 Fax: 08254-230410 E-Mail: co_kundapur@yahoo.co.in (1) Background
More informationPOTABLE WATER COAGULANT TRIALS UTILIZING POLYALUMINIUM CHLORHYDRATE. Michael Dalton. Toowoomba City Council
POTABLE WATER COAGULANT TRIALS UTILIZING POLYALUMINIUM CHLORHYDRATE Paper Presented by: Michael Dalton Author: Michael Dalton, Rockhampton City Council, Toowoomba City Council 33rd Annual Qld Water Industry
More informationCOLLECTION AND DISTRIBUTION OF WATER
COLLECTION AND DISTRIUTION OF WATER Addis Ababa University Addis Ababa Institute of Technology Department of Civil Engineering Collection and Distribution of Water Deals with the transport of water from
More informationStakeholder Understanding and Support
6.0 Stakeholder Understanding and Support Stakeholder Interaction In the course of execution of its mandate, Umgeni Water interacts with a wide array of stakeholders who are impacted on or have an interest
More informationSection 1 - Introduction...7. Section 2 - Raw Water Supply Section 3 - Water Treatment Section 4 - Water Distribution System...
Table of Contents Section 1 - Introduction...7 1.1 Population Growth...7 1.1.1 Service Area...7 1.1.2 Past Population...7 1.1.3 Projected Population Growth...9 1.2 Water Demands...9 1.2.1 Past Water Demands...9
More informationNRW REDUCTION STRATEGY
NRW REDUCTION STRATEGY PREAMBLE : Potable water is becoming scarcer; often making it more energy intensive to procure. More energy is required to pump water to greater distances and from deeper depth in
More informationRefurbishment of Emalahleni Bulk Scheme
Refurbishment of Emalahleni Bulk Scheme Sedimentation tank Rapid Gravity Sand Filter Hartbeespoort Dam Integrated Biological Remediation Programme CLIENT: DWA Gauteng SCOPE: Rand Water is appointed by
More informationHorizon 2020 Steering Committee Water and Wastewater Master Plan Overview
Horizon 2020 Steering Committee Water and Wastewater Master Plan Overview August 11, 2014 Let s Look at the Numbers Water System 2 - Raw Water Sources Clinton Reservoir Kansas River 2 - Water Treatment
More informationThe table below highlights some of the important achievements in this regard: Commissioning of New Water Treatment Plants/Pumping Stations
Water Supply Improving water supply for the city has been a major focus area for KMC during the past few years. This has involved augmenting piped water supply through commissioning of water treatment
More informationTechnical Overview KZN Water Service Delivery Backlogs
Technical Overview KZN Water Service Delivery Backlogs Presented by Viv Naidoo Acting Director Water Sector Support Water Services Master Class # 2 11-12 July 2012 Durban Situational Analysis Global Location
More informationCOMPANY PROFILE CIVIL ENGINEERING CONSTRUCTION, GENERAL BUILDING & PROJECT MANAGEMENT
COMPANY PROFILE CIVIL ENGINEERING CONSTRUCTION, GENERAL BUILDING & PROJECT MANAGEMENT TABLE OF CONTENTS 04 AFFILIATIONS 05 ABOUT US 06 STAFF & EQUIPMENT 07 SERVICES 08-20 CIVILS 21-22 INDUSTRIAL CIVILS
More informationIntegrated waste management using biogas in a decentralised Municipal framework
Integrated waste management using biogas in a decentralised Municipal framework COMPETE & RE-Impact Workshop Bioenergy for Rural Development in Africa and Asia Congress Centre, Hamburg, Germany 30 June
More informationCity of Crosby, ND Municipal Infrastructure Needs Assessment September 2012
City of Crosby, ND Municipal Infrastructure Needs Assessment September 2012 Project made possible by US Dept. of HUD Regional Substantiality Planning Grant and ND Energy Development Infrastructure and
More informationMOROGORO URBAN WATER SUPPLY AND SANITATION AUTHORITY
MOROGORO URBAN WATER SUPPLY AND SANITATION AUTHORITY MONTH: DECEMBER, 2012 A: IMPLEMENTATION OF WATER SECTOR DEVELOPMENT PROGRAMME (WSDP) PROJECTS Introduction Under Water Sector Development Programme,
More informationAbstract. Environmental Impact Statement (EIS) Scoping Report
Abstract On 1 st January 2014, Irish Water assumed responsibility for managing Ireland s water and wastewater investment and maintenance programmes. On that date, Irish Water also took over the management
More informationTOWN OF NEW TECUMSETH WATER SUPPLY, STORAGE AND DISTRIBUTION MASTER PLAN WELCOME
WELCOME PLEASE SIGN IN Public Information Centre, February 11, 2016, 5:30 pm to 8 pm Town of New Tecumseth Council Chambers, Alliston, ON The Town of New Tecumseth welcomes you to this Public Information
More informationEVALUATING NANOFILTRATION, REVERSE OSMOSIS, AND ION EXCHANGE TO MEET CONSUMPTIVE USE CONSTRAINTS AND FINISHED WATER QUALITY GOALS FOR BROWARD COUNTY
EVALUATING NANOFILTRATION, REVERSE OSMOSIS, AND ION EXCHANGE TO MEET CONSUMPTIVE USE CONSTRAINTS AND FINISHED WATER QUALITY GOALS FOR BROWARD COUNTY Frank A. Brinson, P.E., DEE, CDM, Fort Lauderdale, FL
More informationFrancisco Water. January 17, 2018
O San Francisco Water Services of the San Francisco Public Utilities Commission January 17, 2018 Honorable Board of Supervisors San Francisco City Hall 1 Dr. Carlton B Goodlett Place, Room #244 San Francisco,
More informationTongaat WWTW Water Use Licence Application. Draft Report Meeting 1 October 2015
Tongaat WWTW Water Use Licence Application Draft Report Meeting 1 October 2015 Agenda Welcome and purpose Public Participation Process Introduction ethekwini W&S Tongaat Waste Water Treatment Works A Water
More informationDESIGN OF 24X7 WATER SUPPLY SYSTEMS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 DESIGN OF 24X7 WATER SUPPLY SYSTEMS A Case study: Ahmedabad city 1 Swarup Varu and 2 Dipsha Shah 1 Graduate Student, 2 Professor School of Building Science
More informationProject Name: St. Johns River/Taylor Creek Reservoir
Project Name: St. Johns River/Taylor Creek Reservoir Project Location: Osceola and Orange counties Project Number: 126 Project Type: Surface Water Description of project: The proposed St. Johns River/Taylor
More information17.0 INFRASTRUCTURE AND ENERGY
17.0 INFRASTRUCTURE AND ENERGY The Project would place demands on the existing infrastructure systems for supplying water, treating sewage, providing energy and disposing of solid waste. The Project would
More information12.1 OPERATIONAL OPTIMISATION 12.0 ISO ACCREDITED LABORATORY SERVICES ASSURING WATER QUALITY
108 PG 6-7 ORGANISATIONAL PG 8-17 MINISTER S FOREWORD PG 18-21 CHAIRPERSON S PG 22-27 CHIEF EXECUTIVE S PG 28-35 CORPORATE GOVERNANCE PG 36-51 STAKEHOLDER UNDERSTANDING AND SUPPORT PG 52-57 1.0 2.0 3.0
More informationWaste Water Treatment Plant Location Options. Presented by: Ben Greenough, Superintendent of Public Works Date: April 3, 2017 In Camera Meeting
Waste Water Treatment Plant Location Options Presented by: Ben Greenough, Superintendent of Public Works Date: April 3, 2017 In Camera Meeting Sewer Study Review 2010 Sewage Treatment and Disposal Feasibility
More informationArnfield and Godley WTW s are located in Tameside, south east of Manchester and form part of the Longdendale
Arnfield and Godley WTW water quality improvements scheme for United Utilities by Martin Clark Arnfield and Godley WTW s are located in Tameside, south east of Manchester and form part of the Longdendale
More informationPREPARED FOR WELLINGTON CITY COUNCIL - CITY SHAPER 1 SEPTEMBER 2016 SHELLY BAY, WELLINGTON SERVICING FEASIBILITY
PREPARED FOR WELLINGTON CITY COUNCIL - CITY SHAPER 1 SEPTEMBER 2016 SHELLY BAY, WELLINGTON SERVICING FEASIBILITY COMMERCIAL IN CONFIDENCE All intellectual property rights, including copyright, in designs
More informationDRAFT MEMORANDUM OF UNDERSTANDING BETWEEN THE SAN FRANCISCO PUBLIC UTILITIES COMMISSION AND THE SAN FRANCISCO RECREATION AND PARK DEPARTMENT
DRAFT MEMORANDUM OF UNDERSTANDING BETWEEN THE SAN FRANCISCO PUBLIC UTILITIES COMMISSION AND THE SAN FRANCISCO RECREATION AND PARK DEPARTMENT FOR THE APPLICATION AND MANAGEMENT OF WATER USE EFFICIENCY PROGRAMS
More informationM.D. OF FOOTHILLS NO. 31
M.D. OF FOOTHILLS NO. 31 Strategy FINAL REPORT Revised March 31, 2010 (2210 026 00) Prepared by: March, 2010 EXECUTIVE SUMMARY The M.D. of Foothills No. 31 (MD) requires a Water, Wastewater and Stormwater
More informationMAGALIES WATER REQUEST FOR PROPOSAL RFP/MW/10/
Requesting Office: Head Office Contact Person: Mr T Mosete Contact Numbers: 014 597 4636 E-mail address: tenders@magalieswater.co.za MAGALIES WATER REQUEST FOR PROPOSAL RFP/MW/10/2019-20 PROFESSIONAL SERVICE
More informationCHAPTER 4 CAPITAL IMPROVEMENT PROGRAM
CHAPTER 4 CAPITAL IMPROVEMENT PROGRAM Various improvement projects were identified in Chapter 3. A brief description of each project selected for the 6-year and 20-year planning horizons is presented in
More information