R I C H M O N D

Size: px
Start display at page:

Download "R I C H M O N D"

Transcription

1 R I C H M O N D I C H M O N D P I P E L I N E Planning No Project No. UI105 Project Status Design (as at January 2011) Project Description In 2005 the Richmond Municipality requested that Umgeni Water consider supplying potable water to the town of Richmond as the existing water supply systems were proving problematic and unsustainable. Umgeni Water has thus proposed the construction of a pipeline from its 61 Pipeline system to serve the town. The project will serve the potable water demands of the greater Richmond area (initially 8.3Ml/day and ultimately 14 Ml/day) and will also tie into Umgeni Water s existing Thornville sub-system (Section 5.2.1), which is currently served from the Thornville Pump Station situated on the 61 Pipeline between ED2 and Umlaas Road. The project will be fed off the 61 Pipeline downstream of the ED4 take-off. A new pump station is required to lift the water to a new reservoir (Liliefontein Reservoir) sited near Thornville. The proposed Richmond Pipeline will run along the R56 main road to Richmond (Figure 7.14). The existing Thornville Pump Station will be decommissioned and the rising main with revert to a back feed gravity main once the Richmond Pipeline is in operation. The pipeline will terminate at the municipal reservoir that serves Richmond. Key information on this project is summarised in Table Table 7.15 Project information: Richmond Pipeline. Project Components: Capacity: m long section of 450 mm diameter pipeline and a new booster pump station. 27 Ml/day. Institutional Arrangements nts Umgeni Water will own, operate and maintain the Richmond Pipeline infrastructure and will sell potable water from this system to The Msunduzi Municipality and Umgungundlovu District Municipality as per existing bulk water supply agreements. Beneficiaries ies The consumers in The Msunduzi Municipal area and in the Richmond Municipality will benefit from this project. Implementation The construction duration of this project is anticipated to be two years. The total cost is anticipated to be R 181 million at 2010 prices. 366

2 Figure 7.14 General layout of the Richmond Pipeline. 367

3 U M L A A S M L A A S R O A D R E S E R V O I R U P G R A D E Planning No Project No. Project Status Design (as at January 2011) Project Description Umlaas Road Reservoir initially served as balancing storage for the Umlaas Road WTP. The WTP was decommissioned in 2002 as sufficient potable water could be transferred to the Umlaas Road demand node via the 61 Pipeline. The reservoir complex was retained and currently serves the Outer Western areas of ethekwini Municipality via the 57 Pipeline and the Eston/Umbumbulu and Lion Park pipelines. The reservoir site is situated to the east of the N3 National Road, just north of the N3-R603 interchange (Figure 7.15). The reservoir complex consists of two separate reservoirs, viz. the original 9 Ml reservoir and a later 45 Ml reservoir. The reservoir complex currently serves as both a break pressure and balancing storage facility and can be supplied from Midmar WTP via the 61 Pipeline and from D.V. Harris WTP via the recommissioned 53 Pipeline. It is necessary to provide at least 15 hours of balancing storage at Umlaas Road in order to cope with the peak demands placed on the supply system by the downstream consumers. It is therefore recommended that an additional 45 Ml reservoir be constructed in advance of the commencement of the proposed Western Aqueduct load transfer in This will ensure that there is sufficient storage in place to accommodate the load transfer until at least 2022, by which time the Western Aqueduct demand should have been transferred across to the Mkomazi Water Project (Section 7.2.1). Key information on this project is summarised in Table Table 7.16 Project information: Umlaas Road Reservoir Upgrade. Project Components: Capacity: New 45 Ml reservoir. 45 Ml. Institutional Arrangements Umgeni Water will build, own, operate and maintain all water supply infrastructure pertaining to this project. Beneficiaries The upgrade to the Umlaas Road Reservoir Complex will benefit all consumers downstream of the reservoir. These beneficiaries are primarily the ethekwini Municipality, but also include consumers within the Mkhambathini Municipal areas of Umgungundlovu District Municipality. Implementation The construction duration of this project is anticipated to be one year. The total cost is estimated to be R 81 million at 2010 prices. 368

4 Figure 7.15 General layout of the Umlaas Road Reservoir Upgrade. 369

5 G R E A T E R R E A T E R E S T O N B U L K W A T E R S U P P L Y S C H E M E Planning No Project No. Project Status Design (as at January 2011) Project Description The Greater Eston area falls within Wards 4 to 7 in the Mkhambathini Local Municipality and Ward 5 and 7 of the Richmond Local Municipality. These local municipalities fall within the jurisdiction of the umgungundlovu District Municipality (UMDM). The bulk water supply to the Greater Eston area as depicted in Figure 7.16 requires three off-takes on the Eston-Umbumbulu Pipeline. The first off-take will supply the umacalagwala area. The second off-take will supply the following areas: Esigodini/Gulube Ismont Mpangisa Embuthweni Inhlazuka Ukhalo The third off-take will supply the Ogagwini area. Key information on this project is summarised in Table Table 7.17 Project information: Greater Greater Eston BWSS. Project Components: Capacity: 19km of 350mm diameter pipe 16km of 200mm diameter pipe 19km of 160mm diameter pipe 14km of 110mm diameter pipe 1 Break Pressure Tank 3.5 Ml Reservoir 2 Pump Stations Scheme to accommodate ultimate demand of 4.4 Ml/day Institutional Arrangements The scheme is jointly funded by DWA, Umgeni Water and Umgungundlovu District Municipality through its MIG allocation. The proposed scheme will be operated and maintained by Umgeni Water. Bulk water contracts will be entered into with Umgungundlovu District Municipality. 370

6 Figure 7.16 Greater Eston Bulk Water Supply 371

7 Beneficiaries The beneficiaries of this scheme are shown in Table Table 7.18 Beneficiaries for the Proposed Greater Eston BWSS. Area Current Population WARD 4 - Mkhambathini 1,544 WARD 5 - Mkhambathini 5,912 WARD 6 - Mkhambathini 7,400 WARD 7 - Mkhambathini 9,448 WARD 5 & 7 - Richmond 16,936 TOTAL 41,240 Using an allocation of 60 l/c/day, with a population growth of 0.5% to 2.5% over the 30-year planning horizon, the long term demand is estimated to be 4.4 Ml/day. Implementation The project is currently at design and tender stage. Construction is expected to begin in the first quarter of It is envisaged that the project will take 3 to 4 years to implement. 372

M A N Y A V U

M A N Y A V U 7. 4. 1 2 M A N Y A V U A N Y A V U P I P E L I N E Planning No. 105.25 Project No. Project Status Construction (as at January 2011) Project Description The rural community of Manyavu is situated in the

More information

I P E L I N E : M I D M A R I D M A R D A M T O M I D M A R

I P E L I N E : M I D M A R I D M A R D A M T O M I D M A R 7. 4 M G E N I G E N I S Y S T E M 7. 4. 1 2 5 1 R A W A W W A T E R P I P E L I N E Planning No. 105.0 Project No. Project Status Design (as at January 2011) I P E L I N E : M I D M A R I D M A R W T

More information

Time (hours) TOTAL STORAGE REQUIREMENT 6.99

Time (hours) TOTAL STORAGE REQUIREMENT 6.99 7 Ml (Table 5.28) of storage is required at Wartburg Reservoir to accommodate demands in 2020. Table 5.28 Storage Requirement at Wartburg Reservoir. Reservoir Function 2020 Demand (Ml/day) Time (hours)

More information

5.2.1 Upper Mgeni System

5.2.1 Upper Mgeni System 5.2.1 Upper Mgeni System Description The Upper Mgeni System currently serves urban, peri-urban and rural settlements within the Umgungundlovu, Msunduzi and ethekweni (Outer West) municipal areas (Figure

More information

The Mgeni System is an integrated water resources and potable bulk water distribution system comprising of two major sub-systems, viz.

The Mgeni System is an integrated water resources and potable bulk water distribution system comprising of two major sub-systems, viz. 5. 2 M G E N I G E N I S Y S T E M The Mgeni System is an integrated water resources and potable bulk water distribution system comprising of two major sub-systems, viz. The Upper Mgeni System (also referred

More information

Table 7.25 Project information: South Coast Augmentation Booster Pump Station. New in-line booster pump station. 120 Ml/day.

Table 7.25 Project information: South Coast Augmentation Booster Pump Station. New in-line booster pump station. 120 Ml/day. 7. 6 S O U T H 7. 6. 1 S O U T H O U T H C O A S T S Y S T E M O U T H C O A S T A U G M E N T A T I O N B O O S T E R P U M P S T A T I O N Planning No. 305.6 Project No. Project Status Construction (as

More information

S T A T U S. Figure 5.60 Water demand from Hazelmere WTP. Average Daily Sales (Ml/day) Month. Dec-07. Oct-05. Jan-09. Apr-12. Mar-11.

S T A T U S. Figure 5.60 Water demand from Hazelmere WTP. Average Daily Sales (Ml/day) Month. Dec-07. Oct-05. Jan-09. Apr-12. Mar-11. 5. 5. 2 S T A T U S T A T U S Q U O A N D L I M I T A T I O N S Figures 5.56 and 5.64 (schematically) illustrate the North Coast System in its current configuration and the current demands being placed

More information

5.2.2 Lower Mgeni System

5.2.2 Lower Mgeni System 5.2.2 Lower Mgeni System Description The Lower Mgeni System (Figure 5.7 and Figure 5.8) serves the greater ethekwini Municipal area from lower Pinetown/KwaDabeka in the west, to Phoenix/Inanda/Verulam

More information

MEMORANDUM Managing Water for Life Date: 15 September 2016

MEMORANDUM Managing Water for Life Date: 15 September 2016 MEMORANDUM Managing Water for Life Date: 15 September 2016 Subject: WARTBURG TO BRUYNSHILL PIPELINE INFORMATION 1. BACKGROUND Umgeni Water is a Bulk Water Provider to Umgungundlovu District Municipality

More information

6.2 Umgeni Water Owned Wastewater Works

6.2 Umgeni Water Owned Wastewater Works 6. WASTEWATER 6.1 Overview Umgeni Water owns and operates the Darvill and Ixopo Wastewater Works (WWW), but manages a number of other WWW on behalf of Municipalities. Management contracts are in place

More information

This section documents Umgeni Water s water demand forecast review that was completed in September This process:

This section documents Umgeni Water s water demand forecast review that was completed in September This process: 3. DEMAND FORECASTS This section documents Umgeni Water s water demand forecast review that was completed in September 2016. This process: Reviewed the figures for the financial year ending in June 2016

More information

9. CREATING VALUE ANNUAL REPORT 2011/

9. CREATING VALUE ANNUAL REPORT 2011/ 9. CREATING VALUE ANNUAL REPORT 211/212 61 9. CREATING VALUE CONTINUED... 9.1 9.1 PRODUCT QUALITY Management Approach Umgeni Water views the quality of potable water as paramount to its business sustainability

More information

7.5 Lower Mgeni System

7.5 Lower Mgeni System 7.5 Lower Mgeni System 7.5.1 emaphephetheni WTP Upgrade Planning No. 106.0 Project No. UI49A Project Status Construction phase (as of January 2012) Project Description The emaphephetheni Water Treatment

More information

Table 5.51 Reservoirs to be supplied off the South Coast Pipeline Phase 1.

Table 5.51 Reservoirs to be supplied off the South Coast Pipeline Phase 1. Lower South Coast Sub-Region The Lower South Coast sub-region is supplied with bulk treated water from the Bhobhoyi WTP (54 Ml/day), located 8 km inland of Port Shepstone and from the Mtamvuma WTP (20

More information

Creating Value PRODUCT QUALITY MANAGEMENT APPROACH POTABLE WATER QUALITY PERFORMANCE

Creating Value PRODUCT QUALITY MANAGEMENT APPROACH POTABLE WATER QUALITY PERFORMANCE 62 UMGENI WATER AMANZI ANNUAL 2014/2015 PG 04-05 2.0 ORGANISATIONAL PG 06-15 3.0 CHAIRPERSON S PG 16-23 4.0 CHIEF EXECUTIVE S PG 24-31 5.0 CORPORATE GOVERNANCE PG 32-47 6.0 STAKEHOLDER UNDERSTANDING AND

More information

8.O CREATING VALUE 54 UMGENI WATER AMANZI

8.O CREATING VALUE 54 UMGENI WATER AMANZI 8.O CREATING VALUE 54 UMGENI WATER AMANZI 8.1 PRODUCT QUALITY MANAGEMENT APPROACH The most signifi cant impact of Umgeni Water s business is provision of water that does not impact negatively on consumer

More information

6. WASTEWATER. 6.1 Overview. 6.2 Darvill Wastewater Works

6. WASTEWATER. 6.1 Overview. 6.2 Darvill Wastewater Works 6. WASTEWATER 6.1 Overview Umgeni Water currently owns and operates the Darvill and Ixopo Wastewater Works (WWW). The Howick and Lynnfield Park WWW are operated for umgungundlovu District Municipality

More information

6 WASTEWATER. 6.1 Overview. 6.2 Darvill Wastewater Works

6 WASTEWATER. 6.1 Overview. 6.2 Darvill Wastewater Works 6 WASTEWATER 6.1 Overview Umgeni Water currently owns and operates the Darvill and Ixopo Wastewater Works (WWWs). It also operates the Howick WWW for umgungundlovu District Municipality under a management

More information

Performance Scorecards for 2009/2010

Performance Scorecards for 2009/2010 Scorecards for Creating Value for Customers Outcome Exceed Customer Product Expectations Quality Growth / Increase Customer Base Resiliency Optimisation Customer Satisfaction Infrastructure Stability The

More information

5.5 North Coast System

5.5 North Coast System 5.5 North Coast System 5.5.1 Description The North Coast System comprises of the Mdloti System, the Lower Mvoti System and the Lower Thukela System (Figure 5.57). These systems have been grouped together

More information

SOCIO-ECONOMIC GROWTH AND SERVICE DELIVERY TOWARDS RURAL DEVELOPMENT. Umgeni Water s Activities in Support of DWAF Strategies

SOCIO-ECONOMIC GROWTH AND SERVICE DELIVERY TOWARDS RURAL DEVELOPMENT. Umgeni Water s Activities in Support of DWAF Strategies SOCIO-ECONOMIC GROWTH AND SERVICE DELIVERY TOWARDS RURAL DEVELOPMENT Umgeni Water s Activities in Support of DWAF Strategies Presentation to Portfolio Committee on Water Affairs and Forestry Strategic

More information

B A C K G R O U N P R O P O S E D P R O J E C T

B A C K G R O U N P R O P O S E D P R O J E C T 4. 5 W A S T E W A T E R A S T E W A T E R R E U S E 4. 5. 1 B A C K G R O U N A C K G R O U N D A N D E X I S T I N G I N F R A S T R U C T U R E The reuse or reclamation of wastewater not only improves

More information

DHI 2016 ANNUAL CONFERENCE

DHI 2016 ANNUAL CONFERENCE DHI 2016 ANNUAL CONFERENCE Managing Drought The Umgeni Water Experience 18 April 2016 Percy Sithole Water Resources Planning Population Density Current Water Resources Mearns Weir Spring Grove Dam Albert

More information

Hamilton City Water Distribution System Strategic Planning

Hamilton City Water Distribution System Strategic Planning Hamilton City Water Distribution System Strategic Planning Weijun Zhang Hamilton City Council, Private Bay 3010, Hamilton, New Zealand zhangw@dhicn.com, www.hcc.govt.nz ABSTRACT Hamilton s present water

More information

7. WASTEWATER. 7.1 Overview. 7.2 Umgeni Water Owned Wastewater Works Darvill Wastewater Works

7. WASTEWATER. 7.1 Overview. 7.2 Umgeni Water Owned Wastewater Works Darvill Wastewater Works 7. WASTEWATER 7.1 Overview Figure 7.1 illustrates the location of the wastewater works Umgeni Water operates in relation to the existing water system configurations discussed in Section 6. Umgeni Water

More information

5.5 North Coast System

5.5 North Coast System 5.5 North Coast System 5.5.1 Description The North Coast System comprises of the Mdloti System, the Lower Mvoti System and the Lower Thukela System (Figure 5.57). These systems have been grouped together

More information

SINAYO SECURITIES UBS WATER SUMMIT WATER INFRASTRUCTURE DEVELOPMENT. Protea Hotel Breakwater Lodge 25 February 2016

SINAYO SECURITIES UBS WATER SUMMIT WATER INFRASTRUCTURE DEVELOPMENT. Protea Hotel Breakwater Lodge 25 February 2016 SINAYO SECURITIES UBS WATER SUMMIT WATER INFRASTRUCTURE DEVELOPMENT Protea Hotel Breakwater Lodge 25 February 2016 2 Agenda 1 2 3 4 Section 1 Section 2 Section 3 Section 4 WATER SECTOR VALUE CHAIN GROUP

More information

Organisational LEGISLATIVE MANDATE UMGENI WATER 2.2 ACTIVITIES OF

Organisational LEGISLATIVE MANDATE UMGENI WATER 2.2 ACTIVITIES OF 2.0 Organisational Pro le 2.1 LEGISLATIVE MANDATE Umgeni Water is a public entity established in 1974 to provide water services - water supply and sanitation services - to other water services institutions

More information

4.4.4 Mooi/Mgeni Region

4.4.4 Mooi/Mgeni Region 4.4.4 Mooi/Mgeni Region The Mooi/Mgeni region comprises of the two tertiary catchments of U20 (umngeni River) and V20 (Mooi River) (Figure 4.22). The major urban centres of Durban and Pietermaritzburg

More information

Broken Hill Water Supply. Hendrik Van Rhijn

Broken Hill Water Supply. Hendrik Van Rhijn Broken Hill Water Supply Hendrik Van Rhijn Public Works Advisory Who are we? We are the NSW Government s key advisor for large water infrastructure projects and complex water programs and portfolios. We

More information

PROPOSED CAPACITY UPGRADES TO THE N3 FROM LYNNFIELD PARK (KM 30.6) TO GLADYS MANZI (FORMERLY MURRAY) ROAD (KM 6.1) (DEA REF NO: 14/12/16/3/3/1/1966)

PROPOSED CAPACITY UPGRADES TO THE N3 FROM LYNNFIELD PARK (KM 30.6) TO GLADYS MANZI (FORMERLY MURRAY) ROAD (KM 6.1) (DEA REF NO: 14/12/16/3/3/1/1966) 23 October 2018 Ms Zama Hadebe For Attention Thulani Mbokdo Department of and Sanitation (Licensing) PO Box 1018 Durban 4000 Dear Ms Hadebe, PROPOSED CAPACITY UPGRADES TO THE N3 FROM LYNNFIELD PARK (KM

More information

Schedule B Municipal Class Environmental Assessment Potable Water Storage

Schedule B Municipal Class Environmental Assessment Potable Water Storage Schedule B Municipal Class Environmental Assessment Potable Water Storage Town Meeting: Phase 2 Status Update J.L. Richards & Associates Limited Sarah Gore, P.Eng., Project Manager Date: May 22, 2018 JLR

More information

Hydropower from pressurized conduits Energy generation from distribution systems Research project

Hydropower from pressurized conduits Energy generation from distribution systems Research project Energy generation from distribution systems Research project P1-1 Layout of the presentation Introduction Project team and collaborating organisations Study aims Deliverables/products Budget Bloemwater

More information

ENVIRONMENTAL IMPACT ASSESSMENT (BASIC ASSESSMENT) PROCESS: PROPOSED REVERSE OSMOSIS PLANT, IRON ORE HANDLING FACILITY, PORT OF SALDANHA

ENVIRONMENTAL IMPACT ASSESSMENT (BASIC ASSESSMENT) PROCESS: PROPOSED REVERSE OSMOSIS PLANT, IRON ORE HANDLING FACILITY, PORT OF SALDANHA ENVIRONMENTAL IMPACT ASSESSMENT (BASIC ASSESSMENT) PROCESS: PROPOSED REVERSE OSMOSIS PLANT, IRON ORE HANDLING FACILITY, PORT OF SALDANHA BACKGROUND INFORMATION DOCUMENT SRK Project 364470/42G June 2007

More information

Mayfield West Phase Two Secondary Plan Water and Wastewater Servicing Study Part A Report Town of Caledon

Mayfield West Phase Two Secondary Plan Water and Wastewater Servicing Study Part A Report Town of Caledon Water and Wastewater Servicing Study Part A Report Town of Caledon Prepared by 170 Steelwell Road Suite 200 Brampton ON L6T 5T3 Canada File No: MTB 15608 The material in this report reflects best judgement

More information

Community Sustainability

Community Sustainability Community Sustainability R ural Development Umgeni Water has firmly committed to government s strategic priorities through providing sustainable water services that would reduce backlogs in local municipalities

More information

Section 5 - Planning Criteria. Section 5

Section 5 - Planning Criteria. Section 5 Section 5 - Planning Criteria Section 5 SECTION 5 PLANNING CRITERIA This section presents the design criteria and methodologies for analysis used to evaluate the existing distribution system and its facilities

More information

Storage and pumping capacity analysis using hydraulic modeling

Storage and pumping capacity analysis using hydraulic modeling Storage and pumping capacity analysis using hydraulic modeling G. MacPherson City of Chilliwack, B.C., Canada W. de Schaetzen & S. Cripps GeoAdvice Inc., Vancouver, B.C., Canada ABSTRACT: This paper summarizes

More information

DUBAI ELECTRICITY AND WATER AUTHORITY GUIDELINES FOR NEW DEVELOPMENT PROJECTS UPDATE

DUBAI ELECTRICITY AND WATER AUTHORITY GUIDELINES FOR NEW DEVELOPMENT PROJECTS UPDATE DUBAI ELECTRICITY AND WATER AUTHORITY GUIDELINES FOR NEW DEVELOPMENT PROJECTS UPDATE - 2010 POWER & WATER PLANNING (WATER TRANSMISSION PLANNING) DUBAI ELECTRICITY AND WATER AUTHORITY WATER TRANSMISSION

More information

2. ORGANISATIONAL PROFILE AND GOVERNANCE

2. ORGANISATIONAL PROFILE AND GOVERNANCE 2. ORGANISATIONAL PROFILE AND GOVERNANCE 2.1 LEGISLATIVE MANDATE Umgeni Water is a public entity established in 1974 to provide water services - water supply and sanitation services - to other water services

More information

Montara Water and Sanitary District 2011 New Customer CIP and Water Capacity Charge. Presentation to Board April 21, 2011

Montara Water and Sanitary District 2011 New Customer CIP and Water Capacity Charge. Presentation to Board April 21, 2011 Montara Water and Sanitary District 2011 New Customer CIP and Water Capacity Charge Presentation to Board April 21, 2011 PRESENTATION OUTLINE Master Plan Overview Purpose and Approach Supply and Demand

More information

Bloemwater Conduit Hydropower Plant launched

Bloemwater Conduit Hydropower Plant launched Bloemwater Conduit Hydropower Plant launched Marco van Dijk Department of Civil Engineering University of Pretoria marco.vandijk@up.ac.za On 31 March 2015 the Minister of Water and Sanitation, Nomvula

More information

OUTLINE SERVICES SCHEME REPORT (WATER AND SEWER)

OUTLINE SERVICES SCHEME REPORT (WATER AND SEWER) OUTLINE SCHEME REPORT (WATER AND SEWER) 327043 HOLDING 263, WILLOWGLEN AGRICULTURAL HOLDINGS Issue 1 SHELL SUMMIT ROAD PROPOSED FILLING STATION ON THE REMAINING EXTENT OF PORTION 123 (A PORTION OF PORTION

More information

THE USE OF HYDRAULIC TRANSIENT MODELLING IN THE DESIGN OF RESILIENT PIPELINES

THE USE OF HYDRAULIC TRANSIENT MODELLING IN THE DESIGN OF RESILIENT PIPELINES THE USE OF HYDRAULIC TRANSIENT MODELLING IN THE DESIGN OF RESILIENT PIPELINES Alistair Hancox, Grant Pedersen Harrison Grierson Consultants Limited ABSTRACT Pressure surges during the start up, shut down,

More information

Yorkton Rona Commercial and Industrial development. Concept Plan and Serviceability Report

Yorkton Rona Commercial and Industrial development. Concept Plan and Serviceability Report Yorkton Rona Commercial and Industrial development Concept Plan and Serviceability Report Prepared for: 101242326 Sask Ltd. Box Ft Quappelle, SK Canada S0G 1S0 Prepared by: Stantec Consulting Ltd. 302-1345

More information

THE GREAT DROUGHT OF 1895

THE GREAT DROUGHT OF 1895 THE GREAT DROUGHT OF 1895 VISION; To be a provider of sustainable, universally competitive water and sanitation solutions for Africa MISSION; To deliver and supply world class affordable, reliable and

More information

BARRABA WATER SUPPLY. Construction of Split Rock Dam Pipeline and Ancillary Works

BARRABA WATER SUPPLY. Construction of Split Rock Dam Pipeline and Ancillary Works BARRABA WATER SUPPLY Construction of Split Rock Dam Pipeline and Ancillary Works Long history of unreliable water supply Water restrictions in place 50% of time over 10 years to 2012 Various studies looked

More information

Georgetown Water Storage Class Environmental Assessment Study

Georgetown Water Storage Class Environmental Assessment Study Georgetown Water Storage Class Environmental Assessment Study Public Information Centre Cedarvale Community Centre 181-185 Main Street South Thursday, September 4th, 2008 6:30 p.m. 8:30 p.m. Why are we

More information

INNISFIL WATER AND WASTEWATER MASTER SERVICING PLAN UPDATE

INNISFIL WATER AND WASTEWATER MASTER SERVICING PLAN UPDATE INNISFIL WATER AND WASTEWATER MASTER SERVICING PLAN UPDATE Water and Wastewater Servicing Alternatives Public Information Meeting No. 2 March 20, 2018 1 MSP Update Objectives Develop water and wastewater

More information

STAKEHOLDER UNDERSTANDING AND SUPPORT

STAKEHOLDER UNDERSTANDING AND SUPPORT 7.0 INTERACTION One of the key Strategic Objectives of Umgeni Water is to increase customer and stakeholder value. In pursuance of this, customer and stakeholder interaction is a vital component. As a

More information

El Margarita Development Analysis

El Margarita Development Analysis 303 Second Street, Suite 300 South San Francisco, California 94107 415-243-2150 FAX: 415-896-0999 El Margarita Development Analysis 28 January 2015 Prepared for City of Yuba City 1201 Civic Center Boulevard

More information

EWS Planning of Water and Sanitation

EWS Planning of Water and Sanitation EWS Planning of Water and Sanitation 13/02/2015 Strategic Objectives Legislation driving the business plan Time horizon Long term, medium term and short term plan in terms in terms of legislated submission

More information

Infrastructure Master Plan / /2048 Volume 1. Improving Quality of Life and Enhancing Sustainable Economic Development

Infrastructure Master Plan / /2048 Volume 1. Improving Quality of Life and Enhancing Sustainable Economic Development Infrastructure Master Plan 2017 2017/2018 2047/2048 Volume 1 Planning Services, Engineering and Scientific Services Division, Umgeni Water PO Box 9, Pietermaritzburg, 3200, KwaZulu-Natal, South Africa

More information

WATER MAIN EXTENSION DESIGN REQUIREMENTS

WATER MAIN EXTENSION DESIGN REQUIREMENTS This guideline provides minimum requirements for the design of new water main extensions. This guide is not to be used as a substitution for the detailed design of the water system. The Developer s Engineer

More information

African Utility Week Reducing Non-Revenue Water in the Durban Central Business District

African Utility Week Reducing Non-Revenue Water in the Durban Central Business District African Utility Week Reducing Non-Revenue Water in the Durban Central Business District Mark Shepherd PrEng JOAT Consulting Background to Programme: Durban home to approximately 3,5 million 12 000km of

More information

PROPOSED LIBODE & NGQELENI BULK WATER SUPPLY CONVEYANCE CORRIDORS OR TAMBO DISTRICT MUNICIPALITY, EASTERN CAPE

PROPOSED LIBODE & NGQELENI BULK WATER SUPPLY CONVEYANCE CORRIDORS OR TAMBO DISTRICT MUNICIPALITY, EASTERN CAPE PROPOSED LIBODE & NGQELENI BULK WATER SUPPLY CONVEYANCE CORRIDORS OR TAMBO DISTRICT MUNICIPALITY, EASTERN CAPE Background Information Document DEDEA Ref No s: EC 155/ORT/LN1&LN2/M/13 34 EC 157/ORT/LN1&LN3/M/13

More information

4 PROJECT ALTERNATIVES

4 PROJECT ALTERNATIVES 4 PROJECT ALTERNATIVES 4.1 Introduction In terms of the EIA Regulations published in Government Notice R543 of 2 August 2010 in terms of Section 24 of the National Environmental Management Act (Act No.

More information

BURKE WATER STATION TREATMENT, PUMPING AND STORAGE CLASS ENVIRONMENTAL ASSESSMENT

BURKE WATER STATION TREATMENT, PUMPING AND STORAGE CLASS ENVIRONMENTAL ASSESSMENT Welcome to the City of Guelph BURKE WATER STATION TREATMENT, PUMPING AND STORAGE CLASS ENVIRONMENTAL ASSESSMENT PUBLIC INFORMATION CENTRE NO. 1 Wednesday, November 7, 2012 from 6:30 PM to 8:30 PM Please

More information

2.0 STAKEHOLDER UNDERSTANDING AND SUPPORT PG REPORT PROFILE ORGANISATIONAL PROFILE ORGANISATIONAL PROFILE PG 8-17 PG

2.0 STAKEHOLDER UNDERSTANDING AND SUPPORT PG REPORT PROFILE ORGANISATIONAL PROFILE ORGANISATIONAL PROFILE PG 8-17 PG 8 ANNUAL PG 6-7 1.0 MINISTER S FOREWORD PG 18-21 3.0 CHAIRPERSON S PG 22-27 4.0 CHIEF EXECUTIVE S PG 28-35 5.0 CORPORATE GOVERNANCE PG 36-51 6.0 AND SUPPORT PG 52-57 7.0 Organisational Profile 2.1 LEGISLATIVE

More information

SUMMIT PRESENTATION. Presented by: MS B. MSANE. Date: 26 MAY Presented by: Name Surname Directorate. Date

SUMMIT PRESENTATION. Presented by: MS B. MSANE. Date: 26 MAY Presented by: Name Surname Directorate. Date MUNICIPAL PRESENTATION INFRASTRUCTURE TITLE SUMMIT PRESENTATION Presented by: Name Surname Directorate Date Presented by: MS B. MSANE Date: 26 MAY 2016 Contents 1. INTRODUCTION 2. MTEF ALLOCATIONS 3. REGIONAL

More information

EFFLUENT REUSE AT EAST LISMORE WASTEWATER TREATMENT WORKS

EFFLUENT REUSE AT EAST LISMORE WASTEWATER TREATMENT WORKS EFFLUENT REUSE AT EAST LISMORE WASTEWATER TREATMENT WORKS Jeremy Silk Project Engineer, Lismore Water, NSW Janaka Weeraratne A/Manager, Lismore Water, NSW Summary The East Lismore Wastewater Treatment

More information

The West East Link Main is a 125 million pipeline project that will carry water across the North West of England

The West East Link Main is a 125 million pipeline project that will carry water across the North West of England West East Link Main 55km pipeline, carrying 100 million litres, is one of the largest ever undertaken by a water company by Jon Higham The West East Link Main is a 125 million pipeline project that will

More information

WELL, WELL, WELL DRIFT WELL RECOMISSIONING, AN OPERATORS PERSPECTIVE. Adrian Cameron. Tamworth Regional Council

WELL, WELL, WELL DRIFT WELL RECOMISSIONING, AN OPERATORS PERSPECTIVE. Adrian Cameron. Tamworth Regional Council WELL, WELL, WELL DRIFT WELL RECOMISSIONING, AN OPERATORS PERSPECTIVE Paper Presented by: Adrian Cameron Author: Adrian Cameron, Team Leader Water Headworks, Tamworth Regional Council 3 rd Annual WIOA NSW

More information

YES WE CAN! Volume 2. Presented By: Joe Taranto

YES WE CAN! Volume 2. Presented By: Joe Taranto Volume 2 Presented By: Joe Taranto Universal Water Recycling 37 Moon Mountain Drive Mount View NSW 2325 universalwaterrecycling@hotmail.com www.uwr.com.au Option One Option Two Tillegra Dam Desalination

More information

Rethinking wastewater treatment A new type of wastewater treatment plant is gaining a foothold in South Africa, Dominic Uys finds out more.

Rethinking wastewater treatment A new type of wastewater treatment plant is gaining a foothold in South Africa, Dominic Uys finds out more. Rethinking wastewater treatment A new type of wastewater treatment plant is gaining a foothold in South Africa, Dominic Uys finds out more. MUNICIPAL VISIT At the new Wemmmershoek wastwater treatment plant

More information

PIGGING OF THE O SHANNASSY OUTLET MAINS. Paul Balassone. Melbourne Water

PIGGING OF THE O SHANNASSY OUTLET MAINS. Paul Balassone. Melbourne Water PIGGING OF THE O SHANNASSY OUTLET MAINS Paper Presented by : Paul Balassone Authors: Paul Balassone, Senior Asset Engineer, Infrastructure Ian Smith, Technical Specialist, Water Supply Operations, Melbourne

More information

Using Hydraulic Modeling to Determine Viable Emergency Water Supply Options for the City Of San Francisco s Largest Reservoir and Pressure Zone

Using Hydraulic Modeling to Determine Viable Emergency Water Supply Options for the City Of San Francisco s Largest Reservoir and Pressure Zone Using Hydraulic Modeling to Determine Viable Emergency Water Supply Options for the City Of San Francisco s Largest Reservoir and Pressure Zone October 28, 2015 Presented by: Brian Barry, SFPUC Karen Chu,

More information

Town of New Tecumseth. Water Distribution and Storage Master Plan April 2007

Town of New Tecumseth. Water Distribution and Storage Master Plan April 2007 Town of New Tecumseth Water Distribution and Storage Master Plan April 2007 Town of New Tecumseth Water Distribution and Storage Master Plan Executive Summary The Water Distribution and Storage Master

More information

Washburn Booster Pumping Station Expansion and Upgrades Project Update November 2012

Washburn Booster Pumping Station Expansion and Upgrades Project Update November 2012 Washburn Booster Pumping Station Expansion and Upgrades Project Update November 2012 Project Background The Washburn Booster Pumping Station serves as a central water distribution facility and provides

More information

TOWN OF AURORA DRINKING WATER QUALITY ANNUAL REPORT

TOWN OF AURORA DRINKING WATER QUALITY ANNUAL REPORT TOWN OF AURORA DRINKING WATER QUALITY ANNUAL REPORT JANUARY 1 TO DECEMBER 31, 2009 New Regulations Amendments to Ontario Regulation 170/03 came into effect on June 5, 2006. The provincially mandated amendments

More information

A Report on Reduction of Non Revenue Water in Kundapura Municipal Water Supply

A Report on Reduction of Non Revenue Water in Kundapura Municipal Water Supply A Report on Reduction of Non Revenue Water in Kundapura Municipal Water Supply Town Municipal Council Kundapura Udupi (Dist) Ph: 08245-230410 Fax: 08254-230410 E-Mail: co_kundapur@yahoo.co.in (1) Background

More information

POTABLE WATER COAGULANT TRIALS UTILIZING POLYALUMINIUM CHLORHYDRATE. Michael Dalton. Toowoomba City Council

POTABLE WATER COAGULANT TRIALS UTILIZING POLYALUMINIUM CHLORHYDRATE. Michael Dalton. Toowoomba City Council POTABLE WATER COAGULANT TRIALS UTILIZING POLYALUMINIUM CHLORHYDRATE Paper Presented by: Michael Dalton Author: Michael Dalton, Rockhampton City Council, Toowoomba City Council 33rd Annual Qld Water Industry

More information

COLLECTION AND DISTRIBUTION OF WATER

COLLECTION AND DISTRIBUTION OF WATER COLLECTION AND DISTRIUTION OF WATER Addis Ababa University Addis Ababa Institute of Technology Department of Civil Engineering Collection and Distribution of Water Deals with the transport of water from

More information

Stakeholder Understanding and Support

Stakeholder Understanding and Support 6.0 Stakeholder Understanding and Support Stakeholder Interaction In the course of execution of its mandate, Umgeni Water interacts with a wide array of stakeholders who are impacted on or have an interest

More information

Section 1 - Introduction...7. Section 2 - Raw Water Supply Section 3 - Water Treatment Section 4 - Water Distribution System...

Section 1 - Introduction...7. Section 2 - Raw Water Supply Section 3 - Water Treatment Section 4 - Water Distribution System... Table of Contents Section 1 - Introduction...7 1.1 Population Growth...7 1.1.1 Service Area...7 1.1.2 Past Population...7 1.1.3 Projected Population Growth...9 1.2 Water Demands...9 1.2.1 Past Water Demands...9

More information

NRW REDUCTION STRATEGY

NRW REDUCTION STRATEGY NRW REDUCTION STRATEGY PREAMBLE : Potable water is becoming scarcer; often making it more energy intensive to procure. More energy is required to pump water to greater distances and from deeper depth in

More information

Refurbishment of Emalahleni Bulk Scheme

Refurbishment of Emalahleni Bulk Scheme Refurbishment of Emalahleni Bulk Scheme Sedimentation tank Rapid Gravity Sand Filter Hartbeespoort Dam Integrated Biological Remediation Programme CLIENT: DWA Gauteng SCOPE: Rand Water is appointed by

More information

Horizon 2020 Steering Committee Water and Wastewater Master Plan Overview

Horizon 2020 Steering Committee Water and Wastewater Master Plan Overview Horizon 2020 Steering Committee Water and Wastewater Master Plan Overview August 11, 2014 Let s Look at the Numbers Water System 2 - Raw Water Sources Clinton Reservoir Kansas River 2 - Water Treatment

More information

The table below highlights some of the important achievements in this regard: Commissioning of New Water Treatment Plants/Pumping Stations

The table below highlights some of the important achievements in this regard: Commissioning of New Water Treatment Plants/Pumping Stations Water Supply Improving water supply for the city has been a major focus area for KMC during the past few years. This has involved augmenting piped water supply through commissioning of water treatment

More information

Technical Overview KZN Water Service Delivery Backlogs

Technical Overview KZN Water Service Delivery Backlogs Technical Overview KZN Water Service Delivery Backlogs Presented by Viv Naidoo Acting Director Water Sector Support Water Services Master Class # 2 11-12 July 2012 Durban Situational Analysis Global Location

More information

COMPANY PROFILE CIVIL ENGINEERING CONSTRUCTION, GENERAL BUILDING & PROJECT MANAGEMENT

COMPANY PROFILE CIVIL ENGINEERING CONSTRUCTION, GENERAL BUILDING & PROJECT MANAGEMENT COMPANY PROFILE CIVIL ENGINEERING CONSTRUCTION, GENERAL BUILDING & PROJECT MANAGEMENT TABLE OF CONTENTS 04 AFFILIATIONS 05 ABOUT US 06 STAFF & EQUIPMENT 07 SERVICES 08-20 CIVILS 21-22 INDUSTRIAL CIVILS

More information

Integrated waste management using biogas in a decentralised Municipal framework

Integrated waste management using biogas in a decentralised Municipal framework Integrated waste management using biogas in a decentralised Municipal framework COMPETE & RE-Impact Workshop Bioenergy for Rural Development in Africa and Asia Congress Centre, Hamburg, Germany 30 June

More information

City of Crosby, ND Municipal Infrastructure Needs Assessment September 2012

City of Crosby, ND Municipal Infrastructure Needs Assessment September 2012 City of Crosby, ND Municipal Infrastructure Needs Assessment September 2012 Project made possible by US Dept. of HUD Regional Substantiality Planning Grant and ND Energy Development Infrastructure and

More information

MOROGORO URBAN WATER SUPPLY AND SANITATION AUTHORITY

MOROGORO URBAN WATER SUPPLY AND SANITATION AUTHORITY MOROGORO URBAN WATER SUPPLY AND SANITATION AUTHORITY MONTH: DECEMBER, 2012 A: IMPLEMENTATION OF WATER SECTOR DEVELOPMENT PROGRAMME (WSDP) PROJECTS Introduction Under Water Sector Development Programme,

More information

Abstract. Environmental Impact Statement (EIS) Scoping Report

Abstract. Environmental Impact Statement (EIS) Scoping Report Abstract On 1 st January 2014, Irish Water assumed responsibility for managing Ireland s water and wastewater investment and maintenance programmes. On that date, Irish Water also took over the management

More information

TOWN OF NEW TECUMSETH WATER SUPPLY, STORAGE AND DISTRIBUTION MASTER PLAN WELCOME

TOWN OF NEW TECUMSETH WATER SUPPLY, STORAGE AND DISTRIBUTION MASTER PLAN WELCOME WELCOME PLEASE SIGN IN Public Information Centre, February 11, 2016, 5:30 pm to 8 pm Town of New Tecumseth Council Chambers, Alliston, ON The Town of New Tecumseth welcomes you to this Public Information

More information

EVALUATING NANOFILTRATION, REVERSE OSMOSIS, AND ION EXCHANGE TO MEET CONSUMPTIVE USE CONSTRAINTS AND FINISHED WATER QUALITY GOALS FOR BROWARD COUNTY

EVALUATING NANOFILTRATION, REVERSE OSMOSIS, AND ION EXCHANGE TO MEET CONSUMPTIVE USE CONSTRAINTS AND FINISHED WATER QUALITY GOALS FOR BROWARD COUNTY EVALUATING NANOFILTRATION, REVERSE OSMOSIS, AND ION EXCHANGE TO MEET CONSUMPTIVE USE CONSTRAINTS AND FINISHED WATER QUALITY GOALS FOR BROWARD COUNTY Frank A. Brinson, P.E., DEE, CDM, Fort Lauderdale, FL

More information

Francisco Water. January 17, 2018

Francisco Water. January 17, 2018 O San Francisco Water Services of the San Francisco Public Utilities Commission January 17, 2018 Honorable Board of Supervisors San Francisco City Hall 1 Dr. Carlton B Goodlett Place, Room #244 San Francisco,

More information

Tongaat WWTW Water Use Licence Application. Draft Report Meeting 1 October 2015

Tongaat WWTW Water Use Licence Application. Draft Report Meeting 1 October 2015 Tongaat WWTW Water Use Licence Application Draft Report Meeting 1 October 2015 Agenda Welcome and purpose Public Participation Process Introduction ethekwini W&S Tongaat Waste Water Treatment Works A Water

More information

DESIGN OF 24X7 WATER SUPPLY SYSTEMS

DESIGN OF 24X7 WATER SUPPLY SYSTEMS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 DESIGN OF 24X7 WATER SUPPLY SYSTEMS A Case study: Ahmedabad city 1 Swarup Varu and 2 Dipsha Shah 1 Graduate Student, 2 Professor School of Building Science

More information

Project Name: St. Johns River/Taylor Creek Reservoir

Project Name: St. Johns River/Taylor Creek Reservoir Project Name: St. Johns River/Taylor Creek Reservoir Project Location: Osceola and Orange counties Project Number: 126 Project Type: Surface Water Description of project: The proposed St. Johns River/Taylor

More information

17.0 INFRASTRUCTURE AND ENERGY

17.0 INFRASTRUCTURE AND ENERGY 17.0 INFRASTRUCTURE AND ENERGY The Project would place demands on the existing infrastructure systems for supplying water, treating sewage, providing energy and disposing of solid waste. The Project would

More information

12.1 OPERATIONAL OPTIMISATION 12.0 ISO ACCREDITED LABORATORY SERVICES ASSURING WATER QUALITY

12.1 OPERATIONAL OPTIMISATION 12.0 ISO ACCREDITED LABORATORY SERVICES ASSURING WATER QUALITY 108 PG 6-7 ORGANISATIONAL PG 8-17 MINISTER S FOREWORD PG 18-21 CHAIRPERSON S PG 22-27 CHIEF EXECUTIVE S PG 28-35 CORPORATE GOVERNANCE PG 36-51 STAKEHOLDER UNDERSTANDING AND SUPPORT PG 52-57 1.0 2.0 3.0

More information

Waste Water Treatment Plant Location Options. Presented by: Ben Greenough, Superintendent of Public Works Date: April 3, 2017 In Camera Meeting

Waste Water Treatment Plant Location Options. Presented by: Ben Greenough, Superintendent of Public Works Date: April 3, 2017 In Camera Meeting Waste Water Treatment Plant Location Options Presented by: Ben Greenough, Superintendent of Public Works Date: April 3, 2017 In Camera Meeting Sewer Study Review 2010 Sewage Treatment and Disposal Feasibility

More information

Arnfield and Godley WTW s are located in Tameside, south east of Manchester and form part of the Longdendale

Arnfield and Godley WTW s are located in Tameside, south east of Manchester and form part of the Longdendale Arnfield and Godley WTW water quality improvements scheme for United Utilities by Martin Clark Arnfield and Godley WTW s are located in Tameside, south east of Manchester and form part of the Longdendale

More information

PREPARED FOR WELLINGTON CITY COUNCIL - CITY SHAPER 1 SEPTEMBER 2016 SHELLY BAY, WELLINGTON SERVICING FEASIBILITY

PREPARED FOR WELLINGTON CITY COUNCIL - CITY SHAPER 1 SEPTEMBER 2016 SHELLY BAY, WELLINGTON SERVICING FEASIBILITY PREPARED FOR WELLINGTON CITY COUNCIL - CITY SHAPER 1 SEPTEMBER 2016 SHELLY BAY, WELLINGTON SERVICING FEASIBILITY COMMERCIAL IN CONFIDENCE All intellectual property rights, including copyright, in designs

More information

DRAFT MEMORANDUM OF UNDERSTANDING BETWEEN THE SAN FRANCISCO PUBLIC UTILITIES COMMISSION AND THE SAN FRANCISCO RECREATION AND PARK DEPARTMENT

DRAFT MEMORANDUM OF UNDERSTANDING BETWEEN THE SAN FRANCISCO PUBLIC UTILITIES COMMISSION AND THE SAN FRANCISCO RECREATION AND PARK DEPARTMENT DRAFT MEMORANDUM OF UNDERSTANDING BETWEEN THE SAN FRANCISCO PUBLIC UTILITIES COMMISSION AND THE SAN FRANCISCO RECREATION AND PARK DEPARTMENT FOR THE APPLICATION AND MANAGEMENT OF WATER USE EFFICIENCY PROGRAMS

More information

M.D. OF FOOTHILLS NO. 31

M.D. OF FOOTHILLS NO. 31 M.D. OF FOOTHILLS NO. 31 Strategy FINAL REPORT Revised March 31, 2010 (2210 026 00) Prepared by: March, 2010 EXECUTIVE SUMMARY The M.D. of Foothills No. 31 (MD) requires a Water, Wastewater and Stormwater

More information

MAGALIES WATER REQUEST FOR PROPOSAL RFP/MW/10/

MAGALIES WATER REQUEST FOR PROPOSAL RFP/MW/10/ Requesting Office: Head Office Contact Person: Mr T Mosete Contact Numbers: 014 597 4636 E-mail address: tenders@magalieswater.co.za MAGALIES WATER REQUEST FOR PROPOSAL RFP/MW/10/2019-20 PROFESSIONAL SERVICE

More information

CHAPTER 4 CAPITAL IMPROVEMENT PROGRAM

CHAPTER 4 CAPITAL IMPROVEMENT PROGRAM CHAPTER 4 CAPITAL IMPROVEMENT PROGRAM Various improvement projects were identified in Chapter 3. A brief description of each project selected for the 6-year and 20-year planning horizons is presented in

More information