Feasibility Study Report

Size: px
Start display at page:

Download "Feasibility Study Report"

Transcription

1 Report For: [Company Name] ( Customer ) Queue #: Service Location: Forsyth County, NC Total Output: 875 MW Commercial Operation Date: 6/1/2017 Prepared by: Orvane Piper, Duke Energy Carolinas Feasibility Study Report Redacted ( ).docx

2 Table of Contents 1.0 Introduction Study Assumptions and Methodology Thermal Study Results NRIS Evaluation ERIS Evaluation Fault Duty Study Results Reactive Capability Study Results... 5 Page 2 of 5

3 1.0 Introduction Following are the results of the Generation Feasibility Study for the installation of 875 MW of generating capacity in Forsyth County, NC. This site is located near Beckerdite Tie and has an estimated Commercial Operation Date of 6/1/ Study Assumptions and Methodology The power flow cases used in the study were developed from the Duke internal year 2017 summer peak case. The results of Duke s annual screening were used as a baseline to identify the impact of the new generation. All cases were modified to include 875 MW of additional generation at the Customer s facility. To determine the thermal impact on Duke s transmission system, the new generation modeled with a 230 kv connection at Beckerdite Tie. The economic generation dispatch was also changed by adding the new generation and forcing it on prior to the dispatch of the remaining Duke Balancing Authority Area units. The study cases were re-dispatched, solved and saved for use. The NRIS thermal study uses the results of Duke Energy Power Delivery s annual internal screening as a baseline to determine the impact of new generation. The annual internal screening identifies violations of the Duke Energy Power Transmission System Planning Guidelines and this information is used to develop the transmission asset expansion plan. The annual screening provides branch loading for postulated transmission line or transformer contingencies under various generation dispatches. The thermal study results following the inclusion of the new generation were obtained by the same methods, and are therefore comparable to the annual screening. The results are compared to identify significant impacts to the Duke Energy transmission system. Fault studies are performed by modeling the new generator and previously queued generation ahead of the new generator in the interconnection queue. Any significant changes in fault duty resulting from the new generator s installation are identified. Various faults are placed on the system and their impact versus equipment rating is evaluated. Reactive Capability is evaluated by modeling a facility s generators and step-up transformers (GSUs) at various taps and system voltage conditions. The reactive capability of the facility can be affected by many factors including generator capability limits, excitation limits, and bus voltage limits. The evaluation determines whether sufficient reactive support will be available at the Connection Point. Page 3 of 5

4 3.0 Thermal Study Results 3.1 NRIS Evaluation The following network upgrades were identified as being attributable to the studied generating facility: Facility Name/Upgrade Existing Size/Type Proposed Size/Type Mileage Estimated Cost Lead Time (months) 1. Interconnection cost N/A N/A N/A TBD TBD 2. Upgrade Linden St 100 kv Lines (Beckerdite-Linden St) 3. Upgrade Silas 100 kv Lines (Mocksville-Advance Retail) 477 ACSR B477 ACSR 15.7 $20 M 36 2/0 Cu 477 ACSR 9.26 $12.5 M Add Transformer At Buck Tie N/A 448 MVA N/A $5.9 M Replace Transformer At Beckerdite Tie CUSTOMER TOTAL COST ESTIMATE 200 MVA 448 MVA N/A $3.9 M 24 $42.3 M 1 36 The listed upgrades are also required for all scenarios including higher queued generation. 3.2 ERIS Evaluation The Customer did not request evaluation of ERIS service. 4.0 Fault Duty Study Results The following breakers will need to be replaced: 1. At Beckerdite Tie the following twelve 100 kv breakers: Beckerdite Retail HT, SVC Red & Yellow, Bank 1 LT Red & Yellow, Bank 2 LT Red & Yellow, Bank 3 LT Red & Yellow, Bank 4 LT Red & Yellow, capacitor bank 2. At Buck Steam Station the following five 100 kv breakers: Buck Bl, Grants Creek Bl & Wh, Salisbury Bl & Wh 3. At Linden Street the following 100 kv breaker: Randleman Bl 4. At Shattalon Switching Station the following five 100 kv breakers: Bethania Bl & Wh, Shattalon Bl & Wh, Walnut Cove Bl/Wh 5. At Winston Tie the following 100 kv breaker: Salem Wh 1 Interconnection costs are not included in the total estimate at this time. Page 4 of 5

5 Total estimated cost for breaker replacements: $7.5 M The listed breakers are also required for all scenarios including higher queued generation. 5.0 Reactive Capability Study Results With the proposed generating facility, the level of reactive support supplied by the units has been determined to be acceptable at this time. Evaluation of MVAR flow and voltages in the vicinity of Beckerdite Tie indicates adequate reactive support exists in the region. The recommended GSU tap setting is kv. Study completed by: Orvane Piper, Duke Energy Carolinas Reviewed by: Ben Harrison, Duke Energy Carolinas Director, Transmission Planning Carolinas Page 5 of 5

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Click here to enter text. 2x1 Combined Cycle Plant Service Location: Anderson, SC Total Output: 754 MW Commercial Operation Date: 5/1/2016

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Stanly County, NC Total Output Requested By Customer: 30 MW Commercial Operation Date Requested By Customer: 12/1/2019 Feasibility

More information

Generator Interconnection Affected System Impact Study. Plains & Eastern Clean Line Final Report

Generator Interconnection Affected System Impact Study. Plains & Eastern Clean Line Final Report Generator Interconnection Affected System Impact Study Plains & Eastern Clean Line Final Report May 19, 2015 MISO 2985 Ames Crossing Eagan Minnesota - 55121 http://www.misoenergy.org Midcontinent Independent

More information

PID 276 Feasibility Study Report 4.4MW Distribution Inter-Connection Mermentau Substation

PID 276 Feasibility Study Report 4.4MW Distribution Inter-Connection Mermentau Substation PID 276 Feasibility Study Report 4.4MW Distribution Inter-Connection Mermentau Substation Prepared by: Entergy Services, Inc. T & D Planning 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date Description

More information

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee Transmission Expansion Advisory Committee January 6, 2011 Issues Tracking Issues Tracking Open Issues: None New Issues: 3 Baseline Reliability Update Remaining 2015 Analysis 2015 N-1-1 voltage study Results

More information

Feasibility Study for the Q MW Solar Project

Feasibility Study for the Q MW Solar Project Feasibility Study for the Q195 74.9 MW Solar Project August 2018 Bulk Transmission Planning, Florida i This document and any attachments hereto ( document ) is made available by Duke Energy Florida, LLC

More information

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038 Generation Interconnection System Impact Study Report For PJM Generation Interconnection Request Queue Position AA1-038 Lexington Low Moor 230kV 10.1MW Capacity / 78.2MW Energy September / 2015 Introduction

More information

Transmission Expansion Advisory Committee. December 15, 2011

Transmission Expansion Advisory Committee. December 15, 2011 Transmission Expansion Advisory Committee December 15, 2011 Issues Tracking Issues Tracking Open Issues None New Issues 3 Backbone Transmission Project Status Susquehanna to Roseland Project Required June

More information

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017 Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA March 21, 2017 Contents 1 Background...3 2 National and Regional Criteria and Guides...4 2.1 2.1 NERC Transmission Planning Standards...4 2.2

More information

Generation Interconnection Feasibility Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038

Generation Interconnection Feasibility Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038 Generation Interconnection Feasibility Study Report For PJM Generation Interconnection Request Queue Position AA1-038 Lexington Low Moor 230kV 10.1MW Capacity / 78.2MW Energy February / 2015 Introduction

More information

SSR STUDY REPORT FINAL

SSR STUDY REPORT FINAL System Support Resource Study Escanaba 1 & 2: 25 MW Coal 36 Month Suspension 6/15/2012 6/15/2015 SSR STUDY REPORT FINAL June 21, 2012 Redacted version for January 3, 2013 filing EXECUTIVE SUMMARY An Attachment

More information

1.3 Planning Assumptions and Model Development

1.3 Planning Assumptions and Model Development Section 1: Process Overview In addition, projects that originate through local Transmission Owner planning will be posted on the PJM web site. This site will include all currently planned transmission

More information

Artificial Island Proposal III Salem to Red Lion 500 kv Transmission Project

Artificial Island Proposal III Salem to Red Lion 500 kv Transmission Project Artificial Island Proposal III Salem to Red Lion 500 kv Transmission Project A Proposal To: PJM June 28, 2013 Page 1 of 69 Table of Contents 1. Table of Contents 1. Table of Contents... 2 2. Introduction

More information

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA For Compliance with NERC Reliability Standard: TPL-001-4 1/10/2017 Version: 4.2 Table of Contents 1 Revision and Approval History... 2 1.1 Revision

More information

SYSTEM OPERATING LIMITS IN THE PLANNING HORIZON FAC-010 COMPLIANCE

SYSTEM OPERATING LIMITS IN THE PLANNING HORIZON FAC-010 COMPLIANCE SYSTEM OPERATING LIMITS IN THE PLANNING HORIZON FAC-010 COMPLIANCE System Operating Limits (SOLs) in the planning horizon are required to be identified by FAC-010. This guideline describes how Duke Energy

More information

2012 NCTPC PJM Joint Interregional Reliability Study. PJM Interconnection. Duke Energy Carolinas. Progress Energy Carolinas

2012 NCTPC PJM Joint Interregional Reliability Study. PJM Interconnection. Duke Energy Carolinas. Progress Energy Carolinas 2012 NCTPC PJM Joint Interregional Reliability Study PJM Interconnection Duke Energy Carolinas Progress Energy Carolinas January 2013 1 Executive Summary The joint study consisted of a reliability analysis

More information

POTOMAC ELECTRIC POWER COMPANY

POTOMAC ELECTRIC POWER COMPANY POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission

More information

California Independent System Operator Renewable Integration Study

California Independent System Operator Renewable Integration Study California Independent System Operator Renewable Integration Study Clyde Loutan Proposed Transmission Plan for Integration of Renewables Transmission System Analysis - Overview Joint Study between the

More information

Standard TPL Transmission System Planning Performance Requirements

Standard TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

PID275 Feasibility Study Report 9.33 MW Distribution Inter-Connection Valentine Substation

PID275 Feasibility Study Report 9.33 MW Distribution Inter-Connection Valentine Substation PID275 Feasibility Study Report 9.33 MW Distribution Inter-Connection Valentine Substation Prepared by: Entergy Services, Inc. T & D Planning 639 Loyola Avenue L-ENT-17A New Orleans, LA 70113 Rev Issue

More information

Maine Public Service Transmission System Reliability

Maine Public Service Transmission System Reliability Maine Public Service Transmission System Reliability Presentation at the Northern Maine Planning Advisory Group 5/15/13 Today s Presentation will cover: Part I Assumptions & Methodology Assumptions used

More information

Platte River Power Authority. Ten-Year Transmission Plan ( )

Platte River Power Authority. Ten-Year Transmission Plan ( ) Platte River Power Authority Ten-Year Transmission Plan (2015-2024) Prepared by PRPA System Planning December 31, 2014 Table of Contents I. Executive Summary II. III. IV. Scope Assumptions Criteria V.

More information

Connection Study Requirements

Connection Study Requirements Document Release Released: September 20, 2010 The Customer shall comply with all the applicable requirements in this document when performing connection studies to produce the engineering study report.

More information

System Impact Study E001 Moon Lake 230 kv 200 MW Plant

System Impact Study E001 Moon Lake 230 kv 200 MW Plant System Impact Study E001 Moon Lake 230 kv 200 MW Plant Prepared by: Midcontinent Independent System Operator Independent Coordinator of Transmission 720 City Center Drive Carmel, IN 46032 Rev Issue Date

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1)

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1) (R1 FAC-010-AB-2.1) 1 Purpose This document sets out the System Operating Limits Methodology the Alberta Electric System Operator ( AESO ) uses for any studies conducted on the interconnected electric

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Standard Development Timeline

Standard Development Timeline Standard TPL-001-4 Transmission System Planning Performance Requirements Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be

More information

GENERATOR INTERCONNECTION FACILITY STUDY FOR BRIDGEWATER HYDRO POWER HOUSE REPLACEMENT BURKE COUNTY NC

GENERATOR INTERCONNECTION FACILITY STUDY FOR BRIDGEWATER HYDRO POWER HOUSE REPLACEMENT BURKE COUNTY NC GENERATOR INTERCONNECTION FACILITY STUDY FOR BRIDGEWATER HYDRO POWER HOUSE REPLACEMENT BURKE COUNTY NC Prepared by: Geno Price June 22, 2007 Revised Oct 19, 2007 TABLE OF CONTENTS INTRODUCTION... 3 BASELINE

More information

2750 Monroe Blvd Audubon, PA

2750 Monroe Blvd Audubon, PA 2750 Monroe Blvd Audubon, PA 19403-2497 October 21, 2014 Mr. Jonathan Feipel Executive Director Illinois Commerce Commission 527 East Capitol Avenue Springfield, Illinois 62701 Dear Mr. Feipel: This report

More information

XXXX. Bremner Trio Small Hydro Project. Interconnection System Impact Study

XXXX. Bremner Trio Small Hydro Project. Interconnection System Impact Study XXXX Bremner Trio Small Hydro Project Report No. August 2010 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2010. All rights reserved.. DISCLAIMER OF WARRANTY, LIMITATION

More information

AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS

AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS APPENDIX G AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS Transmission Planning Criteria - Basis and Assumptions Version 1.0 1. Introduction This document presents the reliability standards,

More information

FACILITIES STUDY GENERATOR INTERCONNECTION STUDY PID 240

FACILITIES STUDY GENERATOR INTERCONNECTION STUDY PID 240 TRANSMISSION LINE & SUBSTATION PROJECTS COMPANY:ENTERGY SERVICES, INC. CUSTOMER: FACILITIES STUDY EJO NO. F4PPAR0479 GENERATOR INTERCONNECTION STUDY Revision: 1 Rev Issue Date Description of Revision Prepared

More information

Standard MH-TPL Transmission System Planning Performance Requirements

Standard MH-TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: MH-TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

East Kentucky Power Cooperative (EKPC) Baseline RTEP Integration Report

East Kentucky Power Cooperative (EKPC) Baseline RTEP Integration Report East Kentucky Power Cooperative (EKPC) Baseline RTEP Integration Report Updated January 25, 2013 Table of Contents Table of Contents INTRODUCTION... 1 EXECUTIVE SUMMARY... 3 KEY FINDINGS... 5 OBJECTIVE

More information

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved.

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. ASSOCIATED NERC STANDARD(S): TPL-001-4 (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. Phase in of individual TPL-001 requirements will be based on the effective dates

More information

Transmission Expansion Advisory Committee. October 11, 2012

Transmission Expansion Advisory Committee. October 11, 2012 Transmission Expansion Advisory Committee October 11, 2012 Issues Tracking Issues Tracking Open Issues None New Issues 3 2012 RTEP - Renewable Portfolio Standards Scenarios Progress Update Scenario #1

More information

Oswego Complex Export Transient Stability. Limit Analysis. Prepared by Operations Engineering Staff New York Independent System Operator, Inc.

Oswego Complex Export Transient Stability. Limit Analysis. Prepared by Operations Engineering Staff New York Independent System Operator, Inc. Oswego Complex Export Transient Stability Limit Analysis Prepared by Operations Engineering Staff New York Independent System Operator, Inc. Approved by NYISO Operating Committee March 15, 2012 Caution

More information

Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES

Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES Effective Date: September 11, 2017 Revision History Date Version Description June 6, 1998 0.0 Initial LGEE document

More information

EIPC Interconnection-wide Webinar and Stakeholder Discussion. November 17, 2015

EIPC Interconnection-wide Webinar and Stakeholder Discussion. November 17, 2015 EIPC Interconnection-wide Webinar and Stakeholder Discussion November 17, 2015 Webinar Outline Presentation on 2025 Summer Peak (2025S) and 2025 Winter Peak (2025W) Roll-up Case Development Report to be

More information

TRC Solutions. Cost and Feasibility Analysis of a Third Converter Station for the Champlain Hudson Power Express Project

TRC Solutions. Cost and Feasibility Analysis of a Third Converter Station for the Champlain Hudson Power Express Project TRC Solutions Cost and Feasibility Analysis of a Third Converter Station for the Champlain Hudson Power Express Project October 2013 Table of Contents: I. Executive Summary II. Cost Estimate and Physical

More information

Energy Management System (EMS) Model Updates and Quality Assurance (QA)

Energy Management System (EMS) Model Updates and Quality Assurance (QA) PJM Manual 3A: Energy Management System (EMS) Model Updates and Quality Assurance (QA) Revision: 8 Effective Date: January 2, 2014 Prepared by: Operation Support Division PJM 2014 PJM 2007 Revision 0,

More information

Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board

Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board PJM Staff Whitepaper December 2015 EXECUTIVE SUMMARY The PJM Board of Managers previously approved changes to the Regional

More information

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria March 2016 Section 1 Overview and General Discussion The primary purpose of East Kentucky Power Cooperative s (EKPC s) transmission

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

NERC PLANNING STANDARDS

NERC PLANNING STANDARDS NERC PLANNING STANDARDS North American Electric Reliability Council April 2004 Version of All Planning Standards Terms and Their Definitions As Used in the Analysis (Study) an examination or simulation

More information

2013 Economic Study Report

2013 Economic Study Report 2013 Economic Study Report PPL EnergyPlus, LLC December 19, 2013 Electric Transmission Planning Table of Contents Executive Summary... 3 Study Constraints and Conditions... 4 Study Parameters... 5 Steady-State

More information

Black Hills Power, Inc Basin Electric Power Cooperative Powder River Energy Corporation

Black Hills Power, Inc Basin Electric Power Cooperative Powder River Energy Corporation Black Hills Power, Inc Basin Electric Power Cooperative Powder River Energy Corporation Transmission System Planning Methodology, Criteria and Process Business Practice December 07, 2007 Table of Contents

More information

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee Transmission Expansion Advisory Committee April 14, 2010 2010 RTEP Sensitivity Analysis Assumptions Renewable Portfolio Standards RPS Methodology Renewable portfolio standards by state Typically a target

More information

DRAFT STUDY PLAN FOR 2018

DRAFT STUDY PLAN FOR 2018 DRAFT STUDY PLAN FOR 2018 Introduction The Ten-year transmission planning process is intended to facilitate a timely, coordinated and transparent process that fosters the development of electric infrastructure

More information

Wide-Area Trans-Regional Northeast Reliability Assessment

Wide-Area Trans-Regional Northeast Reliability Assessment Wide-Area Trans-Regional Northeast Reliability Assessment Philip A. Fedora Kollin Patten Northeast Power Coordinating Council PowerWorld Corporation 1515 Broadway 43 rd Floor 1816 South Oak Street New

More information

Manual 01 Revision 36

Manual 01 Revision 36 Manual 01 Revision 36 Bilge Derin Engineer, Real-Time Data Mgmt Markets & Reliability Committee December 21, 2017 M01 R36 Changes Summary Section Change to/updated Impact 2.3.1 NERC references updated

More information

Kentucky State Report

Kentucky State Report Kentucky State Report July 2017 Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast 2. Markets Capacity Market Results Market Analysis 3. Operations Emissions

More information

Western Colorado Transmission Study Report

Western Colorado Transmission Study Report Submitted to Colorado Coordinated Planning Group Studies Performed By: Western Slope Study Group November 6, 2013 Updated February 11, 2014 Executive Summary Loads and transfer obligations on the Western

More information

Interconnection Feasibility Study

Interconnection Feasibility Study XXXXX Ditni Yoh Green Energy April 5, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights reserved. DISCLAIMER OF WARRANTY, LIMITATION OF LIABILITY

More information

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) Background On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) The CAISO s deliverability study methodology for resource adequacy purposes was discussed extensively in the CPUC

More information

PJM Regional Transmission Expansion Plan

PJM Regional Transmission Expansion Plan PJM Regional Transmission Expansion Plan 2016 Book 1 PJM 2016 RTEP in Review Book 2 Inputs and Process Book 3 Studies and Results February 28, 2017 Book 3: Preface Preface PJM DE DC IL IN KY MD MI NJ

More information

Limon 100 MW Wind Farm System Interconnection Study

Limon 100 MW Wind Farm System Interconnection Study Limon 100 MW Wind Farm System Interconnection Study October 27, 2004 Studies Conducted By: Garrett Durland Limon Wind Farm Impact Study I. Introduction In April 2004, Western Area Power Administration

More information

PSE&G Assumptions Overview. November 2018

PSE&G Assumptions Overview. November 2018 PSE&G Assumptions Overview November 2018 1 Base Case Models Base Case Model will includes PSE&G 69kV network PJM RTEP models shall be for assessments of RTEP years Multi-regional Modeling Working Group

More information

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: Service Requested

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: Service Requested Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #80439788, under the SaskPower Open Access Transmission Tariff (OATT). The purpose of

More information

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5 Methodology and Assumptions 1.1 Overview These sections describe the process we used to perform a network assessment of the ATC transmission system. The description includes study assumptions, methods

More information

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: IFHS MH MW, firm :00:00 CS

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: IFHS MH MW, firm :00:00 CS Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #80487374, under the SaskPower Open Access Transmission Tariff (OATT). The purpose of

More information

Proposed Facility Study Report. Project: A380_A383_A415_A414_A413 MISO # F088. Prepared for Midwest ISO

Proposed Facility Study Report. Project: A380_A383_A415_A414_A413 MISO # F088. Prepared for Midwest ISO Proposed Facility Study Report Project: A380_A383_A415_A414_A413 MISO # F088 Prepared for Midwest ISO January 15 th, 2010 Great River Energy Contact: Greg Schutte, Project Manager Great River Energy 1

More information

LOCAL PLANNING REPORT

LOCAL PLANNING REPORT Hydro One Networks Inc. 483 Bay Street Toronto, Ontario M5G 2P5 LOCAL PLANNING REPORT Woodstock Sub-region Restoration Region: London Area Date: May 19, 2017 Revision: Final Prepared by: Woodstock Sub-region

More information

I n t e g r a t e d T r a n s m i s s i o n P l a n n i n g N e a r - T e r m S c o p e. June 15, 2016 Engineering

I n t e g r a t e d T r a n s m i s s i o n P l a n n i n g N e a r - T e r m S c o p e. June 15, 2016 Engineering 2017 ITPNT 2 0 1 7 I n t e g r a t e d T r a n s m i s s i o n P l a n n i n g N e a r - T e r m S c o p e June 15, 2016 Engineering Revision History Date or Version Number Author Change Description Comments

More information

Transmission Interconnection Requirements. Table of Contents

Transmission Interconnection Requirements. Table of Contents Transmission Interconnection Requirements Table of Contents I. Introduction II. Interconnection Agreement III. Facility Requirements IV. Interconnection Initiation I. Introduction A. Purpose and Scope

More information

Standard TPL System Performance Following Extreme BES Events

Standard TPL System Performance Following Extreme BES Events A. Introduction 1. Title: System Performance Following Extreme Events Resulting in the Loss of Two or More Bulk Electric System Elements (Category D) 2. Number: TPL-004-1 3. Purpose: System simulations

More information

2018 GridLiance High Plains Planning Study Scope. Transmission Planning

2018 GridLiance High Plains Planning Study Scope. Transmission Planning 2018 GridLiance High Plains Planning Study Scope Transmission Planning July 16, 2018 Overview GridLiance and its subsidiary GridLiance High Plains LLC (GridLiance High Plains) will perform an annual system

More information

Winter Peak Study. Wenzheng Qiu Transmission Planning PJM 2015

Winter Peak Study. Wenzheng Qiu Transmission Planning PJM 2015 Winter Peak Study Wenzheng Qiu Transmission Planning Winter Peak Study Drivers Winter Peak is higher Summer Peak for several zones in PJM Area / Year PN METED JCPL PL PECO PSEG BGE PEPCO AE DPL UGI RECO

More information

PJM White Paper. Transource Independence Energy Connection Market Efficiency Project

PJM White Paper. Transource Independence Energy Connection Market Efficiency Project PJM White Paper PJM Interconnection November 15, 2018 This page is intentionally left blank. PJM 2018 www.pjm.com i P a g e Contents Highlights... 1 Executive Summary... 1 I. Introduction... 2 Reliability

More information

Transmission Losses Report 2015

Transmission Losses Report 2015 SP Energy Networks October 2015 Transmission Losses Report 2015 1. INTRODUCTION Special condition 2K of SPT s transmission licence requires SPT to publish an annual transmission losses report detailing

More information

Session 9: Photovoltaic System Case Studies And Electric Distribution Planning for DER October 21, 2015 Santiago, Chile

Session 9: Photovoltaic System Case Studies And Electric Distribution Planning for DER October 21, 2015 Santiago, Chile Session 9: Photovoltaic System Case Studies And Electric Distribution Planning for DER October 21, 2015 Santiago, Chile Michael Coddington National Renewable Energy Laboratory Golden, Colorado, U.S.A.

More information

Southwest Power Pool, Inc. Entergy ENTERGY SPP RTO REGIONAL PLANNING PROCESS MEETING June 16, 2011 NET CONFERENCE AGENDA 1:30 3:00 PM

Southwest Power Pool, Inc. Entergy ENTERGY SPP RTO REGIONAL PLANNING PROCESS MEETING June 16, 2011 NET CONFERENCE AGENDA 1:30 3:00 PM Southwest Power Pool, Inc. Entergy ENTERGY SPP RTO REGIONAL PLANNING PROCESS MEETING June 16, 2011 NET CONFERENCE AGENDA 1:30 3:00 PM 1. Administrative A. Introductions... All B. SPP Antitrust Guidelines...

More information

Western NY Public Policy Transmission Need: Updated Baseline Results

Western NY Public Policy Transmission Need: Updated Baseline Results Western NY Public Policy Transmission Need: Updated Baseline Results Zach Smith Director, Transmission Planning New York Independent System Operator ESPWG / TPAS October 29, 2015 2000-2015 New York Independent

More information

SERTP PJM Biennial Regional Transmission Plan Review

SERTP PJM Biennial Regional Transmission Plan Review SERTP PJM Biennial Regional Transmission Plan Review May 8, 2018 Transmission Coordination Between the SERTP and PJM Regions Selected points from Tariffs Interregional Transmission Coordination Coordinate

More information

Point to Point US to BC, BC to Alberta. and wheel through US to Alberta. System Impact Study

Point to Point US to BC, BC to Alberta. and wheel through US to Alberta. System Impact Study Point to Point US to BC, BC to Alberta and wheel through US to Alberta System Impact Study Report No. SPA 2007-85 November 2007 Transmission System Planning British Columbia Transmission Corporation British

More information

Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board

Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board PJM Staff Whitepaper April 2018 EXECUTIVE SUMMARY On February 13, 2018, the PJM Board of Managers approved changes to the

More information

Interconnection Feasibility Study

Interconnection Feasibility Study XXXXX Campbell River Power Enterprises Project April 5, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights reserved. DISCLAIMER OF WARRANTY, LIMITATION

More information

AEP Guidelines for Transmission Owner Identified Needs

AEP Guidelines for Transmission Owner Identified Needs AEP Guidelines for Transmission Owner January 2017 1 Document Control Document Review and Approval Action Name(s) Title Prepared by: Kevin Killingsworth Principal Engineer, Asset Performance and Renewal

More information

1.3 Planning Assumptions and Model Development

1.3 Planning Assumptions and Model Development Section 1: Process Overview Owner Initiated projects from past RTEP cycles that are yet to be placed in-service.) This website will provide tracking information about the status of listed projects and

More information

Critical Load Serving Capability by Microgrid using 100% Renewable Energy

Critical Load Serving Capability by Microgrid using 100% Renewable Energy 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Critical Load Serving Capability by Microgrid using 100% Renewable Energy P. PENKEY,

More information

Case Metrics 2015 Summer Base Case Quality Assessment Phase I Powerflow and Dynamics Case Quality Metrics FINAL

Case Metrics 2015 Summer Base Case Quality Assessment Phase I Powerflow and Dynamics Case Quality Metrics FINAL Case s 2015 Summer Base Case Quality Assessment Phase I Powerflow and Dynamics Case Quality s FINAL Introduction Powerflow and dynamics cases are the foundation of virtually all power system studies. Calculations

More information

MAY 1, Variable Generation Integration Costs

MAY 1, Variable Generation Integration Costs MAY 1, 2014 Variable Generation Integration Costs Executive Summary The addition of variable generation (wind and solar) to the electrical system introduces additional costs associated with unit dispatch

More information

2018 Assessment of Planning Transfer Capability for the Near Term Planning Horizon

2018 Assessment of Planning Transfer Capability for the Near Term Planning Horizon 2018 Assessment of Planning Transfer Capability for the Near Term Planning Horizon (NERC Standard FAC-013-2) A Report by the New York Independent System Operator June 11, 2018 Table of Contents 1. INTRODUCTION...

More information

Standard 600 Determine Facility Ratings, System Operating Limits, and Transfer Capabilities

Standard 600 Determine Facility Ratings, System Operating Limits, and Transfer Capabilities These definitions will be posted and balloted along with the standard, but will not be restated in the standard. Instead, they will be included in a separate Definitions section containing definitions

More information

Interconnection Feasibility Study

Interconnection Feasibility Study XXXXX Campbell River Power Enterprises Project April 5, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights reserved. DISCLAIMER OF WARRANTY, LIMITATION

More information

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS J O G Tande and K Uhlen SINTEF Energy Research, Norway SUMMARY Cost efficient utilisation of the wind energy resource requires wind farms to be located

More information

Distribution Information Exchange Code

Distribution Information Exchange Code Distribution Information Exchange Code Version 5.1 Approved September 2007 Comments to this document can be forwarded to: The RSA Grid Code Secretariat Attention: Mr. Bernard Magoro Eskom, Transmission

More information

Electric Power Systems An Overview

Electric Power Systems An Overview Electric Power Systems An Overview Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas Overview Power Generation Conventional and renewable power generation Power transmission

More information

Example of Information for EOL Projects. American Municipal Power October 19, 2017

Example of Information for EOL Projects. American Municipal Power October 19, 2017 Example of Information for EOL Projects American Municipal Power October 19, 2017 Baseline Project: Description of Project Add detailed map for all facilities mentioned for Problem Statement: PJM/NERC/TO

More information

NORTHERN TIER TRANSMISSION GROUP (NTTG) BIENNIAL TRANSMISSION PLAN. DRAFT SUMMARY REPORT - January 2013

NORTHERN TIER TRANSMISSION GROUP (NTTG) BIENNIAL TRANSMISSION PLAN. DRAFT SUMMARY REPORT - January 2013 NORTHERN TIER TRANSMISSION GROUP (NTTG) 2012-2013 BIENNIAL TRANSMISSION PLAN DRAFT SUMMARY REPORT - January 2013 Executive Summary: This report summarizes the findings of power flow studies to determine:

More information

DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA

DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA Transmission Planning Criteria Updated: March Compiled: September 2007 Compiled from: s Comprehensive Transmission Reliability Plan, July 2005 s Strategic

More information

GUYANA POWER AND LIGHT INC

GUYANA POWER AND LIGHT INC GUYANA POWER AND LIGHT INC The Terms of Reference REQUEST FOR PROPOSALS: CONSULTANCY SERVICES COORDINATING GENERATOR PROTECTION WITH TRANSMISSION PROTECTION AND GENERATOR CONTROLS (GPL-PI-094-2016) November

More information

Transmission System Security and Planning Standards

Transmission System Security and Planning Standards ver. 1.4 page 1 from 13 Transmission System Security and Planning Standards April 2014 ver. 1.4 page 2 from 13 TABLE OF CONTENTS 1 Introduction... 4 2 Definitions... 4 2.1 Transmission System... 4 2.2

More information

Grid Interconnection Issues for Wind Generation

Grid Interconnection Issues for Wind Generation Grid Interconnection Issues for Wind Generation NRECA APPA - DOE Teleconference December 8, 2005 By Thomas A. Wind, PE Wind Utility Consulting Jefferson, Iowa Topics I Will Cover What are the key technical

More information

Grid Integration of Renewable Energy. Robert S. Kaneshiro, P.E. Operations Assistant Superintendent Hawaii Electric Light Company (HELCO)

Grid Integration of Renewable Energy. Robert S. Kaneshiro, P.E. Operations Assistant Superintendent Hawaii Electric Light Company (HELCO) Grid Integration of Renewable Energy Robert S. Kaneshiro, P.E. Operations Assistant Superintendent Hawaii Electric Light Company (HELCO) October 2012 Contents HELCO System Overview Challenges of integrating

More information

Plant Load Factor: 50%

Plant Load Factor: 50% Current power sector scenario that also includes: Percentage of growth in generation: 6% (Energy) Percentage of growth in load demand: 10% Plant Load Factor: 50% Outage rate to assess the reliability of

More information