1 Stream Buffer Evaluation Report Snoqualmie Switch Station Improvements Snoqualmie, Washington for Puget Sound Energy February 23, 2016 Earth Science + Technology

2 Stream Buffer Evaluation Report Snoqualmie Switch Station Improvements Snoqualmie, Washington for Puget Sound Energy February 23, South Fawcett Avenue, Suite 200 Tacoma, Washington

3 Stream Buffer Evaluation Report Snoqualmie Switch Station Improvements Snoqualmie, Washington File No February 23, 2016 Prepared for: Puget Sound Energy th Avenue NE, PSE-04E Bellevue, Washington Attention: Jeff McMeekin Prepared by: GeoEngineers, Inc South Fawcett Avenue, Suite 200 Tacoma, Washington Jennifer L. Dadisman, PWS Staff Biologist Joseph O. Callaghan, MS, PWS Associate Biologist JLD:JOC:ab Disclaimer: Any electronic form, facsimile or hard copy of the original document ( , text, table, and/or figure), if provided, and any attachments are only a copy of the original document. The original document is stored by GeoEngineers, Inc. and will serve as the official document of record.

4 Table of Contents INTRODUCTION... 1 Project Location... 1 Site Description... 1 PROJECT DESCRIPTION... 1 Minimization Measures... 1 DATA REVIEW... 2 METHODOLOGY... 2 FIELD INVESTIGATION... 3 Wetland and Stream Delineation... 3 ASSESSMENT OF PROJECT EFFECTS... 5 BUFFER MITIGATION PLAN... 5 Goals and Objectives... 6 Buffer Enhancement... 6 Invasive Species Control... 6 Planting Plan... 6 Functional Analysis of the Buffer... 7 MAINTENANCE, MONITORING AND CONTINGENCY... 7 Maintenance... 7 Monitoring Plan... 8 Performance Standards... 8 As-Built Design Report... 9 Monitoring Stations... 9 Data Collection... 9 Monitoring Reports and Schedule Contingency Plan CONCLUSIONS LIMITATIONS REFERENCES LIST OF FIGURES Figure 1. Vicinity Map Figure 2. OHWM and Buffer Location APPENDICES Appendix A. Site Photographs Appendix B. Mapped Data Appendix C. Lanscape Plan February 23, 2016 Page i File No

5 INTRODUCTION GeoEngineers, Inc. (GeoEngineers) was contracted by Puget Sound Energy (PSE) to provide critical areas reporting and construction support for the Snoqualmie Switch Station Improvements project. As part of this project, stormwater improvements are proposed within the facility that includes installation of a pipe to collect stormwater and release it to an existing outfall that discharges to the Snoqualmie River. Our critical area evaluation services included performing habitat evaluations on the area where the pipe is proposed. The project is located approximately 500 feet above the Snoqualmie River Falls in Snoqualmie, Washington (Figure 1 - Vicinity Map). This report was completed, in part, to identify and address requirements of the City of Snoqualmie (City) Municipal Code (SMC) Title 19 (Environment), Chapter (Sensitive Areas). Project Location The project is located at the existing Snoqualmie Switch Station located south of Railroad Avenue, in Snoqualmie, Washington. The site is approximately 500 feet above the Snoqualmie River Falls, on the northern bank of the river. See Figure 1 for the site location on the Vicinity Map. The project area is located within Section 30 of Township 24 North and Range 08 East of the Willamette Meridian (W.M.). Our critical areas evaluation services included performing habitat evaluations on the area where the pipe is proposed. This area is partially located within the Snoqualmie River buffer. Figure 2 depicts the buffer and project vicinity. Site Description The project site is situated in a developed area. The switch station is located on top of a hill, and the southern area slopes down steeply to a paved road used by PSE for maintenance of the Snoqualmie Falls facility. The steep sloped area, south of the substation is mainly composed of Himalayan blackberry (Rubus armeniacus). South of the paved road a small, approximately 20- to 40-foot riparian buffer exists that is composed of invasive species and young forested vegetation such as Douglas fir (Pseudotsuga menziesii), red alder (Alnus rubra), Himalayan blackberry, and scotch broom (Cytisus scoparius). Appendix A contains photographs of the project site and vicinity. PROJECT DESCRIPTION As part of the overall improvements, the project includes installing a catch basin and vault for stormwater collection and installing an 18-inch-diameter high-density polyethylene (HDPE) pipe to direct the stormwater from the vault into an existing catch basin down slope of the switching station. This pipe will be partially located within the Snoqualmie River buffer. Minimization Measures Minimization measures and best management practices (BMPs) will be utilized during project activities to avoid impacts to critical area habitats. Conservation measures will focus on minimizing construction noise and the possibility of spills, preventing soil erosion, and minimizing impacts to riparian vegetation. Special measures will be taken to ensure that: all waste materials will be disposed of offsite and in accordance with applicable regulations; adequate materials and procedures are readily available on the site to respond to unanticipated weather conditions or accidental releases of materials; and that a protocol for contacting February 23, 2016 Page 1 File No

6 Washington State Department of Ecology (Ecology) is readily available in the event that water quality problems occur. DATA REVIEW Environmental maps of the project area were collected and reviewed as part of a review of published data. The United States Fish and Wildlife Service (USFWS) National Wetlands Inventory (NWI) online mapper does not show wetland habitat on the project site. The river in the vicinity of the project is mapped as a lacustrine unconsolidated bottom system that is permanently flooded (L1UBH) (USFWS, 2016). The United States Department of Agriculture (USDA) Natural Resources Conservation Service (NRCS) Web Soil Survey indicates one soil type on the property: Barneston gravelly ashy course sandy loam, 0 to 8 percent slopes (USDA-NRCS, 2013). Barneston gravelly ashy course sandy loam soils are not hydric but do contain hydric inclusions (USDA-NRCS, 2015). NWI and soil survey information are included in Appendix B. Additional information was obtained from the Washington State Department of Natural Resources (DNR) Forest Practices Application Review System (FPARS), and Washington State Department of Fish and Wildlife (WDFW) Priority Habitat and Species (PHS) mapping application (DNR, 2015; WDFW, 2016). Both PHS and DNR map the Snoqualmie River at the project site (DNR, 2015; WDFW, 2016). DNR types this stream as Type S waterbody and PHS maps rainbow trout (Oncorhynchus mykiss), cutthroat trout (Oncorhynchus clarki) and Dolly Varden/bull trout (Salvelinus malma) within the river (DNR, 2015; WDFW, 2016). The Snoqualmie River flows north and west and eventually discharges into the Snohomish River (DNR, 2015). The King County IMap (King County, 2016) was also reviewed; the IMap depicts the Snoqualmie River but does not map wetland habitat on, or adjacent to, the project site. METHODOLOGY The identification of aquatic critical areas (wetlands and streams) was conducted in accordance with guidelines presented in SMC Title 19, Chapter (Sensitive Areas). The Washington State Wetlands Identification and Delineation Manual (Ecology, 1997), the U.S. Army Corps of Engineers (USACE) Wetlands Delineation Manual (Environmental Laboratory, 1987) and the Regional Supplement to the Corps of Engineers Wetland Delineation Manual: Western Mountains, Valleys, and Coast Region (USACE, 2010) were used to identify potential wetland habitat. Wetland buffer widths were identified from SMC (G), which specifies wetland buffer widths based on the wetland category and land use intensity. The Ordinary High Water Mark (OHWM) is used to define the jurisdictional boundary of streams and rivers according to the Clean Water Act, Washington State Growth Management Act, Washington State Shoreline Management Act, and local critical areas ordinances. The OHWM of streams is typically evaluated by examining breaks in the topography, drift lines, shifts in vegetation and signs of water marks, according to USACE protocol as referenced from Regulatory Guidance Letter (No ), OHWM Identification, (Riley, 2005). The Washington Administrative Code (WAC) was also referenced for the definition of OHWM (WAC ). Due to the high water levels of the season affecting typical OHWM indicators, the OHWM was not identified in the field and instead the ordinary high water (OHW) level elevation was identified by PSE. February 23, 2016 Page 2 File No

7 In addition, streams are classified based on SMC (A), which divides streams into three classes based on fish use and stream type. Stream buffer widths are identified based on stream classification according to SMC (D). The City of Snoqualmie will make the final determination of buffer widths. FIELD INVESTIGATION Wetland and Stream Delineation A GeoEngineers biologist conducted a field assessment on February 9, 2016 to characterize wetland and stream features within the project area. Representative photographs of the site have been included within this report and in Appendix A. Wetland habitat was not identified within the project site. Figure 2 depicts the buffer of the Snoqualmie River within the project area. As discussed above, no wetland habitat was identified within, or adjacent to, the project site. The Snoqualmie River buffer is disturbed and contains riprap adjacent to the river, paved roads, and existing vegetation is predominantly composed of invasive species such as Himalayan blackberry. The area where the pipe will be located (Appendix A, Photographs 1 and 2), is dominated by Himalayan blackberry. Native vegetation will not be removed from the buffer as a result of the stormwater project. Table 1 on the following page summarizes information regarding the Snoqualmie River features within the area of investigation. February 23, 2016 Page 3 File No

8 TABLE 1. SNOQUALMIE RIVER Snoqualmie River Information Location WRIA Local Jurisdiction DNR Stream Type Snoqualmie Stream Type 500 feet above the falls 7 Snohomish City of Snoqualmie Shoreline I 1 Buffer Width 100 feet 2 Average Channel Width Gradient Duration 230 feet 3 0 to 3 percent Perennial Description Summary Documented Fish Use Connectivity Channel Description Riparian/Buffer Condition Rainbow trout (Oncorhynchus mykiss), cutthroat trout (Oncorhynchus clarki) and Dolly Varden/bull trout (Salvelinus malma) 4. Flows north and west and eventually discharges to the Snohomish River. Sediments, gravels and sands. The Snoqualmie River buffer is disturbed and contains riprap adjacent to the river, paved roads, and existing vegetation is predominantly dominated by invasive species such as Himalayan blackberry. There is a small forested strip (approximately 20 to 40 feet wide) adjacent to the river. This forested strip is composed of young Douglas fir and red alder trees with an understory dominated by invasive species. Notes: 1. SMC Chapter A stream is mapped by DNR FPARS as being a shoreline of the state at the project area. WDFW maps this portion of the stream as containing salmonid species. 2. SMC Chapter (D) ( Stream Buffers ). 3. Average Channel Width derived from GoogleEarth measurements. 4. Washington State Department of Fish and Wildlife (WDFW) PHS data (WDFW, 2016). February 23, 2016 Page 4 File No

9 ASSESSMENT OF PROJECT EFFECTS As a result of the proposed project, the potential stream effects will be minor. The project will not affect stream hydrology and flood storage capacity will not change because the site will be restored to pre project conditions after installation of the pipe. In addition, no work will be completed in stream channel. Project effects that are expected to occur as a result of the project will be from the installation of the 18-inch HDPE pipe. The pipe is proposed within a portion of the Snoqualmie River buffer that is dominated by invasive species. There will be no work conducted below the OHWM of the river. The 18-inch pipe will be placed on the existing grade and lie on the surface. The pipe will be connected to the outfall at the bottom of the slope below the switch station. Effects of the proposed action are defined as the direct and indirect effects of an action on the species or critical habitat, together with the effects of other activities that are interrelated or interdependent with the action, that will be added to the environmental baseline (50 CFR ). Project-related effects are confined to the project area. This section provides an analysis of the anticipated effects. The following effects would likely occur for the proposed project: Construction Related Noise. Construction activity and noise in excess of background conditions generated during the project could permeate terrestrial habitats around the project site. This effect will be temporary in nature and will not persist upon project completion. Water Quality Degradation. Water quality degradation is limited to the footprint of the project and is considered to be a temporary effect. Hazardous Material Spills. Potential impacts to water quality, such as spilling hazardous materials or petroleum based products associated with construction machinery, will be controlled through proper implementation of BMPs and are, therefore, not expected to have negative impacts on the environment. Sediments. There is potential for temporary water quality impacts to occur as a result of fine sediments traveling away from the project if sediments are released into the stream. Any potential impacts are expected to be temporary and minor and will be controlled through proper implementations of the temporary erosion and sedimentation control (TESC) plan. Habitat Alteration. Habitat alteration will be limited to the actual footprint of the project, which for the project, will occur within an area with no trees and only dominated by Himalayan blackberry. Also, as part of the proposed project, a landscape plan has been developed along the southern steep slope; approximately 1,500 square feet of buffer will have invasive species removed and tree and shrub species will be installed. Appendix C contains the landscape planting plan for the project. Buffer Impacts. Approximately 75 square feet (50 feet long by 1.5 feet wide) of buffer habitat will be disturbed as a result of the proposed stormwater pipe alignment. The buffer impacts are minimal because the area is dominated by Himalayan blackberry, and the area where vegetation is removed will be re-planted with a native vegetation community. BUFFER MITIGATION PLAN The buffer habitat restoration of the impact area will include overplanting of the impact area with native species. Approximately 1,500 square feet of buffer will be enhanced (invasive species removal and replanting with trees and shrubs) to compensate for approximately 75 square feet of buffer impacts. February 23, 2016 Page 5 File No

10 Appendix C contains the landscape planting plan that is proposed as mitigation for this project. The landscaping plan will mitigate for potential effects from loss of vegetation and disturbance to the buffer. Invasive plant species will be removed and trees and shrubs will be installed in the disturbed areas. The number of plants to be installed and the locations are depicted in the landscape plan prepared for the project (Appendix C). Goals and Objectives Buffers, in good condition, should perform many functions that include: water quality, thermal cover and temperature moderation for aquatic species and habitat features such as food, cover, nesting, perches and wildlife corridors. Baseline conditions are currently degraded within the buffer and many of these functions could be improved. Re-planting the buffer with tree and shrub species will offset project impacts through compensatory gains in buffer functions. This will include installing habitat enhancements such as shrubs and trees in the mitigation site, which can slow and detain water flow that otherwise may flood the Snoqualmie River channel and cause erosional damage to downstream areas. These actions will be performed with the following specific objectives for the buffer: Increase the potential to improve hydrologic functions; Increase the potential to improve water quality functions; Increase the vegetative diversity; and Increase the habitat structure for the buffer. Buffer Enhancement Approximately 1,500 square feet will be replanted with trees and shrubs to compensate for impacts associated from the proposed project. The buffer enhancement activities within this mitigation plan will be accomplished through the following actions: Initial removal of invasive plant species; and Install appropriate tree and shrub vegetation in the buffer habitat. Invasive Species Control Invasive species identified within the mitigation area included Himalayan blackberry. These invasive plants will be removed and tall growing species, capable of providing shade, will be planted throughout the mitigation site. Planting Plan Proposed planting areas and species are identified in the landscape planting plan within Appendix C. Planting activities should generally follow (as applicable) and be timed as follows: 1. Remove invasive and non-native species, and remove debris as needed. 2. Amend area with clean soils as needed. 3. Conduct the planting immediately after soil amendments are placed and in conjunction with the clearing and removal of debris. This will minimize re-growth of invasive species in newly opened or cleared areas. February 23, 2016 Page 6 File No

11 4. Ideally, planting should be conducted in the early spring or late fall during the dormant season. Staging areas for plants should occur in upland areas. 5. Install tree guards as needed around newly installed vegetation to discourage grazing/browsing by deer and rodents. 6. Add mulch as indicated on the landscape plan (Appendix C). 7. Hand water newly planted areas as needed. 8. Conduct regular maintenance and monitoring as described in the Maintenance, Monitoring and Contingency section of this report. Functional Analysis of the Buffer Once the goals and objectives of this mitigation plan are met through implementation of the plan, functions and values of the buffer are expected to become greater than existing functions. Enhanced areas will have additional opportunities to increase water quality and hydrologic functions to aid in reducing pollutants prior to entering Snoqualmie River, as well as reducing flooding events and increase natural screening of water pollutants and sediments. Planting the tree and shrub vegetation will increase native tree and shrub cover within the project area. MAINTENANCE, MONITORING AND CONTINGENCY The mitigation area will be maintained and monitored in accordance with recommendations outlined in the SMC, which states that monitoring programs will last a minimum of five years and up to 10 years for forested and scrub/shrub wetland communities. We propose to monitor the mitigation site for a period of five years since it is a small area, it is a portion of the buffer that is currently dominated by Himalayan blackberry, which is easily controlled and will be replanted with tree and shrub species. A contingency plan will be implemented if performance standards are not met in the buffer enhancement area. Maintenance Proper maintenance of the planted areas is crucial to plant survival. Maintenance will be conducted throughout the monitoring period. Typical maintenance activities will include: Hand water plants if plants are becoming drought stressed; Re-mulching as needed to control competition from non-native invasive species; Removal of trash, litter and other debris that may accumulate; and Removal of Himalayan blackberry from around newly installed plants, if the invasive species are affecting plant survival. To ensure success of the installed vegetation, non-native invasive species may need to be maintained by hand or mechanical removal as needed. Only desirable native volunteer species in addition to those planted will be encouraged to grow. February 23, 2016 Page 7 File No

12 Monitoring Plan Monitoring will occur for five years after the planting has been completed and an as-built record prepared. Reports will be prepared following Years 1, 2, 3 and 5. If the site is successful (meeting performance standards) a release letter will be requested from the appropriate jurisdiction. The reports will be prepared at the end of each year and document findings from the previous years site visits. Observations to be recorded during each monitoring event include plant survival and growth rates and wildlife occurrences. Photographs will also be taken at each monitoring event to document the evolution of the site over the monitoring period. Monitoring reports with a photographic log will be submitted by the end of the year. The reports will describe the condition of the mitigation area. Maintenance requirements such as trash removal, vandalism, invasive species removal and watering of plants will also be noted in the monitoring report. All planted species will have a minimum of 80 percent survival throughout the monitoring period. Survival of the plantings will be determined by counting and documenting the numbers of dead versus live plants. Species, quantities, general conditions and sizes of enhancement plants will be described and recorded. If the project fails to meet the standards discussed below, implementation of a contingency plan will be required. Performance Standards Performance standards provide benchmarks against which the success of the mitigation plan may be evaluated. Performance standards will be evaluated during each monitoring event through the collection of quantitative data as described above. Failure to meet the performance standards will trigger immediate corrective action. The performance standards discussed below have been developed from the constraints listed above in the baseline conditions section of the report. The performance standards are designed to measure key elements of the mitigation plan that have been designed to improve water quality and habitat functions. WATER QUALITY FUNCTIONS Numerous studies show that sediment and pollutants can be filtered out more quickly in areas containing dense herbaceous vegetation than in areas that lack a dense herbaceous vegetation community (Sheldon et al., 2005 and Castelle et al., 1992). Slopes less than 5 percent were the most successful in removing sediment from water. Therefore, the water quality function performance standard includes: Acceptable cover for native emergent (volunteers), shrub (installed and volunteer) and tree (installed and volunteer) species within each monitoring station will be a minimum of 20 percent during Year 1 and show distinct increases during each subsequent year. HABITAT FUNCTIONS Dense shrub and forested vegetation communities within areas connected to undisturbed wetland or upland habitat are considered to have a relatively high quality habitat value (Sheldon et al., 2005 and Castelle et al., 1992). Although there is a potential to increase richness of wildlife, a performance standard will not be established for wildlife. Therefore, performance standards relating to habitat functions will focus on the installed plantings. These performance standards include: There shall be a minimum of 80 percent survival of all planted species throughout the monitoring period. Survival will be determined by counting and documenting the numbers of dead versus live February 23, 2016 Page 8 File No

13 plants within each monitoring station. Volunteer recruits into a monitoring station may be counted toward offsetting dead planted individuals. In addition to this habitat function performance standard, observations will be made and recorded for wildlife use. As-Built Design Report The first step in implementing an effective monitoring regime is to document initial site conditions in an as-built report. This report will be prepared after planting of the mitigation areas is complete. The report will include the following information: Responsible parties (designer, construction contractors, planting contractor, qualified wetland scientist); Construction timeline (including completion date); Plant numbers and condition at established monitoring stations; Changes to the original plan; Problems encountered during construction and corrective measures taken; and Follow-up actions required (e.g., maintenance), if any, including a schedule and the responsible party that will complete these actions. Monitoring Stations Permanent monitoring stations will be established within the buffer during the as-built monitoring event. The number of monitoring stations, as well as location and extent of each station, will be determined by the monitoring biologist during preparation of the as-built documentation. The monitoring stations should be representative of typical conditions within the mitigation area. The location of each station will be marked with a durable stake or metal post. The permanent stations will be numbered to facilitate consistent documentation between subsequent monitoring events. Data Collection Data collection will be focused on recording plant survival and growth. Wildlife occurrences will also be noted at each of these stations throughout the monitoring period because a goal is to create habitat valuable to a variety of wildlife species. Specifically, the following information will be collected and recorded: Photographs. Photographs will be taken in each of the four cardinal directions from the center of the plot. Plant Survival Ratios. Counts of both dead and live plants will be conducted for each species. The general condition of plants, such as observations of new growth and signs of stress or disease, will also be noted. Plant Cover. Percent cover of each species, including both desirable and invasive, will be estimated. Wildlife. Recordings of wildlife observations will be made as general notes by the monitoring biologist during monitoring events. Performance standards have not been established for wildlife. Observations may include sighting of individual species, nests, burrows, droppings or other indicators. The results will be recorded and included in the monitoring report. February 23, 2016 Page 9 File No

14 Maintenance Requirements. The need for invasive species control, trash removal, watering or vegetation trimming will be noted and included in the monitoring report. Monitoring Reports and Schedule Monitoring will occur for a minimum of five years (Years 1, 2, 3 and 5). The first observation event will occur in the fall following the completion of the vegetation installation. Subsequent monitoring events will occur as listed above in the monitoring plan section. Monitoring reports will be submitted annually and each monitoring event will be documented in a monitoring report that summarizes the condition of the mitigation area with respect to the performance standards identified above. Monitoring reports will be submitted to PSE to distribute as needed. The reports should contain the following elements: Project information (project name and location, name and address of responsible party, any applicable project permit numbers, date project was constructed); Mitigation site information (location of the mitigation site, size and type(s) of habitats included in the mitigation plan, date mitigation site construction was completed); A description of monitoring requirements (name and address of party conducting the monitoring, map of the mitigation site including locations of monitoring stations, dates of previous monitoring events, date of the current or most recent monitoring event); A brief summary of previous monitoring results, maintenance performed and contingency actions undertaken at the mitigation site, including a description of any significant events that occurred on the site that may affect ultimate mitigation success; A list of performance standards; Data from the current monitoring event; A description of whether performance standards were met based on analysis of data collected during the current monitoring event; and Photographs of the site taken from each monitoring station during the most recent monitoring event. Contingency Plan If the planted areas fail to meet the standards discussed above, implementation of a contingency plan will be required. The proposed efforts can fail if certain unfavorable factors occur. Human activity, fire, erosion, invasive plant species, settling and disease may have a negative effect on newly planted vegetation. Plants obtained for this project may be diseased or become diseased over time and result in poor survival rates. Monitoring notes should include observations regarding these and other possible problems that may occur over the monitoring period. As problems are recorded, suggestions and possible solutions should be forwarded to the appropriate staff at the appropriate jurisdictional agency as a component of the monitoring reports. If more than 20 percent mortality of plantings occurs within any of the monitoring years, the mitigation plan will be re-evaluated. If alternative plant species are needed to improve survival, the selection of alternative species will be made by the monitoring biologist and approved by PSE and the local regulatory agency. Contingency measures could include but are not limited to: February 23, 2016 Page 10 File No

15 The plants will be hand watered as needed to offset drought stress on installed plants. Grasses will be mowed or trimmed around installed plants if the grasses are outcompeting and stressing native plants. The mitigation area will be over-planted with appropriate tree species, such as willow, if the installed tree species do not survive. Photographic records and monitoring data will be used to identify the need for contingency plan activation. The success of the plan is dependent upon enhancement proposed for the buffers with the component characteristics described in this report. The applicant is responsible for all costs associated with the contingency plan or corrective actions including materials and labor for replanting and maintenance. CONCLUSIONS GeoEngineers performed wetland and stream evaluation services to provide baseline information within the project area. No wetlands were identified on, or adjacent to, the project site. The Snoqualmie River was identified during the field investigation. The Snoqualmie River is a Class 1 shoreline of the state waterbody and will have a 100-foot buffer according to SMC (D). Approximately 75 square feet of disturbed buffer habitat will be impacted as a result of the proposed project. This impact will be mitigated with approximately 1,500 square feet of invasive species removal and replanting with native tree and shrub species. Appropriate TESC BMP s and construction measures will be implemented and maintained throughout construction to minimize/prevent direct impacts to the river and associated buffer. LIMITATIONS GeoEngineers has prepared this Critical Areas Evaluation Report in general accordance with the scope and limitations of our proposal. Within the limitations of scope, schedule and budget, our services have been executed in accordance with the generally accepted practices for wetland delineation in this area at the time this report was prepared. No warranty or other conditions, express or implied, should be understood. This report has been prepared for the exclusive use of Puget Sound Energy, authorized agents and regulatory agencies following the described methods and information available at the time of the work. No other party may rely on the product of our services unless we agree in advance to such reliance in writing. The information contained herein should not be applied for any purpose or project except the one originally contemplated. The applicant is advised to contact all appropriate regulatory agencies (local, state and federal) prior to design or construction of any development to obtain necessary permits and approvals. February 23, 2016 Page 11 File No

16 REFERENCES Cowardin, L.M., V. Carter, F.C. Golet, and E.T. LaRoe Classification of Wetland and Deep Water Habitats of the United States. Performed for Office of Biological Services, Fish and Wildlife Service, U.S. Department of the Interior, Washington, D.C. Environmental Laboratory U.S. Army Corps of Engineers Wetlands Delineation Manual, Technical Report Y-87-1, U.S. Army Engineer Waterways Experiment Station, Vicksburg, Massachusetts. King County IMAP. Available at: Riley, Don T Ordinary High Water Mark Identification. United States Army Corps of Engineers (USACE), Regulatory Guidance Letter, No ). United States Army Corp of Engineers (USACE) Western Mountains, Valleys, and Coast 2013 Regional Wetland Plant List, US Army Corps of Engineers, Cold Regions Research and Engineering Laboratory. Available at: C_2013v1.pdf. United States Army Corps of Engineers (USACE) Regional Supplement to the Corps of Engineers Wetland Delineation Manual: Western Mountains, Valleys, and Coast Region, ed. J.S. Wakeley, R. W. Lichvar, and C.V. Noble. ERDC/EL TR Vicksburg, MS: U.S. Army Engineer Research and Development Center. United States Department of Agriculture National Resource Conservation Service (USDA-NRCS) National Hydric Soils List by State. United States Department of Agriculture National Resource Conservation Service (USDA-NRCS) Web Soil Survey. Available at: United States Fish and Wildlife Service (USFWS) Wetlands Mapper. Available at: Washington State Administrative Code WAC Definitions. Available at: Washington State Administrative Code WAC Water Typing System. Available at: Washington State Administrative Code WAC Interim Water Typing System. Available at: Washington State Department of Ecology (Ecology) Washington State Wetlands Identification and Delineation Manual. Publication No Washington State Department of Fish and Wildlife (WDFW) Priority Habitats and Species (PHS) on the Web. Available at: February 23, 2016 Page 12 File No

17 Washington State Department of Natural Resources (DNR) Forest Practices Application Review System (FPARS) Mapping Application. Available at: Type&extent= , , , February 23, 2016 Page 13 File No

18 P:\0\ \GIS\MXDs\ _F01_VicinityMap.mxd Date Exported: 02/22/16 by cchelf SITE 2,000 µ 0 2,000 Feet Notes: 1. The locations of all features shown are approximate. 2. This drawing is for information purposes. It is intended to assist in showing features discussed in an attached document. GeoEngineers, Inc. cannot guarantee the accuracy and content of electronic files. The master file is stored by GeoEngineers, Inc. and will serve as the official record of this communication. Data Source: Mapbox Open Street Map, 2016 Projection: NAD 1983 UTM Zone 10N Vicinity Map Snoqualmie Switch Station Improvements Snoqualmie, Washington Figure 1

19 SE Snoqualmie Switch Station P:\0\ \GIS\MXDs\ _F02_OWHMandBufferLocation.mxd Date Exported: 02/22/16 by cchelf C ity Sno q ua lmie Rd Approximate Pipe Location PSE Mainten an Sn o q u a Fa ll ce Road l mie R iv er Notes: 1. The locations of all features shown are approximate. 2. This drawing is for information purposes. It is intended to assist in showing features discussed in an attached document. GeoEngineers, Inc. cannot guarantee the accuracy and content of electronic files. The master file is stored by GeoEngineers, Inc. and will serve as the official record of this communication. Data Source: King County Aerial 2013 Projection: NAD 1983 HARN StatePlane Washington South FIPS 4602 Feet Legend Approximate OHWM 100 Foot Buffer 50 µ 0 Feet OHWM and Buffer Location 50 Snoqualmie Switch Station Improvements Snoqualmie, Washington Figure 2

20 APPENDIX A Site Photographs

21 Photograph 1. Looking towards the south and the Snoqualmie River from the east end of the switch station. Photograph 2. Looking northeast at the slope where the pipe will be installed. Dominant vegetation consists of Himalayan blackberry. This area is located within the Snoqualmie River buffer Date Exported: 02/23/16 Site Photographs Snoqualmie Switch Station Improvements Snoqualmie, Washington Appendix A

22 Photograph 3. Looking northwest. The switch station and project area are on the right side of the photograph and the Snoqualmie River is on the left side. The paved roadway is used for maintenance of the Snoqualmie Falls PSE facility. Photograph 4. Looking north from the bank of the Snoqualmie River. OHWM indicators include bank erosion (towards the bottom of the photo). The topography slopes up towards the road and switch station (towards the top of the photo) Date Exported: 02/23/16 Site Photographs Snoqualmie Switch Station Improvements Snoqualmie, Washington Appendix A

23 Photograph 5. Looking towards the west and towards the falls from the bank of the Snoqualmie River. Photograph 6. Looking south across the Snoqualmie River towards the southern bank Date Exported: 02/23/16 Site Photographs Snoqualmie Switch Station Improvements Snoqualmie, Washington Appendix A

24 Photograph 7. Looking southeast at the existing outfall to the Snoqualmie River. Photograph 8. The outfall discharges to the Snoqualmie River in this area. This is looking down the slope from the outfall Date Exported: 02/23/16 Site Photographs Snoqualmie Switch Station Improvements Snoqualmie, Washington Appendix A

25 APPENDIX B Mapped Data

26 Feb 11, 2016 User Remarks: This map is for general reference only. The US Fish and Wildlife Service is not responsible for the accuracy or currentness of the base data shown on this map. All wetlands related data should be used in accordance with the layer metadata found on the Wetlands Mapper web site.

27 121 50' 16'' W Soil Map Snoqualmie Pass Area, Washington (Parts of King and Pierce Counties) ' 58'' W 47 32' 35'' N 47 32' 19'' N ' 35'' N 47 32' 19'' N ' 16'' W N Map Scale: 1:2,410 if printed on A portrait (8.5" x 11") sheet. Meters Feet Map projection: Web Mercator Corner coordinates: WGS84 Edge tics: UTM Zone 10N WGS ' 58'' W Natural Resources Conservation Service Web Soil Survey National Cooperative Soil Survey 2/11/2016 Page 1 of 3

28 Soil Map Snoqualmie Pass Area, Washington (Parts of King and Pierce Counties) MAP LEGEND MAP INFORMATION Area of Interest (AOI) Area of Interest (AOI) Soils Soil Map Unit Polygons Soil Map Unit Lines Soil Map Unit Points Special Point Features Blowout Borrow Pit Clay Spot Closed Depression Gravel Pit Gravelly Spot Landfill Lava Flow Marsh or swamp Mine or Quarry Miscellaneous Water Perennial Water Rock Outcrop Saline Spot Sandy Spot Severely Eroded Spot Sinkhole Slide or Slip Sodic Spot Spoil Area Stony Spot Very Stony Spot Wet Spot Other Special Line Features Water Features Streams and Canals Transportation Rails Interstate Highways US Routes Major Roads Local Roads Background Aerial Photography The soil surveys that comprise your AOI were mapped at 1:24,000. Warning: Soil Map may not be valid at this scale. Enlargement of maps beyond the scale of mapping can cause misunderstanding of the detail of mapping and accuracy of soil line placement. The maps do not show the small areas of contrasting soils that could have been shown at a more detailed scale. Please rely on the bar scale on each map sheet for map measurements. Source of Map: Natural Resources Conservation Service Web Soil Survey URL: Coordinate System: Web Mercator (EPSG:3857) Maps from the Web Soil Survey are based on the Web Mercator projection, which preserves direction and shape but distorts distance and area. A projection that preserves area, such as the Albers equal-area conic projection, should be used if more accurate calculations of distance or area are required. This product is generated from the USDA-NRCS certified data as of the version date(s) listed below. Soil Survey Area: Snoqualmie Pass Area, Washington (Parts of King and Pierce Counties) Survey Area Data: Version 14, Sep 14, 2015 Soil map units are labeled (as space allows) for map scales 1:50,000 or larger. Date(s) aerial images were photographed: Jul 25, 2010 Aug 19, 2010 The orthophoto or other base map on which the soil lines were compiled and digitized probably differs from the background imagery displayed on these maps. As a result, some minor shifting of map unit boundaries may be evident. Natural Resources Conservation Service Web Soil Survey National Cooperative Soil Survey 2/11/2016 Page 2 of 3

29 Soil Map Snoqualmie Pass Area, Washington (Parts of King and Pierce Counties) Map Unit Legend Snoqualmie Pass Area, Washington (Parts of King and Pierce Counties) (WA634) Map Unit Symbol Map Unit Name Acres in AOI Percent of AOI 10 Barneston gravelly ashy coarse sandy loam, 0 to 8 percent slopes 163 Ogarty gravelly loam, 30 to 65 percent slopes 255 Tokul gravelly medial loam, 8 to 15 percent slopes 258 Tokul-Pastik complex, 45 to 90 percent slopes % % % % 285 Water % Totals for Area of Interest % Natural Resources Conservation Service Web Soil Survey National Cooperative Soil Survey 2/11/2016 Page 3 of 3

30 APPENDIX C Landscape Plan

31

32

Soil Map Lewis County, Kentucky (Denham Farm, Sand Hill/Trinity, Lewis Co., KY) Web Soil Survey National Cooperative Soil Survey

Soil Map Lewis County, Kentucky (Denham Farm, Sand Hill/Trinity, Lewis Co., KY) Web Soil Survey National Cooperative Soil Survey 83 37' 43'' W (Denham Farm, Sand Hill/Trinity, Lewis Co., KY) 83 36' 18'' W 38 40' 37'' N 271500 271700 271900 272100 272300 272500 272700 272900 273100 273300 38 40' 37'' N 38 39' 54'' N 4282900 4283100

More information

Soil Map Lowndes County, Alabama (McEvoy_Gordonsville)

Soil Map Lowndes County, Alabama (McEvoy_Gordonsville) 524700 525000 525300 525600 525900 526200 3568000 3568000 3567700 3567700 3567400 3567400 3567100 3567100 3566800 3566800 3566500 3566500 3566200 3566200 3565900 3565900 524700 525000 525300 525600 Map

More information

Vegetation Cover Type Mapping Study Plan for Energy Northwest's Packwood Lake Hydroelectric Project FERC No Lewis County, Washington

Vegetation Cover Type Mapping Study Plan for Energy Northwest's Packwood Lake Hydroelectric Project FERC No Lewis County, Washington Revised Vegetation Cover Type Mapping Study Plan for Energy Northwest's Packwood Lake Hydroelectric Project FERC No. 2244 Lewis County, Washington Submitted to P.O. Box 968 Richland, Washington 99352-0968

More information

Alapaha Tract. Alapaha Tract. Berrien County GA Acres Par LL 320 LD 5. Date: 6/6/2017. TractName

Alapaha Tract. Alapaha Tract. Berrien County GA Acres Par LL 320 LD 5. Date: 6/6/2017. TractName The 996 Planted Slash was st thinned in 0 TractName Alapaha inch equals 74 miles in = 44,786 ft 0 0 60 Miles :,77,40 The 996 Planted Slash was st thinned in 0 TractName Alapaha inch equals miles in = 6,7

More information

39. WETLANDS Introduction. Wetlands and Waterbodies Cook Inlet Drainages

39. WETLANDS Introduction. Wetlands and Waterbodies Cook Inlet Drainages 39. WETLANDS 39.1 Introduction This chapter summarizes the wetlands and waterbodies study for the Cook Inlet drainages study area (Figure 39-1). The objectives of the study were to determine and map the

More information

PORT OF VANCOUVER, USA PARCEL 1A NE LAYDOWN CRITICAL AREAS REPORT

PORT OF VANCOUVER, USA PARCEL 1A NE LAYDOWN CRITICAL AREAS REPORT PORT OF VANCOUVER, USA PARCEL 1A NE LAYDOWN CRITICAL AREAS REPORT February 2012 Prepared by: Port of Vancouver, USA 3103 NW Lower River Road Vancouver, Washington 98660 360.693.3611 CONTENTS 1 Introduction...

More information

Appendix C-3. Wetlands and Other Surface Waters Report

Appendix C-3. Wetlands and Other Surface Waters Report Appendix C-3 Wetlands and Other Surface Waters Report WETLANDS AND OTHER SURFACE WATERS REPORT Hatchet Ridge Wind Energy Project Shasta County, California Prepared for: Hatchet Ridge Wind, LLC Portland,

More information

Attachment C Applicant s Proposed Mitigation Statement Alaska DOT&PF Northern Region Pilot Station Airport Relocation Project POA

Attachment C Applicant s Proposed Mitigation Statement Alaska DOT&PF Northern Region Pilot Station Airport Relocation Project POA Attachment C Applicant s Proposed Mitigation Statement Alaska DOT&PF Northern Region Pilot Station Airport Relocation Project POA-2004-1223 Introduction This mitigation statement was prepared as an attachment

More information

Web Soil Survey National Cooperative Soil Survey

Web Soil Survey National Cooperative Soil Survey 99 52' 37'' W Yields of Irrigated Crops (Component): Cotton lint (Lbs) Haskell County, Texas 99 51' 40'' W 33 21' 4'' N 418500 418600 418700 418800 418900 419000 419100 419200 419300 419400 419500 419600

More information

Arvada Plaza Redevelopment. Walmart Store # (Lot 1) Industrial Realty Group, LLC (Lot 2)

Arvada Plaza Redevelopment. Walmart Store # (Lot 1) Industrial Realty Group, LLC (Lot 2) Drainage Analysis Arvada, CO Arvada Plaza Redevelopment Including: Walmart Store #4734-00 (Lot 1) & Industrial Realty Group, LLC (Lot 2) (W 58 th Ave & Independence Street) Arvada, Colorado Preliminary

More information

THE CITY OF THE VILLAGE PLANNED UNIT DEVELOPMENT DESIGN STATEMENT FOR MULFORD ESTATES

THE CITY OF THE VILLAGE PLANNED UNIT DEVELOPMENT DESIGN STATEMENT FOR MULFORD ESTATES THE CITY OF THE VILLAGE PLANNED UNIT DEVELOPMENT DESIGN STATEMENT FOR MULFORD ESTATES Revised August 18, 2016, August 10, 2016, September 19,2016 Prepared By: Isch and Associates, Inc. 14848 Bristol Park

More information

SR nd Street SE to 112th Street SE (527 Widening) Mitigation Site WIN # A52720B USACE NWP (14)

SR nd Street SE to 112th Street SE (527 Widening) Mitigation Site WIN # A52720B USACE NWP (14) SR 527 132nd Street SE to 112th Street SE (527 Widening) Mitigation Site WIN # A52720B USACE NWP (14) 2002-00046 Northwest Region 2016 MONITORING REPORT Wetlands Program Issued March 2017 Environmental

More information

McColl Fence Addition GEOTECHNICAL ASSESSMENT

McColl Fence Addition GEOTECHNICAL ASSESSMENT McColl Fence Addition GEOTECHNICAL ASSESSMENT Prepared For: Stuart McColl 1038 Hooker Road Sequim, WA 98382 SEPTEMBER 2012 Prepared By: Trent T. Adams, EIT Justin C. Wilson, PE NTI ENGINEERING & LAND SURVEYING

More information

AG-LAND Investment Brokers 275 Sale Lane Red Bluff, CA Fax Paradox Seed Mother Orchard Red Bluff, CA

AG-LAND Investment Brokers 275 Sale Lane Red Bluff, CA Fax Paradox Seed Mother Orchard Red Bluff, CA AG-LAND Investment Brokers 275 Sale Lane Red Bluff, CA 96080 530-529-4400 Fax 530-527-5042 Paradox Seed Mother Orchard Red Bluff, CA AG-LAND INVESTMENT BROKERS 275 Sale Lane / P. O. Box 896 Red Bluff,

More information

Wetland Delineation for the 53 rd Street Overpass Project Corvallis, Oregon

Wetland Delineation for the 53 rd Street Overpass Project Corvallis, Oregon Wetland Delineation for the 53 rd Street Overpass Project (Township 12 South, Range 5 West, Section 4 West end of Tax Lot 120 & north side of Union Pacific right-of-way) Prepared for Benton County Public

More information

Wetland and Stream Sensitive Areas Study for Buffer Reduction Parcels and -0178, Lake Forest Park, WA

Wetland and Stream Sensitive Areas Study for Buffer Reduction Parcels and -0178, Lake Forest Park, WA March 10, 2017 Darin Seader 2301 NE Perkins Way Lake Forest Park, WA 98155 AOA-4800 SUBJECT: Wetland and Stream Sensitive Areas Study for Buffer Reduction Parcels 866590-0181 and -0178, Lake Forest Park,

More information

Pinheiro Ranch 55+/- Acres Orchard Development Ground Orland, CA. Presented By:

Pinheiro Ranch 55+/- Acres Orchard Development Ground Orland, CA. Presented By: Pinheiro Ranch 55+/- Acres Orchard Development Ground Orland, CA Presented By: Pinheiro Ranch 55+/- Acres Orchard Development Ground Orland, CA Location: This property is located on the SE corner of Road

More information

Plant, Wildlife and Wetland Assessment

Plant, Wildlife and Wetland Assessment WSU Project Site Plant, Wildlife and Wetland Assessment approximately 38 acres of the site would be in retained natural area, including passive use portions of the park and smaller natural areas in other

More information

STAFF REPORT CHELAN COUNTY PUD DAROGA DOMESTIC WATER SYSTEM

STAFF REPORT CHELAN COUNTY PUD DAROGA DOMESTIC WATER SYSTEM STAFF REPORT CHELAN COUNTY PUD DAROGA DOMESTIC WATER SYSTEM TO: Douglas County Hearing Examiner FROM: Douglas County Land Services Staff RE: Chelan County PUD, SCUP-12-01 DATE: July 5, 2012 I. GENERAL

More information

Appendix E : Guidelines for Riparian Buffer Areas

Appendix E : Guidelines for Riparian Buffer Areas Appendix E : Guidelines for Riparian Buffer Areas This document should be read in conjunction with the CRCA Planning Policy. 1.0 PURPOSE The purpose of this document is to summarize the recommendations

More information

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans)

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Allen County Stormwater Plan Submittal Checklist The following items must be provided when applying for an Allen County Stormwater

More information

Drainage Letter for Falcon High School Building Expansion

Drainage Letter for Falcon High School Building Expansion August 11, 2017 El Paso County Planning and Community Development Department 2880 International Circle, Suite 110 Colorado Springs, CO 80910 ATTN: RE: Mr. Jeff Rice Drainage Letter for Falcon High School

More information

Maine s Land Use Regulations and Erosion Control Techniques

Maine s Land Use Regulations and Erosion Control Techniques Maine s Land Use Regulations and Erosion Control Techniques Protecting Maine s Air, Land and Water Colin Clark 441-7419 colin.a.clark@maine.gov Tom Gilbert 441-8031 thomas.gilbert@maine.gov Jim Rodrigue

More information

Web Soil Survey National Cooperative Soil Survey

Web Soil Survey National Cooperative Soil Survey 289300 289700 290100 290500 83 12' 5'' W 83 13' 37'' W Farmland Classification Ben Hill and Irwin Counties, Georgia 290900 291300 31 46' 8'' N 3514000 3514000 3514400 3514400 3514800 3514800 3515200 3515200

More information

CCSD#1 Stormwater Standards

CCSD#1 Stormwater Standards SECTION 4 NATURAL RESOURCES AND VEGETATED BUFFERS The provisions of this section are intended to prevent and reduce adverse impacts and to enhance drainageways and natural resources. These requirements

More information

Chapter 10 Natural Environment

Chapter 10 Natural Environment Chapter 10 Natural Environment Existing Conditions The Natural Environment Element addresses the protection, conservation, preservation, and restoration of the natural resources the Bayview Ridge Subarea,

More information

SECTION 10: WETLANDS PROTECTION

SECTION 10: WETLANDS PROTECTION SECTION 10: WETLANDS PROTECTION 10-1 INTENT AND PURPOSE A. Intent 1. The City finds that wetlands serve a variety of beneficial functions. Wetlands maintain water quality, reduce flooding and erosion,

More information

Stormwater Analysis Report

Stormwater Analysis Report Stormwater Analysis Report Solar Panel Array Temple Street (Rt. 14) West Boylston, MA February 24, 216 SITE Prepared for: West Boylston Municipal Lighting Plant 4 Crescent Street West Boylston, MA 1583

More information

STORMWATER POLLUTION PREVENTION PLAN (SWPPP)

STORMWATER POLLUTION PREVENTION PLAN (SWPPP) SIEMENS INDUSTRY, INC. STORMWATER POLLUTION PREVENTION PLAN (SWPPP) COLUMBIA UNIVERSITY/SUN EDISON REMOTE METERING SOLAR ENERGY PROJECT JOHNSON FARM, 121 JOHNSON ROAD CHESTER, NEW YORK 10918 TAX LOT SECTION

More information

Custom Soil Resource Report for Polk County, Wisconsin

Custom Soil Resource Report for Polk County, Wisconsin United States Department of Agriculture Natural Resources Conservation Service A product of the National Cooperative Soil Survey, a joint effort of the United States Department of Agriculture and other

More information

Custom Soil Resource Report for Columbus County, North Carolina

Custom Soil Resource Report for Columbus County, North Carolina United States Department of Agriculture Natural Resources Conservation Service A product of the National Cooperative Soil Survey, a joint effort of the United States Department of Agriculture and other

More information

Wetland and Stream Sensitive Areas Study Boundary Line Adjustment/Reasonable Use Parcels and -0178, Lake Forest Park, WA

Wetland and Stream Sensitive Areas Study Boundary Line Adjustment/Reasonable Use Parcels and -0178, Lake Forest Park, WA March 10, 2017 Darin Seader 2301 NE Perkins Way Lake Forest Park, WA 98155 AOA-4800 SUBJECT: Wetland and Stream Sensitive Areas Study Boundary Line Adjustment/Reasonable Use Parcels 866590-0181 and -0178,

More information

Responses to Comments from State Agencies

Responses to Comments from State Agencies Summary of Comment Letters Received from State Agencies This section provides responses to comments received on the draft environmental document from state agencies. Comment Code Agency S-1 California

More information

M E M O R A N D U M Clallam County Public Works Department

M E M O R A N D U M Clallam County Public Works Department M E M O R A N D U M Clallam County Public Works Department TO: TO: Craig Jacobs, Public Works Director Joel Winborn, Division Manager FROM: Dave Lasorsa, Environmental Coordinator SUBJ: Wetland Assessment

More information

Mule Ranch - Dorris, CA 1,234 +/- acres, Siskiyou County

Mule Ranch - Dorris, CA 1,234 +/- acres, Siskiyou County AG-LAND Investment Brokers 275 Sale Lane Red Bluff, CA 96080 530-529-4400 Fax 530-527-5042 Mule Ranch - Dorris, CA 1,234 +/- acres, Siskiyou County AG-LAND INVESTMENT BROKERS 275 Sale Lane / P. O. Box

More information

Custom Soil Resource Report for Colquitt and Cook Counties, Georgia

Custom Soil Resource Report for Colquitt and Cook Counties, Georgia United States Department of Agriculture Natural Resources Conservation Service A product of the National Cooperative Soil Survey, a joint effort of the United States Department of Agriculture and other

More information

GRADING, EROSION AND SEDIMENTATION CONTROL

GRADING, EROSION AND SEDIMENTATION CONTROL SECTION 500 GRADING, EROSION AND SEDIMENTATION CONTROL 501 Erosion and Sedimentation Control Plan All engineering plans for projects that propose to construct new, or modify existing drainage facilities,

More information

BMP 5.4.2: Protect /Conserve/Enhance Riparian Areas

BMP 5.4.2: Protect /Conserve/Enhance Riparian Areas BMP 5.4.2: Protect /Conserve/Enhance Riparian Areas The Executive Council of the Chesapeake Bay Program defines a Riparian Forest Buffer as "an area of trees, usually accompanied by shrubs and other vegetation,

More information

AG-LAND Investment Brokers 275 Sale Lane Red Bluff, CA Fax Corning Eucalyptus Farm

AG-LAND Investment Brokers 275 Sale Lane Red Bluff, CA Fax Corning Eucalyptus Farm AG-LAND Investment Brokers 275 Sale Lane Red Bluff, CA 96080 530-529-4400 Fax 530-527-5042 Corning Eucalyptus Farm Tehama County,, California 1 of 6 deep irrigation wells Drip tubing rolled at the edge

More information

Title 92 ROADSIDE VEGETATION MANAGEMENT POLICY

Title 92 ROADSIDE VEGETATION MANAGEMENT POLICY Title 92 Chapters: ROADSIDE VEGETATION MANAGEMENT POLICY Chapter 92.04 - ROADSIDE VEGETATION MANAGEMENT Chapter 92.04 Sections: ROADSIDE VEGETATION MANAGEMENT 92.04.010 ROADSIDE MAINTENANCE. 92.04.020

More information

Writing Performance Standards for Wetland Mitigation

Writing Performance Standards for Wetland Mitigation Writing Performance Standards for Wetland Mitigation WSDOT Updated 08/23/17 Performance standards are critical components of any wetland mitigation report. These performance criteria describe measurable

More information

SR 161: Jovita Boulevard to South 360th St. Stage 2 / WSDOT Stream Buffer Mitigation (Agreement Y-9403) 2012 Final Monitoring Report

SR 161: Jovita Boulevard to South 360th St. Stage 2 / WSDOT Stream Buffer Mitigation (Agreement Y-9403) 2012 Final Monitoring Report 2012 SR 161: Jovita Boulevard to South 360th St. Stage 2 / WSDOT Stream Buffer Mitigation (Agreement Y-9403) 2012 Final Monitoring Report SR 161: Jovita Boulevard to South 360th St. Stage 2 (MP 31.95 to

More information

STORMWATER MANAGEMENT REPORT FOR THE BORGATA OUTDOOR EVENT AREA POOL ADDITION

STORMWATER MANAGEMENT REPORT FOR THE BORGATA OUTDOOR EVENT AREA POOL ADDITION STORMWATER MANAGEMENT REPORT FOR THE BORGATA OUTDOOR EVENT AREA POOL ADDITION City of Atlantic City, Atlantic County, New Jersey Prepared For: Marina District Development Company, LLC One Borgata Way Atlantic

More information

Department of the Army Permit Application

Department of the Army Permit Application Department of the Army Permit Application DA File Number U.S. Army Corps of Engineers Honolulu District Date Received by CEPOH-RO Send Completed Application to: Honolulu District, U.S. Army Corps of Engineers

More information

CORNERSTONE RIVER VALLEY VILLAGE FILING NO. 1 STORMWATER MANAGEMENT PLAN

CORNERSTONE RIVER VALLEY VILLAGE FILING NO. 1 STORMWATER MANAGEMENT PLAN CORNERSTONE RIVER VALLEY VILLAGE FILING NO. 1 STORMWATER MANAGEMENT PLAN SITUATED IN THE SW ¼ OF SECTION 18, T.2S., R.67W., OF THE 6 TH P.M. COUNTY OF ADAMS, STATE OF COLORADO PREPARED FOR: Thornton Cornerstone

More information

APPENDIX I. Plan Reviewer Checklist

APPENDIX I. Plan Reviewer Checklist APPENDIX I Plan Reviewer Checklist PLAN REVIEW CHECKLIST Annual Standards and Specifications The ESC/SWM Plan clearly indicates the version of Virginia Tech Annual Standards and Specifications applicable.

More information

SR 520 Medina to SR 202 Eastside Transit and HOV (Yarrow Creek Wetland) Mitigation Site USACE IP NWS

SR 520 Medina to SR 202 Eastside Transit and HOV (Yarrow Creek Wetland) Mitigation Site USACE IP NWS SR 520 Medina to SR 202 Eastside Transit and HOV (Yarrow Creek Wetland) Mitigation Site USACE IP NWS-2009-562 Northwest Region 2018 MONITORING REPORT Wetlands Program Issued March 2019 Environmental Services

More information

Wetlands. DuPage County Stormwater Ordinance Update- Wetlands and Buffers. Is a Stormwater Permit Required? 7/13/2012

Wetlands. DuPage County Stormwater Ordinance Update- Wetlands and Buffers. Is a Stormwater Permit Required? 7/13/2012 DuPage County Stormwater Ordinance Update- Wetlands and Buffers PRESENTED BY: MARY BETH FALSEY WETLAND SPECIALIST Wetlands Section 15-18.A.1.a: If a Stormwater Administrator has the expertise, he/she can

More information

STAFF REPORT FOR POLICY PLAN AMENDMENT S10-CW-1CP

STAFF REPORT FOR POLICY PLAN AMENDMENT S10-CW-1CP STAFF REPORT FOR POLICY PLAN AMENDMENT S10-CW-1CP EXECUTIVE SUMMARY This Plan Amendment would serve to clarify policy guidance regarding circumstances under which proposals for disturbances to Environmental

More information

City of Valdosta Land Development Regulations

City of Valdosta Land Development Regulations Chapter 324 Section 324-1 Environmental Planning Criteria Protection of Groundwater Recharge Areas (A) Purpose and Intent. Pursuant to O.C.G.A. 12-2-8 and the Georgia Department of Natural Resources (DNR),

More information

A GUIDE TO THE WETLAND, DEEPWATER HABITATS, AND RIPARIAN CLASSIFICATIONS USED IN WETLAND AND RIPARIAN MAPPING IN MONTANA

A GUIDE TO THE WETLAND, DEEPWATER HABITATS, AND RIPARIAN CLASSIFICATIONS USED IN WETLAND AND RIPARIAN MAPPING IN MONTANA A GUIDE TO THE WETLAND, DEEPWATER HABITATS, AND RIPARIAN CLASSIFICATIONS USED IN WETLAND AND RIPARIAN MAPPING IN MONTANA Purpose: The Montana Natural Heritage Program s Wetland and Riparian Mapping Center

More information

PHYSICAL SOIL PROPERTIES

PHYSICAL SOIL PROPERTIES PHYSICAL SOIL PROPERTIES Physical Soil Properties Santa Cruz County, California Scotts Valley Target Physical Soil Properties This table shows estimates of some physical characteristics and features that

More information

West Fork White River Watershed Conservation Map Summaries. Prepared for the Beaver Watershed Alliance. By the Watershed Conservation Resource Center

West Fork White River Watershed Conservation Map Summaries. Prepared for the Beaver Watershed Alliance. By the Watershed Conservation Resource Center West Fork White River Watershed Conservation Map Summaries Prepared for the Beaver Watershed Alliance By the Watershed Conservation Resource Center November 2014 The Watershed Conservation Resource Center

More information

* For applicants utilizing bank for compensatory mitigation requirements, information below is not applicable.

* For applicants utilizing bank for compensatory mitigation requirements, information below is not applicable. Mitigation Plan (33 CFR 332.4(c)/40 CFR 230.92.4(c)) A mitigation plan is required for all forms of compensatory mitigation, whether permittee-responsible mitigation, mitigation banks, or in-lieu fee mitigation

More information

Appendix D: MULTI-AGENCY COMPENSATORY MITIGATION PLAN CHECKLIST 1

Appendix D: MULTI-AGENCY COMPENSATORY MITIGATION PLAN CHECKLIST 1 Appendix D: MULTI-AGENCY COMPENSATORY MITIGATION PLAN CHECKLIST 1 Mitigation Goals and Objectives o Describe functions lost at impact site o Describe functions to be gained at mitigation site o Describe

More information

DRAFT FINDING OF NO SIGNIFICANT IMPACT. for. Tioga Sports Park

DRAFT FINDING OF NO SIGNIFICANT IMPACT. for. Tioga Sports Park DRAFT FINDING OF NO SIGNIFICANT IMPACT for Tioga Sports Park The U.S. Fish and Wildlife Service (USFWS) prepared an Environmental Assessment (EA) to analyze the potential effects of the proposal by the

More information

CATEGORY a protection of the natural environment, its ecosystems and biodiversity.

CATEGORY a protection of the natural environment, its ecosystems and biodiversity. 29. ENVIRONMENTAL DEVELOPMENT PERMIT AREA CATEGORY a protection of the natural environment, its ecosystems and biodiversity. The requirement to obtain an environmental development permit is cited in Section

More information

Amphibian Protection Strategies. Presented by: Linda Dupuis, M.Sc., R.P.Bio Wildlife Habitat Ecologist

Amphibian Protection Strategies. Presented by: Linda Dupuis, M.Sc., R.P.Bio Wildlife Habitat Ecologist Amphibian Protection Strategies Presented by: Linda Dupuis, M.Sc., R.P.Bio Wildlife Habitat Ecologist Vulnerability Biphase life histories and physiological limitations make aquatic-breeding amphibians

More information

Vegetative Buffer Regulations to Protect Water quality

Vegetative Buffer Regulations to Protect Water quality Vegetative Buffer Regulations to Protect Water quality Robert Jontos, PWS, CPESC Land-Tech Consultants, Inc. Environmental Scientists and Engineers Connecticut Association of Conservation and Inland Wetland

More information

Critical Areas Ordinance

Critical Areas Ordinance Public Review Draft //7 Public Review Draft //7 4 5 6 Kitsap County Code Title 9 Critical Areas Ordinance 7 8 9 0 Underline / Strike out Version 9.800 Appendices 4 5 6 7 8 9 0 4 5 Public Review Draft //7

More information

The Science Behind Forest Riparian Protection in the Pacific Northwest States By George Ice, Summer 2004

The Science Behind Forest Riparian Protection in the Pacific Northwest States By George Ice, Summer 2004 The Science Behind Forest Riparian Protection in the Pacific Northwest States By George Ice, Summer 2004 Riparian buffers, streamside management zones, and similar measures are essential parts of forest

More information

Site Description. CCR Rule Initial Inflow Design Flood Control System Plan (cont.) 2

Site Description. CCR Rule Initial Inflow Design Flood Control System Plan (cont.) 2 Site Description Kentucky Utilities Company (KU) owns and operates Ghent Gypsum Stack, a CCR surface impoundment, at the Ghent Generating Station in Carroll County, Kentucky. The impoundment is permitted

More information

I THOUGHT IT WAS JUST WET LAND: A GUIDE TO ENVIRONMENTAL PERMITTING FOR AIRPORTS ROAD SCHOOL 2018 SIMON DAVIES, SENIOR SCIENTIST MARCH 7, 2018

I THOUGHT IT WAS JUST WET LAND: A GUIDE TO ENVIRONMENTAL PERMITTING FOR AIRPORTS ROAD SCHOOL 2018 SIMON DAVIES, SENIOR SCIENTIST MARCH 7, 2018 I THOUGHT IT WAS JUST WET LAND: A GUIDE TO ENVIRONMENTAL PERMITTING FOR AIRPORTS ROAD SCHOOL 2018 SIMON DAVIES, SENIOR SCIENTIST MARCH 7, 2018 Definition Regulatory Definition - Those areas that are inundated

More information

3D WETLAND MANAGEMENT

3D WETLAND MANAGEMENT 3D WETLAND MANAGEMENT 1. ISSUE Wetlands are one of the most productive ecosystems. They provide biological and chemical functions to the landscape that serve the watershed including the moderation of nutrient

More information

Final Report of the Riparian Forest Buffer Panel

Final Report of the Riparian Forest Buffer Panel Chesapeake Bay Program Final Report of the Riparian Forest Buffer Panel Introduction Findings Land Use-Specific Findings On Agricultural Land On Forested Land On Developed and Developing Lands Recommendations

More information

Forest Recreation Management

Forest Recreation Management Forest Recreation Management 1 Forest Recreation Management Introduction...3 CONTENTS The Benefits of Guidelines...3 Considerations...4 Planning...5 Construction of Recreation Areas...6 Protecting Cultural

More information

PROSPECTUS. Proposed Beech River Canal Wetland and Stream Mitigation Bank

PROSPECTUS. Proposed Beech River Canal Wetland and Stream Mitigation Bank PROSPECTUS Proposed Beech River Canal Wetland and Stream Mitigation Bank INTRODUCTION This prospectus provides an overview of Beech River Farms, LLC s (BRF) proposed Beech River Canal Wetland and Stream

More information

Minnesota EAW Supplement

Minnesota EAW Supplement Appendix I: Minnesota EAW Supplement Lower Pool 2 Channel Management Study: Boulanger Bend to Lock and Dam No. 2 Minnesota EAW Item Identification A supplement prepared for the Minnesota DNR to identify

More information

Federal Way Link Extension

Federal Way Link Extension vember 216 Federal Way Link Extension Final Environmental Impact Statement ECOSYSTEMS TECHNICAL REPORT Appendix G2 Central Puget Sound Regional Transit Authority Federal Way Link Extension Ecosystems

More information

Appendix J: The Project Stormwater Control Plan by Lea & Braze Engineering, Inc.

Appendix J: The Project Stormwater Control Plan by Lea & Braze Engineering, Inc. Appendix J: The Project Stormwater Control Plan by Lea & Braze Engineering, Inc. STORMWATER CONTROL PLAN 23 LOT SUBDIVISION ON PROCTOR ROAD CASTRO VALLEY, CALIFORNIA Owner/Developer: Hue Tran 4584 Ewing

More information

Funding Guidelines State Fiscal Year 2016

Funding Guidelines State Fiscal Year 2016 State Fiscal Year 2016 Water Quality Financial Assistance Centennial Clean Water Program Clean Water Act Section 319 Program Stormwater Financial Assistance Program Washington State Water Pollution Control

More information

Public Notice: Application for Permit

Public Notice: Application for Permit US Army Corps Of Engineers Walla Walla District 201 North Third Avenue Walla Walla, WA 99362-1876 Public Notice: Application for Permit APPLICATION NO.: NWW-2012-127-I02 WATERWAY: Big Wood River APPLICANT:

More information

Compensatory Mitigation Plan Requirements For Permittee Responsible Mitigation Projects St. Louis District, Corps of Engineers May 2010

Compensatory Mitigation Plan Requirements For Permittee Responsible Mitigation Projects St. Louis District, Corps of Engineers May 2010 Compensatory Mitigation Plan Requirements For Permittee Responsible Mitigation Projects St. Louis District, Corps of Engineers May 2010 The U.S. Army Corps of Engineers (Corps) and U.S. Environmental Protection

More information

Chapter 2: Conditions in the Spring Lake Watershed related to Stormwater Pollution

Chapter 2: Conditions in the Spring Lake Watershed related to Stormwater Pollution Chapter 2: Conditions in the Spring Lake Watershed related to Stormwater Pollution To identify the primary causes and consequences of stormwater discharges to Spring Lake and its adjoining waterbodies,

More information

FINDINGS, CONCLUSIONS AND DECISION

FINDINGS, CONCLUSIONS AND DECISION FINDINGS, CONCLUSIONS AND DECISION Applicant: Agent: File No: Request: Location: Parcel No.s: Shoreline Designation: Summary of Proposal: Public Hearing: Decision: Walla Walla University Rosario Beach

More information

No. 6 December, Wisconsin s Forestry Best Management Practices for Water Quality Forest Roads

No. 6 December, Wisconsin s Forestry Best Management Practices for Water Quality Forest Roads No. 6 December, 1995 Wisconsin s Forestry Best Management Practices for Water Quality Forest Roads Steve Holaday, Wisconsin Dept. of Natural Resources, and Jeff Martin, Dept. of Forestry, UW-Madison BMPs

More information

Dye Creek Orchards Los Molinos, California

Dye Creek Orchards Los Molinos, California AG-LAND INVESTMENT BROKERS 275Sale Lane / P. O. Box 896 Red Bluff, CA 96080 530.529.4400 office / 530.527.5042 fax Dye Creek Orchards Los Molinos, California Listing Price: $1,950,000. Seller financing

More information

IDEM Wetlands and Streams Regulatory Overview. An overview of IDEM permitting for work in Waters of the State

IDEM Wetlands and Streams Regulatory Overview. An overview of IDEM permitting for work in Waters of the State IDEM Wetlands and Streams Regulatory Overview An overview of IDEM permitting for work in Waters of the State Who Has Jurisdiction? Adjacent wetland: USACE & IDEM Stream > 1 sq. mile drainage: IDNR, USACE

More information

5.15 Wetlands and Other Waters of the U.S.

5.15 Wetlands and Other Waters of the U.S. I-70 East Final EIS 5.15 Wetlands and Other Waters of the U.S. 5.15 Wetlands and Other Waters of the U.S. This section discusses wetlands, open waters, and other waters of the U.S. in the study area and

More information

HARVEST PARK/ZIEGLER MIXED USE LOT 2 CITY OF FORT COLLINS, CO

HARVEST PARK/ZIEGLER MIXED USE LOT 2 CITY OF FORT COLLINS, CO EROSION CONTROL REPORT / STORMWATER MANAGEMENT PLAN FOR HARVEST PARK/ZIEGLER MIXED USE LOT 2 CITY OF FORT COLLINS, CO Prepared by: Interwest Consulting Group 1218 West Ash, Suite C Windsor, Colorado 80550

More information

Meacham Creek Restoration Project

Meacham Creek Restoration Project Meacham Creek Restoration Project Meacham Creek Restoration Project Umatilla National Forest Walla Walla Ranger District Michael Rassbach, District Ranger Public Scoping Document Proposal Summary The Walla

More information

U.S. Army Corps of Engineers (USACE) Galveston District

U.S. Army Corps of Engineers (USACE) Galveston District Appendix II U.S. Army Corps of Engineers (USACE) Galveston District SWG MITIGATION BANK PROSPECTUS TEMPLATE This Template includes the information required for a mitigation bank prospectus as outlined

More information

SECONDARY WETLAND IMPACTS ANALYSIS

SECONDARY WETLAND IMPACTS ANALYSIS SECONDARY WETLAND IMPACTS ANALYSIS USACE File. SWG-2012-00153 During the development of the Grand Parkway (State Highway 99) Segments H and I-1 from United States Highway 59/Interstate Highway 69 N to

More information

DOUGLAS COUNTY TRANSPORTATION & LAND SERVICES

DOUGLAS COUNTY TRANSPORTATION & LAND SERVICES DOUGLAS COUNTY TRANSPORTATION & LAND SERVICES 140 19TH STREET NW, SUITE A EAST WENATCHEE, WA 98802 PHONE: 509/884-7173 FAX: 509/886-3954 www.douglascountywa.net STAFF REPORT VANDIVER BOATLIFT TO: Douglas

More information

Implementation of Act 162 of 2014 Riparian Buffer or Riparian Forest Buffer Offsetting

Implementation of Act 162 of 2014 Riparian Buffer or Riparian Forest Buffer Offsetting Implementation of Act 162 of 2014 Riparian Buffer or Riparian Forest Buffer Offsetting March 11, 2015 Dial-in number for Audio: 1-877-668-4493 Access code: 642 373 389 WebEx Technical Support: 866-229-3239

More information

S.R. 4007, Section 14B PADEP Environmental Assessment Form. Enclosure C Description of Aquatic Habitat

S.R. 4007, Section 14B PADEP Environmental Assessment Form. Enclosure C Description of Aquatic Habitat S.R. 4007, Section 14B PADEP Environmental Assessment Form Description of Aquatic Habitat Cresheim Creek is the only water resource that exists within the project area. No jurisdictional wetlands were

More information

PROGRAMMATIC ESA 1 CONSULTATION Specific Project Information Form For Minor Bank Stabilization Repair Activities Version: May 2012

PROGRAMMATIC ESA 1 CONSULTATION Specific Project Information Form For Minor Bank Stabilization Repair Activities Version: May 2012 PROGRAMMATIC ESA 1 CONSULTATION Specific Project Information Form For Minor Bank Stabilization Repair Activities Version: May 2012 Eligibility for Programmatic Consultation To be filled out by Corps This

More information

APPENDIX B. If the GRANIT Data Mapper gets stuck during an operation, use the refresh button in your browser.

APPENDIX B. If the GRANIT Data Mapper gets stuck during an operation, use the refresh button in your browser. APPENDIX B ANSWERING QUESTIONS THAT REQUIRE THE GRANIT DATA MAPPER ONLINE TOOLS AND PRINTED MAPS (Remaining questions are answered during field checking) Each of the questions in the table on the following

More information

Chapter 3 Dispersion BMPs

Chapter 3 Dispersion BMPs Chapter 3 Dispersion BMPs 3.1 BMP L611 Concentrated Flow Dispersion 3.1.1 Purpose and Definition Dispersion of concentrated flows from driveways or other pavement through a vegetated pervious area attenuates

More information

Environmental Check List Georgia Environmental Policy Act

Environmental Check List Georgia Environmental Policy Act Environmental Check List Georgia Environmental Policy Act Project No. : Project Name: GEORGIA IS AREA AFFECTED? IF AFFECTED, HOW SEVERELY? AREA/CATEGORY NO YES UNKNOWN MINOR MEDIAN MAJOR UNKNOWN 1. Wetlands

More information

PRESENTERS. Contact Information: RW Armstrong Union Station, 300 S. Meridian St. Indianapolis, IN

PRESENTERS. Contact Information: RW Armstrong Union Station, 300 S. Meridian St. Indianapolis, IN 1 PRESENTERS David Bourff, Director of Environmental Planning Simon Davies, LEED AP, Environmental Scientist Summer O Brien, PWS, Senior Environmental Scientist Contact Information: RW Armstrong Union

More information

D EROSION AND SEDIMENT CONTROL. Table of Contents

D EROSION AND SEDIMENT CONTROL. Table of Contents Table of Contents D1. GENERAL... 1 D2. OBJECTIVE... 1 D3. REFERENCE MATERIAL... 1 D4. REGULATORY REQUIREMENTS... 1 D5. EROSION AND SEDIMENT CONTROL (ESC) PLANS... 2 D5.1 Goals and Objectives:... 2 D5.2

More information

Specific Project Information Form For Construction of New or Modification of Existing Residential Overwater Structures

Specific Project Information Form For Construction of New or Modification of Existing Residential Overwater Structures Form For Construction of New or Modification of Existing Residential Overwater Structures and Drive Moorage Piling in Lake Washington, Lake Sammamish, the Sammamish River and Lake Union, Including the

More information

Background. Literature Review

Background. Literature Review Ms. Joanna Helms Economic Development Director Town of Apex 73 Hunter Street P.O. Box 250 Apex, North Carolina 27502 October 23, 2015 Reference: Report of Wetland Determination Cash Perkins Site ECS Project

More information

Appendix B Stormwater Site Plan Submittal Requirements Checklist

Appendix B Stormwater Site Plan Submittal Requirements Checklist Stormwater Site Plan Submittal Requirements Checklist The Submittal Requirements Checklist is intended to aid the design engineer in preparing a Stormwater Site Plan. All items included in the following

More information

Quintillion Subsea Project Applicant Proposed Mitigation Statement

Quintillion Subsea Project Applicant Proposed Mitigation Statement 1. Avoidance of impacts to waters of the U.S., including wetlands: Please describe how, in your project planning process, you avoided impacts to waters of the U.S., including wetlands, to the maximum extent

More information

Permit Application: Soil Erosion and Sediment Control Program

Permit Application: Soil Erosion and Sediment Control Program Missaukee Conservation District Soil Erosion and Sediment Control Program 6180 W. Sanborn Road, Suite 3 Lake City, MI 49651 Ph 231.839.7193 Fax 231.839.5411 http://missaukeecd.org/soil-erosion/ kate.nietling@macd.org

More information

Chapter 2: Selecting Best Management Practices (BMPs)

Chapter 2: Selecting Best Management Practices (BMPs) Chapter 2: Selecting Best Management Practices (BMPs) 2.1 - Temporary versus Permanent BMPs The same level of care should be taken to select both temporary BMPs and permanent BMPs. The same level of care

More information

CROSBY BROOK RESTORATION STUDY BRATTLEBORO, VT

CROSBY BROOK RESTORATION STUDY BRATTLEBORO, VT Key Stakeholders: CROSBY BROOK RESTORATION STUDY BRATTLEBORO, VT Funded By: VT Dept. of Environmental Conservation VT Agency of Transportation (VTrans) Town of Brattleboro NEWEA Spring Meeting Omni Mt.

More information

U.S. Army Corps of Engineers, Alaska District PRECONSTRUCTION NOTIFICATION FORM

U.S. Army Corps of Engineers, Alaska District PRECONSTRUCTION NOTIFICATION FORM U.S. Army Corps of Engineers, Alaska District PRECONSTRUCTION NOTIFICATION FORM May be used instead of Form ENG 4345 to request verification under a Nationwide Permit (NWP) Applicant: Address: City, State,

More information