MODULE #5 MECHANICAL, ELECTRICAL, PLUMBING II

Size: px
Start display at page:

Download "MODULE #5 MECHANICAL, ELECTRICAL, PLUMBING II"

Transcription

1 MODULE #5 MECHANICAL, ELECTRICAL, PLUMBING II MICHAEL WALSH PRINCIPAL, R.G. VANDERWEIL ENGINEERS, LLP 274 Summer Street, Boston, MA (T) (F)

2

3 Module 5 Agenda: 1. MEP Systems and Controls (Continued) 2. HEPA Filtration 3. Maintenance Considerations 4. Bio-Waste Management Solids & Liquids SYSTEMS AND CONTROLS II 1

4 Zone Controls Controlled and Stable Airflow Supply/Exhaust Control & Actuator Speed Must Match Fastest Not Always Better (Does Give Ability to Adjust) Conventional VAV Box Venturi Valve Blade Type Valve PneumaValve Constant Flow Valve Iris Damper MODULE 4 MECHANICAL, ELECTRICAL, PLUMBING CONSIDERATIONS I Zone Controls Significant number of components to be commissioned Review Failure Position Each Component (Open, Closed Last) 2

5 MODULE 4 MECHANICAL, ELECTRICAL, PLUMBING CONSIDERATIONS I Zone Controls Significant number of components to be commissioned Minimize Potential for Multiple Zones to Fail at Same Time (Limit Single Suite Level Controllers) MODULE 4 MECHANICAL, ELECTRICAL, PLUMBING CONSIDERATIONS I Air Handling Unit Controls Review All Potential Failure Modes and Define System Reactions (e.g. Freezestat Trip) 3

6 MODULE 4 MECHANICAL, ELECTRICAL, PLUMBING CONSIDERATIONS I Redundant Exhaust Fan Controls Consider Separate Controller for Each Fan Address Control Panel Failure Mechanical System Details Coordinate utilities to all equipment. Plan for isolation without affecting operation 4

7 Mechanical System Details Must consider all installation details and how they impact barrier Mechanical System Details Consider how to access and inspect penetrations Eliminating casework beneath counter allows for inspection of all penetrations Exposed piping up allows inspection of ceiling penetrations Where does barrier begin and end? 5

8 Mechanical System Details Exposed ductwork and piping allows flexibility while maintaining access for inspection But must balance with aesthetically pleasing work space Mechanical System Details Impact of Remote HEPA Containment & Testing 6

9 Plumbing Systems Water Systems Backflow prevention for services entering containment Recirculation of tempered water may need to occur outside containment zone Liquid Waste Disposal Batch Processing Continuous Feed Plumbing Vent Containment In-line HEPA filters Plumbing Systems Piping Material Mechanical joints (standard systems only) Welded steel single wall Double wall gravity containment piping where in accessible Double wall piping for pressurized systems Penetration Seals All seals accessible for visual inspection Bio-seal caulk at all penetrations into BSL-3 Welded steel piping above biocontainment space ceilings 7

10 Plumbing Systems Double Wall Collection Tanks Double Wall Piping Plumbing Systems Underground Double wall polypropylene Thermal weld joints Vs Solvent weld Environmental issues Floor drains Vs Trench trains Much more space required for Y, T and trap connections 8

11 Fire Protection Systems Penetration Seals All seals accessible for visual inspection Bio-seal caulk at all penetrations into BSL-3 Welded steel piping above biocontainment space ceilings Fire Water Drainage Sprinkler Discharge Containment Tank Containment tank provided to collect sprinkler discharge Electrical Systems Penetration Seals Electrical seal fittings accessible for inspection Bio-seal conduits at initial penetration Power Supply Redundant Electric Power Supply On site generation for campus UPS (battery) emergency lighting Standby Power - Required For All ventilation systems Lab decon systems to allow shutdown Security 9

12 Electrical Systems Right sizing standby generator with containment critical loads Location of outlets for containment equipment/ layout Coordination with Low Voltage Systems like security, tel/data, bms, fire alarm Electrical Systems The wrong size can have big cost implications! 10

13 Electrical Systems Programming and user criteria information needed. Identify what systems on standby power in equip matrix Identify how long standby power is needed Decon systems on standby Containment ventilation /lights/bms/monitoring system Electrical Systems Use software to size generator based on equipment matrix Coordinate redundant systems with Mechanical Engineer to avoid double dipping 11

14 Electrical Systems Minimize generator size by creating multiple step loads Multiple transfer switches with different time delays BMS starting sequence coordinated with mechanical Electrical Systems There is no clear industry sizing standard project specific Standards such as NIH, USDA, CDC and ASHRAE vary significantly in opinions when identifying optional standby power needs USDA/ARS standards recommend keeping standby power to a minimum while the NIH is more liberal. 12

15 MEP Containment Sealing Maintain a tight envelope at the containment boundary. Includes: o Sealing Light Fixtures o Sealing All Conduit Penetrations o Sealing Outlet boxes o Sealing Door Bottoms & Edges o Sealing Door Jambs o Sealing All Penetrations o SEAL - SEAL - SEAL HEPA FILTRATION 13

16 Ganged HEPA for Multi-Room Zone or Suite Ganged HEPA for Multi-Room Zone or Suite Large Headers Must Pass Gas Tight Duct Testing 14

17 Individual HEPA for Each Space Comparison of HEPA Options GANGED Local Maintenance Requires large S.S. headers Air valves are on Dirty side of HEPA may have to achieve gas tight construction N+1 achieved with one more large HEPA bank Requires less floor space May require suite level shut down for decon/certification SINGLE Maintenance is spread out Only requires small low pressure S.S. Duct Air valves are on clean side of HEPA N+1 of each unit can be very expensive Requires more floor space Allows isolation of one room at a time for decon/certification 15

18 MAINTENANCE Maintenance Maintenance of equipment and systems outside containment. Minimize penetrations through barrier 16

19 Maintenance Containment Boundary All service access to equipment, dampers, HEPA filters, piping etc located outside the containment boundary Options Partial Interstitial Access to Valves and Controls Only with Remote HEPA Access to HEPA Tough to Maintain and Decontaminate 17

20 Options Full Interstitial Options Full Interstitial Items Requiring Access: Exhaust HEPA filters Access to Allow Decontamination in Place Supply Bioseal Dampers Reheat Coils Environmental Room Condensing Units Process Chillers for Low Humidity Spaces Local Supplemental Cooling Coils Supplemental Humidifiers Supply and Exhaust Duct Mains Heating Hot Water Piping Chilled Water Piping Process Steam Piping 18

21 Options Combination of Options Provide access from interstitial space without buying full floor Decontamination/Waste Disposal 19

22 Room Decontamination Methods VHP Paraformaldehyde Ethylene Oxide Chlorine Dioxide Gamma Cell Protocols Vendors Room or Suite Level Primary Containment Room Ductwork Waste Decon/Disposal Systems Solid Waste Liquid Waste Regulatory Water Quality Public Perception 20

23 Autoclaves Solid Waste Liquid Waste Kill Systems Batch System 21

24 Liquid Waste Kill Systems Continuous Waste Decon System Liquid Waste Kill Systems Localized Collection System 22

25 MODULE 4 MECHANICAL, ELECTRICAL, PLUMBING CONSIDERATIONS I Tradeline Takeaways Zone Airflow & System Control Components Critical Select Materials and Components for MEP Systems to Meet Criteria Identify Emergency Power/Standby Power Needs Can Consider Static Conditions On Failure As Part of Risk Assessment Questions? 23

26 MODULE #5 MECHANICAL, ELECTRICAL, PLUMBING II MICHAEL WALSH PRINCIPAL, R.G. VANDERWEIL ENGINEERS, LLP 274 Summer Street, Boston, MA (T) (F)

27 Date: Session: Presenters: Metrics Tools Resources Innovative Ideas Proofs

28 Date: Session: Presenters: Metrics Tools Resources Innovative Ideas Proofs

29 Date: Session: Presenters: Metrics Tools Resources Innovative Ideas Proofs

30 Date: Session: Presenters: Metrics Tools Resources Innovative Ideas Proofs

MODULE #6 COMMISSIONING, VALIDATION, CERTIFICATIONS

MODULE #6 COMMISSIONING, VALIDATION, CERTIFICATIONS MODULE #6 COMMISSIONING, VALIDATION, CERTIFICATIONS MICHAEL WALSH PRINCIPAL, R.G. VANDERWEIL ENGINEERS, LLP 274 Summer Street, Boston, MA 02210 (T) 617-423-7423 (F) 617-423-7401 mwalsh@vanderweil.com Module

More information

Section 6.6 BSL3 & ABSL3 Biocontainment

Section 6.6 BSL3 & ABSL3 Biocontainment NIH Design Requirements Manual 8-22-12 Section 6.6 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 Section 6.6

More information

CONSTRUCTION REQUIREMENTS

CONSTRUCTION REQUIREMENTS CONSTRUCTION REQUIREMENTS Note: The buildings on the UCCS campus are divided into two categories: General Fund and Auxiliaries. General Fund Buildings include academic and administrative functions. Auxiliary

More information

NC State University Design and Construction Guidelines Division 00 Planning & Design - Laboratory Design

NC State University Design and Construction Guidelines Division 00 Planning & Design - Laboratory Design 1.0 Purpose A. This section discusses the safety features that must be included in university laboratories and the design standards for various classifications of laboratories and laboratory equipment.

More information

INTEGRATED VPHP DECONTAMINATION SYSTEMS THE EMERGING UTILITY

INTEGRATED VPHP DECONTAMINATION SYSTEMS THE EMERGING UTILITY INTEGRATED VPHP DECONTAMINATION SYSTEMS THE EMERGING UTILITY John Klostermyer, Ph.D. ISPE Product Show Track 3 Session 3 September 26, 2018 AGENDA 1. BACKGROUND INFORMATION 2. BENEFITS 3. PROCESS 4. BEST

More information

The Milton S. Hershey Medical Center Academic Support Building. AE Senior Thesis Kari Anne Donovan Mechanical Option

The Milton S. Hershey Medical Center Academic Support Building. AE Senior Thesis Kari Anne Donovan Mechanical Option The Milton S. Hershey Medical Center Academic Support Building AE Senior Thesis Kari Anne Donovan Mechanical Option Presentation Outline Existing Conditions Distributed Chilled Water Feasibility Study

More information

DESIGN CHECKLIST PROJECT NAME DISCIPLINE DATE TYPE REVIEW REVIEWER DRAWINGS REVIEWED

DESIGN CHECKLIST PROJECT NAME DISCIPLINE DATE TYPE REVIEW REVIEWER DRAWINGS REVIEWED DESIGN CHECKLIST PROJECT NAME DISCIPLINE DATE TYPE REVIEW REVIEWER DRAWINGS REVIEWED EVERY ITEM WILL BE REVIEWED AND NOTED FOR COMPLIANCE (C), OR NON- APPLICABILITY (NA). 1. HEATING SYSTEMS: A. GENERAL

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

CONSTRUCTION DOCUMENTS CHECKLIST for the 2012 Michigan Building Code Including Building Permit Application Checklist

CONSTRUCTION DOCUMENTS CHECKLIST for the 2012 Michigan Building Code Including Building Permit Application Checklist CONSTRUCTION DOCUMENTS CHECKLIST for the 2012 Michigan Building Code Including Building Permit Application Checklist This checklist is a convenient reference to the 2012 Michigan Building Code. The checklist

More information

Janice Reedus, Director of Business & Auxiliary Services Campus Center Building A, Room Houbolt Road Joliet, IL 60431

Janice Reedus, Director of Business & Auxiliary Services Campus Center Building A, Room Houbolt Road Joliet, IL 60431 DATE: January 9, 2015 Addendum No. 1 Page 1 of 7 Joliet Junior College 1215 Houbolt Road Joliet, IL 60431 TO: Prospective Respondents SUBJECT: Addendum No. 1 PROJECT NAME: Commissioning Agent Services

More information

DIVISION MEDIUM VOLTAGE VAULT DESIGN Contents MEDIUM VOLTAGE VAULT DESIGN... 2 DIVISION LIST OF FIGURES...

DIVISION MEDIUM VOLTAGE VAULT DESIGN Contents MEDIUM VOLTAGE VAULT DESIGN... 2 DIVISION LIST OF FIGURES... DIVISION 13 00 60 - MEDIUM VOLTAGE VAULT DESIGN Contents 13 00 60 - MEDIUM VOLTAGE VAULT DESIGN... 2 DIVISION 13 00 60 LIST OF FIGURES... 6 13 00 60 - MEDIUM VOLTAGE VAULT DESIGN 1. General Requirements

More information

DIVISION MEDIUM VOLTAGE VAULT DESIGN Contents

DIVISION MEDIUM VOLTAGE VAULT DESIGN Contents DIVISION 13 00 60 - MEDIUM VOLTAGE VAULT DESIGN Contents 13 00 60 - MEDIUM VOLTAGE VAULT DESIGN... 2 DIVISION 13 00 60 LIST OF FIGURES... 6 Page 1 of 6 13 00 60 - MEDIUM VOLTAGE VAULT DESIGN 1. General

More information

The baseline building system for compliance with Senate Bill 668 is defined by Appendix G,

The baseline building system for compliance with Senate Bill 668 is defined by Appendix G, Project: North Carolina A&T State University New Student Health Center SCO #: 08-08109-01A 1.0 Heating, Ventilating and Air Conditioning (HVAC) Baseline Building Systems Senate Bill 668 Compliance The

More information

Form 9: Infection Control Preventive Measures Level 4

Form 9: Infection Control Preventive Measures Level 4 Form 9: Infection Control This form is filled out by the construction planning team or designated person(s) to identify the required preventive measures for the activity described in Form 1 Infection Control

More information

Commissioning at NYP. Joseph Lorino, PE, LEED Corporate Director April 1, 2014

Commissioning at NYP. Joseph Lorino, PE, LEED Corporate Director April 1, 2014 1 Commissioning at NYP Joseph Lorino, PE, LEED Corporate Director April 1, 2014 Presentation Agenda 2 What is Commissioning Why Commission? Developing NYP s Commissioning Program NYP Commissioning Process

More information

Building Permit Application

Building Permit Application Building Permit Application Administrative Use Only PARENT PERMIT NUMBER (Required if part of another project) PERMITTEE: PERMITTEE ADDRESS: E-MAIL ADDRESS: ARCHITECT/ENGINEER: ARCHITECT/ENGINEER ADDRESS:

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

Broad Institute Expansion: Cambridge, Massachusetts. Mechanical Thesis Proposal

Broad Institute Expansion: Cambridge, Massachusetts. Mechanical Thesis Proposal Broad Institute Expansion: Cambridge, Massachusetts Mechanical Thesis Proposal Table of Contents Executive Summary... 2 Building Overview... 3 Mechanical System Overview... 4 Mechanical System Design Objectives...

More information

BIO-WASTE SYSTEMS. Thermal & Chemical Effluent Kill Systems. Biotech & Pharmaceutical. Batch Process Systems. Continuous Process Systems

BIO-WASTE SYSTEMS. Thermal & Chemical Effluent Kill Systems. Biotech & Pharmaceutical. Batch Process Systems. Continuous Process Systems Biotech & Pharmaceutical BIO-WASTE SYSTEMS Thermal & Chemical Effluent Kill Systems Batch Process Systems Continuous Process Systems Sump Collection Systems Heat Inactivation Chemical Inactivation Neutralization

More information

Bid Package 15A Mechanical

Bid Package 15A Mechanical Bid Package 23A Mechanical & HVAC The successful Subcontractor acknowledges and agrees to the requirements set forth by this bid package and its descriptions and in conjunction with all other Construction

More information

DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING

DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING Purpose: The purpose of this Directive is to describe, in outline, the requirements of Commissioning on SUCF Projects. 1. Applicability a. New York

More information

THE IMPORTANCE OF EQUIPMENT ACCESSIBILITY IN BUILDINGS

THE IMPORTANCE OF EQUIPMENT ACCESSIBILITY IN BUILDINGS THE IMPORTANCE OF EQUIPMENT ACCESSIBILITY IN BUILDINGS Throughout the commissioning process, we often find issues with accessibility to equipment, whether it be a heat pump above a ceiling grid or an air

More information

A Closer Look Inspection Service 2015 IECC Residential DFW area handout

A Closer Look Inspection Service 2015 IECC Residential DFW area handout 103.2 Information required on construction documents 1. Designation of the Thermal Building Envelope on the plans 2. Insulation Material and their R Value 3. Fenestration U and SHGC values 4. Area weighted

More information

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 02/06/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 02/06/2013 BUILDING SURVEY DATE 0067 1110 WEST GREEN STREET URBANA, ILLINOIS 61801 SYSTEM CONDITION INDEX.810 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 18,640,900 OFFICE BUILDING GROSS SQUARE FEET 175,513

More information

Inspection requests submitted by 2:30pm will be scheduled for the following business day unless otherwise requested.

Inspection requests submitted by 2:30pm will be scheduled for the following business day unless otherwise requested. Purpose 355 West Queens Road Single Family New Construction Required Inspection Stages Master Requirement GEN 110 Building Department: 604-990-2480, building@dnv.org, fax: 604-984-9683 The following procedure

More information

High Containment Laboratories:

High Containment Laboratories: Building Design and Engineering Approaches to Airborne Infection Control Harvard School of Public Health Center for Continuing Professional Education August 2-13, 2010 Boston, Massachusetts High Containment

More information

Sustainable Laboratory Design: Challenges and Solutions

Sustainable Laboratory Design: Challenges and Solutions Sustainable Laboratory Design: Challenges and Solutions Stephen P. Mead Ph.D. College of Engineering Northern Arizona University U.S.A. Abstract: This paper provides a case study analysis of a biohazard

More information

Commissioning the ABSL-3 Laboratory

Commissioning the ABSL-3 Laboratory Commissioning the ABSL-3 Laboratory Michael C. Rosenberg P.E. Stanley Consultants Synopsis Airflow and pressurization relationships are adjusted and verified in most buildings with temperature / humidity

More information

Identify and Quantify Mission-Critical Factors (How to Perform a Critical Audit) Neil Maldeis, Energy Solutions Engineering Leader, Trane

Identify and Quantify Mission-Critical Factors (How to Perform a Critical Audit) Neil Maldeis, Energy Solutions Engineering Leader, Trane Identify and Quantify Mission-Critical Factors (How to Perform a Critical Audit) Neil Maldeis, Energy Solutions Engineering Leader, Trane Learning Objectives Benefits of a critical system audit How to

More information

Brown University Updated March 11, 2013 Facilities Design & Construction Standards

Brown University Updated March 11, 2013 Facilities Design & Construction Standards SECTION 01 17 90 UTILITY & CRITICAL SYSTEM CONNECTIONS AND INTERRUPTIONS PART 1 - GENERAL 1.1 SUMMARY: A. Brown University operates and maintains extensive campus and building utilities and distribution

More information

Permit Application Commercial / Industrial / Multi-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE

Permit Application Commercial / Industrial / Multi-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE STAFF USE ONLY RECEIVED BY: DATE: Permit Application Commercial / Industrial / Multi-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE Applicant must complete numbered items

More information

Georgetown University New Science Center

Georgetown University New Science Center Georgetown University New Science Center Final Thesis Proposal PENN STATE UNIVERSITY Prepared For: Dr. William P. Bahnfleth Department of Architectural Engineering Prepared By: Kevin M Edstrom Mechanical

More information

2014 British Columbia Building Code Changes

2014 British Columbia Building Code Changes 2014 British Columbia Building Code Changes A City of Prince George interpretation of the 2014 Building Code Changes for 9.32 & 9.36 The following changes reflect the most notable revisions and staff interpretations.

More information

KITCHEN REMODELS CITY OF MISSION VIEJO BUILDING SERVICES DIVISON 200 CIVIC CENTER, MISSION VIEJO, CA (949)

KITCHEN REMODELS CITY OF MISSION VIEJO BUILDING SERVICES DIVISON 200 CIVIC CENTER, MISSION VIEJO, CA (949) CITY OF MISSION VIEJO BUILDING SERVICES DIVISON 200 CIVIC CENTER, MISSION VIEJO, CA 92691 (949) 470-3054 KITCHEN REMODELS A permit is required for kitchen remodels that include removal and replacement

More information

CONSTRUCTION DOCUMENTS NECESSARY FOR PLAN REVIEW

CONSTRUCTION DOCUMENTS NECESSARY FOR PLAN REVIEW 2012 International Residential Code 2012 International Building Code 2012 International Fire Code 2014 NFPA 70 National Electrical Code 2012 International Existing Building Code 2012 International Plumbing

More information

Current as of 11/10/08 1 of 5

Current as of 11/10/08 1 of 5 BEST PRACTICES STANDARDS FOR SCHOOLS UNDER CONSTRUCTION OR BEING PLANNED FOR CONSTRUCTION I. Site Layout A. School buildings shall be provided with a securable perimeter. A securable perimeter means that

More information

Carter's Oshkosh (SIS) # The Center at Pearland Parkway - Pearland, TX Scope Of Work / Bid Qualifications

Carter's Oshkosh (SIS) # The Center at Pearland Parkway - Pearland, TX Scope Of Work / Bid Qualifications Carter's Oshkosh (SIS) #1185 - The Center at Pearland Parkway - Pearland, TX 77581 - Scope Of Work / Bid Qualifications Please fill out the blanks associated with your trade scope or work with the words

More information

COMcheck Software Version Envelope Compliance Certificate

COMcheck Software Version Envelope Compliance Certificate COMcheck Software Version 4.0.2.8 Envelope Compliance Certificate Project Information Energy Code: 20 IECC Location: Cedar Hills, Utah Climate Zone: 5b Project Type: New Construction Vertical Glazing /

More information

Common Plan Review Rejection Reasons

Common Plan Review Rejection Reasons Common Plan Review Rejection Reasons Submitted plans must contain sufficient information for plan reviewers to be able to verify that the proposed construction complies with the Virginia Uniform Statewide

More information

Crawl Space Moisture Control

Crawl Space Moisture Control Crawl Space Moisture Control Crawl space foundations are found in many homes. Typically, these foundation types are equipped with operable vents designed to provide ventilation for moisture control. Unfortunately,

More information

Common Plan Review Rejection Reasons

Common Plan Review Rejection Reasons (CPHD) (ISD) Common Plan Review Rejection Reasons Submitted plans must contain sufficient information for plan reviewers to be able to verify that the proposed construction complies with the Virginia Uniform

More information

Permit Application Commercial / Industrial / Mutli-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE (Form #2)

Permit Application Commercial / Industrial / Mutli-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE (Form #2) STAFF USE ONLY RECEIVED BY: DATE: Permit Application Commercial / Industrial / Mutli-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE (Form #2) Applicant must complete

More information

Overbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements %

Overbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements % 8/13/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 64 64% 2.2 Accessibility 0 66 66% 2.3 Structural 0 77 77% 2.4 Building Envelope 0 4 4% 2. Interior

More information

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 02/07/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 02/07/2013 BUILDING SURVEY DATE 0066 104 SOUTH GOODWIN AVENUE URBANA, ILLINOIS 61801 SYSTEM CONDITION INDEX.860 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 14,711,600 LABORATORY BUILDING GROSS SQUARE

More information

ENGINEERING DESIGN GUIDELINES. Purpose

ENGINEERING DESIGN GUIDELINES. Purpose ENGINEERING DESIGN GUIDELINES Purpose The engineering design guidelines have been established to address the most common project elements at ASU. They are to be used in conjunction with the requirements

More information

ASSESSMENT, CLEANING & RESTORATION OF HVAC SYSTEMS (ACR-2002)

ASSESSMENT, CLEANING & RESTORATION OF HVAC SYSTEMS (ACR-2002) ASSESSMENT, CLEANING & RESTORATION OF HVAC SYSTEMS (ACR-2002) C Cochrane * and T Yacobellis National Air Duct Cleaners Association ACR 2002 Committee, Washington, DC, USA ABSTRACT In the fall of 2001 NADCA

More information

Training Certification Categories

Training Certification Categories Training Certification Categories Residential Residential Building Inspector structures are free from hazardous structural conditions and comply with the UCC. Duties include inspection of footings and

More information

THERMAL POWER PLANT SIMULATOR TPP 200 LABORATORY EXERCISE TUTORIAL N4: INTRODUCTION TO THE HEAT PRODUCTION SYSTEM

THERMAL POWER PLANT SIMULATOR TPP 200 LABORATORY EXERCISE TUTORIAL N4: INTRODUCTION TO THE HEAT PRODUCTION SYSTEM EKV THERMAL POWER PLANT SIMULATOR TPP 200 LABORATORY EXERCISE TUTORIAL N4: INTRODUCTION TO THE HEAT PRODUCTION SYSTEM Master of Science Thesis Division of Heat and Power Technology 2003 Department of Energy

More information

NEBBinar: Managing Building Performance through Commissioning. March 28, 2013

NEBBinar: Managing Building Performance through Commissioning. March 28, 2013 NEBBinar: Managing Building Performance through Commissioning March 28, 2013 0 Moderator Jim Huber, NEBB Vice President and President of Complete Commissioning Jim Huber is the President of Complete Commissioning.

More information

Village of Gurnee Construction Documents Submittal Requirements

Village of Gurnee Construction Documents Submittal Requirements Commercial New Construction 4 sets of complete plans Commercial Alterations 2 sets of complete plans Residential New Construction, Remodel and/or Addition 2 sets of complete plans DETAILED PLAN REQUIREMENTS

More information

Effluent Decontamination

Effluent Decontamination Effluent Decontamination A LARGE RANGE OF SYSTEMS FOR LABS AND BIO-INDUSTRIES Batch and Continuous Technologies EFFLUENT DECONTAMINATION SYSTEMS FOR LABS AND BIOFACILITIES FROM 3 TO 47,500 GALLONS PER

More information

HYDRONIC PIPING CHAPTER 12

HYDRONIC PIPING CHAPTER 12 CHAPTER 12 HYDRONIC PIPING SECTION 1201 GENERAL 1201.1 Scope. The provisions of this chapter shall govern the construction, installation, alteration and repair of hydronic piping systems. This chapter

More information

Date Rater Verified. Rater Verified. Slab / Pre-Drywall / Thermal Inspection

Date Rater Verified. Rater Verified. Slab / Pre-Drywall / Thermal Inspection Slab on Grade & Basements: A capillary break is installed on top of all footings Slab / Pre-Drywall / Thermal Inspection A minimum of 4" of clean or washed gravel (0.5" diameter or greater) is placed over

More information

SECTION LABORATORY FUME HOODS

SECTION LABORATORY FUME HOODS PART 1 - GENERAL 1.1 DESCRIPTION: SECTION 11 53 13 LABORATORY FUME HOODS SPEC WRITER NOTE: Delete between // // if not applicable to project. Delete other items or paragraphs in the section that are not

More information

CHILLED WATER DISTRIBUTION SYSTEM

CHILLED WATER DISTRIBUTION SYSTEM Campus-Wide System: A campus-wide central chilled water system has been developed in recent years and is being expanded to serve additional cooling loads as need arises and opportunity affords. This system

More information

HVAC SYSTEM DESIGN PROCESS

HVAC SYSTEM DESIGN PROCESS HVAC SYSTEM DESIGN PROCESS Ball State Architecture ENVIRONMENTAL SYSTEMS 2 Summer 2011 Grondzik 1 HVAC System Design Process Establish design intents/criteria (including code/standard compliance) Establish

More information

Energy Efficiency Requirements 9.36

Energy Efficiency Requirements 9.36 The following information has been obtained from the HPO Illustrated Guide, Energy Efficiency Requirements for Houses in British Columbia, BCBC 9.36 & 9.32, Building Officials Association of British Columbia

More information

SECTION AIR TERMINAL UNITS

SECTION AIR TERMINAL UNITS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Specification Sections, apply to this Section. B. Related Sections:

More information

Indoor Air Quality and Mechanical Ventilation (Page 1 of 5)

Indoor Air Quality and Mechanical Ventilation (Page 1 of 5) Indoor Air Quality and Mechanical Ventilation (Page 1 of 5) Title 24, Part 6, Section 150.0(o) Ventilation for Indoor Air Quality. All dwelling units shall meet the requirements of ANSI/ASHRAE Standard62.2.

More information

STATE UNIVERSITY CONSTRUCTION FUND

STATE UNIVERSITY CONSTRUCTION FUND DIRECTIVE 1A-8 Issue date: October 2014 CONSTRUCTABILITY REVIEW 1. The Consultant shall be required to perform a constructability review with the College, Fund s Design Coordinator, Fund s Construction

More information

Telecommunication Spaces

Telecommunication Spaces Telecommunication Spaces October 19, 2016 Page 1 Revision History Telecommunication Spaces Standard Effective Date Email Version Contact Phone OIT-TS strevena@csustan.edu 1.0 Stan Trevena 209.667.3137

More information

Chilled Beams. The new system of choice?

Chilled Beams. The new system of choice? Chilled Beams The new system of choice? Presented By: Kevin M. Pope P.E. Jason Leffingwell Hammel Green And Abrahamson, Inc. and Ken Bauer, P.E., LEED AP Butters-Fetting Co., Inc. History of Chilled Beams

More information

DESIGN DEVELOPMENT REVIEW PACKAGE CHECKLIST

DESIGN DEVELOPMENT REVIEW PACKAGE CHECKLIST DESIGN DEVELOPMENT REVIEW PACKAGE CHECKLIST Check off each item that is included within the submitted Design Development Review Package. Provide a written explanation for any omissions. The following items,

More information

IECC 2006 with Hawaii Amendments

IECC 2006 with Hawaii Amendments IECC 2006 with Hawaii Amendments COMMERCIAL PLAN REVIEW CHECKLIST ENVELOPE REQUIREMENTS Instructions This form is intended for use by energy code plan reviewers. Please see also a separate set of checklists

More information

Gerald R. Ford Museum

Gerald R. Ford Museum Gerald R. Ford Museum Grand Rapids, Michigan Executive Summary Building and Plant Energy Analysis Report: Part I Brendan J. Cullen The Pennsylvania State University AE Senior Thesis Mechanical Option September

More information

SPARTANBURG COUNTY BUILDING CODES DEPARTMENT

SPARTANBURG COUNTY BUILDING CODES DEPARTMENT SPARTANBURG COUNTY BUILDING CODES DEPARTMENT PLAN REVIEW CHECK LIST REQUIREMENTS FOR COMMERCIAL BUILDING PERMITS Plan Review Coordinator Kris Brannon 864-596-3180 366 N. Church St Room 500 Spartanburg,

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % 8/11/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 82 82% 2.3 Structural 0 7 7% 2.4 Building Envelope 0 47 47% 2. Interior

More information

Fundamentals of Test & Balance for Engineers, Cx & Energy Providers Course Number: CXENERGY1619

Fundamentals of Test & Balance for Engineers, Cx & Energy Providers Course Number: CXENERGY1619 AABC Commissioning Group AIA Provider Number 50111116 Fundamentals of Test & Balance for Engineers, Cx & Energy Providers Course Number: CXENERGY1619 Jim Hall, PE, TBE, CxA Systems Management & Balancing,

More information

DESIGNER'S GUIDE. Section IV Close Out Procedures (Revised May 22, 2013) Yale University Facilities Planning & Construction

DESIGNER'S GUIDE. Section IV Close Out Procedures (Revised May 22, 2013) Yale University Facilities Planning & Construction DESIGNER'S GUIDE Section IV Close Out Procedures (Revised May 22, 2013) Yale University Facilities Planning & Construction TO ACCESS SECTION CLICK ON TITLE IN INDEX IV. Table of Contents IV. CLOSE OUT

More information

1. ARI 410 Standard for chilled water, hot water and steam coils. 2. ARI 430 Central Station Air Handling Units

1. ARI 410 Standard for chilled water, hot water and steam coils. 2. ARI 430 Central Station Air Handling Units PART 1: GENERAL 1.01 Purpose: A. This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the engineer is

More information

Energy Reduction in Hospitals

Energy Reduction in Hospitals Energy Reduction in Hospitals OSBORN ENGINEERING DAVE CHOUINARD, CBCP, LEED AP, DIRECTOR HEALTHCARE CARL SCHULTZ, PE, DIRECTOR ENERGY AND FACILITY SYSTEMS MARK WUTZ, PE, DIRECTOR ENERGY & COMMISSIONING

More information

Opening a New Hospital: A Case Study Healthcare Commissioning and the Authority Having Jurisdiction

Opening a New Hospital: A Case Study Healthcare Commissioning and the Authority Having Jurisdiction Opening a New Hospital: A Case Study Healthcare Commissioning and the Authority Having Jurisdiction Matthew Tunnard, PE, CCP, LEED AP, Senior Engineer Horizon Engineering Associates, LLP AIA Quality Assurance

More information

Level 1 Modules tdp-101 hvac industry overview tdp-103 concepts of air conditioning tdp-102 abcs of comfort

Level 1 Modules tdp-101 hvac industry overview tdp-103 concepts of air conditioning tdp-102 abcs of comfort TDP-101 HVAC Industry Overview This TDP provides a general overview of the commercial HVAC industry and provides an awareness of the design process and construction. The documents involved in construction,

More information

Margaret Batts Tobin Laboratory

Margaret Batts Tobin Laboratory Roof Evaluation of Margaret Batts Tobin Laboratory The University of Texas At San Antonio Performed for UTSA Zero/Six Consulting, LLC 8423 Stewart Road Galveston, Texas 77554 409 740 0090 voice Table of

More information

TDPs provide you with new technical training materials designed to help your contractors, engineers, and designers to effectively design, specify,

TDPs provide you with new technical training materials designed to help your contractors, engineers, and designers to effectively design, specify, TDP Catalog TDPs provide you with new technical training materials designed to help your contractors, engineers, and designers to effectively design, specify, sell, and apply HVAC equipment in commercial

More information

5. AMCA 301 Method of Publishing Sound Ratings for Air Moving Devices. 6. AMCA 500 Test Methods for Louver, Dampers, and Shutters

5. AMCA 301 Method of Publishing Sound Ratings for Air Moving Devices. 6. AMCA 500 Test Methods for Louver, Dampers, and Shutters PART 1: GENERAL 1.01 Purpose: A. This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the engineer is

More information

INSPECTION TIMING CHECKLIST FOR RESIDENTIAL FRAME BUILDING PRIOR TO INSPECTION REQUEST

INSPECTION TIMING CHECKLIST FOR RESIDENTIAL FRAME BUILDING PRIOR TO INSPECTION REQUEST Village of Vernon Hills Community Development Department - Building Division 290 Evergreen Drive, Vernon Hills, IL 60061 Phone 847-367-3704 - Fax 847-367-2541 - http://www.vernonhills.org INSPECTION TIMING

More information

SECTION PLUMBING PIPING SYSTEM

SECTION PLUMBING PIPING SYSTEM SECTION 15410 - PLUMBING PIPING SYSTEM PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Basic Requirements: Provisions of Section 15010, BASIC MECHANICAL REQUIREMENTS, are a part of this Section. 1.02 SUMMARY

More information

ABSA Anaheim, California

ABSA Anaheim, California ABSA Anaheim, California 54 th Annual Biological Safety Conference Session XIV: Roundtable-Animal Biosafety Prep for Animal Handling, Biocontainment Systems, & Decontamination Options November 2, 2011

More information

Technology and Engineering Development (TED) Building. ASHRAE Std and Std Compliance Report

Technology and Engineering Development (TED) Building. ASHRAE Std and Std Compliance Report Technology and Engineering Development (TED) Building Thomas Jefferson National Accelerator Facility Newport News, VA Tech Report I ASHRAE Std. 62.1-2007 and Std. 90.1-2007 Compliance Report 10/4/2010

More information

Commissioning for Energy Savings

Commissioning for Energy Savings Commissioning for Energy Savings Presented To: AEE / ASHRAE / USGBC 2013 Energy Expo St. Paul RiverCentre, St. Paul, Minnesota October 2, 2013 Presented By: Rebecca T. Ellis, PE LEED AP BD+C, CCP, CPMP

More information

B. ASHRAE 1991 HVAC Applications Handbook: Chapter 34--Testing, Adjusting and Balancing.

B. ASHRAE 1991 HVAC Applications Handbook: Chapter 34--Testing, Adjusting and Balancing. PART 1 GENERAL 1.1 RELATED DOCUMENTS SECTION 230593 TESTING, ADJUSTING, AND BALANCING A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 Specification

More information

FACILITY DESIGN PLAN FOR INDOOR PRACTICE AND HUMAN PERFORMANCE FACILITY SOUTH DAKOTA STATE UNIVERSITY

FACILITY DESIGN PLAN FOR INDOOR PRACTICE AND HUMAN PERFORMANCE FACILITY SOUTH DAKOTA STATE UNIVERSITY FACILITY DESIGN PLAN FOR INDOOR PRACTICE AND HUMAN PERFORMANCE FACILITY SOUTH DAKOTA STATE UNIVERSITY DATE: November 20, 2012 SDSU requests approval of this Facility Design Plan to continue planning the

More information

MODULE 5 HVAC FUNDAMENTALS OF MODERN LABORATORY DESIGN

MODULE 5 HVAC FUNDAMENTALS OF MODERN LABORATORY DESIGN MODULE 5 HVAC FUNDAMENTALS OF MODERN LABORATORY DESIGN Module 5 PG1 MODULE 5 GOAL Provide a fundamental understanding of Laboratory Heating, Ventilating and Air Conditioning Concepts and Systems Module

More information

Chapter 9 - Design Guides 9.18 HVAC GUIDE

Chapter 9 - Design Guides 9.18 HVAC GUIDE A. GENERAL 9.18 HVAC GUIDE 1. The purpose of this guide is to convey general basis-of-design, standard of quality, and OGS preferences as they relate to building HVAC system design. Specific client agency

More information

DARTMOUTH COLLEGE DESIGN January 2019 & CONSTRUCTION GUIDELINES

DARTMOUTH COLLEGE DESIGN January 2019 & CONSTRUCTION GUIDELINES SECTION 15010 (23 00 00) BASIC MECHANICAL REQUIREMENTS PART 1 DESIGN DIRECTIVES 1.1 SUMMARY A. The Dartmouth College Design & Construction Guidelines include general administrative, design, product, and

More information

S CHEDULE G - D OCUMENTS S UBMITTAL R EQUIREMENTS

S CHEDULE G - D OCUMENTS S UBMITTAL R EQUIREMENTS S CHEDULE G - D OCUMENTS S UBMITTAL R EQUIREMENTS This Attachment lists the items to be provided by the Architect in accordance with Owner/Architect Agreement. This list is not all-inclusive, nor is it

More information

NEBBinar: Retro-Commissioning for Comfort and Energy Efficiency. August 21, 2013

NEBBinar: Retro-Commissioning for Comfort and Energy Efficiency. August 21, 2013 NEBBinar: Retro-Commissioning for Comfort and Energy Efficiency August 21, 2013 0 Moderator Jim Huber, NEBB Vice President and President of Complete Commissioning Jim Huber is the President of Complete

More information

DESIGN BASIS FOR AIR CONDITIONING AND VENTILATION SYSTEM FOR SUBSTATION AND CONTROL BUILDING HINDUSTAN PETROLEUM CORPORATION LTD.

DESIGN BASIS FOR AIR CONDITIONING AND VENTILATION SYSTEM FOR SUBSTATION AND CONTROL BUILDING HINDUSTAN PETROLEUM CORPORATION LTD. CONDITIONING AND VENTILATION FOR SUBSTATION AND CONTROL BUILDING HINDUSTAN PETROLEUM CORPORATION LTD. VISAKH REFINERY DHT PROJECT TEIL JOB NO.: 6261 DOCUMENT NO.: 6261-HVAC-PKG-300 TEIL SPECIFICATION NO.:---

More information

HYDRONIC PIPING CHAPTER 12

HYDRONIC PIPING CHAPTER 12 CHAPTER 12 HYDRONIC PIPING SECTION 1201 GENERAL 1201.1 Scope. The provisions of this chapter shall govern the construction, installation, alteration and repair of hydronic piping systems. This chapter

More information

Retail Effects of ANSI/ASHRAE/IES Standard

Retail Effects of ANSI/ASHRAE/IES Standard Retail Effects of ANSI/ASHRAE/IES Standard 90.1-2016 Prepared by Dialectic Inc. INTRODUCTION Background ANSI/ASHRAE/IES 90.1-2016 Energy Standard for Buildings Except Low-Rise Residential Buildings replaces

More information

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 04/08/2013 BUILDING SURVEY DATE

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 04/08/2013 BUILDING SURVEY DATE 0331 501 EAST DANIEL STREET CHAMPAIGN, ILLINOIS 61820 SYSTEM CONDITION INDEX.342 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 3,361,900 OFFICE BUILDING GROSS SQUARE FEET

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % 8/11/ Building Rating System Percent Site: 1.0 Total 0 163 82% Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 92 92% 2.3 Structural 0 91 91% 2.4 Building Envelope 0 84 84% 2. Interior

More information

DARTMOUTH COLLEGE DESIGN January 3, 2012 & CONSTRUCTION GUIDELINES

DARTMOUTH COLLEGE DESIGN January 3, 2012 & CONSTRUCTION GUIDELINES SECTION 15010 BASIC MECHANICAL REQUIREMENTS PART 1 DESIGN DIRECTIVES 1.1 SUMMARY A. The Dartmouth College Design & Construction Guidelines include general administrative, design requirements, products,

More information

Attic Access Hatch to have an area not less than 0.32m²/3.4ft² and no dimension less than 500mm with a min R-15 insulation value Crawlspace

Attic Access Hatch to have an area not less than 0.32m²/3.4ft² and no dimension less than 500mm with a min R-15 insulation value Crawlspace NOTABLE CODE REQUIREMENTS the following list represents important code requirements that shall be implemented into construction while still maintaining full compliance with all other requirements within

More information

2016 HEAPR Project Request. Winona State University

2016 HEAPR Project Request. Winona State University 2016 HEAPR Project Request Winona State University Project Title: Stark Hall HVAC Improvements Project Priority: 2 of 3 Request Amount: $1,805,000 Project Summary: This project started when an academic

More information

Rebel commercial packaged rooftop systems

Rebel commercial packaged rooftop systems Rebel commercial packaged rooftop systems Advanced technologies propel performance and energy savings to uncommon levels 3-28 tons Rebel features and benefits 18 13 6 5 3 6 4 43% Energy Savings 5 11 12

More information

Rebel commercial packaged rooftop systems

Rebel commercial packaged rooftop systems Rebel commercial packaged rooftop systems Advanced technologies propel performance and energy savings to uncommon levels 3-28 tons Capitalize with 43% more energy savings If you are a commercial building

More information

Permit Application Commercial / Industrial / Multi-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE

Permit Application Commercial / Industrial / Multi-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE STAFF USE ONLY RECEIVED BY: DATE: Permit Application Commercial / Industrial / Multi-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE Applicant must complete numbered items

More information