The Project Management Cer8ficate Program. Project Time Management

Size: px
Start display at page:

Download "The Project Management Cer8ficate Program. Project Time Management"

Transcription

1 PMP cross-cutting skills have been updated in the PMP Exam Content Outline June 2015 (PDF of the Examination Content Outline - June 2015 can be found under the Resources Tab). Learn about why the PMP exam is changing in Download the new Exam Content Outline to study cross-cutting skills here: IIL- CERT Interna8onal Ins8tute for Learning, Inc. 1

2 IIL- CERT Interna8onal Ins8tute for Learning, Inc. 2

3 IIL- CERT Interna8onal Ins8tute for Learning, Inc. 3

4 Review these learning objec8ves carefully. The learning content contained within this module is based on these learning objec8ves. At the end of this module or the end of the course, you should be able to answer quiz or test ques8ons related to these learning objec8ves. If you are par8cipa8ng in this course for cer8fica8on, you will be beoer prepared to pass a cer8fica8on exam by recalling these learning objec8ves. 4

5 includes the processes required to manage the 8mely comple8on of the project. PMBOK Guide FiSh Edi8on, Glossary The seven processes of typically begin aser the project team has ini8ated the project planning effort and the scope has been reasonably developed. The Project Time Management processes add the element of how 8me will be managed to the project management plan. It also describes how the schedule will be developed, maintained and controlled. 5

6 The PMBOK Guide FiSh Edi8on describes the key benefit of this process as providing guidance on how the schedule will be managed. PMBOK Guide FiSh Edi8on, p

7 The PMBOK Guide FiSh Edi8on defines the following for this first process: Inputs Project management plan Project charter Enterprise environmental factors Organiza8onal process assets Tools & Techniques Expert judgment Analy8cal techniques Mee8ngs Outputs Schedule management plan 7

8 The project management plan feeds input into the 8me management process such as es8ma8ng dura8ons and resources, as well as how risks will be managed and required reports. 8

9 9

10 Rules of performance measurement include: Which percentage complete to use? What control accounts to roll data into? What earned value measurement techniques to use? What tolerance intervals should be used? 10

11 The PMBOK Guide FiSh Edi8on describes the key benefit of this process as breaking down work packages into ac8vi8es. PMBOK Guide FiSh Edi8on, p. 149 There is osen confusion between ac8vi8es and work packages. To clarify, work packages are the lowest level of the WBS. Once you move the WBS into a schedule, they may further be broken down into ac8vi8es. Whether work packages or ac8vi8es are the lowest level of the schedule, this is the level at which es8ma8ng takes place. Ac8vi8es represent the work of the project. Many 8mes, sosware such as MicrosoS Project, Primavera and Artemis (just to name a few) are used to collect the ac8vity list, es8mates, dependencies and resources. These scheduling ar8facts are later developed into a model of the project. Defining the ac8vi8es is the first step in working with project schedules as defined in the ac8on steps below. Ac8on steps: Setup the scheduling tool s op8ons Enter Ac8vi8es and Enter Dependencies Enter Es8mates Enter and Assign Resources Enter Deadlines/Constraints Level and op8mize (schedule compression) to hit the deadlines/constraints Gain Agreement on the Schedule Baseline Schedule Enter Actual informa8on on start and finish dates and dura8ons Report variances 11

12 The PMBOK Guide FiSh Edi8on defines the following for the second Project Time Management process: Inputs Schedule management plan Scope baseline Enterprise environmental factors Organiza8onal process assets Tools & Techniques Decomposi8on Rolling wave planning Expert judgment Outputs Ac8vity list Ac8vity aoributes Milestone list 12

13 13

14 A prac8cal considera8on in decomposi8on to the ac8vity level is to determine the appropriate ac8vity list. It must be defined in sufficient detail to assign ac8vi8es to resources that will perform the work, as well as enable the project management team to control the project, during execu8on. Ac8vity aoributes extend the descrip8on of the ac8vity by iden8fying the mul8ple components associated with each ac8vity, which may include, but are not limited to: Ac8vity ID WBS ID Ac8vity name Ac8vity codes Ac8vity descrip8on Ac8vity predecessor and successor ac8vi8es, logical rela8onships, leads and lags Ac8vity resource requirements Ac8vity schedule dates Ac8vity constraints and assump8ons Adapted from: PMBOK Guide FiSh Edi8on, p

15 The ac8vity list should include enough detail that the performers can successfully complete the work of the project. It should also be at a level that es8ma8ng resources and dura8ons can take place. Ac8vity aoributes include a descrip8on of skills required, work es8mates, dependencies and other ar8facts to help the performer understand the work that needs to be done. Milestones represent significant events in the life of a project. Typically they are markers that signify repor8ng points, beginning and ending of units of work and are a defined moment in 8me that requires no work and takes no dura8on. Frequently milestones are used to present a high level picture of the projects progression. 15

16 The PMBOK Guide FiSh Edi8on describes the key benefit of this process as defining the logical sequence of work. PMBOK Guide FiSh Edi8on, p. 153 In building the logic of the scheduling model, place one milestone at the beginning (represen8ng the start of the project) and one milestone at the end (represen8ng the end of the project). All the tasks between the beginning and ending milestone should be connected with logical dependencies. This creates a complete network. Without a complete network of dependencies, it makes it very difficult to understand the logic of the model or to trace the cri8cal path. If the scheduler can t think of a successor to a task it should be connected to the final milestone. Different scheduling sosware packages have specific rules on dependencies. OSen in these packages, if a complete network is not present subsequent tasks will not respond to changes in preceding tasks. MicrosoS Project doesn t require a single star8ng milestone. It allows for mul8ple star8ng points, but requires a single ending point. Primavera requests a single milestone at the beginning and ending of the schedule. Logical Dependencies relate to the predecessor (driving) and successor (driven) tasks that determine the order in which tasks are to be done. Resource dependencies are created when you level a schedule to allow for resource availabili8es. Some tasks may not require logical dependencies. Examples include resource dependencies, recurring tasks that are short in dura8on and are 8me dependent rather than task dependent and hammock tasks that are 8ed to a series of tasks by the start of one task and the end of another task. 16

17 The PMBOK Guide FiSh Edi8on defines the following for the third process: Inputs Schedule management plan Ac8vity list Ac8vity aoributes Milestone list Project scope statement Enterprise environmental factors Organiza8onal process assets Tools & Techniques Precedence diagramming method (PDM) Dependency determina8on Leads and lags Outputs Project schedule network diagrams Project documents updates 17

18 Once the method and the tool are indicated the project manager will combine these with the project data and create a model of the project. The end product of this effort is the project schedule. 18

19 In the Precedence Diagramming Method (PDM), there is a start and finish point with all ac8vi8es taking place in between. The nodes, iden8fied by the leoers in boxes, are the ac8vi8es to be performed. Precedence diagramming method (PDM) is the network logic diagram method of choice today. PDM is used in the Cri8cal Path Method (CPM) when sequencing ac8vi8es to diagram a project schedule network. The ac8vi8es are connected by arrows that show the logical rela8onships that exist between the ac8vi8es. This diagramming method is also referred to as Ac8vity- On- Node (AON) diagram. It can u8lize lags, leads and all four types of dependencies to be discussed in the following material. Historical Note: One type of diagramming method rarely used today is called the Arrow Diagramming Method (ADM), also known as Ac8vity- On- Arrow. Here the ac8vi8es are listed on the arrows and the nodes serve as connecters. This method only uses the Finish- to- Start dependencies (sequen8al logic) and may require the use of dummy ac8vi8es to complete the logic. 19

20 PDM includes four types of precedence rela8onships or logical dependencies. In PDM, finish- to- start (sequen8al dependency) is the most commonly used type of precedence rela8onship. Finish- to- start. The ini8a8on of the successor ac8vity depends on the comple8on of the predecessor ac8vity Finish- to- finish. The comple8on of the successor ac8vity depends upon the comple8on of the predecessor ac8vity Start- to- start. The ini8a8on of the successor ac8vity depends upon the ini8a8on of the predecessor ac8vity Start- to- finish. The comple8on of the successor ac8vity depends upon the start of the predecessor ac8vity 20

21 In addi8on to sequencing ac8vi8es using logical rela8onships, three types of dependencies are used to define the sequence among the ac8vi8es: Mandatory dependencies are referred to as hard logic, and osen involve physical limita8ons that makes it impossible to move forward without comple8on the predecessor ac8vity. Discre5onary dependencies are referred to as preferred logic, preferen8al logic or sos logic. These dependencies should be fully documented, because they can create arbitrary total float values and can limit scheduling op8ons that may be posed later in the project life cycle. External dependencies represent a rela8onship between project and non- project ac8vi8es. For example, delivery of compu8ng hardware from an external source is an external dependency for a sosware developing project s tes8ng environment configura8on ac8vity. Internal dependencies show the rela8onships between ac8vi8es within the project. 21

22 Lag. The amount of 8me whereby a successor ac8vity is required to be delayed with respect to a predecessor ac8vity. Lead. The amount of 8me whereby a successor ac8vity can be advanced with respect to a predecessor ac8vity. PMBOK Guide FiSh Edi8on, Glossary The use of leads and lags should not replace schedule logic; however, it may be necessary to use lead or lag 8me between ac8vi8es to support a realis8c project schedule. 22

23 A project schedule network diagram is a graphical representa8on of the logical rela8onships among the project schedule ac8vi8es. PMBOK Guide FiSh Edi8on, Glossary 23

24 The PMBOK Guide FiSh Edi8on describes the key benefit of this process as iden8fying the resources to help with es8ma8ng cost and dura8on. PMBOK Guide FiSh Edi8on, p. 160 Es8mate Ac8vity Resources process is necessary for the Es8mate Ac8vity Dura8on process since that process depends on es8mates from the resources that are going to do the work. Resources are also closely related to the process Es8mate Costs. Resource es8mates will be affected by the availability of resources to do the work, skill level required and cost. 24

25 The PMBOK Guide FiSh Edi8on defines the following for the fourth process: Inputs Schedule management plan Ac8vity list Ac8vity aoributes Resource calendars Risk register Ac8vity cost es8mates Enterprise environmental factors Organiza8onal process assets Tools & Techniques Expert judgment Alterna8ve analysis Published es8ma8ng data BoOom- up es8ma8ng Project management sosware Outputs Ac8vity resource requirements Resource breakdown structure 25

26 The amount of detail and the level of specificity of the resource required can vary by applica8on area. Resource requirements should include: The basis of the es8mate for each resource The type of resource The quan88es needed The availability or when the resources will be needed Working assump8ons Snyder, Cynthia Stackpole, A User s Manual to the PMBOK Guide, John Wiley and Sons 2013, p

27 27

28 These tools and techniques applied to the inputs are intended to produce ac8vity resource requirements, a resource breakdown structure (RBS), and informa8on required to update project documenta8on. 28

29 A resource breakdown structure is similar to an organiza8onal chart, except the rela8onships diagrammed reflect the repor8ng of stakeholders on a project as opposed to formal repor8ng rela8onships. 29

30 The PMBOK Guide FiSh Edi8on describes the key benefit of this process as providing the 8me each ac8vity will take to complete. PMBOK Guide FiSh Edi8on, p. 165 Dura8ons are arrived at by determining who is going to do the work, how much effort is required, the cost of the applied resources and the resource s availability. Here we are referring to all types of resources applied. Human, equipment, material, machinery, facili8es, cost, etc. 30

31 The PMBOK Guide FiSh Edi8on defines the following for the fish process: Inputs Schedule management plan Ac8vity list Ac8vity aoributes Ac8vity resource requirements Resource calendars Project scope statement Risk register Resource breakdown structure Enterprise environmental factors Organiza8onal process assets Tools & Techniques Expert judgment Analogous es8ma8ng Parametric es8ma8ng Three- point es8ma8ng Group decision- making techniques Reserve analysis Outputs Ac8vity dura8on es8mates 31

32 32

33 There is a difference between effort and dura8on. Effort, according to the PMBOK Guide FiSh Edi8on, is the number of labor units required to complete a schedule ac8vity or work breakdown structure component, osen expressed in hours, days, or weeks. Contrasted with effort, dura8on is the total number of work periods (not including holidays or other non- working periods) required to complete a schedule ac8vity or work breakdown structure component. It is usually expressed as workdays or workweeks. PMBOK Guide FiSh Edi8on, Glossary One of the necessary inputs for analysis is the dura8on es8mate for each ac8vity. Knowledge of when an ac8vity can start, plus its dura8on, allows you to calculate when it will finish. The dura8on es8mate for each ac8vity is added to the network diagram. This allows you to determine the start and finish dates for each ac8vity. 33

34 Expert judgment can provide dura8on es8mate informa8on or recommended maximum ac8vity dura8ons from similar projects. Analogous es8ma8ng uses parameters such as dura8on, budget, size, weight, and complexity from previous, similar projects to es8mate the dura8on of the current project. Parametric es8ma8ng uses a sta8s8cal rela8onship between historical data and other variables to calculate an es8mate for ac8vity parameters, i.e., cost, budget, and dura8on. 34

35 Three- Point Es5mates using a Beta Distribu5on: Three(3)- point es8mates were first used by the government and a contrac8ng firm for a defense weapons program. The technique is called the Program Evalua8on and Review Technique (PERT). The resul8ng es8mate is a rough sta8s8cal representa8on of the mean of a beta 8me distribu8on weighted towards the most likely informa8on using the formula shown. Its use is appropriate when there is uncertainty (risk) and varia8on associated with es8mates for the ac8vity. PERT analysis calculates an Expected (te) ac8vity dura8on using a weighted average of these three es8mates: to + 4tM + tp (te) = The standard devia8on for the adapted beta distribu8on formula above is: 6 Tp - to (tσ) = Three- Point Es5mates using a Triangular Distribu5on: This calcula8on needs to be performed using the three es8mates of the ac8vity dura8on and is used in planning the project schedule. Triangular es8ma8ng, an alterna8ve three- point es8ma8ng, averages Op8mis8c, Pessimis8c and Most Like es8mates. Its intent is to provide a close approxima8on of the sta8s8cal mean of a triangular distribu8on instead of a beta distribu8on, as shown. + ML + P 35

36 Dura8on es8mates do not include lag 8me that is needed in between ac8vi8es. Ac8vity Dura8on es8mates include some indica8on of range of possible results. For example: Developing a design document may take 2 workweeks +/- 2 days; or there is a low probability, 10%, that the ac8vity will take more than 2 workweeks. Project documents that may need to be updated include, but are not limited to the ac8vity aoributes and assump8ons that were documented when engaged in the ac8vity to es8mate dura8ons. Adapted from Snyder, Cynthia Stackpole, A User s Manual to the PMBOK Guide, John Wiley and Sons 2013, p

37 37

38 The PMBOK Guide FiSh Edi8on describes the key benefit of this process as genera8ng planned dates for comple8ng project ac8vi8es. PMBOK Guide FiSh Edi8on, p. 172 In this process, all the major outputs from the previous processes are used to assemble a project schedule. The ini8al schedule can be based on dura8ons and dependencies. This is the best es8mate of what the Subject MaOer Experts (SMEs) think it will take to complete the project. ASer the ini8al schedule is developed you may need to level the schedule based on resources constraints and availability. OSen 8mes you will need to use schedule compression techniques to reduce the dura8on to meet imposed deadlines. This is an itera8ve process. There are many reasons people prepare schedules for projects. Four of the most compelling are: To sell upper management on an idea. To do so may require a high- level view of the cost and 8me required. To delegate. When you have a detailed WBS, you can more easily assign ac8vi8es to team members. To effec8vely track progress by entering the current status of ac8vi8es into the schedule. To forecast the project end date and total cost. Adapted from: Dynamic Scheduling with MicrosoA Project 2010 by Rodolfo Ambriz, PMP, PMI- SP, PMI- RMP, MCTS, MCITP and John White, MA, PMP, MCT, MCP, MCTS, MCITP 38

39 The PMBOK Guide FiSh Edi8on defines the following for the sixth process: Inputs Schedule management plan Ac8vity list Ac8vity aoributes Project schedule network diagrams Ac8vity resource requirements Resource calendars Ac8vity dura8on es8mates Project scope statement Risk register Project staff assignments Resource breakdown structure Enterprise environmental factors Organiza8onal process assets Tools & Techniques Schedule network analysis Cri8cal path method Cri8cal chain method Resource op8miza8on techniques Modeling techniques Lead and lags Schedule compression Scheduling tool Outputs Schedule baseline Project schedule Schedule data Project calendars Project management plan updates Project documents updates 39

40 The cri8cal path is determined by logical dependencies, it does not consider resource dependencies. The Cri5cal Path Method (CPM) assumes unlimited resources. This means that resource dependencies (leveling delays) are not highlighted as driving forces in the schedule. This can lead to delays in the schedule do to changes in resource assignments or availability. SoSware applica8ons also do a forward and backward pass The forward and backward pass calculate the following items on each ac8vity: Total Float (ac8vi8es with zero total float are considered cri8cal). Free Float Early Start, Early Finish, Late Start and Late Finish. Free float: The amount of 8me that a schedule ac8vity can be delayed without delaying the early start date of any successor or viola8ng a schedule constraint. Total float: The amount of 8me that a schedule ac8vity can be delayed or extended from its early start date without delaying the project finish date or viola8ng a schedule constraint. Calcula8ng total float: late start early start (or late finish early finish) Slack and Float are synonymous terms. Nega8ve Float occurs when you have a deadline or constraint before (earlier than) the scheduled comple8on of the project schedule. Ac8vi8es with nega8ve float are considered cri8cal since you have already missed a deadline. Also, some8mes you will see Total Float referred to as just Float. The cri8cal paths is the path with the least amount of float. Usually zero float. 40

41 To determine the project cri8cal path, it is necessary to perform a forward pass and a backward pass through the network. The forward pass will iden8fy the early start and early finish 8mes. The backward pass will iden8fy the late start and late finish 8mes. These processes are needed to be able to calculate the float on each ac8vity. Let s take a closer look. 41

42 A forward pass is performed from les to right through the network. This process will iden8fy the early start and early finish for each ac8vity. Start with one for the first ac8vi8es to get the ini8al early start dates, and then add the dura8on to the early start and subtract one to get the early finish for each ac8vity. In the forward pass process, the greater value of the early finish for all predecessors is always used (and incremented by one) when mul8ple predecessors converge onto one successor. Remember: the predecessor s early finish is incremented by one to get the early start for the successor. The early finish for the last ac8vity in the network is also the project dura8on. Therefore the dura8on for the schedule network shown is 24 work periods. SPECIAL NOTE: In previous edi8ons of this course, we used the following method for the forward pass: A forward pass is performed from les to right through the network. This process will iden8fy the early start and early finish for each ac8vity. Start with zero for the first ac8vi8es to get the ini8al early start dates, and then add the dura8on to the early start to get the early finish for each ac8vity. In the forward pass process, the greater value of the early finish for all predecessors is always used when mul8ple predecessors converge onto one successor. The early finish for the last ac8vity in the network is also the project dura8on. Therefore the dura8on for the schedule network shown is 24 work periods. (See the inset on the slide) Because the PMBOK Guide FiSh Edi8on, p. 177 demonstrates the forward pass in the manner we focus on in this slide we will use this method to teach the forward pass. The results of using one method or the other are the same, with the excep8on of the early start. 42

43 A backward pass is performed star8ng from right to les. It will determine the late start and late finish for each ac8vity. Start by inheri8ng the early finish for the late finish in the last ac8vity (J), and then subtract the dura8on from the late finish (and add one) for the late start. The lesser value of all successor tasks that converge from a predecessor (and decremented by one) is used as the late finish for the predecessor, as in ac8vity B. Remember: the successor s late start is decremented by one to get the late finish for the predecessor. SPECIAL NOTE: In previous edi8ons of this course we used the following method for the backward pass: A backward pass is performed star8ng from right to les. It will determine the late start and late finish for each ac8vity. Start by inheri8ng the early finish for the late finish in the last ac8vity (J), and then subtract the dura8on from the late finish for the late start. The lesser value of all successor tasks that converge from a predecessor is used as the late finish for the predecessor, as in ac8vity B. (See the inset on the slide.) Because the PMBOK Guide FiSh Edi8on, p. 177 demonstrates the backward pass in the manner shown on in this slide we will use this method to teach the backward pass. The results of using one method or the other are the same, with the excep8on of the late start. 43

44 The float, denoted in parenthesis, is the amount of 8me you can delay a task without affec8ng the project end date. Float (or Total Slack, Slack or Total Float) can then be calculated as follows: Total float = Late finish Early finish or Total float = Late start Early start Calculate the total float using both formulas as a way of checking for errors. The number should be the same whether using start or finish date formulas. A difference greater than zero indicate tasks that have slack. Zero indicates no slack and a cri8cal ac8vity. Less than zero or nega8ve slack are ac8vi8es that do not meet the project deadline and are also cri8cal. The cri8cal path is comprised of all ac8vi8es that have the least amount of float. Note: Scheduling sosware considers two other elements that were not taken into considera8on during this demonstra8on of the forward pass and backward pass. 1. The demonstra8on assumed that everyday was a working day. In a scheduling tool, the precedence diagram will take into considera8on weekends and non- working days. 2. Scheduling tools will also consider the length of each month. Had this demonstra8on been done on a project covering the month of February there would be only 28 days in the month. This demonstra8on was considering only days, not dates. To replicate the demonstra8on in a scheduling tool: 1. Set the project start date to 1/1/XX. 2. Create a project calendar that has no holidays and shows all seven days of the week as working. 3. Insert columns for Early Start, Early Finish, Late Start, Late Finish and Total Slack. 44

45 The cri8cal chain approach to project management is based on the theory of constraints (TOC), a management philosophy developed and promoted by Eliyahu M. GoldraO. TOC began in manufacturing where the objec8ve is to produce more items in less 8me through the effec8ve use of resources and 8me. Cri8cal chain is used in the project environment to iden8fy the project s schedule constraint and determine how to elevate or in some way improve the situa8on to relieve or eliminate the constraint. TOC differs from the tradi8onal cri8cal path method by focusing on the series of ac8vi8es in a project schedule that becomes the cri8cal chain aser all resource issues have been addressed. Drum resource: The booleneck which is used to schedule an en8re project team. Also refers to the booleneck work sta8on. This resource availability is used to stagger the start of projects. It should be the most highly used resource, and one that is not easy to elevate. Drum Buffer: Buffer placed in the project plan immediately in front of the first use of the drum resource in a project. Its purpose is to enable project accelera8on if the drum resource is available early. Drum buffers are used in a porzolio environment. Add buffers that are non- work schedule ac8vi8es to manage uncertainty. A project buffer is at the end of the cri8cal chain and protects the target finish from slippage A feeding buffer is placed at each point that a chain of dependency ac8vi8es that feeds into the cri8cal chain and protects slippage along the feeding chains Determine the size of the buffer based on dura8on uncertainty in the cri8cal chain. Plan for latest possible start and finish dates and focuses on managing buffer dura8ons. The theory of constraints addresses two major project management goals: Comple8ng projects more quickly Funneling more projects through the organiza8on without adding resources. To reduce project cycle 8me and deliver projects more quickly, cri8cal chain focuses on the longest 45

46 There are several 8mes during the life of a project that the team will need to reduce the dura8on of the project. They include: 1. If aser building an unconstrained schedule (based on SME s es8mates and the order in which the tasks need to be done), a shorter dura8on deadline needs to be met. 2. Once the schedule is baselined and updates start to move the schedule off the baseline, the project team may need to re- plan ( compress) the schedule to get back on the baseline. 3. If resources become over- allocated and need to be leveled. Leveling may move the schedule off the baseline and require op8miza8on (compression). To reduce the dura8on of a project, you have to reduce the dura8on of ac8vi8es on the cri8cal path. Reducing the dura8on of non- cri8cal tasks only adds more float to these tasks. Schedule Compression is divided into two broad categories, Crashing and Fast tracking. In the simplest terms, crashing is throwing money (resources) at the schedule to reduce dura8on. Fast tracking is overlapping tasks to reduce dura8on. A combina8on of these techniques may also offer a workable solu8on. More specific techniques to compress the project schedule include: 1. Using leads and parallelism with serial ac8vi8es 2. Breaking down a long ac8vity and reassigning the smaller ac8vi8es to other resources 3. Removing or changing constraints 4. Reducing scope 5. Adding more resources 6. Working resources over8me 7. Spli{ng ac8vi8es around constrained ac8vi8es 8. Ge{ng an updated es8mate from the SME 9. U8lizing a newer 8me- saving technology 10. Elimina8ng non- value add ac8vi8es 46

47 During execu8on, if schedule slippage is encountered, there are a few sanc8oned compression techniques to consider. Crashing adds over8me or addi8onal people to the project. Fast- tracking adjusts the schedule so that work that was ini8ally intended to be done in sequence is worked concurrently or in parallel. Any 8me a project manager applies one of these techniques, he or she should also assess the risk of doing so, and convey that informa8on to the stakeholders. 47

48 You may be required to work a crashing problem on the PMP exam. If so, it will be a "least- cost" crashing problem. The goal in these type of problems is to get the maximum amount of compression for minimum addi8onal cost. Steps: Build a network diagram from table 1. Iden8fy the cri8cal ac8vi8es in diagram 2. Calculate a crashing cost per unit (cri8cal ac8vi8es) in table 3. Calculate the benefit in 8me per unit (cri8cal ac8vi8es) in table 3. Iden8fy the lowest crashing cost per ac8vity As each change is made, ensure that the cri8cal path has not changed. 7. Calculate the total cost of crashing and the benefit gained. For the problems on the exam, this would be sufficient. In a work environment, you would want to evaluate each change and its impact on the compe8ng constraints. In the example above: Assuming that the cri8cal path doesn t change.a,f, E and B would be crashed in that order. The crashing cost would increase from $120,000 to $157,000 (net increase of $37,500). The dura8on would be decreased from twenty- three weeks to fiseen weeks. Crashing the non- cri8cal ac8vi8es would increase the cost of the project by $7,500 without reducing the total project 8me. 48

49 Develop Schedule Outputs: Milestone chart, bar chart or network diagram can be very effec8ve in displaying the project schedule. Graphic approach (picture) Easy to read and understand A schedule baseline is a specific version of the project schedule developed from the schedule network analysis. Schedule data for the project schedule includes at least the schedule milestones, schedule ac8vi8es, ac8vity aoributes, and documenta8on of all iden8fied assump8ons and constraints. Project documenta8on updates include: Ac8vity resource requirements Ac8vity aoributes Calendar Risk register 49

50 The PMBOK Guide FiSh Edi8on describes the key benefit of this process as recognizing devia8on from the plan and taking appropriate ac8ons. PMBOK Guide FiSh Edi8on, p. 185 Schedule control is concerned with: Determining the current status of the project schedule Influencing the factors that create schedule changes Determining that the project schedule has changed Managing the actual changes as they occur 50

51 The PMBOK Guide FiSh Edi8on defines the following for the seventh Project Time Management process: Inputs Project management plan Project schedule Work performance data Project calendars Schedule data Organiza8onal process assets Tools & Techniques Performance reviews Project management sosware Resource op8miza8on techniques Modeling techniques Lead and lags Schedule compression Scheduling tool Outputs Work performance informa8on Schedule forecasts Change requests Project management plan updates Project documents updates Organiza8onal process assets updates 51

52 52

53 Performance reviews measure, compare, and analyze schedule performance. Project managers can develop project metrics that compare planned start vs. actual start dates, planned finish vs. actual finish, planned effort vs. actual effort and planned dura8on vs. actual dura8on. Using the planned vs. actual informa8on and analyzing the cri8cal path provides a good way to track performance Variance analysis requires schedule performance measurements, i.e., Schedule Variance (SV) and Planned Value (PV), that are used to assess the magnitude of varia8on to the original schedule baseline. Comparing the planned vs. actual work and analyzing the impact to the cri8cal path (or cri8cal chain) the project manager can analyze the variance to determine if the schedule is within the defined control limits, or if it has reached or passed a threshold. If the schedule has exceeded the tolerance limits the project team will need to iden8fy the root cause of the variance in order to determine the appropriate ac8on. PM SoSware and Scheduling Tools are used on most projects to track and measure progress against the baseline and performance metrics. Scheduling tools can also perform a what- if analysis to iden8fy trends. Resource op8miza8on techniques include, but are not limited to leveling, smoothing, realloca8on, etc. Modeling techniques can include porzolio op8miza8on under resource constraints. The effect of changing out different resources can be seen in cost, composi8on of projects selected and dura8on of a project. Lags and leads should not be used in place of logical dependencies between ac8vi8es, but can augment them to op8mize the project schedule or to model the project in a more effec8ve manner. Frequently when we create the unconstrained schedule we need to compress the schedule to hit a deadline. We may also need to re- plan our schedule when we start collec8ng updates in order to stay on the baseline. In both these cases schedule compression techniques are useful. Scheduling tools can facilitate the planning and analysis of project 8melines. They can automate the various calcula8ons to iden8fy the cri8cal path, slack, network logic, and slippage. 53

54 Maintaining the schedule baseline is important. Re- planning is the way to accomplish this. Work performance measurements are the calculated SV and the Schedule Performance Index (SPI). Organiza8onal process assets that could be updated are: causes of variances, correc8ve ac8on chosen and the ra8onale, and lessons learned. Change requests could be generated by variance analysis, performance measures, or requests to change the schedule baseline or other components of the project plan. Change requests can include preven8ve and correc8ve ac8ons needed to bring and keep the schedule performance within the control limits. Project plan updates may include, but are not limited to, schedule baseline, schedule management plan, or cost baseline. Project document updates include, but are not limited to, a revised network diagram and/or schedule. Schedule Forecasts allow project managers drive the project by looking through the windshield rather than the rear- view mirror. Earned Value calcula8ons that assist with this include Es8mate to Complete (ETC), Es8mate at Comple8on (EAC) and To Complete Performance Indicator (TCPI) and all of their varia8ons to reflect differing assump8ons. 54

55 HONESTY STANDARDS We earnestly seek to understand the truth. When we are asking for status informa8on from team members we need to make sure we are clear about the status of their work. Just because 50% of the 8me has passed does not mean 50% of the work is done. We are truthful in our communica8ons and in our conduct. When we report status we discuss the good work we have done as well as the challenges we face. We don t hide bad news hoping the situa8on will improve. We provide accurate informa8on in a 8mely manner. When we determine that we may have a schedule variance we need to communicate the situa8on in a 8mely manner while there is s8ll 8me to take correc8ve ac8on to get the schedule back on track. We make commitments and promises, implied or explicit, in good faith. When we are building our schedules we do our best to build a realis8c schedule. We use good faith when nego8a8ng for resources and developing es8mates, but we are not overly aggressive and we don t accept an unrealis8c schedule. If we are forced to work to an unrealis8c deadline we tell the truth about the risks involved. We do not engage in or condone behavior that is designed to deceive others, including but not limited to, making misleading or false statements, sta8ng half- truths, providing informa8on out of context or withholding informa8on that, if known, would render our statements as misleading or incomplete. Es8mates and schedules can be complex and sensi8ve aspects of the project. Regardless, we disclose all informa8on and are transparent in how we develop and manage the schedule. 56

56 IIL- CERT Interna8onal Ins8tute for Learning, Inc. 57

PMP Exam Preparation Course Project Time Management

PMP Exam Preparation Course Project Time Management Project Time Management 1 Project Time Management Processes Define Activities Sequence Activities Estimate Activity Resources Estimate Activity duration Develop Schedule Control Schedule In some projects,

More information

The Project Management Cer:ficate Program. Project Scope Management

The Project Management Cer:ficate Program. Project Scope Management PMP cross-cutting skills have been updated in the PMP Exam Content Outline June 2015 (PDF of the Examination Content Outline - June 2015 can be found under the Resources Tab). Learn about why the PMP exam

More information

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com

More information

GPE engineering project management. Project Management in an Engineering Context

GPE engineering project management. Project Management in an Engineering Context GPE engineering project management Project Management in an Engineering Context PM Network diagrams in context SOW CHARTER SCOPE DEFINITION WBS circulation, negotiation, translation WBS WP à activities

More information

Project Time Management

Project Time Management Project Time Management Project Time Management Project Time Management includes the processes required to manage timely completion of the project. Plan schedule management The process of establishing

More information

Time Management PLANNING

Time Management PLANNING Time Management 6.1 Plan Schedule Management: The process of establishing policies, procedures and documentation for planning, developing, managing, executing and controlling the project schedule # Schedule

More information

PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT. PMP Exam Prep

PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT. PMP Exam Prep PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT PMP Exam Prep PROJECT SCHEDULE MANAGEMENT Page 223 Schedule Management Process : Contains 6 of the 49 total processes Plan Schedule Management Define

More information

The Project Planning Process Group

The Project Planning Process Group 3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity

More information

Project ended.. Terminated or canceled.

Project ended.. Terminated or canceled. Project ended.. Terminated or canceled. 1 Project ended doesn t mean with success. A project can end in underperformance Terminated or canceled projects consumes funds and resources without results 2 Delega&on

More information

Guten Tag. (good day)

Guten Tag. (good day) Guten Tag (good day) Project Management Process Groups Project 4. Integration Management Knowledge Areas 13. Stakeholder Initiating Planning Executing 5. Scope 6. Time 7. Cost 8. Quality 9. Human Resources

More information

Project Management CSC 310 Spring 2017 Howard Rosenthal

Project Management CSC 310 Spring 2017 Howard Rosenthal Project Management CSC 310 Spring 2017 Howard Rosenthal 1 No?ce This course is based on and includes material from the text: Effective Project Management - Traditional, Agile, Extreme 7TH Edition Authors:

More information

Time has the least. amount of flexibility; Schedule issues are the main reason for

Time has the least. amount of flexibility; Schedule issues are the main reason for PMBOK 5 Ed. DEI- Time has the least amount of flexibility; Schedule issues are the main reason for conflicts on projects, especially during the second half of projects The process required to manage timely

More information

THE PMP EXAM PREP COURSE

THE PMP EXAM PREP COURSE THE PMP EXAM PREP COURSE Session 2 PMI, PMP and PMBOK are registered marks of the Project Management Institute, Inc. www.falconppm.com Agenda 9:00 10:15 Practice the PMP Questions 10:15 10:30 Break 10:30

More information

PMBOK Guide Fifth Edition Pre Release Version October 10, 2012

PMBOK Guide Fifth Edition Pre Release Version October 10, 2012 5.3.1 Define Scope: Inputs PMBOK Guide Fifth Edition 5.3.1.1 Scope Management Plan Described in Section 5.1.3.1.The scope management plan is a component of the project management plan that establishes

More information

Project Management Professional (PMP) Exam Prep Course 6 - Project Schedule Management

Project Management Professional (PMP) Exam Prep Course 6 - Project Schedule Management Project Management Professional (PMP) Exam Prep Course 6 - Project Slide 1 Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster St. #150 Denver, CO 80237 information@lookingglassdev.com

More information

Information Technology Project Management, Seventh Edition

Information Technology Project Management, Seventh Edition Information Technology Project Management, Note: See the text itself for full citations. Understand the importance of project schedules and good project time management Discuss the process of planning

More information

6 PROJECT TIME MANAGEMENT

6 PROJECT TIME MANAGEMENT CHAPTER 6 PROJECT TIME MANAGEMENT LEARNING OBJECTIVES After reading this chapter, you will be able to: Understand the importance of project schedules and good project time management Define activities

More information

Principles of Information Systems

Principles of Information Systems Principles of Information Systems Session 08 Systems Investigation and Analysis An Overview of Systems Development Today, users of informa0on systems are involved in their development Avoid costly failures

More information

Project Management Framework

Project Management Framework Project Management Framework What s Project? - Why Project? What s Project Management? - Why Project Management? What s Project Management Professionals? - Why Project Management Professionals? Project

More information

Project Time Management

Project Time Management Project Time Management Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules. Describe how project managers use

More information

Project Management. Project Planning CE PROJECT MANAGEMENT L- 5

Project Management. Project Planning CE PROJECT MANAGEMENT L- 5 Project Management Project Planning CE 447 - PROJECT MANAGEMENT 1 L- 5 Project Phases 1. Ini7a7on 2. Planning 3. Execu7on 4. Controlling 5. Closing Planning Phase Communica7on plan Scope management plan

More information

Estimating Project Schedule-Time and Cost

Estimating Project Schedule-Time and Cost Estimating Project Schedule-Time and Cost Chapter 5 5 1 Where We Are Now 5 2 1 Overview Seminar Agenda What is involved in schedule and cost management? In-depth Determining the sequence of activities

More information

Introduction to Project Management

Introduction to Project Management Introduction to Project Management Chapter 7 Managing Project Resources Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George 2008 Prentice Hall 7-1 Project Resources

More information

Scheduling. Adapted from John Musser

Scheduling. Adapted from John Musser Scheduling Adapted from John Musser Today Network Fundamentals Gantt Charts PERT/CPM Techniques WBS Review Types: Process, product, hybrid Formats: Outline or graphical organization chart High-level WBS

More information

Project Time Management

Project Time Management Project Time Management Prof. Dr. Daning Hu Department of Informatics University of Zurich Adapted from Managing Information Technology Projects, Schwalbe Learning Objectives Define activities as the basis

More information

PMP Sample Questions Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope?

PMP Sample Questions  Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope? PMP Sample Questions www.techfaq360.com Click here for 1600+ PMP Questions Question No : 1 Which of the following is an output of Define Scope? A. Accepted deliverables B. Change Requests C. Project document

More information

MBP1133 Project Management Framework Prepared by Dr Khairul Anuar

MBP1133 Project Management Framework Prepared by Dr Khairul Anuar MBP1133 Project Management Framework Prepared by Dr Khairul Anuar L4 Project Time Management www.notes638.wordpress.com Content 1. Scheduling 2. Common Scheduling Techniques 3. PERT 4. Network Fundamentals

More information

PROJECT SCHEDULING & CONTROL

PROJECT SCHEDULING & CONTROL PROJECT SCHEDULING & CONTROL Project Project Management PM Knowledge Areas Time Management 1 Project What is a PROJECT? Definition used by PMI: A temporary endeavor undertaken to create a unique product,

More information

Software Project Management

Software Project Management Software Project Management Dr. M.E. Fayad, Professor Computer Engineering Department College of Engineering, San José State University One Washington Square, San José, CA 95192-0180 E-mail: m.fayad@sjsu.edu

More information

The Project Management Cer;ficate Program. Project Stakeholder Management

The Project Management Cer;ficate Program. Project Stakeholder Management PMP cross-cutting skills have been updated in the PMP Exam Content Outline June 2015 (PDF of the Examination Content Outline - June 2015 can be found under the Resources Tab). Learn about why the PMP exam

More information

PROJECT TIME MANAGEMENT

PROJECT TIME MANAGEMENT PROJECT TIME MANAGEMENT 2020 Powered by POeT Solvers Limited SEQUENCE ACTIVITIES PLANNING MONITORING & CONTROLLING 6.1 Plan Schedule Mgt 6.7 Control Schedule 6.2 Define Activities 6.3 Sequence Activities

More information

Week 5 Project Work Plan

Week 5 Project Work Plan Week 5 Project Work Plan 457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304

More information

Audi%ng and Verifica%on of an ISO Energy Management System. Ian Boylan

Audi%ng and Verifica%on of an ISO Energy Management System. Ian Boylan Audi%ng and Verifica%on of an ISO 50001 Energy Management System Ian Boylan +353 86 2353888 ian.boylan@targetenergy.ie Audi%ng & Verifica%on Audi%ng for effec%veness Verifica%on of savings & verifica%on

More information

PMI Lexicon of Project Management Terms

PMI Lexicon of Project Management Terms PMI L E XI CON OFP ROJ E CTMANAGE ME NTT E RMS V E RSI ON3. 2 Se pt e mbe r201 7 Project Management Institute PMI Lexicon of Project Management Terms Version 3.2 Published by: Project Management Institute,

More information

International Association of Certified Practicing Engineers

International Association of Certified Practicing Engineers www.iacpe.com Knowledge, Certification, Networking Page: 1 71 IACPE No 19, Jalan Bilal Mahmood 80100 Johor Bahru Malaysia The International is providing the introduction to the Training Module for your

More information

Agile Project Planning

Agile Project Planning Agile Project Planning Introduction Delivery of Soware projects, to plan and to budget, is always a challenge! Fortunately, even in an Agile environment, keeping the business and stakeholders up to date

More information

Scheduling 2 Day Structure

Scheduling 2 Day Structure Day 1 Session 1: Design and Structure your Schedule 1. The need for planning and scheduling a. Purpose = communication not control b. Understand audience 2. Simple -v- complex projects 3. Planning -v-

More information

GPE engineering project management. Project Management in an Engineering Context

GPE engineering project management. Project Management in an Engineering Context GPE engineering project management Project Management in an Engineering Context Critical Chain Project Management (CCPM) CCPM and TOC Theory of Constraints views systems as chains The weakest link is the

More information

Planning and Scheduling Training Program Course Brochure and Competency Matrix

Planning and Scheduling Training Program Course Brochure and Competency Matrix Planning and Scheduling Training Program Course Brochure and Competency Matrix INDEX: 1. Company Introduction 2. Training Programme Description 3. Training Delivery Options 4. Course Syllabus 5. Programme

More information

MGT/437. Project Management. Session #2 University of Phoenix 02/12/2004 Brian Smithson. 02/12/2004 MGT/437 #2 -- Brian Smithson 1

MGT/437. Project Management. Session #2 University of Phoenix 02/12/2004 Brian Smithson. 02/12/2004 MGT/437 #2 -- Brian Smithson 1 MGT/437 Project Management Session #2 University of Phoenix 02/12/2004 Brian Smithson 02/12/2004 MGT/437 #2 -- Brian Smithson 1 Agenda Review/Questions Session content PMI project framework Project Knowledge

More information

MnDOT Project Management Office Presents: Impact Schedules. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Impact Schedules. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Impact Schedules Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

Seminar 6: Project Management Part 1 Semester 1, 2005

Seminar 6: Project Management Part 1 Semester 1, 2005 IMS 1501 Studio 1: Information Systems Foundations 1 Seminar 6: Project Management Part 1 Semester 1, 2005 Seminar 6.1 - Sem 1, 2005 IMS1501: Unit framework Ethics Documentation Efficiency Tools System

More information

S O Seminar Objective

S O Seminar Objective Introduction to Project Management Welcome! Presenter: Bob Hull CalACT Conference September 202 S O Seminar Objective To provide an overview of project management processes and provide some skills, tools

More information

PMI Scheduling Professional (PMI-SP)

PMI Scheduling Professional (PMI-SP) PMI Scheduling Professional (PMI-SP) E X A M I N AT I O N CO N T E N T O U T L I N E Project Management Institute PMI Scheduling Professional (PMI-SP) Exam Content Outline Published by: Project Management

More information

Seminar 6: Project Management Part 1 Semester 1, 2005

Seminar 6: Project Management Part 1 Semester 1, 2005 IMS1501: Unit framework IMS 1501 Studio 1: Information Systems Foundations 1 Ethics Documentation Developing Information Systems Efficiency Tools Seminar 6: Project Management Part 1 Semester 1, 2005 System

More information

MBH1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar. Lecture 6b Project Time Management - II

MBH1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar. Lecture 6b Project Time Management - II MBH1123 Project Scope, Time and Cost Management Prepared by Dr Khairul Anuar Lecture 6b Project Time Management - II MBP1123 Scope, Time & Cost Management Prepared by Dr. Zohreh Content 1. Introduction

More information

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course PMI REP No 3001 Course Number PP6 Administration Evacuation Timings and meals Facilities Mobile

More information

The Planning Process Group

The Planning Process Group Assalam-o-alaikum Project Management Process Groups Project Integration Management Knowledge Areas Initiating Planning Executing Scope Time Cost Quality Human Resources Communications Monitoring & Controlling

More information

Process Modeling Best Practices. Raphael Derbier Nicolas Marzin

Process Modeling Best Practices. Raphael Derbier Nicolas Marzin Process Modeling Best Practices Raphael Derbier Nicolas Marzin SAFE HARBOR DISCLOSURE During the course of this presenta1on TIBCO or its representa1ves may make forward-looking statements regarding future

More information

Developing a Project Plan

Developing a Project Plan Chapter 6 Developing a Project Plan I had six honest serving men who taught men all I know : their names were what and how and why, and when and where and who. Rudyard Kipling Project Management 105 Figure

More information

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155 GLOSSARY AND INDEX Glossary Index iv 1996 Project Management Institute, 130 South State Road, Upper Darby, PA 19082 USA 155 156 NOTES GLOSSARY 1. Inclusions and Exclusions This glossary includes terms

More information

The Hybrid PMO. How to increase you por5olio s transparency to meet the needs of an Agile enterprise

The Hybrid PMO. How to increase you por5olio s transparency to meet the needs of an Agile enterprise The Hybrid PMO How to increase you por5olio s transparency to meet the needs of an Agile enterprise Presenter: Alan Shefveland, Director - Product Strategy, Changepoint A recent Changepoint survey said

More information

4. Which of the following statements are true regarding The Project Scope Statement based on the PMBOK 5h Edition?

4. Which of the following statements are true regarding The Project Scope Statement based on the PMBOK 5h Edition? 1. Which of the following is true regarding the project charter? A. The project charter is a document that formally authorize a project or phase.. B. The project charter represent a high level planning

More information

This slide shows the,mescales of the Call that is now open. Please note: Deadlines are immutable and set electronically. Your bid will be rejected

This slide shows the,mescales of the Call that is now open. Please note: Deadlines are immutable and set electronically. Your bid will be rejected This presenta,on sets out the essen,al elements of informa,on and prac,cal guidance for poten,al candidates interested in responding to a Call for Proposals within the Clean Sky 2 programme. Several Call

More information

Managing Project Time

Managing Project Time Chapter 6 Managing Project Time THE CHALLENGES OF PROJECT TIME MANAGEMENT IN THE PUBLIC SECTOR Private-sector projects often have time constraints. A company may want to introduce a new product as quickly

More information

Knowledge Areas According to the PMBOK edition 5. Chapter 4 - Integration

Knowledge Areas According to the PMBOK edition 5. Chapter 4 - Integration Knowledge Areas According to the PMBOK edition 5 Chapter 4 - Integration 4.1 - Develop Project Charter Process Project statement of work Expert Judgment Project charter Business case Facilitation techniques

More information

Project Controls Expo - 31 st Oct 2012

Project Controls Expo - 31 st Oct 2012 Project Controls Expo - 31 st Oct 2012 Twickenham Stadium, London Producing a Quality Cost Es=mate; Hints, Tips and Best Prac=ce Carl Dalton Director Polaris Consulting Ltd Speaker Profile - Carl Dalton

More information

Plan Your Work, Work Your Plan. Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology

Plan Your Work, Work Your Plan. Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology Plan Your Work, Work Your Plan Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology Agenda Understand what a project is Understand the basics of

More information

Forecast Scheduling Microsoft Project Online 2018

Forecast Scheduling Microsoft Project Online 2018 Forecast Scheduling Microsoft Project Online 2018 Best Practices for Real-World Projects Eric Uyttewaal, PMP President ProjectPro Corporation Published by ProjectPro Corporation Preface Publishing Notice

More information

Team Member Application

Team Member Application MnDOT Project Management Office Presents: Team Member Application Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

Network Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS)

Network Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS) /11/16 Network Diagram 11//16 1 WORK BREAKDOWN STRUCTURE (WBS) A work breakdown structure is a key project deliverable that organizes the team's work into manageable sections. The Project Management Body

More information

Project Management Concepts, Tools & Techniques

Project Management Concepts, Tools & Techniques Project Management Concepts, Tools & Techniques Course ISI-1438 5 Days Instructor-led, Hands on Introduction This highly interactive 5 day, instructor-led workshop is designed to give participants a solid

More information

The Project Management Cer6ficate Program. Project Quality Management

The Project Management Cer6ficate Program. Project Quality Management PMP cross-cutting skills have been updated in the PMP Exam Content Outline June 2015 (PDF of the Examination Content Outline - June 2015 can be found under the Resources Tab). Learn about why the PMP exam

More information

Ninth Edition. Rita Mulcahy, PMP, etai. Rita Mulcahy s. Inside this book:

Ninth Edition. Rita Mulcahy, PMP, etai. Rita Mulcahy s. Inside this book: Rita s Course in a Book for Passing the Project Management Professional (PMP) Exam Rita Mulcahy s Ninth Edition Inside this book: Tricks of the Trade What you really need to know to pass the exam Straightforward

More information

Project Management PSGLE 122. Time and Resources

Project Management PSGLE 122. Time and Resources Project Management PSGLE 122 Time and Resources Copyright Materials This presentation is protected by US and International Copyright laws. Reproduction, distribution, display and use of the presentation

More information

Scheduling Resources and Costs

Scheduling Resources and Costs Student Version CHAPTER EIGHT Scheduling Resources and Costs McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Gannt Chart Developed by Henry Gannt in 1916 is used

More information

PMP Exam Prep Study Group Input-Output-Tools #3a

PMP Exam Prep Study Group Input-Output-Tools #3a PMP Exam Prep Study Group Input-Output-Tools #3a Presented by Project Masters Inc. *Throughout this presentation, we reference and recognize the following trademarks, service marks, and copyrights of the

More information

Views and Layouts for Program Management

Views and Layouts for Program Management MnDOT Project Management Office Presents: Views and Layouts for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted

More information

Project Management Professional (PMP) Certification Exam Preparation Program Course Outline with Outcomes

Project Management Professional (PMP) Certification Exam Preparation Program Course Outline with Outcomes Module i: Overview of the PMP Certification Gain an understanding of the PMP preparation process. 1. The qualifications required for the PMP 2. How to best study for the PMP 3. General truisms of project

More information

Project Planning and Estimating DJ

Project Planning and Estimating DJ Project Planning and Estimating DJ201 0807 Copyright ESI International August 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any

More information

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL SECTION 01310 COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. COST LOADED CONSTRUCTION SCHEDULE (Construction Schedule): The WORK under this Contract shall be planned, scheduled, executed,

More information

P6 Instructors Sample Presentation

P6 Instructors Sample Presentation Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 to 8.4 Professional and Optional Client 3 day training course PMI REP No 3001 Course Number PP6 Page 2 Page 4 Administration Evacuation

More information

Errata 1 st Printing. Errata 2 nd Printing

Errata 1 st Printing. Errata 2 nd Printing Errata 1 st Printing NOTE: The following errata only pertain to the first printing of the PMBOK Guide Fifth Edition. In order to verify the print run of your book (or PDF), refer to the bottom of the copyright

More information

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish

12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish International Campus Kish Sharif University of Technology Session#11 Instructor Omid Fatahi Valilai, Ph.D. Industrial Engineering Department, Sharif University of Technology Email: Fvalilai@Sharif.edu,

More information

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by.

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones

More information

Appendix. Process Inputs and Outputs

Appendix. Process Inputs and Outputs 3601cA.fm Page 493 Wednesday, October 26, 2005 12:47 AM Appendix A Process and Throughout this book, PMP: Management Professional Study Guide, 3rd Edition, I ve discussed the inputs and outputs to the

More information

Geog 469 GIS Workshop. Project Management

Geog 469 GIS Workshop. Project Management Geog 469 GIS Workshop Project Management Outline Basic principles of project management 6.1 What is a project versus an application? 6.2 What is a scoping statement for your project? 6.3 Why are critical

More information

Antti Salonen KPP KPP227 Antti Salonen

Antti Salonen KPP KPP227 Antti Salonen Antti Salonen KPP227-2015 1 Scheduling may be defined as: the assignment and 1ming of the use of the resources such as personnel, equipment, and facili1es for produc1on ac1vi1es or jobs. Scheduling is

More information

PMP Q&As. Project Management Professional. Pass PMI PMP Exam with 100% Guarantee. Free Download Real Questions & Answers PDF and VCE file from:

PMP Q&As. Project Management Professional. Pass PMI PMP Exam with 100% Guarantee. Free Download Real Questions & Answers PDF and VCE file from: PMP Q&As Project Management Professional Pass PMI PMP Exam with 100% Guarantee Free Download Real Questions & Answers PDF and VCE file from: 100% Passing Guarantee 100% Money Back Assurance Following Questions

More information

Global Project Management, LLC

Global Project Management, LLC Global Project Management, LLC 2250 Gause Boulevard, Suite 310 Slidell, Louisiana 70461 Tel: 985-781-9190 A Projectis a temporary endeavor undertaken to create a unique product, service, or result. Initiation

More information

Week 5 Project Work Plan

Week 5 Project Work Plan Week 5 Project Work Plan 457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304

More information

Project Management CSC 310 Spring 2018 Howard Rosenthal

Project Management CSC 310 Spring 2018 Howard Rosenthal Project Management CSC 310 Spring 2018 Howard Rosenthal 1 Notice This course is based on and includes material from the text: A User s Manual To the PMBOK Guide Authors: Cynthia Stackpole Snyder Publisher:

More information

Scheduling Concepts and MS. Project AZURITE PROJECT TRAINING AND CONSULTING PVT LTD (OPC) 2014

Scheduling Concepts and MS. Project AZURITE PROJECT TRAINING AND CONSULTING PVT LTD (OPC) 2014 Scheduling Concepts and MS Project 1 About the Faculty- Venkat Annapragada Chem Engg from IIT KGP in 1993 Graduation Process Engineer Cement Industry from 1993 to 1997 IT Industry from 1997 to 2010 Corporate

More information

Total Questions: 370 MODULE QUIZ ANSWER KEY. Fundamentals 1 & 2

Total Questions: 370 MODULE QUIZ ANSWER KEY. Fundamentals 1 & 2 Fundamentals 1 & 2 1. Answer: B Process Group. Each project management knowledge area is subdivided into specific process group, each of which is characterized by their inputs, tools and techniques, and

More information

Week 5 Project Work Plan

Week 5 Project Work Plan Week 5 Project Work Plan 457.307 Construction Planning and Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304 호 Project

More information

Compiled by Rajan Humagai

Compiled by Rajan Humagai Compiled by Rajan Humagai www.pavementengineering.com.au Project Processes Inputs, Tools & Techniques and Outputs. (Based on PMBOK 5 th Edition) 1. Project Integration 1. Develop 1. Project Statement Of

More information

A Guide to the Project Management Body of Knowledge (PMBOK Guide) Sixth Edition Errata 3 rd Printing

A Guide to the Project Management Body of Knowledge (PMBOK Guide) Sixth Edition Errata 3 rd Printing A Guide to the Body of Knowledge (PMBOK Guide) Sixth Edition Errata 3 rd Printing NOTE: The following errata only pertain to the first and second printing of the PMBOK Guide Sixth Edition. In order to

More information

Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013)

Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013) Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013) Integration Management: processes & activities needed to properly coordinate all aspects of the project to meet stakeholder

More information

Hawaii Hazards Awareness & Resilience Program. Contents. Module 5: Risk Assessment 3/1/17. Vulnerability and Capacity Assessment (VCA)

Hawaii Hazards Awareness & Resilience Program. Contents. Module 5: Risk Assessment 3/1/17. Vulnerability and Capacity Assessment (VCA) Hawaii Awareness & Resilience Program Produced by Hawaii State Civil Defense HAWAII HAZARDS AWARENESS & RESILIENCE PROGRAM: GOAL: To enhance community resilience to mul?ple hazards through a facilitated

More information

Lessons Learned Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International

Lessons Learned Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International Charlie Jackson, PSP, Primavera Certified Trainer Hill International Construction CPM Conference

More information

Project Management Glossary of Terms

Project Management Glossary of Terms Project Management Glossary of Terms activity An element of project work that has an expected duration, and usually consumes cost and resources. Activities generally cover one or more tasks from a work

More information

Successful Changes with Integrated Change and Project Management

Successful Changes with Integrated Change and Project Management Successful Changes with Integrated Change and Project Management Markus F. Wanner, Managing Partner, Representative of Management, Tiba Management Consulting, Munich/ Germany 1 A way to success?? 2 Agenda

More information

Principles of Planning for Building and. by Eastwood Harris Pty Ltd. Introduction Emergency Evacuation. Course Outline.

Principles of Planning for Building and. by Eastwood Harris Pty Ltd. Introduction Emergency Evacuation. Course Outline. Principles of Planning for Building and Construction by Eastwood Harris Pty Ltd Introduction Emergency Evacuation Timings Meals Mobile Phones Conduct of course Introductions: Your name Position Experience

More information

LookingGlass - Project Management Professional Exam Prep (PMP01)

LookingGlass - Project Management Professional Exam Prep (PMP01) LookingGlass - Project Management Professional Exam Prep (PMP01) Course Overview This course has been designed to prepare participants to take the Project Management Institute's Project Management Professional

More information

Kristin Fitzgerald Director, Global Project and Alliance Management, Merck & Co, Inc.

Kristin Fitzgerald Director, Global Project and Alliance Management, Merck & Co, Inc. Kristin Fitzgerald Director, Global Project and Alliance Management, Merck & Co, Inc. Kris%n s Background BS Behavioral Neuroscience - Lehigh University MBA Monmouth University Merck Career PMP Certification

More information

MnDOT Project Management Office Presents: Risk Management. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Risk Management. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Risk Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions

More information