1 November 2005 Page 3F-1 F stage 3 document review checklist and meetg agenda Contents F.1 Safety management systems stage 3: review meetg 3F-2 F.2 document review checklist 3F-4

2 Page 3F-2 November 2005 F.1 Safety management systems stage 3: review meetg Background For background formation on the document review meetg and a suggested list of meetg attendees refer to these guideles. Objectives Ultimate A is developed that is useful to the RCA, is easy to use by all staff and satisfies the requirement detailed the guidele and is expected to produce a consistently safe road environment for all users. Meetg Review the document usg the document review checklist (part 3 F.2) to identify that: suitable existg /current systems are cluded existg /current systems have been modified if required new systems are cluded if required additional systems are identified to be cluded users are able to operate accordance with of the an appropriate audit regime exists Agree future actions required of the parties

3 November 2005 Page 3F-3 Draft stage 3 review meetg agenda am Welcome and housekeepg Chairperson: representative Scribe: consultant Open review and confirm objectives 10:45 am Endorsement and troduction section Endorsements, purpose and users Shape, size, structure and detail am Road safety strategy (RSS) section Is the RSS contaed with the document or not Key reference document listed, eg, RCA strategic plan, asset management plan, regional land transport strategy am Management section Who will own and operate, ensure ongog development and compliance with Management structure, organisational chart am Standards, guideles, policies and procedures Split -network hierarchy/activity/asset Structure list or template Is what s required cluded pm Lunch 12.30pm Roles and responsibilities Is what is required cluded Any gaps 12:45pm Management systems Who will own, operate, ensure ongog development and compliance with the Management structure and organisational chart 1.15pm Audit systems Level of monitorg evaluation and review detail Key performance dicators (KPIs) role/volvement 1.45pm Appendices Is what required OFI s list Any gaps 2.15pm Where to from here Establish who does what/how/when 3.00pm Fish

4 Page 3F-4 November 2005 F.2 document review checklist For Completed by: Date:

5 November 2005 Page 3F-5 rankg but Endorsement of the ** Appropriate endorsement Introduction/executive summary/philosophy Philosophy Lkage to other documents Road safety strategy ** Vision * Key stakeholders and partners the community Problem analysis Local crash reportg database ** Key safety issues Scope * Community education itiatives * Enforcement itiatives

6 Page 3F-6 November 2005 rankg but Delivery of the strategy ** Crash reduction studies Technical auditg cludg: ** project safety audit ** existg road safety audit. ** Temporary traffic management cludg approval and auditg ** Deficiency analysis and database ** Road safety hazard register of environmental items ** Road hierarchy ** Traffic countg ** Speed management Matenance of traffic control devices cludg: ** signs ** deleation ** roadmarkg traffic signals any other devices.

7 November 2005 Page 3F-7 rankg but Delivery of the strategy, contued Traffic management facilities, ie, LATM ** use planng and regulatory controls cludg district plan and bylaws * Street lightg ** scapg and vegetation control Overdimension and overweight routes * Vulnerable road users * Cycle facilities * Pedestrian facilities * Footpaths Draage systems cludg: * bridges and culverts catchpits and sumps kerb and channel * deep dras and irrigation channels * swale dras.

8 Page 3F-8 November 2005 rankg but Delivery of the strategy, contued * Vehicle crossgs and accessways Stock control, crossgs and underpasses Effluent disposal facilities Weighbridges Rest areas Safety barrier Retag structures Parkg * Emergency response Road closures Pavement matenance cludg: * scrim analysis potholes * physical defects RAMM data and analysis * gradg unsealed roads. * Clear zones

9 November 2005 Page 3F-9 rankg but Delivery of the strategy, contued Railway crossgs Road opengs by utility and other external service authorities. Road opengs by other departments with the RCA. Roads under the control of other RCA s cludg: ports airports Department of Conservation. Standards, guideles and policies ** Standards ** Guideles * Policies ** Compliance with standards, guideles and policies

10 Page 3F-10 November 2005 rankg but Expertise, qualifications and roles * Staff trag and competence ** External service authorities and other commercial road occupiers ** Appotment of consultants and contractors Management of the ** Management/ownership of road safety ** Monitorg of staff compliance with the ** Ongog system development Operational/management structure Audit ** Review, monitorg and evaluation of the RSS ** audit

11 November 2005 Page 3F-11 rankg but General comments

12

13

SMS stage 3 document review checklist and meeting agenda

SMS stage 3 document review checklist and meeting agenda November 2005 Page 3-1 Part 3 Toolbox A SMS stage 1 scoping workshop and draft agenda B Memorandum of Understanding C Delivery plan spreadsheets D Road safety strategy checklist E SMS component workbook

More information

Appendix A Review Checklist for Risk Management Plans

Appendix A Review Checklist for Risk Management Plans Appendix A Review Checklist for Risk Management Plans This checklist was designed to be used conjunction with guidance provided the Risk Management Plan Guide. The Risk Management Plan (RMP) Checklist

More information

Implementing the Pyramid Model State-Wide: State Benchmarks of Quality

Implementing the Pyramid Model State-Wide: State Benchmarks of Quality Implementg the Pyramid Model State-Wide: State Barbara J. Smith, Glen Dunlap, Karen Blase April 3, 3 Purpose The State is used by a collaborative State Leadership Team (SLT) to assess progress and plan

More information

One Network Road Classification (ONRC) Performance Measures

One Network Road Classification (ONRC) Performance Measures 2016 One Network Road Classification (ONRC) Performance Measures 1 Contents Introduction 4 Safety Customer Outcome Performance Measures 5 Customer Outcome 1: the number of fatal and serious injuries on

More information

Standard Appraisal Framework for Hybrid Maintenance Contracts

Standard Appraisal Framework for Hybrid Maintenance Contracts NZ Transport Agency Page 1 of 5 Standard Appraisal Framework for Hybrid Maintenance Contracts This document is considered a guideline for the establishment of a performance system for the NZ Transport

More information

Reconstruction Project Update

Reconstruction Project Update I-65/I-70 North Split Interchange Reconstruction Project Update September 18, 2017 Agenda Welcome/introductions Project overview Scope and limits Need Environmental Assessment Maintenance of traffic Financial

More information

ISO Road Safety Management Systems A Starter s Guide for Road Agencies and irap

ISO Road Safety Management Systems A Starter s Guide for Road Agencies and irap ISO 39001 Road Safety Management Systems A Starter s Guide for Road Agencies and irap Martin Small martin@martinsmallconsulting.com irap Innovation Workshop Melbourne, September, 2014 The UN Decade of

More information

Establish quality requirements, manage, and monitor the installation of subdivision infrastructure

Establish quality requirements, manage, and monitor the installation of subdivision infrastructure Page 1 of 5 Establish quality requirements, manage, and monitor the installation of subdivision infrastructure Level 6 Credits 18 Purpose This unit standard is for people who are working, or who intend

More information

Activity: Roads and Footpaths. How this Activity Contributes to Related Community. Outcome

Activity: Roads and Footpaths. How this Activity Contributes to Related Community. Outcome Activity: Roads and Footpaths How this Activity Contributes to Related Community Outcomes This Activity contributes to the Community Outcomes of Environment, Economy, People, Mobility and Living by: Outcome

More information

Coordinating Minnesota s Transportation Assets and Climate Change and Extreme Weather Vulnerability

Coordinating Minnesota s Transportation Assets and Climate Change and Extreme Weather Vulnerability Coordinating Minnesota s Transportation Assets and Climate Change and Extreme Weather Vulnerability Duane R. Hill, PE District Engineer, District One Minnesota Department of Transportation What is a Transportation

More information

Project Brief. ONRC Gap Analysis. (Updated March 2016) Page 1 of 15

Project Brief. ONRC Gap Analysis. (Updated March 2016) Page 1 of 15 Project Brief ONRC Gap Analysis (Updated March 2016) Page 1 of 15 Document control File name File location Document date Gap Analysis Project Plan https://teams.at.govt.nz/sites/ams/onrc Draft 18 Sept

More information

Timaru District Council. Land Transport. Lifecycle Management Plan

Timaru District Council. Land Transport. Lifecycle Management Plan Timaru District Council Land Transport Lifecycle Management Plan Quality Record Sheet Timaru District Council Land Transport Lifecycle Management Plan Issue Information Issue Purpose Final Draft Issue

More information

Decision 15/CP.10. FCCC/CP/2004/10/Add.2 Page 41. The Conference of the Parties, Recalling decisions 11/CP.7, 19/CP.7, 21/CP.7, 22/CP.7 and 13/CP.

Decision 15/CP.10. FCCC/CP/2004/10/Add.2 Page 41. The Conference of the Parties, Recalling decisions 11/CP.7, 19/CP.7, 21/CP.7, 22/CP.7 and 13/CP. Page 41 Decision 15/CP.10 Good practice guidance for land use, land-use and forestry activities under Article 3, paragraphs 3 and 4, of the Kyoto Protocol The Conference of the Parties, Recallg decisions

More information

ASSET MAINTENANCE, RENEWAL AND CAPITAL EXPENDITURE POLICY

ASSET MAINTENANCE, RENEWAL AND CAPITAL EXPENDITURE POLICY ASSET MAINTENANCE, RENEWAL AND CAPITAL EXPENDITURE POLICY OBJECTIVE To ensure expenditure is classified appropriately in accordance with generally accepted accounting practice. To provide an awareness

More information

Performance audit report. New Zealand Transport Agency: Information and planning for maintaining and renewing the state highway network

Performance audit report. New Zealand Transport Agency: Information and planning for maintaining and renewing the state highway network Performance audit report New Zealand Transport Agency: Information and planning for maintaining and renewing the state highway network Office of the Auditor-General PO Box 3928, Wellington 6140 Telephone:

More information

Condition #1b to Environmental Assessment Certificate #E15-01 requires that:

Condition #1b to Environmental Assessment Certificate #E15-01 requires that: LNG Canada Development Inc. Shell Centre 32 nd Floor 400 4 th Avenue SW PO Box 100, Station M Calgary AB T2P 2H5 Canada Mr Nathan Braun A / Executive Project Director, Oil & Gas Sector Environmental Assessment

More information

Welcome. Public Meeting. August 2, :00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m.

Welcome. Public Meeting. August 2, :00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m. Welcome Public Meeting August 2, 2017 5:00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m. www.glenwoodsouthbridge.net Welcome to the South Bridge Environmental Assessment Public Meeting Why Are We Here Tonight?

More information

Community Advisory Panel Meeting #

Community Advisory Panel Meeting # Community Advisory Panel Meeting # 4 11.07.18.. Agenda Welcome and Introductions Outreach Materials Update Work Plan Update Community Conversations Alternative Review Charleston/Meadow Exhibits and 3D

More information

Michigan Bridge Conference

Michigan Bridge Conference Transportation Asset Management Council Update and Bridge Asset Management Guide Steve Warren, Kent County Road Commission Roger Safford, Michigan Department of Transportation Michigan Bridge Conference

More information

NZQA registered unit standard version 2 Page 1 of 7. Title Pilot an overweight load and an overdimension load as a Class 1 certified pilot

NZQA registered unit standard version 2 Page 1 of 7. Title Pilot an overweight load and an overdimension load as a Class 1 certified pilot Page 1 of 7 Title Pilot an overweight load and an overdimension load as a Class 1 certified pilot Level 5 Credits 10 Purpose This unit standard is for people acting as a Class 1 certified pilot for the

More information

Waikato District Council Waikato Roads Alliance Agreement Request for Proposal (RFP) V3 (14/314)

Waikato District Council Waikato Roads Alliance Agreement Request for Proposal (RFP) V3 (14/314) Waikato District Council Waikato Roads Alliance Agreement Request for Proposal (RFP) V3 (14/314) Prepared by: Frank Aldridge The Integral Group Limited - Director 19 March 2015 Commercial in Confidence

More information

Food Safety Begins on the Farm: A Grower Self Assessment of Food Safety Risks. Pesticide Use PESTICIDE USE

Food Safety Begins on the Farm: A Grower Self Assessment of Food Safety Risks. Pesticide Use PESTICIDE USE Food Safety Begs on the Farm: A Grower Self Assessment Food Safety Rks Pesticide Use PESTICIDE USE PESTICIDE USE Pesticide Use on Produce Farms READ FOLLOW the LABEL. The most important factor pesticide

More information

Masterton District Council ROADING - ASSET MANAGEMENT PLAN

Masterton District Council ROADING - ASSET MANAGEMENT PLAN Masterton District Council 2018-2048 ROADING - ASSET MANAGEMENT PLAN All rights reserved. No part of this publication may be reproduced, adapted, published or transmitted in any form or otherwise dealt

More information

East Ayrshire Council

East Ayrshire Council East Ayrshire Council Construction Consent Checklist (CC9) Developer. Scheme Submitted Drawings East Ayrshire Council 1 CC1 Number(s) Completed correctly?........ Signed by Applicant, not agent?... CC2

More information

Livability 2050 Regional Transportation Plan Update. Transportation Policy Board (TPB) August 23, 2018

Livability 2050 Regional Transportation Plan Update. Transportation Policy Board (TPB) August 23, 2018 Livability 2050 Regional Transportation Plan Update Transportation Policy Board (TPB) August 23, 2018 1 Oct. 2017 Plan Kick-Off Sept. 2019 Plan Adoption Timeline Livability 2050 Regional Transportation

More information

Auckland Transport Code of Practice 2013

Auckland Transport Code of Practice 2013 26 Corridor Access Management 26.1 Background Auckland Transport is the Road Controlling Authority and Corridor Manager for all public roads within the Auckland Region (except motorways and state highways

More information

Mobility and System Reliability Goal

Mobility and System Reliability Goal Mobility and System Reliability Goal Provide surface transportation infrastructure and services that will advance the efficient and reliable movement of people and goods throughout the state. Background:

More information

PBC-01 BAY ROADS. Maintenance Specification

PBC-01 BAY ROADS. Maintenance Specification PBC-01 BAY ROADS 1 Contents 1. General Requirements MS 11 1.1 Contract Description MS 11 1.2 Limit of Works MS 55 1.3 Handover and Handback MS 88 1.4 Ownership MS 99 1.5 Cost Recovery MS 109 1.6 Preventive

More information

Peterborough County Road Safety Audit Guideline Pilot

Peterborough County Road Safety Audit Guideline Pilot Peterborough County Pilot Table of Contents 1.0 Purpose... 3 2.0 Road Safety Audit Objectives... 3 3.0 Legal Issues... 3 4.0 Road Safety Audit Procedures... 4 4.1 Project Selection Criteria... 5 4.2 Scope...

More information

NZQA registered unit standard 1768 version 5 Page 1 of 6. Title Pilot an overweight load and an overdimension load as a Class 2 certified pilot

NZQA registered unit standard 1768 version 5 Page 1 of 6. Title Pilot an overweight load and an overdimension load as a Class 2 certified pilot Page 1 of 6 Title Pilot an overweight load and an overdimension load as a Class 2 certified pilot Level 4 Credits 10 Purpose This unit standard is for people acting as a Class 2 certified pilot for the

More information

R O A D C O R R I D O R A C T I V I T Y M A N A G E M E N T P L A N V E R S I O N 5.0

R O A D C O R R I D O R A C T I V I T Y M A N A G E M E N T P L A N V E R S I O N 5.0 R O A D C O R R I D O R A C T I V I T Y M A N A G E M E N T P L A N 2015-2025 V E R S I O N 5.0 Road Corridor 2015-2025 Activity Management Plan Prepared by Waipa District Council 101 Bank Street Te Awamutu

More information

Volume 5. District Council Supplement

Volume 5. District Council Supplement HAMILTON CITY DEVELOPMENT MANUAL Volume 5 District Council Supplement Volume 5 District Council Supplement Table of Contents Part 1 : General Part 2 : Earthworks and Land Stability (no additions) Part

More information

Agency Mayor's Office of Legal Counsel Agency MOLC Agency AH0

Agency Mayor's Office of Legal Counsel Agency MOLC Agency AH0 2/12/2016 OCA: P... - FY2016 Agency Agency MOLC Agency AH0 Acronym Code To edit agency and POC formation press your agency name (underled and blue above). Agency Tatiana (EOM) Torres Agency Tatiana (EOM)

More information

INTERIM ADVICE NOTE 169/12 Revision 1. Temporary Cover Plates over Bridge Expansion Joints

INTERIM ADVICE NOTE 169/12 Revision 1. Temporary Cover Plates over Bridge Expansion Joints INTERIM ADVICE NOTE 169/12 Temporary Cover Plates over Bridge Expansion Joints Summary This IAN highlights the issues to be considered when using temporary cover plates. IAN 169/12 Page 1 of 6 July 2013

More information

APPENDIX C. ROAD DESIGN AND CONSTRUCTION

APPENDIX C. ROAD DESIGN AND CONSTRUCTION APPENDIX C. ROAD DESIGN AND CONSTRUCTION CONTENTS Drwg R-2-704 Typical Sections of Services 3 Drwg R-9-705 Standard Turning Areas for Residential Streets 4 Drwg R-9-706 Standard Turning Areas for Industrial

More information

Information sheet: STRATEGIC CASE: DEFINING PROBLEMS AND BENEFITS WELL

Information sheet: STRATEGIC CASE: DEFINING PROBLEMS AND BENEFITS WELL NZ TRANSPORT AGENCY Business Case Approach information sheet Strategic case: defining problems and benefits well June 2017 Information sheet: STRATEGIC CASE: DEFINING PROBLEMS AND BENEFITS WELL This information

More information

Workplace Transport Guidance

Workplace Transport Guidance : Workplace Transport Guidance TABLE OF CONTENTS 1. Background... 3 2. Aim /Purpose... 3 3. Content... Error! Bookmark not defined. 3.1 Safe Site......4 3.1.1 Segregation 4 3.1.2 Traffic routes..4 3.1.3

More information

Traffic standards and guidelines 2001/2002 survey. RSS 19 Traffic signs. March 2003 ISSN ISBN

Traffic standards and guidelines 2001/2002 survey. RSS 19 Traffic signs. March 2003 ISSN ISBN Traffic standards and guidelines 2001/2002 survey RSS 19 Traffic signs March 2003 ISSN 1174 7161 ISBN 0 478 241445 Survey of traffic standards and guidelines The Land Transport Safety Authority (LTSA)

More information

Strategic Decision Making Tool for Renewals

Strategic Decision Making Tool for Renewals Case Study Strategic Decision Making Tool for Renewals Initiative number 2014_07 August 2014 Version No Date Item Affected Description of Change 1 01/08/2014 1 st Draft of Report Completed 2 20/10/2014

More information

Response to a Bridge Strike. at a Bridge carrying the Railway. over a Road

Response to a Bridge Strike. at a Bridge carrying the Railway. over a Road Response to a Bridge Strike at a Bridge carrying the Railway over a Road A Protocol for Highway and Road Managers, Emergency Services and Bridge Owners NR/GPG/CIV/008 3 rd March 2009 Note This protocol

More information

TRAFFIC ENGINEERING DIVISION

TRAFFIC ENGINEERING DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION TRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Administrative and Engineering SPECIFIC SUBJECT: Sealing and Signing of Traffic

More information

Oklahoma Long Range Transportation Plan

Oklahoma Long Range Transportation Plan Oklahoma 2015-2040 Long Range Transportation Plan Oklahoma Metropolitan Planning Organization Meetings Tulsa and Oklahoma City Transportation Management Areas July 2014 Agenda Public Input- Structure and

More information

HUTT CITY COUNCIL TEMPORARY ROAD CLOSURES SUBCOMMITTEE

HUTT CITY COUNCIL TEMPORARY ROAD CLOSURES SUBCOMMITTEE HUTT CITY COUNCIL TEMPORARY ROAD CLOSURES SUBCOMMITTEE Temporary Road Closure Subcommittee to be held in the Wainuiomata Chambers, Wainuiomata Library, Queen Street, Wainuiomata on Tuesday 24 March 2015

More information

3. THE RANGE OF PROJECTS PROPOSED FOR EVALUATION

3. THE RANGE OF PROJECTS PROPOSED FOR EVALUATION Prioritisation process for funding of competing Transport related projects (Auckland Perspective) Ayokunle Martins (Land Transport Programme Coordinator) Auckland Regional Transport Authority ABSTRACT

More information

Selecting Projects for Accelerated Bridge Construction

Selecting Projects for Accelerated Bridge Construction Selecting Projects for Accelerated Bridge Construction In January of 2017, the Engineering Services and Operations Division Directors issued a memo instructing Districts to consider accelerated bridge

More information

Safety Performance Management Targets. Transportation Policy Board January 11, 2018

Safety Performance Management Targets. Transportation Policy Board January 11, 2018 Safety Performance Management Targets Transportation Policy Board January 11, 218 Federal Requirements - Background MAP-21/FAST Act established new emphasis on performance and outcome based planning Required

More information

Hounslow PFI Update. Hounslow Highways Pathfinder PFI Asset Management Satbir Gill Network Manager. 8 th November

Hounslow PFI Update. Hounslow Highways Pathfinder PFI Asset Management Satbir Gill Network Manager. 8 th November Hounslow Highways Pathfinder PFI Asset Management Satbir Gill Network Manager 8 th November 2017 www.hounslowhighways.org Agenda The Hounslow PFI Project (Description and Vision) Core Investment Progress

More information

Transportation BUSINESS PLAN ACCOUNTABILITY STATEMENT

Transportation BUSINESS PLAN ACCOUNTABILITY STATEMENT Transportation BUSINESS PLAN 2003-06 ACCOUNTABILITY STATEMENT The for the three years commencing April 1, 2003 was prepared under my direction in accordance with the Government Accountability Act and the

More information

Presentation to NCAUPG/OAPC

Presentation to NCAUPG/OAPC Presentation to NCAUPG/OAPC Industry Objectives Ensure best quality pavements Assisting with QC/QA processes Improve the durability asphalt pavements Currently Managing for pay Driven by current acceptance

More information

UK Power Networks Stakeholder Engagement Strategy

UK Power Networks Stakeholder Engagement Strategy UK Power Networks Stakeholder Engagement Strategy Our vision UK Power Networks vision is to be an employer of choice, a respected corporate citizen, sustainably cost efficient and to be the consistently

More information

Roads and Footpath Activity Management Plan (Part B Asset Based) February 2018

Roads and Footpath Activity Management Plan (Part B Asset Based) February 2018 Roads and Footpath Activity Management Plan (Part B Asset Based) 2018-2028 February 2018 Quality Assurance Statement: Southland District Council 15 Forth Street Invercargill 9840 Telephone 0800 732 732

More information

10.0 ASSET MANAGEMENT PRACTICES. Table of Contents

10.0 ASSET MANAGEMENT PRACTICES. Table of Contents 10.0 ASSET MANAGEMENT PRACTICES Table of Contents 10.0 ASSET MANAGEMENT PRACTICES... 1 10.1 Current Asset Management Practices... 2 10.2 Asset Management Processes... 3 10.2.1 Attribute data collection

More information

Kokatha: Position Description OPERATIONS MANAGER

Kokatha: Position Description OPERATIONS MANAGER OPERATIONS MANAGER KOKATHA - Background: The Kokatha People are the Traditional Owners of a large section of the land in the north of South Australia. This area stretches from Lake Torrens in the East

More information

SSO- WDR Compliance Workshop Electronic Reporting: Reporting Requirements & Tips. Sewer System Management Plan Chapter

SSO- WDR Compliance Workshop Electronic Reporting: Reporting Requirements & Tips. Sewer System Management Plan Chapter Chapter Contents Introduction SSMP Requirements and Suggested Content SSMP Preparation Deadlines Introduction This chapter provides a brief overview of the GWDR requirements for an SSMP and provides some

More information

INTRODUCTION TO ISO 9001:2015. A One-Day Awareness On ISO 9001:2015 Quality Management Systems And The Impact On The Work Place

INTRODUCTION TO ISO 9001:2015. A One-Day Awareness On ISO 9001:2015 Quality Management Systems And The Impact On The Work Place Course no.: ISO 01 INTRODUCTION TO ISO 9001:2015 A One-Day Awareness On ISO 9001:2015 Quality Management Systems And The Impact On The Work Place What is Quality What is ISO 9001:2015 a Quality Management

More information

Roading Procurement Strategy

Roading Procurement Strategy Roading Procurement Strategy 8 September 2010 1. Introduction 1.1 This document is the Council s procurement strategy for roading works as required by the New Zealand Transport Agency s procurement manual.

More information

IDAS form 6 Building or operational work assessable against a planning scheme

IDAS form 6 Building or operational work assessable against a planning scheme IDAS form 6 Building or operational work assessable against a planning scheme (Sustainable Planning Act 2009 version 2.0 effective 17 December 2012) This form must be used for development applications

More information

TRANSPORTATION ASSET MANAGEMENT PLAN. Data Collection Traffic Counting Strategy AUGUST Hastings District Council DRAFT IN PROGRESS

TRANSPORTATION ASSET MANAGEMENT PLAN. Data Collection Traffic Counting Strategy AUGUST Hastings District Council DRAFT IN PROGRESS TRANSPORTATION ASSET MANAGEMENT PLAN Data Collection Traffic Counting Strategy Hastings District Council AUGUST 2014 DRAFT IN PROGRESS CREATING A ROBUST AND BALANCED FOR MONITORING USE OF THE ROADING NETWORK

More information

B1: THE MAIN PROVISIONS OF THE PLANNING REGIME

B1: THE MAIN PROVISIONS OF THE PLANNING REGIME HIGH SPEED TWO INFORMATION PAPER B1: THE MAIN PROVISIONS OF THE PLANNING REGIME This paper outlines the main provisions of the planning regime proposed for Phase One of the HS2 project. It will be of particular

More information

DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS

DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS Construction Impact Mitigation Strategy Guidelines for Major Developments The District of North Vancouver

More information

by N L R Peshve Project Director Date : Nov-2006 Karnataka State Highways Improvement Project

by N L R Peshve Project Director Date : Nov-2006 Karnataka State Highways Improvement Project ON by N L R Peshve Project Director Date : 02-11-06 TRADITIONAL HIGHWAY MAINTENANCE In Karnataka Routine Highway Maintenance was carried out Departmentally through Gang men of PWD. Periodical maintenance

More information

Comprehensive Transportation Study for Glencoe, MN

Comprehensive Transportation Study for Glencoe, MN Comprehensive Transportation Study for Glencoe, MN Introduction and Project Information Introduction There have been a number of planning and preliminary engineering studies completed in the Glencoe area

More information

February 27th, 2018 City of Mayville

February 27th, 2018 City of Mayville February 27th, 2018 City of Mayville Project Location and Schedule Construction work Detour Route Business Access During Construction Temporary Business Signs What WisDOT Can Do During Construction What

More information

Asset Management Plan - Transport

Asset Management Plan - Transport Asset Management Plan - Transport 2015-2018 TRANSPORT ASSET MANAGEMENT PLAN Document Control PCC Transport Asset Management Plan 2015 (#1200309**) Porirua City Council PO Box 50-218 Porirua City NEW ZEALAND

More information

2017 General Obligation Bond. PUBLIC FACILITIES COMMITTEE Presented by Public Works April 6, 2017

2017 General Obligation Bond. PUBLIC FACILITIES COMMITTEE Presented by Public Works April 6, 2017 2017 General Obligation Bond PUBLIC FACILITIES COMMITTEE Presented by Public Works April 6, 2017 Presentation Highlights Public Works Overview Overview of Projects Presentation of Individual Project Needs

More information

Road Safety Audit. Standards. GE-STY March General

Road Safety Audit. Standards. GE-STY March General Road Safety Audit GE-STY-01024 March 2015 General Standards TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure Ireland (TII) is responsible for managing and improving

More information

By Sea, And by Air. Port Administration and Legal Issues Seminar. Brenda L. Enos, CHMM, REM Massachusetts Port Authority April 11, 2013

By Sea, And by Air. Port Administration and Legal Issues Seminar. Brenda L. Enos, CHMM, REM Massachusetts Port Authority April 11, 2013 By Sea, And by Air. Port Administration and Legal Issues Seminar Brenda L. Enos, CHMM, REM Massachusetts Port Authority April 11, 2013 1 OVERVIEW Basics of Climate Change What are we doing about it A Bit

More information

Challenges of Sustainable Infrastructure AAEES UCI

Challenges of Sustainable Infrastructure AAEES UCI Challenges of Sustainable Infrastructure AAEES UCI Sam Ali, PE, LEED AP sam.ali@ocpw.ocgov.com January 16, 2013 Sustainable Infrastructure Defining Sustainable Infrastructure Sustainable Systems Sustainable

More information

Attachment 13 DRAFT. Document number A

Attachment 13 DRAFT. Document number A Attachment 13 DRAFT Asset Management Plan 2015 2025 Part C Managing Our Assets Transportation Attachment 13 CONTENTS PART C: MANAGING OUR ASSETS... 3-1 3 SUMMARY... 3-1 3.1 Activity Description... 3-1

More information

Worksite Safety Update Promoting safety in road construction

Worksite Safety Update Promoting safety in road construction Worksite Safety Update Promoting safety in road construction No 104 February 2011 In this Edition: Mobile Barrier Trailer Developed in USA Page 1 Barrier Crash Attenuators on Urban Freeways Page 6 Draft

More information

2016 Cape Cod Regional Transportation Plan Development

2016 Cape Cod Regional Transportation Plan Development 2016 Cape Cod Regional Transportation Plan Development APRIL 2015 PUBLIC MEETING PRESENTATION REGIONAL TRANSPORTATION P LAN ( RTP) + Long-range plan (2016-2040) + Includes all modes + Establishes the regional

More information

ESF #1Transportation Roles and Responsibilities

ESF #1Transportation Roles and Responsibilities ESF #1Transportation Roles and Responsibilities Purpose: Coordinate all emergency transportation resources for the response to and recovery from any disaster in Woodbury County. Organization Primary Agency:

More information

UMTA : PROPOSED GENERIC STRUCTURE

UMTA : PROPOSED GENERIC STRUCTURE UMTA : PROPOSED GENERIC STRUCTURE Agenda GEOGRAPHICAL COVERAGE ORGANIZATIONAL STRUCTURE GOVERNING BOARD COMPOSITION POWERS AND FUNCTIONS OF UMTA LEGAL PROVISION 2 GEOGRAPHICAL COVERAGE 3 PROPOSED GEOGRAPHICAL

More information

Construction Logistics Plan Guidance

Construction Logistics Plan Guidance Construction Logistics Plan Guidance CLP guidence CLP guidance The purpose of this Construction Logistics Plan (CLP) guidance is to ensure that CLPs of high quality are produced to minimise the impact

More information

ROAD DEVELOPMENT AGENCY

ROAD DEVELOPMENT AGENCY ROAD DEVELOPMENT AGENCY CUSTOMER SERVICE CHARTER RDA: TRANSFORMING ZAMBIA INTO A TRULY LAND LINKED COUNTRY 1 1.0 GLOSSARY ZSIC - Zambia State Insurance Corporation ICT - Information and Communication Technology

More information

Safety Management System for Israel

Safety Management System for Israel Safety Management System for Israel Dr. Simon Lewis and Joe Garvey AgileAssets, Inc. Traffic Records Forum New Orleans July 27, 2010 A nation under pressure * Do things well /smart * Do things right first

More information

IDAS form 6 Building or operational work assessable against a planning scheme

IDAS form 6 Building or operational work assessable against a planning scheme (Sustainable Planning Act 2009 version 3.0 effective 1 July 2013) This form must be used for development applications for building work or operational work assessable against a planning scheme. You MUST

More information

Lessons Learned Impacting Bridget Malinowski and John Stevens

Lessons Learned Impacting Bridget Malinowski and John Stevens Lessons Learned Impacting 2015 Bridget Malinowski and John Stevens Agenda Review lessons learned Maintain the schedule Potential change orders Agency coordination Claims process Design and construction

More information

TAURANGA CITY COUNCIL

TAURANGA CITY COUNCIL TAURANGA CITY COUNCIL CONDITIONS FOR SOUTHERN PIPELINE APPLICATION (RC13559) 1. The proposal shall proceed in accordance with the application submitted including: - The Assessment of Effects on the Environment

More information

Module 5. Other topics, considered relevant for further certification as Business Consultants = Other Skills. Date:

Module 5. Other topics, considered relevant for further certification as Business Consultants = Other Skills. Date: Module 5 Other topics, considered relevant for further certification as Business Consultants = Other Skills Date: 23.-27.01.2017 Quality Management Certification and Food Safety Management Environmental

More information

National Highways Sector Schemes for Quality Management in Highway Works

National Highways Sector Schemes for Quality Management in Highway Works National Highways Sector Schemes for Quality Management in Highway Works SCHEME 0 GUIDE TO THE IDENTIFICATION, DEVELOPMENT, MANAGEMENT AND CERTIFICATION OF NATIONAL HIGHWAY SECTOR SCHEMES PART 1 INTRODUCTION

More information

SUSTAINABLE URBAN MOBILITY PLAN TRAINING WORKSHOP. Module 5 Identifying & Testing Measures, SUMP Strategy Development

SUSTAINABLE URBAN MOBILITY PLAN TRAINING WORKSHOP. Module 5 Identifying & Testing Measures, SUMP Strategy Development SUSTAINABLE URBAN MOBILITY PLAN TRAINING WORKSHOP Module 5 Identifying & Testing Measures, SUMP Strategy Development Selection of Measures & Projects Distinguish between measures and projects! Defining

More information

I-65/I-70 North Split Interchange Reconstruction Project Frequently Asked Questions

I-65/I-70 North Split Interchange Reconstruction Project Frequently Asked Questions I-65/I-70 North Split Interchange Reconstruction Project Frequently Asked Questions General Overview What is the I-65/I-70 North Split Reconstruction Project? The I-65/I-70 North Split Reconstruction Project

More information

Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room.

Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room. APM Project Fundamentals Qualification Examination paper Candidate Number Date Location Examination Paper Sample Paper v1.4 General Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use

More information

THE COMPLETE GUIDE TO ISO14001

THE COMPLETE GUIDE TO ISO14001 THE COMPLETE GUIDE TO ISO14001 1. Introduction... 3 Plan Do Check Act... 5 2. Requirements... 7 Environmental Policy... 7 Environmental Aspects... 7 Legal and Other Requirements... 8 Objectives & Targets...

More information

HIGHWAY 14 NEW ULM TO NICOLLET 4-Lane Expansion Open House

HIGHWAY 14 NEW ULM TO NICOLLET 4-Lane Expansion Open House HIGHWAY 14 NEW ULM TO NICOLLET 4-Lane Expansion Open House HIGHLIGHTS OF HWY 14 PROGRESS 1960s & 70s Four-lane expansion in Rochester and Mankato areas 1993 Owatonna to Kasson EIS Completed (redone to

More information

Roading Policies January 2015

Roading Policies January 2015 Roading Policies Record of Amendments Amendment No. Subject Effective Date Updated By Version 1 Draft for Consultation 18 September 2015 Julie Muir Version 2 Amended to include feedback from February 2014

More information

Freight transport policy and measures in Norway

Freight transport policy and measures in Norway PIARC meeting and seminar 13-15 June 2005 in Ouagadougou Freight transport policy and measures in Norway Senior Adviser Hans Silborn, Norwegian Public Roads Administration Norway is a sparsely inhabited

More information

Transportation Contributed Assets Review January 28, 2015

Transportation Contributed Assets Review January 28, 2015 Transportation Contributed Assets Review January 28, 2015 Office of the City Auditor The Office of the City Auditor conducted this project in accordance with the International Standards for the Professional

More information

Sustainable Urban Mobility Plans: Concept, process, content & benefits

Sustainable Urban Mobility Plans: Concept, process, content & benefits Sustainable Urban Mobility Plans: Concept, process, content & benefits Is the increase of car traffic a natural law? Like a sunrise or a sunset Or like an earthquake No it isn t But we have to reconsider

More information

This qualification has been reviewed. The last date to meet the requirements is 17 December 2018.

This qualification has been reviewed. The last date to meet the requirements is 17 December 2018. NZQF NQ Ref 1326 Version 3 Page 1 of 15 National Certificate in Infrastructure Works with strands in Concrete Kerb and Channel, Concrete Work, Culverts and Drainage Systems, Interlocking Paving, Retaining

More information

Road Safety Audit Guidelines

Road Safety Audit Guidelines Road Safety Audit Guidelines December 2017 TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure Ireland (TII) is responsible for managing and improving the country s national

More information

ACTIVE TRANSPORTATION ADVISORY COMMITTEE. Memphis MPO March 30, 2015

ACTIVE TRANSPORTATION ADVISORY COMMITTEE. Memphis MPO March 30, 2015 ACTIVE TRANSPORTATION ADVISORY COMMITTEE Memphis MPO March 30, 2015 Agenda Welcome & Introductions Announcements and Briefings Livability 2040: Regional Transportation Plan Congestion Management Process

More information

Guidance for Retrofitting Vehicle Restraint Systems on the Single Carriageway National Road Network

Guidance for Retrofitting Vehicle Restraint Systems on the Single Carriageway National Road Network Guidance for Retrofitting Vehicle Restraint Systems on the Single Carriageway National Road Network February 2017 TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure

More information

Strategic Transport Plan

Strategic Transport Plan Strategic Transport Plan Palmerston North SMALL CITY BENEFITS, BIG CITY AMBITION 2018/21 Te Kaunihera o Papaioea Palmerston North City Council Palmerston North City Council Strategic Transport Plan 2 To

More information

2017 Transportation and Storm Drainage Projects

2017 Transportation and Storm Drainage Projects 2017 Transportation and Storm Drainage Projects Request for Qualifications Pre-Submittal Meeting: Welcome and Introductions Sign-in sheet Meeting Agenda Provide overview of solicitation and selection process

More information

Asset Management Program Plan

Asset Management Program Plan ODOT ASSET MANAGEMENT STAYING AHEAD OF THE CURVE... ODOT Asset Management Program Plan March 19, 2008 This Asset Management Program Plan has been developed to provide interested stakeholders a synopsis

More information

Golden Rule #3: Vehicles & Mobile Equipment

Golden Rule #3: Vehicles & Mobile Equipment Golden Rule #3: Vehicles & Mobile Always use mobile equipment and light vehicles for the purpose they were designed and adhere to site pedestrian / vehicle traffic rules. Skill / Experience to Operate

More information

Road Management Plan Version June 2013

Road Management Plan Version June 2013 Road Management Plan Version 4.00 17June 2013 City of Banyule Schedule of Changes & Amendments Version Date Changes/Amendments V1.00 6/12/2004 Adopted by Council at its meeting 6 December, Gazetted 9 December

More information

Welcome to this information session on the proposed Bell Road Reservoir Replacement Project.

Welcome to this information session on the proposed Bell Road Reservoir Replacement Project. Haere mai Welcome to this information session on the proposed Bell Road Reservoir Replacement Project. This session is your opportunity to: meet the team find out more about the project understand our

More information