1 Agenda item MEETING: Technical Strategy Leadership Group DATE: 03 December 2015 SUBJECT: AUTHOR: Annual Report from Vehicle/Vehicle SIC John Hawkins, Chair, Vehicle/Vehicle SIC 1. Purpose of the paper 1.1 This paper is for discussion by TSLG. 2. Issue 2.1 Sixth annual report to TSLG from Chair of the Vehicle/Vehicle System Interface Committee (V/V SIC). 3. Recommendations 3.1 TSLG is invited to note the work of V/V SIC and its sub-groups in the last 12 months and to provide any guidance considered appropriate in relation to activities planned for the coming year. 4. Background 4.1 The V/V SIC assists the Railway Industry to manage all aspects of the vehicle system interfaces in a safe, cost effective and efficient way. It has also now taken on an additional role as Portfolio Champion for the Rolling Stock Chapter of the RTS. 4.2 V/V SIC has formed separate sub-groups to cover specific issues: X-Industry Remote Condition Monitoring Group (XiRCM) Diesel Systems Working Group (DSWG) Fire Forum Key Train Requirements Sub-Group 4.3 In addition, to support its role as RTS Portfolio Champion, V/V SIC has also created a Rolling Stock Portfolio Working Group. TSLG 03 December 2015 Annual Report from Vehicle/Vehicle SIC Page 1 of 6

2 5. Key Areas of Activity 5.1 Key Train Requirements Work on the preparation of Issue 4 of the KTR document is progressing well, with a number of meetings having taken place to consider proposed changes and an initial draft of the document produced. A particular emphasis has been to take account of feedback received from outside the industry as a result of the publicising of Issue 3, following its publication in September Toilets have been recognised as a particularly sensitive area from a passenger perspective and a cross-industry workshop was therefore arranged in September 2015 to identify key problem areas and potential solutions. The output from this workshop will be discussed with groups such as Transport Focus before the content for inclusion in the KTR document is finalised. 5.2 RTS Rolling Stock Chapter Delivery Completed Work The RTS Rolling Stock Portfolio Working Group completed work on the preparation of Benefits Maps for the Rolling Stock Chapter of the RTS in February These maps, together with those prepared by other Portfolio Groups, were subsequently endorsed by RDG T&O Group. The seven Significant Programmes identified for rolling stock were as follows: Passenger Train Architecture Future Freight Trains Train Energy and Motion Passenger Environment and Experience Train Operability and Control Rolling Stock Support (RAMS) Rolling Stock Interfaces Further work has subsequently been undertaken to identify key projects that would be required to deliver the outputs identified for each of the Significant Programmes and to allocate, within the context of the Rolling Stock Portfolio, priorities. Having completed this activity during spring 2015, the Group responded to a request from FutureRailway to suspend further work whilst they assimilated output from the Portfolio Groups and synthesised it into possible programmes (feasibility studies, competitions, research - noting that some may potentially be cross-system) for further consideration. To date, the Rolling Stock Portfolio Group has met only once since this requested pause in its activities. TSLG 03 December 2015 Annual Report from Vehicle/Vehicle SIC Page 2 of 6

3 5.2.2 Planned Work It is anticipated that the next stage of activity for the Rolling Stock Portfolio Group will be to further develop those projects that are identified as delivering the greatest benefits when considered from a whole system perspective. As an example, the ability to achieve high performance, predictable, braking has already been identified as a key enabler to achieving closer running between trains and vehicles. This, in turn, offers the potential to significantly increase capacity without the requirement for major infrastructure investment; for example, through provision of additional tracks. Work is therefore progressing to identify and develop projects that may support the delivery of high performance, predictable, braking. 5.3 Other Industry Support Activities V/V SIC continues to lead other activities providing more tactical support for the rail industry. These include: Research Project T1024, Procedures for dealing with bodyside windows broken in service The objective of this research was to propose a common approach and guidance for dealing with bodyside windows broken in service. Research activities have now concluded and the findings offer significant potential benefits to train operators by enabling a relaxation of restrictions currently applied for trains which have suffered a broken outer pane of a bodyside window. The results from this research are scheduled to be presented to the next meeting of the ATOC Technical and Standards Forum. Research Project T1036, Performance specification and guidance for internal powered train doors to minimise injury potential This research project was initiated in response to concerns raised by Passenger Focus (now Transport Focus) regarding injuries sustained by passengers as a result of encounters with internal power operated doors on trains. There are currently no Standards or Codes of Practice in place relating to desirable design features or performance characteristics for these doors. The research, now completed, has assisted in determining the ideal operating characteristics for internal powered train doors, providing essential material for inclusion in the next issue of the Key Train Requirements document, pending a review of relevant standards. The report has also been shared with Transport Focus in order to demonstrate the responsiveness of the industry to safety concerns raised by passenger representatives. Research Project T1036, Performance specification and guidance for internal powered train doors to minimise injury potential This research project was initiated in response to concerns raised by Passenger Focus (now Transport Focus) regarding injuries sustained by passengers as a result of encounters with internal power operated doors on trains. There are currently no TSLG 03 December 2015 Annual Report from Vehicle/Vehicle SIC Page 3 of 6

4 Standards or Codes of Practice in place relating to desirable design features or performance characteristics for these doors. The research, now completed, has assisted in determining the ideal operating characteristics for internal powered train doors, providing essential material for inclusion in the next issue of the Key Train Requirements document, pending a review of relevant standards. The report has also been shared with Transport Focus in order to demonstrate the responsiveness of the industry to safety concerns raised by passenger representatives. Knowledge Search S096, Rolling stock interior noise This Knowledge Search reviewed work undertaken to manage, and identify appropriate limits for, interior noise levels across a range of transport modes, including rail, automotive and aviation. The results are currently being reviewed with a view to including relevant material in the next issue of the Key Train Requirements document. Following a presentation to V/V SIC of innovative train suspension configurations used for trams and by some mainline railways in other countries, it was concluded that further investigations were required to determine the potential whole system benefits. A subsequent meeting involving representatives from V/V SIC, V/T SIC and ORR concluded there would be benefits from commissioning a research project to use the algorithms in VTISM to identify what reductions in track maintenance and renewal costs might be achievable. Results from this research should inform decisions as to where rolling stock innovation funding might best be focused to support delivery of key outputs identified through the RTS Portfolio Groups. This is now being progressed as a Research Idea. 5.4 Activities of Other V/V-SIC Working Groups X-Industry RCM Strategy Group (XI-RCMSG) Chair Amanda Hall (Network Rail). Meetings scheduled every three months The remit for this group is to identify and, where appropriate, put in place the enablers necessary to achieve the objectives of the Rail Technical Strategy for train-to-infrastructure and infrastructure-to-train Remote Condition Monitoring (RCM) Over the last year, work has been carried out on some of these enablers. T1010 has been completed and is formed of the following four work packages: T RCM data sharing architecture principles and interface specifications; T RCM data sharing business process mapping and commercial framework; TSLG 03 December 2015 Annual Report from Vehicle/Vehicle SIC Page 4 of 6

5 T Standards review and guidance on how to use the products in the work packages; T Cross-industry RCM Business Case Decision Support Tool The outputs of T1010 have been presented at various events, including: a RSSB dissemination event, the RIA Information Management Group and TSLG The response has been positive and, at the request of stakeholders and TSLG, work has commenced on scoping the next steps beyond the deliverables in T1010. This is likely to be in the form of a demonstrator to provide more detail on a practical application of the T1010 approach to the sharing of remote condition monitoring data across different parties An output from T was to recommend standards which need to be produced. Of those submitted to the T&RS Subject Committee, the Automatic Vehicle Identification standard has been accepted as a development priority Automatic Vehicle Identification trials have been carried out by Network Rail in conjunction with some suppliers, TOCs, FOCs and ROSCOs and with the support of the Group. The trials report is at final draft stage and will be issued shortly Diesel Systems Working Group (DSWG) Chair Bryan Donnelly (ATOC). Meetings scheduled quarterly The diesel systems working group meets quarterly and provides industry expertise and exchange of information for: Diesel emissions legislation(especially monitoring proposed changes to Non Road Mobile Machinery Regulations) Changes to fuel specification and quality to include impact assessment, with a particular interest in renewables New technology for reducing fuel consumption and emissions Of particular interest is the NRMM stage 5 proposals and the group is being used to provide expertise into our arguments for a CER position on the proposed changes to the directive Fire Forum Chair Phil Hinde (CrossRail) This Group continues to meet on an approximately annual basis; the last meeting taking place in December Due to pressure of work the next meeting is not expected to take place until early in Whilst other forums, such as BSI Committee and FSH19, are able to provide an overview for fire related standards, Fire Forum provides a unique opportunity to undertake a cross-industry review of fire safety from a rolling stock industry point of view. This includes a review of previous incidents, including not only fire performance but also incident management. TSLG 03 December 2015 Annual Report from Vehicle/Vehicle SIC Page 5 of 6

6 The most noteworthy element from the trends and incident reviewed in December 2014 was the number of occasions when a minor, and technically speaking well-contained, event caused disproportionate disruption and panic behaviour including uncontrolled self-evacuation by passengers. Such outcomes generally appeared to have created greater hazard than the original combustion (e.g. arcing from shoegear damaged by contact with debris) It has been recommended to V/V SIC that RSSB s wider safety expertise is used to review this, with a view to strengthening staff training around understanding of fire risks, incident response, emergency communications with passengers, and evacuation. 6. Future Challenges 6.1 Whilst recognising the importance of continuing its role of providing tactical support for the rail industry where required, and continuing to develop the Key Train Requirements document, the principle focus for V/V SIC over the coming year is expected to be on developing and assisting in the delivery of key projects from the Significant Programmes defined by the Rolling Stock Portfolio Group that have been identified as offering the greatest whole system benefits in delivering the vision described in the RTS. TSLG 03 December 2015 Annual Report from Vehicle/Vehicle SIC Page 6 of 6

This remit should be read alongside the SIC Protocol which sets out arrangements for all SICs in more detail

This remit should be read alongside the SIC Protocol which sets out arrangements for all SICs in more detail REMIT Vehicle/Structures System Interface Committee This remit should be read alongside the SIC Protocol which sets out arrangements for all SICs in more detail 1. Establishment and purpose 1.1. System

More information

THEFUTURERAILWAY THE INDUSTRY S RAIL TECHNICAL STRATEGY 2012 WHOLE-SYSTEM APPROACH

THEFUTURERAILWAY THE INDUSTRY S RAIL TECHNICAL STRATEGY 2012 WHOLE-SYSTEM APPROACH 65 WHOLE-SYSTEM APPROACH Specifying assets in a whole-system context and a whole-life perspective, they will initially cost more......but the components will work well together, the system will be reliable

More information

Future Communications and Positioning Systems Advisory Group (FC&PS AG) Remit Issue No July 2014

Future Communications and Positioning Systems Advisory Group (FC&PS AG) Remit Issue No July 2014 Future Communications and Positioning Systems Advisory Group (FC&PS AG) Remit Issue No. 5 22 July 2014 1 Introduction 1.1 This remit defines the working arrangements for the FC&PS AG, a sub-group of the

More information

Defect Recording Analysis & Corrective Action System Steering Group (DRACAS SG) Remit Issue No. 3, 23 November 2016

Defect Recording Analysis & Corrective Action System Steering Group (DRACAS SG) Remit Issue No. 3, 23 November 2016 System Interface Committee (V/TC&C SIC) Endorsed by V/TC&C SIC System Steering Group (DRACAS SG) 1 Introduction 2 Scope Remit Issue No. 3, 23 November 2016 In accordance with SIC protocol, this remit defines

More information

Rail Industry Technical Leadership Group - Scope and Structure

Rail Industry Technical Leadership Group - Scope and Structure Rail Industry Technical Leadership Group - Scope and Structure Background Following discussions among industry leaders, including representation from RSG and RDG, looking at technical leadership in the

More information

DISIC Remit Final Version 1.0 March 2018

DISIC Remit Final Version 1.0 March 2018 DRAFT REMIT Data and Information System Interface Committee This remit should be read alongside the SIC Protocol, which sets out arrangements for all SICs in more detail. 1 ESTABLISHMENT AND PURPOSE 1.1

More information

12 The Supply Chain What is the rail industry supply chain?

12 The Supply Chain What is the rail industry supply chain? 12 The Supply Chain Not having the right parts when you need them can be a reason for non-availability of vehicles for service (as the analysis described in Section 6.5 may show). It is a false economy

More information

Planning, Reporting and Regulatory Framework

Planning, Reporting and Regulatory Framework Planning, Reporting and Regulatory Framework Strategic Business Plan 9 February 2018 Planning, Reporting and Regulatory Framework This document describes the key elements and methods of working in our

More information

V/TC&C SIC Vehicle/Train Control and Communications System Interface Committee

V/TC&C SIC Vehicle/Train Control and Communications System Interface Committee Future Communications & Positioning Systems Advisory Group (FC&PS AG) Remit Issue (4) July 2013 1 Introduction 1.1 This document defines the working arrangements for the Future Communications & Positioning

More information

Driver Selection Governance Group (DSGG) Strategic Plan Issue two

Driver Selection Governance Group (DSGG) Strategic Plan Issue two Driver Selection Governance Group (DSGG) Strategic Plan 2015 2019 Issue two Approved by the TOM Standards Committee 15 December 2015 Email: enquirydesk@rssb.co.uk www.rssb.co.uk ISSUE RECORD Issue Date

More information

ATOC Guidance Note Planning for Special Events

ATOC Guidance Note Planning for Special Events ATOC Guidance Note Planning for Special Events Synopsis This Guidance Note provides advice on operational, safety and contingency factors to take into consideration when planning for special events. Authorised

More information

Asset Management Policy

Asset Management Policy Asset Management Policy January 2018 Introduction Our Asset Management Policy was last published in 2014. It is being updated to reflect our commitment to regularly review and improve all of our Asset

More information

ATOC Approved Code of Practice Incident Response Duties of Primary Support Operators

ATOC Approved Code of Practice Incident Response Duties of Primary Support Operators Uncontrolled When Printed ATOC Approved Code of Practice Incident Response Duties of Primary Support Operators Submitted by --------------------------------------------------------- Gary Cooper Director,

More information

Guidance Note Emergency Planning - Knowledge, Understanding and Responsibilities

Guidance Note Emergency Planning - Knowledge, Understanding and Responsibilities Uncontrolled when printed RDG-GN011 Guidance Note Emergency Planning - Knowledge, Understanding and Responsibilities Synopsis This Guidance Note provides advice on requirements with regard to knowledge,

More information

CONTRACTUAL AND REGULATORY REFORM WORKSTREAM. RDG vision for the charges and incentives regime in the long run

CONTRACTUAL AND REGULATORY REFORM WORKSTREAM. RDG vision for the charges and incentives regime in the long run CONTRACTUAL AND REGULATORY REFORM WORKSTREAM RDG vision for the charges and incentives regime in the long run Published December 2014 What is the Rail Delivery Group? The Rail Delivery Group (RDG) seeks

More information

WRITTEN SUBMISSION FROM NETWORK RAIL 28 OCTOBER 2008

WRITTEN SUBMISSION FROM NETWORK RAIL 28 OCTOBER 2008 WRITTEN SUBMISSION FROM NETWORK RAIL 28 OCTOBER 2008 Thank you for inviting Network Rail to participate in the Transport, Infrastructure and Climate Change Committee inquiry into the potential benefits

More information

THEFUTURERAILWAY THE INDUSTRY S RAIL TECHNICAL STRATEGY 2012 CONTROL, COMMAND AND COMMUNICATION

THEFUTURERAILWAY THE INDUSTRY S RAIL TECHNICAL STRATEGY 2012 CONTROL, COMMAND AND COMMUNICATION THEFUTURERAILWAY THE INDUSTRY S RAIL TECHNICAL STRATEGY 2012 17 CONTROL, COMMAND AND COMMUNICATION Control centre optimises the positions of trains in real time Drivers receive information to optimise

More information

Auckland Transport HS08-01 Safety In Design

Auckland Transport HS08-01 Safety In Design Auckland Transport HS08-01 Safety In Design (Procedure uncontrolled when printing) Relating to Standard: HS08 Safety In Design December 2016 Health and Safety-Procedure-HS08-01 Safety In Design Contents

More information

London Overground. Mike Stubbs Director London Overground

London Overground. Mike Stubbs Director London Overground London Overground Mike Stubbs Director London Overground Contents What is London Overground? The need for London Overground Where we started Our journey Where we are today Future direction Lessons & Conclusions

More information

Incident Response Planning & Management

Incident Response Planning & Management Incident Response Planning & Synopsis This standard identifies interface requirements for enabling a consistent, comprehensive and structured process for rail incident response planning and management.

More information

Your RSSB: 2018/19. Work Programme Consultation and Update on New Settlement with Members

Your RSSB: 2018/19. Work Programme Consultation and Update on New Settlement with Members Your RSSB: 2018/19 Work Programme Consultation and Update on New Settlement with Members Issue Date:19 Sept 2017 1 Introduction Welcome to the RSSB member consultation for 2018/19. The purpose of the

More information

Rail Industry Safety Strategy

Rail Industry Safety Strategy Rail Industry Safety Strategy 2016 2020 One law One regulator One investigator One industry Context The national rail reform agenda As part of broad reforms to deliver a Seamless National Economy, in 2011

More information

Electro-Magnetic Compatibility Sub-group (EMC SG) DRAFT Remit Issue (1) 22/04/2013

Electro-Magnetic Compatibility Sub-group (EMC SG) DRAFT Remit Issue (1) 22/04/2013 Electro-Magnetic Compatibility Sub-group (EMC SG) DRAFT Remit Issue (1) 22/04/2013 1 Introduction 1.1 This document defines the working arrangements for the Electro-Magnetic Compatibility (EMC) sub-group

More information

Ref What Who When Provide further details of Digital Railway trial, including process for selection of routes

Ref What Who When Provide further details of Digital Railway trial, including process for selection of routes PLANNING OVERSIGHT GROUP MINUTES 9TH MARCH 2016 INTRODUCTIONS AND APOLOGIES FOR ABSENCE Attendees Jo Kaye Mark Havenhand Martin Arter Roger Cobbe Gary Cooper Andy Course Lindsay Durham Russell Evans Graeme

More information

Rail Technical Strategy (RTS 2012)

Rail Technical Strategy (RTS 2012) Rail Technical Strategy (RTS 2012) Technical Strategy Leadership Group An RSSB-facilitated cross-industry expert group Remit, TOR and funding provided via RSSB Board Takes strategic direction from Rail

More information

The Network Rail Hope Valley Capacity Scheme Frequently Asked Questions February 2015

The Network Rail Hope Valley Capacity Scheme Frequently Asked Questions February 2015 The Network Rail Hope Valley Capacity Scheme Frequently Asked Questions February 2015 1. The Plans 1.1 What are you doing and why? Demand for rail travel between Sheffield and Manchester is increasing,

More information

14 No Fault Found Warranty Claims

14 No Fault Found Warranty Claims 14 No Fault Found Warranty Claims This chapter focuses on rolling stock component warranty claims where the supplier cannot find a fault with the returned component. There is a perception in the industry

More information

Driver Advisory Information for Energy Management and Regulation

Driver Advisory Information for Energy Management and Regulation Driver Advisory Information for Energy Management and Regulation Jianhong Jin, Rafat Kadhim RSSB, UK Abstract A big challenge for GB rail is to develop a modern, sustainable system that is accessible and

More information

THEFUTURERAILWAY THE INDUSTRY S RAIL TECHNICAL STRATEGY 2012 INFRASTRUCTURE

THEFUTURERAILWAY THE INDUSTRY S RAIL TECHNICAL STRATEGY 2012 INFRASTRUCTURE 33 INFRASTRUCTURE Automated maintenance is quicker, safer and more cost-effective Well-targeted maintenance enables more train paths to be available at night Advanced suspension system minimises noise

More information

Impact Assessment for Changes to Railway Group Standards

Impact Assessment for Changes to Railway Group Standards Impact Assessment for Changes to Railway Group Standards Version: Publication Date: 16 February 2010 Relevant Railway Group Standard Title: Requirements for the Train Protection and Warning System (TPWS)

More information

Strategic Direction for revised Locomotive and Passenger Rolling Stock (LOC&PAS) TSI. Issue 1.0

Strategic Direction for revised Locomotive and Passenger Rolling Stock (LOC&PAS) TSI. Issue 1.0 Strategic Direction for revised Locomotive and Passenger Rolling Stock (LOC&PAS) TSI Issue 1.0 Approved by the Industry Standards Coordination Committee 22 July 2011 ISCC/010 Copyright 2011 Rail Safety

More information

European Rail Infrastructure Managers Handbook for International Contingency Management

European Rail Infrastructure Managers Handbook for International Contingency Management European Rail Infrastructure Managers Handbook for International RailNetEurope Oelzeltgasse 3/8 AT-1030 Vienna Phone: +43 1 907 62 72 00 Fax: +43 1 907 62 72 90 mailbox@rne.eu www.rne.eu Version 1.5, 23.03.2018

More information

Energy Market Information Technology (EMIT) Data Management Working Group (DMWG)

Energy Market Information Technology (EMIT) Data Management Working Group (DMWG) Energy Market Information Technology (EMIT) Data Management Working Group (DMWG) Terms of Reference February 2011 Background The Energy Markets Information Technology Steering Committee (EMIT-SC) guides

More information

ADMIN 4.2 Developing a Product

ADMIN 4.2 Developing a Product ADMIN 4.2 Developing a Product. Paul Daly CEO RISSB 15 December 2016 DOCUMENT CONTROL Identification Document Title Number Version Date Developing a Standard ADMIN 4.2 1 20/11/2007 Developing a Standard

More information

ADMIN 4.2. V e r s i o n 14. Paul Daly CEO RISSB

ADMIN 4.2. V e r s i o n 14. Paul Daly CEO RISSB ADMIN 4.2 Developing a Product V e r s i o n 14 Paul Daly CEO RISSB 10 December 2017 DOCUMENT CONTROL Identification Document Title Number Version Date Developing a Standard ADMIN 4.2 1 20/11/2007 Developing

More information

Infrastructure Projects Strategic Plan. V4.0 Jan 2018 version

Infrastructure Projects Strategic Plan. V4.0 Jan 2018 version Infrastructure Projects Strategic Plan V4.0 Jan 2018 version Contents 1. Forward & Summary... 4 1.1. Introduction... 4 1.2. Vision & Strategic Objectives... 4 1.3. Role of IP in Network Rail... 6 1.4.

More information

Business Continuity Management Policy and Framework

Business Continuity Management Policy and Framework Management Policy and Framework Version: 9 Produced by: University Manager with the assistance of the Operational Group Date Produced: 11 th March 2010 Approved by: Steering Group (14 December 2010) Updated:

More information

Sector management of regulatory document changes STAR project deliverable 8

Sector management of regulatory document changes STAR project deliverable 8 Sector management of regulatory document changes STAR project deliverable 8 Date: 20 June 2014 Author: Dr Christopher Querée Owner: TAP Phase Two Project Team Client: TAP TSI Steering Committee Version:

More information

Memorandum of Understanding (MoU)

Memorandum of Understanding (MoU) EUROPEAN COMMISSION Memorandum of Understanding (MoU) Between the European Commission and the European Railway Associations (CER UIC UNIFE EIM GSM-R Industry Group ERFA) concerning the strengthening of

More information

The Digital Railway Programme

The Digital Railway Programme The Digital Railway Programme The Digital Railway Programme 2 Modernising our Railways By quickly, safely and efficiently transporting large volumes of passenger and freight traffic, Britain s rail industry

More information

Item No Halifax Regional Council June 20, 2017

Item No Halifax Regional Council June 20, 2017 P.O. Box 1749 Halifax, Nova Scotia B3J 3A5 Canada Item No. 14.2.2 Halifax Regional Council June 20, 2017 TO: Mayor Savage and Members of Halifax Regional Council Original Signed SUBMITTED BY: Councillor

More information

Guidance Note Planning for Special Events

Guidance Note Planning for Special Events Guidance Note Planning for Special Events Synopsis This Guidance Note provides advice on operational, safety and contingency factors to take into consideration when planning for special events. Applicability

More information

Guideline Asset Management

Guideline Asset Management Guideline Asset Management Title of the document National Rail Safety Regulator Page1of28 Document reference number: A389849 Version No. Approved by Publication date 1.0 Chief Executive November 2014 1.1

More information

University of Huddersfield Repository

University of Huddersfield Repository University of Huddersfield Repository Bevan, Adam and Molyneux Berry, Paul Optimisation of Wheelset Maintenance: Current Research Activities Original Citation Bevan, Adam and Molyneux Berry, Paul (2014)

More information

COMPLIANCE MANAGEMENT FRAMEWORK. Conceptual Design Document

COMPLIANCE MANAGEMENT FRAMEWORK. Conceptual Design Document COMPLIANCE MANAGEMENT FRAMEWORK Conceptual Design Document 18 February 2013 1. INTRODUCTION & SUMMARY The purpose of the Compliance Management Framework is to ensure the University meets all of its external

More information

Sustainability and Environment Manager

Sustainability and Environment Manager POSITION DESCRIPTION 1. POSITION DETAILS Position Title: Division: Unit: Management Level: Sustainability and Environment Manager City Projects & Property Property Services M4 2. ORGANISATIONAL RELATIONSHIPS

More information

ATOC. ATOC Operational Resilience & Security Forum Good Practice Guide Competence of Train Operator Liaison Officers (TOLOs)

ATOC. ATOC Operational Resilience & Security Forum Good Practice Guide Competence of Train Operator Liaison Officers (TOLOs) ATOC Association of Train Operating Companies ATOC Operational Resilience & Security Forum Good Practice Guide Competence of Train Operator Liaison Officers (TOLOs) Synopsis This Guide sets out recommended

More information

Safety, Technical & Engineering Strategic Plan

Safety, Technical & Engineering Strategic Plan Safety, Technical & Engineering Strategic Plan Graham Hopkins - Group Director, Safety, Technical and Engineering The railway is a complex technical system which has grown organically over two centuries.

More information

Supplier Assurance Management Services

Supplier Assurance Management Services Supplier Assurance Management Services Business Prospectus December 2015 Table of Contents Foreword 3 Introduction 4 Overview 5 The current arrangements 6 Tender package strategy 8 Business model 9 Scale

More information

CROSSRAIL INFORMATION PAPER H3 CROSSRAIL ACCESS OPTION

CROSSRAIL INFORMATION PAPER H3 CROSSRAIL ACCESS OPTION CROSSRAIL INFORMATION PAPER CROSSRAIL ACCESS OPTION This paper explains how it is intended that access rights for running Crossrail services are obtained. It will be of particular relevance to those interested

More information

ACTION PLAN MAY 2017 MAY

ACTION PLAN MAY 2017 MAY RECONCILIATION ACTION PLAN MAY 2017 MAY 2019 TABLE OF CONTENTS / 3 OUR VISION FOR RECONCILIATION / 4 SUPPORTING OUR VISION FOR RECONCILIATION / 6 INDIGENOUS ENGAGEMENT NETWORK / 7 OUR BUSINESS / 8 OUR

More information

This document outlines the role of the Department of Finance in helping the University to achieve the aims of its Strategic Plan.

This document outlines the role of the Department of Finance in helping the University to achieve the aims of its Strategic Plan. INTERNAL ONLY Departmental Vision This document outlines the role of the in helping the University to achieve the aims of its Strategic Plan. The University s Mission is to educate ourselves and others

More information

Apprenticeship Standard for High Speed Rail and Infrastructure (HSRI) Advanced Technician

Apprenticeship Standard for High Speed Rail and Infrastructure (HSRI) Advanced Technician Context Health and Safety Apprenticeship Standard for High Speed Rail and Infrastructure (HSRI) Advanced Technician Occupational Profile: High speed rail is a specialist occupational area of work. High

More information

NOTES / ACTIONS from 5 July 2017 NTF meeting

NOTES / ACTIONS from 5 July 2017 NTF meeting NOTES / ACTIONS from 5 July 2017 NTF meeting ACTION WHAT WHO WHEN Chair - opening remarks MH welcomed Becky Lumlock (Wessex) as the NR RMD rep, Greg Sugden (NR, for Fiona Dolman) and Gus Dunster (Virgin,

More information

Chiltern Automatic Train Protection User Management Group (CATP UMG) Remit Issue (4) Tuesday 07 May 2013

Chiltern Automatic Train Protection User Management Group (CATP UMG) Remit Issue (4) Tuesday 07 May 2013 Chiltern Automatic Train Protection User Management Group (CATP UMG) Remit Issue (4) Tuesday 07 May 2013 1 Introduction 1.1 This document defines the working arrangements for the Chiltern Automatic Train

More information

JOB DESCRIPTION & PERSON SPECIFICATION

JOB DESCRIPTION & PERSON SPECIFICATION JOB DESCRIPTION & PERSON SPECIFICATION HIAL AMSL DAL 1. JOB DETAILS JOB HOLDER JOB TITLE REPORTS TO Vacant ATM Programme Director Managing Director 2. JOB PURPOSE HIAL is commencing on a major programme

More information

Auckland Integrated Transport Plan

Auckland Integrated Transport Plan Auckland Integrated Transport Plan (AITP) Glossary Auckland Council Auckland Transport New Zealand Transport Agency KiwiRail Auckland Integrated Transport Plan Draft Auckland Plan Auckland Plan (AC) (AT)

More information

REGIONAL DEVELOPMENT AUSTRALIA WHAT IS IT? ROLES AND RESPONSIBILITIES

REGIONAL DEVELOPMENT AUSTRALIA WHAT IS IT? ROLES AND RESPONSIBILITIES REGIONAL DEVELOPMENT AUSTRALIA WHAT IS IT? ROLES AND RESPONSIBILITIES September 2009 This document outlines the roles of Regional Development Australia (RDA). RDA is a national initiative based on building

More information

10 The Infrastructure

10 The Infrastructure 10 The Infrastructure 10.1 The Engineering Interfaces The Systems involved: There are many engineering interfaces between vehicles and infrastructure that can affect train performance if they don t work

More information

Job Description. No of Direct Reports : Titles of Direct Reports: Budget Responsibility (direct) : Revenue Responsibility (direct) :

Job Description. No of Direct Reports : Titles of Direct Reports: Budget Responsibility (direct) : Revenue Responsibility (direct) : Job Description Job Title : Department : Senior Portfolio Analyst Portfolio Management Office Reporting to (Job Title) : Senior Portfolio Manager No of Direct Reports : None Titles of Direct Reports: Size

More information

CENTRAL LAND COUNCIL EFFECTIVE CONSULTATION AND ENGAGEMENT STRATEGY

CENTRAL LAND COUNCIL EFFECTIVE CONSULTATION AND ENGAGEMENT STRATEGY CENTRAL LAND COUNCIL EFFECTIVE CONSULTATION AND ENGAGEMENT STRATEGY 2015 2020 CONTEXT The CLC is a Commonwealth corporate entity pursuant to the Aboriginal Land Rights (Northern Territory) Act 1976, the

More information

ONRSR Guideline. Asset Management

ONRSR Guideline. Asset Management Document control Objective Document ID: A389849 Version number: 2.0 Approved by: Chief Executive Date approved: 26 February 2019 Policy changes to 2.0 Periodic Review Office of the National Rail Safety

More information

CASE FOR CHANGE AUTONOMOUS RAIL VEHICLE & HUMAN FACTORS. TLI TRANSPORT AND LOGISTICS TRAINING PACKAGE Rail Industry Reference Committee

CASE FOR CHANGE AUTONOMOUS RAIL VEHICLE & HUMAN FACTORS. TLI TRANSPORT AND LOGISTICS TRAINING PACKAGE Rail Industry Reference Committee CASE FOR CHANGE AUTONOMOUS RAIL VEHICLE & HUMAN FACTORS TLI TRANSPORT AND LOGISTICS Rail Industry Reference Committee 1 A. ADMINISTRATIVE INFORMATION Industry Reference Committee submitting the Case for

More information

Feedback on the 2015 Government Policy Statement

Feedback on the 2015 Government Policy Statement 7 October 2016 Andrew Jackson Deputy Chief Executive Ministry of Transport PO Box 3175 Wellington 6140 Dear Andrew Feedback on the 2015 Government Policy Statement I write to you today in response to the

More information

Reporting High Risk Defects

Reporting High Risk Defects Reporting High Risk Defects Synopsis This document defines requirements for recording, analysing and reporting safety-related defects on rail vehicles, their components, systems, subsystems and related

More information

TRANSPORT, INFRASTRUCTURE AND CLIMATE CHANGE COMMITTEE AGENDA. 15th Meeting, 2008 (Session 3) Tuesday 24 June 2008

TRANSPORT, INFRASTRUCTURE AND CLIMATE CHANGE COMMITTEE AGENDA. 15th Meeting, 2008 (Session 3) Tuesday 24 June 2008 TIC/S3/08/15/A TRANSPORT, INFRASTRUCTURE AND CLIMATE CHANGE COMMITTEE AGENDA 15th Meeting, 2008 (Session 3) Tuesday 24 June 2008 The Committee will meet at 2.00 pm in Committee Room 4 to consider the following

More information

Signals passed at danger (SPADs) A summary of the rail industry s approach to risk reduction

Signals passed at danger (SPADs) A summary of the rail industry s approach to risk reduction Signals passed at danger (SPADs) A summary of the rail industry s approach to risk reduction 2 RSSB l Signals passed at danger (SPADs) Introduction A signal passed at danger or SPAD occurs when a train

More information

NHS DORSET CLINICAL COMMISSIONING GROUP GOVERNING BODY MEETING ORGANISATIONAL DEVELOPMENT FRAMEWORK UPDATE 2018/2019

NHS DORSET CLINICAL COMMISSIONING GROUP GOVERNING BODY MEETING ORGANISATIONAL DEVELOPMENT FRAMEWORK UPDATE 2018/2019 NHS DORSET CLINICAL COMMISSIONING GROUP GOVERNING BODY MEETING ORGANISATIONAL DEVELOPMENT FRAMEWORK UPDATE 2018/2019 Date of the meeting 14/11/2018 Author Sponsoring Board member Purpose of Report Recommendation

More information

Managing Human Factors in the Signalling Programme

Managing Human Factors in the Signalling Programme Managing Human Factors in the Signalling Programme The latest development in the work of the Human Components Mapping Dr. Amanda C. Elliott Safety Team Banedanmark Presentation Outline Overall aim: To

More information

ATOC Guidance Note Competence of Train Operator Liaison Officers (TOLOs)

ATOC Guidance Note Competence of Train Operator Liaison Officers (TOLOs) Document comes into force Supersedes ATOCGN016 Iss 1 as of ATOC Guidance Note Competence of Train Operator Liaison Officers (TOLOs) Synopsis This Guide sets out recommended criteria for ensuring the competence

More information

Great Western Route Modernisation Industry Systems Integration

Great Western Route Modernisation Industry Systems Integration Great Western Route Modernisation Industry Systems Integration The Railway as a System Tim Coffey 6-Oct-15 / 1 European Railway Benchmarking Passenger Safety Public Safety 6-Oct-15 / 2 UK is the fastest

More information

1.5 Model based Conceptual Design

1.5 Model based Conceptual Design Model based Conceptual Design Working Group (MBCD WG) Charter 1 Overview 1.1 Purpose The purpose of this working group is to advance the body of knowledge and practice of systems engineering (SE) through

More information

Issue 2 8 November Job number

Issue 2 8 November Job number Network Rail and Office of Rail Regulation AO/036: Review of Network Rail VTISM modelling and allocation to market segments for Freight Avoidable Costs 223767-09-04-05 Issue 2 8 November 2012 This report

More information

The changing face of London and Southeast Railway Architecture. Tony Ramanathan Systems Design Engineer Network Rail

The changing face of London and Southeast Railway Architecture. Tony Ramanathan Systems Design Engineer Network Rail The changing face of London and Southeast Railway Architecture Tony Ramanathan Systems Design Engineer Network Rail 1 Agenda What are the drivers Network Rail mandate Network Rail Project Governance (GRIP)

More information

HS2 Skills & Capability

HS2 Skills & Capability HS2 Skills & Capability Agenda 1. Welcome 2. HS2 skills & capability context 3. Thought Leader: Gil Howarth, NSARE 4. Back to the Future: Year 2026 exercise 5. Close 2012 2013 2014 2015 2016 2017 2018

More information

ATOC. ATOC Operational Resilience & Security Forum Competency Assessment of Station Incident Officers (SIOs)

ATOC. ATOC Operational Resilience & Security Forum Competency Assessment of Station Incident Officers (SIOs) Date: January 2010 ATOC Association of Train Operating Companies ATOC Operational Resilience & Security Forum Competency Assessment of Station Incident Officers (SIOs) Synopsis This Guide sets out recommended

More information

Call For Research. Understanding Adhesion Forecasting. 11 June 2018

Call For Research. Understanding Adhesion Forecasting. 11 June 2018 Call For Research Understanding Adhesion Forecasting 11 June 2018 1 The Rail Safety and Standards Board (RSSB) is making up to 300,000 available for feasibility studies to identify data-driven solutions

More information

PASSENGER TRANSPORT SERVICE OPERATIONS Driver - Bus, Coach and Rail Level 2 Assessment Plan

PASSENGER TRANSPORT SERVICE OPERATIONS Driver - Bus, Coach and Rail Level 2 Assessment Plan PASSENGER TRANSPORT SERVICE OPERATIONS Driver - Bus, Coach and Rail Level 2 Assessment Plan 1 of 15 TABLE OF CONTENTS 1. Introduction Page 3 2. Structured Learning (Journey Log) Page 4 3. Readiness for

More information

QUALIFICATION HANDBOOK

QUALIFICATION HANDBOOK QUALIFICATION HANDBOOK Level 4 NVQ Diploma in Spectator Safety Management (6852-04) October 2011 Version 1.0 Qualification at a glance Subject area City & Guilds number 6852 Spectator Safety Age group

More information

Appendix 1 METROPOLITAN POLICE AUTHORITY AND METROPOLITAN POLICE SERVICE COMMUNITY ENGAGEMENT STRATEGY

Appendix 1 METROPOLITAN POLICE AUTHORITY AND METROPOLITAN POLICE SERVICE COMMUNITY ENGAGEMENT STRATEGY Appendix 1 METROPOLITAN POLICE AUTHORITY AND METROPOLITAN POLICE SERVICE COMMUNITY ENGAGEMENT STRATEGY 2006-2009 1. Preface Historically, community engagement has tended to be seen as a means for securing

More information

Leading Health and Safety on Britain s Railway. A strategy for working together Issue 2 May 2017 TICKET OFFICE

Leading Health and Safety on Britain s Railway. A strategy for working together Issue 2 May 2017 TICKET OFFICE TICKET OFFICE zzz Leading Health and Safety on Britain s Railway A strategy for working together Issue 2 May 2017 1 1 Foreword Britain s railway system is one of the safest and most intensively used rail

More information

Self Directed Support

Self Directed Support Appendix 1 Self Directed Support 1.0 Introduction Fife's Self Directed Support (SDS) Strategy Final Revised Draft 1.1 This document sets out the key elements of Fife Council s SDS Strategy, including current

More information

ARRANGEMENTS FOR JOINT OECD- UNDP SUPPORT TO THE GLOBAL PARTNERSHIP FOR EFFECTIVE DEVELOPMENT CO- OPERATION

ARRANGEMENTS FOR JOINT OECD- UNDP SUPPORT TO THE GLOBAL PARTNERSHIP FOR EFFECTIVE DEVELOPMENT CO- OPERATION ARRANGEMENTS FOR JOINT OECD- SUPPORT TO THE GLOBAL PARTNERSHIP FOR EFFECTIVE DEVELOPMENT CO- OPERATION Overview of support activities and remaining resource requirements for 2013-14 January 2013 This note

More information

REAP 1. BACKGROUND 2. CONTEXT

REAP 1. BACKGROUND 2. CONTEXT REAP RETAILERS ENVIRONMENTAL ACTION PROGRAMME TERMS OF REFERENCE 1. BACKGROUND The key challenges addressed by the EU Action Plan on Sustainable Consumption and Production (SCP) are to improve the overall

More information

A guide to RSSB research in. Sustainable development

A guide to RSSB research in. Sustainable development Sustainable development A guide to RSSB research in Sustainable development September 2010 Sustainable development research RSSB Copyright 2010. This publication may be reproduced free of charge for research,

More information

HIGHLAND COUNCIL/NHS HIGHLAND LEADERSHIP AND PERFORMANCE GROUP HIGHLAND COUNCIL. Mrs M Davidson Mr D Hendry Mr J Gray Mr A B Dodds (AD)

HIGHLAND COUNCIL/NHS HIGHLAND LEADERSHIP AND PERFORMANCE GROUP HIGHLAND COUNCIL. Mrs M Davidson Mr D Hendry Mr J Gray Mr A B Dodds (AD) DRAFTHighland NHS Board 6 December 2011 Item 3.12 HIGHLAND COUNCIL/NHS HIGHLAND LEADERSHIP AND PERFORMANCE GROUP Minutes of the Meeting of the Highland Council/NHS Highland Leadership and Performance Group

More information

TAP TSI Update and Masterplanning. Brussels 26 January TAF/ TAP Masterplanning kick-off 1

TAP TSI Update and Masterplanning. Brussels 26 January TAF/ TAP Masterplanning kick-off 1 TAP TSI Update and Masterplanning TAF/ TAP Masterplanning Kick-off Brussels TAF/ TAP Masterplanning kick-off 1 Contents 1. General update on TAP TSI 2. Overall TAP TSI masterplanning approach 3. Focus

More information

CAPABILITY MATRIX FOR PROFESSIONAL STAFF HANDBOOK

CAPABILITY MATRIX FOR PROFESSIONAL STAFF HANDBOOK CAPABILITY MATRIX FOR PROFESSIONAL STAFF HANDBOOK INTRODUCTION TO THE CAPABILITY MATRIX This handbook is intended to help you understand the Capability Matrix and how it will be used at UoN. The Capability

More information

moving ToWards sustainable mobility

moving ToWards sustainable mobility moving ToWards sustainable mobility A STRATEGY FOR 2030 AND BEYOND FOR THE EUROPEAN RAILWAY SECTOR Summary UIC, the international railway association which celebrates its 90th anniversary in 2012, counts

More information

Consultation response. February 2014

Consultation response. February 2014 Department for Transport National road and rail networks: draft national policy statement Consultation response pteg Support Unit Wellington House 40-50 Wellington Street Leeds LS1 2DE 0113 251 7445 info@pteg.net

More information

ATOC. Approved Code of Practice Train Driving Traction Knowledge. Contents. Withdrawn Document. Association of Train Operating Companies

ATOC. Approved Code of Practice Train Driving Traction Knowledge. Contents. Withdrawn Document. Association of Train Operating Companies Uncontrolled When ATOC PrintedApproved Code of Practice ATOC Association of Train Operating Companies Approved Code of Practice Train Submitted by Signatures removed from electronic version Steve Bence

More information

Interim Review of the Public Engagement with Research Catalysts Programme 2012 to 2015

Interim Review of the Public Engagement with Research Catalysts Programme 2012 to 2015 Interim Review of the Public Engagement with Research Catalysts Programme 2012 to 2015 A report for Research Councils UK March 2016 SUMMARY Report author: Ruth Townsley, Independent Researcher 1. The Public

More information

ATOC. Approved Code of Practice Approvals process for GSM-R Cab Mobile Fitment. Issue 2-8 th November Uncontrolled When Printed

ATOC. Approved Code of Practice Approvals process for GSM-R Cab Mobile Fitment. Issue 2-8 th November Uncontrolled When Printed ATOC ATOC Approved Code of Practice ACOP/EC/01009 Association of Train Operating Companies Issue 2-8 th November 2010 Approved Code of Practice Approvals process for GSM-R Cab Mobile Fitment Synopsis To

More information

National Commissioning Board. Leading Integrated and Collaborative Commissioning A Practice Guide

National Commissioning Board. Leading Integrated and Collaborative Commissioning A Practice Guide National Commissioning Board Leading Integrated and Collaborative Commissioning A Practice Guide March 2017 Introduction The short practical guide is intended to stimulate commissioners and other senior

More information

This short presentation provides a summary of work being undertaken in delivering our annual TRICS data collection programme.

This short presentation provides a summary of work being undertaken in delivering our annual TRICS data collection programme. This short presentation provides a summary of work being undertaken in delivering our annual TRICS data collection programme. 1 The TRICS Consortium are pleased to announce that the 2012 TRICS data collection

More information

Strategic Objectives and Organisational Behaviours Report for the AWP NHS Trust Board Meeting Time: 12:00

Strategic Objectives and Organisational Behaviours Report for the AWP NHS Trust Board Meeting Time: 12:00 Meeting Date: 2012-07-25 Strategic Objectives and Organisational Behaviours Report for the AWP NHS Trust Board Meeting Time: 12:00 Agenda Item: 15 Serial: 12.0635 This Report is presented by the Chief

More information

IFE Level 4 Certificate in Fire Science and Fire Safety (HL)

IFE Level 4 Certificate in Fire Science and Fire Safety (HL) IFE Level 4 Certificate in Fire Science and Fire Safety (HL) Unit 3: Fire Service Operations and Incident Command Unit Reference Number: H/505/5933 Introduction This unit focuses on the strategies and

More information

JOB DESCRIPTION. Service Line Manager for [one of Education/Research/Business/Infrastructure] Job Family/Level: Professional Services, level 6

JOB DESCRIPTION. Service Line Manager for [one of Education/Research/Business/Infrastructure] Job Family/Level: Professional Services, level 6 JOB DESCRIPTION Job Title: Department/Division/Faculty: Campus location: Service Line Manager for [one of Education/Research/Business/Infrastructure] ICT (Information and Communication Technologies), South

More information

GREATER MANCHESTER HEALTH AND SOCIAL CARE STRATEGIC PARTNERSHIP BOARD EXECUTIVE. Establishing Leadership and Accountability in Shadow Form

GREATER MANCHESTER HEALTH AND SOCIAL CARE STRATEGIC PARTNERSHIP BOARD EXECUTIVE. Establishing Leadership and Accountability in Shadow Form 5a GREATER MANCHESTER HEALTH AND SOCIAL CARE STRATEGIC PARTNERSHIP BOARD EXECUTIVE Date: 13 th November 2015 Subject: Report of: Establishing Leadership and Accountability in Shadow Form Liz Treacy PURPOSE

More information

Infrastructure Standards Committee / Industry Standards Coordination Committee DATE: 6 January 2015 / 21 January 2015 SUBJECT:

Infrastructure Standards Committee / Industry Standards Coordination Committee DATE: 6 January 2015 / 21 January 2015 SUBJECT: MEETING: Infrastructure Standards Committee / Industry Standards Coordination Committee DATE: 6 January 2015 / 21 January 2015 SUBJECT: SPONSOR: AUTHOR: Agenda item 2.6 TSI / RGS / Network Rail initial

More information