WECC Guideline 2019 Base Case Compilation Schedule Date: January 16, 2018
|
|
- Holly Wright
- 5 years ago
- Views:
Transcription
1 WECC Guideline 2019 Base Case Compilation Schedule Date: January 16, 2018 Introduction The Data Subcommittee compiles eleven steady state and dynamic base cases (base cases) to meet WECC s requirements to compile interconnection-wide base cases. The 2019 Base Case Compilation Schedule provides base case descriptions and a schedule for base cases to be compiled during the 2019 calendar year. Objectives The objectives of the 2019 Base Case Compilation Schedule are: I. Provide a detailed schedule, to appropriate stakeholders, identifying necessary data submittals and data review milestones to compile eleven bases cases. Identify bases cases to be compiled. A typical annual base case compilation schedule includes the following base cases: a. Five operating cases b. Two specialized cases c. One 5-year summer planning case d. One 5-year winter planning case e. One 10-year summer planning case f. One 10-year winter planning case Supporting Information Timely submittal of steady state and dynamics data is necessary for the 2019 Base Case Compilation Schedule to be maintained. In the event of delayed steady state and dynamic data submittals, the Data Subcommittee will follow the Late Data Procedure provided in the WECC Data Preparation Manual. Typical base cases are intended to model anticipated load levels, but in some instances may model slightly heavier or slightly lighter than anticipated load levels to achieve desired stressed transfer levels on designated paths. Typical base cases usually include operating cases, five-year cases, ten-year cases, and additional cases as requested by the RAC membership. Specialized base cases are intended to represent critical operating conditions such as severe weather events, equipment out of service (transmission lines, reactive devices, or static var compensators), unusual generation patterns due to forced outages, and insecure voltage conditions. Some cases may represent extreme load conditions (up to 105 percent of forecasted peak) in a particular sub-region. Data submitters should not be reluctant to model a condition due to lack of historical record of the specialized case actually occurring. WESTERN ELECTRICITY COORDINATING COUNCIL 155 North 400 West, Suite 200 Salt Lake City, Utah
2 2018 Base Case Compilation Schedule 2 The 2019 Base Case Compilation Schedule uses one of the specialized case slots for the NERC required Light Spring Operations case. Since a Light Spring Operations case is now a NERC requirement, it is likely that the DS will approve the Light Spring Operations case to replace the Heavy Spring Operations case in the Base Case Compilation Schedule moving forward. If this occurs, when less than two specialized cases are DS approved for a given schedule, a Heavy Spring case will be automatically added to a Specialized slot. The 2019 Base Case Compilation Schedule includes the following base cases: Typical base cases o Operating base cases Heavy Winter Light Winter 2020 Heavy Spring 2020 Heavy Summer 2020 Light Summer o Five-year base cases 2025 Heavy Summer Heavy Winter o Ten-year base cases Heavy Winter 2030 Heavy Summer Specialized base case o 2030 Light Spring with mid-day load and high renewable generation o 2020 Light Spring-NERC required Light Spring Operating case Generation and load levels referred to in the base case description sheets refer to the season being studied. For example, if a case description sheet for a winter base case calls for high hydro in a specific area, this means high levels of hydro generation for a winter condition. In some areas, a high level of hydro generation in the winter may be less than median hydro generation levels in the spring or summer. Also, light loads may be increased in the importing areas or heavy loads may be decreased in exporting areas to represent the desired interchange schedules. Renewable generation, when specified, should be based on individual entities Renewable Portfolio Standard. Specific information on the desired load levels is contained in the base case description sheets and should be used as a W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
3 2018 Base Case Compilation Schedule 3 guide in preparing cases. All loads are coincident unless indicated otherwise. Specified time supersedes specified percentage of load. Interchange Schedules in the base case description sheets refer to the target flows that should be reached to represent anticipated flow levels and direction for the season being studied. Targets may be altered as anticipated operating conditions become more clearly known. Where no target flows are specified actual scheduled transfers should be based on each area s load and generation (deficiency/surplus) balance and economical generation dispatch. The purpose of the case should be kept in mind and schedules should be coordinated between areas prior to data submittal. Only corrections to the Master Dynamics File (MDF) or new data for the MDF need be submitted for each case build. During the process of compiling each base case, WECC staff and the appropriate functional entities participating in base case compilation process should follow the data requirements and procedures outlined in the WECC Data Preparation Manual. Following the documented requirements and procedures will contribute to developing base cases with compatible steady state and dynamic data, help to ensure the Interconnection-wide Model is adequately modeled, and aid in continual improvement in the accuracy of the data submitted. W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
4 2018 Base Case Compilation Schedule CASE LSP1-S DATE DATA REQUEST MAILED DATE DATA DUE TO DATA SUBMITTER DATE DATA DUE TO WECC STAFF WECC STAFF SEND CASE FOR REVIEW DATE COMMENTS DUE TO DATA SUBMITTER DATE DATA SUBMITTER COMMENTS DUE TO WECC STAFF WECC STAFF FINALIZE DATE 05/25/18 06/22/18 07/20/18 08/17/18 08/24/18 08/31/18 09/14/ HW1 07/06/18 08/03/18 08/31/18 09/28/ /05/ /19/ /2/ HS HSP1-S 10/05/18 11/02/18 11/30/18 12/28/18 1/04/19 1/11/19 02/25/19 CASE HW3-OP LW1-OP 2020 HSP1-OP 2020 LSP1-S DATE DATA REQUEST MAILED DATE DATA DUE TO DATA SUBMITTER 2 DATE DATA DUE TO WECC STAFF WECC STAFF SEND CASE FOR REVIEW DATE COMMENTS DUE TO DATA SUBMITTER DATE DATA SUBMITTER COMMENTS DUE TO WECC STAFF WECC STAFF FINALIZE DATE 11/16/18 12/14/18 01/11/19 02/8/19 02/22/19 03/08/19 03/22/19 01/4/19 02/1/19 03/1/19 03/29/19 04/12/19 04/26/19 05/10/ Case Schedule 2 Data provided to the Data Submitter is expected to include topology corrections common to the set of cases being developed, project files for the out year case (if applicable), and a load, generation and voltage profile for each case. 4
5 HW HS2 02/22/19 03/22/19 04/19/19 05/17/19 05/31/19 06/14/19 06/28/ HS3-OP 2020 LS1-OP HW1 04/12/19 05/10/19 06/07/19 07/05/19 07/19/ /19 08/16/ HS1 5/31/19 06/28/19 07/26/19 08/23/ /06/ /20/ /04/ LSP1-S 07/19/19 08/16/19 09/13/19 10/11/19 10/18/19 10/25/19 11/08/19 5
6 HEAVY WINTER 20 HW3-OP I. CASE DUE DATES: To Data Submitter: December 14, 2018 To WECC Staff: January 11, 2019 PURPOSE: OPERATING CASE TO REPRESENT ANTICIPATED OPERATING CONDITIONS WITH HEAVY FLOWS FROM NORTHWEST TO CALIFORNIA. I ITEMS TO BE PREPARED: From Case HW3 Operating Case IV. LOADS: Expected peak load for the months of December - February V. TIME: hours MST VI. GENERATION HYDRO THERMAL RENEWABLE Canada High/Median Northwest High/Median High -- Idaho/Montana Median High -- Colorado/Wyoming Low High -- Northern California Hydro Median Northern California Low High -- Southern California Low High -- Arizona/New Mexico/Southern Nevada Low High -- V INTERCHANGE CONDITION TARGET % RATING Northwest to British Columbia (Path 3) Moderate % COI (Path 66) Moderate % PDCI (Path 65) Heavy % Idaho to Northwest (Path 14) Montana to Northwest (Path 8) Moderate % Southwest to Calif. (EOR Path 49/WOR Path 46) Moderate 4000/ %/47% Intermountain to Adelanto DC (Path 27) Heavy % San Diego to CFE (Path 45) % Northern to Southern California (Path 26) Heavy % 1 Minimum flows are required to represent the Canadian Entitlement. 6
7 LIGHT WINTER 20LW1-OP I. CASE DUE DATES: To Data Submitter: December 14, 2018 To WECC Staff: January 11, 2019 PURPOSE: OPERATING CASE TO REPRESENT ANTICIPATED OPERATING CONDITIONS DURING LIGHT LOAD PERIODS. I ITEMS TO BE PREPARED: From Case HW3 Operating Case IV. LOADS: Expected minimum load for the months of December - February V. TIME: Early morning (0300 to 0500 hours MST), winter conditions. VI. GENERATION HYDRO THERMAL RENEWABLE Canada Median/Low Northwest Low Median/Low -- Idaho/Montana Median Median -- Colorado/Wyoming Low Median -- Northern California Hydro Median Northern California Low Median -- Southern California -- Median -- Arizona/New Mexico/Southern Nevada -- Median -- V INTERCHANGE CONDITION TARGET % RATING Northwest to British Columbia (Path 3) Moderate % COI (Path 66) Low 0/ % PDCI (Path 65) Low 0/ % Midway Los Banos S-N (Path 15) Moderate % Idaho to Northwest (Path 14) Moderate > % Montana to Northwest (Path 8) Heavy % Southwest to Calif. (EOR Path 49/WOR Path 46) Moderate 5100/ %/65% Intermountain to Adelanto DC (Path 27) Moderate % San Diego to CFE (Path 45) Low 60 15% Northern to Southern California (Path 26) Low % (S-N) 1 Minimum flows are required to represent the Canadian Entitlement. 7
8 2020 HEAVY SPRING 20HSP1-OP I. CASE DUE DATES: To Data Submitter: February 1, 2019 To WECC Staff: March 1, 2019 PURPOSE: OPERATING CASE TO REPRESENT ANTICIPATED OPERATING CONDITIONS WITH HIGH FLOWS FROM NORTHWEST TO CALIFORNIA. I ITEMS TO BE PREPARED: From Case 19 HSP1P Operating Case IV. LOADS: Expected peak load for the months of March - May V. TIME: 1600 to 2000 hours MDT. VI. GENERATION HYDRO THERMAL RENEWABLE Canada Median Northwest High Low -- Idaho/Montana High Median -- Colorado/Wyoming Median Median -- Northern California Hydro Median Northern California High Low -- Southern California Arizona/New Mexico/Southern Nevada Median Median -- V INTERCHANGE CONDITION TARGET % RATING Northwest to British Columbia (Path 3) Moderate % COI (Path 66) Maximum % PDCI (Path 65) Moderate % Idaho to Northwest (Path 14) Low % Montana to Northwest (Path 8) Moderate % Southwest to Calif. (EOR Path 49/WOR Path 46) Low 3600/ %/43% Intermountain to Adelanto DC (Path 27) Heavy % San Diego to CFE (Path 45) Low 60 15% Northern to Southern California (Path 26) Heavy % 1 Minimum flows are required to represent the Canadian Entitlement. 8
9 2020 LIGHT SPRING 20LSP1-S I. CASE DUE DATES: To Data Submitter: February 1, 2019 To WECC Staff: March 1, 2019 I PURPOSE: SPECIALIZED CASE TO REPRESENT ANTICIPATED OPERATING CONDITIONS DURING LIGHT LOAD PERIODS. IV. ITEMS TO BE PREPARED: From Case 19 HSP1 Operating Case V. LOADS: Expected minimum load for the months of March-May VI. TIME: 0300 to 0500 MDT V GENERATION HYDRO THERMAL RENEWABLE Canada -- Northwest -- Idaho/Montana -- Colorado/Wyoming -- Northern California Hydro -- Northern California -- Southern California -- Arizona/New Mexico/Southern Nevada -- VI INTERCHANGE CONDITION TARGET % RATING Northwest to British Columbia (Path 3) Moderate % COI (Path 66) PDCI (Path 65) Idaho to Northwest (Path 14) Montana to Northwest (Path 8) Southwest to Calif. (EOR Path 49/WOR Path 46) -- --/-- --/-- Intermountain to Adelanto DC (Path 27) San Diego to CFE (Path 45) Northern to Southern California (Path 26) *RMR Reliability Must Run 1 Minimum flows are required to represent the Canadian Entitlement. 9
10 HEAVY WINTER 25HW2 I. CASE DUE DATES: To Data Submitter: March 22, 2019 To WECC Staff: April 19, 2019 PURPOSE: GENERAL 5-YEAR CASE - WITH TYPICAL FLOWS THROUGHOUT WECC. I ITEMS TO BE PREPARED: From Case HW2 IV. LOADS: Expected peak load for the months of December - February V. TIME: hours MST VI. GENERATION HYDRO THERMAL RENEWABLE Canada High Northwest High High -- Idaho/Montana Median High -- Colorado/Wyoming Low High -- Northern California Hydro Median Northern California Low Median -- Southern California Low Median -- Arizona/New Mexico/Southern Nevada Low Median -- V INTERCHANGE CONDITION TARGET % RATING Northwest to British Columbia (Path 3) Moderate % COI (Path 66) PDCI (Path 65) Idaho to Northwest (Path 14) Montana to Northwest (Path 8) Southwest to Calif. (EOR Path 49/WOR Path 46) -- --/-- --/-- Intermountain to Adelanto DC (Path 27) San Diego to CFE (Path 45) Northern to Southern California (Path 26) Minimum flows are required to represent the Canadian Entitlement. 10
11 2025 HEAVY SUMMER 25HS2 I. CASE DUE DATES: To Data Submitter: March 22, 2019 To WECC Staff: April 19, 2019 PURPOSE: GENERAL 5-YEAR CASE WITH TYPICAL FLOWS THROUGHOUT WECC. I ITEMS TO BE PREPARED: From Case HW2 IV. LOADS: Expected peak load for the months of June - August V. TIME: 1500 to 1700 hours MDT VI. GENERATION HYDRO THERMAL RENEWABLE Canada High Northwest Median High -- Idaho/Montana Median High -- Colorado/Wyoming Low High -- Northern California Hydro High Northern California High High -- Southern California Low High -- Arizona/New Mexico/Southern Nevada Low High -- V INTERCHANGE CONDITION TARGET % RATING Northwest to British Columbia (Path 3) Moderate < % COI (Path 66) PDCI (Path 65) Idaho to Northwest (Path 14) Montana to Northwest (Path 8) Southwest to Calif. (EOR Path 49/WOR Path 46) -- --/-- --/-- Intermountain to Adelanto DC (Path 27) San Diego to CFE (Path 45) Northern to Southern California (Path 26)
12 2020 HEAVY SUMMER 20HS3-OP I. CASE DUE DATES: To Data Submitter: May 10, 2019 To WECC Staff: June 7, 2019 PURPOSE: OPERATING CASE TO REPRESENT ANTICIPATED OPERATING CONDITIONS WITH HEAVY FLOWS TO CALIFORNIA FROM THE NORTHWEST AND MODERATE FLOWS ELSEWHERE. I ITEMS TO BE PREPARED: From Case 19 HS3-Operating Case IV. LOADS: Expected peak load for the months of June - August V. TIME: Peak time 1500 to 1700 hours MDT VI. GENERATION HYDRO THERMAL RENEWABLE Canada High Northwest Median/High High -- Idaho/Montana Median High -- Colorado/Wyoming Low High -- Northern California Hydro High Northern California High High -- Southern California Low High -- Arizona/New Mexico/Southern Nevada Low High -- V INTERCHANGE CONDITION TARGET % RATING Northwest to British Columbia (Path 3) Heavy % COI (Path 66) Heavy % PDCI (Path 65) Moderate % Idaho to Northwest (Path 14) Light Montana to Northwest (Path 8) Moderate % Southwest to Calif. (EOR Path 49/WOR Path 46) Low/Moderate 3000/ %/57% Intermountain to Adelanto DC (Path 27) Heavy % San Diego to CFE (Path 45) Low % Northern to Southern California (Path 26) Heavy % 12
13 2020 LIGHT SUMMER 20LS1-OP I. CASE DUE DATES: To Data Submitter: May 10, 2019 To WECC Staff: June 7, 2019 PURPOSE: OPERATING CASE TO REPRESENT ANTICIPATED OPERATING CONDITIONS DURING LIGHT LOAD PERIODS. MODERATE FLOWS FROM THE NORTHWEST TO CALIFORNIA AND MODERATE TO HEAVY FLOWS FROM IDAHO/MONTANA TO THE NORTHWEST. I ITEMS TO BE PREPARED: From Case 19 HS3-Operating Case IV. LOADS: Expected minimum load for the months of June - August V. TIME: 0400 to 0600 hours MDT VI. GENERATION HYDRO THERMAL RENEWABLE Canada Median Northwest Median Idaho/Montana Median High -- Colorado/Wyoming Median Median -- Northern California Hydro Median Northern California -- High -- Southern California Arizona/New Mexico/Southern Nevada V INTERCHANGE CONDITION TARGET % RATING Northwest to British Columbia (Path 3) Moderate % COI (Path 66) Heavy % PDCI (Path 65) Moderate % Idaho to Northwest (Path 14) Low % Montana to Northwest (Path 8) Maximum % Southwest to Calif. (EOR Path 49/WOR Path 46) Moderate 4600/ %/55% Intermountain to Adelanto DC (Path 27) Moderate % San Diego to CFE (Path 45) Northern to Southern California (Path 26) Moderate % 13
14 HEAVY WINTER 30HW1 I. CASE DUE DATES: To Data Submitter: June 28, 2019 To WECC Staff: July 26, 2019 I PURPOSE: GENERAL 10-YEAR CASE WITH TYPICAL FLOWS THROUGHOUT WECC. RESOURCE AND TRANSMISSION REPRESENTATION COORDINATED WITH THE REGIONAL PLANNING GROUPS (RPGs) IN WHOSE FOOTPRINT YOUR ENTITY FALLS. IV. ITEMS TO BE PREPARED: From Case HW1 V. LOADS: Expected peak load for the months of December - February VI. V TIME: 1800 to 2000 hours MST GENERATION: Ensure that your entity s resource planner is consulted concerning the resources being represented in this power flow base case. VI HYDRO THERMAL RENEWABLE Canada High Northwest High High -- Idaho/Montana Median High -- Colorado/Wyoming Low High -- Northern California Hydro Median Northern California Low Median -- Southern California Low Median -- Arizona/New Mexico/Southern Nevada Low Median -- IX. INTERCHANGE CONDITION TARGET % RATING Northwest to British Columbia (Path 3) Moderate % COI (Path 66) PDCI (Path 65) Idaho to Northwest (Path 14) Montana to Northwest (Path 8) Southwest to Calif. (EOR Path 49/WOR Path 46) -- --/-- --/-- Intermountain to Adelanto DC (Path 27) San Diego to CFE (Path 45) Northern to Southern California (Path 26) Minimum flows are required to represent the Canadian Entitlement. 14
15 2030 HEAVY SUMMER 30HS1 I. CASE DUE DATES: To Data Submitter: June 28, 2019 To WECC Staff: July 26, 2019 I PURPOSE: GENERAL 10-YEAR CASE WITH TYPICAL FLOWS THROUGHOUT WECC. RESOURCE AND TRANSMISSION REPRESENTATION COORDINATED WITH THE REGIONAL PLANNING GROUPS (RPGs) IN WHOSE FOOTPRINT YOUR ENTITY FALLS. IV. ITEMS TO BE PREPARED: From Case HW1 V. LOADS: Expected peak load for the months of June - August VI. V TIME: 1500 to 1700 hours MDT GENERATION: Ensure that your entity s resource planner is consulted concerning the resources being represented in this power flow base case. VI HYDRO THERMAL RENEWABLE Canada High Northwest Median High -- Idaho/Montana Median High -- Colorado/Wyoming Low High -- Northern California Hydro High Northern California High High -- Southern California Low High -- Arizona/New Mexico/Southern Nevada Low High -- IX. INTERCHANGE CONDITION TARGET % RATING Northwest to British Columbia (Path 3) Moderate < % COI (Path 66) PDCI (Path 65) Idaho to Northwest (Path 14) Montana to Northwest (Path 8) Southwest to Calif. (EOR Path 49/WOR Path 46) -- --/-- --/-- Intermountain to Adelanto DC (Path 27) San Diego to CFE (Path 45) Northern to Southern California (Path 26)
16 2030 LIGHT SPRING 30LSP1-S X. CASE DUE DATES: To Data Submitter: August 16th, 2019 To WECC Staff: September, 2019 I. PURPOSE: Model light-load conditions with solar and wind serving a significant but realistic portion of the WECC total load. The case should only include renewable resource capacity additions that are already planned and included in the 10-year future, and represent likely and expected system conditions consistent with any applicable and enacted public policy requirements. ITEMS TO BE PREPARED: From Case 2028 LSP1 1 I IV. LOADS 2 : Target 60-65% of peak summer loads that would occur during the spring months of March, April, and May. TIME: 1000 to 1400 hours MDT. The time of day has been determined from the data gathered from the latest WECC Production Cost Model. The model uncovered periods of high renewables when loads were approximately 60-65% of WECC peak. The time was chosen to try and capture solar as well as wind generation. V. GENERATION HYDRO THERMAL RENEWABLE 3 Wind and solar generation targets were developed by analysis of the WECC Common Case Production Cost Model, which utilizes historical weather data for its renewable generation profiles. The data was evaluated to find instances of off-peak loading and high renewable generation. Data was filtered to find wind and solar dispatch consistent with the average of the top 10% of generation hours during the chosen time period when loads were between 60-65% of the WECC peak. Target renewable capacity values by powerflow area will be provided. Thermal generation should be adjusted to accommodate the higher renewable dispatch conditions. VI. INTERCHANGE CONDITION TARGET % RATING No Specific Targets NOTE: Where no target flows are specified actual scheduled transfers should be based on each area s load and generation (deficiency/surplus) balance and economical generation dispatch. The objective of the case should be kept in mind and schedules should be coordinated between areas prior to data submittal. 1 Only Corrections to the MDF or new data for the MDF need be submitted. 2 All loads are coincident unless indicated otherwise. Specified time supersedes specified percentage of load. 3 Renewables should be based on individual entities Renewable Portfolio Standard. 16
17 WECC BASE CASES LISTED BY YEAR OF COMPILATION (i.e. 18 = 2018 COMPILED BASE CASE) Winter Cases Identified by the second year of case (e.g. 19 for HW) WINTER SPRING SUMMER AUTUMN Year Light Heavy Light Heavy Light Heavy Light Heavy OP 08G, 13OP 13OP 13OP 03, 07S, 09S, 13OP 09S S, 14OP 04, 09G, 14OP OP 08S, 10G, 15OP S, 16OP 06, 11G, 16OP OP 10S, 12G, 17OP OP 08G, 13G, 18OP OP 14G, 17S, 19OP 14OP 14OP 06S, 09G, 12S, 14OP 12S 15OP 15OP 05, 10G, 15OP 14S, 16S 16OP 16OP 11G, 16OP 09S, 17OP 17OP 07G, 12G, 15S, 17OP 18S 18OP 18OP 08G, 13G, 18OP 19OP 19OP 19OP 09G, 14G, 19OP G 17S 10G, 15G 10S 16S 11S G, 16G 12S 11S 16G G 12G, 17G G, 18G 13S, 18G G, 19G 14G, 19G G 15G G 16G G 17G G 18S 18G G 19G 19G S - Scenario Case (2) G - General/Planning Case (4) OP - Operating/OTC Case (5) V - Validation Case (placeholder) Current Compilation Schedule Proposed Cases 17
WECC Guideline 2018 Base Case Compilation Schedule Date: DRAFT
WECC Guideline 2018 Base Case Compilation Schedule Date: DRAFT Introduction The Data Subcommittee compiles eleven steady state and dynamic base cases (base cases) to meet WECC s requirements to compile
More informationWECC Guideline 2016 Base Case Compilation Schedule Date: TSS Approved Meeting 170
WECC Guideline 2016 Base Case Compilation Schedule Date: TSS Approved Meeting 170 Introduction The System Review Work Group (SRWG) compiles eleven steady state and dynamic base cases (base cases) to meet
More informationCOLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN
COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN January 11, 2018 ColumbiaGrid 8338 NE Alderwood Road, Suite 140 Portland, OR 97220 www.columbiagrid.org (503) 943-4940 8338 NE Alderwood Road, Suite
More informationNORTHERN TIER TRANSMISSION GROUP (NTTG) BIENNIAL TRANSMISSION PLAN. DRAFT SUMMARY REPORT - January 2013
NORTHERN TIER TRANSMISSION GROUP (NTTG) 2012-2013 BIENNIAL TRANSMISSION PLAN DRAFT SUMMARY REPORT - January 2013 Executive Summary: This report summarizes the findings of power flow studies to determine:
More information2017 Study Program PC02: High Wind
2017 Study Program PC02: High Wind Bhavana Katyal 2 PC02: Modeling Logic Production Cost Model Scope Scope Key Questions Assumptions Increased Wind Generation Results Generation Mix/ Curtailment Dump Energy
More informationLoads and Resources Methods and Assumptions
Loads and Resources Methods and Assumptions WECC Staff September 2014 155 North 400 West, Suite 200 Salt Lake City, Utah 84103-1114 Loads and Resources Methods and Assumptions ii Contents Purpose... 1
More informationTable of Contents. To provide a methodology for determining the System Operating Limits (SOL) for the Planning Horizon at the California ISO.
Table of Contents Purpose... 1 Applicable Reliability Standard(s)... 1 Applicability to California ISO... 1 SOLs and IROLs... 1 Study Methodology... 2 Supporting Information... 6 Responsibilities... 6
More informationNorthwest Power Pool Processes
Northwest Power Pool Processes Background The Northwest Power Pool membership (NWPP) was founded in 1941 to promote efficient production of electrical energy. The NWPP is the geographic area encompassed
More informationTransmission Planning Process. Study Scope for
2018-2019 Transmission Planning Process Study Scope for Increased Capabilities for Transfers of Low Carbon Electricity between the Pacific Northwest and California Informational Study April 12, 2018 DRAFT
More informationSeasonal Assessments and Modeling of Sub-100 kv Elements (Southwest Outage Recommendations 5, 6, 7 and NERC2) May 7, 2014
Seasonal Assessments and Modeling of Sub-100 kv Elements (Southwest Outage Recommendations 5, 6, 7 and NERC2) May 7, 2014 Background In April 2012, the Federal Energy Regulatory Commission (FERC) and the
More informationWestern Electricity Coordinating Council Regional Planning Project Review Loads and Resources Working Group
Western Electricity Coordinating Council Regional Planning Project Review Loads and Resources Working Group Demand Analysis of 215 Scenarios To Explore the Range of Need for a Canada/Pacific Northwest
More informationTransmission Planning Process. Study Scope for
2018-2019 Transmission Planning Process Study Scope for Increased Capabilities for Transfers of Low Carbon Electricity between the Pacific Northwest and California Informational Study May 23, 2018 Final
More informationSTATE OF THE INTERCONNECTION DIGEST
SUMMER 217 STATE OF THE INTERCONNECTION DIGEST The State of the Interconnection is a snapshot of evolving trends in the Western Interconnection. Beginning in 217, the Western Electricity Coordinating Council
More informationAnchor Data Set (ADS) Definition, Benefits, Implementation and Management Ver. 6-Aug 15 th DRAFT Proposal only
Anchor Data Set (ADS) Definition, Benefits, Implementation and Management Ver. 6-Aug 15 th 2016 DRAFT Proposal only Formal stakeholder review will begin August 24 th and remain open through September 12
More informationCalifornia Grid Operations: Current Conditions and Future Needs
California Grid Operations: Current Conditions and Future Needs Jim Detmers Vice President, Operations Global Climate & Energy Project November 1, 2007 STANFORD UNIVERSITY Our objective today is identify
More informationDRAFT STUDY PLAN FOR 2018
DRAFT STUDY PLAN FOR 2018 Introduction The Ten-year transmission planning process is intended to facilitate a timely, coordinated and transparent process that fosters the development of electric infrastructure
More informationWECC Standard FAC-501-WECC-1 Transmission Maintenance
A. Introduction 1. Title: Transmission Maintenance 2. Number: FAC-501-WECC-12 3. Purpose: To ensure the Transmission Owner of a transmission path identified in the table titled Attachment B, Major WECC
More informationAgenda Unified Planning Assumptions & Study Plan
Agenda Unified Planning Assumptions & Study Plan Jody Cross Stakeholder Engagement and Policy Specialist 2018-2019 Transmission Planning Process Stakeholder Meeting February 28, 2018 2018-2019 Transmission
More informationCalifornia ISO Preparing California for a Greener and Smarter Grid
California ISO Preparing California for a Greener and Smarter Grid Presented by Jim McIntosh Director Operations Executive Advisor California ISO Agenda CAISO Overview Current & Future Challenges Renewables
More informationIncreased Capabilities for Transfers of Low Carbon Electricity between the Pacific Northwest and California Informational Study
2018-2019 Transmission Planning Process Increased Capabilities for Transfers of Low Carbon Electricity between the Pacific Northwest and California Informational Study Ebrahim Rahimi Lead Regional Transmission
More informationPacific Northwest Power Supply Adequacy Assessment for 2019 Final Report
Pacific Northwest Power Supply Adequacy Assessment for 2019 Final Report May 7, 2014 Council Document Number 2014-04 1 Executive Summary The Pacific Northwest s power supply is expected to be close to
More informationBEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION
BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF A COMMISSION ) INVESTIGATION INTO THE FEASIBILITY ) OF PUBLIC SERVICE COMPANY OF NEW ) MEXICO BECOMING A MEMBER OF THE ) Case No. 17-00261-UT
More informationGridView Review 2026 Common Case Version 2.0
GridView Review 2026 Common Case Version 2.0 Colby Johnson Staff Engineer December 14, 2017 2 Overview GridView Review What is it/what does it do? Inputs and Outputs 2026 Common Case Version 2.0 Changes
More informationTransfer Capability Methodology. for the Near-Term. Transmission Planning Horizon
Transfer Capability Methodology for the Near-Term Transmission Planning FAC-013-2 Version 2.2 June 30, 2018 Table of Contents 1 PURPOSE... 3 2 DEFINITION... 3 3 APPLICABILITY... 3 4 TRANSFER CAPABILITY
More informationProduction Cost Modeling for High Levels of Photovoltaics Penetration
National Renewable Energy Laboratory Innovation for Our Energy Future A national laboratory of the U.S. Department of Energy Office of Energy Efficiency & Renewable Energy Production Cost Modeling for
More informationCAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)
Background On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) The CAISO s deliverability study methodology for resource adequacy purposes was discussed extensively in the CPUC
More informationBEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP. Chapter 2. Direct Testimony of Joseph P. Hoerner and Shayleah J.
Investigation No. -0-0 Exhibit No. Witnesses: Joseph P. Hoerner and Shayleah J. LaBray BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP Chapter Direct Testimony of Joseph P.
More informationThe RMATS footprint covers the States of Colorado, Idaho, Montana, Utah and Wyoming.
On August 22, 2003, Wyoming Governor Dave Freudenthal and Utah Governor Michael Leavitt announced the formation of the Rocky Mountain Area Transmission Study (RMATS). They did so because the electric power
More informationPSE Attachment K Puget Sound Area Transmission Meeting
PSE Attachment K Puget Sound Area Transmission Meeting Stephanie Lu, Engineer Transmission Contracts December 9, 2010 Content Attachment K Review Primary Contacts Economic Studies Process PSE Planning
More informationNORTHWESTERN ENERGY 2018 ELECTRICITY RESOURCE PROCUREMENT PLAN STRAWMAN 1
NORTHWESTERN ENERGY 2018 ELECTRICITY RESOURCE PROCUREMENT PLAN CHAPTER 1. EXECUTIVE SUMMARY STRAWMAN 1 1. Load Service Requirements a. Peaking Capacity (Planning Reserve Margin) b. Dispatchable Capacity
More informationWestern Interconnection Regional Advisory Body
Western Interconnection Regional Advisory Body January 24, 2008 Alberta Arizona British Columbia California Colorado Mexico Montana Idaho Nebraska Nevada New Mexico Oregon South Dakota Utah Washington
More information2016 Probabilistic Assessment. December 5, 2016 Southwest Power Pool
2016 Probabilistic Assessment December 5, 2016 Southwest Power Pool Table of Contents 1. Summary...2 a. SPP Planning Coordinator Footprint...2 b. Seasonal Capacity Totals... Error! Bookmark not defined.
More informationReduced Network Modeling of WECC as a Market Design Prototype
PAPER 2011GM0942 1 Reduced Network Modeling of WECC as a Market Design Prototype James E. Price, Member, IEEE, and John Goodin Abstract California s administration, legislature, and energy regulators have
More informationCommon Case Process. Jon Jensen Staff Engineer System Adequacy Planning
Common Case Process Jon Jensen Staff Engineer System Adequacy Planning 2 Introduction: 2026 Common Case What is it? Year 10 focused Production Cost/Economic Dispatch (SCED) Model (GridView); 8760 hours
More information(This page is intentionally'
FORTISBC INC 2012-13 REVENUE REQUIREMENTS AND REVIEW OF ISP EXHIBIT C9-17 (This page is intentionally' left blank.) to ensure the reliability of the bulk power system The North American Electric Reliability
More informationSPSC 2011 and 2012 Study Requests to WECC/TEPPC: Update for January 2013
SPSC 2011 and 2012 Study Requests to WECC/TEPPC: Update for January 2013 # SPSC Request & Description TEPPC Case Study Program application 1 1. Reference Case: Utility IRPs and Plans (10- year) 2 2A. Scenario
More informationEIPC Interconnection-wide Webinar and Stakeholder Discussion. November 17, 2015
EIPC Interconnection-wide Webinar and Stakeholder Discussion November 17, 2015 Webinar Outline Presentation on 2025 Summer Peak (2025S) and 2025 Winter Peak (2025W) Roll-up Case Development Report to be
More informationStakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5
Methodology and Assumptions 1.1 Overview These sections describe the process we used to perform a network assessment of the ATC transmission system. The description includes study assumptions, methods
More informationCalifornia Independent System Operator Renewable Integration Study
California Independent System Operator Renewable Integration Study Clyde Loutan Proposed Transmission Plan for Integration of Renewables Transmission System Analysis - Overview Joint Study between the
More informationTTC/ATC 1.0 DEFINITIONS
TTC/ATC In this section: Definitions Total Transfer Capability (TTC) Methodology Available Transmission Transfer Capability (ATC) Calculation Counterflow ATC Release of Unused Transmission in Pre- schedule
More informationWECC Standard PRC-STD Transmission Maintenance
A. Introduction 1. Title: Transmission Maintenance 2. Number: PRC-STD-005-1 3. Purpose: Regional Reliability Standard to ensure the Transmission Operator or Owner of a transmission path identified in Attachment
More information2012 Grid of the Future Symposium. Innovations in Bulk Power System Reliability Assessment: A North American View
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2012 Grid of the Future Symposium Innovations in Bulk Power System Reliability Assessment: A North American View M.G.
More informationCalifornia Independent System Operator (CAISO) Challenges and Solutions
California Independent System Operator (CAISO) Challenges and Solutions Presented by Jim Hiebert EMS Power Technology Engineer Lead California ISO by the numbers 65,225 MW of power plant capacity 50,270
More informationUtility Scale Integration of Wind and Solar Power
Utility Scale Integration of Wind and Solar Power Charles Reinhold WestConnect Project Manager Southwest Renewable Energy Conference Flagstaff, AZ Presentation Overview WestConnect Background Area Control
More information2012 Grid of the Future Symposium METHODOLOGY OF COMPUTING SIMULTANEOUS VARIABLE TRANSFER LIMITS ON MULTIPLE PATHS
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2012 Grid of the Future Symposium METHODOLOGY OF COMPUTING SIMULTANEOUS VARIABLE TRANSFER LIMITS ON MULTIPLE PATHS RAMU
More informationBPA Comments on Appendix H. Pacific Northwest California Transfer Increase Informational Special Study
BPA Comments on Appendix H Pacific Northwest California Transfer Increase Informational Special Study February 28, 2019 On February 4, 2019, the California ISO (CAISO) released the 2018 2019 Transmission
More informationGreat Basin Transmission ITP Submission to California ISO. May 2018
Great Basin Transmission ITP Submission to California ISO May 2018 LS Power Power generation and transmission company formed in 1990 39,000+ MW Power generation development, construction or operations
More informationCalifornia ISO Summer Loads and Resources Operations Assessment April 10, Grid Assets California ISO Version 3.0.
California Independent System Operator Corporation 2006 Summer Loads and Resources Operations Assessment April 10, 2006 Grid Assets Version 3.0 Table of Contents I. Executive Summary...2 Table 1 2006 ISO
More informationDRAFT Work in Progress CAISO Integration of Renewable Resources Program (IRRP) - High-Level Program Plan -
CAISO 2008-2013 Integration of Renewable Resources Program (IRRP) - High-Level Program Plan - Purpose The purpose of this document is to provide an initial high-level scoping and program plan for the CAISO
More informationIdaho Power s Transmission System. Greg Travis Nov. 8, 2018
Idaho Power s Transmission System Greg Travis Nov. 8, 2018 Presentation Outline Acronyms and definitions Energy Imbalance Market (EIM) Idaho Power s transmission system Path 14 ID-NW Open discussion Acronyms
More informationPlatte River Power Authority. Ten-Year Transmission Plan ( )
Platte River Power Authority Ten-Year Transmission Plan (2015-2024) Prepared by PRPA System Planning December 31, 2014 Table of Contents I. Executive Summary II. III. IV. Scope Assumptions Criteria V.
More information2016 Summer Reliability Assessment
Table of Contents Preface... 3 Overview... 5 FRCC... 6 MISO... 7 MRO-Manitoba Hydro... 8 MRO-SaskPower... 9 NPCC-Martimes... 10 NPCC-New England... 11 NPCC-Ontario... 13 NPCC- Québec... 14 PJM... 15 SERC...
More informationFull Network Model Expansion Second Revised Straw Proposal
October 30, 2013 Table of Contents 1 Changes from 9/11/2013 revised straw proposal... 3 2 Executive summary... 3 3 Introduction and purpose... 5 4 Plan for stakeholder engagement... 8 5 Scope of initiative...
More informationMISO 2018 Series Dispatch Update. MOD-032 Users Group October 3, 2017
MISO 2018 Series Dispatch Update MOD-032 Users Group October 3, 2017 1 Objective MTEP17 Dispatch Process MTEP18 Dispatch Updates Reminder Station Service Load Modeling Enhancements Wind Capacity Credit
More informationWESTERN ELECTRICITY COORDINATING COUNCIL GENERATING UNIT MODEL VALIDATION POLICY
WESTERN ELECTRICITY COORDINATING COUNCIL GENERATING UNIT MODEL VALIDATION POLICY A. Introduction A.1. Title: Generating Unit Model Validation Policy A.2. Purpose: Accurate models of generators and associated
More informationFirstEnergy Verification Team. Report on the Implementation of Recommendations from the FirstEnergy Readiness Audit of February 26 27, 2004
FirstEnergy Verification Team Report on the Implementation of Recommendations from the FirstEnergy Readiness Audit of February 26 27, 2004 June 22 23, 2005 North American Electric Reliability Council Table
More informationRegional Transmission Planning in the West. State-Federal RPS Collaborative Webinar Hosted by Clean Energy States Alliance October 5, 2011
Regional Transmission Planning in the West State-Federal RPS Collaborative Webinar Hosted by Clean Energy States Alliance October 5, 2011 CEG State-Federal RPS Collaborative With funding from the Energy
More informationRochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017
Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA March 21, 2017 Contents 1 Background...3 2 National and Regional Criteria and Guides...4 2.1 2.1 NERC Transmission Planning Standards...4 2.2
More informationReview of Data Change Management Processes for RTCA and Planning Models (Recommendation 16) March, 2017
Review of Data Change Management Processes for RTCA and Planning Models (Recommendation 16) March, 2017 Background In April 2012, the Federal Energy Regulatory Commission (FERC) and the North American
More informationMOD Data for Power System Modeling and Analysis
MOD-032-1 Data for Power System Modeling and Analysis A. Introduction 1. Title: Data for Power System Modeling and Analysis 2. Number: MOD-032-1 3. Purpose: To establish consistent modeling data requirements
More informationRe: Base Case and Alternative Renewable Resource Portfolios for the CAISO Transmission Planning Process
STATE OF CALIFORNIA EDMUND G. BROWN JR., Governor PUBLIC UTILITIES COMMISSION CALIFORNIA ENERGY COMMISSION 505 VAN NESS AVENUE 1516 NINTH STREET SAN FRANCISCO, CA 94102-3298 SACRAMENTO, CA 95814-5512 February
More informationNTTG Annual Interregional Information
NTTG Annual Interregional Information Annual Interregional Coordination Meeting Folsom, CA February 22, 2018 NTTG Organization and Planning Process Overview Presented by Sharon Helms, NTTG Program Manager
More informationWestern Interconnection Seasonal Operations Planning Coordination Process Rev. 3.0
Western Interconnection Seasonal Operations Planning Rev. 3.0 Issued March 26, 2019 Effective May 1, 2019 PEAK RELIABILITY RELIABILITY COORDINATION 7600 NE 41 st STREET SUITE 201 VANCOUVER WASHINGTON 98662-6772
More informationLS Power. Southwest Intertie Project (SWIP) North. NTTG Stakeholder Meeting April 12, Bringing Energy Forward
LS Power Southwest Intertie Project (SWIP) North NTTG Stakeholder Meeting April 12, 2016 LS Power LS Power is a power generation and transmission group Power Generation Transmission Acquisition Over 32,000
More informationDEMAND PEAK FORECAST SUPPLY RENEWABLES IMPORTS OPERATING RESERVE SUMMER LOADS AND RESOURCES ASSESSMENT. March 15, 2012
SUPPLY 2012 SUMMER LOADS AND RESOURCES ASSESSMENT March 15, 2012 IMPORTS DEMAND FORECAST PEAK RENEWABLES OPERATING RESERVE Prepared by: Market & Infrastructure Development Grid Assets Department Version:
More informationThe Southwest Intertie Project: Assessment of Potential Benefits
The Southwest Intertie Project: Assessment of Potential Benefits November 2008 THE SOUTHWEST INTERTIE PROJECT ASSESSMENT OF POTENTIAL BENEFITS TABLE OF CONTENTS 1 Executive Summary... 2 2 Introduction...
More informationOverview of Issues at the Western Electricity Coordinating Council (WECC)
energy strategies Overview of Issues at the Western Electricity Coordinating Council (WECC) Focusing on those Issues Impacting Independent Generators Presented to The California Independent Energy Producers
More informationITP Year 20 Assessment Scope
ITP 20 Year Scope 1 ITP Year 20 Assessment Scope January 6, 2010 Approved by TWG January 5, 2010 Endsored by ESWG January 5, 2010 Table of Contents Overview... 4 Objective... 4 Modeling... 5 1. Economic...
More information2015 Operational Practices Survey Questions
2015 Operational Practices Survey Questions This document of survey questions has been provided as a courtesy. It is not the actual survey, which will be completed electronically and only by a designated
More informationWith funding provided by the US Department of Energy, NREL, and the Utah Office of Energy Development
With funding provided by the US Department of Energy, NREL, and the Utah Office of Energy Development www.fourcornerswind.org Photo courtesy of Avangrid Renewables, LLC UNDERSTANDING REGIONAL ELECTRICITY
More informationTRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA
TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA For Compliance with NERC Reliability Standard: TPL-001-4 1/10/2017 Version: 4.2 Table of Contents 1 Revision and Approval History... 2 1.1 Revision
More informationStandard MH-TPL Transmission System Planning Performance Requirements
A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: MH-TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon
More informationContingency Modeling Enhancements
Contingency Modeling Enhancements Straw Proposal Discussion May 22, 2013 Delphine Hou Senior Market Design and Policy Specialist and Lin Xu, Ph.D. Senior Market Development Engineer Agenda Time Topic Presenter
More informationNorthern Tier Transmission Group Stakeholder Meeting Boise, Idaho July 22, 2009
Joint Initiative Update Northern Tier Transmission Group Stakeholder Meeting Boise, Idaho July 22, 2009 1 Northern Tier Transmission Group Membership Participating Utilities Deseret Power Electric Cooperative
More informationBulk Energy Storage Resource Case Study Update with the 2016 LTPP Assumptions
Bulk Energy Storage Resource Case Study Update with the 2016 LTPP Assumptions Shucheng Liu Principal, Market Development 2016-2017 Transmission Planning Process Stakeholder Meeting February 28, 2017 Page
More informationApproaches to Generation Dispatch in Transmission Planning
21, rue d Artois, F-75008 PARIS Paper 135 GUILIN 2009 Approaches to Generation Dispatch in Transmission Planning P. J. PALERMO KEMA, Inc. USA SUMMARY A critical factor affecting transmission system development
More informationOrganized Markets in WECC. Status Update and Implications for Planning 2/1/18
Organized Markets in WECC Status Update and Implications for Planning 2/1/18 Agenda Regional Markets Update Regional Market Activity EIM CAISO Mountain West Peak Reliability / PJM Implications for 2018
More informationCalifornia ISO Energy Imbalance Market Operations Overview. June 10, 2014 Webinar
California ISO Energy Imbalance Market Operations Overview June 10, 2014 Webinar Objectives 1. EIM Overview 2. CAISO s process in mitigating Unscheduled Flow (USF) 3. WebSAS tool: how dynamic and pseudo
More informationInadvertent Interchange Accounting Training Document
Inadvertent Interchange Accounting Training Document Training Document Subsections A. Introduction B. Definitions C. Interchange Accounting D. Inadvertent Interchange Energy Accounting Practices E. Interchange
More informationPREPARED DIRECT TESTIMONY OF JEFF HUANG SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY
Application No: A.1-0- Exhibit No.: Witness: Jeff Huang Application of Southern California Gas Company (U 0 G) and San Diego Gas & Electric Company (U 0 G) for Authority to Revise their Natural Gas Rates
More informationWelcome to the California Independent System Operator. August 7, 2015
Welcome to the California Independent System Operator August 7, 2015 The California ISO is one of nine independent/regional transmission operators (ISOs/RTOs) in North America Two-thirds of the United
More informationBC Hydro Renewable Generation Market Competitiveness Report
BUILDING A WORLD OF DIFFERENCE BC Hydro FINAL REPORT B&V Project Number: 172047 July 2011 Black & Veatch Corporation 11401 Lamar Avenue Overland Park, Kansas 66211 Tel: (913) 458 2000 www.bv.com Table
More informationMapping Document for FAC-010-3
Mapping Document for FAC-010-3 The Project 2015 09 standard drafting team (SDT) is proposing the retirement of the NERC FAC 010 3 Reliability Standard. The SDT further proposes a new paradigm regarding
More informationSPP at a Glance. Located in Little Rock. Approximately 600 employees
SPP at a Glance Located in Little Rock Approximately 600 employees Primary jobs electrical engineering, operations, settlements, and IT 24 x 7 operation Full redundancy and backup site 2 Regulatory Environment
More informationMarch 3, Submitted to: CAISO
March 3, 2016 Submitted to: CAISO (regionaltransmission@caiso.com) COMMENTS OF NEXTERA ENERGY TRANSMISSION WEST, LLC ON THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION S 2015-2016 TRANSMISSION PLANNING
More informationMaking Sense of U.S. Energy Markets
Making Sense of U.S. Energy Markets National Conference of State Legislators Task Force on Energy Supply Philip Pettingill, Director Regional Integration January 14, 2017 Two-thirds of the United States
More informationTransmission Planning Process Unified Planning Assumptions and Study Plan. March 31, Final
Unified Planning Assumptions and Study Plan March 31, 2015 Final CAISO Market and Infrastructure Development Division March 31, 2015 Intentionally left blank Table of Contents 1. Introduction... 1 2. Overview
More informationJanuary 3, 2018 MEMORANDUM. Council Members. John Ollis, Power System Analyst. SUBJECT: Marginal Carbon Emissions Rate Study Draft BACKGROUND:
Henry Lorenzen Chair Oregon Bill Bradbury Oregon Guy Norman Washington Tom Karier Washington W. Bill Booth Vice Chair Idaho James Yost Idaho Jennifer Anders Montana Tim Baker Montana January 3, 2018 MEMORANDUM
More informationSummary of Comments, Organized By Question Number
Summary of Comments, Organized By Question Number Monitor and Assess Short-term Transmission Reliability Operate Within Transmission System Limits SAR Second Posting Summary of Comments Background The
More informationWECC Criterion INT-004-WECC-CRT-2.1
WECC Criterion INT-004-WECC-CRT-2.1 A. Introduction 1. Title: Reliability Curtailments and Reload 2. Number: INT-004-WECC-CRT-2.1 3. Purpose: To define treatment and approval of reliability curtailment
More informationPlanning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES
Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES Effective Date: September 11, 2017 Revision History Date Version Description June 6, 1998 0.0 Initial LGEE document
More informationStandards de planification du NERC
Demande R-3498-2002 Standards de planification du NERC PREUVE EN CHEF DE TRANSÉNERGIE Original : 2002-11-27 HQT-4, Document 2 (en liasse) NERC PLANNING STANDARDS North American Electric Reliability Council
More informationDemand Response Association of Energy Engineers. Presenter: David Wylie, P.E. ASWB Engineering
Demand Response 2015 Association of Energy Engineers Presenter: David Wylie, P.E. ASWB Engineering National Energy Peak Leveling Program 1977 2 National Energy Peak Leveling Program 1977 3 When Demand
More informationGenerator Interconnection Affected System Impact Study. Plains & Eastern Clean Line Final Report
Generator Interconnection Affected System Impact Study Plains & Eastern Clean Line Final Report May 19, 2015 MISO 2985 Ames Crossing Eagan Minnesota - 55121 http://www.misoenergy.org Midcontinent Independent
More information2016 Fall Reliability Conference MRO
2016 Fall Reliability Conference MRO CAISO s Coordination, Tracking, and Monitoring Distributed Energy Resources Amber Motley; Manager, Short Term Forecasting November 2 nd, 2016 California ISO Overview
More informationReliability Challenges of the Clean Power Plan
Reliability Challenges of the Clean Power Plan Branden Sudduth Director, Reliability Planning 2 Outline WECC Role in the Western Interconnection Uniqueness of the Western Interconnection WECC efforts related
More informationERCOT Public LTRA Probabilistic Reliability Assessment. Final Report
ERCOT Public 2016 LTRA Probabilistic Reliability Assessment Final Report November 21, 2016 Contents Summary... 1 Software Model Description... 3 Demand Modeling... 3 Controllable Capacity Demand Response
More informationCAISO View of Smart Grid
CAISO View of Smart Grid David Hawkins Lead Renewables Power Engineer March 17, 2010 Slide 2 Slide 2 1 Generation Grid Operators View Leverage smart grid policies to: Increase demand-side participation
More informationCentralia Power Plant Closure Study. Initial Study Results DRAFT. March 17, 2011
Centralia Power Plant Closure Study Initial Study Results DRAFT March 17, 2011 Conditions Studied 5 and 10-year Winter and Summer Peak 5-year Light Autumn High Transfers to and from British Columbia Additional
More informationCase Metrics 2015 Summer Base Case Quality Assessment Phase I Powerflow and Dynamics Case Quality Metrics FINAL
Case s 2015 Summer Base Case Quality Assessment Phase I Powerflow and Dynamics Case Quality s FINAL Introduction Powerflow and dynamics cases are the foundation of virtually all power system studies. Calculations
More information