BWL T&D Restoration Process

Size: px
Start display at page:

Download "BWL T&D Restoration Process"

Transcription

1 BWL T&D Restoration Process BWL Board of Commissioners Meeting January 7, 2014 Dave Bolan, Director of Electric Transmission and Distribution Lynn McKinstry, Manager Electric System Operations Wayne Lynn, Manager of Electric System Integrity Pat Hanes, Manager of Electric Transmission & Distribution 1/15/2014 1

2 1/15/2014 2

3 Topics Discussed Impact of Preventive Maintenance Electric System Distribution Facilities BWL Electric System Restoration Plan Crew Configurations Restoration Process and Timeline Post Storm Analysis 1/15/2014 3

4 Tree Trimming Maintenance Line outages are correlated with areas that have a high tree density. BWL Tree Trimming Program Without the BWL tree trimming program, customer outages from this storm would have exceeded 70%, or at least 67,000 customer outages. We are currently in year 3 of a 7 year trimming cycle. BWL utilized its systematic tree trimming program that regularly trims trees near BWL power lines. Follows industry standard practices. (ANSI A-300 and ANSI Z133.1) Award winning The program will be accelerated in areas that have high density of tree population. 1/15/2014 4

5 Electric Utility Power System Diagram 1/15/2014 5

6 Simplified Distribution Circuit Substation Breaker Primary Circuit Approx 1,500 households Lateral Circuit Approx 100 to 300 households Distribution Transformer Approx. 10 households Secondary or Service Drop 1/15/2014 6

7 Overhead Distribution Service to Customer 1/15/ Courtesy of Tacoma Power

8 Storm Restoration Plan BWL has a restoration plan that is; Based on the Utility Industry Best Practices, Safety conscious, and Prioritizes the restoration of circuits in an efficient manner. The precepts of this plan have been the basis of BWL storm restoration for at least the last 35 years. For many of the previous storms, this plan has restored the BWL system before other regional utilities could do the same. BWL s restoration plan was last reviewed after the November 2013 storm as part of our lessons learn process. 1/15/2014 8

9 Crews BWL Crew design is based on best industry and safety practices. Number of crews is based on the known damage at any point in time during the restoration. Staffing increases as known damage reports increase Information used to determine the type and quantity of crews is based on: Location and number of customers without service. Type of outage (i.e. primary vs secondary and reconnections) Ability of BWL s Operations staff to dispatch and support the crews. Number of BWL staff to guide contractor crews and operate in a safe manner. 1/15/2014 9

10 Crews (continued) Initially, crews are dispatched to cut down power lines and safely secure wires down. Up to 18 Spotter crews were dispatched to identify wire downs that needed crews to make safe. This was our primary source of information of the system condition. Then crews are configured to restore primary circuits (3-person crew). After the major primary work has been completed crews will be configured for both Primary and Secondary repairs and Reconnection work, the result being more crews. 2-person crews are dispatched for Secondary repair and Reconnection of customers. Most secondary repairs and reconnection work does not require a BWL Guide, contract crews can work independently. These crews can be dispatched independent of the BWL control center dispatchers. 1/15/

11 Crews (continued) Mr. Lark gave permission to bring in as many crews as necessary. Right-sizing of crews to prevent safety hazards to BWL and outside resources. Staffing for the T&D line crews increased by 2 linemen and 2 streetlighting workers Use of BWL Personnel as Guides Safety Standards: Failure to repair the system to BWL standards creates future safety hazards to BWL Crews and customers Since Mr. Lark has been at BWL, the list of mutual aid has expanded. 1/15/

12 1/15/

13 Mutual Assistance Agreements Under Peter Lark s Leadership Asplundh Kent Power Hydaker-Wheatlake Michigan Municipal Electric Association (35 Municipal utilities) Consumers Energy FEMA Mutual Aid (Upon a declaration of a State of Emergency) DTE Energy (under negotiations) American Public Power Association (under negotiations) 1/15/

14 BWL Line & Tree Crews Utilized for Restoration = 62 Crews December 2013 Storm BWL Crews Contract Crew Municipal Contract Crew - Other Line Crews (6) Coldwater (1) Hydaker-Wheatlake (5) Electric Service Workers (3) Holland (2) Asplund (7) BWL Tree crews (1) Zeeland (1) Kent Power (13) Wright Tree Crews (4) Sturgis (1) Wright Tree Service (10) Marquette (1) Traverse City (2) Sebewaing (1) Grand Haven (2) Hillsdale (1) Marshall (1) 1/15/201 4 Total = 14 Crews Total = 13 Crews Total = 35 Crews 14

15 Order of Restoration Overview The BWL restoration is prioritized to first isolate equipment that can jeopardize the safety of the community, then restore circuits related to public safety and the well being of the public. Further restoration is prioritized to restore service the largest amount of customers within the shortest amount of time. 1/15/

16 Simplified Distribution Circuit Restoration Priorities Substation Breaker Distribution Transformer Approx. 10 households Primary Circuit Approx 1,500 households Lateral Circuit Approx 100 to 300 households Secondary or Service Drop 1 st - Isolate Equipment that can harm the Community 2 nd - Restore Service related to Public Safety 3 rd - Restore Service to Primary Circuits 4 th - Restore Service to Secondary and Reconnect Customer Services 5 th - Perform Preventive Maintenance and Address Customer Service Problems 1/15/

17 Order of Restoration First Priority Isolate Equipment that can harm the Community Clear and make safe all ENERGIZED DOWNED WIRES. Clear and make safe all DE-ENERGIZED DOWNED WIRES. 1/15/

18 Order of Restoration Second Level Priority Restore Service related to Public Safety Utility Radio Communication and Dispatch Centers Hospitals, Urgent Care Facilities Water Pumping Facilities Police and Fire Departments Waste Water Treatment Plants and Pumping Stations. 1/15/

19 Order of Restoration Third Level Priority Restore Service to Primary Circuits Restore/Trim Primary and Primary Customers Lateral and secondary circuits will not be repaired at this time in the restoration 1/15/

20 1/15/

21 1/15/

22 Order of Restoration Fourth Level Priority Restore Service to Secondary and Reconnect Customer Services Restore/Replace Blown Lateral & Transformer fuses Restore/Replace Secondary Trim/Restore Services (Reconnections of Service) 1/15/

23 1/15/

24 Order of Restoration Fifth Level Priority Perform Preventive Maintenance and Address Customer Service Problems Trim threatened wires Respond to Partial/Flickering Lights calls Non-critical Trimming/Clean-up 1/15/

25 1/15/

26 1/15/

27 Tree Trimming Follow-up During the storm, customers stated that they were approached by a tree trimming service with a name similar to the Wright Tree Service and were asked to pay for utility related tree trimming services. BWL customers do not pay for this tree trimming service. Please call Diana Paul at /15/

28 Post Storm Analysis After each storm, the BWL Departments perform a lessons learned exercise to identify weakness or potential threats within the Restoration plan and/or the execution of the plan. The results of the lesson learned exercise are assigned objectives to mitigate the weakness or threats. The idea is to have a Storm Restoration plan that is more robust to efficiently return service to our customers when future storms occur. 1/15/

29 Questions for the T&D Staff 1/15/

Pennsylvania Summer Reliability

Pennsylvania Summer Reliability 1. Keys to Success A. Reliability Enhancement Programs In 2013, Penn Power is continuing its reliability strategy, consisting of reviewing all outages by outage cause and weather, installing protective

More information

Seattle City Light Outage Management System. May 2014

Seattle City Light Outage Management System. May 2014 Seattle City Light Outage Management System May 2014 1 Objectives for this Presentation Overview of the drivers for the Outage Management System Describe the system and the implementation Summarize the

More information

Tips for Managing through a POWER OUTAGE

Tips for Managing through a POWER OUTAGE Tips for Managing through a POWER OUTAGE Safety Information Stay away from downed power lines and anything touching them. If you see a wire down, call us at 1-888-LIGHTSS (544-4877) or local police or

More information

Storm Response & Onboarding. Safety First and Always

Storm Response & Onboarding. Safety First and Always Storm Response & Onboarding Eversource Safety 2017 Safety Message 2 Safety Message: Stated Expectations: Are they possible? Since 2001: 14 Play off appearances 7 Super Bowl Appearances (roughly one every

More information

PREPARING FOR & RESPONDING TO EXTREME WEATHER & EXTENDED OUTAGES

PREPARING FOR & RESPONDING TO EXTREME WEATHER & EXTENDED OUTAGES 2013 PREPARING FOR & RESPONDING TO EXTREME WEATHER & EXTENDED OUTAGES Forward-Looking Statement Readers are cautioned that statements contained in this presentation about our and our subsidiaries' future

More information

OPERATIONS OM&A. Filed: August 15, 2007 EB Exhibit C1 Tab 2 Schedule 4 Page 1 of INTRODUCTION

OPERATIONS OM&A. Filed: August 15, 2007 EB Exhibit C1 Tab 2 Schedule 4 Page 1 of INTRODUCTION Filed: August, 00 EB-00-0 Tab Schedule Page of OPERATIONS OM&A.0 INTRODUCTION Operations OM&A investments are required to manage the day to day flow of electricity within Hydro One Distribution s system.

More information

Document Updated: 12/5/2018

Document Updated: 12/5/2018 Vice President Energy Delivery Document Updated: 12/5/2018 * Blue shading indicates a qualifying Transmission Function Employee Manager System Operations Manager Substation Supervisor System Control Supervisor

More information

SUMMARY OF DISTRIBUTION BUSINESS

SUMMARY OF DISTRIBUTION BUSINESS Filed: 0-0- EB-0-0 Schedule Page of SUMMARY OF DISTRIBUTION BUSINESS.0 INTRODUCTION Hydro One Networks Inc. is licensed by the Ontario Energy Board (the Board ) to own, operate and maintain electricity

More information

Exhibit to Agenda Item #1

Exhibit to Agenda Item #1 Exhibit to Agenda Item #1 Board Directors Meeting Wednesday,, scheduled to begin at 5:30 p.m. Customer Service Center, Rubicon Room Powering forward. Together. Agenda 2016 SD-4 annual monitoring report

More information

Customer Charter Trusted by our customers to deliver today and create a better tomorrow.

Customer Charter Trusted by our customers to deliver today and create a better tomorrow. Customer Charter Trusted by our customers to deliver today and create a better tomorrow. TasNetworks has developed this customer charter to explain what you can expect from us, your entitlements and the

More information

2015 General Rate Case. Transmission and Distribution (T&D) Volume 7 Grid Operations

2015 General Rate Case. Transmission and Distribution (T&D) Volume 7 Grid Operations Application No.: Exhibit No.: SCE-0, Vol. 0 Witnesses: P. Grigaux (U -E) 01 General Rate Case Transmission and Distribution (T&D) Volume Grid Operations Before the Public Utilities Commission of the State

More information

West Coast Utility Solutions NERC COMPLIANCE FOR UTILITIES; INTEGRATING HENDRIX AERIAL CABLE SYSTEMS

West Coast Utility Solutions NERC COMPLIANCE FOR UTILITIES; INTEGRATING HENDRIX AERIAL CABLE SYSTEMS West Coast Utility Solutions NERC COMPLIANCE FOR UTILITIES; INTEGRATING HENDRIX AERIAL CABLE SYSTEMS NERC COMPLIANCE FOR TRANSMISSION & DISTRIBUTION UTILITY COMPANIES; INTEGRATING HENDRIX AERIAL CABLE

More information

JEA Report to the Florida Public Service Commission Pursuant to Rule , F.A.C. Calendar Year 2016

JEA Report to the Florida Public Service Commission Pursuant to Rule , F.A.C. Calendar Year 2016 1) Introduction JEA Report to the Florida Public Service Commission Pursuant to Rule 25-6.0343, F.A.C. Calendar Year 2016 a) Jacksonville, FL / JEA b) 21 W Church St, Jacksonville, FL 32202-3139 c) Jeremy

More information

Darwin-Katherine Power System. 12 March 2014

Darwin-Katherine Power System. 12 March 2014 Darwin-Katherine Power System System Black 12 March 2014 Approved by: Managing Director Document No: 0.1 Version No: 0.1 Power and Water Corporation ABN 15 947 352 360 www.powerwater.com.au Table of Contents

More information

Conastone to Raphael Road 230kV New Transmission Line and Reconductoring February 28, 2017

Conastone to Raphael Road 230kV New Transmission Line and Reconductoring February 28, 2017 February 28, 2017 The enclosed information is proprietary to PSE&G and is provided solely for your use. It should not be copied, reproduced, or shared with others without PSE&G s prior written consent.

More information

City of Winter Park Report to the Florida Public Service Commission Pursuant to Rule , F.A.C. Calendar Year 2014

City of Winter Park Report to the Florida Public Service Commission Pursuant to Rule , F.A.C. Calendar Year 2014 1) Introduction a) City of Winter Park City of Winter Park Report to the Florida Public Service Commission Pursuant to Rule 25-6.0343, F.A.C. Calendar Year 2014 b) 401 Park Avenue South, Winter Park, Fl.

More information

SPECIFICATION. for LOCAL DISTRIBUTION LINE CLEARANCE. TREE WORK and BRUSH CONTROL

SPECIFICATION. for LOCAL DISTRIBUTION LINE CLEARANCE. TREE WORK and BRUSH CONTROL SPECIFICATION for LOCAL DISTRIBUTION LINE CLEARANCE TREE WORK and BRUSH CONTROL Revision 2014-B Table of Contents Section Page Number General Requirements... 1 Scope of Work... 2 Scheduled Maintenance

More information

CITY OF LODI ELECTRIC UTILITY DEPARTMENT RULE AND REGULATION NO. 16 SERVICE CONNECTIONS AND FACILITIES ON CUSTOMER'S PREMISES

CITY OF LODI ELECTRIC UTILITY DEPARTMENT RULE AND REGULATION NO. 16 SERVICE CONNECTIONS AND FACILITIES ON CUSTOMER'S PREMISES RULE AND REGULATION NO. 16 SERVICE CONNECTIONS AND FACILITIES ON CUSTOMER'S PREMISES A. Service in Areas Supplied by Overhead Facilities 1. Below 600 Volts The City will install, own, operate and maintain

More information

PAPUC Proposed Inspection and Maintenance Standards FirstEnergy s Comments

PAPUC Proposed Inspection and Maintenance Standards FirstEnergy s Comments PAPUC Proposed Inspection and Maintenance Standards FirstEnergy s Comments Good morning. My name is Eric Dickson, and I would like to thank the Commission and its staff for giving FirstEnergy an opportunity

More information

Moderator. How Utilities Apply Technology Throughout an Outage Lifecycle NH Emergency Preparedness Conference

Moderator. How Utilities Apply Technology Throughout an Outage Lifecycle NH Emergency Preparedness Conference How Utilities Apply Technology Throughout an Outage Lifecycle Presented By: 2017 NH Emergency Preparedness Conference Moderator Thomas Murphy Manager, Environmental Health & Safety 603.379.3829 murphyt@unitil.com

More information

TABLE OF CONTENTS. Overview Resource Planning, Energy Efficiency and Renewable Energy Transmission & Distribution System Reliability...

TABLE OF CONTENTS. Overview Resource Planning, Energy Efficiency and Renewable Energy Transmission & Distribution System Reliability... TABLE OF CONTENTS Overview... 3 Resource Planning, Energy Efficiency and Renewable Energy... 5 Transmission & Distribution System Reliability... 6 Customer Service... 7 Regionally Competitive Rates...

More information

GRADY EMC Job Summary descriptions current employees NOT intended to be a complete job posting or final description

GRADY EMC Job Summary descriptions current employees NOT intended to be a complete job posting or final description Applies to Every Job: GRADY EMC Job Summary descriptions current employees NOT intended to be a complete job posting or final description Every employee of this cooperative is ultimately responsible for

More information

CHAPTER 4 ELECTRIC TRANSMISSION AND DISTRIBUTION SYSTEM BENEFITS

CHAPTER 4 ELECTRIC TRANSMISSION AND DISTRIBUTION SYSTEM BENEFITS Application of San Diego Gas & Electric Company (U-0-E) for Adoption of an Advanced Metering Infrastructure Deployment Scenario and Associated Cost Recovery and Rate Design. Application 0-0-01 Exhibit

More information

Nova Scotia Utility and Review Board

Nova Scotia Utility and Review Board Nova Scotia Utility and Review Board IN THE MATTER OF The Public Utilities Act, R.S.N.S. 1989, c.380, as amended Post-Tropical Storm Arthur Progress Update October 31, 2014 1 2 3 4 5 6 TABLE OF CONTENTS

More information

BGE s Incident Command System Logistics of Disaster Management

BGE s Incident Command System Logistics of Disaster Management BGE s Incident Command System Logistics of Disaster Management June 19, 2013 Copyright 2013 by BGE. Published and used by INCOSE and affiliated societies with permission Lecture Agenda Company overview

More information

Kissimmee Utility Authority Storm Hardening Report to the Florida Public Service Commission Pursuant to Rule , F.A.C.

Kissimmee Utility Authority Storm Hardening Report to the Florida Public Service Commission Pursuant to Rule , F.A.C. Kissimmee Utility Authority Storm Hardening Report to the Florida Public Service Commission Pursuant to Rule 25-6.0343, F.A.C. 1) Introduction This report is filed in response to the above referenced rule

More information

Your. Guide CUSTOMER INFORMATION

Your. Guide CUSTOMER INFORMATION Your Guide to CUSTOMER INFORMATION Whether you are a new or existing gas customer, electric customer, or both, NIPSCO welcomes the opportunity to serve your energy needs. We understand that you may have

More information

Pipeline Safety. Topics of Discussion Leo Haynos, Chief of Gas Operations & Pipeline Safety. Corporation Commission

Pipeline Safety. Topics of Discussion Leo Haynos, Chief of Gas Operations & Pipeline Safety. Corporation Commission Pipeline Safety Topics of Discussion 2014 Leo Haynos, Chief of Gas Operations & Pipeline Safety Corporation Commission 2.kcc.ks.gov 2010-2013 Presentations also available. Other presentations available

More information

OMS/DMS Implementation at SDG&E

OMS/DMS Implementation at SDG&E OMS/DMS Implementation at SDG&E Vic Romero Director Asset Management & Smart Grid Projects March 26, 2013 2012 San Diego Gas & Electric Company. All copyright and trademark rights reserved. Outage and

More information

1. Reports to: Line Superintendent, Line Foreman, Working Foreman and Journeyman Lineman, respectively.

1. Reports to: Line Superintendent, Line Foreman, Working Foreman and Journeyman Lineman, respectively. POSITION DESCRIPTION A. Position: APPRENTICE LINEMAN B. Position Function: 1. Under the direction of the Line Superintendent, Line Foreman, Working Foreman and the Journeyman Lineman, the Apprentice Lineman

More information

April 20, VIA ELECTRONIC FILING -

April 20, VIA ELECTRONIC FILING - Kenneth M. Rubin Senior Counsel Florida Power & Light Company 700 Universe Boulevard Juno Beach, FL 33408-0420 (561) 691-2512 (561) 691-7135 (Facsimile) ken.rubin@fpl.com April 20, 2018 -VIA ELECTRONIC

More information

Scheduled Outages and Service Interruptions in Connecticut. Quat Nguyen Connecticut Public Utilities Regulatory Authority August 31, 2015

Scheduled Outages and Service Interruptions in Connecticut. Quat Nguyen Connecticut Public Utilities Regulatory Authority August 31, 2015 Scheduled Outages and Service Interruptions in Connecticut Quat Nguyen Connecticut Public Utilities Regulatory Authority August 31, 2015 1 Topics Profiles of Connecticut EDCs SAIDI and SAIFI Interruptions

More information

ESF 12 Energy and Utilities

ESF 12 Energy and Utilities ESF 12 Energy and Utilities Purpose This ESF Annex provides guidance to help ensure the continued operation of essential utility services in the County. Specifically, ESF #12 addresses: Energy system assessment,

More information

Withlacoochee River Electric Cooperative, Inc. P.O. Box 278 Dade City, FL Billy E. Brown, Executive V.P.

Withlacoochee River Electric Cooperative, Inc. P.O. Box 278 Dade City, FL Billy E. Brown, Executive V.P. Wednesday, February 25, 2015 PSC 25 6.0343 Municipal Electric Utility and Rural Electric Cooperative Reporting Requirements Withlacoochee River Electric Cooperative, Inc. P.O. Box 278 Dade City, FL 33526-0278

More information

REGULATORY CHANGE FOR UTILITY VEGETATION MANAGEMENT IN THE US

REGULATORY CHANGE FOR UTILITY VEGETATION MANAGEMENT IN THE US REGULATORY CHANGE FOR UTILITY VEGETATION MANAGEMENT IN THE US WILL PORTER DIRECTOR OF CONSULTING RULES AND REGULATIONS CHANGE TO MEET SOCIETAL NEEDS State regulators commissions Customer Needs Electric

More information

Tough Stuff. Resilient Infrastructure in a Changing World Wednesday, May 15, 2013 Noon to 1:30 p.m. #resiliency

Tough Stuff. Resilient Infrastructure in a Changing World Wednesday, May 15, 2013 Noon to 1:30 p.m. #resiliency Tough Stuff Resilient Infrastructure in a Changing World Wednesday, May 15, 2013 Noon to 1:30 p.m. Tweet @metroplanners #resiliency @metroplanners #resiliency Moderator PETER SKOSEY METROPOLITAN PLANNING

More information

Walk-through of long-term utility distribution plans: Part 1 - Traditional Distribution Planning

Walk-through of long-term utility distribution plans: Part 1 - Traditional Distribution Planning Walk-through of long-term utility distribution plans: Part 1 - Traditional Distribution Planning Lavelle Freeman GE Energy Consulting Distribution Technology Training for NASUCA 2018 Mid-Year Meeting,

More information

Algoma Power Inc (API) Major Event Day Report (June 11, 2017)

Algoma Power Inc (API) Major Event Day Report (June 11, 2017) Algoma Power Inc (API) Major Event Day Report (June 11, 2017) Introduction On June 11, 2017, severe thunderstorms moved through the API service territory. Initially the effects were felt north of Sault

More information

POSITION DESCRIPTION JOURNEY LINE WORKER (JOURNEYMAN LINEMAN)

POSITION DESCRIPTION JOURNEY LINE WORKER (JOURNEYMAN LINEMAN) I. OBJECTIVES: POSITION DESCRIPTION JOURNEY LINE WORKER (JOURNEYMAN LINEMAN) To develop and contribute to a safe working atmosphere that operates in a coordinated and organized manner, and to provide for

More information

nts Major Event Issue: Date Issued: Summary One s customers. 1. Prior to the occur? Hydro One did not Events. Notification Business (LOB).

nts Major Event Issue: Date Issued: Summary One s customers. 1. Prior to the occur? Hydro One did not Events. Notification Business (LOB). Major Even nts RESPONSE REPORT Issue: July 8 to 9, 2016 2.1.4.2 Major Eventt Response Report Date Issued: July 4, 2017 Prepared for: Publication and Electronicc Filing with the Ontario Energy Board (OEB)

More information

Introduction to Substation Design TADP 542

Introduction to Substation Design TADP 542 Introduction to Substation Design TADP 542 Design Principles- General Framework Instructor: Richard Snell Transmission & Distribution Program Module 2 Outline Presentation 1: General Framework Presentation

More information

ELECTRIC RELIABILITY:

ELECTRIC RELIABILITY: ELECTRIC RELIABILITY: Metrics and Reports in Iowa NARUC Energy Regulatory Partnership Program The Public Services Regulatory Commission of Armenia and The Iowa Utilities Board by Jeff Kaman Manager, Energy

More information

PROPOSAL EVALUATION: BWL ADVANCED DISTRIBUTION MANAGEMENT SYSTEM (ADMS)

PROPOSAL EVALUATION: BWL ADVANCED DISTRIBUTION MANAGEMENT SYSTEM (ADMS) November 28, 2016 PROPOSAL EVALUATION: BWL ADVANCED DISTRIBUTION MANAGEMENT SYSTEM (ADMS) The BWL has completed the evaluation for BWL Advanced Distribution Management System (ADMS) and the work has been

More information

SEMS Emergency Operations Center (EOC) Course for Schools. Orange County Emergency Management Organization Schools Committee

SEMS Emergency Operations Center (EOC) Course for Schools. Orange County Emergency Management Organization Schools Committee SEMS Emergency Operations Center (EOC) Course for Schools Orange County Emergency Management Organization Schools Committee Nine SEMS EOC Course Modules SEMS Overview [C1] Disaster Management Principles

More information

PPL Electric Utilities Summer Readiness Overview June 2018

PPL Electric Utilities Summer Readiness Overview June 2018 SUMMARY PPL Electric Utilities Summer Readiness Overview June 2018 For PPL Electric Utilities (PPL Electric), summer readiness means the company must respond effectively to summer storms as well as provide

More information

Water - Power Lifeline Interaction. Bob Lau 1 John M. Eidinger 2

Water - Power Lifeline Interaction. Bob Lau 1 John M. Eidinger 2 Water - Power Lifeline Interaction Bob Lau 1 John M. Eidinger 2 Abstract The interaction of water and power lifelines is described in three modes of operation: normal, fire and earthquake. Case study applications

More information

FAC Mapping to Proposed NERC Reliability Standard FAC RBS Draft 4 August 22, 2011

FAC Mapping to Proposed NERC Reliability Standard FAC RBS Draft 4 August 22, 2011 Standard FAC-003-1 Proposed Standard FAC-003-2 RBS Draft 4 Observations Definitions of Terms Definitions of Terms Used in Standard Right of Way A corridor of land on which electric lines may be located.

More information

Southwest TN EMC Tree Trimming

Southwest TN EMC Tree Trimming Southwest TN EMC Tree Trimming Trees are important for many reasons. They offer protection from the summer sun and the winter wind. They provide habitat for many species of animals and give children a

More information

LARA is an equal opportunity employer/program.

LARA is an equal opportunity employer/program. RICK SNYDER GOVERNOR STATE OF MICHIGAN DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS PUBLIC SERVICE COMMISSION GREG R. WHITE JOHN D. QUACKENBUSH SALLY A. TALBERG COMMISSIONER CHAIRMAN COMMISSIONER STEVE

More information

Revision Implementation

Revision Implementation 1910.269 Revision Implementation Utility Line Clearance Contractors Perspective Joseph F. Tommasi Corporate Director of Safety The Davey Tree Expert Company President The Utility Line Clearance Coalition

More information

The Benefits of Automating Vegetation Management Practices with Geospatial Solutions. Francisco Sarmento, Progress Energy Kecia Pierce, Intergraph

The Benefits of Automating Vegetation Management Practices with Geospatial Solutions. Francisco Sarmento, Progress Energy Kecia Pierce, Intergraph The Benefits of Automating Vegetation Management Practices with Geospatial Solutions Francisco Sarmento, Progress Energy Kecia Pierce, Intergraph Agenda Regulatory Requirement of Vegetation Management

More information

E(Orlando, Florida, U.S.), knocking

E(Orlando, Florida, U.S.), knocking Fleet Tracking Enables Efficient Crew Dispatch Progress Energy Florida integrates OMS, AVL to create mobile outage management system. By Claude Pitts, Progress Energy Florida arlier this year, a violent

More information

Standard FAC Transmission Vegetation Management Program

Standard FAC Transmission Vegetation Management Program A. Introduction 1. Title: Transmission Vegetation Management Program 2. Number: FAC-003-1 3. Purpose: To improve the reliability of the electric transmission systems by preventing outages from vegetation

More information

Recent Challenges with Storm Recovery. Safety First and Always

Recent Challenges with Storm Recovery. Safety First and Always Recent Challenges with Storm Recovery Eversource Profile We are one company focused on delivering safe, reliable energy and superior customer service. Safely providing energy to 3.6 million customers in

More information

Vegetation Management Plan

Vegetation Management Plan Vegetation Management Plan TABLE OF CONTENTS SECTION TITLE PAGE NUMBER 1. INTRODUCTION 2 2. SAFETY 3 3. RELIABILITY 3 4. VEGETATION MANAGEMENT GUIDELINES 4 5. NEW RIGHT OF WAY GUIDELINES 6 6. VEGETATION

More information

YOUR TREES ARE IMPORTANT.

YOUR TREES ARE IMPORTANT. YOUR TREES ARE IMPORTANT. We know your trees are extremely important to you. We understand that many of your trees are nearing the end of their lifecycle and are therefore vulnerable. There are options

More information

What new capabilities

What new capabilities White Paper Emerging Trends in Analytics What new capabilities mean for distribution grid management Kent Hedrick Director of Grid Management Solutions at Landis+Gyr Future. Ready. SM July 2014 Analytics

More information

Algoma Power Inc (API) Major Event Day Report Report (October 4, 2018)

Algoma Power Inc (API) Major Event Day Report Report (October 4, 2018) Algoma Power Inc (API) Major Event Day Report Report (October 4, 2018) Introduction A storm front with thunderstorms and intense winds rolled through the API region during the overnight and early morning

More information

Transmission Line Worker

Transmission Line Worker COMPETENCY-BASED OCCUPATIONAL FRAMEWORK FOR REGISTERED APPRENTICESHIP Transmission Line Worker ONET Code: 49-9051 RAPIDS Code: 0282 Created: February 2018 Updated: This project has been funded, either

More information

National Grid s Approach to Commissioning of Smart Grid Pilot Devices. J. VALENZUELA M.L. COOPER National Grid USA

National Grid s Approach to Commissioning of Smart Grid Pilot Devices. J. VALENZUELA M.L. COOPER National Grid USA 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2015 Grid of the Future Symposium National Grid s Approach to Commissioning of Smart Grid Pilot Devices J. VALENZUELA

More information

Pepco s Reliability Enhancement Model Using Predictive Reliability to Plan Investment in Electrical Infrastructure

Pepco s Reliability Enhancement Model Using Predictive Reliability to Plan Investment in Electrical Infrastructure 1 Pepco s Reliability Enhancement Model Using Predictive Reliability to Plan Investment in Electrical Infrastructure General Meeting of the IEEE Power Engineering Society Panel Discussion Predictive Reliability

More information

EMERGENCY SUPPORT FUNCTION #12 ENERGY

EMERGENCY SUPPORT FUNCTION #12 ENERGY EMERGENCY SUPPORT FUNCTION #12 ENERGY ESF COORDINATOR: LEAD AGENCY: SUPPORT AGENCIES: Public Works Director Public Works Department Puget Sound Energy Emergency Operations Center Zone 1 Emergency Coordinator

More information

JOB POSTING Traverse City Light & Power

JOB POSTING Traverse City Light & Power JOB POSTING Traverse City Light & Power Announcement No. 18-003LP March 6, 2018 JOURNEYMAN ELECTRIC LINE WORKER Traverse City Light & Power (TCL&P), a municipally owned electric utility in Traverse City,

More information

Frontiers in Energy Research Resilience of Electric Power Supply Systems Max Didier

Frontiers in Energy Research Resilience of Electric Power Supply Systems Max Didier 1 Frontiers in Energy Research Resilience of Electric Power Supply Systems Max Didier Contributors: Salome Baumberger, Marco Broccardo, Eric Delé, Simona Esposito, Siddhartha Ghosh, Benedikt Grauvogl,

More information

Mitigation Plan Mission, Goals and Action Items

Mitigation Plan Mission, Goals and Action Items Section 4: Mitigation Plan Mission, Goals and Action Items Introduction... 2 Mission... 2 Mitigation Plan Goals... 2 Natural Hazard Mitigation Plan Action Items... 3 Coordinating Organization... 4 Partner

More information

Post Incident Action Report December 2016 Ice Storm

Post Incident Action Report December 2016 Ice Storm Post Incident Action Report December 2016 Ice Storm Planning Chiefs: Alan Fraser, Mike McCann, and Tyler Nice Date: March 24, 2017 TABLE OF CONTENTS INTRODUCTION... 2 EVENT SUMMARY... 2 STAFFING METRICS...

More information

Distribution Systems - Program 128

Distribution Systems - Program 128 Distribution Systems - Program 128 Program Description Program Overview Utility distribution systems are challenged by an aging infrastructure, conventional designs, and increased demands for power. Electricity

More information

LONG ISLAND LONG ISLAND

LONG ISLAND LONG ISLAND Utility 2.0 Long Range Plan 1 The proposed Utility 2.0 investments are designed to benefit all Long Island customers. Our Utility 2.0 proposal is a component of a broader set of solutions to improve reliability

More information

Meeting Connection. Customers unable to attend the meeting in person may participate by phone and webinar.

Meeting Connection. Customers unable to attend the meeting in person may participate by phone and webinar. Meeting Connection In compliance with Commission Decision D.16-01-008, PacifiCorp has scheduled a public inperson presentation to review the company s annual reliability report submitted to the Commission

More information

ISOLATION & BARRIER PROCESS WHEN TESTING RELAY AND CONTROL EQUIPMENT

ISOLATION & BARRIER PROCESS WHEN TESTING RELAY AND CONTROL EQUIPMENT Page 1 of 7 ISOLATION & BARRIER PROCESS WHEN TESTING RELAY AND CONTROL EQUIPMENT Table of Contents I. SCOPE... 2 II. DEFINITIONS... 2 III. SAFETY... 2 IV. ISOLATION & BARRIER PROCESS WHEN TESTING RELAY

More information

Utility Vegetation Management & GIS

Utility Vegetation Management & GIS Utility Vegetation Management & GIS Designing A Mobile Geospatial application to streamline field collection & recordkeeping Joshua DeWees Spoon River Electric Cooperative Agenda I. Background II. Case

More information

Page 3, first paragraph in the Task Force on Reliability Indices report should be Joe Viglietta stated

Page 3, first paragraph in the Task Force on Reliability Indices report should be Joe Viglietta stated DRAFT dated Feb 1 st, 2006 Working Group on Distribution Reliability 2006 IEEE/PES Winter Technical Meeting January 17th, 2006 Draft Minutes Las Vegas, Nevada John McDaniel, Vice-Chair, (mcdanielj@dteenergy.com)

More information

Extreme Weather Event Analysis & System Hardening Qualifications

Extreme Weather Event Analysis & System Hardening Qualifications Prepared by: Quanta Technology, LLC Contact: Carl L. Wilkins, P.E. cwilkins@quanta-technology.com 4020 Westchase Blvd., Suite 300 Raleigh, NC 27607 (919) 334-3092 office (919) 279-5848 cell Quanta Technology

More information

DIRECT TESTIMONY OF THE ELECTRIC RELIABILITY PANEL

DIRECT TESTIMONY OF THE ELECTRIC RELIABILITY PANEL BEFORE THE NEW YORK STATE PUBLIC SERVICE COMMISSION ----------------------------------------------------------------------------x Proceeding on Motion of the Commission as to the Rates, Charges, Rules

More information

IMPROVING ELECTRIC SERVICE RELIABILITY

IMPROVING ELECTRIC SERVICE RELIABILITY Energy IMPROVING ELECTRIC SERVICE RELIABILITY EMPLOYING EMERGING TECHNIQUES TO SOLVE AGE-OLD PROBLEMS THE GROWING IMPORTANCE OF RELIABILITY Electricity reliability is becoming ever more important and visible

More information

Re: Docket No EU - Review of electric utility hurricane preparedness and restoration actions. To Whom It May Concern:

Re: Docket No EU - Review of electric utility hurricane preparedness and restoration actions. To Whom It May Concern: Cover Letter Lakeland Electric Re: - Review of electric utility hurricane preparedness and restoration actions. To Whom It May Concern: The following pages are answers to the proposed questions. The questions

More information

FOURTH Quarter REPORT

FOURTH Quarter REPORT 4 1 FOURTH Quarter REPORT FISCAL YEAR 2017 austinenergy.com BENEFITS OF PUBLIC POWER More than just getting the lights back on Hurricane Harvey wreaked havoc on the Gulf Coast when it made landfall, but

More information

SCHEDULE 1. MANITOBA EMERGENCY MANAGEMENT SYSTEM Ver INTRODUCTION. 1.1 General Emergency Response

SCHEDULE 1. MANITOBA EMERGENCY MANAGEMENT SYSTEM Ver INTRODUCTION. 1.1 General Emergency Response SCHEDULE 1 MANITOBA EMERGENCY MANAGEMENT SYSTEM Ver. 2.3 1.0 INTRODUCTION 1.1 General Emergency Response Most emergencies are resolved within a comparatively short time by emergency responders attending

More information

Position Description

Position Description Date: April 17, 2015 Position Description Position Title: Apprentice Lineman 1A, 1B, 2 and 3 Reports To: Region Line Manager Revision Date: May 2015; May 2016 Performance Factors Level: Safety 2 Innovation

More information

Educating System Operators in the New Millennium! Background. Course Level. Target Audience. NERC Continuing Education Hours

Educating System Operators in the New Millennium! Background. Course Level. Target Audience. NERC Continuing Education Hours Background The class will be delivered over a 3-day period. The class is comprised of three training modules covering the areas of: Communications, Critical Thinking, and Restoration. The course consists

More information

Dear New Member: to welcome you as a member and. owner of Rappahannock Electric Cooperative

Dear New Member: to welcome you as a member and. owner of Rappahannock Electric Cooperative Dear New Member: I am pleased to welcome you as a new member and owner of Rappahannock Electric Cooperative (REC). Being a member of one of the most progressive Cooperatives in the country, you now have

More information

Eversource Emergency Response Plan Electric (MA)

Eversource Emergency Response Plan Electric (MA) Eversource Energy Emergency Response Program PLAN Eversource Emergency Response Plan Electric (MA) EP-MAE-PLN-2000 Revision 0 5/13/2016 Approval: Signature: Craig A. Hallstrom Name: Craig A. Hallstrom

More information

PSE&G Assumptions Overview. November 2018

PSE&G Assumptions Overview. November 2018 PSE&G Assumptions Overview November 2018 1 Base Case Models Base Case Model will includes PSE&G 69kV network PJM RTEP models shall be for assessments of RTEP years Multi-regional Modeling Working Group

More information

Effective Project Control using an Automated Gated Process Workflow and Project Scalability

Effective Project Control using an Automated Gated Process Workflow and Project Scalability Effective Project Control using an Automated Gated Process Workflow and Project Scalability Dan Cohen Manager, Project Management Foundational Capability April 22, 2016 1 DTE Energy, a Diversified Energy

More information

nts Issue: April 18 th, 2018 Date Issued: Summary about 11%) of customers. 1. Prior to the occur? Province. 3) If the public Major Event warning of

nts Issue: April 18 th, 2018 Date Issued: Summary about 11%) of customers. 1. Prior to the occur? Province. 3) If the public Major Event warning of Major Even nts RESPONSE REPORT Issue: April 7 th to 9 th, 2017 2.1. 4.2 Major Events Response Report Date Issued: April 18 th, 2018 Prepared for: Publication and Electronicc Filing with the Ontario Energy

More information

LETTER AGREEMENT NO. R PGE

LETTER AGREEMENT NO. R PGE LETTER AGREEMENT NO. R1 05 21 PGE PACIFIC GAS AND ELECTRIC COMPANY INDUSTRIAL RELATIONS DEPARTMENT 2850 SHADELANDS DRIVE, SUITE 100 WALNUT CREEK, CALIFORNIA 94598 (925) 974-4104 INTERNATIONAL BROTHERHOOD

More information

An Garda Síochána. Global Energy Management System Implementation: Case Study. Republic of Ireland

An Garda Síochána. Global Energy Management System Implementation: Case Study. Republic of Ireland Global Energy Management System Implementation: Case Study An Garda Síochána Total cumulative energy cost savings of $11.3m since baseline year 2009. An Garda Síochána are the first national police force

More information

Living on borrowed time

Living on borrowed time Power & Utilities Of special interest to Chief operating officers Chief risk officers Vice presidents of tax Insights for 5executives Living on borrowed time Protecting utilities and the public from aging

More information

PRINCE GEORGE FIRE & EMS

PRINCE GEORGE FIRE & EMS PRINCE GEORGE FIRE & EMS Six-Month Work Plan January June 2012 Prepared by: James B. Owens Deputy Director Prince George Fire and EMS PRINCE GEORGE FIRE & EMS Six-Month Work Plan 2 TABLE OF CONTENTS Executive

More information

Policy PEOPLE S ENERGY COOPERATIVE. To state the policy regarding vegetation management.

Policy PEOPLE S ENERGY COOPERATIVE. To state the policy regarding vegetation management. Policy PEOPLE S ENERGY COOPERATIVE NUMBER: 206 SUBJECT: OBJECTIVE: Right-of-way Vegetation Management To state the policy regarding vegetation management. POLICY: Maintaining adequate vegetation clearance

More information

TABLETOP EXERCISE. Oregon Water/Wastewater Agency Response Network (ORWARN) Williamette Valley Freeze

TABLETOP EXERCISE. Oregon Water/Wastewater Agency Response Network (ORWARN) Williamette Valley Freeze Willamette Valley Freeze TABLETOP EXERCISE Oregon Water/Wastewater Agency Response Network (ORWARN) Welcome Discuss agenda for the day Introductions Review administrative details Start the exercise Review

More information

Engaging Our Team Investing in Our Infrastructure Employing Best Technology Exceptional Customer Service

Engaging Our Team Investing in Our Infrastructure Employing Best Technology Exceptional Customer Service Engaging Our Team Investing in Our Infrastructure Employing Best Technology Exceptional Customer Service 1 Our Mission We ensure safe and reliable services of water, wastewater and electricity, at an affordable

More information

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES --------------------------------------------- GAINESVILLE RENEWABLE ENERGY CENTER OPERATING PROCEDURES Revision 0; September 1, 2012 Revision 1; November

More information

1. INTRODUCTION. Operational Excellence Model. 1.1 Purpose. 1.2 Scope. 1.3 Rate Schedule. 1.4 Cooperation

1. INTRODUCTION. Operational Excellence Model. 1.1 Purpose. 1.2 Scope. 1.3 Rate Schedule. 1.4 Cooperation 1. 1.1 Purpose 1.2 Scope The purpose of this book is to present information and specifications relative to the introduction and use of electricity supplied by PSEG Long Island. This book is to be used

More information

Residential and Small Business Customer Consultation WELCOME

Residential and Small Business Customer Consultation WELCOME Residential and Small Business Customer Consultation WELCOME 1 SYSTEM OPERATOR/DISPATCHER THE REGULATOR TRANSMITTER YOUR LOCAL DISTRIBUTION COMPANY Who we are Centre Wellington Hydro is a Local Distribution

More information

GIS Data Is Actually Important!

GIS Data Is Actually Important! 1 1. Context 2. The Requirements 3. PSNH Context 4. PSNH Challenges 5. Solutions 6. Opportunities 7. Discussion March 5, 2013 Robert Sarfi Thomas Mitchell RSarfi@BoreasGroup.us Thomas.Mitchell@nu.com (720)

More information

Intelligent Load Management

Intelligent Load Management T H E O F F I C I A L P U B L I CAT I O N O F 12 Save Money With Substation Maintenance 22 Grid-Tied Wind Energy Systems 28 Distributed Energy Storage and Utilities, Commercial Buildings Intelligent Load

More information

Business Continuity Through Planning, Prevention and Preparedness. READINESS RESOURCES

Business Continuity Through Planning, Prevention and Preparedness.  READINESS RESOURCES READINESS RESOURCES Federal Emergency Management Agency -- www.fema.gov Emergency Management Guide for Business & Industry: http://www.fema.gov/pdf/business/guide/bizindst.pdf American Red Cross -- www.redcross.org

More information

IMPROVING OUTAGE PERFORMANCE: THE OUTAGE OPTIMIZATION PROCESS

IMPROVING OUTAGE PERFORMANCE: THE OUTAGE OPTIMIZATION PROCESS IMPROVING OUTAGE PERFORMANCE: THE OUTAGE OPTIMIZATION PROCESS Jere LaPlatney VP Outage Optimization Jean-Paul Bombail Outage and Maintenance IB France 17-21 October 2011 AGENDA BACKGROUND OUTAGE OPTIMIZATION

More information