CROSSTOWN LRT Construction Liaison Committee November 1, 2017

Size: px
Start display at page:

Download "CROSSTOWN LRT Construction Liaison Committee November 1, 2017"

Transcription

1 CROSSTOWN LRT Construction Liaison Committee November 1, 2017

2 Avenue Construction Updates 2

3 Avenue Station: What to Expect November & December 2017 Short Term Activities Area Duration Connection borehole and tunnel concrete pour Dewatering work (overnight work) Dewatering work (daytime) Installation pumps and trenching for connection pipes Sewer bypass (daytime) and Sewer lining (24 hour work) At Eglinton and Highbourne Centre line of Eglinton from Braemar to Lascelles, including crossing Avenue Road Eglinton north and south side from Oriole Pkwy to Lascelles Eglinton between Braemar and Lascelles, including crossing Avenue Road 1-2 days remaining to complete drilling 2 weeks concrete pour - upcoming 1-2 weeks preparatory works - completed 1-2 weeks drilling underway Approx. 2 weeks remaining 4 6 weeks Sewer bypass installation underway Watermain lining Eglinton from Avenue to Oriole Parkway 2 weeks Pre-inspections for temporary service connections underway 3

4 Avenue Station: What to Expect November & December 2017 Short Term Activities Area Duration Connection borehole and tunnel concrete pour Crane installation at both entrances Monitoring instruments (installations, surveying and monitoring) Eglinton and just west of Avenue Road December/January 2 weeks drilling 2 weeks concrete pour Main and Secondary Entrances Delivered and installed during 1 week Secondary Entrance mid November Eglinton from Braemar Blvd to Lascelles Blvd Increased frequency of survey/monitoring crews Installations complete in early

5 Avenue Station: Start of 24 Hour Mining Long Term Construction Activity Area Duration Beginning of 24 hour mining work at Secondary Entrance Beginning of 24 hour mining work at Main Entrance Secondary Entrance November Main Entrance January Mining operations are included in the 2010 Toronto Transit Project Noise By-Law Exemption to allow for tunneling and related work to occur 24 hours a day. A robust noise reduction plan based on major international projects such as the Boston Big Dig, Crossrail in London and the Thames Tideway Tunnel has been developed to minimize impacts on the local community. Implement noise reduction measures at the station construction sites Continually monitor noise and vibration throughout construction Adjust noise reduction measures at the construction sites as required If necessary, consider additional measures for residences in potentially sensitive zone Ensure proactive communications with the community before and during construction 5

6 Sewer Lining Update Sewer bypass installation (underway) Bypass pipes and equipment will be in place until lining of the larger sewer line is completed Sewer Lining (November) 3 weeks of work, approximately 3 days of work per section Overnight work required for lining operations occur on a continuous basis for the 3 days per section Overnight work required to avoid sewer/water service disruption to businesses and residences during daytime hours On Eglinton Ave from Braemar to Lascelles, and small section on Avenue Road, Oriole Pwky and Highbourne 6

7 Watermain Lining November Temporary Water Connections for Watermain lining (150mm main) Activity will take approximately 2 weeks Minimal overnight work required (for connections ) to avoid water service disruption to businesses and residences during daytime hours Properties on north side of Eglinton, from Avenue to Oriole Pwky will be connected to temporary water supply Properties will be connected to the temporary services from a feeder pipe in the laneway. Details are currently being determined based on visits to properties. Minor trenching work possible in laneway to accommodate temporary water connections Minor trenching work between 256 and 250 Eglinton Avenue West to connect to the water supply for the temporary water service connections Installation of water valve on 300mm watermain late 2017 Activity will take approximately 1 week of work Sidewalk in front of 259 Eglinton Ave 7

8 Tunnel Backfilling Prior to mining works, CTS must fill portions of the tunnels with concrete, this involves drilling from the surface all the way to the TBM tunnels. There are two separate phases to this work. Phase 2 Concrete Pouring - Upcoming Crews will complete the concrete pours one area at a time. Each area will take approximately 2 weeks to complete the concrete pouring. A work zone will be set up around the concrete trucks as they pour, and it will be taken down nightly. Concrete pour work will occur between 7:00AM and 11:00PM. During the pouring phase, there will be an increase truck flow to deliver the concrete to the site. Once the concrete pouring is complete the roadway holes will be filled and restored. 8

9 Avenue Station - Main Entrance Progress September 2016 June 2016 May 2017 September

10 Avenue Station Secondary Entrance Progress October 2016 April 2016 June 2017 October

11 Avenue Station - Aerial View 90% Design Rendering 11

12 Avenue Station Main Entrance 90% Design Rendering 12

13 Avenue Station Main Entrance 90% Design Rendering 13

14 Avenue Station Secondary Entrance 90% Design Rendering 14

15 Avenue Station Area Map 15

16 Chaplin Construction Updates 16

17 Chaplin Station Construction Update October 2017 Demobilize Tertiary Entrance site Telecommunications (Bell) utilities relocation within the southwest station box area Installation of special piles at the south east station box area November 2017 Continue sanitary sewer installation Commence piling at the southeast corner of Chaplin Cres and Eglinton Ave W Implement new traffic stage on the north side of Eglinton Ave W Nov 1 Commence hydro utilities relocation at the northeast station box area Commence piling at the northeast station box area December 2017 Overnight diversion of existing combined sewer

18 Chaplin Station 2017 Look Ahead Year Quarter Construction Activity Q1 Q4 (October- December) (January-March) Utilities Relocation: Hydro Relocation Sanitary Sewer Installation Support of Excavation: Piling at Northeast Station Box Piling at Southeast Station Box Utilities Relocation: Sanitary Sewer Installation Temporary Watermain Bypass Support of Excavation: Piling at North Station Box Shallow Excavation and Roof Slab Construction

19 Chaplin Station: Current Construction Staging November 1 for approximately three (3) months

20 Chaplin Station Concept: Aerial View Tertiary Entrance Secondary Entrance Main Entrance *60% rendering

21 Chaplin Station Construction Progress GUIDEWALL INSTALLTION TORQUING BOLTS FOR SPECIAL PILE TERTIARY ENTRANCE PILES 21 PREP WORK FOR TRAFFIC FLIP

22 Local Area Map Station(s) under construction 22

Eglinton Crosstown LRT Construction Liaison Committee

Eglinton Crosstown LRT Construction Liaison Committee Eglinton Crosstown LRT Construction Liaison Committee May 30, 2017 Agenda Eglinton Crosstown LRT Overview Eglinton Maintenance & Storage Facility Mount Dennis Station Railway Corridor West Portal & Elevated

More information

EGLINTON CROSSTOWN Fairbank Oakwood CLC April 19, 2018

EGLINTON CROSSTOWN Fairbank Oakwood CLC April 19, 2018 EGLINTON CROSSTOWN Fairbank Oakwood CLC April 19, 2018 INFORMATION IS CURRENT AS OF APRIL 19, 2018 AND SUBJECT TO CHANGE 2 Agenda Caledonia Station Update Fairbank Station Update Oakwood Station Update

More information

WHO IS METROLINX? PLAN BUILD OPERATE

WHO IS METROLINX? PLAN BUILD OPERATE CROSSTOWN LRT WHO IS METROLINX? PLAN BUILD OPERATE THE NEXT REGIONAL TRANSPORTATION PLAN Metrolinx is currently in the process of updating the Regional Transportation Plan (RTP). The Draft Plan (2041)

More information

2

2 CROSSTOWN LRT 2 3 4 5 6 Construction of the Eglinton Crosstown LRT Line Background In September 2008, Metrolinx launched a regional transportation plan a 25-year, $50 billion plan -- to coordinate and

More information

3.6 Construction Methods

3.6 Construction Methods Exhibit 144: Birchmount Stop Layout West Don River Bridge - Girders are adequate to accommodate LRT right-of-way and required deck widening. Supplementary support or deck strengthening may be required

More information

DETROIT RIVER INTERNATIONAL CROSSING STUDY MAG

DETROIT RIVER INTERNATIONAL CROSSING STUDY MAG DETROIT RIVER INTERNATIONAL CROSSING STUDY MAG Meeting September 5 th, 2006 1 Agenda 1. Study Update 2. Construction Staging for Tunneling 3. Other Business 2 Deep Borehole Program 3 Status Update - Engineering

More information

WELCOME LOCAL SEGMENT PUBLIC MEETING SUMMARY OF PRELIMINARY RESULTS CORRIDOR EVALUATION

WELCOME LOCAL SEGMENT PUBLIC MEETING SUMMARY OF PRELIMINARY RESULTS CORRIDOR EVALUATION WELCOME LOCAL SEGMENT PUBLIC MEETING SUMMARY OF PRELIMINARY RESULTS CORRIDOR EVALUATION Relief Line Study Area and Process Relief Line Project Assessment Primary Study Area Background 2009 City Council

More information

COMMUNITY BOARD EIGHT

COMMUNITY BOARD EIGHT SECOND AVENUE SUBWAY PROJECT COMMUNITY BOARD EIGHT PROJECT UPDATE SEPTEMBER 26, 2011 Scope: SECOND AVENUE SUBWAY - PHASE 1 Tunnels from 92 nd St to 63 rd St Stations at 96 th St, 86 th St, 72 nd St and

More information

Second Avenue Subway

Second Avenue Subway Second Avenue Subway Community Board 8 Second Avenue Subway Task Force Update January 22, 2015 Tom Peyton Second Avenue Subway Project Director 0 Scope: Q train service Tunnels from 92nd St to 63rd St

More information

CROSSTOWN LRT Science Centre June 15, 2017

CROSSTOWN LRT Science Centre June 15, 2017 CROSSTOWN LRT Science Centre June 15, 2017 WHO IS METROLINX? 2 3 Construction of the Eglinton Crosstown LRT Line Background In September 2008, Metrolinx launched a regional transportation plan a 25-year,

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Downtown & Mid-Corridor Project Status Update Meeting Holman United Methodist Church Thursday, July 23, 2009 Phase 1 Project Description 8.6 mile corridor from Downtown

More information

Replacement of the Existing Water Siphons between Brooklyn and Staten Island Siphon Project

Replacement of the Existing Water Siphons between Brooklyn and Staten Island Siphon Project August 2011 Update Replacement of the Existing Water Siphons between Brooklyn and Staten Island Siphon Project The New York City Economic Development Corporation (EDC) is administering the Replacement

More information

Preferred Elevated Tank Site

Preferred Elevated Tank Site Preferred Elevated Tank Site Preferred Site No. 3 is on private property owned by Hopewell Developments. Approximately 5 acres of land will be required, including lands required for a permanent access

More information

TRUNK SEWER RELOCATIONS AT 900 ALBERT STREET SERVICING, CONSTRUCTABILITY AND MAINTENANCE REPORT

TRUNK SEWER RELOCATIONS AT 900 ALBERT STREET SERVICING, CONSTRUCTABILITY AND MAINTENANCE REPORT P a g e 0 Prepared for: Trinity Development Group, Inc. TRUNK SEWER RELOCATIONS AT 900 ALBERT STREET SERVICING, CONSTRUCTABILITY AND MAINTENANCE REPORT OTTAWA, ON November 2016 P a g e 1 TABLE OF CONTENTS

More information

Ground Freezing for Tunnel, Shafts, and Adits

Ground Freezing for Tunnel, Shafts, and Adits Ground Freezing for Tunnel, Shafts, and Adits Joseph A. Sopko, Adam Curry Moretrench American Corporation Bianca Messina Skanska USA Civil Stephen Njoloma McMillen Jacobs Associates ABSTRACT Construction

More information

Venice Pumping Plant Dual Force Main Project Draft EIR

Venice Pumping Plant Dual Force Main Project Draft EIR City of Los Angeles Venice Pumping Plant Dual Force Main Project Draft EIR 4.0 ALTERATIVES UDER COSIDERATIO Alternatives under consideration for this Project are defined by the alignment and construction

More information

Purple Line Extension Section 2 Community Meeting September 28, 2017

Purple Line Extension Section 2 Community Meeting September 28, 2017 Purple Line Extension Section 2 Community Meeting September 28, 2017 Agenda Century City/Constellation Station Advance Utility Relocation (AUR) Launch Box Geotech/potholing Rodeo Drive Station Advance

More information

Purple Line Extension. Beverly Hills Community Meeting August 22, 2016

Purple Line Extension. Beverly Hills Community Meeting August 22, 2016 Purple Line Extension Beverly Hills Community Meeting August 22, 2016 1 3 Purple Line Extension Project Alignment 2 Section 2 and 3 Status Under Construction Forecasted Schedule Section 1 Section 2 Section

More information

Progress update (November to March) 03/23/2009 2

Progress update (November to March) 03/23/2009 2 Second Avenue Subway Construction Progress Update (November to March) Presented by S3 Tunnel Constructors AND MTA CAPITAL CONSTRUCTION March 23, 2009 1 Topics Covered Progress update (November to March)

More information

COMMUNITY BOARD EIGHT

COMMUNITY BOARD EIGHT SECOND AVENUE SUBWAY PROJECT COMMUNITY BOARD EIGHT PROJECT UPDATE February 15, 2011 SECOND AVENUE SUBWAY - PHASE 1 Scope: Tunnels from 92 nd St to 63 rd St Stations at 96 th St, 86 th St, 72 nd St and

More information

2.0 PROJ ECT D ESCRI PTION

2.0 PROJ ECT D ESCRI PTION 2.0 PROJ ECT D ESCRI PTION 2.1 PROJECT LOCATION The proposed project is in the City of Los Angeles (Figure 2.1-1, Regional Project Location Map) in the communities of Venice and Playa Del Rey (see Figure

More information

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer APPENDIX I Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer THE CITY OF BARRIE PROJECT NO. 15M-00594-01 CONCEPTUAL DESIGN SALEM ROAD AND MCKAY ROAD TRUNK WATERMAIN AND SANITARY

More information

Plessis Road Twinning and Grade Separation at CN Redditt Subdivision: Design Challenges and Innovative Solutions

Plessis Road Twinning and Grade Separation at CN Redditt Subdivision: Design Challenges and Innovative Solutions Plessis Road Twinning and Grade Separation at CN Redditt Subdivision: Design Challenges and Innovative Solutions Tanya D. Worms, P.Eng. M.Sc., Project Manager, M.D. Steele Construction Ltd. Paper prepared

More information

Purple Line Extension Section 1 Construction Community Meeting September 26, 2017

Purple Line Extension Section 1 Construction Community Meeting September 26, 2017 Purple Line Extension Section 1 Construction Community Meeting September 26, 2017 1 Agenda Sections 1 & 2 Section 1 Construction Updates TBM Art and Naming Contest Project Construction Updates: Wilshire/Western

More information

The Regional Municipality of Peel Basis of Payment

The Regional Municipality of Peel Basis of Payment Page PS-1 THE REGIONAL MUNICIPALITY OF PEEL BASIS OF PAYMENT FOR SANITARY SEWER CONSTRUCTION Page PS-2 INDEX Page No. PS.1. EXCAVATION...4 1.1. Trench Excavation...4 1.2. Asphalt/Concrete Removal...5 PS.2.

More information

Constructability Guidelines

Constructability Guidelines Constructability Guidelines The Constructability Guidelines offer a list of items that should be considered by Constructability function personnel during the Concept Development Phase through the Final

More information

Eastside Transit Corridor Phase 2

Eastside Transit Corridor Phase 2 Eastside Transit Corridor Phase 2 Community Meeting, June 22, 2016 Page 1 Purpose of Tonight s Meeting Page 2 Update on Metro Board directed Technical Study (Nov. 2014) SR-60 Alternative Washington Blvd

More information

April 6, To The Property Owners, Tenants. Re: Invitation to Attend a Public Information Session Eagle Hill Lane Reconstruction

April 6, To The Property Owners, Tenants. Re: Invitation to Attend a Public Information Session Eagle Hill Lane Reconstruction April 6, 2017 To The Property Owners, Tenants Re: Invitation to Attend a Public Information Session Eagle Hill Lane Reconstruction The is proposing to reconstruct Eagle Hill from Cooper Street to Cooper

More information

Woodbridge Redevelopment Update. CLC Meeting #6 Wednesday, December 13, 2017

Woodbridge Redevelopment Update. CLC Meeting #6 Wednesday, December 13, 2017 Woodbridge Redevelopment Update CLC Meeting #6 Wednesday, December 13, 2017 1. Introductions Agenda 2. Project Updates 3. Construction Updates Progress to Date What s Happening Now 3 Month Schedule 4.

More information

To The Property Owners, Tenants Re: Invitation to Attend a Public Information Centre Spruce Street and Briercrest Avenue Reconstruction

To The Property Owners, Tenants Re: Invitation to Attend a Public Information Centre Spruce Street and Briercrest Avenue Reconstruction March 7, 2016 To The Property Owners, Tenants Re: Invitation to Attend a Public Information Centre Spruce Street and Briercrest Avenue Reconstruction The City of Cambridge is proposing to reconstruct Spruce

More information

GENERAL NOTES FOR FORCE MAINS: *CONTACTOR SHALL HAVE RICHMOND UTILITIES PERSONNEL ON SITE WHEN DIGGING OVER OR AROUND UTILITY LINES AND PUMP STATIONS. CONTRACTOR SHALL SCHEDULE EXCAVATION WITH RICHMOND

More information

The Corporation of The City of London

The Corporation of The City of London The Corporation of The City of London Legislative Health and Safety Requirements The following is a health and safety guide for those providing a tender to assist in determining legislative health and

More information

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service.

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service. CHAPTER3 Clark Public Utilities Commercial Electric Service Handbook Commercial Underground Services Preparing for the installation The following checklist will assist in preparing a project for the installation

More information

Trenchless Crossing of a Failure Prone Watermain in Poor Soil Conditions

Trenchless Crossing of a Failure Prone Watermain in Poor Soil Conditions Trenchless Crossing of a Failure Prone Watermain in Poor Soil Conditions Case Study Trevor Kealey, P.Eng. R.V. Anderson Associates Limited TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention

More information

Community Meeting 1269 Danforth Road Traction Power Substation, No Frills and Winter Avenue Emergency Exit Buildings November 7, 2018

Community Meeting 1269 Danforth Road Traction Power Substation, No Frills and Winter Avenue Emergency Exit Buildings November 7, 2018 1 Community Meeting 1269 Danforth Road Traction Power Substation, No Frills and Winter Avenue Emergency Exit Buildings November 7, 2018 Community Meeting Overview Introductions (5 minutes) TTC, City of

More information

Dormay Street & King George s Park Community Liaison Working Group 12 October 2017

Dormay Street & King George s Park Community Liaison Working Group 12 October 2017 Dormay Street & King George s Park Community Liaison Working Group 12 October 2017 DORMAY STREET Dormay Street Overview This site will be used to connect the existing local combined sewer overflow to the

More information

DESIGN AND INSTALLATION OF THE SHORING AND DECKING FOR TTC YONGE STATION

DESIGN AND INSTALLATION OF THE SHORING AND DECKING FOR TTC YONGE STATION DESIGN AND INSTALLATION OF THE SHORING AND DECKING FOR TTC YONGE STATION INTRODUCTION By Dawn Tattle, P. Eng. Anchor Shoring & Caissons Ltd. TTC Yonge Station is the largest and most complicated of the

More information

Construction Look Ahead February 2018

Construction Look Ahead February 2018 To our 9 th and Colorado redevelopment neighbors: Construction Look Ahead February 2018 Block 7South Exterior Bridge walkway between Block 7 South building and the existing Parking Garage the installation

More information

OVERVIEW. Work Progress to Date Action Items Follow Up Community Relations Update Construction Phasing

OVERVIEW. Work Progress to Date Action Items Follow Up Community Relations Update Construction Phasing OVERVIEW Work Progress to Date Action Items Follow Up Community Relations Update Construction Phasing Construction Liaison Group Nov 7th, 2013 1 WORKS IN PROGRESS Construction Liaison Group Nov 7 th, 2013

More information

Mogden Sewage Treatment Works: 2011 updates

Mogden Sewage Treatment Works: 2011 updates Mogden Sewage Treatment Works: 2011 updates 20 December 2011 - Mogden Upgrade update Construction work to increase capacity at Mogden Sewage Treatment Works will wind-down for Christmas at 3pm on Friday

More information

How we would build the proposed storm relief sewer

How we would build the proposed storm relief sewer Counters Creek storm relief sewer How we would build the proposed storm relief sewer We would build the proposed Counters Creek storm relief sewer using the most advanced construction methods and we would

More information

Auburn University Construction Project Update June 2010

Auburn University Construction Project Update June 2010 New Basketball Arena: Construction Cost: $68.5 million. The Arena achieved the Substantial Completion project milestone as of June 4 th, 2010. Punch list item work is ongoing. Work related to the project,

More information

Project Type: Drainage and Storm Systems

Project Type: Drainage and Storm Systems 580 Dakin Avenue Box Culvert & Utility Improvements Project $944,952 Improvements to approx. 3,000 lf of existing 4'x5' concrete box culvert; clean interior, patch surface, fill joints/cracks; install

More information

BARRY S CORNER. Draft Construction Management Plan

BARRY S CORNER. Draft Construction Management Plan 1. Introduction Project description BARRY S CORNER Draft Construction Management Plan 11-21-2013 Prepared for: Boston Transportation Department Project Proponent: Samuels & Associates Construction Manager

More information

ENGINEERING DESIGN & IMPROVEMENT STANDARDS

ENGINEERING DESIGN & IMPROVEMENT STANDARDS ENGINEERING DESIGN & IMPROVEMENT STANDARDS 2016 Prepared by: Engineering Division For latest edition of these Improvement Standards, refer to City of Visalia website at: www.visalia.city/engineeringdocuments

More information

Little Hunting Creek Community Meeting Mt. Vernon High School 12/11/2018

Little Hunting Creek Community Meeting Mt. Vernon High School 12/11/2018 Start 7:15 PM Approximately 27 people in attendance. Little Hunting Creek Community Meeting Mt. Vernon High School 12/11/2018 Tom Grala, Meredith Raetz went through a presentation of the results of the

More information

Westside Subway Extension

Westside Subway Extension Los Angeles County Metropolitan Transportation Authority Westside Subway Extension Community Update Meeting August 2009 Purpose of Tonight s Meeting Summary of Comments from Public Scoping Update on Alternatives

More information

4.0 CONSTRUCTION METHODS AND ACTIVITIES

4.0 CONSTRUCTION METHODS AND ACTIVITIES 4.0 CONSTRUCTION METHODS AND ACTIVITIES 4.1 Introduction This chapter describes the construction methods and activities that are expected to occur during construction of the Proposed Action. The potential

More information

DERRY GREEN BUSINESS PARK WATER AND WASTEWATER SERVICING AREA SERVICING PLAN

DERRY GREEN BUSINESS PARK WATER AND WASTEWATER SERVICING AREA SERVICING PLAN DERRY GREEN BUSINESS PARK WATER AND WASTEWATER SERVICING AREA SERVICING PLAN Submitted to: Town of Milton Regional Municipality of Halton Submitted by: AMEC Earth & Environmental 3215 North Service Road

More information

Purple Line Extension. Construction Community Meeting March 16, 2017

Purple Line Extension. Construction Community Meeting March 16, 2017 Purple Line Extension Construction Community Meeting March 16, 2017 1 Agenda Project Construction Updates: Western, La Brea, Fairfax and La Cienega La Brea Station Street Configuration Update Fairfax Decking:

More information

Stage 4 Geotechnical Investigations Information Sheet

Stage 4 Geotechnical Investigations Information Sheet Stage 4 Geotechnical Investigations Information Sheet Geotechnical specialists will use a range of equipment to examine ground conditions by either excavating small shallow test pits of soil, using a mechanical

More information

John Hart Generating Station Replacement Project. November 2017 Community Construction Update Report #53

John Hart Generating Station Replacement Project. November 2017 Community Construction Update Report #53 John Hart Generating Station Replacement Project November 2017 Community Construction Update Report #53 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Downtown Corridor USC Galen Center November 13, 2007 Project Summary 8.6 mile corridor from 7th/Metro to Culver City 1.3 miles shared with Metro Blue Line 10 stations,

More information

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018 Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018 1 Agenda Project Overview Section 1 Construction Updates Wilshire/La Cienega Station Excavation Section 2 Pre-Construction

More information

Dormay Street & King George s Park Community Liaison Working Group 15 June 2017

Dormay Street & King George s Park Community Liaison Working Group 15 June 2017 Dormay Street & King George s Park Community Liaison Working Group 15 June 2017 Community Liaison Working Group (CLWG) The CLWG will serve as a two-way communications channel between Tideway and local

More information

Index to Technical Specifications

Index to Technical Specifications Index to Technical Specifications Item Number Subject I II EXCAVATION 1.01 Trenching and Excavation Regulations 1.02 Site Grading or General Excavation 1.03 Structural Excavation 1.04 Trench Excavation

More information

Welcome to this information session on the proposed Bell Road Reservoir Replacement Project.

Welcome to this information session on the proposed Bell Road Reservoir Replacement Project. Haere mai Welcome to this information session on the proposed Bell Road Reservoir Replacement Project. This session is your opportunity to: meet the team find out more about the project understand our

More information

Equipment Guide shorten restoration times underground

Equipment Guide shorten restoration times underground Dominion Energy Virginia s Strategic Underground Program is a system-wide initiative to shorten restoration times following major storms by placing certain outage-prone overhead electric distribution lines

More information

Templeton Community Services District Eastside Force Main Improvements. Monthly Progress Report

Templeton Community Services District Eastside Force Main Improvements. Monthly Progress Report Templeton Community Services District Eastside Force Main Improvements Monthly Progress Report Prepared By: Kim Lindbery, Resident Engineer MKN & Associates, Inc. July 31, 2018 1 2 Schedule and Budget

More information

The Standards referred to shall be the most recent edition.

The Standards referred to shall be the most recent edition. Page 1 of 7 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described hereunder shall consist of the excavation of trenches and tunnels; the supply and installation of pipe and/or encasement pipe; the

More information

Please ensure receipt of this Addendum is acknowledged on page 1 of the Form of Tender.

Please ensure receipt of this Addendum is acknowledged on page 1 of the Form of Tender. No. 1 Project: 47th Ave Road Reconstruction Owner: District of Chetwynd Date: March 5, 2019 Ref. No.: 1320.0095.01 This Addendum is issued prior to Tender Closing Date, in accordance with the Tender Documents

More information

UC Press Building 2120 Berkeley Way Berkeley, CA

UC Press Building 2120 Berkeley Way Berkeley, CA CONSTRUCTION NOISE REDUCTION PROGRAM FOR: UC Press Building 2120 Berkeley Way Berkeley, CA RGD Project #: 17-057 PREPARED FOR: Berkeley Way, LLC 1958A University Ave. Berkeley, CA 94704 PREPARED BY: Harold

More information

INFORMATION SHEET WINTER 2013 CLOVER PUMP STATION & CONVEYANCE PIPE. Road to Ogden Point, then under the. to the Treatment Plant planned for

INFORMATION SHEET WINTER 2013 CLOVER PUMP STATION & CONVEYANCE PIPE. Road to Ogden Point, then under the. to the Treatment Plant planned for INFORMATION SHEET WINTER 2013 CLOVER PUMP STATION & CONVEYANCE PIPE Project Background As part of the Seaterra Program, Clover A new conveyance pipe (forcemain) Pump Station will be upgraded and will run

More information

HUDSON TUNNEL PROJECT

HUDSON TUNNEL PROJECT HUDSON TUNNEL PROJECT NORTH BERGEN COMMUNITY MEETING Lido Restaurant 2600 Tonnelle Avenue North Bergen, NJ January 30, 2018 6:00-8:00 PM Agenda Project Overview Construction Activities in North Bergen

More information

Tunnel Works. How we got here - Fort Wayne s Consent Decree. Tunnel Works Program Frequently Asked Questions

Tunnel Works. How we got here - Fort Wayne s Consent Decree. Tunnel Works Program Frequently Asked Questions City Utilities operates the largest municipally-owned wastewater collection and treatment system in Indiana. The system serves 161 square miles and includes 1,014 miles of sanitary sewer lines, 365 miles

More information

Miscellaneous Demolition & Concrete Removal Future Ball Square Station

Miscellaneous Demolition & Concrete Removal Future Ball Square Station Green Line Extension Project Construction Outlook (July 22 Aug. 17) Work schedule subject change based on weather or other factors = New information since last update Miscellaneous Demolition & Concrete

More information

BID PROPOSAL PROPOSAL OF, a Corporation organized and existing under the laws of the State of. a Partnership consisting of

BID PROPOSAL PROPOSAL OF, a Corporation organized and existing under the laws of the State of. a Partnership consisting of BID PROPOSAL PROPOSAL OF, a Corporation organized and existing under the laws of the State of a Partnership consisting of an Individual doing business as. TO THE SAN ANTONIO WATER SYSTEM: Pursuant to Instruction

More information

Public Open House. Proposed Liberty Village Natural Gas Pipeline Project. Please sign-in at the registration table upon arrival

Public Open House. Proposed Liberty Village Natural Gas Pipeline Project. Please sign-in at the registration table upon arrival Proposed Liberty Village Natural Gas Pipeline Project Public Open House Please sign-in at the registration table upon arrival Feel free to approach any team member to discuss the project Share your thoughts

More information

VILLAGE OF MORTON GROVE DEPARTMENT OF PUBLIC WORKS RIGHT-OF-WAY (ROW) PERMIT APPLICATION REQUIREMENTS

VILLAGE OF MORTON GROVE DEPARTMENT OF PUBLIC WORKS RIGHT-OF-WAY (ROW) PERMIT APPLICATION REQUIREMENTS VILLAGE OF MORTON GROVE DEPARTMENT OF PUBLIC WORKS RIGHT-OF-WAY (ROW) PERMIT APPLICATION REQUIREMENTS For general information concerning submittal requirements, please refer to Village Code 7-9-4 (c.).

More information

City of Berkley, Michigan Harvard Road Reconstruction & Water Main Replacement Project FREQUENTLY ASKED QUESTIONS (FAQ)

City of Berkley, Michigan Harvard Road Reconstruction & Water Main Replacement Project FREQUENTLY ASKED QUESTIONS (FAQ) FREQUENTLY ASKED S (FAQ) The purpose of this document is to provide detailed information about the Harvard Road Reconstruction & Water Main Replacement Project. This project will directly affect residents

More information

Description of Phase 2 Modified Design

Description of Phase 2 Modified Design Description of Phase Modified Design. INTRODUCTION This chapter provides an overview of the preliminary engineering design for Phase of the Second Avenue Subway that was evaluated in the Final Environmental

More information

SECTION UNIT PRICES. A. This Section specifies administrative and procedural requirements for the unit prices.

SECTION UNIT PRICES. A. This Section specifies administrative and procedural requirements for the unit prices. SECTION 01220 UNIT PRICES PART 1 GENERAL 1.01 SUMMARY A. This Section specifies administrative and procedural requirements for the unit prices. B. The omission of any unit price description from this Section

More information

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016 Rt. 29 Solutions Project Delivery Advisory Panel February 18, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Feb

More information

Construction Notice: Infrastructure Renewal on York and Talbot Streets

Construction Notice: Infrastructure Renewal on York and Talbot Streets Construction Notice: Infrastructure Renewal on York and Talbot Streets Date: March 22, 2019 To: Business owner, resident and/or property owner Project Details: The City of London in partnership with J-AAR

More information

APPLICATION FOR RIGHT OF WAY PERMIT

APPLICATION FOR RIGHT OF WAY PERMIT City of Danville Department of Engineering & Urban Services APPLICATION FOR RIGHT OF WAY PERMIT PROJECT LOCATION: CONTRACTOR S BUSINESS NAME: CONTRACTOR'S ADDRESS: CONTRACTOR'S PHONE: OWNER S NAME: OWNER

More information

Addendum 1. Valve & Valve Vault Replacement. Issued June 13, 2018

Addendum 1. Valve & Valve Vault Replacement. Issued June 13, 2018 155 Corey Avenue St. Pete Beach, FL 33706-1839 www.stpetebeach.org Addendum 1 Valve & Valve Vault Replacement Issued June 13, 2018 Note that this Addendum does not change the bid due date and time as stated

More information

Safe Work Method Statement (SWMS) for Painting projects

Safe Work Method Statement (SWMS) for Painting projects Safe Work Method Statement (SWMS) for Painting projects This SWMS is a site specific statement that must be prepared before any high risk construction work is commenced. Painting company: Address: Principle

More information

February 27th, 2018 City of Mayville

February 27th, 2018 City of Mayville February 27th, 2018 City of Mayville Project Location and Schedule Construction work Detour Route Business Access During Construction Temporary Business Signs What WisDOT Can Do During Construction What

More information

Kiewit Approach for Tunnel Stabilization and Sewer Pipeline Replacement Project

Kiewit Approach for Tunnel Stabilization and Sewer Pipeline Replacement Project South Coast Water District Kiewit Approach for Tunnel Stabilization and Sewer Pipeline Replacement Project Board of Directors January 14-15, 2013 Overview of Construction Plan Highlights of Kiewit s Construction

More information

Draft Feasibility Study for the Expansion of Southeast Library

Draft Feasibility Study for the Expansion of Southeast Library DC public Library KH KEAST & HOOD METROPOLITAN E N G I N E E R I N G I N C S H A P I RO-O BRIEN Draft Feasibility Study for the Expansion of Southeast Library Draft Submission: November 4, 2016 1 OVERVIEW

More information

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017 Wissahickon School District Natatorium & Central Plant Project Project Update March 27, 2017 Project Features 1. New central plant and receiving area to serve current High School and future Master Plan.

More information

WHO IS METROLINX? PLAN BUILD OPERATE

WHO IS METROLINX? PLAN BUILD OPERATE CROSSTOWN LRT WHO IS METROLINX? PLAN BUILD OPERATE THE NEXT REGIONAL TRANSPORTATION PLAN Metrolinx is currently in the process of updating the Regional Transportation Plan (RTP). The Draft Plan (2041)

More information

6 Preliminary Assessment of Construction Method and Constructability Issues

6 Preliminary Assessment of Construction Method and Constructability Issues 6 Preliminary Assessment of Construction Method and Constructability Issues 6.1 Construction Approach Appendix C includes conceptual designs of the alternatives discussed below. Generally, the conceptual

More information

Jackson s Edge Service Reservoir - Compartment 1 innovative Design for Manufacture and Assembly (DfMA) approach to service reservoir construction

Jackson s Edge Service Reservoir - Compartment 1 innovative Design for Manufacture and Assembly (DfMA) approach to service reservoir construction www.waterprojectsonline.com Jackson s Edge Service Reservoir - Compartment 1 innovative Design for Manufacture and Assembly (DfMA) approach to service reservoir construction by Nathan Crabtree & Daniel

More information

Subsection or plan to be revised: 7-1, 7-8, , On page(s): 27-31(2006), 48-49(2003)

Subsection or plan to be revised: 7-1, 7-8, , On page(s): 27-31(2006), 48-49(2003) Proposed Revision To: Standard Specifications For Public Works Construction Standard Plans For Public Works Construction Public Works Standards, Inc. AGC Southern California Regional Office 1906 West Garvey

More information

RFB for Wastewater Force Main #3. October 2, Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered

RFB for Wastewater Force Main #3. October 2, Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered RFB for Wastewater Force Main #3 October 2, 2015 Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered The proposed force main will be required to transmit up to 1000 gallons of wastewater

More information

TERMS OF REFERENCE PROJECT EDINBURGH ROAD FROM SPEEDVALE AVENUE TO LONDON ROAD

TERMS OF REFERENCE PROJECT EDINBURGH ROAD FROM SPEEDVALE AVENUE TO LONDON ROAD TERMS OF REFERENCE PROJECT EDINBURGH ROAD FROM SPEEDVALE AVENUE TO LONDON ROAD OBJECTIVES/PURPOSE The City of Guelph intends to upgrade the underground services to current standards and carry out complete

More information

SECTION 813 SEWER FLOW CONTROL

SECTION 813 SEWER FLOW CONTROL SECTION 813 SEWER FLOW CONTROL 813-1 DESCRIPTION: Sewer flow control is a set of methods to adjust the flow in the sewer system to allow for inspection, maintenance, repair or replacement. This is accomplished

More information

DIVISION 3 PAVEMENT (FLEXIBLE AND RIGID) CONSTRUCTION SPECIFICATIONS

DIVISION 3 PAVEMENT (FLEXIBLE AND RIGID) CONSTRUCTION SPECIFICATIONS OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 General Conditions of Contract DIVISION 1 GENERAL S OCT 92 102 Weighing of Materials NOV 2004 106 Electrical Work NOV 2003 120 The Use of Explosives APR 2006

More information

SPRR TUPELO ST. R UNION CITY BLVD. ZON PADRE PASEO DEEP CREEK ROAD ARDENWOOD COYOTE HILLS REGIONAL PARK PROJECT LIMITS PATTERSON RANCH ROAD BLVD. COMM

SPRR TUPELO ST. R UNION CITY BLVD. ZON PADRE PASEO DEEP CREEK ROAD ARDENWOOD COYOTE HILLS REGIONAL PARK PROJECT LIMITS PATTERSON RANCH ROAD BLVD. COMM SPRR TUPELO ST. R UNION CITY BLVD. ZON PADRE PASEO DEEP CREEK ROAD ARDENWOOD COYOTE HILLS REGIONAL PARK PROJECT LIMITS PATTERSON RANCH ROAD BLVD. COMMERCE DR. PASEO PADRE PARKWAY KAISER DRIVE DUMBARTON

More information

Albany Park Stormwater Diversion Tunnel

Albany Park Stormwater Diversion Tunnel Albany Park Stormwater Diversion Tunnel Frequently Asked Questions The Basics Who, What, When, Where, Why, How Why is the project being performed? The project is being constructed to reduce flooding in

More information

Albany Park Stormwater Diversion Tunnel

Albany Park Stormwater Diversion Tunnel Albany Park Stormwater Diversion Tunnel Why is the project being performed? Frequently Asked Questions The Basics Who, What, When, Where, Why, How The project is being constructed to reduce flooding in

More information

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring Location of Project Introduction» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring Existing Bridge» Built in 1928» 255-foot Open Spandrel Concrete Arch Bridge» 24-foot

More information

Chapter 3: Permit Procedures and Requirements

Chapter 3: Permit Procedures and Requirements Chapter 1: General Provisions 1 1 Short Title 1 2 Jurisdiction 1 3 Amendments and Revisions 1 4 Enforcement Responsibility 1 5 Review Process 1 6 Prior Approval 1 7 Relationship to Other Standards 1 8

More information

SUPPLEMENTAL DRAWINGS

SUPPLEMENTAL DRAWINGS CITY OF GREATER SUDBURY SUPPLEMENTAL DRAWINGS TO THE ONTARIO PROVINCIAL STANDARD DRAWINGS Rev: February 2012 CITY OF GREATER SUDBURY STANDARD DRAWINGS TABLE OF CONTENTS Greater Sudbury Standard Drawings

More information

ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM

ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM Each applicant needs to thoroughly review the conditions of development issued by the Planning Division in the format of a Resolution approving your project

More information

TransCanada s Napanee Generating Station (NGS) Presentation to the Community Liaison Committee Wednesday, September 17, 2015

TransCanada s Napanee Generating Station (NGS) Presentation to the Community Liaison Committee Wednesday, September 17, 2015 TransCanada s Napanee Generating Station (NGS) Presentation to the Community Liaison Committee Wednesday, September 17, 2015 1 Introductions & Agenda 1. Project Updates 1. E.S. Fox 2. Matrix NAC 2. Transfer

More information

STANDARD SPECIFICATIONS SECTION TEMPORARY BYPASS PUMPING SYSTEMS

STANDARD SPECIFICATIONS SECTION TEMPORARY BYPASS PUMPING SYSTEMS STANDARD SPECIFICATIONS SECTION 02960 TEMPORARY BYPASS PUMPING SYSTEMS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for implementing a temporary pumping system for the purpose of diverting

More information

CITY OF GUELPH CONTRACT NO SUPPLEMENTAL SPECIAL PROVISIONS

CITY OF GUELPH CONTRACT NO SUPPLEMENTAL SPECIAL PROVISIONS CITY OF GUELPH CONTRACT NO. 2-1306 SUPPLEMENTAL SPECIAL PROVISIONS INDEX Contents 1. EXTERNAL CONTRACT DOCUMENTS AND DRAWINGS... 1 2. GENERAL INFORMATION... 4 3. UTILITY COORDINATION, TRAFFIC AND PEDESTRIAN

More information

Questions from Heritage Hunt Grounds Committee Received on 7/7/16

Questions from Heritage Hunt Grounds Committee Received on 7/7/16 Questions from Heritage Hunt Grounds Committee Received on 7/7/16 1. What specific areas are going to be dug up? Portions of the northeast side of the property will require some level of disturbance for

More information