1 REQUEST FOR PROPOSAL Submittal Deadline: 5:00 pm July 7, 2017 The Vermont Chapter of The Nature Conservancy invites proposals from qualified consultants for two fish passage restoration projects on culverts over Alder Brook in Richford, Vermont. PROPOSAL REQUIREMENTS For a proposal to be considered, it must include: Contact Name Firm Name, if applicable Mailing Address Telephone Number address, if available Scope of Work: The work product will be funding in two phases. During both phases, the grantee will meet with TNC and project partners as needed to discuss topics such as scope of work, methodologies, deliverables, and project timelines. Phase 1 1. Analysis of stream channel and existing structure at both culvert locations. The deliverable for this scope item would be a report including: a description of the channel morphology (profile, x-section, substrate, etc.), channel hydrology, and hydraulic analysis of the structure to evaluate fish passage potential (FishXing) and flood capacity. This item would also include photos, design data forms (Vermont Fish Passage Design Data Checklist Hydraulic and Low-Slope Designs) for the existing structure, and a description target species (see project description). All references used should be listed. 2. Replacement Richford South Richford Road (Local ID- srich010; Label- B21) Project Passage Design Alternatives with Existing Cost Estimates. The deliverable for this scope item would be a written description of multiple replacement designs including a bottomless arch, bottomless box/bridge, or alternatives. The design options descriptions should include supporting data from the physical, hydraulic and biological analysis and a summary of why the option is or is not recommended. A design data form (Vermont Fish Passage Design Data Checklist Hydraulic and Low-Slope Designs) is required for the recommended design. All references used should be listed. An example of an acceptable project analysis and report is available upon request. 3. Replacement Richford Coombs Road Culvert Project (Local ID- comb020; Label- B22) Passage Design Alternatives with Existing Cost Estimates. The deliverable for this scope item would be a written description of multiple replacement designs. The design options descriptions should include supporting data from the physical, hydraulic and biological analysis and a summary of why the option is or is not recommended. A design data form (Vermont Fish Passage Design Data Checklist Hydraulic and Low- Slope Designs) is required for the recommended design. All references used should be listed. An example of an acceptable project analysis and report is available upon request.
2 After Phase 1 is completed, TNC and its partners will meet with the Towns and local landowners to select and approve the projects. The Consultant may need to attend a meeting with town officials and adjacent landowners as part of this process. For timeline purposes, plan on a 3 to 4 week interval between the end of Phase 1 and the start of Phase 2. Phase 2: (For both fish passage restoration project sites): 1. Final design for selected alternative. Deliverable would include final design level drawings and description of selected design alternative. 2. Permitting and Regulatory Requirements. The deliverable would include the development and submittal of all permit and regulatory applications for the selected design. 3. Construction scope of work and cost estimate. The deliverable for this scope item would include the development of a construction bid package that could be presented to potential contractors and a cost estimate for the construction portion of the project. Both Phases must be completed by 9/10/2018. Proposal Timeline: Proposal Released: June 2, 2017 Respondent Questions: June 23, 2017 Questions Answered: June 30, 2017 Proposals Due: July 7, 2017 by 5:00 PM Please submit questions and proposal via to pmarangelo@tnc.org. All questions and answers will be released to all potential consultants. Proposals must be submitted by on or before the deadline of 5:00 pm Friday July 7, 2018 to: Paul Marangelo; pmarangelo@tnc.org Senior Conservation Ecologist The Nature Conservancy 575 Stone Cutters Way, Montpelier, VT Proposal Format: The narrative response, cost proposal and proposed timeline should be laid out to correspond to each of the major deliverables under Phase 1 and 2. A staffing summary plus one page biographies should be included for each member of the consultant s team. and include detailed information on the following: Contractor s Professional Qualifications Time to completion with start and completion dates (should be between September 1, 2017 and September 10, 2018; all data entry, field forms and excel files completed and delivered by September 10, 2018). Start time of September 1, 2017 is only an estimate, and is based on having a fully executed contract with all necessary paperwork completed. Cost to complete work (fixed-price bids only) Page 2 of 22
3 Deliverables noted in Scope of WOrk Current contact information for 3 professional references All questions are to be forwarded via and responses will be provided to all applicants. Proposals received later than the deadline will not be considered. Please direct questions to Paul Marangelo at (802) ext. 119, or via to pmarangelo@tnc.org. CONTRACT REQUIREMENTS After bid selection, a contract will be drafted using The Nature Conservancy s standard contract form, a copy of which is provided as an appendix to this RFP. Payments will be processed following receipt of contractor invoice. Work begins after contract is fully executed and concludes by contracted end-date, unless a contract extension is requested and an amendment is drafted and accepted. Page 3 of 22
4 Project Site Details Figure 1. Project site map in Richford VT for culverts under South Richford Road and Coombs Road. Page 4 of 22
5 Structure Details: A. South Richford Road Local ID- srich010 Label- B21 (has a bridge label but it is a culvert) 72 inch diameter, round steel corrugated culvert On tributary of Alder Brook Undersized, bankfull width is at least 12 ft - Significant scour pool at culvert outlet. Culvert has concrete header, footer, and poured concrete bottom. - At least a drop from culvert outlet to water surface. In lower flow, this drop would be more significant. Steep stream elevation change between inlet and outlet. Very long structure ft. Figure 2. Culvert outlet Page 5 of 22
6 Figure 3. View downstream from culvert including large scour pool. Page 6 of 22
7 Figure 4. Inlet of culvert. Page 7 of 22
8 Figure 5. Upstream view from culvert. B. Combs Road Culvert Local ID- comb020 Label- B22 (has a bridge label but it is a culvert) inch diameter, round steel corrugated culvert (culvert inventory from 2014 has 60 inches but out in the field today it looked like 48 inches) 25 ft. in length On tributary of Alder Brook Undersized, bankfull width is at least 10 ft (I believe this is from hydraulic curves, not field measured) Culvert outlet is rusted out on bottom Moderate stream elevation change between inlet and outlet. Page 8 of 22
9 Figure 6. Culvert inlet. Page 9 of 22
10 Figure 7. Culvert outlet. Page 10 of 22
11 Figure 8. Looking downstream from the culvert. Page 11 of 22
CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR
GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS WATER RESOURCES MANAGEMENT DIVISION Water Investigations Section
More informationCulvert Prioritization Model: Aiding Communities in the Selection of Priority Restoration Projects
Culvert Prioritization Model: Aiding Communities in the Selection of Priority Restoration Projects SNHPC Meeting January 24, 2017 1 Undersized Culverts! Culvert Sizes (~7,500 VT culverts) 6,000 5,000 69%
More informationStream Simulation in Very Low Gradient Channels
University of Massachusetts - Amherst ScholarWorks@UMass Amherst International Conference on Engineering and Ecohydrology for Fish Passage International Conference on Engineering and Ecohydrology for Fish
More informationREQUEST FOR CONSTRUCTION BIDS May 23, 2017
REQUEST FOR CONSTRUCTION BIDS May 23, 2017 Cambridge Greenway Trail / Railroad Bridge Replacement Flood Mitigation Project 1.0 Project Background A former railroad bridge that currently carries the Cambridge
More informationTemporary Watercourse Crossing: Culverts
Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol
More informationCreated by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq
Lect.No.9 2 nd Semester Barrages, Regulators, Dams 1 of 15 In order to harness the water potential of a river optimally, it is necessary to construct two types of hydraulic structures, as shown in Figure
More informationLyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual
Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This
More informationCulvert Prioritization Model: Aiding Communities in the Selection of Priority Restoration Projects
Culvert Prioritization Model: Aiding Communities in the Selection of Priority Restoration Projects Meeting #1 of the Technical Advisory Committee March 18, 2016 1 Press 2 Prepared February 2016 Undersized
More informationLocation Drainage Study
Location Drainage Study PROJECT ROUTE: LIMITS: MUNICIPALITY/COUNTY: JOB NUMBER: IL 47 at Burlington Road 750ft NW to 750ft SE of IL 47(Burlington), & 1000ft S to 1000ft N of Burlington (IL47) Kane County
More informationStormwater Local Design Manual For Houston County, Georgia
Stormwater Local Design Manual For Houston County, Georgia Adopted November 15, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 2 2.1. DETENTION REQUIREMENTS... 2 2.1.1.
More informationMODEL Stormwater Local Design Manual. City of Centerville
MODEL Stormwater Local Design Manual City of Centerville Adopted December 6, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 1 2.1. DETENTION REQUIREMENTS... 1 2.1.1. Discharge
More informationLOW WATER CROSSINGS, fords, or drifts, as they
Chapter 9 For ords and Low-Water Crossings Keep the ford profile low, armor the driving surface, and protect against scour. LOW WATER CROSSINGS, fords, or drifts, as they are commonly called, can offer
More informationCulvert Sizing procedures for the 100-Year Peak Flow
CULVERT SIZING PROCEDURES FOR THE 100-YEAR PEAK FLOW 343 APPENDIX A: Culvert Sizing procedures for the 100-Year Peak Flow A. INTRODUCTION Several methods have been developed for estimating the peak flood
More informationiv) Alberta fish weirs
Fish passage at culverts in New Zealand 36 iv) Alberta fish weirs The fish weirs used by Alberta Transportation are weir baffles with a partial slot (Figure 16). The best designs from Rajaratnam et al.
More informationChapter 6 DOCUMENTATION OF HYDRAULIC STUDIES SOUTH DAKOTA DRAINAGE MANUAL
Chapter 6 DOCUMENTATION OF HYDRAULIC STUDIES SOUTH DAKOTA DRAINAGE MANUAL October 2011 Table of Contents Section Page 6.1 INTRODUCTION...6-1 6.1.1 General...6-1 6.1.2 Purpose...6-1 6.1.3 Objectives...6-2
More informationf) Culverts in series shall be spaced at least 20 feet between each other. 2.7 C Culverts
2.7 C Culverts 1. General Culverts are intended to safely pass flow under road crossings. Criteria are designed to protect, maintain, and enhance public health, safety, and the environment. Where culverts
More informationStandards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition
STANDARD FOR SLOPE PROTECTION STRUCTURES Definition Structures to safely conduct surface runoff from the top of a slope to the bottom of the slope. Purpose The purpose of this practice is to convey storm
More informationSection 1000 Culverts and Bridges Table of Contents
Section 1000 Culverts and Bridges Table of Contents 1001 INTRODUCTION... 1000 1 1002 CULVERT DESIGN STANDARDS... 1000 1 1002.1 CONSTRUCTION MATERIALS... 1000 1 1002.2 MINIMUM CULVERT SIZE... 1000 2 1002.3
More informationTask Order Authorization
Task Order Authorization Task Order Number: 6 Task Order Name: 2017 Small Drainage Program Hourly Rate: See attached Exhibit B Budget Not To Exceed: $79,795.00 This Task Order pertains to the On-Call Agreement
More informationGwinnett County Stormwater System Assessment Program
Gwinnett County Stormwater System Assessment Program Jonathan Semerjian, PE Dept. of Water Resources Stormwater Management Sam Fleming, PE Dewberry Presentation Overview Project Background Drivers Enhanced
More informationREQUEST FOR PROPOSALS LIBS PARK PLAYGROUND FOR CITY OF HASTINGS, NEBRASKA
REQUEST FOR PROPOSALS LIBS PARK PLAYGROUND FOR CITY OF HASTINGS, NEBRASKA Sealed proposals will be received by the City of Hastings, Nebraska, at the office of the City Clerk, 220 North Hastings Avenue,
More informationUPRR criteria for sizing waterway openings under bridges and through culverts are as follows:
UNION PACIFIC RAILROAD SCOPE OF HYDROLOGIC/HYDRAULIC DESIGN ENGINEERING AND PERMITTING SERVICES FOR SIZING WATERWAY OPENINGS AT NEW AND REPLACEMENT STRICTURES These flood passage criteria were developed
More informationEL PASO WATER - PUBLIC SERVICE BOARD REQUEST FOR SUBMITTALS RFS June 27, 2017
EL PASO WATER - PUBLIC SERVICE BOARD REQUEST FOR SUBMITTALS RFS 21-17 June 27, 2017 TO: RE: Invited Firms Request for Submittals to El Paso Water - Public Service Board (EPWater) Statement of Work Professional
More informationREROUTING DRAINAGE SYSTEMS
MINNESOTA WETLAND RESTORATION GUIDE REROUTING DRAINAGE SYSTEMS TECHNICAL GUIDANCE DOCUMENT Document No.: WRG 4A-4 Publication Date: 10/14/2015 Table of Contents Introduction Application Design Considerations
More informationTOWN OF BURLINGTON MASSACHSETTS (781) Planning Department
TOWN OF BURLINGTON MASSACHSETTS 01803 (781) 270-1645 Planning Department REQUEST FOR PROPOSALS TOWN OF BURLINGTON MASTER PLAN (PHASE 1) Goals/Community Character Statement & Land Use Responses Due: Deliver
More informationMASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK
MASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK The professional services to be provided by the Consultant under this Agreement shall be as necessary to complete the required analyses, layouts,
More informationApplication for resource consent Form B Damming and diversion of water
Application for resource consent Form B Damming and diversion of water Notes Resource use activities must meet all the conditions of any relevant Permitted Activity Rules in the Waikato Regional Plan or
More informationAppendix D - Evaluation of Interim Solutions
Appendix D - Evaluation of Interim Solutions D.1 Introduction The implementation of long-term improvements is projected to take 5 to 8 years. To reduce the number of years of flooding impacts, the partner
More informationThe following answers are provided in response to questions received.
CARLOS PABELLON Director of Administration COUNTY OF DANE DEPARTMENT OF ADMINISTRATION PURCHASING DIVISION Room 425 City-County Building 210 Martin Luther King Jr. Blvd. Madison, WI 53703-3345 608-266-4131
More informationDRAFT GREATER MOOSES TOOTH TWO (GMT2) DEVELOPMENT PROJECT PERMITTEE RESPONSIBLE WETLANDS MITIGATION PLAN NATIONAL PETROLEUM RESERVE-ALASKA
DRAFT GREATER MOOSES TOOTH TWO (GMT2) DEVELOPMENT PROJECT PERMITTEE RESPONSIBLE WETLANDS MITIGATION PLAN NATIONAL PETROLEUM RESERVE-ALASKA Prepared for: ConocoPhillips Alaska, Inc. Anchorage, AK March
More informationPROFESSIONAL SERVICES REQUEST FOR PROPOSALS Moffat Collection System Siphon 1 River Crossing
Project Description PROFESSIONAL SERVICES REQUEST FOR PROPOSALS Moffat Collection System Siphon 1 River Crossing The Siphon 1 River Crossing project consists of replacing an existing aerial pipe crossing
More information10:00 AM, Wednesday, April 8, 2015
NOTICE OF MANDATORY PRE-BID CONFERENCE WILL BE HELD AT 10:00 AM, Wednesday, April 8, 2015 IN ROOM 16, CITY HALL BUILDING, 101 NORTH MAIN STREET WINSTON-SALEM, NORTH CAROLINA The purpose of this conference
More informationInformation for File # PRH
Information for File # 2016-02602-PRH Applicant Corps Contact Tom Morley Paul Hauser Address 152 Baker Drive, Redwood Falls, MN 56283 E-Mail Paul.R.Hauser@usace.army.mil Phone 651-290-5357 Primary County
More informationKing County Flood Control District approves grants for flood prevention projects Regional projects to benefit from district funds
News Release Contact: Al Sanders 206-477-1016 August 31, 2015 Flood Control District approves grants for flood prevention projects Regional projects to benefit from district funds The Flood Control District
More informationNPDES/SDS Stormwater Permit Program for Construction Activity Inspection Report Corrective Actions. ( ) - ext. ( ) - ext. Owner Name Telephone Fax
NPDES/SDS Stormwater Permit Program for Construction Activity Inspection Report Corrective Actions MPCA use only White-MPCA Canary-Site copy Delta record Project Name / Location MN R100001-C000 Stormwater
More informationSPECIFICATION FOR PIPE CULVERT CONSTRUCTION
SPECIFICATION FOR PIPE CULVERT CONSTRUCTION 1. SCOPE Pipe culverts shall be constructed in accordance with this specification and in conformity with the lines, levels and cross-sections shown on the drawings.
More informationNorth Domingo Baca Extension at Barstow
Modeling Report April 5, 2001 North Domingo Baca Extension at Barstow Prepared for the Albuquerque Metropolitan Arroyo Flood Control Authority Julie Coonrod, Ph.D., P.E. Department of Civil Engineering
More informationDepartment of the Army Permit Application
Department of the Army Permit Application DA File Number U.S. Army Corps of Engineers Honolulu District Date Received by CEPOH-RO Send Completed Application to: Honolulu District, U.S. Army Corps of Engineers
More informationOutlet Structure Modeling
Watershed Modeling using HEC-RAS Outlet Structure Modeling Jeff Wickenkamp, P.E., CFM, D.WRE Patrick Lach, P.E. Hey and Associates, Inc. Water Resources, Wetlands and Ecology Outline of Presentation Why
More informationCITY OF KIMBERLEY HYDROLOGICAL & HYDRAULIC ASSESSMENT
HYDROLOGICAL & HYDRAULIC ASSESSMENT ISSUED FOR USE January 31, 2012 FILE: 2011-015 LACAS CONSULTANTS INC. CONSULTING ENGINEERS & HYDROLOGICAL SPECIALISTS, SINCE 1991 Suite 200, 1311 Howe Street, Vancouver,
More informationDIVISION 5 STORM DRAINAGE CRITERIA
DIVISION 5 STORM DRAINAGE CRITERIA Section 5.01 GENERAL The following storm drainage design criteria shall apply to all storm drainage designs in the City. Additional design criteria are specified in the
More informationSEALED BID. Contract for the Implementation of the State Standard Plan for Electronic Collection and Recycling
Waste Management Division REQUEST FOR PROPOSAL SEALED BID Contract for the Implementation of the State Standard Plan for Electronic Collection and Recycling DATE: March 1, 2013 QUESTIONS DUE BY: April
More informationNEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL
NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by
More informationBELLOWS FALLS HISTORICAL SOCIETY, INC. Post Office Box 466 Bellows Falls, VT I fax
BELLOWS FALLS HISTORICAL SOCIETY, INC. Post Office Box 466 Bellows Falls, VT 05101 802-376-6789 I fax 802-463-9415 Request for Qualifications Design and Build Services for Nature Observation Platforms
More informationREQUEST FOR BIDS BUILDING DEMOLITION 102 W. Main St.
531 N. Nash Street Hortonville, WI 54944-0099 Phone: 920-779-6011 Fax: 920-779-6552 www.hortonvillewi.org REQUEST FOR BIDS BUILDING DEMOLITION 102 W. Main St. Date Issued: February 5, 2016 Date Due: March
More informationVICTORY HALL 401 VALLEY STREET SCOTTSVILLE, VIRGINIA TELEPHONE: (434) FACSIMILE: (434)
Town Administrator GEORGE T. GOODWIN III Town Clerk AMY E. MOYER TOWN OF SCOTTSVILLE VICTORY HALL 401 VALLEY STREET SCOTTSVILLE, VIRGINIA 24590 TELEPHONE: (434) 286-9267 FACSIMILE: (434) 286-4237 www.scottsville.org
More informationREQUEST FOR QUALIFICATIONS FOR DAYTON VALLEY AREA DRAINAGE MASTER PLAN
REQUEST FOR QUALIFICATIONS FOR DAYTON VALLEY AREA DRAINAGE MASTER PLAN Statement of Qualifications due Friday, November 3, 2017 at 12:00 PM (Pacific Time) To the Carson Water Subconservancy District Office
More informationAPPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.
Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations
More informationRelease of RFP February 9, 2017 RFP Questions and Clarifications Deadline February 16, 2017 at 4 p.m.
Request for Proposals Temporary Staffing Services North St. Louis Soil and Water Conservation District 307 First St S Ste 114 Virginia MN 55792 I. Introduction The North St. Louis Soil and Water Conservation
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES OCTOBER 09, 2014 EAST BAY REGIONAL PARK DISTRICT Atlas Road Extension Improvements POINT PINOLE REGIONAL SHORELINE PROPOSALS DUE: 2:00PM, NOVEMBER
More informationNotice No Closing Date: May 12, 2017
Public Notice U.S. Army Corps of Engineers Pittsburgh District In Reply Refer to Notice No. below US Army Corps of Engineers, Pittsburgh District 1000 Liberty Avenue Pittsburgh, PA 15222-4186 Application
More informationREQUEST FOR PROPOSAL. For Technical Contractor CanGym Revitalization City Park Drive, Suite 120 Ottawa, ON K1J 1A3
REQUEST FOR PROPOSAL For Technical Contractor CanGym Revitalization 1900 City Park Drive, Suite 120 Ottawa, ON K1J 1A3 Request for Proposal For Technical Contractor CanGym Revitalization Gymnastics Canada
More information(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08
(b) Discuss in brief shaft spillway with neat sketches. Marks 04 OR Q (2) Explain in brief USBR stilling basin. Marks 08 Stilling Basins The basins are usually provided with special appurtenances including
More informationCONSTRUCTION SURVEY. Construction survey includes personnel, equipment, and supplies required for, but not limited to, the following:
CONSTRUCTION SURVEY PART 1 - GENERAL 1.01 SECTION INCLUDES Construction survey includes personnel, equipment, and supplies required for, but not limited to, the following: A. Construction Survey: 1. Project
More informationAPPENDIX G HYDRAULIC GRADE LINE
Storm Drainage 13-G-1 APPENDIX G HYDRAULIC GRADE LINE 1.0 Introduction The hydraulic grade line is used to aid the designer in determining the acceptability of a proposed or evaluation of an existing storm
More informationNIWA PY 17 One Stop Operator & WIOA Career Services RFP Questions and Answers as of
NIWA PY 17 One Stop Operator & WIOA Career Services RFP Questions and Answers as of 1.23.17 Questions prior to 1.18.17 Bidder s Meeting 1. Q: Is performance data available for the last complete program
More informationREQUEST FOR PROPOSAL (RFP) RFP
REQUEST FOR PROPOSAL (RFP) ENGINEERING CONSULTANT REGIONAL WASTEWATER PIPELINE FEASIBILITY STUDY FEBRUARY 9, 2015 TABLE OF CONTENTS SECTION 1 SUMMARY AND BACKGROUND 2 SECTION 2 PROJECT SCOPE 3 SECTION
More informationEska Creek Preliminary Feasibility Analysis
Introduction Eska Creek Preliminary Feasibility Analysis This report examines the feasibility issues of energy and economics for a 1.8 MW hydroelectric project on Eska Creek (project). The Project is located
More informationSummary of Detention Pond Calculation Canyon Estates American Canyon, California
July 15, 2015 Bellecci & Associates, Inc Summary of Detention Pond Calculation Canyon Estates American Canyon, California 1. Methodology: Method: Unit Hydrograph Software: Bentley Pond Pack Version 8i
More informationThis project consists of design, preparation of three (3) projects, in coordination with LSU HCSD staff, for:
Applications for Architectural Designer Services for the following projects will be accepted until 4:00 p.m., April 4, 2018. (Your attention is called to the 4:00 p.m. deadline -- exceptions WILL NOT be
More informationUrban Hydrology Characteristics and their Influence on Urban Stream Restoration Technology. Presented by:
Urban Hydrology Characteristics and their Influence on Urban Stream Restoration Technology Presented by: Michael Clar Ecosite, Inc. James Gracie Brightwater, Inc. BACKGROUND Many streams in urban areas
More informationTable of Contents. July
Table of Contents 36.1 General... 3 36.1.1 Bridge or Culvert... 3 36.1.2 Box Culvert Size Restrictions... 4 36.1.3 Stage Construction for Box Culverts... 4 36.2 Dead Loads and Earth Pressure... 5 36.3
More informationUnderstanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)
Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Definitions SWPPP: Storm Water Pollution Prevention Plan BMP: Best Management Practice(s) to control pollution IDNR: Iowa Department
More informationREQUEST FOR STATEMENT OF QUALIFICATIONS SOQ #
REQUEST FOR STATEMENT OF QUALIFICATIONS SOQ #2018-010 for PROFESSIONAL SERVICES Architectural, Landscape Architectural, Appraisal, Title, Engineering and Survey FY 2018 Issue date: January 25, 2018 Lake
More informationTOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK
TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK COST EVALUATION FOR ROLLING HILLS AREA WATER MAIN EXTENSION PROFESSIONAL CONSULTING, LLC. Octagon 10, Office Center 1719 Route 10, Suite 225 Parsippany,
More informationGeneva Dam. Design of a Steep, Temporary, Riprap Ramp
Geneva Dam Design of a Steep, Temporary, Riprap Ramp A Run-of of-river Dam Analysis for Geneva Dam Credit to: Yu-Chun Su, Ph.D., P.E., CFM David T. Williams. Ph.D., P.E, CFM Presentation Purpose History
More informationChapter 7. Street Drainage. 7.0 Introduction. 7.1 Function of Streets in the Drainage System. 7.2 Street Classification
7. Introduction This chapter summarizes methods to evaluate runoff conveyance in various street cross sections and curb types in the Town of Castle Rock and identifies acceptable upper limits of street
More informationHOUSING AUTHORITY OF THE CITY OF BOULDER (dba Boulder Housing Partners)
HOUSING AUTHORITY OF THE CITY OF BOULDER (dba Boulder Housing Partners) SOLICITATION TYPE: DESCRIPTION: Request For Proposals Paperless Invoice Automation Software ISSUE DATE: 04/03/2018 DUE DATE: 04/20/2018
More informationEXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID: DISTRICT TWO
EXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID: 430959-1-22-01 DISTRICT TWO Stage I Scope A-1 August 2, 2017 SCOPE OF SERVICES DISTRICTWIDE ENVIRONMENTAL SERVICES FLORIDA DEPARTMENT OF TRANSPORTATION
More informationUS Army Corps of Engineers
I I I ' A I US Army Corps of Engineers LA River Ecosystem Restoration, CA Preconstruction Engineering and Design Phase 104791 LOS ANGELES DISTRICT SOUTH PACIFIC DIVISION August 15, 2017 1 Table of Contents
More informationODFW AQUATIC INVENTORY PROJECT RESTORATION MONITORING STREAM HABITAT REPORT
ODFW AQUATIC INVENTORY PROJECT RESTORATION MONITORING STREAM HABITAT REPORT STREAM: GCG: 5-SC SITE ID: 466 BASIN: ROGUE TREATMENT DATE: 2 SURVEY DATE: 7/29/23 SURVEY CREW: USGS MAPS: ECOREGION: REPORT
More informationOutlet Flow Velocity in Circular Culvert
Archives of Hydro-Engineering and Environmental Mechanics Vol. 61 (2014), No. 3 4, pp. 193 203 DOI: 10.1515/heem-2015-0013 IBW PAN, ISSN 1231 3726 Outlet Flow Velocity in Circular Culvert Wojciech Szpakowski
More informationCITY OF TROY DESIGN STANDARDS AND CONSTRUCTION SPECIFICATIONS
CITY OF TROY DESIGN STANDARDS AND CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587 JANUARY 2010 TABLE OF CONTENTS SECTION 1 SECTION 2 SECTION 3 SECTION 4 SECTION 5 SECTION 6 APPENDIX ROADWAY DESIGN DRAINAGE
More informationREQUEST FOR PROPOSAL Engineering Design for Culinary Water Tank and Secondary Water Tank Conversion
REQUEST FOR PROPOSAL Engineering Design for Culinary Water Tank and Secondary Water Tank Conversion Page 1 of 5 REQUEST FOR PROPOSALS Syracuse City is seeking the services of a qualified engineering consultant
More informationHazen and Sawyer 2101 NW Corporate Boulevard, Suite 301 Boca Raton, Florida Albrey Arrington, Ph.D. / Loxahatchee River District
Hazen and Sawyer 2101 NW Corporate Boulevard, Suite 301 Boca Raton, Florida 33431 561.997.8070 M E M O R A N D U M TO: COPY: FROM: Albrey Arrington, Ph.D. / Loxahatchee River District Clint Yerkes / Loxahatchee
More informationALTERNATIVE PROJECT DELIVERY DIVISION
VIRGINIA DEPARTMENT OF TRANSPORTATION ALTERNATIVE PROJECT DELIVERY DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Design-Build Requirements for Advertisement SPECIFIC SUBJECT: APPROVED:
More informationJULY 2012 RED LAKE WATERSHED DISTRICT MONTHLY WATER QUALITY REPORT
Thief River Watershed Assessment Project (Watershed Restoration and Protection - WRAP) Task 2 Water Quality Monitoring o Water quality samples were collected at continuous dissolved oxygen monitoring sites
More information7/16/2012. Post Construction Best Management Practices (PCBMPs) Article VIII: Post Construction Best Management Practices
Post Construction Best Management Practices (PCBMPs) Article VIII: Post Construction Best Management Practices Presented by Jennifer Boyer DuPage County DEC Includes BMPs intended to provide volume control
More information3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES
3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES All sanitary sewers shall be designed in accordance with these Design Standards, LBWD Rules and Regulations, and to accepted engineering principles. In
More informationINVITATION TO BID (ITB) Sealed Bid Request
INVITATION TO BID (ITB) Sealed Bid Request Tucannon River RM 32.5-34.5, Project Area (PA) 17-18 (1) Construction Materials, (2) Construction Services, and (3) Post Construction Survey Confederated Tribes
More informationAdjusted Flood Prone Acres
Adjusted Flood Prone Acres The flood prone area is defined as the area adjacent to the stream that is innundated or saturated when the elevation of the water is at twice the maximum depth at bankfull stage
More informationHolly Swartz and Jason Shirey
Chapter 105 General Permits for Stream and Wetland Impacts DEP Ch. 105 CONTACTS FOR BERKS COUNTY: Holly Swartz and Jason Shirey What DEP Regulates Under Chapter 105 Waters of the Commonwealth, which includes
More informationCHAPTER 2 STORMWATER MANAGEMENT
CHAPTER 2 STORMWATER MANAGEMENT REVISED SEPTEMBER 11, 2002 WHATCOM COUNTY DEVELOPMENT STANDARDS CHAPTER 2 - STORMWATER MANAGEMENT TABLE OF CONTENTS PART 1: ADMINISTRATIVE PROVISIONS Section 201. Regulatory
More informationThis chapter describes the potential hydrological effects of the Project in terms of:
19. Hydrology Overview The Project will result in changes to existing hydrology from land use changes and from changes to stream morphology. Hydrological and hydraulic modelling has been undertaken to
More informationDRAINAGE DESIGN DOCUMENTATION
June, 2017 DRAINAGE DESIGN DOCUMENTATION (An expansion of the Stormwater Management Design Report) Note: This report outline is not all-inclusive. There may be situations when information not included
More informationChapter 10 CULVERTS SOUTH DAKOTA DRAINAGE MANUAL
Chapter 10 CULVERTS SOUTH DAKOTA DRAINAGE MANUAL October 2011 Table of Contents Section Page 10.1 INTRODUCTION...10-1 10.1.1 Definition...10-1 10.1.2 Purpose...10-1 10.1.3 Concepts...10-1 10.1.4 Symbols...10-2
More information4.1 Browns Canal Introduction Sub-basin Information
Section 4 Withlacoochee Basin 4.1 Browns Canal 4.1.1 Introduction The information presented in this sub-basin plan for Browns Canal is intended to provide the reader with information necessary to understand
More informationPomme de Terre One Watershed, One Plan Request for Proposal Responses DUE: May 19 th, 2017
Pomme de Terre One Watershed, One Plan Request for Proposal Responses DUE: May 19 th, 20 The Pomme de Terre watershed planning area has begun planning in the One Watershed, One Plan (1W1P) program. With
More informationRequest for Proposals (RFP) Information Technology Independent Verification and Validation RFP No IVV-B ADDENDUM NO.
Request for Proposals (RFP) Information Technology Independent Verification and Validation ADDENDUM NO. 2 Questions and Answers RFP Amendments September 2015 Contained herein are the responses to the questions
More informationSW-74 SERENOVA PRESERVE SITES 2, 3, 4, 8 MITIGATION PLAN
SW-74 SERENOVA PRESERVE SITES 2, 3, 4, 8 MITIGATION PLAN BACKGROUND INFORMATION Project SWIM? Aquatic Control? Exotic Control? Mitigation Bank? Type No No No No Mitigation Restoration and enhancement Type
More informationPreface. MNR # Queen s Printer for Ontario, 2012 ISBN (PRINT) ISBN (PDF)
Preface In 2008, the inter-agency Drainage Act & Section 28 Regulations Team (DART) was established by the Ministry of Natural Resources (MNR) and the Ministry of Agriculture, Food and Rural Affairs (OMAFRA)
More informationHydraulic Design of Highway Culverts HDS 5 September 1985
Hydraulic Design of Highway Culverts HDS 5 September 1985 Welcome to HDS 5 - Hydraulic Design of Highway Culverts Table of Contents Preface Tech Doc U.S. - SI Conversions DISCLAIMER: During the editing
More informationSECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements
SECTION 3 DRAINAGE 3-1 General All Drainage plans for proposed development shall be prepared by a Professional Engineer registered in Virginia, except as noted below. Further, their seal and signature
More informationNew Hampshire Stream Crossing Guidelines
New Hampshire Stream Crossing Guidelines May 2009 1 This document was written to assist in the design, construction and permitting of stream crossings in New Hampshire. Many individuals from non-governmental
More informationPlanning and Combination (Planning and Acquisition) Project Proposal
Planning and Combination (Planning and Acquisition) Project Proposal Project Number 15-1308 Project Name Asotin County Geomorphic/Watershed Assessment Sponsor Asotin County Conservation District List all
More informationREQUEST FOR PROPOSALS OREGON CITY ANNEX FIBER OPTIC ENGINEERING & INSTALLATION. Date Due: Friday, September 8, Time Due: 4:00 p.m.
Information Technology 625 Center Street Oregon City OR 97045 Ph (503) 657-0891 fax (503) 657-7892 REQUEST FOR PROPOSALS OREGON CITY ANNEX FIBER OPTIC ENGINEERING & INSTALLATION Date Due: Friday, September
More informationJHI Sweetheart Lake: Spawning Habitat Assessment & Maintenance
Technical Memorandum JHI Sweetheart Lake: Spawning Habitat Assessment & Maintenance Date: April 4, 2014 To: Duff Mitchell Company: JHI From: Dan Miller, Lon Mikkelsen, Inter Fluve, Inc. Introduction Juneau
More informationMC-3500 and MC-4500 Design Manual
MC-3500 / MC-4500 MC-3500 and MC-4500 Design Manual StormTech Chamber Systems for Stormwater Management Table of Contents 1.0 Product Information...2 2.0 Foundations for Chambers...8 3.0 Required Materials/Row
More informationLEVEE DEFICIENCY CORRECTION PROCEDURES
LEVEE DEFICIENCY CORRECTION PROCEDURES USACE, LOS ANGELES DISTRICT 24 APRIL 2015 LEVEE SAFETY PROGRAM Deficiencies noted on the inspection checklist portion of the Periodic Inspection Report shall be addressed
More information