HAMPTON ROADS SANITATION DISTRICT CAPITAL IMPROVEMENT PROGRAM FY 2003 to 2007 PROJECT SUMMARY

Size: px
Start display at page:

Download "HAMPTON ROADS SANITATION DISTRICT CAPITAL IMPROVEMENT PROGRAM FY 2003 to 2007 PROJECT SUMMARY"

Transcription

1 56

2 Nansemond Project Name Bowers Hill and Deep Creek Pressure Reducing Stations Generator Upgrades Line/PS No. Account No XXXXX-2320 VRLF No. Replacement Design Underway This project will design and construct replacements for both the Bowers Hill and Deep Creek Pressure Reducing Stations Generators. Both Deep Creek and Bowers Hill PRS's have 230 KW generators and as designed in the late 1970s have the capacity of starting and running only 2 of the 3 motors at each station. Early in the design life of the PRS's flows were probably such that only 2 of the 3 pumps, as designed, were necessary. Now that the Bowers Hill PRS is approaching capacity, the third pump is needed especially during intense rain events when I/I starts affecting the system. At the present time this additional pumping capacity is lost when commercial power is lost and the generator must carry the load. An upgrade to the Bowers Hill generator is necessary in order to use the additional pumping capacity provided by the third pump. Additionally, if we are limited to only two pumps we will be unable to effect large diversions using the Elizabeth River Crossing. Both Bowers Hill and Deep Creek PRS's are critical when diverting flows across the river. In order to not be limited to a specific flow, the same upgrade needs to be performed at the Deep Creek PRS. Cost Estimate Construction $340,000 9 % of Const. $ 30, % of Const. $ 30,000 Total $400,000 Schedule Start (mo/yr) 05/01 Duration (mo) Inspection Requesting Dept. Interceptor s Dept. Contact Bob Norris Managing Dept. Engineering Date 3/8/02 57

3 58

4 Nansemond Project Name Carolina Road Interceptor Force Main Pressure Control Valve Line/PS No. Account No XXXXX-2000 VRLF No. New Facility Planning Underway This project will install a new pressure control valve on the Carolina Road Interceptor Force Main. The pressure control valve consists of a pressure actuated valve controlled by an upstream pressure sensor that maintains a positive pressure in the main by restricting low flow conditions. The need for a pressure control valve will become apparent once the new Carolina Road Interceptor Force Main is placed into operation. With the new larger main comes low flows and a significant increase in grade as the force main moves into the Piedmont Area away from flatter Tidewater. The control valve will help prevent the main from creating a vacuum at low flows (night conditions) by restricting flow and keeping the pipe full. Cost Estimate Construction $42, % of Const. $ 8, % of Const. $ 5,100 Total $56,100 Schedule Start (mo/yr) 01/01 Duration (mo) Requesting Dept. Interceptor s Dept. Contact Bob Norris Managing Dept. Interceptor s Date 3/11/02 59

5 Nansemond Project Name Nansemond Treatment Plant Disinfection Chemical Feed Facilities Line/PS No. Account No XXXXX-2400 VRLF No. Replacement Design Underway The purpose of this project is to convert the gaseous chlorine and sulfur dioxide facilities at the Nansemond Treatment Plants to liquid sodium hypochlorite and sodium bisulfite facilities. The project will include provision of temporary sodium hypochlorite and sodium bisulfite feed facilities; removal of ton container storage and scale facilities, gas feed equipment, emergency scrubber, and related piping, duct, and electrical from the Disinfection Building; modifications to the Disinfection Building to accommodate the installation of and access to bulk storage tanks and feed pumps; temporary and permanent chemical feed piping to the application points; and process instrumentation utilizing existing or replacement analyzers. A muriatic acid storage and feed system will be provided for scrubber cleaning. Construction will be accomplished by a contract including Disinfection Chemical Feed Facilities at both the Nansemond and Chesapeake Elizabeth Plants. This project will provide a safer means of chemical disinfection. Cost Estimate Construction $ 900, % of Const. $ 180, % of Const. $ 138,500 Total $1,218,500 Schedule Start (mo/yr) 01/02 Duration (mo) 18 Requesting Dept. Engineering Dept. Contact Bruce Husselbee Managing Dept. Engineering Date 2/12/02 60

6 61

7 PROJECT REQUEST VIP Project Name Berkley Trunk Sewer Section M and South Norfolk Trunk Sewer Section Y Replacement Line/PS No. SG 99, SF 147 Account No. VRLF No. Replacement Not Started This project will replace of pipeline at two locations in the Berkley Section of Norfolk: 1. Berkley Trunk Sewer, Section M (SF-099) - This project will replace 1,064 linear feet of 20 inch CI force main installed in South Norfolk Trunk Sewer Section "Y" - This project will replace 48 linear feet of 20 inch CI force main installed in This section of pipeline crosses in a casing under railroad tracks at the intersection of Halifax Avenue and Bainbridge Boulevard. These two repairs are included in the same CIP project because of their close proximity and similar type of repairs. Estimate does not include over pumping. Study of project will determine if this is necessary and cost will be added at that time. The Berkley Trunk Sewer, Section M, has required four repairs in the last 10 years, each successive repair becoming more extensive. Two repairs, completed in the last five years, involved the replacement of approximately 60 LF of pipe due to inadequate remaining pipe crown thickness. These two repairs were made in the vicinity of a vented high point. The initial length of the replacement has been based on replacing that portion of the high point which could have been affected by the internal corrosion. No pipeline testing has been accomplished yet. On January 29, 2002 a leak was discovered in the end of the cased crossing under the railroad tracks close to the HRSD Bainbridge Boulevard Pump Station. The casing has been filled with concrete therefore locating the exact location of the leak in the pipe was impossible. The leak is being managed by lowering the pressure in the force main by sending it to gravity. Both of these projects need to be accomplished on an urgent basis because there are no alternate routes for the flows if a major break occurs, and the possibility of adverse impact on the system from heavy rainfall events will exist until repairs are effected. Cost Estimate Construction $205, % of Const. $ 20, % of Const. $ 20,500 Total $246,000 Schedule Start (mo/yr) 09/02 Duration (mo) Requesting Dept. Interceptor s Dept. Contact John Wade/Paul Wilson Managing Dept. Engineering Date 3/12/02 62

8 63

9 VIP Project Name Elizabeth River Crossing Section I Replacement Line/PS No. SF 95 Account No XXXXX-2120 VRLF No. Replacement Construction Underway This project will design and replace the 1,652 linear feet interceptor river crossing force main. It will increase the size from 24-inch diameter to 30-inch diameter. This increase in diameter will match the diameter of the pipes it connects to and allow for future diversion capacity. The existing 24-inch IFM under the Elizabeth River failed in November Repairs have been completed, but the failure has raised concern about the integrity of the remaining portion of the 52+ year old force main. Russell Corrosion Consultants, Inc. was retained to investigate the cause of the failure. Their conclusion was that graphitization was a major contribution and that this was probably typical of the pipe under the river. Cost Estimate Construction $1,548,100 3 % of Const. $ 46,400 % of Const. $ 198,500 Total $1,793,000 Schedule Start (mo/yr) /01 Duration (mo) Requesting Dept. Interceptor s Dept. Contact Troy McPherson Managing Dept. Engineering Date 3/11/02 64

10 65

11 VIP Project Name Lamberts Point Influent Reinforcement and North Trunk Section O Rehabilitation Line/PS No. SG 47, SG 53, and SG 48 Account No XXXXX-2160 VRLF No. Rehabilitation Design Underway This project consists of three parts: Lamberts Point 54 Inch Gravity: This project will rehabilitate approximately 3,414 linear feet of 54-inch reinforced concrete gravity main along Bluestone Avenue and 43rd Street to the VIP Treatment Plant in the City of Norfolk. The cost estimate for this project is based on an in-house estimate. Lamberts Point Influent Reinforcement Rehabilitation: This project will rehabilitate approximately 1,111 linear feet of 42-inch reinforced concrete pipe along Bluestone Avenue from 38th Street to 42nd Street in Norfolk. The manholes did not appear to be affected by the corrosive atmosphere and are not expected to be included in any rehabilitation effort. North Trunk Sewers Section O Rehabilitation: This project will rehabilitate approximately 1,100 linear feet of 18-inch reinforced concrete gravity main and rehabilitate manholes along Bluestone Avenue between 43rd and 47th Streets in the City of Norfolk. The cost estimate for this project is based on an in-house estimate. The first project would extend the life of this gravity line, which was constructed in CCTV inspection indicated very heavy hydrogen sulfide attack in the interior of pipe along with steel reinforcement (rebar) exposed or missing in the majority of the pipeline. This pipeline is under or adjacent to a heavily used road adjacent to ODU. This line is in virtually the same condition as the 42 inch gravity line, which experienced a failure in September Directly upstream from the 54 inch gravity line is the 42 inch gravity line. On September 16, 1999 the top of a portion of the gravity main of the second project collapsed due to interior corrosion. The failure in the top of our pipe was covered and backfilled as a temporary repair measure while the rest of this portion of the gravity main was CCTV inspected. The inspection revealed significant corrosion along the crown of the pipe for its entire length, with some areas more severe than others. In fact, some portions of the interior concrete and steel reinforcement have deteriorated to such a degree that only a thin shell of concrete on top remains as a conduit to transport sewage. As with previous failures of this type and similar inspection results, timely rehabilitation action needs to be taken to preclude future collapses. The third project would extend the life of this 18 inch gravity line, which was constructed in CCTV inspection indicated heavy hydrogen sulfide attack in the crown of the pipe, with the steel reinforcement (rebar) exposed or missing at numerous locations. The manholes are standard brick design and are in need of rehabilitation. This pipeline is under a heavily used road on the property of ODU. The 48 inch pipeline discharges into the 54 inch gravity line. Cost Estimate Construction $1,788, % of Const. $ 357,800 0 % of Const. $ 214,700 Total $2,361,300 Schedule Start (mo/yr) /01 Duration (mo) 36 Requesting Dept. Interceptor s Dept. Contact John Wade Managing Dept. Engineering Date 2/15/02 66

12 67

13 VIP Project Name Pinners Point Flow Meter Line/PS No. Account No XXXXX-2130 VRLF No. Relocation Purchase/Negotiations Underway VDOT has a project underway that will affect the 48 inch force main near the Pinners Point portion of the City of Portsmouth. The line will have to be relocated in 3 places. While VDOT is doing their work, HRSD would like to install a flow meter in this line to measure flows. VDOT Installation costs - $70,000. Under the Master Metering Plan, staff has planned to measure this flow with the installation of a flow meter. VDOT will have to install four line stops to handle the flow during the tie-ins of the relocated segments of our line. While the relocated segment is inactive, a flow meter can easily be installed in the segment. Installing the flow meter at a later time will require two line stops which will cost HRSD an additional $80,000 to $100,000. Cost Estimate Construction $ 108,800 % of Const. $ 1,200 % of Const. $ 6,000 Total $ 116,000 Schedule Start (mo/yr) /01 Duration (mo) Meter Installation Requesting Dept. Interceptor s Dept. Contact Bob Norris Managing Dept. Interceptor s Date 3/25/02 68

14 69

15 VIP Project Name Sanitary Sewer Project Rehabilitation Phase V Line/PS No. SG 157 Account No. VRLF No. Rehabilitation Not Started This project will rehabilitate approximately 2,206 linear feet of 18-inch extra strength vitrified clay gravity main from Bainbridge Boulevard and Livingston Avenue to HRSD's Ferebee Avenue Pump Station in the City of Chesapeake. The cost estimate for this project is based on an in-house estimate. This project would extend the life of this gravity line which was constructed in CCTV inspection indicated numerous sections of cracked and broken pipe, drop joints and joint leaks. CCTV inspection also recorded 19 direct connections in this gravity main (not including manhole connections). Most of these connections have been punched into the pipeline instead of using lateral fittings. The 9 manholes are standard brick design and are in need of rehabilitation. This pipeline is under a heavily used section of Bainbridge Boulevard. Cost Estimate Construction $328, % of Const. $ 65, % of Const. $ 32,800 Total $426,400 Schedule Start (mo/yr) 04/03 Duration (mo) Requesting Dept. Interceptor s Dept. Contact John Wade/Jeff Midgett Managing Dept. Engineering Date 3/8/02 70

16 71

17 VIP Project Name South Trunk Sewer Section H Rehabilitation Line/PS No. SF 87 Account No. VRLF No. Rehabilitation Not Started This project will rehabilitate approximately 2,170 linear feet of 12-inch cast iron force main, which discharges from HRSD s Chesterfield Pump Station in Norfolk. This force main will be rehabilitated along Norchester Street, from Chesterfield Boulevard Pump Station to Highland Avenue. This force main passes under Interstate 264, at which point it is encased in concrete for a distance of approximately 244 linear feet. The cost estimate for this project is based on an in-house estimate. Costs include: 2,170 linear feet of $100 per linear foot = $217,000; 2,170 linear feet bypass pumping = $40,000. This project would extend the life of this force main, which was constructed in This force main has suffered one corrosion related failure in 1993 and two corrosion related failures in In each case, the physical condition of the pipe has been observed to be extremely deteriorated from both internal and external corrosion. In the two most recent failures, 5 linear feet and 14 linear feet sections of pipe have been removed and replaced. Soil conditions in this area, adjacent to the Eastern Branch of the Elizabeth River, are very corrosive. The 8-inch cast iron force main which connects to this line and was also constructed in 1947, was replaced in 1976 due to an increasing number of corrosion related failures. Cost Estimate Construction $257, % of Const. $ 51, % of Const. $ 30,900 Total $339,300 Schedule Start (mo/yr) 05/02 Duration (mo) 12 Requesting Dept. Interceptor s Dept. Contact John Wade Managing Dept. Engineering Date 3/8/02 72

18 VIP Project Name VIP Treatment Plant Grit Upgrade Line/PS No. Account No. VRLF No. Improvement Study Underway This project will evaluate and modify the VIP grit system in two phases. 1. Phase I: This phase will install two larger pumps, two fluidizers and one higher capacity classifier. This upgrade will eliminate all plugages of the grit system. 2. Phase II: This phase will purchase a second larger classifier, a larger pump and design and install the existing grit drain systems, which includes the plant drain, grit Pista tank drains and classifiers drain system, grit suction and discharge piping system, and the grit conveyance system to the dumpsters. This project will correct deficiencies with the current grit and drain systems and upgrade the grit system to handle 80 MGD maximum flow. The quantity of grit entering VIP is higher than originally designed. Removing grit to meet design specifications provides a more reliable downstream system. Cost Estimate Construction $640, % of Const. $128, % of Const. $ 77,000 Total $845,000 Schedule Start (mo/yr) 01/01 Duration (mo) 28 Requesting Dept. Treatment Dept. Contact Sami Ghosn Managing Dept. Treatment/Engineering Date 3/11/02 73

19 PROJECT REQUEST VIP Project Name VIP Treatment Plant Monitoring and Control Line/PS No. Account No. VRLF No. Replacement Not Started This project will replace existing obsolete monitoring system with a monitoring and control system. This project includes the replacement of the obsolete computer hardware/software platform, the interface software, data highway and PLCs. In addition the Solids Handling and Generator buildings will be included in the upgrade. This project will provide a reliable and improved integrated monitoring and control system. The current monitoring system is both unreliable and obsolete. Data is frequently lost and replacement parts for the system are rapidly becoming unavailable. The existing computer platform is not upgradeable and is no longer reliable or fault tolerant. The operating system and the platform that it resides on needs to be reconfigured to offer stable connectivity and fault tolerence to the system. The programmable logic controllers are obsolete and require replacement to interface with replaced hardware and software. The generator system and solids handling building need to be included in this project as they are currently not being monitored by the existing system. Cost Estimate Construction $1,440, % of Const. $ 288, % of Const. $ 172,000 Total $1,900,000 Schedule Start (mo/yr) 09/02 Duration (mo) 18 Requesting Dept. Treatment Dept. Contact Sami Ghosn Managing Dept. Engineering Date 4/12/02 74

20 VIP Project Name VIP Treatment Plant Odor Control Improvements, Phase I Line/PS No. Account No XXXXX-2210 VRLF No. Improvement In-House Review Underway This project will develop and implement solutions to the odor problems in the VIP bar screen room, administration building, primary clarifier "dog house" and grit dumpster areas. The project will include a review, design and recommendations from consultants to: 1. Eliminate unacceptably high sulfides levels from the bar screen room 2. Eliminate detectable sulfides and odors from the administration building 3. Reduce excessive odors from the primary clarifier "dog house" and grit Dumpster areas. The project will utilize consultants and a combination of in house forces and contractors to install necessary odor system modifications. Sulfide levels in the bar screen room are unacceptably high. Periodic odors and detectable sulfide levels in the administration building are unacceptable. Continuous odors and periodic high sulfide levels in the primary clarifier doghouse, and the grit classifier and dumpster rooms are a nuisance to plant staff and could at times pose potential worker safety issues. In house evaluation indicates the current system does not meet original design criteria. Cost Estimate Construction $294, % of Const. $ 59, % of Const. $ 35,000 Total $388,000 Schedule Start (mo/yr) / Duration (mo) Requesting Dept. Treatment Dept. Contact Sami Ghosn Managing Dept. Treatment/Engineering Date 3/15/02 75

21 VIP Project Name VIP Treatment Plant Water Reclamation Facility Line/PS No. Account No. VRLF No. New Facility Study Underway This project will design and construct a treated effluent polishing system to meet irrigation needs of the new City of Norfolk Golf Course. Due to the close proximity of the VIP site to the golf course and the anticipated cost savings to the City from using the polished effluent inlieu of potable water, this project appears to be an excellent opportunity for both HRSD and the City to demonstrate the viability of wastewater reuse. Scope of the project will be more specific after the study has been completed. This project will reuse treated effluent as a less expensive resource while conserving potable water. Cost Estimate Construction $ 873, % of Const. $ 174, % of Const. $ 104,900 Total $1,153,500 Schedule Start (mo/yr) /05 Duration (mo) 24 Requesting Dept. Treatment Dept. Contact Rhonda Bowen Managing Dept. Treatment Date 3/8/02 76

22 VIP Project Name VIP Treatment Plant Water Reuse Study Line/PS No. Account No XXXXX-1950 VRLF No. Study Study Underway This study is being done in two Phases. Phase I will determine the capability of spray irrigation of Golf Courses in the Tidewater Area with HRSD wastewater effluent as an alternative to potable water to establish and maintain high quality ornamentals and turfgrasses employed in golf greens and fairways. The Virginia Cooperative Extension will then develop a brochure and display explaining and promoting the beneficial reuse of wastewater effluent on golf course and other industrial turf grasses and ornamentals. A field day will be held to educate turfgrass managers and the public about the benefits of the practice. Phase II will continue to evaluate the benefits of drip irrigation of Golf Courses in the Tidewater Area with HRSD wastewater effluent as an alternative to potable water to establish and maintain high quality ornamentals and turfgrasses employed in golf greens and fairways. This phase will evaluate how much nitrogen and phosphorus fertilization rates can be reduced by applying recycled water, and evaluate whether the irrigation can be based on vegetative water needs rather than nutrient needs to determine the ability of vegetation to "clean" the recycled water of nitrogen and phosphorus. The Virginia Cooperative Extension will then develop a publication and write extensive articles explaining and promoting the beneficial reuse of wastewater effluent on golf course and other industrial turf grasses and ornamentals. A field day and other small tours will be conducted to educate turfgrass managers and the public about the benefits of the practice. This study will provide the necessary data to start a program for the use of wastewater effluent for the watering of golf courses. This will help save a scarce resource, potable water, and help eliminate the waste of another valuable resource, effluent water. Cost Estimate Construction $123, % of Const. $ 13, % of Const. $ 52,000 Total $189,500 Schedule Start (mo/yr) /00 Duration (mo) 60 Requesting Dept. Treatment Dept. Contact Rhonda Bowen Managing Dept. Treatment Date 3/8/02 77

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES 3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES All sanitary sewers shall be designed in accordance with these Design Standards, LBWD Rules and Regulations, and to accepted engineering principles. In

More information

SEWER SYSTEM DESIGN GUIDELINES

SEWER SYSTEM DESIGN GUIDELINES SEWER SYSTEM DESIGN GUIDELINES PART 1 GENERAL 1.1 GENERAL GUIDELINES A. The following sewer system design guidelines are based on Federal, State and Local health requirements, and the Berkeley County Water

More information

Polishing Ponds. Biosolids Storage. Ammonia Removal. Digesters. Thickeners. Pretreatment. Final Clarifiers. Primary Clarifiers.

Polishing Ponds. Biosolids Storage. Ammonia Removal. Digesters. Thickeners. Pretreatment. Final Clarifiers. Primary Clarifiers. Wastewater Treatment Facility (2012) Polishing Ponds Biosolids Storage Ammonia Removal Digesters Thickeners Pretreatment Primary Clarifiers Activated Sludge Final Clarifiers OVERVIEW Whenever a home, business,

More information

GUIDANCE MEMO NO : GUIDANCE CRITERIA FOR THE SEPARATION OF WATER MAINS AND NON-POTABLE PIPELINES

GUIDANCE MEMO NO : GUIDANCE CRITERIA FOR THE SEPARATION OF WATER MAINS AND NON-POTABLE PIPELINES State of California Memorandum Department of Health Services Date: April 4, 2003 To: From: Subject: Regional and District Engineers David P. Spath, Ph.D., Chief (Original signed by Dave) Drinking Water

More information

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION 820-1 SCOPE OF WORK: SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION a. Furnish all labor, materials, equipment, and incidentals required for demolition and/or removal and disposal of existing

More information

City of Redlands Wastewater Treatment Plant. Redlands, CA LOCATION: Carollo Engineers; CH2M HILL MBR MANUFACTURER: COMMENTS:

City of Redlands Wastewater Treatment Plant. Redlands, CA LOCATION: Carollo Engineers; CH2M HILL MBR MANUFACTURER: COMMENTS: FACILITY: City of Redlands Wastewater Treatment Plant LOCATION: Redlands, CA GEO. AREA: Southern California STATUS 07/14: Operational CONSTRUCTION: ENGINEERING: Carollo Engineers; CH2M HILL MBR MANUFACTURER:

More information

Region: Year Total Expense Total Revenue Difference ,000,000 4,000, ,000,000 4,000, Prior Years

Region: Year Total Expense Total Revenue Difference ,000,000 4,000, ,000,000 4,000, Prior Years Project Number: 53-120 Automated Meter Reading Equipment and Software Replacement Year Identified: 2008 Start Date: 7/1/2020 Est. Completion Date: 6/30/2025 This project will provide for the replacement

More information

AUTHORITY OF THE BOROUGH OF CHARLEROI WASHINGTON COUNTY, PENNSYLVANIA ACT 537 SEWAGE FACILITIES PLAN UPDATE

AUTHORITY OF THE BOROUGH OF CHARLEROI WASHINGTON COUNTY, PENNSYLVANIA ACT 537 SEWAGE FACILITIES PLAN UPDATE PLAN SUMMARY AUTHORITY OF THE BOROUGH OF CHARLEROI WASHINGTON COUNTY, PENNSYLVANIA ACT 537 SEWAGE FACILITIES PLAN UPDATE The Pennsylvania Sewage Facilities Act (Act 537) was enacted by the Pennsylvania

More information

PROCESSING COMBINED LASER, SONAR AND HD IMAGING FOR BETTER EVALUATION DECISIONS

PROCESSING COMBINED LASER, SONAR AND HD IMAGING FOR BETTER EVALUATION DECISIONS North American Society for Trenchless Technology (NASTT) No-Dig Show 2011 Washington, D.C. March 27-31, 2011 Paper F-3-05 PROCESSING COMBINED LASER, SONAR AND HD IMAGING FOR BETTER EVALUATION DECISIONS

More information

2016 Summary Report Capital Improvement Projects

2016 Summary Report Capital Improvement Projects 2016 Summary Report Capital Improvement Projects The City Commission adopted the Water and Wastewater 2013-2017 Capital Improvement Program (CIP) on March 12, 2013. The CIP identifies water and wastewater

More information

Proposed Wastewater Treatment Facility Equipment Repair and Replacement Project

Proposed Wastewater Treatment Facility Equipment Repair and Replacement Project Proposed Wastewater Treatment Facility Equipment Repair and Replacement Project Presented August 29 th, 2016 Function of IMKWWTP Treatment Facility History Reasons for Proposed Project Why Now? Modest

More information

Pam Iorio, Mayor 306 E. Jackson St * Tampa, FL Wastewater Department. Overflow Report

Pam Iorio, Mayor 306 E. Jackson St * Tampa, FL Wastewater Department. Overflow Report Page 1 / 7 Reported By: Owner: Name: FRED OCASIO with KCI TECHNOLOGIES Name:, Wastewater Department Location of Overflow: 17301 BRUCE B DOWNS BLVD Address: 306 E. Jackson Street Phone Number: 813 495-2460

More information

November 28, Dear Mr. Bechtold:

November 28, Dear Mr. Bechtold: 4000 Hollywood Boulevard Seventh Floor, North Tower Hollywood, Florida 33021 (954) 987-0066 Fax: (954) 987-2949 November 28, 2012 Wastewater Compliance and Enforcement Section FLORIDA DEPARTMENT OF ENVIRONMENTAL

More information

SECTION 7 SEPARATION OF WATER MAINS AND SANITARY SEWERS

SECTION 7 SEPARATION OF WATER MAINS AND SANITARY SEWERS SECTION 7 SEPARATION OF WATER MAINS AND SANITARY SEWERS To prevent the contamination of the public water supplies from nearby sanitary sewers, the following State Water Resources Control Board Division

More information

BEING GOOD STEWARDS: IMPROVING EFFLUENT QUALITY ON A BARRIER ISLAND. 1.0 Executive Summary

BEING GOOD STEWARDS: IMPROVING EFFLUENT QUALITY ON A BARRIER ISLAND. 1.0 Executive Summary BEING GOOD STEWARDS: IMPROVING EFFLUENT QUALITY ON A BARRIER ISLAND Brett T. Messner, PE, Tetra Tech, Inc., 201 E Pine St, Suite 1000, Orlando, FL 32801 Brett.Messner@tetratech.com, Ph: 239-851-1225 Fred

More information

2012 WASTEWATER PROJECTS

2012 WASTEWATER PROJECTS WASTEWATER PROJECTS 1 PROJECT NAME TABLE 1b - Wastewater Projects PROJECT STATUS SUMMARY UP PROJECT NUMBER PROJECT PHASE PERCENT COMPLETION Ocean Outfall Rule Change (Pilot) 10-9086 Design 10% Headworks

More information

Storm Water and Sanitary Sewer

Storm Water and Sanitary Sewer Public Works Department Summary Report on Planned Capital Improvements Storm Water and Sanitary Sewer Introduction Public Works has assembled this summary report to highlight major capital improvements

More information

Wastewater Master Facility Report. (Project Name) (Project Basin Location)

Wastewater Master Facility Report. (Project Name) (Project Basin Location) Wastewater Master Facility Report For (Project Name) (Project Basin Location) The Wastewater Master Facility Report for (Project name) dated (Date); located in the (Basin Name) Basin has been completed

More information

TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK

TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK COST EVALUATION FOR ROLLING HILLS AREA WATER MAIN EXTENSION PROFESSIONAL CONSULTING, LLC. Octagon 10, Office Center 1719 Route 10, Suite 225 Parsippany,

More information

TABLE OF CONTENTS SCHEDULE 18 (TECHNICAL REQUIREMENTS) DBFO AGREEMENT SECTION 2 - WATER AND WASTEWATER SYSTEMS EXECUTION VERSION

TABLE OF CONTENTS SCHEDULE 18 (TECHNICAL REQUIREMENTS) DBFO AGREEMENT SECTION 2 - WATER AND WASTEWATER SYSTEMS EXECUTION VERSION TABLE OF CONTENTS 2. Description of Water and Wastewater Systems... 2 2.1 General... 2 2.2 Existing Facilities Reference and Record Documents... 2 2.3 Existing Infrastructure Location and Legal Description...

More information

Facilities Plan. Technical Memorandum No. TM-WW-7 Hydraulic Analysis and Effluent Pump Station

Facilities Plan. Technical Memorandum No. TM-WW-7 Hydraulic Analysis and Effluent Pump Station City of St. Joseph, Missouri Hydraulic Analysis and Effluent Pump Station By Work Order No. 09-001 B&V Project 163509 May 20, 2010 Table of Contents 1.0 Executive Summary...1 2.0 Purpose of Study...2 3.0

More information

Appendix A EXAMPLE COLLECTION SYSTEM PERFORMANCE INDICATOR DATA COLLECTION FORM

Appendix A EXAMPLE COLLECTION SYSTEM PERFORMANCE INDICATOR DATA COLLECTION FORM Appendix A EXAMPLE COLLECTION SYSTEM PERFORMANCE INDICATOR DATA COLLECTION FORM EXAMPLE COLLECTION SYSTEM PERFORMANCE INDICATOR DATA COLLECTION FORM I. General Information A. Agency Name B. Agency Address

More information

May Preliminary Condition Assessment Report

May Preliminary Condition Assessment Report May 2010 Preliminary Condition Assessment Report PRELIMINARY CONDITION ASSESSMENT REPORT Prepared for Hampton Roads Sanitation District September 2009 Updated May 2010 Table of Contents Hampton Roads Sanitation

More information

Springfield Water and Sewer Commission. Fiscal Year 2017 Budget and Capital Plan Public Hearing June 7, 2016

Springfield Water and Sewer Commission. Fiscal Year 2017 Budget and Capital Plan Public Hearing June 7, 2016 Springfield Water and Sewer Commission Fiscal Year 2017 Budget and Capital Plan Public Hearing June 7, 2016 Joshua Schimmel Executive Director Introduction Overview of System Presentation Summary Commission

More information

EAST VALLEY WATER DISTRICT Wastewater Collection System Master Plan. Table 4-1 Capacity Evaluation d/d Criteria

EAST VALLEY WATER DISTRICT Wastewater Collection System Master Plan. Table 4-1 Capacity Evaluation d/d Criteria EAST VALLEY WATER DISTRICT Wastewater Collection System Master Plan 4 Capacity Analysis The capacity analysis used the calibrated dry weather and wet weather wastewater collection system model to evaluate

More information

TAMDID PIPES GRP MANHOLE BROCHURE

TAMDID PIPES GRP MANHOLE BROCHURE TAMDID PIPES GRP MANHOLE BROCHURE 1) Types & Description of Manholes: Tamdid Pipes offer two types of Manholes; Structural and Liner Manholes: a. Structural Manholes Tamdid Pipes offers concentric and

More information

CHARLES COUNTY GOVERNMENT ITB NO WAKEFIELD PUMPING STATION UPGRADE

CHARLES COUNTY GOVERNMENT ITB NO WAKEFIELD PUMPING STATION UPGRADE CHARLES COUNTY GOVERNMENT Department of Fiscal and Administrative Services Purchasing Division Telephone: 301-645-0656 February 27, 2014 ITB NO. 14-33 WAKEFIELD PUMPING STATION UPGRADE ADDENDUM NUMBER

More information

DESIGN OF SEWER SYSTEMS

DESIGN OF SEWER SYSTEMS Wastewater Engineering (MSc program) DESIGN OF SEWER SYSTEMS Prepared by Dr.Khaled Zaher Assistant Professor, Public Works Engineering Department, Faculty of Engineering, Cairo University 1. Sewer Materials

More information

A Multi-Faceted Approach to Odor Control for a 28.5-Mile Long Force Main

A Multi-Faceted Approach to Odor Control for a 28.5-Mile Long Force Main A Multi-Faceted Approach to Odor Control for a 28.5-Mile Long Force Main Kristen L. Smeby*, David S. Ehrhardt, Brian F. Duane Hazen and Sawyer, P.C. *Email: ksmeby@hazenandsawyer.com ABSTRACT Upon startup

More information

STANDARD DETAILS AND DETAIL SPECIFICATIONS

STANDARD DETAILS AND DETAIL SPECIFICATIONS STANDARD DETAILS AND DETAIL SPECIFICATIONS [THIS PAGE LEFT INTENTIONALLY BLANK] APPENDICES [THIS PAGE LEFT INTENTIONALLY BLANK] APPENDIX 1 CRITERIA

More information

MEMORANDUM. The general findings of the assessment are as follows:

MEMORANDUM. The general findings of the assessment are as follows: November 28, 2006 MEMORANDUM Project No.: 030009-002-01 To: From: Re: WRIA 31 Planning Unit Steve Germiat, LHG, CGWP, and Timothy J. Flynn, LHG, CWGP Evaluation of Winterizing Existing River Pump/Conveyance

More information

THE CARIBBEAN S MOST BEAUTIFUL WASTEWATER TREATMENT SYSTEM: CONSTRUCTED WETLAND AT ANTIGUA, W. I.

THE CARIBBEAN S MOST BEAUTIFUL WASTEWATER TREATMENT SYSTEM: CONSTRUCTED WETLAND AT ANTIGUA, W. I. THE CARIBBEAN S MOST BEAUTIFUL WASTEWATER TREATMENT SYSTEM: CONSTRUCTED WETLAND AT ANTIGUA, W. I. Gregory L. Morris * Laura Carbó Gregory L. Morris Engineering P.O. Box 9024157, San Juan, PR 00902 Tel.

More information

SECTION 4 RECOMMENDED DISTRIBUTION SYSTEM IMPROVEMENTS

SECTION 4 RECOMMENDED DISTRIBUTION SYSTEM IMPROVEMENTS 4.1 General SECTION 4 RECOMMENDED DISTRIBUTION SYSTEM IMPROVEMENTS Distribution system improvements, which have been organized and prioritized in this section, are forecasted and intended to be completed

More information

CHAPTER IV EXISTING SEWAGE TREATMENT FACILITIES IN THE PLANNING AREA

CHAPTER IV EXISTING SEWAGE TREATMENT FACILITIES IN THE PLANNING AREA CHAPTER IV EXISTING SEWAGE TREATMENT FACILITIES IN THE PLANNING AREA A. EXISTING FACILITIES 1. Westtown-Chester Creek Plant Westtown Township acquired the Westtown-Chester Creek Treatment Plant (WCC Plant)

More information

Project Name: Central WWTP Capacity Improvements and CSO Reduction Project. MWS Project Number: 14-SC-0153 Last Updated: 12/19/14

Project Name: Central WWTP Capacity Improvements and CSO Reduction Project. MWS Project Number: 14-SC-0153 Last Updated: 12/19/14 Project Name: Central WWTP Capacity Improvements and CSO Reduction Project MWS Project Number: 14-SC-0153 Last Updated: 12/19/14 BACKGROUND / PURPOSE Metro Water Services (MWS), in order to comply with

More information

North American Society for Trenchless Technology (NASTT) NASTT s 2016 No-Dig Show. Dallas, Texas March 20-24, 2016

North American Society for Trenchless Technology (NASTT) NASTT s 2016 No-Dig Show. Dallas, Texas March 20-24, 2016 North American Society for Trenchless Technology (NASTT) NASTT s 2016 No-Dig Show Dallas, Texas March 20-24, 2016 TA-T1-05 Quantitative pipe condition assessment with Pipe Penetrating Radar Csaba Ékes,

More information

Observations from Several Condition Assessments of Prestressed Concrete Cylinder Pipe used at Energy Generation Facilities

Observations from Several Condition Assessments of Prestressed Concrete Cylinder Pipe used at Energy Generation Facilities 147 Observations from Several Condition Assessments of Prestressed Concrete Cylinder Pipe used at Energy Generation Facilities Todd Stong PE 1, Ron R. Jorgenson 2, and Jacob Sauer 3 1 Senior Engineer,

More information

Chemigation. in Georgia

Chemigation. in Georgia Chemigation in Georgia Table of Contents Chemigation Terminology...3 The Benefits of Chemigation...3 General Principles of Chemigation Safety Considerations...3 Injection Methods...4 Determining Injection

More information

Irvine Ranch Water District Michelson Water Recycling Plant. Irvine, CA LOCATION: MBR MANUFACTURER: COMMENTS:

Irvine Ranch Water District Michelson Water Recycling Plant. Irvine, CA LOCATION: MBR MANUFACTURER: COMMENTS: FACILITY: Irvine Ranch Water District Michelson Water Recycling Plant LOCATION: Irvine, CA GEO. AREA: Southern California STATUS 07/14: Operational CONSTRUCTION: FILANC ENGINEERING: HDR Engineering MBR

More information

Customer Conference Speedway, IN 46224

Customer Conference Speedway, IN 46224 Customer Conference Speedway, IN 46224 DigIndy and Citizens Capital Investment Plan Updates Mark C. Jacob Vice President Capital Programs & Engineering September 18, 2014 A Matter of Trust Challenges Annually

More information

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY IN THE MATTER OF THE DECISION ON THE NEED FOR AN ENVIRONMENTAL IMPACT STATEMENT FOR THE PROPOSED LESTER PRAIRIE WASTEWATER TREATMENT FACILITY EXPANSION

More information

UTILITY SYSTEM OVERVIEW. Water Source Water Distribution Wastewater Collection Wastewater Treatment

UTILITY SYSTEM OVERVIEW. Water Source Water Distribution Wastewater Collection Wastewater Treatment 1 UTILITY SYSTEM OVERVIEW Water Source Water Distribution Wastewater Collection Wastewater Treatment 2 AGENDA Overview of the Utility System (building on the Council tours) ARWA Petersburg SCWWA Infrastructure

More information

UNDERGROUND CONSTRUCTION ISSUE TRAUTWEIN TACKLES NEWHOPE PLACENTIA TRUNK SEWER REPLACEMENT PROJECT CONSTRUCTION, INC. PG. 6

UNDERGROUND CONSTRUCTION ISSUE TRAUTWEIN TACKLES NEWHOPE PLACENTIA TRUNK SEWER REPLACEMENT PROJECT CONSTRUCTION, INC. PG. 6 UNDERGROUND CONSTRUCTION ISSUE TRAUTWEIN CONSTRUCTION, INC. PG. 6 TACKLES NEWHOPE PLACENTIA TRUNK SEWER REPLACEMENT PROJECT TRAUTWEIN CONSTRUCTION, INC. TACKLES NEWHOPE PLACENTIA TRUNK SEWER REPLACEMENT

More information

New York State Department of Environmental Conservation

New York State Department of Environmental Conservation May 2012 New York State Department of Environmental Conservation Award Submission for Environmental Excellence Awards Port Washington Water Pollution Control District (PWWPCD) Submitted by D&B Engineers

More information

HALL COUNTY DEPT OF PUBLIC WORKS & UTILITIES Page 1 of 8 Reuse Water End User Application

HALL COUNTY DEPT OF PUBLIC WORKS & UTILITIES Page 1 of 8 Reuse Water End User Application Page 1 of 8 Reuse Water End User Application Hall County s Reclaimed Water System is currently available in select areas of the County. This packet details the various benefits of reclaimed water and the

More information

Design of Sewerage System for Jaffarpur area in Southwest New Delhi

Design of Sewerage System for Jaffarpur area in Southwest New Delhi International Journal of Civil Engineering Research. ISSN 2278-3652 Volume 5, Number 1 (2014), pp. 29-34 Research India Publications http://www.ripublication.com/ijcer.htm Design of Sewerage System for

More information

17/03/2017 CONTENTS. Real Cases Studies in the Region for Pipelines Inspection & Rehabilitation. Introduction CONTENTS. Introduction / Cont.

17/03/2017 CONTENTS. Real Cases Studies in the Region for Pipelines Inspection & Rehabilitation. Introduction CONTENTS. Introduction / Cont. E M I R A T E S Real Cases Studies in the Region for Pipelines Inspection & Rehabilitation i) Introduction Dubia, UAE 14 March 2017 Trenchless Middle East Faiz Alelweet & Eng. Hamza Ali Maintenance Manager

More information

BIDDING SCHEDULE SEWER LIFT STATION NO. 2 REPLACEMENT PROJECT CITY OF ALHAMBRA City s Project No. N2M17-83

BIDDING SCHEDULE SEWER LIFT STATION NO. 2 REPLACEMENT PROJECT CITY OF ALHAMBRA City s Project No. N2M17-83 Item No. BIDDING SCHEDULE SEWER LIFT STATION NO. 2 REPLACEMENT PROJECT CITY OF ALHAMBRA City s Project No. N2M17-83 DESCRIPTION EST. QTY. UNIT UNIT PRICE TOTAL PRICE GENERAL BID ITEMS 1 Per Plans and Specifications

More information

PUMP STATION CHECK LIST

PUMP STATION CHECK LIST PUMP STATION CHECK LIST I. SITE LOCATION D. E. Location of pump station site has to be reviewed and approved by Planning Department and Department of Public Utilities. (II-V-F-1-J-i) The pump station has

More information

WEKO-SEAL Internal Joint Sealing. internal pipe-joint sealing

WEKO-SEAL Internal Joint Sealing. internal pipe-joint sealing WEKO-SEAL Internal Joint Sealing internal pipe-joint sealing We know seals inside and out. Retaining Band Test Valve WEKO-SEAL WEKO-SEAL is the leading trenchless system for internally and economically

More information

DELTA WASTEWATER TREATMENT PLANT UPGRADES

DELTA WASTEWATER TREATMENT PLANT UPGRADES Delta, Ohio Environmental and Electrical Engineering, Grant Administration Cost $2.6 million $3.2 million OWDA Loan 1,100 SF Admin Building Addition 0.725 MGD Average Daily Flow 1.5 MGD Peak Capacity Professional

More information

Design Considerations for Selection of Pipe Material for Large Diameter CSO Force Main

Design Considerations for Selection of Pipe Material for Large Diameter CSO Force Main Design Considerations for Selection of Pipe Material for Large Diameter CSO Force Main Pacific Northwest Clean Water Association 2010 Conference Presented By M. Patty Nelson, City of Portland Phil Roppo,,

More information

SECTION I FLEXIBLE PIPE VS. RIGID PIPE (GENERAL)

SECTION I FLEXIBLE PIPE VS. RIGID PIPE (GENERAL) h~i:! SECTION I FLEXIBLE PIPE VS. RIGID PIPE (GENERAL) Generally, rigid pipes have the following characteristics: made in discrete lengths use gaskets in joints to form a water-tight seal often produced

More information

CHAPTER 6. Sanitary Sewer

CHAPTER 6. Sanitary Sewer CHAPTER 6 Sanitary Sewer A. Introduction All proposed developments, subdivisions, and buildings must have a properly designed and constructed sanitary sewer collection system. The system shall provide

More information

W O C H H O L Z R E G I O N A L W A T E R R E C L A M A T I O N F A C I L I T Y O V E R V I E W

W O C H H O L Z R E G I O N A L W A T E R R E C L A M A T I O N F A C I L I T Y O V E R V I E W Facility Overview The recently upgraded and expanded Henry N. Wochholz Regional Water Reclamation Facility (WRWRF) treats domestic wastewater generated from the Yucaipa-Calimesa service area. The WRWRF

More information

Wastewater Flow Monitoring Services

Wastewater Flow Monitoring Services Wastewater Flow Monitoring Services For San Gabriel, CA July 13, 2015 through July 21, 2015 Revised October 9, 2015 Leaders in Sewer Flow Monitoring Services 601 N. Parkcenter Dr., Suite 209 Santa Ana,

More information

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL This section covers the furnishing and installation of ductile iron water pipe, fittings, thrust restraint and pipe disinfection. Ductile Iron Pipe MATERIALS

More information

City of Phoenix Superior Pipeline PCCP Investigation and Assessment

City of Phoenix Superior Pipeline PCCP Investigation and Assessment City of Phoenix Superior Pipeline PCCP Investigation and Assessment Ronald Ablin, P.E. 1, Brandy Kelso, P.E. 2, Bethany Williams, P.E. 3, Myron Shenkiryk 4, The City of Phoenix is currently in a multi-year

More information

Grit Collection & Classification Case Studies

Grit Collection & Classification Case Studies Grit Collection & Classification Case Studies OWEA 2010 Specialty Biosolids Specialty Workshop Brian F. McNamara, HRSD Definition of Grit Metcalf & Eddy 2 nd Edition 1979 grit, consisting of sand, gravel,

More information

PIPE USERS GROUP (PUG) July 11, Michelle Beason, PE Regional Manager National Plant Services, Inc., a Carylon Company

PIPE USERS GROUP (PUG) July 11, Michelle Beason, PE Regional Manager National Plant Services, Inc., a Carylon Company PIPE USERS GROUP (PUG) July 11, 2017 Michelle Beason, PE Regional Manager National Plant Services, Inc., a Carylon Company NATIONAL PLANT SERVICES, INC. New Service yard in Hayward, CA. Headquarters in

More information

WATER RESOURCES - WATER SUPPLY

WATER RESOURCES - WATER SUPPLY EXECUTIVE SUMMARY Sacramento County Water Agency (SCWA) constructs water supply improvement projects to serve both newly developing areas and existing customers. This report summarizes those construction

More information

Protective Coatings for Underground Utility Concrete Structures. By: John E. Davis Inside Sales & Marketing Specialist: Sauereisen, Inc.

Protective Coatings for Underground Utility Concrete Structures. By: John E. Davis Inside Sales & Marketing Specialist: Sauereisen, Inc. Protective Coatings for Underground Utility Concrete Structures By: John E. Davis Inside Sales & Marketing Specialist: Sauereisen, Inc. As our cities and municipalities grow older, the utility and wastewater

More information

2013 WASTEWATER PROJECTS

2013 WASTEWATER PROJECTS WASTEWATER PROJECTS 1 PROJECT NAME TABLE 1b - Wastewater Projects PROJECT STATUS SUMMARY UP PROJECT NUMBER PROJECT PHASE April 2013 PERCENT COMPLETION Ocean Outfall Rule Change (Pilot) 10-9086 Design 50%

More information

Town of Sewall s Point Septic Tank to Sanitary Sewer. History

Town of Sewall s Point Septic Tank to Sanitary Sewer. History November 15, 2016 History In 2015, Martin County Utilities completed a Septic to Sewer conversion study which illustrated the need to remove septic tanks from the Indian River Lagoon and St. Lucie Estuary.

More information

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination Highway Drainage Proper drainage is a very important consideration in design of a highway. Inadequate drainage facilities can lead to premature deterioration of the highway and the development of adverse

More information

PRESENTED BY: IR. TAI LEE YOON JURUTERA JASA (SARAWAK) SDN BHD

PRESENTED BY: IR. TAI LEE YOON JURUTERA JASA (SARAWAK) SDN BHD PRESENTED BY: IR. TAI LEE YOON JURUTERA JASA (SARAWAK) SDN BHD PRE-PROJECT SITUATION Black water is partially treated by septic tanks. Grey water is directly discharged into the drains and river system

More information

Sample Bid Specification Revision 2 PVC Expanded-in-Place Pipeline Reconstruction

Sample Bid Specification Revision 2 PVC Expanded-in-Place Pipeline Reconstruction Sample Bid Specification Revision 2 PVC Expanded-in-Place Pipeline Reconstruction 1.00 DESCRIPTION 1.01 WORK INCLUDED: This work shall include the furnishing of all labor, equipment and materials necessary

More information

The New Age for Sewer Planning at the City of Los Angeles

The New Age for Sewer Planning at the City of Los Angeles The New Age for Sewer Planning at the City of Los Angeles Mario Dimzon 1 * P.E., Fernando Gonzalez 1 P.E., Ali Poosti 1 PE, Adel Hagekhalil 1 PE, Erick Heath 2 P.E., Rajan Ray 2 P.E., Erin Breen 2 P.E.

More information

MONTHLY PROJECT REPORTS. As of November 30, Muddy Creek Watershed

MONTHLY PROJECT REPORTS. As of November 30, Muddy Creek Watershed MONTHLY PROJECT REPORTS As of November 30, 2013 Watershed Monthly Reports Watershed Dashboard Name Float (Least) to Milestone Schedule Health Indicator Change in Schedule Health Indicator from Last Month

More information

ASSET MANAGEMENT PROGRAM

ASSET MANAGEMENT PROGRAM ASSET MANAGEMENT PROGRAM July 2017 Orange Water and Sewer Authority Carrboro, North Carolina A public, non-profit agency providing water, sewer and reclaimed water services to the Carrboro-Chapel Hill

More information

Module 2 : System of Sanitation. Lecture 2 : System of Sanitation

Module 2 : System of Sanitation. Lecture 2 : System of Sanitation 1 P age Module 2 : System of Sanitation Lecture 2 : System of Sanitation 2 P age 2.1 BACKGROUND For safe disposal of the sewage generated from a locality efficient collection, conveyance, adequate treatment

More information

Minimum grade (%) Velocity at full flow (m s 1 )

Minimum grade (%) Velocity at full flow (m s 1 ) 1.6 Pipes Effluent can be conveyed by channels or pipes under gravity or in dedicated pipelines under pressure. If pipes are used, pressure rating, water-hammer and excessive friction losses must be considered

More information

Taylor Creek Treatment Plant. Metropolitan Sewer District of Greater Cincinnati

Taylor Creek Treatment Plant. Metropolitan Sewer District of Greater Cincinnati Taylor Creek Treatment Plant Metropolitan Sewer District of Greater Cincinnati Who is this guy and what is he talking about? Brad Blankenship Taylor Creek Operator 3.5 years MSD Operator 5.5 years (total)

More information

INSTALLING A SEPTIC SYSTEM IN LIVINGSTON COUNTY LIVINGSTON COUNTY PUBLIC HEALTH DEPARTMENT 310 TORRANCE AVENUE PONTIAC, IL /

INSTALLING A SEPTIC SYSTEM IN LIVINGSTON COUNTY LIVINGSTON COUNTY PUBLIC HEALTH DEPARTMENT 310 TORRANCE AVENUE PONTIAC, IL / INSTALLING A SEPTIC SYSTEM IN LIVINGSTON COUNTY LIVINGSTON COUNTY PUBLIC HEALTH DEPARTMENT 310 TORRANCE AVENUE PONTIAC, IL 61764 815/844-7174 MALINDA HILLMAN, ADMINISTRATOR DONNIE SIMMONS, L.E.H.P. DIRECTOR

More information

READ ONLY. Adopting Agency BSC SFM. Adopt Entire Chapter Adopt Entire Chapter as amended (amended sections listed below)

READ ONLY. Adopting Agency BSC SFM. Adopt Entire Chapter Adopt Entire Chapter as amended (amended sections listed below) CALIFORNIA PLUMBING CODE MATRIX ADOPTION TABLE APPENDIX C - ALTERNATE PLUMBING SYSTEMS (Matrix Adoption Tables are non-regulatory, intended only as an aid to the user. See Chapter 1 for state agency authority

More information

UNIFORM DESIGN AND CONSTRUCTION STANDARDS FOR EXTENDING WATER DISTRIBUTION SYSTEMS SECTION 2 DESIGN STANDARDS

UNIFORM DESIGN AND CONSTRUCTION STANDARDS FOR EXTENDING WATER DISTRIBUTION SYSTEMS SECTION 2 DESIGN STANDARDS UNIFORM DESIGN AND CONSTRUCTION STANDARDS FOR EXTENDING WATER DISTRIBUTION SYSTEMS SECTION 2 DESIGN STANDARDS DESIGN STANDARDS SECTION 2 INDEX ITEM DESCRIPTION 2.00 GENERAL STATEMENT 2.01 WATER DISTRIBUTION

More information

Tour of Altamonte Springs Regional Water Reclamation Facility

Tour of Altamonte Springs Regional Water Reclamation Facility Name: Date: Tour of Altamonte Springs Regional Water Reclamation Facility Middle School Earth Science Spring Module 3 Regional Water Reclamation Facility NGSSS Big Idea: Big Idea 2 The Characteristics

More information

UNIVERSITY OF SOUTH ALABAMA 2015 UTILITIES MASTER PLAN SUMMARY REPORT

UNIVERSITY OF SOUTH ALABAMA 2015 UTILITIES MASTER PLAN SUMMARY REPORT UNIVERSITY OF SOUTH ALABAMA 2015 UTILITIES MASTER PLAN SUMMARY REPORT August 2015 Prepared by: Krebs Engineering, Inc. 2100 River Haven Drive, Suite 100 Birmingham, AL 35244 www.krebseng.com Page 1 TABLE

More information

FINAL ASSET MANAGEMENT PROGRAM March 2016

FINAL ASSET MANAGEMENT PROGRAM March 2016 FINAL ASSET MANAGEMENT PROGRAM March 2016 Orange Water and Sewer Authority Carrboro, North Carolina A public, non-profit agency providing water, sewer and reclaimed water services to the Carrboro-Chapel

More information

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7: Hydraulic Design of Sewers and Storm Water Drains

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7: Hydraulic Design of Sewers and Storm Water Drains Module 7: Hydraulic Design of Sewers and Storm Water Drains Lecture 7: Hydraulic Design of Sewers and Storm Water Drains 7.0 HYDRAULIC DESIGN OF SEWERS AND STORM WATER DRAINS 7.1 General Consideration

More information

THIS IS A COURTESY COPY OF THIS RULE. ALL OF THE DEPARTMENT S RULES ARE COMPILED IN TITLE 7 OF THE NEW JERSEY ADMINISTRATIVE CODE.

THIS IS A COURTESY COPY OF THIS RULE. ALL OF THE DEPARTMENT S RULES ARE COMPILED IN TITLE 7 OF THE NEW JERSEY ADMINISTRATIVE CODE. (f) The minimum requirements for construction, materials and foundations of grease traps shall be the same as those required for septic tanks, as prescribed in N.J.A.C. 7:9A-8.2. (g) The inlet and outlet

More information

City of Grenora, ND Municipal Infrastructure Needs Assessment August 2012

City of Grenora, ND Municipal Infrastructure Needs Assessment August 2012 City of Grenora, ND Municipal Infrastructure Needs Assessment August 2012 Project made possible by US Dept. of HUD Regional Substantiality Planning Grant and ND Energy Development Infrastructure and Impact

More information

Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control Plan 'Division E'

Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control Plan 'Division E' North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 Paper MA-T4-02 Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control

More information

Pipeline Condition Assessment. The Essential Engineering Step in the Asset Management Process

Pipeline Condition Assessment. The Essential Engineering Step in the Asset Management Process Pipeline Condition Assessment. The Essential Engineering Step in the Asset Management Process Tom Sangster. Principal, Jason Consultants Group, Geneva, Switzerland Synopsis Condition assessment is a critical

More information

UNIVERSITY OF OREGON NORTH CAMPUS CONDITIONAL USE PERMIT PROJECT Draft Conditional Use Permit Stormwater, Sanitary Sewer, and Water Analysis Report

UNIVERSITY OF OREGON NORTH CAMPUS CONDITIONAL USE PERMIT PROJECT Draft Conditional Use Permit Stormwater, Sanitary Sewer, and Water Analysis Report UNIVERSITY OF OREGON NORTH CAMPUS CONDITIONAL USE PERMIT PROJECT Draft Conditional Use Permit Stormwater, Sanitary Sewer, and Water Analysis Report Prepared for: Cameron McCarthy Landscape Architects LLP

More information

Sanitary Sewer Extensions, Lift Stations, and Force Mains Engineering Report Form. I. General Information. 1. Name of Facility:

Sanitary Sewer Extensions, Lift Stations, and Force Mains Engineering Report Form. I. General Information. 1. Name of Facility: Oklahoma Department of Environmental Quality Water Quality Division Phone: 405-702-8100 Construction Permitting Section 707 N. Robinson, OKC, OK 73102-6010 P.O. Box 1677, OKC, OK 73101-1677 Sanitary Sewer

More information

Commonwealth of Massachusetts Title 5 Official Inspection Form Subsurface Sewage Disposal System Form - Not for Voluntary Assessments

Commonwealth of Massachusetts Title 5 Official Inspection Form Subsurface Sewage Disposal System Form - Not for Voluntary Assessments Inspection results must be submitted on this form. Inspection forms may not be altered in any way. Important: When filling out forms on the computer, use only the tab key to move your cursor - do not use

More information

Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000

Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000 Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000 610S.1 This item shall govern the proper care and treatment of all trees and other vegetation

More information

Sanitary Sewer Systems. Sewage Collection System. Types of Sewage 10/12/2016. General Overview

Sanitary Sewer Systems. Sewage Collection System. Types of Sewage 10/12/2016. General Overview Sanitary Sewer Systems General Overview Sewage Collection System Pipes Pumping stations Maintenance entry points manholes Types of Sewage Sanitary Domestic sewage: human wastes and washwater from public

More information

Ellis Creek Water Recycling Facility, City of Petaluma

Ellis Creek Water Recycling Facility, City of Petaluma Ellis Creek Water Recycling Facility, City of Petaluma Historical Timeline Facility Treatment Processes / Flow Schematics Challenges of Wetlands Dechlorination Mode of Operation Benefits of Natural Dechlorination

More information

LOS ANGELES RIVER/RIO HONDO DIVERSION 2 LEVEE SYSTEM LOS ANGELES COUNTY, CALIFORNIA NLD SYSTEM ID #

LOS ANGELES RIVER/RIO HONDO DIVERSION 2 LEVEE SYSTEM LOS ANGELES COUNTY, CALIFORNIA NLD SYSTEM ID # LOS ANGELES RIVER/RIO HONDO DIVERSION 2 LEVEE SYSTEM LOS ANGELES COUNTY, CALIFORNIA NLD SYSTEM ID # 3805010047 PERIODIC INSPECTION REPORT NO 1 GENERALIZED EXECUTIVE SUMMARY FINAL SYSTEM RATING: UNACCEPTABLE

More information

GOALS, OBJECTIVES, & POLICIES

GOALS, OBJECTIVES, & POLICIES ELEMENT 9 INFRASTRUCTURE ELEMENT STORM WATER MANAGEMENT SUB-ELEMENT Goal 1 To provide adequate stormwater management facilities and services to meet the present and future needs of the University and to

More information

Contact the Jurisdictional Engineer for materials allowed by each jurisdiction.

Contact the Jurisdictional Engineer for materials allowed by each jurisdiction. Design Manual Chapter 3 - Sanitary Sewers 3C - Facility Design 3C-1 Facility Design A. Capacity of Pipe Pipe sizes 15 inches and smaller should carry the peak flow at a depth of no more than 0.67 of the

More information

CHAPTER 4 MINIMUM DESIGN CRITERIA

CHAPTER 4 MINIMUM DESIGN CRITERIA 4.1 INTRODUCTION CHAPTER 4 MINIMUM DESIGN CRITERIA Establishing realistic design criteria is paramount to evaluation of the existing water system s adequacy and planning for future water system improvements.

More information

LOS ANGELES RIVER/RIO HONDO DIVERSION 2 LEVEE SYSTEM LOS ANGELES COUNTY, CALIFORNIA NLD SYSTEM ID #

LOS ANGELES RIVER/RIO HONDO DIVERSION 2 LEVEE SYSTEM LOS ANGELES COUNTY, CALIFORNIA NLD SYSTEM ID # LOS ANGELES RIVER/RIO HONDO DIVERSION 2 LEVEE SYSTEM LOS ANGELES COUNTY, CALIFORNIA NLD SYSTEM ID # 3805010047 PERIODIC INSPECTION REPORT NO 1 GENERALIZED EXECUTIVE SUMMARY FINAL SYSTEM RATING: UNACCEPTABLE

More information

Remote Headworks Upgrade. November 4, 2010

Remote Headworks Upgrade. November 4, 2010 Remote Headworks Upgrade November 4, 2010 Chelsea Creek Headworks Comb. and Sep. Trib. Areas (brown shading) Flow discharge to North Met Relief Tunnel Peak Cap (350 MGD), Avg. Flow (135 MGD) Columbus Park

More information

Where Intelligence Meets Infrastructure PA AWWA Conference

Where Intelligence Meets Infrastructure PA AWWA Conference Where Intelligence Meets Infrastructure 2017 PA AWWA Conference Analysis and Verification of PCCP Stiffness Testing Using Non-Invasive Acoustic Testing Name: John Marciszewski jmarciszewski@echologics.com

More information

Appendix A3 Connector Lines Between Stations June 1999 (Updated April 2010)

Appendix A3 Connector Lines Between Stations June 1999 (Updated April 2010) Appendix A3 Connector Lines Between Stations June 1999 (Updated April 2010) MADISON METROPOLITAN SEWERAGE DISTRICT COLLECTION SYSTEM TECHNICAL GUIDELINES APPENDIX 3 CONNECTOR LINES BETWEEN STATIONS Stations

More information

Section 7 Hydraulic Model Development and Evaluation Criteria

Section 7 Hydraulic Model Development and Evaluation Criteria Section 7 Hydraulic Model Development and Evaluation Criteria The hydraulic evaluation conducted to develop this master plan was performed using a computer model of the reclaimed water distribution system.

More information

SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES

SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES 4.1 GENERAL REQUIREMENTS 4.1.1 Water and fire protection distribution facilities are to be provided solely for the purpose of supplying potable

More information