MONTHLY PROJECT REPORTS. As of November 30, Muddy Creek Watershed

Size: px
Start display at page:

Download "MONTHLY PROJECT REPORTS. As of November 30, Muddy Creek Watershed"

Transcription

1 MONTHLY PROJECT REPORTS As of November 30, 2013 Watershed

2 Monthly Reports Watershed Dashboard Name Float (Least) to Milestone Schedule Health Indicator Change in Schedule Health Indicator from Last Month Current Budgeted Cost Estimated Cost at ed (Over-run) or Under-run Budget Health Indicator Change in Budget Health Indicator from Last Month Glenview Pump Station 915 days No change $1,582,300 $1,553,800 $28,500 No change WWTP Grit Replacement 70 days Longer construction duration required $4,309,200 $4,166,000 $143,200 No change WWTP New Dewatering 70 days Longer construction duration required $6,271,800 $6,184,900 $86,900 No change Werk and Westbourne EHRT Facility 0 days Stop work order issued by BOCC $69,372,500 $69,356,000 $16,500 No change Barrington Hills Pump Station Elimination N/A No change $9,609,000 $10,058,000 ($449,000) No change WWTP Electrical Upgrade N/A No change $9,520,000 $6,429,000 $3,091,000 No change WWTP Odor Control N/A No change $888,600 $890,500 ($1,900) No change WWTP Primary Skimmings/Sludge Removal Replacement N/A No change $4,197,400 $3,621,800 $575,600 No change Upper Interceptor Replacement N/A No change $19,131,000 $19,008,000 $123,000 No change

3 Schedule The available float each project milestones is in excess of 180 calendar days. The available float to any project milestone is between 180 and 90 calendar days. The available float to any project milestone is less than 90 calendar days and there is more than 45 calendar days of scheduled work remaining. Budget The estimated project costs at completion are 110% or less of the current estimated project cost. The estimated project costs at completion are between 110% and 120% of the current estimated project cost. The estimated project costs at completion are in excess of 120% of the current estimated project cost.

4 Glenview Pump Station ID Green Township This project address a severely deteriorated pump station that was originally constructed in During wet weather events, sewage can bypass the pump station and overflow into Wesselman Creek. This project was classified as a Phase 1 Wet Weather Improvement Plan project because it has the ability to eliminate an existing sanitary sewer overflow (SSO). Consultant Manager Inspector Manager Consultant Inspector N/A Jim Curry Bill Sara Lutz Cramer Steve Jacobs Jones Engineering Group Inc. Rob Apel CH2M Hill Cincinnati Tunnel Partners This project proposes to upgrade the existing pump station tributary to the Wastewater Treatment Plant. The existing Glenview Pump Station will be replaced with a new pump station. The proposed pump station consists of an 8-foot diameter wet well with duplex pumps, a separate concrete valve chamber, and a diesel-engine generator. New fence and gates will be installed around the proposed pump station. The existing pump station driveway that extends to Virginia Court will be replaced with a new driveway. The proposed pump station is designed for a flow of 570 gallons per minute and will connect to the existing 6-inch force main. A new 18-inch gravity sewer, 15-feet in length, will be installed from the existing wet well manhole to the new pump station wet well. As part of this project, new electrical infrastructure will be installed to provide three-phase power. Milestone Dates Float Status PTI Submittal 12/31/2016 1,037 days No delay 12/31/ days No delay 12/31/2018 1,157 days No delay MSD received formal approval from US EPA in August 26, 2013 to extend the Consent Decree Milestone compliance dates, as requested by the BOCC to the Regulators on March 18, The 90% design review meeting was held on November 13, The PTI is scheduled for submittal in February Phase Activities It is anticipated that two permanent easements will be required and several temporary easements if the force main needs replacement. Legislated January 2015 () June 29, 2011 There are no issues at this time. 100% Planning June 2011 June 30, % November 2014 Ongoing ROW Acquisition February 2014 September 2014 Bidding May 2015 February 27, 2012 (withdrawn) Current Estimated Cost $1,553,803 Legislated Cost $676,500 The extends from just south of Interstate 74 all the way to the Ohio River, and serves a substantial area west of the City of Cincinnati, including portions of Western Hills and Bridgetown and extending westward along River Road (Rt. 50). June 2015 October 2015 Actual Cost To-Date $286,750 % of Current Estimated Cost 18%

5 Wastewater Treatment Plant Grit Replacement ID City of Cincinnati (Sayler Park) This project is part of the Wastewater Treatment Plant Bundle, which consists of projects that will upgrade the facility to be able to treat peak wet weather flows up to 35 million gallons per day (MGD) for extended periods of time. for this bundle of projects was classified under Phase 1 of the Wet Weather Improvement Plan to ensure the Wastewater Treatment Plant has adequate capacity to treat additional flows resulting from elimination of sanitary and combined sewer overflows Consultant Manager Inspector Tony Yee Jacobs Engineering Group, Inc. Maria Donisi The project includes replacement of grit equipment at the WWTP. The purpose of this project is to increase the reliability of the Wastewater Treatment Plant's ability to treat peak flows up to 35 million gallons per day (MGD) for extended periods of time. In order to sustain 35 MGD treatment capacity, improvements to the grit removal system are required. The current grit system is adequate to treat dry weather flow, but is not robust enough to address wet weather flow. This project is located at the WWTP, which is located in the sewershed of the West in the City of Cincinnati s Saylor Park neighborhood, Hamilton County. Milestone Dates Float Status PTI Submittal 12/31/ MET 12/31/ days No delay 12/31/ days No delay Activities Legislated 2013 November 6, 2013 () 100% Planning 2012 November 30, % 2013 October 15, 2013 ROW Acquisition N/A N/A The PTI was submitted in August 2013 and is currently under review by the Ohio EPA. The building permit application was submitted in September The 100% design was submitted in October legislation was approved by the Board of County Commissioners (BOCC) in November All of the bundle projects (Odor Control, Grit Replacement, and New Dewatering) will go out for bid together upon approval of construction legislation by the BOCC for the New Dewatering project. duration is forecasted longer than initially envisioned during development of the final WWIP. MSD and the County will request consideration for an extension of the construction completion milestone from the Regulators to increase the amount of float available such that unforeseen circumstances will not impact meeting the milestone August 15, 2013 Bidding March 2014 April 2014 October 2015 Current Estimated Cost $4,166,072 Legislated Amount $4,309,200 Actual Cost To-Date $418,486 Budget % 10% The extends from just south of Interstate 74 all the way to the Ohio River, and serves a substantial area west of Cincinnati, including portions of Western Hills and Bridgetown and extending westward along River Road (Rt. 50).

6 Wastewater Treatment Plant New Dewatering ID City of Cincinnati (Sayler Park) This project is part of the Wastewater Treatment Plant (WWTP) Bundle, which consists of projects that will upgrade the facility to be able to treat peak wet weather flows up to 35 million gallons per day (MGD) for extended periods of time. for this bundle of projects was classified under Phase 1 of the Wet Weather Improvement Plan to ensure the Wastewater Treatment Plant has adequate capacity to treat additional flows resulting from elimination of sanitary and combined sewer overflows. Consultant Manager Inspector Tony Yee Jacobs Engineering Group, Inc. Maria Donisi This project includes construction of a new dewatering system. It is required to address capacity limitations at the treatment plant. The WWTP currently has one belt filter press. The overall District solids disposal strategy relies on fluidized bed incineration. Belt filter press technology does not produce a sludge cake of sufficient dryness for auto-thermal incineration. This project will provide two centrifuge units to increase the WWTP s firm solids dewatering capacity. This project is located at the WWTP, which is located in the sewershed of the West in the City of Cincinnati s Saylor Park neighborhood, Hamilton County. Milestone Dates Float Status PTI Submittal 12/31/ MET 12/31/ days No delay 12/31/ days No delay Activities Legislated January 2014 () 2014 CIP 100% Planning 2012 November 30, % 2013 October 15, 2013 The PTI was submitted in August 2013 and is currently under review by the Ohio EPA. The building permit application was submitted in September The 100% design was submitted in October Request for construction funding from the Board of County Commissioners is to be determined. Upon approval of construction funding, all of the bundle projects (Odor Control, Grit Replacement, and New Dewatering) will go out for bid together. duration is forecasted longer than initially envisioned during development of the final WWIP. MSD and the County will request consideration for an extension of the construction completion milestone from the Regulators to increase the amount of float available such that unforeseen circumstances will not impact meeting the milestone. ROW Acquisition N/A N/A Bidding March August 15, 2013 April 2014 October 2015 Current Estimated Cost $6,184,900 Legislated Amount $614,600 Actual Cost To-Date $390,750 Budget % 6% The extends from just south of Interstate 74 all the way to the Ohio River, and serves a substantial area west of Cincinnati, including portions of Western Hills and Bridgetown and extending westward along River Road (Rt. 50).

7 Werk and Westbourne EHRT Facility ID Green Township N/A Nate Tetrick This project includes installation of an enhanced high rate treatment (EHRT) facility to provide storage, settling, and screening for combined sewage at CSO 522 located at Werk Road and Westbourne Drive. This project will greatly improve the quality of the water being discharged to during wet weather events. The EHRT facility will be able to store, settle, and screen up to 106 million gallons a day of combined sewage. This project was classified as a Phase 1 Wet Weather Improvement Plan project because it has the ability to improve the quality of water being discharged through CSO 522 during wet weather events. It is also a community priority for aesthetic reasons. All work associated with this project will be fully completed by the Consent Order Milestone date of December 31, 2017 (Attachment 1A Final WWIP). Planning Consultant Manager Consultant Inspector Consultant Inspector Bill Tony Lutz Yee Steve Black Jones and Veatch Corporation Rob Black Apel and Veatch Corporation CH2M Hill Cincinnati Tunnel Partners The consultant continued to work on the 90% design. A 90% design review meeting was held on November 13, A stop work order was issued by the Executive Director on December 6, 2013 per direction received from the BOCC in order to request a six month project extension of the consent decree deadlines from the Regulators. The PTI paperwork is completed and ready to submit by the December 31, 2013 Consent Decree deadline. Milestone Dates Float Status PTI Submittal 12/31/ days No delay 12/31/ days No delay 12/31/ days No delay MSD is focusing on the right-of-way plan for the north side of Werk Road. It is anticipated that MSD will need this property for a period of three years for the construction of the project. This project continues to be coordinated with the Upper Interceptor Sewer ( ) for the replacement of Sanitary Sewer 41. This project also continues to be coordinated with the Dry Weather Channel for Sewer 937 ( ). Activities This project is on hold per direction from the Board of County Commissioners (BOCC). Legislated May 2014 () December 15, % Planning October 2012 October 16, % March 2014 Ongoing December 2013 Ongoing MSD and the County are working to evaluate potential cost-saving approaches related to this watershed. The extends from just south of Interstate 74 all the way to the Ohio River, and serves a substantial area west of Cincinnati, including portions of Western Hills and Bridgetown and extending westward along River Road (Rt. 50). ROW Acquisition February 2014 Bidding September 2014 September 2014 October 2017 Current Estimated Cost $69,355,915 Legislated Funds $7,452,200 Actual Costs to Date $5,861,586 % Current Estimated Cost 8% In the Final WWIP, the Werk and Westbourne project was proposed as the pilot project for enhanced high rate treatment (EHRT). This technology is intended to treat storm water overflows. Since the system proposed by MSD does not include ballasted flocculation, piloting is being performed to determine the effectiveness of the EHRT technology for this specific application.

8 Barrington Hills Pump Station Elimination ID Green Township The purpose of this project is to eliminate five existing pump stations through construction of a new sanitary sewer. It includes construction of 9,600 feet of 8-inch to 15-inch diameter sewer and elimination of five pump stations, including Barrington Hills PS, Barrington Hills Block F PS, Gil Volz PS, Kirkridge Acres PS, and Kildare Crossings PS. This project will provide service to unsewered areas and reduce annual operating and maintenance costs resulting from the pump stations. This project is being coordinated with other active project plans for the sewershed. Manager Consultant Inspector Inspector Consultant Milestone Activities Legislated N/A Casey Walter Bill Lutz Tony Yee Steve Jones CH2M Hill Rob Apel CH2M Hill Cincinnati Tunnel Partners Date May 2018 November () 2017 () 2006, 2007, Planning 100% Planning 2007 The project is located between Leibel Road in Green Township and 1 st Street in the Village of Addyston. The original design included design of the gravity sewers connecting the five pump stations and one replacement pump station. During the detailed design, the MSD Collections group provided an alternative to the replacement pump station with a gravity sewer connecting to an existing sewer. Given the topography and existing structures and infrastructure, the new gravity line will be constructed using trenchless technology to minimize the impact to area residents and businesses. A Business Case Evaluation (BCE) examined the two options. Right-of-way acquisition to obtain four easements is on hold, as well as application for U.S. Army Corps of Engineers (USACOE) 404 permit and the OEPA 401 Water Quality Permit. The BCE turnover memo for design was signed in September Additional design and right-of-way funds were requested for legislation from the Capital Expenditure Core Team (CAPEX) on November 5, Additional design and right-of-way funds will be requested for legislation from the Board of County Commissioners (BOCC). There are no issues at this time.. 100% August 2016 October 2016 ROW Acquisition October 2017 Current Estimated Cost $10,058,400 Bidding April 2018 May 2018 November 2019 Legislated Funds $1,396,700 Actual Costs to Date $845,062 % Current Estimated Cost 8% The extends from just south of Interstate 74 all the way to the Ohio River, and serves a substantial area west of the City of Cincinnati, including portions of Western Hills and Bridgetown and extending westward along River Road (Rt. 50).

9 Wastewater Treatment Plant Electrical Upgrade ID Sayler Park s This Asset Management includes electrical upgrades at MSDGC s Wastewater Treatment Plant. This project includes replacement and relocation of significant electrical components, some of which are 30 years old, and in poor condition. This includes switchgear, panel boards and motor control centers. The components are located throughout the plant and opportunities exist for consolidation of equipment. At several locations in the plant replacement parts are no longer manufactured and will become increasingly difficult to obtain. Consultant Manager Manager Inspector Inspector Consultant N/A Bill Lutz Bill Lutz Automated Systems Steve Jones Maria Donisi Rob Apel Jeff Schaber CH2M Hill ICS Electrical Services, Inc. Cincinnati Tunnel Partners Isolation of components and conditioning of air space along with use of modern equipment can improve power distribution and equipment life spans. Infrared windows are included in the upgrades to facilitate the electrical thermography program. The electrical contractor replaced cables for the Secondary Motor Control Centers (MCCs), finished up branch wiring in the Secondary and Influent Pumping, and installed air conditioning in the Return Activated Sludge (RAS) Building. Treatment Plant buildings are in gray, and the project area is outlined in yellow. River Road crosses the northeastern corner of this snapshot, and the Ohio River crosses the southwestern corner. Milestone Activities Date April 16, 2012 May 2014 Legislated February 2009 February 9, 2009 The HVAC contractor provided the louvers and air handling devices for the Influent Pumping Building. The HVAC subcontractor commenced with the installation of equipment and ductwork in the Influent Pumping Building. Handrail was installed beside the rooftop units at the Influent Pumping Building. The gas line for the new rooftop unit was installed and the wiring was pulled to the junction box on the roof. The HVAC subcontractor also completed the installation of the Mitsubishi Electric split air conditioner in the existing RAS control/electrical room. Upcoming work includes bricking up the Secondary Treatment Electrical Room is make it weather tight. There are no issues at this time. 100% Planning February 2009 February 9, % July 2009 March 3, 2011 ROW Acquisition N/A --- March 2012 April 11, 2012 Current Estimated Cost $6,429,278 Bidding February 2012 February 12, 2012 Legislated Amount $9,520,000 April 2012 April 16, 2012 May 2014 Ongoing Actual Cost To-Date $4,203,016 % Estimated Cost 65% This picture shows duct work in the Influent Pumping Building.

10 Wastewater Treatment Plant Odor Control ID City of Cincinnati (Sayler Park) Tony Yee Consultant Jacobs Engineering Group, Inc. This project is part of the Wastewater Treatment Plant (WWTP) Bundle, which consists of projects that will upgrade the facility to be able to treat peak wet weather flows up to 35 million gallons per day (MGD) for extended periods of time. The project includes construction of an odor control system for the sludge processing areas of the WWTP. The purpose of this project is to improve the working conditions at the WWTP sludge processing building through odor source reduction elimination as well as capture, control, and treatment of odors. The sludge processing system lacks adequate ventilation and existing odor control equipment is outdated, ineffective and is creating poor working conditions for operation personnel. Additional ventilation, chemical feed, odor capture, isolation and treatment are proposed to alleviate the condition. Manager Inspector Maria Donisi This project is located at the WWTP, which is located in the sewershed of the West in the City of Cincinnati s Saylor Park neighborhood, Hamilton County. Milestone Dates Float Status PTI Submittal 12/31/ MET 12/31/ days No delay 12/31/ days No delay Activities Legislated 2013 November 6, 2013 () 100% Planning 2012 November 30, % 2013 October 15, 2013 The PTI was submitted in August 2013 and is currently under review by the Ohio EPA. The building permit application was submitted in September The 100% design was submitted in October legislation was approved by the Board of County Commissioners (BOCC) in November All of the bundle projects (Odor Control, Grit Replacement, and New Dewatering) will go out for bid together upon approval of construction legislation by the BOCC for the New Dewatering project. duration is forecasted longer than initially envisioned during development of the final WWIP. MSD and the County will request consideration for an extension of the construction completion milestone from the Regulators to increase the amount of float available such that unforeseen circumstances will not impact meeting the milestone. ROW Acquisition N/A N/A Bidding March August 15, 2013 April 2014 October 2015 Current Estimated Cost $890,500 Legislated Amount $888,600 Actual Cost To-Date $177,298 Budget % 20% The extends from just south of Interstate 74 all the way to the Ohio River, and serves a substantial area west of Cincinnati, including portions of Western Hills and Bridgetown and extending westward along River Road (Rt. 50).

11 Wastewater Treatment Plant Primary Skimmings / Sludge Removal Replacement ID City of Cincinnati (Sayler Park) This project is part of the Wastewater Treatment Plant Bundle, which consists of projects that will upgrade the facility to be able to treat peak wet weather flows up to 35 million gallons per day (MGD) for extended periods of time. Improvements for the Sludge Removal Replacement portion include replacing the chain-and-flight sludge removal and scum skimming equipment in the primary settling tanks. A non-potable water spray header will be installed, as well as actuator motors at the influent sluice gates. New aluminum baffles for settling tanks will also be installed. N/A Tony Yee Consultant Bill Lutz Jacobs Engineering Group, Inc. Manager Manager Steve Jones Maria Donisi Inspector Inspector Rob Apel Mick Pittman Consultant CH2M Hill Building Crafts, Inc. Cincinnati Tunnel Partners Milestone December 31, 2012 October 2015 The Primary Skimmings handling (wet well for scum skimming) portion of this project is in design with the WWTP Bundle ( ). Please refer to the Level 3 Report. A Progress meeting was held on November 14, Commissioning of Tank No. 4 is complete, with the exception of the PLC. Installation of the equipment for Tank No. 3 began during the first week of November. Concrete testing for Tank No. 3 began on November 19, Equipment for Tank No. 2 arrived during the week of November 18, Primary Settling Tank No. 1 is currently operating without all of the collectors; demolition of that tank is scheduled for January Tanks 2 and 3 are fully operational. funds for the primary skimmings handling portion of this project were approved by the Board of County Commissioners on November 6, The Primary Skimmings project is outlined in the area labeled, CIP Activities Legislated CIP 100% Planning May 2011 May 27, % December 2011 December 29, 2011 ROW Acquisition N/A N/A Installation of the PLC is expected to be complete by the end of December Installation of the equipment for Tank No. 3 is scheduled to be complete with start-up beginning December 5, Concrete testing for Tank No. 3 is expected in December Installation of equipment for Tank No. 2 is scheduled for the week of December 16, Tanks 1, 2, and 3 need additional concrete repair. A Progress meeting is scheduled for December 11, Substantial for the sludge removal portion of this project is scheduled for March There are no issues at this time. May 2011 May 31, 2011 Bidding November 2012 September 11, 2012 Current Estimated Cost $3,621,797 December 2012 December 31, 2012 October 2015 Ongoing Legislated Amount $4,197,400 Actual Cost To-Date $1,920,106 Budget % 53% This photo shows concrete repair being done on Primary Settling Tank Number 3.

12 Upper Interceptor Replacement ID , Green Township This project is intended to reduce overflows in the Upper area. The work consists of installing approximately 3,300 feet of 30-inch sewer from CSO 522 (Werk Road and Westbourne Drive) to the intersection of Road and Westbourne Drive, and approximately 9,000 feet of 36 inch sewer from the intersection of Westbourne Drive and Muddy Creek Road to the oxbow in. Consultant Manager Inspector Manager Consultant Inspector N/A Matt Spidare Bill Jeff Lutz Dean Steve HNTB Jones Rob Apel CH2M Hill This project includes dynamic underflow control at CSO 522, CSO 198, and CSO 518 and the elimination of SSO It is located in the upper portion of the. Because it is intended to address non-enumerated SSOs in this portion of the basin, the project qualifies for funding under the Urgent Capacity allowance. A portion of this project is being coordinated with Werk and Westbourne ( ) for the replacement of Sanitary Sewer 41, which will be designed and constructed separately as Contract 1 ( ID ). Milestone Cincinnati Tunnel Partners Interceptor Upgrade Contract November 2015 May 2014 October 2017 October 2014 No Consent Decree milestones apply to this project, which is being performed under the Urgent Capacity allowance. Work in November focused on the consultant updating the plans for the Interceptor Replacement portion from the 90% design review meeting. The revised 90% plans will be submitted to Ohio EPA for the PTI in November Appraisals for 37 easements are expected in December Easement acquisition is expected to take up to two years for the Interceptor Replacement portion of this project. There are no issues at this time. Bundle Phase Activities s Legislated Interceptor Upgrade July 2015 () Schedule Contract February 2014 () 100% Planning May 2012 May % May 2015 January 2014 ROW Acquisition March 2015 January 2014 May 2015 N/A Bidding October 2015 April 2014 November 2015 May 2014 Bundle Number Legislated Funds Actual Costs funds will be requested for legislation in Current Estimated Cost Sanitary Sewer Replacement (Contract 1) $0 $0 $0 Pump Station Elimination $3,495,400 $1,165,887 $19,007,720 Totals $3,495,400 $1,165,887 $19,007,720 The extends from just south of Interstate 74 all the way to the Ohio River, and serves a substantial area west of Cincinnati, including portions of Western Hills and Bridgetown and extending westward along River Road (Rt. 50). October 2017 October 2014

PHASE 1 OF THE CONSENT DECREE/ WET WEATHER IMPROVEMENT PROGRAM ACCOMPLISHMENTS THROUGH 2017

PHASE 1 OF THE CONSENT DECREE/ WET WEATHER IMPROVEMENT PROGRAM ACCOMPLISHMENTS THROUGH 2017 PHASE 1 OF THE CONSENT DECREE/ WET WEATHER IMPROVEMENT PROGRAM ACCOMPLISHMENTS THROUGH 2017 MSD is delivering Phase 1 is under the original cost estimate Improving Trends in Water Quality MSDGC has completed

More information

DELTA WASTEWATER TREATMENT PLANT UPGRADES

DELTA WASTEWATER TREATMENT PLANT UPGRADES Delta, Ohio Environmental and Electrical Engineering, Grant Administration Cost $2.6 million $3.2 million OWDA Loan 1,100 SF Admin Building Addition 0.725 MGD Average Daily Flow 1.5 MGD Peak Capacity Professional

More information

AUTHORITY OF THE BOROUGH OF CHARLEROI WASHINGTON COUNTY, PENNSYLVANIA ACT 537 SEWAGE FACILITIES PLAN UPDATE

AUTHORITY OF THE BOROUGH OF CHARLEROI WASHINGTON COUNTY, PENNSYLVANIA ACT 537 SEWAGE FACILITIES PLAN UPDATE PLAN SUMMARY AUTHORITY OF THE BOROUGH OF CHARLEROI WASHINGTON COUNTY, PENNSYLVANIA ACT 537 SEWAGE FACILITIES PLAN UPDATE The Pennsylvania Sewage Facilities Act (Act 537) was enacted by the Pennsylvania

More information

Ann Arbor Wastewater Treatment Plant Facilities Renovations Project October 2017

Ann Arbor Wastewater Treatment Plant Facilities Renovations Project October 2017 Ann Arbor Wastewater Treatment Plant Facilities Renovations Project October 2017 The Facilities Master Plan was completed in 2004 and identified the need for improvements to the City of Ann Arbor s Wastewater

More information

Remote Headworks Upgrade. November 4, 2010

Remote Headworks Upgrade. November 4, 2010 Remote Headworks Upgrade November 4, 2010 Chelsea Creek Headworks Comb. and Sep. Trib. Areas (brown shading) Flow discharge to North Met Relief Tunnel Peak Cap (350 MGD), Avg. Flow (135 MGD) Columbus Park

More information

Project Name: Central WWTP Capacity Improvements and CSO Reduction Project. MWS Project Number: 14-SC-0153 Last Updated: 12/19/14

Project Name: Central WWTP Capacity Improvements and CSO Reduction Project. MWS Project Number: 14-SC-0153 Last Updated: 12/19/14 Project Name: Central WWTP Capacity Improvements and CSO Reduction Project MWS Project Number: 14-SC-0153 Last Updated: 12/19/14 BACKGROUND / PURPOSE Metro Water Services (MWS), in order to comply with

More information

Metropolitan Sewer District of Greater Cincinnati. Capital Budget and Capital Improvement Program Year 2016

Metropolitan Sewer District of Greater Cincinnati. Capital Budget and Capital Improvement Program Year 2016 Metropolitan Sewer District of Greater Cincinnati Capital Budget Year 2016 Capital Budget Year 2016 Table of Contents Page Glossary of Terms 3 2016 CIP Funding Request (Exhibit A, B & C) 4-11 2016 CIP

More information

Metropolitan Sewer District of Greater Cincinnati. Capital Budget and Capital Improvement Program Year 2014 REVISED

Metropolitan Sewer District of Greater Cincinnati. Capital Budget and Capital Improvement Program Year 2014 REVISED Metropolitan Sewer District of Greater Cincinnati Capital Budget Year 2014 REVISED Capital Budget Year 2014 Table of Contents Page Glossary of Terms 3 2014 CIP //Easement Funding Request 4 2014 CIP Projects

More information

FY 2018 Proposed Capital Improvement Program

FY 2018 Proposed Capital Improvement Program FY 2018 Proposed Capital Improvement Program Metropolitan St. Louis Sewer District FY 2018 Capital Improvement Program Proposed Engineering Services Rich Unverferth, P.E. Director of Engineering January

More information

Tunnel Works. How we got here - Fort Wayne s Consent Decree. Tunnel Works Program Frequently Asked Questions

Tunnel Works. How we got here - Fort Wayne s Consent Decree. Tunnel Works Program Frequently Asked Questions City Utilities operates the largest municipally-owned wastewater collection and treatment system in Indiana. The system serves 161 square miles and includes 1,014 miles of sanitary sewer lines, 365 miles

More information

Storm Water and Sanitary Sewer

Storm Water and Sanitary Sewer Public Works Department Summary Report on Planned Capital Improvements Storm Water and Sanitary Sewer Introduction Public Works has assembled this summary report to highlight major capital improvements

More information

Proposed Wastewater Treatment Facility Equipment Repair and Replacement Project

Proposed Wastewater Treatment Facility Equipment Repair and Replacement Project Proposed Wastewater Treatment Facility Equipment Repair and Replacement Project Presented August 29 th, 2016 Function of IMKWWTP Treatment Facility History Reasons for Proposed Project Why Now? Modest

More information

2016 Summary Report Capital Improvement Projects

2016 Summary Report Capital Improvement Projects 2016 Summary Report Capital Improvement Projects The City Commission adopted the Water and Wastewater 2013-2017 Capital Improvement Program (CIP) on March 12, 2013. The CIP identifies water and wastewater

More information

Figure 2 shows the monthly SSO Volumes within the system from 2007 through 2008 reported in million gallons (MG).

Figure 2 shows the monthly SSO Volumes within the system from 2007 through 2008 reported in million gallons (MG). 28 Annual Report January 27, 29 As required by Section XIX.B., of the pending Consent Decree, the Metropolitan Government of Nashville and Davidson County, Tennessee (Metro) has prepared the enclosed Annual

More information

MSD Integrated Watershed Management Planning Approach to Achieve Sustainable Communities

MSD Integrated Watershed Management Planning Approach to Achieve Sustainable Communities MSD Integrated Watershed Management Planning Approach to Achieve Sustainable Communities MaryLynn Lodor MSD of Greater Cincinnati Sharon Jean-Baptiste CH2M HILL April 4, 2013 Overview MSD s Environmental

More information

Taylor Creek Treatment Plant. Metropolitan Sewer District of Greater Cincinnati

Taylor Creek Treatment Plant. Metropolitan Sewer District of Greater Cincinnati Taylor Creek Treatment Plant Metropolitan Sewer District of Greater Cincinnati Who is this guy and what is he talking about? Brad Blankenship Taylor Creek Operator 3.5 years MSD Operator 5.5 years (total)

More information

Facilities Plan. Technical Memorandum No. TM-WW-7 Hydraulic Analysis and Effluent Pump Station

Facilities Plan. Technical Memorandum No. TM-WW-7 Hydraulic Analysis and Effluent Pump Station City of St. Joseph, Missouri Hydraulic Analysis and Effluent Pump Station By Work Order No. 09-001 B&V Project 163509 May 20, 2010 Table of Contents 1.0 Executive Summary...1 2.0 Purpose of Study...2 3.0

More information

OPERATIONS OVERVIEW TABLE 1-1 ANTICIPATED FLOW RATES. Design Flows (mgd)

OPERATIONS OVERVIEW TABLE 1-1 ANTICIPATED FLOW RATES. Design Flows (mgd) OPERATIONS OVERVIEW PURPOSE OF THE TREATMENT PLANT The Moundsville WWTP has been designed to protect the waters of the Ohio River from direct raw sewage discharges. To accomplish this, the treatment process

More information

First things first.. A Brief Overview of the PTI Program. Why offer training? PTI Survey Results. Today s Main Topics:

First things first.. A Brief Overview of the PTI Program. Why offer training? PTI Survey Results. Today s Main Topics: The Ohio EPA Division of Surface Water Presents: First things first.. Can I have your attention??? What You Need to Know About a Permit to Install (PTI) Application A Brief Overview of the PTI Program

More information

TABLE OF CONTENTS SCHEDULE 18 (TECHNICAL REQUIREMENTS) DBFO AGREEMENT SECTION 2 - WATER AND WASTEWATER SYSTEMS EXECUTION VERSION

TABLE OF CONTENTS SCHEDULE 18 (TECHNICAL REQUIREMENTS) DBFO AGREEMENT SECTION 2 - WATER AND WASTEWATER SYSTEMS EXECUTION VERSION TABLE OF CONTENTS 2. Description of Water and Wastewater Systems... 2 2.1 General... 2 2.2 Existing Facilities Reference and Record Documents... 2 2.3 Existing Infrastructure Location and Legal Description...

More information

Newtown Creek Superfund Citizens Advisory Group Newtown Creek Combined Sewer Overflow Long Term Control Plan

Newtown Creek Superfund Citizens Advisory Group Newtown Creek Combined Sewer Overflow Long Term Control Plan Newtown Creek Superfund Citizens Advisory Group Newtown Creek Combined Sewer Overflow Long Term Control Plan Location: McCarren Park Community Center Date: July 25, 2017 Agenda 1 Topic Welcome; Recap of

More information

CHARLES COUNTY GOVERNMENT ITB NO WAKEFIELD PUMPING STATION UPGRADE

CHARLES COUNTY GOVERNMENT ITB NO WAKEFIELD PUMPING STATION UPGRADE CHARLES COUNTY GOVERNMENT Department of Fiscal and Administrative Services Purchasing Division Telephone: 301-645-0656 February 27, 2014 ITB NO. 14-33 WAKEFIELD PUMPING STATION UPGRADE ADDENDUM NUMBER

More information

Chapter 9: Alternative Analysis

Chapter 9: Alternative Analysis Chapter 9: Alternative Analysis 9.1 Introduction The development and evaluation of alternatives are key elements in the facilities planning process. The purpose of this chapter is to evaluate alternatives

More information

SEWER SYSTEM DESIGN GUIDELINES

SEWER SYSTEM DESIGN GUIDELINES SEWER SYSTEM DESIGN GUIDELINES PART 1 GENERAL 1.1 GENERAL GUIDELINES A. The following sewer system design guidelines are based on Federal, State and Local health requirements, and the Berkeley County Water

More information

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION 820-1 SCOPE OF WORK: SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION a. Furnish all labor, materials, equipment, and incidentals required for demolition and/or removal and disposal of existing

More information

Sidewalk Repair Program. Charter Township of Canton Engineering Services

Sidewalk Repair Program. Charter Township of Canton Engineering Services Sidewalk Repair Program Charter Township of Canton Engineering Services Sidewalk Repair Program History Canton lost a landmark case at the Michigan Supreme Court level in 1997. The Supreme Court has determined

More information

ENVIRONMENTAL ASSESSMENT

ENVIRONMENTAL ASSESSMENT ENVIRONMENTAL ASSESSMENT Project Identification Name: Piqua Wastewater Plant Expansion NRD WPCLF#: CS390755-0009, AIMS #5945 Contact: Gary Huff, City Manager City of Piqua 201 Water Street Piqua, OH 45356

More information

Customer Conference Speedway, IN 46224

Customer Conference Speedway, IN 46224 Customer Conference Speedway, IN 46224 DigIndy and Citizens Capital Investment Plan Updates Mark C. Jacob Vice President Capital Programs & Engineering September 18, 2014 A Matter of Trust Challenges Annually

More information

MSDGC MODELING GUIDELINES AND STANDARDS VOLUME I SYSTEM WIDE MODEL

MSDGC MODELING GUIDELINES AND STANDARDS VOLUME I SYSTEM WIDE MODEL MSDGC MODELING GUIDELINES AND STANDARDS VOLUME I SYSTEM WIDE MODEL REVISION 3 February 2013 Prepared for: METROPOLITAN SEWER DISTRICT OF GREATER CINCINNATI Project & Business Development Division 1600

More information

SOS. City of Akron Combined Sewer Overflow (CSO) Long Term Control Plan. Separate Our Sewers Save Our Streams. Ohio OWEA Collection Systems Workshop

SOS. City of Akron Combined Sewer Overflow (CSO) Long Term Control Plan. Separate Our Sewers Save Our Streams. Ohio OWEA Collection Systems Workshop City of Akron Combined Sewer Overflow (CSO) Long Term Control Plan SOS Separate Our Sewers Save Our Streams Ohio OWEA Collection Systems Workshop Patrick Gsellman Genny Hanna Jim Hall Thursday, May 9,

More information

Special Report MUB WWTP Expansion and Upgrade Evaluation of Alternatives

Special Report MUB WWTP Expansion and Upgrade Evaluation of Alternatives Special Report MUB WWTP Expansion and Upgrade Evaluation of Alternatives Introduction The expansion and upgrade of the MUB Wastewater Treatment Plant (WWTP) is a critical component of MUB s response to

More information

Appendix A EXAMPLE COLLECTION SYSTEM PERFORMANCE INDICATOR DATA COLLECTION FORM

Appendix A EXAMPLE COLLECTION SYSTEM PERFORMANCE INDICATOR DATA COLLECTION FORM Appendix A EXAMPLE COLLECTION SYSTEM PERFORMANCE INDICATOR DATA COLLECTION FORM EXAMPLE COLLECTION SYSTEM PERFORMANCE INDICATOR DATA COLLECTION FORM I. General Information A. Agency Name B. Agency Address

More information

Milwaukee Metropolitan Sewerage District Conveyance and Treatment System. MACRO made available by

Milwaukee Metropolitan Sewerage District Conveyance and Treatment System. MACRO made available by Milwaukee Metropolitan Sewerage District Conveyance and Treatment System MACRO made available by Eric Loucks,, CDM MMSD Collection System Operations MMSD operates an extensive system of sanitary sewers

More information

Wastewater Master Facility Report. (Project Name) (Project Basin Location)

Wastewater Master Facility Report. (Project Name) (Project Basin Location) Wastewater Master Facility Report For (Project Name) (Project Basin Location) The Wastewater Master Facility Report for (Project name) dated (Date); located in the (Basin Name) Basin has been completed

More information

Development in the City of Toronto

Development in the City of Toronto Development in the City of Toronto Water Infrastructure Challenges and Opportunities Graham Harding, P.Eng. Toronto Water, City of Toronto Urban Land Institute Leadership Program February 16, 2017 Toronto

More information

Tampa Bay Water (TBW) is a regional

Tampa Bay Water (TBW) is a regional FWRJ Enhanced Residuals Treatment Helps Tampa Bay Water Regional Surface Water Treatment Plant Achieve Total Recycling Tony Pevec and Richard D. Moore Tampa Bay Water (TBW) is a regional water supply authority

More information

Effect of holding time on E.coli Densities in Wastewater Samples

Effect of holding time on E.coli Densities in Wastewater Samples Effect of holding time on E.coli Densities in Wastewater Samples Nicki Sava-Schafer, Debmalya (Deb) Bhattacharyya, Mark Citriglia Northeast Ohio Regional Sewer District Outline What we (NEORSD) do? Bacteria

More information

I am writing in response to your request for a Revenue Legal Opinion addressing the Sales Tax on the Wastewater Treatment equipment.

I am writing in response to your request for a Revenue Legal Opinion addressing the Sales Tax on the Wastewater Treatment equipment. STATE OF ARKANSAS REVENUE LEGAL COUNSEL Department of Finance Post Office Box 1272, Room 2380 Little Rock, Arkansas 72203-1272 and Administration Phone: (501) 682-7030 Fax: (501) 682-7599 http://dfa.arkansas.gov

More information

Buffalo Sewer Authority. David P. Comerford General Manager

Buffalo Sewer Authority. David P. Comerford General Manager Buffalo Sewer Authority David P. Comerford General Manager Introduction Like it has since its inception in 1938, the Buffalo Sewer Authority has successfully safeguarded the public health and protected

More information

6 Section Six Development of CSO Control Alternatives

6 Section Six Development of CSO Control Alternatives 6 Section Six Development of CSO Control Alternatives 6.1 Introduction It is required that the CSO Long Term Control Plan (LTCP) contains an evaluation of a reasonable range of control alternatives. This

More information

CHAPTER 10 PRELIMINARY TREATMENT

CHAPTER 10 PRELIMINARY TREATMENT CHAPTER 10 PRELIMINARY TREATMENT TM 5-814-3/AFM 88-11, Volume III 10-1. General considerations. Preliminary treatment of wastewater includes screening, grinding, grit removal, flotation, equilization,

More information

Michigan's. Water Quality Event. 92 nd Annual Conference Boyne Mountain Steve Aiken Regional Sales Manager

Michigan's. Water Quality Event. 92 nd Annual Conference Boyne Mountain Steve Aiken Regional Sales Manager Michigan's Water Quality Event 92 nd Annual Conference Boyne Mountain- 2017 Steve Aiken Regional Sales Manager Presentation Represents: 41 Projects $ 96,655,900 Invested All to improve Clean Water for

More information

The following is required for a complete permit submittal for each unit.

The following is required for a complete permit submittal for each unit. P: (847)810-3502 OR (847)810-3503/3521, F: (847)615-4383 MULTI-FAMILY OR COMMERCIAL ADDITION OR ALTERATION PERMIT REQUIREMENTS The following is required for a complete permit submittal for each unit. MULTI-FAMILY

More information

Background Where did CSO systems begin? Combined Sewer Overflow (CSO) Control. Background. Background. Background

Background Where did CSO systems begin? Combined Sewer Overflow (CSO) Control. Background. Background. Background Background Where did CSO systems begin? Combined Overflow (CSO) Control Eric Bergstrom HDR Engineering Background System Development Before About 196 House Background System Development After 196 Building

More information

CEDAR CREEK Wastewater Treatment Facility

CEDAR CREEK Wastewater Treatment Facility CEDAR CREEK Wastewater Treatment Facility Where does the waste originate Private homes Businesses from? Condominium complexes Nursing homes Apartments ANY DWELING THAT USES WATER AND IS CONNECTED TO THE

More information

TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK

TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK COST EVALUATION FOR ROLLING HILLS AREA WATER MAIN EXTENSION PROFESSIONAL CONSULTING, LLC. Octagon 10, Office Center 1719 Route 10, Suite 225 Parsippany,

More information

WEFTEC.06. **Cobb County Water System, Marietta, Georgia

WEFTEC.06. **Cobb County Water System, Marietta, Georgia CHEMICALLY ENHANCED PRIMARY TREATMENT FOR A LARGE WATER RECLAMATION FACILITY ON A CONSTRICTED SITE - CONSIDERATIONS FOR DESIGN, START-UP, AND OPERATION ABSTRACT Jeffrey A. Mills, P.E., BCEE,* Roderick

More information

FY CAPITAL IMPROVEMENT PROGRAM TABLE OF CONTENTS

FY CAPITAL IMPROVEMENT PROGRAM TABLE OF CONTENTS FY 2015-2019 CAPITAL IMPROVEMENT PROGRAM TABLE OF CONTENTS FY 2015-2019 Capital improvement program 1 Historical Perspective 2 Introduction 3 1.0 Water System 4 1.1. Water Supply 5 1.2. Water Facilities

More information

Integrated. SUSTAINABLE Watershed Management MANUAL

Integrated. SUSTAINABLE Watershed Management MANUAL Integrated SUSTAINABLE Watershed Management MANUAL October 2012 Foreword An integrated approach to wet weather management that links natural systems-based solutions with capital planning was chosen by

More information

Minnesota Pollution Control Agency

Minnesota Pollution Control Agency Minnesota Pollution Control Agency STATE OF MINNESOTA Minnesota Pollution Control Agency MUNICIPAL DIVISION PUBLIC NOTICE OF INTENT TO REISSUE NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM (NPDES)/ STATE

More information

PEIRCE ISLAND WASTEWATER TREATMENT FACILITY UPGRADE

PEIRCE ISLAND WASTEWATER TREATMENT FACILITY UPGRADE REQUEST FOR QUALIFICATIONS CITY OF PORTSMOUTH NEW HAMPSHIRE Public Works Department ENGINEERING SERVICES PEIRCE ISLAND WASTEWATER TREATMENT FACILITY UPGRADE VALUE ENGINEERING REVIEW RFQ No. 59-14 City

More information

KANSAS CITY S OVERFLOW CONTROL PROGRAM ANNUAL REPORT Reporting Period: January 1 to December 31, 2015

KANSAS CITY S OVERFLOW CONTROL PROGRAM ANNUAL REPORT Reporting Period: January 1 to December 31, 2015 KANSAS CITY S OVERFLOW CONTROL PROGRAM ANNUAL REPORT Reporting Period: January 1 to December 31, 2015 CONTENTS I. ANNUAL REPORT PURPOSE AND SCOPE... 2 II. KANSAS CITY S OVERFLOW CONTROL PROGRAM... 2 III.

More information

TOWN OF LONDONDERRY, NEW HAMPSHIRE WASTEWATER FACILITIES PLAN UPDATE TABLE OF CONTENTS

TOWN OF LONDONDERRY, NEW HAMPSHIRE WASTEWATER FACILITIES PLAN UPDATE TABLE OF CONTENTS 6%34(6%4(2 )%&+-+4+(3 1-%/ 51 %4( :=>?;9 406/ 0) -0/ 0/ (227! /(6 *%.13*+2(,8A #""$ TOWN OF LONDONDERRY, NEW HAMPSHIRE WASTEWATER FACILITIES PLAN UPDATE TABLE OF CONTENTS SECTION DESCRIPTION PAGE ES

More information

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY IN THE MATTER OF THE DECISION ON THE NEED FOR AN ENVIRONMENTAL IMPACT STATEMENT FOR THE PROPOSED LESTER PRAIRIE WASTEWATER TREATMENT FACILITY EXPANSION

More information

SEPTIC VS. SEWER: A COST COMPARISON FOR COMMUNITIES IN SARASOTA COUNTY, FLORIDA

SEPTIC VS. SEWER: A COST COMPARISON FOR COMMUNITIES IN SARASOTA COUNTY, FLORIDA ABSTRACT SEPTIC VS. SEWER: A COST COMPARISON FOR COMMUNITIES IN SARASOTA COUNTY, FLORIDA Daniel G. Burden, Ph.D., P.E., and Damann L. Anderson, P.E. Hazen and Sawyer, P.C. Patrick Zoeller, P.E. Sarasota

More information

6 WASTEWATER. 6.1 Overview. 6.2 Darvill Wastewater Works

6 WASTEWATER. 6.1 Overview. 6.2 Darvill Wastewater Works 6 WASTEWATER 6.1 Overview Umgeni Water currently owns and operates the Darvill and Ixopo Wastewater Works (WWWs). It also operates the Howick WWW for umgungundlovu District Municipality under a management

More information

Commonwealth of Massachusetts Title 5 Official Inspection Form Subsurface Sewage Disposal System Form - Not for Voluntary Assessments

Commonwealth of Massachusetts Title 5 Official Inspection Form Subsurface Sewage Disposal System Form - Not for Voluntary Assessments Inspection results must be submitted on this form. Inspection forms may not be altered in any way. Important: When filling out forms on the computer, use only the tab key to move your cursor - do not use

More information

Large Decentralized Systems a Sustainable Wastewater Solution

Large Decentralized Systems a Sustainable Wastewater Solution Large Decentralized Systems a Sustainable Wastewater Solution Agenda The Good Fight Centralized Exposed in the Real World Decentralized Model System Examples Dennis F. Hallahan, P.E. Technical Director

More information

BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION : : : : : : : : : : : : : : : DIRECT TESTIMONY MICHAEL J. GUNTRUM, P.E.

BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION : : : : : : : : : : : : : : : DIRECT TESTIMONY MICHAEL J. GUNTRUM, P.E. BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION Application of Pennsylvania-American Water Company for (1) approval of the transfer, by sale, of substantially all of the Borough of New Cumberland s assets,

More information

CHAPTER 9: SANITARY SEWER INTRODUCTION FORECASTS CHAPTER 9: SANITARY SEWER 9-1

CHAPTER 9: SANITARY SEWER INTRODUCTION FORECASTS CHAPTER 9: SANITARY SEWER 9-1 CHAPTER 9: SANITARY SEWER INTRODUCTION The Metropolitan Land Planning Act (amended 1995) requires local governments to prepare comprehensive plans and submit them to the Metropolitan Council to determine

More information

Sanitary Sewer Extensions, Lift Stations, and Force Mains Engineering Report Form. I. General Information. 1. Name of Facility:

Sanitary Sewer Extensions, Lift Stations, and Force Mains Engineering Report Form. I. General Information. 1. Name of Facility: Oklahoma Department of Environmental Quality Water Quality Division Phone: 405-702-8100 Construction Permitting Section 707 N. Robinson, OKC, OK 73102-6010 P.O. Box 1677, OKC, OK 73101-1677 Sanitary Sewer

More information

REQUEST FOR QUALIFICATIONS -ENGINEERING DESIGN SERVICES-

REQUEST FOR QUALIFICATIONS -ENGINEERING DESIGN SERVICES- BUCKSKIN SANITARY DISTRICT Parker, Arizona PUBLIC NOTICE FOR PROFESSIONAL ENGINEERING SERVICES REQUEST FOR QUALIFICATIONS -ENGINEERING DESIGN SERVICES- PHASE 5&6 WASTEWATER TREATMENT PLANT DESIGN Chairman

More information

WATER AND SEWER CAPACITY FEE STUDY

WATER AND SEWER CAPACITY FEE STUDY DRAFT WATER AND SEWER CAPACITY FEE STUDY MCKINLEYVILLE COMMUNITY SERVICES DISTRICT MAY 5, 2011 OVERVIEW McKinleyville Community Services District (the District) retained Willdan to prepare a capacity fee

More information

ENVIRONMENTAL ASSESSMENT For City of Toledo Lucas County Tunnel Optimization Phase 2 WPCLF Loan Number: CS

ENVIRONMENTAL ASSESSMENT For City of Toledo Lucas County Tunnel Optimization Phase 2 WPCLF Loan Number: CS ENVIRONMENTAL ASSESSMENT For City of Toledo Lucas County Tunnel Optimization Phase 2 WPCLF Loan Number: CS390915-0105 Applicant: The Honorable Michael P. Bell, Mayor City of Toledo Ohio Building 420 Madison

More information

Norwalk, CT Water Pollution Control Facility (WPCF) CSO Capacity and Treatment Evaluation. Subject: Task 3 Existing Grit Removal System Assessment

Norwalk, CT Water Pollution Control Facility (WPCF) CSO Capacity and Treatment Evaluation. Subject: Task 3 Existing Grit Removal System Assessment A Technical Memorandum Date: Project: Norwalk, CT Water Pollution Control Facility (WPCF) CSO Capacity and Treatment Evaluation Subject: Task 3 Existing Grit Removal System Assessment This memorandum presents

More information

City of Redlands Wastewater Treatment Plant. Redlands, CA LOCATION: Carollo Engineers; CH2M HILL MBR MANUFACTURER: COMMENTS:

City of Redlands Wastewater Treatment Plant. Redlands, CA LOCATION: Carollo Engineers; CH2M HILL MBR MANUFACTURER: COMMENTS: FACILITY: City of Redlands Wastewater Treatment Plant LOCATION: Redlands, CA GEO. AREA: Southern California STATUS 07/14: Operational CONSTRUCTION: ENGINEERING: Carollo Engineers; CH2M HILL MBR MANUFACTURER:

More information

CITY OF FORT MYERS CENTRAL ADVANCED WASTEWATER TREATMENT FACILITY

CITY OF FORT MYERS CENTRAL ADVANCED WASTEWATER TREATMENT FACILITY CITY OF FORT MYERS CENTRAL ADVANCED WASTEWATER TREATMENT FACILITY RAW SEWAGE Raw sewage is the water that flows into a wastewater treatment facility. It is made up of waste from toilets, sinks, garbage

More information

CAPITAL IMPROVEMENT PROGRAM

CAPITAL IMPROVEMENT PROGRAM CAPITAL IMPROVEMENT PROGRAM This page intentionally left blank TABLE OF CONTENTS CAPITAL IMPROVEMENT PROGRAM... 5 SIGNIFICANT NON-ROUTINE CAPITAL EXPENDITURES... 6 2016 CAPITAL IMPROVEMENT PROGRAM SUMMARY

More information

The Metropolitan District. Stormwater & I/I Reduction Presentation March 16, 2017

The Metropolitan District. Stormwater & I/I Reduction Presentation March 16, 2017 The Metropolitan District Stormwater & I/I Reduction Presentation March 16, 2017 AGENDA Introductions/MDC Background CWP Background Consent Decree/SSO Program Discussion Private Inflow Discussion Program

More information

Conceptual Design for a Future Wastewater Treatment Plant

Conceptual Design for a Future Wastewater Treatment Plant Wastewater Master Plan DWSD Project No. CS-1314 Conceptual Design for a Future Wastewater Treatment Plant Technical Memorandum Original Date: April 1, 2003 Revision Date: September 2003 Author: CDM Table

More information

Streamlining I/I Repairs in Berlin Charter Township

Streamlining I/I Repairs in Berlin Charter Township Case Study: Streamlining I/I Repairs in Berlin Charter Township Presented by: Rich Grant, PE Agenda Discussion of the problems & the SAW I/I Evaluation & SSES = Asset Management Groundtruthing of Results

More information

ASSET MANAGEMENT PROGRAM

ASSET MANAGEMENT PROGRAM ASSET MANAGEMENT PROGRAM July 2017 Orange Water and Sewer Authority Carrboro, North Carolina A public, non-profit agency providing water, sewer and reclaimed water services to the Carrboro-Chapel Hill

More information

Metropolitan St. Louis Sewer District PRIVATE INFILTRATION and INFLOW REDUCTION PROGRAM

Metropolitan St. Louis Sewer District PRIVATE INFILTRATION and INFLOW REDUCTION PROGRAM PRIVATE INFILTRATION and INFLOW REDUCTION PROGRAM October 27, 2012 TABLE OF CONTENTS 1.0 INTRODUCTION... 1 2.0 PROPOSED REMEDIAL ACTION PLAN... 1 3.0 IDENTIFICATION AND CORRECTION OF PRIVATE LATERAL SOURCES...

More information

EVALUATING ALTERNATIVES FOR DISPOSING OF WATER PLANT SOLIDS INTO A WASTEWATER PLANT

EVALUATING ALTERNATIVES FOR DISPOSING OF WATER PLANT SOLIDS INTO A WASTEWATER PLANT EVALUATING ALTERNATIVES FOR DISPOSING OF WATER PLANT SOLIDS INTO A WASTEWATER PLANT Matthew Valade, P.E. July 25, 2014 Barboe.pptx Presentation Outline Project Background Why Dewater Croton Residuals Offsite?

More information

Town of Sewall s Point Septic Tank to Sanitary Sewer. History

Town of Sewall s Point Septic Tank to Sanitary Sewer. History November 15, 2016 History In 2015, Martin County Utilities completed a Septic to Sewer conversion study which illustrated the need to remove septic tanks from the Indian River Lagoon and St. Lucie Estuary.

More information

HISTORY

HISTORY HISTORY Protecting the environment and meeting all requirements of the national and the EU legislation in this area are a major priority and inseparable part of the business strategy of Sofiyska Voda JSC.

More information

SANITARY SEWER OVERFLOWS AND THE TEXAS COMMISSION ON ENVIRONMENTAL

SANITARY SEWER OVERFLOWS AND THE TEXAS COMMISSION ON ENVIRONMENTAL SANITARY SEWER OVERFLOWS AND THE TEXAS COMMISSION ON ENVIRONMENTAL Greg Diehl DFW Region Office Wastewater Work Leader QUALITY OVERVIEW: The TCEQ s SSO Initiative What is it and how does it work? The data

More information

Operations Division Budget

Operations Division Budget Operations Division Budget OPERATIONS DIVISION In MWRA established the Operations Division to integrate wastewater and water system operations and maintenance, treatment, planning, laboratory services,

More information

APPENDIX E: EXISTING FACILITIES DESCRIPTIONS AND DESIGN CRITERIA

APPENDIX E: EXISTING FACILITIES DESCRIPTIONS AND DESIGN CRITERIA Wastewater Treatment Plant Master Plan APPENDIX E: EXISTING FACILITIES DESCRIPTIONS AND DESIGN CRITERIA E THIS PAGE INTENTIONALLY LEFT BLANK. APPENDIX E - EXISTING FACILITIES DESCRIPTION AND DESIGN CRITERIA

More information

INSTALLING A SEPTIC SYSTEM IN LIVINGSTON COUNTY LIVINGSTON COUNTY PUBLIC HEALTH DEPARTMENT 310 TORRANCE AVENUE PONTIAC, IL /

INSTALLING A SEPTIC SYSTEM IN LIVINGSTON COUNTY LIVINGSTON COUNTY PUBLIC HEALTH DEPARTMENT 310 TORRANCE AVENUE PONTIAC, IL / INSTALLING A SEPTIC SYSTEM IN LIVINGSTON COUNTY LIVINGSTON COUNTY PUBLIC HEALTH DEPARTMENT 310 TORRANCE AVENUE PONTIAC, IL 61764 815/844-7174 MALINDA HILLMAN, ADMINISTRATOR DONNIE SIMMONS, L.E.H.P. DIRECTOR

More information

CHAPTER 5 WASTEWATER FLOWS

CHAPTER 5 WASTEWATER FLOWS CHAPTER 5 WASTEWATER FLOWS 5.1 REGIONAL FACILITIES Regional Water Recycling Plants Figure 5-1 illustrates the service area boundaries for IEUA s four water recycling plants. The four Regional facilities

More information

FINAL ASSET MANAGEMENT PROGRAM March 2016

FINAL ASSET MANAGEMENT PROGRAM March 2016 FINAL ASSET MANAGEMENT PROGRAM March 2016 Orange Water and Sewer Authority Carrboro, North Carolina A public, non-profit agency providing water, sewer and reclaimed water services to the Carrboro-Chapel

More information

CERTIFICATION AND FINANCING PROPOSAL

CERTIFICATION AND FINANCING PROPOSAL EXPANSION OF WATER AND WASTEWATER SERVICES TO UNSERVED AREAS OF THE PIEDRA ANGULAR COLONIA TECATE, BAJA CALIFORNIA Published: November 7, 2014 EXPANSION OF WATER AND WASTEWATER SERVICES TO UNSERVED AREAS

More information

Provider: Water District #1 of Johnson County (www.waterone.org) Quasi-municipal agency operating independently of city and county governments

Provider: Water District #1 of Johnson County (www.waterone.org) Quasi-municipal agency operating independently of city and county governments Utilities (2007) Purpose A key factor in determining the development potential an area is the capacity and accessibility utilities to service that area. The City Overland Park is not a full-service city

More information

West County Treatment Plant Noise and Odor Control Project Update. June 29, 2004

West County Treatment Plant Noise and Odor Control Project Update. June 29, 2004 West County Treatment Plant Noise and Odor Control Project Update June 29, 2004 West County Meeting Purpose 1. Brief history of odor and noise control project 2. Describe odor and noise control systems

More information

November 28, Dear Mr. Bechtold:

November 28, Dear Mr. Bechtold: 4000 Hollywood Boulevard Seventh Floor, North Tower Hollywood, Florida 33021 (954) 987-0066 Fax: (954) 987-2949 November 28, 2012 Wastewater Compliance and Enforcement Section FLORIDA DEPARTMENT OF ENVIRONMENTAL

More information

PRESENTED BY: IR. TAI LEE YOON JURUTERA JASA (SARAWAK) SDN BHD

PRESENTED BY: IR. TAI LEE YOON JURUTERA JASA (SARAWAK) SDN BHD PRESENTED BY: IR. TAI LEE YOON JURUTERA JASA (SARAWAK) SDN BHD PRE-PROJECT SITUATION Black water is partially treated by septic tanks. Grey water is directly discharged into the drains and river system

More information

CHAPTER IV EXISTING SEWAGE TREATMENT FACILITIES IN THE PLANNING AREA

CHAPTER IV EXISTING SEWAGE TREATMENT FACILITIES IN THE PLANNING AREA CHAPTER IV EXISTING SEWAGE TREATMENT FACILITIES IN THE PLANNING AREA A. EXISTING FACILITIES 1. Westtown-Chester Creek Plant Westtown Township acquired the Westtown-Chester Creek Treatment Plant (WCC Plant)

More information

Startup and Performance of the World s first Large Scale Primary Dissolved Air Floatation Clarifier ABSTRACT KEYWORDS INTRODUCTION

Startup and Performance of the World s first Large Scale Primary Dissolved Air Floatation Clarifier ABSTRACT KEYWORDS INTRODUCTION Startup and Performance of the World s first Large Scale Primary Dissolved Air Floatation Clarifier Bruce R. Johnson 1 *, Jennifer Phillips 2, Tim Bauer 3, Greg Smith 4, George Smith 5, John Sherlock 6

More information

Prepared for: Stanislaus County th Street Modesto, CA (209)

Prepared for: Stanislaus County th Street Modesto, CA (209) CROWS LANDING INDUSTRIAL BUSINESS PARK SANITARY SEWER INFRASTRUCTURE AND FACILITIES STUDY November 30, 2017 by AECOM Technical Services, Inc. 2020 L Street, Suite 400 Sacramento, CA 95811 (916) 414-5800

More information

Task Order Authorization

Task Order Authorization Task Order Authorization Task Order Number: 6 Task Order Name: 2017 Small Drainage Program Hourly Rate: See attached Exhibit B Budget Not To Exceed: $79,795.00 This Task Order pertains to the On-Call Agreement

More information

Figure 6.3 STORAGE BASIN AREA OF INFLUENCE INTEGRATED WASTEWATER MASTER PLAN CITY OF SAN MATEO. sm0914f ai

Figure 6.3 STORAGE BASIN AREA OF INFLUENCE INTEGRATED WASTEWATER MASTER PLAN CITY OF SAN MATEO. sm0914f ai sm0914f10-8562.ai Figure 6.3 STORAGE BASIN AREA OF INFLUENCE INTEGRATED WASTEWATER MASTER PLAN CITY OF SAN MATEO 6.6 PRELIMINARY MODELING RESULTS FOR THE STORAGE ALTERNATIVES Following the preliminary

More information

Northfield Township WWTP Capacity Evaluation Report

Northfield Township WWTP Capacity Evaluation Report Northfield Township WWTP Capacity Evaluation Report March 18, 2015 PRESENTED TO PRESENTED BY Northfield Township 8350 Main Street Suite A Whitmore Lake, Michigan 48189 Tetra Tech 710 Avis Drive Suite 100

More information

TABLE OF CONTENTS 4.17 UTILITIES AND SERVICE SYSTEMS...

TABLE OF CONTENTS 4.17 UTILITIES AND SERVICE SYSTEMS... TABLE OF CONTENTS 4.17 UTILITIES AND SERVICE SYSTEMS... 4.17-1 4.17.0 Introduction... 4.17-1 4.17.1 Methodology... 4.17-2 4.17.2 Existing Conditions... 4.17-2 4.17.3 Impacts... 4.17-4 4.17.4 Applicant-Proposed

More information

TODAY S COUPON: 425 MGD PUMP STATION AT 30% OFF

TODAY S COUPON: 425 MGD PUMP STATION AT 30% OFF ABSTRACT TODAY S COUPON: 425 MGD PUMP STATION AT 30% OFF Erin Flanagan, P.E. Freese and Nichols, Inc. 1701 North Market Street Suite 500, LB 51 Dallas, Texas 75202 Bryan Jann, P.E. Freese and Nichols,

More information

Chapter 8 Addressing I/I Issues and High Flows

Chapter 8 Addressing I/I Issues and High Flows Chapter Outline Chapter 8 Addressing I/I Issues and High Flows This chapter is organized into the following sections: Introduction Background Estimation of Infiltration Volume Conveyance Costs Effect of

More information

E1/92. D.C. Water & Sewer Authority Series 2017 A Senior Lien Revenue Bonds. Green Evaluation. Transaction Overview. Green Evaluation Overview

E1/92. D.C. Water & Sewer Authority Series 2017 A Senior Lien Revenue Bonds. Green Evaluation. Transaction Overview. Green Evaluation Overview Green Evaluation D.C. Water & Sewer Authority Series 2017 A Senior Lien Revenue Bonds Transaction Overview In January 2017, the District of Columbia Water & Sewer Authority issued $100 million in series

More information

Mill Creek/Peaks Branch/State- Thomas Drainage Relief Tunnel

Mill Creek/Peaks Branch/State- Thomas Drainage Relief Tunnel Mill Creek/Peaks Branch/State- Thomas Drainage Relief Tunnel Mobility Solutions, Infrastructure & Sustainability Committee January 22, 2018 Sarah Standifer, Director Trinity Watershed Management Overview

More information

COLLECTION SYSTEM O&M AND ASSET MANAGEMENT AT LACSD. Anthony Howard, PE Supervising Engineer Water Reclamation Plants Section

COLLECTION SYSTEM O&M AND ASSET MANAGEMENT AT LACSD. Anthony Howard, PE Supervising Engineer Water Reclamation Plants Section COLLECTION SYSTEM O&M AND ASSET MANAGEMENT AT LACSD Anthony Howard, PE Supervising Engineer Water Reclamation Plants Section April 20, 2015 Sanitation Districts of Los Angeles County Wastewater Collection

More information