CHAPTER 8 COST ESTIMATION

Size: px
Start display at page:

Download "CHAPTER 8 COST ESTIMATION"

Transcription

1 CHAPTER 8 COST ESTIMATION 8.1 Cost Estimation for Rough Planning Stage When you are going to make a trial calculation of construction cost in Rough Planning Stage, it can be calculated by the method shown in Table However, before calculating, it is necessary to carry out an easy field survey, and decide the item mentioned to Table Table8.1.1 Items to make a trial calculation of construction cost Description Item Plan Maximum Out Put (kw) Turbine Discharge (m 3 /s) Effective Head (m) Intake Facilities Height of Dam (m) Length of Dam (m) Headrace Length of Headrace (m) Penstock Diameter of Penstock (m) Distribution Number of Households (kk) Distance to the furthest house from P.S In addition, since indirect costs, such as tax, contractor fee, design cost, and supervisor fee, are contained in the cost of construction calculated by Fig 8.1.2, when a part of these indirect costs can be omitted, examination is required separately

2 Table8.1.2 Method to make a trial calculation of construction cost in Rough Planning Stage No. Description Formulation Remarks (1) PREPARATORY WORKS {(2)+(3)+(4)+(5)} 0.1 Transportation, Clearing, Temporally Works (2) CIVIL WORKS 1~7 1 Intake Facilities Gabion Dam 210,000 (H L) H : Height of Dam(m) L : Length of Dam(m) 2 Settling Basin Stone Masonry Dam 785,000 (H L)+850,000 Concrete Dam 1,650,000 (H L) Long or Mid-Penstock type 60,300,000 Q H : Height of Dam(m) L : Length of Dam(m) H : Height of Dam(m) L : Length of Dam(m) (Rp) Q : Turbine Discharge(m 3 /s) (Back to System Layout : Page4-2) Short Penstock type 54,200,000 Q Q : Turbine Discharge(m 3 /s) (Back to System Layout : Page4-1) 3 Headrace 435,000 Q 0.18 L Q : Turbine Discharge(m 3 /s) L : Length of Headrace(m) 4 Head Tank 47,600,000 Q 0.5 Q : Turbine Discharge(m 3 /s) 5 Penstock Civil Works 775,000 φ L φ : Daiameter of Penstock (m) L : Length of Penstock (m) Pestock L : Length of Penstock (m) 15,000 (Unit waight) L 6 Power House Base 4,890,000 P P : Maximum Output(kW) (Include Tail race) 7 Power House Building 2,460,000 P+20,350,000 P : Maximum Output(kW) (3) ELECTROMECHANICAL WORKS 75,710,000 (P/ He) 0.56 Closs flow Turbine T-13 P : Maximum Output(kW) He : Effective Head(m) (4) DISTRIBUTION WORKS 14,300 X X : Number of Household Distance 2 (5) CONSUMER CONNECTION 428,000X+31,900,000 X : Number of Household (6) OTHERS {(2)+(3)+(4)+(5)} 0.05 TOTAL (1)+(2)+(3)+(4)+(5)+(6)

3 100,000,000 90,000,000 Concrete Dam 80,000,000 Cost (Rp) 70,000,000 60,000,000 50,000,000 40,000,000 Cost(Rp) = 1,650,000*(H L) Stone Masonry Cost(Rp) = 785,000*(H L) + 850,000 30,000,000 20,000,000 10,000,000 y = 210,000*(H L) Gabion Dam H L Fig8.1.1 Cost of Intake facilities Notes: For a trial calculation of construction cost in Rough Planning Stage

4 80,000,000 70,000,000 60,000,000 50,000,000 Long or Mid-length Penstock type Cost(Rp) =60,300,000*Q Cost (Rp) 40,000,000 30,000,000 20,000,000 Short Penstock type Cost(Rp) = 54,200,000*Q ,000, Q (m 3 /s) Fig8.1.2 Cost of Settling Basin Notes: For a trial calculation of construction cost in Rough Planning Stage

5 500,000 Unit Cost(Rp/m) = 435,000*Q , ,000 Unit Cost (Rp/m) 350, , , , Q (m 3 /s) Fig8.1.3 Unit Cost of Headrace Notes: For a trial calculation of construction cost in Rough Planning Stage

6 70,000,000 Cost(Rp) = 47,600,000*Q ,000,000 50,000,000 40,000,000 Cost (Rp) 30,000,000 20,000,000 10,000, Q (m 3 /s) Fig8.1.4 Cost of Head tank Notes: For a trial calculation of construction cost in Rough Planning Stage

7 1,200,000 Cost(Rp) = 775,000φ ,000, ,000 Cost (Rp) 600, , , Daiameter of Penstock φ(m) Fig8.1.5 Cost of Penstock (Civil Works) Notes: For a trial calculation of construction cost in Rough Planning Stage

8 t=3mm y = φ t=4mm y = φ t=5mm y = φ t=5mm 70 Unit vilume waigth (kg/m) t=3mm t=4mm Daiameter of Penstock φ(mm) Fig8.1.6 Unit volume waight of Penstock Notes: For a trial calculation of construction cost in Rough Planning Stage

9 40,000,000 Cost(Rp) = 4,890,000*P ,000,000 30,000,000 25,000,000 Cost (Rp) 20,000,000 15,000,000 10,000,000 5,000, P (kw) Fig8.1.7 Cost of Power house Base (Inc. Tail race) Notes: For a trial calculation of construction cost in Rough Planning Stage

10 250,000,000 Cost(Rp) = 2,460,000P + 20,350, ,000, ,000,000 Cost (Rp) 100,000,000 50,000, P (kw) Fig8.1.8 Cost of Power house builiding Notes: For a trial calculation of construction cost in Rough Planning Stage

11 400,000,000 Cost(Rp) = 75,710,000 (P/ He) ,000, ,000, ,000,000 Cost (Rp) 200,000, ,000, ,000,000 50,000, P/ He Fig8.1.9 Cost of Electromechanical Works Notes: For a trial calculation of construction cost in Rough Planning Stage

12 800,000,000 Cost(Rp) = 14300x ,000, ,000, ,000,000 Cost (Rp) 400,000, ,000, ,000, ,000, ,000, ,000, ,000, ,000, ,000,000 x = (Number of Household) * (Distance) ^ 2 Fig Cost of Distribution Works Notes: For a trial calculation of construction cost in Rough Planning Stage

13 350,000,000 Cost (Rp) = x ,000, ,000, ,000,000 Cost (Rp) 150,000, ,000,000 50,000, Number of Household Fig Cost of Consumer Connection Notes: For a trial calculation of construction cost in Rough Planning Stage

14 8.2 Cost Estimation for Detail Design Stage Construction cost consists of items as shown in Table Table8.2.1 Construction Cost No. Item Cost Direct cost of construction 1 PREPARATORY WORKS Addition item 2 CIVIL WORKS Addition item 3 ELECTRO-MECHANICAL WORKS Addition item 4 DISTRIBUTION WORKS Addition item 5 CONSUMER CONNECTION Addition item SUB TOTAL(A) Indirect cost 1 DESIGN FEE 5~10% of SUB TOTAL(A) 2 SUPERVISOR FEE 5~10% of SUB TOTAL(A) 3 MANAGEMENT FEE 5~10% of SUB TOTAL(A) 4 TAX 12.5% of SUB TOTAL(A) SUB TOTAL(B) TOTAL Items Typical items of a direct cost are shown below. (1) Preparatory works Preparatory works consist of item as follows. - Location setting out - Felling and measurement - Equipment & materials mobilization (2) Civil works Civil works consist of item as follows. - Intake facilities - Settling basin - Headrace - Head tank

15 - Spillway - Penstock and foundation - Powerhouse base - Tailrace - Power house building - Finishing (3) Electro-mechanical works Electro-mechanical works consist of item as follows. - Turbine - Controller - Dummy load - Generator - Accessories, spare parts and tools - Set up and installation - Transportation and packing - Testing - Pre commissioning trial run (4) Distribution works Distribution works consist of item as follows. - Transmission pole - Cable - Transformer - Accessories (5) Consumer connection - Cable - Switch - Accessories

16 8.2.2 Quantity In order to calculate direct cost of construction, it is necessary to calculate the quantity for every work or material based on design. For example, in case of headrace of masonry, quantity will be calculated for excavation, foundation rubble stone, stone masonry, backfill, and plaster like Fig Excavation Foundation rubble stone Plaster Backfill Stone masonry Fig The example of works which should be calculated(headrace) With a natural thing, these items change according to a kind and the quality of structure. For example, in Intake, the item that should calculate will be changed according to type of dam like Table And in Headrace, the item which should calculate will be changed according to the quality of the material of Headrace like Table Table Quantity of dam Gabion dam Masonry dam Concrete dam - Excavation (m 3 ) - Excavation (m 3 ) - Excavation (m 3 ) - Backfill (m 3 ) - Backfill (m 3 ) - Backfill (m 3 ) - Gabion (m 3 ) - Foundation Rubble - Sand filling (m 3 ) Stone (m 3 ) - Concrete (m 3 ) - Stone masonry (m 3 ) - Plaster (m 2 ) - Plaster (m 2 ) - Stoplog (m 2 ) - Stoplog (m 2 ) - Gabion (m 3 ) - Gabion (m 3 )

17 Table8.2.3 Quantity of headrace Simple earth channel Masonry channel Concrete channel - Excavation (m 3 ) - Excavation (m 3 ) - Excavation (m 3 ) - Backfill (m 3 ) - Backfill (m 3 ) - Foundation Rubble - Sand filling (m 3 ) Stone (m 3 ) - Concrete (m 3 ) - Stone masonry (m 3 ) - Plaster (m 2 ) - Plaster (m 2 ) This is the same for other structures too, and care is taken not to omit ay items that should be added up based on drawings.(ref 8.1 Breakdown of Construction Cost of Pilot Project) Unit Cost Table shows standard unit cost of civil work of PU. Unit Price of Table is price of Tana-Toraja. Since unit cost changes according to various situations of each area, it is desirable to perform unit cost setup enough in consideration of the local characteristics

18 Table8.2.4 Unit cost of PU (Toraja) Koef. Unit Unit Price Unit Cost Remark (Rp) (Rp) Excavation(m 3 ) 22,500 unskill labour man 15,000 9,375 foreman man 17,500 1,085 tools ls 12,000 12,000 Total 22,460 Backfill (m 3 ) 15,200 unskill labour man 15,000 2,880 foreman man 17, tools ls 12,000 12,000 Total 15,213 Sand Filling (m 3 ) 50,400 sand m 3 40,000 48,000 unskill labour man 15,000 2,250 foreman man 17, Total 50,425 Fondation Rubble Stone (m 3 ) 108,000 stone m 3 50,000 60,000 sand m 3 40,000 16,000 unskill labour man 15,000 16,875 skill labour man 25,000 14,075 foreman man 17, Total 107,930 Stone Masonry 1:2 (m 3 ) 234,000 stone m 3 50,000 60,000 PC zak 26,500 93,280 sand m 3 40,000 15,200 unskill labour man 15,000 33,750 skill labour man 25,000 28,125 chief labor man 30,000 3,390 foreman man 17, Total 234,043 Stone Masonry 1:3 (m 3 ) 217,000 stone m 3 50,000 60,000 PC zak 26,500 75,260 sand m 3 40,000 16,000 unskill labour man 15,000 33,750 skill labour man 25,000 28,125 chief labor man 30,000 3,390 foreman man 17, Total 216,823 Stone Masonry 1:4 (m 3 ) 209,000 stone m 3 50,000 60,000 PC zak 26,500 66,250 sand m 3 40,000 16,800 unskill labour man 15,000 33,750 skill labour man 25,000 28,125 chief labor man 30,000 3,390 foreman man 17, Total 208,

19 Koef. Unit Unit Price Unit Cost Remark (Rp) (Rp) Surface Finish (m 2 ) 19,100 PC zak 26,500 6,281 sand m 3 40, meduam skill labour man 20,000 5,720 skill labour man 25,000 5,350 chief labor man 30, foreman man 17, Total 19,091 Gabion (m 3 ) 96,600 stone m 3 50,000 60,000 wire cage kg 7,000 24,500 unskill labour man 15,000 6,750 skill labour man 25,000 5,000 foreman man 17, Total 96,600 Stoplogs (unit) 281,000 wood m 3 4,150, ,200 carpenter man 25,000 25,000 labour man 15,000 30,000 foreman man 17,500 1,750 tools ls 25,000 25,000 Total 280,950 Working floor (m 2 ) 261,000 PC zak 26, ,834 sand for concrete m 3 50,000 27,500 split/gravel m 3 75,000 69,750 tools ls 15,000 15,000 labour man 15,000 30,000 skill labour man 25,000 12,500 chief labor man 30,000 1,500 foreman man 17, Total 261,259 Rainforce Concrete K225(m 3 ) 2,211,000 PC zak 26, ,244 split/gravel m 3 75,000 60,750 sand for concrete m 3 50,000 24,500 labour man 15,000 45,000 skill labour man 25,000 12,500 chief labor man 30,000 1,500 foreman man 17,500 1,925 con.+form tools ls 75,000 75,000 steel bar concrete kg 7,000 1,225,000 wire kg 9,000 18,000 labour for steel concrete man 25, ,750 chief for steel concrete man 30,000 67,500 unskill labour man 15, ,250 con.+form nail kg 7,500 30,000 carpenter man 25, ,000 chief of carpenter man 30,000 15,000 Total 2,210,

20 [Ref. 8-1 Cross-sectional method to calculate quantity] It is convenient to use the cross-sectional method when calculating complicated quantities such a headrace. When you want to calculate the quantity of excavation of headrace as shown in the following figure, first, you draw a sectional view for every changing point of cross-sectional form, and the excavation area for every section is calculated using planimeter, etc

21 Next, you can make the next table from the relation between the area of each section, and distance. Section name Excavation Area Average Area Distance Volume A - A B - B C - C D - D E - E 1.31 m m m m m m m m m m 3.00m 3.00m 2.00m 2.690m m m m 3 Total 12.73m 3 This cross-sectional method is applicable not only to excavation area but also to calculation quantities of backfill or masonry

22 [Ref. 8-2 The example of bill of quantity] No Description Unit Quantity Unit Price Amount Total Price Rp Rp Rp I PREPARATORY WORKS II CIVIL WORKS 1 Intake Facilities include setling basin a. Excavation m 3 b. Backfill m 3 c. Foundation rubble stone m 3 d. Stone Masonry 1 : 2 m 3 e. Plaster m 2 f. Gabions m 3 g. Stoplogs (80 w x 100 h ) cm 2 unit h. Flushing Gate (60 w x 210 h ) cm 2 unit i. Screen m 2 sub total 2Headrace a. Excavation m 3 b. Backfill m 3 c. Foundation rubble stone m 3 d. Stone Masonry 1 : 4 m 3 e. Plaster m 2 f. Stoplogs (80w x 100h) cm2 unit sub total 3 Head Tank a. Excavation m 3 b. Backfill m 3 c. Foundation rubble stone m 3 d. Stone Masonry 1 : 3 m 3 e. Plaster m 2 f. Gate (60 w x 200 h ) cm 2 unit g. Screen m 2 sub total 4 Spillway Channel a. Excavation m 3 b. Backfill m 3 c. Foundation rubble stone m 3 d. Stone Masonry 1 : 4 m 3 e. Plaster m 2 sub total 5 Penstock and Foundation a. Excavation m 3 b. Reinforced Concrete m 3 c. Working floor m 3 d. Sand filling m 3 e. Plaster m 2 f. Penstock set work m 1 g. Welded steel m 1 h. Butterfly valve unit I. Reducer pipe unit j. Clamp penstock pcs k. Bend degree angle pcs l. Anchor bolt pcs sub total

23 No Description Unit Quantity Unit Price Amount Total Price Rp Rp Rp 6 Power House Base + Tail Race a. Excavation m 3 b. Backfill m 3 c. Sand filling m 3 d. Working floor m 3 e. Reinforce Concrete m 3 f. Foundation rubble stone m 3 g. Stone Masonry 1 : 4 m 3 h. Surface finish m 2 sub total 7 Power House a. Building m 2 sub total 8 Finishing a. Penstock painting m 1 b. Building Painting ls c. Service Walkway m 1 sub total III MECHANICAL & ELECTRICAL 1 Crossflow Turbine a. Turbine T13 bo. 600 mm unit b. Turbine base frame unit c. Pulley of turbine unit e. Flexible Coupling unit f. Plummer Block Bearing Set unit g. Flat belt unit h. Fence Guard unit I. adapter pipe unit j. Dynamic Balancing ls k. Heat treatment ls l. Pressure gauge unit 2 Electronic Load Controller unit 3 Ballast Load a. Air Heater (54 kva) unit b. Housing Ballast unit 4 Generator a. Syncronous Generator Stamford unit b. Generator base frame unit c. Pulley of generator unit 5 Accessories, Spare parts & Tools unit 6 Set up & Installation ls 7 Transportation & Packaging ls 8 Testing (welding) ls 9 Pre commissioning Trial Run ls sub total sub total sub total sub total sub total sub total sub total sub total sub total

24 No Description Unit Quantity Unit Price Amount Total Price Rp Rp Rp IV DISTRIBUTION WORKS a. Transmission pole pcs b. Twisted Cable 4 * 70 mm 2 m 1 c. Twisted Cable 4 * 35 mm 2 m 1 d. Twisted Cable 2 * 16 mm 2 m 1 e. Accessories ls f. Installation expense ls V CONSUMER CONNECTION a. NYM Cable 2 * 1.5 mm 2 m 1 b. NYM Cable 3 * 1.5 mm 2 m 1 c. Electric Socket pcs d. Series Switch pcs e. Single Switch pcs f. Connector pcs g. Service Wedge Clamp pcs h. Cable Clam pack i. Plafond Fitting pcs j. Hanger Fitting pcs k. Rosset Wood pcs l. Cellophane Tape pcs m. Screw pack n. T - dus pcs o. MCB and housing unit p. Twisted Cable 2 * 10 mm 2 m 1 q. Grounding unit r. Installation Expense unit s MCCB Group unit TOTAL Rp

2 FINDING OF THE POTENTIAL SITES

2 FINDING OF THE POTENTIAL SITES EXECUTIVE SUMMARY 1 Background S-1 2 User of Manual S-1 3 Applicable Range of Micro-hydro power in the Indonesia S-2 4 How to use this Manual S-2 Chapter 1 INTRODUCTION 1-1 1.1 Purpose of the Manual

More information

Table of Contents. A Operate and monitor Micro Hydel Power Plant (MHP) plant 04

Table of Contents. A Operate and monitor Micro Hydel Power Plant (MHP) plant 04 Page 2 Table of Contents Competency Standards A Operate and monitor Micro Hydel Power Plant (MHP) plant 04 B Carry out corrective maintenance procedures on electrical components in a MHP plant 05 C Carry

More information

A 1 1 Approved Contract:

A 1 1 Approved Contract: 200x200 safety mesh cover 350 4x1 rainage pipe 355 Spillway wall 2 6 Section - 0 ccess platform Trash rack (2.4 x 1.8 m ) ccess platform Spillway wall Penstock pipe N 1800 20 64 Reinforced concrete 1 3

More information

Description Unit Quantity Rate Kshs. Amount Kshs.

Description Unit Quantity Rate Kshs. Amount Kshs. BILL No.1 40m3 MASONRY STORAGE TANK No. Description Unit Quantity Rate Kshs. Amount Kshs. 1 SETTING OUT AND EARTH WORKS 1.1 General site clearance and setting out 1.2 Excavate over site 200mm to remove

More information

PND Training Hall Conex Building, Kabul ABSTRACT OF COST

PND Training Hall Conex Building, Kabul ABSTRACT OF COST PND Training Hall Conex Building, Kabul ABSTRACT OF COST A Civil Works All work items shall be carried as per drawing, specification and instruction of the Engineer. 1 Sub-structure Works Earthwork in

More information

Then the revolving speed of turbine is obtained as 300 r/min based on the specific speed of Ns 208 m-kw.

Then the revolving speed of turbine is obtained as 300 r/min based on the specific speed of Ns 208 m-kw. 11.4 Electromechanical Equipment Generally, a turbine-generator is said larger unit capacity has more economical merit of scale. However, the optimum unit size of turbine-generator is determined in consideration

More information

Installation, Operation and Maintenance Manual

Installation, Operation and Maintenance Manual Installation, Operation and Maintenance Manual for Multipurpose Power Unit (MPPU) at Munar Prepered for TIFAC-DST Sponsored Project Development of Standard Water Mills in Uttaranchal Submitted to TIFAC

More information

UNOPS UNITED NATIONS OFFICE FOR PROJECT SERVICES PROJECT BOQ. Original Issue Bamyan MAC Site Services - Phase 1 Bamyan, Bamyan, Afghanistan

UNOPS UNITED NATIONS OFFICE FOR PROJECT SERVICES PROJECT BOQ. Original Issue Bamyan MAC Site Services - Phase 1 Bamyan, Bamyan, Afghanistan UNOPS UNITED NATIONS OFFICE FOR PROJECT SERVICES PROJECT BOQ Original Issue Bamyan MAC Site Services Phase Bamyan, Bamyan, Afghanistan Project Components:. Site Services Phase NOTICE TO ALL BIDDERS COMPLETE

More information

RÍO AMOYÁ - LA ESPERANZA Hydroelectric Power Plant

RÍO AMOYÁ - LA ESPERANZA Hydroelectric Power Plant RÍO AMOYÁ - LA ESPERANZA Hydroelectric Power Plant The power plant is located in southern Tolima, in the municipality of Chaparral, approximately 150 km from Ibague. It has an installed capacity of 80

More information

SUM i) Carry out calibration of 100,000 litres day tank. ii) Pipes, valves and other fittings connection to fuel offloading SUM

SUM i) Carry out calibration of 100,000 litres day tank. ii) Pipes, valves and other fittings connection to fuel offloading SUM 31 st July 2017 TENDER FOR RELOCATION OF ONE GE FRAME 6 GAS TURBINE FROM EMBAKASI IN NAIROBI TO MUHORONI NEAR KISUMU: KGN-GT-012-2017 KenGen wishes to make the following clarification and changes through

More information

Construction works for Establishment of School in Al-Najaf M 2 2,600 M 2 750

Construction works for Establishment of School in Al-Najaf M 2 2,600 M 2 750 1 Preparation of a 18-Classroom School BoQ for constructing a 18-Classroom School - Najaf Site Preparation:Works for leveling the site and remove the garbage to authorized location according to supervisor

More information

Table-K.13 (2/2) Unit Price of Cost Estimate

Table-K.13 (2/2) Unit Price of Cost Estimate Unit Price of Construction Materials Item Table-K.13 (2/2) Unit Price of Cost Estimate Unit Unit Rate (Rp.) Unit Price of Construction Labors Item Unit Price (Rp./day.) Overtime (Rp./hr) Gravel for Draining

More information

Appendix 4. Bills of Quantities

Appendix 4. Bills of Quantities Appendix 4. Bills of Quantities 201 A4.1 Deep trench latrines Partitions of local materials 1m apart Timber foot rests and floor plates Lightweight timber frame Excavated soil (used for back-fill) Plastic

More information

Unit Rate. Subtotal in SDG. Site Clearing Preliminary Works. 1.0 Job. Excavation & Earth Works. Stone Masonry Works in foundation 100 M.

Unit Rate. Subtotal in SDG. Site Clearing Preliminary Works. 1.0 Job. Excavation & Earth Works. Stone Masonry Works in foundation 100 M. Bill of Quantities Nature of work : Construction of Health Center with 8 rooms (Clinics, Pharmacy, Labs, Fence & Latrines) Location: Shakreen- El Fasher Town- North Darfur State No. Description Qty Unit

More information

Construction works for Establishment of School in Al-Latifiyah. Al-Latifiyah BoQ for constructing a 6-pre-fab Classroom School

Construction works for Establishment of School in Al-Latifiyah. Al-Latifiyah BoQ for constructing a 6-pre-fab Classroom School 1 Al-Latifiyah BoQ for constructing a 6-pre-fab Classroom School Preparation of a 6-Classroom School Site Preparation:Works for leveling the site and remove the garbage to authorized location according

More information

Contract Identification No. and Package 1. SUHEP-067/68-Lot No.1-AR: Package B 2. SUHEP-067/68-Lot No.1-AR: Package C

Contract Identification No. and Package 1. SUHEP-067/68-Lot No.1-AR: Package B 2. SUHEP-067/68-Lot No.1-AR: Package C Notice of Amendment No.1 Addendum No.1 to the following Contract Packages has been made in the Bids, for which the first date notice was published in the Gorkhapatra daily on December 14, 2010 by Sanjen

More information

Calculation of requirement of Labour. for construction of IAY/CMRHM

Calculation of requirement of Labour. for construction of IAY/CMRHM Calculation of requirement of Labour for construction of IAY/CMRHM Total cost as per 2012 SOR = Rs 7,01,746.00 Deduct 7.5% Contractor s profit = Rs (-) 52,631.00 = Rs 6,49,115.00 Taking 1/3 as the Labour

More information

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building...

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building... Contents 11. Construction processes and materials... 11-2 11.1 Power House... 11-2 11.2 Maintenance Building... 11-2 11.3 Fuel Treatment Building... 11-3 11.4 Roads & Paths... 11-3 11.5 Fencing... 11-3

More information

Types of Hydropower Facilities

Types of Hydropower Facilities Types of Hydropower Facilities 1 Impoundment Hydropower- uses a dam to store water. Water may be released either to meet changing electricity needs or to maintain a constant water level. 2 Run-of-River

More information

SINAR AHS BILL OF QUANTITIES Cost code Description Unit Qty 1 SINAR AHS Contractors General Conditions Site Works Setting out works: Rates

SINAR AHS BILL OF QUANTITIES Cost code Description Unit Qty 1 SINAR AHS Contractors General Conditions Site Works Setting out works: Rates SINAR AHS BILL OF QUANTITIES Cost code Description Unit Qty 1 SINAR AHS 01000 Contractors General Conditions 02000 Site Works Setting out works: Rates shall include but not limited to all necessary equipments,

More information

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited www.smi.com.np smi.investment.limited@gmail.com Date : August,

More information

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited www.smi.com.np smi.investment.limited@gmail.com Date : January,

More information

EXTERNAL WORKS EXCAVATION,BACKFILLING & SITE WORKS

EXTERNAL WORKS EXCAVATION,BACKFILLING & SITE WORKS BILLS OF QUANTITIES - Name of Project CONSULTANT: Name of Office DATE:APR. 2008 External Works EXTERNAL WORKS EXCAVATION,BACKFILLING & SITE WORKS page 1 BILLS OF QUANTITIES - Name of Project CONSULTANT:

More information

SPECIAL REPAIRS TO EXTERNAL SANITARY ARRANGMENTS AND STREET LIGHTS IN ESI DISPENSARY I & II CAMPUS AT PERAMBUR

SPECIAL REPAIRS TO EXTERNAL SANITARY ARRANGMENTS AND STREET LIGHTS IN ESI DISPENSARY I & II CAMPUS AT PERAMBUR SPECIAL REPAIRS TO EXTERNAL SANITARY ARRANGMENTS AND STREET LIGHTS IN ESI DISPENSARY I & II CAMPUS AT PERAMBUR FINANCIAL BID Item DSR Item Description Qty Units No No. Total 1.1.1 Excavating trenches of

More information

PRE FEASIBILITY REPORT NUKULOA MICRO HYDRO POWER PROJECT

PRE FEASIBILITY REPORT NUKULOA MICRO HYDRO POWER PROJECT Ministry of Infrastructure and Transport PRE FEASIBILITY REPORT NUKULOA MICRO HYDRO POWER PROJECT Prepared by : Department of Energy August, 2013 [DOE] 1 Table of Contents Summary... 3 1. Geographical

More information

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited www.smi.com.np smi.investment.limited@gmail.com Date : August,

More information

MIEL I Hydroelectric Power Plant

MIEL I Hydroelectric Power Plant MIEL I Hydroelectric Power Plant The Miel I Power Plant, which is located in the municipality of Norcasia, forms part of the hydro potential in western Caldas. This region comprises the basins of the rivers

More information

FEASIBILITY STUDY GUIDELINES

FEASIBILITY STUDY GUIDELINES FEASIBILITY STUDY GUIDELINES Pakhtunkhwa Energy Development Organization (PEDO) Energy and Power Department, KP Prepared by Pakhtunkhwa Energy Development Organization Feasibility Study Guidelines Volume

More information

K A H A Y A S u l a w e s i S e l a t a n

K A H A Y A S u l a w e s i S e l a t a n I N V E N T O R Y S T U D Y O N D E V E L O P M E N T P O T E N T I A L F O R R U R A L E L E C T R I F I C A T I O N I N I N D O N E S I A K A H A Y A S u l a w e s i S e l a t a n Bandung, October 4,

More information

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES RFP/GRC/LSV/2017-003: RENOVATION (CIVIL WORKS) AT SKALA SYKAMNIAS CHILDRENS PLAYGROUND BILL OF QUANTITIES 1/7 The Contractor shall consider in his price all costs or expenses of all requirements stipulated

More information

Installation Instructions of Perlite Protect Board

Installation Instructions of Perlite Protect Board I. Select of Light Stud and Components 1. Light gauge steel partition frame usually contains Ceiling U-track, Floor U-track, Cross Channel/Track, and Vertical C-Stud. The main accessory contains wedge

More information

Micro Hydroelectricity Installer Skills Assessment

Micro Hydroelectricity Installer Skills Assessment Micro Hydroelectricity Installer Skills Assessment Philip V. Hofmeyer August 2011 Page 1 Overview: This document contains an extensive skills assessment for renewable energy professionals who intend to

More information

Water for the World. 7 y

Water for the World. 7 y Water for the World For effective water storage and water system operation, ground level storage tanks should be built for sufficient, and even excess, capacity and must be watertight to prevent leakage.

More information

CHAPTER 5 DESIGN FOR CIVIL STRUCTURES

CHAPTER 5 DESIGN FOR CIVIL STRUCTURES CHAPTER 5 DESIGN FOR CIVIL STRUCTURES The main obstacle for a small-scale hydropower plant is the high development cost. In this chapter, element technologies are described assuming the need to reduce

More information

SCHEDULE OF QUANTITIES OF COMPOUND WALL WORK FOR PROPOSED CONSTRUCTION OF TEMPERATURE CONTROLLED WAREHOUSE AT PATALGANGA MIDC, DIST- RAIGARH, MUMBAI.

SCHEDULE OF QUANTITIES OF COMPOUND WALL WORK FOR PROPOSED CONSTRUCTION OF TEMPERATURE CONTROLLED WAREHOUSE AT PATALGANGA MIDC, DIST- RAIGARH, MUMBAI. SCHEDULE OF QUANTITIES OF COMPOUND WALL WORK FOR PROPOSED CONSTRUCTION OF TEMPERATURE CONTROLLED WAREHOUSE AT PATALGANGA MIDC, DIST RAIGARH, MUMBAI. Tender Reference No. BL/LI/CC/TCWMUM/BOUNDARY WALL/1617/04

More information

`AMENDMENT No. 4 TO TENDER DOCUMENTS. Tender No.: RITES/CO/B&A/EE/DTEH-Rohtak Air Cooled Chiller System of HVAC work

`AMENDMENT No. 4 TO TENDER DOCUMENTS. Tender No.: RITES/CO/B&A/EE/DTEH-Rohtak Air Cooled Chiller System of HVAC work `AMENDMENT No. 4 TO TENDER DOCUMENTS Tender No.: RITES/CO/B&A/EE/DTEH-Rohtak Air Cooled Chiller System of HVAC work S.No. Clause of tender 1 1) S.H A, Fashion Design BOQ Item no. 1 a.iii), 2) S.H A, Film

More information

HydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT PUMP-STORAGE HYDROELECTRIC SITES. J. L. GORDON P.Eng.

HydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT PUMP-STORAGE HYDROELECTRIC SITES. J. L. GORDON P.Eng. HydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT OF PUMP-STORAGE HYDROELECTRIC SITES BY J. L. GORDON P.Eng. January, 2009 HydroHelp 5 for pump-turbine sites. A continuation of the

More information

11/10/2009. Lake Uist - BAKER PT. Distributor from bore to penstocks Lowest level in draft tube FSL Top of surge tank.

11/10/2009. Lake Uist - BAKER PT. Distributor from bore to penstocks Lowest level in draft tube FSL Top of surge tank. Parametric Analysis of Pump- Turbine Sites J. L. Gordon, P. Eng. Fellow CSCE 190.0 FSL 203.6 Top of surge tank. Lake Uist - BAKER PT 193.0 Deck El. 2120.6 Surge tank required? Yes 169.5 Bottom of surge

More information

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PIPE HANGERS, Section PIPE HANGERS, SUPPORTS, AND RESTRAINTS

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PIPE HANGERS, Section PIPE HANGERS, SUPPORTS, AND RESTRAINTS PART 1 GENERAL 1.01 SUMMARY Section 15140 PIPE HANGERS, This Section includes the furnishing and subsequent installation of: A. Pipe and equipment hangers, supports, and associated anchors B. Equipment

More information

Stone and Masonry Veneer

Stone and Masonry Veneer Stone and Masonry Veneer R703.7 Stone and masonry veneer, general. Stone and masonry veneer shall be installed in accordance with this chapter, Table R703.4 and Figure R703.7. These veneers installed over

More information

The International Committee of the Red Cross

The International Committee of the Red Cross The International Committee of the Red Cross WATER & HABITAT DEPARTMENT Rozhawa / Hospital / Rehabiliation Phase II Rozhawa Hospital / Erbil City / Erbil 25 - February - 217 Rozhawa / Hospital / Rehabiliation

More information

TERMS OF REFERENCE UPGRADING THE FISHERY SECTOR IN SOUTH SUDAN

TERMS OF REFERENCE UPGRADING THE FISHERY SECTOR IN SOUTH SUDAN UNITED NATIONS INDUSTRIAL DEVELOPMENT ORGANIZATION ORGANISATION DES NATIONS UNIES POUR LE DEVELOPPEMENT INDUSTRIEL TERMS OF REFERENCE UPGRADING THE FISHERY SECTOR IN SOUTH SUDAN CONSTRUCTION OF A FISH

More information

RUWAIS HOUSING COMPLEX PHASE IV CIVIL & ELECTROMECHANICAL WORKS

RUWAIS HOUSING COMPLEX PHASE IV CIVIL & ELECTROMECHANICAL WORKS AL NASR SCOPE OF WORKS: Construction of water storage tank consisting of: 3 Water storage tanks 2,641,721 gal of 42 m diameter and 7.65 m each 2300 m³ of concrete 2450 m² of water proofing external 4300

More information

CIVIL WORKS Mahesh G. Nair

CIVIL WORKS Mahesh G. Nair MEASUREMENT BOOK SUNIL Date Work Order Contractor : : EARTH WORKS CIVIL WORKS Mahesh G. Nair GROUND FLOOR 1 EARTH WORKS EXCAVATION : Earth work excavation for foundation trenches in all classes of soil

More information

Community members assembled to begin the installation

Community members assembled to begin the installation Community Pico Hydro in Sub-Saharan Africa: Case Study 1 Site: Kathamba, Kirinyaga District, Kenya Background This scheme was installed as part of a program implemented by The Micro Hydro Centre at Nottingham

More information

KEMBAR DAM N u s a T e n g g a r a B a r a t

KEMBAR DAM N u s a T e n g g a r a B a r a t I N V E N T O R Y S T U D Y O N D E V E L O P M E N T P O T E N T I A L F O R R U R A L E L E C T R I F I C A T I O N I N I N D O N E S I A KEMBAR DAM N u s a T e n g g a r a B a r a t Bandung, October

More information

Independent Consulting Engineers NV Zaegersgut Rd #13 tel +(599) Date: 25 januari 2008 Project: Troy Hill Saba Projectnr:

Independent Consulting Engineers NV Zaegersgut Rd #13 tel +(599) Date: 25 januari 2008 Project: Troy Hill Saba Projectnr: (Na) (Na) (Na) 1 Preparational works 1.1 Survey roads 1 sum 25,000.00 25,000.00 1.2 Clearing terrain roads 1 sum 45,000.00 45,000.00 Main 2 Earth work 2.1 Earth work 2.11 Excavate terrain 8900 m3 30.00

More information

CONSTRUCTION SPECIFICATION FOR POLE ERECTION

CONSTRUCTION SPECIFICATION FOR POLE ERECTION ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 615 SEPTEMBER 1993 CONSTRUCTION SPECIFICATION FOR POLE ERECTION 615.01 SCOPE 615.02 REFERENCES 615.05 MATERIALS TABLE OF CONTENTS 615.05.01 Concrete.02

More information

BILL OF QUANTITY ENGINEERING & MANAGEMENT CONSULTING CENTRE. "Beit Hanoun Emergency Water Supply Project"

BILL OF QUANTITY ENGINEERING & MANAGEMENT CONSULTING CENTRE. Beit Hanoun Emergency Water Supply Project "Beit Hanoun Emergency Water Supply Project" " Rehabilitation and Construction of Beit Hanoun Water Network " BILL OF QUANTITY ENGINEERING & MANAGEMENT CONSULTING CENTRE Bill of Quantities PREAMBLE TO

More information

Development of Hydropower & Renewable Energy (HRE) Project Khyber-Pakhtunkhwa (Phase-I) TECHNICAL GUIDELINES & REPORTS

Development of Hydropower & Renewable Energy (HRE) Project Khyber-Pakhtunkhwa (Phase-I) TECHNICAL GUIDELINES & REPORTS German Pakistan Financial Cooperation Development of Hydropower & Renewable Energy (HRE) Project Khyber-Pakhtunkhwa (Phase-I) TECHNICAL GUIDELINES & REPORTS VOLUME 3: SUMMARY OF DESIGN STANDARDS JULY 2013

More information

EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT

EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT Addendum No. 2 Attachment B Contract Document Revisions Specifications: TABLE OF CONTENTS ADDENDUM NO. 2 Attachment B Contract

More information

SECTION ALUMINUM HANDRAIL SYSTEMS

SECTION ALUMINUM HANDRAIL SYSTEMS SECTION 05520 ALUMINUM HANDRAIL SYSTEMS PART 1 - GENERAL 1.01 SUMMARY A. Section includes aluminum handrails and railings. B. Related Work: 1. Section 03300 - Cast-in-Place Concrete C. References: 1. American

More information

PRICE BID FOR. Processing zone of Special Economic Zone, MAHINDRA WORLD CITY (JAIPUR) LIMITED, JAIPUR MWCJL/HR/INFRA/HC ZONE/STP/ /T-32

PRICE BID FOR. Processing zone of Special Economic Zone, MAHINDRA WORLD CITY (JAIPUR) LIMITED, JAIPUR MWCJL/HR/INFRA/HC ZONE/STP/ /T-32 PRICE BID FOR DESIGN, SUPPLY, CONSTRUCTION, ERECTION, COMMISSIONING AND OPERATING OF (PHASE I) 3000 M3/DAY CAPACITY SEWAGE TREATMENT PLANT BASED ON ADVANCED SEQUENTIAL BATCH REACTOR TECHNOLOGY AT MAHINDRA

More information

Small Hydro based energy generation

Small Hydro based energy generation Workshop on Capacity Development Program for Afghan Women (Clean Energy Access) Small Hydro based energy generation G Anil Head Small Hydro Power Dn., Energy Management Centre, Trivandrum 695017, Kerala,

More information

CONSTRUCTION SPECIFICATION FOR GROUNDING

CONSTRUCTION SPECIFICATION FOR GROUNDING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 609 NOVEMBER 2001 CONSTRUCTION SPECIFICATION FOR GROUNDING TABLE OF CONTENTS 609.01 SCOPE 609.02 REFERENCES 609.03 DEFINITIONS - Not Used 609.04 DESIGN

More information

Demarcation Points. Example 1

Demarcation Points. Example 1 Example 1 control of distribution equipment including connection assets, ending at the customer. REVISION 03 14/04/10 Example 2 ROAD The transformer is normally at the property line. If the transformer

More information

Fixings, bonds and clamps

Fixings, bonds and clamps Square tape clamp Material 25 x 3mm Copper 0.12kg CT105-H 25 x 6mm Copper 0.30kg CT110-H 50 x 6mm Copper 0.60kg CT115-H Manufactured from high quality copper and aluminium alloys. Simple to install, providing

More information

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017 SECTION 02630 - STORM DRAINAGE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

1. Include plans, elevations, sections, details, and attachments to other work.

1. Include plans, elevations, sections, details, and attachments to other work. SECTION 102213- PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to

More information

ITEM 555 CHAIN LINK FENCING

ITEM 555 CHAIN LINK FENCING ITEM 555 AFTER MARCH 1, 2012 CHAIN LINK FENCING 555.1 Description. This item shall govern for furnishing the quantities of chain link fencing and gates as shown on the plans, including all posts, bracing

More information

Annex II- Lot 2. Bills of Quantities for Civil Works of septic tanks and soak-away wells in 6 Admin Units in localities of Sinar State

Annex II- Lot 2. Bills of Quantities for Civil Works of septic tanks and soak-away wells in 6 Admin Units in localities of Sinar State Annex II- Lot 2 Bills of Quantities for Civil Works of septic tanks and soak-away wells in 6 Admin Units in localities of Sinar State Lot: 2 Site 2-1: Allakandie All Prices of items shall include Supplying,

More information

Connectors. Multi-purpose connecting clamps. Stainless steel cross connectors

Connectors. Multi-purpose connecting clamps. Stainless steel cross connectors Connectors Multi-purpose connecting clamps Thread in lower part With mushroom head bolt and protection against twisting Art. No. Design Pack / Weight 100147 Galvanised steel, 2-part, round/round 100149

More information

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) OF THR 8th PRIMARY SCHOOL TOILETS IN MYTILENE. Annex A - BILL OF QUANTITIES 1/9

RFP/GRC/LSV/ : RENOVATION (CIVIL WORKS) OF THR 8th PRIMARY SCHOOL TOILETS IN MYTILENE. Annex A - BILL OF QUANTITIES 1/9 RFP/GRC/LSV/2017-005: RENOVATION (CIVIL WORKS) OF THR 8th PRIMARY SCHOOL TOILETS IN MYTILENE Annex A - BILL OF QUANTITIES 1/9 The Contractor shall consider in his price all costs or expenses of all requirements

More information

BANGKET LENDANG N u s a T e n g g a r a B a r a t

BANGKET LENDANG N u s a T e n g g a r a B a r a t I N V E N T O R Y S T U D Y O N D E V E L O P M E N T P O T E N T I A L F O R R U R A L E L E C T R I F I C A T I O N I N I N D O N E S I A BANGKET LENDANG N u s a T e n g g a r a B a r a t Bandung, October

More information

A. Attachment A contains the report Hydro Plant Decommissioning Update, July 2010.

A. Attachment A contains the report Hydro Plant Decommissioning Update, July 2010. Requests for Information CA-NP-036 NP 2013/2014 GRA 1 2 3 4 5 6 7 8 9 10 11 12 Q. [Decommissioning] Please all workpapers, assumptions, considerations and material reviewed and/or relied upon in developing

More information

Annex III- Lot 3. Bills of Quantities for Civil Works of septic tanks and soak-away wells in 8 Admin Units in localities of Sinar State

Annex III- Lot 3. Bills of Quantities for Civil Works of septic tanks and soak-away wells in 8 Admin Units in localities of Sinar State Annex III- Lot 3 Bills of Quantities for Civil Works of septic tanks and soak-away wells in 8 Admin Units in localities of Sinar State Lot: 3 Site 3-1: Sinja city All Prices of items shall include Supplying,

More information

Tender Call No.: Likhu/GVN/Pkg-03/2012 OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE SALIENT FEATURES... 1

Tender Call No.: Likhu/GVN/Pkg-03/2012 OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE SALIENT FEATURES... 1 Table of contents OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE... 1 1.1 SALIENT FEATURES... 1 1.2 TRANSPORT LIMITATIONS... 8 1.3 DEVIATIONS FROM SPECIFICATIONS... 9 1.4 APPROVAL OF DRAWINGS...

More information

BRANZ FACTS RESILIENT NON-STRUCTURAL ELEMENTS SEISMICALLY RESILIENT NON-STRUCTURAL ELEMENTS # 3. Restraint systems

BRANZ FACTS RESILIENT NON-STRUCTURAL ELEMENTS SEISMICALLY RESILIENT NON-STRUCTURAL ELEMENTS # 3. Restraint systems SEISMICALLY BRANZ FACTS RESILIENT NON-STRUCTURAL ELEMENTS SEISMICALLY RESILIENT DESIGN CRITERIA # 2 NON-STRUCTURAL ELEMENTS # 3 Restraint systems The next step in the non-specific design pathway in NZS

More information

Nairobi Funeral Home and Forensics INCINERATOR BILLS OF QUANTITIES

Nairobi Funeral Home and Forensics INCINERATOR BILLS OF QUANTITIES Nairobi Funeral Home and Forensics INCINERATOR BILLS OF QUANTITIES 26/10/2015 Item Description Qty Unit INCINERATOR INSTALLATION Supply, deliver, install, test and commission the following incinerator

More information

Annex I- Lot 1. Bills of Quantities for Civil Works of septic tanks and soak-away wells in 7 Admin Units in localities of Sinar State

Annex I- Lot 1. Bills of Quantities for Civil Works of septic tanks and soak-away wells in 7 Admin Units in localities of Sinar State Annex I- Lot 1 Bills of Quantities for Civil Works of septic tanks and soak-away wells in 7 Admin Units in localities of Sinar State Lot: 1 Site 1-1: Sinnar city All Prices of items shall include Supplying,

More information

Delta Level 1000 Hinged Lip Pit Mounted & Suspended Frame Dock Leveller

Delta Level 1000 Hinged Lip Pit Mounted & Suspended Frame Dock Leveller Delta Level 1000 Hinged Lip Pit Mounted & Suspended Frame Dock Leveller Product Description The Delta Level 1000 is one of our ranges of hinged lip dock levellers. Dock levellers are indispensable for

More information

THE STUDY ON INTRODUCTION OF RENEWABLE ENERGIES IN RURAL AREAS IN MYANMAR FINAL REPORT. Volume 4 Main Report Manuals for Sustainable Small Hydros

THE STUDY ON INTRODUCTION OF RENEWABLE ENERGIES IN RURAL AREAS IN MYANMAR FINAL REPORT. Volume 4 Main Report Manuals for Sustainable Small Hydros THE STUDY ON INTRODUCTION OF RENEWABLE ENERGIES IN RURAL AREAS IN MYANMAR FINAL REPORT Main Report Manuals for Sustainable Small Hydros Part 4-1 Part 4-2 Part 4-3 Part 4-4 O&M Manual-Small Hydros Design

More information

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service.

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service. CHAPTER3 Clark Public Utilities Commercial Electric Service Handbook Commercial Underground Services Preparing for the installation The following checklist will assist in preparing a project for the installation

More information

United Nations Development Programme

United Nations Development Programme PROJECT UPGRADE OF EXISTING ISLAND WASTE MANAGMENT CENTER AT MUNDOO ISLAND PREPARED BY CONTENT MUNDHOO DRAWINGS SL.NO DRAWING NAME DRAWING NUMBER 1 SITE PLAN /2017/IWMC/MUN/001 2 FLOOR PLAN /2017/IWMC/MUN/002

More information

1. Remove worn-out old plaster (or any other finishing).

1. Remove worn-out old plaster (or any other finishing). Annexure A SCOPE OF WORK The work should be implemented by contractor under the supervision of Norwegian Refugee Co BoQ s and below instructions. NRC reserves the right to provide further clarifications/drawings

More information

How To Construct a Ferro Cement Tank

How To Construct a Ferro Cement Tank How To Construct a Ferro Cement Tank Be Advised The following power point presentation assumes that individuals using it to construct ferro-cement tanks have a basic knowledge of geometry and calculating

More information

Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION. 1.1 General. 1.2 Establishment of the Company. 1.3 Special Features of the Project

Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION. 1.1 General. 1.2 Establishment of the Company. 1.3 Special Features of the Project Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION 1.1 General The Lower Erkhuwa hydropower Project is located in Kulung and Chauki Danda VDCs of Bhojpur District, in East Nepal. It is located

More information

L_All_Vocatinal_Ed_Construction. Sector: Construction. Sr. No Specialisation Page No 1 Construction and Building Technology 02.

L_All_Vocatinal_Ed_Construction. Sector: Construction. Sr. No Specialisation Page No 1 Construction and Building Technology 02. L_All_Vocatinal_Ed_Construction Sector: Construction Sr. No Specialisation Page No 1 Construction and Building Technology 02 1 P a g e VOCATIONAL EDUCATIONAL QUALIFICATION FRAMEWORK (Sector - Construction

More information

NEMO TANK INSTALLATION GUIDE INSTALLATION INSTRUCTIONS FOR THE NEMO TANK STAGE

NEMO TANK INSTALLATION GUIDE INSTALLATION INSTRUCTIONS FOR THE NEMO TANK STAGE NEMO TANK INSTALLATION GUIDE INSTALLATION INSTRUCTIONS FOR THE NEMO TANK STAGE 1. Before undertaking the work 2. Receiving the materials 3. Handling and storage 4. Tank layout 5. Installing the tanks STAGE

More information

ITEM No. D E S C R I P T I O N UNIT QTY. 5-E343.2 In class III material m³ 1,260 - Max. Depth: m For disposal

ITEM No. D E S C R I P T I O N UNIT QTY. 5-E343.2 In class III material m³ 1,260 - Max. Depth: m For disposal EARTHWORKS Excavation for foundations 5E343.2 In class III material m³ 1,260 Max. Depth: 0.50 1 m For disposal 5E334.2 In class III material m³ 720 Max. Depth: 1 2 m For disposal Filling Ancillaries 5E723.0

More information

A Provide for Contractor's Office, Store etc. Sum

A Provide for Contractor's Office, Store etc. Sum BILL NO.1 - PRELIMINARIES AND GENERAL CONDITIONS A Provide for Contractor's Office, Store etc. Sum B C Provide for Insurance in accordance with the Conditions of the Contract. Allow for the provision of

More information

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016 SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri September 21, 2016 CONTENT Introduction Potential in Southeast Asia Challenges in Small Hydro Main Design Steps (Bad) Examples

More information

Advanced Building & Development, LLC

Advanced Building & Development, LLC Advanced Building & Development, LLC Leading Edge Green Building Technology October 18, 2010 Single Family Budgetary Cost: Slockett w/o loft Excavation & Site Preparation (Included in slab preparation)

More information

BUILDING PERMIT APPLICATION CITY OF SIDNEY BUILDING INSPECTION DEPARTMENT

BUILDING PERMIT APPLICATION CITY OF SIDNEY BUILDING INSPECTION DEPARTMENT BUILDING PERMIT APPLICATION CITY OF SIDNEY BUILDING INSPECTION DEPARTMENT APPLICATION REQUESTED (check all that apply) Is this currently a: Permit # Addition-square footage Single Family Detached Permit

More information

ARCHITECTURAL DRAWINGS

ARCHITECTURAL DRAWINGS PROJECT DETAILS Implementation Partner: Project title: Grant No.: KIS062 Content : ARCHITECTURAL DRAWINGS SHEET NO. REHABILITATION OF GRANT NO.: - KIS062 COVER SHEET INDEX SHEET CONTENTS 01 02 03 04 05

More information

level control gates Waterman Industries of Egypt WATERMAN

level control gates Waterman Industries of Egypt WATERMAN Automatic level control gates WATERMAN DOWNSTREAM LEVEL CONTROL Waterman Types "A" and "B" Automatic gates provide constant downstream water level control regardless of upstream level conditions or downstream

More information

CONSTRUCTION AND REHABILITATION OF FENCE AT GPL'S VERSAILLES COMPOUND

CONSTRUCTION AND REHABILITATION OF FENCE AT GPL'S VERSAILLES COMPOUND BILL Nr1 - PRELIMINARIES 1.0 PRELIMINARY PARTICULARS 1.1 Funding The funding shall be provided by the Guyana Power & light Inc., of 40 Main street, North Cummingsburg, Georgetown. 1.2 Engineer The Engineer

More information

SECTION COMMON WORK RESULTS FOR FIRE SUPPRESSION

SECTION COMMON WORK RESULTS FOR FIRE SUPPRESSION SECTION 21 05 00 COMMON WORK RESULTS FOR FIRE SUPPRESSION PART 1 - GENERAL 1.1 SUMMARY A. This section supplements all sections in this division, including pipe, fittings, valves, and connections for sprinkler

More information

TYPICAL INSTALLATION INSTRUCTIONS

TYPICAL INSTALLATION INSTRUCTIONS TYPICAL INSTALLATION INSTRUCTIONS Environment One Grinder Pump Feature Identification 1. Grinder Pump Basin High density polyethylene (HDPE) 2. Accessway Cover Painted Steel 3. Electrical Quick Disconnect

More information

METATEK POWER HOUSE CONSTRUCTION BUILDER S GUIDE CHECKLIST

METATEK POWER HOUSE CONSTRUCTION BUILDER S GUIDE CHECKLIST BUILDER S GUIDE & CHECKLIST 1 Table of Contents OVERVIEW... 2 CONSTRUCTION GUIDELINES... 2 DO NOT MODIFY LIST... 3 OPTIONAL LIST... 3 BUILDING DRAWINGS... 4 CHECKLIST... 4 MATERIALS LIST... 15 MATERIALS

More information

United Nations Development Programme

United Nations Development Programme PROJECT UPGRADE OF EXISTING ISLAND WASTE MANAGMENT CENTER AT FONADHOO ISLAND PREPARED BY CONTENT FONADHOO DRAWINGS SL.NO DRAWING NAME DRAWING NUMBER 1 SITE PLAN /2017/IWMC/FON/001 2 FLOOR PLAN /2017/IWMC/FON/002

More information

Steel Door Frame Installation in Masonry Construction

Steel Door Frame Installation in Masonry Construction Steel Door Frame Installation in Masonry Construction Steel Door Frame Installation in Masonry Construction This manual provides step-by-step instructions for the installation of a steel door frame in

More information

Nairobi Funeral Home and Forensics BOREHOLE BILLS OF QUANTITIES

Nairobi Funeral Home and Forensics BOREHOLE BILLS OF QUANTITIES Nairobi Funeral Home and Forensics BOREHOLE BILLS OF QUANTITIES 26/10/2015 Item Description Qty Unit Supply, deliver, install, test and commission the following borehole equipment including all materials

More information

NEPAL ELECTRICITY AUTHORITY (An Undertaking of Government of Nepal)

NEPAL ELECTRICITY AUTHORITY (An Undertaking of Government of Nepal) NEPAL ELECTRICITY AUTHORITY (An Undertaking of Government of Nepal) PROJECT MANAGEMENT DIRECTORATE Electricity Transmission Expansion and Supply Improvement Project TAMAKOSHI KATHMANDU 220/400 KV TRANSMISSION

More information

Development of the Urban Water and Sanitation Sector in South Sudan (DUWSS) Bill of Quantities. for LOCATED AT PRIMARY & SECONDARY SCHOOL.

Development of the Urban Water and Sanitation Sector in South Sudan (DUWSS) Bill of Quantities. for LOCATED AT PRIMARY & SECONDARY SCHOOL. Development of the Urban Water and Sanitation Sector in South Sudan (DUWSS) Bill of Quantities for SIX CHAMBER VIP LATRINE FACILITY LOCATED AT PRIMARY & SECONDARY SCHOOL YEI RIVER COUNTY South Sudan JUN,

More information

Cost Analysis for High Head SHP Projects

Cost Analysis for High Head SHP Projects 2012 International Congress on Informatics, Environment, Energy and Applications-IEEA 2012 IPCSIT vol.38 (2012) (2012) IACSIT Press, Singapore Cost Analysis for High Head SHP Projects Sachin Mishra 1,

More information

Issued for Bid West Alexandria, OH 05/2018 WWTP Improvements Contract 2 TABLE OF CONTENTS

Issued for Bid West Alexandria, OH 05/2018 WWTP Improvements Contract 2 TABLE OF CONTENTS 669.7403.001 West Alexandria, OH 05/2018 WWTP Improvements Contract 2 TABLE OF CONTENTS Page C-111 Advertisement for Bids 1-2 C-200 Instruction to Bidders 1-10 C-410 Bid Form for Construction Projects

More information

STRUCTURAL STEEL FRAMING

STRUCTURAL STEEL FRAMING SECTION 05 12 00 - STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.1 SUMMARY A. Section includes 1. Structural steel framing 2. Structural steel framing required for support and framing of rooftop mechanical

More information

Bill of Quantity. Unit Price in words (Nu) Unit Price (Nu) Code Description Unit Quantity. Amount (Nu) CP-AR-

Bill of Quantity. Unit Price in words (Nu) Unit Price (Nu) Code Description Unit Quantity. Amount (Nu) CP-AR- in 02 03 RS-AR- 04 RS-AR- 05 06 07 Access track rehabilitation, to Vegetation clearing as necessary for both the track section to undergo rehabilitation, and track section to be extended/created Earthworks

More information

8-5. RMG プロジェクト監理帳票運用例

8-5. RMG プロジェクト監理帳票運用例 8-5. RMG プロジェクト監理帳票運用例 (1) Daily Report (2) Weekly Meeting Agenda PROJECT FOR CAPACITY DEVELOPMENT ON NATURAL DISASTER-RESISTANT TECH- NIQUES OF CONSTRUCTION AND RETROFITTING FOR PUBLIC BUILDINGS 20

More information