Report on the completion of HPP POBREG RAIFFEISEN BANK SH.A. ALBANIA. Evaluation and Business Plan Supervision of Hydropower Plants

Size: px
Start display at page:

Download "Report on the completion of HPP POBREG RAIFFEISEN BANK SH.A. ALBANIA. Evaluation and Business Plan Supervision of Hydropower Plants"

Transcription

1 Head Office Augustaanlage D Mannheim Germany Reinhold Metzler Project manager Tel: RAIFFEISEN BANK SH.A. ALBANIA entecag Consulting & Engineering Bahnhofstr. 4 CH-9000 St. Gallen Switzerland Hedi Feibel Hydrologist Tel: hedi.feibel@entec.ch Evaluation and Business Plan Supervision of Hydropower Plants intec - GOPA International Energy Consultants GmbH Leopoldsweg Bad Homburg v.d.h. Germany Anja Lassonczyk Energy Economist Tel:: +49 (6172) anja.lassonczyk@gopaintec.de Report on the completion of HPP POBREG Submitted: 29 August

2 1. Objective This completion report: Presents the work and related expenses done to complete the power plant s realisation in June 30, 2013 based on a plausibility check of the information provided by the investor, compares the total expenditures done with the re-allocated budget as of Aug. 12, aims at giving an account on the degree of completion of the works based on: Visual inspection of the components of the plant and functional tests conducted during the site visits of the Consultant on 2 nd July 2013 Evaluation of the documents on commissioning provided by the developer 2. Certification of work The investor provided us with his claim of work, executed from 1 st February up to 30 April 2013, with the remark, that no more work will be claimed after this time. Based on a check against the plans and the work inspected during the site visit this claim appears to be plausible. This statement is made under the condition that a signed copy from the supervisor would be provided after his return from holidays. (3 Sept.) The bank has provided its LC payments up to 30 June 2013, which are include in the assessment. The result of this assessment is reflected in the Table below. Based on the information provided and found plausible, the following can be stated: For the period 1st February up to 30 June 2013 an amount of Euro 740,797 can be certified. Up to the end of June 2013 a total of Mio. Euro or 93.6%% of the agreed budget has been spent. Description Budget March 12 Re-allocated Budget Aug.12 Total expenditure up to 31 Jan 2013 Spent 01 Feb March 2013 Spent 16 March - 30 June 2013 Total Expenditures up to 30 June 2013 Remaining budget as of June 30, 2013 Euro Euro Euro Euro Euro % Euro Headworks(Intake & Desander) Civil works 1,369,183 1,369,183 1,369,183 17,779 5,967 1,392, % -23,746 Hydromechanic equipment 130, ,250 89,275 89,275 80% 21,975 Headrace 0 0 Civil works & Hydromechanic equipment 4,928,029 4,928,029 4,928, ,057 84,853 5,121, % -193, Forebay and Spillway Cascade 0 0 Civil works 146, , ,653 22, , % -22,436 Hydromechanic equipment 66,920 60,510 38,044 38,044 63% 22,466 Penstock 0 0 Civil works 344, , , , , % -113,353 Pipework 445, , , , % -5,614 Powerhouse 0 0 Civil works 225, , ,483 15, , % -15,306 Electromechanical equipment 2,196,957 2,251,772 1,633, ,491 1,998,884 89% 252,888 Tailrace channel 335, , ,000 4,298 2, , % -6,500 Transmission line and connection 369, , , ,726 54% 97,846 Access roads 100, , , , % 452 Infrastructural expenses 145, , , , % -4,492 Planning and construction supervision 1,270,429 1,270,429 1,237,206 1,237,206 97% 33,223 Savings from items 229, , , % 0 Contigiencies 1,207,502 1,207, , ,919 33% 807,583 Project Insurance during construction 8,160 8,160 8,160 8, % 0 Total investment 13,290,684 13,290,684 11,698, ,075 Expenses claimed by Client 153, ,680 14,488, % Expenses certified by Consultant 153, ,171 12,439, % 2

3 3. Degree of completion of the civil works 3.1 Weir, intake and desander Figure 3-1 Weir, intake and desander completed and in operation Weir, intake and desander appear to be completed. Whether the design is functional has bee tested: During the time of high river discharges the structure performed as foreseen. The flush gates together with the weir crown as spillway seem to be sufficiently dimensioned The flushing channel in front of the intake has a good performance. The dividing wall has the right slope and height to create a perpendicular flow towards the intake when the flush gate is closed and changes into a parallel flow for effective flushing when the gate is open (see Fehler! Verweisquelle konnte nicht gefunden werden.) The only open issue regarding the weir is the leakage between the two sections of the weir (Figure 3-2). The engineers are aware of the problem and the consequences it could have if this leakage is not stopped. Their plan is, to seal the joint from the upstream side of the weir once the river water is low enough to allow to open the weir s backside. 3

4 Figure 3-3 Dividing wall correctly dimensioned: perpendicular flow if gate is closed (left), parallel flow during flushing (right) Figure 3-2 Leakage between the two sections of the weir 4

5 The desander has been checked regarding its desilting efficiency and the effectiveness of flushing out the settled sediment. As the river was already relatively low in discharge it did not carry too much sand. Hence it was difficult to actually test the function of the structure. The incoming water flow was relatively turbulent up to half of the chamber length which would lower the effectiveness of the desander significantly. By partially closing the inlet gates and observing the velocity distribution in the individual chamber it could be shown that the flow can be well distributed. It will be the task of the gate operators to find the best position of the gates to achieve a well distributed flow as shown in Figure 3-4 Figure 3-4 Desander under operation: the flow distribution between the chambers can be well adjusted by the inlet gates After a full day of operation, not too much sediment had settled in the chamber and hence the effectiveness of the flushing could not be tested. However, opening the flush gates in the evening of the site visit, released flush water which was loaded with silt (Figure 3-5) which can be taken as an indication that the flushing arrangement is working. Whether further refinement is required will be found out in the next rainy season. 5

6 Figure 3-5 Sediment settled in the chambers is flushed out 3.2 Tunnel and spillway During previous visits the tunnel work had been already inspected and found to be done in a professional way. As the plant was in operation the tunnel the final work on the tunnel was not inspected. Driving along its alignment no leakage could be detected. Hence, this part of the headrace can be considered to be completed. In contrast to previous discussions and plans, the spillway has not been placed close to the forebay but rather at the end of the tunnel. As it leads the water over a solid rock face, no stepped channel part was realised. Instead a chute was constructed. The spillway s capacity appears to be sufficient as it was tested during the emergency shutdown, described further below. The height of the headrace channel walls is sufficient to provide enough freeboard to avoid overtopping during shutdown(figure 3-6, Figure 3-7). 6

7 Figure 3-6 Spillway at the end of the tunnel to release excess water during shutdown Figure 3-7 The chute leading the water to a rock face, from where it drops down into the river 3.3 Forebay and irrigation water release The construction of the forebay is completed and its functions are assured. During the visit a significant amount of water was released into the irrigation scheme. The members of the irrigation committee where present and at first look they seem to be content with the solution. An open issue is still the manual cleaning of the trashrack, which is quite cumbersome. The future will 7

8 show whether the amount of trash arriving at the rack requires a mechanical cleaning device or whether manual cleaning is sufficient. Figure 3-8 Headrace seen from the forebay. Gate (green) for releasing the irrigation water in the foreground Figure 3-9 Forebay with irrigation gate (left) and penstock inlet gate (blue, right) and trashrack 8

9 Figure 3-10 Manual trashrack cleaning Figure 3-11 Discussion with members of the irrigation committee next to the channel leading from the forebay to the irrigation system 3.4 Penstock, powerhouse and tailrace channel The construction of the penstock is completed. This pipeline is made up of buried GRP pipe sections. As documented in previous reports the pipe has been installed under the supervision of the supplier (SUBOR). No problem with this component was apparent. Apart from final touches, the powerhouse and tailrace channel construction is completed and its design has proven to be appropriate. No problem with these components was apparent. 9

10 Figure 3-12 Last part of the burried penstock leading to the powerhouse. Tailrace exiting to the right discharging into the lake Figure 3-13 Turbine water discharging into the tailrace channel at the powerhouse 10

11 Figure 3-14 Tailrace channel leading to the lake 11

12 4. Degree of completion of the electro-mechanical equipment 4.1 Status of the generating units The two generating units with turbines from Gugler and generators from Gamesa are commissioned and operating. Before that a bearing problem on unit 1 was experienced damaging the bearing pads. With the help of local workshops the pads could be restored and since then the unit operates with no bearing problem anymore. The units started commercial operation on the 1st June Figure 4-1The two Gugler/Gamesa generating units under operation Figure 4-2The automatic control, transformer and medium voltage switchgear (back) 12

13 Figure 4-3 Typical display regarding the operational status of the units at the monitor Figure 4-4 Detailed information available on display 13

14 Figure 4-5 Damaged bearing pads on unit 1 Figure 4-6 Dismantled bearing of unit 1 14

15 4.2 Performance of the plant For the following assessment data recorded each minute by the SCADA system in the time 7 th June to 10 th July 2013 have been made available. Further, the daily readings of the electricity meter from 14 June to 12 Aug 2013 were given for the overview of the generation values Performance unit 1 Plotting the active power values recorded by the SCADA system for unit 1 the following graph results: Figure 4-7 Output of unit 1 in the time between 7 June and 10 July 2013 The plot shows that the unit is running in a continuous mode and is performing reliably since its commissioning, which was verbally confirmed by the engineers. The maximum value was recorded on 13 th June during the commissioning with 9.2 MW Performance unit 2 Plotting the active power values recorded each minute by the SCADA system in the time 7 th June to 10 th July 2013 for unit 2 the following graph results: Figure 4-8 Output of unit 2 in the time between 7 June and 10 July 2013 Also this plot shows a continuous and reliable operation from 26 June onwards which was verbally confirmed by the engineers. This unit was running most of its time on its full opening with a recorded maximum output of 3.6 MW 15

16 4.2.3 Output of the entire plant Adding up the output data of the individual units recorded for the same time slot results in the combined output power of both units at one time and therefore the entire plant output can be shown. The graph below shows the result: Figure 4-9 Output of the plant in the time between 7 June and 10 July 2013 It can be seen that the plant reached several days an output > 12 MW. The maximum output of the plant was recorded on 28 June and 4 July with 12.6 MW. This value is just 2% lower than the sum of each unit running on its own i.e 12.8 MW. This small difference is caused by the increased loss in the penstock with the increased flow and indicates that the penstock is sufficiently dimensioned. According to the Gugler supply contract a maximum generator output of 8.5 MW and 3.4 MW was guaranteed (contract page 2+6). Hence it can be concluded that Gugler has fulfilled the condition of output power according to the contract ( 17.2 clause 1, 2 and 3) Electricity generation Using the daily readings from the grid operator s sealed meter and plotting it versus time results in the following graph showing the accumulated generation of the plant: Figure 4-10 Accumulated generation from 14 June up to 12 Aug

17 In the 60 days of reading, the plant has generated some 4.2 GWh. The decreasing daily generation must be attributed to the approaching dry season with decreasing river discharge. This fact is also indicated by the following graph, which plots the average daily output of the plant (calculated from the daily generation). During the planning phase of the project, discharge values were developed by the hydrological study, to forecast an average generation. If the average discharge values for the respective days are used and a 1.5 m³/s reduction for irrigation is considered, the black line in the graph results, depicting the potential generation (not considering part load efficiencies) which would have been forecasted for the respective period. The graph shows that the generation is quite close to what has been forecasted. The difference towards the low levels can be explained by the decreasing efficiency of the units under part load. Figure 4-11 Actual generation vs. predicted values Summarising the issues related to performance it can be said, that in general the units perform reliably and as expected. Whether the units show the efficiency guaranteed by the supply contract (page 2+6), especially under part load, can only be established by a performance test as described in the standard IEC 6004 and mentioned in the contract ( 17.2 clause 4). 4.3 Checking the surge during emergency shut down Apart from the performance under normal conditions it is important that the plant does not create a too strong water hammer during the most severe operating condition: the emergency shut down under full load. The degree of surge pressure (water hammer) is determined mainly by the closing speed of the turbines. To see whether this speed has been adjusted correctly the plant was run on full power with both units open for a short moment and then dripped from the grid by the emergency button. The raise of water was observed in the air tube just next to the penstock inlet valve (Figure 4-12) while the whole test was recorded by the SCADA system (Figure 4-13 through Figure 4-15) 17

18 The observation during the test can be summarised as follows: the rise of the water level in the air tube stayed well below the end of the pipe the pressure raise measured at the turbine is less than 8% and hence the surge is acceptable the available flow in the channel was less than maximum and hence the wave development in the headrace channel could not be simulated good enough. The test showed that the pressure surge due to emergency closing is acceptable. Figure 4-12 Air tube (with black cover) next to the turbine inlet valve (blue steel structure) Figure 4-13 Plot of the opening and frequency of unit 2 during surge test. Closing time of the 18

19 turbine is 85 s Figure 4-14 Plot of the opening and frequency of unit 1 during surge test. Closing time of the turbine is 15 s Figure 4-15 Plot of the pressure raise (0.8 bar) during the surge test 19

20 4.4 Checking the vibration level over the operating range Even so both units run without problem at full load there is a marked increase of vibration at part load in unit 1. At certain power levels this vibration is so strong that the deflection of the turbine shaft can be seen with the naked eye. The vibration can be influenced to some extend by closing the bypass valve for the leakage water and with it increase the backpressure on the runner. However, at certain points of openings this measure is not reducing the vibration anymore. To determine this point of operation unit 1 was opened in steps, the influence of operating the valve on the vibration and the pressure was recorded. The observation is documented in the following table: Output (MW) Valve position Open/closed Pressure at runner back (bar) Observed vibration 0.75 CLOSED 2 Low OPEN 1.5 Low 1.5 CLOSED 2.0 Low OPEN 1.5 Low 2.5 CLOSED 2.5 Low OPEN 1.8 Vibration 3 CLOSED 3.0 strong shaft vibration OPEN 2 strong shaft vibration 5 CLOSED 3.5 Low OPEN 2.0 Vibration 6 CLOSED 4 Low OPEN 2.5 Low 8.5 CLOSED 4.5 Low OPEN 3.2 Low Table 4-1 Observation of vibration at various output levels of unit 1 The observed vibration is so strong that the opening of the turbine between 3 and 5 MW need to be avoided. The investor s engineers are aware of this fact and Gugler needs to be approached regarding this case of warrantee. 4.5 Documentation of the commissioning Asked for the documentation of the commissioning tests the consultant was given only two commissioning test records from GAMES for the two generators. These documents contain the standard onsite tests for generators: Standstill Tests No load tests Load tests The generators have past these tests without complaint. Both documents are signed by the supplier and the investor on 30 May However, the last page of unit 2 was signed later (2 June 2013) and carries a note that.the Generator is not ready to work without supervision under warranty condition (Figure 4-16). It is not clear whether this remark on the bearings has been already dealt with and the note on restriction been withdrawn by GAMESA already. Regarding the commissioning test of the turbines and their control no documentation has been submitted. The information given was, that the investor has not signed the required provisional certificate of commissioning yet, as the delivery and installation of the replacements for the damaged bearing pads and the check valves at the generator ends was still outstanding. Hence it must be stated that the 20

21 equipment has not yet been accepted by the investor. It needs to be noted that according to the contract 17.1 clause 8 The seller is discharged from executing any warranty obligations for the time where the equipment has not been taken over with a signed provisional or final Certificate of Commissioning.. Despite of this, the seller can claim that the warrantee period for the equipment of 27 months has started with the date of readiness of shipment (contract 11.1) which was in Nov So care needs to be taken not to lose time of the warrantee period by prolonging the period of acceptance for too long. Figure 4-16 Note on last page of commissioning test record unit 2 5. Statement of the Consultant on the completion After the visual inspection of the works and the test done as described in more details in the previous chapters, it can be stated that the realization of HPP Pobreg has been generally completed with only minor finishing work left on the civil works side. Regarding the Gugler supply the final and official taking over of the equipment is still outstanding. 21

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016 SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri September 21, 2016 CONTENT Introduction Potential in Southeast Asia Challenges in Small Hydro Main Design Steps (Bad) Examples

More information

11/10/2009. Lake Uist - BAKER PT. Distributor from bore to penstocks Lowest level in draft tube FSL Top of surge tank.

11/10/2009. Lake Uist - BAKER PT. Distributor from bore to penstocks Lowest level in draft tube FSL Top of surge tank. Parametric Analysis of Pump- Turbine Sites J. L. Gordon, P. Eng. Fellow CSCE 190.0 FSL 203.6 Top of surge tank. Lake Uist - BAKER PT 193.0 Deck El. 2120.6 Surge tank required? Yes 169.5 Bottom of surge

More information

FEASIBILITY STUDY GUIDELINES

FEASIBILITY STUDY GUIDELINES FEASIBILITY STUDY GUIDELINES Pakhtunkhwa Energy Development Organization (PEDO) Energy and Power Department, KP Prepared by Pakhtunkhwa Energy Development Organization Feasibility Study Guidelines Volume

More information

Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION. 1.1 General. 1.2 Establishment of the Company. 1.3 Special Features of the Project

Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION. 1.1 General. 1.2 Establishment of the Company. 1.3 Special Features of the Project Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION 1.1 General The Lower Erkhuwa hydropower Project is located in Kulung and Chauki Danda VDCs of Bhojpur District, in East Nepal. It is located

More information

HydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT PUMP-STORAGE HYDROELECTRIC SITES. J. L. GORDON P.Eng.

HydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT PUMP-STORAGE HYDROELECTRIC SITES. J. L. GORDON P.Eng. HydroHelp 5 AN EXCEL PROGRAM DEVELOPED FOR PRE-FEASIBILITY ASSESSMENT OF PUMP-STORAGE HYDROELECTRIC SITES BY J. L. GORDON P.Eng. January, 2009 HydroHelp 5 for pump-turbine sites. A continuation of the

More information

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited www.smi.com.np smi.investment.limited@gmail.com Date : August,

More information

Small Hydro based energy generation

Small Hydro based energy generation Workshop on Capacity Development Program for Afghan Women (Clean Energy Access) Small Hydro based energy generation G Anil Head Small Hydro Power Dn., Energy Management Centre, Trivandrum 695017, Kerala,

More information

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited www.smi.com.np smi.investment.limited@gmail.com Date : August,

More information

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited www.smi.com.np smi.investment.limited@gmail.com Date : January,

More information

Small Hydropower Projects (SHPP) Training Workshop Project Documentation for Project Assessment. Yerevan, 12./

Small Hydropower Projects (SHPP) Training Workshop Project Documentation for Project Assessment. Yerevan, 12./ Consulting Services for the Programme for the Promotion of Renewable Energies: German-Armenian Renewable Energy Fund (GAF-RE) Phase II, BMZ ID 2009.70.285 Small Hydropower Projects (SHPP) Training Workshop

More information

PRE FEASIBILITY REPORT NUKULOA MICRO HYDRO POWER PROJECT

PRE FEASIBILITY REPORT NUKULOA MICRO HYDRO POWER PROJECT Ministry of Infrastructure and Transport PRE FEASIBILITY REPORT NUKULOA MICRO HYDRO POWER PROJECT Prepared by : Department of Energy August, 2013 [DOE] 1 Table of Contents Summary... 3 1. Geographical

More information

2 FINDING OF THE POTENTIAL SITES

2 FINDING OF THE POTENTIAL SITES EXECUTIVE SUMMARY 1 Background S-1 2 User of Manual S-1 3 Applicable Range of Micro-hydro power in the Indonesia S-2 4 How to use this Manual S-2 Chapter 1 INTRODUCTION 1-1 1.1 Purpose of the Manual

More information

MIEL I Hydroelectric Power Plant

MIEL I Hydroelectric Power Plant MIEL I Hydroelectric Power Plant The Miel I Power Plant, which is located in the municipality of Norcasia, forms part of the hydro potential in western Caldas. This region comprises the basins of the rivers

More information

Blue Lake Hydroelectric Project (FERC No. 2230) Expansion Environmental Analysis

Blue Lake Hydroelectric Project (FERC No. 2230) Expansion Environmental Analysis United States Departme nt of Agriculture Forest Service Alaska Region Tongass National Forest (907) 747-6671 Blue Lake Hydroelectric Project (FERC No. 2230) Expansion Environmental Analysis Dear Planning

More information

Evaluation of the hydrological risk during the construction phase of Kavsakbendi Dam and HEPP

Evaluation of the hydrological risk during the construction phase of Kavsakbendi Dam and HEPP Evaluation of the hydrological risk during the construction phase of Dr.-Ing. Ronald Haselsteiner Björnsen Consulting Engineers, Germany (formerly: EnerjiSA) Stavanger, Norway 15-16 June 2015 MSc. Koray

More information

Chakachamna Hydro. AEA Geothermal Conference

Chakachamna Hydro. AEA Geothermal Conference Chakachamna Hydro AEA Geothermal Conference August 2007 Chakachamna Hydro 300+ MW hydro opportunity identified Preliminary FERC License application filed in May 2006 Initial scoping/informational meetings

More information

DORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Monthly Progress Report. February 2018

DORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Monthly Progress Report. February 2018 DORDI KHOLA HYDROPOWER PROJECT Lamjung, Nepal Monthly Progress Report February 2018 --------------------------------------------------- Himalayan Power Partner Limited Energy Sector Research, Development

More information

Hydropower retrofitted onto existing water infrastructure assets

Hydropower retrofitted onto existing water infrastructure assets Hydropower retrofitted onto existing water infrastructure assets Marco van Dijk Lecturer and Principal Researcher University of Pretoria / Water Research Commission South Africa Presentation Layout How

More information

Voith s StreamDiver solution for decentralized low head hydropower plant operations

Voith s StreamDiver solution for decentralized low head hydropower plant operations Voith s StreamDiver solution for decentralized low head hydropower plant operations Stefan Reich Joerg Lochschmidt, Mandar Pachegaokar Voith Hydro Holding GmbH & Co. KG Voith Hydro Holding GmbH & Co. Voith

More information

CASE STUDY JHIMRUK, NEPAL

CASE STUDY JHIMRUK, NEPAL SEDIMENT MANAGEMENT CASE STUDY JHIMRUK, NEPAL Key project features Name: Jhimruk Country: Nepal Category: modifying operating rule (focus or redistribute sediment); adaptive strategies Reservoir volume

More information

Performance improvement of headworks: a case of Kalignadaki A Hydropweor Project through physical hydraulic modelling

Performance improvement of headworks: a case of Kalignadaki A Hydropweor Project through physical hydraulic modelling Performance improvement of headworks: a case of Kalignadaki A Hydropweor Project through physical hydraulic modelling Dr. Ing. Meg B. Bishwakarma General Manager, Hydro Lab Pvt. Ltd., Nepal ABSTRACT: The

More information

DORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Progress Report. January 2018

DORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Progress Report. January 2018 DORDI KHOLA HYDROPOWER PROJECT Lamjung, Nepal Progress Report January 2018 --------------------------------------------------- Himalayan Power Partner Limited Energy Sector Research, Development & Consulting

More information

Types of Hydropower Facilities

Types of Hydropower Facilities Types of Hydropower Facilities 1 Impoundment Hydropower- uses a dam to store water. Water may be released either to meet changing electricity needs or to maintain a constant water level. 2 Run-of-River

More information

Consulting Services for the Programme for the Promotion of Renewable Energies: Phase III, BMZ ID Small Hydropower Projects (SHPP)

Consulting Services for the Programme for the Promotion of Renewable Energies: Phase III, BMZ ID Small Hydropower Projects (SHPP) Consulting Services for the Programme for the Promotion of Renewable Energies: German-Armenian Renewable Energy Fund (GAF-RE) Phase III, BMZ ID 2012.7029.7 Small Hydropower Projects (SHPP) Introduction

More information

compact efficient reliable

compact efficient reliable compact efficient reliable The compact turbine system for highest demands in terms of efficiency and ecology in hydropower compact efficient reliable Milestones 2006 Commissioning DIVE-Turbine prototype

More information

Range of utilization. Envelope

Range of utilization. Envelope Kaplan Turbines Development Based on the principles of a Francis Turbine the Kaplan Turbine was developed by the Austrian engineer Victor Kaplan towards the beginning of the 20th century. Due to its adjustable

More information

Xayaburi Hydroelectric Power Project

Xayaburi Hydroelectric Power Project The MRC Regional Workshop on Discharge and Sediment Monitoring and Geomorphological Tool for the Lower- Mekong Basin, 21-22 22 October 2008 Xayaburi Hydroelectric Power Project TEAM Consulting Engineering

More information

National Hydropower Association Operational Excellence Event Report. Environmental

National Hydropower Association Operational Excellence Event Report. Environmental 1) Submitting Organization: Redacted 2) Name of Preparer, Phone & Email: Redacted 3) Report Number (OE Internal Use): To Be Supplied Later 4) Date & Time of Event: 5) Duration of Event: 6) Functional Area:

More information

John Hart Generating Station Replacement Project. November 2017 Community Construction Update Report #53

John Hart Generating Station Replacement Project. November 2017 Community Construction Update Report #53 John Hart Generating Station Replacement Project November 2017 Community Construction Update Report #53 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

Chris le Grange & Pierre Pisterman Project Manager Hydro Tasmania & CEO HPP South Africa & France

Chris le Grange & Pierre Pisterman Project Manager Hydro Tasmania & CEO HPP South Africa & France Chris le Grange & Pierre Pisterman Project Manager Hydro Tasmania & CEO HPP South Africa & France Delivering South Africa s First Project Financed Run of River Hydro Power Plant: The Neusberg Project Outline

More information

Ultra Low Head Hydro Potential

Ultra Low Head Hydro Potential An Innovative Solution for Harnessing Ultra Low Head Hydro Potential New Delhi, 2014-01-23 Abhishek Swarnkar AHEC 2015-02-06 1 Contents 1. Attractiveness to Hydro Power Plant Developer 2. Need for Sustainable

More information

Aspen Revisited. By Alfred F.A. Patzig, HYDROPOWER TURBINE SYSTEMS INC. (HTS INC), Richmond, Virginia, USA

Aspen Revisited. By Alfred F.A. Patzig, HYDROPOWER TURBINE SYSTEMS INC. (HTS INC), Richmond, Virginia, USA Aspen Revisited By Alfred F.A. Patzig, HYDROPOWER TURBINE SYSTEMS INC. (HTS INC), Richmond, Virginia, USA ABSTRACT Only ten years after installing a new turbine system at their Maroon Creek hydroelectric

More information

Irrigation System. BWCDD Zanjero Training 2/13/2008

Irrigation System. BWCDD Zanjero Training 2/13/2008 Irrigation System BWCDD Zanjero Training Session #7 2/13/2008 Irrigation System The (main) intake structure t directs water from the source of supply, such as a reservoir or a river, into the irrigation

More information

6) Penstocks 3.25m dia and 965m long to lead a design discharge of cumecs

6) Penstocks 3.25m dia and 965m long to lead a design discharge of cumecs Project: Sorang Hydro Electric Project - 100 MW Overview: M/s.Himachal Sorang Pvt.Ltd., Hyderabad, is developing the Run of the River Sorang Hydro Electric Project (100MW) in Kinnaur District of Himachal

More information

Hydropower and Water Resources

Hydropower and Water Resources Hydropower and Water Resources Hydropower and Water Resources The development, planning, design, and construction of hydropower as well as large-scale irrigation schemes and special hydraulic structures

More information

Fig Micro-hydro s economy of scale ( based on data in 1985)

Fig Micro-hydro s economy of scale ( based on data in 1985) CHAPTER 1 INTRODUCTION 1.1 Purpose of the Manual for Micro-Hydro Development Micro-Hydroelectric Power, called as a Micro-Hydro, usually does not supply electricity to the national grid. They are used

More information

Bringing Untapped Hydropower to Reality

Bringing Untapped Hydropower to Reality voith.com Bringing Untapped Hydropower to Reality Whitepaper 2018 Voith Mini Hydro Solutions 1 Reducing Interfaces by Turnkey Solutions 2 Customized Solutions for Standard Applications 3 Water-to-Wire

More information

Tender Call No.: Likhu/GVN/Pkg-03/2012 OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE SALIENT FEATURES... 1

Tender Call No.: Likhu/GVN/Pkg-03/2012 OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE SALIENT FEATURES... 1 Table of contents OLUME III A 1 TABLE OF CONTENTS SALIENT FEATURES 1.0 SCOPE... 1 1.1 SALIENT FEATURES... 1 1.2 TRANSPORT LIMITATIONS... 8 1.3 DEVIATIONS FROM SPECIFICATIONS... 9 1.4 APPROVAL OF DRAWINGS...

More information

John Hart Generating Station Replacement Project. May 2017 Community Construction Update Report #47

John Hart Generating Station Replacement Project. May 2017 Community Construction Update Report #47 John Hart Generating Station Replacement Project May 2017 Community Construction Update Report #47 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

PROJECT INFORMATION AND SHORTLISTING CRITERIA FOR SCREENING OF CONSULTING FIRM. Tamakoshi V Hydroelectric Project

PROJECT INFORMATION AND SHORTLISTING CRITERIA FOR SCREENING OF CONSULTING FIRM. Tamakoshi V Hydroelectric Project PROJECT INFORMATION AND SHORTLISTING CRITERIA FOR SCREENING OF CONSULTING FIRM 1. PROJECT INFORMATION Intoduction: Tamakoshi V Hydroelectric Project The Tamakoshi-V Hydropower Project is a cascade development

More information

ENGINEERING, PROCUREMENT & CONSTRUCTION OF HYDROMECHANICAL WORKS FOR MIDDLE MODI HYDRO POWER PROJECT (15.1 MW) BID DOCUMENT VOLUME 5: PRICE SCHEDULE

ENGINEERING, PROCUREMENT & CONSTRUCTION OF HYDROMECHANICAL WORKS FOR MIDDLE MODI HYDRO POWER PROJECT (15.1 MW) BID DOCUMENT VOLUME 5: PRICE SCHEDULE ENGINEERING, PROCUREMENT & CONSTRUCTION OF HYDROMECHANICAL WORKS FOR MIDDLE MODI HYDRO POWER PROJECT (15.1 MW) BID DOCUMENT VOLUME 5: PRICE SCHEDULE DECEMBER 2016 Middle Modi Hydropower Project (2 x 7.55

More information

INVITATION OF BID (INTERNATIONAL COMPETITIVE BIDDING)

INVITATION OF BID (INTERNATIONAL COMPETITIVE BIDDING) INVITATION OF BID (INTERNATIONAL COMPETITIVE BIDDING) Bid Title : EPC Bid for Planning, detailed design& engineering, construction/manufacturing of civil, electro-mechanical, hydro- mechanical and switch

More information

Annex 5 - Hydropower Model Vakhsh

Annex 5 - Hydropower Model Vakhsh Annex 5 - Hydropower Model Vakhsh 1. The Vakhsh Cascade The construction of dams on the Vakhsh River started in the late 1950s with the construction of the Perepadnaya diversion and power station. Until

More information

John Hart Generating Station Replacement Project. January 2018 Community Construction Update Report #55

John Hart Generating Station Replacement Project. January 2018 Community Construction Update Report #55 John Hart Generating Station Replacement Project January 2018 Community Construction Update Report #55 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

Cost Analysis for High Head SHP Projects

Cost Analysis for High Head SHP Projects 2012 International Congress on Informatics, Environment, Energy and Applications-IEEA 2012 IPCSIT vol.38 (2012) (2012) IACSIT Press, Singapore Cost Analysis for High Head SHP Projects Sachin Mishra 1,

More information

Flow measurements at two 1.4 MW units of the T.W. Sullivan Plant of Portland GeneralElectric

Flow measurements at two 1.4 MW units of the T.W. Sullivan Plant of Portland GeneralElectric Flow measurements at two 1.4 MW units of the T.W. Sullivan Plant of Portland GeneralElectric Michael Hemelstrand, P.E., Portland General Electric Portland, OR, USA and Jan Buermans, P.Eng., ASL AQFlow

More information

Seismic Design and Safety Aspects of Bottom Outlets, Spillways and Intake Structures of Large Storage Dams

Seismic Design and Safety Aspects of Bottom Outlets, Spillways and Intake Structures of Large Storage Dams Seismic Design and Safety Aspects of Bottom Outlets, Spillways and Intake Structures of Large Storage Dams Blank line 11 pt Blank line 11 pt M. Wieland Chairman, Committee on Seismic Aspects of Dam Design,

More information

Compact - Effi cient - Reliable. DIVE-Turbine An innovative turbine concept for small hydro power plants

Compact - Effi cient - Reliable. DIVE-Turbine An innovative turbine concept for small hydro power plants DIVE-Turbine An innovative turbine concept for small hydro power plants The DIVE-Turbine is an innovative turbine concept for small hydropower plants. The concept fulfills all requirements for a modern

More information

Client: Budhi Gandaki Hydroelectric Project Development Committee. General Presentation

Client: Budhi Gandaki Hydroelectric Project Development Committee. General Presentation Client: Budhi Gandaki Hydroelectric Project Development Committee General Presentation 1. Background and objectives 2. Project location 3. Project information/features 4. Project performances 5. Environmental

More information

Modern Dam Safety Concepts and Seismic Safety Aspects of Sustainable Storage Dams

Modern Dam Safety Concepts and Seismic Safety Aspects of Sustainable Storage Dams Modern Dam Safety Concepts and Seismic Safety Aspects of Sustainable Storage Dams Dr. Martin WIELAND Chairman, ICOLD Committee on Seismic Aspects of Dam Design Poyry Switzerland Ltd., Zurich, Switzerland

More information

SEES 503 SUSTAINABLE WATER RESOURCES HYDROELECTRIC POWER. Assist. Prof. Dr. Bertuğ Akıntuğ

SEES 503 SUSTAINABLE WATER RESOURCES HYDROELECTRIC POWER. Assist. Prof. Dr. Bertuğ Akıntuğ SEES 503 SUSTAINABLE WATER RESOURCES HYDROELECTRIC POWER Assist. Prof. Dr. Bertuğ Akıntuğ Civil Engineering Program Middle East Technical University Northern Cyprus Campus SEES 503 Sustainable Water Resources

More information

STANDARDS/MANUALS/ GUIDELINES FOR SMALL HYDRO DEVELOPMENT

STANDARDS/MANUALS/ GUIDELINES FOR SMALL HYDRO DEVELOPMENT STANDARDS/MANUALS/ GUIDELINES FOR SMALL HYDRO DEVELOPMENT General Works Guidelines for Layout of SHP Plants Sponsor: Ministry of New and Renewable Energy Govt. of India Lead Organization: Alternate Hydro

More information

John Hart Generating Station Replacement Project. March 2017 Community Construction Update Report #45

John Hart Generating Station Replacement Project. March 2017 Community Construction Update Report #45 John Hart Generating Station Replacement Project March 2017 Community Construction Update Report #45 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

Hoover Dam Hydropower and River Operations Electric Market Forecasting Conference. Mark Cook, PE Manager, Hoover Dam

Hoover Dam Hydropower and River Operations Electric Market Forecasting Conference. Mark Cook, PE Manager, Hoover Dam Hoover Dam Hydropower and River Operations Electric Market Forecasting Conference Mark Cook, PE Manager, Hoover Dam Hoover Dam Type of Operation Impacts of Drought Mitigating Drought Impacts through Major

More information

RÍO AMOYÁ - LA ESPERANZA Hydroelectric Power Plant

RÍO AMOYÁ - LA ESPERANZA Hydroelectric Power Plant RÍO AMOYÁ - LA ESPERANZA Hydroelectric Power Plant The power plant is located in southern Tolima, in the municipality of Chaparral, approximately 150 km from Ibague. It has an installed capacity of 80

More information

Electricity from a movable power source

Electricity from a movable power source Electricity from a movable power source The first prototypes of hydroelectric stations completely immersed in water but movable, are now in operation. Invisible and nearly without any noise emission, they

More information

Water Power. Modern plant & DAM CONSTRUCTION. New equipment at the Blue Lake Expansion Project. Serving the hydro industry for 67 years

Water Power. Modern plant & DAM CONSTRUCTION. New equipment at the Blue Lake Expansion Project. Serving the hydro industry for 67 years I N T E R N A T I O N A L Water Power & DAM CONSTRUCTION WWW.WATERPOWERMAGAZINE.COM Modern plant New equipment at the Blue Lake Expansion Project Serving the hydro industry for 67 years Uprating & refurbishment

More information

HYDROPOWER AND WATER RESOURCES

HYDROPOWER AND WATER RESOURCES HYDROPOWER AND WATER RESOURCES Shaping our world A company of D-ZM-14137-01-00 Head of Certification body OUR EXPERTISE Hydropower and Water Resources The development, planning, design, and construction

More information

USE OF WHATSAPP MOBILE APPLICATION IN PROJECT MANAGEMENT OF LARGE INFRASTRUCTURE PROJECT

USE OF WHATSAPP MOBILE APPLICATION IN PROJECT MANAGEMENT OF LARGE INFRASTRUCTURE PROJECT USE OF WHATSAPP MOBILE APPLICATION IN PROJECT MANAGEMENT OF LARGE INFRASTRUCTURE PROJECT A CASE STUDY OF 1200 MW TEESTA-III HEP, SIKKIM Abstract - The Case study brings out the use of IT application in

More information

3- Hydropower. Energy conversion and hydropower principles

3- Hydropower. Energy conversion and hydropower principles 3- Hydropower The hydraulic power is one of the oldest energy sources of the mankind, namely for irrigation and industry. Nowadays, small hydro is one of the most valuable answers to the question of how

More information

Water. Power. HYDROMATRIX

Water. Power. HYDROMATRIX Water. Power. HYDROMATRIX HYDROMATRIX An innovative way to hydropower generation Conventional HYDROMATRIX Ø 6+ m Ø 1.3+ m An array ( Matrix ) of small turbines instead of conventional sized turbines Best

More information

INSTALLATION INSTRUCTION IM 317 E

INSTALLATION INSTRUCTION IM 317 E INSTALLATION INSTRUCTION IM 317 E Device: Thermal Gas flow meter Ecoflow 3 with measuring armature E3555 and flow sensor E3510 for measurement of pressured air, nitrogen, oxygen, carbon dioxide, DN 15

More information

DRAFT SEDIMENT and EROSION CONTROL PLAN. BLUE LAKE HYDROELECTRIC PROJECT (FERC No. 2230) EXPANSION. Prepared by:

DRAFT SEDIMENT and EROSION CONTROL PLAN. BLUE LAKE HYDROELECTRIC PROJECT (FERC No. 2230) EXPANSION. Prepared by: DRAFT SEDIMENT and EROSION CONTROL PLAN BLUE LAKE HYDROELECTRIC PROJECT (FERC No. 2230) EXPANSION Prepared by: Electric Department 1.0 INTRODUCTION The Electric Department ( City ) is in the process of

More information

BRILLIANT EXPANSION PROJECT

BRILLIANT EXPANSION PROJECT BRILLIANT EXPANSION PROJECT Utilizes power tunnel 120 MW Capacity 500 GWh Energy Transmission link to Brilliant Terminal Station Will reduce TGP downstream Intake Transmission Link Transmission Link Extent

More information

MCKAYS CREEK HYDRO-ELECTRIC POWER SCHEME ENHANCEMENT FEASIBILITY AND SCOPING REPORT PREPARED FOR SCHEME RECONSENTING

MCKAYS CREEK HYDRO-ELECTRIC POWER SCHEME ENHANCEMENT FEASIBILITY AND SCOPING REPORT PREPARED FOR SCHEME RECONSENTING i MCKAYS CREEK HYDRO-ELECTRIC POWER SCHEME ENHANCEMENT FEASIBILITY AND SCOPING REPORT PREPARED FOR SCHEME RECONSENTING ii Table of contents 1 Enhancement Scope of Work 1 1.1 Introduction 1 2 McKays Intake

More information

Hydropower. See the notes in Compedu Source: Marianne KTH

Hydropower. See the notes in Compedu   Source: Marianne KTH Hydropower See the notes in Compedu http://www.energy.kth.se/compedu/webcompedu/index.html Source: Marianne Salomon @ KTH Global Renewable Energy Source: IEA Worldwide Hydropower Source: IEA Hydropower

More information

Water intake structures for hydropower

Water intake structures for hydropower Water intake structures for hydropower Dritan Bratko1, Alban Doko 1 Department of Hydraulic and Hydrotechnic, Universiteti Politeknik i Tiranes, Albania Department of Hydraulic and Hydrotechnic, Universiteti

More information

ERRATA. Energy Resource Recovery Account (ERRA) Review Of Operations, 2016 Chapters I-VII PUBLIC VERSION

ERRATA. Energy Resource Recovery Account (ERRA) Review Of Operations, 2016 Chapters I-VII PUBLIC VERSION Application No.: A.1-0-00 Exhibit No.: SCE-01 A Witnesses: T. Champ S. Lelewer T. Condit E. Lopez D. Cox M. Palmstrom S. DiBernardo M. Wallenrod S. Handschin T. Watson J. Buerkle R. Hite S. Willis ERRATA

More information

INTERNATIONAL STANDARD

INTERNATIONAL STANDARD INTERNATIONAL STANDARD IEC 62256 Edition 2.0 2017-05 colour inside Hydraulic turbines, storage pumps and pump-turbines Rehabilitation and performance improvement INTERNATIONAL ELECTROTECHNICAL COMMISSION

More information

IMPACT AND PUNCTURING OF JARI TUNNEL AND ENLARGEMENT OF EXISTING TAPPINGS FOR ADDITIONAL WATER SUPPLY AND POWER GENERATION

IMPACT AND PUNCTURING OF JARI TUNNEL AND ENLARGEMENT OF EXISTING TAPPINGS FOR ADDITIONAL WATER SUPPLY AND POWER GENERATION 117 Paper No. 738 IMPACT AND PUNCTURING OF JARI TUNNEL AND ENLARGEMENT OF EXISTING TAPPINGS FOR ADDITIONAL WATER SUPPLY AND POWER GENERATION JAVED MUNIR, SYED ABBAS ALI, IRFAN MAHMOOD 118 Javed Munir,

More information

Rehabilitation of Kidatu Power Plant Project Presentation

Rehabilitation of Kidatu Power Plant Project Presentation Rehabilitation of Kidatu Power Plant Project Presentation Norconsult The 200 MW Kidatu power plant is located on the Great Ruaha River in the region of Morogoro in central Tanzania about 280 km west of

More information

Then the revolving speed of turbine is obtained as 300 r/min based on the specific speed of Ns 208 m-kw.

Then the revolving speed of turbine is obtained as 300 r/min based on the specific speed of Ns 208 m-kw. 11.4 Electromechanical Equipment Generally, a turbine-generator is said larger unit capacity has more economical merit of scale. However, the optimum unit size of turbine-generator is determined in consideration

More information

1 Small Hydro Power Plants Wetzmann

1 Small Hydro Power Plants Wetzmann 5 th Bulgarian-Austrian Seminar SMALL DAMS AND HPP 30 March 2012, Sofia R.9 REFURBISHMENT OF TWO SMALL HYDRO POWER PLANTS IN AUSTRIA P. Tschernutter Abstract: A weir at the River Gail, which was used for

More information

Why and How: Renovation, Modernization and Uprating of Hydro Power Plants

Why and How: Renovation, Modernization and Uprating of Hydro Power Plants INDIAN INSTITUTE OF TECHNOLOGY ROORKEE Workshop on Renovation, Modernization, Uprating & Life Extension of Hydro Power Plant - Diverse Issues & Handling Strategies Dec 16, 2016 at New Delhi Why and How:

More information

Verlagspostamt: 4820 Bad Ischl P.b.b. 03Z M 14. Jahrgang 2016 INTERNATIONAL HYDRO FUTURE TECHNOLOGY HYDRO. credits: Kössler

Verlagspostamt: 4820 Bad Ischl P.b.b. 03Z M 14. Jahrgang 2016 INTERNATIONAL HYDRO FUTURE TECHNOLOGY HYDRO. credits: Kössler photo credits credits: Kössler Verlagspostamt: 4820 Bad Ischl P.b.b. 03Z035382 M 14. Jahrgang 2016 INTERNATIONAL HYDRO FUTURE TECHNOLOGY HYDRO WATER INTAKE AT SUSASCA POWER PLANT Heated screen Heated clearing

More information

John Hart Generating Station Replacement Project. January 2016 Community Construction Update Report #31

John Hart Generating Station Replacement Project. January 2016 Community Construction Update Report #31 John Hart Generating Station Replacement Project January 2016 Community Construction Update Report #31 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

Vinnie Naidoo Technical Executive GIBB (Pty) Limited South Africa

Vinnie Naidoo Technical Executive GIBB (Pty) Limited South Africa Vinnie Naidoo Technical Executive GIBB (Pty) Limited South Africa Structure of Presentation Outline of the Project Development Phases Key Attributes of the Project Environmental Considerations Scheme Layout

More information

Condition of Improvements 30 December 2014 Snettisham, Alaska (CWIS No )

Condition of Improvements 30 December 2014 Snettisham, Alaska (CWIS No ) Snettisham Condition of Improvements 30 December 2014 Snettisham, Alaska (CWIS No. 017020) Authorization Flood Control Act, 23 October 1962 (House Doc. 40, 87th Congress, 1st Session) as adopted, provides

More information

Hydraulic turbines, storage pumps and pump-turbines Rehabilitation and performance improvement

Hydraulic turbines, storage pumps and pump-turbines Rehabilitation and performance improvement IEC 62256 Edition 2.0 2017-05 REDLINE VERSION colour inside Hydraulic turbines, storage pumps and pump-turbines Rehabilitation and performance improvement INTERNATIONAL ELECTROTECHNICAL COMMISSION ICS

More information

John Hart Generating Station Replacement Project. February 2018 Community Construction Update Report #56

John Hart Generating Station Replacement Project. February 2018 Community Construction Update Report #56 John Hart Generating Station Replacement Project February 2018 Community Construction Update Report #56 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

Fossarvirkjun HPP - Iceland

Fossarvirkjun HPP - Iceland Fossarvirkjun HPP - Iceland Glasgow, 2016-11-09 PPT-Anleitung Uwe Gobbers 2012-09-09 1 Geographical Location of Fossarvirkjun The project is located in the north-western part of Iceland, in Skutulsfjörður

More information

Water. Power. HYDROMATRIX

Water. Power. HYDROMATRIX Water. Power. HYDROMATRIX HYDROMATRIX An innovative way to hydropower generation Conventional HYDROMATRIX Ø 6+ m Ø 1.3+ m An array ( Matrix ) of small turbines instead of conventional sized turbines Best

More information

Micro Hydroelectricity Installer Skills Assessment

Micro Hydroelectricity Installer Skills Assessment Micro Hydroelectricity Installer Skills Assessment Philip V. Hofmeyer August 2011 Page 1 Overview: This document contains an extensive skills assessment for renewable energy professionals who intend to

More information

Installation, Operation and Maintenance Manual

Installation, Operation and Maintenance Manual Installation, Operation and Maintenance Manual for Multipurpose Power Unit (MPPU) at Munar Prepered for TIFAC-DST Sponsored Project Development of Standard Water Mills in Uttaranchal Submitted to TIFAC

More information

consulting engineers hydropower

consulting engineers hydropower consulting engineers hydropower Glendoe, Scottish Highlands Front cover The turbine hall in the Dolgarrog Power Station, North Wales consulting engineers Sloy, Loch Lommond, Scotland KGAL acted as Principal

More information

Hydroelectric power plants

Hydroelectric power plants Hydroelectric power plants Hydroelectric power plants can drive from a water stream or accumulation reservoir. Run-of-river hydroelectric plants (those without accumulation reservoirs) built along a river

More information

Compact Hydro.

Compact Hydro. Compact Hydro www.andritz.com 02 COMPACT HYDRO ANDRITZ HYDRO Worldwide leader in hydropower business The ANDRITZ GROUP is a global market leader for customized plant, process technologies and services

More information

Suitable Applications Where concentrated flow of surface runoff must be conveyed down a slope in order to prevent erosion.

Suitable Applications Where concentrated flow of surface runoff must be conveyed down a slope in order to prevent erosion. Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective

More information

DORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Monthly Progress Report. June 2018

DORDI KHOLA HYDROPOWER PROJECT. Lamjung, Nepal. Monthly Progress Report. June 2018 DORDI KHOLA HYDROPOWER PROJECT Lamjung, Nepal Monthly Progress Report June 2018 --------------------------------------------------- Himalayan Power Partner Limited Energy Sector Research, Development &

More information

(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08

(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08 (b) Discuss in brief shaft spillway with neat sketches. Marks 04 OR Q (2) Explain in brief USBR stilling basin. Marks 08 Stilling Basins The basins are usually provided with special appurtenances including

More information

Prepared by: PacifiCorp 825 NE Multnomah Street Portland, OR 97232

Prepared by: PacifiCorp 825 NE Multnomah Street Portland, OR 97232 Wallowa Falls Hydroelectric Project (FERC No. P-308) Grande Ronde River Basin Wallowa County, Oregon June 2, 2017 Prepared by: PacifiCorp 825 NE Multnomah Street Portland, OR 97232 Table of Contents 1.0

More information

Pipelines and Penstocks Avoiding operational issues throughout the life of your project

Pipelines and Penstocks Avoiding operational issues throughout the life of your project Pipelines and Penstocks Avoiding operational issues throughout the life of your project Presenter Dan Murrer, P.E. 322 East Front Street Suite 200 Boise, ID 83702 Tel. 208.383.6108 Daniel.Murrer@CH2M.com

More information

Fast deployment of Small Hydropower

Fast deployment of Small Hydropower Fast deployment of Small Hydropower Plants in Indonesia Company with Profile smart 14.08.2013 smart the instant powerplant, 4th May 2017 Markus Straub, President Director, PT. axerna renewable energy 1.

More information

SIKA AT WORK Rrapun Hydro Power Plant (HPP), Librazhd, Albania

SIKA AT WORK Rrapun Hydro Power Plant (HPP), Librazhd, Albania SIKA AT WORK Rrapun Hydro Power Plant (HPP), Librazhd, Albania CONCRETE PRODUCTION: Sika ViscoCrete, Sika Separol, Sika Sigunit WATERPROOFING: Sika Waterbars, Sikadur -Combiflex SG, SikaSwell SEALING:

More information

2 X 8 MW Patikari Hydroelectric Project, Himachal Pradesh Annual Report. Contents. 1 About the Project Generation Data Analysis 4

2 X 8 MW Patikari Hydroelectric Project, Himachal Pradesh Annual Report. Contents. 1 About the Project Generation Data Analysis 4 2 X 8 MW Patikari Hydro Power Project Annual Plant Performance Report For the year 2017-2018 S No. Contents Title Page No. 1 About the Project 3 2 Plant Performance 4 2.1 Generation Data Analysis 4 2.2

More information

Ingula Pumped Storage Scheme: Project Management Case Study

Ingula Pumped Storage Scheme: Project Management Case Study Ingula Pumped Storage Scheme: Project Management Case Study Colin Logan Project Manager Gibb Engineering & Science South Africa BRAAMHOEK CONSULTANTS JOINT VENTURE Definition of Project Management Planning,

More information

Performance Testing of The Robert Moses Niagara Power Plant and Sir Adam Beck Generating Station

Performance Testing of The Robert Moses Niagara Power Plant and Sir Adam Beck Generating Station Performance Testing of The Robert Moses Niagara Power Plant and Sir Adam Beck Generating Station By Albert F. Mikhail, P.Eng., Ontario Power Generation and Robert J. Knowlton, P.E., New York Power Authority

More information

Sediment Erosion in Hydro Turbines

Sediment Erosion in Hydro Turbines Sediment Erosion in Hydro Turbines Hari Prasad Neopane, PhD Associate Professor & Head Department of Mechanical Engineering Kathmandu University Nepal Outline of Presentation Status of Electricity Generation

More information

Current meters and Pressure - Time flow measurement comparison

Current meters and Pressure - Time flow measurement comparison Current meters and Pressure - Time flow measurement comparison Petr ŠEVČÍK OSC, Brno, Czech Republic, sevcikp@osc.cz Robert BERNÝ Hydrometrics, Czech Republic, berny@hydrometrics.cz Grégory ROLANDEZ EDF-DTG,

More information

Darial Energy LLC. Dariali Hydro Power Plant Construction and Operation Project. Environmental and Social Action Plan, Dariali HPP

Darial Energy LLC. Dariali Hydro Power Plant Construction and Operation Project. Environmental and Social Action Plan, Dariali HPP Darial Energy LLC Dariali Hydro Power Plant Construction and Operation Project Environmental and Social Plan, Dariali HPP Tbilisi 2014 Dariali Energy JSC, the Sponsor, is planning construction and operation

More information