Risk and Safety in Engineering: Lessons from Hurricane Katrina. Byron Newberry Mechanical Engineering
|
|
- Nora Gaines
- 6 years ago
- Views:
Transcription
1 Risk and Safety in Engineering: Lessons from Hurricane Katrina Byron Newberry Mechanical Engineering
2 Is Katrina an engineering ethics issue? There was no evidence of government or contractor negligence or malfeasance the system was generally built as designed, and design approaches were consistent with local practice. IPET* Draft Final Report 1 June 2006 *Interagency Performance Evaluation Taskforce
3 Beyond the basics Not being negligent, not being malfeasant, building to design, and designing according to established practice are all basic requirements for good, ethical engineering practice, but they do not always eliminate the possibility of failure, particularly for complex systems things can go wrong even when everyone is trying to do the right things, and trying to do them well
4 Costs of Failure This event resulted in the single most costly catastrophic failure of an engineered system in history. NSF Report, July 31, 2006 ~$200 Billion in damage ~1500 dead ~450,000 displaced, 200,000 permanently
5 Advanced ethical responsibility Conscientiously striving to understand and avoid the subtle and insidious pitfalls both technological and organizational of complex systems is an ethical responsibility
6 So what are some of the pitfalls that can be identified from Katrina? Unanticipated failure modes Faulty communications: feeding back and using new information Faulty assumptions Incomplete knowledge Lack of conservatism & redundancy Changing conditions over time Risk psychology Physical interfaces and transitions Organizational interfaces and transitions Competing interests Organizational inertia Historical contingency & lock-in
7 Unanticipated failure modes
8 Unanticipated failure modes The following failure mode was not considered in the design of the canal levees, but occurred at locations along the 17 th Street and London Ave Canals Hydrostatic Pressure Gap Shear area Reduction of shear area by half
9 17 th Street Canal Failure
10 Gap on east bank of IHNC
11 Faulty Communications: feeding back and using new information Experimental tests were performed in the 1980s by the USACE on full-scale levee/sheetpile/floodwall systems. Results of the tests demonstrated the potential for a failure mode resulting from a gap developing at the outboard face of the sheet pile This information appears never to have been adequately transmitted to engineers in the field nor to have influenced design practice
12 Faulty Communications: feeding back and using new information The New Orleans Hurricane Protection System was originally designed to protect against a Standard Project Hurricane (SPH), the specifications for which were developed in the 1950s. Over the years, the SPH became the unquestioned standard for the worst case scenario, even as the details and limitations of its origin were lost from view. Enormous advances in atmospheric sciences post- 1950s were never used to adjust or improve the design specifications
13 Faulty assumptions Using average values of soil strength based on widely spaced borings over a highly variable area Assuming the soil shear strength under the levee center is a representative value, rather than the maximum that it is The SPH (standard project hurricane) the design was based upon was thought to be a once in year scenario Basing elevations off of an incorrect datum
14 Faulty assumptions: Datum Flood control structures in the region were authorized and designed relative to a water level datum (mean sea level), but constructed relative to a geodetic vertical datum incorrectly assumed to be equivalent to the water level datum. This resulted, in the case of the outfall canals, in structures built approximately 1 to 2 ft below the intended elevation. Updating of the reference elevation points for the region, although underway, was not completed and left decision makers without an accurate understanding of the actual elevations of the hurricane protection.
15 Incomplete knowledge The science of analyzing storms and predicting their behavior has improved dramatically since the design and construction of the New Orleans hurricane protection system (HPS) was first initiated. The understanding of interrelationships of river systems, wetlands, barrier islands, flooding, and storms has improved dramatically Improved engineering design/analysis tools techniques (soil testing, structures, hydrology, etc.)
16 Lack of redundancy Series system One part fails, the system fails The central concept of [the Dutch] strategy is the controlled flooding of compartments of limited size, thus limiting the affected area and minimising the flood damage. It means designating areas for temporary water storage and dividing the existing large continuous dike-rings (areas surrounded by a dike) into smaller compartments with different flood probabilities. Vis, Klijn, de Bruijn, van Buuren, Int. J. River Basin Management, 2003
17 Lack of conservatism Low margins of safety used despite magnitude of risk Typical levee factor of safety: 1.3 Design practice historically evolving out of levee construction in rural areas, agricultural land not intended for, and never modified for, protection of large populations/high value developments Not in line with factors of safety required for dam construction
18 Lack of priority Plaquemines Parish Pop: ~27,000
19 Changing conditions over time Physical Land subsidence Coastal erosion Societal Continual development of low lying areas Increase in population and property improvements Changing political and economic factors affecting project Flood control isn t just a series of construction projects; rather it has to be a continuous process of adapting to changing conditions
20 Risk psychology After the fact of Hurricane Katrina The group faulted the agency responsible for the levees, the Army Corps of Engineers, for adopting safety standards that were "too close to the margin" to protect human life. Well before Hurricane Katrina Orleans Levee District officials believed that the Corps standards may be too high They recommended the Corps lower its design standards This, they believe would make the project more affordable, provide adequate protection, and speed project completion 1982 GAO report In several instances, State agencies pressured for 'lower cost' solutions not realizing that these solutions would result in lowering the overall quality and reliability The more one invests in mitigation, the less one is likely to continue to invest because of a decrease in negative feedback.
21 Physical interfaces and transitions Physical transitions between types of barriers (e.g., levee with I-wall transitionin g to bare levee)
22 Physical interfaces and transitions Interfaces between barriers and other infrastructure (railways and roadways)
23 Organizational interfaces and transitions USACE design and construction of levees Local Levee Districts operation and maintenance of the levees New Orleans Water and Sewerage pumping stations and outflow canals Various other entities (railroad companies, DOT, etc) at specific locations/penetrations
24 Competing interests The original design the barrier plan called for barriers at the inlets to Lake Pontchartrain to prevent storm surges from entering lake. The corps proposed butterfly valves at the outlets of the drainage canals at Lake Pontchartrain, to prevent storm surges entering city. This plan was abandoned after years of litigation. The Water and Sewerage Board defeated the plan politically because of questionable concerns about the impact on their operations
25 Competing interests The USACE had tried for many years to obtain authorization to install floodgates at the north ends of the three drainage canals Dysfunctional interaction between the local Levee Board (who were responsible for levees and floodwalls, etc.) and the local Water and Sewerage Board (who were responsible for pumping water from the city via the drainage canals) prevented the installation of these gates, however, and as a result many miles of the sides of these three canals had instead to be lined with levees and floodwalls.
26 Organizational inertia & bureaucracy complacency & funding Various articles presciently predicted the results of Katrina years in advance. The Corps knew of subsidence problems, improved storm forecasting, etc., for years Comprehensive plans to mitigate problems with the entire coastal Louisiana region were developed (e.g., Coast 2050)
27 Organizational inertia & bureaucracy complacency & funding The northeast flank of the St. Bernard/Ninth Ward basin s protecting ring of levees and floodwalls was incomplete at the time of Katrina s arrival. The critical 11 mile long levee section fronting Lake Borgne was being constructed in stages, and funding appropriation for the final stage had long been requested by the U.S. Army Corps of Engineers (USACE), but this did not arrive before Katrina struck For many years, the Corps of Engineers has been subjected to extreme pressures at the federal and state levels to do more with less; to do their projects better, faster, and cheaper
28 Organizational inertia & bureaucracy complacency & funding intrinsic risk associated with over-long project durations for these types of massive, regional scale projects. Also that both White House and Congressional attention lapsed, and funds that could have been provided to complete these important levees were instead deferred, as issues elsewhere drew more urgent attention.
29 Organizational inertia & bureaucracy complacency & funding Splash protection on backside of floodwalls low cost fail-safe measure in case of overtopping ( estimated at less than 5% of the overall project section cost ) The USACE were instructed by Congressional edict to design for a specified water level, and to install splash pads would be to provide for a higher level than that which had been authorized.
30 Historical contingency & lock-in Levee system developed piecemeal over 200 years new solutions tend to be extensions of old ones. Storm protection is a locked-in problem for New Orleans. River control is a locked-in problem for New Orleans.
31 Historical contingency & lock-in Old River Control Structure
COASTAL RESILIENCE SYMPOSIUM Mathijs van Ledden & Maarten Kluyver (Haskoning Inc.)
HURRICANE RISK REDUCTION PROGRAM NEW ORLEANS STRUCTURAL SOLUTIONS AND RESILIENCE Mathijs van Ledden Royal Haskoning COASTAL RESILIENCE SYMPOSIUM Mathijs van Ledden & Maarten Kluyver (Haskoning Inc.) HOUSTON
More informationNEW ORLEANS DISTRICT AND THE AND THE
SYSTEM SYSTE NEW ORLEANS DISTRICT PROTECTIO TIO N AND THE AND THE PROTE H U RRI CA N E September 25, 2007 National Environmental Policy Act NEPA Required for all major federal actions Analyze potential
More informationMike Park HPS Program Manager Task Force Hope and. Tim Black Deputy Chief of Contracing New Orleans District U.S. Army Corps of Engineers
Contracting Experiences from Task Force Hope by Mike Park HPS Program Manager Task Force Hope and Tim Black Deputy Chief of Contracing New Orleans District U.S. Army Corps of Engineers February 20, 2009
More informationFrom Disaster to Success: The Cycle of Generational Change in U.S. Levee Engineering Practice. Dr. Raymond Seed U. C. Berkeley
From Disaster to Success: The Cycle of Generational Change in U.S. Levee Engineering Practice Dr. Raymond Seed U. C. Berkeley Evolution of the California CVFPS Massive and repeated flooding in the 1800
More informationEast Jefferson Levee District Status Report April 2008
East Jefferson Levee District LPV 27 26 East Jefferson Levee District Status Report April 2008 The hurricane protection levee system is divided into five Reaches along Lake Pontchartrain, plus the East
More informationSTRUCTURAL PLAN COMPONENT APPENDIX
LOUISIANA COASTAL PROTECTION AND RESTORATION FINAL TECHNICAL REPORT STRUCTURAL PLAN COMPONENT APPENDIX June 2009 U. S. Army Corps of Engineers New Orleans District Mississippi Valley Division Table of
More informationENGINEERING AND CONSTRUCTION BULLETIN
ENGINEERING AND CONSTRUCTION BULLETIN No. 2010-20 Issuing Office: CECW-CE Issued: 7 Sep 2010 Expires: 7 Sep 2012 Subject: Learning Opportunities in New Orleans and Southeast Louisiana Applicability: Information
More informationLMNED-HC 1 October Lake Pontchartrain, Louisiana and Vicinity Hurricane Protection Project - Model Study, Request for Authorization
DEPARTMENT OF T~E ARMY NEW ORLEANS DISTRICT. CORPS OF ENGINEERS,., O. 1I0k 110267 N.W OftL.AN., LOUI.IANA 70160 REPl Y TO ATTENTION OF;. LMNED-HC Commander, Lower Mississippi Valley Division ATTN: LMVED-WH
More informationResilient Water and Wastewater Systems
Resilient Water and Wastewater Systems June 2017 Ryan Berni Deputy Mayor City of New Orleans Patrick Schultz Principal & General Manager, Resource Optimization Veolia New Orleans A challenging delta landscape
More informationSewerage and Water Board of New Orleans Restoration of Water and Wastewater Systems
Sewerage and Water Board of New Orleans Restoration of Water and Wastewater Systems Sarah K. Mack New Orleans, Louisiana, USA Restoration of Water and Wastewater Sewerage and Water Board of New Orleans
More informationImplications of Sea Level Rise: Case Study on the East Land Bridge Ben C. Gerwick, Inc.
Implications of Sea Level Rise: Case Study on the East Land Bridge Ben C. Gerwick, Inc. 1 APRIL 16, 2013 COWI POWERPOINT PRESENTATION SLR Contributions to 2004 NOAA 2012 Global Sea Level Rise Scenarios
More informationInteragency Performance Evaluation Task (IPET) Force. Engineering and Operational Risk and Reliability Analysis. Robert C. Patev
Interagency Performance Evaluation Task (IPET) Force Engineering and Operational Risk and Reliability Analysis Robert C. Patev Deputy and Technical Lead, IPET Risk and Reliability Team IPET Risk Assessment
More informationSummary of Field Observations Relevant to Flood Protection in New Orleans, LA
Summary of Field Observations Relevant to Flood Protection in New Orleans, LA Interim report to Task Force Guardian by the Interagency Performance Evaluation Task Force 5 December, 2005 Table of Contents
More informationDeveloping a Texas Preferred Ike Dike/Coastal Spine
Developing a Texas Preferred Ike Dike/Coastal Spine Planning Environment Time All truth passes through three stages. First, it is ridiculed. Second, it is violently opposed. Third, it is accepted as being
More informationVirginia Beach Comprehensive Sea Level Rise and Recurrent Flooding Planning Study
1 Virginia Beach Comprehensive Sea Level Rise and Recurrent Flooding Planning Study Policy Recommendations and City-wide Flood Protection Strategies January 15, 2019 2 Agenda Project Overview Hazards and
More informationCITY OF NORFOLK COASTAL STORM RISK MANAGEMENT STUDY
1 CITY OF NORFOLK COASTAL STORM RISK MANAGEMENT STUDY 255 255 255 File Name 237 237 237 217 217 217 200 200 200 0 0 0 163 163 163 131 132 122 239 65 53 80 119 27 252 174.59 110 135 120 112 92 56 62 102
More informationPerformance Evaluation of the New Orleans and Southeast Louisiana Hurricane Protection System
Performance Evaluation of the New Orleans and Southeast Louisiana Hurricane Protection System Final Report of the Interagency Performance Evaluation Task Force Volume VI The Performance Interior Drainage
More informationEast St. Tammany Storm Surge Protection Project Request
East St. Tammany Storm Surge Protection Project Request Submitted to Coastal Protection & Restoration Authority of Louisiana (CPRA) August 2015 Contact Information: Thomas Nolan Thompson The East St. Tammany
More informationEverglades Restoration Climate Program
Sea Level Change and Long Range Water Resources Planning for Florida Everglades Restoration Climate Program Change Application Concerns of USACE and Guidance Draft Sea Level on Sea Rise Level Planning
More informationP.O Box 6965 Metairie, LA SaveOurLake.org
P.O Box 6965 Metairie, LA. 70009-6965 - SaveOurLake.org A Post-Katrina Assessment of the Bonnet Carré Spillway in South Louisiana: The Bonnet Carré Spillway Wetland Restoration Project Summary In 2008,
More informationSea Level Rise Impacts on Municipal Stormwater Systems in Hampton Roads
VIRGINIA D.C. MARYLAND CHAPTER Sea Level Rise Impacts on Municipal Stormwater Systems in Hampton Roads Presentation at the APWA Mid-Atlantic Chapter May Regional Conference Virginia Beach, Virginia May
More informationFINAL INDIVIDUAL ENVIRONMENTAL REPORT GOVERNMENT FURNISHED BORROW MATERIAL #4 PLAQUEMINES, ST. BERNARD, AND JEFFERSON PARISHES, LOUISIANA IER #28
FINAL INDIVIDUAL ENVIRONMENTAL REPORT GOVERNMENT FURNISHED BORROW MATERIAL #4 PLAQUEMINES, ST. BERNARD, AND JEFFERSON PARISHES, LOUISIANA IER #28 JULY 2008 TABLE OF CONTENTS TITLE PAGE 1. INTRODUCTION...
More informationSewerage and Water Board of New Orleans Strategic Plan
Sewerage and Water Board of New Orleans Strategic Plan 2011-2020 Mission, Vision, and Values Our mission is to provide safe drinking water to everyone in New Orleans; to remove waste water for safe return
More informationSea Level Rise: Impacts, Adaptation and Information Gaps
University of New Orleans ScholarWorks@UNO Coastal Resilience Workshop Coastal Resilience Workshop 2015 Oct 28th, 10:00 AM - 12:00 PM Sea Level Rise: Impacts, Adaptation and Information Gaps Jeffrey R.
More informationAtlantic Coast of New York East Rockaway Inlet to Rockaway Inlet and Jamaica Bay, NY
Atlantic Coast of New York East Rockaway Inlet to Rockaway Inlet and Jamaica Bay, NY Draft Reformulation Public Information October 2016 US Army Corps of Engineers Presentation Outline Project Overview
More informationCoastal Restoration and Protection Projects - SLFPA-East and Vicinity
Coastal Restoration and Protection Projects - SLFPA-East and Vicinity committed to our coast committed to our coast 2012 Master Plan Project Details 2012 Master Plan Projects in SLFPA-East Projects in
More informationBackground on New Orleans and the Sewerage and Water Board of New Orleans
Hurricane Katrina s Impact on New Orleans Water System: How the System Was Restored and the Lessons Learned Presented to: 2008 American Public Works Association International Public Works Congress & Exposition
More informationPhysical & Program Options for Inland Migration of Louisiana s Coastal Wetlands
Physical & Program Options for Inland Migration of Louisiana s Coastal Wetlands Melissa Kemm & Sam Pardo Duke University Nicholas School of the Environment Client: Louisiana Coastal Protection & Restoration
More informationThe newly updated and comprehensive SWMP shall:
RFQ SCOPE OF SERVICES 2.1 Project Purpose The City of Miami, ( City ) is seeking professional engineering services from a qualified firm for the purpose of planning and developing a newly updated and comprehensive
More informationREGIONAL CONSIDERATIONS FOR LACPR AND MSCIP APPENDIX
LOUISIANA COASTAL PROTECTION AND RESTORATION FINAL TECHNICAL REPORT REGIONAL CONSIDERATIONS FOR LACPR AND MSCIP APPENDIX June 2009 U. S. Army Corps of Engineers New Orleans District Mississippi Valley
More informationThe 9th Disaster Risk Management Seminar
The 9th Disaster Risk Management Seminar "Integrated Urban Flood Risk Management: Obstacles and Opportunities in East Asia-Pacific and Lessons from Japan" INSTITUTIONAL FRAMEWORK, CHALLENGES IN VIETNAM
More informationRoles and Responsibilities of Rijkwaterstaat. Eric Boessenkool
Roles and Responsibilities of Rijkwaterstaat Eric Boessenkool Topics Welcome to the Ministry of Infrastructure and the Environment historical development, current works and projects Deltaprogramme European
More informationWater Management Under Severe Storm Conditions in Central and South Florida
Water Management Under Severe Storm Conditions in Central and South Florida Chandra S. S. Pathak, Ph.D., P.E. Severe Storm Prediction and Global Climate Impact in the Gulf Coast Conference October 29 to
More informationFinal Independent External Peer Review Report Hurricane and Storm Damage Risk Reduction System Design Elevation Report
Final Independent External Peer Review Report Hurricane and Storm Damage Risk Reduction System Design Elevation Report Prepared by Battelle Memorial Institute Prepared for Department of the Army U.S. Army
More informationHIGH PERFORMANCE LEVEE SOLUTIONS
HIGH PERFORMANCE LEVEE SOLUTIONS ARMORING LEVEES FOR RESILIENCY AND PROTECTION In August 2005, Hurricane Katrina made landfall near New Orleans, Louisiana, bombarding the greater metro area with a storm
More informationOverview of USACE Civil Works Climate Preparedness and Resilience and Challenges with Recurring Flood Damage in Virginia
Overview of USACE Civil Works Climate Preparedness and Resilience and Challenges with Recurring Flood Damage in Virginia Michelle Hamor Chief, Flood Plain Management Services Section USACE, Norfolk District
More informationPublic Meeting Summary
Public Meeting Summary Individual Environmental Report (IER) #27 Outfall Canal Remediation Public Meeting September 16, 2010 Location Holy Trinity Greek Orthodox Cathedral Time Open House 6 p.m.- 6:30
More informationMEMORANDUM FOR ASSISTANT SECRETARY OF THE ARMY (CIVIL WORKS)
REPLY TO ATTENTION OF DEPARTMENT OF THE ARMY u.s. ARMY CORPS OF ENGINEERS 441 G STREET, NW WASHINGTON, DC 20314-1000 APR 6 2010 CECW-MVD MEMORANDUM FOR ASSISTANT SECRETARY OF THE ARMY (CIVIL WORKS) SUBJECT:
More informationGENERAL OVERVIEW MEETING JANUARY 10, 2019
Upper Barataria Basin Coastal Storm Risk Management and The Amite River and Tributaries-Comprehensive Study East of the Mississippi River, Louisiana Feasibility Studies GENERAL OVERVIEW MEETING JANUARY
More informationThe Corps is performing additional evaluation of the I-walls along the 17 th, Orleans and London outfall canals to address the 2011 ETL.
http://publications.usace.army.mil/publications/eng-techltrs/etl 1110-2-575/ETL 1110-2-575.pdf The Corps is performing additional evaluation of the I-walls along the 17 th, Orleans and London outfall canals
More informationWEST SHORE LAKE PONTCHARTRAIN HURRICANE AND STORM DAMAGE RISK REDUCTION STUDY INTEGRATED DRAFT FEASIBILITY REPORT AND ENVIRONMENTAL IMPACT STATEMENT
WEST SHORE LAKE PONTCHARTRAIN HURRICANE AND STORM DAMAGE RISK REDUCTION STUDY INTEGRATED DRAFT FEASIBILITY REPORT AND ENVIRONMENTAL IMPACT STATEMENT PLAN FORMULATION APPENDIX E 1 Contents Introduction...
More information2015 HDR, Inc., all rights reserved.
2015 HDR, Inc., all rights reserved. Sandy Raises the Yards Permitting Raises the NEPA Bar MTA-NYCT 207th St Yard Flood Mitigation / Resiliency Project Environmental Railroad Conference November 1-2, 2016
More informationMISSISSIPPI RIVER AND TRIBUTARIES PROJECT
MISSISSIPPI RIVER AND TRIBUTARIES PROJECT 1 237 237 237 217 217 217 200 200 200 80 119 27 252 174.59 255 255 255 0 0 0 163 163 163 131 132 122 239 65 53 110 135 120 112 92 56 62 102 130 102 56 48 130 120
More informationOn The Gulf: Coastlines In Danger*
On The Gulf: Coastlines In Danger* Subject: Physical Science Grades: 9-12 Duration: Two class periods Lesson Plan Sections Objectives Students will Research how the environment of the Mississippi Delta
More informationNew Jersey Back Bays Coastal Storm Risk Management Feasibility Study. Ocean and Burlington Counties Mayor s Meeting Toms River, NJ June 19, 2018
New Jersey Back Bays Coastal Storm Risk Management Feasibility Study Ocean and Burlington Counties Mayor s Meeting Toms River, NJ June 19, 2018 1 State of New Jersey Shore Protection Program State of New
More informationEnsuring Public Safety by Investing in Our Nation s Critical Dams and Levees. Keith Miller, Kristina Costa, and Donna Cooper September 2012
THE ASSOCIATED PRESS/Charlie Riedel Ensuring Public Safety by Investing in Our Nation s Critical Dams and Levees Keith Miller, Kristina Costa, and Donna Cooper September 2012 www.americanprogress.org Introduction
More informationRESTORE Act Planning. Kyle Graham Executive Director CPRA. November 12, committed to our coast
RESTORE Act Planning Kyle Graham Executive Director CPRA November 12, 2014 committed to our coast committed to our coast Oil Spill Funds Allocated to Date NRDA - Early Restoration Project Name Basin Funded
More informationTime and the River: Coastal Restoration as Climate Change Denial
Time and the River: Coastal Restoration as Climate Change Denial Edward P. Richards, JD, MPH Director, Program in Law, Science, and Public Health Clarence W. Edwards Professor of Law LSU Law School richards@lsu.edu
More informationManaging Reservoirs for Atmospheric Rivers The Uneven Balance of Flood Risk and Water Supply
Managing Reservoirs for Atmospheric Rivers The Uneven Balance of Flood Risk and Water Supply Larry Schick Water Management Seattle District 2016 International Atmospheric River Conference Scripps Institute
More informationCHAPTER 3. PLANNING BASIC: LAND USE PLANNING AND ZONING
CHAPTER 3. PLANNING Communities use planning to direct development and public projects and ensure their land use regulations (zoning) meet the community s needs. When done correctly, planning can prevent
More informationNational Planning Center for Coastal Storm Risk Management. U.S. Army Corps of Engineers. 8 April US Army Corps of Engineers BUILDING STRONG
North Atlantic Coast Comprehensive Study Draft Analyses Webinar: Sea Level Rise and Climate Change Adaptation Planning U.S. Army Corps of Engineers National Planning Center for Coastal Storm Risk Management
More informationU.S. Army Corps of Engineers Broward County Planning Assistance to States. Flood Risk Management Study for Tidally Influenced Coastal Areas
U.S. Army Corps of Engineers Broward County Planning Assistance to States Flood Risk Management Study for Tidally Influenced Coastal Areas Initial Stakeholder Resiliency Meeting Wednesday, November 9,
More informationVia October Mr. William Neal, P.E. Technological Specialist DTE Electric Company One Energy Plaza Detroit, MI 48226
17 October 2016 134 N. La Salle Street, Suite 300 Chicago, Illinois 60602 PH 312.658.0500 FAX 312.658.0576 www.geosyntec.com Via Email Mr. William Neal, P.E. Technological Specialist DTE Electric Company
More informationA DUTCH PERSPECTIVE ON COASTAL LOUISIANA FLOOD RISK REDUCTION AND LANDSCAPE STABILIZATION. Final Report
A DUTCH PERSPECTIVE ON COASTAL LOUISIANA FLOOD RISK REDUCTION AND LANDSCAPE STABILIZATION Final Report Prepared for: United States Army EUROPEAN RESEARCH OFFICE OF THE U.S. ARMY London, England A DUTCH
More informationNEW JERSEY BACK BAYS COASTAL STORM RISK MANAGEMENT INTERIM FEASIBILITY STUDY AND ENVIRONMENTAL SCOPING DOCUMENT. Executive Summary 1 March 2019
NEW JERSEY BACK BAYS COASTAL STORM RISK MANAGEMENT INTERIM FEASIBILITY STUDY AND ENVIRONMENTAL SCOPING DOCUMENT Executive Summary 1 March 2019 Document Overview This U.S. Army Corps of Engineers (USACE)
More informationU.S. ARMY CORPS OF ENGINEERS NEW ORLEANS DISTRICT
U.S. ARMY CORPS OF ENGINEERS NEW ORLEANS DISTRICT Lock Replacement Project Cellular Cofferdam Feasibility Study GEOTECHNICAL ADDENDUM DESIGN REPORT 18 November 16 (Intentionally left blank) i TABLE OF
More informationStorm Surge Mitigation: Status and Questions. Scott A. Jones Director of Advocacy Galveston Bay Foundation
Storm Surge Mitigation: Status and Questions Scott A. Jones Director of Advocacy Galveston Bay Foundation Galveston Bay Foundation Mission: To preserve, protect, and enhance the natural resources of Galveston
More informationSoutheast Louisiana Flood Protection Authority - East Levee Safety Permit Policy. Revised November 17, 2017
Southeast Louisiana Flood Protection Authority - East Levee Safety Permit Policy Revised November 17, 2017 A. Background. Levee districts and Flood Authorities, as sponsors of most federally authorized
More informationAppendix G.1 Cost Estimation
Appendix G.1 Cost Estimation Cost Estimation Methodology Due to the large study area and vast array of measures analyzed, cost estimates employed standardization and simplification techniques to ensure
More informationBriefing to Elected Officials
Passaic River Main Stem Flood Risk Management Project Preliminary Alternative Analysis Report Briefing to Elected Officials Bob Martin Commissioner New Jersey Department of Environmental Protection COL
More informationCHAPTER TEN: ENGINEERING OVERVIEW; EARTHEN LEVEES AND FLOODWALLS
CHAPTER TEN: ENGINEERING OVERVIEW; EARTHEN LEVEES AND FLOODWALLS 10.1. Overview The vast majority of flood protection for the greater New Orleans area is strongly dependent upon the presence and ability
More informationFinal Independent External Peer Review Report for the Hurricane and Storm Damage Risk Reduction System Design Elevation Report Addendum
Final Independent External Peer Review Report for the Hurricane and Storm Damage Risk Reduction System Design Elevation Report Addendum Prepared by Battelle Memorial Institute Prepared for Department of
More informationNew techniques for the rapid repair of levee breaches
Flood Recovery, Innovation and Response II 85 New techniques for the rapid repair of levee breaches S. J. Boc, D. T. Resio & E. C. Burg US Army Corps of Engineers, Engineer Research and Development Center,
More informationChapter A-13 STRUCTURAL ANALYSIS ARGENTINE RAISE
Kansas Citys, Missouri and Kansas Flood Damage Reduction Feasibility Study (Section 216 Review of Completed Civil Works Projects) Engineering Appendix to the Interim Feasibility Report Chapter A-13 STRUCTURAL
More informationPUBLIC NOTICE REQUEST FOR PERMISSION TO ALTER A U.S. ARMY CORPS OF ENGINEERS PROJECT PURSUANT TO 33 U.S.C. SECTION 408
DEPARTMENT OF THE ARMY CORPS OF ENGINEERS, NEW ORLEANS DISTRICT 7400 LEAKE AVENUE NEW ORLEANS, LOUISIANA 70118 REPLY TO ATTENTION OF Regional Planning and Environmental Division South Environmental Compliance
More informationLOUISIANA COASTAL PROTECTION AND RESTORATION (LACPR) FINAL TECHNICAL REPORT
LOUISIANA COASTAL PROTECTION AND RESTORATION (LACPR) FINAL TECHNICAL REPORT June 2009 U. S. Army Corps of Engineers New Orleans District Mississippi Valley Division Table of Contents Louisiana Coastal
More informationSURREY COASTAL FLOOD ADAPTATION STRATEGY (CFAS) General Phase 1 Workshop Presentation (February 3 through March 8, 2017)
SURREY COASTAL FLOOD ADAPTATION STRATEGY (CFAS) General Phase 1 Workshop Presentation (February 3 through March 8, 2017) Agenda Introductions and Overview Project Overview Activity 1 Hazards BREAK Activity
More informationTimothy D. Willadsen. Project Manager U.S. Army Corps of Engineers Jacksonville District January US Army Corps of Engineers BUILDING STRONG
HERBERT HOOVER DIKE REHABILITATION TION PROJECT Timothy D. Willadsen Project Manager U.S. Army Corps of Engineers Jacksonville District January 2016 Trusted Partners Delivering ering Value, Today and Tomorrow
More informationEffects of Climate Change on Transportation
Effects of Climate Change on Transportation Preparing for Change Sustainable Transportation in a Changing Environment New Jersey DOT January 8, 2009 presented by Joanne Potter Cambridge Systematics, Inc.
More informationEverglades Restoration Goals
Everglades Restoration Goals Restore natural hydrologic conditions in the remaining 50% of historic Everglades Water quantity, quality, timing and distribution Maintain existing services in developed areas
More informationSea Level Rise and Subsidence Issues and the Coastal Northern Gulf
Sea Level Rise and Subsidence Issues and the Coastal Northern Gulf 1897 The effects of the withholding by the levees from the great areas of the delta of the annual contribution of sedimentary matters
More informationThinking Outside the Box Culvert Eco Systems Marketing Workshop
Thinking Outside the Box Culvert Eco Systems Marketing Workshop DAVID FOWLER, CFM MILWAUKEE METROPOLITAN SEWERAGE DISTRICT ASSOCIATION OF STATE FLOODPLAIN MANGERS December 12, 2012 Floodplain Managers
More informationPW/Engineering. June 20, 2013
PW/Engineering June 20, 2013 1 Three Questions Why is the Eastern Shore Drive Drainage Area Experiencing Recurrent Flooding? What can be done about it? What is being done? Comprehensively On an Interim
More informationPUBLIC INFORMATION MEETING Rahway River Basin Flood Risk Management Feasibility Study
PUBLIC INFORMATION MEETING Rahway River Basin Flood Risk Management Feasibility Study COL Paul E. Owen District Engineer U.S. Army Corps of Engineers New York District New Jersey Department of Environmental
More informationAchieving the Philosophy of GOMA Through MsCIP
Achieving the Philosophy of GOMA Through MsCIP 4 th National Conference on Ecosystem Restoration August 3, 2011 The Spirit of Cooperation Integrating Partnerships for Sustainable Ecosystem Restoration
More informationThe Mississippi River & Tributaries Project
Following the Great Mississippi River Flood of 1927, the nation galvanized in its support for a comprehensive and unified system of public works within the lower Mississippi Valley that would provide enhanced
More informationTOWN OF RHINEBECK RESOLUTION
TOWN OF RHINEBECK RESOLUTION 2018197 REQUESTING AN ETENSION OF THE SCOPING COMMENT PERIOD WITH ADDITIONAL PUBLIC INFORMATION AND SCOPING MEETINGS, FOR THE NY/NJ HARBOR & TRIBUTARIES COASTAL STORM RISK
More informationDAM SAFETY Chena River Lakes Flood Control Project U.S. Army Corps of Engineers, Alaska District
DAM SAFETY Chena River Lakes Flood Control Project U.S. Army Corps of Engineers, Alaska District COL Reinhard Koenig, PE Commander, USACE Alaska District Patricia S. Opheen, PE Chief, Engineering Division
More informationSACRAMENTO SUPPLEMENTAL PROJECTS OVERVIEW
1 SACRAMENTO SUPPLEMENTAL PROJECTS OVERVIEW 131 132 122 8 119 27 252 174.59 11 135 12 112 92 56 CAMERON SESSIONS SUPPLEMENTAL PROGRAM MANAGER 239 65 53 18 October 218 - American River Common Features WRDA
More informationTexas Water Resources Institute
Texas Water Resources Institute May/June 1985 Volume 11 No. 3 Stopping the Sinking By RIC JENSEN Staff Writer, TWRI The notion that some parts of Houston may be sinking is a harsh reality. Some unique
More informationSOUTHEAST FLORIDA S RESILIENT WATER RESOURCES INCLUDING A CASE STUDY FOR THE CITY OF POMPANO BEACH
SOUTHEAST FLORIDA S RESILIENT WATER RESOURCES INCLUDING A CASE STUDY FOR THE CITY OF POMPANO BEACH SOUTHEAST FLORIDA S WATER INFRASTRUCTURE IS VULNERABLE TO CLIMATE CHANGE THE WATER INFRASTRUCTURE IN FLORIDA
More informationSabine Pass to Galveston Bay, TX, Coastal Storm Risk Management and Ecosystem Restoration Feasibility Study
Sabine Pass to Galveston Bay, TX, Coastal Storm Risk Management and Ecosystem Restoration Feasibility Study Public Comment Meetings October 6, 2015 Beaumont, TX October 8, 2015 Freeport, TX Sharon Tirpak,
More informationMay 4, Applicant: Lake Charles Harbor and Terminal District 150 Marine Street Lake Charles, Louisiana 70602
2011 Environmental Excellence Award Application May 4, 2011 Applicant: Lake Charles Harbor and Terminal District 150 Marine Street Lake Charles, Louisiana 70602 Contact: Mr. Channing Hayden, Jr. Director
More informationSabine Pass to Galveston Bay, TX, Coastal Storm Risk Management and Ecosystem Restoration Feasibility Study
Sabine Pass to Galveston Bay, TX, Coastal Storm Risk Management and Ecosystem Restoration Feasibility Study Public Comment Meetings October 6, 2015 Beaumont, TX October 8, 2015 Freeport, TX Sharon Tirpak,
More informationDam Safety & Planning: Examples of Collaboration and Lessons Learned
US Army Corps of Engineers PLANNING SMART BUILDING STRONG Dam Safety & Planning: Examples of Collaboration and Lessons Learned Eric Halpin, P.E. Special Assistant for Dam & Levee Safety, HQUSACE Maria
More informationDesign and Construction of the Lake Borgne Surge Barrier in Response to Hurricane Katrina
Design and Construction of the Lake Borgne Surge Barrier in Response to Hurricane Katrina Scott R. Huntsman, Ph.D., P.E., G.E., D.GE., CPESC, CPSWQ, QSD, F.ASCE 1 1 Shaw Environmental & Infrastructure
More informationClimate Change Adaptation Strategies for Infrastructure Managers
Climate Change Adaptation Strategies for Infrastructure Managers Green Streets and Highways Conference November 17, 2010 Butch Wlaschin Office of Asset Management Federal Highway Administration U.S. Department
More informationClimate Adaptation & Disaster Risk Reduction Building Coastal Resilience
Climate Adaptation & Disaster Risk Reduction Building Coastal Resilience Dr. Michael Beck & Dr. Borja Reguero The Nature Conservancy & Univ. of California Santa Cruz www.nature.org & www.coastalresilience.org
More informationIntegrated flood modelling and mitigation analysis 8 th Australasian Natural Hazards Management Conference (ANHMC2015)
Integrated flood modelling and mitigation analysis 8 th Australasian Natural Hazards Management Conference (ANHMC2015) Raymond Cohen Mahesh Prakash James Hilton Yunze Wang Fletcher Woolard 3:45-4:15pm
More informationFlood Risk Management on the Elwha: Case Study of the Federal Levee Modification Project
Flood Risk Management on the Elwha: Case Study of the Federal Levee Modification Project US Army Corps of Engineers Zac Corum, PE, Hydraulic Engineer Travis Ball, PE, CFM, Hydraulic Engineer Seattle District
More informationUSACE LEVEE AND DAM SAFETY PROGRAM AND ISSUES
USACE LEVEE AND DAM SAFETY PROGRAM AND ISSUES 237 237 237 217 217 217 200 200 200 80 119 27 252 174.59 1 255 255 255 0 0 0 163 163 163 131 132 122 239 65 53 110 135 120 112 92 56 62 102 130 102 56 48 130
More informationP R O G R E S S R E P O R T P R O G R E S S R E P O R T R E S T O R A T I O N
THE R E S T O R A T I O N March, 2012 PAGE 1 Pontchartrain Levee District Board of Commissioners Steven C. Wilson, President Michael Delaune, Vice President 2204 Albert Street Post Office Box 426 Lutcher,
More informationClimate Change and Sea Level Rise Planning and Adaptation Strategies
Climate Change and Sea Level Rise Planning and Adaptation Strategies Kim Shugar Department Director Intergovernmental Programs Palm Beach County EAR Workshop 4/29/10 Jayantha Obeysekera (Obey) Department
More informationWork Group Discussion Guidance
Infrastructure Work Group Discussion Guidance Lead Work Group Member: Agency or Department: Additional Departments/Organizations Identified Please list any contact information for the departments or organizations
More informationGas Guzzlers. Biological Pump
Gas Guzzlers Biological Pump Aquatic Biodiversity Chapter 8 Coral Reefs Open Ocean Deep Sea Marine equivalent of tropical rain forests Habitats for one-fourth of all marine species Coral polyps, which
More informationWetland Losses and Human Impacts
Wetland Losses and Human Impacts Matthew J. Gray University of Tennessee Distribution of North American Wetlands Peatlands of Alaska and Canada Hudson and James Bay Wetlands Prairie Potholes Great Lakes
More informationIndependent Engineering Assessment of the New Orleans Temporary Outflow Canal Pumps
Independent Engineering Assessment of the New Orleans Temporary Outflow Canal Pumps Prepared by Contract No. GS-00F-0005R Parsons Project No. 746558 February 27, 2009 This report was prepared for the Department
More informationUnderstanding Energy: Emergency Preparedness for Nuclear in the US
Understanding Energy: Emergency Preparedness for Nuclear in the US Kimberly Cook, General Manager, Plant Operations Waterford 3 Nuclear Facility Novenber 16, 2011 Tsunami Initiates Nuclear On March 11
More informationMaine Water Conference
Using GIS to bring Superstorm Sandy to Maine: Updating Maine s Hurricane Surge Maps Maine Water Conference April 1, 2014 Rachael E. Dye, Peter A. Slovinsky, Christian H. Halsted Maine Geological Survey
More informationWetland Policy In Vermont and Louisiana. Litsey Corona and Emily Karwat
Wetland Policy In Vermont and Louisiana Litsey Corona and Emily Karwat What is a wetland? An area inundated by surface or groundwater with a frequency sufficient to support plants and animals that depend
More information