WATERCOURSE CROSSINGS HYDROTECHNICAL ASSESSMENT & DESIGN RECOMMENDATIONS Liege Lateral Loop No. 2 Pelican Lake Section

Size: px
Start display at page:

Download "WATERCOURSE CROSSINGS HYDROTECHNICAL ASSESSMENT & DESIGN RECOMMENDATIONS Liege Lateral Loop No. 2 Pelican Lake Section"

Transcription

1 WATERCOURSE CROSSINGS HYDROTECHNICAL ASSESSMENT & DESIGN RECOMMENDATIONS Liege Lateral Loop No. 2 Pelican Lake Section Note: Sub Vendor supplied data January 28, 2016 Page 1 of 22

2 LIEGE LATERAL LOOP NO. 2 PELICAN LAKE SECTION WATERCOURSE CROSSINGS HYDROTECHNICAL ASSESSMENT AND DESIGN RECOMMENDATIONS Sub Supplier Data Report Prepared for: HATCH MOTT MACDONALD Prepared by: MATRIX SOLUTIONS INC. November 2015 Edmonton, Alberta 142, 6325 Gateway Boulevard NW Edmonton, Alberta, Canada T6H 5H6 Phone: Fax: PEL18181-HMM-A-DB-0002 January 28, 2016 Page 2 of 22

3 LIEGE LATERAL LOOP NO.2 PELICAN LAKE SECTION WATERCOURSE CROSSINGS HYDROTECHNICAL ASSESSMENT AND DESIGN RECOMMENDATIONS Report prepared for Hatch Mott MacDonald, November 2015 Pamela Rogers, M.Eng., P.Eng. Water Resources Engineer November 9, 2015 reviewed by Brandyn Coates, M.Eng., P.Eng. Environmental Engineer November 9, 2015 reviewed by Manas Shome, Ph.D., P.Eng. Principal, Water Resources Engineer November 9, 2015 DISCLAIMER We certify that this report is accurate and complete and accords with the information available. Information obtained during the preparation of this report or provided by third parties is believed to be accurate but is not guaranteed. We have exercised reasonable skill, care and diligence in assessing the information obtained during the preparation of this report. This report was prepared for Hatch Mott MacDonald. The report may not be relied upon by any other person or entity without our written consent and that of Hatch Mott MacDonald. Any uses of this report by a third party, or any reliance on decisions made based on it, are the responsibility of that party. We are not responsible for damages or injuries incurred by any third party, as a result of decisions made or actions taken based on this report. January 28, 2016 Page 3 of 22

4 TABLE OF CONTENTS 1 INTRODUCTION Objectives and Scope of Work DESIGN CRITERIA DESIGN METHODS Hydrologic and Hydraulic Analysis Morphologic Analysis Scour Depth Analysis CROSSING DESCRIPTION Loon Creek (WC3) Unnamed Tributary to Athabasca River (WC5) Unnamed Tributary to Livock River (WC6) Livock River (WC7) HYDROLOGY AND HYDROTECHNICAL ASSESSMENT DESIGN RECOMMENDATIONS Loon Creek (WC3) Unnamed Tributary to Athabasca River (WC5) Unnamed Tributary to Livock River (WC6) Livock River (WC7) ADDITIONAL CONSIDERATIONS REFERENCES... 9 January 28, 2016 Page 4 of 22

5 FIGURES FIGURE 1 FIGURE 2 FIGURE 3 FIGURE 4 FIGURE 5 FIGURE 6 FIGURE 7 FIGURE 8 FIGURE 9 FIGURE 10 FIGURE 11 FIGURE 12 FIGURE 13 FIGURE 14 FIGURE 15 FIGURE 16 FIGURE 17 Watercourse Crossings Pipeline Route Location Plan WC3 Loon Creek NW W4M Site Photographs WC3 Loon Creek NW W4M Location Plan WC5 Unnamed Tributary to Athabasca River SE W4M Site Photographs WC5, Unnamed Tributary to Athabasca River SE W4M Location Plan WC6 Unnamed Tributary to Livock River NE W4M Site Photographs WC6 Unnamed Tributary to Livock River NE W4M Location Plan WC7 Livock River SW W4M Site Photographs WC7 Livock River SW W4M Hydrologic Analysis Results WC3 Loon Creek Hydrologic Analysis Results WC5 Unnamed Tributary to Athabasca River Hydrologic Analysis Results WC6 Unnamed Tributary to Livock River Hydrologic Analysis Results WC7 Livock River Creek Profile, Cross-Section and Pipeline Design Details WC3, Loon Creek Creek Profile, Cross-Section and Pipeline Design Details WC5, Unnamed Tributary to Athabasca River Creek Profile, Cross-Section and Pipeline Design Details WC6, Unnamed Tributary to Livock River Creek Profile, Cross-Section and Pipeline Design Details WC7, Livock River LIST OF TABLES TABLE 1 Pipeline Watercourse Crossing Summary... 1 TABLE 2 Hydrologic and Hydrotechnical Assessment Results... 6 January 28, 2016 Page 5 of 22

6 1 INTRODUCTION Hatch Mott MacDonald (HMM) contracted Matrix Solutions Inc. to provide hydrotechnical assessment and design support related to watercourse crossings as part of TransCanada PipeLines Limited s Liege Lateral Loop No. 2 Pelican Lake Section pipeline project near Fort McMurray, Alberta. The proposed pipeline will run from the existing Buffalo Creek Compressor Station located at SW W4M to the existing Pelican Lake Compressor Station located at NE W4M. The proposed 760 mm diameter (NPS 30) pipeline will transport natural gas. The proposed pipeline will cross several watercourses, as shown on Figure 1. Detailed hydrotechnical analysis and design for crossings WC1 (Boivin Creek), WC2 (Athabasca River), and WC4 (Unnamed Tributary to Loon Creek) will be addressed in a separate report. The detailed hydrotechnical analysis and design for the remaining four crossings, WC3 (Loon Creek), WC5 (Unnamed Tributary to Athabasca River), WC6 (Unnamed Tributary to Livock River), and WC7 (Livock River), are discussed herein. 1.1 Objectives and Scope of Work TransCanada is proposing an open-cut method to install the pipeline beneath the watercourses listed below in Table 1. The objectives of this assessment were to determine the burial depth below the river bed to minimize the risks of pipeline exposure due to potential scour or channel migration over the pipeline s life and to recommend preliminary design burial requirements for the pipeline crossing. TABLE 1 Pipeline Watercourse Crossing Summary Survey Crossing ID Watercourse Legal Location Latitude (m) NAD 83 ATS 4.1 Longitude (m) WC3 Loon Creek NW W4M 56 13'28.09"N '42.33"W WC5 Unnamed Tributary to Athabasca River SE W4M 56 23'43.13"N '7.84"W WC6 Unnamed Tributary to Livock River NE W4M 56 25'44.68"N '58.34"W WC7 Livock River SW W4M 56 27'4.39"N '31.21"W Matrix s scope of work for the project included the following: reviewing the proposed pipeline route and verifying the watercourse crossing locations conducting hydrologic analyses to estimate peak flows and understand the flood history at the crossings reviewing background information to assess existing channel and floodplain characteristics, identifying potential constraints, and assessing potential for erosion and channel migration comparing historical aerial photographs to evaluate channel morphology and stability completing hydraulic and scour calculations and providing design recommendations, including cover depths, sagbend setbacks, and erosion protection measures, if required, for the pipeline at the proposed watercourse crossing locations January 28, 2016 Page 6 of 22

7 preparing a report summarizing the results of the hydrotechnical assessment and design recommendations for the pipeline at the proposed watercourse crossing locations The hydrotechnical design presented in this report is based upon the following: the proposed pipeline route provided by HMM on June 9, 2015 (Peters 2015, Pers. Comm.) the Code of Practice for Pipelines and Telecommunication Lines Crossing a Water Body (COP; ESRD 2013) the Pipeline Associated Watercourse Crossings (CAPP et al. 2005) 1:50,000 scale National Topographic System (NTS) mapping streamflow data from Water Survey of Canada (WSC) monitoring stations (WSC 2014) an aquatic assessment completed by TERA Environmental Consultants (2015) survey data provided to Matrix by WSP Canada Inc. on September 18 and 22, 2015 (Peters 2015, Pers. Comm.) 2 DESIGN CRITERIA The following criteria were used for the hydrotechnical design of the pipeline at the proposed crossing locations: Design flow is the 1:100-year instantaneous peak flow as per the COP requirement for a pipeline crossing a watercourse (ESRD 2013). The potential total scour depth was estimated by combining the computed general scour and local scour, as appropriate. Maximum allowable elevation of the top of the pipe was determined from the existing minimum bed elevation and the potential scour depth. Burial depth for a pipeline crossing a watercourse is defined as the vertical distance between the existing minimum bed level (thalweg) and the elevation of the top of the pipe. The minimum cover depth will be 1.8 m or the computed total scour depth, whichever is greater. Sagbend setbacks at the pipeline watercourse crossings were calculated using the Alberta Environment and Parks equation to compute setback (Sb) distance for sand-bed streams (NOVA 1991): Sb = 0.34B 2/3 where B is the top width of the watercourse January 28, 2016 Page 7 of 22

8 A minimum sagbend setback of 1 m from the top of the banks is to be applied at the crossings. Based on the consideration of historical air photograph comparisons, channel sinuosity, the sagbend equation described above, and the field assessment, a farther setback may be required. Sagbend setback recommendations are based upon defining the potential for bank migration during the life of the pipeline. The bank stability and construction method are also considered in establishing the sagbend locations. Final setback distances are typically based on professional experience and judgment. 3 DESIGN METHODS The following methods were used to establish the design recommendations for burial depth and sagbend distances at each pipeline crossing site. 3.1 Hydrologic and Hydraulic Analysis Hydrologic analyses included estimating peak flows, monthly flows, and flow duration curves at the crossing locations. Regional hydrologic analysis or a Single Station Transfer method is typically used to estimate flows at an ungauged location. For these crossing locations, the latter method was used since a hydrometric gauging station is located on the House River in a watershed similar to that of the crossing sites. WSC Station 07CB002 is located on the House River at Highway 63 with a drainage area of 780 km 2 and data spanning 1982 to The estimated extreme peak flows for a range of return periods and flow statistics at gauging station 07CB002 were transposed to each crossing location using a ratio of the drainage area at each crossing and the WSC station. Peak flows associated with various return periods were estimated by conducting a frequency analysis of the instantaneous peak flows at WSC Station 07CB002. Missing instantaneous flow data were estimated through regression analysis of recorded maximum daily flow data and corresponding instantaneous flow data. Flood frequency analysis was conducted using HYFRAN-Plus (2007) software to determine the best fit statistical distribution (e.g., Gamma, Pearson, or Logarithmic). The design water levels corresponding to 1:100-year flood at the crossing sites were calculated using the slope-area method with the Manning equation. Channel profiles and cross-sections were developed using survey data provided by HMM. The roughness characteristics of the main channel and its floodplain areas were estimated based on the field observations and using professional judgment following the guidelines provided in Chow (1959). The potential for ice and debris jams to form at the crossing needs to be considered in the hydrotechnical design of the crossing. January 28, 2016 Page 8 of 22

9 3.2 Morphologic Analysis Potential long-term bank erosion and channel changes that could affect the crossing were estimated based on the field assessment and general experience for the watercourses in the area. The findings of this assessment were used to determine the horizontal extent of the burial depth below the watercourses, the sagbend setback, and any erosion protection requirements. Sagbend setback distances may be extended farther back from the top of the banks based upon potential for bank erosion and channel migration. 3.3 Scour Depth Analysis The potential scour depth was calculated at each crossing during the 1:100-year design flood. These estimates were used to determine the minimum burial depth of the pipeline and assist in defining setback locations. Total scour depth consists of general scour (i.e., the overall lowering of the channel bed during flooding) and local scour (i.e., scour due to secondary currents generated at channel bends, confluences, or obstructions). The general scour at the crossing location was estimated based on the bankfull or maximum confirmed flood level using the Blench (1969) regime theory and graphs developed from rivers with gravel beds in Alberta (ASME 2008). A channel shape factor (Z) was then estimated from a graph for free eroding bends (ASME 2008) and professional judgment based upon site-specific channel conditions. The maximum local scour typically occurs at the outside of the channel bend or at a channel confluence and may be much larger than general scour. Information on bed material size is required to estimate the scour depth. The median bed material size at each crossing was selected based on information provided in the aquatic assessment report (TERA 2015). 4 CROSSING DESCRIPTION Site characteristics at each crossing site were established by reviewing the findings of site assessments, photographs provided by HMM, and historical aerial photographs. 4.1 Loon Creek (WC3) Loon Creek flows east at Crossing WC3 (referred to as crossing 83-WC-02 by WSP) and joins the Athabasca River about 15 km downstream (Figure 2). Site photographs collected in October 2015 were provided to Matrix by HMM and are presented on Figure 3. Loon Creek meanders through a deep valley approximately 200 m wide and 20 m deep at the top of the crossing. The surrounding land is vegetated with shrubs, grasses, and trees. Sharp meander bends are located immediately upstream and downstream of the proposed crossing location and an active beaver dam was located 20 m downstream of the right-of-way. The drainage area of the watercourse at the proposed crossing location is 260 km 2. January 28, 2016 Page 9 of 22

10 The channel has a longitudinal slope of about 0.26%, as estimated from the surveyed profile. The channel top width at the crossing site is about 8.0 m and the bankfull depth is about 1.0 m. The channel bed is composed of fine-grained material with traces of gravel. The banks are composed of fine-grained material with erosion apparent along both banks at the crossing location (Figure 3, Photos 1 and 2). The channel banks rise gently from the banks edges and are vegetated with shrubs, grasses, and trees. 4.2 Unnamed Tributary to Athabasca River (WC5) This Unnamed Tributary flows northeast at Crossing WC5 (referred to as crossing 85-WC-01 by WSP) and joins the Athabasca River about 9 km downstream (Figure 4). Site photographs collected in October 2015 were provided to Matrix by HMM and are presented on Figure 5. The unnamed creek meanders through a deep valley approximately 180 m wide and 20 m deep at the top of the crossing. The surrounding land is vegetated with shrubs, grasses, and trees. Sharp meander bends are located immediately upstream and downstream of the proposed crossing location and an active beaver dam was located 20 m downstream of the right-of-way. At the time of assessment, the area surrounding the crossing location was flooded due to the presence of beaver dams. The drainage area of the watercourse at the proposed crossing location is 88 km 2. The channel has a longitudinal slope of about 0.57%, as estimated from the surveyed profile. The main channel splits into two channels at the proposed crossing location. The north channel top width at the crossing site is about 6.8 m wide and the bankfull depth is about 0.5 m; the south channel top width at the crossing site is about 6.0 m and the bankfull depth is about 1.0 m. The channel bed is composed of fine-grained material with trace gravel and cobble. The banks are composed of a fine-grained material with erosion apparent along the left bank at the crossing location. Large woody debris and instream vegetation were present throughout the crossing reach. The channel banks rise gently from the banks edges and are vegetated with shrubs, grasses, and trees. 4.3 Unnamed Tributary to Livock River (WC6) This Unnamed Tributary flows east at Crossing WC6 (referred to as crossing 86-WC-01 by WSP) and enters the Athabasca River, 10 km downstream (Figure 6). Site photographs collected in October 2015 were provided to Matrix by HMM and are presented on Figure 7. The unnamed creek meanders through a large floodplain area that is vegetated with grasses and trees. Beaver activity is present through the crossing reach with an old beaver dam located 50 m upstream. The drainage area of the watercourse at the proposed crossing location is 11 km 2. The channel has a longitudinal slope of about 0.66%, as estimated from the surveyed profile. The channel top width at the crossing site is about 1.3 m and the bankfull depth is about 0.5 m. The channel bed is composed of fine-grained material with trace gravel; instream vegetation was present throughout the crossing reach. The channel banks are soft and composed of fine-grained and organic material. January 28, 2016 Page 10 of 22

11 4.4 Livock River (WC7) Livock River flows northeast at Crossing WC7 (referred to as crossing 86-WC-02 by WSP) and joins the Athabasca River 11 km downstream (Figure 8). Site photographs collected in October 2015 were provided to Matrix by HMM and are presented on Figure 9. Livock River meanders through a 120 m wide valley that is 15 m deep at the top of the banks at crossing. The surrounding land is vegetated with shrubs, grasses, and trees. Sharp meander bends are located throughout the crossing reach and beaver dams are located 90 m upstream and 200 m downstream of the proposed crossing location. The drainage area of the watercourse at the proposed crossing location is 66 km 2. The channel has a longitudinal slope of about 0.5%, as estimated from the surveyed profile. The channel top width at the crossing site is about 8.0 m and the bankfull depth is about 0.5 m. The channel bed is primarily composed of fine-grained material with trace gravel and cobble. The banks are composed of fine-grained material with unstable sections and erosion apparent throughout. The channel banks rise gently from the banks edges and are vegetated with shrubs, grasses, and trees. Large woody debris was present in the channel throughout the crossing reach. 5 HYDROLOGY AND HYDROTECHNICAL ASSESSMENT The results of the flow frequency analysis and the estimated flow statistics, including minimum, maximum, and mean monthly flows, and flow duration curves at each of the crossing locations are illustrated on Figures 10 (WC3), Figure 11 (WC5), Figure 12 (WC6), and Figure 13 (WC7). The hydrologic and hydrotechnical analysis results for each crossing are summarized in Table 2 below. TABLE 2 Hydrologic and Hydrotechnical Assessment Results Crossing Drainage Area (km 2 ) 1:100 Year Flood Magnitude (m 3 /s) Manning Roughness Coefficient (n) 1:100 Year Water Level (m asl) Channel Slope (%) D 50 (mm) Channel Shape Factor (Z) Estimated Scour Depth (m below channel bed) WC WC WC WC The derived monthly flow statistics and flow duration curves provide information for selecting an appropriate water management method and developing a risk management strategy during construction. The highest monthly flows at the crossing occur between May and August, so instream construction is not recommended during this period. The monthly flow duration curves show the monthly variation of flow with a given exceedance probability. For example, a flow of 3 m 3 /s or higher can be expected 20% of the January 28, 2016 Page 11 of 22

12 time in July (Figure 10). Monthly data was not available from WSC Station 07CB002 for November through February, though seasonally low flows are to be expected during this period. There is significant potential for debris jams to form at all four crossing locations, which could cause local scour. Also, the maximum potential scour at Crossings WC3, WC5, and WC7 could potentially occur due to the development and washout of beaver dams located near the crossing location. In addition to the estimated scour depth at the four crossing sites, there is potential for long-term bed degradation due to downcutting over the lifetime of the pipeline. Therefore, an additional allowance for downcutting was considered in the hydrotechnical design. 6 DESIGN RECOMMENDATIONS The design recommendations are based solely on river engineering considerations. A deeper pipe profile may be required for non-hydrotechnical reasons considering site-specific subsurface conditions and construction installation requirements for the proposed crossing. 6.1 Loon Creek (WC3) Based on the site conditions and calculated scour depth, and due in part to the potential for channel degradation following washout of the beaver dam, a cover depth of 3.1 m below the bed of the channel is recommended at Crossing WC3. The proposed minimum cover depth corresponds to a maximum top-of-pipe elevation of m, as shown on Figure 14. Based on the morphologic assessment, signs of erosion were observed on both banks. Therefore, greater sagbend setbacks are recommended to account for potential erosion at the banks. The pipe should remain horizontal with a maximum top elevation of m between Stations 0+226S and 0+240N, as shown on Figure 14. These setback distances correspond to the anticipated extents of the 1:100-year water level. The recommended setback distances assume restoration grading and stable native vegetation on the channel banks. 6.2 Unnamed Tributary to Athabasca River (WC5) Based on the site conditions and calculated scour depth, and in accordance with the TransCanada typical design cover depth, a cover depth of 2.2 m below the bed of the channel is recommended at Crossing WC5. The proposed minimum cover depth corresponds to a maximum top-of-pipe elevation of m, as shown on Figure 15. Based on the morphologic assessment, signs of erosion were observed on the left bank. Therefore, greater sagbend setbacks are recommended to account for potential erosion at the banks. The pipe should remain horizontal with a maximum top elevation of m between Stations 0+158S and 0+179N, as shown on Figure 15. The recommended setback distances assume restoration grading and stable native vegetation on the valley walls. January 28, 2016 Page 12 of 22

13 6.3 Unnamed Tributary to Livock River (WC6) Based on the site conditions and calculated scour depth, and due in part to the potential for channel degradation following washout of the beaver dam, a cover depth of 1.8 m below the bed of the channel is recommended at Crossing WC6. The proposed minimum cover depth corresponds to a maximum top-of-pipe elevation of m, as shown on Figure 16. Based on the morphologic assessment, the banks appear to be stable at the crossing location. Therefore, the pipe should remain horizontal with a maximum top elevation of m between Stations S and N, as shown on Figure 16. The recommended setback distances assume restoration grading and stable native vegetation on the channel banks. 6.4 Livock River (WC7) Based on the site conditions and calculated scour depth, and due in part to the potential for channel degradation following washout of the beaver dam, a cover depth of 1.8 m below the bed of the channel is recommended at Crossing WC7. The proposed minimum cover depth corresponds to a maximum top-of-pipe elevation of m, as shown on Figure 17. Based on the morphological assessment, the banks through the crossing reach appear to be unstable with erosion observed throughout. Therefore, the pipe should remain horizontal with a maximum top elevation of m between Stations 0+168SE and 0+184NW, as shown on Figure 17. The recommended setback distances assume restoration grading and stable native vegetation on the channel banks. 7 ADDITIONAL CONSIDERATIONS The detailed engineering and construction phase of the crossing should consider operation and maintenance at the crossing, and include a river monitoring program to monitor potential channel changes, specifically after high flows. Should significant changes to the channel cross-section at the crossing location occur before construction, the crossing design should be reviewed by a river engineer. All regulatory requirements should be in place before construction, and an erosion and sediment control plan should be in place during construction. A suitable construction period should be verified considering all environmental requirements. Mean flows at the crossing are expected to be lowest between October and March, so construction during these months would be best. Based on the river width and expected flows, an open-cut method could be suitable during frozen conditions. Flow isolation may be required if construction occurs in non-frozen conditions. January 28, 2016 Page 13 of 22

14 Disturbance of the bed and banks should be kept to a minimum and confined as much as possible to the immediate crossing areas. Final grading should be similar to the undisturbed channel bed and banks, and all of the disturbed areas should be vegetated as soon as possible after construction. 8 REFERENCES Alberta Environment and Sustainable Resource Development (ESRD) Code of Practice for Pipelines and Telecommunication Lines Crossing a Water Body. Made under the Water Act and the Water (Ministerial) Regulation. Consolidated to include amendments in force as of June 24, Queen s Printer. Edmonton, Alberta. American Society of Mechanical Engineers (ASME) Pipeline Geo-Environmental Design and Geohazard Management. ISBN No Blench T Mobile Bed Fluviology. The University of Alberta Press. Edmonton, Alberta. Canadian Association of Petroleum Producers (CAPP), Canadian Energy Pipeline Association (CEPA), and Canadian Gas Association (CGA) Pipeline Associated Watercourse Crossings, Third Edition. Prepared by TERA Environmental Consultants and Salmo Consulting Inc. Calgary, Alberta. October Chow V.T Open-Channel Hydraulics. McGraw-Hill Inc. HYFRAN-Plus Software HYFRAN-PLUS (Version 1.2). Software for Windows. Developed by INRS-EAU with Hydro-Quebec. NOVA Corp. and NOVA Corp. International (NOVA) River Crossing Design Manual. March Peters Brianna (2015), Project Engineer, Hatch Mott MacDonald. TERA Environmental Consultants (TERA) Aquatic Technical Report for the Proposed Nova Gas Transmission Ltd NGTL System Expansion. Technical report prepared for TransCanada Pipelines Limited. Calgary, Alberta. March Water Survey of Canada (WSC) Hydrometric Data. Accessed on June 4, January 28, 2016 Page 14 of 22

15 NOVA Gas Transmission Ltd NGTL System Expansion Project January 28, 2016 Attachment NEB PEL18181-HMM-A-DB-0002 Page 15 of 22

16 January 28, 2016 PEL18181-HMM-A-DB-0002 Page 16 of 22

17 January 28, 2016 PEL18181-HMM-A-DB-0002 Page 17 of 22

18 January 28, 2016 PEL18181-HMM-A-DB-0002 Page 18 of 22

19 January 28, 2016 PEL18181-HMM-A-DB-0002 Page 19 of 22

20 January 28, 2016 PEL18181-HMM-A-DB-0002 Page 20 of 22

21 January 28, 2016 PEL18181-HMM-A-DB-0002 Page 21 of 22

22 January 28, 2016 PEL18181-HMM-A-DB-0002 Page 22 of 22

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS WATER RESOURCES MANAGEMENT DIVISION Water Investigations Section

More information

Hydrotechnical Design Guidelines for Stream Crossings

Hydrotechnical Design Guidelines for Stream Crossings Hydrotechnical Design Guidelines for Stream Crossings Introduction Design of stream crossings and other in-stream highway facilities requires estimation of design highwater elevation and mean channel velocity.

More information

Mill Creek Restoration in Lower Merion Township. PH (610) ; FAX (610) ;

Mill Creek Restoration in Lower Merion Township. PH (610) ; FAX (610) ; Mill Creek Restoration in Lower Merion Township Vincent L. Sortman 1 and Robert M. Lambert 2 1 Biohabitats, Inc., 15 W. Aylesbury Road, Timonium, MD 21093; PH (410) 337-3659; FAX (410) 583-5678; email:

More information

CITY OF KIMBERLEY HYDROLOGICAL & HYDRAULIC ASSESSMENT

CITY OF KIMBERLEY HYDROLOGICAL & HYDRAULIC ASSESSMENT HYDROLOGICAL & HYDRAULIC ASSESSMENT ISSUED FOR USE January 31, 2012 FILE: 2011-015 LACAS CONSULTANTS INC. CONSULTING ENGINEERS & HYDROLOGICAL SPECIALISTS, SINCE 1991 Suite 200, 1311 Howe Street, Vancouver,

More information

nhc MILLENNIUM EMS SOLUTIONS LTD. HYDROLOGY ASSESSMENT FOR GRIZZLY OIL SANDS ALGAR LAKE SAGD PROJECT FINAL REPORT JANUARY, 2010

nhc MILLENNIUM EMS SOLUTIONS LTD. HYDROLOGY ASSESSMENT FOR GRIZZLY OIL SANDS ALGAR LAKE SAGD PROJECT FINAL REPORT JANUARY, 2010 MILLENNIUM EMS SOLUTIONS LTD. HYDROLOGY ASSESSMENT FOR GRIZZLY OIL SANDS ALGAR LAKE SAGD PROJECT FINAL REPORT JANUARY, 2010 nhc northwest hydraulic consultants Leaders in water resource technology HYDROLOGY

More information

Old Mill School Stream Restoration

Old Mill School Stream Restoration Project Overview This conceptual plan restores and stabilizes two consecutive reaches of a highly incised and unstable stream and reconnects them with the floodplain. The restoration reaches are part of

More information

Code of Practice for Pipelines and Telecommunication Lines Crossing A Water Body

Code of Practice for Pipelines and Telecommunication Lines Crossing A Water Body Code of Practice for Pipelines and Telecommunication Lines Crossing A Water Body Effective April 1, 2000 Water Act Water (Ministerial) Regulation Office Consolidation Consolidated to include amendment

More information

Fort McKay Specific Assessment

Fort McKay Specific Assessment SURFACE WATER HYDROLOGY Fort McKay Specific Assessment Fort McKay Industry Relations Corporation March 2010 Contents 4.0... 1 4.1 Fort McKay s Key Concerns Related to Surface Water... 1 4.2 Fort McKay

More information

FISH COLLECTION PERMIT SUMMARY REPORT FOR PERMIT NO.: CB

FISH COLLECTION PERMIT SUMMARY REPORT FOR PERMIT NO.: CB North/South Consultants Inc. 440, 1121 Centre St. NW Calgary, Alberta T2E 7K6 Tel: (403) 410-4068 Fax: (403) 410-5633 Email: cfazakas@nscons.ca Web: www.nscons.ca FISH COLLECTION PERMIT SUMMARY REPORT

More information

SHEEP RIVER AT 128 TH STREET FLOOD HAZARD RISKS AND REVIEW OF MITIGATION OPTIONS

SHEEP RIVER AT 128 TH STREET FLOOD HAZARD RISKS AND REVIEW OF MITIGATION OPTIONS SHEEP RIVER AT 128 TH STREET FLOOD HAZARD RISKS AND REVIEW OF MITIGATION OPTIONS Submitted to: Municipal District of Foothills No. 31 Calgary, Alberta Submitted by: Calgary, Alberta CW2167.SHEEP is committed

More information

PROJECT SCREENING MATRIX: A User s Guide

PROJECT SCREENING MATRIX: A User s Guide Version 2.0 Page 1 of 7 November 9, 2010 PROJECT SCREENING MATRIX: A User s Guide BACKGROUND The Project Screening Matrix (Screening Matrix) is one of several tools that comprise the River Restoration

More information

ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975. Source: Hey and Associates, Inc.

ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975. Source: Hey and Associates, Inc. ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975 Source: Hey and Associates, Inc. DEFINITION A bridge or culvert crossing installed across a stream or watercourse for short-term

More information

Context of Extreme Alberta Floods

Context of Extreme Alberta Floods Context of Extreme Alberta Floods Introduction Design of water management and stream crossing infrastructure requires determination of hydrotechnical design parameters. These parameters often consist of

More information

UNDERGROUND UTILITY CROSSING (TRENCHLESS) General Submission Requirements

UNDERGROUND UTILITY CROSSING (TRENCHLESS) General Submission Requirements COMPLETE APPLICATION CHECKLIST Jan 2016 UNDERGROUND UTILITY CROSSING (TRENCHLESS) The following checklist has been compiled to assist the applicant in preparing their application for approval pursuant

More information

Review of the Fisheries Act 23 DECEMBER 2016 PREPARED BY: THE CANADIAN ENERGY PIPELINE ASSOCIATION

Review of the Fisheries Act 23 DECEMBER 2016 PREPARED BY: THE CANADIAN ENERGY PIPELINE ASSOCIATION Review of the Fisheries Act 23 DECEMBER 2016 PREPARED BY: THE CANADIAN ENERGY PIPELINE ASSOCIATION 1 Contents Introduction 3 Delegation to the NEB 3 Assessments and regulatory guidance 4 Provincial requirements

More information

Code of Practice for Watercourse Crossing

Code of Practice for Watercourse Crossing Code of Practice for Watercourse Crossing Water Act Water (Ministerial) Regulation Consolidated to include amendment of 2001/03/16 and in force as of 2001/04/01, and amendment of 2003/07/29 in force as

More information

Prepared for: City of Jeffersonville. November Prepared by

Prepared for: City of Jeffersonville. November Prepared by JEFFERSONVILLE STORMWATER MASTER PLAN HYDRAULICS APPENDIX JEFFERSONVILLE, INDIANA Prepared for: City of Jeffersonville November 2011 Prepared by Christopher B. Burke Engineering, Ltd. 115 W. Washington

More information

GUIDE TO THE CODE OF PRACTICE FOR WATERCOURSE CROSSINGS, INCLUDING GUIDELINES FOR COMPLYING WITH THE CODE OF PRACTICE

GUIDE TO THE CODE OF PRACTICE FOR WATERCOURSE CROSSINGS, INCLUDING GUIDELINES FOR COMPLYING WITH THE CODE OF PRACTICE GUIDE TO THE CODE OF PRACTICE FOR WATERCOURSE CROSSINGS, INCLUDING GUIDELINES FOR COMPLYING WITH THE CODE OF PRACTICE May 2000 Revised April 2001 TABLE OF CONTENTS Page 1. Introduction 3 2. Topics in the

More information

STREAMBANK STABILIZATION: POST CONSTRUCTION MITIGATION MONITORING REPORT (YEAR 4 OF

STREAMBANK STABILIZATION: POST CONSTRUCTION MITIGATION MONITORING REPORT (YEAR 4 OF STREAMBANK STABILIZATION: POST CONSTRUCTION MITIGATION MONITORING REPORT (YEAR 4 OF 5) July 2008 Contract Number PG3525173 CABIN BRANCH POTOMAC CROSSING CONSULTANTS TABLE OF CONTENTS Executive Summary...

More information

Rascal Goose. Reach 1. Rascal Goose. Reach 2. å å å. Main Goose Pit. Stream Reach 3. Main Goose Pit. Stream Reach 7

Rascal Goose. Reach 1. Rascal Goose. Reach 2. å å å. Main Goose Pit. Stream Reach 3. Main Goose Pit. Stream Reach 7 434000 March 16 2014 434200 434400 ± 434600 434800 435000 Goose Lake 7269800 WRSA B 7269800 7270000 433800 GIS # BAC-06-180a 7270000 PROJECT # 0234411-0005 Rascal Goose Reach 1 Main Goose Pit Stream Reach

More information

Stream Simulation in Very Low Gradient Channels

Stream Simulation in Very Low Gradient Channels University of Massachusetts - Amherst ScholarWorks@UMass Amherst International Conference on Engineering and Ecohydrology for Fish Passage International Conference on Engineering and Ecohydrology for Fish

More information

Temporary Watercourse Crossing: Fords

Temporary Watercourse Crossing: Fords Temporary Watercourse Crossing: Fords DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]

More information

Case Study 1 Red Clover Rock Ford

Case Study 1 Red Clover Rock Ford Case Study Red Clover Rock Ford Location Northeastern California. Plumas National Forest. An unnamed tributary to Red Clover Creek in McReynolds Valley, 5 miles north of Lake Davis, CA. Forest Road 25N05,

More information

Stream Restoration Raccoon Creek A Case Study

Stream Restoration Raccoon Creek A Case Study Stream Restoration Raccoon Creek A Case Study Restoration of a Degraded Stream System Steven Glickauf Presentation Overview Stream Restoration Raccoon Creek Restoration Site Case Study Existing Conditions

More information

Hydrometric Data Review for 3 Sites Upstream of Okotoks, Alberta

Hydrometric Data Review for 3 Sites Upstream of Okotoks, Alberta Prepared for AMEC Foster Wheeler Hydrometric Data Review for 3 Sites Upstream of Okotoks, Alberta 05BL012 Sheep River at Okotoks 05BL013 Three Point Creek at Millarville 05BL014 Sheep River at Black Diamond

More information

FORM B: DAMMING AND DIVERSION OF WATER

FORM B: DAMMING AND DIVERSION OF WATER APPLICATION FOR RESOURCE CONSENT FORM B: DAMMING AND DIVERSION OF WATER NOTES Resource use activities must meet all the conditions of any relevant Permitted Activity Rules in the Waikato Regional Plan

More information

ICELANDIC RIVER / WASHOW BAY CREEK INTEGRATED WATERSHED MANAGEMENT PLAN STATE OF THE WATERSHED REPORT CONTRIBUTION SURFACE WATER HYDROLOGY REPORT

ICELANDIC RIVER / WASHOW BAY CREEK INTEGRATED WATERSHED MANAGEMENT PLAN STATE OF THE WATERSHED REPORT CONTRIBUTION SURFACE WATER HYDROLOGY REPORT ICELANDIC RIVER / WASHOW BAY CREEK INTEGRATED WATERSHED MANAGEMENT PLAN STATE OF THE WATERSHED REPORT CONTRIBUTION SURFACE WATER HYDROLOGY REPORT Disclaimer: The hydrologic conditions presented in this

More information

River reach characterization: a survey strategy for river regime and environmental monitoring and analysis

River reach characterization: a survey strategy for river regime and environmental monitoring and analysis Erosion and Sediment Transport Monitoring Programmes in River Basins (Proceedings of the Oslo Symposium, August 1992). IAHS Publ. no. 210, 1992. 363 River reach characterization: a survey strategy for

More information

CREEK RESTORATION/EROSION PROTECTION WORKS. General Submission Requirements

CREEK RESTORATION/EROSION PROTECTION WORKS. General Submission Requirements COMPLETE APPLICATION CHECKLIST Jan 2016 CREEK RESTORATION/EROSION PROTECTION WORKS The following checklist has been compiled to assist the applicant in preparing their application for approval pursuant

More information

Lake Samish Comprehensive Stormwater Plan Capital Improvement Recommendations

Lake Samish Comprehensive Stormwater Plan Capital Improvement Recommendations Lake Samish Comprehensive Stormwater Plan Capital Improvement Recommendations drainage. The easement could potentially be used to site a surface water quality treatment facility for the flow. The design

More information

Strathcona County Functional Planning Study Highway 15:06 From Range Road 220 to Highway 830 A P P E N D I X G BRIDGE ASSESSMENT E00311A

Strathcona County Functional Planning Study Highway 15:06 From Range Road 220 to Highway 830 A P P E N D I X G BRIDGE ASSESSMENT E00311A Strathcona County Functional Planning Study Highway 15:06 From Range Road 220 to Highway 830 A P P E N D I X G BRIDGE ASSESSMENT E00311A BF 73649 E/W Bridge Culverts Highway 15 Crossing Astotin Creek Bridge

More information

Eco-engineering on the Edge:

Eco-engineering on the Edge: Eco-engineering on the Edge: Decision Making for Stream Restoration and Stabilization in High Profile or Risk Environments Dan Salas, Ecologist Cardno JFNew Types of Risk Physical/Structural = Property

More information

Hydraulic and Sediment Transport Modeling Strategy

Hydraulic and Sediment Transport Modeling Strategy Appendix B Hydraulic and Sediment Transport May 2014 Technical Memorandum Channel Capacity Report September 2014 San Joaquin River Restoration Program Hydraulic and Sediment Transport The San Joaquin River

More information

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans)

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Allen County Stormwater Plan Submittal Checklist The following items must be provided when applying for an Allen County Stormwater

More information

LCI LACAS CONSULTANTS INC. CONSULTING ENGINEERS - HYDROLOGICAL SPECIALISTS, SINCE 1991

LCI LACAS CONSULTANTS INC. CONSULTING ENGINEERS - HYDROLOGICAL SPECIALISTS, SINCE 1991 LCI LACAS CONSULTANTS INC. CONSULTING ENGINEERS - HYDROLOGICAL SPECIALISTS, SINCE 1991 TECHNICAL MEMORANDUM DATE: February 6, 2012 TO: FROM: Cori Barraclough, R.P.Bio. Aqua-Tex Scientific Consulting Ltd.

More information

2013 PREPARED BY: CEPA VERSION # 1. Pipeline Watercourse Management Recommended Practices, 1st Edition

2013 PREPARED BY: CEPA VERSION # 1. Pipeline Watercourse Management Recommended Practices, 1st Edition 2013 PREPARED BY: CEPA VERSION # 1 Pipeline Watercourse Management Recommended Practices, 1st Edition Notice of Copyright Copyright 2013 Canadian Energy Pipeline Association (CEPA). All rights reserved.

More information

Massachusetts River and Stream Crossing Standards: Technical Guidelines

Massachusetts River and Stream Crossing Standards: Technical Guidelines Massachusetts River and Stream Crossing Standards: Technical Guidelines August 6, 2004 INTRODUCTION As long and linear ecosystems, rivers and streams are very important for fish and other wildlife movements,

More information

Appendix B Stormwater Site Plan Submittal Requirements Checklist

Appendix B Stormwater Site Plan Submittal Requirements Checklist Stormwater Site Plan Submittal Requirements Checklist The Submittal Requirements Checklist is intended to aid the design engineer in preparing a Stormwater Site Plan. All items included in the following

More information

Temporary Watercourse Crossing: Culverts

Temporary Watercourse Crossing: Culverts Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol

More information

Alberta Flood Envelope Curve Analysis

Alberta Flood Envelope Curve Analysis Alberta Flood Envelope Curve Analysis Introduction : Flood envelope curves have been used for many years as an attempt to provide context on the magnitude of flood events or design values. One common envelope

More information

Monitoring Report #3 Kenston Lake Stream Restoration Bainbridge, Ohio

Monitoring Report #3 Kenston Lake Stream Restoration Bainbridge, Ohio Monitoring Report #3 Kenston Lake Stream Restoration Bainbridge, Ohio Prepared by: EnviroScience, Inc. 5070 Stow Rd Stow OH 44224 (330) 688-0111 Year Ending: December 31, 2013 I. Project Overview The following

More information

Dawson County Public Works 25 Justice Way, Suite 2232, Dawsonville, GA (706) x 42228

Dawson County Public Works 25 Justice Way, Suite 2232, Dawsonville, GA (706) x 42228 Dawson County Public Works 25 Justice Way, Suite 2232, Dawsonville, GA 30534 (706) 344-3500 x 42228 DAWSON COUNTY STORM WATER REVIEW CHECKLIST Project Name: Property Address: Engineer: Fax #/Email: Date:

More information

CENTRAL ASSINIBOINE INTEGRATED WATERSHED MANAGEMENT PLAN SURFACE WATER HYDROLOGY REPORT

CENTRAL ASSINIBOINE INTEGRATED WATERSHED MANAGEMENT PLAN SURFACE WATER HYDROLOGY REPORT CENTRAL ASSINIBOINE INTEGRATED WATERSHED MANAGEMENT PLAN SURFACE WATER HYDROLOGY REPORT Planning Area Boundary: The Central Assiniboine planning area covers the reach of the Assiniboine River from just

More information

- Site Location and Conditions. A. Project Location. B. Existing Conditions

- Site Location and Conditions. A. Project Location. B. Existing Conditions H&H Report - Site Location and Conditions Page 1 of 2 A. Project Location 1. Site Identification District County Mu nicipali ty 06 Bucks Hilltown (Twp) Site MINSI TRAIL S.R. 4019 Section 60M Segment 0050

More information

Use of IDF Curves Design of a roof drainage system

Use of IDF Curves Design of a roof drainage system Use of IDF Curves Design of a roof drainage system Your engineering firm is currently planning the construction of a residential apartment building in Davos, Switzerland. Your task is to design the roof

More information

10(a) Bridge and culvert design information

10(a) Bridge and culvert design information 10(a) Bridge and culvert design information The following information is required to accompany resource consent applications for bridges or culverts on waterways. Please answer all questions if possible.

More information

STREAMBANK RESTORATION DESIGN

STREAMBANK RESTORATION DESIGN STREAMBANK RESTORATION DESIGN WITH VINYL SHEET PILE GRADE CONTROL STRUCTURES BRUCE M. PHILLIPS, M.S., P.E. ABSTRACT Grade control structures are an effective channel stabilization measure which can eliminate

More information

Temporary Stream Crossing

Temporary Stream Crossing Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective

More information

Use of WARSSS in Stream Restoration and Watershed Planning. Michigan Aquatic Restoration Conference 2015

Use of WARSSS in Stream Restoration and Watershed Planning. Michigan Aquatic Restoration Conference 2015 Use of WARSSS in Stream Restoration and Watershed Planning Michigan Aquatic Restoration Conference 2015 October 22, 2015 Use of WARSSS in Stream Restoration and Watershed Planning 1. Watershed Management

More information

Temporary Stream Crossing

Temporary Stream Crossing Temporary Stream Crossing NS-4 Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution

More information

Failure Consequence Classification

Failure Consequence Classification Failure Consequence Classification Audience: Dam Safety Officers (DSO) Owners of small dams Community emergency preparedness coordinators Introduction This document provides an overview of failure consequence

More information

Application for resource consent Form B Damming and diversion of water

Application for resource consent Form B Damming and diversion of water Application for resource consent Form B Damming and diversion of water Notes Resource use activities must meet all the conditions of any relevant Permitted Activity Rules in the Waikato Regional Plan or

More information

Modular Sediment Barriers (Instream)

Modular Sediment Barriers (Instream) Modular Sediment Barriers (Instream) INSTREAM PRACTICES Flow Control No Channel Flow Dry Channels Erosion Control Low Channel Flows Shallow Water Sediment Control High Channel Flows Deep Water Symbol Photo

More information

SECTION IV WATERSHED TECHNICAL ANALYSIS

SECTION IV WATERSHED TECHNICAL ANALYSIS A. Watershed Modeling SECTION IV WATERSHED TECHNICAL ANALYSIS An initial step in the preparation of this stormwater management plan was the selection of a stormwater simulation model to be utilized. It

More information

S.R. 4007, Section 14B PADEP Environmental Assessment Form. Enclosure C Description of Aquatic Habitat

S.R. 4007, Section 14B PADEP Environmental Assessment Form. Enclosure C Description of Aquatic Habitat S.R. 4007, Section 14B PADEP Environmental Assessment Form Description of Aquatic Habitat Cresheim Creek is the only water resource that exists within the project area. No jurisdictional wetlands were

More information

Hydraulic Report. County Road 595 Bridge over Mulligan Creek. Prepared By AECOM Brian A. Hintsala, P.E

Hydraulic Report. County Road 595 Bridge over Mulligan Creek. Prepared By AECOM Brian A. Hintsala, P.E Prepared for: Prepared by: Marquette County Road Commission AECOM Ishpeming, MI Marquette, MI 60240279 December 9. 2011 Hydraulic Report County Road 595 Bridge over Mulligan Creek Prepared By AECOM Brian

More information

MINNEHAHA COUNTY HIGHWAY DEPARTMENT CULVERT REPLACEMENT REQUEST FORM

MINNEHAHA COUNTY HIGHWAY DEPARTMENT CULVERT REPLACEMENT REQUEST FORM MINNEHAHA COUNTY HIGHWAY DEPARTMENT CULVERT REPLACEMENT REQUEST FORM Instructions & Background Information (This page to be completed by Township personnel) The purpose of this form is to provide a means

More information

COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION

COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION PERMIT GUIDELINES FOR PHASED NPDES STORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY PERMITS, CHAPTER 102 EROSION AND SEDIMENT

More information

APPENDIX 8. NORTHERN GROUND ELECTRODE LINE WATERCOURSE CROSSING ASSESSMENT BOOKLETS

APPENDIX 8. NORTHERN GROUND ELECTRODE LINE WATERCOURSE CROSSING ASSESSMENT BOOKLETS APPENDIX 8. NORTHERN GROUND ELECTRODE LINE WATERCOURSE CROSSING ASSESSMENT BOOKLETS Aquatic Environment November 2011 Bipole III Transmission Project Construction Camp CC1 Location Datum: NAD 83 UTM: Zone:

More information

Uncertainty in Hydrologic Modelling for PMF Estimation

Uncertainty in Hydrologic Modelling for PMF Estimation Uncertainty in Hydrologic Modelling for PMF Estimation Introduction Estimation of the Probable Maximum Flood (PMF) has become a core component of the hydrotechnical design of dam structures 1. There is

More information

Headwater Drainage Feature Assessment:

Headwater Drainage Feature Assessment: Prepared for: Jim Dougan, MSc Principal & Senior Ecologist DOUGAN & ASSOCIATES Ecological Consulting & Design 77 Wyndham Street South, Guelph, ON, N1E 5R3, Headwater Drainage Feature Assessment: In Support

More information

Pajaro River Watershed Flood Prevention Authority. Phase 3 and 4a. Pajaro River Watershed Study

Pajaro River Watershed Flood Prevention Authority. Phase 3 and 4a. Pajaro River Watershed Study Pajaro River Watershed Flood Prevention Authority Phase 3 and 4a FEBRUARY 2005 Funding for this project has been provided in full or in part through a contract with the SWRCB pursuant to the Costa-Machado

More information

FISH HABITAT RESTORATION DESIGNS FOR CAVE CREEK, WITHIN THE NAHWITTI RIVER WATERSHED

FISH HABITAT RESTORATION DESIGNS FOR CAVE CREEK, WITHIN THE NAHWITTI RIVER WATERSHED FISH HABITAT RESTORATION DESIGNS FOR CAVE CREEK, WITHIN THE NAHWITTI RIVER WATERSHED Prepared for: Tom Cole, RPF Richmond Plywood Corporation 13911 Vulcan Way Richmond, B.C. V6V 1K7 March 2004 Prepared

More information

Brannen Lake Storage Feasibility Potential Effects on Water Levels

Brannen Lake Storage Feasibility Potential Effects on Water Levels Brannen Lake Storage Feasibility Potential Effects on Water Levels Brannen Lake Storage Feasibility Potential Effects on Water Levels Prepared for: BC Conservation Foundation #3, 1200 Princess Royal Avenue

More information

CLOCA Rural & Agricultural Guide to Permits

CLOCA Rural & Agricultural Guide to Permits CLOCA Rural & Agricultural Guide to Permits Regulation of Development, Interference with Wetlands and Alterations to Shoreline and Watercourses, Ontario Regulation 42/06 April 2014 Table of contents Introduction...

More information

Ongoing and Completed Studies

Ongoing and Completed Studies Attachment 2 Ongoing and Completed Studies 2014 Monitoring and Analysis Plan November 2013 Attachment 2 Ongoing and Completed Studies 1 Introduction In 2013, the small interdisciplinary study groups for

More information

FORECASTING ICE JAM RISK AT FORT MCMURRAY, AB, USING FUZZY LOGIC

FORECASTING ICE JAM RISK AT FORT MCMURRAY, AB, USING FUZZY LOGIC Ice in the Environment: Proceedings of the 16th IAHR International Symposium on Ice Dunedin, New Zealand, 2nd 6th December 2002 International Association of Hydraulic Engineering and Research FORECASTING

More information

COMMISSION. OGC File: LNG Canada Development Inc th Avenue SW Calgary, AB T2P 0J4. Attention: Surface Land Administrator

COMMISSION. OGC File: LNG Canada Development Inc th Avenue SW Calgary, AB T2P 0J4. Attention: Surface Land Administrator COMMISSION OGC File: 9642638 LNG Canada Development Inc. 400-4th Avenue SW Calgary, AB T2P 0J4 Attention: Surface Land Administrator Re: Approval for Changes in and About a Stream Date of issuance: July

More information

Preface. MNR # Queen s Printer for Ontario, 2012 ISBN (PRINT) ISBN (PDF)

Preface. MNR # Queen s Printer for Ontario, 2012 ISBN (PRINT) ISBN (PDF) Preface In 2008, the inter-agency Drainage Act & Section 28 Regulations Team (DART) was established by the Ministry of Natural Resources (MNR) and the Ministry of Agriculture, Food and Rural Affairs (OMAFRA)

More information

Development of Stage-Discharge Ratings for Site 2240 Bear Creek at Cold Spring

Development of Stage-Discharge Ratings for Site 2240 Bear Creek at Cold Spring Development of Stage-Discharge Ratings for Site 2240 Bear Creek at Cold Spring Prepared for: Urban Drainage and Flood Control District 2480 W. 26 th Avenue Suite 156-B Denver, CO 80211 May 19, 2006 (Rev

More information

NCS Design Approach. Biology/Ecology Primer. Presented by: Jack Imhof, National Biologist Trout Unlimited Canada

NCS Design Approach. Biology/Ecology Primer. Presented by: Jack Imhof, National Biologist Trout Unlimited Canada NCS Design Approach Biology/Ecology Primer Presented by: Jack Imhof, National Biologist Trout Unlimited Canada Biology/Ecology Key biological principles that are applied Need to speak the same language

More information

PRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY

PRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY PRELIMINARY DRAINAGE REPORT FOR THE NEWCASTLE FIRE STATION OLD STATE HIGHWAY PREPARED FOR THE NEWCASTLE FIRE PROTECTION DISTRICT JULY 2014 BY ROSEVILLE DESIGN GROUP, INC. ROSEVILLE DESIGN GROUP, Inc Established

More information

COTTONWOOD CREEK RECLAMATION PHASE I & II

COTTONWOOD CREEK RECLAMATION PHASE I & II COTTONWOOD CREEK RECLAMATION PHASE I & II COTTONWOOD CREEK RECLAMATION Stream Stabilization Approach to Urban Runoff Quality Cherry Creek Basin Water Quality Authority The Problem The Cherry Creek Reservoir

More information

APPENDIX CENTRAL CITY CLEAR FORK / WEST FORK TRINITY RIVER, AND MARINE CREEK FEASIBILITY STUDY

APPENDIX CENTRAL CITY CLEAR FORK / WEST FORK TRINITY RIVER, AND MARINE CREEK FEASIBILITY STUDY APPENDIX CENTRAL CITY CLEAR FORK / WEST FORK TRINITY RIVER, AND MARINE CREEK FEASIBILITY STUDY GENERAL CIVIL DESIGN The purpose of this appendix is to provide feasibility level engineering information

More information

Background. AEM Tier 2 Worksheet Stream & Floodplain Management. Glossary

Background. AEM Tier 2 Worksheet Stream & Floodplain Management. Glossary AEM Tier 2 Worksheet Stream & Floodplain Management Glossary Bankfull Stage: The stage at which water starts to flow over the flood plain; the elevation of the water surface at bankfull discharge. (This

More information

SOUTHEAST TEXAS CONTINUING EDUCATION

SOUTHEAST TEXAS CONTINUING EDUCATION EXAM No. 118 FLOOD - RUNOFF ANALYSIS 1. Information gained from flood - runoff analysis includes which one: A. Stage, discharge, volume. B. Measure depth, volume. C. Velocity, depth, storm occurrence.

More information

MONTHLY UPDATE REPORT - PRIMROSE SOUTH W4M SEPTEMBER 22 TO OCTOBER 19, 2015

MONTHLY UPDATE REPORT - PRIMROSE SOUTH W4M SEPTEMBER 22 TO OCTOBER 19, 2015 MONTHLY UPDATE REPORT - PRIMROSE SOUTH 09-21-067-04 W4M SEPTEMBER 22 TO OCTOBER 19, 2015 1 Introduction The Canadian Natural Resources Limited Primrose South in situ oil sands project is located in the

More information

Appendix P. U.S. Fish and Wildlife Service Planning Aid Letter

Appendix P. U.S. Fish and Wildlife Service Planning Aid Letter Appendix P U.S. Fish and Wildlife Service Planning Aid Letter This page is intentionally left blank. United States Department of the Interior FISH AND WILDLIFE SERVICE Missouri Ecological Services Field

More information

Bridge Planning Updates. Bridge Planning Practitioners Workshop April 2012

Bridge Planning Updates. Bridge Planning Practitioners Workshop April 2012 Bridge Planning Updates Bridge Planning Practitioners Workshop April 2012 Bridge Website Bridge Website Bridge Website Bridge Website BPG 11 Stormwater Management at Rural Bridges Released July 2010 Documents

More information

For NGTL to file calculation of operating condition on pull back stress analysis.

For NGTL to file calculation of operating condition on pull back stress analysis. NOVA Gas Transmission Ltd. Exhibit No. B85 National Energy Board Hearing Order GH-001-2014 Undertaking U-10 Submitted November 25, 2014 Response to Undertaking given by Mr. Trout to Chairman Vergette at

More information

Stream Reaches and Hydrologic Units

Stream Reaches and Hydrologic Units Chapter United States 6 Department of Agriculture Natural Resources Conservation Service Chapter 6 Stream Reaches and Hydrologic Units Rain clouds Cloud formation Precipitation Surface runoff Evaporation

More information

OFFICE OF STRUCTURES MANUAL ON HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 3 POLICY AND PROCEDURES

OFFICE OF STRUCTURES MANUAL ON HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 3 POLICY AND PROCEDURES OFFICE OF STRUCTURES MANUAL ON HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 3 POLICY AND PROCEDURES April 28, 2016 Table of Contents 3.1 Introduction... 2 3.1.1 Purpose of Chapter 3... 2 3.1.2 Policy vs. Design

More information

Appendix VI: Illustrative example

Appendix VI: Illustrative example Central Valley Hydrology Study (CVHS) Appendix VI: Illustrative example November 5, 2009 US Army Corps of Engineers, Sacramento District Prepared by: David Ford Consulting Engineers, Inc. Table of contents

More information

DRAFT MONITORING REPORT LELAND-DOUGLAS HABITAT RESTORATION PROJECT

DRAFT MONITORING REPORT LELAND-DOUGLAS HABITAT RESTORATION PROJECT DRAFT MONITORING REPORT LELAND-DOUGLAS HABITAT RESTORATION PROJECT Prepared for Stillaguamish Tribe of Indians Prepared by Anchor QEA, LLC 1605 Cornwall Avenue Bellingham, Washington 98225 October 2013

More information

California Rapid Assessment Method for Wetlands (CRAM) Riverine Training Module

California Rapid Assessment Method for Wetlands (CRAM) Riverine Training Module California Rapid Assessment Method for Wetlands (CRAM) Riverine Training Module Steps of CRAM Assessment Step 1: Assemble background information Step 2: Classify wetland Step 3: Verify the appropriate

More information

Repairing flow: what to do at the site

Repairing flow: what to do at the site Repairing flow: what to do at the site Page 8 Repairing flow: what to do at the site Strategy 1. Reduce the velocity of instream flow Suitability of strategy: this strategy will be most effective where

More information

3.5 Hydrology & Hydraulics

3.5 Hydrology & Hydraulics 3.5 Hydrology & Hydraulics 3.5.1 Purpose The purpose of this section is to provide results from the analysis and assessment of the impact of the proposed Carmichael Rail Alignment (Option 11 Revision 1)

More information

CLAY STREET BRIDGE REPLACEMENT

CLAY STREET BRIDGE REPLACEMENT HYDROLOGY /HYDRAULICS REPORT. EL DORADO COUNTY CLAY STREET BRIDGE REPLACEMENT Prepared by: Joseph Domenichelli Domenichelli & Associates 1107 Investment Blvd., Suite 145 El Dorado Hills, California 95762

More information

Appendix 14-I Description of Stream Crossing for Electrical Interconnect

Appendix 14-I Description of Stream Crossing for Electrical Interconnect Appendix 14-I Description of Stream Crossing for Electrical Interconnect 14.0 Ecology Appendix 14-I CPV Valley Energy Project Description of Stream Crossing for Electrical Interconnect The CPV Valley Energy

More information

APPENDIX G HYDROSTATIC TEST PLAN

APPENDIX G HYDROSTATIC TEST PLAN APPENDIX G HYDROSTATIC TEST PLAN Preliminary Hydrostatic Test Plan for the Proposed North Montney Project Prepared for: NOVA Gas Transmission Ltd. Calgary, Alberta Prepared by: Stantec Consulting Ltd.

More information

Bluff Creek One Water

Bluff Creek One Water Bluff Creek One Water The Bluff Creek Watershed has no lakes within its boundaries. As the westernmost watershed within the District, land use changes from agricultural to residential have occurred relatively

More information

River Restoration, 2018 Has stormwater management been our Achilles Heel in River Management?

River Restoration, 2018 Has stormwater management been our Achilles Heel in River Management? River Restoration, 2018 Has stormwater management been our Achilles Heel in River Management? By Bill Annable, PhD, PhD, PEng, PE, PGeo Department of Civil & Environmental Engineering, University of Waterloo

More information

RUNNING WATER AND GROUNDWATER

RUNNING WATER AND GROUNDWATER NAME RUNNING WATER AND GROUNDWATER I. Introduction In this exercise we will investigate various features associated with streams and groundwater. Our drinking water ultimately comes from either streams

More information

Developing Tools for Hydromodification Management and Assessment

Developing Tools for Hydromodification Management and Assessment Developing Tools for Hydromodification Management and Assessment Hydromodification: Channel Erosion Before Development After Development Increase in: - Imperviousness - Drainage Slope - Direct Runoff Decrease

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

Department of the Army Permit Application

Department of the Army Permit Application Department of the Army Permit Application DA File Number U.S. Army Corps of Engineers Honolulu District Date Received by CEPOH-RO Send Completed Application to: Honolulu District, U.S. Army Corps of Engineers

More information

Flow Control No Channel Flow Dry Channels Erosion Control Low Channel Flows Shallow Water Sediment Control High Channel Flows [1] Deep Water [2]

Flow Control No Channel Flow Dry Channels Erosion Control Low Channel Flows Shallow Water Sediment Control High Channel Flows [1] Deep Water [2] Geo Logs (coir logs) INSTREAM PRACTICES Flow Control No Channel Flow Dry Channels Erosion Control Low Channel Flows Shallow Water Sediment Control High Channel Flows [1] Deep Water [2] [1] Geo logs can

More information

Transactions on Ecology and the Environment vol 19, 1998 WIT Press, ISSN

Transactions on Ecology and the Environment vol 19, 1998 WIT Press,   ISSN Water surface profiles and scour analysis for a river reach with multiple bridge proposals C.C. Nuthmann & C.C. Chang Sverdrup Civil, Inc., Two Center Plaza, Boston, Massachusetts, USA, 02108 Email: nuthmacc@sverdrup.

More information

Fish Passage Design for Roughened Channels. Pre-Presentation Note

Fish Passage Design for Roughened Channels. Pre-Presentation Note NOAA 9/23/2010 Science, Service, Stewardship Aaron Beavers Hydraulic Engineer Fish Passage Design for Roughened Channels Northwest Region E.I.T. M.S.C.E. NOAA FISHERIES SERVICE Pre-Presentation Note The

More information