Slipstream Office Relocation Project February 2008

Size: px
Start display at page:

Download "Slipstream Office Relocation Project February 2008"

Transcription

1 Slipstream ffice Relocation Project February 2008 Team embers Jill Carley Ruchi Chopra Yelena Faynburd Suchir Gupta Darren Petersen Rudolph Rico Dipali Shah Prem Sujan Dee Wise Team Slipstream

2 Table of Contents Project Scope Statement p. Vision Statement p. Business Need p. Project Description p.4 Project Deliverables p.4 Project bjectives p.5 Project Assumptions p.6 Project Constraints p.6 Project High-Level Risks p.7 Project Approval Signatures p.7 Project Lifecycle p.9 Stakeholder Analysis p.0 Work Breakdown Structure p.2 Project Schedule p.5 Cost Analysis p.8 Cost Baseline p.2 Responsibility Assignment atrix p.24 Communication anagement Plan p.25 Risk Response Plan p.26 Team Slipstream 2

3 Project Scope Statement. Vision Statement Slipstream plans to relocate its corporate headquarters from San Francisco, California to ountain View, California in order to improve and expand the overall infrastructure and to better serve its clients, partners and associates. 2. Business Need Rising San Francisco commercial space rent, outgrowing the current space due to expanded workforce, and a need for a more efficient, updated facility has created a need for Slipstream to relocate corporate head quarters. Slipstream would like to be closer to its clients who are primarily located in the Silicon Valley area, and reduce the amount of traveling for its employees. 240 employees live within 0 miles from new location 70% of company clients are based in Silicon Valley About 60% savings in per sq. ft. rent price ($40 in SF vs. $25 - new locations) Team Slipstream

4 Project Scope Statement (continued). Project Description Slipstream plans to relocate its corporate headquarters from San Francisco, California to ountain View, California in order to improve and expand the overall infrastructure and to better serve its clients, partners and associates. 4. Project Deliverables (Scope) Relocation of corporate headquarters with minor modifications to a currently vacant & operational building Real-time office relocation of current employees & contractors s s Not A major construction/ build out Hiring of additional workforce Functional company T infrastructure and systems along with upgrades online throughout move All associated project documentation deliverables, e.g. Project anagement Plan, construction docs, furniture plans & ove ap including interior layout Setting up redesigned T network & systems ncreased facility and/or operational budgets Team Slipstream 4

5 Project Scope Statement (continued) 5. Project bjectives bjective Sign new lease agreement Terminate current lease agreement Notify all employees, partners and clients of the move Criteria for Evaluation Sign by January, 2008 Send notice by February, 2008 Notification by February 4, 2008 Finalize contracts with vendors and movers Approve construction documentation, furniture plans and ove ap Finalize contracts by arch, 2008 Approve by arch, 2008 New facility infrastructure completed with all the offices, cubicles and office Confirmation by April, 2008 Complete check for live operations (T/telecom) Begin moving employees to new location starting with T department Complete check by April 25, 2008 ove started ay, 2008 and completed ay 5, 2008 Complete any after move assistance for employees Project Complete by ay, 2008 and within budget Complete by ay 0, 2008 Sponsor signoff by ay 0, 2008; review of final costs against budget Team Slipstream 5

6 Project Scope Statement (continued) 5. Project Assumptions Building plans for the new facility are available All permits for the building are approved New floor plans are approved Resource requirements will be met 80% of the employees live in the Silicon Valley Good weather conditions No union related delays 6. Project Constraints Funding limited/set budget Schedule - set date for the relocation 5/5/08 No company downtime during the move Team Slipstream 6

7 Project Scope Statement (continued) 7. Project High-Level Risks High-Level Risks Employees cannot be moved as scheduled. New headquarters cannot be moved into at scheduled date. overs cannot perform move on schedule. Trigger. nsufficient packing materials 2. Unexpected project activity occurring that cannot be interrupted. Community legal action blocks/delays move 2. Delay in coordinating T setup with external providers. Lease agreement with new landlord delayed 4. Unforeseen construction delays. Approval of contract with mover delayed 2. oving company unavailable / partially available on desired move dates. Weather conditions postpone move mpact - (C,S,T) C, T C, T C,T Additional furniture required Additional T infrastructure required onsite Additional T infrastructure required offsite Unexpected loss of employees due to move. Legend S = Scope C = Cost T = Time. Additional employees hired 2. naccurate / incomplete move map. Unplanned insufficient infrastructure at site 2. Building plan incomplete/incorrect. ff-site T infrastructure required to support business during move is insufficient. nvalid assumptions in employee impact analysis 2. Local competitor targets hiring of employees C C C C Team Slipstream 7

8 Project Scope Statement (continued) 7. Project High-Level Risks (continued) High-Level Risks New employees hired Unanticipated changes to building plan required Unexpected additional support to minimize work disruption. Serious injury to mover Furniture damage during the move T equipment damage during the move overs strike Legend S = Scope C = Cost T = Time Trigger. Filling requisitions which were open during feasibility 2. Unplanned growth required prior to move due to business needs. New employees hired 2. Building plan incomplete/incorrect. Unexpected increase in business activity during move schedule requires further support. Unexpected injury of one (or more) of the movers. ffice furniture has been damaged during the move. T equipment has been damaged during the move. overs go on strike unexpectedly (no prior warning) mpact - (C,S,T) S,C S,C S,C C C C, T C, T 8. Project Approval Signatures CF/Sponsor Project anager Team Slipstream 8

9 Project Lifecycle Feasibility Analysis Phase Planning Phase Execution/ Relocation Phase Closing Phase Project anagement Deliverables Project Charter Preliminary Project Scope Develop Project anagement Plan: Final Scope Statement Work Breakdown Structure Project Schedule Cost Baseline Responsibility Assignment atrix (RA) Communication anagement Plan Risk Response Plan Change Controls Vendor Proposals Status Report Change Approval/Rejection Final Project anagement Report Sponsor Sign-off Lessons Learned Contracts Closure Product anagement Deliverables Needs Analysis Feasibility and perational Assets Study Project Team rg Chart Relocation Process Change rders Employee mpact Analysis nternal & External Location Analysis Location Plan/ove ap Vendor Selection/Contracts Lease Agreement Signed Permits Pre-ove Checklist ove ap Pre-ove Test Systems ove Assets Final Test Systems Final Relocation Checklist (ove-n Complete) Press Release Company Celebration Final T System Test Report (All Systems Go) Filing documents to the centralized project repository Team Slipstream 9

10 Stakeholder Analysis Stakeholder Name CE/ Sponsor P Team (Slip Stream) Cost analysis High level relocation plan High level communications Stake holder Need CE/Sponsor support Authority to sign contracts and engage vendors Clear communication Stakeholder Expectation Seamless relocation ove within budget ove within timeframe defined Cooperation of all Stakeholders Timely communication Bonus Employees Timeline of the move Pre-move and post move checklist Boxes to pack personal items New stationary ordered with updated location information Detailed document with the new address, transit facility and amenities of the new location inimal disruption to work and family life Legal Clients Contractors and Architects All the documents that require review and/or approval by Legal Notification of the move Space plan detailing space requirements, employee location in new building etc. Tenant improvements to be done for the relocation T infrastructure plan Appropriate, clear and timely communication inimal disruption to work Regular communication with the P Team n-time payments Team Slipstream 0

11 Stakeholder Analysis (continued) Stakeholder Name Need Expectation overs ld Landlord Signed contract to engage movers Detailed space plan to ensure move of office assets, employee boxes etc. to proper locations Lease termination documents Timely communication with P Timely payments Rent and other payments have been made Tenant follows the negotiated terms for notice to vacate and any repairs that need to be made Notifications of move have been made to all current clients and vendors so that new tenants moving in are not disrupted with mail and calls. New Landlord Neighboring Tenants Community/ City All new lease documents Proper communication of the move Any approvals for the relocation Permits for movers Fees associated with the move Any building/construction permit approvals Proper execution of the lease terms inimal impact to their operations inimal noise inimal or no disruption to the community Company abides with the City Codes Team Slipstream

12 Work Breakdown Structure Feasibility Analysis Phase Planning Phase. Project Charter.2 Preliminary Project Scope. Needs Analysis.. Business needs list..2 Employee needs list.. Customer needs list..4 Alternative solutions study..5 Solution for further feasibility.4 Feasibility and perational Assets Study.4. arketing feasibility study.4.2 perational feasibility study.4. Legal feasibility study.4.4 Economic feasibility study 2. Project anagement Plan 2.. Scope Statement 2..2 WBS 2.. Project Schedule 2..4 Cost Baseline 2..5 Responsibility Assignment atrix 2..6 Communication anagement Plan 2..7 Risk Response Plan 2..8 Change Controls 2.2 Contractor Selection 2.2. RFP and selection Architectural/Construction drawings 2.2. Building materials specifications 2. T Specifications Plan 2.. T migration/test plan 2..2 T deployment/test plan 2.. T upgrade plan 2..4 T equipment order 2..5 T backup plan Team Slipstream 2

13 Work Breakdown Structure (continued) Planning Phase (continued) 2.4 ove ap 2.5 Relocation schedule 2.6 Furniture Vendor Selection 2.6. RFP Contract finalized 2.6. Furniture plan and specifications Furniture delivery plan Furniture orders 2.7 over Selection 2.7. RFP and selection nventory checklist 2.7. Packing material estimates Packing material order 2.8 Permits Execution/Relocation Phase. Status Reports.. Status reports T..2 Status reports legal.. Status report- P.2 Change Control anagement. Furniture delivery checklist.4 Tenant improvement build-out report.5 New T systems delivery checklist.6 Final facility walkthrough report.7 T Systems igration Report.7. Server deployment report.7.2 Workstation installation report.7. Telecom report.7.4 T backup report.8 ove ap and schedule report.9 nventory move checklist Team Slipstream

14 Work Breakdown Structure (continued) Closing Phase 4. Final Project anagement Report 4.2 Sponsor Sign-off 4. Lessons Learned Document 4.4 Contract Closures (payments) 4.4. Furniture vendor contract over contact 4.4. Contractor contract T contract 4.5 Final T system test report 4.6 Checklists 4.6. ove ap Relocation 4.6. Post relocation assistance 4.7 Press release 4.8 Legal documents 4.9 nternal company celebration Team Slipstream 4

15 Project Schedule Team Slipstream 5

16 Project Schedule (continued) Team Slipstream 6

17 Project Schedule (continued) Team Slipstream 7

18 Cost Analysis Project WBS Days Billable Hours Hourly Rate Cost Flat Fees WBS Total Cost Feasibility Analysis Phase. Project Charter.2 Preliminary Project Scope. Needs Analysis.. Business needs list..2 Employee needs list.. Customer needs list..4 Alternative solutions study..5 Solution for further feasibility. Total work package cost.4 Feasibility and perational Assets Study.4. arketing feasibility study.4.2 perational feasibility study.4. Legal feasibility study.4.4 Economic feasibility study.4 Total work package cost Total Feasibility Analysis Phase Cost $00 $00 $00 $50 $00 $,200 $,750 $,050 $,650 $450 $450 $600 $2,000 $2,000 $900 $,800 $4,200 $6,700 $,200 $,750 $4,200 $6,700 $5,850 Team Slipstream 8

19 Cost Analysis (continued) Project WBS Days Billable Hours Hourly Rate Cost Flat Fees WBS Total Cost Planning Phase 2. T Specifications Plan 4 $05, T migration/test plan 4 0 $25 $, T deployment/test plan 20 $25 $2, T upgrade plan 6 $25 $2, T equipment order 8 $25 $,000 $95, T backup plan 2. Total work package cost 8 $25 $,000 $05, ove ap 24 $50 $,600 $, Relocation schedule 2 6 $,200 $, Furniture Vendor Selection 7 $07, RFP 0 40 $, Contract finalized 8 $ Furniture plan and specifications 24 $00 $2, Furniture delivery plan 2 2 $ Furniture orders 2.6 Total work package cost 6 $450 $00,000 $07,50 Team Slipstream 9

20 Cost Analysis (continued) Project WBS Days Billable Hours Hourly Rate Cost Flat Fees WBS Total Cost Planning Phase 2.7 over Selection 6 $2, RFP and selection 0 40 $,000 $60, nventory checklist 4 2 $00 $, Packing material estimates 8 $00 $ Packing material order 2. Total work package cost 4 $45,000 $2, Permits Total Planning Phase Cost 8 $200 $,600 $,600 $452,75 Execution/Relocation Phase 46. Status Reports $4,500.. Status reports T 4 24 $00 $2, Status reports legal 2 $900.. Status report- P 6 $450. Total Work package cost $4,500 Team Slipstream 20

21 Cost Analysis (continued) Project WBS Days Billable Hours Hourly Rate Cost Flat Fees WBS Total Cost.2 Change Control anagement 0 60 $4,500 $4,500. Furniture delivery checklist 8 $600 $600.4 Tenant improvement build-out report 80 $6,000 $6,000.5 New T systems delivery checklist 2 6 $25 $2,000 $2,000.6 Final facility walkthrough report 20 $00 $2,000 $2,000.7 T Systems igration Report $9, Server deployment report 24 $25 $, Workstation installation report 8 $25 $2, Telecom report 6 $25 $2, T backup report.7 Total Work package cost 2 6 $25 $2,000 $9,250.8 ove ap and schedule report 20 $,500 $,500.9 nventory move checklist Total Execution Phase Cost 0 50 $,750 $,750 $4,00 Team Slipstream 2

22 Cost Analysis (continued) Project WBS Days Billable Hours Hourly Rate Cost Flat Fees WBS Total Cost Closing Phase 4. Final Project anagement Report 4.2 Sponsor Sign-off 4. Lessons Learned Document 4.4 Contract Closures (payments) 4.4. Furniture vendor contract over contact 4.4. Contractor contract T contract 4.4 Total work package cost 4.5 Final T system test report 4.6 Checklists 4.6. ove ap Relocation 4.6. Post relocation assistance 4.4 Total work package cost 4.7 Press release 4.8 Legal documents 4.9 nternal company celebration Total Closing Phase Cost $00 $00 $00 $25 $00 $50 $800 $500 $,000 $,750 $600 $600 $2,250 $800 $,750 $45,000 $65,000 $50,000 $5,000 $95,000 $,450 $2,500 $0,000 $800 $500 $,000 $95,000 $,750 $,450 $,00 $,750 $0,000 $22,550 Cost for all Phases $72,875 Team Slipstream 22

23 Cost Baseline Phase Cost Phase Phase 2 Phase Phase 4 Phase - Feasibility Analysis $5,850 $5,850 $5,850 $5,850 $5,850 Phase 2-Planning $452,75 $452,75 $452,75 $452,75 Phase - Execution/Relocation $4,00 $4,00 $4,00 Phase 4-Closing $22,550 $22,550 Total Cumulative Cost $72,875 $5,850 $468,225 $502,25 $72,875 Slipstream Headquarter Relocation Cost Baseline $,000,000 0,000 $500,000 $250,000 Phase 4 Phase Phase 2 Phase $0 Phase - Feasibility Analysis Phase 2-Planning Phase - Execution/Relocation Phase 4-Closing Team Slipstream 2

24 Responsibility Assignment atrix WBS D Deliverable Description CE/ Sponsor P Team Employees Legal T anager Contractors & Architects Clients overs Landlord City Project Charter Preliminary Scope Statement Needs analysis Feasibility and perations assets study Project anagement Plan Contractor selection T specifications plan ove plan Relocation schedule Furniture vendor selection over selection Permits Status Reports Change Control anagement Tenant improvement build-out report Furniture delivery checklist Final facility walkthrough report T Systems migration report oving ap and schedule report nventory move checklist Final project management report Sponsor sign-off Lessons learnt document Contract closures (payments) Final T system test report Checklists Press Release Legal documents S S R R S,R Legend = wner = nput R = Reviewer S = Signoff required S S S S, R S S R, S R, S R, S, R, R R,R, R S Team Slipstream 24, R, R R, R, R S, R R, R R R

25 Communication anagement Plan Communication Frequency Format / Delivery Audience Sender Project Charter nce PDF / Project anager & Project Team Project Sponsor nitial Notice of ove and any Employment Related Changes nce, and then as needed PDF / s and Home ailings Employees & Family of Employees Human Resources via President onthly Progress Reports (PR) onthly PDF / Project Sponsor Project anager Status Reports Bi-weekly S Word / Project anager Project Team embers Termination of Lease nce PDF / ail (UPS) Current Landlord C/CF Scope Statement and Work Breakdown Structure (WBS) nce PDF / Project Sponsor Project anager Notification of ove nce PDF / s and USPS ailings Current Clients President Project Plan Status & Changes Weekly PDF / Project Team, Vendors, Contractors, overs, etc. Project anager Approved Change Requests As needed PDF / Project Team Project anager Project Team eeting Agendas & inutes Weekly S Word / Project Team Project anager Team Slipstream 25

26 Risk Response Plan Risk D Risk Description Affected Areas Probability of ccurrence mpact to Project Priority Strategy Action D Action Action wner Status Employees cannot be moved as scheduled. C, T L H P2. Status reports - monitor move preparation (including moving material availability) P.2 Status reports - monitor/forecast company activity level during planned move P 2 New headquarters cannot be moved into at scheduled date. C, T H P 2. City permits - monitor approval process Legal 2.2 Status reports - T - track progress with any external providers T 2. Lease agreements - monitor approval process Legal overs cannot perform move on schedule. C,T L H P2. over contract - monitor approval process P.2 Status reports - confirm mover availability week prior to move T. Project anagement Plan - include buffer for move delays P 4 Additional furniture required C L L P A N/A N/A N/A C 5 Additional T infrastructure required onsite C L H P2 5. T plan - buffer for additional infrastructure T 5.2 Status reports - T - monitor progress T 6 Additional T infrastructure required offsite C L H P2 6. T plan - buffer for additional infrastructure T 6.2 Status reports - T - monitor progress T * Please see page 28 for description of abbreviations Team Slipstream 26

27 Risk Response Plan (continued) Risk D Risk Description Unexpected loss of employees due to move. New employees hired. Unanticipated changes to building plan required. Unexpected additional support to minimize work disruption. Serious injury to mover Furniture damage during move T equipment damage during move overs strike * Please see page 28 for description of abbreviations Affected Areas C S,C S,C S,C C C C, T C,T Probability of ccurrence L L L L L mpact to Project H H H L H H Priority P P2 P2 P2 P2 P2 P P2 Strategy T T T Action D Action Employee needs analysis - follow-up Status reports - onitor activity of local competitors Project anagement Plan includes buffer for 5% increase in number of employees prior to move Project anagement Plan includes buffer for 5% increase in number of employees prior to move ove map - verify via walkthrough Status reports - monitor/forecast company activity level during planned move T Plan - nclude buffer for increased activity level (20%) over Contract - overs responsible for insuring their employees over Contract - overs responsible for packing furniture over Contract - movers financially liable for damage over Contract - overs responsible for packing T equipment over Contract - movers financially liable for damage over Selection - include state of labor in criteria Action wner Team Slipstream 27 HR P P P P P T Legal Legal Legal Legal Legal Legal Status C

28 Risk Response Plan (continued) Prioritization atrix Probability \ mpact mpact=h mpact= mpact=l Probability = H P P P2 Probability = P P2 P Probability = L P2 P P Affected Areas Abbreviations Strategy Abbreviations Status Abbreviations C=Cost V=Avoidance =pen S=Scope T=Transference C=Closed T=Time =itigation Q=Quality A=Acceptance Team Slipstream 28

X470 Project Management UC Berkeley Extension, Business and Management August 2009

X470 Project Management UC Berkeley Extension, Business and Management August 2009 X470 Project Management UC Berkeley Extension, Business and Management August 2009 Anuradha Vaddadi Miguel Rivera Prasada Martala Wayne Harriman Archina Vishen Kiumars Golriz Table of Contents 1. Project

More information

Dated: April 30, 2014

Dated: April 30, 2014 ADDENDUM #2 for NEW REQUESTS FOR PROPOSALS AIRPORT CITYWORKS IMPLEMENTATION at CHARLOTTE DOUGLAS INTERNATIONAL AIRPORT for the CITY OF CHARLOTTE, NORTH CAROLINA Dated: April 30, 2014 1. Are there additional

More information

Program Lifecycle Methodology Version 1.7

Program Lifecycle Methodology Version 1.7 Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated

More information

Horned Frog Banking Consolidation Project

Horned Frog Banking Consolidation Project Project Charter Horned Frog Banking Consolidation Project Start: September 5, 2018 Projected End: April 10, 2018 Approval of the Project Charter indicates an understanding of the purpose and content described

More information

S3. Step 3 Develop Roadmap

S3. Step 3 Develop Roadmap S3. Step 3 Develop Roadmap PART OF IT STRATEGY TOOLIKIT VERSION 0.5 MAY 2007 1 TABLE OF CONTENTS S3-1. DETERMINE PRIORITIES... 3 S3-1.1 ASSESS DEPENDENCIES... 3 S3-1.2 PRIORITISE BUILDING BLOCKS... 3 S3-1.3

More information

Risks, Dependencies and Mitigation Steps By Function

Risks, Dependencies and Mitigation Steps By Function Risks, Dependencies and Mitigation Steps By Function Cross Team Dependencies: Operations 1 Team Dependency Teams Affected Status Op 1 Early approval of key lead roles & staffing so transition plans can

More information

Information Technology Services Project Management Office Operations Guide

Information Technology Services Project Management Office Operations Guide Information Technology Services Project Management Office Operations Guide Revised 3/31/2015 Table of Contents ABOUT US... 4 WORKFLOW... 5 PROJECT LIFECYCLE... 6 PROJECT INITIATION... 6 PROJECT PLANNING...

More information

HANDOUT 3-1 REQUIREMENTS RECORD PROJECT TITLE: PROJECT MANAGER: REQUIREMENT: ASSUMPTIONS: CONSTRAINTS: REQUIRED RESOURCES:

HANDOUT 3-1 REQUIREMENTS RECORD PROJECT TITLE: PROJECT MANAGER: REQUIREMENT: ASSUMPTIONS: CONSTRAINTS: REQUIRED RESOURCES: Handouts HANDOUT 3-1 REQUIREMENTS RECORD PROJECT TITLE: DATE: PROJECT MANAGER: REQUIREMENT: ASSUMPTIONS: CONSTRAINTS: REQUIRED RESOURCES: FUNCTIONAL GROUPS PARTICIPATING: SAMPLE 3-1 REQUIREMENTS RECORD

More information

Information Technology Audit & Cyber Security

Information Technology Audit & Cyber Security Information Technology Audit & Cyber Security Information System Systems & Infrastructure Lifecycle Management LEARNING OBJECTIVES Describe the steps involved in the project initiation and planning process.

More information

Pulling up the Roots: a Guide to Corporate Relocation

Pulling up the Roots: a Guide to Corporate Relocation Pulling up the Roots: a Guide to Corporate Relocation Overview It is Monday morning and you look forward to starting the new week at work. As you get to your office, you find a note on your desk. Your

More information

<Project Name> Charter

<Project Name> Charter < NOTE: Remove the italicized, bracketed guidance before routing for approvals. > General Information 1. Project Number: 2. Project Name: 3. Executive : 4. Business : 5. IT : 6. Project Manager/Lead: Executive

More information

This document outlines the specifics of the training program that is being developed by M7 Training Solutions (MTS) for PJ Enterprises.

This document outlines the specifics of the training program that is being developed by M7 Training Solutions (MTS) for PJ Enterprises. Project Plan This document outlines the specifics of the training program that is being developed by M7 Training Solutions (MTS) for PJ Enterprises. Project Name This phase of our project is called New

More information

NISQUALLY RED WIND CASINO REQUEST FOR QUALIFICATIONS / PROPOSAL FOR MASTER PLANNING SERVICES

NISQUALLY RED WIND CASINO REQUEST FOR QUALIFICATIONS / PROPOSAL FOR MASTER PLANNING SERVICES NISQUALLY RED WIND CASINO REQUEST FOR QUALIFICATIONS / PROPOSAL FOR MASTER PLANNING SERVICES Proposal Due Date: February 7, 2018 at 1:00 PM PST RED WIND CASINO HOTEL DEVELOPMENT RFQ/P 1 January 23, 2018

More information

Reference B Project Management Requirements

Reference B Project Management Requirements Reference B State of Alaska TABLE OF CONTENTS 1... 2 1.1 Project Life Cycle Methodology... 2 1.2 Preliminary Project Management Narrative and Work Plan... 2 2 Master Project Management Plan and Master

More information

Program/Project Management

Program/Project Management PROCEDURE OVERVIEW PROGRAM/PROJECT MANAGEMENT PROCEDURE defines the project management infrastructure, reporting relationships and project management activities within SDLC.com. Project Managers, Program

More information

Total Cost of Ownership (TCO) Calculator

Total Cost of Ownership (TCO) Calculator Total Cost of Ownership (TCO) Calculator Hardware & Software Management Support Implementation Communications fees Direct Costs The capital expenditures and lease fees for servers, client computers, peripherals,

More information

M3 Playbook Guidance. 1.1 Establish Initial Customer PMO and Processes. Human Resources (HR)/Staffing Plan

M3 Playbook Guidance. 1.1 Establish Initial Customer PMO and Processes. Human Resources (HR)/Staffing Plan M3 Playbook Guidance Phase 1: Readiness This guidance is intended for use by organizations to confirm and validate that their plans are comprehensive and have adequate level of detail for proper migration

More information

Total Cost of Ownership (TCO) Calculator

Total Cost of Ownership (TCO) Calculator Total Cost of Ownership (TCO) Calculator Hardware & Software Management Support Implementation Communications fees Direct Costs The capital expenditures and lease fees for servers, client computers, peripherals,

More information

Big Bang Theory: PeopleSoft HCM 9.2 and PeopleSoft Financials 9.2 Upgrade in Seven Months

Big Bang Theory: PeopleSoft HCM 9.2 and PeopleSoft Financials 9.2 Upgrade in Seven Months Big Bang Theory: PeopleSoft HCM 9.2 and PeopleSoft Financials 9.2 Upgrade in Seven Months 10/25/2015 Matt Peterman Grant Thornton Senior Solution Architect, Kansas City Beth Geer Empire District Electric

More information

Enhancing Project Success

Enhancing Project Success NACCU 2017 Enhancing Project Success Debbie DeYulia, Director of Program Management debbie.deyulia@duke.edu Laurie Harris, DukeCard Program Manager laurie.harris@duke.edu Duke University At A Glance Located

More information

Auditing Timeline. Top-Line Version

Auditing Timeline. Top-Line Version Auditing Timeline Top-Line Version As a complement to their book Agency Audits: How to Achieve Success, Joanne Davis and Jane Twyon have created a timeline that takes marketers through the auditing journey.

More information

Internal Audit Department 350 South 5 th Street, Suite 302 Minneapolis, MN (612)

Internal Audit Department 350 South 5 th Street, Suite 302 Minneapolis, MN (612) Internal Audit Department 350 South 5 th Street, Suite 302 Minneapolis, MN 55415-1316 (612) 673-2056 Date: July 19, 2016 To: Re: Mayor Betsy Hodges; City Council Members; City Coordinator Cronk; Chief

More information

ACTIVITIES CHECKLIST ASSIGNED TO DUE DONE

ACTIVITIES CHECKLIST ASSIGNED TO DUE DONE I 2 3 4 5 6 7 8 9 I0 II I2 I3 I4 I5 I6 I7 Form a Move Committee. Delegate and assign responsibilities to each member of the Move Committee. Find out if any licenses or permits are required at new facilities.

More information

1. IDENTIFICATION. Freebalance coding: PURPOSE 3. SCOPE

1. IDENTIFICATION. Freebalance coding: PURPOSE 3. SCOPE 1. IDENTIFICATION Position No. Job Title Supervisor s Position 14-02986 Manager Informatics Projects Director Government Information and Planning Department Division/Region Community Location Community

More information

Copyright 2013 Pearson Education, Inc. Publishing as Prentice Hall 5-1

Copyright 2013 Pearson Education, Inc. Publishing as Prentice Hall 5-1 Copyright 2013 Pearson Education, Inc. Publishing as Prentice Hall -1 Learning objectives Manage the planning process of a project Understand the work breakdown structure of a project Understand different

More information

RISK MANAGEMENT STRATEGY

RISK MANAGEMENT STRATEGY INSTITUTE of GRUNDSANSIP (IG) RISK ANAGEENT STRATEGY INTRDUCTIN 1.In order for the IG to operate, deliver our services and achieve our objectives some amount of risk taking is necessary. The only way to

More information

City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services

City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services ATTACHMENT A SAMPLE SCOPE OF SERVICES PLC & HMI PROGRAMMING City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services December, 2017

More information

Cost Reduction Strategies Suggested by Participants of the Workshop on December 10 & 11, 2008

Cost Reduction Strategies Suggested by Participants of the Workshop on December 10 & 11, 2008 Strategies Suggested by Participants of the Workshop on December 10 & 11, 2008 Note: The number next to each consideration reflects the number of participants that made that or a similar suggestion. SALARIES

More information

International Diploma in Project Management. (Level 4) Course Structure & Contents

International Diploma in Project Management. (Level 4) Course Structure & Contents Brentwood Open Learning College (Level 4) Page 1 Unit 1 Overview of Project Management The unit 1 covers the following topics: What is A Project? What is Project Management? Project Constraints Tools and

More information

REQUIREMENTS DOCUMENTATION

REQUIREMENTS DOCUMENTATION REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category Priority Acceptance Criteria REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category

More information

Building Contract Closeout. Ahmed Abd Alla Gouda, Chief Contracting Officer

Building Contract Closeout. Ahmed Abd Alla Gouda, Chief Contracting Officer Building Contract Closeout Ahmed Abd Alla Gouda, Chief Contracting Officer Content Construction Contracts Management from Award to Close Out. Barriers to Effective Construction Contract Management. Economy

More information

Telling the Sourcing Story: Driving Stakeholder engagement from startup to maturity. March 9, 2017

Telling the Sourcing Story: Driving Stakeholder engagement from startup to maturity. March 9, 2017 Telling the Sourcing Story: Driving Stakeholder engagement from startup to maturity March 9, 2017 Rent-A-Center Background NASDAQ: RCII The largest operator in the United States rent-to-own industry Stores

More information

PROJECT MANAGEMENT ESSENTIALS. Project Management Plans

PROJECT MANAGEMENT ESSENTIALS. Project Management Plans PROJECT MANAGEMENT ESSENTIALS Project Management Plans BS6079, the British Standard for Project Management, offers guidelines on the level and type of information that should be defined in the early stages

More information

Enterprise Availability Management

Enterprise Availability Management Statement of Work Enterprise Availability Management This Statement of Work ( SOW ) is between the Customer (also called you and your ) and the IBM legal entity referenced below ( IBM ). This SOW is subject

More information

Unit 8 Project Implementation and Closure

Unit 8 Project Implementation and Closure UNIT OVERVIEW Description of the Unit In this unit, you will learn how to execute the project plan, and upon completion, close out the project. You will learn how to develop a role-responsibility matrix,

More information

Project Management Framework with reference to PMBOK (PMI) July 01, 2009

Project Management Framework with reference to PMBOK (PMI) July 01, 2009 Project Management Framework with reference to PMBOK (PMI) July 01, 2009 Introduction Context Agenda Introduction to Methodologies What is a Methodology? Benefits of an Effective Methodology Methodology

More information

Define and Initiate SubPhase

Define and Initiate SubPhase Project Management Methodology Project Management Methodology Training Define and Initiate SubPhase Course Purpose Familiarize team members with the Start Project Sub-Phase processes. Understand process

More information

Facilities Management Department Division and Unit Goals

Facilities Management Department Division and Unit Goals Facilities Management Department 2017-18 Division and Unit Goals Administration Division Goals Business Operations Unit 1. BOPS staff is going to work internally to better standardize and document our

More information

Fixed Scope Offering for Implementation of Oracle Fusion CRM in Cloud

Fixed Scope Offering for Implementation of Oracle Fusion CRM in Cloud Fixed Scope Offering for Implementation of Oracle Fusion CRM in Cloud Today s Business Challenges Adopt leading CRM practices and stream line processes Take advantage of CRM to attract new customers, develop

More information

Gathering Network Requirements

Gathering Network Requirements Gathering Network Requirements Designing and Supporting Computer Networks Chapter 2.1 Copyleft 2012 Vincenzo Bruno (www.vincenzobruno.it) Released under Creative Commons License 3.0 By-Sa Cisco name, logo

More information

RFP Feasibility Design Services: Clinical Education & Assessment Center Expansion Questions & Answers: February 13 th, 2018

RFP Feasibility Design Services: Clinical Education & Assessment Center Expansion Questions & Answers: February 13 th, 2018 Question & Answer: #1 The RFP calls for a survey of the building to gain a comprehensive understanding of the existing building, utilities, building systems, occupancies and all existing conditions as

More information

Facilities Management Project Delivery Model - Process Map - v

Facilities Management Project Delivery Model - Process Map - v Project Delivery Model - Process Map - v8.0-2016-05-25 Overview PLANNING DESIGN IMPLEMENTATION CLOSE OUT Project Identification Initiation Page 2 Project Planning Page 3 Schematic Design / Design Development

More information

Your Office Fit Out Checklist

Your Office Fit Out Checklist Your Office Fit Out Checklist Plan your office refurbishment from start to finish with our definitive Office Fit Out Checklist. We ll take you through the planning process step-by-step, to help ensure

More information

Project and Resource Management: A Do-it-Yourself guide

Project and Resource Management: A Do-it-Yourself guide Project and Resource Management: A Do-it-Yourself guide Shyam Kapoor Partner, Prisio Technologies ShyamK@prisiotechnologies.com Phone: +1 (732) 208-3616 103 Carnegie Center, Ste 300 Princeton, NJ 08540

More information

KillTest *KIJGT 3WCNKV[ $GVVGT 5GTXKEG Q&A NZZV ]]] QORRZKYZ IUS =K ULLKX LXKK [VJGZK YKX\OIK LUX UTK _KGX

KillTest *KIJGT 3WCNKV[ $GVVGT 5GTXKEG Q&A NZZV ]]] QORRZKYZ IUS =K ULLKX LXKK [VJGZK YKX\OIK LUX UTK _KGX KillTest Q&A Exam : PK0-003 Title : CompTIA Project+ Version : Demo 1 / 7 1.There is a minor conflict between several members on a project team; the issue has no significant impact on the project. Which

More information

V3 Pension Administration System Solution. January 2014 Monthly Board Update

V3 Pension Administration System Solution. January 2014 Monthly Board Update V3 Pension Administration System Solution January 2014 Monthly Board Update Agenda V3 Monthly Update Page Project Overall Status Update 3 V3 PASS Project Status Gantt Chart 4 PASS V3 Project Milestones

More information

Planning the Work How to Create a Manageable Enterprise GIS Project Plan

Planning the Work How to Create a Manageable Enterprise GIS Project Plan Planning the Work How to Create a Manageable Enterprise GIS Project Plan Mirjam Stadelmann Esri UC 2014 Technical Workshop Topics Why do we plan How do we plan Planning for project completion How to use

More information

REAL ESTATE DIVISION AUDIT SUMMARY OVERVIEW

REAL ESTATE DIVISION AUDIT SUMMARY OVERVIEW REAL ESTATE DIVISION AUDIT SUMMARY OVERVIEW Performance Audit Scope Review the organizational structure and the policies and procedures of the Real Estate Division (). Benchmark operations to other Divisions

More information

Process Document # 7 Finance

Process Document # 7 Finance Process Document # 7 Finance Version 7.3 Dec 5, 2014 Document Approval Process Owner: Sandra Piperias Finance Controller Signature: Date: Gracy DaSilva Finance Analyst Signature: Date: Jasoda Deonarine

More information

Creating an Actionable Disaster Recovery Plan

Creating an Actionable Disaster Recovery Plan Creating an Actionable Disaster Recovery Plan Presentation Outline Plan Justification Disaster Definitions & Facts Costs of a Disaster Benefits of Planning Building an Actionable Disaster Recovery Plan

More information

Use our moving checklist to set up and implement a detailed schedule and timeline of all tasks and procedures that need to be completed.

Use our moving checklist to set up and implement a detailed schedule and timeline of all tasks and procedures that need to be completed. Relocating a business is a very involved, complicated and stressful process. The job of coordinating the relocation can be fraught with many demands and challenges. Planned correctly, a business move can

More information

Best Practice: Migration Strategies

Best Practice:  Migration Strategies US-Amplify Best Practice: Email Migration Strategies White Paper Contents Executive Summary... 2 Project Scoping Stage... 2 Feasibility Study... 4 Definition Stage... 5 Design Stage... 5 Migration Sizing...

More information

P22 Managing Capital Projects

P22 Managing Capital Projects P22 David Spackman, CHF Canada Jim Kroesen, Housing Services Corporation Agenda 1. Introductions 2. What could possibly go wrong? 3. What are we doing 4. How can we ensure the best outcomes from capital

More information

Project Plan. For Building a Data Management System for FORCE. Prepared for: Andrew Lowery Fundy FORCE

Project Plan. For Building a Data Management System for FORCE. Prepared for: Andrew Lowery Fundy FORCE Project Plan For Building a Data Management System for FORCE Prepared for: Andrew Lowery Fundy FORCE Submitted by: SEG Consulting Inc. www.segconsulting.ca Version 1.0 June 29, 2017 Version Log The following

More information

Project Manager s Roadmap We re all smarter together

Project Manager s Roadmap We re all smarter together Version 7.0a Project Manager s Roadmap We re all smarter together Think Top Down! Methodology Checklists Define Plan Execute Close Conflict Resolution Modes Contract Outsource Management Mentoring References

More information

ITSM Process/Change Management

ITSM Process/Change Management ITSM Process/Change Management Process Documentation Revision Date: December 13, 2017 Version Number: 2.0 Document Ownership Document Owner Maury Collins Revision History ITSM Role, Department Service

More information

Upgrade of Network of Pharmaceutical Company

Upgrade of Network of Pharmaceutical Company Upgrade of Network of Pharmaceutical Company Question- Q1.Design a work break down structure (WBS) for this project with milestones? Q2. What are the key risks and how would you manage them? Q3. What are

More information

HOUSTON, TX, USA 5 8 NOVEMBER 2017 #PMOSym

HOUSTON, TX, USA 5 8 NOVEMBER 2017 #PMOSym HOUSTON, TX, USA 5 8 NOVEMBER 2017 #PMOSym PMO17BR203 Agile Transformation: Real-World Innovative Adaptation Dr. Linda McIntosh, DBA, CSM, ITIL, PMP, Executive Director, IT PMO Sam Houston State University

More information

REPORT TO THE BOARD OF GOVERNORS

REPORT TO THE BOARD OF GOVERNORS REPORT TO THE BOARD OF GOVERNORS SUBJECT INTEGRATED RENEWAL PROGRAM FINANCE/HR/STUDENT MEETING DATE JUNE 14, 2018 APPROVED FOR SUBMISSION Forwarded to the Board of Governors on the Recommendation of the

More information

PMP Exam Preparation Workshop. Chapter # 5 Project Scope Management

PMP Exam Preparation Workshop. Chapter # 5 Project Scope Management PMP Exam Preparation Workshop Chapter # 5 Copyright PMI SOC 2013 1 Learning Objectives By the end of this session you will understand: How scope management processes relate to the process groups Project

More information

Software Zix Resale Service Agreement. 1.0 Terminology. 3.0 Service Options. 4.0 Service Delivery. 2.0 Service Description

Software Zix Resale Service Agreement. 1.0 Terminology. 3.0 Service Options. 4.0 Service Delivery. 2.0 Service Description This Software Zix Resale Service Agreement ( Service Agreement ) sets forth the specific terms and conditions under which LightEdge Solutions, Inc. ( LightEdge ) shall supply certain Services to Customer.

More information

WMS IMPLEMENTATION CHECKLIST

WMS IMPLEMENTATION CHECKLIST WS IPLEENTATION HEKLIST Over 100 steps to WS implementation success GUIDE HIGHLIGHTS reating a WS change management plan Promoting user buy-in and training your team Planning and executing an efficient

More information

Establishing a Program Management Office

Establishing a Program Management Office Establishing a Program Management Office Agenda Why companies need Program Management 3 Objectives of Program Management 4 Program and Project Management definitions 5 Program Management infrastructure

More information

NOTICE OF ADDENDUM TO RFQ DOCUMENTS ADDENDUM NO. 01 August 29, 2018 ENGINEERING SERVICES FOR VARIOUS KERN COMMUNITY COLLEGE DISTRICT PROJECTS

NOTICE OF ADDENDUM TO RFQ DOCUMENTS ADDENDUM NO. 01 August 29, 2018 ENGINEERING SERVICES FOR VARIOUS KERN COMMUNITY COLLEGE DISTRICT PROJECTS Construction & Facilities Planning Dept. Bakersfield College, 1801 Panorama, Bakersfield, CA 93305 Program Office: (661) 395-4254 NOTICE OF ADDENDUM TO RFQ DOCUMENTS ADDENDUM NO. 01 August 29, 2018 ENGINEERING

More information

Integration Knowledge Area

Integration Knowledge Area Integration Knowledge Area Develop Project Charter Project statement of work Expert judgment Project charter Business case Contract (if third party project) EEF: government/industry standards, organizational

More information

Managing Complexity in the Face of Uncertainty

Managing Complexity in the Face of Uncertainty Effective Project Management: Traditional, Agile, Extreme Managing Complexity in the Face of Uncertainty After successful studying this chapter You should be able to: Use tools, templates, and processes

More information

USDA Shared Services Journey

USDA Shared Services Journey USDA Shared Services Journey USDA was named as an SAP Federal Financial Shared Services Provider in May 2014, able to offer financial system services within the federal government. This was in response

More information

<Project Name> Business Case

<Project Name> Business Case Business Case Author(s) Contributors Department Campus DOCUMENT HISTORY Version Date Person Notes 1.0 ITS Portfolio Management Office Business Case Page 1 TABLE OF CONTENTS

More information

Office Relocation for Nonprofits

Office Relocation for Nonprofits Office Relocation for Nonprofits In the second article of this series we talked about what to take into account when deciding whether to go ahead with a facility project. This entails recognizing that

More information

Fundamentals of Project Management with Microsoft Project 2010

Fundamentals of Project Management with Microsoft Project 2010 Fundamentals of Project Management with Microsoft Project 2010 8 Contact Hours Instructor: Michael McDonald Training Manager Information Services Massachusetts Eye & Ear 1 Project Management Fundamentals

More information

Planning & Community Development Department REGULATIONS REQUIRING RETROFIT OF WOOD SOFT -STORY RESIDENTIAL BUILDINGS

Planning & Community Development Department REGULATIONS REQUIRING RETROFIT OF WOOD SOFT -STORY RESIDENTIAL BUILDINGS Agenda Report ; _j TO: Honorable Mayor and City Council THROUGH: Public Safety Committee (February 4, 2019) FROM: SUBJECT: Planning & Community Development Department REGULATONS REQURNG RETROFT OF WOOD

More information

Initiation Group Process. Planning Group Process

Initiation Group Process. Planning Group Process Initiation Group Process Develop Project Charter Project statement of work Expert judgment Project charter Business case Contract (if third party project) EEF: government/industry standards, organizational

More information

Planning the Work How to Create a Manageable Enterprise GIS Project Plan

Planning the Work How to Create a Manageable Enterprise GIS Project Plan 2013 Esri International User Conference July 8 12, 2013 San Diego, California Technical Workshop Planning the Work How to Create a Manageable Enterprise GIS Project Plan Mirjam Stadelmann Topics Why planning

More information

How Your Business Survival Depends On Disaster Recovery.

How Your Business Survival Depends On Disaster Recovery. How Your Business Survival Depends On Disaster Recovery www.itgct.com 1 Business continuity and disaster recovery, known as BCDR or BC/DR, are essential for ensuring the survival of your business in the

More information

2019 Project Prioritization and Budgeting Process

2019 Project Prioritization and Budgeting Process 2019 Project Prioritization and Budgeting Process Brian Hurysz Manager, Market Products Budget and Priorities Working Group May 10, 2018, Krey Corporate Center Agenda Project Prioritization Process Project

More information

MANUFACTURING ERP IMPLEMENTATION CHECKLIST

MANUFACTURING ERP IMPLEMENTATION CHECKLIST ANUFATURING ERP IPLEENTATION HEKLIST Over 70 actionable steps to help your ERP implementation go smoothly GUIDE HIGHLIGHTS Building your ERP implementation team igrating your data, testing, training and

More information

March 4, Accelerating Project Delivery ROW, Utilities & Alternate Contract Method Update JLTOC Mike Holder, PE, Chief Engineer

March 4, Accelerating Project Delivery ROW, Utilities & Alternate Contract Method Update JLTOC Mike Holder, PE, Chief Engineer March 4, 2016 Accelerating Project Delivery ROW, Utilities & Alternate Contract Method Update JLTOC Mike Holder, PE, Chief Engineer Accelerating Project Delivery Utilities Process Improvement Strategic

More information

Project Management Manual Prepared by: Project Support Office, Major Projects Department

Project Management Manual Prepared by: Project Support Office, Major Projects Department Project Management Manual Prepared by: Project Support Office, Major Projects Department Version: 2015 Project Support Office Project Management Manual Version: November 2015 This manual is a living document

More information

Project Green House. Green Team. Making the world greener one house at a time

Project Green House. Green Team. Making the world greener one house at a time Project Green House Making the world greener one house at a time UC Berkeley Extension, Business and Management UCB X470 Project Management February 2008 Green Team Lori Plein Anne Cairney Ferdinand Bueno

More information

IFMS Scope: Modules SCM. Financial. Management (GL) Inventory. Management. Asset. Payroll. Management HRM. Procurement Management Catalogue Management

IFMS Scope: Modules SCM. Financial. Management (GL) Inventory. Management. Asset. Payroll. Management HRM. Procurement Management Catalogue Management Status of IFMS IFMS Background The IFMS project is aimed at replacing aging and fragmented financial (including Payroll), supply chain and human resource (HR) management systems, and associated ageing

More information

Project+ Examination Blueprint Version June 1, 2003

Project+ Examination Blueprint Version June 1, 2003 Introduction The Project + examination is designed for business professionals involved with projects with a technology component. The examination is designed for candidates possessing at least 12 months

More information

Enterprise Data Strategy and Governance

Enterprise Data Strategy and Governance Project Charter DATE: 9/20/2017 VERSION 1.0 Prepared By: Melany Leavitt and Paul Given Page 1 Document Revision History Version Number Date Description.01 5/25/2017 Draft Charter.02 9/1/2017 Draft for

More information

Chapter 3 DESIGN. C. Project Scope: The Designer may proceed only with the authorized scope of work. Scope changes must be approved by the OFD-PM.

Chapter 3 DESIGN. C. Project Scope: The Designer may proceed only with the authorized scope of work. Scope changes must be approved by the OFD-PM. Chapter 3 DESIGN 3.01 INTRODUCTION A. The Designer, in providing professional services for the project in accordance with the terms and conditions of the Owner/Designer Agreement, should adhere to the

More information

Chapter 3 DESIGN. C. Project Scope: The Designer may proceed only with the authorized scope of work. CPCA must approve scope changes.

Chapter 3 DESIGN. C. Project Scope: The Designer may proceed only with the authorized scope of work. CPCA must approve scope changes. Chapter 3 DESIGN 3.01 INTRODUCTION A. The Designer, in providing professional services for the project in accordance with the terms and conditions of the Owner/Designer Agreement, shall adhere to the following

More information

Shared Hosting Service Agreement. 1.0 Terminology. 3.0 Service Options. 2.0 Service Description. 4.0 Service Delivery

Shared Hosting Service Agreement. 1.0 Terminology. 3.0 Service Options. 2.0 Service Description. 4.0 Service Delivery This Shared Hosting Service Agreement ( Service Agreement ) sets forth the specific terms and conditions under which LightEdge Solutions, Inc. ( LightEdge ) shall supply certain Services to Customer. The

More information

<Insert Project Name>

<Insert Project Name> Short Form Business Case Project Phase: Customer: Document ID: Initiation Name Position Title Organization Signature Date

More information

Load Balancing Service Agreement. 1.0 Terminology. 3.0 Service Options. 2.0 Service Description. 4.0 Service Delivery

Load Balancing Service Agreement. 1.0 Terminology. 3.0 Service Options. 2.0 Service Description. 4.0 Service Delivery This Load Balancing Service Agreement ( Service Agreement ) sets forth the specific terms and conditions under which LightEdge Solutions, Inc. ( LightEdge ) shall supply certain Services to Customer. The

More information

S.No RFP Particulars Project Management Equipment Planning: Measurement & Payment:

S.No RFP Particulars Project Management Equipment Planning: Measurement & Payment: S.No RFP Particulars Project Management Can project initiation approval process be created, 1 planned, managed and tracked in the system? Can different types of project lifecycle be defined and 2 managed

More information

Introduction to Project Management

Introduction to Project Management Introduction to Project Management University Business Institute Amir Dabirian Vice President for Information Technology/CIO March 21 st, 2012 2 The Man Month Men and months are interchangeable commodities

More information

PLANNING. Ahmed Elyamany, PhD

PLANNING. Ahmed Elyamany, PhD PLANNING Ahmed Elyamany, PhD Lecture Topics Benefits of Planning Use of Project Plan Problems with Day-to-Day Planning Problems Caused By Not Planning Definition of Activity Activity durations Sequencing

More information

Iowa Department of Transportation Intelligent Work Zone Deployments

Iowa Department of Transportation Intelligent Work Zone Deployments Iowa Department of Transportation Intelligent Work Zone Deployments SMARTER WORK ZONES TECHNOLOGY APPLICATIONS CASE STUDY The Every Day Counts Initiative (EDC-3) aims to accelerate the deployment of identified,

More information

PROJECT RISK MANAGEMENT HANDBOOK

PROJECT RISK MANAGEMENT HANDBOOK PROJECT RISK MANAGEMENT HANDBOOK First Edition Revision 0 June 26, 2003 Office of Project Management Process Improvement Office of Project Management Process Improvement 1120 N Street, Mail Station 28

More information

PROJECT SCOPE MANAGEMENT PLAN TEMPLATE

PROJECT SCOPE MANAGEMENT PLAN TEMPLATE PROJECT SCOPE MANAGEMENT PLAN TEMPLATE This template guides you through each stage of preparing an effective scope management plan that ensures success. With this plan you clearly state the exact work

More information

Introduction. Scope Management Approach. Roles and Responsibilities. Processes included in Scope Management are:

Introduction. Scope Management Approach. Roles and Responsibilities. Processes included in Scope Management are: Introduction Scope Management involves the management of techniques that make sure that the project comprises a Processes included in Scope Management are: 1. Collect Requirements In this process, project

More information

Project Management Proposal

Project Management Proposal Project Management Proposal INTRODUCTION Managing Government Projects can often be challenging. You typically need to manage internal staff, external suppliers, contractors, equipment and materials - while

More information

Chapter HEALTH & WELLNESS CENTER TASK FORCE CHARTER

Chapter HEALTH & WELLNESS CENTER TASK FORCE CHARTER Chapter 10-16 HEALTH & WELLNESS CENTER TASK FORCE CHARTER Task Force Members: Board of Directors Representatives 2 members (one designated as Chair of the Task Force) Management Representatives 3 members

More information

Project Scope Document

Project Scope Document Project Scope Document I. General Information Project Name Project Manager Name BLOCKPLAN Project Number 1 LUIS SILVA Date 02/14/2015 II. Project Overview Describe the product or service of the project,

More information

GMS NETWORK PLUS PRODUCT SPECIFICATION 1. INTRODUCTION 2. SERVICE DEFINITION. 2.1 Service Overview. GMS Network Plus

GMS NETWORK PLUS PRODUCT SPECIFICATION 1. INTRODUCTION 2. SERVICE DEFINITION. 2.1 Service Overview. GMS Network Plus GMS NETWORK PLUS PRODUCT SPECIFICATION 1. INTRODUCTION This document contains product information for the GMS Network Plus Service. If you require more detailed technical information, please contact your

More information

DEPARTMENT OF INFORMATION SERVICES, OFFICE OF TECHNOLOGY SERVICES

DEPARTMENT OF INFORMATION SERVICES, OFFICE OF TECHNOLOGY SERVICES PROCEDURES AND GUIDELINES The Arlington Public Schools recognizes the need to provide administrative staff members with training and support in the use of the various technologies that are available to

More information

Building a Business Case for Shared Services

Building a Business Case for Shared Services Building a Business Case for Shared Services A Discussion of Key Concepts in Evaluating the Feasibility of Shared Services June 2011 Agenda About ScottMadden Business Cases in a Shared Services Context

More information