Martin Smit 1 and Ingrid Pistorius 2. Abstract

Size: px
Start display at page:

Download "Martin Smit 1 and Ingrid Pistorius 2. Abstract"

Transcription

1 WORKING TOWARDS THE VISION OF "THE BEST SAP PLANT MAINTENANCE IMPLEMENTATION IN SOUTH AFRICA EVER" AND ACHIEVING SUCCESS THROUGH STAKEHOLDER PARTICIPATION AND BUY IN. Martin Smit 1 and Ingrid Pistorius 2 1 Eskom Generation, 2 Accenture Abstract Many IT implementations are unsuccessful in that projects are terminated before completion or they are completed late and exceeds the budget by far. In many instances the users are not satisfied with the system or they are not effectively using the system to its fullest potential. In very few instances are any real benefits measured and realised. Eskom Generation is in the process of implementing SAP R/3 Plant Maintenance (PM) version 3.1H at 10 power stations. The objective of this presentation will be to share the project management approach being followed and the lessons learnt to ensure successful implementation. The paper is a case study of a real-world implementation and the authors will present an objective account of the project with specific focus on the PMBOK knowledge areas (i.e. integration, scope, time, cost, quality/performance, human resources, communications, procurement, and risk management). 1 INTRODUCTION Effective plant maintenance is critical to the Eskom Vision of lowest cost electricity in the world and the Generation objective of world class technical performance (90:7:3). To achieve this vision and objective it is essential to have a world class Plant Maintenance (PM) system with embedded best practices. You also need an empowered workforce utilising the system to its fullest potential to maintain the Generation plant assets (book value of R24.044bn and annual maintenance cost of R1.642 for 2000). The current Plant Maintenance system Permac is at the end of its development life cycle and does not serve the needs of the power stations. Permac does not have the functionality of world class PM systems and is not integrated with the plant, financial and other systems. A detailed business case was compiled investigating the cost and associated benefits for different software products and implementation options for an integrated plant maintenance system. Approval was obtained from the Generation Executive Committee to install SAP PM at 10 power stations (9 fossil and 1 nuclear). 2 PROJECT OVERVIEW The project has been divided into three separate projects: 2.1 A detailed business case and approval project The business case and approval project started on 26 July 1999 and was completed on 25 August 2000 when contracts were signed with the successful implementation partners and software vendor. The objective of this part of the project was to make a recommendation considering 4 options: Paper presented at African Rhythm Project Management Conference April 2002, Johannesburg, South Africa Hosted by: Project Management Institute of South Africa (PMISA): ISBN Number:

2 Plant maintenance functionality integrated with the financial and commercial systems (i.e. SAP); Plant maintenance functionality integrated with the plant configuration management system (i.e. PiGo); Plant maintenance functionality using a best of breed system (i.e. Maximo); or Do nothing, keep the status quo (i.e. Permac and PiGo). The second part of the project objective was to obtain buy-in from all the relevant stakeholder forums, to obtain approval form the relevant management bodies, to obtain approval for the capital expenditure and to negotiate contracts with the recommended software and hardware vendors as well as the implementation partners. 2.2 Implementation project The project for the Implementation of the SAP PM system started on 04 September 2000 and is planned for completion in August The objective of this part of the project is to implement the SAP PM system at 10 power stations in the Generation Group (approximately 2500 users). Figure 1 shows the implementation phases of the project S ept ept Oct Nov Dec Jan Jan Feb Feb Mar Apr May Jun Jun Jul Jul Aug Aug S ept ept Oct Nov Dec Jan Jan Feb Feb Mar Apr May Jun Jun Jul Jul Aug Aug DESIGN PH A S E DELIVERY PH A S E PILO T : Tutuka GRO UP 1 D uvha, Lethabo, Matimba GRO UP 2 Hendrina, M ajuba, K end al GRO UP 3 Kriel, M atla KO EBERG Figure 1. Implementation phases of the project 2.3 Benefits realisation project This project is planned to start on 01 June 2002 with a planned finish date of 31 December The objective is to attain the maximum return on the SAP PM investment by facilitating actions across all 10 power stations in order to realise the benefits following the implementation of the SAP PM system in the Generation Group. 3 APPLICATION OF PMBOK KNOWLEDGE AREAS 3.1 Project Integration Management Project plan development One project plan was developed for the business case. For the implementation project, project plans are developed prior to the start of each of the phases. The Accenture Business Integration Methodology and historical information from other, similar Accenture system implementation projects are used as a basis to develop the integrated project plan. During all project phases, the

3 interaction and dependency between the different teams on the project are two important factors to keep in mind to make the plan work effectively for everyone. Another challenging factor during project plan development is the fact that there are many organisations involved in the project each with their own methodologies and thinking. However, the project plan is not developed in isolation. Input from all organisations is sought throughout the planning process. Reports from MS Project are used to guide the project execution and project control. The Theory of Constraints (TOC) buffer management methodology is used where non-critical paths are protected by feeding buffers, and the critical path is protected by the project buffer Project plan execution The project plan is actively managed throughout all the project phases. Each team leader has the responsibility to update his/her part of the plan on a weekly basis, based on the team s progress for the week. The overall project progress is then summarised in an Excel-based graph, which indicates the project buffer penetration (TOC model), as well as the overall project and team progress. This is discussed in a weekly progress meeting, attended by all team leaders Overall change control The initial project plans for each project and each phase are approved by the Project Manager and saved as a baseline against which changes can be controlled. The project plans are updated weekly to indicate the progress. New changes are incorporated into a revised project baseline once the change requests are approved. 3.2 Project Scope Management Initiation The need for the project was initiated from within the business, not from Information Management. The Power Station Managers Forum who realised the need for replacing the plant maintenance system initiated the project. A Maintenance Manager with project management experience from one of the power stations was seconded to lead the project Scope planning A project scope statement was developed for each of the three projects and covered the following elements: Project statement of work with reference to the detailed specifications; Project objectives in terms of time, cost and performance; Key performance areas and quality criteria for each of the PMBOK knowledge areas; and Management plan that includes the project organisation, accountabilities, master plan and implementation methodology/approach. The scope statements were supported by the Steering Committee and authorised by the Project Sponsor Scope definition As scope definition is critical to project success. Detailed specifications were compiled during the business case for the following: Specification for Software Implementation; Specification for Software; and Specification for Hardware.

4 3.2.4 Scope verification The specifications were reviewed by some of the Power Station Managers, the Steering Committee and the Generation Tender Committee, the purpose being to ensure a detailed and accurate project scope accepted by the business that will result in few scope changes Scope change control It was decided to implement SAP PM Vanilla to keep the scope changes to a minimum. The only scope changes that were allowed was to ensure that the system works effectively to cater for specific business needs e.g. nuclear and cold reserve power stations. A detailed position paper is compiled for each scope change and is approved by the Steering Committee to ensure that the changes are beneficial. 3.3 Project Time Management Activity definition The Accenture Business Integration Methodology, project scope statement and historical information from similar Accenture projects are the main inputs for the activity definition. These activities are depicted in the overall project plan and performed to produce the various project deliverables Activity sequencing Based on the Accenture Business Integration Methodology, historical information and work experience, the dependencies between the different project activities are determined, and entered in Microsoft Project (the tool used for the project plan) Activity duration estimation Activity duration estimates are based on historical information, resource availability and resource capabilities, as well as expert judgement that is obtained from various stakeholders Schedule development MS Project is used to assist with the schedule development and resource levelling. Theory of Constraints (TOC) was adapted after assistance from the Goldratt Institute to assist with the compilation of the initial project schedules for the design and development phases of the implementation project Schedule control Few changes are made to the schedule activities, duration estimates and sequences other than adding new activities due to new scope changes. No schedule change control procedures are used other than the overall project plan revisions. 3.4 Project Cost Management Resource planning The Accenture Business Integration Methodology, historical information, the project scope statement and the resource pool available are the major inputs for determining what resources (people, equipment, etc) and what quantities of each are to be used to execute the project activities. The resource planning is not done in isolation by the management team. Being a relatively small project team, it is easy to obtain constant input from the team members regarding their preferences and career aspirations. This ensures that the team members are motivated and they accept the overall project plan.

5 3.4.2 Cost estimating Cost estimating involved developing an approximation of the costs of the resources needed to complete the project activities after consideration was given to various costing alternatives. Cost estimates were compiled from information obtained from the potential software and hardware vendors and implementation partners Cost budgeting The cost baseline was derived from the cost estimates and included the following: External cost (including escalation) for contracts to procure software licences, buy/hire hardware and implementation partner resources; Internal cost (including escalation) for own resources and general project expenses; Cost of cover and IDC (interest during construction); and Project contingency of 4%. Execution Release Approval (ERA) for the project was obtained for the final cost baseline from the Eskom Capital Investment Committee Cost control The cost baseline is changed following approval of the scope and cost changes by the project Steering Committee. The total cost for scope changes are monitored against the project contingency. It was decided to have a formal cost management plan. Cost is monitored during the weekly progress meetings by comparing the estimate at completion with the budget (ERA value). See figure Project Quality Management Quality planning The Quality Plan is the major output of this activity. The Quality Plan aims to ensure that the defined quality objectives are met and stakeholders and sponsors expectations are fulfilled or even exceeded Quality assurance Various processes and tools are used to evaluate the overall project performance on a regular basis to ensure that the project would satisfy the quality standards. One of these is the Client Quality Management Assessment (CQMA). An Accenture on a regular basis does this assessment. The objective of such an assessment is to monitor the overall satisfaction of the various stakeholders of the project as well as to monitor the overall quality processes and suggesting improvements. Eskom Corporate Audit is closely involved with the project. They review project deliverables, monitor solution testing (including user tests) and are present during the final conversion of data into the live system. The system testing process is used to ensure that the solution fulfils the requirements of all stakeholders. It includes different tests for each Power Station, namely unit testing, string testing, system testing, user acceptance testing and dress rehearsal testing. Each of these tests is conducted by different stakeholders, which include project team members and end users Quality control The weekly progress meeting is used as the forum to manage the Quality Plan. During this meeting, the list of project deliverables is reviewed and sign-off dates are recorded.

6 Project management team members, team leaders, site representatives and end users sign off the project deliverables. This records the satisfaction and approval of the various stakeholders with the solution and the overall project. Each project phase is concluded with a Phase Closeout Report. This report is a summary of all the activities and deliverables (with references) that are executed and completed during that phase. The Steering Committee approves and signs-off this report which formally concludes each project phase. 3.6 Project Human Resource Management Organisational planning Journey and Change Mgt Quality Assurance Steering Committee Project Management FSC Project Administration Support Systems Integration Data Preparation Solution Prep Human Performance & Site Preparation Solution Support Software Factory Data Purification Solution Confirmation Site Readiness Training Material Update & Support User Profiles Environment Management (incl Project infrastructure) Production Architecture & Infrastructure Conversion Testing Configuration Solution Testing Training Coordination Figure 2. Project Team Organisation Figure 2 illustrates the project team organisation and reporting relationships. The project team consists of 5 teams, namely the project management team, the systems integration team, the data preparation team, the solution preparation team and the human performance & site preparation team. The Steering Committee plays an overseeing role. They provide overall leadership, guidance and approval of the project. During monthly Steering Committee meetings, the project management team gives status feedback, highlights issues and risks and obtains their input and approval as and when necessary. During rollout/implementation phases, the project team is split in two, due to the fact that some team members have to be at the Power Station sites. The one major challenge that the team is faced with then, is to maintain good communication channels between the central and site based teams. Figure 3 below illustrates the team organisation during Rollout phases:

7 Change Mgmt Data Purif & Conversion Project Mgmt Solution Preparation Interfaces Solution/ Integration FSC Central Change Mgmt Rollout Mgmt Site PS 1 PS 2 PS 3 Roles & Profiles Training Training Logistics Technical Environm Dress Rehearsal Outages Figure 3. Project team organisation during rollout phases Staff acquisition Each organisation involved in the project has its own policies & procedures with regards to staff acquisition. The project team organisation plan (figure 3 above), staffing pool description and recruitment policies are the major inputs to this process. Eskom resources are seconded to the project Team development This is the activity of developing individual and group skills to enhance the overall project performance. In the beginning of the project the team formulated the project vision of being the best SAP PM implementation in South Africa ever. The vision serves as a psychological contract between the organisation, the team members and the project manager. The project vision is constantly communicated to all stakeholders in various forums. The team also attended detailed SAP PM training to help them understand the system that they are working with. Successes are celebrated after key milestones have been achieved, e.g. through activities such as team sport events, social dinners, etc. Much attention is also given to do regular knowledge transfer sessions. This entails that an expert in a subject/area spends time to transfer his/her knowledge to other team members. Individual growth and motivation is a natural result of this effort. Performance contracts are negotiated with each team member to include project objectives as well as individual performance objectives. Team members are provided with regular performance feedback. This leads to clear performance improvements. 3.7 Project Communications Management Communications planning The main objective of communication is to give the right information to the right people, at the right time, in the right format. There are also other reasons for communicating with the project stakeholders (i.e. users, Steering Committee members, Power Station Representatives, etc.). The objectives of communication are to:

8 Ensure consistent messages across all stakeholder groups; Inform, involve and educate all stakeholders whose commitment is required, on the changing maintenance processes and technology (SAP); Address concerns and fears of the people impacted by the SAP PM implementation, thereby beginning and sustaining the acceptance process by promoting buy-in from stakeholders; Ensure that all stakeholder groups know how and when they will be affected by the implementation of the SAP PM; and Create realistic expectations through open and honest communication. All of these objectives are taken into account when the project communication plan is developed for each phase. The communication plan is a matrix that indicates exactly which message is sent to which audience group, when and which communication channel is used. The matrix is a living document that is updated regularly, due to the fact that additional communication needs may arise during the project/phase, audience groups may change, etc Information distribution The cascading model below is the basis of how project information is made available to the various stakeholders: F e e d b a c k M2K+ Communications Coordinators PSMs, PSRs & PS Communication Practitioners Project Champions S p o n s o r s h i p O w n e r s h i p Project Sponsors This body empowers the M2K+ project team to implement SAP PM; They also follow the implementation process & intervenes if necessary All M2K+ End Users Figure 4. Cascading model of communication Figure 4 illustrates the general flow of messages to the stakeholders. Each stakeholder group is responsible to ensure that messages are communicated to the stakeholders on the level below. Power Station Representatives (PSR s) were identified and formally appointed at each Power Station to ensure that the power stations actively participate in the SAP PM system implementation. These individuals co-ordinate all the actions for their power stations to ensure that the requirements of their station are met. They are also responsible for the data purification effort at their power station. All project communication is directed to the PSR. He/she is then responsible to disseminate the information to the right individuals on site. The project sponsors are the Steering Committee members and functional owners. This body empowers the project team to implement SAP PM. They follow the implementation process closely and intervene when necessary.

9 The feedback loops are an essential part of the model. Each stakeholder group is responsible to communicate any feedback (e.g. questions, issues, etc.) to the level above, or directly to the project communication co-ordinators. The feedback is tracked in order to customised future messages Performance reporting The project team leaders compile a weekly status report. These status reports and the project Key Performance Indicators (KPI s) are reviewed at the weekly progress meeting. The Project Manager compiles a bi-weekly status feedback report to the Project Sponsor on all aspects as per the project knowledge areas. See figures 5, 6 and 7 for examples of the key performance Indicators (KPI s). On a monthly basis a performance report presentation is made to the Steering Committee. Group 2 Roll Out Phase Contractual go-live finish date: 2002/03/31 Planned go-live finish date: 2002/03/25 Expected go-live finish date: 2002/03/25 Planned support finish date: 2001/04/25 Project buffer: 4 days Project buffer consumption: 0 days Figure 5. KPI for time management Data Purification Group 3 Target as at 04 Mar 02: 90% (Completion target date is 15 Apr 02) Progress (measured Matla: 86.75% based on data loaded into Kriel: 90.02% the purification tool) Koeberg: 91.19% Figure 6. Data purification progress ACTUAL TO DATE BUDGET (ERA ESTIMATE IN RAND VALUE) IN RAND COMPLETION RAND Accenture Arivia.kom FSC Generation Expenses Infrastructure Hardware Software IDC TOTAL Figure 7. Total project cost as at 08 Mar 02 (escalation and scope changes included) AT IN Administrative closure On completion of each of the projects/phases the documentation for each deliverable is signed-off and filed. A sign-off document for each project/phase with reference to the key documents is compiled and signed off by the Steering Committee. After sign-off by the Steering Committee the project file with documentation is presented to Corporate Audit for review. 3.8 Project Risk Management Risk management planning It was decided to follow a team based risk assessment process. Although the initial process to identify, assess, quantify and compile a response plan for the risks takes some time, it is simple and very effective Risk identification For each of the project deliverables the question is asked what can go wrong. Team members then brainstorm the possible risks than can impact each deliverable.

10 3.8.3 Risk assessment In order to understand each risk the reason for each risk is identified and documented Risk quantification The impact and probability of each risk on scales of 1 to 10 is established (1-3 is low, 4-7 is medium and 8-10 is high). A risk rating is then calculated by multiplying the impact of the risk by the probability Risk response planning Countermeasures for all risks with an unacceptable risk rating as established by the project sponsor are mitigated. In the case of the SAP PM project it was all the risks with a risk rating > Risk monitoring and control The risks, reasons for the risks, impacts, probability, risk ratings and countermeasures are documented in a risk response plan spreadsheet. Bi-weekly risk control meetings are held to identify and review the risks as well as monitor the execution of countermeasures for the risks with a risk rating > 40. See figure 8 for an example of the risk response plan. Risks Impact Probability Reasons for Risks Countermeasures Risk Rating Comments Data not converted in time 8 7 Limited time for conversions to production due to halfyear month end and volume of Koeberg data. Koeberg users not trained 7 7 Koeberg will be busy with an outage during user training. High number of users to be trained. Figure 8. Example of risk response plan Detailed planning to 56 complete work in time available. Meeting held with Koeberg to discuss impacts. Start training earlier and train critical mass. 49 Many users will be trained after the outage. In order to ensure that risks are not overseen a standing agenda item has been added to the two weekly management meetings and weekly project progress meeting to identify any new risks. 3.9 Project Procurement Management Procurement planning A specialist in the disciplines of contract and procurement was involved early during the business case. Approval was also obtained from the relevant procurement and tender committees regarding the procurement strategy before starting with the procurement process. It was also decided to go out on tender and to compile the business case from the tender information received. The NEC Professional Services Contract was used for the procurement of implementation partner services with different main options to be negotiated during each phase of the project e.g. target or termed contracts Solicitation planning Due to the complexity of the decision a decision model was developed to facilitate commitment to the decision in the selection of the software and the implementation partner. The decision model in Figure 11 was agreed with the Steering Committee and Power Station Managers.

11 EVALUATION CRITERIA WEIGHT Software (SW): Evaluation workshop 15% SW vendor profile 8% Implementation partner profile 17% Cost/benefit (NPV) 35% Strategic: Non quantifiable benefits 5% Eskom future direction 5% IT support 5% SMME/BEE policy: SW vendor 2% Implementation partner 8% TOTAL 100% Figure 11. Decision model Evaluation criteria were developed to rate and score the proposals Solicitation The software vendors submitted the names of accredited implementation partners for their products. An enquiry was issued to all potential software and implementation partners during a site meeting where the scope, specifications, contract documents and conditions, etc. were discussed. Proposals were submitted at the time of tender closing Source selection Representatives from each power station participated in the evaluations of the software functionality. The evaluation of the competency and company information of the implementation partner and software vendors was more subjective and was rated by Senior Managers as identified by the Steering Committee. Following the evaluations the decision model was populated and a score calculated. Internal and external auditors verified the results of the evaluations. Following the approval of the business case contracts were negotiated with the successful software vendor and implementation partners Contract administration During the start of the implementation project all the project team members underwent training on the NEC contracts. This afforded all to understand the rules of the game and has reaped a lot of benefits, as there are few contract issues Contract close out Contract close out will follow after the completion of the implementation project. 4 KEY LESSONS LEARNT AND CONCLUSIONS 4.1 Project Integration Management The application of the PMBOK principles work, also for very complex IT projects; Facilitation skills is an essential part of the project managers toolkit; During the start of the implementation project the project team attended a two-day project management course The TOC Way. A key lessons is: It is not important to complete each task in time, it is essential to complete the project in time.

12 4.2 Project Scope Management Need came from the business who initiated the project which implies that there was business commitment The scope statement is the foundation and guide of all project activities/happenings. It is therefor critical that it is supported by the Steering Committee and authorised by the Project Sponsor. Involve all the stakeholders during the initial scope definition and verification. It is the first step to obtain buy in for the new system. 4.3 Project Time Management The TOC principle is applied. Buffer consumption is used to monitor and evaluate project progress. 4.4 Project Quality Management A Client Quality Management Assessment (CQMA) process added value to the project by having an experienced external person broadening the visions, challenging thinking and providing creative ideas and guidance for resolving complex project problems, as well as to ensure that there are no key issues and risks overlooked. 4.5 Project Human Resource Management A project team vision (created by the project team) serves as a psychological commitment and motivates the project team to achieve success. Correct project KPI s ensure project success: It is the primary method of accounting for the results of actions being taken within the project; It is the primary source of feedback to the project sponsors and project team members alike; It has a huge influence on the actions that project team members choose to take since they do more of what has a positive impact on their measurements; Empowerment (alignment between responsibility and authority) of the project manager, team leaders and members is a necessary condition for an effective project organisation: Apply simple, effective techniques to remove obstacles preventing empowerment; Communication, i.e. give clear instructions; and Team work (synergy). 4.6 Project Communications Management Communication is directly proportional to project success, the more successful your communication is the more successful your project will be; Build stakeholders buy-in and commitment by involving them in the activities of the project that will impact them, e.g. process design, solution testing and training delivery; Involve site change management specialists and give them the responsibility to execute site interventions, as they are familiar with the site culture and the users typical reactions to change and are able to customise interventions to assist users to go through all phases of transformation; and Ensure integration between communication and change management efforts. 4.7 Project Risk Management The project team members that participate in the process enjoy the team based risk assessment approach. The identification, assessment, quantification and response planning has been entrenched in the thinking of the project team members when looking at risks.

13 4.8 Project Procurement Management Obtain approval for the procurement strategy before starting with the procurement process Seek the support from specialists in the disciplines of contract and procurement and involve them early in the process as a member of the project team. Involve all the sites with the evaluation of the software functionality. It is the commitment to the decision that counts. References 1. A Guide to the project management Body of Knowledge Edition. Exposure Draft. 2. William R Duncan. Scoping out a Scope Statement. PM Network December Peg Thomas. Creating a Shared Vision with a Project Team. PM Network January Martin Smith Martin Smit is a Project Manager and is working for Eskom Generation. He has National Diplomas in Civil and Mechanical Engineering and Datametrics. He also has a Mechanical Engineers Certificate of Competency. He has been a PMP since 1992 and also is a Professional Technologist (Engineering). He is a member of a number of Institutes and has been a Member of the Project Management Institute (USA) since He held various management positions in construction, project and maintenance management.

International Diploma in Project Management. (Level 4) Course Structure & Contents

International Diploma in Project Management. (Level 4) Course Structure & Contents Brentwood Open Learning College (Level 4) Page 1 Unit 1 Overview of Project Management The unit 1 covers the following topics: What is A Project? What is Project Management? Project Constraints Tools and

More information

HOUSE OF REPRESENTATIVES KNOTT COMMITTEE ROOM 116 OCTOBER 24, 2018

HOUSE OF REPRESENTATIVES KNOTT COMMITTEE ROOM 116 OCTOBER 24, 2018 HOUSE OF REPRESENTATIVES KNOTT COMMITTEE ROOM 116 OCTOBER 24, 2018 3 FACILITATOR: MELISSA TURNER 4 FACILITATOR: MELISSA TURNER 5 FACILITATORS: DAYMON JENSEN, RACHAEL LIEBLICK, MELISSA TURNER Budget FY

More information

Bank of Ireland. Service Integration as a means to govern a multivendor. 11 th October 2013

Bank of Ireland. Service Integration as a means to govern a multivendor. 11 th October 2013 Bank of Ireland Integration as a means to govern a multivendor IT estate 11 th October 2013 Gerry Flanagan (Accenture) Sharon Donnelly (Bank of Ireland) Agenda Introductions What is Introduction and why

More information

Project Management Framework with reference to PMBOK (PMI) July 01, 2009

Project Management Framework with reference to PMBOK (PMI) July 01, 2009 Project Management Framework with reference to PMBOK (PMI) July 01, 2009 Introduction Context Agenda Introduction to Methodologies What is a Methodology? Benefits of an Effective Methodology Methodology

More information

Plymouth Hospitals NHS Trust Business Case for replacement Managed Equipment Service

Plymouth Hospitals NHS Trust Business Case for replacement Managed Equipment Service Plymouth Hospitals NHS Trust Business Case for replacement Managed Equipment Service Purpose The Business Case describes and seeks approval to award the contract for the replacement of the existing Pathology

More information

Guidance on portfolio, programme and project management

Guidance on portfolio, programme and project management Guidance on portfolio, programme and project management The Standard for Infrastructure Procurement and Delivery Management (SIPDM) defines the following two generic terms: Portfolio: collection of projects

More information

Tusla Programme Management (PMO) Design and Establishment. Fergal Collins 20 th September 2018

Tusla Programme Management (PMO) Design and Establishment. Fergal Collins 20 th September 2018 Tusla Programme Management (PMO) Design and Establishment Fergal Collins 20 th September 2018 1 Contents Tusla Overview Executive Summary. Choosing an operating model for the PMO. 3 PMO Models to choose

More information

Project Management Process Groups. PMP Study Group Based on the PMBOK Guide 4 th Edition

Project Management Process Groups. PMP Study Group Based on the PMBOK Guide 4 th Edition Project Management Process Groups PMP Study Group Based on the PMBOK Guide 4 th Edition Introduction PM Process Groups In order for a project to be successful, the project team must: Select appropriate

More information

Revised SMIS+ implementation plan. 4 th August 2015 SMIS+ Team

Revised SMIS+ implementation plan. 4 th August 2015 SMIS+ Team Revised SMIS+ implementation plan 4 th August 2015 SMIS+ Team Content Purpose and rationale Revised implementation plan Design & Build Plan (including workstreams) Design & Build Phases Deployment Phase

More information

UNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DOCUMENTATION GUIDE: STAGE GATES

UNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DOCUMENTATION GUIDE: STAGE GATES UNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DOCUMENTATION GUIDE: STAGE GATES Document Status: Approving Body: Last Update: Author: Approved Information Services

More information

Lessons Learned Keys to Managing a Successful System Implementation Project. PMI North Alabama Chapter October 17, 2006 Huntsville, Alabama

Lessons Learned Keys to Managing a Successful System Implementation Project. PMI North Alabama Chapter October 17, 2006 Huntsville, Alabama Lessons Learned Keys to Managing a Successful System Implementation Project PMI North Alabama Chapter October 17, 2006 Huntsville, Alabama Presenter: Lourdes Godfrey Strategy Consultant, Booz Allen Hamilton

More information

CORROSION MANAGEMENT MATURITY MODEL

CORROSION MANAGEMENT MATURITY MODEL CORROSION MANAGEMENT MATURITY MODEL CMMM Model Definition AUTHOR Jeff Varney Executive Director APQC Page 1 of 35 TABLE OF CONTENTS OVERVIEW... 5 I. INTRODUCTION... 6 1.1 The Need... 6 1.2 The Corrosion

More information

IT PROJECT ANALYST/MANAGER

IT PROJECT ANALYST/MANAGER IT PROJECT ANALYST/MANAGER I. DESCRIPTION OF WORK Positions in this banded class are responsible for project management work involving planning and coordination of information technology projects. To ensure

More information

CONTRACT MANAGEMENT FRAMEWORK

CONTRACT MANAGEMENT FRAMEWORK FRAMEWORK CLIENT ENGAGEMENT 1 CONTRACT (T & Cs) COMMERCIAL ARRANGEMENTS (BUDGET) CUSTOMER REQUIREMENTS AND SCOPE 2 3 4 BUSINESS CONTINUITY PLAN KEY PERFORMANCE BENCHMARKING 5 INDICATORS 6 7 PLAN / IMPLEMENTATION

More information

Topic for today: From tactical to strategic the journey of a PMO

Topic for today: From tactical to strategic the journey of a PMO Topic for today: From tactical to strategic the journey of a PMO The Start-up PMO Structure Chief Executive Officer Director: Strategy Group Executive: Strategic Projects Project Administrator Portfolio

More information

UoD IT Job Description

UoD IT Job Description UoD IT Job Description Role: Service Delivery Manager (People HERA Grade: 8 Management Systems) Responsible to: Assistant Director (Business Services) Accountable for: Day to day leadership of team members

More information

Insurance Professional

Insurance Professional Assessment plan: Insurance Professional ST0241/AP 1. Introduction and Overview This Apprenticeship is designed as a progression route for those having completed the Insurance Practitioner or for higher

More information

DEPARTMENT OF REVENUE BUILDING 2 SEPTEMBER 26, 2018

DEPARTMENT OF REVENUE BUILDING 2 SEPTEMBER 26, 2018 DEPARTMENT OF REVENUE BUILDING 2 SEPTEMBER 26, 2018 3 FACILITATOR: RYAN WEST 4 FACILITATOR: MELISSA TURNER 5 FACILITATORS: MELISSA TURNER, CAROLYN HICKS, PAUL LAVERY, RACHAEL LIEBLICK, ANGIE ROBERTSON

More information

Department: Environment and Resources

Department: Environment and Resources Title: ICT Senior Project Manager Job Purpose: Department: Environment and Resources Post Ref: To project manage ICT and business change projects to the required standard of quality and within the specified

More information

THANK YOU! 5 PROJECT MANAGEMENT TECHNIQUES TO TRANSFORM. Learning Objectives YOUR LEADERSHIP PERFORMANCE. Kristina Krail, MPH, RN, NEA-BC, FACHE, PMP

THANK YOU! 5 PROJECT MANAGEMENT TECHNIQUES TO TRANSFORM. Learning Objectives YOUR LEADERSHIP PERFORMANCE. Kristina Krail, MPH, RN, NEA-BC, FACHE, PMP 5 PROJECT MANAGEMENT TECHNIQUES TO TRANSFORM YOUR LEADERSHIP PERFORMANCE Kristina Krail, MPH, RN, NEA-BC, FACHE, PMP November 8, 2016 2:30 PM 3:30 PM Session 132 Learning Objectives 1 2 3 To recognize

More information

ON-THE-JOB TRAINING BLUEPRINT

ON-THE-JOB TRAINING BLUEPRINT ON-THE-JOB TRAINING BLUEPRINT SUPERVISOR MODULE BUILDING EFFECTIVE CALL CENTRE WORK TEAMS Developed in collaboration with Customer Service Transformation Pte Ltd Copyright Singapore Productivity and Standards

More information

Strategy Analysis. Chapter Study Group Learning Materials

Strategy Analysis. Chapter Study Group Learning Materials Chapter Study Group Learning Materials 2015, International Institute of Business Analysis (IIBA ). Permission is granted to IIBA Chapters to use and modify this content to support chapter activities. All

More information

Capital project planning, design, delivery and operation process review City of Nanaimo November 20, 2017

Capital project planning, design, delivery and operation process review City of Nanaimo November 20, 2017 Capital project planning, design, delivery and operation process review City of Nanaimo November 20, 2017 Background Deloitte s Scope Conduct a review of the City s project planning, design, delivery and

More information

JOB DESCRIPTION. Manager Service Management Technical Systems & Proposed band. Job family

JOB DESCRIPTION. Manager Service Management Technical Systems & Proposed band. Job family Job title Job family Manager Service Management Technical Systems & Proposed Delivery band E Job purpose The Manager, Service Management is responsible for leading a functional team in one of the specialist

More information

PMI Scheduling Professional (PMI-SP)

PMI Scheduling Professional (PMI-SP) PMI Scheduling Professional (PMI-SP) E X A M I N AT I O N CO N T E N T O U T L I N E Project Management Institute PMI Scheduling Professional (PMI-SP) Exam Content Outline Published by: Project Management

More information

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3)

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3) PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3) 3.1 IV&V Methodology and Work Plan 3.1.1 NTT DATA IV&V Framework We believe that successful IV&V is more than just verification that the processes

More information

- Not Protectively Marked - NOTTINGHAMSHIRE POLICE JOB DESCRIPTION

- Not Protectively Marked - NOTTINGHAMSHIRE POLICE JOB DESCRIPTION NOTTINGHAMSHIRE POLICE JOB DESCRIPTION Job title: Department/Location: Responsible to: Responsible for: Project Manager Business & Finance Head of Programme Management N/A Date: 10 th September 2012 Library

More information

PROCESS TRAINING. DIR PM Lite 2.0 Process Training v2.0 1

PROCESS TRAINING. DIR PM Lite 2.0 Process Training v2.0 1 PROCESS TRAINING 1 PM Lite (Project Management Lite) is a project management process made up of tools, templates, and best practices that empowers its users to be more efficient and effective in project

More information

Meter Data Management System (MDMS) Sharing. Ricky Ip CLP Project Manager

Meter Data Management System (MDMS) Sharing. Ricky Ip CLP Project Manager Meter Data Management System (MDMS) Sharing Ricky Ip CLP Manager Agenda Introduction Objectives Critical Success Factors Change Management Lessons Learned 2 CLP Power Hong Kong Limited (CLP Power) is the

More information

Definition. Name of the tool or technique Project mission statement

Definition. Name of the tool or technique Project mission statement Tools and Techniques Definitions (or by alphabetic order ; see below) A definition of each of the tools and techniques is provided below. The primary sources of definitions were the PMBOK Guide and Max

More information

Aligning Process Redesign and Change Management with Project Management (System Implementation Projects)

Aligning Process Redesign and Change Management with Project Management (System Implementation Projects) Aligning Redesign and Change Management with Project Management (System Implementation Projects) Kim Brant-Lucich Director of Redesign St. Joseph Health System Information Services HIMSS 2009: Project

More information

Head of Business Strategy

Head of Business Strategy Empower Limited Job Description empower.co.tz info@empower.co.tz +255 758 778 886 9th Floor Tanzanite Park, Victoria, Dar es Salaam, Tanzania Roles and Responsibilities Head of Business Strategy Strategic

More information

Project Management Body of Knowledge (PMBoK)

Project Management Body of Knowledge (PMBoK) Project Management Body of Knowledge (PMBoK) Knowledge & Practice Areas Project Management PMBoK Prince 2 ISO 10006 General Management Application high performance sport 2 Theory vs. Practice: A Disclaimer

More information

Monthly Independent Verification and Validation Assessment Report

Monthly Independent Verification and Validation Assessment Report Monthly Independent Verification and Validation Assessment Report Florida Planning, Accounting, and Ledger Management (PALM) Project October 2017 Date: 11/13/2017 Version 1.0 Table of Contents Executive

More information

Click to edit Master title style

Click to edit Master title style Click to edit Master title style How Can We Ensure Project Success? Andrew Buchan Senior Project Advisor May 2018 Click to edit Master subtitle style OGA 2018 This presentation is for illustrative purposes

More information

The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th

The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th www.pmlead.net PMI, PMP, CAPM and PMBOK Guide are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not

More information

PROJECT MANAGEMENT. MMANC Winter Forum February 21, 2019

PROJECT MANAGEMENT. MMANC Winter Forum February 21, 2019 PROJECT MANAGEMENT MMANC Winter Forum February 21, 2019 SHUTTLE PROJECT FROM IDEA TO BUS SERVICE https://youtu.be/hksxxwvuwsa 2 SOUTH SAN FRANCISCO ROUTE 132 DISCONTINUED 3 GRANT OPPORTUNITY SHUTTLE PROGRAM

More information

Concept Paper Recommendation 6 The SCCP Prepare a Roadmap and Implementation Plan to Achieve the Single Window Vision

Concept Paper Recommendation 6 The SCCP Prepare a Roadmap and Implementation Plan to Achieve the Single Window Vision 2008/SOM3/SCCP/002attD Agenda Item: 3(i) Concept Paper Recommendation 6 The SCCP Prepare a Roadmap and Implementation Plan to Achieve the Single Window Vision Purpose: Consideration Submitted by: Australia

More information

Program and Project Responsibilities

Program and Project Responsibilities Program and Project Responsibilities The attached roles help establish a project governance system and can be adjusted for your particular organisation. Depending on the selected function(s) of your Project

More information

Core Skills: Contributing Skills: Role Title: Senior Project Manager EXAMPLE. Reference: SFIA level 5

Core Skills: Contributing Skills: Role Title: Senior Project Manager EXAMPLE. Reference: SFIA level 5 Role Title: Senior Project Manager EXAMPLE Reference: SFIA level 5 Core Skills: Requirements definition and management Stakeholder relationship management (REQM) Level 5 (RLMT) Level 5 Financial management

More information

Job description and person specification

Job description and person specification Job description and person specification Position Job title Knowledge Management Facilitator Directorate Operations and Information Pay band AFC Band 8a Responsible to NHS RightCare Knowledge Management

More information

Applied Project Management

Applied Project Management Applied Project Management Duration: 5 Days Course Code: 2807 Overview: This project simulation course combines lectures, hands-on activities, and individual and team assignments to let you experience

More information

Value Engineering. Contents are subject to change. For the latest updates visit Page 1 of 7

Value Engineering. Contents are subject to change. For the latest updates visit Page 1 of 7 Value Engineering Page 1 of 7 Why Attend Value Engineering (VE) is a conscious and explicit set of disciplined procedures designed to seek out optimum value for both initial and long-term investment. First

More information

PgMP Exam Prep Training - 4 Days

PgMP Exam Prep Training - 4 Days PgMP Exam Prep Training - 4 Days Course Length: 4 Days Course ID: PgMP Credits: 21 PDUs Course Duration: 3 or 4 days (Live in person or online class) Course Level: Advanced Day workshop- PgMP Boot Camp

More information

Brighton & Hove is committed to providing restorative practice that is safe, secure and effective and compliant to national standard

Brighton & Hove is committed to providing restorative practice that is safe, secure and effective and compliant to national standard Aim: Brighton & Hove becomes a Restorative City Definition: Restorative practice employs various methods of bringing those harmed by crime or conflict and those responsible for harm, into communication,

More information

NOT PROTECTIVELY MARKED JOB DESCRIPTION

NOT PROTECTIVELY MARKED JOB DESCRIPTION JOB DESCRIPTION APPENDIX C Before completing this form, please read the BTP Guide to writing job descriptions for Police Staff roles Appendix B to the SOP. A. POST DETAILS: Job Title: Senior IT Project

More information

Implementing a Project Infrastructure

Implementing a Project Infrastructure The PROJECT PERFECT White Paper Collection Overview Implementing a Project Infrastructure eville Turbit In working with a client recently, proved an interesting experience. The way in which the organisation

More information

Essential Duties (Roles and Responsibilities)

Essential Duties (Roles and Responsibilities) WorkFace Planner Document Number: COP-WFP-JBI-02-2013-v1 WorkFace Planner Sample Job Description WorkFace Planner Construction Superintendent Prepared by: The WorkFace Planner is responsible for the conversion

More information

IFMS Scope: Modules SCM. Financial. Management (GL) Inventory. Management. Asset. Payroll. Management HRM. Procurement Management Catalogue Management

IFMS Scope: Modules SCM. Financial. Management (GL) Inventory. Management. Asset. Payroll. Management HRM. Procurement Management Catalogue Management Status of IFMS IFMS Background The IFMS project is aimed at replacing aging and fragmented financial (including Payroll), supply chain and human resource (HR) management systems, and associated ageing

More information

POSITION DETAILS. ORGANOGRAM (Adjust as necessary. Include line manager, line manager s manager, all subordinates and colleagues. Include job grades)

POSITION DETAILS. ORGANOGRAM (Adjust as necessary. Include line manager, line manager s manager, all subordinates and colleagues. Include job grades) HR191 JOB DESCRIPTION NOTES Forms must be downloaded from the UCT website: http://www.uct.ac.za/depts/sapweb/forms/forms.htm This form serves as a template for the writing of job descriptions. A copy of

More information

Note: appendix may include further responsibilities or experience necessary for the particular role.

Note: appendix may include further responsibilities or experience necessary for the particular role. Job title Job family Lead Project Manager Project Management Proposed band E Job purpose To lead a major project, significant workstream of a programme, or portfolio of projects, to stakeholder expectations,

More information

Rapport. Organizational Overview. Contents. About Us. Our Services. Our Approach. Our Process. Client Portfolio

Rapport. Organizational Overview. Contents. About Us. Our Services. Our Approach. Our Process. Client Portfolio Rapport Organizational Overview Contents About Us Our Services Our Approach Our Process Client Portfolio 01 Welcome Message Jeanette Grover, Director At the center of our business is rapport we develop

More information

Program Management Professional (PgMP)

Program Management Professional (PgMP) Program Management Professional (PgMP) E X A M I N AT I O N CO N T E N T O U T L I N E Project Management Institute Program Management Professional (PgMP ) Examination Content Outline April 2011 Published

More information

POSITION DETAILS. Enterprise Infrastructure Services

POSITION DETAILS. Enterprise Infrastructure Services HR191 JOB DESCRIPTION NOTES Forms must be downloaded from the UCT website: http://www.uct.ac.za/depts/sapweb/forms/forms.htm This form serves as a template for the writing of job descriptions. A copy of

More information

BID NUMBER PSSS/001/2016 TERMS OF REFERENCE

BID NUMBER PSSS/001/2016 TERMS OF REFERENCE BID NUMBER PSSS/001/2016 TERMS OF REFERENCE Appointment of a Service Provider to Set-Up, Operate and Maintain a Project Management Office; Implement a Project Management System and a SharePoint Solution

More information

Project Management based on the Project Management book of knowledge

Project Management based on the Project Management book of knowledge Project Management based on the Project Management book of knowledge Integration Check parts of your plan are co-ordinated. Make trade off between competing objectives Scope Ensure the project includes

More information

Kent County Council. Job Description: Practice Development Officer - Step Up to Social Work. Children, Young People and Education. Purpose of the job:

Kent County Council. Job Description: Practice Development Officer - Step Up to Social Work. Children, Young People and Education. Purpose of the job: Kent County Council Job Description: Practice Development Officer - Step Up to Social Work Directorate: Unit/Section: Grade: Responsible to: Children, Young People and Education Children s Safeguarding

More information

PROJECT BOARD TERMS OF REFERENCE. Roles and Responsibilities

PROJECT BOARD TERMS OF REFERENCE. Roles and Responsibilities PROJECT BOARD TERMS OF REFERENCE Roles and Responsibilities 1 DOCUMENT CONTROL Change Control Table Version Amendment Description Release Date Updated by 0.1 First draft Alignment with new governance framework

More information

10 weeks 36 hours. Hone your project management knowledge and take your career to the next level with our Project Management training.

10 weeks 36 hours. Hone your project management knowledge and take your career to the next level with our Project Management training. Hone your project management knowledge and take your career to the next level with our Project Management training. 2018 Fall Course START: Monday 10/1 6-9:40pm 10 weeks 36 hours The Schoolcraft College

More information

NSW Council Amalgamations

NSW Council Amalgamations NSW Council Amalgamations Paul Williams Strategic Consulting Lead NSW Council Amalgamations TechnologyOneCorp.com Determining TechOne s Role in your Amalgamation Amalgamations will be a Journey unique

More information

Project Management Professional (PMP)

Project Management Professional (PMP) Project Management Professional (PMP) E X A M I N AT I O N CO N T E N T O U T L I N E Project Management Institute Project Management Professional (PMP) Examination Content Outline June 2015 Published

More information

Submitted to: Project Charter outlining the process to establish a credible. Revision: 1. Author: Kuben Naicker. Date:

Submitted to: Project Charter outlining the process to establish a credible. Revision: 1. Author: Kuben Naicker. Date: Project Charter outlining the process to establish a credible institutional mechanism for skills planning within CHIETA that will impact on the delivery of all 8 the NSDS III goals Revision: 1 Author:

More information

Case study: Developing effective risk management in a global mining group

Case study: Developing effective risk management in a global mining group Creating value from uncertainty Broadleaf Capital International Pty Ltd ABN 24 054 021 117 www.broadleaf.com.au Case study: Developing effective risk management in a global mining group Broadleaf helped

More information

7.11b: Quality in Project Management: A Comparison of PRINCE2 Against PMBOK

7.11b: Quality in Project Management: A Comparison of PRINCE2 Against PMBOK by Peter Whitelaw, Rational Management Pty Ltd, Melbourne Introduction This comparison takes each part of the PMBOK and provides comments on what match there is with elements of the PRINCE2 method. It's

More information

Taylor Hawes. Taylor Hawes Controller Global Platforms & Operations Microsoft Corporation

Taylor Hawes. Taylor Hawes Controller Global Platforms & Operations Microsoft Corporation Taylor Hawes Taylor Hawes Controller Global Platforms & Operations Microsoft Corporation Why this relationship is strategic Program to transform finance operations Expand Microsoft Dynamics platform Grow

More information

Title: Project Director Location: Tallahassee, FL Clearance: none required

Title: Project Director Location: Tallahassee, FL Clearance: none required Title: Project Director Location: Tallahassee, FL Clearance: none required Position Overview: The Project Director (PD) shall define, establish, and direct the planning and operations of the Project Management

More information

CLINICAL & PROFESSIONAL SUPERVISION POLICY (replacing 033/Workforce)

CLINICAL & PROFESSIONAL SUPERVISION POLICY (replacing 033/Workforce) CLINICAL & PROFESSIONAL SUPERVISION POLICY (replacing 033/Workforce) POLICY NUMBER 051/Workforce POLICY VERSION 1 RATIFYING COMMITTEE HR Policy Review Group DATE RATIFIED December 2010 NEXT REVIEW DATE

More information

Appendix. Process Inputs and Outputs

Appendix. Process Inputs and Outputs 3601cA.fm Page 493 Wednesday, October 26, 2005 12:47 AM Appendix A Process and Throughout this book, PMP: Management Professional Study Guide, 3rd Edition, I ve discussed the inputs and outputs to the

More information

Best Practices in Large Program Management

Best Practices in Large Program Management Best Practices in Large Program Management Joyce Meyer-Warren, Express Scripts Amy Easterling, Daugherty Business Solutions Slide 1 Agenda Introductions Tricare Program Overview Challenges and Solutions

More information

Program Lifecycle Methodology Version 1.7

Program Lifecycle Methodology Version 1.7 Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated

More information

Project Scope Management

Project Scope Management Project Scope Management Understand the importance of good project scope management. Discuss methods for collecting and documenting requirements in order to meet stakeholder needs and expectations. Explain

More information

ISD SENIOR MANAGER STRATEGY AND ARCHITECTURE. Purpose. More information

ISD SENIOR MANAGER STRATEGY AND ARCHITECTURE. Purpose. More information ISD SENIOR MANAGER STRATEGY AND ARCHITECTURE Information Technology (IT) and end-to-end communication systems are a critical enabler to HPUK s successful business operations. The Information Systems Department

More information

Business Case for Problem Management

Business Case for Problem Management PROBLEM MANAGEMENT ONLINE RESOURCES An implementation guide for the real world Michael G. Hall www.bcs.org/books/problem Business Case for Problem Management Date: Proposed by: Michael G Hall www.real-worldit.com

More information

Construction Project Management Training Curriculum Integration Map

Construction Project Management Training Curriculum Integration Map Construction Project Management Training Curriculum Integration Map Value of the Project Management is being recognized all over the world. Most businesses manage their business by successfully implementing

More information

Seven Consulting Benefits Management Capability Overview

Seven Consulting Benefits Management Capability Overview Introduction to Seven Consulting Seven Consulting Benefits Management Capability Overview COPYRIGHT SEVEN CONSULTING 2018 ALL RIGHTS RESER Delivering for Australia s most respected organisations since

More information

Programme & Project Planning and Execution

Programme & Project Planning and Execution Portfolio, LEADING THE WAY IN PROJECTS Programme & Project Planning and Execution Caravel Group - Project Management with a total focus on value THE SPECIALIST FOR LARGE COMPLEX MULTI-DISCIPLINED PROJECTS

More information

Logical Framework Project Example: Developing A Project Management Office

Logical Framework Project Example: Developing A Project Management Office Logical Framework Project Example: Logical Frameworks for Strategic Management The LogFrame is a practical management system that helps to plan and execute programs, projects, and strategic initiatives.

More information

Foundation Sample Paper 1

Foundation Sample Paper 1 MSP Foundation and Practitioner training ACADEMY Foundation Sample Paper 1 Copyright exists in all of this material. Copying of any kind is not permitted. D a r e t o C h a l l e n g e Page 259 Quint Wellington

More information

Monthly Independent Verification and Validation Assessment Report

Monthly Independent Verification and Validation Assessment Report Monthly Independent Verification and Validation Assessment Report Florida Planning, Accounting, and Ledger Management (PALM) Project February 2018 Date: 3/12/2018 Version 1.0 Table of Contents Executive

More information

WHITE PAPER JUNE Running a Successful Global Payroll Implementation

WHITE PAPER JUNE Running a Successful Global Payroll Implementation WHITE PAPER JUNE 2017 Running a Successful Global Payroll Implementation CONTENTS Management Summary 3 Transition from procurement to implementation 5 Preparation 6 Project Management 8 Change Management

More information

2017 Training Programmes

2017 Training Programmes 2017 Training Programmes Job Analysis & Job Evaluation Job Analysis This programme will enable you to translate strategic, tactical and operational organisational goals into clear accountabilities and

More information

Certificate IV in Project Management Student Assessment Guide

Certificate IV in Project Management Student Assessment Guide Overview The assessment for the Certificate IV in Project Management comprises Team Assignment Development of a detailed Project Management Plan for chosen case study - 30% for blended classes Individual

More information

JOB DESCRIPTION. Line Management responsibility for the Programmes Senior Programme Officers and Programme Officers

JOB DESCRIPTION. Line Management responsibility for the Programmes Senior Programme Officers and Programme Officers JOB DESCRIPTION DIRECTORATE: SECTION: JOB TITLE: Business & Skills Programme and Fund Services Assistant Programmes Manager RESPONSIBLE TO: Programmes Manager SUPERVISORY RESPONSIBILITY: KEY RELATIONSHIPS:

More information

Manager Asset Planning

Manager Asset Planning POSITION DESCRIPTION Manager Asset Planning 1 POSITION DETAILS Position Title: Reports to: Department: Location: Manager Asset Planning General Manager Assets Assets Traralgon Date: December 2018 Document

More information

Trusted KYC Data Sharing Framework Implementation

Trusted KYC Data Sharing Framework Implementation July 2017 Trusted KYC Data Sharing Framework Implementation Supporting Document Contents Preface... 3 1 Objective of this Document... 4 2 Evolving Benefits Provided by the Data Sharing Environment... 5

More information

How To Manage a Troubled Project GTC Center for Project Management, All Rights Reserved

How To Manage a Troubled Project GTC Center for Project Management, All Rights Reserved How To Manage a Troubled Project GTC 2007 1 How To Manage a Troubled Project 2 Logistics Start and finish Breaks and lunch Morning: one 15-minute break Lunch: 60 minutes Afternoon: one 15-minute break

More information

Measures for Assuring Projects

Measures for Assuring Projects Measures for Assuring Projects APM toolkit June 2016 1 @Association for Project Management 2016 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted,

More information

Director Procurement & Value Delivery

Director Procurement & Value Delivery Position Reports to Direct Reports Band Director Procurement & Value Delivery Chief Executive Heads of Procurement (3), Sustainability Officer (1), Head Procurement Operations (1), Head Clinical Engagement

More information

Note: appendix may include further responsibilities or experience necessary for the particular role.

Note: appendix may include further responsibilities or experience necessary for the particular role. Job title Job family Project Manager Project Management Proposed band D Job purpose To collaborate with a business or product owner to deliver a project, or many projects; deliver expected outcomes and

More information

Significant Service Contracts Framework

Significant Service Contracts Framework 1 Significant Service Contracts Framework The Significant Service Contracts Framework is delivered by New Zealand Government Procurement (NZGP). NZGP delivers on the Ministry of Business Innovation and

More information

PROJECT SCHEDULING & CONTROL

PROJECT SCHEDULING & CONTROL PROJECT SCHEDULING & CONTROL Project Project Management PM Knowledge Areas Time Management 1 Project What is a PROJECT? Definition used by PMI: A temporary endeavor undertaken to create a unique product,

More information

Projects: Stray Rescue

Projects: Stray Rescue Projects: Stray Rescue James Page, Jr., PMP, U. S. Postal Service Ninoska Clarkin, Edward Jones Lynn Pias, Monsanto Jim Bostick, PMP, CSC Barbara Strang, PMP Just the facts by two independent research

More information

The Ministry. Project XYZ. Assurance Plan V.02 July Document Approval. Approved by Senior Responsible Officer

The Ministry. Project XYZ. Assurance Plan V.02 July Document Approval. Approved by Senior Responsible Officer The Ministry Project XYZ Assurance Plan V.02 July 2014 Document Approval Name / Title Sign-off Date Approved by Senior Responsible Officer Endorsed by the Project Board Endorsed by Chief Executive Endorsed

More information

UNITING COMMUNITIES 1 JAN 2018 DEC 2019

UNITING COMMUNITIES 1 JAN 2018 DEC 2019 UNITING COMMUNITIES JAN 2018 DEC 2019 1 ABOUT THE ARTIST The artwork for Uniting Communities Innovate Reconciliation Action Plan titled The Coorong was completed by Ngarrindjeri Kaurna Yunkanytjatjara

More information

GOVERNANCE SMART objectives / SUHFT board development programme

GOVERNANCE SMART objectives / SUHFT board development programme GOVERNANCE SMART objectives / SUHFT board development programme Specific objective Measurable Success Actions required Relevance / Outcome Owner Time Documented set of Trust Board objectives will be in

More information

Supply chain management theory, NQF level 6, Credits 10

Supply chain management theory, NQF level 6, Credits 10 SUPPLY CHAIN MANAGER Knowledge modules 132401-001-01-00 KM-01 Supply chain theory, NQF level 6, Credits 10 132401-001-01-00 KM-02 Supply chain service delivery operational planning, NQF level 6, Credits

More information

Qualification Specification 601/3690/X icq Level 4 NVQ Diploma in Management (RQF)

Qualification Specification 601/3690/X icq Level 4 NVQ Diploma in Management (RQF) Qualification Specification 601/3690/X icq Level 4 NVQ Diploma in Management (RQF) Qualification Details Title : icq Level 4 NVQ Diploma in Management (RQF) Awarding Organisation : ican Qualifications

More information

Project Management Advisory Board Deep Dive Study of Program Management

Project Management Advisory Board Deep Dive Study of Program Management Project Management Advisory Board Deep Dive Study of Program Management Purpose The purpose of this study is twofold: 1. Understand how Saint Louis companies are managing programs 2. Study the maturity

More information

Town Hall February 5, 2019

Town Hall February 5, 2019 Town Hall February 5, 2019 Welcome and Agenda 1. Dr. Klotman s Focus Importance of Staff to the College Opportunities for Improvement Staff Feedback is Important 2. Defining Pathways and Possibilities

More information

Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room.

Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room. APM Project Fundamentals Qualification Examination paper Candidate Number Date Location Examination Paper Sample Paper v1.4 General Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use

More information