Intra-Day Trading Project. Market Participant Technical Overview. Conference call number: , pin: 79592

Size: px
Start display at page:

Download "Intra-Day Trading Project. Market Participant Technical Overview. Conference call number: , pin: 79592"

Transcription

1 Intra-Day Trading Project Market Participant Technical Overview 3 rd August 2011, am 13:00 pm Conference call number: , pin: 79592

2 Welcome Welcome to this information session on the Intra-Day Trading project. The IDT project is a significant change to the SEM and SEMO has established the following workstreams to deliver the project to the timelines requested by the SEM Committee: Modification Development; Operations Readiness; and Systems Implementation. Objectives of this meeting: The main objectives of this session are to inform Participants on the: Latest information on the IDT project across all SEMO workstreams; Main changes at a high-level that will have Participant impacts (both functional and technical); Project Schedule; and Communications framework for the duration of the Project. This session will not will not cover in depth the business rationale behind IDT this is covered within the remit of the Modifications Committee. SEMO would strongly urge all Participants to keep themselves fully informed as to the discussions held and decisions made at the Modifications Committee as these will form the basis of the final solution. 2

3 Agenda High level overview of Intra-Day Trading (IDT) High level overview of the Auction Management Platform Overview of IDT functional changes Overview of IDT technical changes Project schedule Project communications and engagement Business operational readiness Questions and answers 3

4 Why Intra-Day Trading? The EU is moving towards greater integration of electricity market arrangements to facilitate greater trading across Europe (Regulation 714/2009 of the European Parliament and Council ) EU Congestion Management Guidelines require re-allocation of unused Interconnector capacity on both D-1 and D Definition (art. 2.2 (c)): "congestion" means a situation in which an interconnection linking national transmission networks cannot accommodate all physical flows resulting from international trade requested by market participants, because of a lack of capacity of the interconnectors and/or the national transmission systems concerned.

5 Congestion Ireland Infringement Letter - June 2010 Continuing infringement cases against Ireland for violating Electricity Regulations. Issues: 1) no intra-day congestion management mechanism 2) no common co-ordinated congestion management method

6 Development of Intra-Day Trading SEM Committee Decision (SEM-10_011 March 2010) RAs to develop a Modification to facilitate intra-day trading RAs to set up a Working Group to discuss proposal and alternatives RAs to bring a proposed Modification (agreed by the Modifications Committee) to the SEM Committee, no later than September Regulatory Authorities raised Modification Mod_18_10 in March 2010

7 Activities since SEM Committee decision The Modifications Committee established a Working Group Widespread involvement from across the industry Agreement of working assumptions on all major design components Phase 1 : High Level Design Working Groups 1 to 7 25 Nov 2010 Modifications Committee Meeting 32 Modifications Committee unanimously recommended to approve High Level Design 04 March 2011 SEM Committee approve implementation of High Level Design 01 Feb 2011 Modifications Committee Meeting 33 SEMO to develop legal text based on High Level Design

8 Phase 2 of Mod_18_10 Development Phase 2 : Detailed Design 10 May 2011 Working Group 8: Functional Group 1 (Registration and Participant Submissions) 29 June 2011 Working Group 9: Functional Group 3 (Settlement and Credit Risk Management) 27 Sept 2011 Working Group 10: Functional Group 2 (Other Data Transactions, MSP Software Operation, Reports and Publications, New Query Types) 10 Nov 2011 Working Group 11: Recap of design, comments to be addressed and issues resolved 06 Dec 2011 Modifications Committee Meeting: Completed Mod_18_10 to be presented All details of Presentations, Working Group reports, Meeting Minutes etc. published on Intra-Day Trading section of SEM-O website:

9 Proposed SEM Intra-Day Trading Design: Three Gate Windows / Trading Windows OPTIMISATION TIME HORIZON Trading Day - 1 Trading Day EA EA Trading Window Ending Overlap Opt n Period Gate Window Opening (GWO) as per current Gate Window Closure (GWC) EA2 EA Interconnector Unit trades fixed EA2 Trading Window Ending Overlap Opt n Period GWO GWC WD1 EA and EA2 Interconnector Unit trades fixed Start Overlap Opt n Period WD1 Trading Window Ending Overlap Opt n Period GWO GWC GATE WINDOW 10:00 TD-29 to 09:30 TD-1 GATE WINDOW 09:30 TD-1 to 11:30 TD-1 GATE WINDOW 11:30 TD-1 to 08:00 TD

10 Agenda High level overview of Intra-Day Trading (IDT) High level overview of the Auction Management Platform Overview of IDT functional changes Overview of IDT technical changes Project schedule Project communications and engagement Business operational readiness Questions and answers 10

11 Agenda High level overview of Intra-Day Trading (IDT) High level overview of the Auction Management Platform Overview of IDT functional changes Overview of IDT technical changes Project schedule Project communications and engagement Business operational readiness Questions and answers 11

12 Overview of IDT functional changes REGISTRATION No system changes. TRADING (Pricing and Scheduling) Major change 5 Pricing Runs per Day (EA, EA2, WD1, EP1, EP2) instead of 3. Day-Ahead Market: EA and EA2. Within Day Market: WD1 Ex-Post Market (no changes): EP1 and EP2. Important Note: SEM systems are being upgraded to allow flexibility to include additional (>5) gates in the future, if such a change were to be directed by the SEM Committee. As such, it is recommended that Market Participant systems are also designed with similar flexibility. 12

13 Overview of IDT functional changes BID SUBMISSIONS BID submission for up to three runs per day (EA, EA2 and WD1) EA market will open for bids as per existing timing (TD-29) EA will close for COD bids at 09:30 TD-1. EA will close for VTOD selection at 09:20 TD-1. EA2 market will open for bids at 09:30 TD-1. EA2 will close for COD bids at 11:30 TD-1. EA2 will close for VTOD selection at 11:20 TD-1. WD1 market will open for commercial bids at 11:30 TD-1. WD1 will close at 08:00 on TD. VTOD selection is not applicable to Within-Day trading window. The latest Accepted & Utilised VTOD set will be used. That is, from EA or EA2. Note: All markets will have the same number of intervals as existing Trading Days 48 for normal day, 46 for short day, 50 for long day 13

14 BID SUBMISSIONS new elements Overview of IDT functional changes All COD submissions must include a new field: "GATE WINDOW" GATE WINDOW possible values: EA, EA2, or WD1. Interconnector COD will include an optional new field: PRIORITY ORDER. Priority Order is used to prioritise Interconnector Units under the same Code Participant - required for Offered Exposure calculations for Credit Risk purposes. Priority Order has default value = 1 More details on Interconnector Trading in later slides VTOD Selection must include a new field: "GATE WINDOW" with possible values: EA or EA2. 14

15 NEW REPORTS / PUBLICATIONS 40 new reports comprising: Overview of IDT functional changes 30 reports based on 15 existing Ex-Ante reports (split out into EA, EA2, WD1) 15 new EA2 reports 15 new WD1 reports Note: existing EA reports will have EA appended to the end of filename (example to follow) 4 brand new reports (which make up 10 reports) Excluded Bids (3 HTML/XML versions: EA, EA2, WD1) Available Credit Cover (5 HTML/XML versions: EA, EA2, WD[x], EP1, EP2) MSP Cancellation (1 HTML/XML report, ad-hoc) Cancelled Reallocation Agreement (1 CSV report, daily and ad-hoc) EA, EA2 and WD1 reports will contain the full set of Trading Intervals as per existing EA reports. 15

16 Overview of IDT functional changes CHANGED REPORTS / PUBLICATIONS (CONTENT) 27 reports with changed content (new fields) The addition of one or all of the following elements: RUN TYPE: represents the MSP Software run GATE WINDOW: represents the Trading Window associated to the record PARTICIPANT NAME: needed to identify interconnector units Addition of DELIVERY_DATE, DELIVERY_HOUR, DELIVERY_INTERVAL to Generator COD report. Addition of PRIORITY_ORDER to Interconnector COD report. Addition of ISSUE_TIMESTAMP to Daily Interconnector ATC Data report. 16

17 Overview of IDT functional changes CHANGED REPORTS / PUBLICATIONS (FILE NAMES) Ex-Ante reports will include RUN TYPE in file name. Example: MI system, Pre-IDT Report File name: PUB_D_ExAnteMktSchDetail.xml After IDT implementation, the file names will be PUB_D_ExAnteMktSchDetail_EA.xml PUB_D_ExAnteMktSchDetail_EA2.xml PUB_D_ExAnteMktSchDetail_WD1.xml On the public website, Pre-IDT file name: INDICATIVE MARKET SCHEDULE_ _ _ XML After IDT Implementation, the file names will be INDICATIVE MARKET SCHEDULE_EA_ _ _ XML INDICATIVE MARKET SCHEDULE_EA2_ _ _ XML INDICATIVE MARKET SCHEDULE_WD1_ _ _ XML Timing of publications will be confirmed in the MPUD. Note: 68 reports are not changing format or content or filename. 17

18 FUNDS TRANSFER No system changes. SETTLEMENTS No changes for non-interconnector Users For Interconnector Users: Overview of IDT functional changes 3 Interconnector Units per Interconnector User per Interconnector The 3 Interconnector Units are virtual units to enable bidding in each Gate Window (EA, EA2, WD1) Statements, Invoices and Settlement reports will include the 3 Interconnector Units CREDIT COVER Some change to be discussed in Business Readiness section later. 18

19 Agenda High level overview of Intra-Day Trading (IDT) High level overview of the Auction Management Platform Overview of IDT functional changes Overview of IDT technical changes Project schedule Project communications and engagement Business operational readiness Questions and answers 19

20 Overview of IDT technical changes Refresh of the Central Market Systems Infrastructure (Production and Test). Drivers Current CMS hardware reaches end-of-life when IDT goes live. IDT design changes take advantage of the latest hardware and 3 rd party applications. The IDT design requires a greater level of reliability, performance and flexibility. New IDT design will reduce the market outage deployment windows for future releases. 20

21 Overview of IDT technical changes impacting Participants Type 2 Client Changes New browser version IE 8 (Current version is IE 7) Formsplayer (backplanebx) (Current version is Ubiquity ) Java (no change) Windows 7 or Windows XP SP3 running IE8 Type 3 System to System changes None. Important Current CMS will not support IE 8 or Formsplayer Therefore Participant changes must take place at the same time as IDT cut-over. 21

22 Agenda High level overview of Intra-Day Trading (IDT) High level overview of the Auction Management Platform Overview of IDT functional changes Overview of IDT technical changes Project schedule Project communications and engagement Business operational readiness Questions and answers 22

23 Project Schedule summary 23

24 Project Milestones - Approval SEMC approval to implement Mod_18_10: Intra-Day Trading was received on March 4 th, 2011 and stipulated the following: The implementation will reflect the High Level Design Summary as proposed by the Modifications Committee following an extensive working group consultation which had widespread involvement from across the Industry; The CMS changes which are required for Intra-Day Trading will be developed in parallel with Modification Committee discussions on the required drafting to the TSC. All changes to the TSC will be subject to a final Modifications Committee vote and subsequently approved or otherwise by SEMC, as is the normal process; and The timeframe for rollout of the Intra-Day Trading solution will be mid Mod_43_10: Price Taker Generator Units and Firm Access was approved by the SEMC on June 7 th. Our vendors have confirmed there is sufficient capacity available for this change and it has been included in scope. Note the Release Cut-Off Date for the SEM R2.0.0 release to the CMS is August 5 th,

25 Project Milestones Detailed Requirements / Contract Detailed Requirements phase: December 1 st 2010 to April 30 th 2011 Detailed Requirements derived from the High Level Design Summary as proposed by the Modifications Committee; Five iterations of the Detailed Requirements Baseline, covering all subsystems, were generated. Three workshops held with our vendors (December, January & April) to develop a common understanding of the Detailed Requirements; Baseline 5.0 formed the basis of the Statement of Work with our vendors and was signed off at the end of April. Contract was formally signed with our vendors mid-june following extensive discussions re the Statement of Work, Project Governance, schedule etc. 25

26 Project Milestones Vendor Detailed Design Phase Vendor Detailed Design phase: May 3rd to July 29 th 2011 Multiple iterations of review of vendor design documentation; Week long face to face design walkthrough with vendors to: Provide direction/clarification on detailed requirements; and Ensure vendor and SEMO have a common understanding of the detailed requirements. Detailed Design closed July 29 th some immaterial comments outstanding which will be delivered in the as built documentation suite. 26

27 Project Milestones Participant Design Deliverables MPUD / MPI MPUD (including XSD files): target publication date August 29 th 2011 The MPUD is a representation (translations) of the vendor design for Participant consumption. As communicated at MOUG of July 19 th the MPUD will be re-engineered following consultation with Participants into a number of constituent documents as follows: MPUD Overarching Document; MPUD Market Interface Volume 1 (Trading and Registration); MPUD Market Interface Volume 2 (Reporting); and MPUD Technical Volume. The MPUD will be subject to change as follows: Possibility of late addition to scope, e.g. release cut-off date August 5 th etc.; Development of Mod_18_10 in parallel introduces a possibility of change; and Changes forced on our vendors as development progresses. MPI User Guide: target publication date January 30 th 2012 This document will reflect the as-built systems (i.e. post development and delivery) Predominantly geared towards Type 2 Participants. 27

28 Project Milestones Factory Testing (FT) Factory Test phase: November 14 th to December 23 rd Conducted at vendor site; Executed by vendors and witnessed by SEMO; Scripted tests/scenarios approved by SEMO; Objectives: Test that the systems and software functions correctly in line with the agreed design Demonstrate that the software can be delivered for System Integration Testing. Strict Exit Criteria will apply before SEMO will accept delivery of software. 28

29 Project Milestones System Integration Testing (SIT) System Integration Test phase: January 3 rd 2012 to April 27 th 2012 Internal test phase conducted at SEMO site; Fully scripted against agreed requirements and design; Executed by SEMO (with the exception of UUC Certification), supported by our vendors; Objectives: Test that the systems and software functions correctly in line with the agreed design; and Verify the integration of the systems with legacy systems and external interfaces. This time period also encompasses a number of additional test phases: Certification Testing (independent third-party verification of UUC); TSO / IA Testing; Technical Testing; and Performance Testing. 29

30 Project Milestones Market Trial (MT) Market Trial: Preparation January 27 th to April 30 th 2012 Execution April 30 th to July 6 th 2012 Industry wide test phase, managed and co-ordinated by SEMO Will have a dedicated test team Consultation with Industry will begin in January 2012 Objectives: test the inter-operability of participant systems and processes with the CMS; test compliance of the participant business systems and processes with their obligations as defined in the T≻ and test all market procedures and the ability of Market Participants and SEMO (in its role as Market Operator) to follow these procedures. Full simulation of Market Operations including Market Participants, TSOs, IA etc. Fully scripted against agreed requirements and design. IDT Participant Training will be held in advance (early April). Connectivity testing one week prior to execution phase. Environment available for ad-hoc testing post Market Trial and before deployment. 30

31 Project Milestones Deployment Proposed deployment date is July 20 th 2012 subject to: successful completion of all phases of testing; and all parties have indicated readiness to proceed with deployment. 31

32 October 2012 release to the Central Market Systems When considering work programmes and resources for the IDT release, Participants should note that the October 2012 release (SEM R2.1.0) to the Central Market Systems will proceed as scheduled. The Release Cut-Off Date for SEM R2.1.0 is Friday November 18 th,

33 Agenda High level overview of Intra-Day Trading (IDT) High level overview of the Auction Management Platform Overview of IDT functional changes Overview of IDT technical changes Project schedule Project communications and engagement Business operational readiness Questions and answers 33

34 Project Communications and Engagement Systems Group (1 of 2) To ensure effective and clear communication of project progress and activities SEMO will adopt the following communications strategy for the duration of the project: Monthly Project Management Forum (PMF) meetings and/or conference calls to: Deliver project progress updates; Communicate upcoming activities; Communicate changes (if any); and Discuss any topics as requested by Market Participants. Face to Face Meetings will alternate between Dublin and Belfast. Meetings will commence approximately 2 weeks after the MPUD is initially issued. Dedicated design workshops to cover MPUD and technical changes (number and dates to be confirmed). Normal updates will also be communicated via: The MOUG meetings and conference calls; and The SEMO website ( Note Market Trial will have a dedicated and separate communications plan which will be consulted on in January

35 Project Communications and Engagement Systems Group (2 of 2) At key milestones of the project, Participants will be invited to indicate their state of readiness in the context of the overall schedule. Suggested milestones are as follows: November 2011, as Factory Test commences; End February 2012, two months prior to Market Trial; (mid way through SIT); Mid-April 2012 (2 weeks prior to the beginning of Market Trial); Beginning of June 2012 (mid-way through Market Trial); and Beginning of July (towards the end of Market Trial). These indicators will enable SEMO to effectively manage any potential risk to the overall programme and put in place: any necessary measures to mitigate any associated risk and/or put in place appropriate contingency measures if required. 35

36 Agenda High level overview of Intra-Day Trading (IDT) High level overview of the Auction Management Platform Overview of IDT functional changes Overview of IDT technical changes Project schedule Project communications and engagement Business operational readiness Questions and answers 36

37 Basis for Information Current position taken from. High-level Intra-Day Design Intra-Day Workgroups to date Drafts of Code Modifications to date SEMO Business Process Design to date SEMO view of what Participants do you know your own business best! Final Code and Agreed Procedures not until December

38 A Day in the Life (of Pricing) CD - 1 Calendar Day CD-1 11:30 COD, FD CD 08:00 WD1 CD 09:30 Gate Window Opening CD-29 09:30 Gate Window Closure COD, VTOD, FD Publishing Initial Conditions EA1 CD 11:00 Gate Window Opening Gate Window Closure Publishing CD 11:30 CD 13:00 COD, TOD, FD EA2 Gate Window Opening Gate Window Closure Publishing CD 14:00 EP1 CD = Calendar Day COD = Commercial Offer Data FD = Forecast Data VTOD = Validation Technical Offer Data (submit new set, choose set) TOD = Technical Offer Data (choose set) TW = Trading Window WD1 = Within-Day EA1 = Ex-Ante 1 EA2 = Ex-Ante 2 EP1 = Ex-Post Indicative EP2 = Ex-Post Initial EP2 38

39 Pricing and Scheduling (Major Change) Key Changes for Participants Five Pricing Runs per Day Submission of bids for up to three runs per day (EA1, EA2 and WD1) Use latest accepted and utilised bid data, or default data if no bids Submission of TOD allowed dependent on run Different gate opening and closing times for each run (EA1, EA2, WD1) Output from five pricing runs per day Cancellation of pricing runs under certain circumstances Consideration of changes to communication and system failures processes Interconnector Trading Separate bid submission for same Interconnector User in different EA1, EA2, WD1 pricing runs (3 interconnector units, but only one relevant per gate window) Limited time to adjust position between EA1 output and EA2 gate window closure Participants to consider Available Credit Cover before submit Interconnector Bids Market systems to exclude bids for Interconnectors where insufficient Available Credit Cover 39

40 Credit Cover (Some Change) Key Changes for Participants Published Information Credit Report extra information Traded Exposure for Interconnector Units No Undefined Exposure for Interconnector Units More calculation parameters included in report (Estimated Prices, Exposure Periods etc) Use of instead of fax for communication of CCIN New SRA Cancellation Report from credit cover reporting Timelines Required Credit Cover Reports 14:30 hours instead of 17:00 hours Credit Cover Increase Notices still by 17:00 hours but via not fax Interconnectors Available Credit Cover Report after each Pricing Run Interconnector Users need to better manage credit cover Otherwise more CCINs Exclusion of bids where insufficient Available Credit Cover 40

41 Key Changes for Participants Formal Queries (Minor Change) Two new formal query options Credit Cover Reports (Daily) Excluded Bids and Available Credit Cover Reports (for Interconnector Users) Settlement (No Change) No changes to process or timelines Three units per Interconnector User per Interconnector (covering EA1, EA2, WD1) will be shown on statements/reports and invoices Funds Transfer (No Change) No changes to process, timelines or volume of invoices 41

42 SEMO website Intra-Day High-level Design Intra-Day Design Working Groups Presentations Minutes of meetings Need More Information? Intra-Day Communications Monthly updates at MOUG meetings; and Technical/Operational PMFs for IT and Business Readiness. Participant Training April 2012 After modifications approved After SEMO business processes finalised Before Market Trial 42

43 Agenda High level overview of Intra-Day Trading (IDT) High level overview of the Auction Management Platform Overview of IDT functional changes Overview of IDT technical changes Project schedule Project communications and engagement Business operational readiness Questions and answers 43

Market Trial Working Group I-SEM Project

Market Trial Working Group I-SEM Project Market Trial Working Group I-SEM Project Dublin, 31 August 2017 1 Overview of the Session Meeting Details Meeting Purpose Chair Secretariat I-SEM Market Trial Working Group Mark Needham Louise Dalton Amy

More information

I-SEM Interconnectors Project

I-SEM Interconnectors Project Moyle EWIC I-SEM Interconnectors Project Financial Transmission Rights Auction: Initial Trial Report VERSION: 1.0 STATUS: Final for Publication DATE: 29 th SEPTEMBER 2017 Contents Introduction... 3 Objectives

More information

I-SEM Business Liaison Group NEMO. 09 November2017

I-SEM Business Liaison Group NEMO. 09 November2017 I-SEM Business Liaison Group NEMO 09 November2017 1 Agenda Update on NEMO Implementation Project TSO Counter trading Market Trial 2 Agenda Update on NEMO Implementation Project TSO Counter trading Market

More information

I-SEM Interconnectors Project

I-SEM Interconnectors Project Moyle EWIC I-SEM Interconnectors Project Financial Transmission Rights Auction: Trial and Participant Test Plan VERSION: 1.1 STATUS: Final for Publication DATE: 17 th JULY 2017 Contents Introduction...

More information

Business Process. BP_SO_12.1 Unit Testing

Business Process. BP_SO_12.1 Unit Testing Business Process BP_SO_12.1 Unit Testing EirGrid and SONI support the provision of information to the marketplace by publishing operational data, processes, methodologies and reports. This information

More information

Integrated Marketplace. Participant Training Update. April 18, Gay Anthony SPP Customer Training

Integrated Marketplace. Participant Training Update. April 18, Gay Anthony SPP Customer Training Integrated Marketplace Participant Training Update April 18, 2012 Gay Anthony SPP Customer Training ganthony@spp.org Training Update Live deliveries of the Marketplace Overview and Preparing for TCR Mock

More information

DS3 System Services Project Plan Detailed Design and Implementation Phase

DS3 System Services Project Plan Detailed Design and Implementation Phase DS3 System Services Project Plan Detailed Design and Implementation Phase Dated: 20/5/2015 Executive Summary The System Services work stream within the DS3 Programme relates to the procurement of services

More information

SEMOpx Day-ahead Market Products Stage 3 Progress Report. May 2017

SEMOpx Day-ahead Market Products Stage 3 Progress Report. May 2017 SEMOpx Day-ahead Market Products Stage 3 Progress Report May 2017 Contents 1 Introduction... 3 2 Purpose of the Document... 4 3 IAT STAGES... 4 4 Scope of IAT... 6 5 Structure of IAT... 6 5.1 Creation

More information

Chapter 2: Inputs. Chapter 3: Inputs

Chapter 2: Inputs. Chapter 3: Inputs Chapter 2: Inputs Chapter 3: Inputs 1 Foreword (1/2) This section describes the data inputs to the scheduling and dispatch process including the source of the data and how it is used. There are thousands

More information

I-SEM Testing Tariff High Level Options Consultation

I-SEM Testing Tariff High Level Options Consultation I-SEM Testing Tariff High Level Options Consultation 02 June 2017 Version 1.0 EXECUTIVE SUMMARY Testing Tariffs are currently applied to Units Under Test (UUT) in the Single Electricity Market (SEM) on

More information

European Update. 2nd July 2015

European Update. 2nd July 2015 European Update Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. 2nd July 2015 1. General Update

More information

I-SEM Milestones. November 2017

I-SEM Milestones. November 2017 I-SEM Milestones November 2017 1 1.1 Milestone Descriptions Includes update since the approval of JCR 170 Ref Milestone & Description RA / TSO Baseline Date 1 2 3 4 5 6 7a 7b 7c Start Balancing Market

More information

Settlement Frequently Asked Questions Contents

Settlement Frequently Asked Questions Contents Contents 1. What is the Settlement Calendar?... 3 2. How do I View my Invoices?... 3 3. Where can I see the Settlement Calendar?... 6 4. What are SEMO s Settlement Publication Timelines?... 7 5. What Payments

More information

(Non-legislative acts) REGULATIONS

(Non-legislative acts) REGULATIONS 15.6.2013 Official Journal of the European Union L 163/1 II (Non-legislative acts) REGULATIONS COMMISSION REGULATION (EU) No 543/2013 of 14 June 2013 on submission and publication of data in electricity

More information

Balancing Market Principles Statement

Balancing Market Principles Statement Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements Version 1.0 8 September 2017 Version Control Version No. Date Notes 1.0

More information

Joint European Stakeholder Group. Tuesday 9 January 2018 Meeting 28 WebEx

Joint European Stakeholder Group. Tuesday 9 January 2018 Meeting 28 WebEx Joint European Stakeholder Group Tuesday 9 January 2018 Meeting 28 WebEx Agenda ID Title Lead Time 1. Welcome & Introductions Chair 10:00-10:05 2. National Grid Update: European Network Codes Implementation

More information

Unique Sites Plan: Risk Assessment

Unique Sites Plan: Risk Assessment Unique Sites Plan: Risk Assessment Exec summary The US plan is presently on track The US plan contains a high risk profile which is primarily driven by the following factors: Object overlaps with core

More information

SEMOpx Day-ahead Market Products Stage 2 Progress Report. March 2017

SEMOpx Day-ahead Market Products Stage 2 Progress Report. March 2017 SEMOpx Day-ahead Market Products Stage 2 Progress Report March 2017 Contents 1 Introduction... 2 2 Purpose of the Document... 3 3 IAT STAGES... 4 4 Scope of IAT... 4 5 Structure of IAT... 5 5.1 Creation

More information

Billing System Corrections (Baseline)

Billing System Corrections (Baseline) 2 A66 Billing System Corrections (Baseline) Billing Rate Schedule Allocation 8/2 Status: Billing system problem resolution continues on a regular basis by a dedicated team of development staff Once identified,

More information

Balancing Market Principles Statement

Balancing Market Principles Statement Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements Version 2.0 11 th April 2018 Version Control Version No. Date Notes 1.0

More information

European Developments

European Developments European Developments Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Transmission Workgroup

More information

Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements

Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements CONSULTATION VERSION 7 April 2017 IMPORTANT INFORMATION This Balancing

More information

UK Link Shipper Engagement Day Agenda

UK Link Shipper Engagement Day Agenda UK Link Shipper Engagement Day Agenda Date: Thursday 2 nd October Venue: The Studios, Birmingham (capacity 120 cabaret style) Purpose: Share file formats overlaid on To-be processes following formal release

More information

11/02/2016. The Scheduling & Dispatch Process in I-SEM - Design Interpretation

11/02/2016. The Scheduling & Dispatch Process in I-SEM - Design Interpretation 11/02/2016 The Scheduling & Dispatch Process in I-SEM - Design Interpretation Release Date Version No. Summary of Changes 11/02/2016 1.0 Design Interpretation document published for discussion at Market

More information

Regulatory Authority Annual Report. Market Operator Performance

Regulatory Authority Annual Report. Market Operator Performance Regulatory Authority Annual Report Market Operator Performance Period: 1st October 2015 to 30th September 2016 Table of Contents 1 INTRODUCTION... 3 2 MANAGE CHANGE... 4 2.1 IT CAPITAL EXPENDITURE... 4

More information

Market Redesign and Technology Upgrade Budget and Schedule Report

Market Redesign and Technology Upgrade Budget and Schedule Report Market Redesign and Technology Upgrade Budget and Schedule Report Executive Sponsor: Charles A. King, PE Project Manager: Debi Le Vine Board of Governors Meeting October 17, 2007 General Session MRTU Executive

More information

Status: Functional Requirement Specification completed on March 15 th. Development is in progress and a September deployment is planned.

Status: Functional Requirement Specification completed on March 15 th. Development is in progress and a September deployment is planned. Billing System Corrections (Baseline) Status: Billing system problem resolution continues on a regular basis by a dedicated team of development staff Once identified, billing issues are reviewed, solutions

More information

IMPLEMENTATION OF A SECURITY- CONSTRAINED MARKET MODEL

IMPLEMENTATION OF A SECURITY- CONSTRAINED MARKET MODEL IMPLEMENTATION OF A SECURITY- CONSTRAINED MARKET MODEL November 2017 PRESENTED BY AEMO AND PUBLIC UTILITIES OFFICE SLIDE 1 PLANNING FOR FUTURE MARKET REFORMS - AEMO AEMO is working closely with the Public

More information

EU Phase 3 Update. Chris Logue Gas Markets Manager

EU Phase 3 Update. Chris Logue Gas Markets Manager EU Phase 3 Update Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Chris Logue Gas Markets Manager

More information

Alberta Capacity Market

Alberta Capacity Market Alberta Capacity Market Comprehensive Market Design (CMD 1) Design Proposal Document Section 1: Overview of the Alberta Capacity Market Prepared by: Alberta Electric System Operator Date: January 26, 2018

More information

Chapter 3: The Scheduling & Chapter 4: The Scheduling and Dispatch Process

Chapter 3: The Scheduling & Chapter 4: The Scheduling and Dispatch Process Chapter 3: The Scheduling & Chapter 4: The Scheduling and Dispatch Process 1 Foreword Our scheduling and dispatch process incorporates a range of activities associated with managing the close to real-time

More information

I-SEM Trialing of EUPHEMIA: Initial Phase Results Overview. I-SEM EUPHEMIA Working Group 16 th April 2015

I-SEM Trialing of EUPHEMIA: Initial Phase Results Overview. I-SEM EUPHEMIA Working Group 16 th April 2015 I-SEM Trialing of EUPHEMIA: Initial Phase Results Overview I-SEM EUPHEMIA Working Group 16 th April 2015 EUPHEMIA Workshop Agenda Background of EUPHEMIA algorithm Overview of background and goal of EUPHEMIA

More information

I-SEM Small Wind Information Session. 24 November 2016

I-SEM Small Wind Information Session. 24 November 2016 I-SEM Small Wind Information Session 24 November 2016 1 Agenda 1. I-SEM Market Overview 2. I-SEM Registration Overview 3. Market Readiness Update 4. Market Trial Update 5. Systems Overview 6. AOB 2 Power

More information

Gas Charging Review. NTSCMF 5 April 2017 Final slide pack Update provided on 3 April All slides added or updated are marked with a blue star

Gas Charging Review. NTSCMF 5 April 2017 Final slide pack Update provided on 3 April All slides added or updated are marked with a blue star Gas Charging Review Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. NTSCMF 5 April 2017 Final

More information

ECB-UNRESTRICTED T2S OPERATIONAL GOVERNANCE PROCESS FRAMEWORK

ECB-UNRESTRICTED T2S OPERATIONAL GOVERNANCE PROCESS FRAMEWORK T2S OPERATIONAL GOVERNANCE PROCESS FRAMEWORK Status: Baseline TABLE OF CONTENTS 1 INTRODUCTION... 1 2 CHANGE MANAGEMENT... 3 2.1 CHANGE MANAGEMENT FOR COMMON AND SPECIFIC CHANGE... 3 2.2 PRINCIPLES...

More information

IBM Infrastructure Security Services - Managed Security Information and Event Management (Managed SIEM)

IBM Infrastructure Security Services - Managed Security Information and Event Management (Managed SIEM) IBM Infrastructure Security Services - Managed Security Information and Event Management (Managed SIEM) DK_INTC-8838-00 11-2011 Page 1 of 17 Table of Contents 1.Scope of Services...3 2.Definitions...3

More information

Balancing Registration Data User Guide

Balancing Registration Data User Guide Balancing Registration Data User Guide 29 th March 2017 Version 1.2 EirGrid 2016. Commercial In Confidence. Revision History Summary of Changes Version Revised By Initial Publication 1.0 I-SEM Project

More information

2005 Major Projects. Project Description. Status and Milestone Deliverables

2005 Major Projects. Project Description. Status and Milestone Deliverables . 4 A799 Billing Simulator Status: Use case functionality has been delivered iteratively throughout 2005 as planned. The last phase of the project includes delivery of the remaining 39 use cases which

More information

REQUEST FOR AMENDMENT BY ALL REGULATORY AUTHORITIES AGREED AT THE ENERGY REGULATORS FORUM ON

REQUEST FOR AMENDMENT BY ALL REGULATORY AUTHORITIES AGREED AT THE ENERGY REGULATORS FORUM ON REQUEST FOR AMENDMENT BY ALL REGULATORY AUTHORITIES AGREED AT THE ENERGY REGULATORS FORUM ON ALL NEMO s PROPOSAL FOR BACK-UP METHODOLOGY SUBMITTED IN ACCORDANCE WITH ARTICLE 36(3) OF THE COMMISSION REGULATION

More information

Council of the European Union Brussels, 13 December 2017 (OR. en)

Council of the European Union Brussels, 13 December 2017 (OR. en) Council of the European Union Brussels, 13 December 2017 (OR. en) Interinstitutional File: 2016/0379 (COD) 15237/17 ADD 1 NOTE ENER 487 ENV 1016 CLIMA 336 COMPET 841 CONSOM 384 FISC 322 CODEC 1970 From:

More information

Business Rules. Incremental Proposal

Business Rules. Incremental Proposal INC00148-14 2 April 2014 DRAFT Business Rules I. Introduction The objective of this document is to specify business rules based on the ACER Guidance for the amendment on the CAM NC and the ACER Tariff

More information

I-SEM Programme Project Office Programme Change Control Procedure

I-SEM Programme Project Office Programme Change Control Procedure Project Office Programme Change Control Procedure Version: 1.1 FINAL Date: 8 March 2017 Document Control Production Authors Responsibility Date Jim McAllister I-SEM PMO 01/07/2015 Helen Mounsey I-SEM PMO

More information

MARKET MANUAL. Part 9.3: Operation of the Day-Ahead Commitment Process PUBLIC. Enhanced Day-Ahead Commitment (EDAC) Market Manual. EDAC Issue 0.1.

MARKET MANUAL. Part 9.3: Operation of the Day-Ahead Commitment Process PUBLIC. Enhanced Day-Ahead Commitment (EDAC) Market Manual. EDAC Issue 0.1. MARKET MANUAL PUBLIC Enhanced Day-Ahead Commitment (EDAC) Market Manual Part 9.3: Operation of the Day-Ahead Commitment Process EDAC Issue 0.1.6 This procedure provides guidance to Market Participants

More information

Capacity Market Technical Design Stakeholder Update Session

Capacity Market Technical Design Stakeholder Update Session Capacity Market Technical Design Stakeholder Update Session Straw Alberta Market (SAM 3.0) Dec. 11, 2017 Session outline Time Agenda Item 1:30 1:35 p.m. Welcome and session overview: Matt Gray, AESO 1:35

More information

Joint European Stakeholder Group. Thursday 21 September 2017 Meeting 24 WebEx

Joint European Stakeholder Group. Thursday 21 September 2017 Meeting 24 WebEx Joint European Stakeholder Group Thursday 21 September 2017 Meeting 24 WebEx Agenda ID Title Lead Time 1 Welcome & Introductions Chair 10:00-10:05 2 CACM Methodologies, Inc. Recent Submission of the Capacity

More information

Market Simulation Fall 2018 Release

Market Simulation Fall 2018 Release Market Simulation Fall 2018 Release Trang Deluca Sr. Change & Release Planner September 17, 2018 Recordings Calls and webinars are recorded for stakeholder convenience, allowing those who are unable to

More information

Market Operator User Group. Dublin, 22 November 2018

Market Operator User Group. Dublin, 22 November 2018 Market Operator User Group Dublin, 22 November 2018 1 Agenda Item Welcome Ex-Ante Market Balancing Market Disputes, Repricing and Resettlement Update Settlements & Funds Transfer Known Issues Update Query

More information

I-SEM Project Managers Group (PMG) 15 November 2017 Key Notes, Actions & Decisions

I-SEM Project Managers Group (PMG) 15 November 2017 Key Notes, Actions & Decisions I-SEM Project Managers Group (PMG) 15 November 2017 Key Notes, Actions & Decisions Meeting Details Meeting Purpose Location Chair Secretariat I-SEM Project Managers Group (PMG) EirGrid, Dublin / Conference

More information

5MS Systems Working Group

5MS Systems Working Group 5MS Systems Working Group SWG#1 - Friday, 24 August 2018 AEMO Offices: Level 9, 99 Gawler Place, Adelaide Level 10, 10 Eagle Street, Brisbane Level 22, 530 Collins Street, Melbourne Level 2, 20 Bond Street,

More information

Introducing PRISMA European Capacity Platform

Introducing PRISMA European Capacity Platform Introducing PRISMA European Capacity Platform Background of the company and current developments Allocation of Gas Transmission Capacities in the Energy Community Workshop 14 March 2016, Vienna Agenda

More information

3 rd EU Stakeholder Committee Meeting

3 rd EU Stakeholder Committee Meeting 3 rd EU Stakeholder Committee Meeting 03.02.2016 Content 1. Project Progress Key Achievements Challenges 2. Project Timeline 3. Local Implementation Projects and update on Belgian Borders Quick Wins 4.

More information

where implicit capacity allocation methods are applied, national regulatory authorities may decide not to apply Articles 8 to 37.

where implicit capacity allocation methods are applied, national regulatory authorities may decide not to apply Articles 8 to 37. System Operator's METHODOLOGY OF GAS TRANSMISSION CAPACITY ALLOCATION AND CONGESTION MANAGEMENT PROCEDURE AND STANDARD TERMS FOR ACCESSING THE CROSS-BORDER INFRASTRUCTURE 30 th June 2017 1. General provisions...

More information

European Transparency Regulation (ETR / ERGEG) Industry briefing (02-Apr-2014 session) Author: NG ETR team Last Updated: 01-Apr-2014 (V1.

European Transparency Regulation (ETR / ERGEG) Industry briefing (02-Apr-2014 session) Author: NG ETR team Last Updated: 01-Apr-2014 (V1. European Transparency Regulation (ETR / ERGEG) Industry briefing (02-Apr-2014 session) Author: NG ETR team Last Updated: 01-Apr-2014 (V1.1) Agenda Item Approximate start time Welcome: Tea and coffee 09:30

More information

Market Simulation Fall 2018 Release

Market Simulation Fall 2018 Release Market Simulation Fall 2018 Release Trang Deluca Sr. Change & Release Planner October 8, 2018 Recordings Calls and webinars are recorded for stakeholder convenience, allowing those who are unable to attend

More information

BlackBerry Enterprise Mobility Suite Management Edition Jumpstart

BlackBerry Enterprise Mobility Suite Management Edition Jumpstart BlackBerry Enterprise Mobility Suite Management Edition Jumpstart Program Description, August 2017 BlackBerry Enterprise Mobility Suite Management Edition Jumpstart Program Description ( Management Edition

More information

SMD2 Implementation Status Report

SMD2 Implementation Status Report SMD2 Implementation Status Report Rich Dewey Market Structures Working Group November 19, 2004 Revised Deployment Date MP concerns with the December date impacting ability to satisfy 2004 audit requirements

More information

Retail Markets Co-Ordination Working Group

Retail Markets Co-Ordination Working Group Retail Markets Co-Ordination Working Group Wednesday, 14 th January, 2015 CER Offices Dublin Retail Market Design Service ReMCoWG Agenda Agenda Item Presenter Time Introduction J Gregory ReMCoDS 12:30

More information

RDRP Stakeholder Initiative

RDRP Stakeholder Initiative Reliability Demand Response Product RDRP Stakeholder Initiative Draft Final Proposal Review Stakeholder Conference Call September 13, 2010 Reliability Demand Response Product (RDRP) 1 2 3 We are here Project

More information

RCM3 UPDATE. July 2017 PRESENTED BY AEMO SLIDE 1

RCM3 UPDATE. July 2017 PRESENTED BY AEMO SLIDE 1 RCM3 UPDATE July 2017 PRESENTED BY AEMO SLIDE 1 AGENDA High Level Timetable Release 1 o Showcase o Market Trial Release 2 o Proposed Showcases Release 3 o Internal to AEMO no impact on Participants Procedure

More information

TSOs proposal for the methodology for Coordinated Redispatching and Countertrading in accordance with Article 35(1) of Commission Regulation (EU)

TSOs proposal for the methodology for Coordinated Redispatching and Countertrading in accordance with Article 35(1) of Commission Regulation (EU) TSOs proposal for the methodology for Coordinated Redispatching and Countertrading in accordance with Article 35(1) of Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a guideline on capacity

More information

Electricity Market Reform Capacity Market Implementation Plan

Electricity Market Reform Capacity Market Implementation Plan Electricity Market Reform Capacity Market Implementation Plan This implementation plan identifies the key milestones and activities required to successfully implement the Capacity Mechanism Version 1.2

More information

C-Roads Platform Terms of Reference

C-Roads Platform Terms of Reference C-Roads Platform Terms of Reference Dissemination level: C-Roads Platform internal Author: AustriaTech Status: Final Index 1 Purpose... 3 2 Governance Structure... 4 3 C-Roads Steering... 6 3.1 Tasks and

More information

ENERGY IMBALANCE MARKET BUSINESS PRACTICE ( EIM BP ) TABLE OF CONTENTS 1. Introduction 2. Communication with the PSEI EIM Entity 3.

ENERGY IMBALANCE MARKET BUSINESS PRACTICE ( EIM BP ) TABLE OF CONTENTS 1. Introduction 2. Communication with the PSEI EIM Entity 3. ENERGY IMBALANCE MARKET BUSINESS PRACTICE ( EIM BP ) TABLE OF CONTENTS 1. Introduction 2. Communication with the PSEI EIM Entity 3. PSEI EIM Participating Resource Application and Processing 3.1 Application

More information

Business Practice Manual for The Transmission Planning Process

Business Practice Manual for The Transmission Planning Process Business Practice Manual for The Transmission Planning Process Posted: June 2, 2015 Intentionally left blank TABLE OF CONTENTS 1. Introduction... 9 1.1. Purpose of California ISO Business Practice Manuals...

More information

Design options of TERRE Project. (Trans European Replacement Reserves Exchange) Executive Summary

Design options of TERRE Project. (Trans European Replacement Reserves Exchange) Executive Summary Design options of TERRE Project (Trans European Replacement Reserves Exchange) Executive Summary 15 th of June 2016 Executive Summary TERRE (Trans European Replacement Reserve Exchange) is the pilot project

More information

Capacity Market Auction Guidelines

Capacity Market Auction Guidelines Capacity Market Auction Guidelines 2018 year ahead Capacity Auction (T-1) Delivery year 2019/20 2018 four year ahead Capacity Auction (T-4) Delivery year 2022/23 Capacity Market Auction Guidelines 19 th

More information

NATIONAL GRID GAS PLC-UK. Moderator: Sue Hughes-Payne May 16, :07 am CT

NATIONAL GRID GAS PLC-UK. Moderator: Sue Hughes-Payne May 16, :07 am CT NATIONAL GRID GAS PLC-UK Moderator: Sue Hughes-Payne May 16, 2018 5:07 am CT Coordinator: Thank you for standing by. At this time all participants are in listen in only mode. After the presentation we

More information

C-Roads Platform Terms of Reference

C-Roads Platform Terms of Reference C-Roads Platform Terms of Reference Dissemination level: C-Roads Platform internal Author: AustriaTech Status: Final C-Roads Platform Coordinator AustriaTech www.austriatech.at Index 1 Purpose... 3 2 Governance

More information

DEVELOPMENTS IN WESTERN MARKETS: RENEWABLES AND EXPANSION OF ORGANIZED MARKETS IN THE WEST

DEVELOPMENTS IN WESTERN MARKETS: RENEWABLES AND EXPANSION OF ORGANIZED MARKETS IN THE WEST DEVELOPMENTS IN WESTERN MARKETS: RENEWABLES AND EXPANSION OF ORGANIZED MARKETS IN THE WEST Power Regulatory Webinar Series Deanna E. King Stephen J. Hug September 28, 2016 CURRENT DEVELOPMENTS IN WESTERN

More information

Electricity Market Reform Capacity Market Operational Plan

Electricity Market Reform Capacity Market Operational Plan Electricity Market Reform Capacity Market Operational Plan This plan identifies the key milestones and activities required to deliver the Capacity Market Auctions in 2017 / 2018 Version 2.0 Published 15

More information

Interim Governance Arrangements for All Island Retail Market Harmonisation Project

Interim Governance Arrangements for All Island Retail Market Harmonisation Project Interim Governance Arrangements for All Island Retail Market Harmonisation Project Document Revision History Version Date Summary of Change Author Number 2 21 Oct 2009 First draft for review Various 3

More information

GTE+ Capacity Product Coordination First Phase Report

GTE+ Capacity Product Coordination First Phase Report First Phase Report Rue Ducale 83 Tel +32 2 209 05 00 gie@gie.eu.com B 1000 Brussels Fax +32 2 209 05 01 www.gie.eu.com Gas Infrastructure Europe (GIE) represents the interest of the infrastructure industry

More information

Virtual Workshop on PJM ARR and FTR Market 2017/2018

Virtual Workshop on PJM ARR and FTR Market 2017/2018 Virtual Workshop on PJM ARR and FTR Market 2017/2018 PJM State & Member Training Dept. Webex February 10, 2017 PJM 2017 Disclaimer: PJM has made all efforts possible to accurately document all information

More information

NSW Council Amalgamations

NSW Council Amalgamations NSW Council Amalgamations Paul Williams Strategic Consulting Lead NSW Council Amalgamations TechnologyOneCorp.com Determining TechOne s Role in your Amalgamation Amalgamations will be a Journey unique

More information

Financial Transmission Rights

Financial Transmission Rights PJM Manual 06 Financial Transmission Rights Revision: 12 Effective Date: July 1, 2009 Prepared by Market Simulation Department PJM 2009 PJM Revision 05, Effective Date: 12/30/03 iii Table of Contents PJM

More information

European Network Code Workshop

European Network Code Workshop European Network Code Workshop Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Gas European

More information

277/06 - PRELIMINARY TERRE (P344) IMPLEMENTATION IN ADVANCE OF OFGEM DECISION

277/06 - PRELIMINARY TERRE (P344) IMPLEMENTATION IN ADVANCE OF OFGEM DECISION - PRELIMINARY TERRE (P344) IMPLEMENTATION IN MEETING NAME BSC Panel Meeting Date of meeting 12 April 2018 Paper number Owner/author Purpose of paper Classification Summary Rob Greenoak Decision Public

More information

The present ACER Guidance to ENTSOG provides a framework for the development of a

The present ACER Guidance to ENTSOG provides a framework for the development of a ACER guidance to ENTSOG on the development of amendment proposals to the Network Code on Capacity Allocation Mechanisms on the matter of incremental and new capacity 1. Introduction a) The Network Code

More information

Meeting System Needs with Demand Response - Work Plan and Technical Panel Timelines

Meeting System Needs with Demand Response - Work Plan and Technical Panel Timelines IESOTP 278-4b Meeting System Needs with Demand Response - Work Plan and Technical Panel Timelines Technical Panel May 5, 2014 Agenda What is our goal for demand response? Stakeholder Consultation IESO

More information

3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3)

3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3) 3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3) Emagine IT s approach to Independent Verification and Validation (IV&V) has been shaped over the years by hands-on experience and contributions

More information

ISO-NE and NYISO Inter-Regional Interchange Scheduling (IRIS)

ISO-NE and NYISO Inter-Regional Interchange Scheduling (IRIS) Joint Stakeholder Meeting ISO-NE and NYISO Inter-Regional Interchange Scheduling (IRIS) May 20, 2011 / Springfield, MA Agenda Today: Voting Process and Principles - Discussion Q&A on Proposals DBD and

More information

Joint European Stakeholder Group. Monday 25 th May 2017: Meeting 21 Elexon, London

Joint European Stakeholder Group. Monday 25 th May 2017: Meeting 21 Elexon, London Joint European Stakeholder Group Monday 25 th May 2017: Meeting 21 Elexon, London 1. Welcome & Introductions Barbra Vest Independent Chair 2. Interconnector projects update Caroline Kluyver and John Greasley

More information

Information Document Provision of System Access Service and the Connection Process ID No T

Information Document Provision of System Access Service and the Connection Process ID No T and the Connection Process Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between

More information

7. Model based software architecture

7. Model based software architecture UNIT - III Model based software architectures: A Management perspective and technical perspective. Work Flows of the process: Software process workflows, Iteration workflows. Check Points of The process

More information

Reference B Project Management Requirements

Reference B Project Management Requirements Reference B State of Alaska TABLE OF CONTENTS 1... 2 1.1 Project Life Cycle Methodology... 2 1.2 Preliminary Project Management Narrative and Work Plan... 2 2 Master Project Management Plan and Master

More information

JCM Drill Down Report -- Draft. March 21, 2014

JCM Drill Down Report -- Draft. March 21, 2014 JCM Drill Down Report -- Draft March 21, 2014 The purpose of this document is to provide a brief description of each component listed on the JCM Work Plan Timeline compiled by PJM and MISO. This Drill

More information

ANNUAL WORK PROGRAMME. Annual Work Programme. implementing the internal market for gas ENTSOG A FAIR PARTNER TO ALL!

ANNUAL WORK PROGRAMME. Annual Work Programme. implementing the internal market for gas ENTSOG A FAIR PARTNER TO ALL! ANNUAL WORK PROGRAMME 2018 Annual Work Programme 2018 implementing the internal market for gas ENTSOG A FAIR PARTNER TO ALL! Content INTRODUCTION 4 Background 5 Executive Summary of ENTSOG s Activities

More information

APS Stakeholder Meeting. September 9 th 2016

APS Stakeholder Meeting. September 9 th 2016 APS Stakeholder Meeting September 9 th 2016 APS: EIM Implementation & Customer Impact Review 9/9/2016 Emerging Market Opportunity CAISO: Energy Imbalance Market Existing Markets 3 Changing Electrical Grid

More information

Business Practice Energy Imbalance Market (EIM BP) Revision Number: Revision Date: November 30July 29, 2015

Business Practice Energy Imbalance Market (EIM BP) Revision Number: Revision Date: November 30July 29, 2015 Revision Number: 3.02.1 Revision Date: November 30July 29, 2015 Revision Log 0.0 3/31/15 Pre-market initial draft 1.0 5/15/15 Email and phone contacts, Sections 3, 7, 8, 9, 11 and Appendix A for participating

More information

Responses to: ACER public consultation on the influence of existing bidding zones on electricity markets

Responses to: ACER public consultation on the influence of existing bidding zones on electricity markets Responses to: ACER public consultation on the influence of existing bidding zones on electricity markets 30 September EUROPEX Rue Montoyer 31 Bte 9 BE-1000 Brussels T. : +32 2 512 34 10 E.: secretariat@europex.org

More information

MOD-001-1a Available Transfer Capability Implementation Document

MOD-001-1a Available Transfer Capability Implementation Document Available Transfer Capability Implementation Document For NERC MOD-001-2a Page 1 of 18 1.0 Purpose The California Independent System Operator Corporation (ISO), as a Transmission Service Provider 1 and

More information

Virtual Reverse Flow: at Interconnection Points. Implementing EU Regulations. Code Modification No. A064. Business Rules. Version 2.

Virtual Reverse Flow: at Interconnection Points. Implementing EU Regulations. Code Modification No. A064. Business Rules. Version 2. Virtual Reverse Flow: at Interconnection Points Implementing EU Regulations Code Modification No. A064 Business Rules 16 th January 2015 Version 2.0 i VERSION CONTROL Version Date Description 1.0 19 th

More information

This proposal will outline a solution that will enable suppliers to be compliant with the EU three week switching directive.

This proposal will outline a solution that will enable suppliers to be compliant with the EU three week switching directive. Stage 02: What stage is this document in the process? : EU Third package: Three week switching This proposal will outline a solution that will enable suppliers to be compliant with the EU three week switching

More information

Defining Outage States to Include a Mothball Outage

Defining Outage States to Include a Mothball Outage Defining Outage States to Include a Mothball Outage Emilie Nelson Director, Operations Josh Boles Manager ICAP Market Market Issues Working Group November 7, 2013 2013 New York Independent System Operator,

More information

Smart Meter Testing & Trialling Discussion Paper ERA SRSM Group 2.7 7th December 2011

Smart Meter Testing & Trialling Discussion Paper ERA SRSM Group 2.7 7th December 2011 Smart Meter Testing & Trialling Discussion Paper ERA SRSM Group 2.7 7th December 2011 Introduction Recognising the criticality of a successful test and trial phase within the Smart Meter programme the

More information

Nova Scotia Power System Operator (NSPSO)

Nova Scotia Power System Operator (NSPSO) Nova Scotia Power System Operator (NSPSO) Market Procedure MP-09 Outage Planning and Approval Effective Date: 2008 12 31 Wholesale Market Procedure MP-09 Table of Contents Page 1 Document Control and General

More information

METIS. Snapshot from user interface screen

METIS. Snapshot from user interface screen METIS METIS is a research project 1 of DG ENER for the development of an energy simulator software with the aim to further support ENER s evidence based policy making. It is developed by a consortium (Artelys,

More information

Implementation of the Modernised Customs Code (MCCIP)

Implementation of the Modernised Customs Code (MCCIP) HLG of Independent Stakeholders on Administrative Burdens 20 May 2010 Implementation of the Modernised Customs Code (MCCIP) Panayota ANABOLI DG TAXUD/A/2 1 Contents Implementation of the Modernised Customs

More information

Approved by Standing Committees Approved by Board of Trustees

Approved by Standing Committees Approved by Board of Trustees Reliability Functional Model Function Definitions and Responsible Entities Prepared by the Functional Model Working Group Version 4 Approved by Standing Committees Approved by Board of Trustees August

More information

Justification for a Contract Amendment to Contract : Implementation of Individual and Multi-Jurisdiction Allowance Auctions and Reserve Sales

Justification for a Contract Amendment to Contract : Implementation of Individual and Multi-Jurisdiction Allowance Auctions and Reserve Sales Justification for a Contract Amendment to Contract 2013-04: Implementation of Individual and Multi-Jurisdiction Allowance Auctions and Reserve Sales May 17, 2013 Introduction WCI, Inc. proposes to modify

More information