1 SECTION SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section Includes: 1. Use of premises. 2. Coordination with occupants. 3. Work restrictions. 4. Specification and drawing conventions. B. Related Requirements: 1. Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities. 1.3 USE OF PREMISES A. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section. B. Use of Site: Limit use of Project site to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated. 1. Driveways, Walkways and Entrances: Keep driveways, loading areas, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. a. Schedule deliveries to minimize use of driveways and entrances by construction operations. b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site. 2. Contractor is responsible for protection and safekeeping of his materials, products and equipment stored on the premises or incorporated into the construction, until his contract is complete and accepted by the Owner. 3. Move at the Contractor s cost any stored materials, products or equipment which interfere with operations of Owner or others. C. Construction employees shall not use any facilities within existing buildings, unless they are instructed to do so as part of construction or alteration work or unless otherwise indicated within the Contract Documents. This includes, but is not limited to, such areas as restrooms, cafeteria, snack bar, gift shop, and waiting areas. SUMMARY

2 D. All activities required for completion of the work shall be accomplished within the building footprint and as indicated on the drawings, except where extensive work is required and shall be coordinated with the Owner. E. Owner s existing parking lots and roadways may be used for parking construction workers vehicles, but only as directed by the Owner. Coordinate overflow parking, for those not accommodated in the staging and parking lot designated on the drawing cover sheet for parking, with the Owner. Contractor shall be responsible for their own transportation from all remote parking lots, designated as acceptable construction parking by Owner, to the site. F. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations. 1.4 COORDINATION WITH OCCUPANTS A. Full Owner Occupancy: Owner will occupy site and existing building(s) during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits unless otherwise indicated. 1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and approval of authorities having jurisdiction. 2. Notify Owner not less than 7 days in advance of activities that will affect Owner's operations. B. Owner Limited Occupancy of Completed Areas of Construction: Owner reserves the right to occupy and to place and install equipment in completed portions of the Work, prior to Substantial Completion of the Work, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and limited occupancy shall not constitute acceptance of the total Work. 1. Architect will prepare a Certificate of Substantial Completion for each specific portion of the Work to be occupied prior to Owner acceptance of the completed Work. 2. Obtain a Certificate of Occupancy from authorities having jurisdiction before limited Owner occupancy. 3. Before limited Owner occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, Owner will operate and maintain mechanical and electrical systems serving occupied portions of Work. 4. On occupancy, Owner will assume responsibility for maintenance and custodial service for occupied portions of Work. 1.5 WORK RESTRICTIONS A. Work Restrictions, General: Comply with restrictions on construction operations. 1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction. SUMMARY

3 B. On-Site Work Hours: Limit work in the existing building to normal business working hours of 7:00 a.m. to 11:00 p.m., Monday through Friday, unless otherwise indicated. 1. Weekend Hours: Saturday, from 8:00 a.m. to 11:00 p.m., and Sunday from Noon to 11:00 p.m. C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated: 1. Notify Architect and Owner not less than 15 days in advance of proposed utility interruptions. 2. Obtain Owner's written permission before proceeding with utility interruptions. D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner. 1. Notify Owner not less than 3 days in advance of proposed disruptive operations. 2. Obtain Owner's written permission before proceeding with disruptive operations. E. Nonsmoking Building: Smoking is not permitted within the building. Comply with university requirements for smoking on campus. F. Controlled Substances: Use of controlled substances is not permitted. G. Employee Screening: Comply with Owner's requirements for drug and background screening of Contractor personnel working on Project site. 1. Maintain list of approved screened personnel with Owner's representative. 1.6 SPECIFICATION AND DRAWING CONVENTIONS A. Specification Content: The specifications are organized into Divisions and Sections using the 16-division format and CSI/CSC s MasterFormat numbering system. 1. Sections in Division 1 govern the execution of the Work of all Sections in the Specifications, and is intended to supplement, not replace, provisions of AIA document A201. B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows: 1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase. 2. Specification requirements are to be performed by Contractor unless specifically stated otherwise. C. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications. SUMMARY

4 D. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products: 1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections. 2. Abbreviations: Materials and products are identified by abbreviations scheduled on Drawings. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION SUMMARY

5 SECTION ALLOWANCES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section includes administrative and procedural requirements governing allowances. 1. Certain items are specified in the Contract Documents by allowances. Allowances have been established in lieu of additional requirements and to defer selection of actual materials and equipment to a later date when direction will be provided to Contractor. If necessary, additional requirements will be issued by Change Order. B. Types of allowances include the following: 1. Quantity and Unit Price allowances. 2. Contingency allowances. C. Related Requirements: 1. Section "Unit Prices" for procedures for using unit prices. 2. Section "Quality Requirements" for procedures governing the use of allowances for testing and inspecting. 1.3 SELECTION AND PURCHASE A. At the earliest practical date after award of the Contract, advise Architect of the date when final selection and purchase of each product or system described by an allowance must be completed to avoid delaying the Work. B. At Architect's request, obtain proposals for each allowance for use in making final selections. Include recommendations that are relevant to performing the Work. C. Purchase products and systems selected by Architect from the designated supplier. 1.4 ACTION SUBMITTALS A. Submit proposals for purchase of products or systems included in allowances, in the form specified for Change Orders. ALLOWANCES

6 1.5 INFORMATIONAL SUBMITTALS A. Submit invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each allowance. B. Submit time sheets and other documentation to show labor time and cost for installation of allowance items that include installation as part of the allowance. C. Coordinate and process submittals for allowance items in same manner as for other portions of the Work. 1.6 COORDINATION A. Coordinate allowance items with other portions of the Work. Furnish templates as required to coordinate installation. 1.7 QUANTITY AND UNIT PRICE ALLOWANCES A. Allowance shall include cost to Contractor of specific products and materials ordered by Owner or selected by Architect under allowance and shall include applicable taxes, freight, and delivery to Project site. B. Contractor's costs for receiving and handling at Project site, labor, installation, overhead and profit, and similar costs related to products and materials under allowance shall be included as part of the allowance. C. Unused Materials: Return unused materials purchased under an allowance to manufacturer or supplier for credit to Owner, after installation has been completed and accepted. 1. If requested by Architect, retain and prepare unused material for storage by Owner. Deliver unused material to Owner's storage space as directed. 1.8 CONTINGENCY ALLOWANCES A. Use the contingency allowance only as directed by Architect for Owner's purposes and only by Change Orders that indicate amounts to be charged to the allowance. B. Contractor's overhead, profit, and related costs for products and equipment ordered by Owner under the contingency allowance are included in the allowance and are not part of the Contract Sum. These costs include delivery, installation, applicable taxes, insurance, equipment rental, and similar costs. C. Change Orders authorizing use of funds from the contingency allowance will include Contractor's related costs and reasonable overhead and profit margins. D. At Project closeout, credit unused amounts remaining in the contingency allowance to Owner by Change Order. ALLOWANCES

7 1.9 ADJUSTMENT OF ALLOWANCES A. Allowance Adjustment: To adjust allowance amounts, prepare a Change Order proposal based on the difference between purchase amount and the allowance, multiplied by final measurement of work-in-place where applicable. If applicable, include reasonable allowances for cutting losses, tolerances, mixing wastes, normal product imperfections, and similar margins. 1. Include installation costs in purchase amount only where indicated as part of the allowance. 2. If requested, prepare explanation and documentation to substantiate distribution of overhead costs and other margins claimed. 3. Submit substantiation of a change in scope of work, if any, claimed in Change Orders related to unit-cost allowances. 4. Owner reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count. B. Submit claims for increased costs because of a change in scope or nature of the allowance described in the Contract Documents, whether for the purchase order amount or Contractor's handling, labor, installation, overhead, and profit. 1. Do not include Contractor's or subcontractor's indirect expense in the Change Order cost amount unless it is clearly shown that the nature or extent of work has changed from what could have been foreseen from information in the Contract Documents. 2. No change to Contractor's indirect expense is permitted for selection of higher- or lowerpriced materials or systems of the same scope and nature as originally indicated. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.1 EXAMINATION A. Examine products covered by an allowance promptly on delivery for damage or defects. Return damaged or defective products to manufacturer for replacement. 3.2 PREPARATION A. Coordinate materials and their installation for each allowance with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work. 3.3 SCHEDULE OF ALLOWANCES - INCLUDED ON THE BID FORM END OF SECTION ALLOWANCES

8 THIS PAGE INTENTIONALLY LEFT BLANK

9 SECTION UNIT PRICES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section includes administrative and procedural requirements for unit prices. B. Related Requirements: 1. Section "Contract Modification Procedures" for procedures for submitting and handling Change Orders. 2. Section "Quality Requirements" for general testing and inspecting requirements. 1.3 DEFINITIONS A. Unit price is an amount incorporated in the Agreement, applicable during the duration of the Work as a price per unit of measurement for materials, equipment, or services, or a portion of the Work, added to or deducted from the Contract Sum by appropriate modification, if the scope of Work or estimated quantities of Work required by the Contract Documents are increased or decreased. 1.4 PROCEDURES A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit. B. Measurement and Payment: See individual Specification Sections for work that requires establishment of unit prices. Methods of measurement and payment for unit prices are specified in those Sections. C. Owner reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Owner's expense, by an independent surveyor acceptable to Contractor. D. List of Unit Prices: A schedule of unit prices is included in Part 3. Specification Sections referenced in the schedule contain requirements for materials described under each unit price. UNIT PRICES

10 PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.1 SCHEDULE OF UNIT PRICES A. Unit Price 1A: BH Coping Stone Replacement. 1. Description: Baldwin Hall (BH) Coping stone replacement with material to match existing, as required, according to Section "Maintenance of Masonry." 2. Unit of Measurement: Per piece, measured from existing mortar joint to existing mortar joint. 3. Quantity and Unit Price Allowance: Coordinate unit price with allowance adjustment requirements in Section "Allowances." B. Unit Price 1B: PB Coping Stone Replacement. 1. Description: Pershing Building (PB) Coping stone replacement with material to match existing, as required, according to Section "Maintenance of Masonry." 2. Unit of Measurement: Per piece, measured from existing mortar joint to existing mortar joint. 3. Quantity and Unit Price Allowance: Coordinate unit price with allowance adjustment requirements in Section "Allowances." C. Unit Price 1C: VH Coping Stone Replacement. 1. Description: Violette Hall (VH) Coping stone replacement with material to match existing, as required, according to Section "Maintenance of Masonry." 2. Unit of Measurement: Per piece, measured from existing mortar joint to existing mortar joint. 3. Quantity and Unit Price Allowance: Coordinate unit price with allowance adjustment requirements in Section "Allowances." D. Unit Price 2: BH Water Table/Entablature Stone Replacement. 1. Description: Baldwin Hall (BH) water table/entablature stone replacement with material to match existing, as required, according to Section "Maintenance of Masonry." 2. Unit of Measurement: Per piece, measured from existing vertical mortar joint to existing vertical mortar joint. 3. Quantity and Unit Price Allowance: Coordinate unit price with allowance adjustment requirements in Section "Allowances." E. Unit Price 3: Crack Injection. 1. Description: Masonry crack injection, as required, according to Section "Maintenance of Masonry." 2. Unit of Measurement: Per linear foot. 3. Quantity and Unit Price Allowance: Coordinate unit price with allowance adjustment requirements in Section "Allowances." F. Unit Price 4: Repointing with Mortar. UNIT PRICES

11 1. Description: Repointing brick clay masonry, as required, according to Section "Maintenance of Masonry." 2. Unit of Measurement: Per square foot. 3. Quantity and Unit Price Allowance: Coordinate unit price with allowance adjustment requirements in Section "Allowances." G. Unit Price 5: Repointing with Sealant. 1. Description: Repointing stone with sealant, as required, according to Section "Maintenance of Masonry." 2. Unit of Measurement: Per linear foot. H. Unit Price 6A: VH Gutter Substrate Rebuild Straight-Runs. 1. Description: Removal and replacement of damaged gutter wood substrate and framing at straight-runs, and infill/rebuild of areas damaged/demolished, in accordance with Section "Rough Carpentry". 2. Unit of Measurement: Per linear foot. 3. Quantity and Unit Price Allowance: Coordinate unit price with allowance adjustment requirements in Section "Allowances." I. Unit Price 6B: VH Gutter Substrate Rebuild - Corners. 1. Description: Removal and replacement of damaged gutter wood substrate and framing at corners, and infill/rebuild of areas damaged/demolished, in accordance with Section "Rough Carpentry". 2. Unit of Measurement: Per linear foot. 3. Quantity and Unit Price Allowance: Coordinate unit price with allowance adjustment requirements in Section "Allowances." END OF SECTION UNIT PRICES

12 THIS PAGE INTENTIONALLY LEFT BLANK

13 SECTION ALTERNATES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section includes administrative and procedural requirements for alternates. 1.3 DEFINITIONS A. Alternate: An amount proposed by bidders and stated on the Bid Form for certain work defined in the bidding requirements that may be added to or deducted from the base bid amount if Owner decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents. 1. Alternates described in this Section are part of the Work only if enumerated in the Agreement. 2. The cost or credit for each alternate is the net addition to or deduction from the Contract Sum to incorporate alternate into the Work. No other adjustments are made to the Contract Sum. 1.4 PROCEDURES A. Coordination: Revise or adjust affected adjacent work as necessary to completely integrate work of the alternate into Project. 1. Include as part of each alternate, miscellaneous devices, accessory objects, and similar items incidental to or required for a complete installation whether or not indicated as part of alternate. B. Notification: Immediately following award of the Contract, notify each party involved, in writing, of the status of each alternate. Indicate if alternates have been accepted, rejected, or deferred for later consideration. Include a complete description of negotiated revisions to alternates. C. Execute accepted alternates under the same conditions as other work of the Contract. D. Schedule: A schedule of alternates is included at the end of this Section. Specification Sections referenced in schedule contain requirements for materials necessary to achieve the work described under each alternate. ALTERNATES

14 PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION 3.1 SCHEDULE OF ALTERNATES A. Alternate No. 1: Re-roofing and Window Replacement at the Pershing Building. 1. Alternate Description: Re-roofing and Window Replacement as indicated on Sheets PB A1.1, A1.2, and A1.3 and as specified in Sections including but not limited to Rough Carpentry, "Preparation for Reroofing," "Thermoplastic Membrane (TPO) Roofing," Sheet Metal Flashing and Trim, Roof Accessories, Aluminum-Framed Entrances and Storefronts, Glazing, Gypsum Board, and Interior Painting. B. Alternate No. 2: Plaza deck edge waterproofing at Pickler Memorial Library. 1. Alternate Description: Removal of existing brick pavers, base, concrete slab and subgrade, cleaning, priming and sealing/waterproofing, and reconstructing of the concrete slab, sub-grade, pavers to match existing, and paver base, at the eastern edge of the plaza deck at Pickler Memorial Library as indicated on Sheets PML A1.1 and as specified in Sections including but not limited to Self-Adhering Sheet Waterproofing. END OF SECTION ALTERNATES

15 SECTION SUBSTITUTION PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section includes administrative and procedural requirements for substitutions. B. Related Requirements: 1. Section "Allowances" for products selected under an allowance. 2. Section "Alternates" for products selected under an alternate. 3. Section "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers. 1.3 DEFINITIONS A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor. 1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms. 2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required in order to meet other Project requirements but may offer advantage to Contractor and Owner. 1.4 ACTION SUBMITTALS A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles. 1. Substitution Request Form: Use CSI Form 13.1A. 2. Documentation: Show compliance with requirements for substitutions and the following, as applicable: a. Statement indicating why specified product or fabrication or installation cannot be provided, if applicable. b. Coordination information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors, that will be necessary to accommodate proposed substitution. c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable Specification Section. SUBSTITUTION PROCEDURES

16 Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified. d. Product Data, including drawings and descriptions of products and fabrication and installation procedures. e. Samples, where applicable or requested. f. Certificates and qualification data, where applicable or requested. g. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners. h. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated. i. Research reports evidencing compliance with building code in effect for Project, from ICC-ES. j. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery. k. Cost information, including a proposal of change, if any, in the Contract Sum. l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated. m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results. 3. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within seven days of receipt of a request for substitution. Architect will notify Contractor of acceptance or rejection of proposed substitution within 15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later. a. Forms of Acceptance: Change Order, Construction Change Directive, or Architect's Supplemental Instructions for minor changes in the Work. b. Use product specified if Architect does not issue a decision on use of a proposed substitution within time allocated. 1.5 QUALITY ASSURANCE A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers. 1.6 PROCEDURES A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions. SUBSTITUTION PROCEDURES

17 PART 2 - PRODUCTS 2.1 SUBSTITUTIONS A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals. 1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements: a. Requested substitution is consistent with the Contract Documents and will produce indicated results. b. Requested substitution provides sustainable design characteristics that specified product provided. c. Substitution request is fully documented and properly submitted. d. Requested substitution will not adversely affect Contractor's construction schedule. e. Requested substitution has received necessary approvals of authorities having jurisdiction. f. Requested substitution is compatible with other portions of the Work. g. Requested substitution has been coordinated with other portions of the Work. h. Requested substitution provides specified warranty. i. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved. B. Substitutions for Convenience: Architect will consider requests for substitution if received within 30 days after the Notice to Proceed. Requests received after that time may be considered or rejected at discretion of Architect. 1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements: a. Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities Owner must assume. Owner's additional responsibilities may include compensation to Architect for redesign and evaluation services, increased cost of other construction by Owner, and similar considerations. b. Requested substitution does not require extensive revisions to the Contract Documents. c. Requested substitution is consistent with the Contract Documents and will produce indicated results. d. Requested substitution provides sustainable design characteristics that specified product provided. e. Substitution request is fully documented and properly submitted. f. Requested substitution will not adversely affect Contractor's construction schedule. g. Requested substitution has received necessary approvals of authorities having jurisdiction. h. Requested substitution is compatible with other portions of the Work. i. Requested substitution has been coordinated with other portions of the Work. j. Requested substitution provides specified warranty. SUBSTITUTION PROCEDURES

18 k. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved. PART 3 - EXECUTION (Not Used) END OF SECTION SUBSTITUTION PROCEDURES

19 SECTION CONTRACT MODIFICATION PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section includes administrative and procedural requirements for handling and processing Contract modifications. B. Related Requirements: 1. Section "Substitution Procedures" for administrative procedures for handling requests for substitutions made after the Contract award. 1.3 MINOR CHANGES IN THE WORK A. Architect will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on AIA Document G710, "Architect's Supplemental Instructions." 1.4 PROPOSAL REQUESTS A. Owner-Initiated Proposal Requests: Architect will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications. 1. Work Change Proposal Requests issued by Architect are not instructions either to stop work in progress or to execute the proposed change. 2. Within time specified in Proposal Request or 20 days, when not otherwise specified, after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change. a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities. b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts. c. Include costs of labor and supervision directly attributable to the change. d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time. e. Quotation Form: Use CSI Form 13.6D, "Proposal Worksheet Summary," and Form 13.6C, "Proposal Worksheet Detail" or forms acceptable to Architect. CONTRACT MODIFICATION PROCEDURES

20 B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to Architect. 1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time. 2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities. 3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts. 4. Include costs of labor and supervision directly attributable to the change. 5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time. 6. Comply with requirements in Section "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified. 7. Proposal Request Form: Use CSI Form 13.6A, "Change Order Request (Proposal)," with attachments CSI Form 13.6D, "Proposal Worksheet Summary," and Form 13.6C, "Proposal Worksheet Detail" or form acceptable to Architect. 1.5 ADMINISTRATIVE CHANGE ORDERS A. Allowance Adjustment: See Section "Allowances" for administrative procedures for preparation of Change Order Proposal for adjusting the Contract Sum to reflect actual costs of allowances. B. Unit-Price Adjustment: See Section "Unit Prices" for administrative procedures for preparation of Change Order Proposal for adjusting the Contract Sum to reflect measured scope of unit-price work. 1.6 CHANGE ORDER PROCEDURES A. On Owner's approval of a Work Changes Proposal Request, Architect will issue a Change Order for signatures of Owner and Contractor on AIA Document G CONSTRUCTION CHANGE DIRECTIVE A. Construction Change Directive: Architect may issue a Construction Change Directive on AIA Document G714. Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order. 1. Construction Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time. B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive. 1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract. CONTRACT MODIFICATION PROCEDURES

21 PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION CONTRACT MODIFICATION PROCEDURES

22 THIS PAGE INTENTIONALLY LEFT BLANK

23 SECTION PAYMENT PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment. B. Related Requirements: 1. Section "Allowances" for procedural requirements governing the handling and processing of allowances. 2. Section "Unit Prices" for administrative requirements governing the use of unit prices. 3. Section "Contract Modification Procedures" for administrative procedures for handling changes to the Contract. 4. Section "Construction Progress Documentation" for administrative requirements governing the preparation and submittal of the Contractor's construction schedule. 1.3 DEFINITIONS A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract Sum to various portions of the Work and used as the basis for reviewing Contractor's Applications for Payment. 1.4 SCHEDULE OF VALUES A. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's construction schedule. 1. Coordinate line items in the schedule of values with other required administrative forms and schedules, including the following: a. Application for Payment forms with continuation sheets. b. Submittal schedule. c. Items required to be indicated as separate activities in Contractor's construction schedule. 2. Submit the schedule of values to Architect at earliest possible date, but no later than seven days before the date scheduled for submittal of initial Applications for Payment. 3. Subschedules for Separate Elements of Work: Where the Contractor's construction schedule defines separate elements of the Work, provide subschedules showing values coordinated with each element. PAYMENT PROCEDURES

24 B. Format and Content: Use Project Manual table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each Specification Section. 1. Identification: Include the following Project identification on the schedule of values: a. Project name and location. b. Name of Architect. c. Architect's project number. d. Contractor's name and address. e. Date of submittal. 2. Arrange schedule of values consistent with format of AIA Document G Arrange the schedule of values in tabular form with separate columns to indicate the following for each item listed: a. Related Specification Section or Division. b. Description of the Work. c. Name of subcontractor. d. Name of manufacturer or fabricator. e. Name of supplier. f. Change Orders (numbers) that affect value. g. Dollar value of the following, as a percentage of the Contract Sum to nearest onehundredth percent, adjusted to total 100 percent. 1) Labor. 2) Materials. 3) Equipment. 4. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with Project Manual table of contents. Provide multiple line items for principal subcontract amounts in excess of five percent of the Contract Sum. 5. Round amounts to nearest whole dollar; total shall equal the Contract Sum. 6. Provide a separate line item in the schedule of values for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed. a. Differentiate between items stored on-site and items stored off-site. If required, include evidence of insurance. 7. Provide separate line items in the schedule of values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work. 8. Allowances: Provide a separate line item in the schedule of values for each allowance. Show line-item value of unit-cost allowances, as a product of the unit cost, multiplied by measured quantity. Use information indicated in the Contract Documents to determine quantities. 9. Each item in the schedule of values and Applications for Payment shall be complete. Include total cost and proportionate share of general overhead and profit for each item. a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the schedule of values or distributed as general overhead expense, at Contractor's option. PAYMENT PROCEDURES

25 10. Schedule Updating: Update and resubmit the schedule of values before the next Applications for Payment when Change Orders or Construction Change Directives result in a change in the Contract Sum. 1.5 APPLICATIONS FOR PAYMENT A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments as certified by Architect and paid for by Owner. 1. Initial Application for Payment, Application for Payment at time of Substantial Completion, and final Application for Payment involve additional requirements. B. Payment Application Times: The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction work covered by each Application for Payment is the period indicated in the Agreement. C. Application for Payment Forms: Use AIA Document G702 and AIA Document G703 as form for Applications for Payment. D. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Architect will return incomplete applications without action. 1. Entries shall match data on the schedule of values and Contractor's construction schedule. Use updated schedules if revisions were made. 2. Include amounts for work completed following previous Application for Payment, whether or not payment has been received. Include only amounts for work completed at time of Application for Payment. 3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application. 4. Indicate separate amounts for work being carried out under Owner-requested project acceleration. E. Stored Materials: Include in Application for Payment amounts applied for materials or equipment purchased or fabricated and stored, but not yet installed. Differentiate between items stored on-site and items stored off-site. 1. Provide certificate of insurance, evidence of transfer of title to Owner, and consent of surety to payment, for stored materials. 2. Provide supporting documentation that verifies amount requested, such as paid invoices. Match amount requested with amounts indicated on documentation; do not include overhead and profit on stored materials. 3. Provide summary documentation for stored materials indicating the following: a. Value of materials previously stored and remaining stored as of date of previous Applications for Payment. b. Value of previously stored materials put in place after date of previous Application for Payment and on or before date of current Application for Payment. c. Value of materials stored since date of previous Application for Payment and remaining stored as of date of current Application for Payment. F. Transmittal: Submit three signed and notarized original copies of each Application for Payment to Architect by a method ensuring receipt. One copy shall include waivers of lien and similar attachments if required. PAYMENT PROCEDURES

26 1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application. G. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's liens from subcontractors, sub-subcontractors, and suppliers for construction period covered by the previous application. 1. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item. 2. When an application shows completion of an item, submit conditional final or full waivers. 3. Owner reserves the right to designate which entities involved in the Work must submit waivers. 4. Submit final Application for Payment with or preceded by conditional final waivers from every entity involved with performance of the Work covered by the application who is lawfully entitled to a lien. 5. Waiver Forms: Submit executed waivers of lien on forms, acceptable to Owner. H. MBE/WBE Forms: With each Application for Payment, submit forms for construction period covered by the application. I. Certified Payroll: With each Application for Payment, submit certified payroll records from subcontractors, and sub-subcontractors, for construction period covered by the application. J. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following: 1. List of subcontractors. 2. Schedule of values. 3. Contractor's construction schedule (preliminary if not final). 4. Combined Contractor's construction schedule (preliminary if not final) incorporating Work of multiple contracts, with indication of acceptance of schedule by each Contractor. 5. Products list (preliminary if not final). 6. Schedule of unit prices. 7. Submittal schedule (preliminary if not final). 8. List of Contractor's staff assignments. 9. List of Contractor's principal consultants. 10. Copies of building permits. 11. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work. 12. Initial progress report. 13. Report of preconstruction conference. 14. Certificates of insurance and insurance policies. 15. Performance and payment bonds. 16. Data needed to acquire Owner's insurance. K. Application for Payment at Substantial Completion: After Architect issues the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete. 1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum. 2. This application shall reflect Certificate(s) of Substantial Completion issued previously for Owner occupancy of designated portions of the Work. PAYMENT PROCEDURES

27 L. Final Payment Application: After completing Project closeout requirements, submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following: 1. Evidence of completion of Project closeout requirements. 2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid. 3. Updated final statement, accounting for final changes to the Contract Sum. 4. AIA Document G706, "Contractor's Affidavit of Payment of Debts and Claims." 5. AIA Document G706A, "Contractor's Affidavit of Release of Liens." 6. AIA Document G707, "Consent of Surety to Final Payment." 7. Evidence that claims have been settled. 8. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work. 9. Final liquidated damages settlement statement. PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION PAYMENT PROCEDURES

28 THIS PAGE INTENTIONALLY LEFT BLANK

29 SECTION PROJECT MANAGEMENT AND COORDINATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following: 1. General coordination procedures. 2. Project meetings. B. Related Requirements: 1. Section "Construction Progress Documentation" for preparing and submitting Contractor's construction schedule. 2. Section "Closeout Procedures" for coordinating closeout of the Contract. 1.3 GENERAL COORDINATION PROCEDURES A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, that depend on each other for proper installation, connection, and operation. 1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation. 2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair. 3. Make adequate provisions to accommodate items scheduled for later installation. B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings. 1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required. C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following: 1. Preparation of Contractor's construction schedule. 2. Preparation of the schedule of values. 3. Installation and removal of temporary facilities and controls. PROJECT MANAGEMENT AND COORDINATION

TRUMAN STATE UNIVERSITY SITE IMPROVEMENTS, KIRK BLDG, MISSOURI HALL & STUDENT REC CENTER LTD RENOVATIONS

TRUMAN STATE UNIVERSITY SITE IMPROVEMENTS, KIRK BLDG, MISSOURI HALL & STUDENT REC CENTER LTD RENOVATIONS SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

1. Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1. Section Temporary Facilities and Controls for limitations and procedures governing temporary use of Owner's facilities. SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

BOWIE STATE UNIVERSITY CAR PARKING LOT

BOWIE STATE UNIVERSITY CAR PARKING LOT BOWIE STATE UNIVERSITY CAR PARKING LOT TECHNICAL SPECIFICATIONS 100% CD SUBMISSION NOVEMBER 2, 2018 Prepared by WHITNEY, BAILEY COX & MAGNANI, LLC 300 East Joppa Road, Suite 200 Baltimore, Maryland 21286

More information

1. Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1. Section Temporary Facilities and Controls for limitations and procedures governing temporary use of Owner's facilities. CSB 7th Floor Orthopaedic Surgery Office Renovation Phase 2 SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary

More information

RANDOLPH COMMUNITY CENTER GYMNASIUM FLOOR REPLACEMENT

RANDOLPH COMMUNITY CENTER GYMNASIUM FLOOR REPLACEMENT PROJECT MANUAL RANDOLPH COMMUNITY CENTER GYMNASIUM FLOOR REPLACEMENT CITY OF RICHMOND Richmond, Virginia Architect s Project No. 563107 ARCHITECT/ENGINEER RICHMOND, VIRGINIA A/E s Project No. 563107 set

More information

CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT PROJECT MANUAL. Commonwealth Architects

CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT PROJECT MANUAL. Commonwealth Architects CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT 701 North 25th Street Richmond, Virginia 23223 PROJECT MANUAL PERMIT SET FEBRUARY 27, 2017 Commonwealth Architects 101 Shockoe Slip Richmond, VA 23219 CITY

More information

CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT 701 North 25th Street Richmond, Virginia PROJECT MANUAL BID SET April 4, 2018

CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT 701 North 25th Street Richmond, Virginia PROJECT MANUAL BID SET April 4, 2018 CITY OF RICHMOND EDI BUILDING WINDOW REPLACEMENT 701 North 25th Street Richmond, Virginia 23223 PROJECT MANUAL BID SET April 4, 2018 Commonwealth Architects 101 Shockoe Slip, Fl 3 Richmond, VA 23219 CITY

More information

OSNI PONCA OFFICE REMODEL

OSNI PONCA OFFICE REMODEL OSNI PONCA OFFICE REMODEL PROJECT MANUAL OCTOBER 2016 SCHEMMER PROJECT NO. 06571.002 OSNI PONCA OFFICE REMODEL TABLE OF CONTENTS DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 000115 LIST OF DRAWING

More information

NMSU Carlsbad Campus Main Building and Computer Building DDC Control Upgrade. Project Manual Technical Specifications Review Submittal May 12, 2017

NMSU Carlsbad Campus Main Building and Computer Building DDC Control Upgrade. Project Manual Technical Specifications Review Submittal May 12, 2017 NMSU Carlsbad Campus Main Building and Computer Building DDC Control Upgrade NMSU Facilities and Services Department P.O. Box 30001 Las Cruces, NM 88003-8001 Project Manual Technical Specifications Review

More information

PROJECT SPECIFICATIONS PENSACOLA INTERNATIONAL AIRPORT PARKING GARAGE REHABILITATION

PROJECT SPECIFICATIONS PENSACOLA INTERNATIONAL AIRPORT PARKING GARAGE REHABILITATION PROJECT SPECIFICATIONS PENSACOLA INTERNATIONAL AIRPORT PARKING GARAGE REHABILITATION CITY OF PENSACOLA November 2018 SECTION 011000- SUMMARY OF WORK PART 1 - GENERAL 1.1 DOCUMENTS A. Drawings and general

More information

PROJECT MANUAL POINT BLANK RANGE & GUN SHOP. 600 Corporate way Knoxville, TN. Bid/Permit Set

PROJECT MANUAL POINT BLANK RANGE & GUN SHOP. 600 Corporate way Knoxville, TN. Bid/Permit Set PROJECT MANUAL POINT BLANK RANGE & GUN SHOP 600 Corporate way Knoxville, TN Bid/Permit Set Division Section Title SPECIFICATIONS GROUP DIVISION 01 - GENERAL REQUIREMENTS 011000 SUMMARY 012600 CONTRACT

More information

SECTION PAYMENT PROCEDURES

SECTION PAYMENT PROCEDURES SECTION 012900 PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract including General and Supplementary Conditions and other Division 01 Specifications Sections apply

More information

University of Oklahoma Sarkeys Energy Center Atriums Waterproofing Project mass project no Set no. project manual.

University of Oklahoma Sarkeys Energy Center Atriums Waterproofing Project mass project no Set no. project manual. University of Oklahoma Sarkeys Energy Center Atriums Waterproofing Project mass project no. 1801.01 07 12 2018 Set no. project manual. University of Oklahoma Sarkeys Energy Center Atriums Waterproofing

More information

George Washington Middle School - HVAC Replacement 100% Construction Documents May 7, 2018 TABLE OF CONTENTS

George Washington Middle School - HVAC Replacement 100% Construction Documents May 7, 2018 TABLE OF CONTENTS TABLE OF CONTENTS DIVISION 01 GENERAL REQUIREMENTS 011000 SUMMARY 012500 SUBSTITUTION PROCEDURES 012900 PAYMENT PROCEDURES 013100 PROJECT MANAGEMENT AND COORDINATION 013200 CONSTRUCTION PROGRESS DOCUMENTATION

More information

VAE VIEW ELEMENTARY WINDOW REPLACEMENT West 1600 North Layton, UT Specifications. Construction Documents

VAE VIEW ELEMENTARY WINDOW REPLACEMENT West 1600 North Layton, UT Specifications. Construction Documents VAE VIEW ELEMENTARY WINDOW REPLACEMENT 1750 West 1600 North Layton, UT 84041 Specifications 19 March 2018 TABLE OF CONTENTS DIVISION 00 PREREQUIREMENT AND CONTRACTING REQUIREMENTS A101 A201 A310 A312 G701

More information

CHAPEL HILL TOWN HALL RENOVATIONS UPPER LEVEL, SOUTH CHAPEL HILL, NORTH CAROLINA

CHAPEL HILL TOWN HALL RENOVATIONS UPPER LEVEL, SOUTH CHAPEL HILL, NORTH CAROLINA SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

Project Manual. Unitarian Universalist Congregation of Princeton 50 Cherry Hill Road Princeton, New Jersey Lot: 11 Block: 5201

Project Manual. Unitarian Universalist Congregation of Princeton 50 Cherry Hill Road Princeton, New Jersey Lot: 11 Block: 5201 Project Manual for Alterations & Building Addition to: Unitarian Universalist Congregation of Princeton 50 Cherry Hill Road Princeton, New Jersey Lot: 11 Block: 5201 SCHEMATIC DESIGN ISSUE NOT FOR CONSTRUCTION

More information

TOWNES + architects, P.A.

TOWNES + architects, P.A. TOWNES + architects, P.A. 2421 North 12th Avenue, Pensacola, Florida 32503 Telephone: (850) 433-0203 Florida Registration AA-26001051 PROJECT MANUAL City of Pensacola Fleet Maintenace Garage Re ovation

More information

SPECIFICATIONS. Permit Set RICHMOND CITY HALL: SUITE 110 RENOVATIONS. City of Richmond, Virginia Architect s Project No

SPECIFICATIONS. Permit Set RICHMOND CITY HALL: SUITE 110 RENOVATIONS. City of Richmond, Virginia Architect s Project No SPECIFICATIONS Permit Set RICHMOND CITY HALL: SUITE 110 RENOVATIONS ARCHITECT RICHMOND, VIRGINIA MECHANICAL, PLUMBING, FIRE PROTECTION, AND ELECTRICAL ENGINEERS GLEN ALLEN, VIRGINIA A/E s Project No. 563109

More information

1. Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1. Section Temporary Facilities and Controls for limitations and procedures governing temporary use of Owner's facilities. SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

UNIVERSITY OF ROCHESTER DIVISION 01 SPECIFICATIONS April 15, 2015

UNIVERSITY OF ROCHESTER DIVISION 01 SPECIFICATIONS April 15, 2015 SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

Willow Oak Veterinary Hospital

Willow Oak Veterinary Hospital Project Manual For Willow Oak Veterinary Hospital Durham, North Carolina Linton Architects Project #1219 September 11, 2013 Linton Architects 331 West Main Street, Suite 608 Durham, North Carolina 27701

More information

1) Unified School District No. 489 reserves the right to reject any or all bids and to waive any informalities in the bid procedure.

1) Unified School District No. 489 reserves the right to reject any or all bids and to waive any informalities in the bid procedure. Prospective bidders: The Board of Education, Unified School District No. 489, will receive bids for the fabrication and construction of two pre-manufactured metal building in the designated area at the

More information

SPECIFICATIONS. September 27, 2016 Bid Set

SPECIFICATIONS. September 27, 2016 Bid Set SPECIFICATIONS September 27, 2016 Bid Set CITY HALL SUITE 100 & 102 RENOVATIONS TABLE OF CONTENTS (Refer to Project Book under separate cover for additional requirements) SPECIFICATIONS DIVISION 1 - GENERAL

More information

SPECIFICATIONS May 25, Ellicott Station Redevelopment Brewery Building - 40 Ellicott Street Ellicott Street Batavia, New York United States

SPECIFICATIONS May 25, Ellicott Station Redevelopment Brewery Building - 40 Ellicott Street Ellicott Street Batavia, New York United States SPECIFICATIONS May 25, 2018 Ellicott Station Redevelopment Brewery Building - 40 Ellicott Street Ellicott Street Batavia, New York United States Ellicott Station Development, LLC 500 Seneca Street Suite

More information

ENTRY SECURITY MODIFICATIONS

ENTRY SECURITY MODIFICATIONS Rio Rancho Public Schools ENTRY SECURITY MODIFICATIONS Volume 2 of 2 Divisions 01 through 28 Mountain View Middle School Project Number 083105-16-002 Rio Rancho Cyber Academy Project Number 083018-16-001

More information

Hard Rock Hotel and Casino - Tulsa Casino 3 and Suite Hotel Exterior Painting Bid Issue Issue Date: 18 March 2013 Project Number

Hard Rock Hotel and Casino - Tulsa Casino 3 and Suite Hotel Exterior Painting Bid Issue Issue Date: 18 March 2013 Project Number Hard Rock Hotel and Casino - Tulsa Casino 3 and Suite Hotel Exterior Painting Issue Date: 18 March 2013 Project Number 13-201.1 9400 Gateway Drive, Suite B Reno, NV 89521 775.852.3977 (p) 775.852.6543

More information

SSM Project: Centennial School District Issued for Bid AC Unit Replacements 05/16/2014 Klinger and Log College Middle Schools

SSM Project: Centennial School District Issued for Bid AC Unit Replacements 05/16/2014 Klinger and Log College Middle Schools Division Section Title SPECIFICATIONS GROUP General Requirements Subgroup DIVISION 01 GENERAL REQUIREMENTS 011000 SUMMARY 012500 SUBSTITUTION PROCEDURES 012600 CONTRACT MODIFICATION PROCEDURES 012900 PAYMENT

More information

DeKalb County Library Dunwoody Library Staff Area Renovation

DeKalb County Library Dunwoody Library Staff Area Renovation PROJECT MANUAL DeKalb County Library Dunwoody Library Staff Area Renovation OWNER: DeKalb County Library Email: kimbroj@dekalblibrary.org Contact: Jackee Kimbro 404-508-719-, ext. 2236 ARCHITECT: MEP ENGINEER:

More information

RWA, Inc. TECHNICAL SPECIFICATIONS NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS Willow Park Drive Suite 200 Naples, FL 34109

RWA, Inc. TECHNICAL SPECIFICATIONS NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS Willow Park Drive Suite 200 Naples, FL 34109 RWA, Inc. TECHNICAL SPECIFICATIONS NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS 6610 Willow Park Drive Suite 200 Naples, FL 34109 MAY 23, 2012 NORTH COLLIER BOULEVARD PAVING AND DRAINAGE IMPROVEMENTS

More information

University Apartments on Brooklyn PROJECT MANUAL

University Apartments on Brooklyn PROJECT MANUAL Section 011000 - Summary PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Project information. 2. Work covered by Contract Documents. 3. Phased construction. 4. Work under separate contracts. 5. Access

More information

1ARCHITECTURE TABLE OF CONTENTS

1ARCHITECTURE TABLE OF CONTENTS TABLE OF CONTENTS DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 00 0102 COVER 00 0107 SEALS PAGE 00 0111 TABLE OF CONTENTS DIVISION 01 - GENERAL REQUIREMENTS 01 1000 01 2000 01 2100 01 2300 01

More information

PROJECT MANUAL. Phi Delta Theta Phase NW 13 th Street Corvallis, OR Varitone Architecture LLC

PROJECT MANUAL. Phi Delta Theta Phase NW 13 th Street Corvallis, OR Varitone Architecture LLC PROJECT MANUAL Phi Delta Theta Phase 2 120 NW 13 th Street Corvallis, OR 97330 Varitone Architecture LLC 231 SW 2nd Ave. PO Box 3420 Albany, Oregon 97321 Project Contacts Owner Phi Delta Theta Chapter

More information

DREW UNIVERSITY SPECIFICATIONS ARCHITECTURAL & M.E.P. HALL OF SCIENCES LABORATORY 129 AND 133 RENOVATION. 36 Madison Avenue Madison, New Jersey

DREW UNIVERSITY SPECIFICATIONS ARCHITECTURAL & M.E.P. HALL OF SCIENCES LABORATORY 129 AND 133 RENOVATION. 36 Madison Avenue Madison, New Jersey SPECIFICATIONS ARCHITECTURAL & M.E.P. DREW UNIVERSITY HALL OF SCIENCES LABORATORY 129 AND 133 RENOVATION 36 Madison Avenue Madison, New Jersey NK Project #2199.000 ISSUED FOR REVIEW March 09, 2018 95 Washington

More information

Project Manual. Beaverton School District Beaverton High School Gymnasium Improvement Beaverton, Oregon. Issue date: December 21st 2017

Project Manual. Beaverton School District Beaverton High School Gymnasium Improvement Beaverton, Oregon. Issue date: December 21st 2017 Project Manual Beaverton School District Beaverton High School Gymnasium Improvement Beaverton, Oregon Issue date: December 21st 2017 18241 Beaverton High School Gymnasium Improvement TABLE OF CONTENTS

More information

RICHMOND PUBLIC SCHOOLS

RICHMOND PUBLIC SCHOOLS PROJECT MANUAL RICHMOND PUBLIC SCHOOLS E.S.H. GREENE ELEMENTARY SCHOOL CONSTRUCTION PROJECT DEPT. OF EDUCATION NO. 123-144-00-100 DIVISION 1 (DRAFT SPECIFICATIONS) PREPARED BY RRMM ARCHITECTS ARCHITECTURE

More information

New Mexico State University Herritage Farm Interpretive Trail

New Mexico State University Herritage Farm Interpretive Trail PROJECT MANUAL PROJECT MANAGER: SHELLEY ZIVKOVICH 575-646-1991 shelleyz@nmsu.edu New Mexico State University Herritage Farm Interpretive Trail APRIL 28, 2017 PROJECT #206-88 WDG ARCHITECTS 1014 South Main

More information

RICHMOND PUBLIC SCHOOLS

RICHMOND PUBLIC SCHOOLS PROJECT MANUAL RICHMOND PUBLIC SCHOOLS NEW MIDDLE SCHOOL CONSTRUCTION ON HULL STREET CONSTRUCTION PROJECT DEPT. OF EDUCATION NO. 123-108-00-100 DIVISION 1 (DRAFT SPECIFICATIONS) PREPARED BY RRMM ARCHITECTS

More information

THE FORUM ROME, GEORGIA FOR FLOYD COUNTY PROJECT MANUAL (BALLROOM AND CONCESSIONS) Construction Documents

THE FORUM ROME, GEORGIA FOR FLOYD COUNTY PROJECT MANUAL (BALLROOM AND CONCESSIONS) Construction Documents THE FORUM ROME, GEORGIA FOR FLOYD COUNTY PROJECT MANUAL (BALLROOM AND CONCESSIONS) Construction Documents Architect s Project Number: 420.01.01 Issued: November 11, 2016 PEACOCK a r c h i t e c t s 5525

More information

County of Elko, Nevada Requirements, Specifications and Contract Documents. Mechanical System Upgrade, Project Manuel. Jackpot, Elko County, Nevada

County of Elko, Nevada Requirements, Specifications and Contract Documents. Mechanical System Upgrade, Project Manuel. Jackpot, Elko County, Nevada 1 County of Elko, Nevada Requirements, Specifications and Contract Documents for Jackpot Recreation Center Mechanical System Upgrade 2016 Project in Jackpot, Elko County, Nevada Department of Community

More information

The Town will coordinate with the adjacent property Owner for access allowing work to the East side of the building.

The Town will coordinate with the adjacent property Owner for access allowing work to the East side of the building. ADDENDUM #1 EXTERIOR REPAIRS YOUTH SERVICES BUREAU 63 LINDEN STREET MANCHESTER, CT 06040 BID #15/16-68 S/P+A PROJECT NO. 15.207 DATE: March 15, 2016 The following changes to the Drawings and Project Specifications

More information

Project Manual OVERLAND PARK BRANCH & ESIS RELOCATION. for

Project Manual OVERLAND PARK BRANCH & ESIS RELOCATION. for Project Manual OVERLAND PARK BRANCH & ESIS RELOCATION for Chubb Floor 4 34 Corporate Woods 10950 Grandview Drive Overland Park KS 66210 Issued for Bid & Permit July 18, 2016 SECTION 000110 TABLE OF CONTENTS

More information

707 Minnesota Ave., Suite 506 Kansas City, Kansas Tel Fax

707 Minnesota Ave., Suite 506 Kansas City, Kansas Tel Fax ADDENDUM 707 Minnesota Ave., Suite 506 Kansas City, Kansas 66101 Tel. 913.287.1900 Fax. 816.300.4102 www.wskfarch.com A r c h i t e c t u r e I n t e r i o r D e s i g n I l l u s t r a t I o n P l a n

More information

University of South Florida Health Center MDL-0114 Building Reroofing USF Project No. PF

University of South Florida Health Center MDL-0114 Building Reroofing USF Project No. PF University of South Florida Health Center MDL-0114 Building Reroofing USF Project No. PF154317843202 Project Manual October 31, 2017 October 31, 2017 Project Manual For University of South Florida Health

More information

Baseball Performance Development Center A Prevailing Wage Project

Baseball Performance Development Center A Prevailing Wage Project June 30, 2016 Baseball Performance Development Center A Prevailing Wage Project PROJECT MANUAL Owner CENTRAL MICHIGAN UNIVERISTY 206 Combined Services Building Mount Pleasant, Michigan PROJECT NUMBER 15-231

More information

WINDOW REPLACEMENT FOR ARCHITECT'S NO NORWOOD ELEMENTARY SCHOOL. A. Project Name: Window Replacement for Norwood Elementary School.

WINDOW REPLACEMENT FOR ARCHITECT'S NO NORWOOD ELEMENTARY SCHOOL. A. Project Name: Window Replacement for Norwood Elementary School. WINDOW REPLACEMENT FOR ARCHITECT'S NO. 2638 NORWOOD ELEMENTARY SCHOOL DOCUMENT 00 9113A - ADDENDUM NO. 1 1.1 PROJECT INFORMATION A. Project Name: Window Replacement for Norwood Elementary School. B. Owner:

More information

ANTELOPE VALLEY COLLEGE PALMDALE AIRPORT TERMINAL REMODEL

ANTELOPE VALLEY COLLEGE PALMDALE AIRPORT TERMINAL REMODEL PALMDALE AIRPORT TERMINAL REMODEL 21000 20 TH STREET EAST, PALMDALE, CA 93550 for ANTELOPE VALLEY COMMUNITY COLLEGE DISTRICT 3041 WEST AVENUE K LANCASTER, CALIFORNIA 93536-5436 PROJECT MANUAL AUGUST 15,

More information

CONTRACTOR S PROPOSAL

CONTRACTOR S PROPOSAL WEST VIRGINIA DEPARTMENT OF TRANSPORTATION DIVISION OF HIGHWAYS ALL ITEMS MUST BE COMPLETED BY CONTRACTOR CALL NUMBER CONTRACTOR S NAME CONTRACTOR S FEIN BID AMOUNT DBE GOAL (%) WV LICENSE NUMBER PREQUALIFICATION

More information

***Specifications***

***Specifications*** STEM 2 Greenhouse Project Bid No. B17-14 ***Specifications*** Bid RFI Questions Due: Tuesday, July 11, 2017 2:00PM Gale Stevens, Buyer gasteven@cabrillo.edu BID DOCUMENTS: GALE STEVENS, BUYER 831-477-5613

More information

Robert M. Ball Conference Room Renovation Project

Robert M. Ball Conference Room Renovation Project ROBERT M. BALL BUILDING SOCIAL SECURITY ADMINISTRATION CAMPUS WOODLAWN, MARYLAND Robert M. Ball Conference Room Renovation Project Specifications Prepared for: General Services Administration Region 3

More information

Illinois State University Softballl Dugout Replacement Normal, Illinois

Illinois State University Softballl Dugout Replacement Normal, Illinois Illinois State University Softballl Dugout Replacement Normal, Illinois Issue for Bid ISU Project No. 10611 DLR Group Project No. 22-11116-10 July 1, 2016 NOTICE: These documents are instruments of professional

More information

PROJECT MANUAL VOLUME ONE EOP Project # August 17, 2018

PROJECT MANUAL VOLUME ONE EOP Project # August 17, 2018 PROJECT MANUAL VOLUME ONE EOP Project # 201732 August 17, 2018 KCTCS System Office Renovation MECHANICAL ROOM EQUIPMENT DEMOLITION 300 N. Main St. Versailles, Kentucky 40383 ARCHITECT EOP Architects 201

More information

G , Request for Proposal Land Survey

G , Request for Proposal Land Survey G601 1994, Request for Proposal Land Survey AIA Document G601 1994 allows owners to request proposals from a number of surveyors based on information deemed necessary by the owner and architect. G601 1994

More information

PROJECT MANUAL UNIVERSITY HALL BOILER REPLACEMENT PROJECT NO. EM 610

PROJECT MANUAL UNIVERSITY HALL BOILER REPLACEMENT PROJECT NO. EM 610 PROJECT MANUAL For UNIVERSITY HALL BOILER REPLACEMENT PROJECT NO. EM 610 Prepared For: UNIVERSITY OF COLORADO AT COLORADO SPRINGS September 27, 2010 Prepared By: SCHENDT ENGINEERING CORP. 2912 Beacon Street

More information

Ogden Regional Medical Center Courtyard Remodel. Construction Documents. MountainStar Healthcare PROJECT MANUAL FOR

Ogden Regional Medical Center Courtyard Remodel. Construction Documents. MountainStar Healthcare PROJECT MANUAL FOR PROJECT MANUAL FOR Ogden Regional Medical Center 5475 South 500 East Ogden, UT 84405 for MountainStar Healthcare Construction Documents NJRA Architects, Inc. 5272 South College Dr. Murray, Utah 84123 Telephone:

More information

INVITATION FOR BIDS FOR

INVITATION FOR BIDS FOR ********************************************************************************************** IFB NO. Y18-749-RM ISSUED: March 16, 2018 INVITATION FOR BIDS FOR EAST ORANGE HEAD START MODULAR RELOCATION

More information

AWT 9TH FLOOR IMPROVEMENTS CITY OF ANAHEIM, CALL CENTER CREDIT & BILLING DEPARTMENTS, ANAHEIM, CA TECHNICAL SPECIFICATIONS AUGUST 2, 2018

AWT 9TH FLOOR IMPROVEMENTS CITY OF ANAHEIM, CALL CENTER CREDIT & BILLING DEPARTMENTS, ANAHEIM, CA TECHNICAL SPECIFICATIONS AUGUST 2, 2018 CITY OF ANAHEIM, CALL CENTER CREDIT & BILLING DEPARTMENTS, ANAHEIM, CA TECHNICAL SPECIFICATIONS AUGUST 2, 2018 ROBERT BORDERS & ASSOCIATES. General Conditions AIA A201 by reference. TABLE OF CONTENTS DIVISION

More information

AWT 2ND FLOOR IMPROVEMENTS CITY OF ANAHEIM, HOUSING AUTHORITY & WORKPLACE, ANAHEIM, CA TECHNICAL SPECIFICATIONS OCTOBER 24, 2017

AWT 2ND FLOOR IMPROVEMENTS CITY OF ANAHEIM, HOUSING AUTHORITY & WORKPLACE, ANAHEIM, CA TECHNICAL SPECIFICATIONS OCTOBER 24, 2017 CITY OF ANAHEIM, HOUSING AUTHORITY & WORKPLACE, ANAHEIM, CA TECHNICAL SPECIFICATIONS OCTOBER 24, 2017 ROBERT BORDERS & ASSOCIATES. General Conditions AIA A201 by reference. TABLE OF CONTENTS DIVISION 1

More information

SECTION PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 01600 - PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

LCCC MAIN PLANT BOILER BURNER UPGRADES

LCCC MAIN PLANT BOILER BURNER UPGRADES LCCC MAIN PLANT BOILER BURNER UPGRADES FOR Laramie County Community College (LCCC) 1400 East College Drive Cheyenne, WY 82007 ENGINEERS Cator, Ruma & Associates 420 West Lincolnway Cheyenne, WY 82001 PROJECT

More information

PROJECT MANUAL VOLUME ONE EOP Project # November 12, 2018

PROJECT MANUAL VOLUME ONE EOP Project # November 12, 2018 PROJECT MANUAL VOLUME ONE EOP Project # 201732 November 12, 2018 KCTCS System Office Renovation COPY CENTER FIT-UP 300 N. Main St. Versailles, Kentucky 40383 ARCHITECT EOP Architects 201 W. Short St.,

More information

Façade Access Upgrade Project

Façade Access Upgrade Project University of California Hastings College of Law Façade Access Upgrade Project 200 McAllister Street, San Francisco, CA 94102 Project Number 12042.04 ITB #56-0160 (Revised) August 20, 2015 PROJECT MANUAL

More information

PROJECT SPECIFICATIONS. for. Grossmont Community College. Main Chiller Plant Repair. El Cajon, CA. Bid Number B18.014

PROJECT SPECIFICATIONS. for. Grossmont Community College. Main Chiller Plant Repair. El Cajon, CA. Bid Number B18.014 PROJECT SPECIFICATIONS for Grossmont Community College El Cajon, CA Bid Number B18.014 Grossmont College Specification TOC 07/11/2018 DIVISION 01 GENERAL REQUIREMENTS 01 10 00 ~ Summary 01 14 00 ~ Work

More information

Scope of Repair Davenport Grade School Roof Repair

Scope of Repair Davenport Grade School Roof Repair Scope of Repair Grade School Roof Repair Prepared for: Graehm Wallace Perkins Coie LLP 1201 Third Avenue, Suite 4900 Seattle, WA 98101-3099 Date of Issuance: March 19, 2018 SECTION 011000 SUMMARY OF WORK

More information

ORANGE COUNTY UTILITIES RS&H OPERATIONS CENTER PEMB PACKAGE TABLE OF CONTENTS

ORANGE COUNTY UTILITIES RS&H OPERATIONS CENTER PEMB PACKAGE TABLE OF CONTENTS ORANGE COUNTY UTILITIES RS&H 107-0745-001 OPERATIONS CENTER PEMB PACKAGE TABLE OF CONTENTS 100% PERMIT SUBMITTAL March 15, 2013 PART DESCRIPTION SECTION H TECHNICAL PROVISIONS DIVISION 1 GENERAL REQUIREMENTS

More information

PROJECT MANUAL. Bleacher Addition Rigby High School School District No. 251 Rigby, Idaho. Set No. F o r t h e C o n s t r u c t i o n o f :

PROJECT MANUAL. Bleacher Addition Rigby High School School District No. 251 Rigby, Idaho. Set No. F o r t h e C o n s t r u c t i o n o f : PROJECT MANUAL F o r t h e C o n s t r u c t i o n o f : Bleacher Addition Rigby High School School District No. 251 Rigby, Idaho M a r c h 2 0 1 8 Set No. 9 9 0 J o h n A d a m s P a r k w a y, P. O.

More information

A. Project Identification: Wiggums Park Place Renovation. D. See Section Project Team List for additional information.

A. Project Identification: Wiggums Park Place Renovation. D. See Section Project Team List for additional information. SECTION 01 10 00 - SUMMARY PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Project information. 2. Work covered by Contract Documents. 3. Specification and drawing conventions. 4. Miscellaneous provisions.

More information

[FIELDHOUSE] FLOOR R E P L A C E M E N T FLAGSTAFF, AZ

[FIELDHOUSE] FLOOR R E P L A C E M E N T FLAGSTAFF, AZ [FIELDHOUSE] FLOOR R E P L A C E M E N T FLAGSTAFF, AZ P R O J E C T M A N U A L VOLUME 1 OF 1 1729 EAST OSBORN ROAD PHOENIX, AZ 85016 CD ISSUANCE NAU PROJECT NO.: 09.0330.171 LIGHTVOX PROJECT NO.: 3001.16.01

More information

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS SECTION 01 00 00 GENERAL REQUIREMENTS PART 1 - GENERAL 1.1 SECTION INCLUDES A. Summary of Work: 1. General 2. Contract. B. Contract Considerations: 1. Schedule of values. 2. Applications for payment. 3.

More information

SANTA FE STATION KDOT Grant No. 23 TE

SANTA FE STATION KDOT Grant No. 23 TE SANTA FE STATION KDOT Grant No. 23 TE-0373-01 PRESERVATION PROJECT 413 E 7 TH Street - Lawrence, Kansas Project Manual Issue Date: July 15, 2015 KANSAS DEPT. OF TRANSPORTATION Dwight D. Eisenhower State

More information

1. Instructions to Bidders AIA Document A701, 1997 Section of the above referenced IFB is hereby amended and restated as follows:

1. Instructions to Bidders AIA Document A701, 1997 Section of the above referenced IFB is hereby amended and restated as follows: Segments 3, 4, 6 and 7 Pier Repairs Invitation for Bids (IFB) Project/Contract #C4962 Addendum # 1 November 30, 2018 To All Bidders: 1. Instructions to Bidders AIA Document A701, 1997 Section 5.3.1.3 of

More information

1. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following:

1. This Section includes administrative and procedural requirements for contract closeout including, but not limited to, the following: SECTION 01700 - CONTRACT CLOSEOUT PART 1 - GENERAL 1.01 RELATED DOCUMENTS 1. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

ruby ridge terrace apartments

ruby ridge terrace apartments p r o j e c t m a n u a l for: ruby ridge terrace apartments 550 South, 12th Street 89801 Re-Bid Package 01 May 14, 2014 TABLE OF CONTENTS 1. Title page 2. Table of Contents 3. Invitation to Bid 4. Bid

More information

PROJECT MANUAL. New Building Addition for Kenworth Sales Company, Inc. Ontario, Oregon. Set No. 01. For the Construction of: October 2017

PROJECT MANUAL. New Building Addition for Kenworth Sales Company, Inc. Ontario, Oregon. Set No. 01. For the Construction of: October 2017 PROJECT MANUAL For the Construction of: New Building Addition for Kenworth Sales Company, Inc. Ontario, Oregon October 2017 Set No. 01 990 John Adams Parkway, P.O. Box 2212, Idaho Falls, Idaho 83403-2212

More information

AIR CONDITIONING SYRACUSE JUNIOR HIGH SCHOOL

AIR CONDITIONING SYRACUSE JUNIOR HIGH SCHOOL PROJECT MANUAL FOR AIR CONDITIONING DAVIS SCHOOL DISTRICT 1450 S. 2000 W. Syracuse, UT 84075 January 2017 BLANK PAGE TABLE OF CONTENTS DIVISION 01 GENERAL CONDITIONS 01 1000 Summary 01 2900 Payment Procedures

More information

PROJECT MANUAL ISSUE FOR PERMIT 08 AUGUST 2018 Volume 1 of 1 Divisions 00 through 33 ASTERISK EVENT SPACE DENVER, COLORADO Path21 Project No.

PROJECT MANUAL ISSUE FOR PERMIT 08 AUGUST 2018 Volume 1 of 1 Divisions 00 through 33 ASTERISK EVENT SPACE DENVER, COLORADO Path21 Project No. PROJECT MANUAL ISSUE FOR PERMIT 08 AUGUST 2018 Volume 1 of 1 Divisions 00 through 33 ASTERISK EVENT SPACE DENVER, COLORADO Path21 Project No. 18-003 PROJECT MANUAL Asterisk Event Space Denver, Colorado

More information

Northridge High School Remodel

Northridge High School Remodel CONSTRUCTION DOCUMENTS general construction volume divisions 0 thru 48 1 Northridge High School Remodel 2 4 3 0 N H I L L F I E L D R O A D I L A Y T O N, U T A H OWNER D a v i s S c h o o l D i s t r

More information

DIVISION 10 - SPECIALTIES Toilet, Bath, and Laundry Accessories Fire Extinguishers

DIVISION 10 - SPECIALTIES Toilet, Bath, and Laundry Accessories Fire Extinguishers DIVISION 01 GENERAL REQUIREMENTS 012500 Substitution Procedures 012600 Contract Modification Procedures 013100 Project Management and Coordination 013150 Requests for Information 013200 Construction Progress

More information

BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX BID PACKAGE #1 SITE WORK

BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX BID PACKAGE #1 SITE WORK HOSKINS ARCHITECTURE, LLC 1827 1 ST AVENUE NORTH, SUITE 104 BIRMINGHAM, ALABAMA 35203 205.321.4122 ADDENDUM NO. 1 PROJECT: BIRMINGHAM CITY SCHOOLS (BCS) OPERATIONAL CENTER COMPLEX BID PACKAGE #1 SITE WORK

More information

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 01 GENERAL REQUIREMENTS

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 01 GENERAL REQUIREMENTS SECTION 016000 - PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes administrative and procedural requirements for selection of products for use in Project; product delivery, storage,

More information

A. Section includes administrative and procedural requirements for substitutions.

A. Section includes administrative and procedural requirements for substitutions. SPECIFICATIONS NO. XX-XX-XXX-XX SECTION 01 25 00 - SUBSTITUTION PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary

More information

WEST GATE ENTRANCE EXTERIOR IMPROVEMENTS BEXAR COUNTY ARENAS - FENCING PACKAGE

WEST GATE ENTRANCE EXTERIOR IMPROVEMENTS BEXAR COUNTY ARENAS - FENCING PACKAGE PROJECT MANUAL / TECHNICAL SPECIFICATIONS WEST GATE ENTRANCE EXTERIOR IMPROVEMENTS - FENCING PACKAGE 3201 E. HOUSTON STREET SAN ANTONIO, TEXAS 78219 OCTOBER 6, 2017 HUMBERTO SALDANA & ASSOCIATES, INC.

More information

New Mexico State University Roof Replacement Various Buildings

New Mexico State University Roof Replacement Various Buildings Project Manual for New Mexico State University Roof Replacement Various Buildings Fire Station Nason House Nematology Science Hall NEW MEXICO STATE UNIVERSITY LAS CRUCES, NM May 20, 2016 PRE SIGNATURE

More information

1. Division 1 Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1. Division 1 Section Temporary Facilities and Controls for limitations and procedures governing temporary use of Owner's facilities. CFA A HVAC PROJECT SECTION 01100 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

LOS RIOS COMMUNITY COLLEGE DISTRICT 1919 Spanos Court, Sacramento, CA Phone (916) FAX (916) Purchasing Department

LOS RIOS COMMUNITY COLLEGE DISTRICT 1919 Spanos Court, Sacramento, CA Phone (916) FAX (916) Purchasing Department LOS RIOS COMMUNITY COLLEGE DISTRICT 1919 Spanos Court, 95825 Phone (916) 568-3071 FAX (916) 568-3145 Purchasing Department Sacramento City College American River College Cosumnes River College Folsom Lake

More information

Document B252TM 2007

Document B252TM 2007 Document B252TM 2007 Standard Form of Architect s Services: Architectural Interior Design for the following PROJECT: (Name and location or address) This document has important legal consequences. Consultation

More information

HOLLOWAY HALL AUDITORIUM RENOVATION

HOLLOWAY HALL AUDITORIUM RENOVATION HOLLOWAY HALL AUDITORIUM RENOVATION BID DOCUMENTS PROJECT MANUAL JANUARY 2, 2013 SALISBURY UNIVERSITY FACILITIES PLANNING AND CAPITAL PROJECTS 1101 CAMDEN AVENUE SALISBURY, MARYLAND 21801 DESIGN COLLECTIVE,

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 4000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

Amphitheater High School Roof Replacement

Amphitheater High School Roof Replacement Amphitheater Public Schools Amphitheater High School Roof Replacement BG Project No: 17.14.06 Construction Document Specifications Amphitheater High School Roof Replacement SPECIFICATIONS INDEX DIVISION

More information

QUALITY REQUIREMENTS

QUALITY REQUIREMENTS SECTION 014000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

Chapter 6, Construction

Chapter 6, Construction Chapter 6, Construction CHAPTER CONTENTS 6.1 OWNER-CONTRACTOR AGREEMENT A. Preparation B. Owner Signature C. Award 6.2 PRE-CONSTRUCTION CONFERENCE A. Administration B. Attendees C. Pre-Construction Conference

More information

PROJECT MANUAL WAYNE STATE UNIVERSITY FACILITIES PLANNING & MANAGEMENT DESIGN SERVICES 5454 CASS AVENUE DETROIT, MICHIGAN 48202

PROJECT MANUAL WAYNE STATE UNIVERSITY FACILITIES PLANNING & MANAGEMENT DESIGN SERVICES 5454 CASS AVENUE DETROIT, MICHIGAN 48202 PROJECT MANUAL FACILITIES PLANNING & MANAGEMENT DESIGN SERVICES 5454 CASS AVENUE DETROIT, MICHIGAN 48202 ROOF REPLACEMENT SCHOOL OF SOCIAL WORK BUILDING 5447 WOODWARD AVENUE, DETROIT, MICHIGAN 48202 WSU

More information

IBMF STATE OF GOOD REPAIR UPGRADES

IBMF STATE OF GOOD REPAIR UPGRADES IBMF STATE OF GOOD REPAIR UPGRADES City of North Las Vegas, Nevada SPECIFICATIONS For 14-092 December 26, 2013 TABLE OF CONTENTS SECTION 01100 SECTION 01250 SECTION 01290 SECTION 01310 SECTION 01322 SECTION

More information

ELECTRICAL CONSULTANT

ELECTRICAL CONSULTANT INFRASTRUCTURE BUILDINGS 36 & 41 GROSSMONT COLLEGE GROSSMONT CUYAMACA COMMUNITY COLLEGE DISTRICT #B19.005 CLIENT 8800 Grossmont College Drive El Cajon, CA 92021 ELECTRICAL CONSULTANT Johnson Consulting

More information

Richard B. Wilson K-8 School Roof Restoration

Richard B. Wilson K-8 School Roof Restoration Amphitheater Public Schools Richard B. Wilson K-8 School Roof Restoration BG Project No: 17.14.24 Construction Document Specifications Richard B. Wilson K-8 School Roof Restoration SPECIFICATIONS INDEX

More information

DAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower

DAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower DOCUMENT 001153 - REQUEST FOR QUALIFICATIONS 1.1 PURPOSE, LAWS, AND REGULATIONS A. The purpose of the Prequalification Procedure described in this Document is to provide Owner with a mechanism to evaluate

More information

THE HOUSING AUTHORITY OF THE BOROUGH OF HIGHLAND PARK 242 SOUTH SIXTH AVENUE, HIGHLAND PARK, NJ PHONE (732)

THE HOUSING AUTHORITY OF THE BOROUGH OF HIGHLAND PARK 242 SOUTH SIXTH AVENUE, HIGHLAND PARK, NJ PHONE (732) THE HOUSING AUTHORITY OF THE BOROUGH OF HIGHLAND PARK 242 SOUTH SIXTH AVENUE, HIGHLAND PARK, NJ 08904 PHONE (732)572-4420 January 10, 2017 Roof Replacement at Samuel J Kronman Building Addendum #1 Please

More information

Beverly Gardens Park City of Beverly Hills, CA. Block #9: Elm Foothill Garden

Beverly Gardens Park City of Beverly Hills, CA. Block #9: Elm Foothill Garden Beverly Gardens Park Block #9: SPECIFICATIONS 100% CD / BID SET TABLE OF CONTENTS DIVISION 01 GENERAL REQUIREMENTS SECTION No. TITLE 011000.Summary. 3 012213.Unit Prices...1 012500.Substitution Procedures

More information

UMC El Paso Far East Clinic and Neighborhood Healthcare Center West Issue for Construction Page Project No and April 13, 2015

UMC El Paso Far East Clinic and Neighborhood Healthcare Center West Issue for Construction Page Project No and April 13, 2015 Page Project No. 414018 and 414019 April 13, 2015 Table of Contents Division Section Title Pages PROCUREMENT AND CONTRACTING DOCUMENTS GROUP DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS 003100

More information

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition Document B132 2009 Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition AGREEMENT made as of the in the year (In words, indicate day, month and year.) BETWEEN

More information