1 Sidewalk Repair Program Charter Township of Canton Engineering Services
2 Sidewalk Repair Program History Canton lost a landmark case at the Michigan Supreme Court level in The Supreme Court has determined that Townships are responsible for maintenance of sidewalks located within a public right-of-way (ROW). The sidewalk ordinance and repair program was implemented in 1999 to reduce our liability from injury claims and improve the appearance of the community.
3 Sidewalk Repair Program History The program began with inspection of the oldest subdivisions platted in the Township. In the later years we consolidated subdivisions by area. The first cycle of the program covered 16 years. We have inspected sidewalks in all 154 platted subdivisions, totaling 16,353 parcels. The second cycle of sidewalk repair is planned to cover 10 years. Consolidated subdivision areas are depicted on a map in targeted zones.
4 Sidewalk Program Target Zones See Map for Targeted Neighborhood Areas 2015 ZONE ZONE ZONE ZONE ZONE ZONE ZONE ZONE ZONE ZONE 10
5 Sidewalk Repair Program Facts Every year the Township works on three (3) different sidewalk repair programs consisting of the past (warranty work), present (construction repair) and future (marking & quantities). Concerns about the program are typically handled as a service request. Service requests are tracked by software, providing electronic information to staff, prior to addressing. Sidewalk inspection for the following year targeted zone is advertised in our local paper and shown on our website. The area includes all commercial and residential parcels that are located along a public road right-of-way.
6 Sidewalk Program Inspections As inspections are done, defective concrete is marked & photographed. Quantities are then measured and charted by parcel ID. The inspector marks defective concrete with dots: (Red) dots indicate areas of Township responsibility (Green) dots areas of Resident responsibility
7 Code of Ordinances The sidewalk section is in Chapter 62, Article 2, in Section 62-31/38 inclusive. The detailed criteria used to determine sidewalk repair may be viewed on our website:
8 Ordinance Criteria Sidewalk Dots? Here are some examples
9 Sidewalk Displacement Displacement of 3/4 inch or greater between any two slabs.
10 Spalling Sidewalk If, in any five-linear-foot of sidewalk, more than 50 percent of the surface has scaled off to a depth of one-quarter inch or greater.
11 Spider Cracking If spider cracking is visible and adjoining flag(s) need to be removed. Additives placed in the concrete (due to cold or hot weather changes), or used in the finishing process, may cause spider cracking. It is possible that when removing a defective flag, adjacent, unmarked flags with pre-existing spider cracks may crumble from the release in pressure that is currently holding the spider-cracked flag together.
12 Cracked Sidewalks If the sidewalk has more than two cracks of one-quarter inch in width (or more) in any two linear feet of sidewalk section.
13 Ponding of Water If the concrete has settled, allowing water to pond to a depth of three-quarters inch or more.
14 Back Pitch or Back Slope If any section of sidewalk is tilted from the outside edge toward the inside edge. The outside edge being the edge of the sidewalk nearest the street.
15 Utility Repair If a portion of the sidewalk is removed or damaged as a result of a utility repair.
16 Township Owned Utility Sanitary Manhole and Water System Gate Valves If the sidewalk is damaged as a result of a Township utility.
17 Storm Sewer Manholes Owned by Wayne County Sidewalk in the right-of-way that has a defect caused by a County Storm Water structure will be addressed by Canton Township for the safety of our residents. Only sidewalk flags that touch the storm manhole will be repaired by the Township. Any adjoining flags that need repair will be the responsibility of the homeowner.
18 Sidewalk Ramps Bringing into ADA compliance Ramps with concrete defects are brought into compliance per the American Disability Act. Sidewalk ramps will not be assessed to the adjacent property owner. Ramps are considered from the edge of the curb up to the key flag. Ramps that require adjustment in grade to meet the ADA Accessibility Guidelines (including the key flag) will not be assessed to the adjacent property owner. Ramps that lead across into a driveway or go nowhere, such as to a greenbelt area, will be removed and replaced with sod as required by Wayne County standards, only when defective concrete is present.
19 Medians & Common Park Areas Median sidewalk and common park areas with sidewalk fronting the road are considered home owner association responsibility. The cost for this repair will be billed to your association. The sidewalk flags marked within the median will be repaired and brought into compliance to meet the ADA Accessibility Guidelines. Ramps located along common park areas are considered home owner association responsibility.
20 Sidewalk Approach Apron It is the duty of every owner of property to maintain and keep sidewalks and driveway approaches in a condition reasonably safe for public travel.
21 Sidewalk Repair Program Incorporating a Master Gap Plan History In late 1999 to early 2000, a committee of sidewalk members came together prioritizing missing links of sidewalk. The exception on that list of missing sidewalk, were areas under active development. Between 2001 thru 2014 the Township completed approximately 6,000 flags/slabs of sidewalk gap. That equates to about 6 miles.
22 Sidewalk Repair Program Incorporating a Master Gap Plan Facts Locations of missing sidewalk links on worn paths are reported and placed on a list. Some of these locations have been shown on the sidewalk repair program map. The list, depicting missing sidewalk link locations, denote gaps that are to remain and those that are to be installed. A master gap plan from the list will be utilized to establish future installation for projects under review, approval or building permit application.
23 Sidewalk Repair Program Notification Public notification for the necessity of repairs is advertised. Estimate letters are mailed to the homeowner containing information about quantities and price in March. Estimate letters include notification of the public hearing date, homeowner responsibility, the contractor chosen, construction information including contact numbers and information that can be viewed on our website.
24 Sidewalk Repair Program What happens next? The Resident or Business Owner will have 60 days from the date of the Public Hearing to perform one of the following: Replace the sidewalk marked with green dots. All work must meet Canton Township Standards. Contractors must obtain a permit and inspection from the Canton Township Building & Inspection Services Division and obtain a Wayne County Permit for work within the rightof-way (ROW). This work must be done prior to Memorial Day. Do nothing and Canton will repair the sidewalk and invoice the resident for the work performed. Canton will have a contractor perform the work during the months of June and July. Invoices for that work will be mailed in the fall or winter.
25 Construction On June 1 st sidewalk construction repair will begin with an anticipated completion the end of July.
26 Sidewalk Program Conclusion The sidewalk repair program effectively corrects sidewalk defects. Defects occur due to age deterioration, cracking, disintegration, root lifting and construction work activities. Repairing these defects provides safe pedestrian travel for our residents, in a beautiful community that they and their children can enjoy for years!
Sidewalk Repair Program. Charter Township of Canton
Sidewalk Repair Program Charter Township of Canton Engineering Services Sidewalk Repair Program The sidewalk ordinance and repair program was implemented in 1999 to reduce our liability from injury claims
More informationSIDEWALK CONSTRUCTION AND REPAIR
SIDEWALK CONSTRUCTION AND REPAIR Q: Why all the concern over sidewalks? A: Sidewalks are the avenues and streets of pedestrian traffic. Residents should maintain the sidewalks as best as they can. The
More informationCITY OF DES PLAINES-CONCRETE PROGRAM SIDEWALK, CURB AND DRIVEWAY GUIDELINES
CITY OF DES PLAINES-CONCRETE PROGRAM SIDEWALK, CURB AND DRIVEWAY GUIDELINES SUMMARY AND INTENT OF PROJECT The City of Des Plaines Curb and Sidewalk Program is intended to repair hazardous sidewalk and
More informationMaintaining a Walkable Sacramento: SIDEWALK MAINTENANCE PROGRAM HANDBOOK
Maintaining a Walkable Sacramento: SIDEWALK MAINTENANCE PROGRAM HANDBOOK Well-maintained sidewalks and curb ramps provide safe and desirable paths for pedestrians and others to enjoy neighborhoods, commercial
More informationHomeowner s Do-It Yourself Guide for Hazardous Sidewalks
Homeowner s Do-It Yourself Guide for Hazardous Sidewalks The City and County of Denver s Neighborhood Sidewalk Repair Program is a multi-year program addressing damaged, sloping and uneven sidewalks, citywide,
More informationDriveways and Other Concrete Slabs
Driveways and Other Concrete Slabs V I L L A G E O F H A N O V E R P A R K F I R E D E PA R T M E N T I certify that I have received a copy of these regulations and will comply with the regulations contained
More informationCurb and Gutter Replacement Project Phase I
Phase I Prepared for: Prepared by: Cheyenne Downtown Development Authority / Main Street 1601 Capitol Avenue Cheyenne, WY 82001 307 433 9730 BenchMark Engineers, PC 1920 Thomes Avenue, Suite 620 Cheyenne,
More informationPresented By SUCCESSFUL SIDEWALK STRATEGIES: Learning Objectives. Part I Problems Underfoot. Part I Complications. Part I Typical Approaches
SUCCESSFUL SIDEWALK STRATEGIES: EFFECTIVE SIDEWALK MAINTENANCE MANAGEMENT Presented By Overland Park, Kansas, Public Works Dave Bergner, Superintendent Janet Luessenheide, Engineering Technician II Michael
More informationDRIVEWAYS & CURB CUTS (INCLUDING DRIVEWAY EXTENSIONS) BUILDING PERMIT APPLICATION
Community Development 17 Montrose Drive Romeoville, IL 60446-1329 (815) 886-7203 (815) 372-4039 Email: buildinginspections@romeoville.org DRIVEWAYS & CURB CUTS (INCLUDING DRIVEWAY EXTENSIONS) BUILDING
More informationSidewalk Regulations. Table of Contents
Sidewalk Regulations Table of Contents Section 1. Purpose and Intent... 2 Section 2. Pedestrian Sidewalk, Driveway Apron and Curb and Guttering Requirements... 2 Section 3. Sidewalk Provision Criteria...
More informationCITY OF MADRAS RIGHT-OF-WAY CONSTRUCTION & USE PERMIT 125 SW E Street, Madras, OR Telephone (541) Fax (541)
CITY OF MADRAS RIGHT-OF-WAY CONSTRUCTION & USE PERMIT 125 SW E Street, Madras, OR 97741 Telephone (541)475-2344 Fax (541)475-1038 Permit type (may include multiple types, please provide detail in the the
More informationCITY OF LOS ANGELES Sidewalk Repair Program. Amber Elton, PE
CITY OF LOS ANGELES Sidewalk Repair Program Amber Elton, PE Sidewalk Repair Program Civil Engineer APRIL 20, 2017 Century Plaza Towers 2029 Century Park East City s Goal BEFORE AFTER Improve Mobility in
More informationEFFECTIVE AND EFFICIENT SIDEWALK MAINTENANCE: Presented By. Learning Objectives AFFORDABLE AND ACHIEVABLE
EFFECTIVE AND EFFICIENT SIDEWALK MAINTENANCE: AFFORDABLE AND ACHIEVABLE LLC 2011 v.3 1 Presented By Janet Luessenheide, Sr. Engineering Technician Overland Park, KS Public Works Michael Hale, P.E., Supervisory
More informationProject Need and Evaluation
City of Brooklyn Center 2011 Palmer Lake East Street and Utility Reconstruction Project Public Hearings February 14, 2011 Public Improvement Hearing: Special Assessments Local public improvements to the
More informationPart 4. Sidewalk Construction and Repair
Part 4. Sidewalk Construction and Repair 604.01. Permit Required. No sidewalk or curb and gutter shall be constructed on any street, alley, avenue, or other public property in this city without first having
More informationSIDEWALK PROBLEMS AND REPAIR
Borough of New Hope, Pennsylvania 41 North Main Street, New Hope, Pennsylvania, 18938 (215) 862-3347 SIDEWALK PROBLEMS AND REPAIR BACKGROUND New Hope Borough Code of Ordinance Article III, section 233-3
More informationPUBLIC WORKS COMMISSION 2018 STREET EXCAVATION PERMIT PROCEDURE
PUBLIC WORKS COMMISSION 2018 STREET EXCAVATION PERMIT PROCEDURE GENERAL Final restoration of areas within the public right-of-way associated with Street Excavation Permits shall be completed as determined
More informationTOWN OF WINDSOR CONCRETE RATING GUIDE
TOWN OF WINDSOR CONCRETE RATING GUIDE December 2007 TOWN OF WINDSOR Engineering Department Concrete Rating Guide The Concrete Rating system is designed to prioritize concrete replacement and assist in
More informationGRADING & DRAINAGE PERMIT SOIL EROSION AND SEDIMENTATION CONTROL PERMIT PROGRAM OVERVIEW
GRADING & DRAINAGE PERMIT SOIL EROSION AND SEDIMENTATION CONTROL PERMIT PROGRAM OVERVIEW Chapter 8 Building and Building Regulations, Article XIII Grading and Drainage and Article XV Soil Erosion and Sedimentation
More informationSidewalk Replacement Criteria The following are the criteria used to determine if sidewalk needs to be replaced in the City of Watertown:
Sidewalk Replacement Criteria The following are the criteria used to determine if sidewalk needs to be replaced in the City of Watertown: -Any slab raised one-half inch (1/2 ) or more, which is considered
More informationSandstone Curb Replacement Standards
Sandstone Curb Replacement Standards Division of Infrastructure Management SCOPE OF CURB REPLACEMENT (Funding Dependent) Sandstone Curb Section I - Purpose: Sandstone curb may be replaced only if existing
More informationI. STREET CONSTRUCTION AND RECONSTRUCTION
CITY OF OSHKOSH POLICY FOR SPECIAL ASSESSMENTS A. GENERAL I. STREET CONSTRUCTION AND RECONSTRUCTION 1. Assessments shall be levied according to the front foot dimensions of the abutting property to the
More informationZoning Permits 11-1 ZONING PERMITS
Zoning Permits 11-1 ZONING PERMITS (a) Building or structures shall be started, repaired, reconstructed, enlarged or altered only after a zoning permit has been obtained from the administrator and a building
More informationSITE SPECIFIC GRADING PLAN FOR CONTIGUOUS SINGLE LOT SINGLE FAMILY RESIDENTIAL CONSTRUCTION WITH PREVIOUSLY APPROVED PRELIMINARY PLAT (FORM 2)
WASHINGTON COUNTY DIVISION OF PLAN REVIEW AND PERMITTING 80 West Baltimore Street Hagerstown, Maryland 21740-6003 Telephone: (240) 313-2460 FAX: (240) 313-2461 Hearing Impaired call 7-1-1 for Maryland
More informationstudy for 2018 include:
MEMORANDUM TO: Mayor and City Council gk FROM: Shawn Sanders irector of Public Works DATE: March 15, 2018 RE: Feasibility Study for the 2018 Street Improvement Project Project No. 2018-02 INTRODUCTION
More informationARTERIAL BLOCK WALL REPLACEMENT PERMIT APPLICATION Please Type or Print
ARTERIAL BLOCK WALL REPLACEMENT PERMIT APPLICATION Please Type or Print An arterial block wall replacement permit is required for the repair and/or replacement of existing privately-owned block walls located
More informationCHURCHILL DOWNS SUBDIVISION, 2 ND UNIT, RESUBDIVISION OF LOTS
CHURCHILL DOWNS SUBDIVISION, 2 ND UNIT, RESUBDIVISION OF LOTS 105-107 Engineering Comments: Must comply with the Mobile County Flood Damage Prevention Ordinance. Mobile Area Water & Sewer System Comments:
More informationAPPLICATION FOR A SITE CONSTRUCTION PERMIT
CITY OF KLAMATH FALLS PUBLIC WORKS ENGINEERING 226 S. 5 th St., Klamath Falls, OR 97601 Phone (541) 883-5368 Fax (541) 883-5287 APPLICATION FOR A SITE CONSTRUCTION PERMIT For City Use Only: APPLICATION
More informationPavement Surface Evaluation and Rating. Manual RATING RATING RATING PASER RATING. Concrete Roads
PASER MANUAL FOR CONCRETE ROADS PAVEMENT ENGINEERING SERVICES PASER RATING SUNFLOWER VILLAGE HOMES ASSOCIATION 45800 HANFORD ROAD CANTON, MICHIGAN SME Project Number: 074170.00 July 1, 2016 Pavement Surface
More informationMunicipality of Waterville Public Sidewalk Repair Policy
Municipality of Waterville Public Sidewalk Repair Policy Purpose - The purpose of this policy is to protect the public health, safety and welfare of the citizens and inhabitants of the Municipality by
More informationIt is the CONTRACTORS RESPONSIBILITY to use OSHA approved shoring
PERMIT# EXCAVATION/RIGHT OF WAY PERMIT ATE: NOTE: No permit shall be issued \vithout CURRENT Montana Contractors License, Insurance and Bonding on file with the Public Works epartment. It is the CONTRACTORS
More information2008 Street and Utility Improvement Project West Golden Lake Road. Public Informational Meeting January 3, 2008
2008 Street and Utility Improvement Project West Golden Lake Road C P Public Informational Meeting January 3, 2008 Presentation Summary Project Location Existing Conditions Proposed Improvements Project
More informationTRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM
VIRGINIA DEPARTMENT OF TRANSPORTATION TRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Americans with Disabilities Act Requirements of Maintenance and Operational
More informationPLANNED UNIT DEVELOPMENT & SUBDIVISION STAFF REPORT Date: July 11, 2013
PLANNED UNIT DEVELOPMENT & SUBDIVISION STAFF REPORT Date: July 11, 2013 SUBDIVISION NAME DEVELOPMENT NAME LOCATION Northside LTD/Joint Venture Subdivision, Resubdivision of and Addition to Lot 3A Northside
More information20 North Main Alpine, UT (Phone) (Fax) SITE PLAN
Site Plan Instructions New Home Form #1 20 North Main Alpine, UT 84004 801-756-6347 (Phone) 801-756-1189 (Fax) www.alpinecity.org SITE PLAN A detailed site plan, drawn to scale, 1 = 20 min., shall be filed
More informationSIDEWALK REPAIR GUIDE
SIDEWALK REPAIR GUIDE Below are examples of sidewalk deficiencies as defined by Chapter 136 of the Altoona Code of Ordinances. Included with each example is a repair suggestion. Some examples may have
More informationBUILDING & INSPECTIONS DIVISION 200 East Wood Street Palatine, IL Telephone (847)
2018 EXPRESS PERMIT CONCRETE PATIO/ SIDEWALK/STOOP PRINT CLEARLY. ILLEGIBLE AND/OR INCOMPLETE S WILL BE RETURNED (this is a two sided application) Property/Owner Information check if applicant Project
More informationDodge City s, General Information For Driveway/Sidewalk Permits, Utility Permits.
Dodge City s, General Information For Driveway/Sidewalk Permits, Utility Permits. All private construction and/or maintenance activities which take place within the City right-of-way are subject to oversight
More informationBUILDING & INSPECTIONS DIVISION 200 East Wood Street Palatine, IL Telephone (847)
2018 EXPRESS PERMIT PRINT CLEARLY. ILLEGIBLE AND/OR INCOMPLETE S WILL BE RETURNED (this is a two sided application) Property/Owner Information check if applicant Project Address: Owner Name: Day Phone:
More informationKINGS MILL Builder Guidelines
KINGS MILL Builder Guidelines 1. Proposed Square Footage Requirements: Section 1: 50 Lots: 1,500 square feet (minimum) 3,000 square feet (maximum) 60 Lots: 1,800 square feet (minimum) 3,500 square feet
More informationFENCES. This hand out is for REFERENCE ONLY. For more details see specific code sections.
Village of Vernon Hills Community Development Department 290 Evergreen Drive, Vernon Hills, IL 60061 Phone 847-367-3704 - Fax 847-367-2541 - http:// www.vernonhills.org FENCES This hand out is for REFERENCE
More informationLAGRANGE TOWNSHIP 353 South center street p.o. box 565 lagrange ohio 44050
LAGRANGE TOWNSHIP 353 South center street p.o. box 565 lagrange ohio 44050 Resolution 2004-5 Resolution of the Board of Trustees of LaGrange Township, Lorain County, Ohio, adopting general rules and regulations
More informationSTANDARD GRADING AND SOIL EROSION & SEDIMENT CONTROL PLAN FOR SINGLE LOT SINGLE FAMILY RESIDENTIAL CONSTRUCTION AND MINOR EARTH DISTURBANCES
DIVISION OF ENGINEERING & CONSTRUCTION MANAGEMENT PLAN REVIEW DEPARTMENT WASHINGTON COUNTY SOIL CONSERVATION DISTRICT 1260 Maryland Avenue, Suite 101 Hagerstown, MD 21740 Telephone: (301) 797-6821, Ext.
More informationCHANCEFORD TOWNSHIP, YORK COUNTY, PENNSYLVANIA ORDINANCE NO
CHANCEFORD TOWNSHIP, YORK COUNTY, PENNSYLVANIA ORDINANCE NO. 2005-2 AN ORDINANCE REGULATING THE CONSTRUCTION AND REPAIR OF ALL SIDEWALKS IN CHANCEFORD TOWNSHIP, YORK COUNTY, PENNSYLVANIA, BY PROVIDING
More informationPLANNED UNIT DEVELOPMENT, PLANNING APPROVAL & SUBDIVISION STAFF REPORT Date: June 4, 2015
PLANNED UNIT DEVELOPMENT, PLANNING APPROVAL & SUBDIVISION STAFF REPORT Date: June 4, 2015 NAME SUBDIVISION NAME CC Williams Plant Subdivision CC Williams Plant Subdivision LOCATION CITY COUNCIL DISTRICT
More informationDemolition Permit Application
Demolition Permit Application 2012 Michigan Building Code 2015 Michigan Residential Code City of Jackson 161 W. Michigan Avenue Jackson, MI 49201 (517) 788-4012 www.cityofjackson.org Project Information
More informationREQUIREMENTS FOR WIRELESS FACILITY PERMIT APPLICATIONS
REQUIREMENTS FOR WIRELESS FACILITY PERMIT APPLICATIONS (A copy of the full Wireless Telecommunication Facilities Ordinance is available upon request) TABLE OF CONTENTS Page I. GENERAL REQUIREMENTS...
More informationSECTION CURB RAMPS AND OTHER MINOR CONCRETE FACILITIES. Part 1 - General Work Included Related Requirements...
SECTION 02530 CURB RAMPS AND OTHER MINOR CONCRETE FACILITIES CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Inspection And Tests... 1 1.04 Quality Assurance...
More informationCITY OF SAFETY HARBOR 750 MAIN STREET, SAFETY HARBOR, FLORIDA PHONE: 727/ FAX: 727/
CITY OF SAFETY HARBOR 750 MAIN STREET, SAFETY HARBOR, FLORIDA 34695 PHONE: 727/724-1555 FAX: 727/724-1566 RIGHT-OF-WAY / EASEMENT USE PERMIT DATE SUBMITTED: EXPIRATION DATE: Submit the following to the
More informationPennDOT Pub. 170 Highway Occupancy Permit (HOP) Manual Page 56
PennDOT Pub. 170 Highway Occupancy Permit (HOP) Manual Page 56 Additional Fees Additional fees may be charged by PennDOT consistent with Sections 411 and 420 of the State Highway Law and Regulations 441.4(d)
More informationIndex. Composition and Order of Plan Set. Utility Plan... 5
City of Des Plaines Public Works and Engineering Department Revised-October 5, 2012 Index Composition and Order of Plan Set Title Page Number Cover Sheet... 1 Requirements for Site Development... 2 Grading
More informationCITY OF TACOMA RIGHT-OF-WAY RESTORATION POLICY. Guidance on restoration of City Rights-of-Way
CITY OF TACOMA RIGHT-OF-WAY RESTORATION POLICY Guidance on restoration of City Rights-of-Way Public Works Department Directors Office 747 Market Street Suite 408 Tacoma, WA 98402 253-591-5525 Right-of-Way
More informationJanuary 15, The meeting was called to order at 7:00 p.m. by Mayor Docimo. The meeting was advertised in the following manner:
The meeting was called to order at 7:00 p.m. by Mayor Docimo. The meeting was advertised in the following manner: A. Posting written notice on the Official Bulletin Board in the Township Municipal Building
More informationSPECIFICATIONS FOR STREET CONSTRUCTION WITHIN THE TOWN OF PLAINVILLE
SPECIFICATIONS FOR STREET CONSTRUCTION WITHIN THE TOWN OF PLAINVILLE BE IT ORDAINED by the Town Council of the Town of Plainville: SECTION 1. SUBDIVISIONS. All subdivisions hereinafter developed within
More informationDOWNTOWN OXNARD PARKLET PILOT PROGRAM PARKLET DESIGN GUIDELINES
Development Services Planning Division 214 South C Street Oxnard, California 93030 (805) 385-7858 Fax (805) 385-7417 DOWNTOWN OXNARD PARKLET PILOT PROGRAM PARKLET DESIGN GUIDELINES I. INTRODUCTION As part
More informationAPPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT
APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT Engineering Division 550 Landa Street New Braunfels, Texas 78130 (830) 221-4020 1. Subdivision Plat Name: Location Description/ Nearest Intersection: Acreage:
More informationCITY OF ANN ARBOR, MICHIGAN Public Services Area/Project Management Unit 301 E. Huron Street P.O. Box 8647, Ann Arbor, Michigan 48107
CITY OF ANN ARBOR, MICHIGAN Public Services Area/Project Management Unit 301 E. Huron Street P.O. Box 8647, Ann Arbor, Michigan 48107 Web: www.a2gov.org Printed on recycled paper May 17, 2016 Subject:
More informationPUBLIC WORKS DEPARTMENT GENERAL NOTES
PUBLIC WORKS DEPARTMENT GENERAL NOTES 1. All construction shall be in strict accordance with the standards of the City of Southlake and governed by the North Central Texas Council of Government's Standard
More informationSECTION 9000 MAINTENANCE SERVICES
SECTION 9000 MAINTENANCE SERVICES 9000 MAINTENANCE SERVICES... 1 9001 LEGISLATIVE AUTHORITY... 1 9002 GENERAL MAINTENANCE... 1 9003 PEDESTRIAN OVERPASSES... 1 9003.1 GENERAL MAINTENANCE... 1 9003.2 WINTER
More informationGrovewood Homeowners Association, Inc. Architectural Review Committee Guidelines Adopted September 18, 2018
Grovewood Homeowners Association, Inc. Architectural Review Committee Guidelines Adopted September 18, 2018 These Guidelines do not change or replace anything in the Grovewood Deed Restrictions or any
More informationTHE ANTICIPATED SEQUENCE OF EVENTS ARE AS FOLLOWS, BUT THE CONTRACTOR IS RESPONSIBLE FOR ALL MEANS AND METHODS
GENERAL PLAN NOTES PERMANENT SIGNS PROJECT SCOPE THIS PROJECT INCLUDES REMOVAL OF PORTIONS OF CONCRETE CURB & GUTTER AND HMA SURFACE; INSTALLATION OF SANITARY AND STORM SEWER AND UNDERDRAIN; EXCAVATION
More informationSECTION 12 STANDARDS FOR CONSTRUCTION PLANS AND SPECIFICATIONS
SECTION 12 STANDARDS FOR CONSTRUCTION PLANS AND SPECIFICATIONS 12.1 The subdivider shall construct and install the improvements in accordance with the County's Standards for Construction Plans and Specifications
More informationFences, Wall and Hedge Regulations City of St. Petersburg City Code Chapter 16, Land Development Regulations
Section 16.40.040 Fence, Wall and Hedge Regulations 16.40.040.1 All fences, walls and hedges shall comply with the following requirements which relate to height, location and design. 16.40.040.2 Definitions
More informationProject Title: Major Site Review (SR16-06) for Ripon Gardens II Commercial
Planning Commission Staff Report Planning Commission Hearing November 14, 2016 Project Title: Major Site Review (SR16-06) for Ripon Gardens II Commercial Request: A request to develop a 15,996 square foot
More informationOPERATING POLICY MANUAL
Page 1 of 7 Section 1. PURPOSE This policy is to explain the review process that the Bedford Regional Water Authority ( Authority ) utilizes for water and sewer developer projects planned within the service
More informationSTREET IMPROVEMENTS (Refer to Title 18, chapter entitled "STREETS" of the Layton Municipal Code.)
STREET IMPROVEMENTS (Refer to Title 18, chapter 18.24 entitled "STREETS" of the Layton Municipal Code.) I. Street widths STREET TYPE (ALL MEASUREMENTS IN FEET) ROW WIDTH LAYTON CITY STANDARD STREET SECTIONS
More information6 STORMWATER IMPROVEMENTS
6 STORMWATER IMPROVEMENTS 6.01 General Requirements a. In addition to the standards contained in this, the design of stormwater systems is also governed by several ordinances and regulations. (1) Projects
More informationHAROLD L. MOSELEY SUBDIVISION, RESUBDIVISION OF LOT 2
HAROLD L. MOSELEY SUBDIVISION, RESUBDIVISION OF LOT 2 Engineering Comments: Must comply with the Mobile County Flood Damage Prevention Ordinance. Development shall be designed to comply with the storm
More informationPLANNED UNIT DEVELOPMENT & PLANNING APPROVAL STAFF REPORT Date: February 7, 2013
PLANNED UNIT DEVELOPMENT & PLANNING APPROVAL STAFF REPORT Date: February 7, 2013 NAME LOCATION MAWSS Shelton Beach Road East side of Shelton Beach Road Extension, 2/10± mile North of Moffett Road CITY
More informationSECTION RIGHT-OF-WAY DAMAGE REPAIRS PART 1 - GENERAL PART 2 - MATERIALS AND METHODS
SECTION 01200 RIGHT-OF-WAY DAMAGE REPAIRS PART 1 - GENERAL 1.01 SCOPE This specification covers the work within the street right-of-way (property line) for the repair of that area which is disturbed during
More informationT a b l e o f C o n t e n t s
C i t y o f G l a d s t o n e P u b l i c W o r k s D e s i g n S t a n d a r d s T a b l e o f C o n t e n t s SECTION THREE SANITARY SEWER REQUIREMENTS... 1 3.0000 SANITARY SEWERS... 1 3.0010 General
More informationPLEASE READ AND SIGN RESIDENTIAL ENERGY CODE AND EROSION CONTROL!
CITY OF SOLON REQUIREMENTS FOR OBTAINING A SOLON BUILDING PERMIT City Office Telephone Number: 319/624-3755 Public Works Director 319/631-5071 Building Official Telephone Number 319/338-4939 office 319/321-6563
More informationCHAPTER 12 INSTALLATION OF UTILITIES AND OTHER SYSTEMS TABLE OF CONTENTS
CHAPTER 12 INSTALLATION OF UTILITIES AND OTHER SYSTEMS TABLE OF CONTENTS Section Title Page 12.1 General... 12-1 12.2 Design Standards... 12-1 12.2.1 General Requirements...12-1 12.2.2 Minimum Depth...12-1
More informationBeaumont Lot Grading Guidelines
Beaumont Lot Grading Guidelines Updated: 2019-01-14 CONTENTS LOT GRADING OVERVIEW... 3 INTRODUCTION... 3 PURPOSE... 3 DEFINITIONS... 3 LOT GRADING REQUIREMENTS... 3 DESIGN GRADES AND EXISTING GRADES...
More informationCHAPTER 7 - INFRASTRUCTURE INSPECTION AND ACCEPTANCE... 2
CHAPTER 7 - INFRASTRUCTURE INSPECTION AND ACCEPTANCE... 2 7.1. GENERAL.... 2 7.1.1. Inspection Restriction Dates.... 2 7.1.2. Complete Improvements.... 2 7.1.3. Public Improvements.... 2 7.1.4. Warranty
More informationRESOLUTION NO A RESOLUTION ESTABLISHING POLICY ON SUMP PUMP CONNECTIONS TO THE CITY STORM SEWER SYSTEM.
RESOLUTION NO. 3690 A RESOLUTION ESTABLISHING POLICY ON SUMP PUMP CONNECTIONS TO THE CITY STORM SEWER SYSTEM. WHEREAS, the City of Overland Park recognizes that there are locations within the City where
More information6 STORMWATER IMPROVEMENTS
6 STORMWATER IMPROVEMENTS 6.01 General Requirements a. In addition to the standards contained in this, the design of stormwater systems is also governed by several ordinances and regulations. (1) Projects
More informationAppendix 3. POLICY & PROCEDURE No
DEPARTMENT OF PUBLIC WORKS DIVISION: ENGINEERING SERVICES SECTION: ADMINISTRATIVE PAGE NO: 1 OF 10 REVISION NO: 3 DATE: 1995 05 01 ESTABLISHED: 1986 03 03 Appendix 3 POLICY & PROCEDURE No. 2.3.1-020 TITLE:
More informationProvidence Corner HOA Upper Providence Township, Pennsylvania
DEFICIENCY REPORT FOR THE Providence Corner HOA Upper Providence Township, Pennsylvania Project Number: 15-1064 Date: July 8, 2016 W:\2015\15-1064\CORR\Deficiency\Providence Corner Deficiency Report 07
More informationChapter 3: Permit Procedures and Requirements
Chapter 1: General Provisions 1 1 Short Title 1 2 Jurisdiction 1 3 Amendments and Revisions 1 4 Enforcement Responsibility 1 5 Review Process 1 6 Prior Approval 1 7 Relationship to Other Standards 1 8
More informationConstruction Application for Permit (CAP) Instructions
Construction Application for Permit (CAP) Instructions A CAP is required to be completed and submitted to the Wayne Soil & Water Conservation District (SWCD) office for non-farm, earth-disturbing activities
More informationFence and Wall Requirements
Fence and Wall Requirements Definitions Decorative wall - A wall constructed of stone or other material erected for the sole purpose of providing a decorative and/or landscaped feature, and not to include
More informationFranklin County Communique to the Planning Board
Franklin County Communique to the Planning Board PETITIONER(S): Name of Petitioner: Carolina Solar Energy II, LLC Address: 400 W. Main St. Suite 503 City/State/Zip: Durham, NC 27701 LOCATION: REQUEST FOR
More informationImprovement Plan Cost Estimate
Building and Engineering Division Development Services Department 214 S. C Street, Oxnard CA 93030 ph: 805.385.7925 fax 805.385.7854 Improvement Plan Cost Estimate Land Development Permit No. (Tract or
More informationSURFACE WATER UTILITY FEE
The Surface Water Utility Fee section of the FY2014 Budget Message provides background, impacts and actions associated with the County s prior and new surface water level of service in the unincorporated
More informationPLANNED UNIT DEVELOPMENT STAFF REPORT Date: September 7, 2017
PLANNED UNIT DEVELOPMENT STAFF REPORT Date: September 7, 2017 DEVELOPMENT NAME LOCATION Custom Boat Storage 3975 Demetropolis Road (East side of Demetropolis Road, 0.2± miles South of Halls Mill Road.)
More informationEXCAVATION PERMIT CHECKLIST
EXCAVATION PERMIT CHECKLIST Complete These Forms ST. LOUIS COUNTY/MUNICIPAL ZONING APPROVAL FOR PERMIT APPLICATION EXCAVATION PERMIT APPLICATION Present These Documents Drawing showing location of excavation
More informationCity of Norwalk. Residential Development Permit Process
City of Norwalk Residential Development Permit Process City of Norwalk Zoning Department 38 Whittlesey Avenue, PO Box 30 Norwalk, OH 44857 (419) 663-6736 www.norwalkoh.com 1 TABLE OF CONTENTS OVERVIEW...
More informationYork County Engineering Department Roadway Inspection Requirements
York County Engineering Department Roadway Inspection Requirements The following is a list, in order, of the roadway inspections that are required to be passed by York County before a subdivision can receive
More informationCITY OF THOUSAND OAKS APPROVAL CHECKLIST FOR REFUSE/RECYCLING ENCLOSURES
CITY OF THOUSAND OAKS APPROVAL CHECKLIST FOR REFUSE/RECYCLING ENCLOSURES ADMINISTRATIVE ITEMS: Waste Management (a.k.a.: G.I. Industries ) must approve plans for a new refuse/recycling enclosure (enclosure)
More informationCOMMERCIAL RE-ROOF BUILDING PERMIT GUIDE
Nampa Building Safety Department COMMERCIAL RE-ROOF BUILDING PERMIT GUIDE 411 3 rd Street S. Nampa, Idaho 83651 208-468-5435 Fax#: 208-468-5439 www.cityofnampa.us Patrick Sullivan C.B.O Building Safety
More informationJune 5, Prepared By: Thompson Engineering, Inc Cottage Hill Road Ste. 190 Mobile, Al Office (251) Fax: (251)
Addendum No. 3 to the Water Street Signal Planning And Striping Plan Concrete Sidewalk Phase Mobile, Alabama For the City of Mobile, Alabama Project No. 2017-2060-06 June 5, 2017 Prepared By: Thompson
More informationSIDEWALKS ASSESSMENT PROJECT TOWN OF MOUNTAIN VIEW, COLORADO
SIDEWALKS ASSESSMENT PROJECT TOWN OF MOUNTAIN VIEW, COLORADO FEBRUARY 2017 REVISED MAY 2017 PREPARED BY: RGA JOB NO.: 1104.0002 R:\1104 - Town of Mountain View\Report\Sidewalks-Assessment.doc 1 CAPITAL
More informationSection 7: Monitoring and Status Reporting
Section 7: Monitoring and Status Reporting Section 7.1: Introduction SacDOT currently is engaged in an on-going effort to construct curb ramps, sidewalks, and other pedestrian facilities at numerous locations
More informationYork County Engineering Department Roadway Inspection Requirements
York County Engineering Department Roadway Inspection Requirements The following is a list, in order, of the roadway inspections that are required to be passed by York County before a subdivision can receive
More informationRESIDENTIAL BUILDING PERMIT APPLICATION ( MINIMUM Building Requirements-Page 6)
www.shawneeok.org RESIDENTIAL BUILDING PERMIT APPLICATION ( MINIMUM Building Requirements-Page 6) Planning Office 405-878-1666 222 N Broadway Ave Shawnee OK 74801-6917 FAX: (405) 878-1587 cosinspections@shawneeok.org
More information2018 Utility & Street Reconstruction
2018 Utility & Street Reconstruction Public Hearing On Proposed Special Assessments/Hookup Fees for Installation and Construction of Public Improvements Introduction of the Village technical staff Laura
More informationMarbella Isles Homeowners Association, Inc.
REQUEST FOR ARCHITECTURAL REVIEW Please Note: There is a $25.00 non-refundable processing fee for all requests. The application will not be processed if it is not included with application. Make check
More informationENGINEERING DEPARTMENT. Provide engineering and public improvements in the most economical manner.
ENGINEERING DEPARTMENT MISSION STATEMENT: Provide engineering and public improvements in the most economical manner. The Engineering Department performs the following services to maintain and improve the
More informationBONDING REQUIREMENTS AND PROCEDURES
Town of Apex Development Services 73 Hunter Street, 3 rd Floor Apex, NC 27502 (919) 249-3394 BONDING REQUIREMENTS AND PROCEDURES ORDINANCE RATIFYING THE REQUIREMENT FOR BONDING: (From the Unified Development
More information