Module #4 Time Impact Analysis

Size: px
Start display at page:

Download "Module #4 Time Impact Analysis"

Transcription

1 Reviewing & Analyzing CPM Construction Schedules Module #4

2 Forward looking schedule analysis technique that adds a modeled delay to an accepted contract schedule to determine the possible impact of that delay to the project completion. (AACE)

3 References Association for the Advancement of Cost Engineers (AACE) International Recommended Practice No. 52R-06, Time Impact Analysis - as Applied in Construction Web site:

4 Goals Determine the impact of a delay to the project completion date Give time due to the contractor in the contract modification

5 Assumptions Acceptable baseline schedule exists Regular schedule updates Forward looking Keep it simple

6 Schedule Terminology Project Scheduler Schedule Reviewer

7 Schedule Terminology Critical and Non-Critical Delays: Critical delays impact the project completion date Non-critical delays don t

8 Example New Building Addition Approximately 200 CY of petroleum contaminated soil was discovered on October 27 while contractor was excavating the building foundation, and underground water and electrical lines. Excavation cannot continue until the soil is removed. Govt. issued NTP on October 29 to remove soil, haul it away, and backfill with clean fill. Total delay duration is 5 days (2-days stop work and 3-days for excavating and hauling soil to storage yard).

9 Step 1 Identify affected activity(s) Model delay impact

10

11 Step 1 Affected Activity: BA650 Excavation

12 Step 1 Determine delay impact 2 days stop work + 3 days removal/back fill = 5 Day Delay

13 Step 1 Model impact with a schedule fragnet

14 Step 1 Fragnet Opt. 1 Act. 1 Delay Act. 2 Opt. 2 Act. 1a Delay Act. 1b Act. 2 Opt. 3 Act. 1 Act. 2 Delay

15 Step 1 Un-Impacted Excavation 10-days Impacted Install Underground Water Install Underground Electrical Install Underground Water Excavation 7-days Mod. 1 Remove Contaminated Soil 5-days Finish Excavation 3-days Install Underground Electrical

16 Step 2 Select the appropriate schedule Use the last updated schedule prior to the delay start Progress schedule if time frame between previous schedule update and impact too great

17

18 Step 2 Note project completion date Completion Date August 4, 2000

19

20 Step 3 Insert fragnet into the updated schedule (don t forget calendar, logic, etc.) Set delay duration to zero

21 Install Underground Water Excavation 7-days Mod. 1 Remove Contaminated Soil 0-days Remaining Excavation 3-days Install Underground Electrical

22 Step 3 Re-compute CPM completion date should not change Original completion date August 4, 2000

23

24 Time Impact Schedule Step 4 Insert delay duration: 5 days Re-compute CPM

25

26 Step 5 Note new completion date If applicable, note completion date(s) for all other contractual milestones

27

28 Step 6 Determine the number of days owed to the contractor: Old completion date is August 4 New completion date is August 11 Total Float = -5 days 5 or 7 days?

29 Step 7 Determine actual dates for the critical delay Delay begins on first day of negative float; ends when the number of delay days are exhausted October 28 November 3

30

31 Step 8 Review Schedule for Concurrent Delays Contractor delay during same period, then Excusable and noncompensable No contractor delay, then Excusable and compensable

32 Step 9 Document TIA Price Negotiation Memorandum (Act ID, issue, affected trades, date changes, etc.) Contract Modification

33 Sample Problem

Managing Schedule Change

Managing Schedule Change Managing Schedule Change Ted Douglas, CCP, PSP, FAACE CPM Construction Conference Orlando, Florida January 11, 2017 Managing Schedule Change Outline Change Drivers Contract Changes Clause Schedule Change

More information

AACE Planning and Scheduling Professional (PSP) Certification Preparation Training Course Brochure and Competency Matrix

AACE Planning and Scheduling Professional (PSP) Certification Preparation Training Course Brochure and Competency Matrix AACE Planning and Scheduling Professional (PSP) Certification Preparation Training Course Brochure and Competency Matrix INDEX: 1. Course Description 2. Course Development 3. Certifications offered by

More information

Lessons Learned Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International

Lessons Learned Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International Charlie Jackson, PSP, Primavera Certified Trainer Hill International Construction CPM Conference

More information

LONG INTERNATIONAL. Richard J. Long, P.E., Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA

LONG INTERNATIONAL. Richard J. Long, P.E., Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA Richard J. Long, P.E., Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax:

More information

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL SECTION 01310 COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. COST LOADED CONSTRUCTION SCHEDULE (Construction Schedule): The WORK under this Contract shall be planned, scheduled, executed,

More information

THE CONTRACTS GROUP LTD. THE SOCIETY OF CONSTRUCTION LAW DELAY & DISRUPTION PROTOCOL 2 nd Edition

THE CONTRACTS GROUP LTD. THE SOCIETY OF CONSTRUCTION LAW DELAY & DISRUPTION PROTOCOL 2 nd Edition THE CONTRACTS GROUP LTD. THE SOCIETY OF CONSTRUCTION LAW DELAY & DISRUPTION PROTOCOL 2 nd Edition 18 January 2017 SCL Delay & Disruption Protocol 2 nd Edition INTRODUCTION TIME - Methods of Delay Analysis

More information

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by.

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones

More information

Principles of Schedule Contingency Management

Principles of Schedule Contingency Management Principles of Schedule Contingency Management Ted Douglas, CCC, PSP ACTPMA, LLC Consulting 2014 Construction CPM Conference Orlando, Florida Schedule Contingency Management Background Outline of Presentation

More information

Andrew Avalon, P.E., PSP

Andrew Avalon, P.E., PSP Andrew Avalon, P.E., PSP LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Andrew Avalon,

More information

Richard J. Long, P.E.

Richard J. Long, P.E. Richard J. Long, P.E. LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Construction Contract

More information

Planning & Scheduling CSTM 102

Planning & Scheduling CSTM 102 Planning & Scheduling CSTM 102 Items Big A Project on Website Thursday Discuss Big A Project next Tuesday April 18, 2011 CPM Scheduling You were the successful bidder! What s next? Procurement/Buy

More information

SCHEDULE DELAY IN CONSTRUCTION PROJECT USING TIME IMPACT ANALYSIS

SCHEDULE DELAY IN CONSTRUCTION PROJECT USING TIME IMPACT ANALYSIS International Journal of Civil, Structural, Environmental and Infrastructure Engineering Research and Development (IJCSEIERD) ISSN(P): 2249-6866; ISSN(E): 2249-7978 Vol. 3, Issue 5, Dec 2013, 53-64 TJPRC

More information

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...

More information

Jacksonville District Master

Jacksonville District Master USACE / NAVFAC / AFCEC / NASA UFGS-01 32 01 (August 2008) Change 1-08/13 --------------------------------- Preparing Activity: USACE Superseding UFGS-01 32 01.00 10 (July 2007) UNIFIED FACILITIES GUIDE

More information

Joint Seminar on Project Management Techniques

Joint Seminar on Project Management Techniques Joint Seminar on Project Management Techniques. Scheduling Testing, Balancing & Commissioning. Thomas Carcaterra, P.E., LLC 1375 Piccard Drive Suite 225 Rockville, MD 20850 Tel: 301.330.6044 Presented

More information

Project Management Concepts, Tools & Techniques

Project Management Concepts, Tools & Techniques Project Management Concepts, Tools & Techniques Course ISI-1438 5 Days Instructor-led, Hands on Introduction This highly interactive 5 day, instructor-led workshop is designed to give participants a solid

More information

Forensic Schedule Analysis and Discretionary Logic

Forensic Schedule Analysis and Discretionary Logic TECHNICAL ARTICLE Forensic Schedule Analysis and Discretionary Logic John C. Livengood Esq., CCP CFCC PSP FAACE Abstract: Forensic Schedule Analysis (FSA) and real time schedule reviews do not handle CPM

More information

Ronald J. Rider, MBA

Ronald J. Rider, MBA Ronald J. Rider, MBA LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Ronald J. Rider,

More information

Project Engineers and Supervisors Conference. CPM Scheduling

Project Engineers and Supervisors Conference. CPM Scheduling Project Engineers and Supervisors Conference March 15 th and 16 th 2010 CPM Scheduling Prepared and Presented By Project Engineers and Supervisors Conference Benefits of CPM Scheduling Lessons Learned

More information

by Ron Winter Consulting LLC January 6, 2015

by Ron Winter Consulting LLC January 6, 2015 Schedule Analyzer by Ron Winter Consulting LLC January 6, 2015 Schedule Analyzer P6 version released in 2003 Over 150 updates since then Over 1,000 licenses sold Works with Oracle/Primavera P6 & EPPM Looks

More information

Understanding Import & Export with NetPoint 4.2

Understanding Import & Export with NetPoint 4.2 Understanding Import & Export with NetPoint 4.2 Eric Lowther PMA Consultants 1 Primary Differences Regarding Import/ Export CPM Tools F9 and Early/Late Dates Float & Total Float Gantt Charts (Waterfall

More information

Views and Layouts for Program Management

Views and Layouts for Program Management MnDOT Project Management Office Presents: Views and Layouts for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted

More information

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Page 2 Copyright Eastwood Harris Pty Ltd IMPORTANT POINTS FOR

More information

Document No: SB002-P3 Revision No: Last Updated: April

Document No: SB002-P3 Revision No: Last Updated: April BRIEF People often are confused with the term - Out-of-Sequence, and use them in inappropriate ways. While we talk about Out-of-Sequence, we also need to discuss the difference between Retained Logic and

More information

Scott M. Francis, P.E., PSP

Scott M. Francis, P.E., PSP Scott M. Francis, P.E., PSP LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Scott M. Francis,

More information

Project Management. Kristian Sandahl

Project Management. Kristian Sandahl Project Management Kristian Sandahl 2 Maintenance Requirements Validate Requirements, Verify Specification Acceptance Test (Release testing) System Design (Architecture, High-level Design) Verify System

More information

Microsoft Office Project 2007, Managing Projects

Microsoft Office Project 2007, Managing Projects Microsoft Office Project 2007, Managing Projects Course 5927A: Three days; Instructor-Led Introduction Elements of this syllabus are subject to change. This three-day instructor-led course provides students

More information

Risk Evolution from Planning to Construction on the LA Metro Crenshaw/LAX Light Rail Transit Project

Risk Evolution from Planning to Construction on the LA Metro Crenshaw/LAX Light Rail Transit Project Risk Evolution from Planning to Construction on the LA Metro Crenshaw/LAX Light Rail Transit Project Kimberly Ong, P.E. LACMTA, Deputy Executive Officer Project Mgmt. Los Angeles, CA Matt Gallagher, P.E.

More information

Estimating Project Schedule-Time and Cost

Estimating Project Schedule-Time and Cost Estimating Project Schedule-Time and Cost Chapter 5 5 1 Where We Are Now 5 2 1 Overview Seminar Agenda What is involved in schedule and cost management? In-depth Determining the sequence of activities

More information

FORENSIC SCHEDULE ANALYSIS CHAPTER 2: DELAY ANALYSIS ON NON-CPM SCHEDULED PROJECTS 1

FORENSIC SCHEDULE ANALYSIS CHAPTER 2: DELAY ANALYSIS ON NON-CPM SCHEDULED PROJECTS 1 GLOBAL CONSTRUCTION FORENSIC SCHEDULE ANALYSIS CHAPTER 2: DELAY ANALYSIS ON NON-CPM SCHEDULED PROJECTS 1 By Steven A. Collins 2 and James G. Zack, Jr., CCM, CFCC, FAACE, FRICS, PMP 3 Association for the

More information

P6 Instructors Sample Presentation

P6 Instructors Sample Presentation Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 to 8.4 Professional and Optional Client 3 day training course PMI REP No 3001 Course Number PP6 Page 2 Page 4 Administration Evacuation

More information

Project Time Management

Project Time Management Project Time Management Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules. Describe how project managers use

More information

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course PMI REP No 3001 Course Number PP6 Administration Evacuation Timings and meals Facilities Mobile

More information

Consulting Newsletter

Consulting Newsletter Spring 2014 Newsletter In this, our 2014 Spring newsletter, are 2 articles. The first article is Programme Review and Acceptance. Our second article is titled, Acceleration Roger Gibson June 2014 PROGRAMME

More information

Downloaded from Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide

Downloaded from  Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide Version 0.9 October 21, 2005 TABLE OF CONTENTS SECTION PAGE List of Figures... ii 1. Introduction...1 1.1 Purpose of the

More information

PDM. Precedence Diagramming Method (PDM) Part 1. Finish to Start (FS) PDM. Finish to Start (FS) (cont.) Start to Start (SS) Con E 441 P05

PDM. Precedence Diagramming Method (PDM) Part 1. Finish to Start (FS) PDM. Finish to Start (FS) (cont.) Start to Start (SS) Con E 441 P05 PDM Precedence Diagramming Method (PDM) Part 1 Con E 441 P05 A. Four (4) possible relationships 1. Finish to Start (FS). Start to Start (SS) 3. 4. Start to Finish (SF) B. Plus combined relationships SS

More information

Foreword Acknowledgments Introduction to Second Edition

Foreword Acknowledgments Introduction to Second Edition Contents Foreword Acknowledgments Introduction to Second Edition xi xiii xv Chapter 1: Project Scheduling 1 The Project Schedule 1 The Purpose of a Project Schedule 2 Types of Project Schedules 3 What

More information

Artificial Intelligence

Artificial Intelligence Artificial Intelligence Combinatorial Optimization G. Guérard Department of Nouvelles Energies Ecole Supérieur d Ingénieurs Léonard de Vinci Lecture 4 Outline 1 2 Decisions about Resource Allocation Which

More information

Managing Projects (Course Code: 5927A) Course length: 3 days

Managing Projects (Course Code: 5927A) Course length: 3 days Managing Projects (Course Code: 5927A) Course length: 3 days Course Summary: This three-day instructor-led course provides students with the knowledge and skills to build, maintain, and control well-formed

More information

Planning & Scheduling

Planning & Scheduling Planning & Scheduling Dr. Nabil I. El Sawalhi Assistant Professor of Construction Management Chapter 3 1 Planning Successful Project Management depends on continues planning. The activities of Designers,

More information

The Differences Between CPM and Resource-Loaded Scheduling and How They Applied to The Martinez Tesoro Refinery Flare Header Replacement Project

The Differences Between CPM and Resource-Loaded Scheduling and How They Applied to The Martinez Tesoro Refinery Flare Header Replacement Project The Differences Between CPM and Resource-Loaded Scheduling and How They Applied to The Martinez Tesoro Refinery Flare Header Replacement Project Conor Carone California Polytechnic State University San

More information

PMI Scheduling Professional (PMI-SP)

PMI Scheduling Professional (PMI-SP) PMI Scheduling Professional (PMI-SP) E X A M I N AT I O N CO N T E N T O U T L I N E Project Management Institute PMI Scheduling Professional (PMI-SP) Exam Content Outline Published by: Project Management

More information

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com

More information

Govt. Contracting, Dynamics 365 Operations Implementing Dynamics 365 Operations for Govt. Contractors PVBS

Govt. Contracting, Dynamics 365 Operations Implementing Dynamics 365 Operations for Govt. Contractors PVBS Implementing Dynamics 365 Operations for Govt. Contractors PVBS Contents Background... 4 Setups... 4 Project Management and Accounting... 4 Ledger Posting Setup... 4 Category Groups... 4 Category Group

More information

Course Outline. TEC D 205 Engineering Tech Project Planning Olympic College Bremerton, WA. Week 1 Chapter 4: DEFINING THE PROJECT

Course Outline. TEC D 205 Engineering Tech Project Planning Olympic College Bremerton, WA. Week 1 Chapter 4: DEFINING THE PROJECT Course Outline TEC D 205 Engineering Tech Project Planning Week 1 Chapter 4: DEFINING THE PROJECT 1. Step one: Defining the Project Scope A. Employing a Project Scope Checklist 1. Project objective 2.

More information

Ir. Herwin Rubijono Hotel Ambhara 19 September Manajemen Proyek. Pengelolaan Waktu, Pengelolaan Biaya Pengelolaan Resiko, Pengelolaan Klaim

Ir. Herwin Rubijono Hotel Ambhara 19 September Manajemen Proyek. Pengelolaan Waktu, Pengelolaan Biaya Pengelolaan Resiko, Pengelolaan Klaim Ir. Herwin Rubijono Hotel Ambhara 19 September 2016 Manajemen Proyek Pengelolaan Waktu, Pengelolaan Biaya Pengelolaan Resiko, Pengelolaan Klaim Resume : M.A. Herwin Rubijono, Ir herwin.rub@gmail.com WA/SMS

More information

PS.08. Let s Scrap the Precedence Diagramming Method

PS.08. Let s Scrap the Precedence Diagramming Method 2004 AACE International Transactions PS.08 Let s Scrap the Precedence Diagramming Method Earl T. Glenwright Jr. THE STATE OF CONSTRUCTION SCHEDULING PRACTICES AND SCHEDULES WHY PRECEDENCE DIAGRAMMING WAS

More information

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 & 8.2 Professional and Optional Client 3 day training course SAMPLE SLIDE SHOW

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 & 8.2 Professional and Optional Client 3 day training course SAMPLE SLIDE SHOW Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 & 8.2 Professional and Optional Client 3 day training course SAMPLE SLIDE SHOW PMI REP No 3001 Course Number PP6 Page 2 Page 4 Administration

More information

48R06 SCHEDULECONSTRUCTABI

48R06 SCHEDULECONSTRUCTABI E 48R06 SA M PL SCHEDULECONSTRUCTABI LI TY REVI EW AACE International Recommended Practice No. 48R-06 SCHEDULE CONSTRUCTABILITY REVIEW TCM Framework: 7.2 Schedule Planning and Development 11.5 Value Management

More information

Presented by. H. Wynnlee Crisp

Presented by. H. Wynnlee Crisp Presented by H. Wynnlee Crisp Presented by H. Wynnlee Crisp 3213 W. Main Ste. 218 Rapid City, SD 57702-2314 hwcrisp@aol.com (425) 681-7887 CONTENTS Managing Project Schedules Part 1: Schedule Management

More information

Project Management Assignment Guidelines Tri 2. Andre Samuel

Project Management Assignment Guidelines Tri 2. Andre Samuel Project Management Assignment Guidelines 2015 16 Tri 2 Andre Samuel Part A General Overview This component requires the use both theoretical (journals, texts) as well as practitioner references in your

More information

STO Navigator Canada Best-Practices Manual

STO Navigator Canada Best-Practices Manual Page 1 / 5 24.1- SCHEDULING METHODOLOGY 24.1.1. PURPOSE The following best-practice guideline provides the STO Project Controls Team with a defined methodology for scheduling, to accurately identify the

More information

A Structured Approach to Minimum Cost Recovery Scheduling

A Structured Approach to Minimum Cost Recovery Scheduling A Structured Approach to Minimum Cost Recovery Scheduling Chris Carson, PSP Project Controls Manager Alpha Corporation Norfolk, Virginia Email: chris.carson@alphacorporation.com Background Project management

More information

PST Rulemaking: Draft Rule Changes

PST Rulemaking: Draft Rule Changes PST Rulemaking: Draft Rule Changes Lonnie Gilley Technical Specialist/Environmental Investigator TCEQ OCE, DFW Region Office 817-588-5841 lonnie.gilley@tceq.texas.gov 1 Texas UST Rulemaking Process Stakeholder

More information

Fairsail Collaboration Portal: Guide for Users

Fairsail Collaboration Portal: Guide for Users Fairsail Collaboration Portal: Guide for Users Version 11 FS-HCM-CP-UG-201504--R011.00 Fairsail 2015. All rights reserved. This document contains information proprietary to Fairsail and may not be reproduced,

More information

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155 GLOSSARY AND INDEX Glossary Index iv 1996 Project Management Institute, 130 South State Road, Upper Darby, PA 19082 USA 155 156 NOTES GLOSSARY 1. Inclusions and Exclusions This glossary includes terms

More information

P6 Schedule Maintenance Process

P6 Schedule Maintenance Process Minnesota Department of Transportation P6 Schedule Maintenance Process Prepared by: Project Management Unit, Office of Project Management Technical Support 12/10/2014 Minnesota Department of Transportation

More information

How to Cost Load a schedule. OR Understanding the SDEF

How to Cost Load a schedule. OR Understanding the SDEF How to Cost Load a schedule for USACE s QCS/RMS OR Understanding the SDEF (understanding the SDEF) Introduction David Long Sr. Project Controls Specialist With 20+ years of Scheduling and Cost Analysis

More information

PMP Sample Questions Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope?

PMP Sample Questions  Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope? PMP Sample Questions www.techfaq360.com Click here for 1600+ PMP Questions Question No : 1 Which of the following is an output of Define Scope? A. Accepted deliverables B. Change Requests C. Project document

More information

HCM Project Planning SUN October 1, 2017

HCM Project Planning SUN October 1, 2017 HCM Project Planning SUN 2727 October 1, 2017 Session Objective This session explores how to incorporate key lessons learned from actual implementations of Oracle HCM Cloud into up-front project planning

More information

P6 Version 8.2 to 8.4 EPPM Web Power Sample Point Slide Show

P6 Version 8.2 to 8.4 EPPM Web Power Sample Point Slide Show THIS SLIDE REQUIRES NEW PICTURE Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 8.4 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Page 2 Administration Evacuation

More information

Guten Tag. (good day)

Guten Tag. (good day) Guten Tag (good day) Project Management Process Groups Project 4. Integration Management Knowledge Areas 13. Stakeholder Initiating Planning Executing 5. Scope 6. Time 7. Cost 8. Quality 9. Human Resources

More information

What's New - Task Planning

What's New - Task Planning What's New - Task Planning by Dale Howard and Gary Chefetz With this chapter, teach yourself how to use Microsoft Project 2010 s new manual scheduling feature. This self-paced study guide includes hands-on

More information

Verizon Wireless Collocation Guidelines Washington/Baltimore/Virginia

Verizon Wireless Collocation Guidelines Washington/Baltimore/Virginia Verizon Wireless Washington/Baltimore/Virginia Network Engineering 1831 Rady Court Richmond, VA 23222 804-347-2572 Verizon Wireless Collocation Guidelines Washington/Baltimore/Virginia The Verizon Wireless

More information

Retained Logic and Progress Override in Primavera P6

Retained Logic and Progress Override in Primavera P6 By Pat Hendricks TEPCO, LLC www.tepco.us Retained Logic and Progress Override The retained logic and progress override setting can drastically affect a schedule depending on which is used, so understanding

More information

PROJECT MEASUREMENT CARBON CREDIT CALCULATIONS CITY OF RICHMOND ORGANIC WASTE DIVERSION (WASTE DROP-OFF SERVICE)

PROJECT MEASUREMENT CARBON CREDIT CALCULATIONS CITY OF RICHMOND ORGANIC WASTE DIVERSION (WASTE DROP-OFF SERVICE) PROJECT MEASUREMENT CARBON CREDIT CALCULATIONS CITY OF RICHMOND ORGANIC WASTE DIVERSION (WASTE DROP-OFF SERVICE) The carbon credit calculations completed for the 2007 2013 calendar years for the City of

More information

DELAY TO PROJECTS CAUSE, EFFECT AND MEASURES TO REDUCE / ELIMINATE DELAY BY MITIGATION / ACCELERATION

DELAY TO PROJECTS CAUSE, EFFECT AND MEASURES TO REDUCE / ELIMINATE DELAY BY MITIGATION / ACCELERATION DELAY TO PROJECTS CAUSE, EFFECT AND MEASURES TO REDUCE / ELIMINATE DELAY BY MITIGATION / ACCELERATION SHAIKH ASIF ABDUS SAEED PROJECT MANAGEMENT PROGRAMME INSTITUTION OF BUSINESS AUGUST 2009 DISSERTATION

More information

jmt.com PROJECT CONTROLS Part of a diversified family of solutions

jmt.com PROJECT CONTROLS Part of a diversified family of solutions jmt.com PROJECT CONTROLS Part of a diversified family of solutions Services Program Management/Project Control CPM Scheduling Training e-construction Cost Engineering Cost Estimating Claims/Change Order

More information

Construction Simulation An Introduction

Construction Simulation An Introduction Construction Simulation An Introduction Tim O Leary Construction Solutions Europe & Africa Solutions BRIDGES BUILDINGS CADASTRE AND LAND DEVELOPMENT CAMPUSES COMMUNICATION S ELECTRIC AND GAS UTILITIES

More information

Project Risk Analysis (with Pertmaster)

Project Risk Analysis (with Pertmaster) Project Risk Analysis (with Pertmaster) AACE Toronto Section October 2, 2008 Brought to you by: Presenter Ian Nicholson, P.Eng. VP Solutions, Emerald Associates Mechanical Engineer Primavera Systems Authorized

More information

GUIDE SPECIFICATION Los Angeles World Airports. xx xx xx CALM Review Procedures. CALM Element Background

GUIDE SPECIFICATION Los Angeles World Airports. xx xx xx CALM Review Procedures. CALM Element Background xx xx xx CALM Review Procedures CALM Element Background The CALM (Coordination and Logistics Management) Team s goal is to minimize construction-related impacts to passenger service and tenants while maintaining

More information

Microsoft Project study guide

Microsoft Project study guide Microsoft Project study guide Chap 1 An estimated duration appears with a(n) after the duration. a. pound sign c. question mark b. exclamation point d. red bullet Which of the following tasks in a LAN

More information

CITY OF ATLANTIC BEACH BID NUMBER PURCHASING DEPARTMENT 800 SEMINOLE ROAD ATLANTIC BEACH, FLORIDA (904)

CITY OF ATLANTIC BEACH BID NUMBER PURCHASING DEPARTMENT 800 SEMINOLE ROAD ATLANTIC BEACH, FLORIDA (904) CITY OF ATLANTIC BEACH BID NUMBER 1314-08 PURCHASING DEPARTMENT 800 SEMINOLE ROAD ATLANTIC BEACH, FLORIDA 32233 (904) 247-5880 REQUEST FOR BID CONTRACT - CONCRETE REPAIRS FOR THE PUBLIC WORKS/UTILITIES

More information

Proposal Pricing with Deltek MPM TM

Proposal Pricing with Deltek MPM TM technical brief Proposal Pricing with Deltek MPM TM A typical proposal pricing process and alternative ways to build a cost estimate in MPM Table of Contents Introduction 1 The Scenario 1 Scope of Work

More information

Quality Assurance Plan D9.1.1

Quality Assurance Plan D9.1.1 Quality Assurance Plan D9.1.1 Deliverable Number: D9.1.1 Contractual Date of Delivery: month 3 Actual Date of Delivery: 27/07/2001 Title of Deliverable: Quality Assurance Plan Work-Package contributing

More information

~ Guidance ~ Buy America. All Federally Funded Construction Projects

~ Guidance ~ Buy America. All Federally Funded Construction Projects Buy America All Federally Funded Construction Projects Reference: The FHWA Buy America statutory provisions are in 23U.S.C.313 and the regulatory provisions are in 23CFR635.410. Buy America Q&A s: http://www.fhwa.dot.gov/construction/contracts/buyam_qa.cfm

More information

Less than 8 feet finished water depth. 4-Foot Cap 3-Foot Cap Foot Cap. 4 Ft

Less than 8 feet finished water depth. 4-Foot Cap 3-Foot Cap Foot Cap. 4 Ft Herbivorous Animals Consuming Plants & Sediment Piscivorous Wildlife Consuming Fish Insectivorous Wildlife Consuming Emerging Aquatic Invertebrates Burrowing Organisms Contacting Contaminated Sediment

More information

Developing a Project Plan

Developing a Project Plan Chapter 6 Developing a Project Plan I had six honest serving men who taught men all I know : their names were what and how and why, and when and where and who. Rudyard Kipling Project Management 105 Figure

More information

Cambridge International AS & A Level Computer Science

Cambridge International AS & A Level Computer Science Topic Support Guide Cambridge International AS & A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains

More information

Q/P Management Group, Inc.

Q/P Management Group, Inc. Can SAP be Function Point Counted? Debra Maschino Q/P Management Group, Inc. 10 Bow Street Stoneham, MA 02180 Tel: (781) 438-2692 FAX: (781) 438-5549 http:/www.qpmg.com 1 Introduction Can you function

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report November 2013 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

Schedule Quality Delay Analysis Perspective

Schedule Quality Delay Analysis Perspective Schedule Quality Delay Analysis Perspective Research into defending the forensic schedule analysis to protect EPC contractor s true entitlement Varun Aasish Yerramreddy Schedule Quality Delay Analysis

More information

INTEGRATED MANAGEMENT OF THE CONSTRUCTION PROJECT DURING THE BUILDING PHASE

INTEGRATED MANAGEMENT OF THE CONSTRUCTION PROJECT DURING THE BUILDING PHASE INTEGRATED MANAGEMENT OF THE CONSTRUCTION PROJECT DURING THE BUILDING PHASE Yun Na WU, Na YAO School of Business & Management, North China Electric Power University, Beijing 102206, China Abstract: Traditional

More information

Project Green House. Green Team. Making the world greener one house at a time

Project Green House. Green Team. Making the world greener one house at a time Project Green House Making the world greener one house at a time UC Berkeley Extension, Business and Management UCB X470 Project Management February 2008 Green Team Lori Plein Anne Cairney Ferdinand Bueno

More information

Commercial Policy Group Guideline No 2 - Incentivisation Of Contractor Performance

Commercial Policy Group Guideline No 2 - Incentivisation Of Contractor Performance Commercial Policy Group Guideline No 2 - Incentivisation Of Contractor Performance SUMMARY The following broad principles are to be pursued, in the area of incentivisation in order to help to implement

More information

Line of balance programming

Line of balance programming Line of balance programming 1. INTRODUCTION Most contractors are familiar with programming a single project where a critical path analysis or, more likely, a bar chart is drawn up indicating what activities

More information

SYSCOM-SPECIFIC Award Structures and Requirements

SYSCOM-SPECIFIC Award Structures and Requirements SYSCOM-SPECIFIC Award Structures and Requirements NAVSEA Predecisional Working Papers 2 NAVSEA SBIR/STTR Phases & CRP Req ts Topic Generation & Approval Concept Development & Feasibility Technology Development

More information

ADDENDUM NO. 1 APRIL 24, 2017

ADDENDUM NO. 1 APRIL 24, 2017 DERBY DESTINATION DEVELOPMENT PUBLIC PROJECT NO. 1 EAST FREEDOM STREET PUBLIC PROJECT NO. 2 WEST FREEDOM STREET PUBLIC PROJECT NO. 3 WATERLINE IMPROVEMENTS PUBLIC PROJECT NO. 4 SANITARY SEWER IMPROVEMENTS

More information

Integral Risk Management for DBFM Tenders and Contracts in the Netherlands

Integral Risk Management for DBFM Tenders and Contracts in the Netherlands 770 Geotechnical Safety and Risk V T. Schweckendiek et al. (Eds.) 2015 The authors and IOS Press. This article is published online with Open Access by IOS Press and distributed under the terms of the Creative

More information

MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM)

MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM) MODULE 15 OPERATIONAL PLANNING TECHNIQUES (USE OF PLANNING TOOLS LIKE GANTT CHART, PERT/CPM) Content Writer/Author: Email id: Mrs. RENU ARORA renu214@gmail.com Structure of Module/Syllabus of module(define

More information

WEST VIRGINIA DEPARTMENT OF TRANSPORTATION DIVISION OF HIGHWAYS

WEST VIRGINIA DEPARTMENT OF TRANSPORTATION DIVISION OF HIGHWAYS WEST VIRGINIA DEPARTMENT OF TRANSPORTATION DIVISION OF HIGHWAYS ALL ITEMS MUST BE COMPLETED BY CONTRACTOR CALL NUMBER CONTRACTOR S NAME CONTRACTOR S FEIN BID AMOUNT DBE GOAL (%) WV LICENSE NUMBER CONTRACTOR

More information

AUTHORIZE THE CHIEF EXECUTIVE OFFICER (CEO) TO EXECUTE CONTRACT MODIFICATIONS

AUTHORIZE THE CHIEF EXECUTIVE OFFICER (CEO) TO EXECUTE CONTRACT MODIFICATIONS One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro. net CONSTRUCTION COMMITTEE APRIL 16, 2015 SUBJECT: ACTION: TUNNEL ADVISORY PANEL AUTHORIZE THE CHIEF EXECUTIVE OFFICER (CEO) TO EXECUTE

More information

Delays in Construction Projects: Causes and Mitigation

Delays in Construction Projects: Causes and Mitigation Delays in Construction Projects: Causes and Mitigation Aleksander Srdić, Ph.D. University of Ljubljana, Faculty of Civil and Geodetic Engineering, Slovenia aleksander.srdic@fgg.uni-lj.si Assoc. Prof. Jana

More information

Sitemanager Policy Manual

Sitemanager Policy Manual OKLAHOMA DEPARTMENT OF TRANSPORTATION CONSTRUCTION DIVISION / TRNS*PORT BRANCH Sitemanager Policy Manual CONTAINS : 501.0 - Daily Work Reports 502.0 - Diary 503.0 - History 504.0 - Diary Adjustments 505.0

More information

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4.

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4. Exam Code:74-343 Number: 74-343 Passing Score: 800 Time Limit: 120 min File Version: 35.4 http://www.gratisexam.com/ Exam Code:74-343 Exam Name:Managing Projects with Microsoft Project 2013 Examsoon QUESTION

More information

Deltek Acumen 7/15/16. Learning Objectives. Introduction to Project Risk Analysis. Planning, Risk, Acceleration. The 5 steps. Worked examples Q&A

Deltek Acumen 7/15/16. Learning Objectives. Introduction to Project Risk Analysis. Planning, Risk, Acceleration. The 5 steps. Worked examples Q&A Deltek Acumen Planning, Risk, Acceleration Tom Polen Director, Solution Architecture Learning Objectives The 5 steps 1. Capturing uncertainty: calibrating the schedule 2. Identifying risk events: accounting

More information

WAIKOLOA RESERVOIR NO. 1 EARTHQUAKE REPAIR PROJECT Information Sheet

WAIKOLOA RESERVOIR NO. 1 EARTHQUAKE REPAIR PROJECT Information Sheet March 5, 2015 WAIKOLOA RESERVOIR NO. 1 EARTHQUAKE REPAIR PROJECT Information Sheet Overview The purpose of this Project is to repair damages to the Waikoloa Reservoir No. 1 which were sustained during

More information

Index. Page locators in italics and bold respectively refer to figures and tables separate from the corresponding text.

Index. Page locators in italics and bold respectively refer to figures and tables separate from the corresponding text. Construction Planning ISBN 978-0-7277-6057-9 ICE Publishing: All rights reserved http://dx.doi.org/10.1680/cp2e.60579.191 Index Page locators in italics and bold respectively refer to figures and tables

More information

ICES Core Cost Engineering Competencies

ICES Core Cost Engineering Competencies CM CORE 1 Cost Engineering Commercial Management Core Competency Cost Engineering Specialism COMPETENCIES AND ASSESSMENT Financial and commercial processes in civil engineering January 2015 Technical Member

More information

PMI-001 Questions & Answers

PMI-001 Questions & Answers PMI-001 Questions & Answers Number: PMI-001 Passing Score: 700 Time Limit: 137 min File Version: 21.2 http://www.gratisexam.com/ PMI-001 Questions & Answers Exam Name: Project Management Professional v5

More information