2014 WORKSHOP Field Trip 3

Size: px
Start display at page:

Download "2014 WORKSHOP Field Trip 3"

Transcription

1 2014 WORKSHOP Field Trip 3 This trip visits a RoaDrain geosynthetic drainage material demo, GRS-IBS bridge project, and a completed project from Site 1 - Laurel Run Road: Recently completed project that used RoaDrain geosynthetic drainage material. Site 2 - Potter Run Road: An in-progress Geosynthetically Reinforced Soil-Integrated Bridge System (GRS-IBS) project. Site 3 - Sharer Road: A Program project completed in 2011 employing a cooperative effort with multiple entities. We will discuss project details and maintenance. The Ramada 3 2 1

2 Site 1: Laurel Run Road (RoaDrain Demo) Field Trip 3 As part of the Center s Bureau of Forestry (BOF) Demonstration project budget, BOF was interested in utilizing the TENSAR RoaDrain RD-5 roadway drainage system. This product consists of a synthetic sub-surface drainage layer sandwiched in nonwoven geotextile, which TENSAR states, will provide flow rates up to 5X greater than the typical open-graded base layer. Since the product is only 0.5 inches thick, it could greatly reduce the over-excavation depth needed to install a conventional French mattress. This section of Laurel Run Road is plagued with hillside seeps that have historically saturated the road base. Also, shelf rock is evident in the road base, which makes excavation problematic for a conventional French mattress. TENSAR s TX160 Triaxial Geogrid was utilized on top of the RD-5 to provide additional structural support. A new crosspipe was installed above a site to separate the ditch flow from the seep flow drainage. The RD-5 was installed in three steps, as indicated in the design drawing below, to account for the excessive road grade. Each step was sloped from the ditch line side to the out slope side at approximately 5% in an effort to drain the seep flow under the road profile. The lower crosspipe was also replaced as part of normal road maintenance operations. 1 2 Dra Design Drawing 3 This drawing depicts the effort to use the RD-5 to its maximum extent. The steps allow for even distribution of the seep flow away from the road. The four labeled sites correspond to the before and during/after pictures on the following page. Note that all before pictures show road impacted by bank seepage and limited drainage outlets, which combined together, increase flow volumes in the drainage structure. DISCLAIMER: The purpose of this project is to demonstrate a poten al new technology. This project or document is for educa on only and does not cons tute an "endorsement" of TENSAR or RoaDrain by the Center or Program. 4 Site Location: South off of US Route 322 just east of Boalsburg in Rothrock State Forest. A 7% sloped road that faces heavy vehicle traffic because of its direct access from Tussey Mountain to Route 26 at Whipple s Dam. What was done: Installed one new crosspipe and replaced one existing crosspipe. Provided outlet stabilization for the crosspipes. Excavated and constructed three steps that utilized the RD-5 roadway drainage system. TX160 Triaxial Geogrid overlaid on RD-5 to provide additional structural support Reinforced the ditch structure with R-3 riprap to protect the inlet side of the RD-5. All affected areas were seeded and mulched.

3 Site 1: Laurel Run Road (RoaDrain Demo) Field Trip 3 During 1 During Photo: In-progress replacement of existing crosspipe. During 2 During Photo: Installation of RD-5 roadway drainage system and TX160 geotextile. A er 3 After Photo: R-3 riprap lined ditch and bank stabilization through seeding and mulch. A er 4 After Photo: New crosspipe installation with outlet stabilization.

4 Site 1: Laurel Run Road (RoaDrain Demo) Field Trip 3 h p:// content/uploads/2013/08/roaddrain Brochure.pdf

5 Site 2: Potter Run Road (GRS-IBS Bridge) Field Trip 3 This Geosynthetically Reinforced Soil-Integrated Bridge System (GRSIBS) bridge pilot project is part of the Bureau of Forestry s (BOF) ongoing effort to utilize cost-effective methodology for vehicle roadways over waterway crossings. This structure was designed by the BOF s Facility Design and Construction department. The before pictures demonstrate the need to replace a deteriorating bridge structure on the low-volume Potter Run road. A temporary bridge was utilized to enable vehicle traffic access prior to the GRS-IBS bridge installation. Site Location: Located just west of Penn Nursery off of US 322 on Potter Run Road. This site is adjacent to Rothrock State Forest and Bald Eagle State Forest. During During During: The upper photo shows the abutment construction on top of foundation and the lower photo shows the compaction of AASHTO #57 stone.

6 Site 2: Potter Run Road (GRS-IBS Bridge) Field Trip 3 Geosynthetic Reinforced Soil (GRS) Integrated Bridge System (IBS) FHWA GRS-IBS Implementation Guide. GRS-IBS Quick Facts : Bridges constructed with the Geosynthetic Reinforced Soil (GRS) Integrated Bridge System (IBS) cost 25 to 60 percent less than bridges built with traditional methods, depending on the standard of construction and the method of contracting (local forces versus a private contractor). Compared with a DOT standard bridge, a GRS-IBS can potentially save up to 60 percent in cost. GRS IBS uses common, readily available materials and equipment. The use of GRS makes bridge abutments that are easier and faster to build. GRS IBS construction is much faster than traditional construction methods (weeks, not months). GRS IBS eliminates the "bump at the end of the bridge" problem caused by differential settlement between the bridge abutment and the approaching roadway. Construction is simpler with GRS IBS since it has fewer parts, involves basic methods and practice. IBS does not require a deep foundation. GRS IBS is environmentally sensitive and results in minimal environmental impacts. GRS technology is durable if built with quality materials. A GRS bridge performs well in earthquakes if constructed properly with closely spaced reinforcement. GRS IBS can be built in variable weather conditions and can be adapted very easily in the case of unforeseen site conditions. GRS structures are generally more ductile and flexible. Since GRS IBS bridges have fewer parts, they are easier to maintain. Approximately 44 bridges have been built on GRS abutments in the US; 27 of those using GRS IBS FHWA 8/2012 (

7 Site 2: Potter Run Road (GRS-IBS Bridge) Field Trip 3

8 Site 2: Potter Run Road (GRS-IBS Bridge) Field Trip 3

9 Site 3: Sharer Road (Completed in 2011) Field Trip 3 Off-right-of-way flow from a mountain tributary and a new residential development previously drained to the east ditch of Sharer Road at the top of the site. The ditch picked up additional flow from road drainage and was discharged directly to the creek. The stream pipe lacked the capacity to move flood flows through the road, which was washed out on a consistent basis. The installation of a wing plug on the US 322 headwall divides the sources of the run-on flow and notably reduces flow volume handled in the Sharer Road drainage system. Replacement of the stream culvert, installation of overflow pipes and a constructed wetland depression are the primary ESM practices incorporated to reduce the volume of road material and sediment entering Spring Creek during wet weather events. Sta on Map 2 1 Site Location: North off of US Route 322 just east of Boalsburg in Harris Township, PA. Headwaters of Spring Creek, a World-Renowned trout fishery. A moderately sloped road bordered by agricultural lands. 3 4 This station map depicts the work completed in The four labeled sites correspond to the before and after pictures on the following page. Note that all before pictures show road impacted by stream flooding, mountain drainage, and run-on flows from paved roads and developed areas. There were no existing ditch outlets in project area. What was done: Installed a headwall wing/ditch plug at the inlet of the US 322 ditch culvert to reduce run-on flow. Installed ditch protection in eroded ditch section. Diverted ditch flow away from road and stream with a new turn-out that drains to a constructed wetland in the former corn field. Installed four new crosspipes and replaced three existing crosspipes. Constructed a 50 long High Water By-pass. Placed and compacted one lift of 2A base material to gain road elevation. Installed riprap stream bank protection.

10 Site 3: Sharer Road (Completed in 2011) Field Trip After Photo: In-progress installation of high-water bypass After Photo: Relief pipes functioning well during high-water event Stream Crossing Stream Crossing 3 After Photo: Installed turn-out to wetland filter area After Photo: Functioning headwall wing/ditch plug. Reduces flow volume to Sharer Road.

Day 2 field sites 2012 WORKSHOP

Day 2 field sites 2012 WORKSHOP Jefferson Elk 2012 WORKSHOP Day 2 field sites SITE KEY: 1: GRS-IBS: the only Geosynthetically Reinforced Soil Bridge in PA. 2: Elk Center: Elk Country Visitor Center (lunch stop). Includes option for Conservation

More information

Training on Roads for Water and Resilience

Training on Roads for Water and Resilience Training on Roads for Water and Resilience 1 DRAINAGE FROM UNPAVED ROADS Outline 3 1. 2. 3. 4. 5. 6. 7. Introduction Important considerations Drainage management Surface drainage features Subsurface drainage

More information

PART 1 GENERAL REQUIREMENTS

PART 1 GENERAL REQUIREMENTS PART 1 GENERAL REQUIREMENTS Contract Closeout Plan 110 Arrow diagram for project close-out...3 Erosion Control 121 Straw bale barrier... 5 122 Silt fence... 7 123 Diversion dike... 9 124 Inlet protection...

More information

PART 3 - STANDARDS FOR SEWERAGE FACILITIES DESIGN OF STORM SEWERS

PART 3 - STANDARDS FOR SEWERAGE FACILITIES DESIGN OF STORM SEWERS PART 3 - STANDARDS FOR SEWERAGE FACILITIES 3.3 - DESIGN OF STORM SEWERS 3.301 Design of Storm Sewers A. General Information B. Investigations and Surveys C. Special Projects 3.302 Design Criteria for Storm

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

Temporary Watercourse Crossing: Culverts

Temporary Watercourse Crossing: Culverts Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol

More information

BMP 6.4.4: Infiltration Trench

BMP 6.4.4: Infiltration Trench BMP 6.4.4: Infiltration Trench An Infiltration Trench is a leaky pipe in a stone filled trench with a level bottom. An Infiltration Trench may be used as part of a larger storm sewer system, such as a

More information

SECTION TRENCHING & BACKFILLING

SECTION TRENCHING & BACKFILLING SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications

More information

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN

More information

MECHANICALLY STABILIZED EARTH (MSE) WALL SYSTEMS

MECHANICALLY STABILIZED EARTH (MSE) WALL SYSTEMS DRAINAGE SOLUTIONS SINCE 1908 MECHANICALLY STABILIZED EARTH (MSE) WALL SYSTEMS PERMANENT AND TEMPORARY ENGINEERED WALL SOLUTIONS ECONOMICAL DURABLE VERSATILE ARMTEC.COM MSE RETAINING WALLS Armtec Mechanically

More information

Geosynthetic Solutions

Geosynthetic Solutions Geosynthetic Solutions For Paved and Unpaved Applications Dave Lipomi Tensar Products and Applications Geogrids Uniaxial-Walls and Reinforced Slopes Biaxial-Reinforced Slopes, Roads, Foundations, Crane

More information

Best Practices for Building High-Performance Resource Roads. Road Drainage. Developed by: The Roads and Infrastructure Group

Best Practices for Building High-Performance Resource Roads. Road Drainage. Developed by: The Roads and Infrastructure Group Best Practices for Building High-Performance Resource Roads Road Drainage Developed by: The Roads and Infrastructure Group THIS GUIDE IS INTENDED FOR EQUIPMENT OPERATORS CONSTRUCTION CONTRACTORS FIELD

More information

Forks Hill Rd SUSQUEHANNA LACKAWANNA. Woodlands

Forks Hill Rd SUSQUEHANNA LACKAWANNA. Woodlands 2011 WORKSHOP Day 2 field sites BRADFORD Carizo Tour Salt Spring SP Forks Hill Rd SUSQUEHANNA Marcellus Trip It is difficult to create an effective field trip for both gas patch and non-gas patch attendees.

More information

CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS

CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS 8.1 INTRODUCTION To minimize the detrimental effects of erosion and sedimentation, Henrico County requires that those individuals responsible for

More information

SITE DESIGN ENGINEER'S STATEMENT:

SITE DESIGN ENGINEER'S STATEMENT: SITE DESIGN ENGINEER'S STATEMENT: THESE DETAILED PLANS AND SPECIFICATIONS WERE PREPARED UNDER MY DIRECTION AND SUPERVISION. SAID PLANS AND SPECIFICATIONS HAVE BEEN PREPARED ACCORDING TO THE CRITERIA ESTABLISHED

More information

E. STORMWATER MANAGEMENT

E. STORMWATER MANAGEMENT E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson

More information

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL Section 300 General Summary All projects constructed within the Town of Essex shall be constructed in strict accordance with

More information

Unit E: Basic Principles of Soil Science. Lesson 7: Understanding Soil Erosion and Management Practices

Unit E: Basic Principles of Soil Science. Lesson 7: Understanding Soil Erosion and Management Practices Unit E: Basic Principles of Soil Science Lesson 7: Understanding Soil Erosion and Management Practices 1 Important Terms Accelerated erosion Conservation tillage Cover crops Diversion ditches Geologic

More information

ARTICLE V: STORMWATER MANAGEMENT AND DRAINAGE SYSTEMS

ARTICLE V: STORMWATER MANAGEMENT AND DRAINAGE SYSTEMS ARTICLE V: STORMWATER MANAGEMENT AND DRAINAGE SYSTEMS Section 501: Purpose An adequate drainage system including necessary ditches, pipes, culverts, drains, inlets, bridges, detention ponds, etc. shall

More information

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination Highway Drainage Proper drainage is a very important consideration in design of a highway. Inadequate drainage facilities can lead to premature deterioration of the highway and the development of adverse

More information

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular

More information

TEMPORARY SEDIMENT TRAP CODE

TEMPORARY SEDIMENT TRAP CODE ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY SEDIMENT TRAP CODE 960 Source: DEFINITION A small temporary stormwater storage structure designed to trap sediment. PURPOSE The purpose of this practice

More information

4.8. Subsurface Infiltration

4.8. Subsurface Infiltration 4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of stormwater as it infiltrates into the ground. Dry wells, infiltration

More information

MOA Project # Golden View Drive Intersection & Safety Upgrades

MOA Project # Golden View Drive Intersection & Safety Upgrades Appropriate transitions can include extending the insulation beyond the roadway improvements, reducing the insulation thickness, or angling the insulation downward. Use of a frost tolerant section, an

More information

Municipal Stormwater Ordinances Summary Table

Municipal Stormwater Ordinances Summary Table APPENDIX F Municipal Ordinances Summary Table Municipality Abington Bryn Athyn Borough Hatboro Borough Ordinance, SALDO Runoff equals pre post Erosion Sediment Control Water Quality Requirements Any which

More information

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields 4.1-d SUBSURFACE INFILTRATION SYSTEM Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields BMP DESIGN APPROACH Pollutant Source Control Hydrologic Source Control Stormwater

More information

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Definitions SWPPP: Storm Water Pollution Prevention Plan BMP: Best Management Practice(s) to control pollution IDNR: Iowa Department

More information

Recommended Resources: The following resources may be useful in teaching this lesson:

Recommended Resources: The following resources may be useful in teaching this lesson: Unit E: Basic Principles of Soil Science Lesson 7: Understanding Soil Erosion and Management Practices Student Learning Objectives: Instruction in this lesson should result in students achieving the following

More information

U.S. ARMY CORPS OF ENGINEERS. Little Rock District

U.S. ARMY CORPS OF ENGINEERS. Little Rock District U.S. ARMY CORPS OF ENGINEERS Little Rock District SEDIMENT AND EROSION CONTROL GUIDELINES FOR PIPELINE PROJECTS Table of Contents 1.0 INTRODUCTION... - 1-2.0 PROJECTS IN WATERS OF THE UNITED STATES...

More information

REROUTING DRAINAGE SYSTEMS

REROUTING DRAINAGE SYSTEMS MINNESOTA WETLAND RESTORATION GUIDE REROUTING DRAINAGE SYSTEMS TECHNICAL GUIDANCE DOCUMENT Document No.: WRG 4A-4 Publication Date: 10/14/2015 Table of Contents Introduction Application Design Considerations

More information

4.8. Subsurface Infiltration

4.8. Subsurface Infiltration 4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of storm water as it infiltrates into the ground. Dry wells, infiltration

More information

PERMEABLE INTERLOCKING PAVERS

PERMEABLE INTERLOCKING PAVERS PERMEABLE INTERLOCKING PAVERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subgrade Preparation B. Placement of Storage Aggregate C. Placement of Filter Aggregate D. Placement of Bedding Course E. Placement

More information

At least 2 feet above the seasonal high water table Overflow path or structure provided

At least 2 feet above the seasonal high water table Overflow path or structure provided General Conditions Map of proposed subwatershed to each subbasin, including total area and CN Design Flow or Design Volume to each STF, as appropriate Operation and Maintenance instructions for each STF

More information

FIRM NAME DESIGNER: CHECKER: DATE: FPID #: DESCRIPTION: COUNTY: DRAINAGE DESIGN CHECKLIST. Designers Initials. Checkers Initials.

FIRM NAME DESIGNER: CHECKER: DATE: FPID #: DESCRIPTION: COUNTY: DRAINAGE DESIGN CHECKLIST. Designers Initials. Checkers Initials. I. Drainage Report A. Executive Summary - Brief Overview of Project Drainage Design B. Project Description 1. Existing Conditions 2. Proposed Project Conditions 3. Project Justification Narrative - Basin

More information

Chapter 11 Culverts and Bridges

Chapter 11 Culverts and Bridges Chapter 11 Culverts and Bridges Contents 1.0 Introduction... 1 2.0 General Design... 1 2.1 Design Criteria... 1 2.2 Design Flows... 1 2.3 Permitting and Regulations... 1 2.4 Aesthetics and Safety... 2

More information

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by

More information

W. Goodrich Jones State Forest. Best Management Practices Virtual Demonstration Tour

W. Goodrich Jones State Forest. Best Management Practices Virtual Demonstration Tour W. Goodrich Jones State Forest Best Management Practices Demonstrations of commonly implemented Texas Forestry BMPs for Water Quality Protection Texas Forest Service Water Resources P.O. Box 310 Lufkin,

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432 PAN 16-112, Westwood Middle School, Page 1 of 6 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: August 22, 2016 AGENDA NUMBER: 10 FILE NUMBER: 16-112 ITEM: Westwood Middle School RECOMMENDATION:

More information

Information for File # PRH

Information for File # PRH Information for File # 2016-02602-PRH Applicant Corps Contact Tom Morley Paul Hauser Address 152 Baker Drive, Redwood Falls, MN 56283 E-Mail Paul.R.Hauser@usace.army.mil Phone 651-290-5357 Primary County

More information

Stormwater Local Design Manual For Houston County, Georgia

Stormwater Local Design Manual For Houston County, Georgia Stormwater Local Design Manual For Houston County, Georgia Adopted November 15, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 2 2.1. DETENTION REQUIREMENTS... 2 2.1.1.

More information

Storm Drain Inlet Protection for Construction Sites (1060)

Storm Drain Inlet Protection for Construction Sites (1060) Storm Drain Inlet Protection for Construction Sites (1060) Wisconsin Department of Natural Resources Conservation Practice Standard I. Definition A temporary device installed in or around a storm drain

More information

MODEL Stormwater Local Design Manual. City of Centerville

MODEL Stormwater Local Design Manual. City of Centerville MODEL Stormwater Local Design Manual City of Centerville Adopted December 6, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 1 2.1. DETENTION REQUIREMENTS... 1 2.1.1. Discharge

More information

North Umpqua Hydroelectric Project (FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form

North Umpqua Hydroelectric Project (FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form (FERC 1927) Erosion Control Plan Site Remediation/ Assessment Form Site # CW2-3 Priority Ranking Med Locator Information/GPS Lat: Long: Impact Rating 3 Start Project Development: Clearwater 2 Risk Rating

More information

10.1 INTRODUCTION 10.1 DRAINAGE

10.1 INTRODUCTION 10.1 DRAINAGE CHAPTER 10 DRAINAGE 10.1 INTRODUCTION The drainage system manages both surface and subsurface water coming off the road surface and from the surrounding countryside. The purpose of the system is to ensure

More information

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements SECTION 3 DRAINAGE 3-1 General All Drainage plans for proposed development shall be prepared by a Professional Engineer registered in Virginia, except as noted below. Further, their seal and signature

More information

Section 3 Guidelines for Forest Roads

Section 3 Guidelines for Forest Roads Section 3 Guidelines for PART 1. OVERVIEW... 2 PART 2. ROAD MAINTENANCE AND ABANDONMENT PLANNING... 2 2.1 Road Maintenance and Abandonment Plans... 2 2.2 Changes in Ownership... 3 2.3 Family Forest Fish

More information

DRAINAGE & DESIGN OF DRAINAGE SYSTEM

DRAINAGE & DESIGN OF DRAINAGE SYSTEM Drainage on Highways DRAINAGE & DESIGN OF DRAINAGE SYSTEM P. R.D. Fernando Chartered Engineer B.Sc.(Hons), M.Eng. C.Eng., MIE(SL) Drainage Requirement of Highway Drainage System Introduction Drainage means

More information

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment. POND SITE SELECTION AND CONSTRUCTION Uses, Planning, & Design David Krietemeyer Area Engineer USDA-NRCS June 20, 2008 Uses Considerations for Location of Commonly Used Terms Pond A water impoundment made

More information

PERVIOUS PAVEMENT. Alternative Names: Permeable Pavement, Porous Concrete, Porous Pavers

PERVIOUS PAVEMENT. Alternative Names: Permeable Pavement, Porous Concrete, Porous Pavers 4.1-a PERVIOUS PAVEMENT Alternative Names: Permeable Pavement, Porous Concrete, Porous Pavers DESCRIPTION Pervious pavement is any system comprised of a load bearing surface that allows for movement of

More information

SECTION IV. PIPELINE EXCAVATION AND BACKFILL

SECTION IV. PIPELINE EXCAVATION AND BACKFILL SECTION IV. PIPELINE EXCAVATION AND BACKFILL A. Description of Work B. Surface Types C. Backfill D. Surface Restoration A. DESCRIPTION OF WORK 1. Extent: Excavation of trenches for pipelines shall include

More information

f) Culverts in series shall be spaced at least 20 feet between each other. 2.7 C Culverts

f) Culverts in series shall be spaced at least 20 feet between each other. 2.7 C Culverts 2.7 C Culverts 1. General Culverts are intended to safely pass flow under road crossings. Criteria are designed to protect, maintain, and enhance public health, safety, and the environment. Where culverts

More information

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR GRASSED WATERWAYS. Definition. Purpose

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR GRASSED WATERWAYS. Definition. Purpose STANDARD FOR GRASSED WATERWAYS Definition A natural or constructed watercourse shaped or graded in earth materials and stabilized with suitable vegetation for the safe conveyance of runoff water. Purpose

More information

WEST VIRGINIA DIVISION OF FORESTRY STATE FOREST STANDARDS for LOGGING ROADS AND SKID TRAILS HAUL ROADS

WEST VIRGINIA DIVISION OF FORESTRY STATE FOREST STANDARDS for LOGGING ROADS AND SKID TRAILS HAUL ROADS WEST VIRGINIA DIVISION OF FORESTRY STATE FOREST STANDARDS for LOGGING ROADS AND SKID TRAILS HAUL ROADS The objective of these specifications is to provide the construction requirements for haul roads and

More information

ALABAMA S BEST MANAGEMENT PRACTICES. Protection of Water Quality During Timber Harvesting

ALABAMA S BEST MANAGEMENT PRACTICES. Protection of Water Quality During Timber Harvesting ALABAMA S BEST MANAGEMENT PRACTICES Protection of Water Quality During Timber Harvesting Water Quality Responsibility Landowners and/or involved professional forestry practitioners such as: Forest resource

More information

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition STANDARD FOR SLOPE PROTECTION STRUCTURES Definition Structures to safely conduct surface runoff from the top of a slope to the bottom of the slope. Purpose The purpose of this practice is to convey storm

More information

RWSSHP Resource Manual # 3b. Spring Development. Construction Manual

RWSSHP Resource Manual # 3b. Spring Development. Construction Manual RWSSHP Resource Manual # 3b Spring Development Construction Manual Introduction This manual is Part B of Manual#3 Hand Dug Wells and Spring Development Construction, which in turn is part of a series of

More information

NEW ENGLAND COUNCIL ON FOREST ENGINEERING CASE STUDY MARCH 6, 2012

NEW ENGLAND COUNCIL ON FOREST ENGINEERING CASE STUDY MARCH 6, 2012 NEW ENGLAND COUNCIL ON FOREST ENGINEERING CASE STUDY MARCH 6, 2012 CONSTRUCTING A TEMPORARY ACCESS ROAD ACROSS AN ATLANTIC WHITE CEDAR ORGANIC BOG FOR THE PURPOSE OF MINING GRAVEL TEMPORARY BOG CROSSING

More information

APPENDIX E. CONSTRUCTION SPECIFICATIONS FOR ACCESS ROADS (January 2005)

APPENDIX E. CONSTRUCTION SPECIFICATIONS FOR ACCESS ROADS (January 2005) APPENDIX E CONSTRUCTION SPECIFICATIONS FOR ACCESS ROADS (January 2005) i TABLE OF CONTENTS 1.0 INTRODUCTION...1 2.0 CONSTRUCTION SPECIFICATIONS FOR ACCESS ROADS................... 1 3.0 PLANNING AND LOCATION...2

More information

Erosion & Sedimentation Control Policy

Erosion & Sedimentation Control Policy Issue Date 10/22/2010 Page 1 of 8 Erosion & Sedimentation Control Policy Introduction: Soil erosion is the removal of soil by water, wind, ice or gravity and sediment deposition occurs when the rate of

More information

SECTION STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 402 STORM DRAINAGE DESIGN CRITERIA 400-1

SECTION STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 402 STORM DRAINAGE DESIGN CRITERIA 400-1 CITY OF THORNTON Standards and Specifications Revised: October 2012 SECTION 400 - STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 401 GENERAL PROVISIONS 400-1

More information

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering Geotechnical Bulletin GB 2 SPECIAL BENCHING AND SIDEHILL EMBANKMENT FILLS Geotechnical Bulletin GB2

More information

STREAM STABILIZATION PLAN

STREAM STABILIZATION PLAN DISTRICT COUNTY ROUTE SECTION SHEET 6- PHILADELPHIA 47 14B 1 OF 2 NOTES: REVISION NUMBER REVISIONS DATE BY 1. REFER TO EROSION AND SEDIMENT POLLUTION CONTROL PLANS FOR LOCATION OF TEMPORARY CONSTRUCTION

More information

Filter Tube Barriers (Instream)

Filter Tube Barriers (Instream) Filter Tube Barriers (Instream) INSTREAM PRACTICES Flow Control No Channel Flow Dry Channels Erosion Control Low Channel Flows Shallow Water Sediment Control High Channel Flows Deep Water Symbol Photo

More information

The Good, The Bad, and The Ugly

The Good, The Bad, and The Ugly Overview The Good, The Bad, and The Ugly Stormwater Regulations for the Construction Industry Seminar March 20, 2012 Wendy Terlizzi Arizona Department of Transportation Office of Environmental Services

More information

Leachate Management Leachate Control and Collection

Leachate Management Leachate Control and Collection Leachate Management Leachate Control and Collection Leachate Collection Sanitary landfills have leachate collection and removal system above liner At un-lined landfills and dump sites Perimeter Ditch -

More information

SEGMENTAL BLOCK RETAINING WALLS. Comply with Division 1 - General Provisions and Covenants, as well as the following:

SEGMENTAL BLOCK RETAINING WALLS. Comply with Division 1 - General Provisions and Covenants, as well as the following: SEGMENTAL BLOCK RETAINING WALLS PART 1 - GENERAL 1.01 SECTION INCLUDES Segmental Block Retaining Walls 1.02 DESCRIPTION OF WORK Constructing segmental block retaining walls. 1.03 SUBMITTALS Comply with

More information

10:00 AM, Wednesday, April 8, 2015

10:00 AM, Wednesday, April 8, 2015 NOTICE OF MANDATORY PRE-BID CONFERENCE WILL BE HELD AT 10:00 AM, Wednesday, April 8, 2015 IN ROOM 16, CITY HALL BUILDING, 101 NORTH MAIN STREET WINSTON-SALEM, NORTH CAROLINA The purpose of this conference

More information

2.1 Backfill - General

2.1 Backfill - General 2.1 Backfill - General Excavations are made for the purpose of constructing bridge substructure elements, and consequently requiring competent backfill material. The backfill material must be adequately

More information

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

CONCRETE SEGMENTAL RETAINING WALL SYSTEM CONCRETE SEGMENTAL RETAINING WALL SYSTEM PART 1: GENERAL SPECIFICATIONS 1.01 Work Included A. Work shall consist of furnishing and constructing a Rockwood Classic 8, Classic 6 and Legend unit segmental

More information

The Modern and Cost-Effective Solution for Track & Field Drainage and Player Safety TERMINATOR

The Modern and Cost-Effective Solution for Track & Field Drainage and Player Safety TERMINATOR The Modern and Cost-Effective Solution for Track & Field Drainage and Player Safety TERMINATOR 2 TERMINATOR...www.sportsedge.com TERMINATOR Patent No,: US 8,894,324 B2 Rope Wedge Resilient Protective Cap

More information

SOIL EROSION CONTROL PERMIT APPLICATION

SOIL EROSION CONTROL PERMIT APPLICATION SOIL EROSION CONTROL PERMIT APPLICATION Pursuant to Part 91, Soil Erosion and Sedimentation Control, of Act 451 of the Public Acts of 1994, as amended A Soil Erosion Control Permit is required for earth

More information

Storm Drain Inlet Protection

Storm Drain Inlet Protection Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category

More information

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016 SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri September 21, 2016 CONTENT Introduction Potential in Southeast Asia Challenges in Small Hydro Main Design Steps (Bad) Examples

More information

StormwaterWise Landscapes: Pervious Surfaces Specifications

StormwaterWise Landscapes: Pervious Surfaces Specifications StormwaterWise Landscapes: Pervious Surfaces Specifications Purpose & Benefits Stormwater runoff reduction High pollutant removal Control localized drainage problems Attractive alternative for walkways

More information

Public Notice ISSUED: June 29, 2017 EXPIRES: July 31, 2017

Public Notice ISSUED: June 29, 2017 EXPIRES: July 31, 2017 SPONSOR: Gary Pestorious Public Notice ISSUED: June 29, 2017 EXPIRES: July 31, 2017 REFER TO: 2012-01634-DAS SECTION:404 - Clean Water Act 1. WETLAND COMPENSATORY MITIGATION BANK PROPOSAL: Pickerel Lake

More information

Corrugated Metal Pipe Design Guide

Corrugated Metal Pipe Design Guide Corrugated Metal Pipe Temporary Cover For Construction Loads Height-Of-Cover Finished Grade Backfill D Bedding INNOVATIVE SITE SOLUTIONS & STORMWATER MANAGEMENT Corrugated Metal Pipe Table of Contents

More information

Welded Mesh Gabions and Mattresses River Protection Design Guide Anping County Zhuoda Hardware Mesh Co.,Ltd. Wire Mesh Industrial Zone, Anping

Welded Mesh Gabions and Mattresses River Protection Design Guide Anping County Zhuoda Hardware Mesh Co.,Ltd. Wire Mesh Industrial Zone, Anping Welded Mesh Gabions and Mattresses River Protection Design Guide Anping County Zhuoda Hardware Mesh Co.,Ltd. Wire Mesh Industrial Zone, Anping County, Hebei, P. R. China. Tel : 0086-318-7752001 7531068

More information

Module 4 Regulatory requirements for Land Disturbing Activities

Module 4 Regulatory requirements for Land Disturbing Activities Module 4 Regulatory requirements for Land Disturbing Activities MODULE 4 REGULATORY REQUIREMENTS FOR A LDA Module 4a Overview MODULE 4A REGULATORY REQUIREMENTS FOR A LDA ESC Regulations Overview 1990 First

More information

Landscaping and Fencing

Landscaping and Fencing Landscaping and Fencing Fences, driveways, paving, retaining walls, landscaping & other garden features To be read in conjunction with General Requirements: A guide to building on properties containing

More information

Brush layering construction

Brush layering construction Brush layering construction Brush layering consists of embedding live branches on successive horizontal rows along contours on the face of a slope. Rooted plants can also be placed among the live branches.

More information

Nevada Contractors Field Guide for Construction Site BMPs

Nevada Contractors Field Guide for Construction Site BMPs Nevada BMP Field Guide 2013 Update Nevada Contractors Field Guide for Construction Site BMPs This document has been approved by the Nevada Division of Environmental Protection (NDEP) and reflects best

More information

Erosion and Sediment Control Plan for a Timber Harvesting Operation

Erosion and Sediment Control Plan for a Timber Harvesting Operation 3930-FM-WM0155 Rev. 7/2004 Erosion and Sediment Control Plan for a Timber Harvesting Operation 1. GENERAL INFORMATION A. Location Municipality B. Timber sale area = acres Date County C. Landowner Name

More information

PROPOSED STOCK PILE YARD PHASE 1 SITE: MYRA FALLS MINE

PROPOSED STOCK PILE YARD PHASE 1 SITE: MYRA FALLS MINE SITE NOT TO SCALE 635-8-STOCKPILEPHGA- 00 SHEET: OF DRAWING INDEX: SHEET 2 OF 0 - NOTES SHEET 3 OF 0 - PLAN VIEW :000 SHEET 4 OF 0 - PLAN VIEW :000 WITH REFERENCE SHEET 5 OF 0 - PLAN VIEW :500 SHEET 6

More information

Utility and Sanitary Sewer Permitting & Design. Gibson-Thomas Engineering Co., Inc. Consulting Engineers

Utility and Sanitary Sewer Permitting & Design. Gibson-Thomas Engineering Co., Inc. Consulting Engineers Utility and Sanitary Sewer Permitting & Design Gibson-Thomas Engineering Co., Inc. Consulting Engineers Utility Line Design Provide service to communities in need with minimal piping needed minimize $$

More information

Smarter, Cheaper, Ash Pond Dewatering

Smarter, Cheaper, Ash Pond Dewatering 2017 World of Coal Ash (WOCA) Conference in Lexington, KY - May 9-11, 2017 http://www.flyash.info/ Smarter, Cheaper, Ash Pond Dewatering David M. Seeger, PhD, Steven Kosler AECOM, 9400 Amberglen Blvd.,

More information

Watershed size and name: The drainage area is acres. The pond is located within the Ohio River watershed. (2016 Inflow Design Plan)

Watershed size and name: The drainage area is acres. The pond is located within the Ohio River watershed. (2016 Inflow Design Plan) A. B. Brown History of Construction 40 CFR 257.73 (c) (i.) (ii.) (iii.) Owner Name: Southern Indiana Gas and Electric Company dba Vectren Power Supply Owner Address: One Vectren Square, PO Box 209, Evansville,

More information

Nutrient Management in. A presentation to the West Metro Water Alliance

Nutrient Management in. A presentation to the West Metro Water Alliance Nutrient Management in Developing and Agricultural Areas A presentation to the West Metro Water Alliance Chris Meehan, P.E. May 25, 2011 Agenda Physical Improvements Planning Improvements How to get it

More information

C. This project shall be designed to meet LEED Silver design criteria. Construction activity pollution prevention is a mandatory requirement.

C. This project shall be designed to meet LEED Silver design criteria. Construction activity pollution prevention is a mandatory requirement. SECTION 31 25 13 EROSION AND SEDIMENTATION CONTROL PART 1 GENERAL 1.1 SCOPE OF WORK A. This Section pertains to the provisions for the control of erosion in the construction area and in stockpile areas

More information

Mr. Paul Dunlap, California Department of Water Resources

Mr. Paul Dunlap, California Department of Water Resources Memorandum To: From: Mr. Paul Dunlap, California Department of Water Resources Oroville Dam Spillway Incident Independent Forensic Team Date: September 5, 2017 Re: Interim Status Memorandum Introduction

More information

All driveways shall have a separate site plan when the application is submitted.

All driveways shall have a separate site plan when the application is submitted. Driveway Submittal Requirements All driveways shall have a separate site plan when the application is submitted. Within 24 hours of application submittal, all proposed driveways shall: be addressed with

More information

Open Trench Construction Plan Review The open trench construction plan review involves the following general investigative elements:

Open Trench Construction Plan Review The open trench construction plan review involves the following general investigative elements: TNC Fisher Slough Final Design and Permitting Subject: Inverted Siphon Construction Feasibility To: From: Jenny Baker (TNC) Dave Olson (DD3) Brian Olson (DD17) Bob Boudinot Skagit County David Cline (Tetra

More information

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CS 3-01 GENERAL: A. The foundation, bedding and backfill for all trenches shall conform with the requirements of the City Standard

More information

Understanding Soil Erosion and Management Practices

Understanding Soil Erosion and Management Practices Lesson C6 8 Understanding Soil Erosion and Management Practices Unit C. Plant and Soil Science Problem Area 6. Basic Principles of Soil Science Lesson 8. Understanding Soil Erosion and Management Practices

More information

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION SPECIFICATION FOR PIPE CULVERT CONSTRUCTION 1. SCOPE Pipe culverts shall be constructed in accordance with this specification and in conformity with the lines, levels and cross-sections shown on the drawings.

More information

Town of New Tecumseth Engineering Design Criteria and Standards for Subdivisions and Capital Works Projects

Town of New Tecumseth Engineering Design Criteria and Standards for Subdivisions and Capital Works Projects 2.0 ROADWAYS 2.1 Road Classification 2.1.1 Standard Drawing Classification All Road Widths and Road Allowances shall be designed in accordance with the most recent Town of New Tecumseth Standards: TNT.SD

More information

CHAPTER 6. Sanitary Sewer

CHAPTER 6. Sanitary Sewer CHAPTER 6 Sanitary Sewer A. Introduction All proposed developments, subdivisions, and buildings must have a properly designed and constructed sanitary sewer collection system. The system shall provide

More information

SECTION SPECIFICATION FOR STONEBRIDGE RETAINING WALL SYSTEM

SECTION SPECIFICATION FOR STONEBRIDGE RETAINING WALL SYSTEM SECTION 32 32 23 SPECIFICATION FOR STONEBRIDGE RETAINING WALL SYSTEM PART 1: GENERAL 1.01 Scope Work includes furnishing all materials, labor, equipment, and supervision to install a Stonebridge segmental

More information

28 February 2017 ATTENTION: MR HENNIE WOOD AND MS MAGGIE VON RONGE NORTHAM BOOYSENDAL CC: AMANDA PYPER AMEC FOSTER WHEELER NOTE FOR THE RECORD

28 February 2017 ATTENTION: MR HENNIE WOOD AND MS MAGGIE VON RONGE NORTHAM BOOYSENDAL CC: AMANDA PYPER AMEC FOSTER WHEELER NOTE FOR THE RECORD Project Reference: 720.01092.00001 File Ref. 170228 Erosion & Silt Management NFTR Rev1 28 February 2017 PROJECT: Booysendal South EIA Hydrology Specialist Study CLIENT: Amec Foster Wheeler ORDER No: 2338/9149/1294

More information

Annex I Lyons Ferry Hatchery Modification Plan

Annex I Lyons Ferry Hatchery Modification Plan Annex I Lyons Ferry Hatchery Modification Plan Table I1 Figure I1 Figure I2 Figure I3 Figure I4 Figure I5 Well Characteristics Lyons Ferry Hatchery Vicinity Map Lyons Ferry Hatchery Site Plan Water Supply

More information

Providing proper drainage system

Providing proper drainage system Environment Friendly and Cost Effective Alternative to Conventional Graded Filters Providing proper drainage system for structures such as earth retaining structures, pavements, water front structures,

More information