1 Proper Construction of detention and sediment basins and their conversions By Chris Droste, CESCO Senior Erosion Control Specialist Westmoreland Conservation District

2 Discussed topics Pond embankment construction Installing the Outfall barrel Installing the risers Building fore bays and weirs Conversions and as-built surveys Problems with ponds (embankment failures)

3 Embankment construction & compaction

4 Keyway and embankment construction Location of select material for embankment needs decided early Inspections are critical at this time

5 Embankment construction Soils should be compacted according to plan specs or by an on-site geotechnical engineer. Final slopes should be to plan configuration

6 Excavation for keyway

7 Ensure the excavation is close to depth as shown on the plans

8 Inspections of keyway drains Inspectors should witness the installation of these

9 Material for the embankment should compose of clay or silty clay. Locate the soils drawing to determine about where the soils may be

10 Slow layering and moving of the earth to establish proper lifts is important to the compaction of the soil

11 The embankment should be constructed with a NONvibratory roller/ sheep foot from suitable materials using 6-9 lifts

12 The Final stage Now is the time to make sure the pond Complies with the plan design Is the embankment to correct elevation? Are the slopes 2:1, 3:1? Is the pond about the right volume?

13 Outlet barrel Cradle Detail

14 Observing the barrel installation

15 Method to install the barrel The barrel should be placed early Avoid having the contractor cut through the embankment to install the pipe. If they must cut through the embankment..

16 Outlet Barrel Installation Detail

17 Problem Seep collars should be notched Into existing embankment Compaction around sides of the pipe is important

18 Barrel and seep collar installation Bedding with 2A modified Around pipe is an acceptable Fill material around the pipe 2A modified solidifies when Moisture comes in contact. ADS HD (grey) pipe is used in this example

19 Hand work is needed to push the 2A modified into the base ADS- HD plastic pipe is acceptable To using concrete if it meets the Standards

20 Small compactors wackers can be used to tamp The 2A modified around the base of the pipe

21 Ensure your seep collar excavated area is into the excavated area of embankment

22 Forms can be used, or backing up the trench with the 2A modified, to pour the collar

23 The poured collar should be high enough above the pipe as shown in the plan details

24 Problems with using plastic pipe

25 The problems using corrugated plastic pipe as the barrel Plastic is meant to be bed with Stone to prevent collapse. The sides of the pipe will compress with compaction or weight on top unless there is sufficient support on each side of the pipe. Using stone around the pipe will act as a French drain and water will pull soil with it. This causes failure of the embankment.

26 Sinkhole Sinkholes that develop near the riser will tell you there is a problem with the barrel.

27 The Cause A joint failed under compaction Pond was draining too fast Sediment pollution occurred

28 Another example

29 Water is traveling along side the pipe in the Embankment, causing a sinkhole to develop

30 A Sign that you have a problem is a hole in the embankment resulting from Piping.

31 Pipe is elliptical due to compaction on top Pipe sections have separated allowing Water to seep through embankment

32 Riser installation

33 Riser/outlet barrel should be properly sealed

34 Outlet risers require footing and trash racks

35 Concrete footing for (Type M) outlet riser

36 Skimmers

37 Skimmers Must be attached to either a permanent Riser box or barrel Skimmer flexible hose should be secured and water tight to Type M inlet box Close off holes in the box riser Install correct orifice plate in dewatering tube.

38 Skimmers Skimmers must be set on a concrete block or perch, not a haybale! Guide posts are required to keep the skimmer moving and detaching from the flex hose A rope is recommended to be attached to skimmer and tied to embankment for access.

39 Skimmer with rebar posts and rebar perch at sediment cleanout

40 Skimmers problems Skimmer will move of block and be stuck in mud Skimmer needs guideposts or skimmer will move off block

41 Skimmers with long flex hoses Avoid Long flex hoses as they float and do not allow for dewatering of the skimmer

42 Problems with Contractor made skimmers This skimmer won t drain and may break off fittings The discharge pipe is not long enough Skimmer won t rise.

43 Problems with Contractor made skimmers Furnco Fittings do not work well!

44 Skimmer is very large and heavy and won t float

45 Skimmer problems Corrugated plastic pipe Duck taped is not a good alternative For connection

46 Skimmer Problems Guideposts are laying down Skimmer is disconnected from flexible pipe

47 Skimmer problems Guideposts and perch are good Holes in riser box are not sealed

48 Emergency spillway ** Over-excavate to Accommodate the size of rock Ensure the rock does not fill in the entire spillway

49 Cutoff walls in spillway Make sure the depth and width is correct.

50 Forebay construction

51 Wet Pond with Forebay Detail

52 Forebay weirs Correctly lined Extend the rock into the bottom of the pond or erosion WILL occur!

53 Forebay weirs with concrete.

54 Forebays with inlet overflows Install Barrel in embankment the same as the main pond

55 Aprons Discharge should exit onto a Proper rock lined apron Should be installed very soon after end wall is installed

56 Are the aprons to the correct size?

57 Use the proper size rock. Too large blocks the flow Too small: water washes out the apron.

58 - Watch using cheaper Quarry rock or on-site rock. - Shale or broken sandstone will weather and fall apart. - The Rock should be to the correct size according to the plans

59 Conversions

60 Vegetation has grown on sediment mounds. - Old Baffles need removed - Sediment needs removed to original elevation - Sediment Riser needs removed - New Apron Rock will need installed, low flow channels

61 Does the pond need to be cleaned out before conversion? Yes: if the pond was used as a sediment basin, most likely it will need cleaned out

62 - Most of the time Ponds are full of water, soils are very mucky - A Hauling material out is very time consuming - Keeping water to one side helps, create a dam and keep a - Pump handy to remove water from entering workspace. - Place a layer of 2B stone around old riser base to filter sediment

63 -Phased projects may allow you to find a spot to dig a pit to dump the mucky soil and Allow to dry. -Place orange fence around the area to keep people from entering and getting stuck.

64 - Establishing the bottom elevation (survey) - Installing the underdrains - Preparing for the low flow channels Sourcing good material For the pond bottom may Be a problem at the end Of many projects

65 Seed with the appropriate mix, slope mix And detention pond mix can be used. Embankments need to be stable with Straw/net blanket or hydro-mulch

66 Survey in the orifice elevations of the riser when converting as to ensure as-builts are correct

67 Inspection and measurement of the orifices is very important to the functionality of the pond and for the As-built survey to be correct

68 Establish the aprons and taper into the low flow channels (if required on plans)

69 Pond bottoms should be stabilized. Blankets work better than blown straw mulch. At this pond, the surveyor can come in and perform the final pond survey.

70 The end Contact Chris Droste or

Construction Inspection Checklists

Construction Inspection Checklists III. Construction Inspection Checklists 33 Bioretention - Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: Construction Sequence Satisfactory / Unsatisfactory Comments

More information

ENGINEERING CHECKLIST SEDIMENT & STORMWATER MANAGEMENT BASIN CONSTRUCTION

ENGINEERING CHECKLIST SEDIMENT & STORMWATER MANAGEMENT BASIN CONSTRUCTION NEW CASTLE COUNTY DEPARTMENT OF LAND USE ENGINEERING CHECKLIST SEDIMENT & STORMWATER MANAGEMENT BASIN CONSTRUCTION For Permanent Structures, pursuant to Delaware Pond Code 378 and Delaware Sediment and

More information

q Item meets standard Project ID: X Item not acceptable Contractor: N/A Item not applicable Inspector: C Item requires engineer s cert.

q Item meets standard Project ID: X Item not acceptable Contractor: N/A Item not applicable Inspector: C Item requires engineer s cert. SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST For permanent structures per Delaware SCS Pond Code 378 and Delaware Sediment and Stormwater Regulations KEY PROJECT INFORMATION q Item meets

More information

Sediment Basins and Skimmers. Jay Dorsey/John Mathews Ohio Dept. of Natural Resources, Division of Soil and Water Resources

Sediment Basins and Skimmers. Jay Dorsey/John Mathews Ohio Dept. of Natural Resources, Division of Soil and Water Resources Sediment Basins and Skimmers Jay Dorsey/John Mathews Ohio Dept. of Natural Resources, Division of Soil and Water Resources Dewatering Risers in Basins: Single orifice Perforated and wrapped riser And now

More information

Installation and Maintenance of Erosion Control BMPs

Installation and Maintenance of Erosion Control BMPs Installation and Maintenance of Erosion Control BMPs Or Common BMPs Applications Specifications Installation Problems Maintenance Utility Design Professionals Clarifications, proactive problem solving

More information

Sediment Basin. Fe= (Depends on soil type)

Sediment Basin. Fe= (Depends on soil type) 3.9 Sediment Control Description: A sediment basin is an embankment with a controlled outlet that detains stormwater runoff, resulting in the settling of suspended sediment. The basin provides treatment

More information

TEMPORARY SEDIMENT TRAP CODE

TEMPORARY SEDIMENT TRAP CODE ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY SEDIMENT TRAP CODE 960 Source: DEFINITION A small temporary stormwater storage structure designed to trap sediment. PURPOSE The purpose of this practice

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

Richland County Department of Public Works Engineering (Land Development) Division

Richland County Department of Public Works Engineering (Land Development) Division Richland County Department of Public Works Engineering (Land Development) Division Commercial Projects What is a Commercial Project? Projects that are not related to residential single family homes and/or

More information

City of Charlotte BMP Maintenance and Inspection Check List Grassed Channels / Swales [Note: a separate form must be used for each BMP]

City of Charlotte BMP Maintenance and Inspection Check List Grassed Channels / Swales [Note: a separate form must be used for each BMP] City of Charlotte BP aintenance and Inspection Check List Grassed Channels / Swales [Note: a separate form must be used for each BP] Project Name: Project Address: Owner s Name: Owner s Address: Recorded

More information

Extended Detention Basin Maintenance Plan for [[== Insert Project Name ==]]

Extended Detention Basin Maintenance Plan for [[== Insert Project Name ==]] Extended Detention Basin Plan for [[== Insert Project Name ==]] [[== Insert Date =]] Project Address and Cross Streets Assessor s Parcel No.: Property Owner: Phone No.: Designated Contact: Phone No.: Extended

More information

B. Install storm drain inlet protection to prevent clogging of the stormsewer and sediment loads to downstream stormwater facilities or waterbodies.

B. Install storm drain inlet protection to prevent clogging of the stormsewer and sediment loads to downstream stormwater facilities or waterbodies. The language provided in these specifications is meant to serve as a reminder and provide a generic example of the type of language that should be provided in final construction documents. This language

More information

At least 2 feet above the seasonal high water table Overflow path or structure provided

At least 2 feet above the seasonal high water table Overflow path or structure provided General Conditions Map of proposed subwatershed to each subbasin, including total area and CN Design Flow or Design Volume to each STF, as appropriate Operation and Maintenance instructions for each STF

More information

Best Management Practice (BMP) Guidance Manual

Best Management Practice (BMP) Guidance Manual Best Management Practice (BMP) Guidance Manual INTRODUCTION BMP examples in this guide provide ways to meet erosion and sediment control requirements. Best Management Practices are not limited to these

More information

GUIDELINES FOR INSTALLATION OF ON-SITE SEWAGE SYSTEMS

GUIDELINES FOR INSTALLATION OF ON-SITE SEWAGE SYSTEMS UTAH COUNTY HEALTH DEPARTMENT Div. of Environmental Health 151 South University Avenue, Provo 84601 (801) 851-7525 FAX 851-7521 GUIDELINES FOR INSTALLATION OF ON-SITE SEWAGE SYSTEMS This is intended to

More information

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN

More information

PERMEABLE INTERLOCKING PAVERS

PERMEABLE INTERLOCKING PAVERS PERMEABLE INTERLOCKING PAVERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subgrade Preparation B. Placement of Storage Aggregate C. Placement of Filter Aggregate D. Placement of Bedding Course E. Placement

More information

CITY UTILITIES DESIGN STANDARDS MANUAL

CITY UTILITIES DESIGN STANDARDS MANUAL CITY UTILITIES DESIGN STANDARDS MANUAL () September 2017 Page Chapter 1 Acronyms and Definitions 1.01 Purpose 1 1.02 Acronyms 1 1.03 Definitions 3 Chapter 2 Introduction 2.01 Purpose 1 2.02 Applicability

More information

ACTIVITY: Wet Detention Basin ST 02

ACTIVITY: Wet Detention Basin ST 02 Pond surface Outlet Forebay Littoral zone Targeted Constituents Significant Benefit Partial Benefit Low or Unknown Benefit Sediment Heavy Metals Floatable Materials Oxygen Demanding Substances Nutrients

More information

ROLES AND RESPONSIBILITIES Small Pond Approval. SWM MD-378 Pond Checklist Training 10/17/07. Exemptions EMBANKMENT HEIGHT. Height of Dam Weir Wall

ROLES AND RESPONSIBILITIES Small Pond Approval. SWM MD-378 Pond Checklist Training 10/17/07. Exemptions EMBANKMENT HEIGHT. Height of Dam Weir Wall SWM MD-378 Pond Checklist Training 10/17/07 Ken Wolfe Warren Johnson USDA, NRCS Frederick, Maryland ROLES AND RESPONSIBILITIES Small Pond Approval MDE, WMA, Dam Safety Division Authority (COMAR 26.17.04.03)

More information

Section 401. PIPE CULVERTS

Section 401. PIPE CULVERTS 401.02 Section 401. PIPE CULVERTS 401.01. Description. This work consists of constructing pipe culverts of the size and class required, including excavation and backfill. 401.02. Materials. Provide materials

More information

SECTION UNCLASSIFIED EXCAVATION AND GRADING

SECTION UNCLASSIFIED EXCAVATION AND GRADING SECTION 02210 UNCLASSIFIED EXCAVATION AND GRADING PART 1 GENERAL 1.1 DESCRIPTION Work in this section includes the excavation, undercut excavating, grading, earthwork and compaction required as shown on

More information

Diversion Dikes. Fe=0.95

Diversion Dikes. Fe=0.95 2.2 Diversion Dike Erosion Control Description: A diversion dike is a compacted soil mound, which redirects runoff to a desired location. The dike is typically stabilized with natural grass for low velocities

More information

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by

More information

Constructed Wetland Use in Nonpoint Source Control

Constructed Wetland Use in Nonpoint Source Control Constructed Wetland Use in Nonpoint Source Control Description Constructed wetlands are excavated basins with irregular perimeters and undulating bottom contours into which wetland vegetation is purposely

More information

APPENDIX A EARTHEN EMBANKMENT. VERSION 1.0 March 1, 2011

APPENDIX A EARTHEN EMBANKMENT. VERSION 1.0 March 1, 2011 APPENDIX A EARTHEN EMBANKMENT VERSION 1.0 March 1, 2011 SECTION A-1: DESCRIPTION OF PRACTICE An earthen embankment is a raised impounding structure made from compacted soil. The embankment is the feature

More information

Constructed Wetland Pond T-8

Constructed Wetland Pond T-8 Constructed Wetland Pond T-8 Description A constructed wetlands pond is a shallow retention pond designed to permit the growth of wetland plants such as rushes, willows, and cattails. Constructed wetlands

More information

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES SECTION 02221 EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02200 - Earthwork. 2. 02660 - Water Systems. 3. 02720 - Storm Drainage System. 4.

More information

SEPTIC TANK CONSTRUCTION GUIDELINES

SEPTIC TANK CONSTRUCTION GUIDELINES SEPTIC TANK CONSTRUCTION GUIDELINES Septic tank for this airport will be designed/ built by the general contractor of the building facilities. At the time of the project design, availability of a septic

More information

City of Bozeman. Construction Site Management Program

City of Bozeman. Construction Site Management Program City of Bozeman Construction Site Management Program Best Management Practice (BMP) Manual for Construction Sites Version 6 June 30, 2017 Blank Page 2 Section 1 - Overview Table of Contents Manual Introduction

More information

CATCH BASIN ST-1 ENGINEERING DEPARTMENT PLATE NUMBER 3.33' 3.0' 2.0' 4.33' 3.0' 4.0' 1.00' TO BACK OF CURB LINE

CATCH BASIN ST-1 ENGINEERING DEPARTMENT PLATE NUMBER 3.33' 3.0' 2.0' 4.33' 3.0' 4.0' 1.00' TO BACK OF CURB LINE 3.33' 3.0' 2.0' 4.33' 4.0' 3.0' 1.00' TO BACK OF CURB LINE TOP OF GRATE ELEV. - SEE PLAN NEENAH CASTING R-3067-V OR AS NOTED ON PLANS. "INFA-SHIELD" SEAL OR EQUAL. RINGS (2 MIN., 1' MAX. OF RINGS AND MORTAR).

More information

APPENDIX C DURING CONSTRUCTION BMP TABLES

APPENDIX C DURING CONSTRUCTION BMP TABLES APPENDIX C DURING CONSTRUCTION BMP TABLES Table C.1 Table C.2 Table C.3 Erosion Prevention BMPs Sediment Control BMPs Stormwater Runoff and Ground Control Measures STORM WATER QUALITY DESIGN MANUAL Appendix

More information

Supplemental Watershed Plan Agreement No. 10 for Neshaminy Creek Watershed Core Creek Dam (PA-620) Bucks County, Pennsylvania

Supplemental Watershed Plan Agreement No. 10 for Neshaminy Creek Watershed Core Creek Dam (PA-620) Bucks County, Pennsylvania Supplemental Watershed Plan Agreement No. 10 for Neshaminy Creek Watershed Core Creek Dam (PA-620) Bucks County, Pennsylvania Project Authorization USDA's Small Watershed Program is carried out under the

More information

INSTALLATION INSTRUCTIONS

INSTALLATION INSTRUCTIONS INSTALLATION INSTRUCTIONS FOR HORIZONTAL INSTALLATIONS OF THE SMART DRAIN SUBSURFACE DRAINAGE SYSTEM GENERAL GUIDELINES 1. Smart Drain is ALWAYS laid with its inlet (ribbed) side facing downward. LAYING

More information

Visual Inspection Checklist

Visual Inspection Checklist APPENDIX Q. Visual Inspection Checklist Thispageintentionallyleftblank. VISUAL INSPECTION CHECKLIST CITY OF AUBURN PUBLIC WORKS DEPARTMENT INSPECTION YEAR: TYPE OF INSPECTION: (Informal, Regular, Formal):

More information

CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS

CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS 8.1 INTRODUCTION To minimize the detrimental effects of erosion and sedimentation, Henrico County requires that those individuals responsible for

More information

GWINNETT COUNTY STORM SEWER PIPE STANDARDS

GWINNETT COUNTY STORM SEWER PIPE STANDARDS 1.0 Standard Specifications GWINNETT COUNTY STORM SEWER PIPE STANDARDS 1.1 Unless otherwise specifically set forth herein or in the Gwinnett County Standard Drawings, all of the materials, methods of the

More information

The Pond Management Protocol. Tom Schueler Chesapeake Stormwater Network

The Pond Management Protocol. Tom Schueler Chesapeake Stormwater Network The Pond Management Protocol Tom Schueler Chesapeake Stormwater Network Key Topics Pond Basics Evaluating Pond Functions Visual Indicators for Water Quality Visual Indicators for Dam Safety Techniques

More information

Erosion and Sedimentation Pollution Control (ESPC) Plan Narrative

Erosion and Sedimentation Pollution Control (ESPC) Plan Narrative Model Poultry Burial E&S Plan (7-2-15) 1. GENERAL INFORMATION Name of project Name of person responsible Erosion and Sedimentation Pollution Control (ESPC) Plan Narrative Address Phone number Municipality

More information

SECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS.

SECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS. SECTION 1100 GRADING 1101 SCOPE. This section covers the performance of all work required for grading the project in coordination with all previous work performed at the locations shown on the contract

More information

HOW TO INSTALL PATIOS AND WALKWAYS STEP 2 STEP 1. For all Patios and Walkways. The base is the most important step in your patio and walkway projects.

HOW TO INSTALL PATIOS AND WALKWAYS STEP 2 STEP 1. For all Patios and Walkways. The base is the most important step in your patio and walkway projects. New Project (replacing grass/dirt) STEP 1 PREPARING YOUR PROJECT AREA Determine how much to excavate using the example below. Remove the grass to desired depth (skim rather than dig deep) and a few inches

More information

Brush layering construction

Brush layering construction Brush layering construction Brush layering consists of embedding live branches on successive horizontal rows along contours on the face of a slope. Rooted plants can also be placed among the live branches.

More information

Choctaw Lake Property Owners Association DRAINAGE SPECIFICATIONS (Approved by the Board of Trustees January 9, 2018)

Choctaw Lake Property Owners Association DRAINAGE SPECIFICATIONS (Approved by the Board of Trustees January 9, 2018) ADOPTED BY CHOCTAW LAKE BOARD OF TRUSTEES ORIGINAL APPROVAL SEPTEMBER 20, 1990 REVISED AND APPROVED AUGUST 10, 2004, JANUARY 9, 2018 THIS DOCUMENT IS A PART OF THE CLPOA BUILDING CODE CHANGES TO THIS DOCUMENT

More information

TYPICAL INSTALLATION INSTRUCTIONS

TYPICAL INSTALLATION INSTRUCTIONS TYPICAL INSTALLATION INSTRUCTIONS Environment One Grinder Pump Feature Identification 1. Grinder Pump Basin High density polyethylene (HDPE) 2. Accessway Cover Painted Steel 3. Electrical Quick Disconnect

More information

SACHSE EROSION CONTROL GUIDELINES

SACHSE EROSION CONTROL GUIDELINES SACHSE EROSION CONTROL GUIDELINES Section I. Definitions The following words, terms, and phrases, when used in this guideline, shall have the meanings ascribed to them in this Section, except where the

More information

BMP #: Infiltration Basin

BMP #: Infiltration Basin Structural BMP Criteria BMP #: Infiltration Basin An Infiltration Basin is a shallow impoundment that stores and infiltrates runoff over a level, subtle, uncompacted, (preferably undisturbed area) with

More information

TYPE "A" CATCH BASIN

TYPE A CATCH BASIN 27" 1.67' TO BACK OF CURB LINE TOP OF GRATE ELEV. - SEE PLAN NEENAH CASTING R-3250-BV OR APPROVED EQUAL. "INFI SHIELD" SEAL OR APPROVED EQUAL RINGS (2 MIN., 1' MAX. OF RINGS AND MORTAR). PLASTER OUTSIDE,

More information

Town of Fortville Utility Street Standards

Town of Fortville Utility Street Standards Town of Fortville Utility Street Standards SECTION 02101 - TEMPORARY EROSION AND DUST CONTROL PART 1 - GENERAL 1.1 DESCRIPTION A. Temporary Erosion and Dust Control measures must meet the current Town

More information

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing

More information

REROUTING DRAINAGE SYSTEMS

REROUTING DRAINAGE SYSTEMS MINNESOTA WETLAND RESTORATION GUIDE REROUTING DRAINAGE SYSTEMS TECHNICAL GUIDANCE DOCUMENT Document No.: WRG 4A-4 Publication Date: 10/14/2015 Table of Contents Introduction Application Design Considerations

More information

Table of Contents. Attachments Attachment A Photos Attachment B Inspection Map. Pages 3 of 10

Table of Contents. Attachments Attachment A Photos Attachment B Inspection Map. Pages 3 of 10 Table of Contents 1.0 Introduction...4 2.0 Description of Landfill...4 3.0 Review of Available Information...5 4.0 Inspection...5 4.1 Changes in Geometry since Last Inspection...5 4.2 Volume...5 4.3 Definitions

More information

The Good, The Bad, and The Ugly

The Good, The Bad, and The Ugly Overview The Good, The Bad, and The Ugly Stormwater Regulations for the Construction Industry Seminar March 20, 2012 Wendy Terlizzi Arizona Department of Transportation Office of Environmental Services

More information

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION SPECIFICATION FOR PIPE CULVERT CONSTRUCTION 1. SCOPE Pipe culverts shall be constructed in accordance with this specification and in conformity with the lines, levels and cross-sections shown on the drawings.

More information

Stormwater Management and Sediment and Erosion Control Plan Review Checklist for Design Professionals

Stormwater Management and Sediment and Erosion Control Plan Review Checklist for Design Professionals Page 1 of 7 Florence County MS4 Stormwater Management and Sediment and Erosion Control Plan Review Checklist for Design Professionals Please indicate the location and page number(s) where each item below

More information

***************************************************************************************************************

*************************************************************************************************************** 02720 STORM DRAINAGE SYSTEM *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 33 40 00. ***************************************************************************************************************

More information

C. Foundation stabilization for pipe and utility structures.

C. Foundation stabilization for pipe and utility structures. PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization

More information

Underground Exhaust System

Underground Exhaust System Operation and Maintenance Manual Underground Exhaust MONOXIVENT - SOURCE CAPTURE SYSTEMS - info@ Oct. - 2015 Underground Duct Construction Standards 1. Dig trench depth to allow for minimum distance from

More information

INSPECTION, MAINTENANCE AND HOUSEKEEPING PLAN

INSPECTION, MAINTENANCE AND HOUSEKEEPING PLAN INSPECTION, MAINTENANCE AND HOUSEKEEPING PLAN Bates College 55 & 65 Campus Avenue Housing Lewiston, Maine Introduction The following plan outlines the anticipated inspection and maintenance procedures

More information

SECTION TRENCHING & BACKFILLING

SECTION TRENCHING & BACKFILLING SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications

More information

HOW TO INSTALL PATIOS AND WALKWAYS STEP 2 STEP 1. For all Patios and Walkways. The base is the most important step in your patio and walkway projects.

HOW TO INSTALL PATIOS AND WALKWAYS STEP 2 STEP 1. For all Patios and Walkways. The base is the most important step in your patio and walkway projects. STEP 1 PREPARING YOUR PROJECT AREA Most commonly this is removing a grass area that is around your current concrete patio. You will incorporate this area into your new larger outdoor patio design. You

More information

BMP 6.4.4: Infiltration Trench

BMP 6.4.4: Infiltration Trench BMP 6.4.4: Infiltration Trench An Infiltration Trench is a leaky pipe in a stone filled trench with a level bottom. An Infiltration Trench may be used as part of a larger storm sewer system, such as a

More information

PART 1 GENERAL REQUIREMENTS

PART 1 GENERAL REQUIREMENTS PART 1 GENERAL REQUIREMENTS Contract Closeout Plan 110 Arrow diagram for project close-out...3 Erosion Control 121 Straw bale barrier... 5 122 Silt fence... 7 123 Diversion dike... 9 124 Inlet protection...

More information

POND CONSTRUCTION. Woodland Steward Series

POND CONSTRUCTION. Woodland Steward Series POND CONSTRUCTION Woodland Steward Series BOB TWOMEY DISTRICT CONSERVATIONIST USDA NATURAL RESOURCES CONSERVATION SERVICE COURSE OUTLINE DEFINITION OF A POND OR LAKE TYPES OF PONDS GEOLOGIC CONSIDERATIONS

More information

NPDES - PCSM. National Pollutant Discharge Elimination System Post Construction Stormwater Management Permit Preparation

NPDES - PCSM. National Pollutant Discharge Elimination System Post Construction Stormwater Management Permit Preparation NPDES - PCSM National Pollutant Discharge Elimination System Post Construction Stormwater Management Permit Preparation Jim Pillsbury PE, Kathy Hamilton RLA Engineer s Workshop March 19-20, 2015 WCD 2015

More information

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES SECTION 02215 EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES PART 1 - GENERAL 1.1 DESCRIPTION: This section includes materials, testing, and installation of earthwork for excavations, fills, and

More information

SECTION RIPRAP, BOULDERS, AND BEDDING

SECTION RIPRAP, BOULDERS, AND BEDDING SECTION 31 37 00 RIPRAP, BOULDERS, AND BEDDING PART 1 GENERAL 1.01 SECTION INCLUDES A. The WORK includes excavation, grading, and installation of riprap, boulders, soil riprap, void-filled riprap, and

More information

Erosion & Sedimentation Control Policy

Erosion & Sedimentation Control Policy Issue Date 10/22/2010 Page 1 of 8 Erosion & Sedimentation Control Policy Introduction: Soil erosion is the removal of soil by water, wind, ice or gravity and sediment deposition occurs when the rate of

More information

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

Filter Tube Barriers (Instream)

Filter Tube Barriers (Instream) Filter Tube Barriers (Instream) INSTREAM PRACTICES Flow Control No Channel Flow Dry Channels Erosion Control Low Channel Flows Shallow Water Sediment Control High Channel Flows Deep Water Symbol Photo

More information

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition STANDARD FOR SLOPE PROTECTION STRUCTURES Definition Structures to safely conduct surface runoff from the top of a slope to the bottom of the slope. Purpose The purpose of this practice is to convey storm

More information

Dam Safety Inspection Checklist

Dam Safety Inspection Checklist Dam Safety Inspection Checklist Complete All Portions of This Section (Pre-inspection) Date of Inspection: Name of Dam: EAP: (yes, no) OM&I: (yes, no) File Number: Review Inventory - Highlight missing

More information

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Definitions SWPPP: Storm Water Pollution Prevention Plan BMP: Best Management Practice(s) to control pollution IDNR: Iowa Department

More information

Mike Sarmento Senior Construction Manager Floodplain Management Program Urban Drainage and Flood Control District

Mike Sarmento Senior Construction Manager Floodplain Management Program Urban Drainage and Flood Control District Mike Sarmento Senior Construction Manager Floodplain Management Program Urban Drainage and Flood Control District Today s Objectives Understanding of the Maintenance Eligibility Program (MEP) Get us all

More information

Dry structural excavation is usually done with front-end loaders, bulldozers or backhoes.

Dry structural excavation is usually done with front-end loaders, bulldozers or backhoes. 1.1 Excavation - General Excavation is the removal of all material (including ice, water, etc.) required for the construction of foundations or substructures as indicated on the drawings or as determined

More information

LIPUMAX GREASE SEPARATOR

LIPUMAX GREASE SEPARATOR ACO Passavant Installation guide LIPUMAX GREASE SEPARATOR AUTHOR Kate Jennings DATE COMPLETED 8 August 2016 v14 ACO Polycrete, 134-140 Old Bathurst Road, Emu Plains, NSW 2750 Tel: +61 2 4747 4000 Fax:

More information

P U B L I C H E A L T H P R O T E C T I O N. Ministry of Health and Ministry Responsible for Seniors

P U B L I C H E A L T H P R O T E C T I O N. Ministry of Health and Ministry Responsible for Seniors P U B L I C H E A L T H P R O T E C T I O N Ministry of Health and Ministry Responsible for Seniors Canadian Cataloguing in Publication Data Main entry under title: Proper sewage disposal Rev. 1994 ISBA

More information

SECTION STORM DRAINAGE AND STORMWATER MANAGEMENT

SECTION STORM DRAINAGE AND STORMWATER MANAGEMENT SECTION 322 - STORM DRAINAGE AND STORMWATER MANAGEMENT 322.01 DESCRIPTION Work includes all labor, material and equipment to construct storm drain systems and stormwater management facilities, including

More information

Stormwater Management and Sediment and Erosion Control Plan Review Checklist For Design Professionals

Stormwater Management and Sediment and Erosion Control Plan Review Checklist For Design Professionals Stormwater Management and Sediment and Erosion Control Plan Review Checklist For Design Professionals This Plan Review Checklist for Design Professionals has been developed to aid those who prepare Stormwater

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

901 - TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL

901 - TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL 901.1 DESCRIPTION Install, maintain and remove temporary erosion and pollution control devices as required during the construction of the project. BID

More information

Training on Roads for Water and Resilience

Training on Roads for Water and Resilience Training on Roads for Water and Resilience 1 DRAINAGE FROM UNPAVED ROADS Outline 3 1. 2. 3. 4. 5. 6. 7. Introduction Important considerations Drainage management Surface drainage features Subsurface drainage

More information

Builder s enviro guide

Builder s enviro guide BC3337 Builder s enviro guide Preventing pollution from your building project Find out more: phone Auckland Council on 09 301 0101 or visit aucklandcouncil.govt.nz Contents Why compliance matters 2 The

More information

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment. POND SITE SELECTION AND CONSTRUCTION Uses, Planning, & Design David Krietemeyer Area Engineer USDA-NRCS June 20, 2008 Uses Considerations for Location of Commonly Used Terms Pond A water impoundment made

More information

BIOPOD TM BIOFILTER WITH STORMMIX BIOFILTRATION MEDIA. Inspection and Maintenance Guide

BIOPOD TM BIOFILTER WITH STORMMIX BIOFILTRATION MEDIA. Inspection and Maintenance Guide BIOPOD TM BIOFILTER WITH STORMMIX TM BIOFILTRATION MEDIA Inspection and Maintenance Guide BioPod Biofilter with StormMix Biofiltration Media Description The BioPod Biofilter System (BioPod) is a stormwater

More information

SECTION 1 BIO-INFILTRATION BUMP OUTS (BIBO)

SECTION 1 BIO-INFILTRATION BUMP OUTS (BIBO) SECTION 1 BIO-INFILTRATION BUMP OUTS (BIBO) This guide specification for U.S. applications describes construction of bio-infiltration bump outs (or bioretention ) systems. From the surface down to the

More information

Section [ ] Storm Water Treatment Device

Section [ ] Storm Water Treatment Device PART 1 GENERAL Section [ ] Storm Water Treatment Device 01.01.00 Purpose The purpose of this specification is to establish generally acceptable criteria for Storm Water Treatment Devices (SWTD) that treat

More information

SPECIAL SPECIFICATION 3504 Septic Tank System

SPECIAL SPECIFICATION 3504 Septic Tank System 1993 Specifications CSJ s 3136-01-126, etc. & 0683-01-070, etc. SPECIAL SPECIFICATION 3504 Septic Tank System 1. Description. This Item shall govern for all materials, equipment and labor necessary for

More information

Standard Operating Procedure (SOP) For Sand Filter Basin (SFB) Inspection and Maintenance

Standard Operating Procedure (SOP) For Sand Filter Basin (SFB) Inspection and Maintenance Standard Operating Procedure (SOP) For Sand Filter Basin (SFB) Inspection and Maintenance Douglas County, Colorado 2014 1 TABLE OF CONTENTS ACRONYMS... 3 SFB-1 BACKGROUND... 4 SFB-2 INSPECTING SAND FILTER

More information

Storm Drain Inlet Protection

Storm Drain Inlet Protection Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category

More information

Temporary Watercourse Crossing: Culverts

Temporary Watercourse Crossing: Culverts Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol

More information

Manure Storage for Environmental Management Systems

Manure Storage for Environmental Management Systems WiMStor01 MStor Manure Storage for Environmental Management Systems Key: 1)Low Risk 2)Low-Moderate Risk 3)Moderate-High Risk 4)High Risk Location of Manure Storage Are the manure storage facilities in

More information

DTE Energy St. Clair Power Plant

DTE Energy St. Clair Power Plant DTE Energy St. Clair Power Plant Unit 6 Scrubber Basins CCR Rule Compliance Project Annual Inspection Report - 2017 Project Number: 60546402 June 30, 2017 Prepared by: 27777 Franklin Road, Suite 2000 Southfield,

More information

CARROLL COUNTY SUPPLEMENT TO THE 2000 MARYLAND STORMWATER DESIGN MANUAL VOLUMES I & II

CARROLL COUNTY SUPPLEMENT TO THE 2000 MARYLAND STORMWATER DESIGN MANUAL VOLUMES I & II CARROLL COUNTY SUPPLEMENT TO THE 2000 MARYLAND STORMWATER DESIGN MANUAL VOLUMES I & II Carroll County Bureau of Resource Management May 200 Adopted by Resolution July 200 STORMWATER MANAGEMENT PLAN REVIEW

More information

Anchorplex retaining wall construction guide. Building. Anchorplex. Retaining Wall Systems

Anchorplex retaining wall construction guide. Building. Anchorplex. Retaining Wall Systems Anchorplex retaining wall construction guide Building Anchorplex Retaining Wall Systems Table of Contents and ow to Use This Guide table of contents ow to Use This Guide. 2 About the Anchorplex System.

More information

SECTION WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING

SECTION WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING SECTION 334701 - WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING PART 1 - GENERAL 1.1 DESCRIPTION A. Scope: 1. The Contractor shall provide all labor, materials, tools, and equipment required

More information

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements SECTION 3 DRAINAGE 3-1 General All Drainage plans for proposed development shall be prepared by a Professional Engineer registered in Virginia, except as noted below. Further, their seal and signature

More information

BIG O HDPE TUBING HDPE CORRUGATED TUBING FOR AGRICULTURAL, RESIDENTIAL AND HIGHWAY DRAINAGE INCREASE CROP YIELDS LOWER PRODUCTION COSTS

BIG O HDPE TUBING HDPE CORRUGATED TUBING FOR AGRICULTURAL, RESIDENTIAL AND HIGHWAY DRAINAGE INCREASE CROP YIELDS LOWER PRODUCTION COSTS DRAINAGE SOLUTIONS SINCE 1908 BIG O HDPE TUBING HDPE CORRUGATED TUBING FOR AGRICULTURAL, RESIDENTIAL AND HIGHWAY DRAINAGE INCREASE CROP YIELDS LOWER PRODUCTION COSTS PROTECT FOUNDATIONS IMPROVE HIGHWAY

More information

Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure

Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure ArchCast Bridge 3-Sided Precast Concrete Bridge Structure Installation Manual Salem Location: 749 West Commercial Ave. Salem, IL 62881 (618) 548-1190 countymaterials.com Email: info@countymaterials.com

More information

Converting Temporary Sediment Basins to Permanent Stormwater Detention Ponds in Tennessee

Converting Temporary Sediment Basins to Permanent Stormwater Detention Ponds in Tennessee Converting Temporary Sediment Basins to Permanent Stormwater Detention Ponds in Tennessee Prepared for ASCE-TSPE-ACEC Joint Annual Meeting presentation, Sept. 13-14, 2012, Murfreesboro, TN Abstract Dr.

More information

LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO S3N-R2 AFIN

LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO S3N-R2 AFIN LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO. 0200-S3N-R2 AFIN 32-00042 OCTOBER 12, 2016 LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT

More information