2010 NATIONAL BUILDING CODE
|
|
- Kory Howard
- 6 years ago
- Views:
Transcription
1 2010 NATIONAL BUILDING CODE
2 2010 NBC The 2010 Building and Fire codes will be adopted and in place as of September 1 st, There are many changes to both codes. Due to the number of changes this presentation will not be able to address all aspects but provide only a general overview There are multiple changes to Fire rating, Limiting Distance, allowable opening and construction requirements. A building identical to one built last year, may now have higher requirements in regards to construction. (Combustible or NonCombustible, Fire Ratings, cladding and windows or other openings). The new code makes allowances in regards to what is required for the construction of a building when sprinklers are installed Construction requirements for all building types including houses are lessened when a building includes sprinklers.
3 2010 NBC Care and Detention Occupancies have been changed from 2 classifications to 3 B1 Detention Occupancies include Jails, police stations, prisons and other similar uses B2 Treatment Occupancies include Hospitals, convalescent homes and similar uses B3 Care Occupancies include care facilities w/o treatment, Group homes, Children s custodial homes and similar uses There are many changes to the requirements for Fire Alarms, sprinklers and other ancillary emergency systems. A new section deals with the protection of electrical conductors for emergency equipment. All Smoke detectors in any type of Building must now have a temporal signal, (no beep,beep, beep), be hard wired and have battery backup
4 2010 NBC Smoke alarms are now required in each sleeping room, in a hallway adjacent sleeping rooms and must be hard wired, have a temporal signal and battery back-up For all buildings except detached garages on residential property. Eaves/Soffits may not be closer than 0.45m (1 6 ) from a property line or another building Eaves/Soffits within a 1.2m (4ft) setback from property line or another building May Not have any openings and shall be enclosed by 0.38mm Steel, 12.7mm Gyproc, 11mm plywood, 12.5mm OSB or 11mm Lumber
5 2010 NBC All operable windows in in residential suites (Condo/ apartment) shall be protected by a guard at 3 6 mm high or restricted to a 4 opening unless the window is 3 6 ½ above the floor level or less than 1.8m above grade Exit signs now must be the green pictogram style, the EXIT text is no longer in use and the code now recognizes the use of photo luminescent exit signs in some instances. New Section requirements specific to the Ventilation of Laboratories There are now maximum window allowances for houses that are unsprinkled and within 2m of a property line The requirements for the type of sprinkler system that may be installed, has been lowered for houses and care occupancies with 10 occupants or less
6 2010 NBC - Houses Openings are not allowed within 4ft of a corner of a ICF foundation wall, all openings >900mm (3ft) require a minimum 8 concrete (No openings to top of wall) The code does now carry provisions for foundation walls to 3m in height Non load bearing walls running parallel to joists shall be blocked below with 38x89 mm lumber at 4ft apart Braced wall panels section added to code to provide for minimum bracing and cladding of walls New requirements maximize the number of windows that may be used in the wall of a building that is within 2m of a property line (unless sprinkled)
7 2010 NBC Windows, doors and skylights in houses must now be certified under AAMA/WDMA/CSA 101/I.S.2/A440 North American Fenestration Standard/specification for doors, windows and skylights and be selected as per A440S1-Canadian Supplement to the above standard We are in Zone C U-Factor Minimum = 1.7w/sq.m.k (Metric/SI) Minimum Class is R This is the type of label and the information we will be looking for ensure that your installer does not remove stickers prior to inspection.
8 Housing Minimum performance level for Doors/windows/skylights shall be Class R Exterior wood doors shall conform to Can/CSA and shall meet a Grade 10-Security Level (45mm Solid Core or Rail and stile with 19mm panels) Windows within 2m of grade shall meet requirements for resistance to forced entry New Requirements For House Windows
9 Housing Minimum clear height over ramps and landings shall be 1.95m for dwelling units and 2.05m for all others Bed and breakfast dwellings used as lodging houses with more than 4 bedrooms shall have 45 minute separations between suites Limiting distance (which determines fire rating and construction type) will be doubled for any building wherein the fire department cannot respond within 10 minutes unless the building is Sprinklered Smoke alarms are now required in each bedroom, in a hallway and one on each level and be wired-in, interconnected and complete with a battery back-up Carbon monoxide alarms are required in each bedroom or in each bedroom hallway: they shall be hard wired, interconnected
10 2010 Housing All requirements for Radon must now be met: Health Canada has lowered accepted levels from 800 Bq/m3 to 200 Bq/m3 Perimeter sealing of foundation floors from radon is now required New section dealing with the installation of a sub-floor depressurization system (now required in all dwelling units) Rough in required inlet, outlet and poly (100mm pipe) New requirements for sump pumps and sump pump covers Seal all penetrations
11 2010 NBC - Housing Floors must be anchored to foundation walls as per listing in a new table Prior to a final inspection, the department will require that the form attached to your permit application, verifying minimum standards for plumbing and ventilation be completed and signed by the installer. Dryer vents must be metal and must vent to the outside
12 2010 NBC Secondary Suites The NBC now specifies requirements for secondary suites Secondary suites are allowed to be up to a maximum size of 80m.sq (860sq.ft) and they may not exceed 80% of the Floor area (i.e. A house 1000sq.ft on the main level can have a 800sq.ft suite) An upper level story that shares an entrance with a secondary suite shall have a second entrance/exit If any dwelling containing more than 2 main units (i.e. Duplex) has a secondary suite incorporated it shall be separated from the adjacent dwellings by a firewall (in essence if any combination creates greater than 4 dwelling units, they shall be separated from any other units by a firewall)
13 2010 Secondary Suites Ventilation and heating systems for a secondary suite shall be independent of those in the main living area In a secondary suite in an existing house, separate heating controls shall be provided for each suite The separation between suites no longer requires a 45minute rating This presentation has provided a limited over view of the changes that come into effect with the 2010 National Building Code as of September 1 st, Please be advised that we will be enforcing the Code as of that date, and like you we will be learning some aspects as time moves forward. Hopefully this document will provide you with time to make changes to a project you have planned in the near future. The City of Prince Albert Building Department can be reached at
2010 National Building Code Adoption and Associated Process Changes
Building Inspection City of Moncton 655 Main Street Moncton, NB E1C 1E8 Phone: (506) 856-4375 Fax: (506) 856-4348 Bulletin No. 14 From: Randy Richard Date: February 9, 2015 Subject: 2010 National Building
More informationPLANNING, PROPERTY AND DEVELOPMENT DEPARTMENT. Construction requirements for LOWER LEVEL DEVELOPMENT. in residential dwellings
PLANNING, PROPERTY AND DEVELOPMENT DEPARTMENT Construction requirements for LOWER LEVEL DEVELOPMENT in residential dwellings January 2018 contents GENERAL INFORMATION... 3 BUILDING CODE REQUIREMENTS...
More informationVillage of Glen Ellyn Basement Remodeling Project Guidelines
Village of Glen Ellyn Basement Remodeling Project Guidelines Existing unfinished basement space is often remodeled to create more habitable (living, sleeping, eating, dining) space in a home. Building
More information2003 International Residential Building Code
2003 International Residential Building Code Section R305 Ceiling Height Habitable rooms, hallways, corridors, bathrooms, toilet rooms, laundry rooms and basements shall have a ceiling height of not less
More informationResidential Accessory Structures & Room Additions
Residential Accessory Structures & Room Additions Planning and Development Services Department Building Safety Division 8500 Santa Fe Drive Overland Park, KS 66212 (913) 895-6225 Fax (913) 895-5016 Email:
More informationRESIDENTIAL BUILDING REQUIREMENTS
RESIDENTIAL BUILDING REQUIREMENTS Residential Building Requirements This is an informational booklet with some of the general residential construction requirements taken from the codes adopted by Campbell
More informationBASEMENT FINISH PERMIT AND BUILDING CODE REQUIREMENTS (REVISED 3/6/2018)
BASEMENT FINISH PERMIT AND BUILDING CODE REQUIREMENTS (REVISED 3/6/2018) PERMIT SUBMITTAL CHECKLIST: Signed and completed Building Permit application form. A separate Electrical permit is required from
More informationORDINANCE. APPROVED EMERGENCY: (Yes) (No) VETOED: Date
ORDINANCE AN ORDINANCE OF THE COMMISSION OF KNOX COUNTY, TENNESSEE RESCINDING ARTICLE III. CABO ONE- AND TWO-FAMILY DWELLING CODE, SEC. 10-56, SEC. 10-57 AND SEC. 10-58 AND ADOPTING THE 2006 INTERNATIONAL
More informationACCESSORY STRUCTURE Building permit information For 1 & 2-family dwellings
ACCESSORY STRUCTURE Building permit information For 1 & 2-family dwellings Building Safety Department 400-2 nd Street South St. Cloud, MN 56301 (320) 255-7239 A building permit is required for any accessory
More informationCITY OF CEDAR FALLS DEPARTMENT OF DEVELOPMENTAL SERVICES INSPECTION SERVICES DIVISION PHONE Residential Accessory Structures
CITY OF CEDAR FALLS DEPARTMENT OF DEVELOPMENTAL SERVICES INSPECTION SERVICES DIVISION PHONE - 268-5161 Residential Accessory Structures This information has been compiled for the benefit of any person
More informationTypical Finished Basement Details
Albemarle County, Virginia Typical Finished Basement Details Based on the 2012 Virginia Residential Code Finished basements must be constructed in conformance with these details. For requirements, details
More informationAdministrative Changes
Revised 11/29/06 Knox County Residential Building Codes Significant Changes From The 1995 CABO One And Two Family Dwelling Code To The 2006 International Residential Code All one and two family dwellings
More informationPart 9 deals with all single family dwellings as well as multi family up to 600 m2.
Part 9 deals with all single family dwellings as well as multi family up to 600 m2. 1 2 3 4 The National Research Council develops the national building codes in Canada. The codes are put together based
More informationPENNSAFE BUILDING INSPECTION SERVICES LLC Deck and Roof Cross Section Submittal
PENNSAFE BUILDING INSPECTION SERVICES LLC Deck and Roof Cross Section Submittal Roof Size: Width: Length: Roof Type: Gable: Hip: Shed: Roof Pitch: (check one) Trusses: Rafters: Spacing of Trusses or Rafters:
More informationPENNSAFE BUILDING INSPECTION SERVICES LLC PERMIT APPLICATION
PENNSAFE BUILDING INSPECTION SERVICES LLC PERMIT APPLICATION Permit No. 175 Beaver Drive, P.O. Box 486 DuBois, PA 15801 Phone: 814-375-1111 Fax: 814-375-1117 Toll Free: 855-PENNSAF LOCATION OF PROPOSED
More informationResidential Building Permit Application
City of Twin Falls Building Department 324 Hansen Street East P.O. Box 1907 Twin Falls, ID 83303-1907 208-735-7238 208-736-2256 www.tfid.org PROJECT INFORMATION Project Residential Building Permit Application
More informationBASEMENT FINISH CONSTRUCTION PLANS REFERENCE: 2015 INTERNATIONAL RESIDENTIAL CODE. PERMITS
BASEMENT FINISH REFERENCE: 2015 INTERNATIONAL RESIDENTIAL CODE. PERMITS A construction permit is required. A homeowner may perform the construction work on his own property where he resides, without a
More informationBasement Renovation Guide For Residential Dwellings
1 Development Services Department Building Permit & Inspection Services Basement Renovation Guide For Residential Dwellings This document is a guide for home owners and does not cover all possible conditions.
More informationTruth in Sale of Housing Disclosure Report NOTICE - Read Entire Report Carefully. This is not a Buyer's Inspection!
NOTICE - Read Entire Report Carefully. This is not a Buyer's Inspection! Current Owner Name: FREDDIE MAC Contact: FREDDIE MAC Business/Relationship: Owner Address: C/O 8937 AZTEC DRIVE I declare to the
More informationMinnesota Healthcare Engineers Association, Fall Conference. Bob Dehler, P.E. Engineering Program Manager September 14, 2017
Minnesota Healthcare Engineers Association, Fall Conference Bob Dehler, P.E. Engineering Program Manager September 14, 2017 Categories of Rehabilitation Work in Healthcare Facilities Bob Dehler, P.E. robert.dehler@state.mn.us
More informationResidential Building Inspections
Residential Building Inspections Foundations, Grade Beams, Pile Caps, Foundation Pads 1. All trenches or excavations and formwork shall be in accordance with the size(s) and configuration(s) as per approved
More informationHow to Prepare Your LSE Report
LSE Rule Category Required Documentation Information Comments / Applicable Code Sections/ 10.1 Building Height Provide the Building height in Feet Provide the number of stories above grade Helpful Hints
More informationBuilding Guide. Colorado Chapter of the International Code Council
12/29/16 Building uide Colorado Chapter of the International Code Council How to Use this uide Check with your jurisdiction regarding type of submittal (paper or electronic) and for additional requirements.draw
More informationPage 3 of 12. Inspected Describe. Explained. Health & Safety. Maj. Def. Examiner Notes STRUCTURE N/A. Financial Impact. Impact.
STRUCTURE Foundations * Floor structure * Wall structure * Ceiling structure * Roof structure * Deficiencies in structure * Access Method d Under floor crawlspace/attic * Page 3 of 12 EXTERIOR Exterior
More informationInspection Checklist Residential Building Final July 2016
Inspection Checklist Residential Building Final July 2016 This Inspection Checklist reflects code requirements of the 2015 International Residential Code (IRC), 2015 Uniform Plumbing Code (UPC), 2014 National
More information2018 APPENDIX B BUILDING CODE SUMMARY FOR ALL COMMERCIAL PROJECTS (EXCEPT 1 AND 2-FAMILY DWELLINGS AND TOWNHOUSES)
2018 APPENDIX B BUILDING CODE SUMMARY FOR ALL COMMERCIAL PROJECTS (EXCEPT 1 AND 2-FAMILY DWELLINGS AND TOWNHOUSES) (Reproduce the following data on the building plans sheet 1 or 2) Name of Project: Address:
More informationSPARTANBURG COUNTY BUILDING CODES DEPARTMENT
SPARTANBURG COUNTY BUILDING CODES DEPARTMENT PLAN REVIEW CHECK LIST REQUIREMENTS FOR COMMERCIAL BUILDING PERMITS Plan Review Coordinator Kris Brannon 864-596-3180 366 N. Church St Room 500 Spartanburg,
More informationGeneral Residential Code Requirements
Residential building code review will be based on compliance with the requirements of the Louisiana State Uniform Construction code in accordance with ACT 12 of the 2005 First Extraordinary Session of
More informationWOOD USE IN NONCOMBUSTIBLE BUILDINGS
INTRODUCTION The National Building Code of Canada (NBCC) 1 requires that some buildings be of noncombustible construction under its prescriptive requirements. Its use in certain types of buildings such
More information1 AND 2 FAMILY DWELLING REQUIREMENTS
PLAN REQUIREMENTS: 1 AND 2 FAMILY DWELLING REQUIREMENTS All residential plans including additions and attached garages shall be designed to the current edition of the International Residential Code. Plans
More informationTOWNSHIP OF LOGAN 125 MAIN STREET, PO BOX 314 BRIDGEPORT, NJ FAX
TOWNSHIP OF LOGAN 125 MAIN STREET, PO BOX 314 BRIDGEPORT, NJ 08014 856-467-3626--- FAX 856-467-9260 Application for Certificate of Occupancy for Change of Occupancy Pursuant to Chapter 119 of the Township
More informationRequirements for Additions/Enclosed Deck/Finished Bonus Room/Dormer
Requirements for Additions/Enclosed Deck/Finished Bonus Room/Dormer Architectural prints one (1) set floor plan addressing the following items: o Decay-resistant sill plates o Show how and where combustion
More information10/23/2011. Plan Examination. Plan ExaminationPurpose. Catch problems in advance of construction.
Plan Examination 1 Plan ExaminationPurpose 2 Catch problems in advance of construction. 3 1 Discovery of problems in the field results in higher cost. 4 Can a good plan review eliminate all problems in
More informationRESIDENTIAL BUILDING PLAN REQUIREMENTS
CITY OF MANSFIELD BUREAU OF BUILDING AND CODES 30 NORTH DIAMOND STREET 3RD FLOOR MANSFIELD, OHIO 44902 Phone (419) 755-9688 Fax (419) 755-9453 www.ci.mansfield.oh.us RESIDENTIAL BUILDING PLAN REQUIREMENTS
More informationFast Track Re-Roof Permit Checklist
Fast Track Re-Roof Permit Checklist ADDRESS I will abide by attached City Re-Roofing Building Permit Required Guidelines, including applicable Siding and Roofing Match and Smoke Detector requirements.
More informationUBC. (1997 Edition) (p.1-116) 2-hr. shaft required for
Protection of Shaft Enclosures (Exit Stairs) Protection of Shaft Enclosures (Other Shafts) Comparison on Fire Safety Provisions* (Revised 2/28/03) (S) = Small difference in fire protection, (M) = Moderate
More informationOne and Two Family Additions
One and Two Family Additions An addition to a house, duplex, garage, or an accessory structure requires a building permit prior to performing any construction. Building Department & Permit Office Mon-Fri
More informationThe Inspection Process. Waxhaw N.C.
The Inspection Process In Waxhaw N.C. This information is provided by the Waxhaw Enforcement Division to assist you in the progression of your project. Nothing in this document should be considered "Code"
More informationCONSTRUCTION CODE PERMIT INFORMATION
CONSTRUCTION CODE PERMIT INFORMATION INTRODUCTION The Lebanon County Planning Department is a Pennsylvania Certified 3 rd Party Inspection Agency. The Lebanon County Planning Department is under contract
More informationAGREEMENT CONCERNING EXISTING AS BUILT CONSTRUCTION
AGREEMENT CONCERNING EXISTING AS BUILT CONSTRUCTION Building Permit Number: Date Received: By: I,, as owner of record of the above property, hereby request a permit for and final inspection of the installation
More informationCITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT. Submittal Requirements
CITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT 1 East Franklin Street Phone: 301-790-4163 Third Floor Hagerstown, MD 21740 Fax: 301-791-2650 BUILDING PERMIT APPLICATION FOR RESIDENTIAL ACCESSORY
More informationA HOMEOWNER S GUIDE TO ACCESSORY DWELLING UNITS
L3Y 4X7 A HOMEOWNER S GUIDE TO ACCESSORY DWELLING UNITS Planning & Building Services October 2015 TOWN OF NEWMARKET www.newmarket.ca 35 Mulock Drive buildings@newmarket.ca P.O. Box 328 05-53-5300 ext.
More informationThe better way to build TM. Installation Manual FOUNDATION SIPs & FROST WALLS SIPs
The better way to build TM Installation Manual FOUNDATION SIPs & FROST WALLS SIPs November 2016 PWF FOUNDATION & FROST WALL SIPs Installation Manual Table of Contents Topics General Requirements....................................
More informationCommercial Remodel Permit
Commercial Remodel Permit Zoning requirements Staff recommends always verifying the zoning requirements for your project before deciding to build. Warrensburg has eleven separate zoning districts, each
More informationRESIDENTIAL CONSTRUCTION New Dwellings and Additions
How to Obtain a Building Permit For RESIDENTIAL CONSTRUCTION New Dwellings and Additions MIAMI COUNTY, KANSAS CODE SERVICES DEPARTMENT 201 South Pearl Street, Suite 201 Paola, Kansas 66071-1777 Phone:
More informationBC BUILDING CODE ERRATA
BC BUILDING CODE ERRATA The following changes should be made to print and offline copies of the 2012 BC Codes. The 2012 BC Codes subscription products include these changes. Highlighted text is used in
More informationFEMA P-593 STEP-BY STEP PRESCRIPTIVE RETROFIT FOR CRIPPLE WALL BRACING & ANCHORAGE TO FOUNDATION
INTRODUCTION Objective of provisions: The provisions of IEBC Appendix Chapter A3 are intended to reduce hazard of earthquake-induced damage (IEBC A301.1). These provisions are not intended to eliminate
More informationElko County Building & Safety Division
Elko County Building & Safety Division 540 Court St., Suite 104, Elko, Nevada 89801 (775) 738-6816, Fax (775) 738-4581 www.elkocountynv.net Residential Design Criteria & Checklist One & Two Family Dwellings
More informationCITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application
CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application DATE: / / PERMIT # REQUEST FOR: NEW BUILDING ADDITION REMODEL PLUMBING ONLY ELECTRIC ONLY
More informationWINDOW AND DOOR REPLACEMENT SAMPLE PLAN
To aid in communication between yourself, the inspectors, and the plans examiners, we have prepared this sample plan to assist in the preparations of your plan for window and door replacement. Follow the
More informationBuilding Codes and Ordinances ARC 227
Building Codes and Ordinances ARC 227 Week 6 Fire Resistive Construction 03.02.10 Instructor: Rick Staub, AIA Email: staub@pointonearchitects.com Phone: 860-434-7707 Fire Resistive Construction Passive
More informationHERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW
HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW 27 September 2007 prepared by: J. CHRIS EVANS ARCHITECT 3220 E. Terra Alta Blvd. No. 9 Tucson, Arizona 85716 520.319.8835 evansarch@hotmail.com
More informationContinuing Certificate of Occupancy Pre-Inspection Checklist
Pre-Inspection Checklist INTRODUCTION: This pre-inspection checklist has been produced to assist you in preparing for a Continuing Certificate of Occupancy (CCO) inspection. The inspection criteria and
More informationEach proposed project will be reviewed for compliance with the following codes as applicable.
VILLAGE OF PALATINE DEPARTMENT OF BUILDING AND INSPECTION SERVICES 200 EAST WOOD STREET PALATINE, IL 60067-5339 Telephone (847)359-9042 Obtaining a Residential Building Permit: Submittal Requirements The
More informationRepair or replace section of driveway, approach, or sidewalk that are a trip hazard.
City of Gibraltar Pre-Sale Inspection Report Checklist FLATWORK: Repair or replace section of driveway, approach, or sidewalk that are a trip hazard. EXTERIOR PROPERTY: Fences/Sheds/Retaining walls: Repair,
More informationJC Code & Construction Consultants, Inc. Advanced 2010 FBC Update Ch. 1 to 16
JC Code & Construction Consultants, Inc. Advanced 2010 FBC Update Ch. 1 to 16 Welcome! This course is designed to provide an overview of the most significant changes to the 2010 edition of the Florida
More informationR vertical and horizontal.
CITY OF WENTZVILLE RESIDENTIAL CODE PLAN REVIEW CHECK LIST Items indicated with an X are to be addressed by incorporation into revised plans. A checkmark indicates O.K. Date: Lot # Subdivision: Address:
More informationCHECKLIST Inspecting a Garage
CHECKLIST Inspecting a Garage By Ben Gromicko This section deals with the details of the garage or carport inspection that may be performed. At the end of this section, you shall be able to: describe the
More informationTOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit:
TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION 355-7575 Ext. 395 Needed to Obtain Permit: 1. Building Permit Application, and/or residential plumbing permit application, as applicable, to be
More informationAdvanced Ventilation for Residential applications FBC Res 2010.
Advanced Ventilation for Residential applications FBC Res 2010. Course Description Review of the Residential Ventilation requirements in the Florida Building Code, Residential 2010. I. Introduction Dean
More informationInspection of New One- and Two- Family Dwellings
Building Safety Division 8500 Santa Fe Drive Overland Park, KS 66212 (913) 895-6225 Fax (913) 895-5016 Email: permitservices@opkansas.org Inspection of New One- and Two- Family Dwellings Planning and Development
More informationApplying for Permits to build a new house in Linn County
Planning & Development Linn County, Iowa Building Division Linn County Building Code Residential Guidelines Single Family Dwellings Page 1 of 4 Applying for Permits to build a new house in Linn County
More information1 BASE HOME CONSTRUCTION SPECIFICATIONS: TOWNHOMES 5-13-2015 Note: Specifications noted below may change based on selected options. Verify upgrades from the base specifications with the option sheets and
More informationBuilding Permits A Guide for Homeowners
Building Permits A Guide for Homeowners Why Bother With a Building Permit? Building Permits provide the means for Building Officials to ensure the health, safety and welfare of building occupants. The
More informationTOWN OF SOUTH KINGSTOWN REQUIREMENTS FOR BUILDING PERMITS RESIDENTIAL SINGLE FAMILY
TOWN OF SOUTH KINGSTOWN REQUIREMENTS FOR BUILDING PERMITS RESIDENTIAL SINGLE FAMILY ACCESSORY STRUCTURES (Barn, Garage, Shed) ********************************* BUILDING PERMIT APPLICATIONS FOR ACCESSORY
More informationChapter 4-16 SPECIAL DESIGN STANDARDS FOR TYPE V CONSTRUCTION
Chapter 4-16 SPECIAL DESIGN STANDARDS FOR TYPE V CONSTRUCTION Sections: 4-16-01 PURPOSE 4-16-02 APPLICABLE AREA 4-16-03 CONSTRUCTION AND OCCUPANCY 4-16-04 UPPER BUILDING AREA, HEIGHT, NUMBER OF STORIES
More informationBUILDING PERMIT BASICS
Corey Bingham, Building Official 2930 Tongass Avenue, Ketchikan, AK 99901 Phone: 907.228.4727 Fax: 907.228.8721 Website: www.city.ketchikan.ak.us BUILDING PERMIT BASICS 1. When is a building permit required?
More informationSingle Family Detached home submittal Workbook
1880 Main Street, Centerville, Minnesota 55038 (651) 429-4750 Fax (651) 792-7949 Single Family Detached home submittal Workbook Site Address: Contractor Name: (print) Contractor Phone #: Contractor E-mail:
More informationChapter 2: Foundation
Chapter 2: Foundation Crawlspace [V502.1.2] [V502.1.2] [V502.1.3] Vents. Vents in the crawlspace help keep floor insulation and floor framing dry. Crawlspace vents also reduce the potential for radon buildup
More informationUniversal Design Standards
Universal Design Standards For applications submitted and approved after April 16, 2007 Introduction to Universal Design Universal design is a building concept that incorporates products, general design
More informationFairfax County, Virginia
Fairfax County, Virginia Typical Finished Basement Details Based on the 2009 International Residential Code CONTENTS General Requirements... 2 Emergency Escape and Rescue... 2 Wall Construction... 3 Floor/ceiling
More informationDate Rater Verified. Rater Verified. Slab / Pre-Drywall / Thermal Inspection
Slab on Grade & Basements: A capillary break is installed on top of all footings Slab / Pre-Drywall / Thermal Inspection A minimum of 4" of clean or washed gravel (0.5" diameter or greater) is placed over
More informationApplication for Commercial Plan Review and Building Permit. Address:
City of Warrenton 200 West Booneslick Warrenton, MO 63383 : 636-456-3535 Fax: 636-456-1336 www. war r ent o n- mo.org Application for Commercial Plan Review and Building Permit PERMIT# Purpose: Commercial
More informationA Closer Look Inspection Service 2015 IECC Residential DFW area handout
103.2 Information required on construction documents 1. Designation of the Thermal Building Envelope on the plans 2. Insulation Material and their R Value 3. Fenestration U and SHGC values 4. Area weighted
More informationInterior FRT Wood. References to ICC Building Codes
Interior FRT Wood References to ICC Building Codes Table of Contents International Building Code (IBC) 1 International Residential Code (IRC) 6 International Mechanical Code (IMC) 7 INTERNATIONAL BUILDING
More informationBUILDING PERMIT APPLICATION
Town of Dansville 1487 Day Road Arkport, NY 14807 607-295-7223 http://townofdansvilleny.com/ Page 1 of 5 Date Recd: Fee Pd: How Pd: Recd by: Permit #: BUILDING PERMIT APPLICATION Please review all pages.
More informationRENTAL HOUSING SAFETY PROGRAM INSPECTION CHECKLIST
Rental Property Address: Owner Name: Rental Property Contact (Name & Phone #): Rental Property Registration Number: Inspector: Date and Time of Inspection: Unit # Inspected: Note: A box checked with pass
More informationKITCHEN REMODELS CITY OF MISSION VIEJO BUILDING SERVICES DIVISON 200 CIVIC CENTER, MISSION VIEJO, CA (949)
CITY OF MISSION VIEJO BUILDING SERVICES DIVISON 200 CIVIC CENTER, MISSION VIEJO, CA 92691 (949) 470-3054 KITCHEN REMODELS A permit is required for kitchen remodels that include removal and replacement
More informationSection Asbestos Containment Procedures
Section Cover Page Section 02 82 05 2017-10-01 Use this Section where full containment will be required, or if a Contractor option, may be required, depending on the removal method(s) selected by the Contractor.
More informationThe Uniform Building and Accessibility Standards Regulations
UNIFORM BUILDING AND 1 The Uniform Building and Accessibility Standards Regulations being Chapter U-1.2 Reg 5 (effective April 10, 1992) as amended by Saskatchewan Regulations 102/92, 81/93, 35/94, 23/98
More informationHOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS
St. Louis County Department of Public Works Division of Code Enforcement HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS This guide is intended to provide the homeowner or contractor with the
More informationTC54. for architects & designers. Dimensions Clearances Venting
for architects & designers TC54 Series D Dimensions Clearances enting IMPORTANT This booklet is intended as a basic specification guide for architects, designers and builders. Please refer to the Instruction
More informationFENCE PERMIT APPLICATION
Department of Building, Zoning & Housing 26789 Highland Road Richmond Heights, Ohio 44143-1429 216-383-6312 Fax: 216-383-6319 richmondheightsohio.org FENCE PERMIT APPLICATION LOCATION OF JOB LOT # SUBDIVISION
More informationAKF Group LLC. A. Vernon Woodworth FAIA
AKF Group LLC 780 CMR 9 th Edition: Major Changes AKF T A. Vernon Woodworth FAIA 3/14/17 Credit(s) earned on completion of this course will be reported to AIA CES for AIA members. Certificates of Completion
More informationFormulating a Korea Industrial Standard for light-frame wood construction
Formulating a Korea Industrial Standard for light-frame wood construction Jang, Sang Sik 1, Dong Ho Kim 2 ABSTRACT Light-frame wood construction has been widely recognized by Korean people since it was
More informationINSULATION RETROFIT DESIGN ENERGY SOLUTIONS CENTRE YUKON GOVERNMENT
INSULATION RETROFIT DESIGN ENERGY SOLUTIONS CENTRE YUKON GOVERNMENT MAY 2009 prepared by N. A. JACOBSEN, P.Eng. CIVIL ENGINEERING CONSULTANT Whitehorse, Yukon ENERGY SOLUTIONS CENTRE YUKON GOVERNMENT MAY
More informationCode Requirements for Solar Photovoltaic (PV) Systems for One and Two-Family Dwellings
5 Part RESOURCES AND INFORMATION Understanding the Code Code Requirements for Solar Photovoltaic (PV) Systems for One and Two-Family Dwellings Based on the 2013 California Building Code (CBC), the 2013
More informationSt. Clair County Electrical Code Regulations
St. Clair County Electrical Code Regulations St. Clair County has adopted the 2011 National Electrical Code as amended with the following listed articles as the St. Clair County version of the National
More informationCity of High Point Airport Overlay District Noise Level Reduction Design Standards
City of High Point Airport Overlay District Noise Level Reduction Design Standards Part A. Residential Design Standards for Zone 3 I. NOISE LEVEL REDUCTION (NLR) REQUIREMENT FOR ZONE 3. The City of High
More informationEducational Occupancies such as schools, and day care centers (more than 12 children).
State Fire Marshal Approval Your project may require approval from the Maine Office of the State Fire Marshal. Below is some information regarding Construction Permits and Barrier Free Permits. Other permits
More informationCITY OF CALABASAS RESIDENTIAL PLAN REQUIREMENTS 1 OF 5 8/2017 PLAN INFORMATION
1 PLAN INFORMATION Residential plans must be legible and capable of digital scanning. All sheets shall be the same size and distinctly labeled with a sheet title and number. The minimum dimension of the
More informationZoning- check the zoning on the property you are planning to build on, this can be done at the municipal office.
SINGLE DETACHED DWELLING Before your application can be deemed complete and ready for processing you will need the following: (Please hand in entire application package including this cover sheet) Zoning-
More information2012 IRC Sections R303 R310 Building Planning II
Study Session 3 2012 IRC Sections R303 R310 Building Planning II OBJECTIVE: To develop an understanding of the health and safety criteria of the code, including light and ventilation; minimum room areas
More informationModular Wood Framing Goes Vertical
Modular Wood Framing Goes Vertical By: Troy Bean, P.E., S.E. DCI Engineers January 2013 The Wood Products Council is a Registered Provider with. Credit(s) earned on completion of this program will be reported
More informationDistrict of Barriere A GUIDE TO BUILDING PERMITS
District of Barriere A GUIDE TO BUILDING PERMITS THIS BROCHURE EXPLAINS: When a Building Permit is required Building Application Procedure District of Barriere Review of the Permit Application Additional
More informationCode Requirement for Solar Photovoltaic (PV) Systems - General
City/County of [NAME OF CITY] Department of [NAME OF DEPARTMENT] TOOLKIT DOCUMENT City/County of [NAME OF CITY] Department of [NAME OF DEPARTMENT] Code Requirement for Solar Photovoltaic (PV) Systems -
More informationr e s i d e n t i a l o u t s i d e v i l l a g e c e n t e r
N e w A l b a n y, O h i o r e s i d e n t i a l o u t s i d e v i l l a g e c e n t e r D e s i g n G u i d e l i n e s & R e q u i r e m e n t s s e c t i o n 5 I. Overview This section applies to all
More informationGarage Construction. Permit Guide. Development Center. General Information. Zoning Ordinance Requirements. Building Code Requirements
General Information Site Card. Before starting construction, post the site card (issued by the City) in a front window visible from the street. Miss Dig. Before you dig, call Miss Dig at 800.482.7171 This
More informationNatrona County Development Department 200 North Center Street, Room 205 Casper, WY Phone: Fax:
Natrona County Development Department 200 North Center Street, Room 205 Casper, WY 82601 Phone: 307-235-9435 Fax: 307-235-9436 The purpose of the Natrona County Development Department is to provide necessary
More informationIRC 2012 Key Changes
IRC 2012 Key Changes Overview of changes between the 2009 and 2012 IRC A Webinar Provided by The Pennsylvania Housing Research Center November 4, 2011 Presented by Mike Turns; Associate Director, PHRC