John Hart Generating Station Replacement Project. July 2016 Community Construction Update Report #37

Size: px
Start display at page:

Download "John Hart Generating Station Replacement Project. July 2016 Community Construction Update Report #37"

Transcription

1 John Hart Generating Station Replacement Project July 2016 Community Construction Update Report #37 Prepared by: Stephen Watson, BC Hydro (O) or (C)

2 Project Status Powerhouse cavern. Forming and concrete work underway for the water intake maintenance gate; The 60 metre power tunnel intake shaft (downstream of dam) is complete. Work progressing on the elbow that will connect to the horizontal section of the power tunnel; About 420 metres of the 1,575 metre power tunnel is completed with progress continuing toward the dam; Surge shaft boring just beginning using a raised bore method working from the bottom of the shaft to top. This shaft will be 110 metres deep; About 15% of Phase 1 concrete work complete in the powerhouse. The first phase is structural work, and the second is embedding the turbine and the base of the generator; Main access tunnel will reach the powerhouse by August; About 15% of the 520 metre tailrace tunnel has been excavated; and Special thanks to the 1,100 people who took in the project advancements by bus and the 1,600 people overall who participated in the July 17 annual John Hart project community site event! Unit 3

3 Project Schedule September: Surge shaft boring (from bottom) completed; October: Concrete surface structure for surge tank begins; November: Maintenance gate at upstream side of dam installed; and January: Excavate under the existing John Hart dam. Underground equipment on display at the July 17 John Hart project community site event.

4 Construction Pictures John Hart Dam Area 4 July 26

5 Construction Pictures Cofferdam Area Operating maintenance gate and trash rack works. 5

6 Construction Pictures Downstream Work Area Below John Hart Dam Area The opening of the power tunnel intake shaft (shown on left) drops down 60 metres into an elbow (shown below) connecting to the horizontal section of the power tunnel. When complete water will drop down the shaft and flow through the tunnel to eventually spin the turbines within the underground powerhouse. In the diagram below, the various numbered sections show future blast areas. 6

7 Construction Pictures Power Tunnel 7

8 Construction Pictures Surge Tank Area 8 The existing three white surge towers will be replaced by one mostly underground surge tank. To create the shaft that will provide the same service the towers do, a test hole was drilled downward to join up with the underground power tunnel. Boring equipment was then attached to the drill shaft and has begun to remove the rock upwards.

9 Construction Pictures Powerhouse Cavern July 18 9

10 Construction Pictures Powerhouse Cavern 10

11 Construction Pictures Powerhouse Cavern 11

12 Construction Pictures Powerhouse Cavern Did You Know? The powerhouse cavern rock excavation took 13 months to complete (May 2016), with 485 blasts to remove 60,000 cubic metres of rock enough rock to fill an Olympic-sized swimming pool 24 times. 12

13 Construction Pictures Main Access Tunnel 13 The 6 metre by 9 metre main access tunnel is almost complete.

14 Construction Pictures Tailrace Outlet 14

15 John Hart Project Community Site Event The event started in downtown Campbell River with site tours of the underground portal entrance, John Hart dam, and the interpretive centre area with all the event festivities. Campbell River Mirror July 22 15

16 John Hart Project Community Site Event 16

17 John Hart Project Community Site Event 17

18 John Hart Project Community Site Event 18

19 Environment Update The heat of the summer is welcomed by many including the project s environmental team who see their own unique challenges and opportunities this time of year. Temporary Home: Swallows made nests in some site equipment recently a crane at the tailrace and in lock-blocks at another site. The equipment can t be moved while there are nests and they are regularly monitored by the project s environment team. The birds have now fledged the nests but diligent monitoring continues. Twenty-minute flood: While winter requires regular, ongoing management of rain, managing summer downpours requires adaptations to mitigation measures. A short downpour back in May after a period of dry weather highlighted the need for additional swales and pumps to ensure sediment doesn t reach the river. The new plans are in place and working well. New faces: A summer co-op student has joined the environment team: Mackenzie Kwaksistala is a 4th-year biology student at University of Victoria and will work with the environmental team for July and August helping with monitoring and day-to-day management on site. Mackenzie is originally from Campbell River and is a member of the Wei Wai Kum First Nation. 19

20 People Profile Jennie Gagnon About Jennie Background: Jennie s professional career has centered on accounts payable and receivable, and collections, for a range of companies including some in property management, trucking and mining sectors. Home: Born in Quebec, Jennie graduated high school in Winnipeg. Mining has always been a big part of her family, and that work took her from Quebec to Manitoba, Northern Ontario to Yellowknife and onto Campbell River in 2000 when her husband started at Myra Falls. With eight grandkids now living here too, Campbell River is her home. Hobbies: Along with shopping and baking, Jennie is an avid walker, covering kilometres each day. She s also a sports fan: hockey and the Blue Jays but her favorite athletes are her grandchildren who she watches regularly. One grandson is currently playing on the ASL-JV Dambusters baseball team, who won the Island Championship and are heading to Kelowna for the Provincials. Sharing laughs with friends and family is key as well. Project Responsibility: As Accounts Payable Clerk for ASL-JV, Jennie and her co-workers ensure that suppliers are paid in a timely manner. When she says the cheque s in the mail it s the truth; she really does mail them! She also helps keep the office running booking flights for team members and keeping the office supplies stocked. The John Hart project is huge for a city like Campbell River and it makes me proud to be a part of it!

21 Construction Point Of Interest Each month, BC Hydro and InPower BC will provide a construction fact, occurrence, or situation. Off-site Manufacturing. There is a lot of important work happening in Campbell River and also around the globe. Some of the key components to be manufactured are currently being built in far away places, in preparation to arrive as soon as the local site is ready for them to be installed: Parts of the three turbine/generators by GE (formally Alstom) are being fabricated in Quebec, Italy, Germany, Czech Republic and China; Before manufacturing in other countries, representatives from the project visited and assessed the manufacturing facilities to ensure they were operating at required standards; The individual spiral case and stay assembly ring for each of the three generating units are expected to arrive in September, October and November Inlet valves will follow in the spring of All permanent parts will be at site by end of summer 2017; and Timing of delivery has to be coordinated with the progress of the powerhouse concrete work. Permanent parts have to arrive and be moved underground right away.

John Hart Generating Station Replacement Project. January 2018 Community Construction Update Report #55

John Hart Generating Station Replacement Project. January 2018 Community Construction Update Report #55 John Hart Generating Station Replacement Project January 2018 Community Construction Update Report #55 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

John Hart Generating Station Replacement Project. May 2017 Community Construction Update Report #47

John Hart Generating Station Replacement Project. May 2017 Community Construction Update Report #47 John Hart Generating Station Replacement Project May 2017 Community Construction Update Report #47 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

John Hart Generating Station Replacement Project. November 2017 Community Construction Update Report #53

John Hart Generating Station Replacement Project. November 2017 Community Construction Update Report #53 John Hart Generating Station Replacement Project November 2017 Community Construction Update Report #53 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

John Hart Generating Station Replacement Project. February 2018 Community Construction Update Report #56

John Hart Generating Station Replacement Project. February 2018 Community Construction Update Report #56 John Hart Generating Station Replacement Project February 2018 Community Construction Update Report #56 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

John Hart Generating Station Replacement Project. October 2014 Community Construction Update Report #16

John Hart Generating Station Replacement Project. October 2014 Community Construction Update Report #16 John Hart Generating Station Replacement Project October 2014 Community Construction Update Report #16 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 steve.watson@bchydro.com

More information

John Hart Generating Station Replacement Project. December January 2014 Community Construction Update Report #8

John Hart Generating Station Replacement Project. December January 2014 Community Construction Update Report #8 John Hart Generating Station Replacement Project December 2013 - January 2014 Community Construction Update Report #8 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 steve.watson@bchydro.com

More information

Lower Mattagami River Project

Lower Mattagami River Project Lower Mattagami River Project 2016 Canadian Consulting Engineering Awards Project summary Ontario Power Generation s (OPG) Lower Mattagami River (LMR) project, its largest hydro project in 40 years, added

More information

Annex V Concrete Structures Removal Plan

Annex V Concrete Structures Removal Plan Appendix D Annex V Concrete Structures Removal Plan Figure V1 Lower Granite Sequences of Concrete Removal and Cofferdam Figure V2 Little Goose Sequence of Concrete Removal and Cofferdam Figure V3 Lower

More information

PROJECT BRIEF for the John Hart Generating Station Replacement Project

PROJECT BRIEF for the John Hart Generating Station Replacement Project PROJECT BRIEF for the John Hart Generating Station Replacement Project Issue Date: March 13, 2012 TABLE OF CONTENTS John Hart Generating Station Replacement Project Page ii of 17 1. INTRODUCTION... 3 1.1

More information

Previous Tunnel News

Previous Tunnel News Previous Tunnel News July 2012 Good progress has been made on the tunnel lining and at the intake and outlet sites. At the intake site, which is located at the International Niagara Control Works above

More information

EMERGENCY STORAGE PROJECT San Vicente Pipeline and San Vicente Dam Raise Update Presentation Summary

EMERGENCY STORAGE PROJECT San Vicente Pipeline and San Vicente Dam Raise Update Presentation Summary EMERGENCY STORAGE PROJECT San Vicente Pipeline and San Vicente Dam Raise Update Presentation Summary DATE: Nov. 2, 2005 EVENT: MEETING LOCATION: PRESENTER(S): STAFF RESOURCES: TIME: 7:30 p.m. Lakeside

More information

Introduction. General Description

Introduction. General Description Introduction General Description The 3-Gorges project is a vitally important and backbone project in the development and harnessing of the Yangtze River (Changjiang River). The dam site is situated at

More information

Diaphragm wall Construction

Diaphragm wall Construction Diaphragm wall Construction Diaphragm wall is a continuous wall constructed in ground in to facilitate certain construction activities, such as: a) As a retaining wall b) As a cut-off provision to support

More information

Why The Oak Tree on Allman Avenue is Special

Why The Oak Tree on Allman Avenue is Special Why The Oak Tree on Allman Avenue is Special Some trees are kept as markers or monuments so that visitors can remember certain events or people. The Red Oak tree on the Kuse farm on Allman Avenue is that

More information

Types of Hydropower Facilities

Types of Hydropower Facilities Types of Hydropower Facilities 1 Impoundment Hydropower- uses a dam to store water. Water may be released either to meet changing electricity needs or to maintain a constant water level. 2 Run-of-River

More information

Ingula Pumped Storage Scheme: Project Management Case Study

Ingula Pumped Storage Scheme: Project Management Case Study Ingula Pumped Storage Scheme: Project Management Case Study Colin Logan Project Manager Gibb Engineering & Science South Africa BRAAMHOEK CONSULTANTS JOINT VENTURE Definition of Project Management Planning,

More information

Then the revolving speed of turbine is obtained as 300 r/min based on the specific speed of Ns 208 m-kw.

Then the revolving speed of turbine is obtained as 300 r/min based on the specific speed of Ns 208 m-kw. 11.4 Electromechanical Equipment Generally, a turbine-generator is said larger unit capacity has more economical merit of scale. However, the optimum unit size of turbine-generator is determined in consideration

More information

Coire Glas Pumped Storage Scheme

Coire Glas Pumped Storage Scheme About SSE SSE is one of the UK s largest energy companies and is headquartered in Perth. Our purpose is to provide the energy people need in a reliable and sustainable way. We're involved in producing,

More information

Techno-Economic Assessment Study Rogun HPP. Phase II Considerations. Riparian Consultations

Techno-Economic Assessment Study Rogun HPP. Phase II Considerations. Riparian Consultations Techno-Economic Assessment Study Rogun HPP Phase II Considerations Riparian Consultations July 2014 Engineering and Dam Safety Panel of Experts Presenters: R.Gill (Chair), L.Spasic-Gril, Prof. Dr. E. Todini

More information

COMMUNITY BOARD EIGHT

COMMUNITY BOARD EIGHT SECOND AVENUE SUBWAY PROJECT COMMUNITY BOARD EIGHT PROJECT UPDATE SEPTEMBER 26, 2011 Scope: SECOND AVENUE SUBWAY - PHASE 1 Tunnels from 92 nd St to 63 rd St Stations at 96 th St, 86 th St, 72 nd St and

More information

ANNEXURE-III SALIENT FEATURES OF DUGAR HYDRO ELECTRIC PROJECT. Himachal Pradesh. Latitude. Longitude Nearest Railhead; Udhampur (J&K)

ANNEXURE-III SALIENT FEATURES OF DUGAR HYDRO ELECTRIC PROJECT. Himachal Pradesh. Latitude. Longitude Nearest Railhead; Udhampur (J&K) ANNEXURE-III SALIENT FEATURES OF DUGAR HYDRO ELECTRIC PROJECT Project Location State District River Vicinity Latitude Longitude Nearest Railhead; Udhapur (J&K) Hiachal Pradesh Chaba Chenab River Luj village

More information

THE ÄSPÖ HARD ROCK LABORATORY

THE ÄSPÖ HARD ROCK LABORATORY THE ÄSPÖ HARD ROCK LABORATORY A dress rehearsal for the construction of a final repository for spent nuclear fuel is currently being held deep down in the Swedish bedrock in the Äspö Hard Rock Laboratory

More information

National Hydropower Association Operational Excellence Event Report. Environmental

National Hydropower Association Operational Excellence Event Report. Environmental 1) Submitting Organization: Redacted 2) Name of Preparer, Phone & Email: Redacted 3) Report Number (OE Internal Use): To Be Supplied Later 4) Date & Time of Event: 5) Duration of Event: 6) Functional Area:

More information

Darial Energy LLC. Dariali Hydro Power Plant Construction and Operation Project. Environmental and Social Action Plan, Dariali HPP

Darial Energy LLC. Dariali Hydro Power Plant Construction and Operation Project. Environmental and Social Action Plan, Dariali HPP Darial Energy LLC Dariali Hydro Power Plant Construction and Operation Project Environmental and Social Plan, Dariali HPP Tbilisi 2014 Dariali Energy JSC, the Sponsor, is planning construction and operation

More information

Turbine flow measurement in low-head plants Hydro-Québec's and Corps of Engineers' experience with ASFM: continuous flow monitoring

Turbine flow measurement in low-head plants Hydro-Québec's and Corps of Engineers' experience with ASFM: continuous flow monitoring Turbine flow measurement in low-head plants Hydro-Québec's and Corps of Engineers' experience with ASFM: continuous flow monitoring Gilles Proulx Essais spéciaux de production Expertise de centrale Hydro-Québec,

More information

BOARD BRIEFING DAM SAFETY QUARTERLY REPORT

BOARD BRIEFING DAM SAFETY QUARTERLY REPORT EXECUTIVE SUMMARY The purpose of this report is to update the Capital Projects Committee of the Board of Directors on key dam risk management activities during the period from July 1, 2015 to September

More information

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016 SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri September 21, 2016 CONTENT Introduction Potential in Southeast Asia Challenges in Small Hydro Main Design Steps (Bad) Examples

More information

Project Photo Tour Updated July 15, Tom Blackman Project Lead. Gary Cambre Senior Communications Manager 1

Project Photo Tour Updated July 15, Tom Blackman Project Lead. Gary Cambre Senior Communications Manager 1 Soil Remedial Actions Planned at Middle River Complex - 2015 Project Photo Tour Updated July 15, 2015 Tom Blackman Project Lead Gary Cambre Senior Communications Manager 1 This Project is composed of:

More information

Voith s StreamDiver solution for decentralized low head hydropower plant operations

Voith s StreamDiver solution for decentralized low head hydropower plant operations Voith s StreamDiver solution for decentralized low head hydropower plant operations Stefan Reich Joerg Lochschmidt, Mandar Pachegaokar Voith Hydro Holding GmbH & Co. KG Voith Hydro Holding GmbH & Co. Voith

More information

Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options

Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options A local utility company issued a Request for Proposal to our university s capstone design class for structural improvements

More information

Campbell River System. Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights

Campbell River System. Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights Campbell River System Water Use Plan Revised for Acceptance by the Comptroller of Water Rights Generation Resource Management Nov 21, 2012 v6 Campbell River System Water Use Plan Page i Table of Contents

More information

Finnish Underground Lab

Finnish Underground Lab Finnish Underground Lab Juha Peltoniemi Centre for Underground Physics in Pyhäsalmi University of Oulu cupp.oulu.fi Location of the Pyhäsalmi site Pyhäsalmi mine in Pyhäjärvi town Connections Roads open

More information

BC Hydro Contact: Vancouver Island Community Relations Phone:

BC Hydro Contact: Vancouver Island Community Relations Phone: BC Hydro Contact: Vancouver Island Community Relations Phone: 250 755-7173 Project Team: Trade-off Analyst and Facilitator: Tony Wong, Quintry Management Consulting Inc. Resource Valuation Task Manager:

More information

Long Lake Small Hydro Project

Long Lake Small Hydro Project Long Lake Small Hydro Project Minerals North 2005 29 April 2005 Presented by David Carter Regional Power Inc. Stuart Croft - Summit Power Group Project Location 25 km north of Stewart, in northwest B.C.

More information

Tsunami Countermeasures at Hamaoka Nuclear Power Station

Tsunami Countermeasures at Hamaoka Nuclear Power Station Tsunami Countermeasures at Hamaoka Nuclear Power Station Reference Reactor No. 5 Reactor No. 4 Reactor No. 3 Reactor No. 2 Reactor No. 1 March 16, 2012 2011 Chubu Electric Power Co., Inc. All rights reserved.

More information

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by Construction Technology B (CON4313) Self Assessment Questions: Chapter 1 Prestressed Concrete 1. How does the prestressing of steel tendons in prestressed concrete offer a higher loading capacity than

More information

Funding was provided by the City of New York via the Hudson Yards Infrastructure Corporation and Hudson Yards Development Corporation.

Funding was provided by the City of New York via the Hudson Yards Infrastructure Corporation and Hudson Yards Development Corporation. FACT SHEET GENERAL INFORMATION The project extends the existing No.7 Line subway service via a 1.5 mile extension from Times Square to the new 34 Street Hudson Yards station located at West 34th Street

More information

Ardnacrusha Generating Station

Ardnacrusha Generating Station Ardnacrusha Generating Station Contents Part 1 Electricity for an expanding economy Part 2 The Shannon Scheme Part 3 ESB and hydro-generation power Part 4 How hydro-generation works Part 5 Looking into

More information

WHY THE CHANNEL TUNNEL WAS BUILT

WHY THE CHANNEL TUNNEL WAS BUILT LOCATION MAP WHY THE CHANNEL TUNNEL WAS BUILT As the United Kingdom is an island and has water surrounding it, the ways of going out of the United Kingdom into the rest of Europe and coming back were limited

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

Texas-Sized Challenges

Texas-Sized Challenges Aerial view of the City of Austin s Water Treatment Plant No. 4 in northwest Austin near the intersection of RM 620 and Bullick Hollow Road. cover story Delivering Water Provides Texas-Sized Challenges

More information

10. Why is photosynthesis necessary for biofuel production?

10. Why is photosynthesis necessary for biofuel production? Biomass 1. Describe Biomass. 3. How much did the percentage of energy that biomass gives change from the mid-1800s to today? 4. What replaced biomass as the main source of our energy? 5. How does biomass

More information

Cochise Hall Water Harvesting / Storm water Management - Class Project

Cochise Hall Water Harvesting / Storm water Management - Class Project 1 The modern water harvesting movement is part of a broader change, or paradigm shift, in how water is treated on sites. And that is the shift from viewing water as a problem to seeing it as a resource.

More information

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona, USA. Current Status of the Nuclear Waste Management Programme in Finland 13441

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona, USA. Current Status of the Nuclear Waste Management Programme in Finland 13441 Current Status of the Nuclear Waste Management Programme in Finland 13441 ABSTRACT Kimmo Lehto and Petteri Vuorio Posiva Oy, Olkiluoto, FI-27160 Eurajoki, Finland (kimmo.lehto@posiva.fi) Pursuant to the

More information

SEDIMENT MANAGEMENT PLAN

SEDIMENT MANAGEMENT PLAN SEDIMENT MANAGEMENT PLAN DRAFT October 2012 October 2012 POINTE DU BOIS SPILLWAY REPLACEMENT PROJECT Sediment Management Plan DRAFT Report Prepared for October 2012 October 2012 PREFACE Manitoba Hydro

More information

Hydroelectric power. Made by: Kekoa, Sara, Kupaa and Bree

Hydroelectric power. Made by: Kekoa, Sara, Kupaa and Bree Hydroelectric power Made by: Kekoa, Sara, Kupaa and Bree How it s produced General: Hydroelectric power creates kinetic energy by using water to turn a propeller turbine which turns a metal shaft in a

More information

UNDERGROUND CHARACTERISATION AND RESEARCH FACILITY ONKALO ANTTI IKONEN, MIA YLÄ-MELLA, TIMO ÄIKÄS POSIVA Oy Olkiluoto, Finland

UNDERGROUND CHARACTERISATION AND RESEARCH FACILITY ONKALO ANTTI IKONEN, MIA YLÄ-MELLA, TIMO ÄIKÄS POSIVA Oy Olkiluoto, Finland UNDERGROUND CHARACTERISATION AND RESEARCH FACILITY ONKALO ANTTI IKONEN, MIA YLÄ-MELLA, TIMO ÄIKÄS POSIVA Oy 27160 Olkiluoto, Finland 1. Introduction ABSTRACT Posiva s repository for geological disposal

More information

Who are we and what do we do?

Who are we and what do we do? 1 Who are we and what do we do? Group of young tunnelling engineers Educate current tunnelling engineers Educate potential future engineers - You! We look into tunnelling in the future We network between

More information

6 Preliminary Assessment of Construction Method and Constructability Issues

6 Preliminary Assessment of Construction Method and Constructability Issues 6 Preliminary Assessment of Construction Method and Constructability Issues 6.1 Construction Approach Appendix C includes conceptual designs of the alternatives discussed below. Generally, the conceptual

More information

THE GEOTHERMAL ADVANTAGE

THE GEOTHERMAL ADVANTAGE THE GEOTHERMAL ADVANTAGE reduce your heating and cooling bills by up to 70% for the next 50 years. the benefits of a ground source heat pump Geothermal systems provide heating and cooling from stored solar

More information

Hydropower and Water Resources

Hydropower and Water Resources Hydropower and Water Resources Hydropower and Water Resources The development, planning, design, and construction of hydropower as well as large-scale irrigation schemes and special hydraulic structures

More information

TUG - Institute of Hydraulic Engineering and Water Resources Management 1

TUG - Institute of Hydraulic Engineering and Water Resources Management 1 Large Dams Design, Construction and Performance Gerald Zenz Graz - University of Technology 1 Dam Structures & Geotechnique Design Construction / Observation Operation / Monitoring Cooperation & Transfer

More information

North and South Dams Project Overview

North and South Dams Project Overview North and South Dams Project Overview Construction performed by Barnard Pennecon LP Mobilized in late-2015 Anticipated Completion in mid-2019 Major Features of Our Contract Include: Diversion of Churchill

More information

PROJECT INFORMATION AND SHORTLISTING CRITERIA FOR SCREENING OF CONSULTING FIRM. Tamakoshi V Hydroelectric Project

PROJECT INFORMATION AND SHORTLISTING CRITERIA FOR SCREENING OF CONSULTING FIRM. Tamakoshi V Hydroelectric Project PROJECT INFORMATION AND SHORTLISTING CRITERIA FOR SCREENING OF CONSULTING FIRM 1. PROJECT INFORMATION Intoduction: Tamakoshi V Hydroelectric Project The Tamakoshi-V Hydropower Project is a cascade development

More information

13/05/2016. Introductions of Pipe Roof. Focuses. Application of Rectangular Shield Jacking

13/05/2016. Introductions of Pipe Roof. Focuses. Application of Rectangular Shield Jacking 9-10 May 2016 KL Rectangular shield jacking/tbm and comparison with pipe roof Singapore Society for Trenchless Technology () Focuses Introduction of rectangular shield jacking Comparison of Pipe roof /

More information

Hydropower retrofitted onto existing water infrastructure assets

Hydropower retrofitted onto existing water infrastructure assets Hydropower retrofitted onto existing water infrastructure assets Marco van Dijk Lecturer and Principal Researcher University of Pretoria / Water Research Commission South Africa Presentation Layout How

More information

Dewatering solutions that work

Dewatering solutions that work Dewatering solutions that work COMPLETE RENTALS SERVICES FOR SEWAGE BY-PASS, CONSTRUCTION DEWATERING, FLOOD DRAINAGE, SURFACE IRRIGATION AND MINE DEWATERING Pumps, Mixers, Generators and Accessories Sewage

More information

Keeyask Generation Project. Sediment Management Plan for In-stream Construction

Keeyask Generation Project. Sediment Management Plan for In-stream Construction Keeyask Generation Project Sediment Management Plan for In-stream Construction Manitoba Conservation and Water Stewardship Client File 5550.00 Manitoba Environment Act Licence No. 3107 July 2014 SEDIMENT

More information

Effect of Niche-Tunnel Face Distance and Excavation Time in Tunnel Construction

Effect of Niche-Tunnel Face Distance and Excavation Time in Tunnel Construction Effect of Niche-Tunnel Face Distance and Excavation Time in Tunnel Construction Erion Periku 1 Fan River Hydro Power Project, Aydiner Construction Co., Lezhe, Albania ABSTRACT Estimated time and costs

More information

(this cover page left intentionally blank)

(this cover page left intentionally blank) 4. Siting the Well (this cover page left intentionally blank) 4. Siting the Well Chapter Table of Contents Chapter Table of Contents Chapter Description... 4 Regulatory Requirements Well Siting... 4 Relevant

More information

Coal is obtained from mines. It's a black solid material that must be transported by ships, trains or big trucks to the power plants where it's burnt

Coal is obtained from mines. It's a black solid material that must be transported by ships, trains or big trucks to the power plants where it's burnt Energy Sources Fossil Fuels Coal, Oil and Gas are called "fossil fuels" because they have been formed from the fossilized remains of prehistoric plants and animals. They provide most of the world's total

More information

GEOGRAPHY Grade 7 Term

GEOGRAPHY Grade 7 Term 1 GEOGRAPHY Grade 7 Term 4 2016 Table of Contents Topic: Natural resources and conservation in South Africa Page Content 2 Natural resources 8 Management of resources 11 Water in South Africa 2 NATURAL

More information

Biomass. Coal. 10 Intermediate Energy Infobook Activities. Description of biomass: Renewable or nonrenewable: Description of photosynthesis:

Biomass. Coal. 10 Intermediate Energy Infobook Activities. Description of biomass: Renewable or nonrenewable: Description of photosynthesis: Biomass Description of biomass: Description of photosynthesis: Ways we turn biomass into energy we can use: Who uses biomass and for what purposes: Effect of using biomass on the environment: Important

More information

Grouting Bilfinger Spezialtiefbau GmbH

Grouting Bilfinger Spezialtiefbau GmbH Grouting Bilfinger Spezialtiefbau GmbH Goldsteinstrasse 114 D-60528 Frankfurt Phone: +49 69 6688-345 Fax: +49 69 6688-277 Email: info.spezialtiefbau@bilfinger.com www.foundation-engineering.bilfinger.com

More information

OLMSTED LOCKS AND DAM

OLMSTED LOCKS AND DAM SITE REPORT OLMSTED LOCKS AND DAM IN-THE-WET 1 AS PART OF ONE OF THE FINAL PHASES OF THE OLMSTED LOCKS AND DAM PROJECT, A PUTZMEISTER CONCRETE PLACING SYSTEM IS PLACING UP TO 140,000 CUBIC YARDS (107,308M³)

More information

The water cycle. What is the water cycle? Fact file 2

The water cycle. What is the water cycle? Fact file 2 Fact file 2 The water cycle The water we use at home and at work comes from the natural environment. It is being recycled all the time in what is called the water cycle. What is the water cycle? Water

More information

Report on the completion of HPP POBREG RAIFFEISEN BANK SH.A. ALBANIA. Evaluation and Business Plan Supervision of Hydropower Plants

Report on the completion of HPP POBREG RAIFFEISEN BANK SH.A. ALBANIA. Evaluation and Business Plan Supervision of Hydropower Plants Head Office Augustaanlage 62-64 D-68165 Mannheim Germany Reinhold Metzler Project manager Tel: +49-7531 3620 882 email: metzler@enerm.de RAIFFEISEN BANK SH.A. ALBANIA entecag Consulting & Engineering Bahnhofstr.

More information

The Corporation of The City of London

The Corporation of The City of London The Corporation of The City of London Legislative Health and Safety Requirements The following is a health and safety guide for those providing a tender to assist in determining legislative health and

More information

What is Run-of-river hydro?

What is Run-of-river hydro? The Project: The Corporation of the Village of Slocan submitted a waterpower project application on Springer Creek in May 2010 Engineering & Environmental studies were performed on the project site to

More information

16. The Law of the Big Mo Momentum is the Leader s Best Friend. The two keys for creating momentum are preparation and motivation.

16. The Law of the Big Mo Momentum is the Leader s Best Friend. The two keys for creating momentum are preparation and motivation. 16. The Law of the Big Mo Momentum is the Leader s Best Friend Principles of the Law: All leaders face the challenge of creating change in an organization. Just as every sailor knows that you can t steer

More information

SNOWY 2.0 Feasibility Study Summary

SNOWY 2.0 Feasibility Study Summary SNOWY 2.0 Feasibility Study Summary THE MODERN SNOWY HYDRO WHY DID WE UNDERTAKE THE SNOWY 2.0 STUDY? Snowy Hydro is a dynamic energy company supplying electricity to more than one million homes and businesses.

More information

Tazi Twé Hydroelectric Project. Environmental Assessment Report

Tazi Twé Hydroelectric Project. Environmental Assessment Report Tazi Twé Hydroelectric Project Environmental Assessment Report July 2015 Cover photo credited to Ross Phillips, Golder Associates Ltd. Her Majesty the Queen in Right of Canada, represented by the Minister

More information

Presentation -- Three Gorges Dam (TGD) on the Yangtze River

Presentation -- Three Gorges Dam (TGD) on the Yangtze River Presentation -- Three Gorges Dam (TGD) on the Yangtze River Alex Buchanan Rudy Koester Ali Elahi Michael Jane It is in the Yichang city, Hubei province in China C O N S T R U T I O N S I T E Brief Introduction

More information

A day in the life of Project Fuso. One of my big design goofs on the rig was not preparing it for sub-freezing temperatures.

A day in the life of Project Fuso. One of my big design goofs on the rig was not preparing it for sub-freezing temperatures. A day in the life of Project Fuso One of my big design goofs on the rig was not preparing it for sub-freezing temperatures. You can attribute this gaffe to living in San Diego, home of perfect weather,

More information

Finnish Underground Lab

Finnish Underground Lab Finnish Underground Lab Juha Peltoniemi Centre for Underground Physics in Pyhäsalmi University of Oulu cupp.oulu.fi The CUPP project CUPP Centre for Underground Physics in Pyhäsalmi The purpose is to establish

More information

Dewatering solutions that work

Dewatering solutions that work Dewatering solutions that work COMPLETE RENTALS SERVICES FOR SEWAGE BY-PASS, CONSTRUCTION DEWATERING, FLOOD DRAINAGE, SURFACE IRRIGATION, AND MINE DEWATERING Pumps, Mixers, Generators, and Accessories

More information

TURBINE VENTING FOR DISSOLVED OXYGEN IMPROVEMENTS AT BULL SHOALS, NORFORK, AND TABLE ROCK DAMS

TURBINE VENTING FOR DISSOLVED OXYGEN IMPROVEMENTS AT BULL SHOALS, NORFORK, AND TABLE ROCK DAMS TURBINE VENTING FOR DISSOLVED OXYGEN IMPROVEMENTS AT BULL SHOALS, NORFORK, AND TABLE ROCK DAMS Introduction E. Dean 1, M. ASCE Bethel Herrold 2 George Robbins 3, M. ASCE James C. Carter 4 The Southwestern

More information

Pump storage hydro power plant (PSKW) Reißeck

Pump storage hydro power plant (PSKW) Reißeck Roland Schorn Short description The new pump storage power plant (PSKW) Reißeck II represents an expansion of the already existing group of power plants, Malta and Reißeck/Kreuzeck in Carinthia. The new

More information

Modelling of subsurface vortex vibrations

Modelling of subsurface vortex vibrations Modelling of subsurface vortex vibrations S. J. van Vuuren University of Pretoria, Department Civil and Biosystems Engineering, South Apica Abstract During 2001 the Paris Dam (South Africa) was constructed

More information

Field trips 7, 14, 15. Brenner Base Tunnel

Field trips 7, 14, 15. Brenner Base Tunnel Geo.Alp, Vol. 13 2016 205-214 Field trips 7, 14, 15 Brenner Base Tunnel Ulrich Burger 1, Georg Orsi 1, Roland Arnold 1, Andrea Lussu 1, Heimo Schierl 1 1 Brenner Basistunnel BBT-SE, Amraser Str. 8, 6020

More information

CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES

CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 902 DECEMBER 1983 CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES 902.01 SCOPE 902.02 REFERENCES 902.03 DEFINITIONS TABLE OF

More information

Pipelines and Penstocks Avoiding operational issues throughout the life of your project

Pipelines and Penstocks Avoiding operational issues throughout the life of your project Pipelines and Penstocks Avoiding operational issues throughout the life of your project Presenter Dan Murrer, P.E. 322 East Front Street Suite 200 Boise, ID 83702 Tel. 208.383.6108 Daniel.Murrer@CH2M.com

More information

Muskrat Falls Project Independent Engineer Report & Project Overview April 15, 2014

Muskrat Falls Project Independent Engineer Report & Project Overview April 15, 2014 Muskrat Falls Project Independent Engineer Report & Project Overview April 15, 2014 Take a Moment for Safety 2 Outline 1. Muskrat Falls Project Update 2. Nalcor/Project Oversight 3. Government of Canada

More information

Best Management Practice (BMP) Guidance Manual

Best Management Practice (BMP) Guidance Manual Best Management Practice (BMP) Guidance Manual INTRODUCTION BMP examples in this guide provide ways to meet erosion and sediment control requirements. Best Management Practices are not limited to these

More information

Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan

Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan West Rail Tsing Kwai Tunnel Location of major Tunnel Portal West Rail Tsing Kwai Tunnel Construction Features -

More information

A proposal to realize sustainable development of large hydropower project

A proposal to realize sustainable development of large hydropower project A proposal to realize sustainable development of large hydropower project Yoshifumi NISHIWAKI President, Tokyo Electric Power Services Co., Ltd. (3-3, Higashi-Ueno 3, Taito-ku, Tokyo 110-0015, Japan) E-mail:

More information

3- Hydropower. Energy conversion and hydropower principles

3- Hydropower. Energy conversion and hydropower principles 3- Hydropower The hydraulic power is one of the oldest energy sources of the mankind, namely for irrigation and industry. Nowadays, small hydro is one of the most valuable answers to the question of how

More information

2. TECHNICAL DESCRIPTION OF THE PROJECT

2. TECHNICAL DESCRIPTION OF THE PROJECT 2. TECHNICAL DESCRIPTION OF THE PROJECT 2.1. What is a Combined Cycle Gas Turbine (CCGT) Plant? A CCGT power plant uses a cycle configuration of gas turbines, heat recovery steam generators (HRSGs) and

More information

Integra Gold Receives Underground Exploration Permits for Triangle Zone, Commences Surface Preparation and Provides Project Permitting Overview

Integra Gold Receives Underground Exploration Permits for Triangle Zone, Commences Surface Preparation and Provides Project Permitting Overview P.O Box 11144, Royal Centre #2270-1055 West Georgia Street Vancouver, BC Canada, V6E 3P3 Email: chris@integragold.com FOR IMMEDIATE RELEASE May 27, 2015 TSX-V: ICG, OTCQX: ICGQF www.integragold.com Integra

More information

2012 Joint Water Use Plan for the Capilano and Seymour Watersheds

2012 Joint Water Use Plan for the Capilano and Seymour Watersheds ATTACHMENT 1 2012 Joint Water Use Plan for the Capilano and Seymour Watersheds Greater Vancouver Water District - 33 Joint Water Use Plan for the Capilano and Seymour Watersheds OCTOBER 2012 Greater Vancouver

More information

Liquid Waste Coordination Committee

Liquid Waste Coordination Committee Annacis Island Wastewater Treatment Plant Outfall Project Liquid Waste Coordination Committee FOR LWCC BY KEN MASSÉ. 19 JANUARY 2017 Ken Massé, P.Eng. METRO VANCOUVER April 3, 2017 CONTRACTOR INFORMATION

More information

Preferred Elevated Tank Site

Preferred Elevated Tank Site Preferred Elevated Tank Site Preferred Site No. 3 is on private property owned by Hopewell Developments. Approximately 5 acres of land will be required, including lands required for a permanent access

More information

SALTWATER INTRUSION IN THE BAIE DE RUPERT, JAMES BAY, CANADA

SALTWATER INTRUSION IN THE BAIE DE RUPERT, JAMES BAY, CANADA IAIA17 Conference Proceedings IA s Contribution in Addressing Climate Change 37 th Annual Conference of the International Association for Impact Assessment 4-7 April 2017 Le Centre Sheraton Montréal Canada

More information

PARR. PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC JANUARY 2013

PARR. PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC JANUARY 2013 PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No. 1894 - SC JANUARY 2013 PARR Relicensing Project PARR AND FAIRFIELD LOCATIONS FFPS PARR

More information

Chapter Six{ TC "Chapter Six" \l 1 } System Simulation

Chapter Six{ TC Chapter Six \l 1 } System Simulation Chapter Six{ TC "Chapter Six" \l 1 } System Simulation In the previous chapters models of the components of the cooling cycle and of the power plant were introduced. The TRNSYS model of the power plant

More information

The Dalles East Fish Ladder Auxiliary Water System Emergency Operation Backup System Alternatives Columbia River, Oregon-Washington

The Dalles East Fish Ladder Auxiliary Water System Emergency Operation Backup System Alternatives Columbia River, Oregon-Washington U.S. Army Corps of Engineers, Portland District (Contract No. W9127N-08-D-0006) Task Order No. 0026 DRAFT Brainstorming Meeting Report The Dalles East Fish Ladder Auxiliary Water System Emergency Operation

More information

Tunnel Works. How we got here - Fort Wayne s Consent Decree. Tunnel Works Program Frequently Asked Questions

Tunnel Works. How we got here - Fort Wayne s Consent Decree. Tunnel Works Program Frequently Asked Questions City Utilities operates the largest municipally-owned wastewater collection and treatment system in Indiana. The system serves 161 square miles and includes 1,014 miles of sanitary sewer lines, 365 miles

More information

THE CONSTRUCTION PHASES OF THE NEW NAGA HAMMADI BARRAGE COFFERDAMS

THE CONSTRUCTION PHASES OF THE NEW NAGA HAMMADI BARRAGE COFFERDAMS Ninth International Water Technology Conference, IWTC9 2005, Sharm El-Sheikh, Egypt 355 THE CONSTRUCTION PHASES OF THE NEW NAGA HAMMADI BARRAGE COFFERDAMS Yasser Shawky ( 1), Hala Badawy ( 2) (1) Researcher,

More information

Update On Our Investment in Glasgow Summer/Autumn 2015

Update On Our Investment in Glasgow Summer/Autumn 2015 . Update On Our Investment in Glasgow Summer/Autumn 2015 The transformation of some of Greater Glasgow s most important infrastructure is progressing deep beneath the city streets largely out of sight

More information

ROTARY DRILLING TECHNIQUES LARGE DIAMETER

ROTARY DRILLING TECHNIQUES LARGE DIAMETER INTRODUCTION This paper presents details about large diameter rotary drilling techniques typically employed in the civil engineering industry. These techniques have also been applied to the resources /

More information