OPERATION & MAINTENANCE SPECIFICATIONS MANUAL 05 10

Size: px
Start display at page:

Download "OPERATION & MAINTENANCE SPECIFICATIONS MANUAL 05 10"

Transcription

1 INTRODUCTION AND SCOPE The purpose of hot tapping is to provide a connection to an existing loaded line, where operating conditions so not permit the line to be taken out of service. The main applications of such a connection are for the provision of new sales take-off points, tie-over points, and as part of a stopple application. This section is intended to provide guidance on the safety, job planning, site preparation, installation and testing of hot tap connections that involve a welded connection of a branch to a mainline pipeline, and reinforced by means of a full-encirclement saddle, designed and manufactured in accordance with the requirements of WEI SP Figure 6A and 6B. SAFETY Operational Considerations The installation of steel pressure containing sleeves and hot tap fittings involve the deposition of weld metal directly on the carrier pipe. The installation of such fittings requires that welding be undertaken in such a manner that the possibility of burning through or cracking is eliminated. This may entail a reduction of flow rates (to prevent weld cracking), or a reduction in pressure (to prevent an unsafe condition in the event of burn-through). Care must be taken to ensure that the required flow rate restriction or pressure reduction has been effected prior to the start of the hot tap installation. Flow rate guidelines are presented in section Installation Requirements of this reference, and pressure reduction requirements are presented in the Section 12 Reference 07 - Safe Working Pressure. Orientation and Hazard Identification Once the hot tap site has been identified, the pipeline shall be located and staked by M&NP s Operations group. The Construction group will provide access with support from the Lands group as required. The Construction group shall also ensure that prior to the commencement of site work, the prime contractor conducts an initial, site-specific hazard assessment and continues to do so on a daily basis. All personnel involved in the site work must attend a general orientation that, as a minimum, includes delivery of both the M&NP and contractor s safety programs. All personnel working on site shall also be made aware of planned activities and site hazards on a daily basis. Excavation Excavation of the site shall be shall be undertaken in accordance with the requirements of the M&NP Pipeline Construction Specifications. The site of the excavation shall be away from bends and girth welds. Prior to mechanically excavating the operating pipeline, its location shall be physically confirmed by hand excavation, hydrovac or other approved method that will not mechanically damage the pipe. Mechanical excavation shall not be conducted within 5 meters of the pipeline until it can be seen. During mechanical excavation, both the top and side(s) of the pipeline shall remain in sight at all times. When mechanically excavating within 5 meters of an in-service pipeline, a signal person, who must maintain site of the part of the pipe closest to the excavator Page 1 of 14

2 bucket, shall direct the excavator operator. The excavator shall be operated so that the bucket moves away from the pipe when material is being removed. Ditches intended for entry by personnel shall conform with proper excavating requirements. GENERAL GUIDELINES The ditch shall be 10 meters long and shall have a minimum distance between the ditch wall and the pipe of 1 m. Steps shall be excavated at either end of the ditch to facilitate entry and egress. The ditch bottom shall be flat and horizontal with the bottom of the pipe, except that a bell-hole 2.5 m long and 0.6 m below the bottom of the pipe shall be excavated in the vicinity of the hot tap. If the excavation is in wet or muddy soil, the bell-hole in the vicinity of the hot tap shall be lined with a level platform so that the top of the platform is 0.6 m below the bottom of the pipe. Figure 1 shows the required ditch dimensions. If necessary, a wind/rain/snow shelter shall be erected over the site of the hot tap and shall remain in place if required until branch welding is complete. 1m Steps 1m Steps 10m Figure 1 Ditch Preparation Page 2 of 14

3 JOB PLANNING M&NP Responsibilities The division having responsibilities within M&NP shall consist of: 1. M&NP Design Engineering Group Identify the hot tap location, obtain and provide material parameters, including: o Pipe size, o Wall Thickness, o Grade, o Coating, o Materials Test Reports, and o Specifications for the branch connection and reinforcing sleeve 2. M&NP Construction Group Identify, qualify and retain the contractor/subcontractor that will perform the work; Ensure that regulatory agencies are made aware of the activities to be performed, provide the required information to them and obtain approvals as required; and, 3. M&NP Operations Group Ensure that all work conducted on and in the immediate vicinity of the operating facilities is safe and does not hamper M&NP s ability to maintain continuous uninterrupted service. Perform locates and stake the locations of pipelines Provide required inspection on the work to be performed to ensure it is carried out in accordance with all federal and provincial regulations, corporate policies and commitments; Ensure the work and inspection activities are appropriately documented; Ensure that access to the work site is provided. Site Organization A Contractor s Representative and an M&NP Operations Representative shall be appointed prior to the start of construction. The Contractor s Representative shall be responsible for ensuring that all equipment and material required for the job is available and in good working order. The Contractor s Representative shall also be responsible for organizing the crew(s) and scheduling the day s activities with the M&NP Operating Representative and Gas Control. As an aid to site planning, suggested lists of equipment and personnel are provided in Tables 1 and 2. Table 1 Typical Minimum Personnel Requirements Number of Type of Personnel Personnel 2 Welders 2 Welders Helpers 1 NDT Technician 2 Pipe Fitters 1 Crane or Picker Truck Operator 2 Labourers Page 3 of 14

4 Hot Tap Manual Table 2 Typical Minimum Equipment Requirements Number of Type of Equipment Units 1 Crane or Picker Truck 2 Welding Machines 1 NDT Unit 2 Oxy-acetylene sets 2 Spare acetylene bottles 1 Nitrogen bottle 4 Fire extinguishers 2 Hydraulic jacks 2 10 m length of chain 2 Power grinders 2 Power brushes 1 Pyrometer 1 Electrode hot box The Contractor shall prepare a Hot Tap Manual to ensure that the hot tap is performed in strict adherence with this section, M&NP Operation & Maintenance Specifications Manual, as well as the Contractor s Specifications. The purpose of the Hot Tap Manual is to collect all the above specifications and practices into one document. As a minimum, the Hot Tap Manual shall contain the following documents: M&NP Practice Installation of Hot Tap Connections (this document); Welding Procedure Specification; Welding Procedure Qualification Report; Contractor s Relevant Safety Procedures; Regulatory Permits (if any); Contractor s Tapping Procedure (in conformance with the Tapping Machine Manufacturer s Recommendations); Pipeline Technical Data and Maps (location, pipe diameter, pipe grade, pipe wall thickness, operating pressure, flow rate, coating type, mill test reports); and, Key Personnel Contact Information Scheduling of the hot tap installation shall be coordinated between the Contractor s Representative and the M&NP Company Representative along with M&NP s Gas Control Department. Page 4 of 14

5 SITE PREPARATION Pipe Preparation The coating shall be removed to allow for the necessary NDE work to be carried out, and proper fit-up of the fittings. After removal of the coating, the pipe surface shall be inspected to locate the seam weld. It is not permissible to weld a branch stub over an ERW seam. It is only permissible to weld a branch stub over a double submerged arc welded seam if the seam is positioned as indicated in Figure 2. Hot Tap Cutter A Longitudinal Seam 1/2 A 1/2 A Unacceptable Long Seam Location Acceptable Long Seam Location Figure 2 Acceptable Seam Orientation For Tapping Into DSAW Pipelines Page 5 of 14

6 The area on the mainline upon which the welding shall be performed during the installation of the hot tap shall be ultrasonically examined to determine the wall thickness and the presence of laminations that would preclude hot tapping in that location. Ultrasonic inspection shall be undertaken in accordance with the requirements of O&MSM Section 09 Reference 07 - Ultrasonic Measurement Testers T-MIKE-E. Pipe seam welds shall be radio graphed in accordance with the requirements of M&NP s Pipeline Construction Specifications. Where the pipeline upon which the hot tap weld is to be completed contains laminations, unacceptable pipe seam defects, or pipe body defects, an alternate location shall be chosen. Non-destructive examination shall be continued until a sound site has been located for the hot tap. Determination of Carbon Equivalent The carbon equivalent of the pipeline being welded shall be determined. Where the pipe can be correlated to a mill test report by means of pipe location records, the carbon equivalent shall be determined by referring to the appropriate mill test record. Otherwise, pipe filings shall be obtained for analysis. Carbon equivalence shall be determined in accordance with the requirements of O&MSM Section 12 Reference 06 - Detection of Carbon Equivalency. The approved Welding Procedure shall be referenced to determine whether the carbon equivalent of the pipe is within the qualified range and to determine whether any flow reduction is necessary during in-service welding, given the carbon equivalent of the mainline pipe. If the carbon equivalent is outside the range qualified in the approved hot tap welding procedure, or if the required flow reduction cannot be achieved, then another pipe joint shall be selected. Pipe Seam Preparation After all nondestructive inspection and carbon equivalent testing has been conducted and the candidate pipe accepted, any weld reinforcement associated with the presence of a double submerged arc pipe seam shall be ground flush with the base metal throughout the length of the hot tap fitting. INSTALLATION REQUIREMENTS Welding Procedure Qualification and Limitations Welding procedures to be used for welding on live lines shall be qualified in accordance with the requirements of CSA Z662. The cooling rate at which the welding procedure was qualified must be equal to or more severe than the cooling rate experienced on the pipeline to be welded. In general, this will be the case for any flowing gas condition provided that the welding procedure was qualified while water was flowing through the qualification pipe. In order to confirm that this is the case, the heat sink capacity of the pipeline to be welded can be compared against the heat sink capacity that was recorded during the qualification of the welding procedure. 1 Heat Sink Capacity Test Method The cooling rate experienced during the qualification of a welding procedure must be greater than the cooling rate of an operating pipeline if that welding procedure is to be used to weld onto that particular pipeline while it is 1 Development of Simplified Cooling Rate Models For In-Service Gas Pipelines Pipeline Research Committee International Project , Cola, M.J., Keifner, J.F., Fischer, R.D., Bubanek, T.A., Jones, D.J., and Bruce, W.A., July, Page 6 of 14

7 operating. In order for this to be the case, the average T , as defined in the step-by-step procedure (below) must be greater for the operating pipeline than in the test pipe that was used to qualify the welding procedure. The Heat Sink Capacity Test Method is described below. The equipment necessary to carry out this test is as follows: Chalk or soap stone; Acetylene Torch (with rosebud tip); Digital Contact Thermometer/Temp Sticks; Stopwatch The procedure for determining the heat sink capacity is as follows: 1. Determine the direction of flow for the contents of the pipeline. 2. Using chalk or soapstone, scribe three 50 mm diameter circles approximately 30 cm apart on both sides of the pipe. 3. Starting with the downstream circle, use the acetylene torch and quickly heat the entire region within the circle to 300 o C using a circular motion. The maximum temperature should not exceed 325 o C. 4. After attaining a temperature of between 300 o C and 325 o C, remove the acetylene torch and apply the contact thermometer to the center of the circle. 5. While holding the thermometer in contact with the pipe, measure with the stopwatch the time required for the temperature to fall from 250 o C to 100 o C. This is the T time for that particular spot. 6. Repeat steps 3, 4, and 5 on the next untested upstream circle on the opposite side of the pipe. If the pipe is still warm, wait until the pipe returns to its normal operating temperature. 7. Once all the measurements are complete, determine the average T time from all the recorded readings. Welder Qualification Welders shall be qualified in accordance with the requirements of CSA Z662. Welding Consumables The use of low hydrogen welding consumables is mandatory for all passes of all welds that are conducted on inservice pipelines. Once removed from their hermetically sealed packages, all low-hydrogen electrodes must be held at a temperature of 100 o C to 150 o C until they are used. If any low-hydrogen electrode is removed from its holding oven for a period of more than four hours, it shall be re-baked at 350 o C to 425 o C. Welded Installation Requirements Installation of Reinforcing Ring When the outside diameter of the branch pipe is equal to or greater than ½ the outside diameter of the mainline pipe, a reinforcing ring should be welded to the mainline pipe. This will prevent excessive deformation from occurring in the coupon during the cutting process, and will facilitate the retrieval of the coupon. The reinforcing ring should be no longer than 50 mm, and shall be made of pipe whose outside diameter is the next nominal pipe diameter smaller than the inside diameter of the cutter. The reinforcing ring shall be centered on the pilot guide, and welded in place utilizing the approved in-service welding procedure. Page 7 of 14

8 Preparation of Branch Stub The branch stub shall be pre-tested in accordance with the requirements of CSA Z662 Clause 8, and then contoured to fit the mainline pipe utilizing one of the following methods: By hand; By using templates; or, Machine cut on a profiler Regardless of what method is used to contour the branch stub, measurements must be taken to ensure that the branch is contoured to fit square and center to the mainline, and once square and center, the branch must be level on the face. Prior to the squaring of the branch stub, the pipe longitudinal seam shall be radiographed in accordance with the requirements of M&NP s Pipeline Construction Specifications, and if it passes the examination, any weld reinforcement shall then be ground flush with the base metal. The Branch must be perfectly centered on the mainline, at exactly right-angles to the mainline, and perfectly level coming off the mainline. The method to be used for lining up the branch is outlined in Figure 3. After the branch has been fitted to the mainline pipe, spacer tabs shall be welded to the contoured (i.e., fishmouth ) end of the branch and the mainline pipe. Welding is necessary, since the spacer tabs may fall out during preheating, resulting in misalignment of the branch. The spacer tabs shall all have thicknesses that are equal to the root opening specified in the approved welding procedure, and shall be placed at the 12:00, 3:00, 6:00, and 9:00 positions. Once this is complete, the squareness of the branch shall once again be checked in accordance with the requirements of Figure 3 before the branch can be considered to be ready for welding, in accordance with the requirements of the Welding Consumables section. If misalignment occurs during preheating, it may be necessary to secure the branch to the mainline pipe by means of a chain and hydraulic jack once the branch has been squared. Page 8 of 14

9 #4: Equal Distances B2 Branch Line-Up Procedure A1 B1 A2 1. Level on side of Branch Pipe 2. Level on Face of Branch Pipe 3. Branch Pipe Square to Run Pipe 4. Distances to Center Pin A1 and A2 Equal: B1 and B2 Equal Top view #2: Level #1: Level C L #3: Branch Square to Mainline Cross-sectional sideview Projected sideview Figure 3 Branch Line-Up Procedure Page 9 of 14

10 Welding of Branch Welding of the branch shall be completed in accordance with the requirements of the approved in-service welding procedure qualified in accordance with the requirements of the Welding Procedure Qualifications and Limitations section. If gas flow rate modifications are required to ensure that the heat sink capacity of the mainline is below that which occurred during the qualification of the approved in-service welding procedure, arrangements should be made with Gas Control to reduce the flow rate to an acceptable value prior to commencement of welding. Preheat shall be checked before each arc is struck. After the branch is in position, four substantial tacks, placed in pairs at opposite sides of the pipe, and separated from one another by 90 o are required to hold the branch in position. To minimize distortion and possible misalignment, it is important that the welder complete the weld in such a manner that they are always welding opposite quadrants. The welding sequence shall be in accordance with the requirements of Figure 4. During welding, it is critical that the same amount of filler metal is applied in all four positions indicated in Figure 4 at any given point in time. To further assist in minimizing distortion, it is recommended that an internal clamp should be placed inside the branch until welding is complete. Once welding has been competed, the area inside the branch must be clear of all foreign material (slag, sand, etc.) to prevent damage to the cutter. Page 10 of 14

11 12 O clock Hot Tap Branch 9 O clock 3 O clock 6 O clock Figure 4 Hot Tap Branch Installation Welding Sequence Page 11 of 14

12 Installation of Reinforcing Sleeve The following procedure shall be used when installing reinforcing sleeves: 1. The portion of the pipeline on which the split sleeve is to be installed, including the branch weld area shall be coated with an approved coating system. The area of the branch where the sleeve-to-branch weld will be completed should be cleaned, but not coated. 2. The open neck section of the sleeve shall be installed first, and then the back of the sleeve shall be installed. The two halves shall be brought together as tightly as possible using chains and hydraulic jacks. The gap between the two halves of the sleeves shall be adjusted so that it is even along its length on each side of the sleeve. Also, the gap between the outlet of the sleeve and the branch shall be evenly spaced around the circumference of the branch. 3. The two halves of the sleeve shall be welded together using an approved welding procedure. Welding of the two halves shall be accomplished with either a backing bar or by means of lap bars to prevent the root bead from damaging the pipe. To minimize distortion, each welding pass shall be deposited in accordance with the sequence shown in Figure The outlet of the split sleeve shall be fillet welded to the branch pipe once the longitudinal welds have been cooled. Page 12 of 14

13 Mainline Pipe Spli Sleev Sequence 2 Sequence 2 Sequence 4 Sequence 4 Sequence 5 Branc Pip Sequence 5 Sequence 3 Sequence 3 Sequence 1 Sequence 1 Plan View Progression of Welding Passes Welding shall be completed by depositing one pass at a time, starting at t location, and then progressing to the Sequence 2, Sequence 3, Sequence 4 and Sequence 5 locations before beginning the next pass. pass. Figure 5 Sequence for Welding Longitudinal Seams of Split Sleeve Reinforcing Tee Page 13 of 14

14 Nondestructive Testing Requirements Qualification of NDT Technicians Nondestructive inspection of welds shall be performed by personnel who: a) Are qualified to at least Level II of CGSB Standard CAN/CGSB in the applicable inspection method; and, b) Have demonstrated their ability to interpret indications correctly in accordance with the guidelines of Canadian Association of Petroleum Producers Recommended Practice for Qualification of Technicians for Nondestructive Examination of Pipeline Full Encirclement Fitting Fillet Welds to Identify Cracks. Preliminary MPI Inspection Nondestructive testing of the branch-to-carrier pipe weld and the sleeve outlet-to-branch pipe weld shall not commence until a period of 48 hours has elapsed since the completion of the weld. Once this period of time has elapsed, the entire circumference of the weld shall be inspected using magnetic particle inspection, using wet fluorescent techniques in accordance with the requirements of ASME Boiler and Pressure Vessel Code, Section V, Article 7. Ultrasonic Inspection Ultrasonic inspection shall be conducted on the entire circumference of the branch-to-mainline weld in accordance with the requirements of ASME Boiler and Pressure Vessel Code Section V Article 5. The weld shall be inspected from both the branch and mainline sides, utilizing a minimum of two shear wave probes, having angles of 45 and 70 degrees, and having probe frequencies of 2 MHz. PRESSURE TESTING Once nondestructive inspection has been completed in accordance with the requirements of the Nondestructive Testing Requirements section, and prior to starting the hot tap, the tapping machine, fittings, and hot tap valve shall be leak tested using nitrogen. The leak test shall be conducted with the boring bar extended and the pilot touching the pipe. During the leak test, nitrogen shall be injected through the purge valve on the tapping machine, which pressurizes the branch fitting, hot tap valve, and tapping machine adaptor. Unless a detailed engineering assessment indicates otherwise, the test pressure shall not exceed 60 percent of the operating pressure in the line at the moment of test. After pressurizing, all mechanical and welded joints shall be tested for soundness by means of a soap test. The tapping may not proceed unless the assembly is leak-free. TAPPING PROCEDURE Hot tapping shall be undertaken in accordance with the Contractor s approved procedure, and in accordance with the hot tap equipment manufacturer s recommended practice. Prior to undertaking the tapping procedure, the tapping equipment shall be checked to ensure that it is in good working order. Consideration shall be given to completing the tapping operation while the branch area is pressurized with nitrogen to a pressure equal to the current operating pressure of the pipeline. This will reduce or eliminate any pressure differential across the pipeline wall while the cutting operation is being conducted. Page 14 of 14

Pipeline Systems PIP PLSC0013 Non-Destructive Examination of ASME B31.4 and B31.8 Metallic Pipelines

Pipeline Systems PIP PLSC0013 Non-Destructive Examination of ASME B31.4 and B31.8 Metallic Pipelines February 2017 Pipeline Systems PIP PLSC0013 Non-Destructive Examination of ASME B31.4 and B31.8 Metallic Pipelines PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort to minimize the cost of process

More information

EQT MIDSTREAM DESIGN AND CONSTRUCTION MANUAL DESIGN STANDARD WELDING AND JOINING 3.4 HOT TAP AND BRANCH CONNECTIONS Total Pages: 13

EQT MIDSTREAM DESIGN AND CONSTRUCTION MANUAL DESIGN STANDARD WELDING AND JOINING 3.4 HOT TAP AND BRANCH CONNECTIONS Total Pages: 13 Table of Contents Scope... 845 References... 845 Governmental... 845 EQT Midstream Publications... 845 Industry Standards... 846 Computer Programs... 846 1 Manufactured Branch Connections... 846 1.1 Extruded

More information

WELDING PROCEDURE SPECIFICATION. Shielded Metal Arc Welding-SMAW

WELDING PROCEDURE SPECIFICATION. Shielded Metal Arc Welding-SMAW WELDING PROCEDURE SPECIFICATION Shielded Metal Arc Welding-SMAW WPS Number: WPS-SMAW-CS Revision: 0 Company Name & Address ABC WELDING & FABRICATING 123 WeldProc Boulevard Toronto, ON A1B 2C3 CWB Approval

More information

INSPECTION AND TEST. PROCEDURE Total Page 13

INSPECTION AND TEST. PROCEDURE Total Page 13 PROCEDURE Total Page 13 Client : Project Name: P/O No. : Item No. : 3 2 1 0 FOR APPROVAL Rev Description Date Prepared By Checked By Approved By PROCEDURE Page 1 of 8 1. General 1.1 Scope This specification

More information

INSPECTION OF FIELD WELDING

INSPECTION OF FIELD WELDING INSPECTION OF FIELD WELDING Objective Types of Projects Involving Welding Common Welding Terms & Symbols Welder Qualifications Common Welding Requirements Welding Inspection Types of Projects Involving

More information

Accreditation of Hot Tap Organizations

Accreditation of Hot Tap Organizations Accreditation of Hot Tap Organizations TSSA Guide for Survey Teams Technical Standards & Safety Authority Boiler & Pressure Vessels Safety Division 3300 Bloor Street West 14 th Floor, Centre Tower, Etobicoke,

More information

Welding of Pipelines and Related Facilities API STANDARD 1104 TWENTY-FIRST EDITION, SEPTEMBER 2013

Welding of Pipelines and Related Facilities API STANDARD 1104 TWENTY-FIRST EDITION, SEPTEMBER 2013 Welding of Pipelines and Related Facilities API STANDARD 1104 TWENTY-FIRST EDITION, SEPTEMBER 2013 Special Notes API publications necessarily address problems of a general nature. With respect to particular

More information

CONSTRUCTION SPECIFICATION FOR STRUCTURAL STEEL

CONSTRUCTION SPECIFICATION FOR STRUCTURAL STEEL ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 906 FEBRUARY 1993 CONSTRUCTION SPECIFICATION FOR STRUCTURAL STEEL 906.01 SCOPE 906.02 REFERENCES 906.03 DEFINITIONS TABLE OF CONTENTS 906.04 SUBMISSION

More information

NAPCA Workshop August 19, 2010 Houston, Texas Kenneth Y. Lee Office of Pipeline Safety

NAPCA Workshop August 19, 2010 Houston, Texas Kenneth Y. Lee Office of Pipeline Safety Pipeline Construction Challenges NAPCA Workshop August 19, 2010 Houston, Texas Kenneth Y. Lee Office of Pipeline Safety PHMSA Mission To ensure the operation of the Nation s pipeline transportation system

More information

Inspection and Welding Repairs of Pressure Vessels

Inspection and Welding Repairs of Pressure Vessels Inspection and Welding Repairs of Pressure Vessels BY S. V. GUPTE B.E., D.M.E. ASNT LEVEL III - RT,MT,PT,VT PRESSURE VESSEL INSPECTOR (API 510), (CCOE) PAINT AND COATING INSPECTOR (NACE INDIA) LEAD AUDITOR

More information

Manual. Standards WOC HSE WOC LP. 1 tel) ( W. McIntosh. WO Executive Vice President Operations DOCUMENT NO: WOC-HSE-ST Section H003 Hot Tapping

Manual. Standards WOC HSE WOC LP. 1 tel) ( W. McIntosh. WO Executive Vice President Operations DOCUMENT NO: WOC-HSE-ST Section H003 Hot Tapping 1_91,,(16,.. r - A. 4 On. c WOC LP & EP Department WOC HSE Standards Manual DOCUMENT NO: WOC-HSE-ST-0001 Section H003 Hot Tapping REV ISSUE PREPARED BY REVIEWED BY APPROVED BY ISSUE DATE 0 Issued for Use!.1v/A

More information

THE TECHNICAL STANDARDS AND SAFETY ACT, 2000, S.O. 2000, c. 16 ( the Act ) and

THE TECHNICAL STANDARDS AND SAFETY ACT, 2000, S.O. 2000, c. 16 ( the Act ) and TECHNICAL STANDARDS & SAFETY AUTHORITY 14 th Floor, Centre Tower 3300 Bloor Street West Toronto, Ontario Canada M8X 2X4 IN THE MATTER OF: THE TECHNICAL STANDARDS AND SAFETY ACT, 2000, S.O. 2000, c. 16

More information

QC Inspection and Qualification Procedure- TX-EDU-VT-1-07, Revision # by Richard J DePue, Supersedes IW-VT-1 Visual Inspection Procedure

QC Inspection and Qualification Procedure- TX-EDU-VT-1-07, Revision # by Richard J DePue, Supersedes IW-VT-1 Visual Inspection Procedure 1.0 Scope: QC Inspection and Qualification Procedure- TX-EDU-VT-1-07, Revision #6 03-04-2016 by Richard J DePue, Supersedes IW-VT-1 Visual Inspection Procedure The purpose of this procedure is to define

More information

Item 448 Structural Field Welding

Item 448 Structural Field Welding Item 448 Structural Field Welding 1. DESCRIPTION 2. MATERIALS Field-weld metal members using the shielded metal arc or flux cored arc welding processes. Provide electrodes for shielded metal arc welding

More information

INSULATED JOINTS. Monolithic Joints for Electrically Isolating Pipelines

INSULATED JOINTS. Monolithic Joints for Electrically Isolating Pipelines INSULATED JOINTS Monolithic Joints for Electrically Isolating Pipelines INSULATED JOINTS TUBE TURNS INSULATED JOINTS are a pre-fabricated, non-separable, union used to isolate specific sections of pipelines

More information

Canadian Welding Bureau Comparative Review AWS D1.1 vs CSA W47.1 & CSA W59

Canadian Welding Bureau Comparative Review AWS D1.1 vs CSA W47.1 & CSA W59 Comparative Review Canadian Bureau Comparative Review The Similarities and Differences This document summarizes the similarities and key difference in the requirements between welding standards published

More information

IGS-M-PL-033(1) April Approved مصوب IGS. Hot Tapping Split Tee. Fax:(9821)

IGS-M-PL-033(1) April Approved مصوب IGS. Hot Tapping Split Tee. Fax:(9821) IGS-M-PL-033(1) April. 2016 Approved مصوب شركت ملي گازايران مديريت پژوهش و فنĤوري امورتدوين استانداردها IGS مشخصات فني خريد اتصال سه راهي انشعاب گرم Hot Tapping Split Tee Fax:(9821)-8487-5032 براي استفاده

More information

SYLLABUS FOR SIX MONTHS - FULL TIME CERTIFICATE COURSE IN WELDING AND FABRICATION. Effective From :- UNDER DEVELOPMENT.

SYLLABUS FOR SIX MONTHS - FULL TIME CERTIFICATE COURSE IN WELDING AND FABRICATION. Effective From :- UNDER DEVELOPMENT. SYLLABUS FOR SIX MONTHS - FULL TIME CERTIFICATE COURSE IN WELDING AND FABRICATION Effective From :- UNDER DEVELOPMENT Prepared by: Curriculum development cell Institute of Research Development & Training,

More information

METHOD STATEMENT FOR PIPE WELDING WORKS

METHOD STATEMENT FOR PIPE WELDING WORKS METHOD STATEMENT FOR PIPE WELDING WORKS Introduction This Method statement describes in detail the welding process for pipe work and the welder s qualification test procedures. This includes addressing

More information

AASHTO/AWS D1.5M/D1.5:2008. Table of Contents

AASHTO/AWS D1.5M/D1.5:2008. Table of Contents Table of Contents Personnel...v Foreword...ix List of Tables... xviii List of Figures...xix List of Forms...xxi 1. General Provisions...1 1.1 Application...1 1.2 Base Metal...1 1.3 Welding Processes...1

More information

QUALITY ASSURANCE MANUAL FOR APPLICATORS OF ELASTOMERIC SHEET LININGS

QUALITY ASSURANCE MANUAL FOR APPLICATORS OF ELASTOMERIC SHEET LININGS QUALITY ASSURANCE MANUAL FOR APPLICATORS OF ELASTOMERIC SHEET LININGS 1.0 Purpose To establish a recommended quality assurance program for applicators of elastomeric sheet linings. 2.0 Scope This bulletin

More information

QUALIFICATION TESTING OF FIELD WELDERS

QUALIFICATION TESTING OF FIELD WELDERS Page 1 of 9 Oklahoma DOT Materials & Testing December 5, 2003 (Updated to Reference 2009 Specifications 11/26/2012) (Added paragraph to the bottom of Roles and Responsibilities section. 11/14/2017) Publication:

More information

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS - June 2013 Addendum GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS SUBSECTION "A" : GENERAL RULES SUBSECTION "B" : CLASS 1 COMPONENTS SUBSECTION "C" : CLASS 2 COMPONENTS SUBSECTION "D" : CLASS

More information

Use of Underwater Dry Welding for In Situ Repair to Offshore Structures. Elleftheria Deligeorges; Jai Tulsi

Use of Underwater Dry Welding for In Situ Repair to Offshore Structures. Elleftheria Deligeorges; Jai Tulsi Use of Underwater Dry Welding for In Situ Repair to Offshore Structures Elleftheria Deligeorges; Jai Tulsi engineering@neptunems.com 11/03/2015 In Situ Welding Steel Structures Suitability of Repair Methods

More information

Phase 2 Guidance for Field Segmentation and Welding of Induction Bends and Elbows

Phase 2 Guidance for Field Segmentation and Welding of Induction Bends and Elbows Phase 2 Guidance for Field Segmentation and Welding of Induction Bends and Elbows INGAA Foundation Workshop on Welding of Field Segmented Induction Bends and Elbows for Pipeline Construction Bill Bruce

More information

CONSTRUCTION SPECIFICATION FOR CHAIN-LINK FENCE

CONSTRUCTION SPECIFICATION FOR CHAIN-LINK FENCE ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.PROV 772 NOVEMBER 2017 (Formerly OPSS 772, November 2012) Note: The PROV published in November 2017 replaces OPSS 772 COMMON, November 2012 with no technical

More information

Review of ASME Guidance Articles on Repair Strategies

Review of ASME Guidance Articles on Repair Strategies Review of ASME Guidance Articles on Repair Strategies Clay Rodery BP Chemicals Technology & Engineering Member/ASME Post Construction Standards Committee ASME PCC-2: Repair of Pressure Equipment and Piping

More information

PART UF REQUIREMENTS FOR PRESSURE VESSELS FABRICATED BY FORGINGS

PART UF REQUIREMENTS FOR PRESSURE VESSELS FABRICATED BY FORGINGS p 1 of 6 UF-1 UF-12 PART UF REQUIREMENTS FOR PRESSURE VESSELS FABRICATED BY FORGING the test temperature be higher than 20 F ( 29 C). Certification is required. An ultrasonic examination shall be made

More information

b) provide evidence of his qualifications and practical experience in welding.

b) provide evidence of his qualifications and practical experience in welding. NEPALESE CIVIL AIRWORTHINESS REQUIREMENTS SECTION D APPROVAL PROCEDURES CHAPTER D.6 ISSUE 1 NOVEMBER 1994 1. GENERAL WELDERS 1.1 This chapter is applicable to persons who weld parts which are essential

More information

5. POST-EARTHQUAKE INSPECTION

5. POST-EARTHQUAKE INSPECTION 5. POST-EARTHQUAKE INSPECTION When required by the building official, or recommended by the Interim Guidelines in Chapter 4, post-earthquake inspections of buildings may be conducted in accordance with

More information

Welding Performance Qualification Test Administrators GUIDE FOR APPLICANTS

Welding Performance Qualification Test Administrators GUIDE FOR APPLICANTS BRITISH COLUMBIA SAFETY AUTHORITY Welding Performance Qualification Test Administrators GUIDE FOR APPLICANTS Date: April 25, 2017 Controlled Document: MAN-4018-01 MAN-4018-01 Page 1 of 27 Contents Contents...

More information

CONSTRUCTION SPECIFICATION FOR CHAIN-LINK FENCE

CONSTRUCTION SPECIFICATION FOR CHAIN-LINK FENCE ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 541 NOVEMBER 2005 CONSTRUCTION SPECIFICATION FOR CHAIN-LINK FENCE TABLE OF CONTENTS 541.01 SCOPE 541.02 REFERENCES 541.03 DEFINITIONS 541.04 SUBMISSION

More information

CONSTRUCTION SPECIFICATION FOR STEEL REINFORCEMENT FOR CONCRETE

CONSTRUCTION SPECIFICATION FOR STEEL REINFORCEMENT FOR CONCRETE ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 905 APRIL 2007 CONSTRUCTION SPECIFICATION FOR STEEL REINFORCEMENT FOR CONCRETE TABLE OF CONTENTS 905.01 SCOPE 905.02 REFERENCES 905.03 DEFINITIONS

More information

Stainless Steel Aeration Equipment Specification

Stainless Steel Aeration Equipment Specification Section 15 Stainless Steel Aeration Equipment Specification Part 1 - General 1.01 Description A. Scope of Work 1. Furnish, install and test aeration system including air mains, drop pipes, valves, expansion

More information

AWS B1.10M/B1.10:2009 An American National Standard. Guide for the Nondestructive Examination of Welds

AWS B1.10M/B1.10:2009 An American National Standard. Guide for the Nondestructive Examination of Welds An American National Standard Guide for the Nondestructive Examination of Welds An American National Standard Approved by the American National Standards Institute July 1, 2009 Guide for the Nondestructive

More information

STANDARD SPECIFICATIONS FOR PIPING - WELDING DOCUMENT NO : Z SS 005 PREVIOUS DOC. NO. : BSS-26-03/1

STANDARD SPECIFICATIONS FOR PIPING - WELDING DOCUMENT NO : Z SS 005 PREVIOUS DOC. NO. : BSS-26-03/1 Page 1 of 1 STANDARD SPECIFICATIONS FOR PIPING - WELDING DOCUMENT NO : Z SS 005 PREVIOUS DOC. NO. : BSS-26-03/1 Rev No. Issue Date Pages Rev Description Prepared By Checked By Approved By 0 02.11.2001

More information

North Atlantic ENGINEERING STANDARD SPECIFICATION 1/7 REV. QUALITY SLAG BOWL WELDING AND QUALITY REQUIREMENTS. Approved by.

North Atlantic ENGINEERING STANDARD SPECIFICATION 1/7 REV. QUALITY SLAG BOWL WELDING AND QUALITY REQUIREMENTS. Approved by. 1/7 Rev Description Revision by Approved by Issue Date YYYY/MM/DD 1 Update from Job 497-01 KLR 015/04/01 Updated 1.0 and 4.3 PB 016/03/09 KLR 015/04/01 PB 016/03/09 015/04/01 016/03/09 Sud = Sudbury, Ontario,

More information

DOUBLE WALLED PIPING SYSTEMS

DOUBLE WALLED PIPING SYSTEMS DOUBLE WALLED PIPING SYSTEMS The design and construction of a double wall pipe is more complex than a single wall pipe because of the additional pipe, associated welds and tie in procedures. There are

More information

192GasCatalog.

192GasCatalog. 192GasCatalog www.energyu.org www.midwestenergy.org 192-Abnormal Operating Conditions... 4 192-0101 Characteristics and Hazards of Natural Gas... 4 192-0201 Gas Detection and Alarm System Maintenance...

More information

Welding Inspection Defects/Repairs Course Reference WIS 5

Welding Inspection Defects/Repairs Course Reference WIS 5 Copy from Welding Inspection Defects/Repairs Course Reference WIS 5 Weld Defects Defects which may be detected by visual inspection can be grouped under five headings Cracks Surface irregularities Contour

More information

welding equipment Prepare and use manual TIG or plasma-arc Performance evidence required You must be able to:

welding equipment Prepare and use manual TIG or plasma-arc Performance evidence required You must be able to: 006 UNIT 028 Preparing and using manual TIG or plasma-arc Learning outcomes 1 2 Know how to prepare and use manual TIG or plasma-arc Performance evidence must be the main form of evidence gathered. Candidates

More information

AWS B1.10:1999 An American National Standard. Guide for the Nondestructive Examination of Welds

AWS B1.10:1999 An American National Standard. Guide for the Nondestructive Examination of Welds AWS B1.10:1999 An American National Standard Guide for the Nondestructive Examination of Welds Key Words Guide, eddy current examination, magnetic particle examination, nondestructive examination, penetrant

More information

QUALITY ASSURANCE SPECIFICATION WELDING HEAT TREATMENT PAGE 1 OF 6

QUALITY ASSURANCE SPECIFICATION WELDING HEAT TREATMENT PAGE 1 OF 6 QUALITY ASSURANCE SPECIFICATION REVISION: 0 DATE: 08/29/14 WELDING HEAT TREATMENT PAGE 1 OF 6 1.0 Purpose The purpose of this specification is to establish the minimum quality assurance requirements for

More information

REFERENCE SYLLABUS. for WELDING EXAMINER & WELDING EXAMINER IN TRAINING CERTIFICATES OF COMPETENCY EXAMINATIONS

REFERENCE SYLLABUS. for WELDING EXAMINER & WELDING EXAMINER IN TRAINING CERTIFICATES OF COMPETENCY EXAMINATIONS WELDING EXAMINER & CERTIFICATES OF COMPETENCY S AB-94 Edition 1, Revision 6, 2016-05-01 This syllabus is being phased out and will be discontinued on April 30, 2018. GENERAL INFORMATION INTRODUCTION: This

More information

Michael T. Anderson, Stephen E. Cumblidge, Steven R. Doctor Pacific Northwest National Laboratory, Richland, WA, USA

Michael T. Anderson, Stephen E. Cumblidge, Steven R. Doctor Pacific Northwest National Laboratory, Richland, WA, USA THROUGH WELD INSPECTION OF WROUGHT STAINLESS STEEL PIPING USING PHASED ARRAY ULTRASONIC PROBES Michael T. Anderson, Stephen E. Cumblidge, Steven R. Doctor Pacific Northwest National Laboratory, Richland,

More information

Materials and Qualification Procedures for Ships

Materials and Qualification Procedures for Ships Materials and Qualification Procedures for Ships Approval of Works for the Manufacture of Fusion Welded Pressure Vessels Revision 4, July 2015 Page 1 of 17 Lloyd s Register Group Limited, its subsidiaries

More information

WELD PROCEDURE DATA. Carrier Pipe Thickness (WT): 6.4 mm < WT = 31.8 mm (Design and CSA Z662 Cl )

WELD PROCEDURE DATA. Carrier Pipe Thickness (WT): 6.4 mm < WT = 31.8 mm (Design and CSA Z662 Cl ) WELD PROCEDURE DATA WPS: WEI-30-1 Rev. 0 Application: Branch and Lap (Sleeve) Connections on non-flowing, gas lines which are either pressured or non-pressured. Supporting PQR: WEI-30-1-1 (Branch) Qualification

More information

HIGH ENERGY PIPING INSPECTION PROGRAM

HIGH ENERGY PIPING INSPECTION PROGRAM HIGH ENERGY PIPING INSPECTION PROGRAM JOEL LUNDQUIST STRESS ANALYSIS SECTION B&V ENERGY AGENDA About Black & Veatch Introduction Power Piping Code Initial Baseline Assessment Evaluation by Non-Destructive

More information

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS SECTION 02620 PART 1 GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment, and incidentals required to install High Density Polyethylene (HDPE) pressure pipe, fittings, and appurtenances

More information

VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur

VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur 603 203 DEPARTMENT OF MECHANICAL ENGINEERING QUESTION BANK VII SEMESTER ME 6008-WELDING TECHNOLOGY Regulation 2013 Academic Year 2017 18 Prepared

More information

1. Poor attitude toward any of the other students, instructors, or judges. 2. Failure to use personal protective equipment (PPE).

1. Poor attitude toward any of the other students, instructors, or judges. 2. Failure to use personal protective equipment (PPE). Welding Contest Rules and Score Sheet 2016 4G Rules: 1. Be Safe & Have Fun 2. Can tack in any position but groove welding must be in accordance with your WPS. 3. Can use wire brush, chipping hammer, and

More information

Preparing and using manual TIG or plasma-arc welding equipment

Preparing and using manual TIG or plasma-arc welding equipment Unit 028 Preparing and using manual TIG or plasma-arc welding equipment Level: 2 Credit value: 15 NDAQ number: 500/9514/6 Unit aim This unit covers the skills and knowledge needed to prove the competences

More information

ANSI/AWS D An American National Standard. Structural Welding Code Sheet Steel

ANSI/AWS D An American National Standard. Structural Welding Code Sheet Steel ANSI/AWS D1.3-98 An American National Standard Structural Welding Code Sheet Steel Key Words Sheet steel, allowable stresses, details of welded joints, workmanship qualification, visual acceptance criteria,

More information

ASME B31.3 Process Piping

ASME B31.3 Process Piping ASME B31.3 Process Piping Charles Becht IV, PhD, PE Don Frikken, PE Instructors BECHT ENGINEERING COMPANY, INC. Fabrication and Installation - 1 Piping Development Process 1. Establish applicable system

More information

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) SECTION 02623 HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE) PART 1 - GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals required and install high density

More information

WELDER S. Visual Inspection HANDBOOK. May 2013

WELDER S. Visual Inspection HANDBOOK. May 2013 WELDER S Visual Inspection HANDBOOK May 2013 -- NOTE -- This handbook is NOT intended to serve as a work procedure or to replace any existing procedures. It is solely intended to provide basic information

More information

GAIL (INDIA) LIMITED BID DOCUMENT FOR ANNUAL RATE CONTRACT (ARC) FOR HOT TAPPING WORKS INCLUDING SUPPLY OF SPLIT TEES VOL II OF II TECHNICAL

GAIL (INDIA) LIMITED BID DOCUMENT FOR ANNUAL RATE CONTRACT (ARC) FOR HOT TAPPING WORKS INCLUDING SUPPLY OF SPLIT TEES VOL II OF II TECHNICAL GAIL (INDIA) LIMITED (A.GOVT OF INDIA UNDERTAKING) BID DOCUMENT FOR ANNUAL RATE CONTRACT (ARC) FOR HOT TAPPING WORKS INCLUDING SUPPLY OF SPLIT TEES VOL II OF II TECHNICAL (BID DOCUMENT NO.- 110398 A /WGI/GAIL/01-R0)

More information

DELIVERING THE SOLUTIONS YOU NEED TO STAY PRODUCTIVE

DELIVERING THE SOLUTIONS YOU NEED TO STAY PRODUCTIVE E S CO ST Y L E S U P E R - V B U C K E T T E E T H DELIVERING THE SOLUTIONS YOU NEED TO STAY PRODUCTIVE E S CO ST Y L E S U P E R - V T E E T H & A DA P T E R S 2-STRAP ADAPTERS Part No A B C D KG Machine

More information

Cast Steel Propellers W27. (May 2000) (Rev.1 May 2004)

Cast Steel Propellers W27. (May 2000) (Rev.1 May 2004) (May 2000) (Rev.1 May 2004) Cast Steel Propellers 1. Scope 1.1 These unified requirements are applicable to the manufacture of cast steel propellers, blades and bosses. 1.2 Where the use of alternative

More information

CONSTRUCTION SPECIFICATION FOR CHAIN-LINK FENCE

CONSTRUCTION SPECIFICATION FOR CHAIN-LINK FENCE ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 772 NOVEMBER 2010 CONSTRUCTION SPECIFICATION FOR CHAIN-LINK FENCE TABLE OF CONTENTS 772.01 SCOPE 772.02 REFERENCES 772.03 DEFINITIONS 772.04 DESIGN

More information

"Welder Certification"

Welder Certification "Welder Certification" The purpose of this presentation is to introduce you to the various aspects of welder certification. This is not intended to cover all of the requirements for certification but only

More information

LUNA COMMUNITY COLLEGE

LUNA COMMUNITY COLLEGE LUNA COMMUNITY COLLEGE Welding Program Curriculum Profile 2012-2015 COMPETENCIES 1 Program Goal: The program prepares students with entry-level job skills in all phases of the welding industry and provides

More information

SECTION REINFORCING STEEL

SECTION REINFORCING STEEL SECTION REINFORCING STEEL 1. DESCRIPTION This specification shall govern the furnishing and placing of reinforcing steel, deformed and smooth, of the size and quantity designated on the plans and in accordance

More information

Pipe Pile. New Jersey Department of Transportation, Brielle, NJ. Route 70 Bridge over the Manasquan River, Brielle, NJ. USACE, Santa Maria, CA

Pipe Pile. New Jersey Department of Transportation, Brielle, NJ. Route 70 Bridge over the Manasquan River, Brielle, NJ. USACE, Santa Maria, CA Pipe Pile Similar to H-piles, pipe piles are also designed to transfer structural loads through the foundation to soils below. Where H-piles are typically classified as point bearing, pipe piles are most

More information

Manitoba Welder Practical Examination STRUCTURAL LEVEL 2

Manitoba Welder Practical Examination STRUCTURAL LEVEL 2 STRUCTURAL LEVEL 2 The Manitoba Welder Practical Examination is designed to test the scope of practical knowledge and skills of the trade. Please read all the information throughout this package. All candidates

More information

WATER UTILITY WORKER, 3912 WATER UTILITY SUPERVISOR, 3976

WATER UTILITY WORKER, 3912 WATER UTILITY SUPERVISOR, 3976 3-25-88 WATER UTILITY WORKER, 3912 WATER UTILITY SUPERVISOR, 3976 Summary of Duties : Installs, maintains, replaces, and repairs water mains, services, irrigation systems, fire hydrants, and appurtenant

More information

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe. STANDARD SPECIFICATIONS SECTION 02445 BORING AND JACKING PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for boring and jacking casing pipe. 1.2 DEFINITIONS A. Carrier Pipe: Sewer or water

More information

WELDING. ELIGIBILITY Open to active SkillsUSA members enrolled in Career and Technical Education programs with welding as the occupational objective.

WELDING. ELIGIBILITY Open to active SkillsUSA members enrolled in Career and Technical Education programs with welding as the occupational objective. The following rules are for the state contest only. Students/Teams that qualify for the national contest need to adhere to the rules and guidelines for that national contest. The rules can be found in

More information

7. Allowable Fittings.

7. Allowable Fittings. 7. Allowable Fittings. a. General Requirements. 1) The fittings listed in this section are generally the allowable fittings for the design of DIP and PVC pipe. For steel pipe and fittings, see Part One,

More information

Module 4 Design for Assembly

Module 4 Design for Assembly Module 4 Design for Assembly Lecture 2 Design for Welding-I Instructional Objective By the end of this lecture, the student will learn: (a) how a weld joint should be designed to improve the joint performance,

More information

Magnetic Particle Inspection Proficiency Testing Program

Magnetic Particle Inspection Proficiency Testing Program y REPORT NO. 542 Magnetic Particle Inspection Proficiency Testing Program May 2007 ACKNOWLEDGMENTS PTA wishes to gratefully acknowledge the technical assistance provided for this program by Mr Jim Scott,

More information

Division 11 - Equipment Section 11401

Division 11 - Equipment Section 11401 PART 1 - GENERAL 1.1 GENERAL A. Division 1 General Requirements applies and becomes a part of this Section of the Specification as fully as if repeated herein. B. Items of equipment which are included

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-40 17 26.00 20 (April 2006) -------------------------------- Preparing Activity: NAVFAC Replacing without change UFGS-15216N (September 1999) UNIFIED FACILITIES GUIDE

More information

Section 906. STRUCTURAL STEEL

Section 906. STRUCTURAL STEEL 906.01 Section 906. STRUCTURAL STEEL 906.01. General Requirements. Finished rolled shapes must be free from imperfections that affect strength and durability in accordance with ASTM A 6. Rolled shapes

More information

DNVGL-CG-0287 Edition December 2015

DNVGL-CG-0287 Edition December 2015 CLASS GUIDELINE DNVGL-CG-0287 Edition December 2015 The electronic pdf version of this document, available free of charge from http://www.dnvgl.com, is the officially binding version. FOREWORD DNV GL class

More information

195LiquidsCatalog.

195LiquidsCatalog. 195LiquidsCatalog www.energyu.org www.midwestenergy.org 195 Abnormal Operating Conditions... 3 195-0060 General Abnormal Operating Conditions (CT60)... 3 195-0000 Documentation & Reporting... 3 195-0403

More information

Colphene BSW Training and Application Guide. Colphene BSW Waterproofing Membrane. 1. Prepare substrate

Colphene BSW Training and Application Guide. Colphene BSW Waterproofing Membrane. 1. Prepare substrate Colphene BSW Training and Application Guide Colphene BSW Waterproofing Membrane. 1. Prepare substrate Substrate must be structurally sound. Surface must be free of voids, spalled areas, loose aggregate,

More information

Lincoln Electric External Evaluation Evaluation of EXX45-P2 Welding Electrodes

Lincoln Electric External Evaluation Evaluation of EXX45-P2 Welding Electrodes Lincoln Electric External Evaluation Evaluation of EXX45-P2 Welding Electrodes Evaluation of EXX45-P2 Welding Electrodes Final Report for Lincoln Electric Company Report No.: 82674761 April 22, 2008 Evaluation

More information

REMOVAL OF CAST LIP STEP 1 STEP 2. Layout cut lines, based on existing welds and verify with dimension taken from new lip. STEP 3

REMOVAL OF CAST LIP STEP 1 STEP 2. Layout cut lines, based on existing welds and verify with dimension taken from new lip. STEP 3 REMOVAL OF CAST LIP STEP 1 fig. 1-1 Brace clam from cheek plate to cheek plate (A). Brace clam from bucket floor, (just behind back of lip joint), to upper cheek plate on both sides (B). The purpose of

More information

PART 5 WELDING. 5.1 General 5.2 Preparation 5.3 Dimensions of welds 5.4 Materials 5.5 Aluminium alloys 5.6 Welding details 5.

PART 5 WELDING. 5.1 General 5.2 Preparation 5.3 Dimensions of welds 5.4 Materials 5.5 Aluminium alloys 5.6 Welding details 5. PART 5 WELDING PART 5 WELDING SECTION SUBJECT 5.1 General 5.2 Preparation 5.3 Dimensions of welds 5.4 Materials 5.5 Aluminium alloys 5.6 details 5.7 Symbols WELDING Section 5.1 General 5.1.1 of structures

More information

Qualification scheme for welders of hull structural steels

Qualification scheme for welders of hull structural steels (Sept 2016) Qualification scheme for welders of hull structural steels 1. Scope 1.1 This document gives requirements for a qualification scheme for welders intended to be engaged in the fusion welding

More information

Comparison of BS and BS EN for steel materials

Comparison of BS and BS EN for steel materials Comparison of BS and BS EN for steel materials Appendix This table only highlights the comparison of BS and BS EN on steel materials, which are relevant to plan approval. Title of BS BS BS EN Title of

More information

SECTION HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT

SECTION HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT SECTION 220529 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

EASTERN ARIZONA COLLEGE Welding

EASTERN ARIZONA COLLEGE Welding EASTERN ARIZONA COLLEGE Welding Course Design 2015-2016 Course Information Division Industrial Technology Education Course Number WLD 101 Title Welding Credits 2-3 Developed by Carlton Penn Lecture/Lab

More information

American Welding Society Nashville Section. Welding Procedure Development

American Welding Society Nashville Section. Welding Procedure Development American Welding Society Nashville Section Welding Procedure Development AWS & ASME Welding Procedures Welding Procedure Specification (WPS) Written document that provides direction to the welder for making

More information

Materials and Qualification Procedures for Ships

Materials and Qualification Procedures for Ships Materials and Qualification Procedures for Ships Approval of a Foundry for the Manufacture of Steel Castings Revision 3, January 2015 Lloyd s Register Group Limited, its subsidiaries and affiliates and

More information

Oil and Gas Pipeline Design, Maintenance and Repair

Oil and Gas Pipeline Design, Maintenance and Repair Oil and Gas Pipeline Design, Maintenance and Repair Dr. Abdel-Alim Hashem El-Sayed Professor of Petroleum Engineering Mining, Petroleum & Metallurgical Eng. Dept. Faculty of Engineering Cairo University

More information

Sample Bid Specification Revision 2 PVC Expanded-in-Place Pipeline Reconstruction

Sample Bid Specification Revision 2 PVC Expanded-in-Place Pipeline Reconstruction Sample Bid Specification Revision 2 PVC Expanded-in-Place Pipeline Reconstruction 1.00 DESCRIPTION 1.01 WORK INCLUDED: This work shall include the furnishing of all labor, equipment and materials necessary

More information

VPAR Instruction Brochure Rev. B, June 11, 2003

VPAR Instruction Brochure Rev. B, June 11, 2003 1. Purpose The purpose of this document is to provide guidance and information to supplement and clarify the requirements of welding procedure qualification specifications PPD 803-6335695 and S9074-AQ-

More information

Pressure Equipment Repair and Alteration Requirements

Pressure Equipment Repair and Alteration Requirements the pressure equipment safety authority Pressure Equipment Repair and Alteration Requirements AB-513 Edition 3, Revision 0 - Issued 2018-01-30 Table of Contents FOREWORD... iii 1.0 INTRODUCTION... 1 2.0

More information

Guide for AWS Visual Weld Inspection

Guide for AWS Visual Weld Inspection Guide for Visual Weld Overview & Contents Scope This guide is intended to assist Owner/Operators, Contractors, Authority Having Jurisdiction (AHJ) personnel, Inspectors, Manufacturers and Contractors/Fabricators

More information

Welcome. Mission. About Us. to Sharjah Steel Corporate Portfolio

Welcome. Mission. About Us. to Sharjah Steel Corporate Portfolio Corporate Portfolio About Us Us Sharjah Steel Pipe Manufacturing Company (SSPMC) was founded in 1982, specialized in steel pipe manufacturing using the most developed machines and equipments in terms of

More information

Canadian Welding Bureau Welding Procedure Qualification AWS D1.1 vs CSA W47.1

Canadian Welding Bureau Welding Procedure Qualification AWS D1.1 vs CSA W47.1 Welding Procedure Qualification Canadian Welding Bureau Welding Procedure Qualification Comparison of Key Concepts and Requirements This document provides a general comparison of key concepts and requirements

More information

Assessment of Weld Integrity through Full Range Burst Test of API 5L X-70 Grade Line Pipe

Assessment of Weld Integrity through Full Range Burst Test of API 5L X-70 Grade Line Pipe Available online at www.scholarsresearchlibrary.com European Journal of Applied Engineering and Scientific Research, 2017, 5(2):1-5 ISSN: 2278-0041 Assessment of Weld Integrity through Full Range Burst

More information

SCHEDULE OF RATES (SOR)

SCHEDULE OF RATES (SOR) SCHEDULE OF RATES (SOR) TENDER NO: GAIL/C&P/JP13/FL-69/3300051935/RC/2013-14 E-tender No. : 8000005689 Description of job: INSTALLATION OF 12 DIA. X 600 M LONG PIPELINE THROUGH HDD TECHNIQUE ACROSS SHADARA-NALA-YAMUNA

More information

Industrial Technology Intermediate Welding Curriculum and Scope and Sequence First Quarter

Industrial Technology Intermediate Welding Curriculum and Scope and Sequence First Quarter Industrial Technology Intermediate Welding Curriculum and Scope and Sequence First Quarter Students are to increase their skill level and knowledge of Shielded Welding (SMAW) process in flat position.

More information

welder certification welder performance qualification

welder certification welder performance qualification Chapter 29 Welder Certification OBJECTIVES After completing this chapter, the student should be able : Explain welder qualification and certification. Outline the steps required certify a welder. Make

More information

PART UIG THE ASME CODE FOR IMPREGNATED GRAPHITE PRESSURE VESSELS

PART UIG THE ASME CODE FOR IMPREGNATED GRAPHITE PRESSURE VESSELS PART UIG THE ASME CODE FOR IMPREGNATED GRAPHITE PRESSURE VESSELS Presented by: Ed Soltow Engineering and Design Manager SGL Carbon Technic LLC Member ASME Standards Committee on Pressure Vessels (BPV VIII)

More information