Status Evaluation & Analysis on Equipments of Power Transmission & Distribution in Lushan Earthquake (April 20, 2013)
|
|
- Howard Bryant
- 6 years ago
- Views:
Transcription
1 Status Evaluation & Analysis on Equipments of Power Transmission & Distribution in Lushan Earthquake (April 20, 2013) Delivered by: Liu Fan State Grid Sichuan Electric Power Company 09/2013
2 Outline Background Equipments Status Evaluation & Analysis of 500kV Substation Equipments Status Evaluation & Analysis of 220kV Substation & Below Status Evaluation & Analysis for 500kV Transmission Lines Cause Analysis & Seismic Design of Equipments 2
3 Background Lushan Earthquake at 8:02 20/04/2013 3
4 Background First time into Ya'an 4
5 Background Damage to Power Grid Load Loss MW Loss of Generation 1917MW 5
6 Background Outage of Substations Due to Earthquake 220kV:1 110kV:3 35kV:5 550kV:1 220kV:1 110kV:2 35kV:4 110kV:2 35kV:6 110kV:2 35kV:5 35kV:1 110kV:1 35kV:1 6
7 Evaluation & Analysis on 500kV Substation Status of Ya'an Substation Severely Damaged Substation Location Capacity No. of Transformer Type of Transformer Function Ya'an Shiyang Town, Tianquan County, Ya'an City 1500MVA 2 (750MVA for each) Three-phase Off-circuit Tap Changing Auto Transformer For Local Power Supply Gather & Transfer Hydropower from Ya'an District and 500kV Shimian & Jiulong Substation 7
8 Evaluation & Analysis on 500kV Substation Damage of Primary Equipments Equipments Transformer 1# & 2# 500kV Bus & Line 220kV Bus & Line Other Damage #1: Oil Leakage of Phase A B C HV Bushing; #2: Breakage on Phase A Medium Voltage Bushing Oil Leakage of Phase B Shunt Reactors for Shiya Line 2# Oil Leakage of Bushings of Shiya Line 2# Phase A & C Shunt Reactors Oil Leakage of Shunt Reactors for Shiya Line 1# & 2# Oil Leakage of Yashan Line 2# Phase A Shunt Reactor (Discovered on 26th of April) Damage of Surge Arresters for 220kV Bus 3 & 4 Damage of Surge Arrester Post Insulator on #2 Transformer Medium Voltage Side Oil Leakage found on Phase C CT of 319# Breaker for 1# Auxiliary Transformer Breakage of Joint on 3kV Bus II HV Fuse Foundation Sinking found at where 400V feeder panel sets 8
9 Evaluation & Analysis on 500kV Substation Damage of Primary Equipments HV Bushing: Oil Leakage Collapse of Surge Arrestor 9
10 Evaluation & Analysis on 500kV Substation Damage of Primary Equipments Breakage of Bushing Collapse of Surge Arrester 10
11 Evaluation & Analysis on 500kV Substation Damage of Primary Equipments Line Outage Due to Severe Leakage Oil Leakage 11
12 Evaluation & Analysis on 500kV Substation Defects Detection & Handling of Primary Equipments Detect of Equipment Defects throughout the Substation Equipments Volts Measures Quantity AC Breaker 500kV 39 SF 6 & Infrared Diagnosis 220kV 30 Isolator 500kV 78 Infrared Diagnosis 220kV 72 Surge Arrestor 500kV 21 Infrared Diagnosis 220kV 33 PT 500kV 33 Infrared Diagnosis 220kV 12 Shunt Reactor 500kV Infrared Diagnosis 21 CT 500kV 7 Infrared Diagnosis 220kV 7 12
13 Evaluation & Analysis on 500kV Substation Defects Detection & Handling of Primary Equipments Examine damage of Surge Arrester Collapse of 500kV MOA 13
14 Evaluation & Analysis on 500kV Substation On Site Examination of Porcelain MOA On Site Examination of Porcelain MOA 14
15 Evaluation & Analysis on 500kV Substation On Site Examination of Transformer & Shunt Reactor 15
16 Evaluation & Analysis on 500kV Substation On Site Examination of Transformer & Shunt Reactor Oil Leakage Due to Ceramic envelope Breakage Position Appears Breakage 16
17 Evaluation & Analysis on 500kV Substation Damage to 500kV Neijiang Substation HV Bushing Oil Leakage 17
18 Evaluation & Analysis on 500kV Substation Damage to 500kV Neijiang Substation Deformation of Connecting Bolts Transposition of Gaskets 18
19 Evaluation & Analysis on 500kV Substation Technical Support On Site Examination of Damaged Equipments Provision of Suggestion for Equipment Replacement Technology Supervision of Hand-Over Test Oil & Gas Analysis Urgent Repair Plan Formulation and Technical Support Live Detection of Power Euipments Support of Strategy for Power Grid Operation 19
20 Evaluation & Analysis on Substation of 220kV & Below Damage of Equipments of 220kV & Below Including 220kV Huanggang and Tianquan, 110kV Shaping Chengnan and Shiyang Substation Substation Volts Equipments No. Type of Defects Transformer 1 Bushing Breakage & Transpostion, Oil Leakage on Huanggang 220kV Relaying Protective Cabinet Door Fallen 1 Protection Off, LCD Pannel Cracking Radiator Surge Arrester 11 Damaged Tianquan 220kV Transformer 1 Bushing Oil Leakage, Gaskets Transposition Transformer 3 Bushing Oil Leakage Shaping 110kV Breaker 4 Collapsed CT 1 Collapsed Chengnan 110kV Transformer 1 Bushing Oil Leakage Shiyang 110kV No Physical Damage Found 20
21 Evaluation & Analysis on Substation of 220kV or Below Examination of Damaged Equipments Loosening of 35kV Bushing Sealing CT Collapse 21
22 Evaluation & Analysis on Substation of 220kV or Below Examination of Damaged Equipments Damage of Circuit Breakers 22
23 Evaluation & Analysis on Substation of 220kV or Below Technical Support Recovery of Transformer Strategy for Maintenance & Operation Routine Test Live Diagnosis 23
24 Evaluation & Analysis on 500kV Transmission Lines 500kV Transmission Lines Operating Well, Few Tower Base, Slope Protection and Tower Structure Were Partially Damaged Crack of Tower Base and Slope Protection 24
25 Evaluation & Analysis on 500kV Transmission Lines Lessons From Earthquake Crack of Slope Protection and Tower Structure 25
26 Cause Analysis & Seismic Design of Equipments Causes of Damage In both Wenchuan and Ya'an Earthquake, bushings of transformers & shunt reactors appear breakage at the root, and Leads to oil leakage, whereras the Body Parts were rare to see damage Bushing Structure (b/w Bushing Root and Turrets) Bolts Connected without caging devices Bolts Connected with caging devices Pouring Connected Cause Analysis Mostly caused by gaskets transposition, then bolts deformation and shed breakage Rare to see gaskets transposition, but bushing shed breakage could lead to oil leakage unless there is a notable shearstress Rare to see gaskets transposition, but bushing shed breakage could lead to massive oil leakage unless there is a huge shearstress 26
27 Causes Analysis & Seismic Design of Equipments Importance of Seismic Research Power Equipments Vulnerability Solid Demands after Earthquake Lack of Experience Sichuan Laying on Seismic Belt PGA Distribution Map of Sichuan Power Grid 27
28 Causes Analysis & Seismic Design of Equipments Status Quo of Seismic Research Vulnerability & Complexity of Power System Equipments Seismic Freq. 1-10Hz Equipments Materials Low Intensity & Ductility Poor Damping Capability Close to Resonance Oscillation Equipment Freq. 1-10Hz Other Factor Concerned Nature of Earthquake Damping, Rigidity, Material, External Load 28
29 Causes Analysis & Seismic Design of Equipments Seismic Qualification for Electric Power Facilities List of Seismic Qualification Category Code Name IEC IEC2771-2:2003 IEC :2006 IEC High-voltage switchgear and controlgear-seismic qualification for rated voltages of 72,5 kv and above 2. Seismic qualification of AC circuit-breakers 3. Bushings Seismic qualification USA IEEE693 Seismic Qualification of Composites for Substation High-Voltage Equipments JAPAN JEAG Guide for Seisimic Design of Substation Equipment CHINA GB/T GB Seismic Qualification for High-Voltage Swichgear and Controlgear 2. Code for Design of Seismic of Electrical Installations 29
30 Causes Analysis & Seismic Design of Equipments Seismic Qualification for Electric Power Facilities Scope of Application Adaptible to Electric Power Facility Installation, Expansion and Reconstructon in Area of Seismic Fortification Design b/w 6~9: 1. Facilities from 110kV~750kV AC Projects; 2. Facilities from DC Projects of ±660kV or Below 30
31 Causes Analysis & Seismic Design of Equipments Seismic Qualification for Electric Power Facilities 1 Propose Seismic Standard for HV Projects Seismic Design for Power Facility in China 2 Confirm Seismic Test Requirements 2 2 Supplement of Isolation & Dissipation 3 Design for Electrical Power Facility 4 More Specified Framework DAF 4 5 Specified Load Combination 31
32 Causes Analysis & Seismic Design of Equipments Propose Seismic Standard for HV Projects 1. Seismic Design Subjected to being Surpassed with a 2% Probability; 2. Proposed Seismic Design Response Spectum for HV Equipments 32
33 Causes Analysis & Seismic Design of Equipments Confirmed Test Requirements To test the seismic capability of new facility or large-size equipments, Earthquake Simulator is required; for those equipments unable to test due to problems of size, weight, complexity etc., or even already passed the test but with slight change on structure, we can adopt stochasticly test or test & analisis method. Institutes Satisfied the Requirements In Operation Under Construction China Academy of Building Research, Tongji Uniersity, Chongqing Jiaotong Designing Institute In stitute of Engineering Mechanics, China Earthquake Administration (Beijing), Chongqing University 33
34 Causes Analysis & Seismic Design of Equipments Supplement of Isolation & Dissipation Design for Electrical Power Facility For facilities located at area of high intensity, which is unable to satisfy seismic requirements or subjected to higher or specialized requirements, this article applies. Capacitor(NewZealand) Reactor(USA) 34
35 Causes Analysis & Seismic Design of Equipments Tipical Isolation & Dissipation Design Surge Arrester(Japan) 35
36 Causes Analysis & Seismic Design of Equipments Tipical Isolation & Dissipation Design: Bushing Acceleration Rate From 1.02g Down to 0.289g Isolation Test for Transformer Bushing(UC) 36
37 Causes Analysis & Seismic Design of Equipments Tipical Isolation & Dissipation Design FPS-isolation System:Relate to Surface Radius & Gravity Coefficients,Independant of mass 37
38 Causes Analysis & Seismic Design of Equipments Research Have Down After Wenchuan Earthquake: Lounch a Project "Research on Damage of Power Equipments at Wenchuan Earthquake" Together withtongji University "Research on 500kV Ya'an Substation Bushing Damage at 4.20 Lushan Earthquake" 38
39 Causes Analysis & Seismic Design of Equipments Isolation & Dissipation Design and Application for 220kV Xiameng Substation Post Insulator Transformer Base 39
40 Causes Analysis & Seismic Design of Equipments Analysis on Transformer Bushing Breakage at 500kV Ya'an Substation High Seismic Intensity Level 9, Almost Upper Limit Bushing Structure? 1. Connected by caging devices 2. Large gravitational torque Materials? Easy to Damage Bushing of Transformer 1# after Disassembly 40
41 Causes Analysis & Seismic Design of Equipments Comparison of Bushing Connection Type of Connection Clamped by Caging Devices Pouring Connected Prons Mature Tech., Easy for Installation, with Certain Resiliance and Deflection As a Whole, Easy to Withstand Earthquake of Certain Level Cons High Cost, Vulnerable Subjected to Collision Highly Rely on Intensity of Porcelain Shed, Can Lead to Devastating Result Subjected to Violent Earthquake 41
42 Causes Analysis & Seismic Design of Equipments Seimic Design of Power System Equipments No. Suggestions for Equipments Withstanding Earthquake 1 Use High Intensity Porcelain Material or Silicon Envilope 2 Select Post Insulator with High Intensity Porcelain and Equipments with Solid Insulator as Support 3 Use Equipments with Low Centre of Gravity, such as GIS, HGIS etc. 4 Suggest Not to Use Rod Insulator Supported Distribution Equipment of Tubular Bus Bar, Aluminum Tubular Bus Bar is Suggested to use Suspension Insulator 5 Use Damping Devices for Equipments Easy Subjected to Resonance Oscillation, Therefore Change System Frequency and Damping Ratio 6 Renforce Floating Equipments Connection to Avoid Transposition or Collapse 7 Considering 3/2 Connection Scheme unless Equipments and Site Area Allow 42
43 Causes Analysis & Seismic Design of Equipments Research Plan Project: Study on Substation Equipments Vulnerability at High Seismic Intensity Area of Sichuan 1 Analysis of Failure mode and Law of Electrical Equipments in Earthquake 2 Exploration of Evaluation Approach for Level of Damage to Substation Equipments 3 Evalution of Seismic Withstand ability for Substation & its Equipments at High Intensity Area of Sichuan 4 Evaluation of Substation Capability to Withstand Earthquake as a Whole, Propose Scheme for Capablity Improvement 5 Proposing Optimal Solutions to Flange Connection of Bushing Type Equipments 43
44 Thank You for your attention! 44
Seismic Considerations of Circuit Breakers
Seismic Considerations of Circuit Breakers Willie Freeman, IEEE 693 Working Group ABB Inc, Mt. Pleasant PA, USA IEEE Tutorial - 2008 Abstract: The tutorial covers the seismic qualification of high voltage
More informationSeismic-Resistant Switchboards Conforming to New Regulatory Standards Concerning Commercial Nuclear Reactors
Seismic-Resistant Switchboards Conforming to New Regulatory Standards Concerning Commercial Nuclear Reactors KONNO, Masayuki * FUJIMOTO, Yoshio NAGASAWA, Takenori A B S T R A C T Nuclear power plants and
More information4 September 2010 and 22 February 2011 Christchurch Earthquakes from a Transmission Grid Infrastructure Perspective
4 September 2010 and 22 February 2011 Christchurch Earthquakes from a Transmission Grid Infrastructure Perspective Asset Structural Performance and Lessons Learned By Craig McGhie and Christophe Tudo-Bornarel
More informationPOLYMER HOUSED SURGE ARRESTORS
POLYMER HOUSED SURGE ARRESTORS March 2015 Engineering Department WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED Regd. Office: VidyutBhawan, Block DJ, Sector-II, Bidhannagar, Kolkata 700091.
More informationCIGRE Seismic Behavior of Siemens Circuit Breakers during the Earthquake on 27 February 2010 in Chile. October 19th, 2010
CIGRE 2010 Seismic Behavior of Siemens Circuit Breakers during the Earthquake on 27 February 2010 in Chile October 19th, 2010 Siemens circuit breaker sold by factory Berlin and percentage of CB with seismic
More informationSection-12 (Revision 01 dated ) Page 1 of 9. SPECIAL CONDITIONS OF CONTRACT (for both parts A and B) 12.
Section-12 (Revision 01 dated 05.05.2006) Page 1 of 9 SPECIAL CONDITIONS OF CONTRACT (for both parts A and B) 12.0 TERMS OF PAYMENT 12.0.1 The contractor should submit his monthly on account bills with
More informationSeismic Reliability Evaluation of Electrical Power Transmission Systems and its Effect on Core Damage Frequency
Seismic Reliability Evaluation of Electrical Power Transmission Systems and its Effect on Core Damage Frequency Tetsukuni OIKAWA 1), Sei ichiro FUKUSHIMA 2), Hidekazu TAKASE 2), Tomoaki UCHIYAMA MURAMATSU
More informationStudy Committee A3. High Voltage Equipment. Action Plan
Study Committee A3 High Voltage Equipment Action Plan October 2011 CIGRE Study Committee A3 - High Voltage Equipment Action Plan 1 Content 1 Content...2 2 Purpose of the Action Plan...3 3 Activities of
More informationPLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES
Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)
More informationThis section applies to the requirements for electrical Inspection, calibration, and testing.
Basis of Design This section applies to the requirements for electrical Inspection, calibration, and testing. Design Criteria Edit attached guide specification, as required, to meet the project requirements.
More informationB. Provide liquid-filled secondary substation transformers as indicated on drawings.
SECTION 26 12 13 PART 1 - GENERAL 1.01 WORK INCLUDED A. Comply with the provisions of Sections 26 05 00. B. Provide liquid-filled secondary substation transformers as indicated on drawings. 1.02 RELATED
More informationCandidate NICET ID No.: NICET ENGINEERING TECHNICIAN CERTIFICATION Experience Application, Part II: Verifier Data. (Please print legibly or type)
Candidate: Experience Application, Part II: Verifier Data Candidate NICET ID No.: SM Standard Model (Please print legibly or type) To be completed by the Verifier only Name: Title: Current employer: Daytime
More informationStation Post Insulators (SPI), an Emerging Application for Composite Hollow Core Insulators PETER STAHL
Station Post Insulators (SPI), an Emerging Application for Composite Hollow Core Insulators PETER STAHL Composite Hollow Core Station Post Insulators (SPI) Peter Stahl, July 2015 Applications for composite
More informationIEC Oil Filled & SF 6 Gas Current Transformers
g IEC Oil Filled & SF 6 Gas Current Transformers 72.5kV - 550kV (325kV - 1550kV BIL) with Primary Plus TM Pre-engineered solution set that digitizes XD GE primary equipment and provides factory installed
More informationDesignated Entity Design Standards Task Force (DEDSTF) Minimum Design Requirements for FERC Order 1000 Projects. System Protection Subgroup
Designated Entity Design Standards Task Force (DEDSTF) Minimum Design Requirements for FERC Order 1000 Projects System Protection Subgroup For any substation facility included in the scope of a transmission
More informationPre-Qualification Certificate
Nordic Utility Pre-Qualification System Pre-Qualification Certificate Awarded to Registration number: 984 277 032 Sellihca Id: Sellihca Qualification hereby confirms that is now fully registered as a supplier
More informationReport Number: G Date: February 3, 2012 INTRODUCTION
Bul l et i neu1595 Report Number: G12-02-01 Date: February 3, 2012 INTRODUCTION The industry standard to which Hubbell Power Systems - Ohio Brass qualifies the seismic capability of its arresters is IEEE
More informationEast Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria
East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria March 2016 Section 1 Overview and General Discussion The primary purpose of East Kentucky Power Cooperative s (EKPC s) transmission
More informationManufacturing and Application of Cage Design High Voltage Metal Oxide Surge Arresters
Manufacturing and Application of Cage Design High Voltage Metal Oxide Surge Arresters K. Steinfeld, B. Kruska and W. Welsch Siemens Surge Arresters and Limiters, Berlin, Germany Abstract: Metal oxide surge
More informationFIELD TEST AND OPERATIONAL CHECK SECTION A. Refer to Section 16010, Electrical General Requirements.
FIELD TEST AND OPERATIONAL CHECK SECTION 16080 PART 1 GENERAL 1.1 GENERAL REQUIREMENTS A. Refer to Section 16010, Electrical General Requirements. 1.2 WORK INCLUDED A. General Scope: 1. The Contractor
More informationSTANDARD DRAWINGS. September 2013 UPDATED FEBRUARY 2016
STANDARD DRAWINGS September 2013 UPDATED FEBRUARY 2016 CONSTRUCTION STANDARD DRAWINGS DIVISION 15 LIST OF DRAWINGS: 1. 01 2004-1 Rev. A - Concrete Standards General Outline and Reinforcement Notes 2. 01
More informationCompany Introduction and Information EPTCON LTD. 560 SHELDON DRIVE, CAMBRIDGE ONTARIO. PHONE:
Company Introduction and Information EPTCON LTD. 560 SHELDON DRIVE, CAMBRIDGE ONTARIO. PHONE: 519 620 4414 WWW.EPTCON.COM Company Background ABOUT US EPTCON Ltd. (Electrical Power & Transmission Construction),
More informationSummary of Seismic Reliability in Electric Power System
Summary of Seismic Reliability in Electric Power System WEN Bo 1 AND NIU Di-tao 2, ZHAO Peng 3 1 Doctoral Candidate, Dept. of Civil Engineering, Xi an University of Architecture & Technology, Xi an. China
More information2009 NZSEE Conference 2-5 April Christchurch ESTIMATING SEISMIC IMPACTS ON LIFELINES: AN INTERNATIONAL REVIEW FOR RISKSCAPE
2009 NZSEE Conference 2-5 April Christchurch ESTIMATING SEISMIC IMPACTS ON LIFELINES: AN INTERNATIONAL REVIEW FOR RISKSCAPE Sonia GIOVINAZZI 1 and Andrew KING 2 1 University of Canterbury 2 GNS Science
More informationNIGERIA ELECTRICITY TRANSMISSION PROJECT (NETAP)
NIGERIA ELECTRICITY TRANSMISSION PROJECT (NETAP) TERMS OF REFERENCE (TOR) For TECHNICAL ASSISTANCE FOR ENGINEERING SUPERVISION AND SITE MANAGEMENT OF REHABILITATION & REINFORCEMENT OF 330/132kV & 132/33kV
More informationSECTION ENCLOSED BUS ASSEMBLIES
SECTION 262500 ENCLOSED BUS ASSEMBLIES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationProduct brochure Multi Functional Switchgear PASS M kv Flexible and compact switchgear solutions for windfarms
Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms The future of Wind Farms In 2010, offshore wind farms accounted for 9.5% of the overall
More informationSPECIFICATIONS FOR Gas-to-Cable termination
Product GSM-145 1.0 APPLICATION: Gas-to-cable termination is a part of high voltage gas insulated indoor switchgear equipment. The component is intended for a high voltage system of 132 kv (AC), 50 Hz.
More informationTransient Stability Analysis of an Industrial Cogeneration System
Transient Stability Analysis of an Industrial Cogeneration System Hung-Cheng Chen Shang-Yi Chen Shun-Chung Shih Department of Electrical Engineering, National Chin-Yi University of Technology hcchen@ncut.edu.tw
More informationImportant Considerations for Specifying MV Mining Switchgear Western Mining Electrical Association Edmonton, Canada June 13, 2008
Important Considerations for Specifying MV Mining Switchgear Western Mining Electrical Association Edmonton, Canada June 13, 2008 (Above 1000V and up to 38kV for Surface Mining) Key Components of Specification:
More informationFIBRE REINFORCED PLASTICS IN HIGH VOLTAGE APPLICATIONS
FBRE RENFORCED PLASTCS N HGH VOLTAGE APPLCATONS Volker Bergmann, Reinhausen Power Composites GmbH Page 1 OVERVEW 1. ntroduction 2. Hollow core composite insulators and their application 3. Dielectric and
More informationTECHNICAL SPECIFICATION
IEC/TS 62371 TECHNICAL SPECIFICATION Edition 1.0 2008-05 Characteristics of hollow pressurised and unpressurised ceramic and glass insulators for use in electrical equipment with rated voltages greater
More informationCode No: II B. Tech II Semester Regular Examinations, April/May 2009 POWER SYSTEMS I. ( Electrical & Electronics Engineering)
Code No: 3220201 II B. Tech II Semester Regular Examinations, April/May 2009 SET - 1 POWER SYSTEMS I ( Electrical & Electronics Engineering) Time: 3 hours Max Marks: 80 Answer Any FIVE Questions All Questions
More informationDRAFT. GUIDELINES FOR Usage of AIR INSULATED SUBSTATION (AIS) or GAS INSULATED SUBSTATION(GIS)
DRAFT GUIDELINES FOR Usage of AIR INSULATED SUBSTATION (AIS) or GAS INSULATED SUBSTATION(GIS) CENTRAL ELECTRICITY AUTHORITY 2018 1. Introduction Substations are an important part of the electrical distributions.
More informationSUMMARY OF PRICES FOR 30MVA 161/24/36 kv MOBILE SUBSTATION ACCORDING to SR-152
Israel Electric Corporation Ltd. Tender no. Name of Contractor: SUMMARY OF PRICES FOR 30MVA 161/24/36 kv MOBILE SUBSTATION ACCORDING to SR-152 1. GENERAL INSTRUCTIONS 2.1. Prices for the above captioned
More informationComposite Insulator Components
Composite Insulator Components Composite insulator components A composite insulator is made of at least two insulating parts a core and housing. It is equipped with end fittings. Core. The core is the
More informationSECTION SECONDARY UNIT SUBSTATIONS
SECTION 26 12 16 SECONDARY UNIT SUBSTATIONS PART 1 GENERAL 1.1 SUMMARY This section describes metal-clad, indoor or outdoor, secondary unit substations with integral primary fused disconnect switches,
More informationGROUP A. Polymeric Insulators.
GROUP A Polymeric Insulators PYUNGIL Bldg., 1475-10, Gwanyang 2-dong, Dongan-gu, Anyang-si, Gyeonggi-do, 431-808, Korea Tel : 82-31-420-6650~3 FAX : 82-31-424-7300 www.pyungil.com Silicone Railway
More informationHigh Voltage Products. High Voltage Products Service Professionals at your service. Power and productivity for a better world TM
High Voltage Products High Voltage Products Service Professionals at your service Power and productivity for a better world TM High Voltage Products Service Professionals at your service The increasing
More informationSECTION SECONDARY UNIT SUBSTATIONS
PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 11 16 SECONDARY UNIT SUBSTATIONS SPEC WRITER NOTE: Delete between //----// if not applicable to project. Also delete any other item or paragraph not applicable
More informationDESIGN OF ENERGY DISSIPATOR DEVICES TO PROTECT EQUIPMENTS OF A 400 KV POWER SUBSTATION AGAINST EARTHQUAKE IN NEISHABOUR - IRAN
13 th World Conference on Earthquake Engineering Vancouver, B.C., Canada August 1-6, 2004 Paper No. 3262 DESIGN OF ENERGY DISSIPATOR DEVICES TO PROTECT EQUIPMENTS OF A 400 KV POWER SUBSTATION AGAINST EARTHQUAKE
More informationPOWER TRANSFORMER INSTALLATION
Project Procedure POWER TRANSFORMER INSTALLATION No.: P-6.2-8-1 07/20/2011 PAGE 1 OF 6 1.0 PURPOSE The purpose of this procedure is to ensure that power transformer installations are accomplished in compliance
More informationISO Rules Part 500, Facilities Division 502, Technical Requirements Section Bulk Transmission Technical Requirements
Part 500, Facilities Division 502, Technical Requirements Section 502.2 Bulk Transmission Technical Requirements Applicability 1 This section 502.2 applies to: Requirements the legal owner of any bulk
More informationI. CLARIFICATIONS SOUGHT BY PROSPECTIVE BIDDERS
This clarification forms part of the Request for Proposal and Contract documents, and modifies them as follows: I. CLARIFICATIONS SOUGHT BY PROSPECTIVE BIDDERS S. No. 1. Refer to section Bid Data Sheet
More informationELECTRICITY SUPPLY - POWER SYSTEM MAINTENANCE Carry out routine inspection and service on oil filled distribution power transformers 11kV to 400V
1 of 8 level: 4 credit: 8 planned review date: December 2006 sub-field: purpose: entry information: Electricity Supply People credited with this unit standard are able to: prepare for routine service transformers
More informationTechnical report on alternative to SF6 gas in medium voltage & high voltage electrical equipment
TECHNICAL REPORT 20/02/2018 Technical report on alternative to SF6 gas in medium voltage & high voltage electrical equipment T&D Europe aisbl 1 FOREWORD... 4 1 - METHODOLOGY... 4 2 - SCOPE... 5 3 - INTRODUCTION...
More informationLow Voltage Switchgear Construction Checklist (under 500 kva)
Low Voltage Switchgear Checklist (under 500 kva) Project: Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing.
More informationMONTE CARLO SIMULATION FOR THE SEISMIC RESPONSE ANALYSIS OF ELECTRIC POWER SYSTEM IN TAIWAN
MONTE CARLO SIMULATION FOR THE SEISMIC RESPONSE ANALYSIS OF ELECTRIC POWER SYSTEM IN TAIWAN Gee-Yu Liu National Center for Research on Earthquake Engineering, Taipei, Taiwan karl@ncree.gov.tw C.-W. Liu
More informationFINAL REPORT SUMMARY. November Prepared for: The Ministry of Economy, Trade and Industry. Prepared by:
Feasibility Study for Promotion of International Infrastructure Projects in FY2011 STUDY ON THE SUBSTATION REHABILITATION PROJECT IN YANGON, THE REPUBLIC OF THE UNION OF MYANMAR FINAL REPORT SUMMARY November
More informationRecent Technical Trends of Vacuum Circuit-Breakers (VCBs)
Switchgear Technical Trends and Basic Technologies Recent Technical Trends of Vacuum Circuit-Breakers (VCBs) Hitoshi Saito, Makoto Honma, Masayuki Sakaki Keywords Circuit-breaker, Switchgear, Vacuum interrupter,
More informationDISTRIBUTION OPERATIONS AND MAINTENANCE
EB-00-00 Exhibit F Tab Schedule Filed: 00 Aug Page of DISTRIBUTION OPERATIONS AND MAINTENANCE 0 PREDICTIVE MAINTENANCE Predictive maintenance expenditures fund work that is required to test and audit distribution
More informationA. Section includes busway and fittings including plug-in units.
SECTION 26 25 00 ENCLOSED BUS ASSEMBLIES PART 1 - GENERAL 1.1 SUMMARY A. Section includes busway and fittings including plug-in units. 1.2 REFERENCES A. Institute of Electrical and Electronics Engineers:
More informationMica Gas Insulated Switchgear (GIS) Replacement Project Workshop
B-3 Mica Gas Insulated Switchgear (GIS) Replacement Project Workshop 26 August 2009 Agenda Mica GIS Replacement Project BCUC Order Mica Generating Station and GIS equipment Need for the Project Project
More information9KV/18KV METAL OXIDE LIGHTNING ARRESTORS WITHOUT GAPS WITH STANDARD NOMINAL DISCHARGE CURRENT 5KA
9KV/18KV METAL OXIDE LIGHTNING ARRESTORS WITHOUT GAPS WITH STANDARD NOMINAL DISCHARGE CURRENT 5KA Technical specification for 9KV/18KV 5KA Metal oxide Lightning Arrestors without Gap. ----------------------------------------------------------------------------------------------------------------
More informationGrid Interconnection Issues for Wind Generation
Grid Interconnection Issues for Wind Generation NRECA APPA - DOE Teleconference December 8, 2005 By Thomas A. Wind, PE Wind Utility Consulting Jefferson, Iowa Topics I Will Cover What are the key technical
More informationDuresca. Duresca. Tiresca. Travesca. Gaslink
MGCExpertise Product range: Duresca Busbar system Duresca Wall bushings Tiresca Busbar system Travesca Transformer bushings Gaslink Busbar system 3 4 one... 5...team 6 Summary Product range 2 Preface 3
More informationIntroduction to Substation Design TADP 542
Introduction to Substation Design TADP 542 Design Principles- General Framework Instructor: Richard Snell Transmission & Distribution Program Module 2 Outline Presentation 1: General Framework Presentation
More informationThe Earthquake Actions and Testing Approaches for Curtain Wall
2013 UBC-Tongji-CSRN Symposium The Earthquake Actions and Testing Approaches for Curtain Wall Yangling Wang, Wensheng Lu, Baofeng Huang E-mail:wenshenglu@vip.163.com State Key Laboratory Of Disaster Reduction
More information--> Buy True-PDF --> Auto-delivered in 0~10 minutes. GB Translated English of Chinese Standard: GB
GB50303-2002 GB 50303-2002 Translated English of Chinese Standard: GB50303-2002 NATIONAL STANDARD OF THE PEOPLE S REPUBLIC OF CHINA Excerpt / simplified PDF version (some pages are intentionally omitted)
More informationNEPAL ELECTRICITY AUTHORITY (An Undertaking of Government of Nepal) Project Management Directorate
NEPAL ELECTRICITY AUTHORITY (An Undertaking of Government of Nepal) SAMUNDRATAR TRISHULI 3B HUB 132 KV TRANSMISSION LINE PROJECT BIDDING DOCUMENT FOR DESIGN, SUPPLY AND CONSTRUCTION OF 132/33 KV SUBSTATION
More informationPacific Earthquake Engineering Research Center
Pacific Earthquake Engineering Research Center Development of an Electrical Substation Equipment Performance Database for Evaluation of Equipment Fragilities Thalia Anagnos San Jose State University PEER
More informationAdvances in Computer Science Research, volume 63 International Conference on Artificial Intelligence and Engineering Applications (AIEA 2016)
International Conference on Artificial Intelligence and Engineering Applications (AIEA 2016) Quality Importance Evaluation for Wind/Photovoltaic Energy Storage and Transmission Demonstration Project via
More informationDistribution Tradesperson (Jobsplus Permit No. 706/2017)
CAREER OPPORTUNITIES Enemalta plc is the leading energy service provider in the Maltese Islands, entrusted with the generation and distribution of electricity and the development of the national electricity
More informationPublic Utility District Number 1 of Snohomish County
Public Utility District Number 1 of Snohomish County Facility Connection Requirements September 29, 2011 1 Revision History: Number Date Description Original Sept. 29, 2011 Document Origination Compilation
More informationPotential and E-Field Calculation Along an Ice- Covered Composite Insulator with Finite Element Method
Potential and E-Field Calculation Along an Ice- Covered Composite Insulator with Finite Element Method Qing Yang, Caixin Sun, Wenxia Sima, Lichun Shu, Ji Yang, Jianlin Hu The Key Laboratory of High Voltage
More informationIntroduction of an innovative base isolation system for seismic protection of HV components based on a combination of wire ropes and viscous dampers
Earthquake Resistant Engineering Structures X 147 Introduction of an innovative base isolation system for seismic protection of HV components based on a combination of wire ropes and viscous dampers M.
More informationACS OTHER PRIMARY EQUIPMENT
ACS OTHER PRIMARY EQUIPMENT Fleet Strategy Document 31/10/2013 Transpower New Zealand Limited 2013. All rights reserved. Page 1 of 70 C O P Y R I G H T 2013 T R A N S P O W E R N E W Z E A L A N D L I
More informationIBC-2003 Seismic Rating What s Shakin? The IBC and IEEE seismic standards and the seismic qualification process
GE Consumer & Industrial Electrical Distribution IBC-2003 Seismic Rating What s Shakin? The IBC and IEEE seismic standards and the seismic qualification process BACKGROUND International Building Code 2003
More informationRochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017
Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA March 21, 2017 Contents 1 Background...3 2 National and Regional Criteria and Guides...4 2.1 2.1 NERC Transmission Planning Standards...4 2.2
More informationCast Resin LV Busway (IP68) Taiwan Busway Company
Cast Resin LV Busway (IP68) Taiwan Busway Company TBC Company Overview Taiwan Busway Company, Ltd. Est. 2002; located in Taipei Brand: TBC Busway market leader in Taiwan, presence in China, Germany/ Europe,
More informationWhat to Look for in a Good Quality Arrester
All good quality arresters have much in common. This first in a series of articles, sponsored by NEMA Surge Arrester Section members, covers what to look for in that quality arrester. Introduction We've
More informationTransmission Line General Requirements Including Typical Overhead Line Structures. Document Number: 1-03-FR-09
Transmission Line General Requirements Including Typical Overhead Line Structures Document Number: 1-03-FR-09 VERSION 1.0 June 2018 This functional requirements document is in line with the organisation's
More informationGUYANA POWER AND LIGHT INC
GUYANA POWER AND LIGHT INC The Terms of Reference REQUEST FOR PROPOSALS: CONSULTANCY SERVICES COORDINATING GENERATOR PROTECTION WITH TRANSMISSION PROTECTION AND GENERATOR CONTROLS (GPL-PI-094-2016) November
More informationBharat Heavy Electricals Limited. Ceramic Business Unit. ollow. An ISO 9001, & Certified Company
Bharat Heavy Electricals Limited Ceramic Business Unit ollow An ISO 9001, 14001 & 18001 Certified Company Hollow 1 Alternate shed Plain shed 2 1 Flange 2 Porcelain Shell 3 Ground Collar 3 Straight bore
More informationWenchuan Earthquake Impact to Power Systems. John Eidinger 1
Wenchuan Earthquake Impact to Power Systems John Eidinger 1 1 G&E Engineering Systems Inc., P. O. Box 3592 Olympic Valley, CA 96146-3592; eidinger@earthlink.net ABSTRACT The Wenchuan M 7.9 earthquake of
More informationA Proper Design of Wind Turbine Grounding Systems under Lightning
A Proper Design of Wind Turbine Grounding Systems under Lightning M. A. Abd-Allah, Mahmoud N. Ali, A. Said Abstract Lightning protection systems (LPS) for wind power generation is becoming an important
More informationPractical Experience Gained from Dissolved Gas Analysis at an Aluminium Smelter. Ian.A.R. Gray
Practical Experience Gained from Dissolved Gas Analysis at an Aluminium Smelter Ian.A.R. Gray Largest aluminium smelter in the Southern hemisphere South Africa's major producer of primary aluminium It
More informationTransmission Silicone Insulators Line Post 69 kv to 230 kv
K-LINE INSULATORS LIMITED Catalogue T-LP Transmission Silicone Insulators Line Post 69 kv to 230 kv ISO9001 SAI GLOBAL FILE No. 000117 Transmission Silicone Insulators Line Post Today transmission lines
More informationElectric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas
Electric Power Systems An Overview Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas Overview Power Generation Conventional and renewable power generation Power transmission
More information500 MW Wind Farm Technical System Impact Study
FINAL REPORT Report to: El Paso Electric for 500 MW Wind Farm Technical System Impact Study Prepared by: Goran Drobnjak Sang Lee Emad Ahmed Reigh Walling Einar Larsen February 19, 2008 EPE_TechSIS_Final.doc
More informationProposed Facility Study Report. Project: A380_A383_A415_A414_A413 MISO # F088. Prepared for Midwest ISO
Proposed Facility Study Report Project: A380_A383_A415_A414_A413 MISO # F088 Prepared for Midwest ISO January 15 th, 2010 Great River Energy Contact: Greg Schutte, Project Manager Great River Energy 1
More informationElectric Power Systems An Overview
Electric Power Systems An Overview Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas Overview Power Generation Conventional and renewable power generation Power transmission
More informationDetails of technical leaflets/write-up on various pieces of equipment.
Details of technical leaflets/write-up on various pieces of equipment. (1) Insulator Designs: The insulators are provided in one, two, three, or four insulator designs per location and spaced to provide
More informationWEST ZONE POWER DISTRIBUTION CO. LTD. (WZPDCL) TENDER DOCUMENT FOR
WEST ZONE POWER DISTRIBUTION CO. LTD. (WZPDCL) TENDER DOCUMENT FOR SUPPLY, DELIVERY, INSTALLATION, TESTING AND COMMISSIONING OF 2 NOS. (MOHESSORPASA (KHULNA) & CAMPUS (KUSHTIA)) 33/11 KV 2X20/26.66 MVA
More informationCarry out routine inspection and service on high voltage indoor metal clad circuit breakers and bus
Page 1 of 7 Carry out routine inspection and service on high voltage indoor metal clad circuit breakers and bus Level 4 Credits 4 Purpose People credited with this unit standard are able to: prepare for
More informationParameter Analysis and Shaking Table Test on Seismic Isolation System of Transformer with Bushings
Parameter Analysis and Shaking Table Test on Seismic Isolation System of Transformer with Bushings CAO Mei-gen, CHENG Yong-feng & DAI Ze-bing China Electric Power Research Institute of SGCC, Beijing ZHOU
More informationPlatte River Power Authority. Ten-Year Transmission Plan ( )
Platte River Power Authority Ten-Year Transmission Plan (2015-2024) Prepared by PRPA System Planning December 31, 2014 Table of Contents I. Executive Summary II. III. IV. Scope Assumptions Criteria V.
More informationHigh Energy Arcing Faults (HEAF) and Their Impact on PRA for a Nuclear Power Plant Latest International Operating Experience and Research Activities
High Energy Arcing Faults (HEAF) and Their Impact on PRA for a Nuclear Power Plant Latest International Operating Experience and Research Activities Marina Roewekamp GRS ggmbh, Germany Nicholas Melly,
More informationStructural Performance Assessment and Control of Super Tall Buildings During Construction
Available online at www.sciencedirect.com Procedia Engineering 14 (211) 253 251 The Twelfth East Asia-Pacific Conference on Structural Engineering and Construction Structural Performance Assessment and
More informationCOMPANY PROFILE INESING SPA
COMPANY PROFILE INESING SPA HISTORY The Company INESING has matured in the lasts 10 years the experience, knowledge and professionalism at the highest level, consolidating its presence in the market for
More informationPRY-MOULD. High Voltage Accessories for Extruded Cables
PRY-MOULD High Voltage Accessories for Extruded Cables Linking the future As the worldwide leader in the cable industry, Prysmian Group believes in the effective, efficient and sustainable supply of energy
More informationSECTION BUSWAYS
PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 25 11 BUSWAYS SPEC WRITER NOTE: Delete between //----// if not applicable to project. Also delete any other item or paragraph not applicable to the section and
More informationMSME Testing Centre, 65/1, G. S. T. Road, Guindy, Chennai, Tamil Nadu. Discipline Electrical Testing Issue Date
Last Amended on - Page 1 of 7 I. TRANSMISSION LINE EQUIPMENT & ACCESSORIES ]] 1 Stockbridge Vibration dampers for Power lines Examination & IS 9708:1993 Cl. 7.2 Cl. 7.3 Mass pull off (Slip) Cl. 7.6 120
More informationUnit Substation Transformer Construction Checklist (under 500 kva)
Unit Substation Transformer Checklist (under 500 kva) Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing.
More informationDesign features - Polymer-housed arresters, PEXLIM
features - Polymer-housed arresters, PEXLIM PEXLIM arresters, using the same ZnO blocks as the EXLIM arresters, match their electrical performance. Silicone as outer insulation material has been used for
More informationEnergy Division Insulators
Energy Division http://energy.tycoelectronics.com Insulators R Insulators Tyco Electronics Energy Division covers a wide range of polymeric, hybrid and porcelain insulators. For decades all these products
More informationEXPERIMENTAL AND ANALYTICAL STUDY OF A HIGH VOLTAGE INSTRUMENT TRANSFORMER
13 th World Conference on Earthquake Engineering Vancouver, B.C., Canada August 1-6, 2004 Paper No. 2550 EXPERIMENTAL AND ANALYTICAL STUDY OF A HIGH VOLTAGE INSTRUMENT TRANSFORMER Mehran HATAMI 1, Mohsen
More information