Status Evaluation & Analysis on Equipments of Power Transmission & Distribution in Lushan Earthquake (April 20, 2013)

Size: px
Start display at page:

Download "Status Evaluation & Analysis on Equipments of Power Transmission & Distribution in Lushan Earthquake (April 20, 2013)"

Transcription

1 Status Evaluation & Analysis on Equipments of Power Transmission & Distribution in Lushan Earthquake (April 20, 2013) Delivered by: Liu Fan State Grid Sichuan Electric Power Company 09/2013

2 Outline Background Equipments Status Evaluation & Analysis of 500kV Substation Equipments Status Evaluation & Analysis of 220kV Substation & Below Status Evaluation & Analysis for 500kV Transmission Lines Cause Analysis & Seismic Design of Equipments 2

3 Background Lushan Earthquake at 8:02 20/04/2013 3

4 Background First time into Ya'an 4

5 Background Damage to Power Grid Load Loss MW Loss of Generation 1917MW 5

6 Background Outage of Substations Due to Earthquake 220kV:1 110kV:3 35kV:5 550kV:1 220kV:1 110kV:2 35kV:4 110kV:2 35kV:6 110kV:2 35kV:5 35kV:1 110kV:1 35kV:1 6

7 Evaluation & Analysis on 500kV Substation Status of Ya'an Substation Severely Damaged Substation Location Capacity No. of Transformer Type of Transformer Function Ya'an Shiyang Town, Tianquan County, Ya'an City 1500MVA 2 (750MVA for each) Three-phase Off-circuit Tap Changing Auto Transformer For Local Power Supply Gather & Transfer Hydropower from Ya'an District and 500kV Shimian & Jiulong Substation 7

8 Evaluation & Analysis on 500kV Substation Damage of Primary Equipments Equipments Transformer 1# & 2# 500kV Bus & Line 220kV Bus & Line Other Damage #1: Oil Leakage of Phase A B C HV Bushing; #2: Breakage on Phase A Medium Voltage Bushing Oil Leakage of Phase B Shunt Reactors for Shiya Line 2# Oil Leakage of Bushings of Shiya Line 2# Phase A & C Shunt Reactors Oil Leakage of Shunt Reactors for Shiya Line 1# & 2# Oil Leakage of Yashan Line 2# Phase A Shunt Reactor (Discovered on 26th of April) Damage of Surge Arresters for 220kV Bus 3 & 4 Damage of Surge Arrester Post Insulator on #2 Transformer Medium Voltage Side Oil Leakage found on Phase C CT of 319# Breaker for 1# Auxiliary Transformer Breakage of Joint on 3kV Bus II HV Fuse Foundation Sinking found at where 400V feeder panel sets 8

9 Evaluation & Analysis on 500kV Substation Damage of Primary Equipments HV Bushing: Oil Leakage Collapse of Surge Arrestor 9

10 Evaluation & Analysis on 500kV Substation Damage of Primary Equipments Breakage of Bushing Collapse of Surge Arrester 10

11 Evaluation & Analysis on 500kV Substation Damage of Primary Equipments Line Outage Due to Severe Leakage Oil Leakage 11

12 Evaluation & Analysis on 500kV Substation Defects Detection & Handling of Primary Equipments Detect of Equipment Defects throughout the Substation Equipments Volts Measures Quantity AC Breaker 500kV 39 SF 6 & Infrared Diagnosis 220kV 30 Isolator 500kV 78 Infrared Diagnosis 220kV 72 Surge Arrestor 500kV 21 Infrared Diagnosis 220kV 33 PT 500kV 33 Infrared Diagnosis 220kV 12 Shunt Reactor 500kV Infrared Diagnosis 21 CT 500kV 7 Infrared Diagnosis 220kV 7 12

13 Evaluation & Analysis on 500kV Substation Defects Detection & Handling of Primary Equipments Examine damage of Surge Arrester Collapse of 500kV MOA 13

14 Evaluation & Analysis on 500kV Substation On Site Examination of Porcelain MOA On Site Examination of Porcelain MOA 14

15 Evaluation & Analysis on 500kV Substation On Site Examination of Transformer & Shunt Reactor 15

16 Evaluation & Analysis on 500kV Substation On Site Examination of Transformer & Shunt Reactor Oil Leakage Due to Ceramic envelope Breakage Position Appears Breakage 16

17 Evaluation & Analysis on 500kV Substation Damage to 500kV Neijiang Substation HV Bushing Oil Leakage 17

18 Evaluation & Analysis on 500kV Substation Damage to 500kV Neijiang Substation Deformation of Connecting Bolts Transposition of Gaskets 18

19 Evaluation & Analysis on 500kV Substation Technical Support On Site Examination of Damaged Equipments Provision of Suggestion for Equipment Replacement Technology Supervision of Hand-Over Test Oil & Gas Analysis Urgent Repair Plan Formulation and Technical Support Live Detection of Power Euipments Support of Strategy for Power Grid Operation 19

20 Evaluation & Analysis on Substation of 220kV & Below Damage of Equipments of 220kV & Below Including 220kV Huanggang and Tianquan, 110kV Shaping Chengnan and Shiyang Substation Substation Volts Equipments No. Type of Defects Transformer 1 Bushing Breakage & Transpostion, Oil Leakage on Huanggang 220kV Relaying Protective Cabinet Door Fallen 1 Protection Off, LCD Pannel Cracking Radiator Surge Arrester 11 Damaged Tianquan 220kV Transformer 1 Bushing Oil Leakage, Gaskets Transposition Transformer 3 Bushing Oil Leakage Shaping 110kV Breaker 4 Collapsed CT 1 Collapsed Chengnan 110kV Transformer 1 Bushing Oil Leakage Shiyang 110kV No Physical Damage Found 20

21 Evaluation & Analysis on Substation of 220kV or Below Examination of Damaged Equipments Loosening of 35kV Bushing Sealing CT Collapse 21

22 Evaluation & Analysis on Substation of 220kV or Below Examination of Damaged Equipments Damage of Circuit Breakers 22

23 Evaluation & Analysis on Substation of 220kV or Below Technical Support Recovery of Transformer Strategy for Maintenance & Operation Routine Test Live Diagnosis 23

24 Evaluation & Analysis on 500kV Transmission Lines 500kV Transmission Lines Operating Well, Few Tower Base, Slope Protection and Tower Structure Were Partially Damaged Crack of Tower Base and Slope Protection 24

25 Evaluation & Analysis on 500kV Transmission Lines Lessons From Earthquake Crack of Slope Protection and Tower Structure 25

26 Cause Analysis & Seismic Design of Equipments Causes of Damage In both Wenchuan and Ya'an Earthquake, bushings of transformers & shunt reactors appear breakage at the root, and Leads to oil leakage, whereras the Body Parts were rare to see damage Bushing Structure (b/w Bushing Root and Turrets) Bolts Connected without caging devices Bolts Connected with caging devices Pouring Connected Cause Analysis Mostly caused by gaskets transposition, then bolts deformation and shed breakage Rare to see gaskets transposition, but bushing shed breakage could lead to oil leakage unless there is a notable shearstress Rare to see gaskets transposition, but bushing shed breakage could lead to massive oil leakage unless there is a huge shearstress 26

27 Causes Analysis & Seismic Design of Equipments Importance of Seismic Research Power Equipments Vulnerability Solid Demands after Earthquake Lack of Experience Sichuan Laying on Seismic Belt PGA Distribution Map of Sichuan Power Grid 27

28 Causes Analysis & Seismic Design of Equipments Status Quo of Seismic Research Vulnerability & Complexity of Power System Equipments Seismic Freq. 1-10Hz Equipments Materials Low Intensity & Ductility Poor Damping Capability Close to Resonance Oscillation Equipment Freq. 1-10Hz Other Factor Concerned Nature of Earthquake Damping, Rigidity, Material, External Load 28

29 Causes Analysis & Seismic Design of Equipments Seismic Qualification for Electric Power Facilities List of Seismic Qualification Category Code Name IEC IEC2771-2:2003 IEC :2006 IEC High-voltage switchgear and controlgear-seismic qualification for rated voltages of 72,5 kv and above 2. Seismic qualification of AC circuit-breakers 3. Bushings Seismic qualification USA IEEE693 Seismic Qualification of Composites for Substation High-Voltage Equipments JAPAN JEAG Guide for Seisimic Design of Substation Equipment CHINA GB/T GB Seismic Qualification for High-Voltage Swichgear and Controlgear 2. Code for Design of Seismic of Electrical Installations 29

30 Causes Analysis & Seismic Design of Equipments Seismic Qualification for Electric Power Facilities Scope of Application Adaptible to Electric Power Facility Installation, Expansion and Reconstructon in Area of Seismic Fortification Design b/w 6~9: 1. Facilities from 110kV~750kV AC Projects; 2. Facilities from DC Projects of ±660kV or Below 30

31 Causes Analysis & Seismic Design of Equipments Seismic Qualification for Electric Power Facilities 1 Propose Seismic Standard for HV Projects Seismic Design for Power Facility in China 2 Confirm Seismic Test Requirements 2 2 Supplement of Isolation & Dissipation 3 Design for Electrical Power Facility 4 More Specified Framework DAF 4 5 Specified Load Combination 31

32 Causes Analysis & Seismic Design of Equipments Propose Seismic Standard for HV Projects 1. Seismic Design Subjected to being Surpassed with a 2% Probability; 2. Proposed Seismic Design Response Spectum for HV Equipments 32

33 Causes Analysis & Seismic Design of Equipments Confirmed Test Requirements To test the seismic capability of new facility or large-size equipments, Earthquake Simulator is required; for those equipments unable to test due to problems of size, weight, complexity etc., or even already passed the test but with slight change on structure, we can adopt stochasticly test or test & analisis method. Institutes Satisfied the Requirements In Operation Under Construction China Academy of Building Research, Tongji Uniersity, Chongqing Jiaotong Designing Institute In stitute of Engineering Mechanics, China Earthquake Administration (Beijing), Chongqing University 33

34 Causes Analysis & Seismic Design of Equipments Supplement of Isolation & Dissipation Design for Electrical Power Facility For facilities located at area of high intensity, which is unable to satisfy seismic requirements or subjected to higher or specialized requirements, this article applies. Capacitor(NewZealand) Reactor(USA) 34

35 Causes Analysis & Seismic Design of Equipments Tipical Isolation & Dissipation Design Surge Arrester(Japan) 35

36 Causes Analysis & Seismic Design of Equipments Tipical Isolation & Dissipation Design: Bushing Acceleration Rate From 1.02g Down to 0.289g Isolation Test for Transformer Bushing(UC) 36

37 Causes Analysis & Seismic Design of Equipments Tipical Isolation & Dissipation Design FPS-isolation System:Relate to Surface Radius & Gravity Coefficients,Independant of mass 37

38 Causes Analysis & Seismic Design of Equipments Research Have Down After Wenchuan Earthquake: Lounch a Project "Research on Damage of Power Equipments at Wenchuan Earthquake" Together withtongji University "Research on 500kV Ya'an Substation Bushing Damage at 4.20 Lushan Earthquake" 38

39 Causes Analysis & Seismic Design of Equipments Isolation & Dissipation Design and Application for 220kV Xiameng Substation Post Insulator Transformer Base 39

40 Causes Analysis & Seismic Design of Equipments Analysis on Transformer Bushing Breakage at 500kV Ya'an Substation High Seismic Intensity Level 9, Almost Upper Limit Bushing Structure? 1. Connected by caging devices 2. Large gravitational torque Materials? Easy to Damage Bushing of Transformer 1# after Disassembly 40

41 Causes Analysis & Seismic Design of Equipments Comparison of Bushing Connection Type of Connection Clamped by Caging Devices Pouring Connected Prons Mature Tech., Easy for Installation, with Certain Resiliance and Deflection As a Whole, Easy to Withstand Earthquake of Certain Level Cons High Cost, Vulnerable Subjected to Collision Highly Rely on Intensity of Porcelain Shed, Can Lead to Devastating Result Subjected to Violent Earthquake 41

42 Causes Analysis & Seismic Design of Equipments Seimic Design of Power System Equipments No. Suggestions for Equipments Withstanding Earthquake 1 Use High Intensity Porcelain Material or Silicon Envilope 2 Select Post Insulator with High Intensity Porcelain and Equipments with Solid Insulator as Support 3 Use Equipments with Low Centre of Gravity, such as GIS, HGIS etc. 4 Suggest Not to Use Rod Insulator Supported Distribution Equipment of Tubular Bus Bar, Aluminum Tubular Bus Bar is Suggested to use Suspension Insulator 5 Use Damping Devices for Equipments Easy Subjected to Resonance Oscillation, Therefore Change System Frequency and Damping Ratio 6 Renforce Floating Equipments Connection to Avoid Transposition or Collapse 7 Considering 3/2 Connection Scheme unless Equipments and Site Area Allow 42

43 Causes Analysis & Seismic Design of Equipments Research Plan Project: Study on Substation Equipments Vulnerability at High Seismic Intensity Area of Sichuan 1 Analysis of Failure mode and Law of Electrical Equipments in Earthquake 2 Exploration of Evaluation Approach for Level of Damage to Substation Equipments 3 Evalution of Seismic Withstand ability for Substation & its Equipments at High Intensity Area of Sichuan 4 Evaluation of Substation Capability to Withstand Earthquake as a Whole, Propose Scheme for Capablity Improvement 5 Proposing Optimal Solutions to Flange Connection of Bushing Type Equipments 43

44 Thank You for your attention! 44

Seismic Considerations of Circuit Breakers

Seismic Considerations of Circuit Breakers Seismic Considerations of Circuit Breakers Willie Freeman, IEEE 693 Working Group ABB Inc, Mt. Pleasant PA, USA IEEE Tutorial - 2008 Abstract: The tutorial covers the seismic qualification of high voltage

More information

Seismic-Resistant Switchboards Conforming to New Regulatory Standards Concerning Commercial Nuclear Reactors

Seismic-Resistant Switchboards Conforming to New Regulatory Standards Concerning Commercial Nuclear Reactors Seismic-Resistant Switchboards Conforming to New Regulatory Standards Concerning Commercial Nuclear Reactors KONNO, Masayuki * FUJIMOTO, Yoshio NAGASAWA, Takenori A B S T R A C T Nuclear power plants and

More information

4 September 2010 and 22 February 2011 Christchurch Earthquakes from a Transmission Grid Infrastructure Perspective

4 September 2010 and 22 February 2011 Christchurch Earthquakes from a Transmission Grid Infrastructure Perspective 4 September 2010 and 22 February 2011 Christchurch Earthquakes from a Transmission Grid Infrastructure Perspective Asset Structural Performance and Lessons Learned By Craig McGhie and Christophe Tudo-Bornarel

More information

POLYMER HOUSED SURGE ARRESTORS

POLYMER HOUSED SURGE ARRESTORS POLYMER HOUSED SURGE ARRESTORS March 2015 Engineering Department WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED Regd. Office: VidyutBhawan, Block DJ, Sector-II, Bidhannagar, Kolkata 700091.

More information

CIGRE Seismic Behavior of Siemens Circuit Breakers during the Earthquake on 27 February 2010 in Chile. October 19th, 2010

CIGRE Seismic Behavior of Siemens Circuit Breakers during the Earthquake on 27 February 2010 in Chile. October 19th, 2010 CIGRE 2010 Seismic Behavior of Siemens Circuit Breakers during the Earthquake on 27 February 2010 in Chile October 19th, 2010 Siemens circuit breaker sold by factory Berlin and percentage of CB with seismic

More information

Section-12 (Revision 01 dated ) Page 1 of 9. SPECIAL CONDITIONS OF CONTRACT (for both parts A and B) 12.

Section-12 (Revision 01 dated ) Page 1 of 9. SPECIAL CONDITIONS OF CONTRACT (for both parts A and B) 12. Section-12 (Revision 01 dated 05.05.2006) Page 1 of 9 SPECIAL CONDITIONS OF CONTRACT (for both parts A and B) 12.0 TERMS OF PAYMENT 12.0.1 The contractor should submit his monthly on account bills with

More information

Seismic Reliability Evaluation of Electrical Power Transmission Systems and its Effect on Core Damage Frequency

Seismic Reliability Evaluation of Electrical Power Transmission Systems and its Effect on Core Damage Frequency Seismic Reliability Evaluation of Electrical Power Transmission Systems and its Effect on Core Damage Frequency Tetsukuni OIKAWA 1), Sei ichiro FUKUSHIMA 2), Hidekazu TAKASE 2), Tomoaki UCHIYAMA MURAMATSU

More information

Study Committee A3. High Voltage Equipment. Action Plan

Study Committee A3. High Voltage Equipment. Action Plan Study Committee A3 High Voltage Equipment Action Plan October 2011 CIGRE Study Committee A3 - High Voltage Equipment Action Plan 1 Content 1 Content...2 2 Purpose of the Action Plan...3 3 Activities of

More information

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

This section applies to the requirements for electrical Inspection, calibration, and testing.

This section applies to the requirements for electrical Inspection, calibration, and testing. Basis of Design This section applies to the requirements for electrical Inspection, calibration, and testing. Design Criteria Edit attached guide specification, as required, to meet the project requirements.

More information

B. Provide liquid-filled secondary substation transformers as indicated on drawings.

B. Provide liquid-filled secondary substation transformers as indicated on drawings. SECTION 26 12 13 PART 1 - GENERAL 1.01 WORK INCLUDED A. Comply with the provisions of Sections 26 05 00. B. Provide liquid-filled secondary substation transformers as indicated on drawings. 1.02 RELATED

More information

Candidate NICET ID No.: NICET ENGINEERING TECHNICIAN CERTIFICATION Experience Application, Part II: Verifier Data. (Please print legibly or type)

Candidate NICET ID No.: NICET ENGINEERING TECHNICIAN CERTIFICATION Experience Application, Part II: Verifier Data. (Please print legibly or type) Candidate: Experience Application, Part II: Verifier Data Candidate NICET ID No.: SM Standard Model (Please print legibly or type) To be completed by the Verifier only Name: Title: Current employer: Daytime

More information

Station Post Insulators (SPI), an Emerging Application for Composite Hollow Core Insulators PETER STAHL

Station Post Insulators (SPI), an Emerging Application for Composite Hollow Core Insulators PETER STAHL Station Post Insulators (SPI), an Emerging Application for Composite Hollow Core Insulators PETER STAHL Composite Hollow Core Station Post Insulators (SPI) Peter Stahl, July 2015 Applications for composite

More information

IEC Oil Filled & SF 6 Gas Current Transformers

IEC Oil Filled & SF 6 Gas Current Transformers g IEC Oil Filled & SF 6 Gas Current Transformers 72.5kV - 550kV (325kV - 1550kV BIL) with Primary Plus TM Pre-engineered solution set that digitizes XD GE primary equipment and provides factory installed

More information

Designated Entity Design Standards Task Force (DEDSTF) Minimum Design Requirements for FERC Order 1000 Projects. System Protection Subgroup

Designated Entity Design Standards Task Force (DEDSTF) Minimum Design Requirements for FERC Order 1000 Projects. System Protection Subgroup Designated Entity Design Standards Task Force (DEDSTF) Minimum Design Requirements for FERC Order 1000 Projects System Protection Subgroup For any substation facility included in the scope of a transmission

More information

Pre-Qualification Certificate

Pre-Qualification Certificate Nordic Utility Pre-Qualification System Pre-Qualification Certificate Awarded to Registration number: 984 277 032 Sellihca Id: Sellihca Qualification hereby confirms that is now fully registered as a supplier

More information

Report Number: G Date: February 3, 2012 INTRODUCTION

Report Number: G Date: February 3, 2012 INTRODUCTION Bul l et i neu1595 Report Number: G12-02-01 Date: February 3, 2012 INTRODUCTION The industry standard to which Hubbell Power Systems - Ohio Brass qualifies the seismic capability of its arresters is IEEE

More information

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria March 2016 Section 1 Overview and General Discussion The primary purpose of East Kentucky Power Cooperative s (EKPC s) transmission

More information

Manufacturing and Application of Cage Design High Voltage Metal Oxide Surge Arresters

Manufacturing and Application of Cage Design High Voltage Metal Oxide Surge Arresters Manufacturing and Application of Cage Design High Voltage Metal Oxide Surge Arresters K. Steinfeld, B. Kruska and W. Welsch Siemens Surge Arresters and Limiters, Berlin, Germany Abstract: Metal oxide surge

More information

FIELD TEST AND OPERATIONAL CHECK SECTION A. Refer to Section 16010, Electrical General Requirements.

FIELD TEST AND OPERATIONAL CHECK SECTION A. Refer to Section 16010, Electrical General Requirements. FIELD TEST AND OPERATIONAL CHECK SECTION 16080 PART 1 GENERAL 1.1 GENERAL REQUIREMENTS A. Refer to Section 16010, Electrical General Requirements. 1.2 WORK INCLUDED A. General Scope: 1. The Contractor

More information

STANDARD DRAWINGS. September 2013 UPDATED FEBRUARY 2016

STANDARD DRAWINGS. September 2013 UPDATED FEBRUARY 2016 STANDARD DRAWINGS September 2013 UPDATED FEBRUARY 2016 CONSTRUCTION STANDARD DRAWINGS DIVISION 15 LIST OF DRAWINGS: 1. 01 2004-1 Rev. A - Concrete Standards General Outline and Reinforcement Notes 2. 01

More information

Company Introduction and Information EPTCON LTD. 560 SHELDON DRIVE, CAMBRIDGE ONTARIO. PHONE:

Company Introduction and Information EPTCON LTD. 560 SHELDON DRIVE, CAMBRIDGE ONTARIO. PHONE: Company Introduction and Information EPTCON LTD. 560 SHELDON DRIVE, CAMBRIDGE ONTARIO. PHONE: 519 620 4414 WWW.EPTCON.COM Company Background ABOUT US EPTCON Ltd. (Electrical Power & Transmission Construction),

More information

Summary of Seismic Reliability in Electric Power System

Summary of Seismic Reliability in Electric Power System Summary of Seismic Reliability in Electric Power System WEN Bo 1 AND NIU Di-tao 2, ZHAO Peng 3 1 Doctoral Candidate, Dept. of Civil Engineering, Xi an University of Architecture & Technology, Xi an. China

More information

2009 NZSEE Conference 2-5 April Christchurch ESTIMATING SEISMIC IMPACTS ON LIFELINES: AN INTERNATIONAL REVIEW FOR RISKSCAPE

2009 NZSEE Conference 2-5 April Christchurch ESTIMATING SEISMIC IMPACTS ON LIFELINES: AN INTERNATIONAL REVIEW FOR RISKSCAPE 2009 NZSEE Conference 2-5 April Christchurch ESTIMATING SEISMIC IMPACTS ON LIFELINES: AN INTERNATIONAL REVIEW FOR RISKSCAPE Sonia GIOVINAZZI 1 and Andrew KING 2 1 University of Canterbury 2 GNS Science

More information

NIGERIA ELECTRICITY TRANSMISSION PROJECT (NETAP)

NIGERIA ELECTRICITY TRANSMISSION PROJECT (NETAP) NIGERIA ELECTRICITY TRANSMISSION PROJECT (NETAP) TERMS OF REFERENCE (TOR) For TECHNICAL ASSISTANCE FOR ENGINEERING SUPERVISION AND SITE MANAGEMENT OF REHABILITATION & REINFORCEMENT OF 330/132kV & 132/33kV

More information

SECTION ENCLOSED BUS ASSEMBLIES

SECTION ENCLOSED BUS ASSEMBLIES SECTION 262500 ENCLOSED BUS ASSEMBLIES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

Product brochure Multi Functional Switchgear PASS M kv Flexible and compact switchgear solutions for windfarms

Product brochure Multi Functional Switchgear PASS M kv Flexible and compact switchgear solutions for windfarms Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms The future of Wind Farms In 2010, offshore wind farms accounted for 9.5% of the overall

More information

SPECIFICATIONS FOR Gas-to-Cable termination

SPECIFICATIONS FOR Gas-to-Cable termination Product GSM-145 1.0 APPLICATION: Gas-to-cable termination is a part of high voltage gas insulated indoor switchgear equipment. The component is intended for a high voltage system of 132 kv (AC), 50 Hz.

More information

Transient Stability Analysis of an Industrial Cogeneration System

Transient Stability Analysis of an Industrial Cogeneration System Transient Stability Analysis of an Industrial Cogeneration System Hung-Cheng Chen Shang-Yi Chen Shun-Chung Shih Department of Electrical Engineering, National Chin-Yi University of Technology hcchen@ncut.edu.tw

More information

Important Considerations for Specifying MV Mining Switchgear Western Mining Electrical Association Edmonton, Canada June 13, 2008

Important Considerations for Specifying MV Mining Switchgear Western Mining Electrical Association Edmonton, Canada June 13, 2008 Important Considerations for Specifying MV Mining Switchgear Western Mining Electrical Association Edmonton, Canada June 13, 2008 (Above 1000V and up to 38kV for Surface Mining) Key Components of Specification:

More information

FIBRE REINFORCED PLASTICS IN HIGH VOLTAGE APPLICATIONS

FIBRE REINFORCED PLASTICS IN HIGH VOLTAGE APPLICATIONS FBRE RENFORCED PLASTCS N HGH VOLTAGE APPLCATONS Volker Bergmann, Reinhausen Power Composites GmbH Page 1 OVERVEW 1. ntroduction 2. Hollow core composite insulators and their application 3. Dielectric and

More information

TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION IEC/TS 62371 TECHNICAL SPECIFICATION Edition 1.0 2008-05 Characteristics of hollow pressurised and unpressurised ceramic and glass insulators for use in electrical equipment with rated voltages greater

More information

Code No: II B. Tech II Semester Regular Examinations, April/May 2009 POWER SYSTEMS I. ( Electrical & Electronics Engineering)

Code No: II B. Tech II Semester Regular Examinations, April/May 2009 POWER SYSTEMS I. ( Electrical & Electronics Engineering) Code No: 3220201 II B. Tech II Semester Regular Examinations, April/May 2009 SET - 1 POWER SYSTEMS I ( Electrical & Electronics Engineering) Time: 3 hours Max Marks: 80 Answer Any FIVE Questions All Questions

More information

DRAFT. GUIDELINES FOR Usage of AIR INSULATED SUBSTATION (AIS) or GAS INSULATED SUBSTATION(GIS)

DRAFT. GUIDELINES FOR Usage of AIR INSULATED SUBSTATION (AIS) or GAS INSULATED SUBSTATION(GIS) DRAFT GUIDELINES FOR Usage of AIR INSULATED SUBSTATION (AIS) or GAS INSULATED SUBSTATION(GIS) CENTRAL ELECTRICITY AUTHORITY 2018 1. Introduction Substations are an important part of the electrical distributions.

More information

SUMMARY OF PRICES FOR 30MVA 161/24/36 kv MOBILE SUBSTATION ACCORDING to SR-152

SUMMARY OF PRICES FOR 30MVA 161/24/36 kv MOBILE SUBSTATION ACCORDING to SR-152 Israel Electric Corporation Ltd. Tender no. Name of Contractor: SUMMARY OF PRICES FOR 30MVA 161/24/36 kv MOBILE SUBSTATION ACCORDING to SR-152 1. GENERAL INSTRUCTIONS 2.1. Prices for the above captioned

More information

Composite Insulator Components

Composite Insulator Components Composite Insulator Components Composite insulator components A composite insulator is made of at least two insulating parts a core and housing. It is equipped with end fittings. Core. The core is the

More information

SECTION SECONDARY UNIT SUBSTATIONS

SECTION SECONDARY UNIT SUBSTATIONS SECTION 26 12 16 SECONDARY UNIT SUBSTATIONS PART 1 GENERAL 1.1 SUMMARY This section describes metal-clad, indoor or outdoor, secondary unit substations with integral primary fused disconnect switches,

More information

GROUP A. Polymeric Insulators.

GROUP A. Polymeric Insulators. GROUP A Polymeric Insulators PYUNGIL Bldg., 1475-10, Gwanyang 2-dong, Dongan-gu, Anyang-si, Gyeonggi-do, 431-808, Korea Tel : 82-31-420-6650~3 FAX : 82-31-424-7300 www.pyungil.com Silicone Railway

More information

High Voltage Products. High Voltage Products Service Professionals at your service. Power and productivity for a better world TM

High Voltage Products. High Voltage Products Service Professionals at your service. Power and productivity for a better world TM High Voltage Products High Voltage Products Service Professionals at your service Power and productivity for a better world TM High Voltage Products Service Professionals at your service The increasing

More information

SECTION SECONDARY UNIT SUBSTATIONS

SECTION SECONDARY UNIT SUBSTATIONS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 11 16 SECONDARY UNIT SUBSTATIONS SPEC WRITER NOTE: Delete between //----// if not applicable to project. Also delete any other item or paragraph not applicable

More information

DESIGN OF ENERGY DISSIPATOR DEVICES TO PROTECT EQUIPMENTS OF A 400 KV POWER SUBSTATION AGAINST EARTHQUAKE IN NEISHABOUR - IRAN

DESIGN OF ENERGY DISSIPATOR DEVICES TO PROTECT EQUIPMENTS OF A 400 KV POWER SUBSTATION AGAINST EARTHQUAKE IN NEISHABOUR - IRAN 13 th World Conference on Earthquake Engineering Vancouver, B.C., Canada August 1-6, 2004 Paper No. 3262 DESIGN OF ENERGY DISSIPATOR DEVICES TO PROTECT EQUIPMENTS OF A 400 KV POWER SUBSTATION AGAINST EARTHQUAKE

More information

POWER TRANSFORMER INSTALLATION

POWER TRANSFORMER INSTALLATION Project Procedure POWER TRANSFORMER INSTALLATION No.: P-6.2-8-1 07/20/2011 PAGE 1 OF 6 1.0 PURPOSE The purpose of this procedure is to ensure that power transformer installations are accomplished in compliance

More information

ISO Rules Part 500, Facilities Division 502, Technical Requirements Section Bulk Transmission Technical Requirements

ISO Rules Part 500, Facilities Division 502, Technical Requirements Section Bulk Transmission Technical Requirements Part 500, Facilities Division 502, Technical Requirements Section 502.2 Bulk Transmission Technical Requirements Applicability 1 This section 502.2 applies to: Requirements the legal owner of any bulk

More information

I. CLARIFICATIONS SOUGHT BY PROSPECTIVE BIDDERS

I. CLARIFICATIONS SOUGHT BY PROSPECTIVE BIDDERS This clarification forms part of the Request for Proposal and Contract documents, and modifies them as follows: I. CLARIFICATIONS SOUGHT BY PROSPECTIVE BIDDERS S. No. 1. Refer to section Bid Data Sheet

More information

ELECTRICITY SUPPLY - POWER SYSTEM MAINTENANCE Carry out routine inspection and service on oil filled distribution power transformers 11kV to 400V

ELECTRICITY SUPPLY - POWER SYSTEM MAINTENANCE Carry out routine inspection and service on oil filled distribution power transformers 11kV to 400V 1 of 8 level: 4 credit: 8 planned review date: December 2006 sub-field: purpose: entry information: Electricity Supply People credited with this unit standard are able to: prepare for routine service transformers

More information

Technical report on alternative to SF6 gas in medium voltage & high voltage electrical equipment

Technical report on alternative to SF6 gas in medium voltage & high voltage electrical equipment TECHNICAL REPORT 20/02/2018 Technical report on alternative to SF6 gas in medium voltage & high voltage electrical equipment T&D Europe aisbl 1 FOREWORD... 4 1 - METHODOLOGY... 4 2 - SCOPE... 5 3 - INTRODUCTION...

More information

Low Voltage Switchgear Construction Checklist (under 500 kva)

Low Voltage Switchgear Construction Checklist (under 500 kva) Low Voltage Switchgear Checklist (under 500 kva) Project: Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing.

More information

MONTE CARLO SIMULATION FOR THE SEISMIC RESPONSE ANALYSIS OF ELECTRIC POWER SYSTEM IN TAIWAN

MONTE CARLO SIMULATION FOR THE SEISMIC RESPONSE ANALYSIS OF ELECTRIC POWER SYSTEM IN TAIWAN MONTE CARLO SIMULATION FOR THE SEISMIC RESPONSE ANALYSIS OF ELECTRIC POWER SYSTEM IN TAIWAN Gee-Yu Liu National Center for Research on Earthquake Engineering, Taipei, Taiwan karl@ncree.gov.tw C.-W. Liu

More information

FINAL REPORT SUMMARY. November Prepared for: The Ministry of Economy, Trade and Industry. Prepared by:

FINAL REPORT SUMMARY. November Prepared for: The Ministry of Economy, Trade and Industry. Prepared by: Feasibility Study for Promotion of International Infrastructure Projects in FY2011 STUDY ON THE SUBSTATION REHABILITATION PROJECT IN YANGON, THE REPUBLIC OF THE UNION OF MYANMAR FINAL REPORT SUMMARY November

More information

Recent Technical Trends of Vacuum Circuit-Breakers (VCBs)

Recent Technical Trends of Vacuum Circuit-Breakers (VCBs) Switchgear Technical Trends and Basic Technologies Recent Technical Trends of Vacuum Circuit-Breakers (VCBs) Hitoshi Saito, Makoto Honma, Masayuki Sakaki Keywords Circuit-breaker, Switchgear, Vacuum interrupter,

More information

DISTRIBUTION OPERATIONS AND MAINTENANCE

DISTRIBUTION OPERATIONS AND MAINTENANCE EB-00-00 Exhibit F Tab Schedule Filed: 00 Aug Page of DISTRIBUTION OPERATIONS AND MAINTENANCE 0 PREDICTIVE MAINTENANCE Predictive maintenance expenditures fund work that is required to test and audit distribution

More information

A. Section includes busway and fittings including plug-in units.

A. Section includes busway and fittings including plug-in units. SECTION 26 25 00 ENCLOSED BUS ASSEMBLIES PART 1 - GENERAL 1.1 SUMMARY A. Section includes busway and fittings including plug-in units. 1.2 REFERENCES A. Institute of Electrical and Electronics Engineers:

More information

Mica Gas Insulated Switchgear (GIS) Replacement Project Workshop

Mica Gas Insulated Switchgear (GIS) Replacement Project Workshop B-3 Mica Gas Insulated Switchgear (GIS) Replacement Project Workshop 26 August 2009 Agenda Mica GIS Replacement Project BCUC Order Mica Generating Station and GIS equipment Need for the Project Project

More information

9KV/18KV METAL OXIDE LIGHTNING ARRESTORS WITHOUT GAPS WITH STANDARD NOMINAL DISCHARGE CURRENT 5KA

9KV/18KV METAL OXIDE LIGHTNING ARRESTORS WITHOUT GAPS WITH STANDARD NOMINAL DISCHARGE CURRENT 5KA 9KV/18KV METAL OXIDE LIGHTNING ARRESTORS WITHOUT GAPS WITH STANDARD NOMINAL DISCHARGE CURRENT 5KA Technical specification for 9KV/18KV 5KA Metal oxide Lightning Arrestors without Gap. ----------------------------------------------------------------------------------------------------------------

More information

Grid Interconnection Issues for Wind Generation

Grid Interconnection Issues for Wind Generation Grid Interconnection Issues for Wind Generation NRECA APPA - DOE Teleconference December 8, 2005 By Thomas A. Wind, PE Wind Utility Consulting Jefferson, Iowa Topics I Will Cover What are the key technical

More information

Duresca. Duresca. Tiresca. Travesca. Gaslink

Duresca. Duresca. Tiresca. Travesca. Gaslink MGCExpertise Product range: Duresca Busbar system Duresca Wall bushings Tiresca Busbar system Travesca Transformer bushings Gaslink Busbar system 3 4 one... 5...team 6 Summary Product range 2 Preface 3

More information

Introduction to Substation Design TADP 542

Introduction to Substation Design TADP 542 Introduction to Substation Design TADP 542 Design Principles- General Framework Instructor: Richard Snell Transmission & Distribution Program Module 2 Outline Presentation 1: General Framework Presentation

More information

The Earthquake Actions and Testing Approaches for Curtain Wall

The Earthquake Actions and Testing Approaches for Curtain Wall 2013 UBC-Tongji-CSRN Symposium The Earthquake Actions and Testing Approaches for Curtain Wall Yangling Wang, Wensheng Lu, Baofeng Huang E-mail:wenshenglu@vip.163.com State Key Laboratory Of Disaster Reduction

More information

--> Buy True-PDF --> Auto-delivered in 0~10 minutes. GB Translated English of Chinese Standard: GB

--> Buy True-PDF --> Auto-delivered in 0~10 minutes. GB Translated English of Chinese Standard: GB GB50303-2002 GB 50303-2002 Translated English of Chinese Standard: GB50303-2002 NATIONAL STANDARD OF THE PEOPLE S REPUBLIC OF CHINA Excerpt / simplified PDF version (some pages are intentionally omitted)

More information

NEPAL ELECTRICITY AUTHORITY (An Undertaking of Government of Nepal) Project Management Directorate

NEPAL ELECTRICITY AUTHORITY (An Undertaking of Government of Nepal) Project Management Directorate NEPAL ELECTRICITY AUTHORITY (An Undertaking of Government of Nepal) SAMUNDRATAR TRISHULI 3B HUB 132 KV TRANSMISSION LINE PROJECT BIDDING DOCUMENT FOR DESIGN, SUPPLY AND CONSTRUCTION OF 132/33 KV SUBSTATION

More information

Pacific Earthquake Engineering Research Center

Pacific Earthquake Engineering Research Center Pacific Earthquake Engineering Research Center Development of an Electrical Substation Equipment Performance Database for Evaluation of Equipment Fragilities Thalia Anagnos San Jose State University PEER

More information

Advances in Computer Science Research, volume 63 International Conference on Artificial Intelligence and Engineering Applications (AIEA 2016)

Advances in Computer Science Research, volume 63 International Conference on Artificial Intelligence and Engineering Applications (AIEA 2016) International Conference on Artificial Intelligence and Engineering Applications (AIEA 2016) Quality Importance Evaluation for Wind/Photovoltaic Energy Storage and Transmission Demonstration Project via

More information

Distribution Tradesperson (Jobsplus Permit No. 706/2017)

Distribution Tradesperson (Jobsplus Permit No. 706/2017) CAREER OPPORTUNITIES Enemalta plc is the leading energy service provider in the Maltese Islands, entrusted with the generation and distribution of electricity and the development of the national electricity

More information

Public Utility District Number 1 of Snohomish County

Public Utility District Number 1 of Snohomish County Public Utility District Number 1 of Snohomish County Facility Connection Requirements September 29, 2011 1 Revision History: Number Date Description Original Sept. 29, 2011 Document Origination Compilation

More information

Potential and E-Field Calculation Along an Ice- Covered Composite Insulator with Finite Element Method

Potential and E-Field Calculation Along an Ice- Covered Composite Insulator with Finite Element Method Potential and E-Field Calculation Along an Ice- Covered Composite Insulator with Finite Element Method Qing Yang, Caixin Sun, Wenxia Sima, Lichun Shu, Ji Yang, Jianlin Hu The Key Laboratory of High Voltage

More information

Introduction of an innovative base isolation system for seismic protection of HV components based on a combination of wire ropes and viscous dampers

Introduction of an innovative base isolation system for seismic protection of HV components based on a combination of wire ropes and viscous dampers Earthquake Resistant Engineering Structures X 147 Introduction of an innovative base isolation system for seismic protection of HV components based on a combination of wire ropes and viscous dampers M.

More information

ACS OTHER PRIMARY EQUIPMENT

ACS OTHER PRIMARY EQUIPMENT ACS OTHER PRIMARY EQUIPMENT Fleet Strategy Document 31/10/2013 Transpower New Zealand Limited 2013. All rights reserved. Page 1 of 70 C O P Y R I G H T 2013 T R A N S P O W E R N E W Z E A L A N D L I

More information

IBC-2003 Seismic Rating What s Shakin? The IBC and IEEE seismic standards and the seismic qualification process

IBC-2003 Seismic Rating What s Shakin? The IBC and IEEE seismic standards and the seismic qualification process GE Consumer & Industrial Electrical Distribution IBC-2003 Seismic Rating What s Shakin? The IBC and IEEE seismic standards and the seismic qualification process BACKGROUND International Building Code 2003

More information

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017 Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA March 21, 2017 Contents 1 Background...3 2 National and Regional Criteria and Guides...4 2.1 2.1 NERC Transmission Planning Standards...4 2.2

More information

Cast Resin LV Busway (IP68) Taiwan Busway Company

Cast Resin LV Busway (IP68) Taiwan Busway Company Cast Resin LV Busway (IP68) Taiwan Busway Company TBC Company Overview Taiwan Busway Company, Ltd. Est. 2002; located in Taipei Brand: TBC Busway market leader in Taiwan, presence in China, Germany/ Europe,

More information

What to Look for in a Good Quality Arrester

What to Look for in a Good Quality Arrester All good quality arresters have much in common. This first in a series of articles, sponsored by NEMA Surge Arrester Section members, covers what to look for in that quality arrester. Introduction We've

More information

Transmission Line General Requirements Including Typical Overhead Line Structures. Document Number: 1-03-FR-09

Transmission Line General Requirements Including Typical Overhead Line Structures. Document Number: 1-03-FR-09 Transmission Line General Requirements Including Typical Overhead Line Structures Document Number: 1-03-FR-09 VERSION 1.0 June 2018 This functional requirements document is in line with the organisation's

More information

GUYANA POWER AND LIGHT INC

GUYANA POWER AND LIGHT INC GUYANA POWER AND LIGHT INC The Terms of Reference REQUEST FOR PROPOSALS: CONSULTANCY SERVICES COORDINATING GENERATOR PROTECTION WITH TRANSMISSION PROTECTION AND GENERATOR CONTROLS (GPL-PI-094-2016) November

More information

Bharat Heavy Electricals Limited. Ceramic Business Unit. ollow. An ISO 9001, & Certified Company

Bharat Heavy Electricals Limited. Ceramic Business Unit. ollow. An ISO 9001, & Certified Company Bharat Heavy Electricals Limited Ceramic Business Unit ollow An ISO 9001, 14001 & 18001 Certified Company Hollow 1 Alternate shed Plain shed 2 1 Flange 2 Porcelain Shell 3 Ground Collar 3 Straight bore

More information

Wenchuan Earthquake Impact to Power Systems. John Eidinger 1

Wenchuan Earthquake Impact to Power Systems. John Eidinger 1 Wenchuan Earthquake Impact to Power Systems John Eidinger 1 1 G&E Engineering Systems Inc., P. O. Box 3592 Olympic Valley, CA 96146-3592; eidinger@earthlink.net ABSTRACT The Wenchuan M 7.9 earthquake of

More information

A Proper Design of Wind Turbine Grounding Systems under Lightning

A Proper Design of Wind Turbine Grounding Systems under Lightning A Proper Design of Wind Turbine Grounding Systems under Lightning M. A. Abd-Allah, Mahmoud N. Ali, A. Said Abstract Lightning protection systems (LPS) for wind power generation is becoming an important

More information

Practical Experience Gained from Dissolved Gas Analysis at an Aluminium Smelter. Ian.A.R. Gray

Practical Experience Gained from Dissolved Gas Analysis at an Aluminium Smelter. Ian.A.R. Gray Practical Experience Gained from Dissolved Gas Analysis at an Aluminium Smelter Ian.A.R. Gray Largest aluminium smelter in the Southern hemisphere South Africa's major producer of primary aluminium It

More information

Transmission Silicone Insulators Line Post 69 kv to 230 kv

Transmission Silicone Insulators Line Post 69 kv to 230 kv K-LINE INSULATORS LIMITED Catalogue T-LP Transmission Silicone Insulators Line Post 69 kv to 230 kv ISO9001 SAI GLOBAL FILE No. 000117 Transmission Silicone Insulators Line Post Today transmission lines

More information

Electric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas

Electric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas Electric Power Systems An Overview Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas Overview Power Generation Conventional and renewable power generation Power transmission

More information

500 MW Wind Farm Technical System Impact Study

500 MW Wind Farm Technical System Impact Study FINAL REPORT Report to: El Paso Electric for 500 MW Wind Farm Technical System Impact Study Prepared by: Goran Drobnjak Sang Lee Emad Ahmed Reigh Walling Einar Larsen February 19, 2008 EPE_TechSIS_Final.doc

More information

Proposed Facility Study Report. Project: A380_A383_A415_A414_A413 MISO # F088. Prepared for Midwest ISO

Proposed Facility Study Report. Project: A380_A383_A415_A414_A413 MISO # F088. Prepared for Midwest ISO Proposed Facility Study Report Project: A380_A383_A415_A414_A413 MISO # F088 Prepared for Midwest ISO January 15 th, 2010 Great River Energy Contact: Greg Schutte, Project Manager Great River Energy 1

More information

Electric Power Systems An Overview

Electric Power Systems An Overview Electric Power Systems An Overview Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas Overview Power Generation Conventional and renewable power generation Power transmission

More information

Details of technical leaflets/write-up on various pieces of equipment.

Details of technical leaflets/write-up on various pieces of equipment. Details of technical leaflets/write-up on various pieces of equipment. (1) Insulator Designs: The insulators are provided in one, two, three, or four insulator designs per location and spaced to provide

More information

WEST ZONE POWER DISTRIBUTION CO. LTD. (WZPDCL) TENDER DOCUMENT FOR

WEST ZONE POWER DISTRIBUTION CO. LTD. (WZPDCL) TENDER DOCUMENT FOR WEST ZONE POWER DISTRIBUTION CO. LTD. (WZPDCL) TENDER DOCUMENT FOR SUPPLY, DELIVERY, INSTALLATION, TESTING AND COMMISSIONING OF 2 NOS. (MOHESSORPASA (KHULNA) & CAMPUS (KUSHTIA)) 33/11 KV 2X20/26.66 MVA

More information

Carry out routine inspection and service on high voltage indoor metal clad circuit breakers and bus

Carry out routine inspection and service on high voltage indoor metal clad circuit breakers and bus Page 1 of 7 Carry out routine inspection and service on high voltage indoor metal clad circuit breakers and bus Level 4 Credits 4 Purpose People credited with this unit standard are able to: prepare for

More information

Parameter Analysis and Shaking Table Test on Seismic Isolation System of Transformer with Bushings

Parameter Analysis and Shaking Table Test on Seismic Isolation System of Transformer with Bushings Parameter Analysis and Shaking Table Test on Seismic Isolation System of Transformer with Bushings CAO Mei-gen, CHENG Yong-feng & DAI Ze-bing China Electric Power Research Institute of SGCC, Beijing ZHOU

More information

Platte River Power Authority. Ten-Year Transmission Plan ( )

Platte River Power Authority. Ten-Year Transmission Plan ( ) Platte River Power Authority Ten-Year Transmission Plan (2015-2024) Prepared by PRPA System Planning December 31, 2014 Table of Contents I. Executive Summary II. III. IV. Scope Assumptions Criteria V.

More information

High Energy Arcing Faults (HEAF) and Their Impact on PRA for a Nuclear Power Plant Latest International Operating Experience and Research Activities

High Energy Arcing Faults (HEAF) and Their Impact on PRA for a Nuclear Power Plant Latest International Operating Experience and Research Activities High Energy Arcing Faults (HEAF) and Their Impact on PRA for a Nuclear Power Plant Latest International Operating Experience and Research Activities Marina Roewekamp GRS ggmbh, Germany Nicholas Melly,

More information

Structural Performance Assessment and Control of Super Tall Buildings During Construction

Structural Performance Assessment and Control of Super Tall Buildings During Construction Available online at www.sciencedirect.com Procedia Engineering 14 (211) 253 251 The Twelfth East Asia-Pacific Conference on Structural Engineering and Construction Structural Performance Assessment and

More information

COMPANY PROFILE INESING SPA

COMPANY PROFILE INESING SPA COMPANY PROFILE INESING SPA HISTORY The Company INESING has matured in the lasts 10 years the experience, knowledge and professionalism at the highest level, consolidating its presence in the market for

More information

PRY-MOULD. High Voltage Accessories for Extruded Cables

PRY-MOULD. High Voltage Accessories for Extruded Cables PRY-MOULD High Voltage Accessories for Extruded Cables Linking the future As the worldwide leader in the cable industry, Prysmian Group believes in the effective, efficient and sustainable supply of energy

More information

SECTION BUSWAYS

SECTION BUSWAYS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 25 11 BUSWAYS SPEC WRITER NOTE: Delete between //----// if not applicable to project. Also delete any other item or paragraph not applicable to the section and

More information

MSME Testing Centre, 65/1, G. S. T. Road, Guindy, Chennai, Tamil Nadu. Discipline Electrical Testing Issue Date

MSME Testing Centre, 65/1, G. S. T. Road, Guindy, Chennai, Tamil Nadu. Discipline Electrical Testing Issue Date Last Amended on - Page 1 of 7 I. TRANSMISSION LINE EQUIPMENT & ACCESSORIES ]] 1 Stockbridge Vibration dampers for Power lines Examination & IS 9708:1993 Cl. 7.2 Cl. 7.3 Mass pull off (Slip) Cl. 7.6 120

More information

Unit Substation Transformer Construction Checklist (under 500 kva)

Unit Substation Transformer Construction Checklist (under 500 kva) Unit Substation Transformer Checklist (under 500 kva) Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing.

More information

Design features - Polymer-housed arresters, PEXLIM

Design features - Polymer-housed arresters, PEXLIM features - Polymer-housed arresters, PEXLIM PEXLIM arresters, using the same ZnO blocks as the EXLIM arresters, match their electrical performance. Silicone as outer insulation material has been used for

More information

Energy Division Insulators

Energy Division  Insulators Energy Division http://energy.tycoelectronics.com Insulators R Insulators Tyco Electronics Energy Division covers a wide range of polymeric, hybrid and porcelain insulators. For decades all these products

More information

EXPERIMENTAL AND ANALYTICAL STUDY OF A HIGH VOLTAGE INSTRUMENT TRANSFORMER

EXPERIMENTAL AND ANALYTICAL STUDY OF A HIGH VOLTAGE INSTRUMENT TRANSFORMER 13 th World Conference on Earthquake Engineering Vancouver, B.C., Canada August 1-6, 2004 Paper No. 2550 EXPERIMENTAL AND ANALYTICAL STUDY OF A HIGH VOLTAGE INSTRUMENT TRANSFORMER Mehran HATAMI 1, Mohsen

More information