Poly B Packaging Warehouse, The Dow Co. Plaquemine, LA

Size: px
Start display at page:

Download "Poly B Packaging Warehouse, The Dow Co. Plaquemine, LA"

Transcription

1 Poly B Packaging Warehouse, The Dow Co. EXCELLENCE IN CONSTRUCTION

2 Poly B Packaging Warehouse Plaquemine, LA

3 Poly B Packaging Warehouse Plaquemine, LA

4

5 Poly B Packaging Warehouse, The Dow Co. EXCELLENCE IN CONSTRUCTION CONTRACTED SCOPE Poly B Packaging Warehouse Plaquemine, LA

6 SCOPE OF WORK: The new Poly B Packaging Warehouse provides critical product storage capacity for Dow s Plaquemine plant, one of the largest petrochemical facilities in Louisiana and home to most of Dow s global businesses. The 3,000-acre integrated manufacturing site produces more than 50 different basic and specialty chemical products. The 86,000-square-foot structure includes a pre-engineered metal warehouse and precast concrete office complex. Despite flooding rains, high river stages and 25 change orders threatening to delay the project, GROUP Contractors completed the project on schedule. TYPE OF CONSTRUCTION: Pre-engineered metal building and precast office project providing vital storage capacity for Dow s Plaquemine location. Included were significant concrete forming and construction, interior buildout, finishing, HVAC, electrical and instrumentation, among other installations. Numerous subcontractors were managed to erect the buildings in overlapping phases, since high river levels and a host of change orders forced a re-sequencing of the project schedule. SIZE OF PROJECT: 86,000-square-foot in building construction at Dow Plaquemine. Buildings comprised of 10,000 cubic yards of concrete; pre-engineered metal panels; poured-in-place footings, some measuring as deep as 6 feet; concrete slabs meeting stringent 1/4-inch levelness specifications; precast panels; structural steel; interior stucco; 25 change orders; numerous days of delays caused by high river levels. CONTRACT VALUE: $8,810,000 LENGTH OF PROJECT: Contract award and notice to proceed July 6, Substantial completion August 1, PERCENTAGE OF LABOR SELF-PERFORMED: 20%; 80% of subcontracted work performed by ABC members, suppliers or associate

7 Poly B Packaging Warehouse, The Dow Co. EXCELLENCE IN CONSTRUCTION PROJECT NARRATIVE

8 GROUP s performance to accomplish this project was outstanding. This project was met with many challenging obstacles ranging from constant inclement weather to a Mississippi river lever that hindered the start of the project causing delays in ground preparations. My hats off to you, David Talbot, and the site supervisor, Dustin Cutrer, for outstanding leadership and guidance to accomplish this project work successfully and overcoming these obstacles. The work was performed safety, and with high quality, which is a direct reflection of the efforts you and your staff displayed in this task. Kerry Cautrelle, Construction Manager, Dow USA When flooding rains, high river stages and 25 change orders threatened to delay completion of the 86,000- square-foot pre-engineered metal warehouse and precast office complex at Dow s Louisiana Operations near Plaquemine, GROUP Contractors was determined to find a way to make it happen. The new Poly B Packaging Warehouse provides critical product storage capacity for Dow s Plaquemine plant, one of the largest petrochemical facilities in Louisiana and home to most of Dow s global businesses. The 3,000-acre integrated manufacturing site produces more than 50 different basic and specialty chemical products. From the beginning, the Mississippi River levels were a problem, with crews having performed only minimal work before the river stages rose to unacceptable levels, hindering work for three weeks in late summer At the time, crews had only performed some of the formwork for the building s grade beams and slabs in the MCC and office areas, and were about to begin digging for footings and walls. Given the resulting loss in time to the schedule, the owner had doubts that GROUP or any contractor for that matter could make deadline.

9 Project manager David Talbot and the GROUP field staff quickly developed a plan of action that involved working weekends, re-arranging schedules and closely collaborating with a host of subcontractors. Facing an immovable deadline, GROUP chose to begin erecting the metal warehouse building concurrently with the concrete form work. While the original schedule called for much of the foundation and formwork to have been completed prior to building erection, GROUP faced an immovable deadline, meaning certain phases had to be performed concurrently. If not, the schedule would have been severely impacted. GROUP also revised its safety plan to incorporate additional precautions since its ground crew had to work in close proximity to the steel erection crew, primarily through the addition of safety barricades and safety tape to ensure crafts didn t venture into other areas. The crane lift plan was also adjusted, as well as lift and crane locations, with all changes communicated to the entire project team. Another challenge numerous change orders were necessary throughout the erection of the building, caused by an abundance of design errors discovered as materials arrived at the site. Imprecise cuts, improper lengths and inaccurate bolt hole locations were widespread throughout the building, forcing GROUP s jobsite superintendent, Dustin Cutrer, to coordinate closely with the Texas-based metal building supplier over every design change. Since GROUP supervisors knew they needed more control over the building s design in order to maintain schedule, Dow provided them with the authority to make all necessary changes. When a design error was

10 discovered, Cutrer would electronically deliver photos and descriptions to the manufacturer for correction. Since the building is designed to be blast resistant, new blast calculations had to be re-run by the manufacturer for every change, then approved by Dow. Concrete Complications The building required an impressive 10,000 cubic yards of concrete and came with some significant footings reaching as deep as 6 feet. The unusually deep footings were used in lieu of pilings, with some of the more substantial footings constructed to support a large conveyor system coming into the building. Throughout the process, GROUP had difficulty finding a concrete supplier who could provide the volume of concrete necessary at the time it was needed. Most of the concrete was poured overnight, beginning at 1 a.m., which is more conducive to the summertime heat. While one of the suppliers had a batch plant in close proximity, its location near a neighborhood prohibited it from operating at night due to sound ordinances. Ultimately, the concrete had to be batched across the Mississippi River and transported to Plaquemine. There were additional issues during the concrete testing phase, when the testing agency came back with a bad break in one of the slabs. Resulting in another 1-week delay, no formwork could be performed as they determined if the concrete had to demolished and re-poured. Ultimately, the test results came back favorably, and the project was allowed to proceed. Another challenge concrete flatness requirements were specified in the MCC area, where a tolerance of 1/8

11 inch in a 10-foot span had to be maintained. To achieve the stringent tolerance, GROUP crews determined the locations for each piece of equipment and laid out 2-foot by 2-foot intervals throughout the area, using chalk lines and shooting each corner. While more typical flatness specifications of a quarter of an inch were specified for the remainder of the site, the equipment within the MCC area had to be precisely level in order to operate properly. Other areas, such as the office building and the packaging area, did not require specific tolerances. The specification for the use of screed guides, while meant to ensure that flatness requirements were maintained, ultimately caused further delays. In fact, ACI suggests not using screed guides, since they can hinder a contractor s ability to accurately measure flatness in some situations. Fortified Precast Panels For the office building, explosion resistance was incorporated throughout the building, primarily through additional reinforcing steel on the east and west sides of the precast panels, which were then filled with grout. The precast was given a textured, beige-colored finished. Manufactured by Tindall Corp., the panels reach as high as 22 feet. The panels were lifted by a 200-ton crane operating from within the building. The tallest column within the building was 45 feet. Additionally, the crew installed nine overhead doors, one providing entry into the building while the others were needed for the loading dock.

12 Poly B Packaging Warehouse, The Dow Co. EXCELLENCE IN CONSTRUCTION PHOTOGRAPHS

13 Concrete work early in the project had to be performed concurrently with other crafts.

14 Stringent levelness specifications were required in some areas.

15 Form work is constructed for building slabs and grade beams.

16 The pre-engineered metal structure required 25 change orders, which significantly impacted the schedule.

17 Precast panels reaching as high as 22 feet were necessary for the office building.

18 The crane lift plan was adjusted when multiple crafts had to work concurrently during building construction.

19 Cable trays weave through the interior of the warehouse.

20 Aesthetic interior finishes were required in areas within the office space.

21 Situating mechanical and electrical components within the warehouse was challenging.

22 The 86,000-square-foot Poly B Packaging Warehouse project is vital to Dow s Louisiana operations.

23 Poly B Packaging Warehouse, The Dow Co. EXCELLENCE IN CONSTRUCTION PROJECT SAFETY

24

25

26

27

28 Poly B Packaging Warehouse Plaquemine, LA

29

30

31

32

33

34

35

36

37

38

39

40 Tool Box Talks and Job Safety Analysis For efficiency, the documentation of the daily Took Box Talks was combined with the Job Safety Analysis Worksheet (see below and the following page).

41

42 Specialized Safety Training & Innovative Safety Programs When high river levels and multiple change orders forced a re-ordering of the project schedule, forcing many crafts to work concurrently, GROUP revised its safety plan to incorporate additional precautions since its ground crew had to work in close proximity to the steel erection crew, primarily through the addition of safety barricades and safety tape to ensure crafts didn t venture into other areas. The crane lift schedule was also adjusted, as well as lift and crane locations, with all changes communicated to the entire project team. Throughout the project, GROUP also leaned heavily upon its Ask about Life safety program, incorporating the safety slogan Live Incident Free Every Day. The program provides a way for management to interact with employees at the jobsite level, with the goal of safety improvement. Any employee, whether management, superintendent or crew member, can approach a fellow employee and Ask About Life, and if the employee responds properly with Live Incident Free Every Day they are eligible to receive an incentive. Of course, the true purpose of the program is to open a dialogue about safety. GROUP also uses Safety Observation Cards, which employees can fill out should they notice a safety violation without identifying the employee. By allowing employees to report violations in that manner, GROUP is better able to pinpoint problem areas and track safety trends. In effect, this provides employees with a way to talk to upper management without fear of backlash. They are also encouraged to talk to the employee who is in violation in order to correct the problem. Other safety policies include: Daily Hand Safety Analysis: The analysis forces the employees to think about possible hand safety hazards that exist while working on a specific task. The forms (included in this binder) are completed individually by each crew member prior to the daily tool box meeting. At the site each morning, GROUP superintendents discussed the job responsibilities of every worker, and each worker signed the Job Safety Analysis (JSA) acknowledging that he understood the hazards. GROUP s impressive safety statistics Zero OSHA Recordables, Zero Lost Time Accidents & Zero First Aids provide proof that safety is its No. 1 goal.

43 2016 Poly B Packaging Warehouse Site Specific Safety Training 1) Met w/all subcontractors & Group supervisors before starting work 2) Discuss work activities daily w/subcontractors & Group supervisors 3) Group supervisors & subcontractors to communicate w/employees 4) Installed construction fence & signage to keep non-construction personnel out of danger 5) Follow up on discussed plan of action, if changes were made share w/personnel onsite. 6) Stay in your work area as discussed the day before. 7) Identify hazards before incident/injury occurs 8) Head count of all personnel onsite for each subcontractor & Group daily 9) Hold all personnel accountable for their actions 10) Stressed housekeeping daily ( A clean worksite is a safe worksite) 11) Observed subcontractor & Group personnel working ( Safety Audits) 12) Stopped personnel if not complying to safety policies & explained proper way to be safe while performing task 13) Preplan all activities ( Three Week Work Plan updated weekly & shared w/supervisors) 14) All Group personnel to lead by example ( Subcontractors will follow) 15) Always had full support from Home Office Management

44

45 Near Miss Reporting

46 Near Miss Reporting, Page 2

47 Near Miss Reporting, Page 3

48 Near Miss Reporting, Page 4

49 Substance Abuse Policy Implementation & Table of Contents, Page 1 At GROUP Industries, our priorities include protecting the safety of our employees, property, the public, as well as an interest in the productivity of our workforce. In an effort to ensure the success of our priorities, GROUP has adopted a Controlled Substance Use & Alcohol Misuse Policy that is applicable to all employees. Our purpose in adopting this policy is to further GROUP s objective of establishing and maintaining a work environment free from the adverse effects of drug use and alcohol misuse. In order to verify compliance with GROUP s Controlled Substance Use and Alcohol Misuse Policy, all candidate employees are required to complete a drug and alcohol screening (provided by a qualified and accredited Occupational Medicine provider) prior to employment. As a condition of continued employment, all employees are required to complete a drug and alcohol screening at least annually, as well as consent to random drug and alcohol screenings. as required. on a monthly basis.

50 Substance Abuse Policy Implementation & Table of Contents, Page 2

51 New Employee Safety Orientation

52 GROUP s Safety Program Overview

53 Weekly Field Observation Report, Pie Chart

54

55 Weekly Field Observation Report

56 Poly B Packaging Warehouse, The Dow Co. EXCELLENCE IN CONSTRUCTION REFERENCES

57

58

59

60 Poly B Packaging Warehouse, The Dow Co. EXCELLENCE IN CONSTRUCTION SUPPLEMENTAL MATERIALS

61 Excerpt from Houston Business Journal, referencing plastics expansion at Plaquemine plant: Poly B Packaging Warehouse Plaquemine, LA

62 Excerpt from IMPACT, Dow Louisiana s Official Magazine: Poly B Packaging Warehouse Plaquemine, LA

63 Excerpt from Dow Louisiana Website:

64 Poly B Packaging Warehouse, The Dow Co. EXCELLENCE IN CONSTRUCTION AQC CONTRACTOR Poly B Packaging Warehouse, The Dow Co., Plaquemine, LA

65

66 Project Team Poly B Packaging Warehouse, The Dow Co. James Construction (Civil) Baton Rouge, LA TWA Erectors (Building Erection) Baton Rouge, LA All Service Plumbing (Mechanical) Baton Rouge, LA Union Service and Maintenance (HVAC) Mandeville, LA Lanehart Painting (Painting) Baton Rouge, LA TSC of Louisiana (Drywall and Masonry) Baton Rouge, LA Himmels (Doors) Baton Rouge Cornerstone Flooring (Flooring) Baton Rouge, LA Fisk Electric (Electrical) New Orleans

67

Are designed to provide a safe working environment, and Govern use of fall protection procedures and equipment.

Are designed to provide a safe working environment, and Govern use of fall protection procedures and equipment. Fall Protection Plan for Construction OSHA currently regulates fall protection for construction under Part 1926, Subpart M. The standards for regulating fall protection systems and procedures are intended

More information

INOVA Office Building I. Adolfson & Peterson Construction. Keri Burson:

INOVA Office Building I. Adolfson & Peterson Construction. Keri Burson: INOVA Office Building I Adolfson & Peterson Construction Keri Burson: kburson@a-p.com; 303-363-7101 Category #9 Best Building Project General Contractor ($10 - $40 Million) Why this project should win

More information

Legal Eagle: OSHA s Multi-Employer Policy

Legal Eagle: OSHA s Multi-Employer Policy Legal Eagle: OSHA s Multi-Employer Policy Michael C. Wright, PE, CSP, CPE President of STE Inc. Jeremy T. Deason, PE Managing Principal Mark Williams Director of Training A Multi-Employer Is... OSHA 1926.16

More information

Construction Innovations / Sustainability

Construction Innovations / Sustainability Category: 2 Meeting the Challenge of a Difficult Job Specialty Contractor Contractor: Baker Concrete Construction, Inc. Project Name: Confluence Park Tower Project Overview Construction projects are never

More information

Fall Protection Plan for Construction

Fall Protection Plan for Construction Safety & Health Program 10627 Midwest Industrial Boulevard, St. Louis, MO Phone: 314-785-6425 Fax: 314-785-6426 Fall Protection Plan for Construction OSHA currently regulates fall protection for construction

More information

GOLDEN TRIANGLE BUSINESS ROUNDTABLE CONTRACTOR SAFETY AWARDS PROGRAM

GOLDEN TRIANGLE BUSINESS ROUNDTABLE CONTRACTOR SAFETY AWARDS PROGRAM CONSTRUCTION CATEGORY SUBMITTAL INSTRUCTIONS AND APPLICATION REVISED 1-2-18 OWNERS: 1.0 Give a copy of the submittal instructions, application and evaluation forms to the contractor(s) you will be nominating.

More information

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS SECTION 01 00 00 GENERAL REQUIREMENTS PART 1 - GENERAL 1.1 SECTION INCLUDES A. Summary of Work: 1. General 2. Contract. B. Contract Considerations: 1. Schedule of values. 2. Applications for payment. 3.

More information

STATEMENT OF BIDDER S QUALIFICATIONS

STATEMENT OF BIDDER S QUALIFICATIONS STATEMENT OF BIDDER S QUALIFICATIONS Eastside Trail Extension This Statement is to accompany bids submitted for the project identified above. Bidders must meet the minimum qualification criteria set forth

More information

Performance Verification Packet. Supervisor

Performance Verification Packet. Supervisor Performance Verification Packet Supervisor This performance verification is designed as one method to evaluate job skills and safe work habits of a participant. The performance of the participant must

More information

RK Specialties, Inc. (DBA: RK Steel) UCCS Village at Alpine Valley Best Building Project ($2-$6 Million Specialty Contractor)

RK Specialties, Inc. (DBA: RK Steel) UCCS Village at Alpine Valley Best Building Project ($2-$6 Million Specialty Contractor) RK Specialties, Inc. (DBA: RK Steel) UCCS Village at Alpine Valley Best Building Project ($2-$6 Million Specialty Contractor) AN OVERFLOWING RIVER: STUDENT GROWTH INCREASES NEED FOR HOUSING As the fastest

More information

Meeting the Challenge of a Difficult Job GC The Beck Group Colorado Mills Mall Restoration 1

Meeting the Challenge of a Difficult Job GC The Beck Group Colorado Mills Mall Restoration 1 2018 AGC ACE Awards Entry Category 3 Meeting the Challenge of a Difficult Job GC Contractor The Beck Group Project Name Colorado Mills Mall Restoration When the costliest storm in state s history unleashed

More information

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08 Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08 Table of Contents 1. Title 2. Designation 3. List of Figures 4. Scope 5. Referenced

More information

Jobsite Layout Considerations

Jobsite Layout Considerations 1 Jobsite Layout Considerations The controlling contractor must consider many factors when laying out a site to support construction operations Site and building size and Equipment requirements configuration

More information

Trolley Square Whole Foods Store & Parking Structure. Case Study CS 2. Grounded in strength.

Trolley Square Whole Foods Store & Parking Structure. Case Study CS 2. Grounded in strength. Trolley Square Whole Foods Store & Parking Structure CS 2 Case Study Grounded in strength. Forterra Structural & Specialty Products Thin Brick Precast Walls Copy the Look of Century-Old Trolley Barns Project

More information

High Stakes. Solutions of Special Projects:

High Stakes. Solutions of Special Projects: Category 2: Meeting the Challenge of a Difficult Job Specialty Contractor Specialty Contractor: Colorado Cleanup Corporation (CCC) Project Name: Monarch Casino Garage Implosion High Stakes After months

More information

03 CONCRETE TAKEOFF SUMMARY REPORT Takeoff and Items Cost Summary. Ryan Manocchio

03 CONCRETE TAKEOFF SUMMARY REPORT Takeoff and Items Cost Summary. Ryan Manocchio 03 CONCRETE TAKEOFF SUMMARY REPORT Takeoff and Items Cost Summary Ryan Manocchio rmanocchio@stackct.com Concrete Takeoff Summary Report The STACK To Go Team is capable of performing takeoff for concrete

More information

New Reclaim Tunnel at Coal Fired Plant

New Reclaim Tunnel at Coal Fired Plant Omaha SAME Post Monthly Meeting 10 July 2014 New Reclaim Tunnel at Coal Fired Plant By: Steve Morrissette Zapata Incorporated Omaha, NE Coal Fired Power Plant Generating capacity: 2,090 megawatts base

More information

Massachusetts FACE Occupational Fatality Report

Massachusetts FACE Occupational Fatality Report Massachusetts FACE Occupational Fatality Report Massachusetts Department of Public Health Occupational Health Surveillance Program Fatality Assessment and Control Evaluation Project Municipal Lead Custodian

More information

Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure

Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure ArchCast Bridge 3-Sided Precast Concrete Bridge Structure Installation Manual Salem Location: 749 West Commercial Ave. Salem, IL 62881 (618) 548-1190 countymaterials.com Email: info@countymaterials.com

More information

SECTION US Patent 8,857,130 B1 CAST-IN-PLACE CONCRETE WITH ARDEX CONCRETE MANAGEMENT SYSTEMS (ACMS ) EARLY MC APPLICATION

SECTION US Patent 8,857,130 B1 CAST-IN-PLACE CONCRETE WITH ARDEX CONCRETE MANAGEMENT SYSTEMS (ACMS ) EARLY MC APPLICATION ARDEX GUIDE SPECIFICATION ARDEX CONCRETE MANAGEMENT SYSTEMS (ACMS ) Cast-In-Place Concrete to Receive the ARDEX Concrete Management Systems including ARDEX Self-Leveling Underlayments SECTION 03 30 00

More information

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority

More information

SECTION 9700 SPECIAL FLOORING AND FLOORING TREATMENTS DEGREE OF CUT - VISION

SECTION 9700 SPECIAL FLOORING AND FLOORING TREATMENTS DEGREE OF CUT - VISION SECTION 9700 SPECIAL FLOORING AND FLOORING TREATMENTS DEGREE OF CUT - VISION FOR THE GREEN ENDURANCE FLOORING INSTALLATION TO BE A SUCCESS THE STRUCTURAL ENGINEER MUST INCORPORATE THE GREEN ENDURANCE FLOORING

More information

INTERNSHIP REPORT GOUTHAM.J

INTERNSHIP REPORT GOUTHAM.J INTERNSHIP REPORT GOUTHAM.J M.E Structural Engineering SNS College of Technology, Coimbatore Mail : tcegoutham@gmail.com TEEMAGE PRECAST IN College Road, 1st Cross Street, Tirupur 641602. TamilNadu, India.

More information

Doc No: SUBCON Midland Engineering Co., Inc. Initial Issue Date 12/04/15 Safety Management System

Doc No: SUBCON Midland Engineering Co., Inc. Initial Issue Date 12/04/15 Safety Management System Revision Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 6 PURPOSE Define subcontractor responsibility for developing, implementing and adhering to their own environmental,

More information

CHOCTAW WAREHOUSE & DISTRIBUTION

CHOCTAW WAREHOUSE & DISTRIBUTION CHOCTAW WAREHOUSE & DISTRIBUTION 6191 CHOCTAW DRIVE BATON ROUGE, LA 70805 SVN GRAHAM, LANGLOIS & LEGENDRE COMMERCIAL REAL ESTATE ADVISORS 6160 PERKINS ROAD, SUITE 200, BATON ROUGE, LA 70808 SALE PROPOSAL

More information

Pre-Construction Conference for Concrete Construction

Pre-Construction Conference for Concrete Construction Pre-Construction Conference for Concrete Construction Alabama Concrete Industries Association www.alconcrete.org Johnny Canfield, Technical Director 1 National Ready Mixed Concrete Association CLP 32 Concrete

More information

Root Cause Analysis Procedure

Root Cause Analysis Procedure Root Cause Analysis Procedure Employee / Incident Information: Employee Name: Date of Hire: Job Title: Total Years in Job classification: Shift Start Time: Shift End Time: Exact location of incident (Bldg/Level/Area):

More information

StormPod Arch Installation Guide

StormPod Arch Installation Guide StormPod Arch Installation Guide xx Foundation Bed Preparation Use standard construction procedures for the construction of the bed for StormPod Modular Arch Systems. As with any construction project,

More information

Rocky Top Materials, Inc.

Rocky Top Materials, Inc. Rocky Top Materials, Inc. 2707 John Deere Dr. Knoxville, TN 37917 (865) 522-0060 1806 Middlecreek Rd. Pigeon Forge, TN 37863 (865) 453-3723 Disclaimer: This document contains brief descriptions of Rocky

More information

DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY QUALITY ASSURANCE MEASUREMENT ANALYSIS AND IMPROVEMENT

DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY QUALITY ASSURANCE MEASUREMENT ANALYSIS AND IMPROVEMENT DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY 10550 QUALITY ASSURANCE TABLE OF CONTENTS SECTION I SECTION 2 SECTION 3 SECTION 4 SECTION 5 QUALITY MANAGEMENT SYSTEM MANAGEMENT RESPONSIBILITY RESOURCE

More information

Sunnyvale Plaza. Mid-Atlantic Region, United States. Nathan Braskey Construction Management. November 15, Technical Assignment #3

Sunnyvale Plaza. Mid-Atlantic Region, United States. Nathan Braskey Construction Management. November 15, Technical Assignment #3 November 15, 2013 Sunnyvale Plaza Mid-Atlantic Region, United States Nathan Braskey Construction Management FACULTY CONSULTANT: CRAIG DUBLER EXECUTIVE SUMMARY The following technical report explores several

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #53 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #53 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 5484» Total Man Hours on Project: 135019» Crafts On Project This Week: 11» OSHA Recordable Rate: 0 February 28, 2016 Page 1 CURRENT CONSTRUCTION ACTIVITIES EAST

More information

Bonner Bridge Replacement Update:

Bonner Bridge Replacement Update: Bonner Bridge Replacement Update: Jerry D. Jennings, PE - NCDOT Division 1 Engineer Pablo A. Hernandez, - NCDOT Resident Engineer September 18, 2017 Bonner Bridge Replacement Timeline Refresher Bonner

More information

THE WORLD LOOKS UP TO COMPOSITE ELEVATED TANK

THE WORLD LOOKS UP TO COMPOSITE ELEVATED TANK THE WORLD LOOKS UP TO COMPOSITE ELEVATED TANK or our breadth of capability. Of all the storage tank manufacturers doing business today, no other offers Caldwell s range of capability. We are the only manufacturer

More information

Section 5 Crew Requirements

Section 5 Crew Requirements Section 5 Crew Requirements Panel Fabrication After the home s design has been approved by the client and permitting agencies, Nexframe will begin production according to the construction schedule. The

More information

FrameSAFE Site-Specific Fall Protection Plan Template. Instructions for Use DO NOT INCLUDE THIS PAGE IN YOUR MANUAL SAMPLE

FrameSAFE Site-Specific Fall Protection Plan Template. Instructions for Use DO NOT INCLUDE THIS PAGE IN YOUR MANUAL SAMPLE FrameSAFE Site-Specific Fall Protection Plan Template Instructions for Use DO NOT INCLUDE THIS PAGE IN YOUR MANUAL Step 1: Complete Site-Specific Form Enter the site-specific information in the form on

More information

Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options

Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options A local utility company issued a Request for Proposal to our university s capstone design class for structural improvements

More information

Project Address: Name of Person Completing Form:

Project Address: Name of Person Completing Form: Statement of Inspections This form is provided as a way to list aspects of the project that require special inspection and testing in accordance with IBC Sections 107.1, 1704, and 1705 and define duties

More information

1.5 Other than persons listed above, number of full-time office employees: 1.6 Number of full-time, permanent field employees:

1.5 Other than persons listed above, number of full-time office employees: 1.6 Number of full-time, permanent field employees: 1.4 Names of officers, owners, partners and principals. Identify relationship of each to firm and if active in firm: 1.5 Other than persons listed above, number of full-time office employees: 1.6 Number

More information

Introduction to Construction, June 2013, page 1 of 6

Introduction to Construction, June 2013, page 1 of 6 Indiana Department of Education Academic Content Framework INTRODUCTION TO CONSTRUCTION Introduction to Construction is a course that will offer hands-on activities and real world experiences related to

More information

Transitioning to the New Erector Standard from a Checklist

Transitioning to the New Erector Standard from a Checklist Transitioning to the New Erector Standard from a Checklist With the release of the Standard, what does that mean for the industry and you? AISC Certification will be introducing an updated Erector Certification

More information

Health, Safety, Security and Environment

Health, Safety, Security and Environment HSSE General Safety Document owner and change code Document Owner Aaron Perronne Title HSSE Manager Mark X Change Code Description X N/A First Issue A Typographical/Grammatical correction; formatting change;

More information

THE. Unitized Advantage

THE. Unitized Advantage THE Unitized Advantage The BCi Unitized Advantage Packaging & Delivery 1. Identification Prior to packaging, each panel or item is marked with a unique alphanumeric identifier corresponding to a unique

More information

T-WALL Retaining Wall System

T-WALL Retaining Wall System CONSTRUCTION MANUAL T-WALL Retaining Wall System The T-WALL Solution... THE NEEL COMPANY 8328 Traford Lane Springfield, VA 22152 Phone 703-913-7858 Fax 703-913-7859 T-WALL Retaining Wall System CONSTRUCTION

More information

Commercial Portfolio

Commercial Portfolio Commercial Portfolio Entire School District - $21,475,490 FLOODING The flood of 2016 strikes Baton Rouge and floods 26 campuses in a local parish. INSPECTION Guarantee inspects buildings and sites affected,

More information

CHAPTER 2 REVIEW QUESTIONS

CHAPTER 2 REVIEW QUESTIONS DEWALT Construction Estimating Complete Handbook Excel Estimating Included 2nd Edition Ding SOLUTIONS MANUAL Full download at: https://testbankreal.com/download/dewalt-construction-estimating-completehandbook-excel-estimating-included-2nd-edition-ding-solutions-manual/

More information

Office Building. Analysis #2: Utilizing a Matrix Schedule

Office Building. Analysis #2: Utilizing a Matrix Schedule Analysis #2: Utilizing a Matrix Schedule Problem Statement In the past, the team has accelerated the schedule by re-sequencing or re-designing a specific system and/or piece of the schedule to gain back

More information

Texas Tech University Health Sciences Campus - MSBII Supplemental Bid Instructions March 3, 2017

Texas Tech University Health Sciences Campus - MSBII Supplemental Bid Instructions March 3, 2017 Texas Tech University Health Sciences Campus - MSBII Supplemental Bid Instructions March 3, 2017 Plumbing - 220000 Without limiting the application of all of the Contract Documents to the Subcontract,

More information

2018 ConocoPhillips Alaska Excellence in Safety Awards

2018 ConocoPhillips Alaska Excellence in Safety Awards Introduction These awards are to promote and recognize excellence in safety throughout the construction industry in Alaska. Applications are reviewed by an independent panel of safety professionals with

More information

MANDATORY SUPPLEMENTAL SPECIFICATIONS FOR CONTRACTOR QUALITY CONTROL Contractor Quality Control - is replaced with the following:

MANDATORY SUPPLEMENTAL SPECIFICATIONS FOR CONTRACTOR QUALITY CONTROL Contractor Quality Control - is replaced with the following: MANDATORY SUPPLEMENTAL SPECIFICATIONS FOR CONTRACTOR QUALITY CONTROL EFFECTIVE DATE: OCTOBER 14, 2011 200.07 Contractor Quality Control - is replaced with the following: (a) (b) (c) Scope: These requirements

More information

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The Ashland Project Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The garage and bedroom extend from the front of this three bedroom home, drawing you visually into the entryway. Brick and stucco

More information

MVDC F041 Safety Inspection Checklist

MVDC F041 Safety Inspection Checklist MVDC F041 Safety Inspection Checklist JOB TITLE: DEPARTMENT: JOB NO.: DATE: LEGEND 1 Satisfactory 2 Requires Improvement 3 Non Existent 4 Not Applicable EMERGENCY PREPAREDNESS Emergency procedure is posted

More information

July 15, 2010 Report No. 11 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY

July 15, 2010 Report No. 11 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY July 15, 2010 Report No. 11 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority

More information

Safety Approach. September 2016

Safety Approach. September 2016 Safety Approach The San Francisco Public Utilities Commission (SFPUC) Construction Safety Approach applies to all personnel and companies contracted to work on any Project related to SFPUC Capital Improvement

More information

Section 4 - Design and Construction Overview

Section 4 - Design and Construction Overview Section 4 - Design and Construction Overview 4-1 Building Architecture/Enclosure The Pearland Recreation Center and Natatorium houses a recreation center and natatorium as shown in Figures 4-1.1 First

More information

DOCUMENT BID DOCUMENT

DOCUMENT BID DOCUMENT DOCUMENT 00 40 00 BID DOCUMENT 1 Submit bids in compliance with Document 00 21 00Instructions to Bidders. Fill in blanks which pertain to the project or indicate N/A. The Owner reserves the right to reject

More information

TECHNICAL ASSIGNMENT THREE

TECHNICAL ASSIGNMENT THREE TECHNICAL ASSIGNMENT THREE PENN STATE SENIOR AE THESIS New York Police Academy College Point, New York Shawn Sidelinger Construction Management Dr. Robert Leicht Table of Contents Executive Summary...3

More information

Division 03 - Concrete Section New Westminister Multi-Use Civic Facility & Office Building Project No Page 1

Division 03 - Concrete Section New Westminister Multi-Use Civic Facility & Office Building Project No Page 1 Project No. 210022 Page 1 PART 1 GENERAL 1.7 Documents.1 The General Conditions of the Canadian Standard Construction Document CCDC-2, together with all amendments and supplements and Division 1 General

More information

Preventing Electrocutions:

Preventing Electrocutions: SAFETY CORNER Preventing Electrocutions: While Working with Scaffolds Near Overhead Power Lines Warning! Workers may be electrocuted when erecting, moving, or working from metal or conductive scaffolds

More information

Level 2 NVQ Diploma in Trowel Occupations (Construction) (QCF) Qualification Specification

Level 2 NVQ Diploma in Trowel Occupations (Construction) (QCF) Qualification Specification (QCF) Qualification Specification ProQual 2015 Contents Page Introduction 3 The Qualifications and Credit Framework (QCF) 3 Qualification profile 4 Rules of combination 5 Centre requirements 6 Support

More information

SECTION TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:

SECTION TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following: PART 1 GENERAL 1.01 SUMMARY SECTION 03460 TILT-UP PRECAST CONCRETE SANDWICH PANELS A. Work includes, but is not limited to, the following: 1. Architectural precast concrete sandwich wall panels. 2. Integral

More information

2014 SAFETY EXCELLENCE AWARD SAFETY SURVEY FORM FINAL EVALUATION FOR GENERAL & HARD/SOFT CRAFT CONTRACTORS

2014 SAFETY EXCELLENCE AWARD SAFETY SURVEY FORM FINAL EVALUATION FOR GENERAL & HARD/SOFT CRAFT CONTRACTORS 2014 SAFETY ECELLENCE AWARD SAFETY SURVEY FORM FINAL EVALUATION FOR GENERAL & HARD/SOFT CRAFT CONTRACTORS SCORING: For each item listed below, decide if the entry meets the criteria as follows: 0 = Below

More information

Document Supplementary Conditions State of Ohio Standard Requirements for Public Facility Construction

Document Supplementary Conditions State of Ohio Standard Requirements for Public Facility Construction Document 00 73 00 - Supplementary Conditions State of Ohio Standard Requirements for Public Facility Construction Certifications These Supplementary Conditions amend and supplement the General Conditions

More information

NW Region Tribal Transportation Symposium March 6-9, PROJECT DOCUMENTATION for Tribes Administering Construction Projects

NW Region Tribal Transportation Symposium March 6-9, PROJECT DOCUMENTATION for Tribes Administering Construction Projects NW Region Tribal Transportation Symposium March 6-9, 2017 PROJECT DOCUMENTATION for Tribes Administering Construction Projects Slides adopted from Karl Gleason, FHWA - Senior Tribal Coordinator, presentation

More information

CONSTRUCTION MANUAL. T-WALL Retaining Wall System FOR RAILROAD PROJECTS. The T-WALL Solution...

CONSTRUCTION MANUAL. T-WALL Retaining Wall System FOR RAILROAD PROJECTS. The T-WALL Solution... T-WALL Retaining Wall System CONSTRUCTION MANUAL FOR RAILROAD PROJECTS T-WALL railroad units are 5.0' high x 7.5' wide. (stem lengths will vary) The T-WALL Solution... T-WALL Retaining Wall System CONSTRUCTION

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #91 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #91 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 21450» Total Man Hours on Project: 669792» Crafts On Project This Week: 24» OSHA Recordable Rate: 0 November 7, 20 Page 1 CURRENT CONSTRUCTION ACTIVITIES East

More information

TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:

TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following: PART 1 GENERAL 1.01 SUMMARY SECTION 03460 TILT-UP PRECAST CONCRETE SANDWICH PANELS A. Work includes, but is not limited to, the following: 1. Architectural precast concrete sandwich wall panels. 2. Integral

More information

F.A.C.E. INVESTIGATION REPORT

F.A.C.E. INVESTIGATION REPORT F.A.C.E. INVESTIGATION REPORT Fatality Assessment and Control Evaluation Project FACE #97-NJ-067-01 Iron Worker Dies After Falling 26 Feet From a Steel Beam New Jersey Department of Health and Senior Services

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #92 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #92 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 19935» Total Man Hours on Project: 689727» Crafts On Project This Week: 24» OSHA Recordable Rate: 0 November 13, 2016 Page 1 CURRENT CONSTRUCTION ACTIVITIES East

More information

Level 2 NVQ Diploma in Trowel Occupations (Construction) Qualification Specification

Level 2 NVQ Diploma in Trowel Occupations (Construction) Qualification Specification Level 2 NVQ Diploma in Trowel Occupations (Construction) Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Qualification structure 4 Centre requirements 5 Support

More information

Floor Panelized Systems

Floor Panelized Systems Floor Panelized Systems Introduction In construction, an easier and faster way of completing a job is always top priority. Using wood as a construction material allows for an easily obtainable and replenished

More information

Level 2 NVQ Diploma in Formwork (Construction)

Level 2 NVQ Diploma in Formwork (Construction) Qualification Specification ProQual 2013 Contents Page Introduction 3 The Qualifications and Credit Framework (QCF) 3 Qualification profile 4 Rules of combination 5 Centre requirements 6 Support for candidates

More information

Construction Management Study

Construction Management Study Construction Management Study CONSTRUCTION MANAGEMENT STUDY A construction management study of the alternate concrete system was done to examine the impact that changing the building s superstructure material

More information

Technical Report II. The Office Building. Rendering courtesy of DAVIS. Brett Miller. Dr. Gannon Construction

Technical Report II. The Office Building. Rendering courtesy of DAVIS. Brett Miller. Dr. Gannon Construction Technical Report II The Office Building Rendering courtesy of DAVIS Brett Miller Dr. Gannon Construction 10/16/2013 Executive Summary This technical report analyzes key features of The Office Building

More information

Masonry Wall Bracing. A Simplified Approach To Bracing Masonry Walls Under Construction. Masonry Bracing Task Force.

Masonry Wall Bracing. A Simplified Approach To Bracing Masonry Walls Under Construction. Masonry Bracing Task Force. Masonry Wall Bracing A Simplified Approach To Bracing Masonry Walls Under Construction Produced by the Masonry Wall Bracing A Simplified Approach to Bracing Masonry Walls Under Construction Produced by

More information

Essentials QA/QC Plan Sample for Ericsson Qualifications

Essentials QA/QC Plan Sample for Ericsson Qualifications Essentials QA/QC Plan Sample for Ericsson Qualifications Good for smaller projects and bid qualifications Has All the Essential Elements of a well-founded Quality Control Plan Contact: Ed Caldeira 410-451-8006

More information

GUIDE TO IMPLEMENTING AN EFFECTIVE SAFETY PROGRAM

GUIDE TO IMPLEMENTING AN EFFECTIVE SAFETY PROGRAM GUIDE TO IMPLEMENTING AN EFFECTIVE SAFETY PROGRAM NAHB Builder s Show Orlando, Florida February 2008 Leon Rogers President Construction Management Associates, LLC PO Box 867 Thayne, WY 83127 (801) 310-0035

More information

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring Location of Project Introduction» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring Existing Bridge» Built in 1928» 255-foot Open Spandrel Concrete Arch Bridge» 24-foot

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #69 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #69 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 13462» Total Man Hours on Project: 268272» Crafts On Project This Week: 17» OSHA Recordable Rate: 0 June 5, 2016 P a g e 1 CURRENT CONSTRUCTION ACTIVITIES East

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION S WATER SYSTEM IMPROVEMENT PROGRAM (WSIP) SAFETY APPROACH

SAN FRANCISCO PUBLIC UTILITIES COMMISSION S WATER SYSTEM IMPROVEMENT PROGRAM (WSIP) SAFETY APPROACH SAN FRANCISCO PUBLIC UTILITIES COMMISSION S WATER SYSTEM IMPROVEMENT PROGRAM (WSIP) SAFETY APPROACH WSIP Safety Approach. The Water System Improvement Program (WSIP) Construction Safety Approach applies

More information

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #63 Douthit Hills Student Community, Clemson University Project Joe Jett

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #63 Douthit Hills Student Community, Clemson University Project Joe Jett SAFETY» Total Man Hours Worked This Week: 9086» Total Man Hours on Project: 188636» Crafts On Project This Week: 13» OSHA Recordable Rate: 0 April 24, 2016 Page 1 CURRENT CONSTRUCTION ACTIVITIES» Continued

More information

Providing Engineered Concrete Solutions. Precast and Mission Critical Facilities A Natural Fit

Providing Engineered Concrete Solutions. Precast and Mission Critical Facilities A Natural Fit Providing Engineered Concrete Solutions Precast and Mission Critical Facilities A Natural Fit Total precast solutions eliminate trade overlap in the construction of the core and shell system A total precast

More information

SCAFFOLDS Revision No: 3

SCAFFOLDS Revision No: 3 PAGE 1 OF 6 1.0 PURPOSE/ SCOPE To communicate the safety requirements for the erection, inspection and safe use of scaffolds. Compliance with these requirements will assure employee safety while working

More information

Phone:

Phone: Washington State Construction Crane Certifiers Mobile Cranes (Lattice / Hydraulic / Fixed) Articulating Cranes Tower Maritime Crane Certification Experienced certifiers throughout Washington State More

More information

Conditions of the Contract and Division 1 General Requirements are a part of this section.

Conditions of the Contract and Division 1 General Requirements are a part of this section. NOTES TO SPECIFIER General notes about the specifications and the reasons for them are listed here in general statements. Use this as a guide when choosing the correct selection of statements that apply

More information

***************************************************************************************************************

*************************************************************************************************************** 03365 POST-TENSIONED CONCRETE *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 03 38 00. ***************************************************************************************************************

More information

Level 3 NVQ Diploma in Trowel Occupations (Construction) (QCF) Qualification Specification

Level 3 NVQ Diploma in Trowel Occupations (Construction) (QCF) Qualification Specification (QCF) Qualification Specification ProQual 2015 Contents Page Introduction 3 The Qualifications and Credit Framework (QCF) 3 Qualification profile 4 Rules of combination 5 Centre requirements 6 Support

More information

Statement of Special Inspections Michigan Building Code 2012 (MBC 2012)

Statement of Special Inspections Michigan Building Code 2012 (MBC 2012) Gaines Charter Township 8555 Kalamazoo Ave SE Caledonia MI 49316 PH: 616 698-6640 Fax: 616 698-2490 www.gainestownship.org Building Department Statement of Special Inspections Michigan Building Code 2012

More information

Section 5 - Project Logistics

Section 5 - Project Logistics Section 5 - Project Logistics The project schedule for the Pearland Recreation Center and Natatorium begins with commencement of design on March 1, 2007 and ends with substantial completion on May 12,

More information

CHAPTER 8 RESPONSIBILITIES OF CONTRACTOR AND INSPECTOR Contract and Specifications

CHAPTER 8 RESPONSIBILITIES OF CONTRACTOR AND INSPECTOR Contract and Specifications CHAPTER 8 RESPONSIBILITIES OF CONTRACTOR AND INSPECTOR Contract and Specifications Road and highway construction in Virginia is performed under contract. The contract is a written agreement between the

More information

Patrick Malloy Communities Quality Assurance System

Patrick Malloy Communities Quality Assurance System Patrick Malloy Communities Quality Assurance System Page 1 of 83 Log of Quality Manual Revisions Version Number Revision Date Type of Revision 1 April 9, 2007 1 st release 1 April 13, 2007 Sec 1.10 removed

More information

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12 SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: - ATTACHED SKETCH Complete; Geotechnical Engineering Report as prepared by Building and

More information

SPECIAL INSPECTION AND OBSERVATION PROGRAM City of Walnut Creek Building Division. Project Address:

SPECIAL INSPECTION AND OBSERVATION PROGRAM City of Walnut Creek Building Division. Project Address: SPECIAL INSPECTION AND OBSERVATION PROGRAM City of Walnut Creek Building Division Permit Application #: Project Address: Purpose: To meet the requirements of City of Walnut Creek Municipal Code Section

More information

Below-grade pours (such as foundations) can be done out of the chute of the concrete truck or conveyer, however using a pump is best.

Below-grade pours (such as foundations) can be done out of the chute of the concrete truck or conveyer, however using a pump is best. Concrete Placement Below-grade pours (such as foundations) can be done out of the chute of the concrete truck or conveyer, however using a pump is best. Above-grade pours require lifting equipment. Most

More information

New Main Hospital, Site Park, and Underground Garage Construction Progress Update #8

New Main Hospital, Site Park, and Underground Garage Construction Progress Update #8 New Main Hospital, Site Park, and Underground Garage Construction Progress Update #8 Date: July 1, 2009 From: Gary Claar Engineering Services 355-1660 Gary.Claar@NationwideChildrens.org June was a very

More information

DEMOLITION OF BUILDINGS

DEMOLITION OF BUILDINGS INFORMATION BULLETIN / PUBLIC - BUILDING CODE REFERENCE NO.: LABC Chapter 33 Effective: 01-01-2014 DOCUMENT NO.: P/BC 2014-039 Revised: 05-11-2016 Previously Issued As: P/BC 2008-039 DEMOLITION OF BUILDINGS

More information

SECTION STAY-IN-PLACE INSULATED CONCRETE FORMING SYSTEM

SECTION STAY-IN-PLACE INSULATED CONCRETE FORMING SYSTEM ARCHITECTURAL SPECIFICATIONS MANUFACTURER: InterBlock LLC PO Box 1123, Sheboygan, WI 53082 Phone Number 920-207-7234 SECTION 03100 STAY-IN-PLACE INSULATED CONCRETE FORMING SYSTEM PART 1 GENERAL 1.01 Summary

More information

SECTION 1: APPLICANT INFORMATION. 1. Have you contacted your local Chapter regarding their established submission process or procedure?

SECTION 1: APPLICANT INFORMATION. 1. Have you contacted your local Chapter regarding their established submission process or procedure? 2018 CONSTRUCTION SAFETY EXCELLENCE AWARDS APPLICATION INSTRUCTION STEPS: 1. DOWNLOAD FORM 2. FILL OUT 3. SUBMIT DEADLINE FEBRUARY 2, 2018 SECTION 1: APPLICANT INFORMATION 1. Have you contacted your local

More information

PAGE 1 OF 5 HEALTH, SAFETY & ENVIRONMENTAL MANUAL PROCEDURE: S085 Hazard Recognition Program REV

PAGE 1 OF 5 HEALTH, SAFETY & ENVIRONMENTAL MANUAL PROCEDURE: S085 Hazard Recognition Program REV PAGE 1 OF 5 PURPOSE The Hazard Recognition program is geared towards pre-loss identification and treatment of potential hazard exposures than inspections and job safety analyses. It involves several layers

More information