Miami Marlins Baseball Park
|
|
- Arlene Cummings
- 5 years ago
- Views:
Transcription
1 Miami Marlins Baseball Park Roof Support Track Beams Construction by Incremental Lifting
2 Project Owner Miami Dade County General Contractor Hunt-Moss JV Frame Contractor Formworks-Baker Concrete JV Engineer of Record Bliss & Nyitray Structural Engineers Heavy Lifting, Post-Tensioning Contractor VSL-Florida
3 Const. Joint Const. Joint NORTH TRACK ELEVATION 5 SPANS TOTAL L= Const. Joint Const. Joint
4 30-3 NORTH TRACK PIER SEGMENT TYPICAL SECTION NORTH TRACK TYPICAL SECTION
5 Const. Joint Const. Joint Const. Joint Const. Joint SOUTH TRACK ELEVATION 5 SPANS TOTAL L=
6 35-3 SOUTH TRACK PIER SEGMENT TYPICAL SECTION SOUTH TRACK TYPICAL SECTION
7 01 Service Level Original Design; Casting in place on falsework
8 Roof Track Construction, Original Construction method Disadvantages Full shoring to grade which compromise overall project schedule Safety risks, due to the Height of construction Production risks Construction and wind loads Labor resources Limited shoring resources
9 VSL Proposed Construction Method Build Foundations Cast Piers Cast Pier Tables
10 PHASE 2 Pour Span 1 Bottom Slab
11 PHASE 3 Pour Span 1 Webs Pour Span 2 Bottom Slab
12 PHASE 4 Pour Span 1 Top Slab Pour Span 2 Webs Pour Span 3 Bottom Slab
13 PHASE 5 Stress Stage 1 PT in Span 1 Lift Span 1 Pour Span 2 Top Slab Pour Span 3 Webs Pour Span 4 Bottom Slab
14 PHASE 6 Stress Stage 2 PT in Span 1 Stress Stage 1 PT in Span 2 Lift Span 2 Pour Span 3 Top Slab Pour Span 4 Webs Pour Span 5 Bottom Slab
15 PHASE 7 Stress Stage 2 PT in Span 2 Stress Stage 1 PT in Span 3 Lift Span 3 Pour Span 4 Top Slab Pour Span 5 Webs
16 PHASE 8 Stress Stage 2 PT in Span 3 Stress Stage 1 PT in Span 4 Lift Span 4 Pour Span 5 Top Slab
17 PHASE 9 Stress Stage 2 PT in Span 4 Stress Stage 1 PT in Span 5 Lift Span 5
18 PHASE 10 Stress Stage 2 PT in Span 5
19 Lifting Equipment Schematic Front Lift on Trailing End Back Lift on Leading End
20 VSL Proposal Challenges: Check spans capacity for lifting load Check Columns and foundations for temporary load induced by the heavy lifting method. Rearrange Post-Tensioning layout and check final Posttensioning forces Coupling of approximately 260 #11 Bars per span Splicing top rebar at the pier table
21 Creating North Track Lifting Sequence
22 2 x 339 k 2 x 674 k 2 x 674 k 2 x 718 k 2 x 718 k 2 x 645 k 2 x 645 k 2 x 718 k 2 x 718 k Creating South Track Lifting Sequence
23 Lifting Detail Column T1
24 Lifting Detail Column T2
25 Lifting Detail Column T7, T5, T3 T8, T6, T4
26 Post-Tensioning Layout Phase I ECI6-12 Tendons Stressed at the diaphragm Phase II ECI6-19 Tendons Stressed at the blisters
27 Post-Tensioning Layout Phase I ECI6-12 Tendons Stressed at the diaphragm Phase II ECI6-19 Tendons Stressed at the Blisters
28 Step-1 1. Connect Tie-Down cables to adjacent span or rock anchor 2. Lifting Span into place 3. Securing Span to Pier Table 4. Check Span elevation
29 Step-2 1. Raise closure forms into place 2. Install male bar in form savers, webs and bottom slab 3. Splice top rebar and web rebar 4. Couple #11 bottom bars 5. Splice PT ducts at the closure
30 Step-3 1. Pour closure pour
31 Step-4 1. Stress Phase I PT cables 2. Remove Lifting equipment to the next Pier Table
32 Heavy Lifting beams Approximately Weight 50 Tons
33 Heavy Lifting Jacks SLU -330
34 Bottom lifting Anchors VSL 6-37 Stay Cable anchor with ring nut
35 Lifting Strand 0.6 Dyform strand Grade 270 A=0.256 sq in
36 Place Lifting Beams on top of Pier Segment
37 Drop Lifting Cables
38 Connect Lifting Cables to Tie Down Rock Anchors
39 Connect Lifting Cables to span Bottom Lifting Anchors Detail
40 Lift-off and Finishing Bottom Beam
41 Lifting Span
42 Aliment span to final elevation
43 Coiling Lifting Cables
44 Coupling and splicing rebar and PT Ducts
45 Pouring Closure pour
46 Stress Post-Tensioning Tendons
47 Release Lifting Cables and Transfer the Load
48 Finished Track Spans
49 Finished Track Spans
50 QUESTIONS?
Bonner Bridge Replacement Update:
Bonner Bridge Replacement Update: Jerry D. Jennings, PE - NCDOT Division 1 Engineer Pablo A. Hernandez, - NCDOT Resident Engineer September 18, 2017 Bonner Bridge Replacement Timeline Refresher Bonner
More informationElevated Slab Sequence
Elevated Slab Sequence The following group of photos shows the sequence for installa4on of a one- way elevated slab. (Slab & Beam with Reinforcing & Post- Tensioning) Columns Placed & Form Support (Scaffolding)
More informationThe Hashemite University Department of Civil Engineering. Dr. Hazim Dwairi. Dr. Hazim Dwairi 1
Department of Civil Engineering Lecture 2.1 Methods of Prestressing Advantages of Prestressing Section remains uncracked under service loads Reduction of steel corrosion (increase durability) Full section
More informationCrossroads at Westfields Building II
Crossroads at Westfields Building II Chantilly, Va STEPHEN LUMPP Structural option Faculty Consultant: Dr. Andres Lepage Technical Report 2 EXECUTIVE SUMMARY This report is a study of alternate floor systems
More informationCONCRETE SPLICED GIRDERS IN TEXAS. Nicholas Nemec, P.E. TxDOT-BRG
CONCRETE SPLICED GIRDERS IN TEXAS Nicholas Nemec, P.E. TxDOT-BRG October 15, 2014 What is a Concrete Spliced Girder? 2 What is a Concrete Spliced Girder? What it is NOT : Continuous For Live Load 3 What
More informationFlorida DOT efforts toward improving Post Tension Durability
Florida DOT efforts toward improving Post Tension Durability By William Nickas 1 (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 1 of 73 Post-Tensioning Strategies Enhanced PT Systems
More informationPOST-TENSIONING APPLICATION AND TECHNOLOGY. Moe Kyaw Aung
POST-TENSIONING APPLICATION AND TECHNOLOGY Moe Kyaw Aung Overview 1. Background 2. Basic Design Concept 3. Application and Benefits 4. Components of Post-tensioning System 5. Installation Process 6. Construction
More informationConstruction Measurement III SBQ3314. Precast Pre stressed Concrete Works. Dr. Sarajul Fikri Mohamed
Construction Measurement III SBQ3314 Precast Pre stressed Concrete Works Dr. Sarajul Fikri Mohamed Table of Contents 1. Pre stressed concrete in bridgeworks: technological aspects 2. SMM2 measurement rules
More informationIronton Russell Bridge Project
Construction Update January 1, 2016 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails
More informationCONSTRUCTABILITY IMPROVEMENT OF BRIDGES USING STEPPING FORMWORK
CONSTRUCTABILITY IMPROVEMENT OF BRIDGES USING STEPPING FORMWORK By Mohamed Emam Abd El-Razek, 1 and Ismail M. Basha 2 ABSTRACT: Many construction systems have been used to build several highway bridges
More informationComparative Study on Post - Tensioned and Reinforced Concrete flat Slab Systems for a Multistory Building
Comparative Study on Post - Tensioned and Reinforced Concrete flat Slab Systems for a Multistory Building Thayapraba M Civil Department, NIT Trichy, (India) ABSTRACT Designers have a huge number of choices
More informationMajor Building and Special Structures
TECHNICAL SESSION 1 Major Building and Special Structures Moderator Russell B. Price, P.E. Suncoast Post-Tension L.P. Houston, Texas 2004 PTI Technical Conference Session 1 Dennis Wittry -- Denver's Invesco
More informationGarage Beam System DAYTONSUPERIOR.COM FORMING. For Post-Tensioned Beam and Slab Parking Structures
Garage Beam System For Post-Tensioned Beam and Slab Parking Structures FORMING The Garage Beam System is a complete forming system designed specifically for post-tensioned beam and slab multi-story parking
More informationCONSTRUCTION OF BALANCE CANTILEVER APPROACH SURAMADU BRIDGE
CONSTRUCTION OF BALANCE CANTILEVER APPROACH SURAMADU BRIDGE By Masakazu Matsubara Resident Engineer for Approach & Main Bridge Suramadu Bridge Project 1. DESIGN 1.1. Concept of Design of Cantilever Erection
More informationLaunching Bridges in to the Future. CBDG Annual Conference. Simon Bourne Managing Director. 26 June 2008
Launching Bridges in to the Future CBDG Annual Conference 26 June 2008 Simon Bourne Managing Director WWW.BENAIMGROUP.COM Use of Incremental Launching Deck lengths of more than 200m 30-70m spans, typically
More informationConstruction of Transfer Plate - from various case studies. Presentation prepared by Raymond Wong
Construction of Transfer Plate - from various case studies Presentation prepared by Raymond Wong Transfer plate is a structure sometimes finds in high-rise buildings in Hong Kong. Building design often
More information2016 ACEC/PA ANNUAL MEETING
2016 ACEC/PA ANNUAL MEETING z I-49 North, Segment K (I-220 to Martin Luther King Drive) Interchange Project Durk Krone, P.E., TRC Engineers Inc., Baton Rouge, La 1 I-49 North Segment K Project 2 AGENDA
More informationConcrete Bridge Design and Construction series
www.thestructuralengineer.org 41 CBDC series July 2014 Concrete Bridge Design and Construction series This series is authored by the Concrete Bridge Development Group (CBDG). The group aims to promote
More informationMARTA Rapid Transit Bridges
MARTA Rapid Transit Bridges his precast segmental post-tensioned concrete project for the T Metropolitan Atlanta Rapid Transit Authority demonstrates the ability of the segmental technique to economically
More informationCOURTYARD INFILL STRUCTURE DESIGN
COURTYARD INFILL STRUCTURE DESIGN Executive Summary The existing design for the courtyard within the G wing is for a cast-in-place concrete structure. The design being proposed within this analysis is
More informationTHE FORENSIC MEDICAL CENTER
THE FORENSIC MEDICAL CENTER Image courtesy of Gaudreau, Inc. TECHNICAL REPORT #2 OCTOBER 26, 2007 KEENAN YOHE STRUCTURAL OPTION DR. MEMARI FACULTY ADVISOR EXECUTIVE SUMMARY Image courtesy of Gaudreau,
More informationThesis Proposal Executive Summary Depth and Breadth Analysis
Mathew Nirenberg Structural Option Metropolis at Dadeland Adviser: Schneider Proposal Executive Summary 12/12/05 Thesis Proposal Executive Summary Depth and Breadth Analysis The Metropolis at Dadeland
More informationEvaluation and Repair of Existing Post- Tensioned Buildings with Paper Wrapped Tendons Experiencing Corrosion Damage
Evaluation and Repair of Existing Post- Tensioned Buildings with Paper Wrapped Tendons Experiencing Corrosion Damage K. Dirk Bondy, S.E. President Seneca Structural Engineering, Inc. The Great American
More informationWilliam R. Bennett Bridge. W.R. Bennett Bridge, Kelowna, B.C. Canada. July 2005 to December 2008
William R. Bennett Bridge W.R. Bennett Bridge, Kelowna, B.C. Canada. July 2005 to December 2008 Contract Details Scope: Design & Build the new W.R. Bennett Floating Bridge & Decommission existing Okanagan
More informationUS-131 Over the Muskegon River. Corey Rogers, P.E. Bridge Construction Engineer
US-131 Over the Muskegon River Corey Rogers, P.E. Bridge Construction Engineer NB and SB US-131 Each bridge is a three-span, 580 foot long, cast-in-place, post-tensioned concrete box girder structure resting
More informationPROJECT UPDATE SOUTH NORFOLK JORDAN BRIDGE CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA. April 2012
PROJECT UPDATE Rendering View from the City of Chesapeake Elizabeth River Boat Landing and Park looking across the Elizabeth River at Portsmouth CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA The new 5,375
More informationI-94/I-69 Interchange Bridge Construction
I-94/I-69 Interchange Bridge Construction General Project Information Let in August 2013 Cost of $76 million Prime Contractor Walter Toebe Construction Company Reconstruction of I-94 from Griswold to Lapeer
More informationSCHEME COMPARISONS OF NANPAN RIVER GRAND BRIDGE ON RAILWAY FROM YUNNAN TO GUANGXI
SCHEME COMPARISONS OF NANPAN RIVER GRAND BRIDGE ON RAILWAY FROM YUNNAN TO Xu Yong, Chen Kejian, Ren Wei, Hu Jintao, He Tingguo & You Lihui China Railway Eryuan Engineering Group Co. Ltd, Chengdu, Sichuan
More informationMIDAS Civil 2016 v2.1 Release Webinar. PSC Composite Design Check / Load rating
2016 v2.1 Release Webinar PSC Composite Design Check / Load rating What is Composite Girder Module? Wizard-modeling - Steel Composite Bridge - PSC Composite Bridge Report Generation for Design & Load Rating
More informationLesner Bridge Replacement
Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A Construction Camera has been installed to view images of the bridge construction. Images are updated on
More information1. Cast-in-place concrete is specified in Section
SECTION 03 38 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for furnishing and installing post-tensioned slabs, jacks, jacking and anchors at Parking Structure, and record
More information151 First Side. Technical Assignment 2 November 16 th, William J. Buchko. AE 481w Senior Thesis The Pennsylvania State University
November 16 th, 2007 William J. Buchko AE 481w Senior Thesis The Pennsylvania State University Thesis Advisor: Kevin Parfitt Table of Contents Executive Summary... 3 Structural System Overview Foundation...
More information2. Outline of the bridge 3-span continuous deck extradosed bridge Bridge length
Construction of Extradosed Bridge in the Government Financed Section EUI-NAM PARK, PM, Incheon Bridge Section 5, Doosan Construction & Engineering corporation KYUNG-KUK JUNG, GM, Incheon Bridge Section
More informationw w w. d u t c h l a n d i n c. c o m
RECTANGULAR TANKS TYPICAL INSTALLATION Precast concrete elements are manufactured at a Precast/ Prestressed Concrete Institute (PCI) certified facility. Precast concrete elements are set on a poured-in-place
More informationIronton Russell Bridge Project
Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014
More informationAnchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi
STRUCTURAL NOTES MATERIAL STRENGTHS Structural Steel Reinforcing Steel Concrete Masonry Structural Lumber Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel
More informationSPECIAL SPECIFICATION 4584 Segmental Concrete Bridge Unit
2004 Specifications CSJ: 0028-09-111 SPECIAL SPECIFICATION 4584 Segmental Concrete Bridge Unit 1. Description. Construct cast-in-place segmental concrete box girder superstructure according to the plans,
More informationTable of Contents.2. Introduction...3 Gravity Loading and Deflections..4. Existing Structural System..8
WISCONSIN PLACE RESIDENTIAL TECHNICAL ASSIGNMENT 2 OCTOBER 29, 2007 KURT KRASAVAGE THE PENNSYLVANIA STATE UNIVERSITY STRUCTURAL OPTION FACULTY ADVISOR: DR. ALI MEMARI 1 Table of Contents Table of Contents.2
More informationPLANNING DEPARTMENT 701 OCEAN STREET, 4 TH FLOOR, SANTA CRUZ, CA (831) FAX: (831)
County of Santa Cruz PLANNING DEPARTMENT 701 OCEAN STREET, 4 TH FLOOR, SANTA CRUZ, CA 95060 (831) 4542580 FA: (831) 4542131 STATEMENT OF SPECIAL INSPECTIONS California Building Code 1704.3 Prior to issuance,
More informationIronton Russell Bridge Project
Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014
More informationSUMMARY SHEETS OF INTEGRAL CONNECTIONS
APPENDIX F SUMMARY SHEETS OF INTEGRAL CONNECTIONS NCHRP 12-88 Connection Evaluations Appendix F F-1 APPENDIX F SUMMARY SHEETS OF INTEGRAL CONNECTIONS NCHRP 12-88 Connection Evaluations Appendix F F-2
More informationMIDAS Training Series
MIDAS midas Civil Title: All-In-One Super and Sub Structure Design NAME Edgar De Los Santos / MIDAS IT United States 2016 Substructure Session 1: 3D substructure analysis and design midas Civil Session
More informationTechnical Assignment 1 10/8/03
Executive Summary Technical Assignment 1 10/8/03 The is 55 story high-rise condominium being built off the northern Miami coast. The structural design presented in this building is a direct result of its
More informationFlexible Building Design
Flexible Building Design Introduction Technology in the healthcare field has continued to steadily advance in the past decade. As healthcare technology rapidly advances, the functionality of building spaces
More informationSpecial Considerations for Maintenance of the Sunshine Skyway Bridge
Florida Department of TRANSPORTATION Special Considerations for Maintenance of the Sunshine Skyway Bridge 2014 NATIONAL BRIDGE PRESERVATION PARTNERSHIP CONFERENCE James J. Jacobsen, P.E. District Structures
More informationTechnical Report #2 10/26/06
Photo courtesy of OTO Development, http://www.otodevelopment.com/ Dr. Memari Thesis Advisor Technical Report #2 10/26/06 Executive Summary Systems Overview Hollow Core Plank (precast) Solid Flat Slab (precast)
More informationLong Railway Viaducts with Special Spans: Part-1. Arch Construction by Balanced Cantilever with Auxiliary Cables
Long Railway Viaducts with Special Spans: Part-1. Arch Construction by Balanced Cantilever with Auxiliary Cables J. Manterola A. Martínez Carlos Fernández Casado S.L., Spain B. Martín J.A. Navarro M. A:
More informationSpliced Segmental Prestressed Concrete 1-Beams for Shelby Creek Bridge
PCI DESIGN AWARDS PROGRAM WINNER Spliced Segmental Prestressed Concrete 1-Beams for Shelby Creek Bridge William B. Caroland, P.E. Chief Bridge Engineer American Engineering Company Lexington, Kentucky
More informationGUIDELINES FOR EXECUTION OF ADAPT-PT 1
Structural Concrete Software System GUIDELINES FOR EXECUTION OF ADAPT-PT 1 Update: December 09, 2004 TN172 guide_to_run_pt_12 120904 The guidelines presented will assist you in the selection of design
More informationGARAGES/ONE-STORY City of Grand Rapids Building Safety Division
GARAGES/ONE-STORY City of Grand Rapids Building Safety Division 218-326-7601 www.cityofgrandrapidsmn.com This handout is intended only as a guide and is based in part on the 2015 Minnesota State Building
More informationShoring and Reshoring Fundamentals
Shoring and Reshoring Fundamentals by Mary Bordner Tanck, PE SHORING AND RESHORING FUNDAMENTALS Because it has such a significant impact on schedule and material movements, it is important for everyone
More informationA Research on Comparison of R.C.C and Post Tensioned Flat Slab with or Without Drop Using Software
2016 IJSRSET Volume 2 Issue 2 Print ISSN : 2395-1990 Online ISSN : 2394-4099 Themed Section: Engineering and Technology A Research on Comparison of R.C.C and Post Tensioned Flat Slab with or Without Drop
More informationJFK Airport Light Rail Transit System
JFK Airport Light Rail Transit System Author: Co-Author: Company: José M. Rodriguez, P.E., Senior Project Director D. Brice Urquhart, P.E., Project Manager Figg Bridge Engineers, Inc. Address: 424 N. Calhoun
More informationStructural System Design
Structural System Design STRUCTURAL SYSTEM DESIGN DESIGN CRITERIA The primary goals and criteria governing the alternate concrete superstructure design are as follows: -maintain an open office layout,
More informationBRIDGES WITH PROGRESSIVELY ERECTED DECKS
Istanbul Bridge Conference August 11-13, 2014 Istanbul, Turkey BRIDGES WITH PROGRESSIVELY ERECTED DECKS P. Novotny 1, P. Svoboda 2 and J. Strasky 3 ABSTRACT Two types of bridges with progressively erected
More informationThe New, Balanced Cantilever, Bridge over Acheloos River in Greece
The New, Balanced Cantilever, Bridge over Acheloos River in Greece Chrysanthos Maraveas 1, Konstantina Tasiouli 1 and Konstantinos Miamis 1 1 C. MARAVEAS PARTNERSHIP Consulting Engineers, Athens, Greece.
More informationSINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT. Srdjan Brasic, M.Sc., P.Eng.
SINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT Srdjan Brasic, M.Sc., P.Eng. UMA Engineering Ltd. Paper prepared for presentation at the Technical
More informationFolsom Lake Crossing by Hans Strandgaard, Alex Harrison, Jeff Aldrich, and Jeff Thomure, CH2M HILL
Design and Construction Folsom Lake Crossing by Hans Strandgaard, Alex Harrison, Jeff Aldrich, and Jeff Thomure, CH2M HILL View of the Folsom Dam and the canyon just upstream of construction. The area
More informationConstruction Techniques of The 3 rd Bosphorus Bridge in Istanbul, Turkey
International Symposium on Industrial Chimneys and Cooling Towers, Prague, Oct 8-11, 2014 Construction Techniques of The 3 rd Bosphorus Bridge in Istanbul, Turkey M. Orçun TOKUÇ 1 and Tamer TUNCA 2 1 Engineer
More informationTilikum Crossing Transit Bridge. Portland, OR
Tilikum Crossing Transit Bridge Portland, OR Technical Information Size of Project: The Tilikum Crossing Transit Bridge is 1,720 ft. long and required 24,000 cy total concrete Strength Requirements: The
More informationSPECIAL INSPECTION AND OBSERVATION PROGRAM CITY OF CONCORD BUILDING DIVISION. Project Address:
SPECIAL INSPECTION AND OBSERVATION PROGRAM CITY OF CONCORD BUILDING DIVISION Permit Application #: Project Address: Purpose: To meet the requirements of CBC Section 1704.3 this form may be used as a statement
More informationTopic Outline. Two Stage Analysis Procedure: Podium Design. Part 2: Rigid Lower Portion Philip Miller, S.E. 2/8/2018
Two Stage Analysis Procedure: Podium Design Part 2: Rigid Lower Portion Philip Miller, S.E. Topic Outline Types of Podium Construction Example Buildings PT Basics PT Analysis Modeling Tips Load Balancing
More information7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by
Construction Technology B (CON4313) Self Assessment Questions: Chapter 1 Prestressed Concrete 1. How does the prestressing of steel tendons in prestressed concrete offer a higher loading capacity than
More informationPost-tensioned Concrete Design PT Installation Guidance
Post-tensioned Concrete Design PT Installation Guidance Lee Maartensz Construction Manager - Structural Systems UK Ltd PT Installation Bonded Flat Slabs Installation 1 Flat Slabs Beam and Slab Installation
More informationDIVISION 03 CONCRETE SPECIFICATION : FORMS AND FORMWORK
DIVISION 03 CONCRETE SPECIFICATION 031000: FORMS AND FORMWORK PART 1.0 GENERAL 1.1 DESCRIPTION The work of this specification includes furnishing of all labor, materials, equipment and incidentals to install,
More informationPrincipal Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE
Design of continuity slabs and the 020 Gajanan Chaudhari Principal Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE Anand Panpate Senior Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE
More informationLecture 13 CONCRETE WORKS
Lecture 13 TSP-308 MPK Ferdinand Fassa CONCRETE WORKS Concrete works Concrete is a man-made (rock) construction material, which is a mixture of portland cement, water, aggregates, and in some cases, admixtures.
More informationSouthern Cross Hospitals Ltd Endoscopy Consultants PRESSS Building
ENG.HAV.0001.1 Southern Cross Hospitals Ltd Endoscopy Consultants PRESSS Building Gary Haverland BE (Civil)(Hons) Director / Senior Engineer Structex, Christchurch ENG.HAV.0001.2 ENG.HAV.0001.3 ENG.HAV.0001.4
More informationIn Association with. DSE PROJECTS - Lebanon
In Association with DSE PROJECTS - Lebanon Pre-Stressing System Pre-Stressing, results in thinner slabs, which produces valuable extra space, and in turn will be used to create additional floors. This
More informationIntermountain Section AWWA Conference - 2.0MG Layton Water Tank. Jake O Brien
Intermountain Section AWWA Conference - 2.0MG Layton Water Tank Jake O Brien Presentation Outline Layton City s decision process Tank Design/Construction Tendon Tanks - don t shed the good stuff Layton
More informationLesner Bridge Replacement
Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A Construction Camera has been installed to view images of the bridge construction. Images are updated on
More informationDesign and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.
Design and Construction of the SH58 Ramp A Flyover Bridge over IH70 Gregg A. Reese, PE, CE, Summit Engineering Group, Inc., Littleton, CO ABSTRACT: The SH58 Ramp A bridge in Golden, CO is the latest on
More informationFAIRFIELD INN & SUITES, MARRIOT PITTSBURGH, PA
10/28/2009 TECHNICAL REPORT II FAIRFIELD INN & SUITES, MARRIOT PITTSBURGH, PA Advisor: Dr. Ali Memari Structural Option TABLE OF CONTENTS Table of Contents 2 Executive Summary...3 Introduction: Fairfield
More informationNew Main Hospital, Site Park, and Underground Garage Construction Progress Update #8
New Main Hospital, Site Park, and Underground Garage Construction Progress Update #8 Date: July 1, 2009 From: Gary Claar Engineering Services 355-1660 Gary.Claar@NationwideChildrens.org June was a very
More informationSPECIAL INSPECTION AND TESTING AGREEMENT
COUNTY OF MENDOCINO DEPARTMENT OF PLANNING AND BUILDING SERVICES 860 NORTH BUSH STREET UKIAH CALIFORNIA 95482 120 WEST FIR STREET FT. BRAGG CALIFORNIA 95437 STEVE DUNNICLIFF, DIRECTOR PHONE: 707-234-6650
More informationTips For Designing Constructable Concrete Buildings
Tips For Designing Constructable Concrete Buildings by Clifford Schwinger, P.E. The Harman Group, Structural Engineers King of Prussia, Pa. Structural Engineers Association of Ohio Annual Conference Presentation
More informationNATIONAL HARBOR BUILDING M
NATIONAL HARBOR BUILDING M 120 Waterfront St. Oxon Hill, Maryland Ryan Sarazen Structural Option Senior Thesis Presentation Spring 2008 Faculty Consultant Dr. Lepage BUILDING LOCATION BUILDING M SITE PLAN
More informationPrecast Prestressed Segmental Elevated Urban Motorway in Italy
Precast Prestressed Segmental Elevated Urban Motorway in Italy Bruno Gentilini Lino Gentilini Consulting Engineers Trento, Italy Bruno Gentilini Lino Gentilini The authors, who were responsible for the
More informationPrepared by Elie F. Issa, Eng. D.E.C. August 2016
Prepared by Elie F. Issa, Eng. D.E.C. August 2016 SAMA BEIRUT Sama Beirut is the tallest reinforced concrete tower in Lebanon soaring at a height of 220m from ground level Project Entities Owner Antonios
More information18. Wall rebar arrangement
18. Wall rebar arrangement 1) Sequence of rebar arrangement The worker is not allowed to change the rules and instructions of reinforcement without permission. All the reinforcement should be in accordance
More informationSelection guide for Adapt Builder:
PRODUCT PAGE: Adapt - New For over two decades, engineers worldwide have relied on ADAPT's industry leading software solutions to achieve the highest levels of design productivity. Since 1981, ADAPT has
More informationIronton Russell Bridge Project
Construction Update October 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2015
More informationRESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO
RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO QUARTERLY REPORT July 1, 2017 to September 30, 2017 Period Year 2 Project Shake Table Studies of a Bridge System with ABC Connections Submitted by M. Saiidi,
More informationHalls River Bridge Update
2018 FTBA Construction Conference February 8 & 9, 2018 Orlando, FL 2017 FTBA Construction Conference Registration February 2 & 3, 2017 Orlando, FL Halls River Bridge Update Antonio Nanni, U. Miami, nanni@miami.edu
More informationRESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO
RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO QUARTERLY REPORT October 1, 2017 to December 31, 2017 Period Year 2 Project Shake Table Studies of a Bridge System with ABC Connections Submitted by M. Saiidi,
More informationSUMMARY SHEETS OF HYBRID CONNECTIONS
APPENDIX E SUMMARY SHEETS OF HYBRID CONNECTIONS NCHRP 12-88 Connection Evaluations Appendix E E-1 APPENDIX E SUMMARY SHEETS OF HYBRID CONNECTIONS NCHRP 12-88 Connection Evaluations Appendix E E-2 Location:
More informationConcrete Bridge Design and Construction series
40 Concrete Bridge Design and Construction series This series is authored by the Concrete Bridge Development Group (CBDG). The group aims to promote excellence in the design, construction and management
More informationNew Parkland Hospital Post Tensioned Walls
New Parkland Hospital Post Tensioned Walls TAHFM Interlink 2014 Craig Williams & Kevin Yu Austin Commercial Subsidiary of Austin Industries, founded in 1918 Ranked 23 rd on ENR s Top CM at Risk firms Annual
More informationSection 5 - Project Logistics
Section 5 - Project Logistics The project schedule for the Pearland Recreation Center and Natatorium begins with commencement of design on March 1, 2007 and ends with substantial completion on May 12,
More informationConcrete Design Guide
Number 7 38 TheStructuralEngineer Technical July 2015 Post-tensioned slabs Concrete Design Guide No. 7: Design of post-tensioned slabs This series is produced by The Concrete Centre to enable designers
More informationInternational Journal of Advance Engineering and Research Development
Scientific Journal of Impact Factor (SJIF): 5.71 International Journal of Advance Engineering and Research Development Volume 5, Issue 4, April -218 e-issn (O): 2348-447 p-issn (P): 2348-646 ANALYSIS OF
More informationPrecast Segmental Bridge Construction Part 4 - Balanced Cantilever Erection Method
Precast Segmental Bridge Construction by John E. Kristensen PE., PLS., PMP. Introduction The popularity of precast concrete segmental bridge construction has grown worldwide in the last few decades. A
More information***************************************************************************************************************
03365 POST-TENSIONED CONCRETE *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 03 38 00. ***************************************************************************************************************
More informationNational Craft Assessment and Certification Program S P E C I F I C A T I O N S
National Craft Assessment and Certification Program S P E C I F I C A T I O N S Industrial Carpentry V5 TBD Focus Statement An industrial carpenter erects concrete forms, plumb, level and to grade; places
More informationStructural Tests and Special Inspections Form. Inspection of Fabricators (1704.2)
Inspection of Fabricators (1704.2) Furnish inspection reports (1704.2.1) - Fabricators that have not been approved Provide a Certificate of Compliance (1704.2.2) - Approved Fabricators Steel Construction
More informationLong Key Bridge, a spectacular example. Design Features and Prestressing Aspects of Long Key Bridge
Design Features and Prestressing Aspects of Long Key Bridge { i Thomas M. Gallaway* Principal Cutler-Gallaway Services, Inc. Consulting Engineers San Antonio, Texas Long Key Bridge, a spectacular example
More informationDESIGN OF THE MAIN SPANS OF THE CHONGQING CAIYUANBA BRIDGE
Design of the Main Spans of the Chongqing Caiyuanba Bridge ARCH 04 M.C. Tang and J. Sun @CIMNE, Barcelona, 2004 DESIGN OF THE MAIN SPANS OF THE CHONGQING CAIYUANBA BRIDGE Man-Chung Tang* and John Sun+
More informationConcrete Prestressed Concrete Pretensioned Concrete Posttensioned Concrete Typical Tendon Layout
Concrete 45 1.13.0 Prestressed Concrete Concrete in which internal stresses (forces) are induced by means of prestressing steel tendons such that tensile stresses resulting from loads are counteracted
More informationLintel Tables Design Notes and Limitations
LINTEL TABLES Lintel Tables Design Notes and Limitations 1. These tables apply to one and two family residential structures only that conform to the requirements of the 2006, 2009 or 2012 International
More information