Attachment A Exterior Building Improvements Susquehanna County, Roadside Rest Site #56, I-81 SB Project # Building # 045R561
|
|
- Andrea Morton
- 5 years ago
- Views:
Transcription
1 I. Bidding Requirements Contractor to provide one bid for the following: Planter removal, sidewalk repair/replacement/installation, exterior thru wall in fill. II. Work Included The following items are site specific requirements of the project. Contractor to repair, replace and install the necessary materials to complete the work identified below. NOTE: Items and products listed herein, by a single manufacturer, are for setting benchmarks for the products to be used. The phrase or Department approved equal means that any product submitted, not specifically named herein, must meet or exceed all of the qualifications of those items called for in this specification. NOTE: The contractor shall obtain permits from the Department of Labor and Industry and all local municipalities as may be required. Existing L & I Permit Number is NOTE: The contractor shall use environmentally safe products wherever possible Planter Removal Remove all concrete block/brick planter(s), dirt, electrical wiring and conduit, light fixtures and any other components required, associated with the planters. All remaining lighting (sidewalk lighting) should be working. The two (2) up lights in the planter bed are to remain and be working. Regrade the area to match the surrounding grade levels. Contractor is responsible to identify any underground utilities including all utility company owned or Department owned utilities. Contractor to remove brick wing wall at addition at addition down to existing foundation and fill void with ground, compacted back up to existing surrounding grade levels. o If existing brick wing wall abuts existing building wall, remove wing wall and all mortar from the existing building wall. Patch and repair or replace any existing wall brick and mortar joints to match existing. o If wing wall is toothed into existing building wall, grind out existing mortar joints and remove wing wall. Install new brick or re-use Page 1 of 8 11/1/2012
2 good brick from wing wall being removed to infill the toothed area of existing building wall to remain. Contractor to frame, insulate and infill to match existing where the thru wall units penetrate building exterior by means of one of the following methods. CMU and brick with ties. Steel studs packed with fiberglass batten insulation, cement board (or Department approved equal) and brick Materials o 6 CMU o Type S mortar, color to match existing adjacent mortar o Cement board o Wall ties, if required o New brick to match existing wall brick in color, type and size o Type S mortar, color to match existing adjacent mortar OR o 22 gauge steel studs o Minimum R19 fiberglass insulation o Cement board (or approved equal) o New brick to match existing wall brick in color, type and size o Type S mortar, color to match existing adjacent mortar Installation o Remove any existing materials, currently in place, from the openings. o Install the new wall system using the approved method o Contractor is to submit details of the proposed method of reconstruction to the Department for approval Sidewalk/Repair/Replacement/Installation Contractor to remove and replace approximately 200 square feet of concrete. To be identified and marked at pre-bid. Contractor to install approximately 250 square feet of new sidewalk. To be identified at pre-bid. Contractor to grind high edges of concrete to eliminate trip hazards. Approximately 100 lineal feet. To be marked at pre-bid. Contractor to remove all deteriorated caulking and expansion materials and replace with new. This is where the concrete is ground and where there is replacement concrete. Page 2 of 8 11/1/2012
3 Contractor shall place 6 X 6 #10 gauge wire mesh with chairs for reinforcement. Contractor shall drill into any adjoining concrete pad(s) to a minimum depth of six inches (6 ). Then set a minimum eighteen inches (18 ) long #4 rebar in epoxy in the hole. Rebar are to be placed at a maximum of twelve inch (12 ) spaced intervals along the existing pad (s) starting six inches (6 ) from each end. Rebar is to be set at the height of the chairs supporting the wire mesh so the mesh can be wired to the rebar for additional stability. Contractor shall seal new concrete. Contractor to power wash and seal all existing concrete. Contractor shall follow National Concrete and Masonry requirements and standards. This project will also include the testing for air slump, and cylinders molded for testing the psi. Contractor to reestablish vegetation where disturbed. Contractor is responsible for verifying all quantities and measurements. Contractor to use environmentally safe products whenever possible. Materials. Sub base shall be clean, Type 2A aggregate material Cement Portland cement concrete shall be air-entrained and have a minimum 28 day compressive strength shall be 3,800 psi. Slump: 1 minimum 4 maximum. Air Content: 4.5% minimum 7.5% maximum. Temperature: 45 degrees F minimum 100 degrees F maximum. Forms - shall be. Approved metal forms. Wood forms, not less than 2-inch nominal thickness, planed on finish side. Forms - shall be coated with a form release agent just prior to placement of concrete. Form release agents shall be none staining, liquid chemical coatings free of Kerosene, oil which effectively prevent absorption of moisture into the forms and bonding of the concrete to the forms. Reinforcement welded wire mesh 6 X 6 #10 gauge wire, and chairs. Epoxy coated #4 rebar Bars/Pins grade 60 Billet steel. Joint Material - Joint filler premolded expansion joint material shall be fiber joint filler. Sealtight or Department approved equal Page 3 of 8 11/1/2012
4 Joint Material Closed cell foam backer rod Concrete curing compound shall be clear, non-staining liquid coatings containing no oil or wax. Safe-Cure, Seal tight 1100, Klear seal R-75 or Envirocure Clear 500, or a Department approved equal. Joint Sealant Sonolastic SL 2, Sicaflex-2c, or Department approved equal. Concrete sealant Linseed Oil, Thompson s Waterseal or Department approved equal. Sidewalk Construction Excavate to required depth to remove and dispose of all concrete material, aggregate and sub grade material to a sound foundation. Replace disturbed ground sub grade, compacted back to a level to match existing adjoining sub grade to insure a solid foundation. Install new, clean, Type 2A aggregate base material compacted back to the level to match the existing adjoining base material. Exposed edges of existing work shall be smooth and square and protected from damage during new construction. Contractor shall repair any damages, caused by him or his worker/sub-contractors, to adjoining areas, to the satisfaction of the Department and at no additional cost to the contract. Open trenches and excavations shall be free from standing water and protected from rain water build up in the event of inclement weather. No items under contract shall be placed over frozen base, sub base or sub grade materials. No new materials shall be installed under contract when the forecast is for freezing temperatures. Failure to adhere to this requirement will result in removal and replacement of all items by the Contractor, at the direction of the Department, and at no additional cost to the contract. The contractor shall provide the Department with a jointing detail(s) for construction and expansion joints. The detail will be reviewed and approved by the department prior to the start of any installation. Sidewalk Installation. All work shall be performed by responsible, skilled and qualified trade s person Erect forms to match the shape lines grades and dimensions to obtain the same finished size of concrete that is being replaced. Forms shall be erected plumb, true, and square. All joints shall be tight to prevent leakage of concrete and/or grout. All forms shall be sufficiently braced, tied or shored so as to maintain the desired position and shape before, during and after placement. Page 4 of 8 11/1/2012
5 Score control joints at five (5) foot intervals to sufficient depth to ensure cracking at the joint. Do not saw cut the control joints. Provide 1/2 expansion joint material where adjoining existing concrete. Apply light broom finish immediately after float finish, to match existing. Begin proper curing immediately following placement. Apply a moisture-retaining cover to prevent premature drying of concrete. Wet down as required. Protection. Forms should be removed from the immediate areas of work after stripping. Store forms in an area and manner, which will limit potential hazards and/or injury. Take precautions necessary to ensure against damage to existing work to remain in place, to be reused, or to remain the property of the Department. Damage to such work shall be repaired, or replacement shall be made, as directed by, and to the satisfaction of, and at no additional cost to the Department. Ensure the safe passage of persons around the area of construction. Provide temporary barricades, fencing and signs as required to keep the work site controlled and the public safe from harm. Clean-up Sidewalk Grinding Remove debris and rubbish from the site promptly. Remove debris from the site in a manner which will minimize interference with traffic. Remove and transport debris in a manner that will prevent spillage on the road. Comply with local regulations regarding hauling and disposal. Description Grind so the sidewalk surface has essentially the same or slightly rougher texture adjacent to the grinding and is no more than 1/4" higher than the existing sidewalk adjacent to the work. Grinding to be performed so that the finished grind has a straight back line with no stray grinding marks. Page 5 of 8 11/1/2012
6 The finished slope to be a maximum of 8:1 The area shall be cleaned and sealed. Submittals and final Deliverable items o The Department will provide the awarded contractor a complete breakdown of the required submittals based off of the System identified, I.E. Roofing System o Contractor to provide three (3) copies of the entire project documentation in three (3) ring Binders. o Binders to include the following items: Bid Documents & Specifications All project meeting minutes (pre-bid, pre-job, Interim, and Final inspection) Correspondence Submittals L&I approved Engineered Drawings (Paper/CD) L&I Building Permits, Inspection Logs, Occupancy Permit, Other correspondence Certifications Certified Payrolls (Prevailing Wage rates) Waste receipts Photos Before, during and after o A sufficient amount of Photos is required for all phases of construction on all buildings, base on award. o Building Final-Exterior all four sides Operation and Maintenance manuals Contractors Warranty Manufactures Warranty I. SUBMITTAL PROCEDURE A. Submit Two (2) copies of all items shown on submittal schedule except for "samples". B. Identify project number, project name and location, and contractor's name and address on all submittals. Page 6 of 8 11/1/2012
7 C. Provide space for review stamps of Contractor and Department. Put contractor stamp of approval on each item submitted. D. Revise and resubmit submittals as required, identify all changes made since previous submittal. E. No work shall be performed until all submittals are approved by the Department. Work performed prior to submittal approval is performed at the Contractor's risk and may be subject to repair, replacement or other corrective measures as deemed necessary by the Department with no additional contract time or money. F. Review of shop drawings will be general and for the limited purpose of checking for general conformance with the design; and shall not relieve the Contractor from the responsibility for proper fitting and construction of the work, nor from furnishing materials and work required by the Contract which may not be indicated on the shop drawings when reviewed. G. The submittals required by this contract are subject to reproduction for the Department's internal use only. By signature on this bid proposal, both the Contractor and the equipment manufacturer authorize the Department to reproduce any materials including printed literature and training aids, submitted in fulfillment of this contract. II. MANUFACTURER'S INSTRUCTIONS A. When specified in individual specification sections, submit manufacturer's printed instructions for delivery, storage, assembly, installation, start-up, adjusting and finishing, and maintenance, in quantities specified for product data. B. Identify conflicts between manufacturer's instructions and contract documents. III. MANUFACTURER'S CERTIFICATES A. When specified in individual specification sections or on submittal schedule, submit manufacturer's certificates to for review. B. Indicate that material or product conforms to or exceeds specified requirements. Submit supporting reference date, affidavits and certifications as appropriate. Page 7 of 8 11/1/2012
8 C. Certificates may be recent or previous test results on material or product, but in all cases must be acceptable to Department. IV. SUBMITTAL SCHEDULE A. Abbreviations: SoSu - Source of Supply DeDa - Descriptive Data or Catalog Cuts ShDr - Shop or Installation Drawings CoCh - Color Chart Cert - Certificates Samp Samples B. Schedule: Description of items to be submitted SoSu DeDa ShDr CoCh Samp Cert 1. Line Item Cost Breakdown 2. Work Schedule X X 3. Aggregate Material X X 4. Steel Certifications Rebar, Cold Formed Steel 5. Joint Material X X 6. Concrete Curing Cmpnd. X X 7. Concrete Sealant X X 8. Joint Sealant X X 9. Conc. Crack/Spall Repair X X X X X X X 10. Insulation X X X 11. Exterior Infill Drg. X X X 12. Waste Receipts X 13.Final Deliverable (2) three ring binders X Page 8 of 8 11/1/2012
Attachment A Concrete Curb and Sidewalk Replacement Cambria County, Johnstown Driver s Exam Center Project# Building# 093DL01
I. Bidding Requirements The Contractor to provide bid for entire project. II. Work Included The following items are site specific requirements of the project. Contractor to repair, replace and install
More informationAttachment A Repair Knee Brace on High Arch Salt Building Fayette County, Mill Run Stockpile #24 Project # Building #PA
I. Base Bidding Requirements This is a Base Bid project; the following describes the Base Bid requirements. Contractors are to provide bids for Base Bid #1. A. BASE BID #1: II. Work Included The following
More informationAttachment A Project Specification Repair of a Salt Dome Building Philadelphia County, Betsy Ross Stockpile # Dome# Project #
I. Base Bidding Requirements This is not a Base Bid project. II. Work Included The following items are site specific requirements of the project. A. Contractor to repair, replace and install the necessary
More informationATTACHMENT A Sanitary Sewage Line Replacement Columbia County, Roadside Rest Site# 38, I-80 WB Project# Roadside Rest Grounds# 031R380
I. Base Bidding Requirements This is not a base bid project. II. Work Included The following items are site specific requirements of the project. Contractor to repair, replace and install the necessary
More informationAttachment A Perry County Maintenance Facility 8-9 Floor Repair New Bloomfield
I. Bidding Requirements The following describes the Bid Requirements. Contractors are to provide bid for the entire project which includes: Provide concrete floor repairs to the 2 nd level of the maintenance
More informationSECTION PORTLAND CEMENT CONCRETE
PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including the supplemental documents as indicated in the Site Work General Provisions, apply to work of this
More informationSECTION CAST-IN-PLACE CONCRETE
SECTION 03300 CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.01 SECTION INCLUDES A. The Contractor shall furnish all work and materials, including cement, sand and coarse aggregate, water, admixtures, curing
More informationREINFORCED CONCRETE MASONRY SECTION
SECTION 04 22 02 - REINFORCED CONCRETE MASONRY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 01 Specification
More informationSECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS
SECTION 01 00 00 GENERAL REQUIREMENTS PART 1 - GENERAL 1.1 SECTION INCLUDES A. Summary of Work: 1. General 2. Contract. B. Contract Considerations: 1. Schedule of values. 2. Applications for payment. 3.
More informationSECTION RIGID PAVEMENT
SECTION 02750 PART 1 GENERAL RIGID PAVEMENT 1.1 SUMMARY A. Section Includes: 1. Concrete sidewalks. 2. Concrete stair steps. 3. Concrete integral curbs gutters. 4. Concrete parking areas and roads. B.
More informationSECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course.
SECTION 02750 RIGID PAVEMENT PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Portland Cement Concrete (PCC) pavement. B. Related Sections: 1.2 REFERENCES 1. Section 02315 Excavation. 2. Section 02721
More information1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK
1993 SPECIFICATIONS CSJ 581-1-95 SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1. DESCRIPTION. This Item shall govern for the furnishing and installation of all materials and equipment for
More informationReCote Finish System over Concrete
Part 1 General 1.01 GENERAL A. The Master Wall ReCote Finish System for smooth precast and cast in place concrete consists of an acrylic primer and ReCote acrylic finish. When needed an acrylic modified
More informationSECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS
SECTION 32 16 13 CONCRETE CURBS, GUTTERS AND SIDEWALKS PART 1 GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide all labor, materials, equipment, and incidentals as shown, specified, and required
More informationParagraph Description Page No General Materials Concrete Masonry Work Altitude Valve Vault Cover 25-4
City of Columbia Engineering Regulations PART 25: SPECIFICATIONS FOR ALTITUDE VALVE VAULT Table of Contents Paragraph Description Page No. 25.1 General 25-1 25.2 Materials 25-1 25.3 Concrete Masonry Work
More informationSECTION CONCRETE PAVING
SECTION 32 13 13 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for providing portland cement concrete work and all other incidental concrete improvements for the project
More informationSECTION UNIT MASONRY
SECTION 04200 UNIT MASONRY PART 1 GENERAL 1.01 SUMMARY A. Furnish labor, materials, and equipment and perform functions required in the installation and maintenance of the work covered by this Section.
More informationMaster Specifications for Microcotta November 2017
SECTION 042130 - MICROCOTTA PART 1 - GENERAL 1.1 SUMMARY A. Provide Architectural Microcotta, cast architectural polymer resin units manufactured in accordance with the Contract Documents. 1.2 WORK INCLUDED
More informationSECTION BRICK MASONRY ASSEMBLIES
PART 1 - GENERAL 1.1 SUMMARY A. Section includes the following: 1. Face brick. 2. Mortar and grout. 3. Ties and anchors. 4. Miscellaneous masonry accessories. 1.2 SUBMITTALS A. Product Data: For each type
More informationSECTION MORTAR
PART l - SCOPE SECTION 04100 - MORTAR A. This Section includes all labor, materials, equipment, and related items required for the work of mortar as shown on the Drawings and specified herein. The work
More informationSECTION SITE CONCRETE
SECTION 321313 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting
More informationSPECIAL SPECIFICATION 2042 Decorative Colored Pattern Concrete Paving
2004 Specifications CSJ 0196-02-120 SPECIAL SPECIFICATION 2042 Decorative Colored Pattern Concrete Paving 1. Description. This Item shall govern for the furnishing and placing of colored concrete wave
More informationSECTION TILT-UP PRECAST CONCRETE. A. Work includes, but is not limited to, the following:
SECTION 03470 TILT-UP PRECAST CONCRETE PART 1 GENERAL 1.01 SUMMARY A. Work includes, but is not limited to, the following: 1. Precast wall panels. 2. Forms and casting beds. 3. Concrete. 4. Reinforcing
More informationTILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:
PART 1 GENERAL 1.01 SUMMARY SECTION 03460 TILT-UP PRECAST CONCRETE SANDWICH PANELS A. Work includes, but is not limited to, the following: 1. Architectural precast concrete sandwich wall panels. 2. Integral
More information17.0 CONSTRUCTION OF OPEN DRAINAGE SYSTEMS
17.0 CONSTRUCTION OF OPEN DRAINAGE SYSTEMS 17.1 Description The work covered by this section of the specifications consists of furnishing all labor, the construction and installation of open storm drain
More informationGUIDE SPECIFICATIONS For STRUCTURAL PRECAST HOLLOW CORE SLABS SECTION 03410
GUIDE SPECIFICATIONS For STRUCTURAL PRECAST HOLLOW CORE SLABS SECTION 03410 Note to user: These guide specifications are provided by Mid- States Concrete Products as a service to you; they are NOT specific
More informationSECTION TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:
PART 1 GENERAL 1.01 SUMMARY SECTION 03460 TILT-UP PRECAST CONCRETE SANDWICH PANELS A. Work includes, but is not limited to, the following: 1. Architectural precast concrete sandwich wall panels. 2. Integral
More informationSection CONCRETE SIDEWALKS. 1. Payment for concrete sidewalks is on square foot basis.
PART 1 GENERAL 1.01 SUMMARY A. This Section includes the following: Section 02775 1. Reinforced concrete sidewalks. 2. Wheelchair Ramps. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices. 1. Payment for concrete
More informationKU Design Guidelines APPENDIX II PERMEABLE BITUMINOUS PAVEMENT
PERMEABLE BITUMINOUS PAVEMENT PART 1: GENERAL 1.01. RELATED DOCUMENTS: A. Drawings and general provisions of Contract, including Special Requirements General Conditions and Division 1 Specifications Sections,
More informationSPECIAL SPECIFICATION 4703 Repair Of Impact Damaged Prestressed Concrete Bridge Beams
1993 Specifications CSJ 0162-01-080, etc. SPECIAL SPECIFICATION 4703 Repair Of Impact Damaged Prestressed Concrete Bridge Beams 1. Description. This Item shall govern for the repair of impact damaged prestressed
More informationFOR PROJECTS INITIATED AFTER FEBRUARY 1, 2010 REVISION 3 ITEM 530 CONCRETE CURB, GUTTER, CURB AND GUTTER SIDEWALKS AND DRIVEWAYS
AFTER FEBRUARY 1, 2010 ITEM 530 CONCRETE CURB, GUTTER, CURB AND GUTTER SIDEWALKS AND DRIVEWAYS 530.1 Description. This item shall govern for curb, gutter, combined curb and gutter, sidewalks and/or driveways,
More informationUNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:
SECTION 321610 - CURBING PART 1 - GENERAL 1.1 DESCRIPTION A. This Section specifies requirements for furnishing and installing all types of curbing including the following: granite curb, concrete and bituminous
More informationITEM 431 PNEUMATICALLY PLACED CONCRETE. All material shall conform to the pertinent requirements of the following items:
ITEM 431 PNEUMATICALLY PLACED CONCRETE 431.1. Description. This Item shall govern for furnishing and placing of "Pneumatically Placed Concrete" for encasement of designated structural steel members, the
More informationSECTION CONCRETE PAVING
PART 1 GENERAL 1.1 SECTION INCLUDES SECTION 32 13 13 CONCRETE PAVING A. Extent of concrete curbs, walks, and paving as show on drawings B. Earthwork and prepared sub-base C. Concrete and related materials
More informationMANUFACTURER S (SHORT FORM) SPECIFICATION / SECTION
STUC-O-FLEX - ELASTOMERIC ACRYLIC FINISH APPLICATION TO PORTLAND CEMENT PLASTER / CONCRETE RENDER MANUFACTURER S (SHORT FORM) SPECIFICATION / SECTION 09220-09 24 00 PART 1-GENERAL SCOPE: Manufacturer's
More informationMANUFACTURERS (SHORT FORM) SPECIFICATION / SECTION
STUC-O-FLEX - ELASTOMERIC ACRYLIC FINISH APPLICATION TO PORTLAND CEMENT PLASTER / CONCRETE RENDER MANUFACTURERS (SHORT FORM) SPECIFICATION / SECTION 09220-09 24 00 PART 1-GENERAL SCOPE: Manufacturer's
More informationSECTION TILING
PART 1 GENERAL 1.01 SECTION INCLUDES A. Ceramic Tile for floor applications. B. Ceramic Tile for wall applications. C. Ceramic accessories. D. Ceramic trim. E. Non-ceramic trim. 1.02 RELATED REQUIREMENTS
More informationSECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES
Section SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL... 39-1 39-2 PRECAST CONCRETE MANHOLES... 39-1 39-2.01 Precast Concrete Storm Drain Manholes... 39-1 39-3 SADDLE MANHOLES... 39-2 39-3.01 Saddle
More informationA. Section includes cast-in-place concrete, including reinforcement, concrete materials, mixture design, placement procedures, and finishes.
SECTION 033053 - CONCRETE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationSECTION CONTROLLED LOW STRENGTH MATERIAL
SECTION 03300 CONTROLLED LOW STRENGTH MATERIAL PART 1 GENERAL 1.1 DESCRIPTION A. This Section specifies Controlled Low Strength Material (CLSM) to be used as described in this specification, including
More informationCONCRETE PAVEMENTS GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 7 WATER RECLAMATION PROJECT JUNE 2013
WATSON ROAD FACILITY PAGE 1 OF 7 PART 1 - GENERAL 1.1 Description The work covered by this Section shall be all labour, materials, equipment, and supervision necessary to complete all concrete work shown
More informationCounty of Sacramento Standard Construction Specifications January 1, 2008 TECHNICAL PROVISIONS
County of Sacramento Standard Construction Specifications January 1, 2008 TECHNICAL PROVISIONS SECTION 27 CURBS, GUTTERS, SIDEWALKS, AND DRAINAGE STRUCTURES 27-1 GENERAL Concrete curbs, gutters, sidewalks,
More informationCELCORE CELLULAR INSULATING CONCRETE SPECIFICATION FOR RETROFIT PLACEMENT OVER EXISTING ROOF MEMBRANES
PART 1: SCOPE CELCORE CELLULAR INSULATING CONCRETE SPECIFICATION FOR RETROFIT PLACEMENT OVER EXISTING ROOF MEMBRANES 1.1 An Approved Celcore Applicator shall furnish all labor, materials and supervision
More informationSECTION CURB RAMPS AND OTHER MINOR CONCRETE FACILITIES. Part 1 - General Work Included Related Requirements...
SECTION 02530 CURB RAMPS AND OTHER MINOR CONCRETE FACILITIES CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Inspection And Tests... 1 1.04 Quality Assurance...
More informationCONCRETE WALKS AND CURBS SECTION CONCRETE WALKS AND CURBS PART 1 - GENERAL
13686.00 CONCRETE WALKS AND CURBS 033015-1 1.1 RELATED DOCUMENTS: SECTION 033015 CONCRETE WALKS AND CURBS PART 1 - GENERAL A. Drawings and general provisions of Contract, including General and Supplementary
More informationC. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of:
02070 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.1 STIPULATIONS A. The specifications sections " General Conditions of the Construction Contract ", "Special Conditions", and "Division 1 - General Requirements"
More informationSECTION 39 - MANHOLES TABLE OF CONTENTS
Section SECTION 39 - MANHOLES TABLE OF CONTENTS Page 39-1 GENERAL... 39.1 39-2 CONCRETE MANHOLES... 39.1 39-2.01 NOT USED... 39.1 39-2.02 Concrete Storm Drain Manholes... 39.1 39-3 SADDLE SEWER MANHOLES...
More informationROOF BALLAST MATERIALS ARCHITECTURAL CONCRETE PAVING SLABS SRS LEVELING BLOCK SYSTEM INSTALLATION PART GENERAL 1.
07555 - ROOF BALLAST MATERIALS ARCHITECTURAL CONCRETE PAVING SLABS SRS LEVELING BLOCK SYSTEM INSTALLATION PART 1.00 - GENERAL 1.01 SUMMARY: A. The work of this section consists of furnishing and installing
More information1.02 STANDARD REFERENCES: The following standard specifications shall apply to the Work of this Section as indicated:
SECTION 04220 CONCRETE UNIT MASONRY PART 1 - GENERAL 1.01 SCOPE: A. The CONTRACTOR shall furnish all labor, materials and equipment necessary for the masonry construction as shown on the drawings or as
More informationUPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04
UPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04 1. Description This work shall consist of the design, manufacture and construction of a T-WALL structure
More informationITEM 432 RIPRAP. Dry Riprap is defined as Stone Riprap of the required type with voids filled only with spalls or small stones.
ITEM 432 RIPRAP 432.1. Description. This Item shall govern for the furnishing and placing of riprap of the type and details shown on the plans and in accordance with this Item. 432.2. General. Riprap furnished
More informationBID NO VOLUME II. Date Due: May 7, 2018 at 10:30am
BID NO. 1804 Hardscape Repair At Multiple Sites Summer 2018 VOLUME II Date Due: May 7, 2018 at 10:30am BID NO. 1804 Hardscape Repair At Multiple Sites Summer 2018 - Page 1 TABLE OF CONTENTS - VOL-2 VOLUME
More informationCONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING DISTRIBUTION EQUIPMENT
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DISTRIBUTION EQUIPMENT SPECIFICATION EO-1007 REVISION 13 DECEMBER 2013 EFFECTIVE DATE DECEMBER 16,
More informationA. Prepare formwork shop drawings using qualified professional engineer. Include detail of fabrication, assembly, and support of formwork.
DIVISION 03 CONCRETE 03 0100 MAINTENANCE OF CONCRETE 03 0505 UNDER SLAB VAPOR BARRIER A. Sheet vapor retarder shall be polyethylene sheet, ASTM D 4397, 10 mils thick minimum. Consult with Facilities Management
More informationSPECIAL SPECIFICATION 4897 Repair Structural Concrete
1993 Specifications CSJ 0331-04-045 SPECIAL SPECIFICATION 4897 Repair Structural Concrete 1. Description. This Item shall govern for the repair of delaminated, spalled and chipped areas of concrete foundations,
More informationSPECIAL SPECIFICATION 4491 Type CAC Concrete
2004 Specifications SPECIAL SPECIFICATION 4491 Type CAC Concrete 1. Description. Remove unsound concrete and replace with Type CAC, calcium aluminate concrete for ultra high early strength concrete repairs.
More informationCSI SECTION MAINTENANCE OF CONCRETE Repair & Resurfacing with Rapid Hardening, High Strength, Low-Shrink, Non-Metallic Cementitious Materials
CSI SECTION 03 01 00 MAINTENANCE OF CONCRETE Repair & Resurfacing with Rapid Hardening, High Strength, Low-Shrink, Non-Metallic Cementitious Materials EDITOR NOTE: The following guideline specification
More informationSECTION EPOXY TERRAZZO
SECTION 09402 PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to
More informationThin Architectural Splitface Block Veneer Specification Guide
Thin Architectural Splitface Veneer System with AccuTab Technology R Thin Architectural Splitface Block Veneer Specification Guide Section 04711: Manufactured Concrete Veneer Use this specification guide
More informationPASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017
SECTION 02770 - CONCRETE SIDEWALKS AND CURBS PART ONE-GENERAL 1.1 DESCRIPTION 1.1.1 General Concrete curb shall be constructed as part of the restoration work that may be necessary to replace existing
More information.1 Concrete mix shall be in accordance with the following:.1 The average of all tests shall exceed 25 MPa.
Page 1 1.0 CONCRETE 1.1 CONCRETE MIX.1 Concrete mix shall be in accordance with the following: Minimum 28 Day Strength 25 MPa* Designated Aggregate Size.maximum 25 mm (1 inch) Slump. 25-75 mm (1-3 inches)
More information1.01 GENERAL. l.02 PIPELINE TRENCH EXCAVATION PIPELINES AND STRUCTURES REVISION: SECTION 1 PAGE : 1-1
1.01 GENERAL A. The Contractor shall perform all excavation, backfilling, grubbing and grading required for construction and installation of pipelines, structures and appurtenances. Excavation shall include
More informationSECTION MINOR CONCRETE
SECTION 03300 - MINOR CONCRETE CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And Payment...
More informationSECTION THERMOPLASTIC POLYOLEFIN (TPO) ROOFING PART 1 - GENERAL 1.1 RELATED DOCUMENTS
SECTION 075423 - THERMOPLASTIC POLYOLEFIN (TPO) ROOFING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including Division 00 Bidding Requirements and other Division
More informationSECTION DETECTABLE GUIDE TACTILES
SECTION 09655 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for surface applied and recessed detectable guide or directional tactiles (tactiles) for use on the station platforms
More information1. Payment for concrete sidewalks is on square foot basis. a. Limits for measurement for trench excavation as follows:
Section 02775 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Reinforced concrete sidewalks. B. Wheelchair ramps. C. Reinforced slope paving. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices. 1. Payment for concrete
More informationEXECUTION REQUIREMENTS
PART 1 - GENERAL 1.1 SUMMARY A. Section includes: Execution requirements. B. Related Requirements: 1. Specification Sections 2 through 49. PART 2 - PRODUCTS (Not Used). PART 3 - EXECUTION 3.1 SAFETY 01
More informationRECOMMENDED DESIGN SPECIFICATION
RECOMMENDED DESIGN SPECIFICATION SILICONE COATED SPF ROOFING 1 General 1.1 Section Includes A. Silicone coated SPF roofing system, including substrate board, roof insulation boards, foam insulation materials,
More informationSPECIAL SPECIFICATION 5787 Manhole Rehabilitation
2004 Specifications CSJ 1062-04-047 SPECIAL SPECIFICATION 5787 Manhole Rehabilitation 1. Description. Repair, rehabilitate, or replace deteriorated, leaking, or structurally unsound existing sanitary sewer
More informationLITHOCRETE ARCHITECTURAL CONCRETE PAVING
LITHOCRETE ARCHITECTURAL CONCRETE PAVING PART 1 GENERAL 1.1 GENERAL CONDITIONS A. Requirements of "General Conditions of the Contract" and of Division 1, "General Requirements," apply to work in this Section
More informationSTATEMENT OF SPECIAL INSPECTION FORM
Project Title: Permit #: Project Address: STATEMENT OF SPECIAL INSPECTION FORM This Statement of Special Inspections is submitted in fulfillment of the requirements of CBC Sections 1704 and 1705. Special
More information2014 Capital Project Phase 3 Grand Island Central School District Cannon Design Project No SECTION PAVING PART 1 - GENERAL
SECTION 321200 - PAVING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. The Contractor for this work shall be held to have read all of the Bidding Requirements, the Proposal Forms, the General Conditions of
More informationPERM-FLEX ASSEMBLY DIRECT APPLICATION TO CEMENTITIOUS SUBSTRATES MANUFACTURERS SPECIFICATION / SECTION 09960
STUC-O-FLEX PERM-FLEX ASSEMBLY DIRECT APPLICATION TO CEMENTITIOUS SUBSTRATES MANUFACTURERS SPECIFICATION / SECTION 09960 PART 1 - GENERAL 1.01 DESCRIPTION Provide all labor, materials and equipment necessary
More informationStructural Tests and Special Inspections Form. Inspection of Fabricators (1704.2)
Inspection of Fabricators (1704.2) Furnish inspection reports (1704.2.1) - Fabricators that have not been approved Provide a Certificate of Compliance (1704.2.2) - Approved Fabricators Steel Construction
More informationThe work required for this project includes, but is not limited to, the following items, not listed in order of execution.
ESTIMATE OF QUANTITIES SPECIFICATIONS Construction Specifications: South Dakota Standard Specifications for Roads and Bridges, 2004 Edition and Required Provisions, Supplemental Specifications and/or Special
More informationUniversity of New Hampshire Scholars' Repository
University of New Hampshire University of New Hampshire Scholars' Repository Division 07 Thermal and Moisture Protection Chapter 5 Technical Construction and Renovation Standards 1-25-2013 075423 - TPO
More informationDivision 03 Concrete Section includes various guidelines for general concrete use, curing, forming, reinforcing, finishing and concrete accessories.
Section includes various guidelines for general concrete use, curing, forming, reinforcing, finishing and concrete accessories. This design guideline is written to the designer of record (DOR). This guideline
More informationSECTION PRECAST CONCRETE COVER SYSTEM
SECTION 13500 PRECAST CONCRETE COVER SYSTEM PART 1 GENERAL 1.1 SYSTEM DESCRIPTION A. Design Criteria: 1. Precast manufacturer shall be responsible for structural design of individual precast components,
More information1. Cast-in place structural concrete including footers, foundations, and other non-slab applications. 2. Formwork 3. Reinforcement
SECTION 03 31 00 - CAST-IN-PLACE STRUCTURAL CONCRETE PART 1 - GENERAL 1.1 SUMMARY A. Section includes: 1. Cast-in place structural concrete including footers, foundations, and other non-slab applications.
More informationConditions of the Contract and Division 1 General Requirements are a part of this section.
NOTES TO SPECIFIER General notes about the specifications and the reasons for them are listed here in general statements. Use this as a guide when choosing the correct selection of statements that apply
More informationSECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS
SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS Section Page 44-1 SHOTCRETE... 44.1 44-1.01 Description... 44.1 44-1.02 Materials... 44.1 44-1.03 Proportions...
More informationCONCRETE FORMWORK. .2 CSA , Supplement No.1 to CAN/CSA , Engineering Design in Wood. .4 CSA O151, Canadian Softwood Plywood.
CITY OF BRAMPTON LANDSCAPE SPECIFICATIONS SECTION 03100-1 PART 1 GENERAL 1.1 Related Work.1 All Division 1 Specification Sections.2 Section 02233 Granular Base.3 Section 02311 Site Grading.4 Section 03200
More informationSECTION MISCELLANEOUS CAST-IN-PLACE CONCRETE
SECTION 033053- MISCELLANEOUS CAST-IN-PLACE CONCRETE PART 1- GENERAL 1.1 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01
More informationCITY OF FARGO SPECIFICATIONS CONCRETE SIDEWALKS AND DRIVEWAYS
CONCRETE SIDEWALKS AND DRIVEWAYS PART 1 DESCRIPTION OF WORK The work to be done under this section of the Specifications and the accompanying plans consists of all labor, material, and equipment necessary
More informationRENOVATE BUILDING 18-C FTFA SECTION GYPSUM BOARD 05/11
SECTION 09 29 00 GYPSUM BOARD 05/11 PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text
More informationSECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS
SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS Section Page 44-1 SHOTCRETE 44-1 44-1.01 Description 44-1 44-1.02 Materials 44-1 44-1.03 Proportions 44-1 44-1.04
More informationSECTION STRUCTURAL PRECAST HOLLOW CORE SLABS
PART 1 GENERAL 1.01 SCOPE OF WORK A. The Contractor shall furnish all labor, materials, equipment and incidentals to provide a complete structural precast hollow core slab system as shown on the Contract
More informationSECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.
SECTION 311000 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting
More informationUnion County Vocational - Technical Schools Scotch Plains, New Jersey
SECTION 096623 - RESINOUS MATRIX TERRAZZO FLOORING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division
More informationGensler 2014/06/16 Hertz Global Headquarters ISSUE FOR BUILDING PERMIT Estero, Florida SECTION
SECTION 072700 VAPOR PERMEABLE AIR BARRIER LIQUID MEMBRANE PART 1 GENERAL 1.1 GENERAL REQUIREMENTS A. The Work of this Section, as shown or specified, shall be in accordance with the requirements of the
More information***************************************************************************************************************
03100 CONCRETE FORMWORK *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 03 11 00 ***************************************************************************************************************
More informationSECTION INSTALLATION AND/OR REPLACEMENT OF MASONRY UNITS AND REPOINTING
SECTION 04210 INSTALLATION AND/OR REPLACEMENT OF MASONRY UNITS AND REPOINTING PART I GENERAL 1.1 SUMMARY A. Provide installation of new or replacement of masonry units and/or repointing of masonry units
More informationDIVISION 04 MASONRY. Section Title Number MASONRY Maintenance of Masonry Masonry Mortaring Masonry Accessories
04 00 00 MASONRY 04 01 00 Maintenance of Masonry 04 01 20 Maintenance of Masonry 04 05 13 Masonry Mortaring 04 05 23 Masonry Accessories 04 20 00 UNIT MASONRY 04 21 00 Clay Unit and Brick Veneer 04 22
More informationSECTION Vitrified Clay Wall Coping 2014
SECTION 04220 2014 PART 1 GENERAL 1.1 DESCRIPTION A. SCOPE OF WORK 1. Provide new coping as indicated on Drawings. B. RELATED SECTIONS 1. Section 02050: Selective Demolition. 2. Section 07650: Metal Flashing.
More informationKANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION OF 1990
KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION OF 1990 90P-270 Sheet 1 of 5 SECTION PAVEMENT PATCHING Page 591, Section. Delete the Section and replace with
More informationSECTION Fiber Reinforced Stucco 1
CSI SECTION 09200 FIBER REINFORCED STUCCO PART 1 GENERAL 1.01 SUMMARY A. Section Description: Provided lath and plaster where shown on the Drawings, as specified herein, and as needed for complete and
More informationA. Submittal Procedures: See Article 13 of the General Conditions.
SECTION 321313 - CONCRETE PAVING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Driveways. 2. Roadways. 3. Parking lots. 4. Curbs and gutters. 5. Walks. B. Proposed Substitutions: See Article 2,
More informationSECTION ARCHITECTURAL PRECAST CONCRETE. C. Section Joint Sealers: Perimeter joints with sealant and backing.
SECTION 03451 ARCHITECTURAL PRECAST CONCRETE PART 1 GENERAL 1.01 SECTION INCLUDES A. Architectural precast concrete wall panels; with integral insulation. B. Supports, anchors, and attachments. C. Intermediate
More informationThe following specification refers to the Stepstone, Inc. product known as: Steptreads
The following specification refers to the Stepstone, Inc. product known as: Steptreads If you need any additional information please call Stepstone, Inc. at 800-572-9029 or visit our website www.stepstoneinc.com
More information