RIICCM209D Carry Out Concrete Work Assessment Plan

Size: px
Start display at page:

Download "RIICCM209D Carry Out Concrete Work Assessment Plan"

Transcription

1 RIICCM209D Carry Out Concrete Work Assessment Plan

2 Assessment Plan This document contains all details of how the assessment will be conducted and the resources required to complete the assessment. The task details, specific instructions to assessors and task checklists are available in the Final Practical Test Assessor Only document. Make sure all resources outlined within this plan are available before starting the final assessment. Assessment 1 Confirm Details of Concreting Work The learner is required to read all relevant documentation for planning out the task and making sure work activity meets requirements for safety and quality. The assessor will need to make sure all resources, information and documents are available for the purposes of the assessment and determine that the learner knows where to look for them on the work site. The assessor needs to ensure that any health and safety guidelines used during the assessment are relevant to the civil construction industry and make a note of the health and safety guidelines used. 1 set of task instructions, plans or specifications for a civil construction concreting task. 1 project document that identifies quality requirements (may be included with the work instructions or in a civil construction plan). 1 copy of a policy or procedure relevant to civil construction, concreting or site operations. 1 copy of emergency response instructions relevant to the work site. Civil force Training Assessment Plan Page 2

3 Assessment 2 Inspect and Prepare the Work Area The learner is required to identify, report and manage hazards in the work area at a basic level, using predetermined control methods and techniques outlined in task instructions or safety documentation. At a minimum hazards that should be identified and managed during this assessment should include: Selection of PPE. Traffic control and site isolation. Space or Location Requirements: There should be enough space to allow a learner to walk around the work area to carry out the task of hazard identification. Any environmental hazards or issues identified need to be managed as appropriate. All details of environmental protection measures implemented during the assessment need to be documented. Reporting of hazards needs to be demonstrated. This may be achieved through the use of a form (such as a Take-5 or equivalent) or verbally. Details of verbal reporting need to be documented by the assessor. Work instructions outlining control measures for common hazards related to the task. Personnel protective equipment relevant to the task including a minimum of: Hi-vis clothing. Safety helmet. Safety boots. Barricades and signage for traffic control and site isolation. Civil force Training Assessment Plan Page 3

4 Assessment 3 and 4 Carry Out Concrete Work For each assessment the learner is required to carry out a concreting task as part of a civil construction project. This includes: Confirming the details of the task and choosing appropriate materials and equipment. Setting out the concrete work in accordance with the plan. Constructing and placing reinforcements for the concrete. Erecting formwork. Placing, compacting and finishing concrete to achieve the required finish. Covering and protecting concrete after the work is complete. Space or Location Requirements: The work area should be adequately isolated from any other operations for the duration of the assessment. The location needs to be large enough, and made up of materials that can be levelled using basic techniques and equipment. Care must be taken at all times to prevent any harm to the environment through the spilling of chemicals or materials that may be harmful. The task needs to reflect realistic work requirements. The dimensions, type and complexity of tasks needs to be consistent with common civil construction project concreting activities. 1 set of task instructions, plans or specifications for a civil construction concreting task. Concrete (materials). Formwork components and materials. Reinforcement components and materials. Cutting tools and equipment. Tape measure. String line and pegs. Concreting tools and equipment (select from the list): Floats. Curing agent applicators. Short handle shovels. Hoses. Tremmies. Steam generators. Trowels. Nips. Rods. Buckets. Chutes. Shutters. Edging tools. Bolt cutters. Hammers. Edging tools. Vibrators. Brushes. Screeds. Reinforcement benders. Pre-mix trucks. Tarpaulins. Rakes. Cranes. Wheelbarrows. Mesh guillotines. Kibbles. Civil force Training Assessment Plan Page 4

5 Assessment 5 Strip Formwork and Conduct Housekeeping Activities The learner is required to strip the formwork from the area and tidy up. This includes: Removing all components in the right order. Cleaning all parts. Disposing damaged equipment. Storing components. Clearing the work area. Cleaning and maintaining all tools and equipment. Processing written records. Cleaning needs to be done in a designated area that does not have a negative impact on the environment through the use and disposal of cleaning agents. Completion of a fault report. Completion of isolation of defective equipment in line with site or common civil construction safety requirements. Note: If no fault is identified the assessor needs to give the learner a scenario where defective, damaged or faulty equipment has been identified and ensure that they complete a fault report to reflect the details provided in the scenario. Tools and equipment used during concreting activities. Cleaning equipment and product. Fault report. Relevant housekeeping records (Assessor must identify the type and purpose of any written records that need to be processed). Civil force Training Assessment Plan Page 5

RIICCM211D Erect and Dismantle Temporary Fencing and Gates Assessment Plan

RIICCM211D Erect and Dismantle Temporary Fencing and Gates Assessment Plan RIICCM211D Erect and Dismantle Temporary Fencing and Gates Assessment Plan Assessment Plan This document contains all details of how the assessment will be conducted and the resources required to complete

More information

RIIMPO318E Conduct Civil Construction Skid Steer Loader Operations Assessment Plan

RIIMPO318E Conduct Civil Construction Skid Steer Loader Operations Assessment Plan RIIMPO318E Conduct Civil Construction Skid Steer Loader Operations Assessment Plan RIIMPO318E Conduct Civil Construction Skid Steer Loader Operations Assessment Plan This document contains all details

More information

RIIMPO320E Conduct Civil Construction Excavator Operations Assessment Plan

RIIMPO320E Conduct Civil Construction Excavator Operations Assessment Plan RIIMPO320E Conduct Civil Construction Excavator Operations Assessment Plan RIIMPO320E Conduct Civil Construction Excavator Operations Assessment Plan This document contains all details of how the assessment

More information

RIIMPO334D Conduct Skid Steer Loader Operations Using Attachments Assessment Plan

RIIMPO334D Conduct Skid Steer Loader Operations Using Attachments Assessment Plan RIIMPO334D Conduct Skid Steer Loader Operations Using Attachments Assessment Plan RIIMPO334D Conduct Skid Steer Loader Operations Using Attachments Assessment Plan This document contains all details of

More information

Contents. Before you begin. Introduction: Carrying out concreting to simple forms 1. Element 1: Planning and preparing 3

Contents. Before you begin. Introduction: Carrying out concreting to simple forms 1. Element 1: Planning and preparing 3 Contents Contents Before you begin v Introduction: Carrying out concreting to simple forms 1 Element 1: Planning and preparing 3 Section 1.1: Obtaining, confirming and applying work instructions and 4

More information

Carry out concrete work

Carry out concrete work Training Package Title Unit code BCGCO2004B General Construction (BCG03) Carry out concrete work Unit Descriptor This unit specifies the competency required to carry out concreting work on general construction

More information

Working with Concrete

Working with Concrete Working with Concrete Call: 1300 094 979 Measure & Order Work out how much Concrete is required? Concrete is measured and purchased in cubic metres. Follow these easy steps to work out the volume of concrete

More information

Entry 3 Skills for Working Life ( )

Entry 3 Skills for Working Life ( ) Entry 3 Skills for Working Life (4807-03) August 2014 Version 1.0 www.cityandguilds.com August 2014 Version 1.0 Unit recording documents for Construction (Units 380-385) City & Guilds Believe you can www.cityandguilds.com

More information

Use concreting tools and equipment

Use concreting tools and equipment Training Package Title Unit code BCGCO2002B General Construction (BCG03) Use concreting tools and equipment Unit Descriptor This unit specifies the competency required to safely select and use concreting

More information

Pembroke Hopkins Park Construction Outreach Program E S. Rd., Pembroke Township, IL Tel: (815) Fax: (815)

Pembroke Hopkins Park Construction Outreach Program E S. Rd., Pembroke Township, IL Tel: (815) Fax: (815) Pembroke Hopkins Park Construction Outreach Program 13355 E. 3000 S. Rd., Pembroke Township, IL 60958 Tel: (815) 944-8897 Fax: (815) 944-5675 Cement Materials and Equipment Level One MODULE 23101 INTRODUCTION

More information

Mix and lay concrete tutor notes

Mix and lay concrete tutor notes Mix & lay concrete Tutor Tutor Mix and lay concrete tutor notes What students will learn When they have fi nished this module, students should be able to: Prepare the ground for a concrete slab Build formwork

More information

PPC Cement TUTORIAL. how to screed a floor

PPC Cement TUTORIAL. how to screed a floor PPC Cement TUTORIAL how to screed a floor Pre-build: TOOLs & Materials ITEM Quantity Check. Builders bucket. Wheelbarrow 3. Shovel 4. Builder s line 5. 50mm steel pegs 6. Rigid timber forms 7. Flexible

More information

Release 1. CPCCCO3044A Carry out decorative finishes to concrete

Release 1. CPCCCO3044A Carry out decorative finishes to concrete Release 1 CPCCCO3044A Carry out decorative finishes to concrete CPCCCO3044A Carry out decorative finishes to concrete Modification History This version first released with CPC08 Construction, Plumbing

More information

Unit 9 Reinstatement of modular surfaces and concrete footways

Unit 9 Reinstatement of modular surfaces and concrete footways This unit covers the requirements that you must meet when reinstating modular surfaces and concrete. You must ensure that you act in accordance with all current specifications and procedures and that you

More information

CPCCLSF3001A Licence to erect, alter and dismantle scaffolding intermediate level

CPCCLSF3001A Licence to erect, alter and dismantle scaffolding intermediate level CPCCLSF3001A Licence to erect, alter and dismantle scaffolding intermediate level Release: 1 CPCCLSF3001A Licence to erect, alter and dismantle scaffolding intermediate level Modification History Not Applicable

More information

LANH42 SQA Unit Code H52X 04 Install flexible flag surfaces

LANH42 SQA Unit Code H52X 04 Install flexible flag surfaces Overview This standard is one of six which covers installation of the various forms of hardstanding surfaces that are used within the landscaping industries. This standard is targeted at operatives working

More information

Apprenticeship Curriculum Standard. Cement (Concrete) Finisher. Levels 1 & 2. Trade Code: 244G

Apprenticeship Curriculum Standard. Cement (Concrete) Finisher. Levels 1 & 2. Trade Code: 244G Apprenticeship Curriculum Standard Cement (Concrete) Finisher Levels 1 & 2 Trade Code: 244G 2004 Hours Disclaimer: It is agreed that Training Delivery Agents (TDAs) may need to make slight adjustments

More information

About this guide 1. Section 1: Unit of competency 3

About this guide 1. Section 1: Unit of competency 3 Contents About this guide 1 Section 1: Unit of competency 3 1.1 Elements of competency and performance criteria 4 1.2 Range statement 6 1.3 Required skills and knowledge 11 1.4 Evidence guide 13 1.5 Employability

More information

Laborers Cement Mason Concrete Placement and Finishing Tech 2 Syllabus

Laborers Cement Mason Concrete Placement and Finishing Tech 2 Syllabus Concrete Placement and Finishing Tech 2 Time: 40 hours Maximum Class Size: 12 Prerequisites: LCM Construction Math, LCM Concrete Placement and Finishing Tech 2 Course Description: This course is designed

More information

Gas Network Team Leader

Gas Network Team Leader Gas Network Team Leader Unit SMLMAO12 Reinstatement of Modular Surfaces and Concrete Footways This unit is designed to allow the candidate to demonstrate the skills and knowledge required to carry out

More information

Laborers Cement Mason Concrete Placement and Finishing Tech 1 Syllabus

Laborers Cement Mason Concrete Placement and Finishing Tech 1 Syllabus Concrete Placement and Finishing Tech 1 Time: 40 hours Maximum Class Size: 12 Prerequisites: LCM Construction Math Course Description: This course is designed to introduce the participant to the basic

More information

Erect and dismantle cantilever scaffolds

Erect and dismantle cantilever scaffolds Reference : K/506/5119 Level : Level 2 Credit Value : 18 Guided Learning Hours : 144 Grading Type : Graded Erect and dismantle cantilever scaffolds Aim : The aim of this unit is to provide the learner

More information

SAFETY METHOD STATEMENT

SAFETY METHOD STATEMENT SAFETY METHOD STATEMENT OUR POLICY The safety of our employees and those of our clients is our main priority when carrying out any work on site. This method statement is designed to let you, the client

More information

PRACTICAL TASK MANUAL

PRACTICAL TASK MANUAL 6709-22 Level 2 Certificate in Construction Operations - General Construction PRACTICAL TASK MANUAL July 2013 Version 1.0 Contents Candidate details 1 Unit assessment overview 2 Practical task completion

More information

Apprenticeship Training Standard. Cement (Concrete) Finisher. Trade Code: 244G. Development Date: August 2009

Apprenticeship Training Standard. Cement (Concrete) Finisher. Trade Code: 244G. Development Date: August 2009 Apprenticeship Training Standard Cement (Concrete) Finisher Trade Code: 244G Development Date: August 2009 This document is the property of the apprentice named inside and represents the official record

More information

ERMCO EUROPEAN READY MIXED CONCRETE ORGANIZATION ASSOCIATION EUROPEENNE DU BETON PRET A L EMPLOI EUROPÄISCHER TRANSPORTBETONVERBAND

ERMCO EUROPEAN READY MIXED CONCRETE ORGANIZATION ASSOCIATION EUROPEENNE DU BETON PRET A L EMPLOI EUROPÄISCHER TRANSPORTBETONVERBAND Preparation for pour Planning the pour Apply mould oil thinly and evenly. Clean out the forms with a magnet and water. Planning the pour Remove any litter from the formwork. Stick to the plan. Take care

More information

TrowelPave Concrete - Regular Set (20lb 40lb Bucket Kit)

TrowelPave Concrete - Regular Set (20lb 40lb Bucket Kit) For more information, visit FEATURES & BENEFITS: TrowelPave Concrete - Regular Set is a cold mix, cold applied concrete patching repair product. The patented technology is commonly used for both aged and

More information

PRACTICAL TASK MANUAL

PRACTICAL TASK MANUAL 6710-13 Level 1 Diploma in Wall and Floor Tiling July 2013 Version 1.0 PRACTICAL TASK MANUAL Contents Candidate details 1 Unit assessment overview 2 Practical task completion record 2 Instructions to candidates

More information

HEALTH AND SAFETY MANUAL

HEALTH AND SAFETY MANUAL HEALTH AND SAFETY MANUAL Title: Concrete and Masonry Construction Approved by: Greg Savoy Rev. 1/1/08 1 Purpose/Scope: This program sets forth safety requirements and hazard controls for concrete or grout

More information

Health & Safety Policy and Procedures Manual SECTION 23 MASONRY CONSTRUCTION

Health & Safety Policy and Procedures Manual SECTION 23 MASONRY CONSTRUCTION SECTION 23 MASONRY CONSTRUCTION 1. Masonry Construction: A. Whenever a masonry wall is being constructed, a limited access zone will be established prior to construction meeting the following requirements.

More information

International Journal of Scientific & Engineering Research Volume 8, Issue 10, October-2017 ISSN

International Journal of Scientific & Engineering Research Volume 8, Issue 10, October-2017 ISSN 506 To study of Compression strength of cement concrete Sumit bijlwan 1, Dr.Sanjeev Gill 2 Assit Prof. Department of Civil Engineering, JBIT, Dehradun(U.K) HOD Civil Engineering Department,JBIT,Dehradun

More information

COSVR773 SQA Unit Code HM69 04 Operate and control operations of road plant, machinery or equipment for laying rigid paving

COSVR773 SQA Unit Code HM69 04 Operate and control operations of road plant, machinery or equipment for laying rigid paving Overview This standard is about interpreting information, adopting safe, healthy and environmentally responsible work practices, selecting and using materials, components and tools to prepare, set up,

More information

WORLDSKILLS STANDARD SPECIFICATION

WORLDSKILLS STANDARD SPECIFICATION WORLDSKILLS STANDARD SPECIFICATION Skill 46 Concrete Construction Work WSC2017_WSSS46 THE WORLDSKILLS STANDARDS SPECIFICATION (WSSS) GENERAL NOTES ON THE WSSS The WSSS specifies the knowledge, understanding

More information

Overview COSVR773. Operate and control operations of road plant, machinery or equipment for laying rigid paving

Overview COSVR773. Operate and control operations of road plant, machinery or equipment for laying rigid paving Overview This standard is about interpreting information, adopting safe, healthy and environmentally responsible work practices, selecting and using materials, components and tools to prepare, set up,

More information

Release: 1. CPCCBC4002A Manage occupational health and safety in the building and construction workplace

Release: 1. CPCCBC4002A Manage occupational health and safety in the building and construction workplace Release: 1 CPCCBC4002A Manage occupational health and safety in the building and construction workplace CPCCBC4002A Manage occupational health and safety in the building and construction workplace Modification

More information

Iron Ore Company of Canada Health, Safety & Environment

Iron Ore Company of Canada Health, Safety & Environment Barricading 1 PURPOSE To protect personnel by preventing or controlling access to hazards in work areas by the installation and maintenance of barricades, demarcation and restricting access. This work

More information

RIIMPO318A Conduct skid steer loader operations Unit descriptor. Employability skills Application of the unit. Competency field

RIIMPO318A Conduct skid steer loader operations Unit descriptor. Employability skills Application of the unit. Competency field RIIMPO318A Unit descriptor Employability skills Application of the unit Competency field Conduct skid steer loader operations This unit covers conducting skid steer loader operations in resources and infrastructure

More information

Contents. Before you begin. Introduction: Installing trench support 1. Element 1: Planning and preparing 3

Contents. Before you begin. Introduction: Installing trench support 1. Element 1: Planning and preparing 3 Contents Contents Before you begin v Introduction: Installing trench support 1 Element 1: Planning and preparing 3 Section 1.1 Accessing, interpreting and applying compliance documentation 4 to the work

More information

Below-grade pours (such as foundations) can be done out of the chute of the concrete truck or conveyer, however using a pump is best.

Below-grade pours (such as foundations) can be done out of the chute of the concrete truck or conveyer, however using a pump is best. Concrete Placement Below-grade pours (such as foundations) can be done out of the chute of the concrete truck or conveyer, however using a pump is best. Above-grade pours require lifting equipment. Most

More information

Interiors Sources Decor LLC. Method Statement BLOCK WORK. Civil Works 6/26/2016

Interiors Sources Decor LLC. Method Statement BLOCK WORK. Civil Works 6/26/2016 Method Statement BLOCK WORK Civil Works 6/26/2016 The purpose of this Work Method Statement for Block Works (Concrete Masonry Units) is to outline and describe in detail the procedure such as setting and

More information

Pre-build: TOOLs & Materials

Pre-build: TOOLs & Materials Pre-build: TOOLs & Materials ITEM a. Builder s square b. Brick bolster c. Bricks d. Builder s bucket e. Mortar trowel f. Mason's string g. Square-nosed spade h. Spirit level i. Tape measure j. kg hammer

More information

Unit 32: Plastering and Rendering Surfaces

Unit 32: Plastering and Rendering Surfaces Unit 32: Unit code: QCF Level: 2 Credit value: 10 Guided learning hours: 100 Unit aim and purpose Plastering and Rendering Surfaces J/503/4945 This unit should enable learners to gain the knowledge needed

More information

CONCRETE WALKS AND CURBS SECTION CONCRETE WALKS AND CURBS PART 1 - GENERAL

CONCRETE WALKS AND CURBS SECTION CONCRETE WALKS AND CURBS PART 1 - GENERAL 13686.00 CONCRETE WALKS AND CURBS 033015-1 1.1 RELATED DOCUMENTS: SECTION 033015 CONCRETE WALKS AND CURBS PART 1 - GENERAL A. Drawings and general provisions of Contract, including General and Supplementary

More information

CPCCPD3023A Matrix Map

CPCCPD3023A Matrix Map CPCCPD3023A Matrix Map (Generated Saturday, 14 Apr 2018, 02:34pm) ELEMENTS AND PERFORMANCE CRITERIA Element Peformance Criteria Task / Question Map 1. Plan and prepare. 1.1. Work instructions and operational

More information

Name Phone Logo

Name  Phone Logo Curriculum Document Curriculum Code Curriculum Title 641403003 Civil Road Construction Constructor Name Email Phone Logo Development Quality Partner Construction Seta madibengt@ceta.co.za 011 265 5900

More information

Laborers Cement Mason Machine Operations & Concrete Sawing Syllabus

Laborers Cement Mason Machine Operations & Concrete Sawing Syllabus Machine Operations & Concrete Sawing Time: 40 hours Maximum Class Size: 12 Prerequisites: LCM Concrete and Finishing Tech 1 Course Description: This course is designed to introduce the participant to the

More information

UNIT TITLE: CLEAN AND MAINTAIN INDUSTRIAL WORK AREA AND EQUIPMENT

UNIT TITLE: CLEAN AND MAINTAIN INDUSTRIAL WORK AREA AND EQUIPMENT UNIT TITLE: CLEAN AND MAINTAIN INDUSTRIAL WORK AREA AND EQUIPMENT NOMINAL HOURS: UNIT NUMBER: UNIT DESCRIPTOR: This unit deals with skills and knowledge required to clean and maintain industrial work areas

More information

U16902 Install and maintain drainage systems

U16902 Install and maintain drainage systems U16902 Unit Descriptor: Install and maintain drainage systems This unit is about installing and maintaining drainage systems. It is for members of staff who can carry out work described under limited supervision

More information

CONCRETE FORMWORK CHECKLIST AT SITE

CONCRETE FORMWORK CHECKLIST AT SITE CONCRETE FORMWORK CHECKLIST AT SITE Concrete formwork is a temporary supporting structure for concrete when it is placed at the construction site to keep the concrete in position and shape till it gets

More information

State of Nevada Department of Transportation Materials Division

State of Nevada Department of Transportation Materials Division State of Nevada Department of Transportation Materials Division METHOD OF TEST FOR UNOBSTRUCTED SLUMP FLOW AND STABILITY OF HYDRAULIC-CEMENT SELF-CONSOLIDATING CONCRETE SCOPE This test method covers the

More information

5-Year Pothole Patch: Highway Grade Concrete (25lb 45lb Bucket Kit)

5-Year Pothole Patch: Highway Grade Concrete (25lb 45lb Bucket Kit) FEATURES & BENEFITS: 5-Year Pothole Patch: Highway Grade Concrete is the strongest pothole patch in the world! The fast setting plasticomposite patching material meets the most stringent demands for repairing

More information

Concrete Framing Systems - Walls and Columns

Concrete Framing Systems - Walls and Columns Concrete Framing Systems - Walls and Columns Casting a Concrete Wall Wall Footing Reinforcing Wall Forms Pouring Concrete Finishing the Concrete Controlling Cracking Insulating Concrete Forms (ICF) Tilt-Up

More information

Monitoring Reinstatement in Bituminous Materials

Monitoring Reinstatement in Bituminous Materials National Unit specification: general information Unit title: Monitoring Reinstatement in Bituminous Materials Unit code: F93E 04 Superclass: TK Publication date: October 2014 Source: Version: Scottish

More information

Level 3 Advanced Technical Diploma in Bricklaying (450) ( )

Level 3 Advanced Technical Diploma in Bricklaying (450) ( ) Level 3 Advanced Technical Diploma in Bricklaying (450) (7905-30) Version 1.1 Practice Tasks Level 3 Advanced Technical Diploma in Bricklaying [7905-30] Introduction General information about structure

More information

Model Curriculum. Cutter (Footwear) SECTOR: SUB-SECTOR: OCCUPATION: REF ID: NSQF LEVEL: LEATHER FOOTWEAR CUTTING LSS/Q2301, V1.0 4

Model Curriculum. Cutter (Footwear) SECTOR: SUB-SECTOR: OCCUPATION: REF ID: NSQF LEVEL: LEATHER FOOTWEAR CUTTING LSS/Q2301, V1.0 4 Model Curriculum SECTOR: SUB-SECTOR: OCCUPATION: REF ID: NSQF LEVEL: Cutter (Footwear) LEATHER FOOTWEAR CUTTING LSS/Q2301, V1.0 4 TABLE OF CONTENTS 1. Curriculum 01 2. Trainer Prerequisites 05 3. Annexure:

More information

DRAINAGE SOLUTIONS SINCE 1908 SURFACE DRAINAGE. Installation Guide ARMTEC.COM

DRAINAGE SOLUTIONS SINCE 1908 SURFACE DRAINAGE. Installation Guide ARMTEC.COM DRAINAGE SOLUTIONS SINCE 1908 SURFACE DRAINAGE Installation Guide ARMTEC.COM RECYFIX PRODUCTS RECYFIX trench drain systems are available in a wide range of load class ratings and grate options. They are

More information

ATTACHMENT 1. To be used by candidates where recognition is being sought (RPL- Recognition of Prior Learning) CANDIDATE S NAME: DATE:

ATTACHMENT 1. To be used by candidates where recognition is being sought (RPL- Recognition of Prior Learning) CANDIDATE S NAME: DATE: ATTACHMENT 1 To be used by candidates where recognition is being sought (RPL- Recognition of Prior Learning) SELF-ASSESSMENT CHECKLIST Qualification title: Certificate I in General Construction CANDIDATE

More information

SAFE WORK PROCEDURE 041 CONCRETE WORKS SEPTEMBER 2014 DOC. NO. D14/265945

SAFE WORK PROCEDURE 041 CONCRETE WORKS SEPTEMBER 2014 DOC. NO. D14/265945 MORELAND CITY COUNCIL Operations Centre 7-9 Walter Street Hadfield Vic 3046 Tel: 8311 4300 Approved by the Walter Street OHS committee Date: September 2014 Operation Brief Description of Activity Construction

More information

RIIHAN204A Load and unload cargo/goods Unit descriptor. Employability skills Application of the unit. Competency field

RIIHAN204A Load and unload cargo/goods Unit descriptor. Employability skills Application of the unit. Competency field RIIHAN204A Unit descriptor Employability skills Application of the unit Competency field Load and unload cargo/goods This unit covers the loading and unloading of cargo/goods in the resources and infrastructure

More information

FIELD EXAMPLES. 1 Implementation. 1.1 Quantity estimates

FIELD EXAMPLES. 1 Implementation. 1.1 Quantity estimates B FIELD EXAMPLES 1 Implementation 259 1.1 Quantity estimates 259 1.2 Time necessary for the construction of a well 260 1.3 Planning the construction of ten wells 261 2 Resources required 262 2.1 Human

More information

Handle and prepare bricklaying and blocklaying materials

Handle and prepare bricklaying and blocklaying materials Training Package Title Unit code BCGBL2001B General Construction (BCG03) Handle and prepare bricklaying and blocklaying materials Unit Descriptor This unit specifies the competency required to safely handle

More information

Level 2 Diploma in Construction Operations (Construction)

Level 2 Diploma in Construction Operations (Construction) (Construction) Qualification Specification ProQual 2015 Contents Page Introduction 3 The Qualifications and Credit Framework (QCF) 3 Qualification profile 4 Rules of combination 5 Centre requirements 6

More information

Contents. Before you begin. Introduction: Preparing for construction waterproofing process 1. Element 1: Planning and preparing 3

Contents. Before you begin. Introduction: Preparing for construction waterproofing process 1. Element 1: Planning and preparing 3 Contents Contents Before you begin v Introduction: Preparing for construction waterproofing process 1 Element 1: Planning and preparing 3 Section 1.1: Obtaining, confirming and applying work instructions

More information

2009 HSC Construction Sample Answers

2009 HSC Construction Sample Answers 2009 HSC Construction Sample Answers This document contains sample answers, or, in the case of some questions, answer may include. These are developed by the examination committee for two purposes. The

More information

2.15 CONCRETE PLACEMENT

2.15 CONCRETE PLACEMENT 2.15 CONCRETE PLACEMENT PRE-PLACEMENT CHECKLIST DATE: FOREMAN: JOB: Prior to placing concrete in Logix insulated concrete forms, be certain to mark off each item on the checklist provided in this section.

More information

SECTION CONCRETE PAVING

SECTION CONCRETE PAVING SECTION 32 13 13 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for providing portland cement concrete work and all other incidental concrete improvements for the project

More information

Concrete to Simple Forms

Concrete to Simple Forms LEARNING GUI D E Concrete to Simple Forms CPCPCO2013A Concrete to Simple Forms CPCPCO2013A Contents 1. Work Procedures 1 Observe Safety Signs 1 Concrete Strength 2 Water-Cement Ratio 3 Compaction 3 Curing

More information

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS. A. Formwork complete with shoring, bracing and anchorage.

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS. A. Formwork complete with shoring, bracing and anchorage. SECTION 02528 CONCRETE CURBS, GUTTERS AND SIDEWALKS PART 1 GENERAL 1.01 WORK INCLUDED A. Formwork complete with shoring, bracing and anchorage. B. Concrete reinforcement complete with required supports,

More information

MVDC F041 Safety Inspection Checklist

MVDC F041 Safety Inspection Checklist MVDC F041 Safety Inspection Checklist JOB TITLE: DEPARTMENT: JOB NO.: DATE: LEGEND 1 Satisfactory 2 Requires Improvement 3 Non Existent 4 Not Applicable EMERGENCY PREPAREDNESS Emergency procedure is posted

More information

2.1.1 Concrete shall conform to Section Granular Material shall conform to: SIEVE DESIGNATION. Plasticity Index 0-6

2.1.1 Concrete shall conform to Section Granular Material shall conform to: SIEVE DESIGNATION. Plasticity Index 0-6 1.0 GENERAL 1.1 Scope 2.0 PRODUCTS 1.1.1 Concrete sidewalk, sidewalk crossing, curb and gutter, rolled curb and gutter, monolithic walk, curb and gutter, concrete apron and structural sidewalk shall be

More information

TECHNICAL INFORMATION

TECHNICAL INFORMATION PAGE 1 of 8 TECHNICAL INFORMATION TOPFLOW HORIZONTAL TOPFLOW Horizontal s finishing characteristics and high quality surface finish can eliminate the need to power float concrete on site dependant on project

More information

Model Curriculum. Buffing Operator (Finished Leather) SECTOR: SUB-SECTOR: OCCUPATION: REF ID: NSQF LEVEL:

Model Curriculum. Buffing Operator (Finished Leather) SECTOR: SUB-SECTOR: OCCUPATION: REF ID: NSQF LEVEL: Model Curriculum Buffing Operator (Finished Leather) SECTOR: SUB-SECTOR: OCCUPATION: REF ID: NSQF LEVEL: LEATHER FINISHED LEATHER BUFFING LSS/Q0801, V1.0 4 TABLE OF CONTENTS 1. Curriculum 01 2. Trainer

More information

Model # 95-S8. Page 1 of 8

Model # 95-S8. Page 1 of 8 Model # 95-S8 Page 1 of 8 Page 2 of 8 WARRANTY & TERMS WARRANTY: 5 Year Limited Warranty on Thermoplastic coated elements. Ultra Play guarantees all items for one full year to be free of defects in workmanship

More information

Asset Protection Bond Information Sheet

Asset Protection Bond Information Sheet Asset Protection Bond Information Sheet What Is A Asset Protection Bond? An Asset Protection Bond is a surety relating to: a) Potential damage to Council assets such as: underground pipework. footpaths.

More information

Helper Carpenter Shuttering and Scaffolding CURRICULUM/SYLLABUS

Helper Carpenter Shuttering and Scaffolding CURRICULUM/SYLLABUS Ref:NSDC/QA&Std/1.0/ CON/ Q 0301 Helper Carpenter Shuttering and Scaffolding CURRICULUM/SYLLABUS This program is aimed at training candidates for the job of a Helper Carpenter Shuttering and scaffolding,

More information

SECTION STAY-IN-PLACE INSULATED CONCRETE FORMING SYSTEM

SECTION STAY-IN-PLACE INSULATED CONCRETE FORMING SYSTEM ARCHITECTURAL SPECIFICATIONS MANUFACTURER: InterBlock LLC PO Box 1123, Sheboygan, WI 53082 Phone Number 920-207-7234 SECTION 03100 STAY-IN-PLACE INSULATED CONCRETE FORMING SYSTEM PART 1 GENERAL 1.01 Summary

More information

Important: Before You Start

Important: Before You Start Advantage ICF System Advantage ICF System TM Field Guide Important: Before You Start Does Your Building Inspector Know You Are Building with the Advantage ICF System? You are required to check with your

More information

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS 6.1 DESCRIPTION This work shall consist of constructing curbs, gutters, sidewalks, ramps, local depressions and driveways of the form and dimensions shown

More information

MATERIAL HANDLING, STORAGE, AND DISPOSAL

MATERIAL HANDLING, STORAGE, AND DISPOSAL SECTION 14 MATERIAL HANDLING, STORAGE, AND DISPOSAL 14.A MATERIAL HANDLING 14.A.01 Employees shall be trained in and shall use safe lifting techniques. 14.A.02 Requirements for PPE are covered in Section

More information

stone oasis collection oasis circle patio (diameter ) instruction guide

stone oasis collection oasis circle patio (diameter ) instruction guide stone oasis collection oasis circle patio (diameter - 147 ) instruction guide This manual is updated on September 2017. Please check www.barkmanconcrete.com/resources for any manual updates. Materials

More information

Plant, Construction & Business NVQs

Plant, Construction & Business NVQs Plant, Construction & Business NVQs We offer a wide range of National Vocational Qualifications (NVQs). NVQs are qualifications that allow you to prove your competence in the workplace. You will have the

More information

A GUIDE TO LAYING ARTIFICIAL GRASS BEFORE 0 %INTEREST* MINIMUM SPEND $499 AFTER

A GUIDE TO LAYING ARTIFICIAL GRASS BEFORE 0 %INTEREST* MINIMUM SPEND $499 AFTER A GUIDE TO LAYING ARTIFICIAL GRASS BEFORE AFTER 0 %INTEREST* MINIMUM SPEND $499 Step 1: Preparation Mark Out Area: Before starting, please note that in order to avoid water pooling on your grass, you will

More information

CHAPTER 13 - MECHANICALLY STABILIZED EARTH WALLS AND PATENTED EARTH RETAINING SYSTEMS

CHAPTER 13 - MECHANICALLY STABILIZED EARTH WALLS AND PATENTED EARTH RETAINING SYSTEMS CHAPTER 13 - MECHANICALLY STABILIZED EARTH WALLS AND PATENTED EARTH RETAINING SYSTEMS DS Temple 13.1 SCOPE This section covers the inspection of mechanically stabilized earth walls and other patented earth

More information

7Do not walk on concrete for 24 hours. 8

7Do not walk on concrete for 24 hours. 8 4 On an uneven or clay base, place a 50mm layer of sand or road base to form an even bedding for concrete. This will also reduce the likelihood of cracking as the concrete has a firm base on which to rest.

More information

Stretch Your Dollar Theme Designs Fire Pit

Stretch Your Dollar Theme Designs Fire Pit Stretch Your Dollar Theme Designs Fire Pit Tools Garden gloves Garden hose String (5 length) Stake Hammer or rubber mallet 3 Mason Chisel Tape measure 2 level 4 level (most homeowners don t have. We don

More information

SAFE WORK PROCEDURE 038 PIT CONSTRUCTION MARCH 2014 DOC. NO. D14/184671

SAFE WORK PROCEDURE 038 PIT CONSTRUCTION MARCH 2014 DOC. NO. D14/184671 MORELAND CITY COUNCIL Operations Centre 7-9 Walter Street Hadfield Vic 3046 Tel: 8311 4300 Approved by the Walter Street OHS committee Date: September 2014 Operation Brief Description of Activity Limitations

More information

OUTSIDE PLANT. Specialized Civil Works Training

OUTSIDE PLANT. Specialized Civil Works Training OUTSIDE PLANT Specialized Civil Works Training Date/s: Enquiries: danie@fibreonix.co.za/ joebotha@telkomsa.net Cost: R 8700.00 p.p. incl. VAT Duration: 5-days Time: 08h30 to 16h30 daily Registration: Please

More information

CONTENTS. Cellular Confinement System INTRODUCTION MATERIALS Multi-Cell Fill... 2

CONTENTS. Cellular Confinement System INTRODUCTION MATERIALS Multi-Cell Fill... 2 Johannesburg +27 (0)11 922 3300 Pinetown +27 (0)31 717 2300 Cape Town +27 (0)21 531 8110 East London +27 (0)43 727 1055 www.kaytech.co.za Cellular Confinement System CONTENTS INTRODUCTION... 2 1. MATERIALS...

More information

MANUFACTURER S SPECIFICATIONS Section LIME CONCRETE. A. This section describes the requirements for floors and slabs on grade.

MANUFACTURER S SPECIFICATIONS Section LIME CONCRETE. A. This section describes the requirements for floors and slabs on grade. MANUFACTURER S SPECIFICATIONS Section 03330 LIME CONCRETE ST. ASTIER NATURAL HYDRAULIC LIME CONCRETE PART 1 GENERAL 1.01 General A. This section describes the requirements for floors and slabs on grade.

More information

RIIMPO319A Conduct backhoe/loader operations Unit descriptor. Employability skills Application of the unit. Competency field

RIIMPO319A Conduct backhoe/loader operations Unit descriptor. Employability skills Application of the unit. Competency field RIIMPO319A Unit descriptor Employability skills Application of the unit Competency field Conduct backhoe/loader operations This unit covers the conducting backhoe/loader operations in the civil construction

More information

Record of Work Experiences Trade Qualifier or Pre Apprenticeship Credits CONCRETE FINISHER OCCUPATION

Record of Work Experiences Trade Qualifier or Pre Apprenticeship Credits CONCRETE FINISHER OCCUPATION Record of Work Experiences Trade Qualifier or Pre Apprenticeship Credits CONCRETE FINISHER OCCUPATION Note to Apprenticeship Applicants The work experiences on this form are for credit only and must have

More information

SENTINEL BARRIER - GENERAL INSTALLATION GUIDELINES

SENTINEL BARRIER - GENERAL INSTALLATION GUIDELINES SENTINEL BARRIER - GENERAL INSTALLATION GUIDELINES Safety Precautions in the Excavation of a Sentinel Wedge take all necessary steps to make sure the pit is secured. Follow all OSHA requirements for digging

More information

Portland HOLLOWCORE. The obvious choice

Portland HOLLOWCORE. The obvious choice Portland HOLLOWCORE Portland The obvious choice Introduction 1 Technical Information 2-3 Decking 4 Walling 5 Staircases 6 Environmental Benefits 7 Advantages 7 Complete precast solution 8 Requirements

More information

INFORMATION AGILIA HORIZONTAL

INFORMATION AGILIA HORIZONTAL AGILIA HORIZONTAL PAGE 1 of 7 INFORMATION AGILIA HORIZONTAL Agilia Horizontal s finishing characteristics and high quality surface finish eliminate the need to power float concrete on site. Applications

More information

Contents QUALIFICATIONS PACK - OCCUPATIONAL STANDARDS FOR CONSTRUCTION INDUSTRY. Introduction. Qualifications Pack Helper Façade Installer

Contents QUALIFICATIONS PACK - OCCUPATIONAL STANDARDS FOR CONSTRUCTION INDUSTRY. Introduction. Qualifications Pack Helper Façade Installer QUALIFICATIONS PACK - OCCUPATIONAL STANDARDS FOR CONSTRUCTION INDUSTRY Contents 1. Introduction and Contacts...P1 2. Qualifications Pack....P2 3. Glossary of Key Terms P3 4. OS Units......P4 OS describe

More information

OUTSIDE PLANT. Specialized Construction of Aggregation Node Training

OUTSIDE PLANT. Specialized Construction of Aggregation Node Training OUTSIDE PLANT Specialized Construction of Aggregation Node Training Date/s: TBC Cost: R 6000.00 p.p. incl. VAT Duration: 3-days Time: 08h30 to 16h30 daily Registration: Please complete and email Registration

More information

A man walking on the moon? No ways!

A man walking on the moon? No ways! bigger = better Thicker = stronger A man walking on the moon? No ways! concrete = rigid? innovation = flexibility Join us on the road to innovation Inspired ideas It all started Inspired ideas In the USA:

More information

We are Manufacturers,Traders, and Wholesaler of all kinds of Construction equipments, Dewatering Pumpsets, Survey instruments, and Safety solutions.

We are Manufacturers,Traders, and Wholesaler of all kinds of Construction equipments, Dewatering Pumpsets, Survey instruments, and Safety solutions. +91-8048765487 Raj Engineering & Vibrators http://www.rajengineering.net/ We are Manufacturers,Traders, and Wholesaler of all kinds of Construction equipments, Dewatering Pumpsets, Survey instruments,

More information

Resin Bound Installation Guide

Resin Bound Installation Guide Resin Bound Installation Guide Key Contact Details Customer Service / Sales: 01484 400855 Email: info@theresinmill.co.uk The Resin Mill ltd, St Pegs Mill, Thornhill Beck Lane, Brighouse HD6 4AH Introduction