Rhondda Tunnel RSB 1m 44c

Size: px
Start display at page:

Download "Rhondda Tunnel RSB 1m 44c"

Transcription

1 Rhondda Tunnel RSB 1m 44c Special Examination - 17 April Background 1.1 Rhondda Tunnel was built in It was nearly 2 miles long and connected the village of Blaencwm in the Rhondda Valley with the village of Blaengwynfi in the Afan Valley. The tunnel suffered from water ingress and movement of the brick and stone lining throughout its operational life due to subsidence caused by coal mining above and below it. Several attempts were made to resist the movement by installing arched steel ribs around the tunnel lining but even some of these were pushed out of shape by the movement of the ground squeezing the sidewalls in and pushing the arch upwards. 1.2 The tunnel was closed to rail traffic in In 1970 the Minister for Transport made the decision not to repair the tunnel and the line was permanently closed. Land at each tunnel portal was later sold by the British Railways Board to the local authorities: West Glamorgan on the western side at Blaengwynfi and Rhondda Borough on the eastern side at Blaencwm. The majority of the tunnel passes under mountainous terrain but at the Blaengwynfi end the cover is relatively shallow and part of it passes under a corner of a playing field. 1.3 The approach cuttings at both ends were infilled by the local authorities and landscaped so that no visible trace of the tunnel remained. A series of concrete pipes were built into the infill material at the Blaencwm portal so that personnel access was still possible via a lockable hatch at the newly infilled ground level. The hatch was subject to vandalism so British Rail s Regional Civil Engineer decided to plug it with concrete which meant that inspection of the tunnel was no longer possible. In 2008 the concrete plug was removed by persons unknown but suspected to be urban explorers. BRB (Residuary) Ltd then installed a lockable steel hatch to the top of the access point. 1.4 Following the abolition of BRB (Residuary) Ltd in 2013, ownership of the tunnel passed to the Secretary of State for Transport who appointed the Historical Railways Estate (HRE) team to manage it. 2. Reasons for the Examination 2.1 Historically, the tunnel has been considered to be low risk to outside parties due to the nature of the terrain above and the very limited access. However, the risk could not be ignored due to the following facts: 1. Some of the land above the tunnel is owned by third parties and their property may be affected by any subsidence caused by the potential collapse of any parts of the tunnel.

2 2. No records were available of the tunnel s condition since the 1960s so prior to the recent inspection its current condition and the degree of risk that it presented to properties above was unknown. 3. Significant interest within the community in respect of the condition of the tunnel and ownership being transferred and potentially reopened. 2.2 The difficult access route and the unknown condition of the tunnel meant that normal examination by HRE s contractors was not possible. As part of the information gathering exercise forming HRE s Tunnels Strategy in 2014 a decision was taken to enter the tunnel via the access point with the assistance of confined space specialists who were suitably qualified to assess the potential danger and to undertake rescue operations if necessary. 3. Inspection Results 3.1Details of the findings are given in a report by Hammond (ECS) Ltd who were contracted to arrange a safe system of working and take photographs of the various forms of construction and the major defects. This was carried out over three days and I accompanied them on the third day to make notes. 3.2 Access via the narrow shaft and horizontal pipe was difficult due to the narrow diameter. The eastern end of the tunnel was wet underfoot with running water entering through the arch and sidewalls at several locations. This was seen to be flowing away via the original track drainage towards the infilled cutting at Blaencwm with no ponding in the tunnel. 3.3 Steel ribs around the arch were in poor condition but did not appear to be unsafe. However, the timber laggings that had been placed between the ribs and the stonework of the tunnel arch were in very bad condition with many having rotted and fallen. Small patches of stonework had fallen from the crown of the tunnel, probably as a result of the movement recorded in the mid-twentieth century, but did not appear to be in danger of further collapse. 3.4 Heading towards Blaengwynfi the tunnel was found to be relatively dry. Mass concrete was noted in the sidewalls, presumably having been placed in front of the original masonry. At approximately half way along the length of the tunnel substantial recesses have been built into the sidewalls with the arch correspondingly wider. 3.5 Continuing towards Blaengwynfi a timber cwg was found where the tunnel arch was at its most distorted. This structure was in two separate lengths, formed of railway sleepers built up into the shape of the tunnel arch with a central opening left for personnel access through the structure. The purpose of the structure was presumably to resist any further movement of the tunnel lining so that any falling material would not completely block the tunnel. It was noted that the timber structure was not in contact with the tunnel arch and the masonry, whilst clearly distorted in the southern haunch, did not appear to be in danger of collapse. Odd timbers had rotted and fallen but overall the cwg appeared to be stable.

3 3.6 The last 100m of the tunnel at the Blaengwynfi end is blocked off with a concrete block wall, probably constructed when West Glamorgan infilled the cutting and landscaped the area. Close to this internal wall is the only air shaft in the tunnel. This is circular and brick lined and was estimated to be 11m high above the crown of the tunnel arch. The top of the air shaft was sealed and a large volume of brick rubble in the tunnel directly beneath the shaft suggests that the chimney above ground was demolished by knocking it down the shaft. There is no visible trace of the capped shaft at ground level now although its location may be plotted from old maps. 4. Conclusions and Recommendations 4.1The condition of the masonry forming the tunnel does not appear to have become any worse since it was closed to rail traffic. The movement of the ground around the tunnel seems largely a result of extensive coal mining but since this activity has stopped the ground appears to have settled. The biggest danger to anyone entering the tunnel is the risk of being struck by loose, rotten timbers in the ribbed section. It is recommended that the tunnel is not in a condition that would prevent future similar examinations. 4.2 The western end of the tunnel where cover is relatively low near Blaengwynfi is in fair condition. It is recommended that the geology and mining history around this section of tunnel should be investigated so that the likelihood of movement and the effects of subsidence can be calculated. 4.3 It is recommended that ownership of the land above the tunnel should be checked with the Land Registry as part of it was originally purchased by the Rhondda and Swansea Bay Railway and is likely to be unregistered. 4.4 It is recommended that the shaft location should be marked at surface level and land ownership of this area should be confirmed and the capping should be investigated to ensure it is in good structural condition. 4.5 Providing the ground is found to be stable it is recommended that the tunnel should be examined on a frequency of every 6 years. The hazardous conditions in the tunnel mean that remote inspections would be preferable to having persons entering the tunnel. If regular entry were to be made into the tunnel then the rotten timbers should be removed from above head height and the steel ribs checked for stability and removed if necessary. This could be an expensive and hazardous activity in itself hence the preference for remote inspections. Lee Holland Engineer - Historical Railways Estate 14 th May 2015

4 Details of the tunnel construction Location Tunnel Construction 0m Access shaft. (NE Portal) 0m 395m Masonry sidewalls and soffit. 395m 644m Concrete sidewalls with arches and a brickwork soffit. 644m 1205m Masonry sidewalls and soffit. 1205m 1460m Concrete sidewalls with arches and a brickwork soffit. 1460m 1650m Brickwork sidewalls and soffit. 1650m 1748m Concrete sidewalls with arches and a brickwork soffit. 1748m 1955m Brickwork sidewalls and soffit. 1955m 1975m Concrete sidewalls with arches and a masonry soffit. 1975m 2134m Masonry sidewalls and soffit. 2134m 2166m Concrete sidewalls with arches and a masonry soffit. 2166m 2282m Masonry sidewalls and soffit. 2282m 2298m Concrete sidewalls with arches and a masonry soffit. 2295m 2351m Masonry sidewalls and soffit. 2351m 2381m Concrete sidewalls with arches and a masonry soffit. 2381m 2494m Masonry sidewalls and soffit. 2494m 2503m Concrete sidewalls with arches and a masonry soffit. 2503m 2526m Masonry sidewalls and soffit. 2526m 2543m Concrete sidewalls with arches and a masonry soffit. 2543m 3180m Masonry sidewalls and soffit. 3180m Block-work wall and capped ventilation shaft. (Towards SW Portal) General summary of tunnel condition Location Condition Poor condition: Very wet, open joints throughout. 0m 295m Isolated areas of missing masonry in the haunch. Severe hinging in the haunches and missing or partially collapsed masonry in the soffit in the ribbed areas only. Good condition: 295m 850m Poor condition: 850m 1054m Isolated soffit bulges and collapses in the ribbed areas only. Poor condition: 1054m 2022m Timber cog has been erected in an area where the haunch is severely hinging. Good condition: 2046m General Note The defects are concentrated in the areas where the steel reinforcing ribs are. Summary of where the tunnel is wet/damp/dry Location Condition 0m 850m Wet, with heavy water ingress through sidewalls/haunches/crown in isolated areas 850m 2691m Completely dry (tunnel lining and trackbed) 2691m 3180m Damp/Wet. Trackbed is generally dry Page 2 of 11

5 TUNNEL SURVEY NOTES Hammond (ecs) ltd Contract No: HRE823 Region: South Wales Location: Rhondda Tunnel HRE Engineer Lee Holland Structure Number: RSB 1m 44ch Date of Survey 16/04/2015 Grid Reference: SS Completed by JM, NG Location 0m 0m 295m 15m 50m 50m 61m 62m 62m 78m 78m 206m 206m 212m 212m 212m 395m 395m 644m 644m 838m 838m 850m 2691m 850m 961m 978m 1054m 1054m 2022m 2022m 2046m 2046m 2691m 2691m 3180m 3180m Comments/Defects Access shaft. (NE Portal) Generally wet with very deep open joints to the entire cross section of tunnel. The pointing material is very soft to the touch. Very deep open joints in entire cross section of tunnel. Isolated small areas of missing masonry in the haunch. Heavy water ingress through haunch and soffit. Corrugated steel sheeting fixed up into the arch to collect the water ingress and channel it down to the sidewalls. Steel reinforcing ribs. Severe hinging in the haunch. Masonry peeling away in the haunches revealing the rock behind. Several areas of partially collapsed or missing masonry in the soffit. 3no Steel reinforcing ribs. Spalling to the concrete sidewalls in isolated areas throughout its length. 6no Steel reinforcing ribs. The tunnel and trackbed is completely dry for this length. Steel reinforcing ribs. Isolated soffit collapses. Steel reinforcing ribs. Isolated soffit bulges and collapses. Timber Cog. The timber is soft, hollow and generally rotten. Severe hinging in middle of haunch. Bulge monitoring points evident. The cog has been erected to prevent the tunnel from hinging any further. Damp section. Block-work wall and capped ventilation shaft. (Towards SW Portal) Page 1 of 11

6 Photo Ref: A Entrance shaft at the NE portal Photo Ref: B General photo showing tunnel in the masonry section Page 3 of 11

7 Photo Ref: C Photo showing an example of the reinforcing ribbed section. This is where all the defects were noted Photo Ref: D General photo showing tunnel in the masonry section Page 4 of 11

8 Photo Ref: E Photo Ref: F Corrugated sheeting fixed into the soffit at 62m to contain the water cascading through the soffit Corrugated sheeting fixed into the soffit at 62m to contain the water cascading through the soffit Page 5 of 11

9 Photo Ref: G Photo showing an example of the reinforcing ribbed section. This is where all the defects were noted Photo Ref: H Photo showing the typical defect in the soffit of the arch (missing or partially collapsed masonry) Page 6 of 11

10 Photo Ref: I Photo Ref: J Photo showing the typical defect in the haunch of the arch (missing or partially collapsed masonry) Photo showing an example of the reinforcing ribbed section. This is where all the defects were noted Page 7 of 11

11 Photo Ref: K A timber cog has been erected at m to prevent a tunnel collapse due to severe hinging in the haunch Photo Ref: L Photo looking through the 24m long cog section Page 8 of 11

12 Photo Ref: M Blockwork wall and shaft at 3180m towards the SW portal Photo Ref: N Photo looking up the shaft. The top includes a permanent steel shutter supported by 5no beams Page 9 of 11

13 Photo Ref: O Photo Ref: P General photo showing tunnel in the section where the sidewalls are concrete (including arches) General photo showing tunnel in the section where the sidewalls are concrete (including arches) Page 10 of 11

14 Photo Ref: Q Photo showing water cascading through the sidewall at 62m where the tunnel is very wet. Note very deep open joints in the sidewall which is typical from 0m 295m. Photo Ref: R Photo showing the typical defect in the haunch of the arch (missing or partially collapsed masonry) Page 11 of 11

15

REPORT OF BUILDING INSPECTIONS TECOLUCA, EL SALVADOR. Prepared by: Global Village Engineers

REPORT OF BUILDING INSPECTIONS TECOLUCA, EL SALVADOR. Prepared by: Global Village Engineers REPORT OF BUILDING INSPECTIONS TECOLUCA, EL SALVADOR Prepared by: Global Village Engineers 23 JANUARY, 2001 23 January 2001 Senor Carlos Cortez Hernandez Alcaldia Municipal de Tecoluca San Vicente, El

More information

VISUAL CONDITION SURVEY OF PORCHE COCHERE THE HEIGHTS, MIDDLEBURY, VERMONT REPORT INTO EMERGENCY REPAIRS AND EXAMINATION OF FOOTINGS

VISUAL CONDITION SURVEY OF PORCHE COCHERE THE HEIGHTS, MIDDLEBURY, VERMONT REPORT INTO EMERGENCY REPAIRS AND EXAMINATION OF FOOTINGS VISUAL CONDITION SURVEY OF PORCHE COCHERE THE HEIGHTS, MIDDLEBURY, VERMONT REPORT INTO EMERGENCY REPAIRS AND EXAMINATION OF FOOTINGS NIGEL COPSEY FOR TOM KEEFE OCTOBER 2003 The Heights is a significant

More information

GAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT

GAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT GAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT BUILDING ASSESSMENT REPORT STRUCTURAL FOR CORNER HOUSE AUG 2014 i P a g e Table of Contents 1. INTRODUCTION... 3 1.1 Design Criteria and Specifications...

More information

11.1 INTRODUCTION 11.2 SLOPE MANAGEMENT SYSTEM 11.1 GEOTECHNICAL AND SLOPE STABILITY

11.1 INTRODUCTION 11.2 SLOPE MANAGEMENT SYSTEM 11.1 GEOTECHNICAL AND SLOPE STABILITY CHAPTER 11. GEOTECHNICAL AND SLOPE STABILITY 11.1 INTRODUCTION Geotechnical and stability related problems can occur on cut and fill slopes. These can be in the following forms: Subsidence resulting in

More information

MEMORANDUM. To Ian and Daniel,

MEMORANDUM. To Ian and Daniel, MEMORANDUM Date 17 September 2015 Reference UA007705-19-ECV-MEM-HYD-1503 rev A01 From Richard Shimell To Ian Grimes, Daniel Perez Copies Toby Skeels, James Buckley, Tom Faith, Andy Barnes Subject Alton

More information

STRUCTURAL ASSESSMENT SURVEY REPORT

STRUCTURAL ASSESSMENT SURVEY REPORT Level 6, River Park House, 225 High Road, Wood Green, London N22 8HQ Tel: 020 8489 5504 Fax: 020 8489 5229 Email: building.control@haringey.gov.uk www.haringey.gov.uk Head of Building Control Robert McIver

More information

PRINCIPAL INSPECTION. GRAND UNION CANAL AYLESBURY ARM Lock 12. Functional Location: GA Chainage Code: GA-00416

PRINCIPAL INSPECTION. GRAND UNION CANAL AYLESBURY ARM Lock 12. Functional Location: GA Chainage Code: GA-00416 PRINCIPAL INSPECTION OF GRAND UNION CANAL AYLESBURY ARM Lock 12 Functional Location: GA-005-001 Chainage Code: GA-00416 Date: 12 January 2006 PRINCIPAL INSPECTION - MMS SUMMARY AND SIGNING OFF SHEET Note:

More information

INSPECT DIRECT Pty Ltd

INSPECT DIRECT Pty Ltd Web Page: www.inspectdirect.com.au INSPECT DIRECT Pty Ltd Property Address: Sample.Dilapidation.Report Victoria Building Status / Dilapidation Report This is not a Pest Inspection The Building Status /

More information

UK POWER NETWORKS BATTERSEA CABLE TUNNEL: POWERING A RENAISSANCE AT BATTERSEA S ICONIC POWER STATION

UK POWER NETWORKS BATTERSEA CABLE TUNNEL: POWERING A RENAISSANCE AT BATTERSEA S ICONIC POWER STATION UK POWER NETWORKS BATTERSEA CABLE TUNNEL: POWERING A RENAISSANCE AT BATTERSEA S ICONIC POWER STATION Gerard Quigg CEng MICE Senior Civil Engineer COWI UK Ltd. Table of Contents 1 Introduction... 1 2 Ground

More information

Christchurch City Council

Christchurch City Council 36 Lichfield Street Detailed Engineering Evaluation Quantitative Assessment Report Christchurch City Council 36 Lichfield Street Kathmandu/Rexel Building Detailed Engineering Evaluation Quantitative Assessment

More information

Homebuyers Survey. Final Report. Mr Client. A Home, A Street, A Town. 3rd July 2014

Homebuyers Survey. Final Report. Mr Client. A Home, A Street, A Town. 3rd July 2014 Homebuyers Survey Final Report Mr Client A Home, A Street, A Town 3rd July 2014 Alpine Water Management Ltd Dorset House Regent Park Kingston Road Leatherhead KT22 7PL Tel: 0845 319 9 319 www.alpinedamp.co.uk

More information

FEATURES & BENEFITS OF ARMTEC TUNNEL LINER PLATE

FEATURES & BENEFITS OF ARMTEC TUNNEL LINER PLATE TUNNEL LINER PLATE FEATURES & BENEFITS OF ARMTEC TUNNEL LINER PLATE SAFE ECONOMICAL VERSATILE SIMPLE EASY TO HANDLE READILY AVAILABLE All underground work can be undertaken from within the assembled shell.

More information

Observed Earthquake Damage to Christchurch City Council Owned Retaining Walls and the Repair Solutions Developed

Observed Earthquake Damage to Christchurch City Council Owned Retaining Walls and the Repair Solutions Developed Lessons learned from one of New Zealand s most challenging civil engineering projects: rebuilding the earthquake damaged pipes, roads, bridges and retaining walls in the city of Christchurch 2011-2016.

More information

PHILMONT WAREHOUSE BUILDING PRELIMINARY STRUCTURAL ASSESSMENT

PHILMONT WAREHOUSE BUILDING PRELIMINARY STRUCTURAL ASSESSMENT PHILMONT WAREHOUSE BUILDING PRELIMINARY STRUCTURAL ASSESSMENT Prepared for: GATTER ARCHITECTS 111 MAIN ST. PHILMONT, NY 12565 Prepared by: TACONIC ENGINEERING, DPC PO BOX 272 CHATHAM, NY 12037 TACONIC

More information

East Lyme Middle School EAST LYME MIDDLE SCHOOL

East Lyme Middle School EAST LYME MIDDLE SCHOOL Description: N EAST LYME MIDDLE SCHOOL The school consists of a multi story building with lower, main and upper level floors. The typical floor framing for the main and upper levels is wide flange steel

More information

City of Washburn Building Assessment

City of Washburn Building Assessment City of Washburn Building Assessment Structural Assessment Report 204 W. Bayfield St. September 30, 2016 KOA No. 162078.01 Prepared For: City of Washburn 119 Washington Ave. Washburn, WI 54891 Prepared

More information

inspection, assessment

inspection, assessment CIRIA C671 London 2009 Tunnels: inspection, assessment and maintenance L McKibbins R Elmer K Roberts Mott MacDonald Ltd Golder Associates (UK) Ltd Atkins Classic House, 174-180 Old Street, London EC1V

More information

Facade retention. HSE Health & Safety Executive. Guidance Note GS 51 from the Health and Safety Executive

Facade retention. HSE Health & Safety Executive. Guidance Note GS 51 from the Health and Safety Executive HSE Health & Safety Executive Guidance Note GS 51 from the Health and Safety Executive Facade retention General Series 51 (January 1992) These Guidance Notes are published under five subject headings:

More information

Denis Creedon, B.E., MIEI. CONSULTING ENGINEER

Denis Creedon, B.E., MIEI. CONSULTING ENGINEER Denis Creedon, B.E., MIEI. CONSULTING ENGINEER PROPERTY INSPECTION REPORT PROPERTY: CLIENT: DATE: Denis Creedon, B.E., MIEI, CONSULTING ENGINEER Tel: 02221157, 0868072327 N0.6 Chapel Lane, Mallow, Co.

More information

3. INSPECTION FINDINGS

3. INSPECTION FINDINGS 3. INSPECTION FINDINGS Pier 40 is in overall Poor condition with 22% of the H-piles rated Major and 35% of the H-piles rated Severe, primarily due to severe corrosion within the splash zone at the top

More information

SERIES NG 2400 brickwork, blockwork and

SERIES NG 2400 brickwork, blockwork and MANUAL OF CONTRACT DOCUMENTS FOR HIGHWAY WORKS VOLUME 2 NOTES FOR GUIDANCE ON THE SPECIFICATION FOR HIGHWAY WORKS SERIES NG 2400 brickwork, blockwork and stonework Contents Clause Title Page NG 2401 Cement

More information

SCHEDULE OF CONDITION. Fulham, London SW6 FOR. Mr S Of XXXX Limited. Prepared by: INDEPENDENT CHARTERED SURVEYORS

SCHEDULE OF CONDITION. Fulham, London SW6 FOR. Mr S Of XXXX Limited. Prepared by: INDEPENDENT CHARTERED SURVEYORS SCHEDULE OF CONDITION Fulham, London SW6 FOR Mr S Of XXXX Limited Prepared by: INDEPENDENT CHARTERED SURVEYORS Marketing by: CONTENTS SCHEDULE OF CONDITION Elevations page 4 Internal Rooms page 12 GROUND

More information

STRUCTURAL ASSESSMENT REPORT HOFFMAN BRICKWORKS FORMER BRICK PRESS BUILDING CORNER DAWSON STREET AND BRICKWORKS DRIVE BRUNSWICK, VICTORIA PREPARED BY

STRUCTURAL ASSESSMENT REPORT HOFFMAN BRICKWORKS FORMER BRICK PRESS BUILDING CORNER DAWSON STREET AND BRICKWORKS DRIVE BRUNSWICK, VICTORIA PREPARED BY STRUCTURAL ASSESSMENT REPORT HOFFMAN BRICKWORKS FORMER BRICK PRESS BUILDING CORNER DAWSON STREET AND BRICKWORKS DRIVE BRUNSWICK, VICTORIA PREPARED BY THE O NEILL GROUP PTY LTD 2 OXFORD STREET SOUTH YARRA

More information

Safe Site 1 RUMÖH LÖEN SYURGA LÖEN

Safe Site 1 RUMÖH LÖEN SYURGA LÖEN Safe Site 1 It is not always possible to choose where we live, but understanding the site will help you to make the desicions that will help keep your family safe and protect your house from damage. THINK

More information

Response to a Bridge Strike over the Railway

Response to a Bridge Strike over the Railway Response to a Bridge Strike over the Railway A Protocol for Highway and Road Managers, Police and Bridge Owners NR/GPG/CIV/007 Note This protocol has been produced for the benefit of Network Rail staff

More information

Stonework Renovation

Stonework Renovation Stonework Renovation Cathedral Church of the Advent Birmingham, Alabama 2001-2005 Stonework Committee: Dr. Thomas A. S. Wilson John C. Carraway Lowell K. Christy Bryan F. Helm John Morse Matt Owen Rick

More information

Presentation Outline

Presentation Outline St. John s Tunnel Rehabilitation A Demonstration of Successful Fast- Track Design and Construction Christopher P. Russell, P.E. Shannon & Wilson Inc., Staff Engineer Gregory R. Fischer, Ph.D., P.E. Shannon

More information

New Zealand Geomechanics News Magazine June 2013 Article - Retaining Walls and Ground Improvements in Christchurch

New Zealand Geomechanics News Magazine June 2013 Article - Retaining Walls and Ground Improvements in Christchurch Lessons learned from one of New Zealand s most challenging civil engineering projects: rebuilding the earthquake damaged pipes, roads, bridges and retaining walls in the city of Christchurch 2011-2016.

More information

Self Assessment Questionnaire Inrushes and Subsidence Major Hazard Standard

Self Assessment Questionnaire Inrushes and Subsidence Major Hazard Standard WMC Environment, Health & Safety Management System Self Assessment Questionnaire Inrushes and Subsidence Major Hazard Standard MHS-09 DocsOpen : 57250, 11/07/2000 Uncontrolled copy check web for latest

More information

GEM Associates Limited

GEM Associates Limited JOB REFERENCE: MH/MGM Request for Further Information and Clarification on Table of Proposed Works FOR An Apartment Block in London FOR Tenants / Leaseholders of an Apartment Block Prepared by: INDEPENDENT

More information

Plastic Piling Solutions

Plastic Piling Solutions Introduction Planet 14 Landscapes Ltd began supplying and installing plastic piling in 2009. One of our very first projects involved the stablisation of a bank around a moat for a private client. We are

More information

This report has been prepared at the request of the Client, Mr & Mrs A Bellamy. Its purpose is to:

This report has been prepared at the request of the Client, Mr & Mrs A Bellamy. Its purpose is to: The Brewery Hook Norton Banbury Oxfordshire OX15 5NY SITE VISIT REPORT Telephone: 0845 241 4705 Email: info@solid-structures.com www.solid-structures.com Project Name:- 6 The Square, Aynho Project Address:-

More information

Mondol Fabrics Ltd. Nayapara,kasimpur, Gazipur ( N, E0) 8th March 2014

Mondol Fabrics Ltd. Nayapara,kasimpur, Gazipur ( N, E0) 8th March 2014 Mondol Fabrics Ltd Nayapara,kasimpur, Gazipur (23.990028N, 90.317336E0) 8th March 2014 1 2 Observations 3 Column Stresses in Toilet Area North of Building Cursory calculations indicate that column size

More information

Contract No. NE/2016/01 Site Formation and Infrastructure Works for Development of Anderson Road Quarry Site

Contract No. NE/2016/01 Site Formation and Infrastructure Works for Development of Anderson Road Quarry Site Contract No. NE/2016/01 Site Formation and Infrastructure Works for Development of Anderson Road Quarry Site Award submission for Temporary Works Excellence Award 2017 PROJECT BACKGROUND This Contract

More information

ENGINEERING, CONSTRUCTION AND MATERIAL STANDARD FOR FENCING AND GATES ORIGINAL EDITION MAY. 1997

ENGINEERING, CONSTRUCTION AND MATERIAL STANDARD FOR FENCING AND GATES ORIGINAL EDITION MAY. 1997 ENGINEERING, CONSTRUCTION AND MATERIAL STANDARD FOR FENCING AND GATES ORIGINAL EDITION MAY. 1997 This standard specification is reviewed and updated by the relevant technical committee on Jul. 2002. The

More information

The Effect of mixed foundations on the response of some buildings to excavation

The Effect of mixed foundations on the response of some buildings to excavation The Effect of mixed foundations on the response of some buildings to excavation J.N. Shirlaw Golder Associates (Singapore) Pte Ltd D. Wen Land Transport Authority of Singapore R.A. Algeo CJ Associates,

More information

Condition assessment of corrugated steel underpasses including threedimensional. terrestrial laser scanning

Condition assessment of corrugated steel underpasses including threedimensional. terrestrial laser scanning Condition assessment of corrugated steel underpasses including threedimensional terrestrial laser scanning Nathan Roberts 1, Alan Michie 1, and Lindsay Brown 2 1 Aurecon, 2 Roads and Maritime 9 th Australian

More information

Section 02 SUBSTRUCTURE

Section 02 SUBSTRUCTURE 02 Section 02 SUBSTRUCTURE 1. Trenches to be level, square and free from loose material and standing water. Steps and sides of foundations must be plumb. 2. All tree roots must be removed. Trench depths

More information

2016 STRUCTURE INSPECTION APPRAISAL REPORT. Prepared For: THE CORPORATION OF THE TOWNSHIP OF AMARANTH COUNTY OF DUFFERIN

2016 STRUCTURE INSPECTION APPRAISAL REPORT. Prepared For: THE CORPORATION OF THE TOWNSHIP OF AMARANTH COUNTY OF DUFFERIN 2016 STRUCTURE INSPECTION APPRAISAL REPORT Prepared For: THE CORPORATION OF THE TOWNSHIP OF AMARANTH COUNTY OF DUFFERIN by K. SMART ASSOCIATES LIMITED 8 McIntyre Drive Kitchener ON N2R 1H6 August 2016

More information

Rational approach for the management of a medium size bridge stock

Rational approach for the management of a medium size bridge stock Bridge Maintenance, Safety, Management, Health Monitoring and Informatics Koh & Frangopol (eds) 2008 Taylor & Francis Group, London, ISBN 978-0-415-46844-2 Rational approach for the management of a medium

More information

1 Introduction. 2 Site Description. Auckland Transport Private Bag Auckland 1142 New Zealand. 2 March Attention: Sunil Kariyawasam

1 Introduction. 2 Site Description. Auckland Transport Private Bag Auckland 1142 New Zealand. 2 March Attention: Sunil Kariyawasam 21 Pitt Street PO Box 6345, Auckland 1141, New Zealand T: +64 9 300 9000 // F: +64 9 300 9300 E: info@beca.com // www.beca.com Auckland Transport Private Bag 92250 Auckland 1142 New Zealand Attention:

More information

Construction Technology B (CON4313)

Construction Technology B (CON4313) 3 - Basement 1 Quick Revision 1.1 Problems arising from basement construction a. Excavation method. b. Surface and ground water control c. Lateral stability of basement excavation. d. Stability of adjoining

More information

Civil Engineering Construction I (CBE5031)

Civil Engineering Construction I (CBE5031) Civil Engineering Construction I (CBE5031) Basement 1 1 Quick Revision 1.1 Problems arising from basement construction a) Excavation method. b) Surface and ground water control c) Lateral stability of

More information

(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08

(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08 (b) Discuss in brief shaft spillway with neat sketches. Marks 04 OR Q (2) Explain in brief USBR stilling basin. Marks 08 Stilling Basins The basins are usually provided with special appurtenances including

More information

Residential Commercial Minor Works Owners Abroad. yes. Inspection Date Inspector

Residential Commercial Minor Works Owners Abroad. yes. Inspection Date Inspector Residential Commercial Minor Works Owners Abroad yes Inspection Date 01.04.2005 Inspector MJM Client Name Mr M Property Address Development Name Developer/Builder Warranty type NHBC SNAGGING REPORT Terms

More information

Technical Data Sheet NEC/GRAN/95:01

Technical Data Sheet NEC/GRAN/95:01 Technical Data Sheet NEC/GRAN/95:01 Installation Guidance Notes Granular Surround Note : These guidance notes refer only to the installation of Granular surround underground tanks. These guidance notes

More information

******** Condominiums Masonry Assessment

******** Condominiums Masonry Assessment ******** Condominiums Masonry Assessment On April 23rd, 2014, I examined the exterior masonry conditions and photographed both general and specific conditions on the building. I was directed by **********,

More information

ENGINEERING, CONSTRUCTION AND MATERIAL STANDARD FOR FENCING AND GATES ORIGINAL EDITION MAY 1997

ENGINEERING, CONSTRUCTION AND MATERIAL STANDARD FOR FENCING AND GATES ORIGINAL EDITION MAY 1997 ENGINEERING, CONSTRUCTION AND MATERIAL STANDARD FOR FENCING AND GATES ORIGINAL EDITION MAY 1997 This standard specification is reviewed and updated by the relevant technical committee on Jul. 2002(1) and

More information

Pathological Analysis of Suspension Corridor and Floor Structures of Residential Buildings

Pathological Analysis of Suspension Corridor and Floor Structures of Residential Buildings Pathological Analysis of Suspension Corridor and Floor Structures of Residential Buildings Bukovics, A. Széchenyi István University Győr (email: bukovics@sze.hu) Abstract Load bearing structure was studied

More information

SCHEDULE OF CONDITION

SCHEDULE OF CONDITION SCHEDULE OF CONDITION West Hampstead, London NW6 FOR Mr J Prepared by: INDEPENDENT CHARTERED SURVEYORS Marketing by: CONTENTS SCHEDULE OF CONDITION Elevations page 4 Limitations page 28 Signature Document

More information

Project Findings: Appendix 2

Project Findings: Appendix 2 NSF Final Report CMMI-1034874 Project Findings: Appendix 2 Selected Damage Photos of Engineered Buildings PART 2. Teleco Office Tower Civil Engineering and Engineering Mechanics Department University of

More information

MAJOR DEFECTS BUILDING SURVEY REPORT

MAJOR DEFECTS BUILDING SURVEY REPORT MAJOR DEFECTS BUILDING SURVEY REPORT XXXXXX Road Bedminster Bristol BS3 XXX Prepared for Mr XXXXXXX July 2017 T J Maggs MRICS MAGGS AND ALLEN 22 Richmond Hill Clifton Bristol BS8 1BA 0117 973 4049 survey@maggsandallen.co.uk

More information

INGLEBEAMS. Our Inglebeam range is available in either solid aggregate versions or hollow light weight version.

INGLEBEAMS. Our Inglebeam range is available in either solid aggregate versions or hollow light weight version. INGLEBEAMS Important Note: Our Inglebeam range is available in either solid aggregate versions or hollow light weight version. Ensure you select the correct fitting guidelines for the model being installed.

More information

329 Race Street Philadelphia, PA TEL FAX bcausa.com

329 Race Street Philadelphia, PA TEL FAX bcausa.com 329 Race Street Philadelphia, PA 19106 215.923.2834 TEL 215.923.2835 FAX bcausa.com MEMO To: Cindy Petkac, Union Station Redevelopment Corporation (USRC) From: Lauren Drapala, Building Conservation Associates,

More information

CONDITION REPORT and PROPOSED WORKS January 2014

CONDITION REPORT and PROPOSED WORKS January 2014 Birsay Heritage Trust Buildings at HMS TERN Twatt, Birsay CONDITION REPORT and PROPOSED WORKS January 2014 Leslie Burgher Chartered Architect Introduction This survey was carried out to make an assessment

More information

Building Preservation

Building Preservation building Building Preservation Basement Waterproofing waterproofing our pedigree a wealth of technical and contracting experience RTC specialise in basement and structural waterproofing, the diagnosis

More information

INGLEBEAMS. Our Inglebeam range is available in either solid aggregate versions or hollow light weight version.

INGLEBEAMS. Our Inglebeam range is available in either solid aggregate versions or hollow light weight version. INGLEBEAMS Important Note: Our Inglebeam range is available in either solid aggregate versions or hollow light weight version. Ensure you select the correct fitting guidelines for the model being installed.

More information

GRADE 11 NOVEMBER 2011 CIVIL TECHNOLOGY

GRADE 11 NOVEMBER 2011 CIVIL TECHNOLOGY Province of the EASTERN CAPE EDUCATION NATIONAL SENIOR CERTIFICATE GRADE 11 NOVEMBER 2011 CIVIL TECHNOLOGY MARKS: 200 TIME: 3 hours This question paper consists of 10 pages. 2 CIVIL TECHNOLOGY (NOVEMBER

More information

INGLEBEAMS. Our Inglebeam range is available in either solid aggregate versions or hollow light weight version.

INGLEBEAMS. Our Inglebeam range is available in either solid aggregate versions or hollow light weight version. INGLEBEAMS Important Note: Our Inglebeam range is available in either solid aggregate versions or hollow light weight version. Ensure you select the correct fitting guidelines for the model being installed.

More information

DGM Consultants, P.A. Structural Engineering and Masonry Consulting FIELD REPORT #01

DGM Consultants, P.A. Structural Engineering and Masonry Consulting FIELD REPORT #01 DGM Consultants, P.A. Structural Engineering and Masonry Consulting FIELD REPORT #01 Project Carnegie Library Date 5/15/2012 DGM Project # 2012014 Location th 9 and Vermont Contractor The Garland Company,

More information

Civil Engineering Quantities

Civil Engineering Quantities Civil Engineering Quantities By the same author Building Economics Building Maintenance Building Quantities Explained Building Technology Civil Engineering Specification Municipal Engineering Practice

More information

STRUCTURAL CONDITION ASSESSMENT

STRUCTURAL CONDITION ASSESSMENT STRUCTURAL CONDITION ASSESSMENT ALLEN JAY ROCK GYM 1201 FAIRFIELD ROAD HIGH POINT, NC Prepared for: Prepared by: Guilford County Schools 617 West Market Street Greensboro, NC Adrian S. Durham, PE, SE,

More information

Project Findings: Appendix 2

Project Findings: Appendix 2 NSF Final Report CMMI-1034874 Project Findings: Appendix 2 Selected Damage Photos of Engineered Buildings PART 1. St. Louis Gonzague Cafeteria Building Civil Engineering and Engineering Mechanics Department

More information

6 Preliminary Assessment of Construction Method and Constructability Issues

6 Preliminary Assessment of Construction Method and Constructability Issues 6 Preliminary Assessment of Construction Method and Constructability Issues 6.1 Construction Approach Appendix C includes conceptual designs of the alternatives discussed below. Generally, the conceptual

More information

Risk Assessment & Safe Working Practice

Risk Assessment & Safe Working Practice RA Ref Number: 08 Revision: 3 Project/Job Number Reference Insert Job Number Approval Date: 30/03/2018 RA Description: Working above false ceilings (in false ceiling s) Next Review Date: 01/04/2019 Notes:

More information

South Quay. hayle harbour : : regeneration. Development Proposal for South Quay/Foundry Yard Hayle Harbour. Quay Walls Restoration Method Statement

South Quay. hayle harbour : : regeneration. Development Proposal for South Quay/Foundry Yard Hayle Harbour. Quay Walls Restoration Method Statement hayle harbour : : regeneration South Quay Development Proposal for South Quay/Foundry Yard Hayle Harbour December 2010 Quay Walls Restoration Method Statement 027802 Hayle Harbour, South Quay/Foundry

More information

Comprehensive condition assessment program on the fire damaged structure a project case in Singapore

Comprehensive condition assessment program on the fire damaged structure a project case in Singapore Comprehensive condition assessment program on the fire damaged structure a project case in Singapore Gunawan Budi Wijaya 1,* 1 Petra Christian University, Department of Civil Engineering, Indonesia Abstract.

More information

IEEE 18-May Intake. Tunnel. Outlet

IEEE 18-May Intake. Tunnel. Outlet IEEE 18-May-2011 Intake Tunnel Outlet 1 Increase water diversion capacity at the Sir Adam Beck complex by 500 m 3 /s (+27%) Increase average annual energy output at the Sir Adam Beck complex by 1.6 billion

More information

ENG.ACA.0001F Madras. New Zealand significant. (a) spandrel 2010) were solid

ENG.ACA.0001F Madras. New Zealand significant. (a) spandrel 2010) were solid ENG.ACA.0001F.111 Figure 5.15 137 Manchester Street, pull out of the canopy supports 5.4 Clay brick URM building that have been partially or fully demolished 5.4.1 192 Madras Street This building was designed

More information

Town Office Building, 17 School Road, Community Room, addition completed 2007

Town Office Building, 17 School Road, Community Room, addition completed 2007 Town Office Building, 17 School Road, Community Room, addition completed 2007 Existing Conditions and Needed Improvements: Poor acoustics in the room; No internet connection, no guest WIFI; No generator

More information

The Butler Gallery at the Evans Home CONSERVATION REPORT. McCullough Mulvin Architects. September 2016

The Butler Gallery at the Evans Home CONSERVATION REPORT. McCullough Mulvin Architects. September 2016 The Butler Gallery at the Evans Home CONSERVATION REPORT McCullough Mulvin Architects September 2016 To be read in conjunction with impact statement and condition survey / recommendations in Carrig reports

More information

Schedule of Condition

Schedule of Condition Schedule of Condition Prepared with regard to The Drill Hall, High Street, Wellingborough Produced for and on behalf of The Borough Council of Wellingborough 2nd October 2014 BS1715 Contents Page 1 Preliminaries

More information

Structural Conditions Assessment of Current Lapeer District Schools Administration Building 250 Second Street, Lapeer, Michigan

Structural Conditions Assessment of Current Lapeer District Schools Administration Building 250 Second Street, Lapeer, Michigan November 2, 2015 Melissa A. Malcolm Library Director Lapeer District Library 201 Village West Dr S Lapeer, MI 48446 RE: Structural Conditions Assessment of Current Lapeer District Schools Administration

More information

SCAFFOLDS Revision No: 3

SCAFFOLDS Revision No: 3 PAGE 1 OF 6 1.0 PURPOSE/ SCOPE To communicate the safety requirements for the erection, inspection and safe use of scaffolds. Compliance with these requirements will assure employee safety while working

More information

4th International Engineering and Construction Conference - July 28, 2006

4th International Engineering and Construction Conference - July 28, 2006 4th International Engineering and Construction Conference - July 28, 2006 BOX-JACKING - A USEFUL CONSTRUCTION TOOL By Anthony Lynn, Berkeley Engineering Company, Inc. Box jacking is jacking a large precast

More information

DOLOMITE RISK MANAGEMENT PROCEDURE FOR IRENE GLEN HOMEOWNERS ASSOCIATION

DOLOMITE RISK MANAGEMENT PROCEDURE FOR IRENE GLEN HOMEOWNERS ASSOCIATION DOLOMITE RISK MANAGEMENT PROCEDURE FOR IRENE GLEN HOMEOWNERS ASSOCIATION INDEX 1. INTRODUCTION 1 2. INFRASTRUCTURE MANAGEMENT PLAN 1 3. RESIDENCE MANAGEMENT PLAN 3 4. EMERGENCY REACTION PLAN 6 5. MONITORING

More information

STRUCTURAL ASSESSMENT REPORT

STRUCTURAL ASSESSMENT REPORT STRUCTURAL ASSESSMENT REPORT FOR WASHINGTON PARK NATIONAL BANK 6300 South Cottage Grove Ave. Chicago, Illinois 60637 Prepared For: Cook County Land Bank Authority 69 W. Washington, Chicago Illinois April

More information

INTERNATIONAL BUILDING CODE

INTERNATIONAL BUILDING CODE INTERNATIONAL BUILDING CODE MODEL BUILDING CONDITIONS ASSESSMENT The Reid and Hughes building is a four-story, four-bay, brick building, constructed in 1869 with a later addition known as the Williams

More information

Railway noise mitigation factsheet 05: Cuttings and earth berms

Railway noise mitigation factsheet 05: Cuttings and earth berms Railway noise mitigation factsheet 05: Cuttings and earth berms 1.1 Overview In certain locations, the best option for the mitigation of railway noise may be to place the railway line low relative to the

More information

Excavation Safety Program

Excavation Safety Program Excavation Safety Program Excavation, Trenching & Shoring Safety I. Purpose The purpose of this policy is to establish safe operating procedures for any earthwork or underground work that is done on a

More information

1 2016 SVCA Asset Status for Reserve Study Update This brochure contains supplemental information regarding changes, repairs, and maintenance to the capital assets in our association. Page two reiterates

More information

Construction of the Manulife Tower Redevelopment of the previous Lee Gardens Hotel in Causeway Bay

Construction of the Manulife Tower Redevelopment of the previous Lee Gardens Hotel in Causeway Bay Construction of the Manulife Tower Redevelopment of the previous Lee Gardens Hotel in Causeway Bay External view of Manulife Tower from various location Block plan showing the building layout of the new

More information

Structural Engineers Report

Structural Engineers Report Consulting Civil and Structural Engineers 68D Swan Yard King Street Norwich NR1 1PG Tel 01603 760588 Fax 01603 760598 e-mail: burrell@paston.co.uk www.theburrellpartnership.co.uk Structural Engineers Report

More information

Management Plan: Hazardous Materials Removal & Demolition

Management Plan: Hazardous Materials Removal & Demolition Management Plan: Hazardous Materials Removal & Demolition Kingswood School (Upper Site), Corby 1.0 Introduction 1.1 Background Lambert Smith Hampton has been instructed by Northamptonshire County Council

More information

SEMMERING BASE TUNNEL LOGISTIC CHALLENGES

SEMMERING BASE TUNNEL LOGISTIC CHALLENGES SEMMERING BASE TUNNEL LOGISTIC CHALLENGES Dipl.-Ing. Michael Proprenter ic consulenten ZT GmbH Vienna, Austria Mail: m.proprenter@ic-group.org Dipl.-Ing. Oliver K. Wagner ÖBB - Austrian Federal Railways

More information

Brighton & Hove City Council

Brighton & Hove City Council Albion Hill Estate John Street Brighton BN2 9PJ Feasibility Report Date : 17 August 2015 Ref : 1436 Revision : One Copyright This report is the copyright of pod LLP. Any unauthorised reproduction or usage

More information

Subject: Amphitheater School District Reroofing Projects Amphi High School, Building 900 Roof Evaluation SCI Project Number:

Subject: Amphitheater School District Reroofing Projects Amphi High School, Building 900 Roof Evaluation SCI Project Number: 27 June 2016 Mr. Shane Chism, AIA Breckenridge Group 4625 E. Fort Lowell Road Tucson, Arizona 85712 Subject: Amphitheater School District Reroofing Projects Amphi High School, Building 900 Roof Evaluation

More information

De Montfort Mark 7 Incinerator (Flatpack)

De Montfort Mark 7 Incinerator (Flatpack) De Montfort Mark 7 Incinerator (Flatpack) Introduction This design is specially for those occasions when a large number of incinerators are to be built at one location and transported to the places where

More information

Tuff Toilet TM. Please comply with any local government regulations that may be in force in your area when installing your new Tuff Toilet.

Tuff Toilet TM. Please comply with any local government regulations that may be in force in your area when installing your new Tuff Toilet. Bellatrines TM Tuff Toilet TM Your new Tuff Toilet is a maintenance free clean toilet system based on the VIP (ventilated improved pit) latrine system in universal use all over the world. A sewer connection

More information

Ipswich Tidal Barrier Project a 20m tidal barrier gate to protect Ipswich from flooding and prevent surge tides

Ipswich Tidal Barrier Project a 20m tidal barrier gate to protect Ipswich from flooding and prevent surge tides River & Coastal and Flood Alleviation Ipswich Tidal Barrier Project a 20m tidal barrier gate to protect Ipswich from flooding and prevent surge tides I pswich s position on the estuary of the River Orwell

More information

Baynards Park, Cranleigh, Surrey

Baynards Park, Cranleigh, Surrey Baynards Park, Cranleigh, Surrey An Archaeological Investigation for Baynards Park Construction Limited by Jennifer Lowe Thames Valley Archaeological Services Ltd Site Code BPC04/02 January 2004 Summary

More information

SEISMIC REHAB OF RC STRUCTURES

SEISMIC REHAB OF RC STRUCTURES Seismic Design and Rehabilitation of Buildings Conference, Tbilisi, May 31, 2014 An Overview for Practicing Engineers SEISMIC REHAB OF RC STRUCTURES A. T. Tankut Middle East Technical University Ankara,

More information

Brick Works (cont.) Building in bricks: Factors affecting the stability of brick building: Properties of bricks:

Brick Works (cont.) Building in bricks: Factors affecting the stability of brick building: Properties of bricks: Brick Works (cont.) Building in bricks: Building in brick by using mortar of cement and sand or gypsum paste. When a mortar cement and sand used, bricks must be soaked with water before use to achieve:

More information

5. CONCLUSIONS, RECOMMENDATIONS, COST ESTIMATES

5. CONCLUSIONS, RECOMMENDATIONS, COST ESTIMATES 5. CONCLUSIONS, RECOMMENDATIONS, COST ESTIMATES 5.1 CONCLUSIONS In general, Pier 40 is in overall Poor condition. The allowable uniform live load rating for the pier has been significantly reduced from

More information

Regulations Detail Sheet 1

Regulations Detail Sheet 1 Roger Bullivant Ltd Walton Road Drakelow Burton-on-Trent Staffordshire DE15 9UA Tel: 01283 511115 Fax: 01283 543395 CI/SfB (17.9) Ef2 Agrément Certificate No 02/3894 Designated by Government to issue European

More information

EXTERIOR SIDING CONDITION SURVEY

EXTERIOR SIDING CONDITION SURVEY EXTERIOR SIDING CONDITION SURVEY FOR FARRWOOD 2 CONDOMINIUMS 49-176 FARRWOOD DRIVE HAVERHILL, MA APRIL 2016 c/o PROPERTY MANAGEMENT OF ANDOVER, INC. P.O. BOX 488 ANDOVER, MA 01810 213 WEST STREET, MILFORD,

More information

Garage Conversions. Technical Issues

Garage Conversions. Technical Issues Garage Conversions Introduction: if you need more space and you do not want to move house you may wish to consider converting your garage. Your home is probably your most valuable asset so it is important

More information

Contents BRICKWORK, BLOCKWORK AND STONEWORK. Series NG 2400 Brickwork, Blockwork and Stonework

Contents BRICKWORK, BLOCKWORK AND STONEWORK. Series NG 2400 Brickwork, Blockwork and Stonework BRICKWORK, BLOCKWORK AND STONEWORK Contents Clause Title Page NG2401 Cement 320 NG2404 Mortar 320 NG2405 Lime Mortar 320 NG2406 Bricks 320 NG2407 Blocks 321 NG2408 Reconstructed Stone 321 NG 2409 Natural

More information

UNDERPINNING A CRANE FOUNDATION

UNDERPINNING A CRANE FOUNDATION UNDERPINNING A CRANE FOUNDATION Donald R. McMahon, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New York, USA Andrew J. Nichols, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New

More information

FDA OC/ORA Office Building

FDA OC/ORA Office Building FDA OC/ORA Office Building Table of Contents Executive Summary... 3 Introduction... 4 Structural System... 5 Foundation:... 5 Floor System:... 7 Building 31:... 7 Building 32:... 9 Columns... 10 Lateral

More information