ENVIRONMENTAL MANAGEMENT PLAN

Size: px
Start display at page:

Download "ENVIRONMENTAL MANAGEMENT PLAN"

Transcription

1 NATIONAL POWER TRANSMISSION CORPORATION NORTHERN VIET NAM POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT TR B SUB-PROJECT BAC NINH 3 220KV SUBSTATION AND CONNECTION LINE ENVIRONMENTAL MANAGEMENT PLAN (Final) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized January 2015

2 NATIONAL POWER TRANSMISSION CORPORATION NORTHERN VIET NAM POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT TR B SUB-PROJECT BAC NINH 3 220KV SUBSTATION AND CONNECTION LINE ENVIRONMENTAL MANAGEMENT PLAN (Final) Power Engineering Consulting Northern Viet Nam Power Project Joint Stock Company 2 Management Board 32 Ngo Thoi Nhiem St., Ward 7 04 Nguyen Khac Nhu St., District 3, Ho Chi Minh City Hoan Kiem District, Ha Noi City

3 ABBREVIATIONS CP CSC EVN NPT EMP EIA EHS ESMF MONRE PC : Government : Construction Supervision Consultant : National Power Transmission Corporation : : Environmental Impact Assessment : Environmental, Health, and Safety : Environmental and Social Management Frame : Ministry of Natural Resources and Environment : People s Committee PECC2 : Power Engineering Consulting Joint Stock Company 2 QCVN QCVN QTD SEO SEMP NPMB TEP TCVN VND WB : Vietnam Codes : Vietnam Codes and Power Process : Safety and Environment Officer : Site : Southern Vietnam Power Project Management Board : Transmission Efficiency Project : Vietnam Standards : Vietnamese Dong : Work Bank Page 1

4 TABLE OF CONTENTS TABLE OF CONTENTS... 2 List of tables... 3 Figure... 3 Appendices... 3 II. POLICIES, REGULATIONS AND INSTITUTIONAL FRAMEWORKS Government s Environmental Regulations WB s Safeguard Policy... 6 III. SUBPROJECT DESCRIPTION Objectives of the Subproject Scope of the Subproject Location of the Subproject Subproject Management and Operation Scope of the Subproject kv substation Connection line Subproject Main Activities Main activities of the subproject before and during construction period Source of equipment and material and transportation alternative Subproject Main Work Quantity Employment Subproject Implementation Schedule and Total Investment Subproject Implementation Schedule Total Investment...21 IV. SUBPROJECT ENVIRONMENTAL BACKGROUND Geographical Location Climate, Topography, Pedology Natural Resource Environmental Baseline Data Air Environment Quality and Noise Water Environment Quality Socio-economic Status Economics Culture and Society...26 V. POTENTIAL IMPACTS...27 VI. MITIGATION MEASURES...41 VII. MONITORING PROGRAM Objectives Environmental Monitoring Plan...65 VIII. EMP IMPLEMENTATION ARRANGEMENTS EMP Implementation Arrangement EMP Implementation Reporting Requirement Capacity Building for EMP Implementation...76 Page 2

5 IX. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE Public Consultation Information Disclosure...84 APPENDICES...85 List of tables Table 3.1. Description of connection line route Table 3.2. Main construction items of substation Table 3.3. Quantity of main construction and erection of substation Table 3.4. Quantity of main construction and erection of connection line Table 3.5. Investment cost of the subproject Table 4.1. Land use situation on area affected by subproject Table 4.2. House and building affected in ROW Table 5.1. Potential negative impacts of the subproject Table 6.1. Environmental Mitigation Measures of the subproject Table 7.1. Environmental monitoring plan of the subproject Table 8.1. Responsibility for EMP implementation by different stakeholders Table 8.2. Reporting procedures Table 8.3. Proposed training of environmental management program Table 8.4. Cost estimate for training program Table 9.1. Summary of ideas of public consultation meeting Figure Figure 1.1. Location of the subproject Figure 4.1. Situation of paddy field at substation location Figure 4.2. Interior canal on the West at substation location Figure 4.3. Irrigation canal at substation location Figure 4.4. Paddy field around route of connection line Figure 4.5. Two houses near to location of tower No.9A Figure 4.6. Ground-graves at proposed substation location Appendices Appendix 1. Map of subproject location compared with natural reserves Appendix 2. Terms of Reference for construction supervision consultant (CSC) Appendix 3. Environmental specification for the Contractor Appendix 4. Approval decision of EIA report Page 3

6 I. INTRODUCTION The subproject Bac Ninh 3 220kV substation and connection line is one of the subproject identified for the second phase implementation under the World Bank financed Transmission Efficiency Project (TEP). The subproject will be implemented in Yen Phong district of Bac Ninh province and Soc Son district of Ha Noi City. The implementation of the subproject is in line with the national Power Development Master Plan 7 (PDMP7). This implementation is to receive and transmit capacity of 220kV voltage from national power system, to distribute capacity to 110/22kV substation in region and to meet load demands, strengthen reliability and supply energy for industrial zones of Yen Phong 1, Yen Phong 2, urban and residential zones, in Yen Phong district, other regions in Bac Ninh province and surrounding regions. Activities of the subproject are to (i) construct a 220/110/22kV substation with capacity of three transformer units of 220/110kV-250MVA and two transformer units of 110/22kV 63MVA; (ii) construct a double-circuit 220kV connection line with 4,723m in length from connection tower of Hiep Hoa Dong Anh Bac Ninh 2 500/220kV transmission line to 220kV switchyard of Bac Ninh 3 220/110kV substation. These activities could cause negative impacts to environment and local communities during the period of preconstruction, construction and operation. To ensure the potential negative impacts are identified and mitigated during the implementation period of the subproject and to comply with the Bank s Policy on Environmental Assessment, an (EMP) of the subproject has been prepared in compliance with the Environmental and Social Management Framework (ESMF) of the TEP and in connection with the subproject EIA. This EMP is an instrument that details: a) all anticipated adverse and social environmental impacts; b) the mitigation measures to be taken during the implementation and operation of a the subproject to eliminate or offset adverse environmental impacts, or to reduce them to acceptable levels; c) monitoring objectives and type of monitoring with linkages to the impacts assessed in the EIA report and the mitigation measures described in the EMP; d) the actions needed including institutional arrangements to implement these measures; e) capacity development and training to support timely and effective implementation of environmental project components and mitigation measures; and f) implementation schedule and cost estimates for implementing the EMP. The mitigation measures proposed in the EMP shall be integrated into the bidding and contractual documents, and monitored and supervised during all the phases of subproject implementation and operation. According to Vietnam s environmental assessment regulation, the subproject is subject to prepare an EIA for submission to the Ministry of Natural Resources and Environment (MONRE) for appraisal and approval. The report on EIA was submitted to MONRE in February 2014 and was approved by MONRE under the Decision No.919/QD-BTNMT on 05 th May II. POLICIES, REGULATIONS AND INSTITUTIONAL FRAMEWORKS 2.1. Government s Environmental Regulations The following national laws and regulations are applied for the subproject: - Law of Land No.45/2013/QH13 passed by National Assembly of the Socialist Republic of Vietnam on November 29, 2013 and became effective as from July 01, 2014; - Law on Electricity No.28/2004/QH11 passed by the Eleventh National Assembly of the Socialist Republic of Vietnam at its 6 th session dated on 03/12/2004; - Law No.24/2012/QH13 on 20/11/2012 of National Assembly of the Socialist Republic Page 4

7 regarding amendment and supplement some of articles of Law on Electricity No.28/2004/QH13; - Law on Water resources No.17/2012/QH13 passed by the Thirteenth National Assembly of the Socialist Republic of Vietnam at its 3 rd session dated on 21/6/2012; - Law on Cultural Heritage passed by the Twelfth National Assembly of the Socialist Republic of Vietnam at its 5 th session dated on 18/6/2009; - Biological Law passed by the Twelfth National Assembly of the Socialist Republic of Vietnam at its 4 th session dated on 13/11/2008; - Law on Protection of the Environment No. 55/2014/QH13 passed by the National Assembly on June 23th, 2014, effective January 1, Law on Fire Protection and Prevention No.27/2001/QH10 passed by the Tenth National Assembly of the Socialist Republic of Vietnam at its 9 th session dated on 29/6/2001; - Decree No. 43/2014/ND-CP of the Government on May 15, 2014 detailing the implementation of some articles of the Land law; - Decree No. 47/2014/ND-CP of the Government on May 15, 2014 detailing regulations on compensation, support and resettlement when the land is recovered by the State; - Decree No. 14/2014/ND-CP of the Government on February 26, 2014 detailing the implementation of the Electricity Law of electrical safety; - Decree No.29/2011/ND-CP dated 18 April 2011 regarding regulations on strategic environmental assessment, environmental impacts assessment and environmental protection commitments; - Decree No. 59/2008 / ND-CP dated April 09, 2008 of the Government on management of solid waste; - Circular No.26/2011/TT-BTNMT of July 18, 2011, detailing a number of articles of the Government's Decree No.29/2011/ND-CP of April 18, 2011, on strategic environmental assessment, environmental impact assessment and environmental protection commitment; - Circular No.12/2011/TT-BTNMT dated 14 April 2011 regarding the management of hazardous wastes; - Circular No.03/2010/TT-BTC of Ministry of Trade and Industry on 22/01/2010,detailing some contents related to safety protection of high-voltage power grid. Some applicable Standards and Regulations: - QCVN 05:2013/BTNMT - National technical regulation on ambient air quality; - QCVN 06:2009/BTNMT - Ambient air quality National technical regulation on a number of toxic substances in ambient air; - QCVN 19:2009/BTNMT - National techincal regulation on industrial waste gas for dusty and inorganic substances; - QCVN 08:2008/BTNMT - National technical regulation on surface water quality; - QCVN 09:2008/BTNMT - National technical regulation on underground water quality; - QCVN 14:2008/BTNMT - National technical regulation on sewage water; - QCVN 40:2011/BTNMT - National technical regulation on industrial waste water; - QCVN 26:2010/BTNMT - National technical regulation on noise; Page 5

8 - QCVN 27: 2010/BTNMT National technical regulation on vibration. - QCVN QTD 05:2009/BCT National technical codes for testing, acceptance test for power facilities; - QCVN QTD 06:2009/BCT National technical regulation on power technique Operation, Repairment of power facilities; - QCVN QTD 07:2009/BCT National technical codes for installation power network; - QCVN QTD 08:2010/BCT Low voltage power technical codes; - QCVN 01:2008/BCT National technical codes for safety regulations when working with transmission lines and electrical equipment; - TCVN 5308:1999 Technical safety regulation for construction; - TCVN 4086:1995 Power safety Standard for construction; - TCVN 3147:1990 Safety regulation on loading and unloading works; - TCVN 2292:1978 General requirement on safety for painting work; - TCVN 4244:1986 Safety technical regulation for lifting equipment; - TCVN 5863:1995 Safety requirement on lifting equipment, steel strand, drum, hoist, chain and sprocket WB s Safeguard Policy The environmental and social screening according to the criteria described in the Bank s policy on environmental assessment has been carried out, and the result shows that the WB policies on Environmental Assessment (OP 4.01), Physical Cultural Resources (OP 4.11), and Involuntary Resettlement (OP/BP 4.12) are triggered for this subproject. The subproject has also to comply with the WB s requirements on public consultation and Policy on Access to Information. The implementation of the policy on Involuntary Resettlement (OP/BP 4.12) is addressed in the Resettlement Policy Framework (RPF) of the TEP project and the Resettlement Plan (RP) of this subproject. Environmental Assessment (OP/BP 4.01): Environmental Assessment (EA) is an umbrella policy for the Bank s safeguard policies. The overarching objective is to ensure that Bank-financed projects are environmentally sound and sustainable, and that decision-making is improved through appropriate analysis of actions and of their likely environmental impacts. The EA process is intended to identify, avoid and mitigate potential impacts of Bank operations. EA takes into account the natural environment (air, water, and land); human health and safety; social aspects (involuntary resettlement, indigenous peoples, and physical cultural resources); and transboundary and global environmental aspects. EA considers natural and social aspects in an integrated way. This subproject triggers OP 4.01 because it involves the installation and operation of a highvoltage substation, requiring the identification, mitigation and monitoring of potential adverse environmental and social impacts. As required by OP 4.01 and the government EA regulation, the subproject has prepared an EIA and an EMP that meet the Government s and the World Bank s safeguards requirements. By the TEP appraisal, the subproject EIA and EMP have been disclosed locally at the subproject sites as required by OP 4.01 and the Bank s policy on access to information. Involuntary Resettlement (OP/BP 4.12) Page 6

9 The Involuntary Resettlement policy seeks to prevent severe long-term hardship, impoverishment, and environmental damage to the affected peoples during involuntary resettlement. OP 4.12 applies whether or not affected persons must move to another location. The Bank describes all these processes and outcomes as involuntary resettlement, or simply resettlement, even when people are not forced to move. Resettlement is involuntary when the government has the right to expropriate land or other assets and when affected people do not have the option to retain the livelihood situation that they have. This policy is triggered because the subproject would have impacts involving the temporary and permanent involuntary taking of land and the loss of structures and assets associated with the land for the power towers and the right-of-way of the transmission line. By appraisal, the subproject has prepared and disclosed a RP locally at the subproject sites and at the Bank s InfoShop. The RP includes the measures to ensure that displaced people are: (i) informed about the options regarding resettlement; (ii) consulted and offered alternative resettlement choices; and (iii) provided with effective compensation and livelihood restoration. The final subproject final RP will be disclosed locally at the subproject sites, at the Bank s InfoShop, and the Vietnam Development Information Center. Physical Cultural Resources (OP/BP 4.11): Physical Cultural Resources Policy (PCR) is intended to ensure that projects identify and inventory cultural resources that are potentially affected by the project. PCRs include resources of archaeological, paleontological, historical, architectural, religious, aesthetic or other cultural significance. Projects should include mitigation measures when there are adverse impacts on physical cultural resources. Appropriate agencies, NGOs and universities should be consulted. OP 4.11 will be applied to this sub-project because the subproject would involve the relocation of seven (07) graves at proposed substation s location. Mitigation measures will be addressed in the respective subproject s RP. For this subproject, it is required that all construction activities will include mechanisms to address chance finds to avoid or mitigate adverse impacts on PCRs. Chance finds procedures have been prepared and included in environmental management plan of the subproject. These chance finds procedures shall form part of the safeguard procedures in the Technical specifications for Contractors. World Bank Group Environmental, Health, and Safety Guidelines World Bank-financed projects should also take into account the World Bank Group Environmental, Health, and Safety Guidelines 1 (known as the "EHS Guidelines"). The EHS Guidelines are technical reference documents with general and industry-specific examples of Good International Industry Practice. The EHS Guidelines contain the performance levels and measures that are normally acceptable to the World Bank Group and are generally considered to be achievable in new facilities at reasonable costs by existing technology. The environmental assessment process may recommend alternative (higher or lower) levels or measures, which, if acceptable to the World Bank, become project- or site-specific requirements. This subproject should conform the Environmental, Health, and Safety Guidelines for Electric Power Transmission and Distribution and the General EHS Guidelines. 1 The EHS Guidelines can be consulted at Page 7

10 III. SUBPROJECT DESCRIPTION 3.1. Objectives of the Subproject The subproject Bac Ninh 3 220kV substation and connection line will be implemented to meet the following objectives: - Receive and transmit capacity of 220kV voltage from national power system and distribute capacity to 110/22kV substations in region of Bac Ninh province; - Meet load demands, strenghen reliability and supply energy for industrial zones of Yen Phong 1, Yen Phong 2, urban and residential zones, in Yen Phong district, other regions in Bac Ninh province and surrounding regions Scope of the Subproject The scope of subproject is to (i) construct a 220/110/22kV substation with its capacity of three transformer units of 220/110kV - 250MVA and two transformer units of 110/22kV - 63MVA; (ii) construct a double-circuit connection line with 4,723 m in length from the connection tower of Hiep Hoa Dong Anh Bac Ninh 2 500/220kV transmission line to 220kV switchyard of Bac Ninh 3 220/110kV substation Location of the Subproject Location of Bac Ninh 3 220kV Substation: Bac Ninh 3 220kV substation will be constructed in paddy field near to the National Highway No.18 and irrigation canal (boundary between Cho town and Yen Phu commune) in Phu Man hamlet, Cho town, Yen Phong district, Bac Ninh province. Geographical location is bounded by paddy field and the National Highway No.18 to the North; paddy field to the South and the East and paddy field and irrigation canal (boundary between Cho town and Yen Phu commune) to the West. Bac Ninh 3 220kV substation will be located in delta region. There are two rice-crops which is cultivated annually by the local people. Terrian is flat. Elevation fluctuates from 3.9m to 4.5m. Substation s location is determined according to the plan of the local authority in Cho town, Yen Phong district away from residential area; and this location will not affect civil buildings and industrial zones. Location of 220kV Connection Line: Connection line starts from the connection tower (starting point) of Hiep Hoa Dong Anh Bac Ninh 2 500/220kV transmission line in Kim Lu commune, Soc Son district, Ha Noi city and ends at 220kV switchyard of Bac Ninh 3 220/110kV substation (ending point) in Phu Man hamlet, Cho town, Yen Phong district, Bac Ninh province. The route of connection line runs over Kim Lu commune, Soc Son district, Ha Noi city and in communes of Hoa Tien, Yen Phu and Cho town of Yen Phong district, Bac Ninh province. The route of connection line runs parallel with the National Highway No.18 (from Ha Noi city to Bac Ninh province) and away from road edge of 50m to 91m. Terrain of the route is flat. Land situation within the ROW is paddy field and it will be a greenery corridor of the National Highway No.18 according to the plan of local authority. Location of the subproject is illustrated in Figure Subproject Management and Operation - Owner: National Power Transmission Corporation - Subproject Management Unit: Northern Vietnam Power Project Management Board Page 8

11 - Design Consulting Unit: Power Engineering Consulting Joint Stock Company 2 - Operation Management Unit: Power Transmission Company No Scope of the Subproject kv substation Construction area: - Total construction area is 48,191m 2, in which: + The substation is 34,889 m 2. + The guest-house and its access road is 1,106 m 2. + The substation s access road is 780 m 2. + The operation-house s access road is 11,416 m 2 (this is the domestic road and it will return the local authority for management after completing the subproject). Voltage: - High voltage: 220/110kV - Medium voltage: 22kV Capacities of the substation and transformer: - 220kV side is inclusive of three transformer units of 220/110kV - 250MVA. + The first phase will install the transformer unit of 220/110kV - 250MVA; + The next phase will install the two transformer units of 220/110kV - 250MVA kV side is inclusive of the two transformer units of 110/22kV - 63MVA. + The first phase will provide the standby location; + The next phase will install the two transformer units of 110/22kV - 63MVA. Technical specification of transformer: Transformer will be a new one according to the standard of IEC with the main specification as follows: - Nominated voltage: 250/250/50MVA. - Type of transformer: 3 phases, auto-transformer, core type, submerged-oil, outdoor - Frequency: 50Hz. - Noise level: Under 75 db at distance of 3 m. - Weigth of transformer: 203 tons. - Dimension of transformer: Length x Width x Height = 7,840mm x 7,250mm x 4,100mm. - Oil volume: 48.3 tons. - Type of oil: mineral oil, distallation form mineral oil (hydrocarbons), main components is CnH2n and CnH2n + 2, type of Shell Diala A.X according to the standard of ANSI/ASTM D3487, the transformer s oil does not contain hazardous ingredients (PCBs). Number of bays: - 220kV side: The 220kV busbar will be implemented in the first phase, the number of Page 9

12 220kV distribution bays is 11 bays, in which: + Four (04) bays will install in the first phase, including: 01 bay of Hiep Hoa 500/220kV substation. 01 bay of Dong Anh 220kV substation. 01 bay of transformer of 220/110kV -250MVA. 01 bus coupler. + Seven (07) bays will provide a standby location, including: 02 standby bays of the second and third transformer of 220/110kV -250MVA. 05 standby feeders kV side: The 110kV busbar will be implemented in the first phase, the number of 110kV distribution bays is 17 bays, in which: + Six (06) bays will install in the first phase, including: 02 bays of Yen Phong 1 110kV substation. 02 bays of Yen Phong 2 110kV substation. 01 bus coupler. 01 out-going bay of transformer of 220/110kV -250MVA. + Eleven (11) bays will provide a standby location, including: 02 standby out-going bays of the second and third transformer of 220/110kV - 250MVA. 02 standby bays of the second transformer of 110/22kV -63MVA. 01 standby bay of 110kV capacitor. 06 standby feeders. - 22kV side: the 22kV side will provide 22kV equipment for auto-transformer to supply power for the substation: 01 auto-transformer from 220kV transformer with capacity of 22/ kVA 01 auto-transformer from 22-35kV local power network with capacity of 35-22/ kVA Connection Line Scope of the subproject: 220kV connection line will connect into Bac Ninh 3 220/110kV substation with the scope and specification as follows: - Voltage : 220kV - The number of circuits - Length - Starting point : 02 circuits : 4,723 m : 500/220kV tension tower of Hiep Hoa Dong Anh Bac Ninh 2 Page 10

13 500/220kV transmission line - Ending point : at gate tower of Bac Ninh 3 220kV substation - Conductor : ACSR 400/51 (use of three wires/phase) - Lighting wire : Use of two lighting wires; in which 01 wire is PASTEL 147 and 01 wire is OPGW 120, 12 optical wires with ITU-T G655 standard. - Insulation - Fittings : Insulation by ceramic insulator or glass, type of 70kN and 300kN. : Fittings are in accordance with insulated weight, wire and lighting wire - Tower : Double circuit galvanized steel tower. - Foundation : Cast-in-place reinforced concrete - Earthing : Radial form with galvanized steel φ12, steel of L63x63x Main specification of connection line: - The maximum value at G0 tension angle is P The minimum value at G5B tension angle is T The longest section from G6 - G7 is 1,303 m. - The shortest section from G5A G5B is 106 m. - The number of intersections over the road (Highway No.3 and 18) is 2 times. - The number of intersections over the communication and power line is 5 times. - The number of intersections over river is 3 times. Description of connection line: The length of each section of the connection line and the crossing communes of the connection line are specifically described in the following table 3.1. Table 3.1. Description of connection line route No. Locations of connection line Length (m) Description of route 01 Cho town (From Bac Ninh 3 220kV substation to G0) 02 Cho town and Yen Phu commune (From G0 (starting point) to G1 03 Yen Phu commune anf Cho town (From G1 to G2) 36 - Starting point from 220kV bay at switchyard of Bac Ninh 3 220kV substation, G0 location is in rice region in Cho town, Yen Phong district, Bac Ninh province At G0, the route will turn right on , crossing irrigation canal, G1 will locate in rice region of Yen Phu commune, Yen Phong district, Bac Ninh province At G1, the route will turn right on , crossing rice field and canal. G2 will locate in rice region of Cho town, Yen Phong district, Bac Ninh province. Page 11

14 No. Locations of connection line Length (m) Description of route 04 Cho town and Yen Phu commune (From G2 to G3) 05 Yen Phu commune anf Hoa Tien commune (From G3 to G4) 06 Hoa Tien commune (From G4 to G5) 07 Hoa Tien commune (From G5 to G5A) 08 Hoa Tien commune (From G5A to G5B) 09 Hoa Tien commune (From G5B to G5C) 10 Hoa Tien commune (From G5C to G6) 11 Hoa Tien commune and Kim Lu commune 1,242 - At G2, the route will turn left on and run parallel to Highway No.18 (towards from Bac Ninh province to Ha Noi city), the route crosses over Highway No.3 (being constructed). G3 will locate in rice field of Yen Phu commune, Yen Phong district, Bac Ninh province. - The route crosses Highway No.3 one time at PK At G3, the route will turn right on and crosses Highway No. 18 to G4. Location of G4 locates in rice field of Hoa Tien commune, Yen Phong district, Bac Ninh province. - The route crosses Highway N.18 at PK At G4, the route will turn left on and runs parallel to Highway No.18 (towards from Bac Ninh province to Noi Bai) to G5. The location of G5 will locate in rice field of Hoa Tien commune, Yen Phong district, Bac Ninh province At G5, the route will turn left on , the route will run parallel to Highway No.18 (towards from Bac Ninh province to Noi Bai) to G5A. Location of G5A is in rice field of Hoa Tien commune, Yen Phong district, Bac Ninh province At G5A, the route will turn left on and run parallel to Highway No.18 (towards from Bac Ninh province to Noi Bai) to G5B. Location of G5B locates in rice field of Hoa Tien commune, Yen Phong district, Bac Ninh province. - Four houses located in ROW (12 m from the centre line to each side) At G5B, the route will turn left on and run parallel to Highway No.18 (towards from Bac Ninh province to Noi Bai) to G5C. Location of G5C will locate in rice field of Hoa Tien commune, Yen Phong district, Bac Ninh province. - The route crosses over 35kV transmission line one time at PK At G5C, the route will turn right on and runs parallel to Highway No.18 (towards from Bac Ninh province to Noi Bai). Location of G6 will locate in rice field of Hoa Tien commune, Yen Phong district, Bac Ninh province. - The route crosses over 35kV transmission line one time at PK At G6, the route will turn left on and run parallel to Highwat No.18 (towards from Bac Ninh province to Noi Bai), crossing Ca Lo river (boundary between Bac Page 12

15 No. Locations of connection line Length (m) Description of route (From G6 to G7) Ninh province and Ha Noi city). Location of G7 will locate in rice field of Kim Lu commune, Soc Son district, Ha Noi city. - The route crosses some the following features: + Communication line at PK31+63 and 35+16: 2 times. + Mid-low voltage at PK38+07 and 39+53: 2 times. + Ca Lo river at PK32+03: 01 time. + Lake at PK39+95: 01 time. 12 Kim Lu commune (From G7 to ending point) At G7, the route will turn right on and run parallel to Highway No.18 (towards from Bac Ninh province to Noi Bai) to ending point. At the ending point, the route will turn right and connect into Hiep Hoa Pho Noi 220kv transmission line (to be constructed) in Kim Lu commune, Soc Son district, Ha Noi city. - Lake at PK44+51: 01 time. Page 13

16 Figure 1.1. Location of the subproject Page 14

17 3.6. Subproject Main Activities Main Activities of the Subproject Before and During Construction Period Activities before construction period: - PMB and manager of the subproject are responsible for information disclosure on the subproject to local authority and people in the subproject s region. They are also responsible for site s agreement of substation and connection line with the local and relevant authorities. - Public consultation with local people in the subproject s region is to record and respond their ideas and these reponses will report to PMB for proposing a properly mitigation measure. - Compensation and land clearance. - Preparation for construction of worker camps, storage facilities. Activities during construction period: - Transportation of construction materials and equipment; - Leveling; - Excavation; - Preparation of formwork and steel rods; - Preparation of mortar and concrete; - Construction; - Installation of steel structure; - Installation of equipment and power network Source of Equipment and Material and Transportation Alternative a) Source of Equipment and Material The sources of equipment and materials for the subproject include; locally produced equipment and materials; and imported materials and equipment that cannot be domestically produced. The local materials and equipment will be purchased from selling agents of construction materials and equipment in Bac Ninh province and Ha Noi city. These agents must be in legal operation and have an business license. The construction materials and equipment will be bought and transported to the construction sites as follows: - Sand, stone, gravel, brick, formwork and bamboo wattle will be purchased from local agents in Bac Ninh province and Ha Noi city. - Reinforced concrete, grounding, formwork will be purchased from local agents in Bac Ninh province and Ha Noi city and manufactured at the site. - Galvanized steel and bolts are taken from the manufacturer who has a business license. - Wires, fittings, insulators, equipment of the subproject which have not been domestically manufactured, they will be imported to Hai Phong port and will be transported to NPMB s warehouse and then will be transported to the site according to the construction schedule. b) Transportation alternative of equipment and materials to the site Substation: - Electrical equipment, materials and galvanized steel: Page 15

18 + The imported equipment and materials will be transported from Hai Phong port to NPMB s warehouse (the average distance is 110km) and from NPMB s warehouse to the site is 40km and then will be transported to the site according to the implementation schedule. + Galvanized steel and bolts will be transported from Ha Noi city to the site. The average distance is 40km. - Transformer will be transported from factory in Ha Noi city to the site with the average distance of 40km. Connection line: - Long-way transportation is applied to convey equipment and materials stored at NPSM s warehouse such as steel towers, conductors, insulators, fittings. Transportation vehicles are trucks on national highways with an average length of 40km. - Manual transportation: The transportation of equipment and materials from gathering places to each tower position is mainly performed manually or semi-manually. The average manual transport distance for the entire route is 80 m Solution of Leveling and Layout of Substation Substation bed will be constructed with the designed elevation from +5.5m to +5.7m to ensure drainage and not affected by flood. In addition, the substation bed also meets the current elevation surrounding the substation s location. Section of irrigation and drainage canals and local roads within the substation s location will be restored after completion. These canals and local roads will be designed along substation s fence. Structure of local road is made from gravelly soil of 3m in width with the current elevation. Canals are made by M200 concrete with the current dimension. Main characteristics of leveling and layout of substation are as follows: - Interior area of substation: 24,960m 2 ; - Construction area: 16,055 m 2 ; - Percentage of building density: 64%; - Substation bed with rock of 2x4, 1x2 and 0.1m in depth. Area of substation bed: m 2 ; - The average embankment in comparison with natural elevation: 1.84m. Table 3.2: Main construction items of substation No. Items Unit Quantity 1 220kV outdoor switchyard m 2 10, kV outdoor switchyard - 8, MVA power transformer foundation KVA auto-transformer foundation x2= Control room house 01 6 Pumping house Operation house Guest- house - 01 Page 16

19 No. Items Unit Quantity 9 Storage of firefighting tool Warehouse Motorcycle parking garage Emergency oil tank tank Water tank for firefighting of 95m Lighting pile 30m pile Road outside of substation with 5m in width m Access road (reinforced concrete) Gate and fence of substation Subproject Main Work Quantity Quantity of main construction and erection for the subproject is prescribed in the following table: Table 3.3. Quantity of main construction and erection of substation No. Works Unit Quantity Method of construction I. Preparation of construction m 2 48, Clearance - 34, Clearance of the rest-house s site - 1,106.0 Included the slope of substation s foundation Included the slope of substation s platform 3 Clearance of the access road s site Included the slope 4 II. Clearance of the temporary access road s site Proposed quantity for unexploded ordnance s clearance - 11,416.0 Included the slope m 2 48, Substation bed - 34, Guest-house - 1, Access road Temporary road for construction - 11,416.0 III. Excavation, backfill and leveling III.1 Excavation (including the substation s foundation) 1 Excavation of construction works - 14, Excavation of leveling works - 9, Excavation of rest-house s site Excavation of road at location out of the substation m³ 25,330.8 Manually + machinery - 1,005.0 Page 17

20 No. Works Unit Quantity Method of construction III.2 Backfill + Leveling + construction of road 1 Backfill - 11, Leveling by soil - 5, Leveling by sand - 73, Backfill of soil and leveling road at location out of substation Backfill of sand and leveling road at location out of substation m³ 101,768.1 Manually + machinery - 3, ,085.0 IV. Concrete work m³ 2,383.0 Manually + machinery 1 Mortar of M Mortor of M Mortor of M Mortor of M200-1,606.0 V. Wood slad m³ Framework by wooden Manufactured at the site VI. Reinforced steel ton Roll reinforced steel Manufactured at the site 2 Tension bolt Manufactured at the factory VII. Erection work ton Galvanized reinforced steel Manual erection VIII. Construction of structure m 2 645,0 1 Control room According to m2 of construction area 2 Guest-house According to m2 of construction area IX Fire Fighting Construction of a water tank with volume of 95 m 3 for fire fighting Construction of an emergency oil tank (6m x 7.2m x 3.5m) Installation of a pipe system and fire dydzant Installation of pulverization system for fire fighting of 220kV transformer 5 Installation of a fire alarm system tank tank syste m syste m syste m 6 Pumping machine with electric motor set Reinforced concrete 01 Reinforced concrete Page 18

21 No. Works Unit Quantity Method of construction 7 Pumping machine with diesel motor set 01 X. Electrical works (main equipment and materials) 1 Conductor m 64,714 Manually + machinery 2 Installation of a 250MVA transformer set 1 3 Installation of a 400kVA transformer set 2 4 Installation of a 220kV circuit-breaker set 4 5 Installation of a 110kV circuit -breaker set 7 6 Installation of a 220kV disconnector et 17 7 Installation of a 110kV disconnector set Installation of a 220kV current transformer Installation of a 110kV current transformer Installation of a 220kV voltage transformer Installation of a 110kV voltage transformer 12 Installation of a 220kV arrestor nos. nos. nos. nos. nos Installation of a 110kV arrestor 14 Installation of a 24kV arrestor 15 Installation of a 220kV post- insulator 16 Installation of a 110kV post-insulator nos. nos. nos. nos Installation of a 220kV suspension insulator Installation of a 110kV suspension insulator nos. 36 nos. 39 Table 3.4. Quantity of main construction and erection of connection line No. Works Unit Quantity Method of construction I. Reparation of construction 1 Clearance m Cutting trees tree Leveling m 2 6, II. Proposed quantity for unexploded ordnance s clearance m 2 48, Layout of tower foundation - 4,750.6 Page 19

22 No. Works Unit Quantity Method of construction III. Excavation, backfill and eboulement 1 Excavation of foundation m³ 12, Manually + machinery - Soil of the first grade: - 12, Foundation s backfill - 8, Manually + machinery IV. Concrete of foundation and pile 1 Concrete of M100 m³ Manually + machinery 2 Concrete of M200-3, Manually + machinery 3 Concrete of M300 (pile) - 2, Manually + machinery V. Reinforced steel of foundation and pile 1 Reinforced steel of foundation and pile ton Manufactured at site. 2 Tension bolt ton Manufactured at site 3 Grounding Manufactured at site VI. Erection works 1 Galvanized steel ton Manual erection VII Quantity of pile foundation Soil quantity (temporary road, substation s surface, pile fabricating yard) Piling (temporary road, construction s surface, pile fabricating yard) Bamboo wattle (temporary road, construction s surface, pile fabricating yard) Steel of f4 (temporary road, construction s surface, pile fabricating yard) m 3 11, nos. 17, m 2 5, kg Reinforced concrete of 1,2m, length of 4m pile Reinforced concrete of 0.6m, length of 4m pile 2.00 VIII. Electrical works 1 Stringing wire km Lighting wire km Optical wire km Employment The construction period is expected in about 12 months. About one construction team will be provided at site and about 80 workers will be mobilized for construction activities as follows: + Direct construction : 70 people. + Indirect construction : 06 people. + Project Management Board (at site) : 04 people. Page 20

23 3.7. Subproject Implementation Schedule and Total Investment Subproject Implementation Schedule The subproject implementation schedule is expected in about 12 months and will be operated in October The schedule will be proposed as follows: - Completion and approval of investment document: March 2011; - Technical approval: June 2014; - Completion of bidding documents: August 2014; - Bidding and signing contract: November 2014; - Construction and installation: From October 2014 to October Completion and commissioning: October Total Investment Total investment of the subproject is 399,709,546,000 VND according to the decision of National Power Transmission Corporation (NPT). The investment cost of the subproject isdetailed in the following table: Table 3.5. Investment cost of the subproject No. Items Amount (VND) 1 Cost of construction 161,094,656,000 2 Cost of equipment 106,692,900,000 3 Cost of compensation 12,573,915,000 4 Cost of subproject management 3,863,104,000 5 Consultation cost 11,899,348,000 6 Other costs 34,509,767,000 7 Contingency cost 69,075,855,000 Total 399,709,546,000 IV. SUBPROJECT ENVIRONMENTAL BACKGROUND 4.1. Geographical Location The subproject will be implemented in Yen Phong district, Bac Ninh province and Soc Son district, Ha Noi city. The connection line of the subproject will start at Bac Ninh 2 220kV substation in Cho town (center of Yen Phong district), run parallel with highway No.18, and ends at connection point in Kim Lu commune (in the Southeast of Soc Son district). This location is the gateway to the east of Ha Noi city and highway No.18. This is of great advantage to traffic and foreign affair in order to develop rapidly socioeconomic Climate, Topography, Pedology a. Climate Location of the subproject has a general characteristic of monsoon tropical climate, specifically the Red River Delta region. Average temperature is 30 C - 36 C and 15 C - 20 C Page 21

24 in the summer and winter, respectively. Cold season is from October to March of the following year. The weather is affected by the Northeast monsoon, which usually brings frosts and hoarfrost. Dry season is from April to October, and itis affected by the Southeast weather, which usually brings rains. Rain depends to the season. Annual rainfall is about 1,600 mm peryear. Rainyfall during the rainy season is accounted for 80% of the annual rainfall. Average air humidity is 83% per year. Sunny hour is 1,700 hour per year, which is favourable for rice crops, industrial trees, and other trees. b. Topography The subproject is located in the riverside plain region to the South of Soc Son district and the plain region of Yen Phong district. The elevation of the proposed substation location is from 3.9m to 4.5m and the elevation of the connection line in the field region is from 4.2 m to 7.0 m. c. Pedology The subproject location at Cho town, communes of Yen Phu, Hoa Tien and Soc Son is riverside plain region. This region has consolidated alluvium of Cau river and Ca Lo river; thus, the soil is rich and available for the cultivation of agriculture, farm products, and industrial trees within a short period (such as rice and crops) Situation of Technical Infrastructure a) Traffic Location of the subproject is the gateway to the east of Ha Noi city so the traffic infrastructure system is relatively developed. Highway No.18, Noi Bai international airport and Cai Lan port (in Quang Ninh) will run parallel with the subproject s location; this route will be 150m from the substation to the north and run parallel with the connection line and will be 50 to 91m from the subproject s location. In addition, a complete traffic system connected between the cities, provinces and economic region (in districts of Yen Phong and Soc Son). Road system connected between highway No.3 in Ha Noi and Thai Nguyen, highway No.18 and connection line route in Yen Phu commune. Provincial road No.295 to the north connected with highway No.18 at Cho town and highway No.1A to the south upgraded. Provincial road No. 286 to Bac Ninh province and Ha Noi was connected with highway No.3. Therefore, traffic condition is relatively advantage. b) Hydraulic Work Water sources used for agricultural cultivation at the subproject s location are taken from Cau river and Ca Lo river via irrigation and interior canals system. At location of the subproject has about 630m in length of irrigation canal. Section of this canal will be filled during leveling the substation so this canal will be restored around the substation s fence in order to supply and drain water for paddy fields surrounding the subproject s location. c) Domestic Water Sources People use currently local water system and well water to provide daily needs in Cho town and communes of Yen Phu, Hoa Tien and Kim Lu, respectively. Water for fire-fighting and daily needs of operators will use local water system in operation phase. d) Power Supply Currently, 100% of households in subproject s location have been used power source from the national power grid of the existing 220kV transmission line along highway No.18 via 22/0.4kV transformer installed on poles. Construction phase, the subproject will use the Page 22

25 current local power grid. In addition, the subproject will propose to construct a 22kV shunt line (about 200m long) from the existing 22kV transmission line along highway No.18 to substation and install a 22/0.4kV transformer on pole with nominated capacity of 3x25kVA in order to provide power in construction phase and testing equipment Land Use and Buildings on Land a) Land Use Total area of the subproject s ROW is 103,906 m 2, in which construction area of 19 tower foundations is 4,750.6 m 2. This area is mostly paddy field. Total construction area of substation and access road is 48,191 m 2. In which, access-road takes 11,416 m 2 ; this area is public road and will be returned to local authorities and managed by them after completion. A status of land use of this region in comparison with land acquisition area of the subproject is described in the following table: Table 4.1. Land Use situation on area affected by subproject No. Item/Location Area (m 2 ) Land Area (m 2 ) Rice Crop Resident River Traffic Grave I Substation 36, , , , , Cho town 36, , , , , II Access road 11, , Cho town 11, , III ROW 103, , , , ,640.0 Cho town 11, , , Yen Phu commune 27, , , , Hoa Tien commune 31, , , , Kim Lu commune 32, , , ,224.7 Total 152, , , , , , ,840.0 Note: ROW s area includes construction area of tower foundations (4,750.6m 2 ) Figure 4.1. Situation of paddy field at substation location Figure 4.2. Interior canal on the West at substation location Page 23

26 Figure 4.3. Irrigation canal at substation location Figure 4.4. Paddy field around route of connection line b) Houses/Buildings on Land Affected by the Subproject Total residential area within ROW (11m from the center of line to each side) is 1,694 m 2. There are not any houses/buildings within permanent acquistion land area. There are four houses and buildings within the ROW. They will be limited height as stipulated in Article 13 of Decree No.14/2014/ND-CP. Table 4.2. House and building affected in ROW No. House Address Floor area (m 2 ) Floor area in ROW (m 2 ) Height of roof Materials of roof Structure Materials of wall Materials of floor 1 House Hoa Tien commune ,5 Tole Concrete Brick 2 House Hoa Tien commune Tole Concrete Brick 3 House Hoa Tien commune Tole Concrete Brick 4 House Hoa Tien commune Tole Concrete Brick Height of the existing houses and buildings in ROW is from 4 to 13.8 m. The average height is 6.6 m. Designed heigth of the transmission line will be at least 18m and 6m to ensure distance from the lowest point of wire in the maximum sagging state to natural surface of ground and from any parts of house/building to the nearest wire, respectively. The current house and building will be rehabilitated and grounded to ensure safety condition for existence of them within 220kV ROW. Therefore, the existing houses will not cause displacement and relocation. Page 24

27 c) Grave in Construction Area of Substation Figure 4.5. Two houses near to tower No.9A There are seven (07) graves located in the construction area of Bac Ninh 3 220kV substation; the area of these graves is around 200 m2. This is the single graves, which existed on rice land for a long time. These graves will be moved to another location. During the leveling period of the substation, the subproject s owner will co-operate with People s Committee of Yen Phong district and Cho town for implementing relocation. Figure 4.6. Ground graves at proposed substation location 4.5. Environmental Baseline Data In the investment project stage, the subproject s owner will take samples and analyze the quality of the physical environment (including quality of air, noise, surface water, underground water, and etc.). These measurements will be the standards in identifying and evaluating components of the physical environment for the subproject area Air Environment Quality and Noise The air sampling indicates the air quality is quite good in the subproject location. Most of the pollution criteria obtained at the sampling location of the substation and connection line met Page 25

28 permissible limits according to QCVN 05:2013/BTNMT National technical regulation on ambient air quality Water Environment Quality a) Surface Water Quality Surface water sampling at interior canals of the subproject location shows there are signs of pollution and microbial contamination. This also shows that some specific surface water in the agricultural region will be highly impacted by the amount of fertilizer which will pollute the high nutrient content in water. Other pollution criteria such as ph, suspension of solid substance, oil, and etc. have met the permissible limits of the QCVN 08:2008/BTNMT National technical regulation on surface water quality. b) Quality of Underground Water According to the result, the quality of the underground water at certain wells of households in the subproject s location is fairly good. Thus, the permissible limits of pollution criteria are met according to QCVN 09:2008/BTNMT National technical regulation on underground water quality. However, due to the effect of geology in local region, iron contents in underground water at the sampling locations have exceeded lightly in comparison with the stipulation from 1.09 to Socio-economic Status Economics a) Yen Phong district The Gross Domestic Product (GDP) of Yen Phong district in 2013 is around 6,000 VND billion, an increase of 11% since The average income per person is 28 million VND each year. The economic structure continues to grow and attract new investments into the zone. Industrial zones have increased rapidly with a participation of nearly 100 domestic and foreign enterprises. This will increase the number of employees to over 52 thousand people in the region. b) Soc Son district The output value of Soc Son district has an estimate of an increase of 6.84% in Its value will be higher in comparison with the planed criteria but will increase in the following quarter. Industrial and handicraft fields have increased 7.15%; basic construction has increased 6.84%; trade and services has increased 12.06%; agriculture forestry fishery have decreased 0.65% in comparison with Economical mechanism will grow positively. Trade and services will increase and agriculture products will decrease in ratio. Per capita income is estimated to be 23 million VND per year Culture and Society a) Population Soc Son district The population of district is about 300,000 people with 75,000 households, of which 44,000 households are accounted for 58.7% of agricultural production. The population density is 992people/square kilometer. The district has implemented vocational training and created 14,000 labors in the past five years ( ). The rate of created labors will increase to 33.73% in Page 26

29 Yen Phong district The population of the district is about 139,100 people. The population density is about 1,436 people/square kilometer. Elderly working population is about 88,212 people, of which 6,482 people are working in the zones or industrial zones. There are 6,324 people working in enterprises of the district region. Also, there are 636 labors which involve in working in foreign country and the remaining are the agricultural labors. b) Ethnicity The subproject s location (Yen Phong district, Bac Ninh province and Soc Son district, Ha Noi city) is the oldest settlement of the Kinh ethnic group. This is the main ethnic group of Vietnam. The subproject s location does not exist any other minority ethnic group. c) Culture and Society Issues around the culture and society within the subproject s location is the local authority s main concern. The subproject will contribute directly and indirectly into the improvement of living standard for the local people, such as supplying power for production, development of econimics, the lighting of all public works, and etc. The subproject is not in area of historical area, cultural heritage site, social-culture structure, nor national defense. V. POTENTIAL IMPACTS The screening of the environment around the subproject areas indicate that it is eligible for financing with an exception that the subproject will not involve possible high risk and will not create potential adverse impacts on: (a) critical natural habitats and/or protected area including proposed protected areas; (b) loss or damage to cultural property, including sites having archeological (prehistoric), paleontological, historical, religious, cultural, and unique natural values; (c) water regime, particularly water flow; and (d) other significant environmental and social impacts. The subproject will bring about positive changes to the local and regional economies and creating favorable conditions for local production activities and other social benefits. The implementation of the subproject would mainly cause land acquisition, increased dust generation, air pollution, domestic waste, and health and safety issues due to construction activites and electrical magnetic field. However, these impacts are not significant, temporary, and localized with available mitigation measures. So the subproject has been categorized as a Category B project according to Policies of OP 4.01 and satisfied to use the World Bank s loan. The potential negative impacts of the subproject are identified in Table 5.1. These can be minimized by applying the proposed mitigation measures which has been developed for the subproject in Table 6.1. Page 27

30 Table 5.1. Potential negative impacts of the subproject No. Impacts Pre-construction phase 1 Location of the subproject 2 Permanent land acquisition and affected land in the ROW Significance of impacts Impact duration Impact Description Small Short-term The subproject s location is not near or in cultural heritage sites, nature reserves or buffer zone of protected areas, wetlands, estuaries, nor forests. However, the subproject s location will affect the land and cultivation activities of 63 households, whose land will be permanently acquired by the subproject. In addition, Ca Lo river, lake, and Highway No.18 will cross the connection line. Impacts at the intersection will take place during the preconstruction and construction stages. These impacts will be minimized during the implementation. Moderate Short-term and longterm Area of permanent land acquisition is 52,941,6m 2, in which construction area of substation is 36,775.0 m 2. Access road area is 11,416.0 m 2. Tower foundation area is 4,750.6 m 2. Area of rice field is 42,637.6 m 2 ; it accounts for 85% of total affected area. Area of crops land is 1,390 m 2 ; it accounts for 2.6% of the total affected area. Irrigation canal land is 6.536,0 m 2 ; it accounts for 12.3%. Local road is 2,178.0 m 2 ; it accounts for 4,1%; Area of grave land is m 2 ; it accounts for 0.4% of total affected area for construction of the project. Residential land and house don t exist in permanent land acquisition area of the subproject. However, 63 houses will be permanently affected by the subproject. There are seven graves with a land area of 200m 2 located in the substation. These graves had existed for a long time and they will be moved to another place. In addition, the overhead connection line also affects the use of land in the ROW with area of 99,155 m 2. Most of areas affected by the ROW is rice land. Rice fields do not violate the safety distance from the conductors to land surface; thus, the local people can cultivate in the ROW without any impacts. There are four houses in the ROW with metal roofs. These houses will continue to exist in the ROW when they comply with a roof-grounding to ensure a safety for the project. The land acquisition will affect 63 households, whose land is in the proposed substation and the connection line. However, there are not anyhouseholds to be moved by this acquisition. Additionally, according to the investigation and collection from rice activities Page 28

31 No. Impacts Significance of impacts Impact duration Impact Description of these households, the land acquisition only reduces one portion of total their income. Most of them has obtained other income from non-agricultural activitives. Site clearance will be implemented after the harvest season to reduce damages to crops. In addition, according to the statistical report on socio-economic, the economical mechanism at the subproject s location is being grown in the industry as well as trade and services. Many industrial zones are being established and attracted investors to Bac Ninh province. Many works of the industrial field are being grown each year. Therefore, a heavy burden of the local authority in finding a new job for workers who are impacted by the acquisition will be minimized. The cultivation land acquired will affect local people; however, these impacts can be minimized through measures of compensation and assistance according to the stipulation of the Government to ensure their life and security. 3 Temporary land acquisition Small Short-term The land acquisition will be temporarily acquired during the subproject s implementation such as storage of materials and equipment and stringing wire. This land will be recovered after completing the subproject. This land locates in the ROW and it does not affect life of the local people. Land acquisition area for construction of a connection line is summarized as follows: - Temporary land acquisition for tower foundation is 6,483.6 m 2 - Warehouse, storage of equipment and materials is m 2 - Stringing wire: 800 m 2 Construction and storage of equipment and materials will be implemented at the substation so it is not necessary for expanding a temporary land area. Construction at each tower foundation location only lasts from one to two months so the temporary acquisition for construction only affects a crop. Page 29

32 No. Impacts 4 Effects on vegetation and habitat area due to site clearance 5 Effects on irrigation canal and local road in substation s location 6 Risk on healthy and environment due to explosive and chemnical substance 7 Impacts on historical area and cultural heritage site. Significance of impacts Impact duration Impact Description Small Short-term Vegetation is mainly rice at the subproject s location. Site clearance will be done after harvest season so the vegetation is mainly rice stubble. Wheat plant is low and harvesting period is short so they can stay in the ROW without being chopped down. Land clearance only includes area of construction and temporary acquisition plan. Generally, these clearance activities at the substation and connection line is assessed as a minor impact and mitigable. The affected trees mainly get an economical value without ecological one. Moderate Short-term At proposed substation location has interior canals with 630m in length and 2-4.5m in width; these canals is used for irrigation of the surrounding rice field and area of them is 6,536 m 2. Local road runs along with irrigation canal, which is used to access rice-field of local people. Length of this local road is 630m and affected area by the subproject is 2,178 m 2. These canals and local roads will be filled prior to construction of the project so they will cause a clogging of irrigation system and as well as a stopping of entrance to local road of people. This affects the production of farmers around the proposed subproject location. Therefore, these canals and local roads should be re-establised before leveling the substation s site. Small Short-term The subproject does not use chemical and explosive substances for clearance and leveling. However, according to the opinion of the Bac Ninh province Military Command, the subproject s location can also remain unexploded ordnance underground, and they can explode in case of having collision between them and construction equipment. This will cause accident for workers and damage assests of local people. Therefore, the subproject should prepare a removal plan for unexploded ordnances to ensure safety prior to construction. Moderate Short-term The subproject s location is not near to or in historical area or cultural heritage site. However, there are seven ground-graves in the proposed substation location. Relocation of graves can cause effects on spiritual life of households, who owned them if the relocation does not do properly with the local customs. But this is the ground-graves, which was existed for a long time so they ensure time for reburing according to local customs. Page 30

33 No. Impacts Construction phase 8 Effects on air quality due dust generation, exhaust gas from construction vehicles and transportation means 9 Impacts from noise and vibration 10 Increase water turbidity due to run-off and erosion Significance of impacts Impact duration Impact Description Moderate Short term Dust will generate during construction such as excavation, backfill and transportation. This dust is mainly generated from ground and it is easy to accumulate in a short time. This source will be generated temporarily during construction phase. The subproject locates in the agricultural region so its impact is small. Dust and exhaust gas are generated from activities of engines of transportation means and machineries. These means are used the clean-fuel so pollution content of waste gas is not high. Effects on the waste gas are not significant in the subproject region because generated location is mainly in rural region. At section G5A G5C of the subproject crosses over the residential region of Hoa Tien commune. This location will bear strictly air pollution, the remaining locations of connection line cross over the agricultural region so the effects on air pollution is small. Small Short term Noise and vibration can be caused by transportation means and mechinaries. However, construction activities are mainly carried out manually or semi-mechineries with a small means so the intensity of noise is not high. Most of the construction locations are located in the rural region, away from residiential region. The region caused strictly noise is the foundation locations crossing over the residential region in Hoa Tien commune; section G5A G5B has the foundation near the local house. Moderate Short term Ground and sand sweep away by the surface water flow at construction location can cause erosion and increase turbidity. Especially, the subproject will mainly be located on agricultural land with many interior canals and connection line will traverse Ca Lo river and it also intersects two times with the lake. However, it is assessed as a small impact because towers of this connection line will be 50m and 30m away from river and lake edges, respectively. Terrain of the subproject s location is flat. The construction period is short. The construction site will provide pits and trenches for water drainage surrounding the tower foundations. Quantity of excavation will be stored and maintained in a short time Page 31

34 No. Impacts 11 Impacts on environmental quality due to water waste. 12 Impacts on environmental quality due to waste. Significance of impacts Impact duration Impact Description and they can reuse to fill foundation after completing concrete work, and it also uses for filling slope work. The subproject will not construct towers on river, lake and canal so impacts causes by erosion, run-off are assessed as moderate. Moderate Short term Worker at the site is 80 persons in construction duration. Volume of domestic wastewater will estimate 9.3m 3 /day. This volume would generate at tents of the substation and connection line. However, these tents are far from canals and domestic wastewater only generates in the construction period and rural region so impact on wastewater is not significant. The wastewater is assessed as small and mitigable. Apart from the domestic wastewater, during the construction period, the subproject also generates construction wastewater, including pump pit drainage and a little capacity from equipment and machinery s sanitary during construction. This volume only happens in the construction duration and component of the pollutant in waste water is mainly soil, sand, non-hazardous substances. The soil and suspended-sand mixed in water will be easy to deposit sediment in the temporary drainage trenches. Therefore, impacts on waste water are as moderate. Moderate Short term The amount of generated waste is 48kg/day for total 80 persons of the whole subproject in construction duration. These amounts will be allocated at the two tents. Quantity of waste is small; it does not contain hazardous components. This waste will be collected and handled properly so it will not cause negative impacts on environment, unsanitary and effect on the surrounding aesthetics. Quantity of excavation will be reused for backfill work. Thus quantity of redundant soil is small. These quantities will be fully utilized to slope banks against erosion in the tower foundation of the connection line and do slope work at the substation. Redundant quantity is small but if the contractor does not collect and store them properly; it will cause negative impact on environment. In the process of construction and installation of the subproject can generate a lot of construction wastes such as concrete debris, formworks, steel scrap, crates, and etc. Page 32

35 No. Impacts 13 Water and soil due to hazardous waste 14 Soil erosion and eboulement generation caused by excavation, leveling and fillback duration Significance of impacts Impact duration Impact Description However, most of these construction wastes can be recycled and reused so it would be easy to control and collect this waste. The waste substance will be collected and treated according to stipulations of solid waste substance and the implementation schedule is short term (15 months). Thus, the generation of solid waste substances is assesses as moderate and mitigable. Small Short term Hazardous waste is mainly oil and oil rags, which will be generated from activities of maintenance of equipment, machineries and transportation means in the construction process. The waste oil volume generates from 41 construction means will be estimated about 287 liters/time, around liters/month. This volume only happens at the maintenance agents and they are collected by these agents. Therefore, this waste oil volume is low at construction site; it only happens when having samll repairment at site. Waste oil and oily rags can collect strictly, store and streat safely so these impacts are assessed as small. Moderate Short term Excavation, backfill, leveling and construction of the subproject will change structure of soil surface, it will cause a soil erosion due to rain-water run off or wind. Specially, substation base is filled higher than the natural ground level of 1.84m so if the contractor has not a suitable measure for reinforcing the substation base, and then risk of landslide will happen and can affect the surrounding rice-field. Construction of pole foundation can cause a erosion of canal edge at location near canal and river. This will reduce the capacity of the natural drainage in the regional location if it is not properly managed. Especially, the connection line will traverse one time via Ca Lo river and twice via the lake. However, the subproject s terrain is flat and the construction its construction always meets stipulations on safety distance at the location near to canal. The contractor will apply reinforcement measures to protect soild erosion during the leveling and excavation of foundation pit. The total quantity of excavated soil would utilize to slope and backfill foundations and substation plan. In addition, river and interior canals in the subproject s Page 33

36 No. Impacts Significance of impacts Impact duration Impact Description region will be reinforced by the protection wall. 15 Impacts on road Moderate Short term Transportation, storage of equipment and materials at the site would affect local traffic and installing tower and stringing wire at the cross section would interrupt traffic for a short period of time only. 16 Impacts on waterway traffic The substation would locate near Highway No.18, this location will be 150m from road edge and the connection line will be 50-90m from road edge so transportation of equipment and construction materials from Ha Noi city and local agents to the site is benefited by Highway No.18. Therefore, transportation would not effect significantly to local traffic. In addition, traffic activities will be affected by stringing wire work via road at intersection section (Highway No.18 and Highway 3). However, the contractor will provide scaffold to limit affects of local traffic during stringing wire. Traffic affects can also happen at the rush hour during construction of tower foundations at the residential region of Hoa Tien. None None Connection line will intersect one time with Ca Lo river, the width of this river is 48m; and twice with the lake, its width is 63m and 67m. Activities of stringing wire at section via river can interrupt waterway traffic from one to two hours. However, cross section at Ca Lo river and the lake does not exist the waterway traffic. Therefore, the subproject will not affect the waterway traffic. Local people sometimes use small boat to fish in the Ca Lo river, but its activity does not happen regularly in section of the subproject s location because river fish currently is small. During the stringing wire, these boats can be affected at section across the river. However, period of influence is short so effects on boat in the river is assessed as a minor impact. Page 34

37 No. Impacts 17 Effects on house near to section of G5A G5B 18 Effects on local traffic system quality 19 Effects on health and safety from camps and spread of infectious diseases Significance of impacts Impact duration Impact Description Moderate Short-term There are four houses located at section of G5A G5B in Yen Vy village, Hoa Tien commune, Yen Phong district. Two of them is near to location of tower foundation; it is tower location No.9A. Distance between them is at least 20m. They are the fourth grade house, brick wall, tole-roof with height of 4-4.5m. People lived in these houses will be affected by noise and dust from construction activities. Structure of house can be affected by shock from piling activity and landslide from excavation work. However, this is a house without upstairs (single house); its height is low so negative impacts from these activities is small. Landslide during excavation can be minimized by techinical method in construction duration; and then impacts on noise and dust can be also minimized. Small Short term The transportation of materials with the high frequency can affect the rural road system in the local region. The substation is 150m from Highway No.18 and the subproject will contruct an access road for transportation of materials during construction and use for operation period. The tower foundations of the connection line is 50m - 90m from Highway No.18 so materials will be transported by manual means to the site. Highway No.18 is designed to bear a heavy load so the transportation of equipment and machineries for the subproject will not affect significantly. Transportation activities would be carried out by manual means from Highway No.18 to the site, therefore, the transmission frequency mostly increase low on the paths with bad quality. The subproject s activities will rarely affect these paths. Nowadays, government authorities and local people closely monitor traffic management at the local region. The means a weight load exceeding the limit will not be permitted access to the local roads. This is also an issue for the contractor who must meet and carefully propose the transportation solution and avoid damaging the local roads system and edge of rice field. Small Short term Total workers are 80 persons at the subproject s site. Sanitary condition and safety at the tents and the site can affect the worker s health. However, these works will be paid attention by the contractor and these workers will be managed and checked periodically on health. Therefore, the disease transmission from the worker is assessed as small because Page 35

38 No. Impacts Significance of impacts Impact duration Impact Description this transmission would be treated by prevention measures. 20 Conflict between construction workers and local people 21 Accident risks to workers and community Small Short term Conflict between workers and local people can happen due to difference of income, culture and behavior. Living period of worker at the site is short (maximum of 15 months). The estimated workers at the site is 80 people, in which, it is proposed 30% of the total labor workforce will be local residents. Most of the non-local workers are technical labors who have extensive construction experience. Therefore, the conflict between non-local workers and local people and community are expected to be minor. Moderate Short-term Accident risk can happen in construction duration if the contractor is not paid attention to safety measures. Accident can happen due to foundation excavation, crane operation, tower erection and stringing wire, and etc. Accident can also happen to the construction workers or local people surrounding the subproject. Particularly, workers do works at height and install equipment on overhead poles; the posibility of accident is large when the contractor does not provide labor protection measures appropriately. Effects on health due to accidents is high and death from these accidents for victims is very high. However, according to the current stipulations, labor safety measures will prevent and solve accidents in the construction duration. Therefore, it will minimize accident risks. 22 Interruption of services Small Short-term During construction process of the substation and the connection line, it is necessary to deenergize some regions so it willinterrupt some services using power network. However, this de-energizing work only happens at the end construction period when this line is connected to the power network. The estimated de-energizing time is from one to two hours. Operation phase Page 36

39 No. Impacts 23 Effects on environemental quality due to domestic waste of operators 24 Effects on environmental quality due to hazardous waste 25 Impacts due to noise of the transformer Significance of impacts Impact duration Impact Description Small Long term Operators estimates about 22 persons at the substation during operation, these people will be divided into three shifts and five groups. The substation operation activities will be carried out according to shift regime, the actual number of operators is 7 persons per shift in maximum. Operator s activites will be generated a little volume of the domestic waste water and solid waste. The volume of domestic waste water of the operators is about 0.84 m 3 /day. The quantity of domestic solid is about 4.2 kg/day. Waste water and solid waste of the operators will generate with the small quantity so they will not affect to environment. Waste water will be collected and properly treated by septic tank before discharging into sewerage source. Domestic waste will be collected strictly and stored temporarily in bins at the site after that they will be moved by sanitation agent in local region. Small Long term Hazardous waste generates during operation period is mainly oil leakage of the transformer and oily rags. Oil of the transformer is fixed the interior of its one or capacitor and used to cool or hold a function as an insulator so oil the transformer will not generate into the environment. However, the oil can leak in the operation, repairment and maintenance processes of the transformer, or the oil leakage can also happen in the process of oil change. In addition, maintenance and santitation processes of the transformer will also generate oily rags and this quantity estimates about kg/month. Oil of the transformer is mineral component with a long existence, it will affect to the environment in case of leakage. But the transformer does not ensurely contain any hazardous components of PCBs. Oil of the transformer and oily rags can collect strictly and safely store and they will be transferred to the relevant agents for treatment. Small Long term As the technical result of 220kV transformer, they are designed according to the international standard (IEC standard), the noise is around 76 dba at distance of 2 m, so it meets permissive limit (85 dba) on noise in productive region issued at Decision No.3733/2002/QD-BYT. In reference with the monitored data which is being operated at 220kV substations, the noise is 70 dba at distance of 6 m to the transformer location, it meets value as mentioned in QCVN 26:2010/BTNMT maximum limits on noise in the production region at 6 a.m to Page 37

40 No. Impacts 26 Effects on health due electromagnetic field 27 Effects on telecommunity system 28 Risk on electric shock to health of workers and operators and local people around the high voltage Significance of impacts Impact duration Impact Description 9 p.m. Therefore, the noise only affects to operators, but its impact is a small, it will not affect to their hearing and health. Small Long term The substation and connection line are designed according to electrical standards and met stipulations on safety at Decree No. 14/2014/ND-CP. And then, the connection line is designed with suspension height that will ensure maximum electric field intensity. The electric field intensity should be less than 5kV/m in the ROW at the height of 1m above ground level as stipulated in Clause 2, Article 7 of Decree No. 14/2014/NĐ-CP. In reference the monitored value of electric field intensity at some locations of 220kV substation which is being operated, it was shown that value of electric field intensity is more than 5kV/m at the location of circuit-breaker and transformer. But there are not any locations in the substation that its value is over 25kV/m maximum permissive limit of the electric field intensity in working environment as stipulated at Decision No.3733/2002/QD- BYT of Ministry of Health. Therefore, the substation s operators can access to working locations in the substation when meeting time as stipulated at Clause 2, Article 7 of Decree No.14/2014/NĐ-CP. None None Communication system can be affected by the subproject, including communication line is near the substation and radio communication centers. However, the impact is calculated and considered according to the current stipulations when designing the subproject so this impact is assessed as a minor. The phenomenon of corona on surface of wire was designed according to IEC and TCVN standards to limit properly effects to radio and television communication. Moderate Short term Design of the subproject focus on safety measures. Network risk and accidents can happen in operation phase if the workers do not comply to the safety rules or local people do not meet the safety stipulation on power network. 29 Fire hazard and oil- Moderate Short term Oil overflow will not be significant since the transformer is operated in a normal condition. Page 38

41 No. Impacts overflow of the transformer 30 Hazard on collapsed tower Significance of impacts Impact duration Impact Description The oil over-flow only occurs when the transformer meets risks such as fire, which the transformer should be paid close attention to during the operation. Fire hazard can happen in many different reasons. They can occur inside or outside of the transformer and can be increase the risk to high. However, the substation has designed a fire-fighting system for the transformer. If fire occurs, the fire-fighting system will alert with signals and extinguish the fire automatically. This will prevent the fire from spreading to the outside location of the transformer and outside of the substation s gate.. Therefore, transformer s risk will not impact to the surrounding of the substation. In addition, the substation also provides a pit to collect all oily leakage volumes if any. Moderate Short term Towers of 220kV transmission line can be collapsed by lighting, wind, or storms. Weak foundation, especially at towers in flooded location can cause the transmission line to collapse as well. However, design and supervision have been implemented will and met safety standards. Tower foundation is designed on the basic of topography conditions, geology, and hydrometeorology of the region. Its design withstands against natural elements as statistics has shown over the last 20 years. Page 39

42 Conclusion: The implementation of the subproject would mainly cause land acquisition, increased dust generation, air pollution. However, these impacts are not significant, temporary, localized impacts with available mitigation measures. Therefore, the subproject is assessed as B environmental category in accordance with the WB s criterion and eligible for funding by Transmission Efficiency Project. Page 40

43 VI. MITIGATION MEASURES Environmental mitigation measures of the subproject are shown in Table 6.1. Page 41

44 Table 6.1. Environmental Mitigation Measures of the Subproject No. Environmental Social Issues Pre-construction stage 1 Location of the subproject 2 Permanent land acquisition Impact Assessment Mitigable Mitigable Mitigation Measures - Survey site and consult with local government, relevant agents affected by the subproject to select an optimal alternative to minimize damages on plant, land, house, works and infrastructures; - Design according to scheme on socio-economic development of local government. - Meet design as approved by EVN. - Careful site-survey, consultation with community and local authorities to choose optimal solutions in order to minimize land acquisition; - Disclosure detailed plan for permanent land acquisition for affected households; - Compensate damages satisfactorily in accordance with the RPF of the TEP project and the Resettlement Plan of the subproject; - Prepare a compensation and assistance plan according to the stipulations of Government and provincial People s Committee; - Complete compensation and assistance as specified before construction the subproject; - Plan working schedule after harvest times to avoid impacts, losses for local people; - Select tower foundation locations properly to minimize impacts on land, rice field, or garden losses of Vietnam Code/Regulation - Meet regulations of TCVN on electrical design. - Circular No. 14/2009/TT- BTNMT dated on 1/10/2009 of Ministry of Natural Resource and Environment; - Decree No. 47/2014/ND-CP dated on 15/5/2014 of the Government; - Decree No. 14/2014/ND-CP dated on 26/02/2014 of the Government. Responsibility - Design unit - Subproject s Owner - Local authority - Design unit - Subproject s Owner - Local authority Page 42

45 No. Environmental Social Issues Impact Assessment Mitigation Measures local people; tower locations should be arranged properly in local people land so that affected households can still use the remaining part of their land comfortably. Vietnam Code/Regulation Responsibility 3 Temporary land acquisition Mitigable - Careful site-survey, consultation with community and local authorities to choose optimal solutions in order to minimize impact on land and living activities as well during construction; - Disclosure detailed plan for temporary land acquisition for affected households; - Agree with the affected people to pay rent for land and compensate plants, crops in temporary acquisition area and unify alternative on return of site after construction; - Prepare leveling schedule for temporary site after harvest times to avoid losses for local people; - Return of site as an original status or as unified alternative between local people and authority. - Circular No. 14/2009/TT- BTNMT dated on 1/10/2009 of Ministry of Natural Resource and Environment; - Decree No. 47/2014/ND-CP dated on 15/5/2014 of the Government. - Construction contractor - Subproject s Owner 4 Effects on vegetation and habitat area due to site clearance. Mitigable - The Contractor shall prepare a Clearance, Revegetation and Restoration Management Plan for prior approval by the Construction Engineer, following relevant regulations. The Clearance Plan shall be approved by Construction Supervision Consultant and followed strictly by contractor. Areas to be cleared should be minimized as much as possible; - The Contractor shall remove topsoil from all areas where topsoil will be impacted on by rehabilitation activities, including temporary activities such as storage Law on Environment protection No. 52/2005/QH11 - Construction contractor Page 43

46 No. Environmental Social Issues Impact Assessment Mitigation Measures and stockpiling, etc; the stripped topsoil shall be stockpiled in areas agreed with the Construction Supervision Consultant for later use in re-vegetation and shall be adequately protected; - The application of chemicals for vegetation clearing is not permitted; - Prohibit cutting of any tree unless explicitly authorized in the vegetation clearing plan; - When needed, erect temporary protective fencing to efficiently protect the preserved trees before commencement of any works within the site; - No area of potential importance as an ecological resource should be disturbed unless there is prior authorization from CSC, who should consult with PMUs, and the relevant local authorities. This could include areas of breeding or feeding of birds or animals, fish spawning areas, or any area that is protected as a green space; - Work with local authoritites to well prepare construction schedule to avoiding harvesting time. Vietnam Code/Regulation Responsibility 5 Effects on irrigation canal and local road in substation s location Mitigable - Agree with local authority on re-establishnent plan for irrigation canal and local road affected by the substation location; - Redesign irrigation canal and local road in the area of substation, which is filled by the construction of project. These canals and roads are designed close together. They are arranged along and from outside of substation s Law on Environment protection No. 52/2005/QH11 - Design consultant; - Subproject s owner; - Construction Contractor; - Local authority Page 44

47 No. Environmental Social Issues Impact Assessment Mitigation Measures Vietnam Code/Regulation Responsibility fence. - Structure of local road is made from red-gravel mixed soils with width of 3m and elevation is as the same the current local road. Irrigation and drainage canals are made from M200 concrete with dimension as the same the current one. - All irrigation, drainage canals and local road must be completed before leveling and filling them; - Rehabilitate landscape of irrigation, drainage area and local road. In addition, slope and bank of irrigation, drainage and local road shall be planted grass to protect erosion. 6 Effects on historical area and cultural heritage site (seven ground-graves in proposed substation location) Mitigable - Survey carefully, consult community and local authority to propose an optimal solution and minimize impacts on spiritual life of household, who owned these graves; - Prepare a reasonable compensation and removal plan. The removal plan shall ensure environmental sanitary and it does not affect the local customs and religious belief of people. - Compensation and removal plans must be disclosed publicly and take advice of people, who owned the grave affected by the subproject. - Removal of graves shall be implemented completely before leveling the subproject s site. - Removal shall be implemented ritually and affected households shall choose a good date for the removal of Decree No. 47/2014/ND-CP on 15/5/2014 of the Government - Subproject s owner; - Local authority Page 45

48 No. Environmental Social Issues Construction stage Impact Assessment Mitigation Measures these graves. - Apart from compensation and assistance cost, NPMB should create an advanatge condition for households in chosing date to relocate these graves. Vietnam Code/Regulation Responsibility 7 Dust generation caused by construction activity, exhaust gas of transportation means of equipment and materials during construction. Mitigable - The Contractor is responsible for compliance with relevant Vietnamese legislation with respect to ambient air quality; - The Contractor shall implement dust suppression measures (e.g. water spray vehicles, covering of material stockpiles, etc.) as required; - Construction vehicles shall comply with speed limits and haul distances shall be minimized; - Material loads shall be suitably covered and secured during transportation to prevent the scattering of soil, sand, materials or dust; - The Contractor shall be responsible for any clean-up resulting from the failure by his employees or suppliers to property secure transported materials; - Exposed soil and material stockpiles shall be protected against wind erosion and the location of stockpiles shall take into consideration the prevailing wind directions and locations of sensitive receptors; - Dust masks should be used where dust levels are excessive; - All vehicles must comply with Vietnamese regulations controlling allowable emission limits of - QCVN 05: 2013/BTNMT: National technical regulation on ambient air quality; - TCVN : Road vehicles Maximum permitted emission limits of exhaust gas; - Decision 35/2005/QD- BGTVT on inspection of quality, technical safety and environmental protection. - Construction contractor - Shipping agent Page 46

49 No. Environmental Social Issues Impact Assessment Mitigation Measures exhaust gases; - Vehicles in Vietnam must undergo a regular emissions check and get certified named: Certificate of conformity from inspection of quality, technical safety and environmental protection following Decision No. 35/2005/QD-BGTVT; - There should be no burning of waste or construction materials or cleared vegetation on site; - Concrete mixer should be located far from the residential area. Vietnam Code/Regulation Responsibility 8 Impacts from noise and vibration Mitigable - The contractor is responsible for compliance with the relevant Vietnamese legislation with respect to noise and vibration; - All vehicles must have appropriate Certificate of conformity from inspection of quality, technical safety and environmental protection following Decision No. 35/2005/QD-BGTVT; to avoid exceeding noise emission from poorly maintained machines; - When needed, measures to reduce noise to acceptable levels must be implemented and could include silencers, mufflers, acoustically dampened panels or placement of noisy machines in acoustically protected areas. - Avoiding or minimizing transportation though or material processing near community areas; - Avoiding construction activities from 10:00 p.m at the site near to residential region. - QCVN 26:2010/BTNMT: National technical regulation on noise; - QCVN 27:2010/BTNMT: National technical regulation on vibration. - Construction contractor - Shipping agent Page 47

50 No. Environmental Social Issues Impact Assessment Mitigation Measures Vietnam Code/Regulation Responsibility 9 Increase of turbidity due to surface water flow Mitigable - Construction process should be ensured at least 50m and 30m from the river and cannal edges, respectively as specified in the design; - Backfill soil to stop overflow from rainy water acrossing construction site and provide temporary trenches at and surrouding construction locations to minimize overflow of rainy water; - Stockpile should be covered and provided trenches for drainage of rainy water at the surrounding locations to minimize erosion of soil into flow. - TCVN 4447:1987: Earth works-codes for construction. - Construction contractor 10 Impacts on environmental quality due to wastewater Mitigable - The Contractor must be responsible for compliance with the relevant Vietnamese legislation relevant to wastewater discharges into watercourses; - Portable or constructed hygienic toilets must be provided on site for construction workers. Wastewater from toilets as well as kitchens, showers, sinks, etc. shall be discharged into a conservancy tank for removal from the site or discharged into municipal sewerage systems; there should be no direct discharges to any water body; - Wastewater over standards set by relevant Vietnam technical standards/regulations must be collected in a conservancy tank and removed from site by licensed waste collectors; - Using techniques as berming or diversion during construction to limit the exposure of disturbed sediments to moving water; - Before construction, all necessary wastewater - QCVN 08:2008/BTNMT: National Technical Standard on surface water Quality; - QCVN 09:2008/BTNMT: National Technical Standard on underground water Quality; - QCVN 14:2008/BTNMT: National technical regulation on domestic wastewater; - Construction contractor Page 48

51 No. Environmental Social Issues Impact Assessment Mitigation Measures disposal permits/licenses and/or wastewater disposal contract have been obtained; - At completion of construction works, wastewater collection tanks and septic tanks shall be safely disposed or effectively sealed off. Vietnam Code/Regulation - QCVN 40:2011/BTNMT: National technical regulation on industrial wastewater. Responsibility 11 Impacts on environmental quality due to waste Mitigable - Before construction, a solid waste control procedure (storage, provision of bins, site clean-up schedule, bin clean-out schedule, etc.) must be prepared by Contractors and it must be carefully followed during construction activities; - Before construction, all necessary waste disposal permits or licenses must be obtained; - Measures shall be taken to reduce the potential for litter and negligent behavior with regard to the disposal of all refuse. At all places of work, the Contractor shall provide litter bins, containers and refuse collection facilities; - Solid waste may be temporarily stored on site in a designated area approved by the Construction Supervision Consultant and relevant local authorities prior to collection and disposal through a licensed waste collector; - Waste storage containers shall be covered, tip-proof, weatherproof and scavenger proof; - No burning, on-site burying or dumping of solid waste shall occur; - Law on environmental protection 52/2005/QH11 - Decree No. 59/2007/ND-CP on solid waste management - Construction contractor Page 49

52 No. Environmental Social Issues Impact Assessment Mitigation Measures - Recyclable materials such as wooden plates for trench works, steel, scaffolding material, site holding, packaging material, etc shall be collected and separated on-site from other waste sources for reuse, for use as fill, or for sale; - If not removed off site, solid waste or construction debris shall be disposed of only at sites identified and approved by the Construction Supervision Consultant and included in the site specific measures. Under no circumstances shall the contractor dispose of any material in environmentally sensitive areas, such as in areas of natural habitat or in or close to watercourses. Vietnam Code/Regulation Responsibility 12 Water and soil pollution due to hazardous waste Mitigable - Used oil and grease shall be removed from site and sold to an approved used oil recycling company; - Used oil, lubricants, cleaning materials, etc. from the maintenance of vehicles and machinery shall be collected in holding tanks and removed from site by a specialized oil recycling company for disposal at an approved hazardous waste site; - Unused or rejected tar or bituminous products shall be returned to the supplier s production plant; - Relevant agencies shall be promptly informed of any accidental spill or incident; - Organize information program and training for worker at site on safety working measure of hazardous waste; - Prepare and initiate a remedial action following any - Decision No. 23/2006/QD- BTNMT List of hazardous waste substances - Circular No. 12/2011/TT- BTNMT on hazardous waste management. - Construction contractor Page 50

53 No. Environmental Social Issues 13 Soil erosion and eboulement generation caused by excavation, leveling and fillback duration Impact Assessment Mitigable Mitigation Measures spill or incident. In this case, the contractor shall provide a report explaining the reasons for the spill or incident, remedial action taken, consequences/damage from the spill, and proposed corrective actions. - During construction at locations close to rivers and canals, the contractor shall perform methods to reinforce the banks with wood or iron columns to prevent eboulement and soil erosion; - Surrounding areas of substation plane shall be embanked, reinforced by pile and soil embankment for stability of the slope during leveling and compacting as well; - When opening of foundations, it is necessary to protect foundation holes with cajuput, bamboo and regular water drainage (for locations immersed in water or groundwater existence) should be performed; - Embanking dikes, edges to prevent erosion and eboulement around the construction areas; - Stockpile should be covered and provided trenches for drainage of rainy water at the surrounding locations to minimize erosion of soil into flow; - Slope will be reinforced and planted grass for antierosion upon completion of the subproject; - The Contractor shall restore all damaged road as the original status or any temporary layouts or other infrastructures caused by subproject activities. Vietnam Code/Regulation - TCVN 4447:1987: Earth works-codes for construction; - Circular No. 22/2010/TT-BXD on regulation of construction safety; - QCVN 08:2008/BTNMT National technical regulation on quality of surface water. Responsibility - Construction Contractor; 14 Traffic management Mitigable - Before construction, carry out consultations with - Law on traffic and - Construction Page 51

54 No. Environmental Social Issues Impact Assessment Mitigation Measures Vietnam Code/Regulation transportation No. 23/2008/QH12; - Law on construction No. 16/2003/QH11; - Decree No. 22/2010/TT-BXD on regulation of construction safety. Responsibility local government and community and with traffic police; - Significant increases in number of vehicle trips must be covered in a construction plan previously approved. Needs to take into account sensitive sites such as schools, hospitals, and markets; - Installation of lighting at night must be done if this is necessary to ensure safe traffic circulation; - Place signs around the construction areas to facilitate traffic movement, provide directions to various components of the works, and provide safety advice and warning; - Employing safe traffic control measures, including road/rivers/canal signs and flag persons to warn of dangerous conditions; - Avoid material transportation for construction during rush hour; - Transmission line shall ensure clearance-height as specified in road management; - Passageways for pedestrians and vehicles within and outside construction areas should be segregated and provide for easy, safe, and appropriate access. Signpost shall be installed appropriately in both water-ways and roads where necessary. Contractor 15 Effects on house near to section of G5A G5B Mitigable - Construction site shall be covered by tole with height of at least 2m; it includes covering at tower No.9A. The contractor shall also implement mitigation measures on noise, waste gas, waste water and waste substances; - Law on environmental protection 52/2005/QH11 - Construction Contractor Page 52

55 No. Environmental Social Issues Impact Assessment Mitigation Measures Vietnam Code/Regulation Responsibility - Contractor shall propose reasonable reinforcement measures during foundation excavation and pile driving to minimize landslide; it makes effect on foundation of surrounding local houses; - Manual construction method will prevail at items if necessary. Minimize operation of heavy means at locations near to local house; - Announce the affected households on implementation schedule to arrange their living activities for minimizing impacts; - Clean site and restore landscape of construction site; agree with the affected household to compensate damage (if any) caused by construction activities. 16 Effects on local traffic system quality caused by construction and transportation activities Mitigable - Transportation means shall meet load as specified for road route or contractor shall choose the route in accordance with its load; - Restore all damaged roads and bridges and rural infrastructures caused by subproject activities, if any. - Regulations of the contractor. - Construction Contractor 17 Workforce, Camps and Site Management and spread of infectious diseases Mitigable - Workers camps will be located at least 200 m away from schools and health care centres and not be located on steep slopes. The workforce shall be provided with safe, suitable and comfortable accommodations and safe portable water. They have to be maintained in clean and sanitary conditions. - Site offices, worker camps, warehouse shall be located NOT within 100m from any water courses, 500 meters of existing residential area. - Labor Law; - Stipulations of the Contractor. - Construction Contractor Page 53

56 No. Environmental Social Issues Impact Assessment Mitigation Measures Vietnam Code/Regulation Responsibility - Septic toilets must be provided at all construction camp areas where there will be concentration of labor. - Engineers and workers shall register their temporary residence with the local authority. - Periodically check health of worker. - First aid boxes shall be provided in each construction camp site. - Training workers on measures to prevent infectious diseases, and kill factors causing deceases such as flies, mosquitoes, grubs. 18 Conflict between construction workers and local people Mitigable - Educate awareness for labors and workers; - Priority is given to use local labours for properly work; - Strictly treat all cases that non-performance according to site s regulations. - Labor law; - Stipulations of the Contractor. - Construction Contractor 19 Risk on accident for worker and community Mitigable - Safety method in construction duration: + Contractor shall comply with all Vietnamese regulations regarding worker safety; + Prepare and implement action plan to cope with risk and emergency; + Preparation of emergency aid service at construction site + Training workers on occupational safety regulations; + Ensure that ear pieces are provided to and used by - Decree No. 22/2010/TT-BXD on regulation of construction safety; - Instruction No. 02/2008/CT-BXD on safety and sanitation issues in construction agencies; - TCVN : - Construction Contractor Page 54

57 No. Environmental Social Issues Impact Assessment Mitigation Measures Vietnam Code/Regulation Technical regulation on safety in construction. - Decision No.96/2008/QD-TTg on unexploded ordnance clearance; - Power safety regulation (issued with Decision No.1186/QD-EVN). Responsibility workers who must use noisy machines such as piling, explosion, mixing, etc., for noise control and workers protection; + Install fences, barriers, dangerous warning/prohibition site around the construction area which showing potential danger to public people; + The contractor shall provide safety measures as installation of fences, barriers warning signs, lighting system against traffic accidents as well as other risk to people and sensitive areas. + Relevant authorities shall execute unexploded ordinance clearance when it illustrates that the subproject still exists them. - Safety measures for workers who are being done at high level (overhead): + Check structures in prior to work; + Prepare a working-program at overhead location such as training on technical climbing and protection method during working at height, checking maintenance work and relocation of equipment and rescuing worker from accident. + Fixed installation on the top of tower to protect workers when they are being done at high level (overhead). + Safety belt should be not less than two-in-one with nylon of 16mm (millimeters) or materials with equivalent strength. Safety belt should replace before Page 55

58 No. Environmental Social Issues Impact Assessment Mitigation Measures Vietnam Code/Regulation Responsibility having a sign of aging or broken fibres. + Operators should have a spare part safety belt when they work at high level. + Signal panels and other obstructions should remove from the tower/pole or structures before performing work. + Operator should use a tool bag, which has checked carefully to raise or lower tool or materials during operation. - Planned and unplanned interruptions to water, gas, power, internet services: the Contractor must undertake prior consultation and contingency planning with local authorities about the consequences of a particular service failure or disconnection; - Coordinate with relevant utility providers to establish appropriate construction schedules; - Provide information to affected households on working schedules as well as planned disruptions (at least 5 days in advance); - Interruptions of water supply to agricultural areas must also be avoided. - The contractor should ensure alternative water supply to affected residents in the event of disruptions lasting more than one day; - Any damages to existing utility systems of cable shall be reported to authorities and repaired. - String the conductor after crop havesting season. 20 Interruption of utility services and agricultural activities Mitigable - Decree No. 73/2010/ND-CP on administrative penalization security and society issues. - Construction Contractor Page 56

59 No. Environmental Social Issues Impact Assessment Mitigation Measures Vietnam Code/Regulation Responsibility 21 Restoration of affected areas - Cleared areas such as temporary layout, stringing area, disposal areas, site facilities, workers camps, stockpiles areas, working platforms and any areas temporarily occupied during construction of the project works shall be restored as original status or better; - Start revegetation at the earliest opportunity. Appropriate local native species of vegetation shall be selected for the planting and restoration of the natural landforms; - Spoil heaps and excavated slopes shall be re-profiled to stable batters, and grassed to prevent erosion; - All affected areas shall be landscaped and any necessary remedial works shall be undertaken without delay, including green-spacing, roads, bridges and other existing works; - Trees shall be planted at exposed land and on slopes to prevent or reduce land collapse and keep stability of slopes; - Provide temporary irrigations canals if neccesary and restore all damaged irrigation canals caused by project activities. - Law on Environment protection No. 52/2005/QH11 - Construction Contractor 22 Communication with local communities - Maintain open communications with the local government and concerned communities; the contractor shall coordinate with local authorities (leaders of local wards or communes, leader of villages) for agreed schedules of construction activities at areas nearby sensitive places or at sensitive times; - Decree No. 73/2010/ND-CP on administrative penalization security and society issues. - Construction Contractor; - Local authority. Page 57

60 No. Environmental Social Issues Impact Assessment Mitigation Measures - Provide local communities and labors at site with copy of ECOPs and safety environmental documents. - Disseminate project information to affected parties (for example local authority, enterprises and affected households, etc) through community meetings before construction commencement; - Provide all information, especially technical findings, in a language that is understandable to the general public and in a form of useful to interested citizens and elected officials through the preparation of fact sheets and news release, when major findings become available during project phase; - Monitor community concerns and information requirements as the project progresses; - Respond to telephone inquiries and written correspondence in a timely and accurate manner; - Inform local residents about construction and work schedules, interruption of services, traffic detour routes and provisional bus routes, blasting and demolition, as appropriate; - Provide technical documents and drawings to PC s community, especially a sketch of the construction area and the EMP of the construction site; - Notification boards shall be erected at all construction sites providing information about the project, as well as contact information about the site managers, environmental staff, health and safety staff, telephone numbers and other contact information so that any Vietnam Code/Regulation Responsibility Page 58

61 No. Environmental Social Issues Impact Assessment Mitigation Measures affected people can have the channel to voice their concerns and suggestions. Vietnam Code/Regulation Responsibility 23 Chance finding procedures in case of founding objects with historical or cultural values If the Contractor discovers archeological sites, historical sites, remains and objects, including graveyards and/or individual graves during excavation or construction, the Contractor shall: - Stop the construction activities in the area of the chance find; - Delineate the discovered site or area; - Secure the site to prevent any damage or loss of removable objects. In cases of removable antiquities or sensitive remains, a night guard shall be arranged until the responsible local authorities or the Department of Culture and Information takes over; - Notify the Construction Supervision Consultant who in turn will notify responsible local or national authorities in charge of the Cultural Property of Viet Nam (within 24 hours or less); - Relevant local or national authorities would be in charge of protecting and preserving the site before deciding on subsequent appropriate procedures. This would require a preliminary evaluation of the findings to be performed. The significance and importance of the findings should be assessed according to the various criteria relevant to cultural heritage; those include the aesthetic, historic, scientific or research, social and economic values; - Law on Cultural Heritage (2002); - Law on Cultural Heritage (2009) supplemented and amended; - Decree No. 98/2010/ND-CP, supplemented and amended. - Construction Contractor Page 59

62 No. Environmental Social Issues Impact Assessment Mitigation Measures - Decisions on how to handle the finding shall be taken by the responsible authorities. This could include changes in the layout (such as when finding an irremovable remain of cultural or archeological importance) conservation, preservation, restoration and salvage; - Decisions concerning the management of the finding shall be communicated in writing by relevant authorities; - Construction works could resume only after permission is granted from the responsible local authorities concerning safeguard of the heritage. Vietnam Code/Regulation Responsibility Operation stage 24 Impacts on environmental quality due to domestic waste of operators Mititgable - Before construction, a solid waste and a waste water control procedure must be prepared by Contractors and it must be carefully followed during construction activities; - Before construction, all necessary waste disposal permits or licenses must be obtained; - Working location at site shall provide bins and collection means of waste; - Waste storage containers shall be covered, tip-proof, weatherproof and scavenger proof; - Provide toilet and septic tank at operation room of substation to collect and treat domestic waster water of operators; - Solid waste may be temporarily stored on site in a designated area approved by the Construction Supervision Consultant and relevant local authorities - Law on Environment protection No. 52/2005/QH11; - Decree No. 59/2007/ND-CP on solid waste management; - QCVN 14:2008/BTNMT: National technical regulation on domestic wastewater. - Subproject s owner; - Design Consultant; - Operation unit. Page 60

63 No. Environmental Social Issues 25 Impacts on environmental quality due to hazardous waste Impact Assessment Mitigation Measures prior to collection and disposal through a licensed waste collector. Mitigable - Before operation, a hazardous waste control procedure must be prepared by management and operation unit and it must be carefully followed during operation process; - Prohibit using PCBs in the subproject; - Periodical maintenance for oil leakage of transformer; - Provide emergency oil tank to collect volune of oil leakage if happening transformer s risk; - Provide storage and tank of hazardous waste in accordance with stipulation of its management; - Sign a contract with relevant unit to transfer periodically hazardous waste. 26 Noise of transformer Mitigable - State technical requirement on noise of transformer into bidding document; - Transformer location will be far from operation room; - Periodical maintenance for transformer. 27 Impacts on health due to magnetic field Mitigable - Design works have complied with international standards to protect human s health (electric field is less than 5kV/m at fence location of substation and ROW of transmission line); - Earthing iron roof and metal structure for house in the ROW of transmission line; Vietnam Code/Regulation - Circular No.12/2011/TT- BTNMT management of hazardous wastes. - QCVN 26:2010/BTNMT: National technical regulation on noise - Quy phạm trang bị điện; - Decree No. 14/2014/NĐ-CP. Responsibility - Subproject s owner; - Design Consultant; - Operation unit. - Subproject s owner; - Design Consultant; - Operation unit. - Subproject s owner; - Design Consultant; - Operation unit. Page 61

64 No. Environmental Social Issues Impact Assessment Mitigation Measures - The post structures and connection points will locate far from residential area and avoid climbing of small animal; - Operator must meet the operation procedure and working time to ensure safety requirement; - Operator must meet requirement to work in shifts for ensuring contact time with electric field as specified limit; - Execute the environmental Monitoring Plan, investigation, periodically check of magnetic field at substation and transmission line; - Periodical check and maintenance the safety distance between objects in ROW of transmission line and substation. The safety distance of high voltage wires is specified in Decree No.14/2014/NĐ-CP. Vietnam Code/Regulation Responsibility 28 Impacts on health of operator and local people due to electric shock Mitigable - Provide a relay system, grounding system and lighting system for equipment of substation and transmission line; - Provide signals at tower location to warn operator, maintenance worker and local people of a danger under the high voltage transmission line; - Provide signals at crossing section of national road to warn of a transportation of traffic means in accordance with stipulations of relevant authorities; - Check regularly safety corridors of high voltage power grid to maintain the power safety conditions; - Operators must meet operation procedures to ensure - Meet the relevant regulations on power sector; - Circular No. 01/2011/TTLT- BLDTBXH-BYT on 10/01/2011 of Ministry of Labor Invalids and Social Affairs and Ministry of Health Portal; - Decree No. - Subproject s owner; - Design Consultant; - Operation unit. Page 62

65 No. Environmental Social Issues Impact Assessment Mitigation Measures Vietnam Code/Regulation 14/2014/ND-CP. Responsibility the power safety requirement; - Equip fully instruments of labor protection, meet stipulation on working time at area with high electrical field to ensure safety requirements; - Coordinate with the local government at location crossed by the project and communicate, and disseminate knowledge on safety corridors of high voltage power grid to community; and announce them on loudspeaker system and use posters at office of People s committee of commune. 29 Risk of fire, explosion and oil overflow incidents Mitigable - Provide an emergency oil-tank and a fire fighting system; - Provide an automatic and manual fire alarm system; - Check periodically all equipment and tools of fire fighting system; - Check and maintain regularly transformer and auxiliary equipment to meet good operation; - Educate operator on the fire fighting work. - Decree No. 35/2003/ND-CP on 04/4/2003 of the Government; - Circular No. 11/2014/TT-BCA on 12/3/2014 of Ministry of Public Security. - Subproject s owner; - Design Consultant; - Operation unit. 30 Effects due to collapsed tower Mitigable - Carry out measure to reinforce the tower foundation at locations of underground-water or geological condition that it is not guranteed under the provisions of the construction and power sectors. - Consultant will supervise reinforcement of foundation in accordance with the design as approved on quantity, quality and construction stipulations during construction process; - Decree No. 15/2013/ND-CP on 06/02/2013 the Government; - Regulation on power sector. - Subproject s owner; - Design Consultant; - Construction Contractor - Operation unit. Page 63

66 No. Environmental Social Issues Impact Assessment Mitigation Measures - Check carefully welding-gore and tighten bolts before operation; - Design foundation and tower based on the geological investigation result; - Check periodically quality of the project and repair timely the collapsed tower; - Case of the broken wire, relay will automatically switch; and alarm system will operate and then operators will repair timely at site. Vietnam Code/Regulation Responsibility Notes: All mitigation measures will be concretized as terms of construction contract, transportation contract and procurement contract of equipment and materials in duration of construction and operation. Page 64

67 VII. MONITORING PROGRAM 7.1. Objectives It is essential to design the monitoring program and monitoring frequency appropriately to be able to demonstrate both the overall performance of the subproject works as well as the shortterm impact due to peak construction activities. More specifically, as the integral and critical part of the EMP, the environment-monitoring program should have the following objectives: - Determine the actual extent of the impacts. - Control impacts which are generated from construction process and mentioned in the EMP. - Check and supervise implementation of environmental protection solutions during construction based on EMP. - Suggest mitigation measures in case of unexpected impacts. - Suggest to the related parties to coordinate with central and local environmental organizations to solve any pending issues that might arise relating to environmental protection under the scope of the subproject. - Assess the effect of mitigation measures in pre-construction, construction and operation stages and recommend for improvement Environmental Monitoring Plan The environmental monitoring plan of the subproject is described in Table 7.1 below. Page 65

68 Table 7.1. Environmental monitoring plan of the subproject Impact Pre-construction phase 1. The permanent and temporary land acquisition in ROW. 2. Temporary land acquisition. 3. Vegetation cover clearance or cutting down trees. Construction phase Monitored parameter - Compensation and assistance works. - Compensation and return of siteplan. - Clearance technique; - Disposal of cut-down trees. Monitored point - Tower and substation location; - The ROW. - Temporary siteplan during construction - Construction location and along the connection line. - Warehouse and stockpile. Monitoring method - Checking the implementation minutes of compensation and assistance; - Observing and consultating with local residentials. - Checking the implementation minutes of compensation; - Observing and consultating with local residentials. Timing/ frequency of monitoring - During period of compensation and land acquisition. - During period of agreement and compensation; - During return-period of site plan after construction - Observing - From beginning to the last moment. Responsibility - Owner s supervision; - Independent supervision in compensation and land acquisition. - Construction contractor; - Supervision Consultant. - Construction contractor; - Supervision Consultant. 4. Dust and - Dust - Location of site - Observing and - Every week, when - Construction Verification Page 66

69 Impact air pollution from construction and transportation means Monitored parameter contamination at site and transportation road; - Operation condition of construction and transportation machinery. Monitored point and warehouse and stockpile; - Along transportation road. Monitoring method consultating with local residentials; - Checking register license of machinery. Timing/ frequency of monitoring having official acceptance of work. Responsibility contractor; - Supervision Consultant. Verification 5. Noise level and vibration. - Noise level by machinery; - Local resident response to noise from the construction process. - The line section running over residental area. - Observing and consultating with local residents; - Checking register license of machinery. - During activities that may result in high noise level; - Complaints by local residents. - Construction contractor; - Supervision Consultant. 6. Increase of turbidity due to surface water flow - Drainage system, sediment gate, weather condition (season), vegetation cover clearance and slope. - In boudary of substation, along ROW of connection line, near to water resource and slope in region of the subproject. - Observing - During and after heavy rain. - Construction contractor; - Supervision Consultant. 7. Environment - Situation of wastewater at site - At site; - Gathering area of - Observing - Every week, when having official - Construction contractor; Page 67

70 Impact al quality due to wastewater Monitored parameter location; - The tents have been supplied clean water and had sanitary latrines. Monitored point Monitoring method Timing/ frequency of monitoring Responsibility workers. acceptance of work. - Supervision Consultant. Verification 8. Environment al quality due to waste - Domestic waste, construction waste and collection method and discharge - At drainage location, camp and stockpile of waste - Observing - Every week, when having official acceptance of work. - Construction contractor; - Supervision Consultant. 9. Water and soil pollution due to hazardous waste - Maintenance and repair activities for construction means - Construction means gathering area. - Observing - During maintenance and repair period of construction means - Construction contractor; - Supervision Consultant. 10. Erosion and eboulement due to excavation and backfill - Situation of erosion and eboulement at the site location - Substation and tower foundation location; - Canals near to construction location. - Observing and consultating with local residents - During excavation and backfill process of tower foundation. - Construction contractor; - Supervision Consultant. 11. Traffic interruption due to - Number of transportation - At access roads of stockpiles; - Observing and consultating with - During gathering materials; - Construction contractor; Page 68

71 Impact construction activities 12. Effects on local traffic system quality 13. Safety and health from camps and disease 14. Conflict between construction workers and local people Monitored parameter means; - Traffic condition at the intersected location with the traffic roads. - Weight vehicles on the local roads; - Situation of roads surface, density of traffic. - Sanitation situation and hygiene of worker's camp; - Sanitary situation at stockpiles. - Worker and their livingcondition. Monitored point - Traffic section at the intersected location. - Along the transportation route. - Worker's camps; - Stockpiles's location. Monitoring method local residents - Observing and consultating with local residents - Observing; - Consulting with workers. - Worker's camps. - Observing; - Consulting with worker and local residents Timing/ frequency of monitoring - During constructing at the intersected locations. - Every week, when transporting material and equipment to the site; - Completion of construction. - Every week, when official acceptance of work. - Every week, when official acceptance of work. Responsibility - Supervision Consultant. - Construction contractor; - Supervision Consultant. - Construction contractor; - Supervision Consultant. - Construction contractor; - Supervision Consultant. 15. Risks for - Safety - At site and - Observing; - Every week, when - Construction Verification Page 69

72 Impact worker and local people. Monitored parameter condition at site; - Complying with regulation of labor safety Monitored point worker s camp. Monitoring method - Consulting with worker and local residents; - Checking site s diary Timing/ frequency of monitoring official acceptance of work. Responsibility contractor; - Supervision Consultant. Verification Operation phase 16. Domestic waste of operator - Situation of collection, storage and discharge - At substation s site - Observing; - Checking receipt of waste collection; - Consulting with operator. - 3 months/time - Operation unit. 17. Environment al quality due to hazardous waste - Situation of collection, storage and transfer of hazardous waste - At substation s site - Observing; - Checking documents in transfer the hazardous waste; - Consulting with operator. - 3 months/time - Operation unit. 18. Noise of transformer - Noise level - Complaints by local residents. - Observing and consulting with local residens; - Noise meter. - Complaint - Operation unit. Page 70

73 Impact 19. Impact on health due to high magnetic field Monitored parameter - Magnetic field. Monitored point - At house nearest to the ROW; - At house nearest to the substation. Monitoring method - Consulting with local residents; - Electro magnetic meter. Timing/ frequency of monitoring - 6 months/time; - Complaint of local people. Responsibility - Operation unit. Verification 20. Accident due to electricity - Safety condition of high voltage power grid; - Frequency of check and maintenance of safety condition - At substation and surrouding area; - At ROW. - Observing; - Consulting with local residents and operator; - Checking procedures of safety and implementation document - 6 months/time; - Complaint of local people. - Operation unit. 21. Fire hazard and oil-overflow of the transformer - Safety condition; - Available situation to treat and overcome risk - At substation, location of transformer and control room - Observing; - Consulting with operator; - Checking procedures for prevention and treatment and document of implementation - 3 months/time. - Operation unit. Page 71

74 Impact 22. Hazard on collapsed tower Monitored parameter - Loading situation of tower and foundation. Monitored point - At tower location. Monitoring method - Ovserving; - Checking. Timing/ frequency of monitoring - 3 months/time; - When a storm will be proposed to happen. Responsibility - Operation unit. Verification Page 72

75 VIII. EMP IMPLEMENTATION ARRANGEMENTS 8.1. EMP Implementation Arrangement Proper environmental management during construction requires the involvement of several stakeholders and agencies, each with different roles and responsibilities including: NPT, NPMB, DONREs (Provincial Department of Natural Resources and Environment) of Bac Ninh province and Ha Noi city, the Contractors, the Construction Supervision Consultant, and local communities. To ensure effective implementation of the EMP, the following actions will be carried out during the implementation of the subproject: a) During the detailed design and tender documentation making - During the detailed design of technical specifications and preparation of bidding contract documents for each contract, the technical design consultant will incorporate into these bidding and contractual documents the parts of the EMP specific to that contract, as well as the specific measures identified in the EMP. - In preparing the bidding and contract documents, make an effort to ensure that the contractors are aware of the safeguard obligation and commit to comply. The environmental and social specifications needs to be included in the bidding and contractual documents. b) During the course of preconstruction and construction NPMB will assign the Construction Supervising Consultant (CSC) and/or field engineer to be responsible for supervision of safeguard performance of contractor on a daily basis. A generic Terms of Reference (TOR) is provided in Appendix 2. CSC and/or field engineers will carry out, but not limited to, the following tasks: - Before the commencement of the construction, confirm that all compensation for land and facilities are provided and relocation and/or land acquisition/donation has been completed. - Review and approve Site (SEMP) to be prepared by contractor before the commencement of the construction. - Closely supervise the implementation of the EMP throughout the construction period. - Confirm the compliance with the agreed environmental plan and inspect any damages incurred by the contractor. If necessary, prepare an order to compensate/restore the construction sites as specified in the contracts. Contractor safeguard performance will be included in the subproject progress report. The role and responsibilities of relevant parties in the implementation of EMP are described in the following table: Table 8.1. Responsibility for EMP implementation by different stakeholders Community/ agencies Subproject Implementing Agency: EVNNPT Responsibilities - EVNNPT will be responsible for overseeing the subproject implementation including ESMF implementation and environmental performance of the subproject. - The NPMB will be responsible for monitoring the subproject implementation, including environmental compliance of the project. Page 73

76 Community/ agencies Subproject Implementing Agency: NPMB Environmental Unit EU (EU) under NPMB Construction Supervision Consultant (CSC) and/or Field Engineer Responsibilities SPMB will have the final responsibility for ESMF implementation and environmental performance of the subproject during both the construction and operational phases. - The NPMB is responsible for fostering effective coordination and cooperation between contractor, local authorities, and local communities during construction phase. NPMB will be assisted by the environmental staff, and CSC/or field engineer. - Specifically NPMB will: i) closely coordinate with local authorities in the participation of the community during subproject preparation and implementation; ii) monitor and supervise EMP implementation including incorporation of EMP into the detailed technical designs and bidding and contractual documents; iii) ensure that an environmental management system is set up and functions properly; iv) be in charge of reporting on EMP implementation to EVNNPT and the World Bank. - In order to be effective in the implementation process, NPMB will establish an Environmental Unit with at least an environmental staff to help with the environmental aspects of the project. - The EU is responsible for monitoring the implementation of WB s environmental safeguard policies in all stages and process of the subproject. Specifically, this unit will be responsible for: i) reviewing the subproject EIAs and EMPs prepared by consultants to ensure that they follow the project ESMF and meet the government and the Bank requirements; ii) helping NPMB incorporate EMPs into the detailed technical designs and civil works bidding and contractual documents; iii) helping NPMB incorporate responsibilities for EMP monitoring and supervision into the TORs, bidding and contractual documents for CSC; iv) providing relevant inputs to the consultant selection process; v) reviewing reports submitted by the CSC; vi) conducting periodic site checks; vii) advising SPMB on solutions to environmental issues of the project; and viii) preparing environmental performance section on the progress and review reports to be submitted to EVNNPT, the Bank, and the local authorities if requested. - The CSC will be responsible for routine supervising and monitoring all construction activities and for ensuring that Contractors comply with the requirements of the contracts and the EMP. The CSC shall engage sufficient number of qualified staff (e.g. Environmental Engineers) with adequate knowledge on environmental protection and construction project management to perform the required duties and to supervise the Contractor s performance. - The CSC also assists NPMB in reporting and maintaining close coordination with the local community. - Based on the approved EMP and environmental specifications/requirements in the bidding and contractual documents, Page 74

77 Community/ agencies Contractor Local community Mass organizations Province and District People s Committees (PPCs/DPCs), Provincial DONRE Responsibilities the Contractor is responsible for establishing a site-specific EMP for each construction site area, submit the plan to the NPMB and CSC for review and approval before commencement of construction. In addition, it is required that the Contractor get all permissions for construction (traffic control and diversion, excavation, labor safety, etc. before civil works) following current regulations. - The contractor is required to appoint a competent individual as the contractor s on-site Safety and Environment Officer (SEO) who will be responsible for monitoring the contractor s compliance with the EMP requirements and the environmental specifications. - Take actions to mitigate all potential negative impacts in line with the objective described in the EMP. - Actively communicate with local residents and take actions to prevent disturbance during construction. - Ensure that all staff and workers understand the procedure and their tasks in the environmental management program. - Report to the NPMB on any difficulties and their solutions. - Report to local authority and NPMB if environmental accidents occur and coordinate with agencies and keys stakeholders to resolve these issues. - Community: According to Vietnamese practice, the community has the right and responsibility to routinely monitor environmental performance during construction to ensure that their rights and safety are adequately protected and that the mitigation measures are effectively implemented by contractors and the PMB. In case of unexpected problems, they will report to CSC/PMB. - These organizations could play a role as a bridge between the PPC/DPC, communities, contractors, and PMB by assisting in community monitoring. - Mobilizing communities participation in the subproject, providing training to communities. - Participating in solving environmental problems if any. - Oversee implementation of subprojects under recommendations of DONRE and PMB to ensure compliance of Government policy and regulations. - DONRE is responsible for monitoring the compliance with the Government environmental requirements EMP Implementation Reporting Requirement The safeguard performance will be included in the subproject and Project progress reports. PMBs with assistance from the CSC will include safeguard performance at subproject level to PMBs periodically. At the project level, EVNNPT will prepare safeguard performance report Page 75

78 twice per year for submission to the World Bank describing the Project progress and compliance with the ESMF and other safeguard requirements. The reporting requirement is described in Table 8.2 below. Table 8.2. Reporting Procedures Report Prepared by Submitted to Frequency of Reporting 1 Contractor to the Employer NPMB Once before construction commences and monthly thereafter 2 Construction Supervision consultant (CSC) PMB Weekly and monthly 4 Community Monitoring PMB When the community has any complaint about the subproject safeguards implementation 5 PMBs EVNNPT Six-monthly 6 EVNNPT WB Six-monthly PMBs report on environmental performance/compliance of the subproject should be included in the progress report submitted to the NPT before each project implementation support mission and must include sufficient information on: i) preparation and disclosures of environmental safeguards instruments for subprojects; ii) incorporation of new subproject EMPs in the bidding and contractual documents; iii) monitoring and supervision of EMP implementation by the contractor, the construction supervision engineer, and the PCs; iv) any challenges in safeguard implementation, solutions, and lessons learned Capacity Building for EMP Implementation Training plan includes: - Training program of EVN: Internal training about implementation of on-site environmental management, six-month/annual environmental reports. Mitigation measures for corrective actions of unexpected environmental impacts which are different from predictions in EMP also mentioned in the program. - Training program of EVNNPT: for local Power Companies and some local residents about: + Safety: Periodical training of safety, grid maintenance; + Supervision method and EMP report: for relevant parties of province and districts where subproject is located. The training also gives guidelines for corporation with community in environmental management; + Environmental management, hazardous waste management. + Proposed training of environmental management program is shown in table 8.3. Table 8.3. Proposed training of environmental management program No. Training content Period Responsibility of EVN 1 On-site environmental management, periodical environmental reports submitted to EVNNPT and WB, other tasks relevant to environmental management of the Twice a year Page 76

79 No. Training content Period subproject. Responsibility of EVN NPT 2 Safety, maintenance of transmission line. Yearly 3 Environmental management, hazardous waste management for substation and transmission line. 4 Supervision method and EMP report in accordance with TEP s project. Table 8.4. Cost estimate for training program No. Training Cost (VND) CONSTRUCTION PHASE 1 Yearly training for interested parties conducted by EVN 2 Workshop for sharing experiences of Environment Impact Assessment and EMP implementation Yearly Yearly Included in operation cost of EVN. NPMB will pay for expenditures of accommodation, travelling for participants Participants: 3 persons of SPMB of EVNNPT 3 persons x 2 days x VND7,000,000/person = VND42,000,000 Included in operation cost of EVN Participants: 2 persons x 2 days x VND 7,000,000/person = VND 28,000, EMP implementation Participants: 2 persons of SPMB Sub-total cost for construction phase OPERATION PHASE 4 Safety training conducted by PTC1 (Normally implemented by the provincial operation management unit) Grand total for life cycle of subproject 2 persons x 2 days x VND5,000,000/person= VND 20,000,000 VND90,000,000 Included in operation cost of the operation management unit. 8 people x 1 day x VND 1,000,000/person x 20 years (Life cycle of subproject) = VND 160,000,000 IX. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE 9.1. Public Consultation During the subproject preparation stage, the following activities were accomplished: Activity 1: Investigation and discussion with local authorities about the route location. VND250,000,000 Page 77

80 Activity 2: Site investigation, Preparation of Environmental Impact Assessment and for the subproject. Activity 3: Organization of public consultation The meetings with local authorities and local people effected were carried out at the offices of Kim Lu Commune People Committee, Soc Son district, Ha Noi city, Hoa Tien and Yen Phu Commune People Committee, Cho town, Yen Phong district, Bac Ninh province from September 11, 2014 to September 12, There are 35 persons and 72 persons, who were representing the local authorities and the affected people of Kim Lu commune, Soc Son district, Ha Noi city, and Hoa Tien and Yen Phu communes, Cho town, Yen Phong district, Bac Ninh province, respectively, participated in the public consultation meeting. Representative of Commune/town People Committee were presided and managed at the meetings. Representative of PECC2 was presented the main investment items, information on environment, environmental protection solutions, policies on compensation, clearance and power safety of the subproject to representatives of local authorities and the affected people in region of the subproject. Parties were discussed environment and social issues and representative of PECC2 and the subproject s owner were responded all their ideas and provided more relevant information. The ideas of public consultation at the meeting are summarized as follows: Table 9.1: Summary of ideas of public consultation meeting No. Location Where Consultation Took Place, Date and Time Participants Summary of Issued or Concerns Discussed/Raised How Concerns were Taken into Account or Why Not 1 - Location: Cho town, Yen Phong district, Bac Ninh province. - Time: 8:30 a.m on 11/9/2014 Local Authority Representatives and social organizations: 06 persons Affected people Representatives: 45 persons Opinions of local people: - Subproject will construct in a large area, so the construction has or has not impact on irrigation canal. If any, it should provide measures to restore the irrigation canal and to ensure irrigation for the surrounding paddy field; - Substation and transmission line has or has not impacts on rice productivity. - Some of paddy fields can be acquired with a large area and the remaining area is small, which can not cultivate on them, so the subproject has or has not compensation for the remaining area. - Affected area should be measured exactly to properly Owner/Consultant s answers: - Substation construction will fill a part of irrigation canal, however, the part of the canal will be backfilled surrounding the substation fence to ensure impacts on irrigation condition of paddy fields according to the design. - Substation and transmission line will be designed in accordance with power safety regulations. The current substation and transmission line has existed in paddy field but it does not impact on rice productivity. - For paddy field has a small area after acquisition, the subproject s owner will consider, measure its area and he will propose to Page 78

81 No. Location Where Consultation Took Place, Date and Time Participants Summary of Issued or Concerns Discussed/Raised How Concerns were Taken into Account or Why Not compensate the local people damages; - Compensation has or has not paid damages on rice during construction; and how is compensation level? Opinions of local authorities: - Unify environmental management plan of the subproject s owner as reported in the meeting. It is required to fully execute environmental protection measures in phases of construction and operation as well. - Unify compensation alternative according to the Government s stipulation. The subproject s owner is required to inventory in details and properly compensate damages for affected people. Conclusion: Unify alternatives of environmental protection, compensation and assistance of the subproject. The subproject s owner should cooperate with local authority and negotiate with local people to unify proper compensation. Compensation Council for acquisition and compensation or assistance. - During RP s implementation, the inventory will be carried out after the cut-off date and properly compensate for affected people; - All damages during construction will be compensated properly by the construction contractor. 2 - Location: Yen Phu commune, Yen Phong district, Bac Ninh province. - Time: 2:00 p.m on Local Authority Representatives and social organizations: 12 persons Affected people Representatives: 14 persons Opinions of local people: - It is required to construct after harvesting crop to avoid affecting to rice productivity; - Towers should design in the large paddy field to reduce impacts on household; it should detail the affected data; Owner/Consultant s answers: - Construction schedule will consider to execute after harvesting crop. All damages will be properly compensated in case of the urgent construction according to the government s policy. Page 79

82 No. Location Where Consultation Took Place, Date and Time Participants Summary of Issued or Concerns Discussed/Raised 11/9/ Local people always meet the Government s regulation for country s development but compensation shall execute according to the stipulations of province. - Land is acquired with a large area, and the remaining land area is small; so it should consider to compensate the remaining area when it can not use. - Compensation will execute when damages caused duration construction. Opinions of local authorities: - Unify to construct the subproject. Implementation schedule meets design and in time. - Construction method should provide to avoid affecting to local people s produce. Temporary site shall restore as the original situation. - Subproject must meet the government s policies on compensation and resettlement. Conclusion: Unify to construct subproject. The subproject should design tower location properly to reduce damages of household. It must restore all damages if affected during construction. It is unified compensation and assistance in accordance with the government s regulation. It must detail impacts to How Concerns were Taken into Account or Why Not - Duration of RP s implementation, it shall detail data of damages for compensation and assistance; - Subproject has designed and chosen the optimal alternative to minimize impacts on household. - After recovery, the remaining paddy fields are too small and it can not cultivate. The owner shall consider to propose with Compensation Council to acquire, compensate and assist them. - Construction contractor shall compensate properly all damages in construction duration. - Construction shall meet schedule and design of subproject. - Construction contractor is required by the owner to minimize impacts in construction duration and shall restore all temporary sites as the original situation. Page 80

83 No. Location Where Consultation Took Place, Date and Time Participants Summary of Issued or Concerns Discussed/Raised How Concerns were Taken into Account or Why Not compensate properly. 3 - Location: Hoa Tien commune, Yen Phong district, Bac Ninh province. - Time: 1:00 p.m on 12/9/2014 Local Authority Representatives and social organizations: 05 persons Affected people Representatives: 8 persons Opinions of local people: - Construction shall ensure safe condition and restore site as the original situation; - Local people unify compensation unit according to the Government s regulations. The owner shall cooperate publicly with local authority and affected people compensation policies. - Opinions of local authorities: - The subproject management board should strictly cooperate with local authority to construct as design and determine landmark of transmission line route. Implementation schedule shall be reasonable to minimize damages; - How does construction method to cultivation will not affect local people. Implementation schedule shall announce local people for their arrangement in production. - It shall compensate reasonably temporary impacts for households. Compensation will complete before construction. Conclusion: People s Committee unify to construct the subproject. Compensation will be done according to the Government s unit price and assistance will be done under the provincial stipulation. Crop will compensate in accordance with unit price at Owner/Consultant s answers: - Contractor shall be submitted a construction method for the owner s approval before constructing the subproject. The method is to ensure safe and environment in construction duration. Implementation schedule shall be reasonable in order to minimize impacts during construction and the contractor shall restore the temporary site as the original situation; - RP s implementation should cooperate with local authority and affected people. Compensation alternative, RP s report and implementation schedule shall be disclosed at office of commune People s Committee; - Subproject is the national electrical work so the subproject must be done in accordance with the design s approval; - Landmark will be measured, determined specifically during RP s implementation; - Temporary impacts will be compensated properly. Compensation will be done before leveling the subproject s site; - Compensation unit price will be updated during RP s implementation; - The remaining paddy fields Page 81

84 No. Location Where Consultation Took Place, Date and Time Participants Summary of Issued or Concerns Discussed/Raised How Concerns were Taken into Account or Why Not acquisition time. The owner should acquire the remaining area if it is too small. is too small and it can not cultivate. The owner shall consider to propose with Compensation Council to acquire, compensate and assist them. 4 - Location: Kim Lu commune, Soc Son district, Ha Noi city. - Time: 3:00 p.m on 12/9/2014 Local Authority Representatives and social organizations: 12 persons Affected people Representatives: 5 persons Opinions of local people: - Local people unify to construct a subproject but the subproject shall propose environmental protection measures properly. Opinions of local authorities: - Tower foundation location shall determine specifically on map. The owner shall cooperate with local officials to determine exactly affected household by the subproject; - Local authority and people agree construction of a subproject but the owner shall determine and announce exactly affected households; - Construction contractor is responsible for compensation and assistance according to the Government s policy. Conclusion: Local authority and people unify construction of a subproject. The owner should coordinate with local authority to protect environment, compensate, survey and inventory damages. And there is a specific compensation policy to facilitate a dissemination to the local people. Owner/Consultant s answers: - Environmental protection plan is preparing in this phase and it will be disclosed information at office of commune People s Committee. - Tower foundation location has been determined in RP s implementation duration. The owner will dispatch an official to coordinate with local authority for determining damages and affected households. The result of inventory will be basis of compensation and assistance; - RP s report is prepared on the basis of the Government and WB s policy; the report will be disclosed at office of commune Committee. People s Beside the above-mentioned issues, subproject owner and Consultant also agree to receive all comments and will consider and update it to EMP report. Activity 4: Review and update the EMP according to collected comments. Continue to receive Page 82

85 feedback from affected households. In addition, public consultation of affected households will continue upon the detailed design approval. During the subproject construction phase, a supervising construction consultant will be hired to monitor the implementation of EMP. Page 83

86 9.2. Information Disclosure Disclosure of information was carried out in accordance with the World Bank requirements. The disclosure is as follows: - The draft EMP of the subproject in Vietnamese will propose to disclose in March of 2015 at the office of People Committee of affected communes and districts in order for local people and institutions to approach and search. - Also, the draft EMP in both Vietnamese and English versions will disclose at the Vietnam Development Information Center (VDIC, 63 Ly Thai To St., Hanoi City) in March of 2015 for relevant organizations to read, inquire and give their opinions about the report. - The final EMP of the subproject in English will disclose at the Bank s InfoShop in Washington DC in April of Page 84

87 APPENDICES Appendix1: Map of subproject location compared with natural reserves The subproject locates in region of Ha Noi city and Bac Ninh province. Page 85

88 Page 86

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL POWER TRANSMISSION CORPORATION ---------------------------------------------------------------

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL POWER TRANSMISSION CORPORATION ---------------------------------------------------------------

More information

NORTH POWER CORPORATION Electric Network Project Management Board RESETTLEMENT PLAN (RP) SUBPROJECT:

NORTH POWER CORPORATION Electric Network Project Management Board RESETTLEMENT PLAN (RP) SUBPROJECT: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Sub-project: Improving grid medium, low voltage NORTH POWER COORATION Electric Network

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN Public Disclosure Authorized NATIONAL POWER TRANMISSION CORPORATION Northern Power Projects Management Board ------------------------------- Public Disclosure Authorized TRANSMISSION EFFICIENCY PROJECT

More information

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Copy Public Disclosure Copy Date ISDS Prepared/Updated: 04-Apr-2014

More information

The Northern Delta Transport Development Project (NDTDP) Environmental Management Process Framework For Phase 2 Investments

The Northern Delta Transport Development Project (NDTDP) Environmental Management Process Framework For Phase 2 Investments Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The Northern Delta Transport Development Project (NDTDP) Environmental Management Process

More information

NATIONAL POWER TRANMISSION CORPORATION. Northern Power Projects Management Board ENVIRONMENTAL IMPACT ASSESSMENT

NATIONAL POWER TRANMISSION CORPORATION. Northern Power Projects Management Board ENVIRONMENTAL IMPACT ASSESSMENT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL POWER TRANMISSION CORPORATION Northern Power Projects Management Board -------------------------------

More information

Initial Environmental Examination. Multitranche Financing Facility Socialist Republic of Viet Nam: Power Transmission Investment Program

Initial Environmental Examination. Multitranche Financing Facility Socialist Republic of Viet Nam: Power Transmission Investment Program Power Transmission Investment Program (RRP VIE 42039) Initial Environmental Examination Project Number: 42039-034 November 2011 Multitranche Financing Facility Socialist Republic of Viet Nam: Power Transmission

More information

Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL POWER TRANSMISSION CORPORATION SOUTHERN POWER PROJECT MANAGEMENT BOARD -------------------------------

More information

NATIONAL POWER TRANSMISSION CORPORATION REPORT OF ENVIRONMENTAL IMPACT ASSESSMENT (FINAL)

NATIONAL POWER TRANSMISSION CORPORATION REPORT OF ENVIRONMENTAL IMPACT ASSESSMENT (FINAL) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL POWER TRANSMISSION CORPORATION SOUTHERN VIETNAM POWER PROJECT MANAGEMENT BOARD

More information

SUBPROJECT: IMPROVEMENT AND UPGRADING OF THE CAI LAY- CAO LANH 220kV TRANSMISSION LINE

SUBPROJECT: IMPROVEMENT AND UPGRADING OF THE CAI LAY- CAO LANH 220kV TRANSMISSION LINE Public Disclosure Authorized NATIONAL POWER TRANSMISSION CORPORATION SOUTHERN POWER PROJECT MANAGEMENT BOARD ------------------------------- Public Disclosure Authorized Public Disclosure Authorized ENVIRONMENTAL

More information

REPORT ON ENVIRONMENTAL IMPACT ASSESSMENT

REPORT ON ENVIRONMENTAL IMPACT ASSESSMENT Ha Nam Province People's Committee Phu Ly City People's Committee Public Disclosure Authorized Public Disclosure Authorized MEDIUM CITIES DEVELOPMENT PROJECT - PHU LY CITY SUBPROJECT, HA NAM PROVINCE REPORT

More information

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Resettlement Due Diligence Report April 2016 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Ho Chi Minh City Power Corporation for the Asian Development Bank. Resettlement

More information

VIETNAM ELECTRICITY TRUNGSON HYDROPOWER COMPANY LIMITED ENVIRONMENTAL MANAGEMENT PLAN

VIETNAM ELECTRICITY TRUNGSON HYDROPOWER COMPANY LIMITED ENVIRONMENTAL MANAGEMENT PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Subproject: Mai Chau 110 kv substation and 35 kv power line supply for construction of

More information

ENVIRONMENTAL IMPACT ASSESSMENT

ENVIRONMENTAL IMPACT ASSESSMENT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION ---------------------------------------------------------------

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized TABLE OF CONTENTS 1. INTRODUCTION... 5 2. LEGAL FRAMEWORKS... 5 2.1. Vietnamese Legislations...

More information

Lloydminster to Spruce Lake 138kV Transmission Line Projects

Lloydminster to Spruce Lake 138kV Transmission Line Projects Lloydminster to Spruce Lake 138kV Transmission Line Projects Preferred Corridor Presentation June 2017 SaskPower continues to invest in the province s electricity system to ensure we have the infrastructure

More information

Summary of Preliminary Study Result for Technical Cooperation Project. Date: 2008/10/8

Summary of Preliminary Study Result for Technical Cooperation Project. Date: 2008/10/8 Summary of Preliminary Study Result for Technical Cooperation Project Date: 2008/10/8 1. Full title of the Project The Project on Integrated UMRT and Urban Development for Hanoi 2. Type of the study Feasibility

More information

SUBPROJECT: Rehabilitation of transmission overheadline 180, 181 E1.1 Dong Anh (Section from pole No. 70 to E1.15)

SUBPROJECT: Rehabilitation of transmission overheadline 180, 181 E1.1 Dong Anh (Section from pole No. 70 to E1.15) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized HA NOI POWER CORPORATION ------------------------------------------------------------

More information

THE GOVERNMENT THE SOCIALIST REPUBLIC OF VIETNAM Independence Freedom Happiness No. 64/2012/ND-CP Hanoi, September 04, 2012

THE GOVERNMENT THE SOCIALIST REPUBLIC OF VIETNAM Independence Freedom Happiness No. 64/2012/ND-CP Hanoi, September 04, 2012 THE GOVERNMENT THE SOCIALIST REPUBLIC OF VIETNAM ------- Independence Freedom Happiness --------------- No. 64/2012/ND-CP Hanoi, September 04, 2012 DECREE ON CONSTRUCTION PERMIT Pursuant to the Law on

More information

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Social Monitoring Report #1 Semestral Report Project Number: 46391-001 August 2017 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Ho Chi Minh Power Corporation for the

More information

REGULATIONS OF ENVIRONMENTAL MANAGEMENT OF THE CONSTRUCTION PROJECTS Dr. Pham Van Bo Vice president Academy of Managers for Construction and Cities Ministry of Construction - Vietnam List of abbreviations

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB4343 Project Name. VIETNAM: Haiphong Urban Transport Project Region

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB4343 Project Name. VIETNAM: Haiphong Urban Transport Project Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB4343 Project Name VIETNAM:

More information

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project ENVIRONMENTAL MONITORING REPORT Project Number: 46391-001 March 2018 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Hanoi City Power Corporation, Electricity of Vietnam

More information

QUANG NGAI PROVINCE PEOPLE S COMMITTEE. Quang Ngai Provincial Project Management Unit of Construction Works for Agriculture & Rural Development

QUANG NGAI PROVINCE PEOPLE S COMMITTEE. Quang Ngai Provincial Project Management Unit of Construction Works for Agriculture & Rural Development SFG3446 V5 REV QUANG NGAI PROVINCE PEOPLE S COMMITTEE Quang Ngai Provincial Project Management Unit of Construction Works for Agriculture & Rural Development ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (ESMP)

More information

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project ENVIRONMENTAL MONITORING REPORT Project Number: 46391-001 January 2018 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Hanoi City Power Corporation, Electricity of Vietnam

More information

VIE: Mong Duong 1 Thermal Power Plant

VIE: Mong Duong 1 Thermal Power Plant 7 th Independent Monitoring Report September 2011 VIE: Mong Duong 1 Thermal Power Plant Prepared by the Development Research and Consultancy Center (DRCC) for Viet Nam Electricity (EVN) Thermal Power Project

More information

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Subproject NORTH POWER CORPORATION Electric Network Project Management Board -------------------------------

More information

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Subproject NORTH POWER CORPORATION Electric Network Project Management Board -------------------------------

More information

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project NORTH POWER CORPORATION Electric Network Project Management Board -------------------------------

More information

NATIONAL POWER TRANMISSION CORPORATION Northern Power Projects Management Board ENVIRONMENTAL IMPACT ASSESSMENT

NATIONAL POWER TRANMISSION CORPORATION Northern Power Projects Management Board ENVIRONMENTAL IMPACT ASSESSMENT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL POWER TRANMISSION CORPORATION Northern Power Projects Management Board -------------------------------

More information

ENVIRONMENTAL MANAGEMENT PLAN (EMP)

ENVIRONMENTAL MANAGEMENT PLAN (EMP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized MINISTRY OF TRANSPORT DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 June

More information

Ex-ante Project Evaluation

Ex-ante Project Evaluation Ex-ante Project Evaluation 1. Name of project Country: Socialist Republic of Vietnam Name of project: Hai Phong City Environmental Improvement Project (II) L/A signing date: March 31, 2009 Loan amount:

More information

ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (ESMP)

ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (ESMP) SFG3446 V1 REV BINH DINH PROVINCIAL PEOPLE S COMMITTEE BINH DINH PMU FOR CONSTRUCTION INVESTMENT WORKS OF AGRICULTURE AND RURAL DEVELOPMENT --------------o0o-------------- ENVIRONMENTAL AND SOCIAL MANAGEMENT

More information

SEMI-ANNUAL ENVIRONMENTAL MONITORING REPORT. VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

SEMI-ANNUAL ENVIRONMENTAL MONITORING REPORT. VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project SEMI-ANNUAL ENVIRONMENTAL MONITORING REPORT Project Number: 46391-001 October 2017 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Hanoi City Power Corporation, Electricity

More information

Japanese ODA loan. Ex-ante Evaluation

Japanese ODA loan. Ex-ante Evaluation Japanese ODA loan Ex-ante Evaluation 1. Name of the Project Country: The Socialist Republic of Viet Nam Project: North-South Expressway Construction Project (Ben Luc Long Thanh Section)(II) L/A signed

More information

ENVIRONMENTAL MANAGEMENT PLAN (EMP)

ENVIRONMENTAL MANAGEMENT PLAN (EMP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized VIETNAM ELECTRICITY NORTH POWER CORPORATION Electric Network Project Management Board

More information

MOIT FiT Circular No. 02 Decision No. 39

MOIT FiT Circular No. 02 Decision No. 39 Renewable Energy Vietnam Client Alert January 2019 For further information, please contact: Fred Burke +84 28 3520 2628 frederick.burke@bakermckenzie.com Dang Chi Lieu +84 24 3936 9341 chilieu.dang@bakermckenzie.com

More information

Summary of Environmental and Social Consideration in Development Study (Preparatory Study)

Summary of Environmental and Social Consideration in Development Study (Preparatory Study) Summary of Environmental and Social Consideration in Development Study (Preparatory Study) 1. Full title of the Project The Study on Integrated Development Strategy for Danang City and Its Neighboring

More information

VIE: Power Transmission Investment Program, Tranche 1 220kV Song May-Uyen Hung Transmission Line

VIE: Power Transmission Investment Program, Tranche 1 220kV Song May-Uyen Hung Transmission Line Environmental Monitoring Report Semestral Report July to December 2014 VIE: Power Transmission Investment Program, Tranche 1 220kV Song May-Uyen Hung Transmission Line Prepared by the Southern Vietnam

More information

Europe and Central Asia Region Capacity Development Trust Fund

Europe and Central Asia Region Capacity Development Trust Fund Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Europe and Central Asia Region Capacity Development Trust Fund RP1439 Draft Terms of

More information

VIE: Power Transmission Investment Program - Tranche 2 220kV Cau Bong-Hoc Mon-Branches to Binh Tan Transmission Line

VIE: Power Transmission Investment Program - Tranche 2 220kV Cau Bong-Hoc Mon-Branches to Binh Tan Transmission Line Environmental Monitoring Report 4th Quarterly Report February 2016 VIE: Power Transmission Investment Program - Tranche 2 220kV Cau Bong-Hoc Mon-Branches to Binh Tan Transmission Line Prepared by Southern

More information

ENVIRONMENTAL MANAGEMENT PLAN (EMP)

ENVIRONMENTAL MANAGEMENT PLAN (EMP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Sub-project: Nhon Hoi 110 kv substation and branch line VIETNAM ELECTRICITY CENTRAL POWER

More information

Japanese ODA. Ex-ante Evaluation

Japanese ODA. Ex-ante Evaluation Japanese ODA Ex-ante Evaluation 1. Name of the Project Country: The Socialist Republic of Vietnam Project: North-South Expressway Construction Project (Da Nang Quang Ngai Section) (I) (II) (III) L/A signed

More information

MINISTRY OF TRANSPORT DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 =================

MINISTRY OF TRANSPORT DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 ================= Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized MINISTRY OF TRANSPORT DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 =================

More information

Sri: Sustainable Power Sector Support Project

Sri: Sustainable Power Sector Support Project Environmental Monitoring Report June 2015 Sri: Sustainable Power Sector Support Project Prepared by Ceylon Electricity Board for the Asian Development Bank. This environmental monitoring report is a document

More information

SAMOA ENVIRONMENTAL AND SOCIAL SCREENING AND ASSESSMENT FRAMEWORK FOR A POST-TSUNAMI RECOVERY PROJECT

SAMOA ENVIRONMENTAL AND SOCIAL SCREENING AND ASSESSMENT FRAMEWORK FOR A POST-TSUNAMI RECOVERY PROJECT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SAMOA ENVIRONMENTAL AND SOCIAL SCREENING AND ASSESSMENT FRAMEWORK FOR A POST-TSUNAMI

More information

VIE: POWER TRANSMISSION INVESTMENT PROGRAM, TRANCHE 3 Loan: 3374-VIE

VIE: POWER TRANSMISSION INVESTMENT PROGRAM, TRANCHE 3 Loan: 3374-VIE ENVIRONMENTAL MONITORING REPORT Project Number: 42039-036 Period: April - June, 2017 VIE: POWER TRANSMISSION INVESTMENT PROGRAM, TRANCHE 3 Loan: 3374-VIE COVERING THE FOLLOWING SUBPROJECTS: (i) 500kV My

More information

Public Disclosure Authorized EXECUTIVE SUMMARY

Public Disclosure Authorized EXECUTIVE SUMMARY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized EXECUTIVE SUMMARY Introduction Georgia is an important transport corridor connecting

More information

VIE: Northern Power Transmission Expansion Sector Project

VIE: Northern Power Transmission Expansion Sector Project Environmental Monitoring Report Semestral Report July-December 2012 VIE: Northern Power Transmission Expansion Sector Project Prepared by the Local Implementation consultant (LIC), with information mostly

More information

THE UNITED REPUBLIC OF TANZANIA MINISTRY OF AGRICULTURE FOOD SECURITY AND COOPERATIVES

THE UNITED REPUBLIC OF TANZANIA MINISTRY OF AGRICULTURE FOOD SECURITY AND COOPERATIVES Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized THE UNITED REPUBLIC OF TANZANIA MINISTRY OF AGRICULTURE FOOD SECURITY AND COOPERATIVES

More information

VIE: Power Transmission Investment Program, Tranche 1 220kV Song May Uyen Hung Transmission Line

VIE: Power Transmission Investment Program, Tranche 1 220kV Song May Uyen Hung Transmission Line Environmental Monitoring Report Quarterly Report October to December 2014 VIE: Power Transmission Investment Program, Tranche 1 220kV Song May Uyen Hung Transmission Line Prepared by the Southern Vietnam

More information

ENVIRONMENTAL MANAGEMENT PLAN (EMP)

ENVIRONMENTAL MANAGEMENT PLAN (EMP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized MINISTRY OF TRANSPORT DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 June

More information

Terms of Reference I. PROJECT MANAGEMENT SUPPORT AND CAPACITY DEVELOPMENT CONSULTANTS

Terms of Reference I. PROJECT MANAGEMENT SUPPORT AND CAPACITY DEVELOPMENT CONSULTANTS Terms of Reference I. PROJECT MANAGEMENT SUPPORT AND CAPACITY DEVELOPMENT CONSULTANTS A. Background 1. The Government of the Socialist Republic of Viet Nam, has requested a loan and grant from the Asian

More information

Multitranche Financing Facility Socialist Republic of Viet Nam: Power Transmission Investment Program

Multitranche Financing Facility Socialist Republic of Viet Nam: Power Transmission Investment Program [VIE MFF0066 PFR2] POWER TRANSMISSION INVESTMENT PROGRAM Initial Environmental Examination July 2012 Multitranche Financing Facility Socialist Republic of Viet Nam: Power Transmission Investment Program

More information

NATIONAL POWER TRANSMISSION CORPORATION SOUTHERN POWER PROJECT MANAGEMENT BOARD

NATIONAL POWER TRANSMISSION CORPORATION SOUTHERN POWER PROJECT MANAGEMENT BOARD Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL POWER TRANSMISSION CORPORATION SOUTHERN POWER PROJECT MANAGEMENT BOARD -------------------------------

More information

Subproject: Jointing 110kV line at 220kV Bim Son substation

Subproject: Jointing 110kV line at 220kV Bim Son substation Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Subproject: Jointing 110kV line at 220kV Bim Son substation NORTH POWER CORPORATION Electric

More information

SEATON MUNICIPAL TRANSFORMER STATION. Welcome to our Public Information Centre

SEATON MUNICIPAL TRANSFORMER STATION. Welcome to our Public Information Centre Welcome to our Public Information Centre Delivering Power to Your Community Hydro One Networks Inc. s (Hydro One) transmission system carries high-voltage electricity across the province to local distribution

More information

ENVIRONMENTAL MANAGEMENT PLAN (EMP)

ENVIRONMENTAL MANAGEMENT PLAN (EMP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized MINISTRY OF TRANSPORT DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 June

More information

Japanese ODA Loan. Ex-Ante Evaluation

Japanese ODA Loan. Ex-Ante Evaluation Japanese ODA Loan Ex-Ante Evaluation 1. Project Country: People's Republic of Bangladesh Name of the Project: Haor Flood Management and Livelihood Improvement Project Loan Agreement: June 16, 2014 Loan

More information

VIE: Power Transmission Investment Program Multi- Tranche Financing Facility Tranche 3

VIE: Power Transmission Investment Program Multi- Tranche Financing Facility Tranche 3 Initial Environmental Examination December 2015 VIE: Power Transmission Investment Program Multi- Tranche Financing Facility Tranche 3 Subproject: 500kV My Tho Duc Hoa Transmission Line Prepared by National

More information

ENVIRONMENTAL MANAGEMENT FRAMEWORK. For Vietnam Distribution Efficiency Project

ENVIRONMENTAL MANAGEMENT FRAMEWORK. For Vietnam Distribution Efficiency Project Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK

More information

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized b Date ISDS Prepared/Updated: 13-Feb-212 1. BASIC INFORMATION INTEGRATED SAFEGUARDS DATA

More information

VIE: Power Transmission Investment Program -Tranche 3

VIE: Power Transmission Investment Program -Tranche 3 Environmental Monitoring Report # Quarterly Report (Q2 2018) Jan 2019 VIE: Power Transmission Investment Program -Tranche 3 COVERING THE FOLLOWING SUBPROJECTS: (i) 500kV My Tho Duc Hoa transmission line,

More information

Doc. No H1 Rev. 0 - July 2011 APPENDIX C ENVIRONMENTAL AND SOCIAL ACTION PLAN

Doc. No H1 Rev. 0 - July 2011 APPENDIX C ENVIRONMENTAL AND SOCIAL ACTION PLAN APPENDIX C ENVIRONMENTAL AND SOCIAL ACTION PLAN APPENDIX C ENVIRONMENTAL AND SOCIAL ACTION PLAN Taking into account the findings of the ESDD, an Environmental and Social Plan (ESAP) has been developed

More information

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Environmental Monitoring Report # Semestral Report June 2018 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Ho Chi Minh City Power Corporation, Electricity of Viet Nam

More information

Japanese ODA loan. Ex-ante Evaluation

Japanese ODA loan. Ex-ante Evaluation Japanese ODA loan Ex-ante Evaluation 1.Name of the Project Country: The Socialist Republic of Vietnam Project: North-South Expressway Construction Project (Da Nang Quang Ngai Section)(I) L/A signed on:

More information

NORTHERN POWER TRANSMISSION EXPANSION PROJECT

NORTHERN POWER TRANSMISSION EXPANSION PROJECT SEMI-ANNUAL ENVIRONMENTAL MONITORING REPORT Project Number: 38196-013 Period: July- December 2013 NORTHERN POWER TRANSMISSION EXPANSION PROJECT Prepared by the Local Implementation consultant (LIC) for

More information

MINISTRY OF TRANSPORT DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 =================

MINISTRY OF TRANSPORT DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 ================= Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized MINISTRY OF TRANSPORT DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 =================

More information

NATIONAL POWER TRANSMISSION CORPORATION CENTRAL VIETNAM POWER PROJECTS MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT (TEP) Subproject

NATIONAL POWER TRANSMISSION CORPORATION CENTRAL VIETNAM POWER PROJECTS MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT (TEP) Subproject NATIONAL POWER TRANSMISSION CORPORATION CENTRAL VIETNAM POWER PROJECTS MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT (TEP) Subproject 220kV QUANG NGAI - QUY NHON TRANSMISSION LINE E4420 V19 ENVIRONMENTAL

More information

Ex-ante Evaluation - 1 -

Ex-ante Evaluation - 1 - Ex-ante Evaluation 1. Name of the Project Country: The Socialist Republic of Vietnam Project: The North-South Expressway Construction Project (Ho Chi Minh City Dau Giay) (I) (Loan Agreement: March 31,

More information

VIE: Power Transmission Investment Program -Tranche 3

VIE: Power Transmission Investment Program -Tranche 3 Environmental Monitoring Report # Quarterly Report January March 2018 VIE: Power Transmission Investment Program -Tranche 3 COVERING THE FOLLOWING SUBPROJECT (i) (ii) (iii) (iv) (v) (vi) (vii) (viii) (ix)

More information

22.1 ISSUES OBJECTIVES POLICIES RULES PERFORMANCE STANDARDS 10

22.1 ISSUES OBJECTIVES POLICIES RULES PERFORMANCE STANDARDS 10 22 NETWORK UTILITIES 22.1 ISSUES 3 22.2 OBJECTIVES 4 22.3 POLICIES 4 22.4 RULES 6 22.5 PERFORMANCE STANDARDS 10 Whanganui District Plan (15 January 2018) Chapter 22 Network Utilities 22-1 22 NETWORK UTILITIES

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB5812 Project Name. Vietnam Industrial Pollution Control Project Region

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB5812 Project Name. Vietnam Industrial Pollution Control Project Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB5812 Project Name Vietnam

More information

SEMI-ANNUAL ENVIRONMENTAL MONITORING REPORT. VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

SEMI-ANNUAL ENVIRONMENTAL MONITORING REPORT. VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project SEMI-ANNUAL ENVIRONMENTAL MONITORING REPORT Project Number: 46391-001 December 2017 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Ho Chi Minh City Power Corporation,

More information

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Initial Environmental Examination June 2014 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project (Mo Lao 110kV Substation and Transmission Line) Prepared by Ha Noi Power Corporation for

More information

Japanese ODA. Ex-ante Evaluation

Japanese ODA. Ex-ante Evaluation Japanese ODA Ex-ante Evaluation 1. Name of the Project Country: The Socialist Republic of Vietnam Project: Second Ho Chi Minh City Water Environment Improvement Project (I) (II) (III) L/A signed on: March

More information

EXECUTIVE SUMMARY ENVIRONMENTAL ASSESSMENT REPORT

EXECUTIVE SUMMARY ENVIRONMENTAL ASSESSMENT REPORT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized VIETNAM - DANANG CITY PEOPLE S COMMITTEE DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB6558 Project Name. Danang Sustainable City Development Project (SCDP) Region

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB6558 Project Name. Danang Sustainable City Development Project (SCDP) Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB6558 Project Name Danang

More information

E767 May 2003 ISLAMIC REPUBLIC OF IRAN EARTHQUAKE EMERGENCY RECOVERY PROJECT. Objectives

E767 May 2003 ISLAMIC REPUBLIC OF IRAN EARTHQUAKE EMERGENCY RECOVERY PROJECT. Objectives Objectives ENVIRONMlENT AND SOCIAL SAFEGUARD FRAMEWORK ISLAMIC REPUBLIC OF IRAN EARTHQUAKE EMERGENCY RECOVERY PROJECT E767 May 2003 The environmental and social safeguards framework provides general policies,

More information

Cao trình đập bê tông trọng lực vị trí I

Cao trình đập bê tông trọng lực vị trí I F-31 Hình S4.3 Cao trình đập bê tông trọng lực vị trí I F-32 Hình S4.4 Mặt cắt điển hình đập bê tông trọng lực vị trí I F-33 Hình S4.5 Bố trí khoan phụt đập bê tông trọng lực vị trí I Description Quantity

More information

Organizational Report Department of Water Resources Management, MoNRE Vietnam

Organizational Report Department of Water Resources Management, MoNRE Vietnam Organizational Report Department of Water Resources Management, MoNRE Vietnam 1. Organisational Structure and Role: Name: Department of Water Resources Management, Ministry of Natural Resources and Environment

More information

CONSTRUCTION SPECIFICATION FOR NOISE BARRIER SYSTEMS

CONSTRUCTION SPECIFICATION FOR NOISE BARRIER SYSTEMS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 760 NOVEMBER 2014 CONSTRUCTION SPECIFICATION FOR NOISE BARRIER SYSTEMS TABLE OF CONTENTS 760.01 SCOPE 760.02 REFERENCES 760.03 DEFINITIONS 760.04 DESIGN

More information

PROPOSED REGULATION OF THE STATE CONTRACTORS BOARD. LCB File No. R May 14, Section 1. NAC is hereby amended to read as follows:

PROPOSED REGULATION OF THE STATE CONTRACTORS BOARD. LCB File No. R May 14, Section 1. NAC is hereby amended to read as follows: PROPOSED REGULATION OF THE STATE CONTRACTORS BOARD LCB File No. R090-08 May 14, 2008 EXPLANATION Matter in italics is new; matter in brackets [omitted material] is material to be omitted. AUTHORITY: 1,

More information

JOBS AROUND THE WORLD

JOBS AROUND THE WORLD PILE DRIVERS AND THE U.S. SUPREME COURT: A STORIED FOUNDATION OF CONSTRUCTION LAW EST. 1984 THE INTERNATIONAL PILE DRIVERS, DEEP FOUNDATIONS & MARINE CONTRACTOR S MAGAZINE PILE BUCK PRESENTS 2013 VOLUME

More information

SUMMARY INITIAL ENVIRONMENTAL EXAMINATION REPORT. Supplementary Appendix to the Report and Recommendation of the President To the Board of Directors

SUMMARY INITIAL ENVIRONMENTAL EXAMINATION REPORT. Supplementary Appendix to the Report and Recommendation of the President To the Board of Directors Supplementary Appendix A 1 SUMMARY INITIAL ENVIRONMENTAL EXAMINATION REPORT Supplementary Appendix to the Report and Recommendation of the President To the Board of Directors on the ASSAM POWER SECTOR

More information

VIE: Northern Power Transmission Expansion (Sector) Project

VIE: Northern Power Transmission Expansion (Sector) Project Environmental Monitoring Report Post-Evaluation Report January 2016 VIE: Northern Power Transmission Expansion (Sector) Project Prepared by the Local Implementation Consultant (LIC) for Northern Power

More information

Bosnia and Herzegovina Route Donja Gračanica - Klopče and Svilaj - Odzak (Part of Corridor Vc) ENVIRONMENTAL AND SOCIAL ASSESSMENT

Bosnia and Herzegovina Route Donja Gračanica - Klopče and Svilaj - Odzak (Part of Corridor Vc) ENVIRONMENTAL AND SOCIAL ASSESSMENT Bosnia and Herzegovina Route Donja Gračanica - Klopče and Svilaj - Odzak (Part of Corridor Vc) ENVIRONMENTAL AND SOCIAL ASSESSMENT Environmental and Social Action Plan August 2016 Project: Bosnia and Herzegovina

More information

Vietnam Ministry of Agricultural and Rural Development (MARD) Central Project Office (CPO) Dam Rehabilitation and Safety Improvement Project (DRSIP)

Vietnam Ministry of Agricultural and Rural Development (MARD) Central Project Office (CPO) Dam Rehabilitation and Safety Improvement Project (DRSIP) SFG1131 REV Vietnam Ministry of Agricultural and Rural Development (MARD) Central Project Office (CPO) Dam Rehabilitation and Safety Improvement Project (DRSIP) ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK

More information

Operative Ashburton District Plan

Operative Ashburton District Plan Operative Ashburton District Plan Rural B Zone Map R62 Designations D53 and D65 RDR and MHIS infrastructure A49 Lower Rangitata River identified as site of Significant Nature Conservation Value G21 Geoconservation

More information

VIETNAM: MEDIUM CITIES DEVELOPMENT PROJECT ADDITIONAL FINANCING UPDATED EXECUTIVE SUMMARY FOR THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT

VIETNAM: MEDIUM CITIES DEVELOPMENT PROJECT ADDITIONAL FINANCING UPDATED EXECUTIVE SUMMARY FOR THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT VIETNAM: MEDIUM CITIES DEVELOPMENT PROJECT ADDITIONAL FINANCING UPDATED EXECUTIVE SUMMARY FOR THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT LAO CAI CITY SUBPROJECT PHU LY CITY SUBPROJECT Public Disclosure

More information

The Red River Delta Transport Development Program

The Red River Delta Transport Development Program Vietnam-Japan Joint Program Evaluation Study Chapter 2 The Red River Delta Transport Development Program 2-1 Overview of Vietnam s Transport Sector Vietnam s transport sector provides a full range of transport

More information

Peace Region Electricity Supply Project open house

Peace Region Electricity Supply Project open house Peace Region Electricity Supply Project open house Welcome! Please take a look at our materials to learn more about the project and what to expect during construction. Project team members are here to

More information

Georgetown Water Storage Class Environmental Assessment Study

Georgetown Water Storage Class Environmental Assessment Study Georgetown Water Storage Class Environmental Assessment Study Public Information Centre Cedarvale Community Centre 181-185 Main Street South Thursday, September 4th, 2008 6:30 p.m. 8:30 p.m. Why are we

More information

Executive Summary Sri Lanka Strategic Cities Development Project (SCDP)

Executive Summary Sri Lanka Strategic Cities Development Project (SCDP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Executive Summary Sri Lanka Strategic Cities Development Project (SCDP) Executive Summary

More information

Environmental and Social Assessment of Storm Water Drains for the Selected Areas of Corporation of Chennai. Executive Summary

Environmental and Social Assessment of Storm Water Drains for the Selected Areas of Corporation of Chennai. Executive Summary Environmental and Social Assessment of Storm Water Drains for the Selected Areas of Corporation of Chennai INTRODUCTION Executive Summary 1. Government of Tamil Nadu has proposed to implement the World

More information

6. Project Description

6. Project Description 6. Project Description As previously noted, the Project will supply electricity from the 500 kv system to the 230 kv system in order to replace the loss of the Pickering NGS (see Section 1.1 for the need

More information

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized o Date ISDS Prepared/Updated: 19-Jan-2016 INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL

More information

SIEA LUNGGA POWER STATION RETAINING WALL

SIEA LUNGGA POWER STATION RETAINING WALL SIEA LUNGGA POWER STATION RETAINING WALL 1. Glossary In this scope of work the following abbreviations and definitions apply. Term AS 3000 AS 3600 AS 3700 Boundary Lines AS 4678 Brick Works Contract Contractor

More information

Japanese ODA loan. Ex-ante Evaluation

Japanese ODA loan. Ex-ante Evaluation Japanese ODA loan Ex-ante Evaluation 1. Name of the Project Country: The Socialist Republic of Viet Nam Project: Lach Huyen Port Infrastructure Construction Project (I) L/A signed on: November 2, 2011

More information