ENVIRONMENTAL MANAGEMENT PLAN (EMP)

Size: px
Start display at page:

Download "ENVIRONMENTAL MANAGEMENT PLAN (EMP)"

Transcription

1 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Sub-project: Nhon Hoi 110 kv substation and branch line VIETNAM ELECTRICITY CENTRAL POWER CORPORATION DISTRIBUTION EFFICIENCY PROJECT (DEP) SUB-PROJECT NHON HOI 110KV SUBSTATION AND BRANCH LINE BINH DINH PROVINCE ENVIRONMENTAL MANAGEMENT PLAN (EMP) E3035 v4 Da Nang, 14 April 2012 CENTRAL POWER NETWORK PROJECT MANAGEMENT BOARD Report on Environmental Management Plan Page 1

2 VIETNAM ELECTRICITY CENTRAL POWER CORPORATION CENTRAL POWER NETWORK PROJECT MANAGEMENT BOARD Add: 4 floor - 78A Duy Tan, Da Nang city Tel: ; Fax: DISTRIBUTION EFFICIENCY PROJECT (DEP) SUB-PROJECT NHON HOI 110KV SUBSTATION AND BRANCH LINE BINH DINH PROVINCE ENVIRONMENTAL MANAGEMENT PLAN (EMP) Made by : Nguyen Thanh Phong Review by : Nguyen Dinh Cong Da Nang, April 2012 DIRECTOR Le Nam Hai Report on Environmental Management Plan Page 2

3 TABLE OF CONTENTS I. GENERAL INTRODUCTION... 5 II. LEGAL FRAMEWORK Vietnamese Legislations: World Bank Environmental Safeguard Policies... 6 III. SUBPROJECT DESCRIPTION AND SCOPE OF WORK Subproject Objectives: Subproject Location: Subproject Management Organizations: Subproject Components: kV Branch Line: Nhon Hoi 110kV Substation: Scope of the Subproject: Volume of project s main works Main Works Before and During Construction Phase, and Transportation Main Works Before and During Construction Phase Means for Transportation of Construction Materials and Equipment Subproject Implementation Schedule and Total Investment Capital Subproject Implementation Schedule Total Investment Capital of the subproject IV. SUMMARY OF SOCIO ENVIRONMENTAL BACKGROUND IN THE SUBPROJECT AREA Geographical Area Climate, Topography and Pedology Natural Resources Traffic system V. POTENTIAL IMPACTS VI. ENVIRONMENTAL MANAGEMENT PLAN Mitigation Measures Environmental monitoring VII. INSTITUTIONAL ARRANGEMENT FOR EMP IMPLEMENTATION Responsibility for implementing the Environmental Management Plan Capacity building for EMP implementation: Reporting procedures Total estimated costs for EMP implementation VIII. CONSULTATION AND INFORMATION DISCLOSURE ANNEXE ANNEXE 1: TOR for Construction Supervision Consultant (CSC) Annex 2: Sample for supervision report on EMP implementation for CSC Annex 3: Sample for supervison report on EMP implementation for contractor Annex 4: Summary of environmental consultation Report on Environmental Management Plan Page 3

4 Abbreviation CPC CSC DEP DPs ECOP EIA EMF EMP EVN HH S Km kva MVA NPMU PAHs PPC PPs ROW s/s SEMP TL TOR WB ABBREVIATION EXPLAINATIONS Full descriptions Central Power Corporation Construction Supervision Consultant Distribution Efficiency Project Displaced Persons Environmental Codes of Practice Environmental Impact Assessment Environmental Management Framework Environmental Management Plan Vietnam Electricity Households Kilometre Kilovolt ampere Megavolt ampere Central power network project management unit Project affected households Provincial People s Committee Project affected persons Right of Way Substation Site environmental management plan Transmission line (branch line) Terms of Reference World Bank Report on Environmental Management Plan Page 4

5 I. GENERAL INTRODUCTION The Quy Nhon city - Binh Dinh Province is surrounded by the Sea in the East, and it is bounded by Tuy Phuoc district in the West, by Phu Cat and Tuy Phuoc districts in the North, by Song Cau District - Phu Yen province in the South, with the area of km 2. Quy Nhon is one of the six first class urban centers directly under the province of Vietnam and the centre of economy, politics, culture and tourism of Binh Dinh province. Quy Nhon city has 21 administrative units comprising 16 precincts and five communes. Nhon Hoi Economic Zone the key one of Binh Dinh province is invested to be constructed on the territory of Nhon Hoi commune belonging to Quy Nhon City. Nhon Hoi Economic Zone with the area of 12,000 ha will have Quy Nhon city enlarged to be the center of industry, port service, commerce, tourism, education and training of the Central coastline area. Currently, Nhon Hoi economic zone, the load in area of Nhon Hoi commune and part of the load of Quy Nhon city is received electricity from Quy Nhon 2 110kV substation with a capacity of about 8MW. Based on analysis of existing sources and the power grid there should not meet the load demand during the time when non-tariff zone (capacity of about 7MW), Nhon Hoi container port (capacity about 6MW) came into operation and the development of other services in synchronisation with Nhon Hoi economic Zone in the future. Therefore, the need to invest some 110 kv substation to the local load must be considered, in which, it is necessary to build Nhon Hoi 110kV substation and branch line to provide load for investors in Nhon Hoi Economic Zone. Aware of the need to implement of this project construction investment, Binh Dinh Province has asked the World Bank (WB) for sub-project financing. Sub-project "Nhon Hoi 110 kv Substation and branch line" that is one of the sub-projects will be implemented in Phase I of distribution efficiency project (DEP) under the Electricity of Vietnam by World Bank loans. Sub-projects will be implemented in Tuy Phuoc district and Quy Nhon city, Binh Dinh Province. The subproject activities include: i) Construction of an 110/22KV substation; ii) construction of the control house, distribution system, and the shifting house of the substation; and iii) newly built 110KV branch line of 26.33km long, in which in which there are 2.46km to be gone together with the power line to An Nhon. These activities can cause negative impacts on the environment and local communities during pre-construction, construction and operation. In order to ensure that potential negative impacts can be identified and during the preparation and mitigated during the subproject implementation process and that the subproject complies with the Environmental Assessment Policy OP / BP 4:01) of the World Bank, an Environmental Management Plan (EMP) of the sub-project has been prepared that follows the guidance provided in the Environmental Management Framework (EMF) of the DEP project. This EMP includes: the sub-project description, policy framework, applied environmental technological standards and regulation, potential negative impacts, proposed mitigation measures implemented during pre-construction, construction and operation, implementation arrangement of EMP and budget. The EMP will be incorporated into tender documents and contracts, along with environmental monitoring and supervision. According to the EIA regulations of the Government, the subproject is subject to the preparation of an Environmental Impact Assessment Report (EIA). This report was prepared and approved by Binh Dinh Provincial People Committee under Decision No No 544/QĐ- CTUBND dated 23 March Report on Environmental Management Plan Page 5

6 II. LEGAL FRAMEWORK 2.1. Vietnamese Legislations: The following Vietnamese Legislations are applicable to the sub-project: - Environment Protection Law 52/2005/QH11 passed by the National Assembly dated on November 29 th, 2005 regulating responsibilities of individuals and organizations regarding environment protection - Law on Forest Development and Protection No.29/2004/QH11 - Law on Cultural Heritage No. 28/2001/QH10 - Law on Water Resources No. 08/1998/QH10 dated May 20th Government Decree No. 80/2006/ND-CP dated August 9 th, 2006 Vietnamese Government on detail regulations and guidance on the implementation of some Articles of the Environment Law - Decree No. 29/2011/ND-CP dated April 18 th, 2011 regarding regulations on strategic environmental assessment, environmental impacts assessment, and environmental protection commitments - Circular No. 26/2011/TT-BTNMT dated July 18 th, 2011 of the Ministry of Natural - Resources and Environment: regarding regulations on strategic environmental assessment, environmental impacts assessment, environmental protection commitments - Decree 106/2005/ND-CP dated on August 17 th, 2005 guiding the implementation of a number of articles under the Electricity Law regarding safety protection of high-voltage power grid - Decree No. 81/2009/ND-CP dated on October 12 th, 2009 of the Government, amending or supplementing a number of articles of the Government s Decree No.106/2005/ND-CP of August 17th, 2005 which details and guide a number of articles of the Electricity Law regarding the safety protection of high-voltage power grid works - Circular No. 12/2011/TT-BTNMT dated April 14 th, 2011 regarding the management of hazardous wastes - National Technical Regulations: QCVN01: 2009/BYT - National technical regulations on quality of drinking water ; QCVN 02:2009 / BYT - National technical regulations on quality of domestic water ; QCVN08: 2008/BTNMT - National technical regulations on quality of surface water ; QCVN09: 2008/BTNMT - National technical regulations on quality of ground-water ; QCVN 05:2009 / BTNMT - Air quality -Standards for ambient air quality; QCVN06: 2009/BTNMT - Air quality - Maximum allowable concentration of hazardous substances in the ambient air - EVN Guidance No.2623/CV-EVN-KHCN dated May 28 th, 2007 regarding the management and pollution prevention and exposure to PCBs 2.2. World Bank Environmental Safeguard Policies Environmental Screening in accordance with the criteria provided in the EMF of the DEP has been performed and the results shown that this subproject has to apply Environmental Assessment Policy (OP 4.01), Involuntary Resettlement Policy (OP 4.12) and Information Disclosure Policy of the WB. The safeguard document related to OP 4.12 will be Report on Environmental Management Plan Page 6

7 presented in a separate report. The subproject will also meet the WB s requirements on public consultation and information disclosure. III. SUBPROJECT DESCRIPTION AND SCOPE OF WORK 3.1 Subproject Objectives: Investment in construction of Nhon Hoi 110kV substation and branch line to: - Enlarge the market and increase consumption output. - Improve the reliability and safety in electrical supply for customers; ensure operational safety. - Provide sufficient power for Silicon Industrial Plant and Industrial Zone - Area A of Nhon Hoi Economic Zone and the adjacent load, contributing to local economic development. Sub-project "Nhon Hoi 110 kv Substation and branch line" will be implemented to aim at: (i) Ensure power supply capability for Nhon Hoi Economic Zone and the loads in the area of Quy Nhon city and Tuy Phuoc district - Binh Dinh Province; (ii) enhance the safety in power supply due to fault reduction; (iii) reduce electric energy loss Subproject Location: - Location of Nhon Hoi 110kV substation: Located in area A belonging to Nhon Hoi Economic Zone, Nhon Hoi commune, Qui Nhon city, Binh Dinh Province kV line passes through the territory of Tran Quang Dieu precinct, Nhon Hoi commune belonging to Qui Nhon city and the townlets of Dieu Tri, Tuy Phuoc, the communes of Phuoc An, Phuoc Loc, Phuoc Hiep, Phuoc Nghia, Phuoc Son, Phuoc Hoa belonging to Tuy Phuoc district, Binh Dinh Province Subproject Management Organizations: - Subproject owner, Central Power Corporation. - Design and consultant Unit: Central Power Engineering Consultant Company (CPECC) - CPC - Project management Unit: Central Power Network Project Management Unit CPC 3.4. Subproject Components: kV Branch Line: The whole branch line and Nhon Hoi 110kV Substation are built in the territory of Tran Quang Dieu precinct, Nhon Hoi commune belonging to Qui Nhon city and the townlets of Dieu Tri, Tuy Phuoc, the communes of Phuoc An, Phuoc Loc, Phuoc Hiep, Phuoc Nghia, Phuoc Son, Phuoc Hoa belonging to Tuy Phuoc district, Binh Dinh Province. The location of the project is as follows: - Branch Line: newly built 110KV branch line of km long (in which, upgraded 110kV branch line of 2,455m long and newly built 110KV branch line of 23,085m long), the starting point of newly built 110KV branch line is at 110kV busbar (line bay E13) of Quy Nhon 220kV Substation and the ending point is at the gantry of Nhon Hoi newly built 110KV substation. The topography that the line passes through is complex, the elevation changes abundantly, as the terrain is mainly mountainous with bowl shape at the start route section as Report on Environmental Management Plan Page 7

8 well as at the end route section, the middle route section is located in the coastal plain, geographical location are mainly of eucalyptus, acacia, rice fields and shrimp ponds. The route section to Nhon Hoi Industrial and Economic Zone passing through the sand dunes planted willows. The line almost goes over the hill slope to avoid residential areas, sometimes there are route sections crossing through the area with sparse houses. In ROW there are some cross-lines such as Highway No.1A, Highway No.19, provincial road 638, 639, 640, inter-communal, inter-village, productive road, planning road in Industrial Zone, so that the transportation of construction apparatus is rather favorable. The length of each route section and the communal areas that the line passing though is described as follows: No I 1 II Localities have the line passing through Length (m) Description of line route Quy Nhon city (upgraded route section from Quy Nhon 220kV substation to tower No 11) Tran Quang Dieu precinct Tuy Phuoc district Phuoc An commune 1,801 2 Dieu Tri townlet From the newly built tower next to Quy Nhon 220kV substation, the route section goes through the newly built tower next to tower No 02 (of Quy Nhon An Nhon 110kV line) up to Dieu Tri river bank it goes inside Phu Tai Industrial Zone. - In the ROW, 15 meters (from the heart line on both sides) cut asphalt road with R = 5m in Industrial Zone 02 times. - The route section goes on the territory of Phuoc An commune, Tuy Phuoc district. From Dieu Tri river bank it crosses over the river and goes along with the Quy Nhon An Nhon existing 110kV line, it goes next to tower No 06 creating the right rudder angle to cross over the provincial road 638, up to tower No 07 it creates the left rudder angle and passes through residential area. From tower No 08 it crosses over the railway and passes through the rice field towards tower No 10, from tower No 10 it goes through residential area, passing through the rice field up to Ho Den mountain and reaching to tower No In the ROW, 15 meters (from the heart line on both sides) there are 03 four-grade houses under the existing ROW, cutting asphalt roads with R = 5m in Industrial Zone (04 roads), cutting provincial road 638 with R = 5m. - The route section goes through the territory of Dieu Tri townlet, at G1 it creates the left rudder angle and then Report on Environmental Management Plan Page 8

9 No Localities have the line passing through Length (m) 3 Tuy Phuoc towlet 2,484 4 Phuoc Loc commune 2, Phuoc Hoa commune Phuoc Nghia commune 1,025 1,177 Description of line route keeps it apart from existing line to create G2 on the wild hilltop. From G2 it skirts the hillside on the right side of existing line up to G3. The terrain in this section is relatively complex, high mountains, steep slopes, geographical location are mostly of wild trees intermixed with eucalyptus. - The route section goes on the territory of Tuy Phuoc townlet, from G3 it turns right to go slowly down the hillside of eucalyptus with many small stagnant pools and cliffs so it creates more rudder angles then goes down the hill base and create G6, From G6 it crosses over the railway, over the Highway No 1A and over 22kV line creating G7, then it then cut through brick-kiln to avoid planning plot of Quy Nhon city to go to G8. - The terrain in this section is relatively complex, high mountains, steep slopes, geographical location are mostly of wild trees mixed with eucalyptus. Brick kiln that was cut through by the route section to be dismantled by mutual agreement. - The route section goes on the territory of Phuoc Loc commune, Tuy Phuoc district. From G8 it turns right, going through the rice field, coming near Mr. Mit bridge to create G9, from G9 it crosses over the Highway No 19 that is 10m far from Mr. Mit bridge then passes through the rice field to G10, from G10 it crosses over the river going up the rich soil area to create G11 right after the concrete road. - The terrain in this section is relatively flat; the route section mainly goes through the rice fields. - The route section goes on the territory of Phuoc Hoa commune, from G11, the route section goes through the rice field, then crosses over concrete intervillage going up the rice field to G12. The terrain in this section is relatively flat; the route section mainly goes through the rice fields. - Not affected households within 15 meters (from the heart line on both sides). - The route section goes on the territory of Phuoc Nghia commune, from G12, the route section goes through the rice field, then goes up Kim Son mountain to G13. - The terrain in this section is relatively complex; the route section mainly goes on the hills and mountains. 7 Phuoc Son commune 7,709 - The route section goes on the territory of Phuoc Son Report on Environmental Management Plan Page 9

10 No 8 Localities have the line passing through Phuoc Hoa commune Length (m) Nhon Hoi commune 6,990 Total 26,330 Description of line route commune. At G13 it turns right going down Kim Son hill base, crossing over provincial road 640 to goes in the middle of Mr Phat and Mr Long s houses, then creates G14 right on the field that is 20m far from 22kV line (planning area of Phuoc Son commune), from G14 it goes on the rice field to avoid residential area, it create angles 15, 16, 17 coming to G18 that is nearby the saline dam base of hamlet Vinh Quang 2. From G18, it crosses over Thi Nai river > 500m then goes on shrimp pond and Thi Nai lagoon to Piket ( ). The terrain in this section is relatively flat; the route section mainly goes through the rice fields and shrimp pond. - There are two affected households within 15 meters (from the heart line on both sides). - The route section goes through the territory of Phuoc Hoa commune, Phuoc Son district, this route section mainly goes through the shrimp pond (alluvial mound between the rivers). - The route section goes through the territory of Nhon Hoi commune belonging to Quy Nhon city, from Piket ( ), it continuously goes through the shrimp pond, crosses over saline dam, passes through the rice field, crosses over 0.4kV line and provincial road 639, passes through residential area up to sand dune to create G19. From G19 to G22 it goes in Nhon Hoi Economic Zone and mainly on sand dune with willows. From G22 it goes up Phuong Mai mountain side, skirting the hillside of wild trees that intermixed with eucalyptus to the end point of Nhon Hoi substation. The terrain in this section is bumpy (sand dunes), from G22 to the ending point the terrain changes much, and geographical location is mainly of willow trees, eucalyptus and wild plants.. The transmission line does not go through the conservation areas and other sensitive areas Nhon Hoi 110kV Substation: Substation location: The newly built 110/22kV substation with the anticipated capacity of 2x40MVA (At the early stage install one transformer with the capacity of 1x40MVA) is built on the planning area of Nhon Hoi Economic Zone, Nhon Hoi commune, Quy Nhon city, Binh Dinh province, as follows: The North: is bounded by Phuong Mai mountain. The South: is bounded by Phuong Mai mountain. Report on Environmental Management Plan Page 10

11 The West: is bounded by ring road (opposite Lot B5, area A of Nhon Hoi Economic Zone through ring road). The East: is bounded by Phuong Mai mountain. The area of Nhon Hoi 110kV substation is about 50m far from the ring road of Nhon Hoi Economic Zone. The terrain is relatively flat. It is very convenient for the connection of 110kV outgoing and incoming feeders as well as 22kV outgoing feeders. Due to the substation location is adjacent to planning road so it should be very convenient for the transportation of equipment as well as operation and management of substation later Scope of the Subproject: a/ Nhon Hoi 110kV Substation: - Newly built one substation: Capacity of 2x40MVA - Voltage level: 110/22kV. - The substation is designed to be semi-outdoor. - Substation operation to be in the regulations concerning regular watch of the staff. - Substation location: Nhon Hoi commune Quy Nhon city Binh Dinh province. - Expected area of substation construction: 5,461m2 including outdoor distribution systems, shift dorm, control house, yard, substation gate and substation fence, access road to substation. (Map of substation s simple layout attached) b/ The connection part of 110kV outgoing feeder bay at Quy Nhon 220kV substation: - Install one the 110kV line bay E13. - Install one control cubicle, two protection cubicles for 110kV line bay. - Build the control system, supervision from Load Dispatch Centre of the Central Power System (A3). c. 110kV Branch Line. - Starting point: the 110kV busbar (line bay E21) of Quy Nhon 220kV substation. - Ending point: Gantry of Nhon Hoi 110kV substation. - Voltage level: 110kV. - Number of circuits: 02 circuits, at this stage only build one circuit. - Length of the 110kV branch line: km, in which. There are 2.455km to be gone together with the power line to An Nhon. - The ROW: 7.5 m from the heart to each side (total 15m). - Construction location: Tuy Phuoc district Quy Nhon city Binh Dinh province. - Conductor: ACSR-300/39. - Lightning wire: GW Optical cable: OPGW Insulation: Glass, ceramic or polymer. Report on Environmental Management Plan Page 11

12 - Tower: galvanized pyramid steel tower, 02 free standing circuits, the starting route section from position 01 to position 12 goes together with the power line to An Nhon. - Foundations: job- placed steel concrete. - Earthing: Earthing in rays and rays combined with rods. (L63x63x6, Φ 60/51). d/ Upgraded line to Don Pho: - Starting point: tower No 01 (tower for 02 circuits) goes to both An Nhon and Don Pho. - Ending point: newly built tower No 05 (tower of single circuit) goes to Don Pho. - Voltage level: 110kV. - Number of circuits: 01 circuit. - Length of the 110kV branch line: 800km, in which. There are 507m to be gone together with the power line to An Nhon. - The ROW: 7.5 m from the heart to each side (total 15m). - Construction location: Tuy Phuoc district Quy Nhon city Binh Dinh province. - Conductor: ACSR-185/29. - Lightning wire: GW Insulation: Glass, ceramic or polymer. - Tower: galvanized pyramid steel tower, 01 free standing circuit. - Foundations: job- placed steel concrete. - Earthing: Earthing in rays and rays combined with rods. (L63x63x6, Φ 60/51) e/ Upgraded line to An Nhon: - Starting point: 110kV busbar (line bay E02) of Quy Nhon 220kV substation. - Ending point: newly built tower No 12 goes to both An Nhon and Nhon Hoi. - Voltage level: 110kV. - Number of circuits: 01 circuit. - Length of the 110kV branch line: 2,455m. - The ROW: 7.5 m from the heart to each side (total 15m). - Construction location: Tuy Phuoc district and Quy Nhon City - Binh Dinh Province. - Conductor: ACSR-185/29. - Lightning wire: GW Insulation: Glass, ceramic or polymer. - Tower: galvanized pyramid steel tower, 01 free standing circuit. - Foundations: job- placed steel concrete. - Earthing: Earthing in rays and rays combined with rods. (L63x63x6, Φ 60/51) Volume of project s main works. Report on Environmental Management Plan Page 12

13 No Main construction work Unit Volume Construction methodologies I/ 110kV substation Level the surface of the substation foundation * Excavation m 3 14,113 m 3 Manually and mechanically * Soil fill-up m 3 Manually and mechanically Sawn stone for abutment, fence stone masonry 03 Processing all sorts of reinforcement Ton 47, Excavation at tower foundations and earthing Leveling and filling soil at foundation holes 06 Concrete M100 m Concrete M150 m Concrete M200 m Installation of insulation, 110kV accessories m 3 m 3 m 3 String Tower erection Tower Erection of centrifugal concrete poles Pole Manually Cutter + Welding machine 1,223 Manually 1,064 Manually Manually and mechanically Manually and mechanically Manually and mechanically Manually and mechanically Manually and mechanically Manually and mechanically 12 Zinc plated earthling Ton 5.56 Manually 13 Zinc plated steel of all sorts Ton Equipment + accessories Ton 85 Manually and mechanically Manually and mechanically II/ 110kV branch line 01 Excavation at tower foundations m 3 34,274 Manually and mechanically Report on Environmental Management Plan Page 13

14 No Main construction work Unit Volume 02 Leveling and filling foundation holes + road surface + roads with soil m 3 49, Concrete M100 m Concrete M200 m 3 5, Concrete M300 m 3 1,890 Construction methodologies Manually and mechanically Manually and mechanically Manually and mechanically Manually and mechanically 06 Tower erection Tower 86 Manually 07 Stretching conductors ACSR-300/39 m 90, Stretching lightning wire OPGW-50 m 3,067 Manually and mechanically Manually and mechanically 09 Earthing installation Position 86 Manually Installation of insulation, 110kV accessories Galvanized steel of all sorts String 902 Ton 1, Manually and mechanically Manually and mechanically 12 Steel of all sorts for foundations and rods Ton Manually and mechanically III/ Fire fighting equipment and tools 01 5Kg CO2 fire extinguisher Container Kg CO2 fire extinguisher Container Kg foam extinguisher Container Shovel Pcs Fire ladder Pcs littre portable water bucket, galvanized steel type Pcs Racks for CO2 fire extinguisher Pcs Sentry s orders and firefighting regulations Concrete pipe with Φ 1,1m containing sand Set 03 Pipe 06 Manually 10 3m 3 firefighting tank Tank 02 Manually Report on Environmental Management Plan Page 14

15 No Main construction work Unit Volume 11 Long-handled sickle Pcs 04 Construction methodologies 12 Sand m Fire alarm button Set Fire sirens Set Control panel for fire alarm center Panel Indoor temperature probes Pcs Indoor temperature probe in a kind of explosion - proof Pcs Outdoor temperature probes Pcs Rack for temperature probe of 110kV transformer Set Indoor smoke probes Pcs Outdoor smoke probes Pcs Fire alarm lights Set Wall twisted plastic pipe Φ 20 for wire passing. Twisted plastic pipe Φ 32 for wire passing to transformer Sheathed copper cable PVC with the cross section of 2x2,5mm2 m 250 m 50 m 520 Sheathed copper cable PVC with the cross section of 2x6mm 2 m Main Works Before and During Construction Phase, and Transportation Main Works Before and During Construction Phase - Carry out compensation, site clearance; - Take over the construction site, set up temporary camps - Transport materials, equipment and human resources to the site - Level the surface, build access road. - Build substation and control house, dig foundation pits, set up towers, install transformer and power line. - Build substation gate and fence walls, etc Report on Environmental Management Plan Page 15

16 Means for Transportation of Construction Materials and Equipment - Materials and equipment will be transported from freight yards and storehouses of investors to temporary storehouses of the project by specific trucks suitable with packaged format. After that, they will be transported to project s site by trucks with load capacity of tons. Roads that are used to transport materials to substation site and some tower locations are Highway No1A, Highway No19, provincial road and other inter hamlet, inter-village roads. The load capacity of the trucks has to be suitable with traffic load in the area. After temporarily loaded near the roads, materials and equipment will be manually carried to construction site. The substation construction site is near the roads, the manually carried distance is inconsiderable. For the line construction site, there are many positions far away from the roads or located on hill slopes so the manual transportation is relatively expensive, the weighted average of manual transportation distance is of about m. These roads do not cross residential areas, schools, hospitals and medical stations. - Building materials such as: sand, grit, cement will be supplied by suppliers who have got business license in locality within the radius of km Subproject Implementation Schedule and Total Investment Capital Subproject Implementation Schedule The subproject implementation schedule is expected to be as follows: - Making investment subproject: September Making the subproject technical design document: November Choosing construction contractors and suppliers of materials and equipment: June Launch the project construction: August, Pre-commissioning and Completion: August, Total Investment Capital of the subproject The total investment cost for the subproject is as follows: No Capital structure Investment capital (VND) 1 Cost for construction 153,130,000,000 2 Cost for equipment 38,439,000,000 3 Cost for compensation and site clearance 8,342,000,000 4 Cost for the project management 3,217,000,000 5 Cost for consultants of investment and construction 10,604,000,000 6 Other costs 13,100,000,000 7 Contingency 10% 22,684,000,000 Total 249,516,000,000 Report on Environmental Management Plan Page 16

17 IV. SUMMARY OF SOCIO ENVIRONMENTAL BACKGROUND IN THE SUBPROJECT AREA 4.1. Geographical Area Binh Dinh is located on the coast of Central Vietnam, the province's territory stretches 110km along the north south with the average narrow width of 55km (narrowest place is 50km, maximum width is 60 km). It is surrounded by Quang Ngai in the north with the common border of 63km, the South China Sea in the east with the coastline of 134km, Phu Yen in the south with the common border of 50km Gia Lai in the west with the common border of 130km. Binh Dinh is considered a gateway to the sea of the Central Highlands provinces and southern Laos. The total natural land area of Binh Dinh province is 6, km2, the province's population is 1,489,900 people, a population density of 247 people per km2 (2009 data). On the administrative organization, Binh Dinh has 11administrative units, Qui Nhon city is the provincial capital that is first grade city and10 districts are: An Lao, Van Canh and Vinh Thanh (mountainous districts), Hoai An, Tay Son (Midland districts), Hoai Nhon, Phu Cat, Phu My, Tuy Phuoc, An Nhon, (deltaic districts), the whole province has 159 communes, precincts and townlets (of which: 129 communes, 14 townlets, 16 precincts). Currently, Qui Nhon city is the center of politics, culture of Binh Dinh Climate, Topography and Pedology a) Climate The climate of Binh Dinh Province in general, Qui Nhon and Tuy Phuoc in particular have humid tropical monsoon climate, due to the complex topography when the monsoon got into the mainland, its direction and intensity has changed quite a lot. The annual average air temperature: in the mountainous area varies from 20.1 to 26.1ºC, the highest one is 31.7ºC and the lowest one is 16.5ºC. In coastal area the annual average air temperature is 27ºC, the highest one is 39.9ºC and the lowest one is 15.8ºC. - Monthly average absolute humidity in the year: in the mountainous area varies from 22.5 to 27.9ºC and the relative humidity is 79.92%, and in coastal area average absolute humidity is 27.9% and the average relative humidity is 79%. - Precipitation: Rainy season starts from August to December, sunny season from January to July. Particularly, mountainous areas have one more aid rainy season lasting from May to August under the influence of Highland s rainy season. The dry season lasts from January to August. For the mountainous districts, the average rainfall during the year from 2,000 to 2,400mm. For coastal areas, the total rainfall is 1,751mm. The total rainfall tends to decrease from the mountainous area to coastal one and from the Northwest to Southeast. - About storm: Binh Dinh is located on the coast of Central Vietnam, so the storms are often landed the mainland. Annually in the coast from Quang Nam-DaNang to Khanh Hoa there is the average of 1.04 hurricane landfall, frequency of typhoons appearance from September to November. b) Topography: The line goes through Tran Quang Dieu precinct, Phuoc Hoi commune belonging to Quy Nhon city and towlets of Dieu Tri, Tuy Phuoc, communes of Phuoc An, Phuoc Loc, Phuoc Nghia, Phuoc Son, Phuoc Hiep, Phuoc Hoa belonging to Tuy Phuoc district, Binh Dinh province, it almost goes on the hillsides, there are several sections running through sparsely Report on Environmental Management Plan Page 17

18 populated areas and Industrial Zones in relatively flat terrain, in ROW there are some crosslines such as Highway No1A, Highway No19, provincial road 638, 639, 640, intercommunal, inter-village, productive road, planning road in Industrial Zone, so that the transportation of equipment, materials and construction apparatus is rather favorable. Particularly, the terrain at the start route section as well as at the end route section is rather complicated, the elevation changes constantly, most line route goes on the high hills and mountains so it s very difficult in execution latter. c) Pedology: Geology here is mostly land of gray, gray brown, clay, loam of the yellow, lemon yellow, medium grained quartz sand coarse medium light gray, pale yellow and quite a lot of shells, livid and dark blue clay. Heterogeneous structure and content of rock chips and pebbles stone is quite large, 5.0 meters thick Natural Resources Soil resources: The natural area of Binh Dinh province is 6.039km ², there are11 groups of land with 30 different kinds, of which, the alluvial land accounts for 71,000 hectares. Currently there are approximately 136,350 hectares of agricultural land, 249,310 hectares of forestry land, and 62,870 hectares of non-agricultural land, over 150,000 hectares of unused land that can be exploited to develop agriculture, forestry and other uses (2009 data) Rivers and streams: Binh Dinh river system mostly stems from the high mountains of Truong son Mountain range to the east side, the rivers are not large, high slope, short, low in silt content, The total water volume is 5.2 billion m3, hydropower potential is million kw. There are four major rivers in the province, they are Con river, Lai Giang river, La Tinh river, Ha Thanh river and small rivers as Chau Truc or Tam Quan ones. The province has about 15 artificial lakes and 03 fresh water lagoons that are favorable for the development of agriculture and aquaculture. Especially the big Thi Nai lagoon is favorable for the development of national-caliber port and contributes to the development of Nhon Hoi Economic Zone, Thi Nai lagoon has the largest over sea bridge in Vietnam today. Mineral resources: Binh Dinh has many kinds of minerals such as bauxite, gold, titanium, ilmenite placer... and some non-metallic minerals such as kaolin, white sand, granite...in the whole province there are 5 points of mineral springs: Hoi Van, Chanh Thang, Dinh Quang, Vinh Thinh, Long My. Especially hot mineral water quality of Long My reaches international standards, it can be exploited 50 million liters / year. The project did not go through the area with the resources listed above. Marine and coastal resources:binh Dinh has a coastline of 134 km with three large bays: Qui Nhon, De Gi and Tam Quan, has Thi Nai Lagoon and more than 7600 hectares of water surface capable of aquaculture and marine products. Binh Dinh marine ecosystem is suitable for many types of seafood that are of high value and preferred by domestic market as well as foreign one. The coast has many beautiful landscapes. However, the project is not located in this area. Flora and fauna resources: With hot and humid climatic conditions, rainfall, diversified topography and land, vegetation in Binh Dinh is abundant in genders and species, there are 66 classes, 175 groups, 1,848 species. Wildlife in Binh Dinh forest are associated with animal systems of Kong Ha Nung (Gia Lai), Ba To, Tra Bong (Quang Ngai),Tra My and Phuoc Son (Quang Nam) includes seven classes with 19 groups, Report on Environmental Management Plan Page 18

19 38 species and 13 classes of birds with 37 groups, 77 species. However, the project area is located away from these areas; flora in this area are mostly rice and crops and some fruit trees, common timber; animals are mainly domestic ones as the special livestock, poultry, wildlife mainly birds, bats, squirrels Traffic system The transportation system in Binh Dinh province is rather synchronous. Highway No.1A (runs through the province from north to south with a length of 118 km), national railway (150 km through the province) runs through the province from north to south along with Highway No.14D (34km long); Highway No19 (70km through the province) that connects Qui Nhon port to the outside is very convenient, Phu Cat airport that is 30km far from Qui Nhon city to the north has been opened more flights to welcome passengers to and from Binh Dinh. Notably, the coastal road connection from Nhon Hoi to Tam Quan facilitates socio-economic development and exploits the potential of the province s hills and mountains. The traffic conditions in the project area is relatively favorable, construction site position is about 300 meters far from Highway No.1A, in the substation location there s the planning road in the Industrial Zone so it is very convenient for the transportation of materials and equipment V. POTENTIAL IMPACTS Table 4: The project potential impacts are described in the following table: No Impact Yes No Description of impact Construction preparation stage 1 Acquisition of land temporarily and permanently? 2 Impact of affected households? 3 Any household needs to be relocated? Yes Yes No - Short-term impact because of temporary land acquisition for ROW and construction. - Long-term impact because of permanent land acquisition for tower foundations and substation. - The area of permanent land acquisition is 9,600m 2, the area of temporary land acquisition is 385,150 m households whose crops and trees are affected, but mainly due to the construction of tower foundations, the area of land acquisition is minor, while the substation is built on the available land of the Economic Zone NPMU will satisfactorily compensate the permanent as well as temporary affected land, houses and trees. None of households must be resettled. 4 Affected to the Yes - Any tree higher than 4m in ROW where the Report on Environmental Management Plan Page 19

20 No Impact Yes No Description of impact flora due to transmission line runs through will be cut down. clearance for - When constructing the T/L, soil excavation, site ROW? clearance and other activities in the ROW are unavoidable. The land area for the ROW is about (including the land area for tower foundations): 26,330mx 15m = 394,950m 2. All the damage about trees will be appropriately compensated under the regulations of the Government. 5 Any impact on natural conservations? 6 Any risk to people s health caused by explosive or chemical substances? 7 Any devalue of cultural and historical works? Construction stage 8 Does soil erosion cause pollution to the surface water and conductor stretching affect rice fields and shrimp ponds of the people, affect traffic when crossing roads.? 9 Noise, and vibration, and dust? Yes Yes No No No The transmission line and the location of installing the substation do not run through any natural forest, protection forest or conservations, so the clearance does not affect the flora and fauna in the area. The project does not use chemical substance and explosive. - The T/L and s/s is not in the area where there are cultural, historical and public works so it does not affect on them. - When excavating for tower foundation and substations, objects of cultural / historical values may be discovered. Construction units should follow the guidance in Item 14, section the measures to minimize environmental impact. - When excavating soil at tower foundation positions and the substation one (foundation of transformer, shift dorm, control house), the surface soil will be excavated. When it rains, this surface soil will be eroded and swept away. Materials for construction will be scattered if they are not protected. While stretching conductor will affect rice fields and shrimp ponds of the people and affect traffic when crossing roads. - Noise and vibration are caused by material transportation means and some activities of the project such as: tower erection, conductor stretching and generator. - If the construction work is near other Report on Environmental Management Plan Page 20

21 No Impact Yes No Description of impact infrastructure ones, it must be embanked and covered in order to avoid landslides by vibration and limit the effect on adjacent works. For this project, its position is far from other infrastructure works so there is no impact on them. 10 Air pollution? Yes - Air pollution can be occurred due to the exhaust and dust of material trucks during transportation, loading materials; or dust during project implementation. 11 Rural traffic obstruction? 12 Any damage or degrading to rural traffic-ways and traffic safety? 13 Any damage to biological diversity? Yes No No - However, with the average number of 1 truck per week - 2 trips per day for every tower foundation and 2 trucks per month 2 trips per day for substation (implementation in about 2 months) (see the main volume in table 2).Therefore, the level of dust and exhaust by transportations affected on the environment is minor. - Materials and equipment are transported in long distance from the yard and storehouse of Investors by specific trucks with suitable form of packaging goods and equipment to the temporary project storage. After that, they are transported to the construction sites by 5 tons to 7.5 tons trucks. Building materials such as: sand, grits, stones, cement will be supplied by suppliers who have got business license in locality and transported directly to the construction sites. - With the average frequency of transporting as above (item 9) and constructing activities such as: soil excavating and conductor stretching, local traffic obstruction will happen. However, the time for loading materials and equipment is short (about 1 hour), building materials (sand, grits, stones, soil, etc) is loaded by dumper trucks so the level of traffic jam is not high. All materials and equipment are classified for transportation in accordance with the load of the roads; traffic here is an asphalt road (Highway No14, provincial roads and some other intervillage, inter-commune roads). In the project construction site, no species of wild animals and plants live. The permanent acquisition land is about 100m 2 /1 tower foundation (86 positions) and acquired substation of 4,651m 2. These positions are located far away from each other, in a distance of a tower foundation (about 250m); particularly the leveling area for substation Report on Environmental Management Plan Page 21

22 No Impact Yes No Description of impact is too minor and mainly industrial crops and fruit trees of the households. Therefore, as the level of flora surface clearance as well as land acquisition for animals is not considerable, there is no loss to the biological diversity in the area. 14 Solid waste causes by soil excavation, tree cutting in ROW and constructing activities? 15 Any impact on environment caused by the workers? 16 Is there any conflict between construction workers and local people? Yes Yes Yes Solid waste due to soil excavation (remains of soil and stones), tree cutting (body) or construction activities (junk iron, stones, sand, plastic bottles, cement wraps) will arise during implementation. The impacts of solid waste will be minimized through waste reduction practice and the other measures presented in Item 6.1 of this EMP. It is expected to build 01 camp in construction site of substations for workers. Local people s houses will be rented for warehouses and storehouses of materials and equipment. Therefore, water and sewages of workers will affect the surrounding environment if no method to protect the environment is applied. However, the organization of construction site is always concerned by the investors and always be expressed in the bidding documents, contract terms, therefore there are measures to handle each environmental issues during construction such as installing septic tanks, create drainage channels, installing manholes septic, etc in compliance with the regulations of the local area. Hence, the impact on environment by workers is not considerable. The appropriate mitigation measures specified in Item 6.1 of this EMP will be implemented to minimize impacts to the environment from workers. - There are differences between the workers and local people in income, lifestyle and custom. However, there is no deep conflict between them because they all use Vietnamese as a means of communication. The workers have to follow contractors regulations as well as local ones. Besides, to minimize the risk of conflict, the project uses some local labors in manual work. So, there is no big conflict between workers and local people. - Otherwise, the project will bring benefits to the local community so it gains lots of agreement from the local people as well as the close coordination with local Authorities. 17 Health and safety Yes Accidents can occur during implementation if Report on Environmental Management Plan Page 22

23 No Impact Yes No Description of impact for workers and local people? safety regulations is not strictly followed, such as: checking tools before use, setting up danger indicators (at sites of incomplete tower foundation, at sites of generators and conductor stretching, sites near roads, sites where loading materials and equipment is being carried out, sites where there are people working high above). These accidents can happen not only to the workers but also to local people. These risks can be limited more by the application of mitigation measures specified in Item 6.1 of this EMP. 18 Any landmine or bomb left after war? 19 Any other special effects due to construction activities: tower foundation excavation and conductor stretching? Operation stage 20 Development and poverty reduction? 21 Causing partition of natural environment that lead to the easy invasion into wild land? 22 Health and safety for operators and local people? Yes Yes Yes No In the past, this area was at war but the war raged less than other regions. However, the years of the war was over, this area has been exploited and constructed many works, so the remained landmines or bombs after war are inconsiderable. During tower foundation excavation in the area of rice fields there will affect irrigation canals in this area. The conductor stretching will affect crops, rice and trees of the people in the region. These risks can be limited more by the application of mitigation measures specified in Item 6.1 of this EMP. - Mainly taking part in the attraction of investment and local economic development because industrial production cannot be done without power. - Assisting agricultural production and other services including healthcare and education. - The project does not build more temporarily access roads. - After the construction of tower foundation, the temporary acquired layout will be returned as it was in the past. The entire flora less than 4m in the ROW will be remained so the impact to natural environment is inconsiderable. The project is not located in wild land so there is no impact. Electrical shocks and other accidents can occur. However, all measures and safe tools are always checked under the regulations for every tool and frequently before use. Danger indicators always have to be remained so accidents are unlikely to happen. Report on Environmental Management Plan Page 23

24 No Impact Yes No Description of impact 23 Electromagnetic field? 24 Any impact on planes, birds and bats? 25 Any pollution by oil-wastes? 26 Risks of fire and explosion? Yes No No The transmission line and the substation are designed, constructed according to the current regulations and standards of the Power Sector, in which the calculations of the effects of electromagnetic fields and standards to ensure electrical safety, operational safety has been calculated to avoid harm. Before putting the project into operation, all safe indicators have to be specified through tests, experiments and acceptance to ensure that they meet the standards and regulations set by the investors, Construction Unit, Operational Management Unit so the operators and the local people will not be harmed by electromagnetic field. In the project area, there are only some flying animals like bats or squirrels but a few kinds of birds and domestic animals, so there is no impact on flying animals. The tower/pole height is about 32 m to 37 m. Therefore, the poles will be equipped with signals for safety flight inside and surrounding the region, particularly helicopter operations or activities of take-off and landing outside the airport. The project does not remove the old transformer and does not use the equipment that contains PCB and other dangerous chemical substances. Transformer oil may be leaked in case of failure. However, this is rarely occurred and there is already the tank for containing this oil. Leakage oil will be refilled into the transformer without spilling on surrounding areas and without pollution caused by oil sewage. Yes Transformers and other equipment can be exploded and transformer oil can be leaked when faults occur. Therefore, fire-fighting equipment and fault oil tank must be equipped. Report on Environmental Management Plan Page 24

VIETNAM ELECTRICITY TRUNGSON HYDROPOWER COMPANY LIMITED ENVIRONMENTAL MANAGEMENT PLAN

VIETNAM ELECTRICITY TRUNGSON HYDROPOWER COMPANY LIMITED ENVIRONMENTAL MANAGEMENT PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Subproject: Mai Chau 110 kv substation and 35 kv power line supply for construction of

More information

ENVIRONMENTAL MANAGEMENT PLAN (EMP)

ENVIRONMENTAL MANAGEMENT PLAN (EMP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized VIETNAM ELECTRICITY CENTRAL POWER CORPORATION DISTRIBUTION EFFICIENCY PROJECT (DEP) SUB-PROJECT

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized TABLE OF CONTENTS 1. INTRODUCTION... 5 2. LEGAL FRAMEWORKS... 5 2.1. Vietnamese Legislations...

More information

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Subproject NORTH POWER CORPORATION Electric Network Project Management Board -------------------------------

More information

DECISION Approving a program to strengthen and upgrade the sea dyke system From Quang Ngai to Kien Giang

DECISION Approving a program to strengthen and upgrade the sea dyke system From Quang Ngai to Kien Giang PRIME MINISTER ------- No: 667/QD-TTg SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness -------------- Hanoi, 27 2005 2009 DECISION Approving a program to strengthen and upgrade the sea

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN NATIONAL POWER TRANSMISSION CORPORATION NORTHERN VIET NAM POWER PROJECT MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT TR2-09-005B SUB-PROJECT BAC NINH 3 220KV SUBSTATION AND CONNECTION LINE ENVIRONMENTAL

More information

REGULATIONS OF ENVIRONMENTAL MANAGEMENT OF THE CONSTRUCTION PROJECTS Dr. Pham Van Bo Vice president Academy of Managers for Construction and Cities Ministry of Construction - Vietnam List of abbreviations

More information

FLOOD MANAGEMENT IN THE RED THAI BINH RIVER BASIN VIET NAM

FLOOD MANAGEMENT IN THE RED THAI BINH RIVER BASIN VIET NAM FLOOD MANAGEMENT IN THE RED THAI BINH RIVER BASIN VIET NAM By Dr. To Trung Nghia Director of Institute of Water Resources Planning Chief of the Red Thai Binh RBO Office E-mail: iwrp.hanoi@hn.vnn.vn INTRODUCTION

More information

ENVIRONMENTAL MANAGEMENT PLAN (EMP)

ENVIRONMENTAL MANAGEMENT PLAN (EMP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized VIETNAM ELECTRICITY NORTH POWER CORPORATION Electric Network Project Management Board

More information

NORTH POWER CORPORATION Electric Network Project Management Board RESETTLEMENT PLAN (RP) SUBPROJECT:

NORTH POWER CORPORATION Electric Network Project Management Board RESETTLEMENT PLAN (RP) SUBPROJECT: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Sub-project: Improving grid medium, low voltage NORTH POWER COORATION Electric Network

More information

FLOOD MANAGEMENT IN THE RED THAI BINH RIVER BASIN

FLOOD MANAGEMENT IN THE RED THAI BINH RIVER BASIN FLOOD MANAGEMENT IN THE RED THAI BINH RIVER BASIN 1. INTRODUCTION OF THE RED THAI BINH RIVER BASIN The Red Thai Binh river basin (RRB) is situated at 20 to 30 30 of the north latitude, 100 to 107 10 of

More information

EXECUTIVE SUMMARY ENVIRONMENTAL ASSESSMENT REPORT

EXECUTIVE SUMMARY ENVIRONMENTAL ASSESSMENT REPORT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized VIETNAM - DANANG CITY PEOPLE S COMMITTEE DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT

More information

Subproject: Jointing 110kV line at 220kV Bim Son substation

Subproject: Jointing 110kV line at 220kV Bim Son substation Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Subproject: Jointing 110kV line at 220kV Bim Son substation NORTH POWER CORPORATION Electric

More information

NORTHERN POWER TRANSMISSION EXPANSION PROJECT

NORTHERN POWER TRANSMISSION EXPANSION PROJECT SEMI-ANNUAL ENVIRONMENTAL MONITORING REPORT Project Number: 38196-013 Period: July- December 2013 NORTHERN POWER TRANSMISSION EXPANSION PROJECT Prepared by the Local Implementation consultant (LIC) for

More information

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Social Monitoring Report #1 Semestral Report Project Number: 46391-001 August 2017 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Ho Chi Minh Power Corporation for the

More information

Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL POWER TRANSMISSION CORPORATION SOUTHERN POWER PROJECT MANAGEMENT BOARD -------------------------------

More information

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Subproject NORTH POWER CORPORATION Electric Network Project Management Board -------------------------------

More information

SUBPROJECT: Rehabilitation of transmission overheadline 180, 181 E1.1 Dong Anh (Section from pole No. 70 to E1.15)

SUBPROJECT: Rehabilitation of transmission overheadline 180, 181 E1.1 Dong Anh (Section from pole No. 70 to E1.15) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized HA NOI POWER CORPORATION ------------------------------------------------------------

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL POWER TRANSMISSION CORPORATION ---------------------------------------------------------------

More information

Current status of exploitation and utilization of mineral water and hot water resources in South central Vietnam

Current status of exploitation and utilization of mineral water and hot water resources in South central Vietnam Current status of exploitation and utilization of mineral water and hot water resources in South central Vietnam By: Nguyen Thac Cuong Department of Science and Technology Ministry of Natural Resources

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN Public Disclosure Authorized NATIONAL POWER TRANMISSION CORPORATION Northern Power Projects Management Board ------------------------------- Public Disclosure Authorized TRANSMISSION EFFICIENCY PROJECT

More information

E1712 VOL. 28 ENVIRONMENTAL MANAGEMENT PLAN ELECTRICITY OF VIETNAM POWER COMPANY I

E1712 VOL. 28 ENVIRONMENTAL MANAGEMENT PLAN ELECTRICITY OF VIETNAM POWER COMPANY I Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized ELECTRICITY OF VIETNAM POWER COMPANY I COMPONENT: RD - 110KV THANH NONG - KIM BOI TRANSMISSION

More information

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Resettlement Due Diligence Report April 2016 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Ho Chi Minh City Power Corporation for the Asian Development Bank. Resettlement

More information

SALINITY INTRUSION TREND IN RIVER AND CANAL SYSTEMS AND SOME PREVENTION METHODS IN BEN TRE PROVINCE

SALINITY INTRUSION TREND IN RIVER AND CANAL SYSTEMS AND SOME PREVENTION METHODS IN BEN TRE PROVINCE Vietnam-Japan Estuary Workshop 2006 August 22 nd -24 th, Hanoi, Vietnam SALINITY INTRUSION TREND IN RIVER AND CANAL SYSTEMS AND SOME PREVENTION METHODS IN BEN TRE PROVINCE TRAN THI XUAN MY 1 AND NGUYEN

More information

VIE: Mong Duong 1 Thermal Power Plant

VIE: Mong Duong 1 Thermal Power Plant 7 th Independent Monitoring Report September 2011 VIE: Mong Duong 1 Thermal Power Plant Prepared by the Development Research and Consultancy Center (DRCC) for Viet Nam Electricity (EVN) Thermal Power Project

More information

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project NORTH POWER CORPORATION Electric Network Project Management Board -------------------------------

More information

VIE: Northern Power Transmission Expansion Sector Project

VIE: Northern Power Transmission Expansion Sector Project Environmental Monitoring Report Semestral Report July-December 2012 VIE: Northern Power Transmission Expansion Sector Project Prepared by the Local Implementation consultant (LIC), with information mostly

More information

ASIAN DISASTER REDUCTION CENTER Visiting Researcher Program (FY2017B)

ASIAN DISASTER REDUCTION CENTER Visiting Researcher Program (FY2017B) JAPAN, 2018 ASIAN DISASTER REDUCTION CENTER Visiting Researcher Program (FY2017B) Viet Nam Country Report 2017 ADRC visiting researcher PHAM HONG THANH Disaster Management Policy And Technology Center

More information

ENVIRONMENT MANAGEMENT PLAN

ENVIRONMENT MANAGEMENT PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized BINHDINH PROVINCIAL PEOPLE'S COMMITTEE Feasibility Study Binh Dinh Province Rural Energy

More information

VIE: POWER TRANSMISSION INVESTMENT PROGRAM, TRANCHE 3 Loan: 3374-VIE

VIE: POWER TRANSMISSION INVESTMENT PROGRAM, TRANCHE 3 Loan: 3374-VIE ENVIRONMENTAL MONITORING REPORT Project Number: 42039-036 Period: April - June, 2017 VIE: POWER TRANSMISSION INVESTMENT PROGRAM, TRANCHE 3 Loan: 3374-VIE COVERING THE FOLLOWING SUBPROJECTS: (i) 500kV My

More information

INTRODUCTION VINH PHUC INVESTMENT PROMOTION AGENCY. Nguyen Tien Hanh Director, IPA Vinh Phuc

INTRODUCTION VINH PHUC INVESTMENT PROMOTION AGENCY. Nguyen Tien Hanh Director, IPA Vinh Phuc VINH PHUC INVESTMENT PROMOTION AGENCY INTRODUCTION INVESTMENT CLIMATE & POLICIES FOR INVESTMENT ATTRACTION IN VINH PHUC PROVINCE VIET NAM Nguyen Tien Hanh Director, IPA Vinh Phuc CONTENT 1 ADVANTAGES OF

More information

VIE: Power Transmission Investment Program, Tranche 1 220kV Song May Uyen Hung Transmission Line

VIE: Power Transmission Investment Program, Tranche 1 220kV Song May Uyen Hung Transmission Line Environmental Monitoring Report Quarterly Report October to December 2014 VIE: Power Transmission Investment Program, Tranche 1 220kV Song May Uyen Hung Transmission Line Prepared by the Southern Vietnam

More information

Vietnam Sea-Ports Sector Overview

Vietnam Sea-Ports Sector Overview TAN VIET SECURITIES INCORPORATION (TVSI) 5 th Floor, HANESC Bld.152 Thuy Khue Str., Tay Ho, Hanoi, Vietnam Phone: 04 728 0921 Website: www.tvsi.com.vn Fax: 04 728 0920 Email: info@tvsi.com.vn Vietnam Sea-Ports

More information

SUBPROJECT: IMPROVEMENT AND UPGRADING OF THE CAI LAY- CAO LANH 220kV TRANSMISSION LINE

SUBPROJECT: IMPROVEMENT AND UPGRADING OF THE CAI LAY- CAO LANH 220kV TRANSMISSION LINE Public Disclosure Authorized NATIONAL POWER TRANSMISSION CORPORATION SOUTHERN POWER PROJECT MANAGEMENT BOARD ------------------------------- Public Disclosure Authorized Public Disclosure Authorized ENVIRONMENTAL

More information

Japanese ODA. Ex-ante Evaluation

Japanese ODA. Ex-ante Evaluation Japanese ODA Ex-ante Evaluation 1. Name of the Project Country: The Socialist Republic of Vietnam Project: North-South Expressway Construction Project (Da Nang Quang Ngai Section) (I) (II) (III) L/A signed

More information

QUANG NGAI PROVINCE PEOPLE S COMMITTEE. Quang Ngai Provincial Project Management Unit of Construction Works for Agriculture & Rural Development

QUANG NGAI PROVINCE PEOPLE S COMMITTEE. Quang Ngai Provincial Project Management Unit of Construction Works for Agriculture & Rural Development SFG3446 V5 REV QUANG NGAI PROVINCE PEOPLE S COMMITTEE Quang Ngai Provincial Project Management Unit of Construction Works for Agriculture & Rural Development ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (ESMP)

More information

"Action Plan toward Effective Flood Hazard Mapping in Vietnam"

Action Plan toward Effective Flood Hazard Mapping in Vietnam FLOOD HAZARD MAPPING TRAINNING COURSE CONCLUDING REPORT "Action Plan toward Effective Flood Hazard Mapping in Vietnam" By NGUYEN HIEP Department of Dyke Flood and Storm Control Ministry of Agriculture

More information

Vietnam seaport system. PHAM ANH TUAN Deputy General Director Portcoast Consultant Corporation

Vietnam seaport system. PHAM ANH TUAN Deputy General Director Portcoast Consultant Corporation 1 Vietnam seaport system PHAM ANH TUAN Deputy General Director Portcoast Consultant Corporation 4 LARGE INFRASTRUCTURE PROJECT CONFERENCE 2018 BUILD FOR LIFE HCMC - OCTOBER, 2018 PRESENTED BY: PHAM ANH

More information

NATIONAL POWER TRANMISSION CORPORATION. Northern Power Projects Management Board ENVIRONMENTAL IMPACT ASSESSMENT

NATIONAL POWER TRANMISSION CORPORATION. Northern Power Projects Management Board ENVIRONMENTAL IMPACT ASSESSMENT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL POWER TRANMISSION CORPORATION Northern Power Projects Management Board -------------------------------

More information

Preparatory Study for Development Study (M/P or F/S)

Preparatory Study for Development Study (M/P or F/S) Preparatory Study for Development Study (M/P or F/S) 1. Title of the Cooperation Project and Name of the Project Proponent (1) Title of the Cooperation Project The Study for Groundwater Development in

More information

EMP for Subproject Upgrading anti-erosion embankment for dyke safety of Kon River in An Nhon and Tuy Phuoc districts - Binh Dinh province - VN-Haz

EMP for Subproject Upgrading anti-erosion embankment for dyke safety of Kon River in An Nhon and Tuy Phuoc districts - Binh Dinh province - VN-Haz Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized E2993 v10 THE SOCIALIST REPUBLIC OF VIETNAM MINISTRY OF AGRICULTURE AND RURAL DEVELOPMENT

More information

ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (ESMP)

ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (ESMP) SFG3446 V1 REV BINH DINH PROVINCIAL PEOPLE S COMMITTEE BINH DINH PMU FOR CONSTRUCTION INVESTMENT WORKS OF AGRICULTURE AND RURAL DEVELOPMENT --------------o0o-------------- ENVIRONMENTAL AND SOCIAL MANAGEMENT

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL POWER TRANSMISSION CORPORATION ---------------------------------------------------------------

More information

Japanese ODA loan. Ex-ante Evaluation

Japanese ODA loan. Ex-ante Evaluation Japanese ODA loan Ex-ante Evaluation 1. Name of the Project Country: The Socialist Republic of Viet Nam Project: North-South Expressway Construction Project (Ben Luc Long Thanh Section)(II) L/A signed

More information

MOIT FiT Circular No. 02 Decision No. 39

MOIT FiT Circular No. 02 Decision No. 39 Renewable Energy Vietnam Client Alert January 2019 For further information, please contact: Fred Burke +84 28 3520 2628 frederick.burke@bakermckenzie.com Dang Chi Lieu +84 24 3936 9341 chilieu.dang@bakermckenzie.com

More information

DEP Sub-project: Cam Khe 110-kV Overhead Line and Substation EMP VIETNAM ELECTRICITY

DEP Sub-project: Cam Khe 110-kV Overhead Line and Substation EMP VIETNAM ELECTRICITY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized DEP Sub-project: Cam Khe 110-kV Overhead Line and Substation EMP VIETNAM ELECTRICITY

More information

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The Rual Energy Project Additional Financing Phase 4, Ha Tinh Province Environmental

More information

Briefing on Drought on Mekong Delta

Briefing on Drought on Mekong Delta 2016/SOM3/EPWG/016 Agenda Item: 9.3 Briefing on Drought on Mekong Delta Purpose: Information Submitted by: Viet Nam 10 th Emergency Preparedness Working Group Meeting Lima, Peru 15-16 August 2016 THE 10

More information

Summary of Environmental and Social Consideration in Development Study (Preparatory Study)

Summary of Environmental and Social Consideration in Development Study (Preparatory Study) Summary of Environmental and Social Consideration in Development Study (Preparatory Study) 1. Full title of the Project The Study on Integrated Development Strategy for Danang City and Its Neighboring

More information

VIET NAM LOSSES CAUSED BY TYPICAL DISASTERS FROM 1978 TO 2005 TYPICAL DISASTERS IN VIET NAM ECONOMIC LOSS RECORDED FROM

VIET NAM LOSSES CAUSED BY TYPICAL DISASTERS FROM 1978 TO 2005 TYPICAL DISASTERS IN VIET NAM ECONOMIC LOSS RECORDED FROM VIET NAM Việt Nam is located at the Southeast of Asia, with 333. km 2 of the total natural area and 32km of coastline. Population: 84 million (24 s statistics) Population density: 226 capitas/km2 Urban

More information

NATIONAL POWER TRANSMISSION CORPORATION CENTRAL VIETNAM POWER PROJECTS MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT (TEP) Subproject

NATIONAL POWER TRANSMISSION CORPORATION CENTRAL VIETNAM POWER PROJECTS MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT (TEP) Subproject NATIONAL POWER TRANSMISSION CORPORATION CENTRAL VIETNAM POWER PROJECTS MANAGEMENT BOARD TRANSMISSION EFFICIENCY PROJECT (TEP) Subproject 220kV QUANG NGAI - QUY NHON TRANSMISSION LINE E4420 V19 ENVIRONMENTAL

More information

ANNEX 6 PUBLIC CONSULTATION

ANNEX 6 PUBLIC CONSULTATION Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Environmental Assessment (EA) A6.1. Objective and Methodology A6.2. Identification of

More information

Area: km2. The province has 07 districts, 01 town, 284 communes, wards and townships.

Area: km2. The province has 07 districts, 01 town, 284 communes, wards and townships. THAI BINH PROVINCE General Information: Geographical location: Thai Binh is a coastal province in the Red River Delta, directly affected by the economic triangle of Hanoi-Hai Phong-Quang Ninh. Thai Binh

More information

EXPERIENCE OF URBAN DEVELOPMENT AND CLIMATE CHANGE ADAPTATION IN DA NANG CITY

EXPERIENCE OF URBAN DEVELOPMENT AND CLIMATE CHANGE ADAPTATION IN DA NANG CITY VIET NAM DA NANG Lessons from ACCCRN in Viet Nam Series EXPERIENCE OF URBAN DEVELOPMENT AND CLIMATE CHANGE ADAPTATION IN DA NANG CITY Lessons from the urbanization process of Hoa Tien and Hoa Chau communes,

More information

REPORT ON ENVIRONMENTAL IMPACT ASSESSMENT

REPORT ON ENVIRONMENTAL IMPACT ASSESSMENT Ha Nam Province People's Committee Phu Ly City People's Committee Public Disclosure Authorized Public Disclosure Authorized MEDIUM CITIES DEVELOPMENT PROJECT - PHU LY CITY SUBPROJECT, HA NAM PROVINCE REPORT

More information

Meeting Vietnam s Energy Demands in a Sustainable Way

Meeting Vietnam s Energy Demands in a Sustainable Way TRUNG SON HYDROPOWER PROJECT Meeting Vietnam s Energy Demands in a Sustainable Way Photo by: World Bank 1 Photo by: Mai Ky/World Bank, 2012 OVERVIEW Trung Son Hydropower Project (TSHPP) is a US$411.57

More information

Summary of Preliminary Study Result for Technical Cooperation Project. Date: 2008/10/8

Summary of Preliminary Study Result for Technical Cooperation Project. Date: 2008/10/8 Summary of Preliminary Study Result for Technical Cooperation Project Date: 2008/10/8 1. Full title of the Project The Project on Integrated UMRT and Urban Development for Hanoi 2. Type of the study Feasibility

More information

LIST OF CONSTRUCTION MATERIALS COMPANIES IN VIETNAM

LIST OF CONSTRUCTION MATERIALS COMPANIES IN VIETNAM LIST OF CONSTRUCTION MATERIALS COMPANIES IN VIETNAM 1 COSEVSO 19 - Cement Company / Midland Construction Corporation Add: Hoa Khuong Commune, Hoa Vang District, Da Nang City Phone: 84-511-378 0329 Fax:

More information

Initial Environmental Examination. Multitranche Financing Facility Socialist Republic of Viet Nam: Power Transmission Investment Program

Initial Environmental Examination. Multitranche Financing Facility Socialist Republic of Viet Nam: Power Transmission Investment Program Power Transmission Investment Program (RRP VIE 42039) Initial Environmental Examination Project Number: 42039-034 November 2011 Multitranche Financing Facility Socialist Republic of Viet Nam: Power Transmission

More information

VIE: Power Transmission Investment Program, Tranche 1 220kV Song May-Uyen Hung Transmission Line

VIE: Power Transmission Investment Program, Tranche 1 220kV Song May-Uyen Hung Transmission Line Environmental Monitoring Report Semestral Report July to December 2014 VIE: Power Transmission Investment Program, Tranche 1 220kV Song May-Uyen Hung Transmission Line Prepared by the Southern Vietnam

More information

Ex-ante Project Evaluation

Ex-ante Project Evaluation Ex-ante Project Evaluation 1. Name of project Country: Socialist Republic of Vietnam Name of project: Hai Phong City Environmental Improvement Project (II) L/A signing date: March 31, 2009 Loan amount:

More information

Japanese ODA loan. Ex-ante Evaluation

Japanese ODA loan. Ex-ante Evaluation Japanese ODA loan Ex-ante Evaluation 1.Name of the Project Country: The Socialist Republic of Vietnam Project: North-South Expressway Construction Project (Da Nang Quang Ngai Section)(I) L/A signed on:

More information

Lam Du Son Vice President of EVN, Vietnam

Lam Du Son Vice President of EVN, Vietnam BRIEF INTRODUCTION TO ELECTRICITY SECTOR IN VIET NAM Lam Du Son Vice President of EVN, Vietnam I. OVERVIEW OF VIETNAM ELECTRICITY SECTOR. A. EVN Electricity of Vietnam Established in 994. Main responsibility

More information

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Copy Public Disclosure Copy Date ISDS Prepared/Updated: 04-Apr-2014

More information

VIE: Northern Power Transmission Expansion (Sector) Project

VIE: Northern Power Transmission Expansion (Sector) Project Environmental Monitoring Report Post-Evaluation Report January 2016 VIE: Northern Power Transmission Expansion (Sector) Project Prepared by the Local Implementation Consultant (LIC) for Northern Power

More information

NEW FEED-IN- TARIFF MECHANISM FOR VIETNAMESE SOLAR ENERGY PROJECTS

NEW FEED-IN- TARIFF MECHANISM FOR VIETNAMESE SOLAR ENERGY PROJECTS BRIEFING NEW FEED-IN- TARIFF MECHANISM FOR VIETNAMESE SOLAR ENERGY PROJECTS FEBRUARY 2019 THE VIETNAMESE GOVERNMENT HAS CONSIDERED NEW SOLAR FEED-IN-TARIFFS WHICH WILL BE IN PLACE FOR APPROXIMATELY TWO

More information

CHANGES IN WATER QUALITY AT BUNG RIVER BASIN, QUANG NAM AFTER THE DAM CONSTRUCTION. Vietnam

CHANGES IN WATER QUALITY AT BUNG RIVER BASIN, QUANG NAM AFTER THE DAM CONSTRUCTION. Vietnam CHANGES IN WATER QUALITY AT BUNG RIVER BASIN, QUANG NAM AFTER THE DAM CONSTRUCTION Nguyen Viet Hung 1 and Long Bui Ta 1 1 University of Technology, Vietnam National University Hochiminh city, 268 Ly ThuongKiet,

More information

VIE: Power Transmission Investment Program - Tranche 2 220kV Cau Bong-Hoc Mon-Branches to Binh Tan Transmission Line

VIE: Power Transmission Investment Program - Tranche 2 220kV Cau Bong-Hoc Mon-Branches to Binh Tan Transmission Line Environmental Monitoring Report 4th Quarterly Report February 2016 VIE: Power Transmission Investment Program - Tranche 2 220kV Cau Bong-Hoc Mon-Branches to Binh Tan Transmission Line Prepared by Southern

More information

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Environmental Monitoring Report # Semestral Report June 2018 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Ho Chi Minh City Power Corporation, Electricity of Viet Nam

More information

STRATEGY OF VIETNAM TOWARDS ADDRESSING ENVIRONMENT AND CLIMATE RISKS

STRATEGY OF VIETNAM TOWARDS ADDRESSING ENVIRONMENT AND CLIMATE RISKS STRATEGY OF VIETNAM TOWARDS ADDRESSING ENVIRONMENT AND CLIMATE RISKS BUI CACH TUYEN, Assoc. Prof. Dr. Director General Vietnam Environment Administration ENVIRONMENT AND CLIMATE Vietnam has been facing

More information

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project NORTH POWER CORPORATION Electric Network Project Management Board -------------------------------

More information

CURRENT STATUS OF WATER-RELATED SANITATION CONDITIONS IN HUE CITY, VIETNAM

CURRENT STATUS OF WATER-RELATED SANITATION CONDITIONS IN HUE CITY, VIETNAM CURRENT STATUS OF WATER-RELATED SANITATION CONDITIONS IN HUE CITY, VIETNAM Pham Khac Lieu, D.Eng. Department of Environmental Science College of Sciences, Hue University, Vietnam Contents 1. Hue city at

More information

VIE: Northern Power Transmission Expansion Project

VIE: Northern Power Transmission Expansion Project Environmental Monitoring Report Semi-Annual Report January-June 2014 VIE: Northern Power Transmission Expansion Project Prepared by the Local Implementation consultant (LIC) for the Northern Power Project

More information

Cao trình đập bê tông trọng lực vị trí I

Cao trình đập bê tông trọng lực vị trí I F-31 Hình S4.3 Cao trình đập bê tông trọng lực vị trí I F-32 Hình S4.4 Mặt cắt điển hình đập bê tông trọng lực vị trí I F-33 Hình S4.5 Bố trí khoan phụt đập bê tông trọng lực vị trí I Description Quantity

More information

ENVIRONMENTAL IMPACT REPORT

ENVIRONMENTAL IMPACT REPORT PEOPLE COMMITTEE OF DA NANG CITY Public Disclosure Authorized DA NANG DEPARTMENT OF TRANSPORT DANANG PRIORITY INFRASTRUCTURE INVESTMENT PROJECT MANAGEMENT UNIT SFG2442 Public Disclosure Authorized ENVIRONMENTAL

More information

VIE: Power Transmission Investment Program -Tranche 3

VIE: Power Transmission Investment Program -Tranche 3 Environmental Monitoring Report # Quarterly Report (Q2 2018) Jan 2019 VIE: Power Transmission Investment Program -Tranche 3 COVERING THE FOLLOWING SUBPROJECTS: (i) 500kV My Tho Duc Hoa transmission line,

More information

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project ENVIRONMENTAL MONITORING REPORT Project Number: 46391-001 March 2018 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Hanoi City Power Corporation, Electricity of Vietnam

More information

Annex F Scoping Checklist

Annex F Scoping Checklist Scoping Checklist Table F1: Scoping Checklist Table. Questions to be considered in Scoping /? Which Characteristics of the Project 1. Will construction, operation or decommissioning of the Project involve

More information

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project : Rural Energy Project No. II Supporting the Medium Voltage for the North (The

More information

MINISTRY OF TRANSPORT DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 =================

MINISTRY OF TRANSPORT DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 ================= Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized MINISTRY OF TRANSPORT DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 =================

More information

To establish the Panama Canal Authority (ACP) occupational safety requirements for excavations.

To establish the Panama Canal Authority (ACP) occupational safety requirements for excavations. 1.0 PURPOSE To establish the Panama Canal Authority (ACP) occupational safety requirements for excavations. 2.0 BACKGROUND Excavation activities are highly dangerous and thus require adequate planning

More information

COASTAL DUNE STABILISATION IN CENTRAL VIETNAM

COASTAL DUNE STABILISATION IN CENTRAL VIETNAM COASTAL DUNE STABILISATION IN CENTRAL VIETNAM Tran tan Van, Elise Pinners and Paul Truong The results presented here are extracts from progress reports of the on growing project: Introduction of Vetiver

More information

The Red River Delta Transport Development Program

The Red River Delta Transport Development Program Vietnam-Japan Joint Program Evaluation Study Chapter 2 The Red River Delta Transport Development Program 2-1 Overview of Vietnam s Transport Sector Vietnam s transport sector provides a full range of transport

More information

OVERVIEW OF RURAL WATER SUPPLY IN VIETNAM

OVERVIEW OF RURAL WATER SUPPLY IN VIETNAM OVERVIEW OF RURAL WATER SUPPLY IN VIETNAM Le Thieu Son Director NCERWASS Hanoi, July 2016 General Information: Location: South East Asian region The Capital: Hanoi City Area: about 331,000 km 2 Population

More information

Peace Region Electricity Supply Project open house

Peace Region Electricity Supply Project open house Peace Region Electricity Supply Project open house Welcome! Please take a look at our materials to learn more about the project and what to expect during construction. Project team members are here to

More information

A geo-spatial assessment of flood impacts on agriculture in Quang Nam province, Vietnam

A geo-spatial assessment of flood impacts on agriculture in Quang Nam province, Vietnam A geo-spatial assessment of flood impacts on agriculture in Quang Nam province, Vietnam Vu Ngoc Chau John Holland Mike Tuohy Sue Cassells Bangkok, 19 th October 2011 Photo: Hoang Dinh Nam Presentation

More information

CCAI Demonstration Projects in Viet Nam. Dr. Nguyen Anh Duc National CCAI Coordinator, Viet Nam National Mekong Committee

CCAI Demonstration Projects in Viet Nam. Dr. Nguyen Anh Duc National CCAI Coordinator, Viet Nam National Mekong Committee 1 CCAI Demonstration Projects in Viet Nam Dr. Nguyen Anh Duc National CCAI Coordinator, Viet Nam National Mekong Committee Outline Project: Preliminary Study on Climate Change Adaptation Plan in Kien Giang

More information

Initial Environmental Examination

Initial Environmental Examination Initial Environmental Examination June, 2015 VIE: INTEGRATED RURAL DEVELOPMENT SECT PROJECT IN THE CENTRAL PROVINCES (Additional Financing) SUBPROJECT: UPGRAGDING PHO LAI - THANH CAN - NAM DUONG - CO THAP

More information

Abstract GENDER IN VIETNAM

Abstract GENDER IN VIETNAM WOMEN S PARTICIPATION IN NATURAL RESOURCES MANAGEMENT AND ENVIRONMENTAL PROTECTION IN VIETNAM: SOME EXPERIENCE AND LESSONS FROM THE SIDA ENVIRONMENTAL FUND PROJECTS. Abstract Do Thi Huyen The author would

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB4343 Project Name. VIETNAM: Haiphong Urban Transport Project Region

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB4343 Project Name. VIETNAM: Haiphong Urban Transport Project Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB4343 Project Name VIETNAM:

More information

VUNG TAU PETRO JSC 2013

VUNG TAU PETRO JSC 2013 VUNG TAU PETRO JSC 2013 INVESTMENT HIGHLIGHTS The demand of petroleum port and depot in Vietnam is currently very high, especially in the South All current petroleum ports in Vietnam are small in terms

More information

VIE: Power Transmission Investment Program -Tranche 3

VIE: Power Transmission Investment Program -Tranche 3 Environmental Monitoring Report # Quarterly Report January March 2018 VIE: Power Transmission Investment Program -Tranche 3 COVERING THE FOLLOWING SUBPROJECT (i) (ii) (iii) (iv) (v) (vi) (vii) (viii) (ix)

More information

ENVIRONMENTAL MANAGEMENT FRAMEWORK. For Vietnam Distribution Efficiency Project

ENVIRONMENTAL MANAGEMENT FRAMEWORK. For Vietnam Distribution Efficiency Project Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK

More information

Abnormal Behavior of Storm and Tropical Cyclones That Hit Viet Nam

Abnormal Behavior of Storm and Tropical Cyclones That Hit Viet Nam 2017/SOM3/EPWG/028 Agenda Item: 13.7 Abnormal Behavior of Storm and Tropical Cyclones That Hit Viet Nam Purpose: Information Submitted by: Viet Nam 12 th Emergency Preparedness Working Group Meeting Ho

More information

VIE: Power Transmission Investment Program, Tranche 2

VIE: Power Transmission Investment Program, Tranche 2 Environmental Monitoring Report Semestral Report January to June 2014 VIE: Power Transmission Investment Program, Tranche 2 Prepared by the Central Vietnam Power Project Management Board (CPPMB) for the

More information

INTRODUCTION. THUA THIEN HUE CONSTRUCTION & WATER SUPPLY CO.LTD - HueWACO ( )

INTRODUCTION. THUA THIEN HUE CONSTRUCTION & WATER SUPPLY CO.LTD - HueWACO ( ) INTRODUCTION THUA THIEN HUE CONSTRUCTION & WATER SUPPLY CO.LTD - HueWACO (1909-2015) 1 Introduction of Thua Thien Hue province & Hue city Thua Thien Hue province Central Vietnam. Area: 5033.2 km 2 Population:

More information

Implementation Status & Results Vietnam Second Transmission and Distribution Project (P084871)

Implementation Status & Results Vietnam Second Transmission and Distribution Project (P084871) losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Vietnam Second Transmission and Distribution Project

More information

PPP Policies and Potential PPP projects in waste treatment and water supply in Vietnam

PPP Policies and Potential PPP projects in waste treatment and water supply in Vietnam SOCIALIST REPUBLIC OF VIETNAM MINISTRY OF PLANNING AND INVESTMENT Public Procurement Agency Ministry of Planning and Investment of 4 th ASEAN Connectivity Forum PPP Policies and Potential PPP projects

More information

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project ENVIRONMENTAL MONITORING REPORT Project Number: 46391-001 January 2018 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Hanoi City Power Corporation, Electricity of Vietnam

More information

Multitranche Financing Facility Socialist Republic of Viet Nam: Power Transmission Investment Program

Multitranche Financing Facility Socialist Republic of Viet Nam: Power Transmission Investment Program [VIE MFF0066 PFR2] POWER TRANSMISSION INVESTMENT PROGRAM Initial Environmental Examination July 2012 Multitranche Financing Facility Socialist Republic of Viet Nam: Power Transmission Investment Program

More information