SUMMER VILLAGE CONDITIONS ASSESSMENT ENVELOPE BUILDING

Size: px
Start display at page:

Download "SUMMER VILLAGE CONDITIONS ASSESSMENT ENVELOPE BUILDING"

Transcription

1 SUMMER VILLAGE BUILDING ENVELOPE CONDITIONS ASSESSMENT PREPARED FOR: Summer Village Townhomes c/o Kim Patterson Parker Brown Real Estate 187 W Main Street Lehi, UT PROJECT NUMBER: REPORT DATE: October 5, 2015 REVISION DATE: PREPARED BY: (P) (F) Oregon Utah - Washington 2015 FORENSIC BUILDING CONSULTANTS. ALL RIGHTS RESERVED.

2 TABLE OF CONTENTS Table of Contents 2 Executive Summary 3 BECA Scope 3 BECA Findings 4 Recommended Next Steps 6 Background Information 8 Property Site 9 Property Elevations 10 Exterior Assemblies: Observations & Discussion Deck Observations Roof Diverter Observations Window and Door Observations Masonry Veneer Exterior Weather Wall Protection 34 Summary of Observations 40 Appendix A: Important Information 42 Appendix A1: Disclosures and Limitations 43 End of Document 44 FORENSIC HEADQUARTERS UT # PAGE 2

3 EXECUTIVE SUMMARY Client Name: Summer Village Townhomes c/o Kim Patterson Property Name: Summer Village Townhomes (Property) Parker Brown Real Estate Client Address: 187 W. Main Street Property Address: Sunshine Drive Lehi, UT Saratoga Springs, UT Report Type: Building Envelope Conditions Assessment (BECA) Report Date: September 21, 2015 Dear Mrs. Patterson: On September 14, 2015, Forensic Building Consultants (Forensic) performed a BECA at the Property in general conformance with ASTM E2128 Standard Guide for Evaluating Water Leakage of Building Walls, The intent of Forensic s BECA was to evaluate the existing condition of the Property s accessible building envelope assemblies at limited locations, noting evidence of nonconforming construction conditions (i.e., construction defects ), water leakage-facilitating conditions and evident water leakage pathways, and resultant property damage (if any). The following report has been prepared to provide representative photographic documentation, discussion, and a summary of Forensic s BECA observations, and to specify preliminary remediation recommendations for each observed condition, as applicable 1. BECA SCOPE Forensic s BECA was limited to observation and evaluation of the as-built construction assemblies or building locations listed below 2, as they existed at the time of our presence on site at the Property. All other construction assemblies or building locations not specifically identified below were beyond the scope of our BECA. Note that Forensic s BECA was limited to the following: l l l l Visual review of exterior wall coverings and fenestration (window and door) assemblies Visual review of roof coverings and surface drainage provisions Visual review of deck coverings and surface drainage provisions Visual review of concrete flatwork and soil finish grade adjacent to exterior walls 1 Please refer to Appendix A of this report for important information regarding Forensic s disclosures and limitations, performance criteria & methodology, and standard definitions & abbreviations. 2 Please refer to Background Information section of this report for additional description of the Property s as-built construction assemblies. PAGE 3

4 l Examination of concealed building envelope assemblies at 24 specific inspection opening (IO) locations 3 BECA FINDINGS Forensic s BECA has identified multiple nonconforming and water leakage-facilitating conditions at the Property, which individually or in combination have resulted in property damage or have the potential to result in future property damage. The conditions observed at the time of our presence on site at the Property are summarized and analyzed on the following pages. Please refer to the Summary of Observations section and appropriate Observations and Discussion photo section of this report for detailed information regarding a given condition. l l l 2 nd floor Front Deck Concerns Forensic noted multiple nonconforming conditions that fail to provide adequate weather protection for the 2 nd floor decks on the front elevations facilitating water infiltration behind exterior coverings and facilitating water absorption by moisture-sensitive structural building components. Examples of weather-resistance concerns noted throughout the decks on the property include the following: Inadequately waterproofed deck surfaces Omitted diverter flashings at the deck to wall junctions Unsealed penetrations on the horizontal surface of deck Open voids at omitted, discontinuous, and inadequate deck to wall flashings Inadequate coverage of deck edge flashing over cladding Inadequate clearances at horizontal terminations of cladding systems over deck surfaces Inadequately sloped deck surfaces Unsealed vent or HVAC intake penetrations Moisture-deteriorated building envelope components Corroded building envelope components Damage to structural components, weather resistive barriers, and cladding materials due to above mentioned deficiencies Roof Diverter Concerns Roof to sidewall transitions are particularly vulnerable to moisture intrusion and thus require diverters installed to adequately convey water away from the buildings exterior coverings. Examples of roof diverter concerns noted throughout the property include the following: Omitted, discontinuous, and/or inadequate diverter flashing provisions at roof-to-wall step flashing terminations Damage to structural components, weather resistive barriers, and cladding materials due to the above mentioned deficiencies Window and Door Concerns Forensic also observed multiple conditions throughout the Property related to the windows and doors that should be addressed with repair or replacement of the affected assembly. All of the wood framed door assemblies on the second floor decks showed some level of deterioration or damage due to moisture. These doors should be replaced as the decks are 3 Please refer to Observations & Discussion photo sections of this report for additional information regarding IO locations. PAGE 4

5 being repaired. The remaining wood doors should be replaced as needed. Examples of window and door concerns that were noted are: l l l l Moisture damaged wood doors and door frames Omitted head flashings over windows and door trim Improperly installed window fasteners Failed internal glazing units in vinyl windows Masonry Concerns Forensic also observed multiple conditions related to the masonry veneer that are allowing path ways for moisture intrusion and preventing egress of incidental moisture. The combination of these two conditions promotes moisture to be absorbed into weather resistive and structural building components causing property damage. Examples of masonry concerns noted throughout the Property include the following: Omitted, discontinuous, or inadequate flashing over brick water table Omitted sealant joints between dissimilar materials Omitted, sealed, and/or blocked weep provisions at the base of wall and other horizontal wall terminations Inadequate slope of the brick water table Excessive mortar blocking the drainage cavity Moisture staining and mineral leaching on the face of the brick indicating moisture intrusion Exterior Weather Wall Protection Concerns Forensic also observed multiple conditions in the cladding systems throughout the Property that promote water infiltration, prevent incidental moisture egress, and/or decrease the expected life span of the building envelope components. Examples of exterior weather wall protection concerns noted throughout the Property include the following: Omitted, sealed, and/or blocked weep provisions at horizontal wall covering terminations Omitted or improperly-constructed dynamic sealant joints between dissimilar materials, failing to accommodate differential thermal movement and facilitating premature sealant failure Improperly installed stucco system and stucco accessories causing cracking and open voids Gaps and voids in the cladding system facilitating moisture intrusion Inadequate clearances at horizontal or diagonal terminations of cladding systems above roof and other horizontal surfaces Corroded building envelope components Reverse-lapped components (lower layer improperly lapped over upper layer) within the building envelope Omitted, discontinuous, and/or inadequate water-resistive barrier (WRB) provisions behind exterior wall coverings Omitted, discontinuous, and/or inadequate flexible flashing provisions at rough opening locations Structural Concerns At the time of Forensic s investigation, multiple conditions were observed that have the potential to compromise the structural integrity of the Property or its component assemblies. Specific examples of structural concerns include the deteriorated state of the 2 nd floor decks. Immediate repairs should be made to these decks before the damage spreads to more costly and serious structural components. Concrete Flat Work Concerns- Forensic also noted several areas of cracked and settled concrete areas. Cracked and settled concrete can be indications of more sever geotechnical concerns. These conditions also create trip and fall hazards that should be addressed to prevent personal injury. PAGE 5

6 RECOMMENDED NEXT STEPS Forensic believes that the nonconforming and water leakage-facilitating conditions identified in this report need to be remediated in order to help ensure that the longevity and weather-resistance of the Property are not compromised. As such, we recommend pursuing the following course of action in a timely manner: l l l l Follow-Up Meeting Meet with Forensic at your earliest convenience to further discuss our investigation findings and recommended next steps, and to begin to develop a plan for further action. The action plan will outline the following: Establish Project remediation goals Prioritize nonconforming conditions according to risk Identify available repair options and strategies Formulate a final repair strategy using established budgets in relation to remediation goals Complete replacement of all deck waterproofing components The damage found at most of the deck investigative openings was quite extensive and in need of immediate repair. If these repairs are deferred the damaged structural components will continue to deteriorate. If continued deterioration occurs these repairs will become more costly, result in imminent collapse concerns, and pose life and safety risks. Consult Structural Engineer The 2nd floor decks on the front elevation are supported by cantilevered TJI floor joists. Many of the floor joists have seen extensive damage. Cantilevered framing members are extremely difficult and costly to replace. Repairs to these damaged floor joists should be made only under the direction of a licensed structural engineer. Preliminary Repair Assessment (PRA) Have Forensic generate a PRA for the Property, which will provide an outline of the steps necessary to remediate the conditions identified throughout this report. The PRA can then be used to solicit repair bids in order to analyze initial cost assessments provided by bidding contractors. Due to the limited nature of Forensic s investigation scope, additional measures may be required in order to develop an accurate PRA. These additional measures should include Additional Investigation Have Forensic return to examine additional inspection openings (IOs) at select locations throughout the Property s building envelope assemblies. Forensic found that many of the defective building envelope conditions were not consistent. Since construction methods seam to differ from building to building it is difficult to comprise a repair method that will be all encompassing without requiring 100% replacement. Additional Investigations can also be beneficial for comprising a final and more accurate repair cost. Attic and Crawlspace Review At the time of additional investigation, have Forensic perform a visual representative review of the Property s under-floor crawlspaces, basements, and attic cavities. Visual review of these locations will allow Forensic to more effectively document and evaluate the presence of sub-grade water leakage, structural concerns, ventilation concerns, moisture accumulation, and/or microbial growth (if any) at the Property. Water Leakage Replication Testing Have Forensic return to observe pressurized chamber testing performed on select fenestration assemblies throughout the Property in order to simulate environmental conditions that have the potential to facilitate water leakage in an attempt to re-create water leakage pathways. Pressurized chamber testing should be conducted by a qualified testing agency in general conformance with the test methods outlined in ASTM E1105 Standard Test Method for Field Determination of Water Penetration of Installed Exterior Windows, Skylights, Doors and Curtain Walls, by Uniform or Cyclic Static Air Pressure Difference. PAGE 6

7 We appreciate your confidence in Forensic and we look forward to addressing any questions or concerns that you may have regarding the contents of this report. Please do not hesitate to contact Forensic at (503) or if we can be of further assistance. Thank you. Respectfully submitted, FORENSIC BUILDING CONSULTANTS Chad Fackler Project Manager and Building Science Consultant Director of Investigative and Litigation Services Building Science Specialist Toby C. White, Vice President and Director of Technical Services PAGE 7

8 BACKGROUND INFORMATION Building Occupancy Type: Multi-family townhomes # of Buildings: 10 # of Stories: 2 # of Units: 76 Reported Construction Date: 2006 Building Permit Issue Date 4 : TBD Description of Exterior Wall Assemblies: n n n n n Brick veneer w/ 30 lb felt 2-coat stucco Fiber cement lap siding and shingles (believed to be James Hardie) Wood trim members, exterior sealant joints, and sheet metal flashing Paper-based waterresistive barrier (WRB believed to be Super JumboTex, manufactured by Fortifiber) Description of Roof Assemblies: n n n n Asphalt roofing shingles (manufacturer TBD) Wood trim members, exterior sealant joints, and sheet metal flashing Felt-based roof underlayment (manufacturer TBD) Plywood roof sheathing and wood framing members n Oriented strand board (OSB) wall sheathing and wood framing members Description of Fenestration Assemblies: n n n Vinyl flange-mounted window (believed to be manufactured by Jones Paint and Glass (JG-1) a member of the American Architectural Manufacturers Association AAMA) Wood framed exterior inswing French doors. Manufacturer unknown. Flexible flashing at fenestration rough openings (believed to be mix of SK-10 and MoistStop by Fortifiber) Description of Deck Assemblies: n n n n n Steel guardrail assemblies Tile surface and cementitious coating Sheet metal flashing No waterproofing membrane on most decks Plywood deck sheathing and TJI framing members PAGE 8

9 PROPERTY SITE The aerial image below, obtained from Google Maps, illustrates the overall site conditions at the Property with the investigative opening noted. Note that this image is oriented so that North corresponds with the top of the page. PAGE 9

10 PROPERTY ELEVATIONS The photos below illustrate the typical building elevations at the Property. Note that elevations may be referred to as Front, Left, Rear, & Right, throughout this report, rather than North, West, South, & East. Overview: Typical Front Elevation PAGE 10

11 Overview: Typical Right Elevation PAGE 11

12 Overview: Typical Rear Elevation PAGE 12

13 Overview: Typical Left Elevation PAGE 13

14 Exterior Assemblies: Observations & Discussion PAGE 14

15 1. DECK OBSERVATIONS 1.1. DECK OBSERVATIONS AND RESULTANT DAMAGE Overview of decks (typical) Moisture staining on the underside of decks Condition indicates moisture intrusion from the top side of the deck and collecting in the framing cavity Omitted waterproofing beneath deck coverings Condition fails to provide adequate moisture protection for underlying deck assembly components. Notice corroded fasteners and reinforcing lath. PAGE 15

16 1. DECK OBSERVATIONS Additional example of condition shown previously. Note omitted waterproofing over drip edge flashing Discontinuous waterproofing at deckto-wall interface Condition fails to provide adequate incidental water protection for underlying deck assembly components. Note open void and corroded flashing. Additional example of condition shown previously, illustrating open voids in deck to wall flashing which facilitates moisture infiltration into the deck assembly. PAGE 16

17 1. DECK OBSERVATIONS Un-sealed penetration through horizontal deck surface Condition facilitates water infiltration into deck assembly. Additional example of condition shown previously, illustrating un-sealed fasteners and delaminated coating. Additional example of condition shown previously, illustrating un-sealed and corroded fasteners. PAGE 17

18 1. DECK OBSERVATIONS Omitted or discontinuous flashing diverter at deck-to-wall flashing termination Condition fails to adequately convey surface drainage away from wall interface and increases likelihood of water infiltration into exterior wall assembly. Close-up of location shown previously, illustrating omitted diverter and damage of deck framing PAGE 18

19 1. DECK OBSERVATIONS SMACNA requirements for deck-to-wall flashing termination, illustrating proper installation of flashing diverter to convey surface drainage away from deck-to-wall interface Omitted or discontinuous sill pan flashing at door threshold adjacent to membrane deck Condition impedes incidental water egress and facilitates water infiltration into deck and exterior wall assemblies at door threshold location. During our investigation, many home owners had reported water flowing into their homes under the deck doors. ASTM E2112 requirements for proper sill pan flashing construction at door threshold. PAGE 19

20 1. DECK OBSERVATIONS Less than 1-2 clearance between cladding and deck surface Condition impedes incidental water egress and facilitates moisture accumulation within exterior wall assembly. Additional example of condition shown previously, illustrating inadequate cladding clearances Less than 2% positive deck wearing surface slope Condition impedes proper conveyance of surface drainage away from structure, increasing likelihood of water infiltration into deck and exterior wall assemblies..2 degrees of slope convers to.35% slope. PAGE 20

21 1. DECK OBSERVATIONS Exhaust vent termination not tightlined to exterior through deck TJI bay Condition impedes outdoor discharge of moisture-laden exhaust air and facilitates moisture accumulation within floor framing cavity, increasing likelihood of condensation events Resultant Damage Resultant Damage PAGE 21

22 1. DECK OBSERVATIONS Resultant Damage Damage has extended to the interior of the building on the affected floor joists Resultant Damage Resultant Damage PAGE 22

23 1. DECK OBSERVATIONS Resultant Damage Leaks from the deck above have caused damage to the brick below resulting in more costly repairs as the condition continues to deteriorate. Close-up of location shown previously, illustrating moisture staining and cracks in the brick. Moisture entering the brick from above can freeze causing the excessive cracks seen here. PAGE 23

24 2. ROOF DIVERTER OBSERVATIONS 2.1. ROOF TO WALL OBSERVATIONS AND RESULTANT DAMAGE Omitted or discontinuous kick-out flashing at roof-to-wall step flashing termination Condition fails to adequately convey surface drainage away from wall interface and increases likelihood of water infiltration into exterior wall assembly. Building code requirements for roof-to-wall step flashing termination, illustrating proper installation of kick-out flashing to convey surface drainage away from roof-to-wall interface Moisture-deteriorated wall assembly components Exterior wall sheathing exhibits damage below omitted diverter flashing. Damage results from sustained presence of moisture due to water leakage and/or moisture accumulation within exterior wall assembly. PAGE 24

25 2. ROOF DIVERTER OBSERVATIONS Close-up of location shown previously, illustrating damage resulting from omitted diverter flashing Less than 1-2 clearance between siding and roof surface Condition impedes incidental water egress and facilitates moisture accumulation within exterior wall assembly. The use of J-Channel for the siding termination facilitates a larger volume of water collecting in the channel termination. Tis is not an approved installation method for this cladding type Less than 1-2 clearance between stucco and roof surface Condition impedes incidental water egress and facilitates moisture accumulation within exterior wall assembly. PAGE 25

26 2. ROOF DIVERTER OBSERVATIONS Close-up of location shown previously, illustrating moisture staining resulting from improperly constructed diverter flashing. PAGE 26

27 3. WINDOW AND DOOR OBSERVATIONS Omitted dynamic sealant joint between dissimilar materials Condition fails to allow for dimensional movement of adjacent siding components and facilitates deflection of siding and or window. Un-sealed transitions from building components promote moisture intrusion. Note: The unique use of J-Channel with fiber cement cladding is not a manufacturer approved installation method. The use of J-channel with fiber cement cladding will promote moisture absorption into the cladding and decrease the serviceable life of this material. Additional example of condition shown previously, illustrating omitted sealant and avenue for moisture intrusion Omitted head flashing at window Omitted head flashing at window negates incidental water egress within wall assembly. Note: The unique use of J-Channel with fiber cement cladding is not a manufacturer approved installation method. The use of J-channel with fiber cement cladding will promote moisture absorption into the cladding and decrease the serviceable life of this material. PAGE 27

28 3. WINDOW AND DOOR OBSERVATIONS Omitted or discontinuous sill pan flashing at door threshold adjacent to membrane deck Condition impedes incidental water egress and facilitates water infiltration into deck and exterior wall assemblies at door threshold location. During our investigation, many homeowners had reported water flowing into their homes under the deck doors. ASTM E2112 requirements for proper sill pan flashing construction at door threshold Moisture damaged door assembly All of the wood door assemblies showed some level of deterioration due to moisture absorption. PAGE 28

29 \ SUMMER VILLAGE TOWNHOMES 3. WINDOW AND DOOR OBSERVATIONS Additional example of moisture damaged door assembly Cracked fenestration mounting flange Damage results from improper fenestration installation and/or fastener schedule Omitted or discontinuous sealant bedding beneath fenestration mounting flange Condition fails to provide adequate air leakage control and facilitates moisture transport through exterior wall assembly at fenestration rough opening. PAGE 29

30 4. MASONRY VENEER Less than 1/4" clearance between brick and vinyl fenestration frame Condition fails to allow for installation of properly dimensioned dynamic sealant joint to accommodate differential thermal movement between dissimilar materials, resulting in premature sealant failure. Additional example of condition shown previously, illustrating lack of clearance between vinyl window and brick cladding Less than 15 positive slope on projecting brick surface Condition impedes surface drainage away from wall coverings, increasing likelihood of water infiltration into exterior wall assembly. Note: 6.8% converts to 3.89 PAGE 30

31 4. MASONRY VENEER Omitted or discontinuous flashing atop brick water table at horizontal cladding transition Condition fails to compartmentalize dissimilar cladding components, impedes incidental water egress, and facilitates moisture accumulation within exterior wall assembly. Additional example of condition shown previously, illustrating discontinuous water table flashing. SMACNA requirements for proper installation of metal flashing atop masonry veneer. Note installation of up-turned end dam at butted flashing termination and proper integration of flashing vertical back leg behind WRB, permitting incidental water egress from within exterior wall assembly. PAGE 31

32 4. MASONRY VENEER Omitted up-turned end dam at butted flashing termination Condition fails to compartmentalize dissimilar cladding components, impedes incidental water egress, and facilitates moisture accumulation within exterior wall assembly Cracked mortar in brick Damage likely results from a combination of omitted diverter flashing and insufficient water table flashing. Cracking in masonry can occur when moisture is absorbed by the brick and subsequently freezes thus expanding and cracking the brick. Additional example of condition shown previously, illustrating cracked masonry. PAGE 32

33 4. MASONRY VENEER Damage resulting from inadequate flashing above brick Deteriorated WRB due to moisture intrusion. Additional example of condition shown above. Moisture staining noted on OSB. PAGE 33

34 5. EXTERIOR WEATHER WALL PROTECTION 5.1. IMPROPER CLADDING INSTALLATION Omitted, sealed, or blocked weep provisions Condition prevents evacuation of incidental moisture away from building components. Additional example of condition shown previously, illustrating omitted weep provisions. Condition fails to compartmentalize dissimilar cladding components, impedes incidental water egress, and facilitates moisture accumulation within exterior wall assembly Omitted or improperly constructed dynamic sealant joints. Condition fails to accommodate thermal movement between dissimilar materials and allows avenues for moisture intrusion. PAGE 34

35 5. EXTERIOR WEATHER WALL PROTECTION Additional example of condition shown previously, illustrating omitted sealant joints Improperly installed stucco and accessories Open voids in stucco allow for moisture infiltration. Note: omitted casing bead at stucco terminations. This condition promotes premature failure of the stucco system. Additional example of condition shown previously, illustrating exposed framing and moisture staining on stucco. Note: omitted casing bead at stucco terminations. This condition promotes premature failure of the stucco system. PAGE 35

36 5. EXTERIOR WEATHER WALL PROTECTION Stucco reinforcing lath exposed on the back side of the stucco. Lath should be located at the center of the stucco assembly. This condition promotes the potential for excessive cracking in the stucco system. Deteriorated building envelope components due to moisture infiltrations caused by the above mentioned deficiencies INADEQUATE FLASHING, WRB, AND FLEXIBLE FLASHINGS Less than 2 overlap of flashing components at splice joint Condition facilitates water infiltration into exterior wall assembly and fails to provide adequate incidental water protection for underlying building components. PAGE 36

37 5. EXTERIOR WEATHER WALL PROTECTION Less than 4-5 height of flashing vertical back leg at roof-to-wall interface Condition fails to allow for proper WRB overlap or provide adequate incidental water protection for underlying exterior wall assembly components. Additional example of condition shown previously, illustrating insufficient height of roof to wall step flashing Discontinuous or omitted WRB Condition fails to adequately protect building wall from moisture intrusion. PAGE 37

38 5. EXTERIOR WEATHER WALL PROTECTION Additional example of condition shown previously, illustrating omitted WRB over window flange Reverse-lap of flashing vertical back leg over exterior wall coverings Condition facilitates water infiltration behind flashing back leg and fails to provide adequate weather protection for underlying components Discontinuous flashing at the roof to wall hip Condition facilitates water infiltration behind flashing back leg and fails to provide adequate weather protection for underlying components. Note the open void in the flashing directly at the roof line. PAGE 38

39 5. EXTERIOR WEATHER WALL PROTECTION 5.3. CONCRETE FLAT WORK CONCERNS Cracked and settled concrete concerns Cracked and settled concrete can be indications of more sever geotechnical concerns. These conditions also create trip and fall hazards that should be addressed to prevent personal injury. Additional example of condition noted above showing cracks in the driveway and garage floor slab. PAGE 39

40 SUMMARY OF OBSERVATIONS The summary below provides a listing of the conditions noted throughout the Observations & Discussion photo sections above. For additional information regarding a specific condition, please refer to appropriate Observations & Discussion photo section of this report. 1. Deck Observations 1.1. Deck observations and Resultant Damage Overview of decks (typical) Moisture staining on the underside of decks Omitted waterproofing beneath deck coverings Discontinuous waterproofing at deck-to-wall interface Un-sealed penetration through horizontal deck surface Omitted or discontinuous flashing diverter at deck-to-wall flashing termination Omitted or discontinuous sill pan flashing at door threshold adjacent to membrane deck Less than 1-2 clearance between cladding and deck surface Less than 2% positive deck wearing surface slope Exhaust vent termination not tight-lined to exterior through deck TJI bay Resultant Damage Resultant Damage Resultant Damage Resultant Damage Resultant Damage Resultant Damage 2. Roof Diverter Observations 2.1. Roof to Wall Observations and resultant Damage Omitted or discontinuous kick-out flashing at roof-to-wall step flashing termination Moisture-deteriorated wall assembly components Less than 1-2 clearance between siding and roof surface Less than 1-2 clearance between stucco and roof surface 3. Window and Door Observations Omitted dynamic sealant joint between dissimilar materials Omitted head flashing at window Omitted or discontinuous sill pan flashing at door threshold adjacent to membrane deck Moisture damaged door assembly Cracked fenestration mounting flange Omitted or discontinuous sealant bedding beneath fenestration mounting flange 4. Masonry Veneer Less than 1/4" clearance between brick and vinyl fenestration frame PAGE 40

41 Less than 15 positive slope on projecting brick surface Omitted or discontinuous flashing atop brick water table at horizontal cladding transition Omitted up-turned end dam at butted flashing termination Cracked mortar in brick Damage resulting from inadequate flashing above brick 5. Exterior Weather Wall Protection 5.1. Improper Cladding Installation Omitted, sealed, or blocked weep provisions Omitted or improperly constructed dynamic sealant joints Improperly installed stucco and accessories 5.2. Inadequate flashing, WRB, and Flexible flashings Less than 2 overlap of flashing components at splice joint Less than 4-5 height of flashing vertical back leg at roof-to-wall interface Discontinuous or omitted WRB Reverse-lap of flashing vertical back leg over exterior wall coverings Discontinuous flashing at the roof to wall hip 5.3. Concrete Flat Work Concerns Cracked and settled concrete concerns PAGE 41

42 Appendix A: Important Information PAGE 42

43 APPENDIX A1: DISCLOSURES AND LIMITATIONS 1. Nonconforming Conditions: Forensic defines nonconforming conditions as construction conditions that fail to conform with the Property s applicable building code requirements, project documents available for Forensic s review, referenced standards and other industry association standards, as well as sound construction and weatherproofing principles. Because the Property s building permit issue date was not known by Forensic at the time of our presence on site at the Property or prior to the time that this report was generated, the identification of nonconforming conditions throughout the course of our investigation of the Property has been based on current building code requirements, industry association standards, and typical building product manufacturer installation requirements. 2. Project Documents: Within the scope of Forensic s services at the Property, project documents include (but are not necessarily limited to) the following: construction document drawings, project manual or written specifications, submittals or test reports, and building product manufacturer information. 3. Review of Project Documents: To assist Forensic s evaluation of the design intent or product manufacturers requirements for the installed construction assemblies at the Property, the following Project documents were made available for Forensic s review at the time of our presence on site at the Property or prior to the time that this report was generated: a. Project documents were not made available for Forensic s review at the time of our presence on site at the Property or prior to the time that this report was generated. 4. Service History Information: Within the scope of Forensic s services at the Property, service history information includes (but is not necessarily limited to) the following: accounts of previous water leakage or symptoms of leaks reported by building owners or occupants, maintenance or repair records, or previous investigation reports by others. 5. Review of Service History Information: To assist Forensic s evaluation of the previous occurrence of water leakage through the Property s building envelope assemblies, the following service history information was made available for Forensic s review at the time of our presence on site at the Property or prior to the time that this report was generated: a. Service history information was not made available for Forensic s review at the time of our presence on site at the Property or prior to the time that this report was generated. 6. Investigation Methodology: Forensic s investigation techniques consisted of examining select building components and/or systems throughout the Property s building envelope assemblies at locations where our experience has shown us that nonconforming construction conditions, water leakage, and/or property damage have a high likelihood of existing or developing. However, because Forensic s investigation did not include the complete removal of the Property s exterior wall coverings, roof coverings, fenestration (door & window) assemblies, and any other building components or systems overlaying the Property s underlying structure, water-resistive barrier (WRB), and other concealed building envelope assemblies, there remains the possibility of the existence of concealed property damage, water leakage, and/or nonconforming construction conditions that Forensic could neither detect, document, nor report on. 7. Visual Review: In general conformance with the investigation methods described by ASTM E 2128 Standard Guide for Evaluating Water Leakage of Building Walls, and/or ASTM D 7053 Standard Guide for Determining and Evaluating Causes of Water Leakage of Low-Sloped Roofs, Forensic performed a visual review of the unconcealed and accessible surfaces of the building components, systems, and locations included within the scope of Forensic s services at the Property. The objectives of Forensic s visual review were to document the existing construction conditions at the Property, to identify workmanship and/or building product deficiencies that have the potential to compromise the weather resistance of the Property s building envelope assemblies, and to formulate an initial hypotheses regarding the causes of evident weather resistance deficiencies or damage at the Property. 8. Inspection Openings: In general conformance with the investigation methods described by ASTM E 2128 Standard Guide for Evaluating Water Leakage of Building Walls, and/or ASTM D 7053 Standard Guide for Determining and Evaluating Causes of Water Leakage of Low-Sloped Roofs, Forensic also examined concealed building envelope assemblies at multiple limited inspection opening (IO) locations at the Property. Such investigation enabled Forensic to better verify the presence of concealed conditions within the Property s building envelope assemblies while documenting and evaluating the condition, sequencing, and integration of concealed building envelope components and systems. 9. Water Leakage Replication Testing: At no time during Forensic s investigation was water leakage replication testing performed to simulate environmental conditions that have the potential to facilitate water leakage in an attempt to re-create water leakage pathways at select building envelope locations. 10. Report Revisions: Forensic reserves the rights to amend, modify, and/or re-issue this report as more information becomes available for Forensic s review, or as additional investigation proceeds. This report is intended solely for use by Forensic s client and should, in any event, be reproduced only in its entirety, with this disclaimer included. PAGE 43

44 End of Document PAGE 44

WeatherSmart Air Barrier Installation Guide

WeatherSmart Air Barrier Installation Guide WeatherSmart Air Barrier Installation Guide 1 The intent of this document is to provide a guide for the installation of WeatherSmart as both a Weather Resistive Barrier (W.R.B.) and an Air Barrier Material

More information

INSTALLING WATER-RESISTIVE BARRIERS & FLASHING

INSTALLING WATER-RESISTIVE BARRIERS & FLASHING INSTALLING WATER-RESISTIVE BARRIERS & FLASHING IN A TWO-LAYER STUCCO APPLICATION Fortifiber Building Systems Group provides this guide to assist installers by demonstrating a two-layer installation of

More information

Forensics Engineering 8th Congress Forging Forensic Frontiers November 29 December 2, 2018, Austin, TX

Forensics Engineering 8th Congress Forging Forensic Frontiers November 29 December 2, 2018, Austin, TX This paper was published at the Forensic Engineering 8th Congress, held November 29-December 2, 2018 in Austin, TX. The published version of this paper is available for purchase and download at: https://ascelibrary.org/doi/book/10.1061/9780784482018

More information

PROPERTY PRESERVATION AND CAPITAL PLANNING

PROPERTY PRESERVATION AND CAPITAL PLANNING PROPERTY PRESERVATION AND CAPITAL PLANNING Overview What am I looking for Remaining Useful Life Estimating Planning TERMINOLOGY Shake Siding Service Head Barge Board Soffit / Overhang Belly Band Knee Brace

More information

2019 IAQA Annual Meeting

2019 IAQA Annual Meeting Daniel Stih, CMC. CIEC Healthy Living Spaces Stanley Yeskolski CIEC, CMC Investigative Inspection Services Inc. 2 Purpose The presentation will provide a over view of: Installation Details Problem Areas

More information

The better way to build TM. Installation Manual NAILBASE PANELS

The better way to build TM. Installation Manual NAILBASE PANELS The better way to build TM Installation Manual PANELS November 2018 SIPs Installation Manual Table of Contents Topics General Requirements................................... 3 Materials..............................................

More information

Stucco Moisture Inspection Report

Stucco Moisture Inspection Report Website:www.ibgoodinspector.com E-Mail:support@ibgoodinspector.com January 11, 2006 Stucco Moisture Inspection Report Property Address 123 Our Street OurTown, USA 12345 Report Ordered By: Mr. & Mrs. Client

More information

SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE:

SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE: IRC CODE UPDATES TO: RESIDENTIAL BUILDING CONTRACTORS FROM: GARY STABER, BUILDING OFFICIAL SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE: 6/1/2003 INTERNATIONAL RESIDENTIAL CODE (IRC) APPLICABILITY:

More information

GLOBAL PROPERTY INSPECTIONS TECHNICAL BULLETIN

GLOBAL PROPERTY INSPECTIONS TECHNICAL BULLETIN GLOBAL PROPERTY INSPECTIONS TECHNICAL BULLETIN TM June 1, 2002 TOPIC: Exterior Coverings This is the sixth in a series of technical bulletins in which an over-all examination of the home will be discussed

More information

FMA/WDMA FMA/WDMA

FMA/WDMA FMA/WDMA FMA/WDMA 250-10 FMA/WDMA 250-10 Standard Practice for the Installation of Non-Frontal Flange Windows with Mounting Flanges for Surface Barrier Masonry Construction for Extreme Wind / Water Conditions FENESTRATION

More information

Exterior Elevated Elements Inspection Guidelines

Exterior Elevated Elements Inspection Guidelines Exterior Elevated Elements Inspection Guidelines Planning and Development 1. Guideline Purpose These guidelines are intended to assist practicing professionals in complying with Berkeley Municipal Code

More information

A M E R I C A N A R C H I T E C T U R A L M A N U F A C T U R E R S A S S O C I A T I O N

A M E R I C A N A R C H I T E C T U R A L M A N U F A C T U R E R S A S S O C I A T I O N A M E R I C A N A R C H I T E C T U R A L AAMA 2410-13 Standard Practice for Installation of Windows with an Exterior Flush Fin Over an Existing Window Frame M A N U F A C T U R E R S A S S O C I A T I

More information

Aqua Coast Engineering

Aqua Coast Engineering Aqua Coast Engineering Ltd. P.O. Box 1367 Station A Delta, B.C. V4M 3Y8 Tel: (604)948-0958 Fax: 604)948-0959 September 1, 2011 Matthew Cheng File#:11145 Matthew Cheng Architect Inc. Fax: 604-731-3908 Unit

More information

Insulation. First Revison October DC14 Drainage Mat INSTALLATION GUIDE FOR RESIDENTIAL & COMMERCIAL APPLICATIONS

Insulation. First Revison October DC14 Drainage Mat INSTALLATION GUIDE FOR RESIDENTIAL & COMMERCIAL APPLICATIONS Insulation First Revison October 2016 DC14 Drainage Mat INSTALLATION GUIDE FOR RESIDENTIAL & COMMERCIAL APPLICATIONS 1. General Information This Guide describes the use of Kingspan GreenGuard DC14 Drainage

More information

U.S. EDITION RESIDENTIAL CONSTRUCTION DETAILS SAMPLE. A visual guide to construction detailing. Emma Walshaw

U.S. EDITION RESIDENTIAL CONSTRUCTION DETAILS SAMPLE. A visual guide to construction detailing. Emma Walshaw RESIDENTIAL CONSTRUCTION DETAILS U.S. EDITION A visual guide to construction detailing Emma Walshaw Contents INTRODUCTION 4 PRINCIPLES OF CONSTRUCTION DETAILING 6 FOUNDATIONS 9 PRINCIPLES OF FOUNDATION

More information

Primary Concerns and Defects

Primary Concerns and Defects Primary Concerns and Defects Primary Concerns and Defects: Home Inspector Observations: Where to Look. What to Look For. What Observed condition may mean. Primary Concerns The points to be inspected per

More information

Building Construction and Water Intrusion

Building Construction and Water Intrusion Building Construction and Water Intrusion RAY CHOY-MARSHALL GOVAN ASSOCIATES an architectural corporation ray_choy-marshall@sbcglobal.net 2930 camino diablo, suite 210, walnut creek, ca 94597 2004 Design

More information

A. Section includes fluid applied, vapor permeable membrane air barriers.

A. Section includes fluid applied, vapor permeable membrane air barriers. Master Construction Specifications Insert Project Name SECTION 072726 FLUID APPLIED MEMBRANE AIR BARRIERS PART 1 GENERAL 1.1 SUMMARY A. Section includes fluid applied, vapor permeable membrane air barriers.

More information

2002 Advanced Building Products, Inc., P.O. Box 98, Springvale, Maine TEL: ; FAX: ; WEBSITE:

2002 Advanced Building Products, Inc., P.O. Box 98, Springvale, Maine TEL: ; FAX: ; WEBSITE: SECTION 07651 FLEXIBLE COPPER SHEET FLASHINGS Advanced Building Products, Inc. manufacturer many types of flexible copper sheet flashings. Due to their ductility, high tensile strength, and resistance

More information

SURESILL WATER MANAGEMENT GUIDE

SURESILL WATER MANAGEMENT GUIDE THE SURE LEVEL OF PROTECTION SURESILL WATER MANAGEMENT GUIDE FOR WINDOWS AND DOORS *1 SLOPED SILL PAN ASSEMBLY Cut the channel plate ¼ smaller than the rough opening. Check the fit with end caps before

More information

BUILDING EXTERIOR SHELL TRAINING

BUILDING EXTERIOR SHELL TRAINING BUILDING EXTERIOR SHELL TRAINING Course Handout Part 1 Background and Insurance Issues (19min) Causes of Building Exterior Shell Problems Bad Design Poor Planning Failure to Follow Manufacturer s Recommendations

More information

Stucco Detailing for Buildings With Unique Geometry

Stucco Detailing for Buildings With Unique Geometry Stucco Detailing for Buildings With Unique Geometry Richard W. Mosco, AIA Wiss, Janney, Elstner Associates, Inc. 225 south lake ave., Pasadena, Ca 91101 Phone: 626-696-4650 626-696-4699 e-mail: rmosco@wje.com

More information

FMA / AAMA / WDMA Installation Committee Update. Jim Katsaros / DuPont Building Innovations FMA Installation Committee April 24, 2012

FMA / AAMA / WDMA Installation Committee Update. Jim Katsaros / DuPont Building Innovations FMA Installation Committee April 24, 2012 FMA / AAMA / WDMA Installation Committee Update Jim Katsaros / DuPont Building Innovations FMA Installation Committee April 24, 2012 Topics for discussion. Review & Update on FMA/AAMA/WDMA Window & Door

More information

A. Omega-Lite aluminum-faced composite panels, air and vapor barrier, attachments and sealants.

A. Omega-Lite aluminum-faced composite panels, air and vapor barrier, attachments and sealants. Section 07 42 13 Page 1 PART 1 GENERAL 1.1 SECTION INCLUDES A. Omega-Lite aluminum-faced composite panels, air and vapor barrier, attachments and sealants. 1.2 RELATED SECTIONS A. Section 06112 - Framing

More information

SC-01 Cross-Section. Cement Board Substrate Master Wall Mesh and Base Coat Superior Finish

SC-01 Cross-Section. Cement Board Substrate Master Wall Mesh and Base Coat Superior Finish Master Wall Mesh and Base Coat Plastic Control Joint Accessory, Plastic Components 22027-16 or equal. See notes for placement recommendations Notes: Control joints are required and should be located by

More information

Corium Brick Rainscreen System Specifications

Corium Brick Rainscreen System Specifications CORIUM BRICK RAINSCREEN SYSTEM PART 1 - GENERAL 1.1 SUMMARY A. Work Included: The Work of this Section shall include but not be limited to the following: 1. Corium brick plates 2. Galvanized and coated

More information

FirstEnergy Program Overview

FirstEnergy Program Overview FirstEnergy Program Overview Builder incentives $400 per unit + $0.10/kWh in projected savings Eligibility Located in service area of a FirstEnergy Utility Certificate of Occupancy Dates: FirstEnergy Ohio

More information

Building Science Control Layer Glossary. Façade Visible exterior face of a building, usually vertical or nearly so, but imprecisely used.

Building Science Control Layer Glossary. Façade Visible exterior face of a building, usually vertical or nearly so, but imprecisely used. It is far more important than often appreciated to use precise, unambiguous, clear definitions when describing aspects of buildings, building enclosures, and building science performance. The following

More information

SECTION STAINLESS STEEL WALL PANELS

SECTION STAINLESS STEEL WALL PANELS SECTION 07400 PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Dry joint, Rainscreen stainless steel wall panel system. 2. Accessories including attachments, clips, sub girts, shims, and fasteners 3.

More information

Carroll County Bureau of Permits and Inspection Residential Code Compliance Guidelines Detached Garage

Carroll County Bureau of Permits and Inspection Residential Code Compliance Guidelines Detached Garage Carroll County Bureau of Permits and Inspection Residential Code Compliance Guidelines Detached Garage The following list of code requirements is intended to assist you in complying with the Code of Public

More information

Revised January buildingscience.com. Water Management Details. Housewraps/Flashings/Windows buildingscience.com

Revised January buildingscience.com. Water Management Details. Housewraps/Flashings/Windows buildingscience.com Revised January 2007 Housewraps/Flashings/Windows BSP-020: for Residential Buildings Table of Contents Introduction... 4 Water Management Concept...4 Risk Factors... 4 Building Paper/Housewraps as the

More information

Gensler 2014/06/16 Hertz Global Headquarters ISSUE FOR BUILDING PERMIT Estero, Florida SECTION

Gensler 2014/06/16 Hertz Global Headquarters ISSUE FOR BUILDING PERMIT Estero, Florida SECTION SECTION 072700 VAPOR PERMEABLE AIR BARRIER LIQUID MEMBRANE PART 1 GENERAL 1.1 GENERAL REQUIREMENTS A. The Work of this Section, as shown or specified, shall be in accordance with the requirements of the

More information

Chapter 2 Understanding The Problem

Chapter 2 Understanding The Problem Chapter 2 Understanding The Problem What Causes Most Of The Problems With Stucco? EIFS was originally intended to seal and insulate the exterior of the home from the elements. Problems occur when poorly

More information

CALIFORNIA COMMERCIAL BUILDING INSPECTOR CONTENT OUTLINE 01. GENERAL ADMINISTRATION 6% Project Administration 1%

CALIFORNIA COMMERCIAL BUILDING INSPECTOR CONTENT OUTLINE 01. GENERAL ADMINISTRATION 6% Project Administration 1% CALIFORNIA COMMERCIAL BUILDING INSPECTOR CONTENT OUTLINE EXAM ID: I1 80 multiple-choice questions 3-1/2-hour time limit Open book 01. GENERAL ADMINISTRATION 6% 0101. Project Administration 1% Verify that

More information

BULLETIN FROM THE FIRST COAST CHAPTER ICC~BOAF

BULLETIN FROM THE FIRST COAST CHAPTER ICC~BOAF FIRST COAST CHAPTER INTERNATIONAL CODE COUNCIL (ICC) AND BUILDING OFFICIALS ASSOCIATION OF FLORIDA, INC. (BOAF) SERVING BAKER, BRADFORD, CLAY, DUVAL, NASSAU, PUTNAM, ST. JOHNS & UNION COUNTIES BULLETIN

More information

SECTION METAL FRAMED SKYLIGHT. A. Engineering, preparation of fabrication drawings and structural calculations for the entire skylight system.

SECTION METAL FRAMED SKYLIGHT. A. Engineering, preparation of fabrication drawings and structural calculations for the entire skylight system. SECTION 08625 METAL FRAMED SKYLIGHT PART 1 GENERAL 1.01 SECTION INCLUDES: A. Engineering, preparation of fabrication drawings and structural calculations for the entire skylight system. B. Fabrication

More information

Limited Leak Assessment

Limited Leak Assessment Website:www.moistureconsultantsinc.com E-Mail:support@moistureconsultantsinc.com December 2th, 2005 Limited Leak Assessment Property Address US Naval Facility Building 484 Panama City Beach, Florida Report

More information

OCS ONE COAT STUCCO A custom blend of Portland cement, sand, extenders, fiber reinforcement and modifiers.

OCS ONE COAT STUCCO A custom blend of Portland cement, sand, extenders, fiber reinforcement and modifiers. OCS ONE COAT STUCCO A custom blend of Portland cement, sand, extenders, fiber reinforcement and modifiers. Designed to save material by functioning as an exterior cladding in thicknesses ranging from 3/8

More information

Commercial Flashing Details

Commercial Flashing Details This technical note illustrates many of the most common flashing details for commercial buildings. The purpose for flashing is to direct moisture to the exterior and in so doing, prevent moisture from

More information

Stone and Masonry Veneer

Stone and Masonry Veneer Stone and Masonry Veneer R703.7 Stone and masonry veneer, general. Stone and masonry veneer shall be installed in accordance with this chapter, Table R703.4 and Figure R703.7. These veneers installed over

More information

Water Management & Damage Prevention: A Guide for Homeowners

Water Management & Damage Prevention: A Guide for Homeowners Water Management & Damage Prevention: A Guide for Homeowners This article provides homeowners with basic information to make these decisions and take the appropriate actions to keep their homes dry and

More information

SECTION SELF-ADHERING SHEET FLASHING

SECTION SELF-ADHERING SHEET FLASHING MANUFACTURER S GUIDE SPECIFICATIONS SECTION 076526 SELF-ADHERING SHEET FLASHING 900 Hensley Lane Wylie TX 75098 800-527-7092 www.carlisleccw.com 604129 03.24.15 Carlisle, Flexphalt, Sure-Seal and CAV-GRIP

More information

Keene Building Products

Keene Building Products Keene Building Products Keene Building Products is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported

More information

Guideline for Building Envelope Commissioning: New Buildings

Guideline for Building Envelope Commissioning: New Buildings Guideline for Building Envelope Commissioning: New Buildings Introduction Building envelope failures may arise from inadequacies in the design, construction and operation of buildings and appear to be

More information

Groundwater Seepage. Causes of Basement Seepage and Leaks Hydrostatic Pressure

Groundwater Seepage. Causes of Basement Seepage and Leaks Hydrostatic Pressure Groundwater Seepage The following guide can be used by you and your crews when assessing seepage at a property. Bear in mind that this guide is not all-inclusive, and should be used in a supplementary

More information

RECREATIONAL EAGLE CENTER METAL ROOF ASSESSMENT AND SOLUTION

RECREATIONAL EAGLE CENTER METAL ROOF ASSESSMENT AND SOLUTION RECREATIONAL EAGLE CENTER METAL ROOF ASSESSMENT AND SOLUTION Recreational Eagle Center (00550) La Crosse, WI DSF Project No. 07H1E SEG Project No. 10975 Prepared for Division of State Facilities 101 E.

More information

0103 Plan Reading 4% Read plans to verify the project conforms with the code, approved plans, and construction documents.

0103 Plan Reading 4% Read plans to verify the project conforms with the code, approved plans, and construction documents. Certification: Commercial Building Inspector Exam ID: B2 Scope: A Commercial Building Inspector will be responsible for performing inspections of structures to determine compliance with the various Building

More information

Detail Booklet StoTherm ci XPS

Detail Booklet StoTherm ci XPS Detail Booklet Series 53sxx Steel Frame Construction February 2017 professional, general contractor or builder They should be installed in accordance with those specifications and Sto s instructions Sto

More information

Magnum Board Coatings

Magnum Board Coatings Master Wall Mesh and Base Coat Plastic Control Joint Accessory, Plastic Components 22027-16 or equal. See notes for placement recommendations Notes: Control joints are required and should be located by

More information

Tile on Existing. Viewpoint

Tile on Existing. Viewpoint Viewpoint Tile on Existing Exterior Reinforced Concrete BalconieS By Steven C. Turner Exterior reinforced concrete balconies are often covered by tile set in mortar beds with grouted joints. These installations

More information

Accent is cracked with stains Accent is sloped away from the home Flat accent is not sealed to window

Accent is cracked with stains Accent is sloped away from the home Flat accent is not sealed to window Glossary of Terms Accent Bands/Trim Bands An accent band is decorative stucco trim constructed over a wood or EIFS foam attachment. Trim bands are decorative bands constructed of wood or other material.

More information

Distances are not shown to scale. Existing porch. Community. Building. Distances are not shown to scale

Distances are not shown to scale. Existing porch. Community. Building. Distances are not shown to scale patio and deck 00 Building Two story Four-plex Entrance 0 0 00 Building Single Story Duplex 0 patio Contact Information: Owner: Housing Authority of Yamhill County, NE Dunn Place, McMinnville, OR 9. Contact:

More information

Building Envelope Investigation UTHSCSA - CTRC. San Antonio, Texas. June 20, 2016

Building Envelope Investigation UTHSCSA - CTRC. San Antonio, Texas. June 20, 2016 DRAFT DRAFT Building Envelope Investigation At UTHSCSA - CTRC San Antonio, Texas June 20, 2016 Zero/Six Consulting, LLC 2550 S. IH-35 Ste. 215 Austin, Texas 78739 512.806.0376 z6consulting.com Table of

More information

R-Matte Plus-3: Insulation for the Building Envelope

R-Matte Plus-3: Insulation for the Building Envelope Attic and Crawl Space Applications R-Matte Plus-3 may be applied to the interior face of stud walls or roof rafters within attics and crawl spaces to provide a layer of continuous insulation (ci). Simply

More information

Acrocrete Platinum CI Stucco Typical details for an impact resistant cement plaster stucco system featuring Neopor rigid insulation board

Acrocrete Platinum CI Stucco Typical details for an impact resistant cement plaster stucco system featuring Neopor rigid insulation board Acrocrete Platinum CI Stucco Typical details for an impact resistant cement plaster stucco system featuring Neopor rigid insulation board Acrocrete Platinum CI Stucco Typical details for an impact resistant

More information

Finestone Stucco System

Finestone Stucco System Typical Details Finestone Stucco System Cement Plaster Stucco 1. Typical Finestone Stucco System with Steel Framing 2. Typical Finestone Stucco System with Wood Framing 3. Typical Finestone Stucco System

More information

application instructions

application instructions application instructions FOUNDATIONS 76 & 120 SERIES PRIMED PANEL SIDING ARCHITECTURAL COLLECTION REVERSE BOARD & BATTEN AND STUCCO PANEL SIDING General At the time of manufacture, siding meets or exceeds

More information

SECTION ROOF MOUNTED ATTIC EXHAUST VENT

SECTION ROOF MOUNTED ATTIC EXHAUST VENT SECTION 07 72 00 ROOF MOUNTED ATTIC EXHAUST VENT **This is a CSI Three-Part Specification using CSI MasterFormat 2004-2010 Section Numbers and Titles. This specification must be edited to suit your particular

More information

Administrative Changes

Administrative Changes Revised 11/29/06 Knox County Residential Building Codes Significant Changes From The 1995 CABO One And Two Family Dwelling Code To The 2006 International Residential Code All one and two family dwellings

More information

TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS

TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS AIA General Conditions... GC-1 to GC-44 Amendments to General Conditions... AM-1 to AM-2 Supplements to General Conditions... SU-1 to SU-7 00200 Instructions To Bidders... 1 3 00201 Contractor s Bidding

More information

BUILDING ENCLOSURE COMMISSIONING PLAN PROJECT NAME

BUILDING ENCLOSURE COMMISSIONING PLAN PROJECT NAME BUILDING ENCLOSURE COMMISSIONING PLAN For The PROJECT NAME Building Enclosure Commissioning Plan Overview The purpose of the Building Enclosure Commissioning Plan is to provide a clear and concise roadmap

More information

Brick Walls MTI. Rainscreen Retrofit for. Flood Recovery Hurricane Recovery Restoration Flood Resilient Retrofit. Guide to Wet Flood-Proofing

Brick Walls MTI. Rainscreen Retrofit for. Flood Recovery Hurricane Recovery Restoration Flood Resilient Retrofit. Guide to Wet Flood-Proofing Rainscreen Retrofit for Brick Walls Flood Recovery Hurricane Recovery Restoration Flood Resilient Retrofit Revised 1/14/19 Guide to Wet Flood-Proofing MTI MASONRY TECHNOLOGY INCORPORATED Note: The retrofit

More information

Henri Fennell, CSI/CDT ABX 2015

Henri Fennell, CSI/CDT ABX 2015 Henri Fennell, CSI/CDT ABX 2015 Henri is an architect and building envelope specialist with over forty years of experience in the construction industry. He was a pioneer in the solar industry, introduced

More information

Sentry Stucco Ultra Wall System

Sentry Stucco Ultra Wall System Typical Details Sentry Stucco Ultra Wall System Premium impact and puncture resistant, rain screen design cement plaster stucco system with enhanced water management 1. Typical Sentry Stucco Ultra Wall

More information

Finestone Platinum CI Stucco Typical details for an impact resistant cement plaster stucco system featuring Neopor rigid insulation board

Finestone Platinum CI Stucco Typical details for an impact resistant cement plaster stucco system featuring Neopor rigid insulation board Finestone Platinum CI Stucco Typical details for an impact resistant cement plaster stucco system featuring Neopor rigid insulation board Finestone Platinum CI Stucco Typical details for an impact resistant

More information

SPECIFICATION GUIDELINE

SPECIFICATION GUIDELINE Environmental StoneWorks specification guideline should be used to assist design professionals in the preparation of projects. Edit and delete items that may not be applicable. Verify all referenced section

More information

Building Envelope Enclosures That Work, What Owners Want!

Building Envelope Enclosures That Work, What Owners Want! WEBINAR February 23, 2017 Building Envelope Enclosures That Work, What Owners Want! Will Ikerd, P.E. (TX), LEED AP Webinar Speakers Karl Strand President of Vertical Solutions Consulting Will Ikerd, PE

More information

CTIOA REPORT

CTIOA REPORT CERAMIC TILE INSTITUTE OF AMERICA, INC. 12061 Jefferson Blvd., Culver City, CA 90230-6219 CTIOA REPORT 2003-4-17 SUBJECT: FLASHING DETAILS EXTERIOR TILE DECK CONSTRUCTION By Mark Marsch Preface Having

More information

DIVISION 7 THERMAL AND MOISTURE PROTECTION

DIVISION 7 THERMAL AND MOISTURE PROTECTION DIVISION 7 THERMAL AND MOISTURE PROTECTION UCSC Campus Standards Handbook Waterproofing Standards 07100 1 SECTION 07100: WATERPROOFING STANDARDS A. Guarantee 1. Provide a guarantee on Contractor's letterhead

More information

Building Envelope

Building Envelope 9.36.2. Building Envelope Module 2 BCBC 9.36. 2014 1 Richard Kadulski Architect 9.36.2. Building Envelope Focus is on total building performance, not just thermal insulation Heat transfer and air leakage

More information

CALIFORNIA BUILDING PLANS EXAMINER CONTENT OUTLINE 01. GENERAL ADMINISTRATION 3 % Project Administration 3%

CALIFORNIA BUILDING PLANS EXAMINER CONTENT OUTLINE 01. GENERAL ADMINISTRATION 3 % Project Administration 3% CALIFORNIA BUILDING PLANS EXAMINER CONTENT OUTLINE EXAM ID: I6 80 multiple-choice questions 3-1/2-hour time limit Open book 01. GENERAL ADMINISTRATION 3 % 0101. Project Administration 3% Verify that plans,

More information

Architectural Wall Products Guide Specifications

Architectural Wall Products Guide Specifications Western States Metal Roofing 901 W. Watkins St. Phoenix, AZ 85007 PH: 602-495-0048 FX: 602-261-7726 Architectural Wall Products Guide Specifications FORMED METAL WALL PANELS This Guide Specification is

More information

HIDDEN HOLES IN WOOD FRAMED BALCONY WATERPROOFING

HIDDEN HOLES IN WOOD FRAMED BALCONY WATERPROOFING HIDDEN HOLES IN WOOD FRAMED BALCONY WATERPROOFING ROCCO ROMERO, RA WISS, JANNEY, ELSTNER ASSOCIATES, INC. 960 South Harney St., Seattle, Washington 98108 Phone: 206-622-1441 Fax: 206-622-0701 E-mail: rromero@wje.com

More information

TABLE OF CONTENTS Updated 1/2014 SECTION TITLE DATE

TABLE OF CONTENTS Updated 1/2014 SECTION TITLE DATE TABLE OF CONTENTS SECTION TITLE DATE Division 00 Procurement and Contracting Requirements 000101... Project Title Page 000116... CAD Standards 001116... Invitation to Bid 002113... Instructions to Bidders

More information

FMA/AAMA Standard Practice for the Installation of Windows with Flanges or Mounting Fins in Wood Frame Construction

FMA/AAMA Standard Practice for the Installation of Windows with Flanges or Mounting Fins in Wood Frame Construction A M E R I C A N A R C H I T E C T U R A L FMA/AAMA 100-07 Standard Practice for the Installation of Windows with Flanges or Mounting Fins in Wood Frame Construction M A N U F A C T U R E R S A S S O C

More information

U.S. Department of Housing and Urban Development Office of Policy Development and Research

U.S. Department of Housing and Urban Development Office of Policy Development and Research U.S. Department of Housing and Urban Development Office of Policy Development and Research WATER INTRUSION EVALUATION FOR CAULKLESS SIDING, WINDOW, AND DOOR SYSTEMS WATER INTRUSION - LABORATORY TESTING

More information

Tender No Section St. James - Assiniboia Centennial Pool Fitness Facility Addition Page 1

Tender No Section St. James - Assiniboia Centennial Pool Fitness Facility Addition Page 1 Fitness Facility Addition Page 1 PART 1 GENERAL 1.1 SECTION INCLUDES.1 Extruded aluminum windows with fixed sash..2 Factory glazed..3 Perimeter sealant. 1.2 RELATED SECTIONS.1 Section 05500 - Metal Fabrications.2

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE GRANT NO: UNIVERSITY OF CALIFORNIA, DAVIS DAVIS, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE GRANT NO: UNIVERSITY OF CALIFORNIA, DAVIS DAVIS, CALIFORNIA The following standard specification is intended to be edited according to the specifics of the project. Brackets [ ] and areas shaded in gray [e.g. format] indicate requirements that are optional depending

More information

Installation Guidelines

Installation Guidelines Installation Guidelines The Vertibreak Wall System: Installation Guidelines Rainscreen Insulation for New or Retrofit Construction Applications Vertibreak rainscreen insulation is an expanded polystyrene

More information

Slate. Material description

Slate. Material description Slate Material description Roofing slate is a dense, durable, naturally occurring material that is essentially nonabsorbent. Two properties of slate are cleavage and fracture. It has natural cleavage,

More information

2015 MICHIGAN UNIFORM ENERGY CODE Effective: February 8, 2016

2015 MICHIGAN UNIFORM ENERGY CODE Effective: February 8, 2016 CHEBOYGAN COUNTY DEPARTMENT OF BUILDING SAFETY 870 South Main Street P.O. Box 70 Cheboygan, Michigan 49721 Phone: (231) 627-8813 Fax: (231) 627-8454 www.cheboygancounty.net 2015 MICHIGAN UNIFORM ENERGY

More information

WATERGATE COMMUNITY ASSOCIATION 8 Captain Drive Emeryville, California Office: / Fax: WINDOW REPLACEMENT GUIDELINES

WATERGATE COMMUNITY ASSOCIATION 8 Captain Drive Emeryville, California Office: / Fax: WINDOW REPLACEMENT GUIDELINES WINDOW REPLACEMENT GUIDELINES GENERAL 1. Complete and receive approval for WCA s Unit Modification Application for window replacement. 2. Obtain a permit for replacement window installation from the City

More information

UCC Permit Application Procedures

UCC Permit Application Procedures How do I apply for a permit? UCC Permit Application Procedures 1. Please complete the CodeMaster Pan Review Application 2. Please provide the scope of work description and/or construction documents/plans.

More information

ARTICLE 12 INTERNATIONAL RESIDENTIAL CODE 2012 International Residential Code Modification Summary (Statutory Authority: 1976 Code Section )

ARTICLE 12 INTERNATIONAL RESIDENTIAL CODE 2012 International Residential Code Modification Summary (Statutory Authority: 1976 Code Section ) 8-1200. International Residential Code. ARTICLE 12 INTERNATIONAL RESIDENTIAL CODE 2012 International Residential Code Modification Summary (Statutory Authority: 1976 Code Section 6-9-40) NOTE-This article

More information

SECTION MANUFACTURED ROOF EXPANSION JOINTS

SECTION MANUFACTURED ROOF EXPANSION JOINTS SECTION 07 71 29 - MANUFACTURED ROOF EXPANSION JOINTS PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

Senergy Platinum CI Stucco Typical details for an impact resistant cement plaster stucco system featuring Neopor GPS Plus Rigid Insulation Board

Senergy Platinum CI Stucco Typical details for an impact resistant cement plaster stucco system featuring Neopor GPS Plus Rigid Insulation Board Senergy Platinum CI Stucco Typical details for an impact resistant cement plaster stucco system featuring Neopor GPS Plus Rigid Insulation Board NOTES Senergy Platinum CI Stucco Typical details for an

More information

INNISGLEN CONDOMINIUMS, BELLEVUE, WASHINGTON LIMITED ROOF EXAMINATION EXECUTIVE SUMMARY

INNISGLEN CONDOMINIUMS, BELLEVUE, WASHINGTON LIMITED ROOF EXAMINATION EXECUTIVE SUMMARY 626 120 th Ave NE suite B101 Bellevue WA 98005 o: 425 455 2046 / f: 425 455 2069 dimensionalbc.com GSG Group Incorporated 144 Railroad Ave. #101 Edmonds, WA 98020 Attention: RE. Mr. Bruce Goodson, LEED

More information

GA APPLICATION OF GYPSUM SHEATHING

GA APPLICATION OF GYPSUM SHEATHING 1. Scope 1.1 This specification describes the minimum requirements for, and the methods of handling, storage, and application of, gypsum sheathing for use as a substrate for exterior claddings. 1.1.1 Exterior

More information

Perimeter Relief and Control Joints in Fire-Rated Gypsum Board

Perimeter Relief and Control Joints in Fire-Rated Gypsum Board Perimeter Relief and Control Joints in Fire-Rated Gypsum Board In multi-family residential construction, involving fire-rated assemblies stress relief in the firerated assemblies is important, but often

More information

Differences between EnCon Insulated Precast and EIFS

Differences between EnCon Insulated Precast and EIFS Differences between EnCon Cover Differences between EnCon EnCon produces a number of different insulated precast concrete products. They range from Insulated Wall panels, Styrocore Insulated Wall Panels,

More information

Architectural Roof and Wall Products Guide Specifications

Architectural Roof and Wall Products Guide Specifications Architectural Roof and Wall Products Guide Specifications 901 W. Watkins St. Phoenix, AZ 85007 PH: 602-495-0048 FX: 602-261-7726 FORMED METAL ROOF AND WALL PANELS This Guide Specification is to be used

More information

Inspection Report. Riverpark Place Condominium Complex S. Riverside Dr. Tulsa, Oklahoma. For

Inspection Report. Riverpark Place Condominium Complex S. Riverside Dr. Tulsa, Oklahoma. For Inspection Report Riverpark Place Condominium Complex 1501-1567 S. Riverside Dr. Tulsa, Oklahoma For Travelers Insurance Company Claim No.: ETM 3045 May 21, 2012 EI File No.: 25374TC Prepared by: Mr. Shawn

More information

Exterior Stucco and Siding Installation

Exterior Stucco and Siding Installation Exterior Stucco and Siding Installation CITY OF NEWARK, CALIFORNIA BUILDING INSPECTION DIVISION 37101 Newark Boulevard, Newark, CA 94560-3796 510-578-4261 Fax 510-578-4307 e-mail: building.inspection@newark.org

More information

GAF EnergyGuard Polyiso Wall Sheathing

GAF EnergyGuard Polyiso Wall Sheathing From: Technical Services May 15, 2013 GAF EnergyGuard Polyiso Wall Sheathing GAF s EnergyGuard Polyiso Wall Sheathing is intended to be installed on residential construction only. Application types include:

More information

2006 INTERNATIONAL ENERGY CONSERVATION CODE

2006 INTERNATIONAL ENERGY CONSERVATION CODE 2006 INTERNATIONAL ENERGY CONSERVATION CODE DOCUMENTATION Code Change No: EC28-06/07 Original Proposal Sections: IECC: 202, 402.5, 402.5.1 (New), Table 402.5.1 (New), 402.5.2 (New), 402.5.3 (New), 402.2.8,

More information

COMPOSITE CLADDING FOR RAIN SCREEN APPLICATIONS

COMPOSITE CLADDING FOR RAIN SCREEN APPLICATIONS COMPOSITE CLADDING FOR RAIN SCREEN APPLICATIONS WATER AND THE BUILDING ENVELOPE Water intrusion is one of the leading causes of construction-related call-backs and litigation. Wind-driven rain and high

More information

2009 IECC Chapter 1 Additions, alterations, renovations or repairs.

2009 IECC Chapter 1 Additions, alterations, renovations or repairs. 2009 IECC Chapter 1 Additions, alterations, renovations or repairs. Additions, alterations, renovations or repairs to an existing building, building system or portion thereof shall conform to the provisions

More information

A. Meet at Project site <insert number> days before starting installation.

A. Meet at Project site <insert number> days before starting installation. SECTION 074643 - COMPOSITION SIDING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Engineered wood cladding. 2. Soffit panels. 3. Trim and fascia. 4. Sealant. 5. Weather barrier. 6. Flashing. 1.2

More information

Introduction Observations

Introduction Observations Architecture Roof Consulting Construction Technology AA C000932 601 North Fern Creek Avenue Suite 100 Orlando, Florida 32803-4899 (407) 896-7875 FAX (407) 898-6043 October 12, 2013 Mr. David Martin, Project

More information