Construction of the Salt River Bridge and Mitigation of Unforeseen Subsurface Conditions

Size: px
Start display at page:

Download "Construction of the Salt River Bridge and Mitigation of Unforeseen Subsurface Conditions"

Transcription

1 Construction of the Salt River Bridge and Mitigation of Unforeseen Subsurface Conditions ABSTRACT Duncan Paterson PE PhD, HDR Inc. (principal author) Steve Lorek, PE, HDR Inc. Doug Voegele, PE, HDR Inc. Eric Reuschling, PE, CSX Transportation The 740 Salt River Bridge in Katharyn, KY was originally constructed in 1905 with a 338ft centerpinned swing truss carrying a single track. The swing truss was fixed in place in the 1940 s. The bridge was selected for replacement in 2005 due to significant deterioration of the bridge, pin connections, and members. Several replacement alternates were evaluated and the selected alternate was four 85ft span deck girders. The design was chosen based on factors including geometric site constraints, yearly river level fluctuations, and mobility concerns. This design adds two concrete piers in the Salt River waterway. Construction was first completed successfully on the new southern pier. While attempting to install the northern pier pile foundation, however, a debris field consisting of stones, concrete, and other materials was discovered. After evaluating the results of a preliminary investigation and excavation, it is believed that the original pivot pier had partially collapsed during a flood event shortly after construction and was abandoned to the river. A new pier was then built on top of the remains. A reassessment of the alternates and additional geotechnical exploration indicated that the traditional pile foundation should be replaced with a micro-pile system that penetrates the debris field. Thus, the original pier location and superstructure layout were maintained. Presented herein is the evaluation of the original pin truss for replacement and demolition, the debris field discovery, reevaluation of superstructure alternatives, the foundation redesign including impacts of obstructions, a revised construction plan, and final construction of the bridge. In addition, a three dimensional representation of the construction phasing and lifting plan will supplement the construction portion of the presentation. All analysis and design were completed according to the current applicable edition of the American Railway Engineering and Maintenance-of-Way Association, Chapters 8 - Concrete Structures, and Chapter 15 - Steel Structures (1).

2 THE SALT RIVER BRIDGE The 740 Salt River Bridge in Katharyn, KY was originally constructed in 1905 with a 338 center-pinned swing truss, carrying a single track (Figure 1). The truss is located over the Salt River, a tributary to the Ohio River, Southwest of Louisville, KY (Figure 2). The effective construction period at normal pool elevation is from June through September. Each truss has seven 24ft panels of Figure 1. Swing Span varying depth out from the main pier and is connected at the crown by tension bars that were loaded during the stress reversal from opening the span. With the exception of the tension bars, the truss, floorbeams, and stringers are all built up sections fabricated from plates, angles, and lattice bars. Additionally, the main truss members all terminate at pin-connection joints. The North approach to the truss consists of one 40ft and two 60ft deck girder spans, whereas the South approach consists of twenty 12ft timber spans on a 2 curve. The truss was fixed in place in 1940s and is no longer permitted to swing open. The existing substructure for the truss spans are N.T.S Figure 2. Bridge Location of masonry construction. The truss ends are supported by two approximately 6ft deep end support seats, whereas the pivot point is supported by a massive 20ft diameter center swing pier. Pier heights vary from 51ft to 64ft measuring from top of cap to top of spread footing. Due to significant deterioration of the bridge, pin connections and members, as well as evidence of impact damage from debris and derailments, the structure was selected for replacement in 2005 by its owner, CSX Transportation.

3 BRIDGE REPLACEMENT Alternates for bridge replacement were evaluated, including repairing the existing structure, replacement of entire bridge on new alignment, replacement with a new 340ft truss, replacement with two new 170ft through plate girders, and different variations of deck girder spans. Each evaluation included corresponding estimates of probable construction costs. Due to multiple factors, including geometric site constraints, yearly river level fluctuations, and mobility concerns, the recommended alternate was a four span deck girder with 85ft spans. The design consisted of a timber ballasted deck supported by four 65in depth deck girders. The recommended alternate would reuse the existing center pier, and add two additional piers within the Salt River waterway. Since the new piers would be located in a navigable portion of the Salt River, approval was obtained from multiple agencies including, the United States Coast Guard, the Army Corps of Engineer s Louisville District, the Kentucky Department of Environmental Protection (Division of Water), Bullitt County, Hardin County, and the City of West Point. Historic records indicated that the Salt River was once used for transportation but is now primarily used for recreational purposes. Modifications were made to the existing piers to accommodate the new spans. An approximately 4ft tall pedestal was added to the center pier to raise the cap to the new required elevation. Portions of the existing truss span end piers were removed to accept the new depth of the deck girders and associated bearings. Each pier was determined to be more than adequate for the load patterns for the new span configuration. Foundation Construction & Obstruction Discovery Construction activities commenced as planned in June of 2006 with pile driving at the new southern pier location. Once the pile driving was completed, the footer concrete was poured concurrently with modification work to the existing piers to accommodate the new spans. After completion of the southern pier and modification work, construction staging was set for the northern pier in June of It was quickly discovered, however, during driving of the initial HP 14x89 piles that the subsurface condition at

4 the northern Pier 2 was vastly different than that previously encountered during subsurface exploration, or at the southern Pier. The piles were refusing at a depth of only 15 to 20 feet below pool level. Exploratory probing by the contractor suggested that the piles were refusing on a rather large anomaly within the riverbed. An initial underwater investigation led to the discovery of a debris field consisting of masonry stones, concrete, and other materials including metals. As a result, the swing span was left in service while the pier construction was immediately halted to investigate the obstruction. Divers experienced in bridge inspection explored the extents of the obstruction by direct measurement of the object where it was exposed, and by probing beneath the mud-line. In addition, geotechnical borings were advanced through the obstruction to obtain an estimation of the obstruction thickness as well as to help ascertain the extent of the debris field, particularly given that much of the obstruction Figure 3. Original Gear was below the mud-line. Portions of the debris field were excavated, as well. Among the debris field was the original rack and gearing for the swing span which was salvaged for recycling (Figure 3). Additionally as a part of the investigation, local historians were contacted about the possible origin of the obstruction. The combined historical background and excavation of portions of the debris field lead to the conclusion that the original pivot pier had partially collapsed during a flood event shortly after its initial construction. Although unclearly documented in the full project file, the original center pier appears to have been abandoned to the river while a new pier was built on top of the remains. The extent of the debris field incorporated an approximate volume of 15ft depth x 35ft width x 25ft length, but was of oblong shape (Figure 4). The debris field was positioned such that piling could not be shifted and the new pier (as designed) would have to be relocated. Alternately, the debris could be excavated or demolished. It was quickly determined that demolition of the obstruction using explosives would not be a viable option due to the proximity of a gas main line running through the river near the bridge. Furthermore, other methods such as the use of a hydraulic impact hammer would be overly time

5 Obstruction 15ft x 12ft Pier Footing Figure 4. Approximate Extents of Obstruction consuming given the lateral and vertical extent of the obstruction (over 20 feet thick in certain locations). Therefore, other alternates needed to be considered. Two additional considerations were necessary for discussing design options. First, Salt River has large fluctuations in river levels and has demonstrated scour on the existing piers. Second, the obstruction is presumably resting on alluvial sediments, rather than rock. Should the foundation for the new pier penetrate the debris field, it is conceivable that it would need to demonstrate an ability to carry any loads introduced by the obstruction, including lateral, vertical and moment loads. Thus, the obstruction s weight and potential effects on the substructure needed to be estimated. If exposed by scour, it was estimated that the obstruction would add nearly 2000 kips of axial load and an additional 3800kip-ft of overturning moment. These loads assume that the current location of the pier remains in the same location and that any load created by the settlement would be carried solely by the foundation. Design options A final complicating factor in consideration of the options was that the 85ft steel girder spans had already been fabricated while the southern pier was being constructed. The following represents an abbreviated list of options that were considered as alternates for the replacement bridge design once the obstruction was discovered.

6 Alternative Options: Straddle the obstruction with a structural footing Since the extents of the obstruction were investigated but not fully known, the width of the required extension would have been large and possibly eccentric (i.e. centerline pier would not be in line with centerline of footing). This created two undesirable effects, the increased possibility structural torsion movement and excessive cost for construction. Drilled Shafts Four drilled shafts would be used to replace the piles. The shafts would be advanced by coring through the debris field. There were three problems for this option. First, the required diameter of the shafts was too large for the equipment already mobilized and a coring bit of sufficient diameter was not available. Second, metal pieces of the former swing span gearing were discovered in multiple locations during the underwater inspection and in the additional geotechnical borings. Thus, there was no guarantee that coring equipment would be able to penetrate the debris field. Third, there were concerns about equipment losses or damage due to the steeply sloping sides of the obstruction. Modify Superstructure Design - Change the span length, or eliminate the second pier. Several options were considered (Figure 5): o o Revise span lengths to one 55ft span and one 115ft span to shift the pier location Design a new 170ft steel span as either a deck girder, Through Plate Girder (TPG), or a new truss span. o Rehabilitate the truss pins at the approximately 20 locations of severe deterioration and elongation of the tension bars. Each of these options proved to be excessively expensive, especially considering that the two new 85ft spans were already fabricated and were on sight.

7 Deck Girder Option (115ft) TPG Option (170ft) Deck Girder Option (170ft) Truss Option (170ft) Figure 5. Superstructure Alternates Pin Replacement Option Micropile Foundation Micropile foundation would be used to replace the piles. This option provided the greatest potential. From a construction standpoint, the relatively small diameter of the piles ( 7 inches) would be easier to install. From a design standpoint, multiple micro-piles could be installed within the same planned footprint for the pier, thereby providing adequate redundancy should one or more piles not fully penetrate the debris field. That is, the micropile system could be designed such that the whole system would still function properly without the risk of overstressing the micropiles if the obstruction could not be penetrated at one or more locations. Conversely, there is inherent risk for this approach. For example, an excessive number of micropiles may be unable to penetrate the obstruction. Or, a large number of nonfunctioning micropiles could introduce excessive lateral or torsional forces to the group. In other words, the system could still fail.

8 After considering the concerns of the contractor, the designer, and the owner, the micropile system was selected since it had the greatest opportunity for success and had the potential to limit project losses, both monetary and schedule related. FOUNDATION REDESIGN The original foundation redesign was performed by Teasley Services Group (Teasley) of Nashville, Tennessee as a subconsultant to Nicholson Construction Company. Utilizing the structural design loads and geotechnical design information provided by HDR Engineering, Teasley developed a micropile foundation system consisting of twenty, 7-inch diameter micropiles extending through the obstruction and socketed 15 feet into the underlying shale bedrock. Reinforcing of the micropile consisted of a inch outside diameter (O.D.) casing extending to the top of rock and a full length No. 18 (75 ksi) all thread center bar. In addition, a second No. 18 all thread bar would be located in the bond zone (lower 20 feet) of the pile. Teasley also designed a structural bracing system to fully transfer all axial and lateral loads from the pile cap to the mud-line, with the micropiles designed for the full loads transferred to the mud-line by the bracing system. The bracing system was further designed to serve as the template for the micropile installation. A rendering of the bracing system is shown in Figure 6. Approval of the design was provided after an engineer s review. Complications arose, however, after the contract was rebid by CSXT. Figure 6. Micropile Rendering The foundation subcontractor listed by the successful general contractor did not have the required equipment to install the micropile foundation system. As designed, a concentric underreamer was required to enlarge the borehole once the bit had passed through the bracing system as designed. Therefore a smaller diameter casing was necessary to accommodate the new contractor. As such, a reduced casing diameter of inches and a single 2.5-

9 inch diameter 150 ksi bar for the entire length of the micropile was proposed. This revised system made allowances for the reduced diameter of the rock socket. The rock socket also needed to be extended an additional 7 feet, to a minimum length of 22 feet. One of the main complicating issues with the redesign was that the bracing system was designed specifically for a inch O.D. casing, and the system needed to be reevaluated to ensure that the load transfer would occur as intended. The proposed equivalent micropile foundation system was approved after it was determined that the redesign satisfied the design intent of the original micropile design. Proposed Truss Removal A particular challenge of railroad work on active rail lines is the time period in which projects can be completed. The cost of train rerouting, train stoppage and other effects can greatly affect the profitability of the rail line. As such, it is imperative that all demolition and preparations for new construction that can safely be accomplished prior to halting trains (down-time) be finished while the rail line is still active. For the truss structures, this included removal of all members not critical to the operation of the bridge in order to reduce the weight of truss components and expedite demolition of the remaining structure. This maximizes the amount of the bridge that can be removed in one crane pick. Understanding that the original span was designed as a swing truss, the truss spans were originally proposed to be separated into its two swing span portions. The two spans (North and South of the center swing pier) were proposed to be removed and new spans placed in two 96 hour work windows. As such it was necessary to analyze the truss for load from multiple crane pick points, and with a portion of its secondary members removed, particularly the lateral bracing system and the center top-chord tension bars. A 3-D model was initially created to analyze the trusses from multiple construction angles with both fixed and pinned connections. The model included the truss main members, floorbeams, stringers, and bottom chord members with or without the lateral bracing. Initially, the model was run with the complete swing span as constructed. Next, the model was reduced to one span and the lateral bracing was

10 removed (Figure 7). As expected, the lateral bending moment of the bottom chords was Figure 7. Idealized Model of Lateral Bracing greatly increased. The increase in out-of-plane bending, however, was still far below the allowable stress of the members even with full loading applied to the truss (operational load values). Additionally, stability from the increased out-of-plane deflection was not a great concern since the bottom chords act as tension members (in the closed position). COMPLETING CONSTRUCTION Installation of the micropile system was completed as planned (Figure 8). Three of the twenty micropiles were initially unable to penetrate the debris field but after reconfiguration of the drilling equipment, all piles were drilled per plan. After completion of the micropile system in August of 2008, normal construction resumed, with completion of the northern pier in September of Demolition of the swing span and erection of the new girder spans were completed in September of Thus, the bridge was completed a little over two years after construction was halted due to discovery of the Figure 8. Micropile Installation obstruction.

11 Figure 9. Construction Demolition and Erection Plan (Advanced Consulting Technology, Inc.)

12 One of the key elements in expediting the demolition of the truss and construction of the new spans was a 3-Dimnesional (3D) construction plan to help visualize the procedure. Advanced Consulting Technology, Inc. prepared an alternate construction erection plan for Figure 10. Truss Removal Hall Contracting of Kentucky. This included removing the truss in three sections while balancing the center pivot area as the end spans were removed (Figure 9). Hall Contracting proposed full demolition of the existing structure and erection of the new spans in a 7 day track outage (Figure 10). Aside from the substructure construction and modifications to the existing piers, the actual time from train stoppage to reopening the bridge to train traffic was approximately 6 days, including inclement weather and unanticipated construction delays. The completed project is shown in Figure 11. Figure 11. Completed Structure CONCLUSIONS AND HINDSIGHT With the benefit of perspective, would the design and construction of this bridge gone forward in the same manner? One argument is to insist borings are completed at all foundation locations. This is a customary recommendation of geotechnical engineers, but is also commonly not done due to the large expense, drilling at every foundation location for every bridge, over the long term. It is possible that the boring would have hit a portion of the masonry or metal and lead to increased scrutiny. The counter

13 argument is that there was no guarantee that a boring at the pier location would have been given special notice. That is, the boring might have missed the masonry, or metal. Furthermore, even if some of the debris had been cored, there is the possibility it would not have been treated as out of the ordinary. Routinely consulting a local historian is another consideration. In this instance it did lead to information indicating an abandoned pier is the likely cause of the obstruction. The futility of researching arcane information from local historians for each construction project, however, is readily apparent. That is not to say that historical information is not beneficial for particular projects with known concerns. Weighing the cost/benefit analysis of boring at each location and gathering historic information, therefore, still rests with the bridge owner. In this instance, it could be argued that not taking these steps cost the owner considerable cost and delays, including two separate mobilizations. But, it can not be stated conclusively that the additional information would have changed the outcome.

14 REFERENCES (1) Manual for Railway Engineering (2010), American Railway Engineering and Maintenance-of-Way Association (AREMA).

15 LIST OF FIGURES Figure 1. Swing Span (Photo) Figure 2. Bridge Location Figure 3. Original Gear (Photo) Figure 4. Approximate Extents of Obstruction Figure 5. Superstructure Alternates Figure 6. Micropile Rendering Figure 7. Idealized Model of Lateral Bracing Figure 8. Micropile Installation (Photo) Figure 9. Construction Demolition and Erection Plan (Advanced Consulting Technology, Inc.) Figure 10. Truss Removal Figure 11. Completed Structure

CSX BRIDGE OVER TENNESSEE RIVER SLOUGH NEAR BRIDGEPORT, ALABAMA BRIDGE REPLACEMENT AND TRACK IMPROVEMENTS. Introduction

CSX BRIDGE OVER TENNESSEE RIVER SLOUGH NEAR BRIDGEPORT, ALABAMA BRIDGE REPLACEMENT AND TRACK IMPROVEMENTS. Introduction CSX BRIDGE 122.6 OVER TENNESSEE RIVER SLOUGH NEAR BRIDGEPORT, ALABAMA BRIDGE REPLACEMENT AND TRACK IMPROVEMENTS AREMA PRESENTATION September 13, 1999 Presented by: Rick Garro, P.E. Assistant Chief Engineer

More information

KEYWORDS: Barge Stability, Steel Truss Erection, Horizontal Sliding of Steel Trusses

KEYWORDS: Barge Stability, Steel Truss Erection, Horizontal Sliding of Steel Trusses Replacement of the BNSF Approach Spans over the Mississippi River DAVID ROGOWSKI, P.E. AND JOSH CRAIN, Genesis Structures Inc., Kansas City, Missouri and DAN SIEVE AND KEVIN BECKER, Walsh Construction

More information

DESIGN AND FLOAT-IN CONSTRUCTION OF A 500 FT. TRUSS SPAN

DESIGN AND FLOAT-IN CONSTRUCTION OF A 500 FT. TRUSS SPAN DESIGN AND FLOAT-IN CONSTRUCTION OF A 500 FT. TRUSS SPAN Kevin R. Eisenbeis, PE, SE Harrington & Cortelyou, Inc. 911 Main Street, Suite 1900, Kansas City, MO 64105 Phone: 816 421 8386 Fax: 816 471 6109

More information

2.0 Purpose. 3.0 Work Plan. Page 1 of 7

2.0 Purpose. 3.0 Work Plan. Page 1 of 7 2.0 Purpose The purpose of this document is to present the findings of the field investigation and concept design study, as well as recommend appropriate track relocation and bridge modifications to provide

More information

STANDARDIZED CONCRETE BRIDGES IN TEXAS. John Holt, PE, Texas Department of Transportation Ronald Medlock, PE, Texas Department of Transportation

STANDARDIZED CONCRETE BRIDGES IN TEXAS. John Holt, PE, Texas Department of Transportation Ronald Medlock, PE, Texas Department of Transportation STANDARDIZED CONCRETE BRIDGES IN TEXAS John Holt, PE, Texas Department of Transportation Ronald Medlock, PE, Texas Department of Transportation ABSTRACT Standardized concrete bridge plans are used extensively

More information

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring Location of Project Introduction» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring Existing Bridge» Built in 1928» 255-foot Open Spandrel Concrete Arch Bridge» 24-foot

More information

ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA

ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE 412.1 OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA BURLINGTON NORTHERN AND SANTA FE RAILWAY By: John W. Hronek

More information

Norfolk Southern s Online Rebuild of the Coosa River Bridge

Norfolk Southern s Online Rebuild of the Coosa River Bridge Norfolk Southern s Online Rebuild of the Coosa River Bridge Author: Harold Hal E. Lewis, PE, Vice President, HDR Engineering, Inc. 200 West Forsyth Street, Suite 800, Jacksonville, Florida 32202 Telephone:

More information

Fort (M-85) Street Bascule Bridge

Fort (M-85) Street Bascule Bridge Fort (M-) Street Bascule Bridge DESIGN Overview History Geotech/Substructures Superstructure Aesthetics CONSTRUCTION Steel and Machinery Fabrication Existing Bridge Removal Road Reconstruction Bridge Replacement

More information

Rehabilitation of Masonry Piers at Nipigon, Ontario

Rehabilitation of Masonry Piers at Nipigon, Ontario Rehabilitation of Masonry Piers at Nipigon, Ontario Daniel E. J. Adamson, P. Eng. Canadian Pacific Railway 2881 Alyth Road SE Calgary, AB Canada, T2G 5S3 Phone (403) 303-8835 Fax (403) 303-8830 ABSTRACT

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014

More information

Review of Plans and Specs from a Constructability Perspective

Review of Plans and Specs from a Constructability Perspective Review of Plans and Specs from a Constructability Perspective The Executive Regional Manager and the Project Manager, with approval of the Director of Project Management, may request the Constructability

More information

Deep Water Drilled Shafts for the Herrington Lake Bridge Replacement Project

Deep Water Drilled Shafts for the Herrington Lake Bridge Replacement Project Deep Water Drilled Shafts for the Herrington Lake Bridge Replacement Project Darrin Beckett, P.E. Kentucky Transportation Cabinet 49 th Southeastern Transportation Geotechnical Engineering Conference October

More information

INVESTIGATING AN AGING INFRASTRUCTURE: BRIDGE LESSONS FROM THE FIELD

INVESTIGATING AN AGING INFRASTRUCTURE: BRIDGE LESSONS FROM THE FIELD INVESTIGATING AN AGING INFRASTRUCTURE: BRIDGE LESSONS FROM THE FIELD Word count: 5,795 Duncan Paterson PE PhD, HDR Inc. (principal author) Steve Lorek, PE, HDR Inc. Jon Winer, PE, HDR Inc. ABSTRACT As

More information

AREMA 2008 Annual Conference. LOW PROFILE RAILROAD BRIDGE Steve K. Jacobsen, PE NNW, Inc. Rochester, Minnesota

AREMA 2008 Annual Conference. LOW PROFILE RAILROAD BRIDGE Steve K. Jacobsen, PE NNW, Inc. Rochester, Minnesota AREMA 2008 Annual Conference LOW PROFILE RAILROAD BRIDGE Steve K. Jacobsen, PE NNW, Inc. Rochester, Minnesota 55904 507-281-5188 Steve K. Jacobsen, PE 2 LOW PROFILE RAILROAD BRIDGE Steve K. Jacobsen, PE

More information

Foundation Strengthening Of Bascule Piers At The Bridge Of Lions

Foundation Strengthening Of Bascule Piers At The Bridge Of Lions Paper No. 22 Foundation Strengthening Of Bascule Piers At The Bridge Of Lions Structural Elements Jian Huang, Ph.D., P.E. G. Alan Klevens, P.E. Lichtenstein Consulting Engineers TENTH BIENNIAL SYMPOSIUM

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014

More information

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08 Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08 Table of Contents 1. Title 2. Designation 3. List of Figures 4. Scope 5. Referenced

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2016 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

RETROFIT AND REPLACEMENT OF DUMBARTON RAILROAD BRIDGES

RETROFIT AND REPLACEMENT OF DUMBARTON RAILROAD BRIDGES RETROFIT AND REPLACEMENT OF DUMBARTON RAILROAD BRIDGES Kuan S. Go, P.E., Semyon Treyger, S.E., Michael Jones, S.E., HNTB Corporation Stephen J. Hill, Bernard Susanto, Wenlin Yang, San Mateo County Transit

More information

Foundation Innovations Ensure Successful Bridge Replacement

Foundation Innovations Ensure Successful Bridge Replacement COVER STORY Foundation Innovations Ensure Successful Bridge Replacement Rhode Island s new $163.7 million, 2,265 ft (690 m) long, fourlane Sakonnet River Bridge sits just south of the existing bridge in

More information

TIMBER BRIDGES AND 286 LOADING

TIMBER BRIDGES AND 286 LOADING TIMBER BRIDGES AND 286 LOADING AREMA TECHNICAL CONFERENCE 2002 Presented on behalf of Committee 10, Structures Maintenance & Construction by: David Franz, Area Engineer Osmose Inc., Railroad Division P.O.

More information

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc. Design and Construction of the SH58 Ramp A Flyover Bridge over IH70 Gregg A. Reese, PE, CE, Summit Engineering Group, Inc., Littleton, CO ABSTRACT: The SH58 Ramp A bridge in Golden, CO is the latest on

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2015

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update September 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: September

More information

ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING. Kansas City Terminal Railway Company

ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING. Kansas City Terminal Railway Company James P. Hyland Page 1 ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING Kansas City Terminal Railway Company James P. Hyland, P.E. Senior Bridge Engineer TranSystems Corporation James P. Hyland Page 2

More information

SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA

SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA ASHE NATIONAL PROJECT OF THE YEAR SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA For the PENNSYLVANIA DEPARTMENT OF TRANSPORTATION Engineering District 12-0 Submitted By: January 29, 2018 AMERICAN

More information

Steve Haines, P.E., Parsons, (303) , James Studer, Kiewit, (926) ,

Steve Haines, P.E., Parsons, (303) , James Studer, Kiewit, (926) , PLACEMENT OF PRECAST PRESTRESSED CONCRETE GIRDER BRIDGE SPANS WITH SELF PROPELLED MODULAR TRANSPORTERS PIONEER CROSSING DESIGN/BUILD PROJECT, AMERICAN FORK, UT Steve Haines, P.E., Parsons, (303) 831-8100,

More information

STATE OF NEW HAMPSHIRE DEPARTMENT OF TRANSPORTATION LOAD RATING REPORT GENERAL SULLIVAN BRIDGE - DOVER 200/023 OVER THE LITTLE BAY

STATE OF NEW HAMPSHIRE DEPARTMENT OF TRANSPORTATION LOAD RATING REPORT GENERAL SULLIVAN BRIDGE - DOVER 200/023 OVER THE LITTLE BAY STATE OF NEW HAMPSHIRE DEPARTMENT OF TRANSPORTATION LOAD RATING REPORT GENERAL SULLIVAN BRIDGE - DOVER 200/023 OVER THE LITTLE BAY NEWINGTON-DOVER, 11238S August 15, 2016 Vanasse Hangen Brustlin, Inc.

More information

Design & Seismic Detailing of Nonstandard Deep Precast Concrete Box Girders For Long Span Railroad Bridges By:

Design & Seismic Detailing of Nonstandard Deep Precast Concrete Box Girders For Long Span Railroad Bridges By: Design & Seismic Detailing of Nonstandard Deep Precast Concrete Box Girders For Long Span Railroad Bridges By: ABSTRACT Shafi M. Sharifan, Ph.D., P.E. Wei Koo & Associates Orange, California Kosal Krishnan,

More information

Modjeski and Masters, Inc. Consulting Engineers 04/18/06 St. Croix River Bridge 3D Analysis Report Introduction

Modjeski and Masters, Inc. Consulting Engineers 04/18/06 St. Croix River Bridge 3D Analysis Report Introduction Introduction This memo presents a summary of a three dimensional (3D) analysis of the Organic concept for the proposed St. Croix River bridge project. The Organic concept has several attributes that are

More information

UNDERWATER BRIDGE INSPECTION REPORT RED RIVER OF THE NORTH DISTRICT 4 - CLAY COUNTY

UNDERWATER BRIDGE INSPECTION REPORT RED RIVER OF THE NORTH DISTRICT 4 - CLAY COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 6646 CSAH NO. 36 OVER THE RED RIVER OF THE NORTH DISTRICT 4 - CLAY COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO MSAS NO. 119 OVER THE RED LAKE RIVER DISTRICT 2 - POLK COUNTY, CITY OF EAST GRAND FORKS

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO MSAS NO. 119 OVER THE RED LAKE RIVER DISTRICT 2 - POLK COUNTY, CITY OF EAST GRAND FORKS UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 60019 MSAS NO. 119 OVER THE RED LAKE RIVER DISTRICT 2 - POLK COUNTY, CITY OF EAST GRAND FORKS AUGUST 29, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF

More information

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 6 - RICE COUNTY

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 6 - RICE COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 66532 227 th STREET (TWP 45) OVER THE STRAIGHT RIVER DISTRICT 6 - RICE COUNTY SEPTEMBER 12, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update July 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The entails the construction of a cast in place

More information

penetrometer test (CPT) soundings were done to supplement the SPT data. Construction recommendations were made for most of the new buildings.

penetrometer test (CPT) soundings were done to supplement the SPT data. Construction recommendations were made for most of the new buildings. 2016 ASCE Ridge Branch Florida Section Project of the Year Grouted Pulldown Micropile foundation design for Four-story Building at Southeastern University, Lakeland, Florida Introduction and Project Description

More information

Fort Street M-85 Bascule Bridge Looking to the Past to Build Bridge for the Future

Fort Street M-85 Bascule Bridge Looking to the Past to Build Bridge for the Future Fort Street M-85 Bascule Bridge Looking to the Past to Build Bridge for the Future Richard A. Wianecki, PE, Hardesty & Hanover, Okemos, MI Jane Abadir, PE, LEED A P, SOMAT Engineering Detroit, MI Rouge

More information

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction Chapter 1 Bridge Design Manual General Design Information Section 1.02 Selection and Geometry Introduction Selection or Rehabilitation Report This section of the design manual provides guidance on the

More information

DESIGN-BUILD-TEST PROCESS FOR HIGH CAPACITY MICROPILES: CONSTRUCTION CASE STUDY ON DUTCHESS RAIL TRAIL BRIDGE FOUNDATIONS, POUGHKEEPSIE, NEW YORK

DESIGN-BUILD-TEST PROCESS FOR HIGH CAPACITY MICROPILES: CONSTRUCTION CASE STUDY ON DUTCHESS RAIL TRAIL BRIDGE FOUNDATIONS, POUGHKEEPSIE, NEW YORK ABSTRACT DESIGN-BUILD-TEST PROCESS FOR HIGH CAPACITY MICROPILES: CONSTRUCTION CASE STUDY ON DUTCHESS RAIL TRAIL BRIDGE FOUNDATIONS, POUGHKEEPSIE, NEW YORK James Barron 1, P.E., Thomas Hattala 2, P.E.,

More information

Chapter 13 Bridge Load Rating

Chapter 13 Bridge Load Rating Chapter 13 Bridge Load Rating Contents 13.1 General 13.1-1 13.1.1 WSDOT Rating (LRFR) 13.1-2 13.1.2 NBI Rating (LFR) 13.1-8 13.2 Special Rating Criteria 13.2-1 13.2.1 Dead Loads 13.2-1 13.2.2 Live Load

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PREFABRICATED STEEL PEDESTRIAN BRIDGE, TYPE 1

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PREFABRICATED STEEL PEDESTRIAN BRIDGE, TYPE 1 MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PREFABRICATED STEEL PEDESTRIAN BRIDGE, TYPE 1 OFS:MJF 1 of 10 APPR:JAB:POJ:09-29-18 FHWA:APPR:10-01-18 a. Description. This work consists of

More information

REHABILITATION AND STRENGTHENING OF BURLINGTON NORTHERN SANTA FE RAILWAY BRIDGE OVER THE MISSISSIPPI RIVER MEMPHIS, TENNESSEE.

REHABILITATION AND STRENGTHENING OF BURLINGTON NORTHERN SANTA FE RAILWAY BRIDGE OVER THE MISSISSIPPI RIVER MEMPHIS, TENNESSEE. REHABILITATION AND STRENGTHENING OF BURLINGTON NORTHERN SANTA FE RAILWAY BRIDGE 482.1 OVER THE MISSISSIPPI RIVER MEMPHIS, TENNESSEE by: John W. Hronek & Ron G. Berry HNTB Companies 1201 Walnut, Suite 700

More information

NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA

NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA PURPOSE AND SCOPE These criteria modify and supplement the applicable sections of the AREMA Manual of Recommended Practice in connection

More information

ABRAHAM LINCOLN BRIDGE

ABRAHAM LINCOLN BRIDGE ABRAHAM LINCOLN BRIDGE PROJECT LOCATION: CONNECTING LOUISVILLE, KY WITH JEFFERSON, IN ACROSS THE OHIO RIVER. CATEGORY B: TRANSPORTATION PROJECT OWNER: KENTUCKY TRANSPORTATION CABINET COWI North America

More information

I-74 over the Mississippi River

I-74 over the Mississippi River I-74 over the Mississippi River Design and Construction of Arch Foundations 104 th Transportation and Highway Engineering Conference Presented by: Andrew J. Keaschall, PE, SE, Alfred Benesch & Company

More information

GLENWOOD ROAD BRIDGE REPLACEMENT

GLENWOOD ROAD BRIDGE REPLACEMENT Wood County, Ohio, Construction Administration and Observation Project Cost $.92 million Professional Services 2014 Construction: 2015 GLENWOOD ROAD BRIDGE REPLACEMENT PDG was hired by the Wood County

More information

SECTION / ENGINEERED AGGREGATE PIERS (SOIL REINFORCEMENT AND FOUNDATION SYSTEM)

SECTION / ENGINEERED AGGREGATE PIERS (SOIL REINFORCEMENT AND FOUNDATION SYSTEM) PART 1 GENERAL 1.01 WORK INCLUDED SECTION 02360 / 31 34 30.13 ENGINEERED AGGREGATE PIERS (SOIL REINFORCEMENT AND FOUNDATION SYSTEM) A. Provide all equipment, material, labor and supervision to design and

More information

Using Load Testing to Save Money and Time on the I-35W Bridge Project

Using Load Testing to Save Money and Time on the I-35W Bridge Project Using Load Testing to Save Money and Time on the I-35W Bridge Project MATTHEW GLISSON, PE, M.ASCE, Braun Intertec Corporation, St. Louis, MO; MORGAN RACE, PH.D., PE, M.ASCE, Braun Intertec Corporation,

More information

The Design of the New Portageville Bridge

The Design of the New Portageville Bridge The Design of the New Portageville Bridge Daniel B. Irwin, P.E. Modjeski and Masters, Inc 100 Sterling Parkway, Suite 302 Mechanicsburg, PA 17050 (717)790-9565 dbirwin@modjeski.com Kevin W. Johns, P.E.

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO COUNTY STATE AID HIGHWAY 10 OVER THE POMME DE TERRE RIVER DISTRICT 4 STEVENS COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO COUNTY STATE AID HIGHWAY 10 OVER THE POMME DE TERRE RIVER DISTRICT 4 STEVENS COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 75501 COUNTY STATE AID HIGHWAY 10 OVER THE POMME DE TERRE RIVER DISTRICT 4 STEVENS COUNTY SEPTEMBER 24, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION

More information

Implementation of this Special Provision requires a complete understanding of the following documents:

Implementation of this Special Provision requires a complete understanding of the following documents: VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR Quality Assurance/Quality Control (QA/QC) for the Construction of Deep Foundation Systems for Design-Build and PPTA Contracts November 10, 2009

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 3 OVER THE RED LAKE RIVER DISTRICT 2 - PENNINGTON COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 3 OVER THE RED LAKE RIVER DISTRICT 2 - PENNINGTON COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 57518 CSAH NO. 3 OVER THE RED LAKE RIVER DISTRICT 2 - PENNINGTON COUNTY AUGUST 27, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY AYRES

More information

Lantz-Boggio Architects, P.C LBA Project No

Lantz-Boggio Architects, P.C LBA Project No SECTION 313430- PART 1 GENERAL 1.1 WORK INCLUDED A. Provide all equipment, material, labor and supervision to design and install Engineered Aggregate Piers for the soil reinforcement. Design shall rely

More information

Replacing the Aging US 52 Mississippi River Bridge

Replacing the Aging US 52 Mississippi River Bridge 2019 TRANSPORTATION & HIGHWAY ENGINEERING CONFERENCE F. Duncan, PE, G. Hasbrouck, PE and A. Dour, PE Replacing the Aging US 52 Mississippi River Bridge February 26, 2019 Project Overview US 52 / IL 64

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PREFABRICATED STEEL PEDESTRIAN BRIDGE, TYPE 2

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PREFABRICATED STEEL PEDESTRIAN BRIDGE, TYPE 2 MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PREFABRICATED STEEL PEDESTRIAN BRIDGE, TYPE 2 OFS:MJF 1 of 10 APPR:JAB:POJ:09-29-18 FHWA:APPR:10-01-18 a. Description. This work consists of

More information

Strengthened Bascule Piers for the Newly Rehabilitated Bridge of Lions

Strengthened Bascule Piers for the Newly Rehabilitated Bridge of Lions 13 th BIENNIAL SYMPOSIUM OCTOBER 25-28, 2010 Strengthened Bascule Piers for the Newly Rehabilitated Bridge of Lions Jian Huang, Ph.D., P.E. and R. Wayne McLennon, P.E. TranSystems Corporation 2400 E. Commercial

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PREFABRICATED STEEL PEDESTRIAN BRIDGE, TYPE 2

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PREFABRICATED STEEL PEDESTRIAN BRIDGE, TYPE 2 MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PREFABRICATED STEEL PEDESTRIAN BRIDGE, TYPE 2 OFS:MJF 1 of 10 APPR:JAB:POJ:07-07-17 FHWA:APPR:07-11-17 a. Description. This work consists of

More information

103rd Annual T.H.E. Conference February 28 & March 1, 2017 University of Illinois at Urbana-Champaign. Planning and Design. of IL-104 BRIDGE OVER

103rd Annual T.H.E. Conference February 28 & March 1, 2017 University of Illinois at Urbana-Champaign. Planning and Design. of IL-104 BRIDGE OVER 103rd Annual T.H.E. Conference February 28 & March 1, 2017 University of Illinois at Urbana-Champaign Planning and Design of IL-104 BRIDGE OVER ILLINOIS RIVER MEREDOSIA, IL Presenter: Vinod C. Patel, PE,

More information

CASE STUDY OF LONG SPAN STEEL BRIDGE STABILITY DURING DESIGN AND CONSTRUCTION

CASE STUDY OF LONG SPAN STEEL BRIDGE STABILITY DURING DESIGN AND CONSTRUCTION CASE STUDY OF LONG SPAN STEEL BRIDGE STABILITY DURING DESIGN AND CONSTRUCTION KEVIN D. SEAR, PE SUSAN STEELE, PE BIOGRAPHY Kevin Sear has been a structural engineer for over 42 years, the first 10 years

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 15 OVER THE ARCOLA CHANNEL HENNEPIN COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 15 OVER THE ARCOLA CHANNEL HENNEPIN COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 27510 CSAH NO. 15 OVER THE ARCOLA CHANNEL HENNEPIN COUNTY MAY 21, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS, INC.

More information

TECHNICAL REPORT 1. Structural Concepts / Structural Existing Conditions. Penn State Hershey Medical Center Children s Hospital. Hershey, Pennsylvania

TECHNICAL REPORT 1. Structural Concepts / Structural Existing Conditions. Penn State Hershey Medical Center Children s Hospital. Hershey, Pennsylvania TECHNICAL REPORT 1 Structural Concepts / Structural Existing Conditions Penn State Hershey Medical Center Children s Hospital Matthew V Vandersall The Pennsylvania State University Architectural Engineering

More information

Executive Summary. ES-1 Introduction. ES-2 Background

Executive Summary. ES-1 Introduction. ES-2 Background ES-1 Introduction The Federal Transit Administration (FTA) and the (CTDOT) are preparing a combined Environmental Assessment (EA), Section 4(f) Evaluation, and Environmental Impact Evaluation (EIE) to

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

DESIGN AND CONSTRUCTION OF A LONG SPAN STEEL PLATE I- GIRDER BRIDGE: I-270 BRIDGE OVER CHAIN OF ROCKS CANAL

DESIGN AND CONSTRUCTION OF A LONG SPAN STEEL PLATE I- GIRDER BRIDGE: I-270 BRIDGE OVER CHAIN OF ROCKS CANAL DESIGN AND CONSTRUCTION OF A LONG SPAN STEEL PLATE I- GIRDER BRIDGE: I-270 BRIDGE OVER CHAIN OF ROCKS CANAL BRANDON CHAVEL LANCE PETERMAN BIOGRAPHY Brandon Chavel is a Senior Bridge Engineer and Professional

More information

National Truss for Historic Preservation

National Truss for Historic Preservation National Truss for Historic Preservation JANUARY 2019 A new truss brings structural modernization to a century-old Washington apartment building. BY JASON MYERS, SE, PE, SHANE MAXEMOW, SE, PE, AND TIMON

More information

Construction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT

Construction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT CHAPTER Construction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT Sixth Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering 19 By Dr. Ibrahim

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2013 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

Designing for Longitudinal Force

Designing for Longitudinal Force AREMA Annual Technical Conference Structures Session Tuesday, September 19, 2006 KICC, Louisville, KY Designing for Longitudinal Force Design of Steel Bridges for Longitudinal Force John F. Unsworth, P.Eng.

More information

MINNESOTA HISTORIC PROPERTY RECORD PART I. PROPERTY IDENTIFICATION AND GENERAL INFORMATION

MINNESOTA HISTORIC PROPERTY RECORD PART I. PROPERTY IDENTIFICATION AND GENERAL INFORMATION MINNESOTA HISTORIC PROPERTY RECORD PART I. PROPERTY IDENTIFICATION AND GENERAL INFORMATION Common Name: Camp Ripley Bridge Bridge Number: 4969 Identification Number: Location: Feature Carried: TH 115 Feature

More information

Grade Separation Systems. Single-Span Rail Bridge Construction Procedure. An innovation from art engineering inc.

Grade Separation Systems. Single-Span Rail Bridge Construction Procedure. An innovation from art engineering inc. Grade Separation Systems Single-Span Rail Bridge Construction Procedure An innovation from art engineering inc. GSS Single-Span Example Shown: An existing railroad grade crossing. Existing railroad Existing

More information

Unionport Bridge Replacement Design Twin Single Leaf Bascules

Unionport Bridge Replacement Design Twin Single Leaf Bascules SIXTEENTH BIENNIAL SYMPOSIUM September 19th 22nd, 2016 Unionport Bridge Replacement Design Twin Single Leaf Bascules Rahul P. Shah, PE NYCDOT Division of Bridges William E. Nyman, PE Hardesty & Hanover,

More information

MEMORANDUM. From: Moffatt & Nichol. Date: April 3, Subj: Wharf J-10 Evaluation of Structure for EIR Document. M&N File No:

MEMORANDUM. From: Moffatt & Nichol. Date: April 3, Subj: Wharf J-10 Evaluation of Structure for EIR Document. M&N File No: 2001 North Main St, Ste 360, Walnut Creek, CA 94596 Ph: 925-944-5411 ; Fax: 925-944-4732 MEMORANDUM To: Ed Byrne From: Moffatt & Nichol Date: April 3, 2006 Subj: Wharf J-10 Evaluation of Structure for

More information

Fracture Critical Bridge Inspection. Presented by MN/DOT Bridge Safety Inspections

Fracture Critical Bridge Inspection. Presented by MN/DOT Bridge Safety Inspections Fracture Critical Bridge Inspection Presented by MN/DOT Bridge Safety Inspections MN/DOT s s fracture critical bridge inspection team performs in-depth and special inspections for State, County and City

More information

MODEL SPECIFICATIONS: Hydraulically Driven Steel Underpinning Pile Specifications

MODEL SPECIFICATIONS: Hydraulically Driven Steel Underpinning Pile Specifications MODEL SPECIFICATIONS: Hydraulically Driven Steel Underpinning Pile Specifications Mar/2008 v1.0 SECTION 02255 HYDRAULICLY DRIVEN STEEL UNDERPINNING PILES PART 1 GENERAL 1.01 SCOPE OF WORK The work shall

More information

STEEL DECKS FOR RAIL BRIDGES

STEEL DECKS FOR RAIL BRIDGES STEEL DECKS FOR RAIL BRIDGES Duncan Paterson PE PhD HDR Inc. 9987 Carver Rd Cincinnati OH 513-984-7500 duncan.paterson@hdrinc.com Steve Lorek, PE HDR Inc. 9987 Carver Rd Cincinnati OH 513-984-7500 Steve.Lorek@hdrinc.com

More information

Superstructure Guidelines

Superstructure Guidelines Superstructure Guidelines The following are additional guidelines on using the following types of superstructure. Pre-stressed Concrete Beams To check beam size use the beam size chart. The chart was created

More information

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 3 - MORRISON COUNTY

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 3 - MORRISON COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 49528 CSAH NO. 26 OVER THE MISSISSIPPI RIVER DISTRICT 3 - MORRISON COUNTY OCTOBER 25, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS

More information

APRIL 2017 MAMARONECK & SHELDRAKE RIVERS NEW YORK FLOOD RISK MANAGEMENT GENERAL REEVALUATION REPORT FOR THE VILLAGE OF MAMARONECK

APRIL 2017 MAMARONECK & SHELDRAKE RIVERS NEW YORK FLOOD RISK MANAGEMENT GENERAL REEVALUATION REPORT FOR THE VILLAGE OF MAMARONECK MAMARONECK & SHELDRAKE RIVERS NEW YORK FLOOD RISK MANAGEMENT GENERAL REEVALUATION REPORT FOR THE VILLAGE OF MAMARONECK APRIL 2017 APPENDIX C4: STRUCTURAL Table of Contents 1.0 STRUCTURAL INTRODUCTION...

More information

UNDERWATER BRIDGE INSPECTION REPORT RED RIVER OF THE NORTH DISTRICT 4 - CLAY COUNTY, CITY OF MOORHEAD

UNDERWATER BRIDGE INSPECTION REPORT RED RIVER OF THE NORTH DISTRICT 4 - CLAY COUNTY, CITY OF MOORHEAD UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 14511 MSAS NO. 115 OVER THE RED RIVER OF THE NORTH DISTRICT 4 - CLAY COUNTY, CITY OF MOORHEAD PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY

More information

JOHNSON ROAD COVERED BRIDGE DESCRIPTION

JOHNSON ROAD COVERED BRIDGE DESCRIPTION JOHNSON ROAD COVERED BRIDGE DESCRIPTION The Johnson Road Bridge was built in 1869 and is possibly the oldest Smith Truss in existence. This structure was built using Smith's 1869 patent. This bridge carries

More information

9 Conclusion. 9.1 Introduction

9 Conclusion. 9.1 Introduction 9 Conclusion 9.1 Introduction This final chapter presents a synthesis of the evaluation criteria leading to conclusions and recommendations. Also included is a summary of the current status of the Tappan

More information

Movable Bridge Maintenance and Preservation

Movable Bridge Maintenance and Preservation Movable Bridge Maintenance and Preservation National Bridge Preservation Partnership Conference Orlando, Florida April 22 to 25, 2014 Stan Kaderbek, S.E., P.E. Agenda Movable Bridge Overview Structural

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO TRUNK HIGHWAY NO. 3 rd Avenue/Central Avenue OVER THE MISSISSIPPI RIVER

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO TRUNK HIGHWAY NO. 3 rd Avenue/Central Avenue OVER THE MISSISSIPPI RIVER UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 2440 TRUNK HIGHWAY NO. 3 rd Avenue/Central Avenue OVER THE MISSISSIPPI RIVER DISTRICT M HENNEPIN COUNTY OCTOBER 23, 2008 PREPARED FOR THE MINNESOTA DEPARTMENT

More information

DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION

DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION Vireak Hinh, P.Eng. R.V. Anderson Associates Ltd., Toronto, Canada Jennifer Trimble Region of Halton, Oakville, Canada

More information

OHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. BROAD ST., COLUMBUS, OHIO

OHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. BROAD ST., COLUMBUS, OHIO OHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. BROAD ST., COLUMBUS, OHIO 43216-0899 January 20, 2012 To: Users of the Bridge Design Manual From: Tim Keller, Administrator, Office of Structural

More information

KORA_Req._for_Eng._Studies_on_Stouffer_Apts. KU Reference No

KORA_Req._for_Eng._Studies_on_Stouffer_Apts. KU Reference No 000130 1 PURPOSE: Professional Engineering Consultants, P.A. (PEC) was engaged by University of Kansas Design & Construction Management to perform an assessment of Stouffer Place Apartment Building 20

More information

SECTION DRILLED CONCRETE PIERS AND SHAFTS

SECTION DRILLED CONCRETE PIERS AND SHAFTS 1 PART ONE - GENERAL 1.1 COORDINATION SECTION 02466 DRILLED CONCRETE PIERS AND SHAFTS A. The General, Supplementary, and Special Conditions of these specifications shall all be considered as a part of

More information

Conceptual Design Report

Conceptual Design Report Conceptual Design Report I-244/Arkansas River Multimodal Bridge Tulsa, Oklahoma Prepared for the Oklahoma Department of Transportation Prepared by: August 2009 I-244 / ARKANSAS RIVER MULTIMODAL BRIDGE

More information

The construction technology of Chongqing Chaotianmen Bridge

The construction technology of Chongqing Chaotianmen Bridge The construction technology of Chongqing Chaotianmen Bridge Zhongfu Xiang School of Civil Engineering & Architectures, Chongqing Jiaotong University, Chongqing, China Wei Xu China zhongtie major bridge

More information

Upon speaking with the representatives with Technical Foundations as well as Walder Foundations, it was determined that:

Upon speaking with the representatives with Technical Foundations as well as Walder Foundations, it was determined that: As part of our analyses, we have considered the design and construction of the cantilever retaining wall that will be located along the north side of Lucks Lane, between Falling Creek and Gladstone Glen

More information

BRIDGE DESIGN MANUAL UPDATES. Jamie F. Farris, P.E.

BRIDGE DESIGN MANUAL UPDATES. Jamie F. Farris, P.E. BRIDGE DESIGN MANUAL UPDATES Jamie F. Farris, P.E. October 2015 Table of Contents 1 BDM Chapter 2 Limit States and Loads 2 BDM Chapter 3 Superstructure Design 3 BDM Chapter 4 Substructure Design 4 Questions

More information

Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact

Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact Executive Summary:, located in Pigeon Forge, Tennessee, is designed as a multifunctional space and

More information

3.0 TEMPORARY DETOUR BRIDGES

3.0 TEMPORARY DETOUR BRIDGES 3.0 TEMPORARY DETOUR BRIDGES Table of Contents 3.1 General...1 3.2 STORAGE SITES:...2 3.3 BID ITEMS:...2 3.4 INDEX OF PLAN SHEETS with H-Pile:...3 3.5 INVENTORY SHEET FOR DETOUR BRIDGES WITH H-PILE:...4

More information

Red Wing Bridge Alternates

Red Wing Bridge Alternates Alternate 1 Tied Arch Alternate 2 Simple Span Truss Alternate 1 Design Drawing Alternate 2 Design Drawing Similar Bridge Design to Alternate 1 Similar Bridge Design to Alternate 2 Evaluation Matrix for

More information

COVER FEATURE. Micropile. Design Minimizes. California Edison Project

COVER FEATURE. Micropile. Design Minimizes. California Edison Project COVER FEATURE Micropile Foundation Design Minimizes Environmental Impact for Southern California Edison Project by Chih-Hung Chen, P.E., Burns & McDonnell, and Nick Salisbury, Crux Subsurface, Inc. Micropiles

More information

BRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT)

BRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT) SPECIAL PROVISION August 31, 2009 PROJECT # S-R399(42) PROJECT # S-R399(59) PIN # 6697/7236 SECTION 03253S BRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT) Add Section 03253S: PART

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CR 27 OVER THE RED LAKE RIVER DISTRICT 2 PENNINGTON COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CR 27 OVER THE RED LAKE RIVER DISTRICT 2 PENNINGTON COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 57521 CR 27 OVER THE RED LAKE RIVER DISTRICT 2 PENNINGTON COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS, INC. JOB

More information

Introduction to Structural Analysis TYPES OF STRUCTURES LOADS AND

Introduction to Structural Analysis TYPES OF STRUCTURES LOADS AND AND Introduction to Structural Analysis TYPES OF STRUCTURES LOADS INTRODUCTION What is the role of structural analysis in structural engineering projects? Structural engineering is the science and art

More information

SECTION DRILLED CONCRETE PIERS AND SHAFTS

SECTION DRILLED CONCRETE PIERS AND SHAFTS SECTION 31 63 29 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply

More information

OHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. BROAD ST., COLUMBUS, OHIO

OHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. BROAD ST., COLUMBUS, OHIO OHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. BROAD ST., COLUMBUS, OHIO 43216-0899 July 21, 2017 To: Users of the Bridge Design Manual From: Tim Keller, Administrator, Office of Structural

More information