DEMONSTRATING WATER STEWARDSHIP THROUGH INTEGRATED WASTEWATER MANAGEMENT: THE CITY OF KINGSTON, ONTARIO, CANADA

Size: px
Start display at page:

Download "DEMONSTRATING WATER STEWARDSHIP THROUGH INTEGRATED WASTEWATER MANAGEMENT: THE CITY OF KINGSTON, ONTARIO, CANADA"

Transcription

1 DEMONSTRATING WATER STEWARDSHIP THROUGH INTEGRATED WASTEWATER MANAGEMENT: THE CITY OF KINGSTON, ONTARIO, CANADA Bruce C. Anderson (1), An Dong (2), and Allen Lucas (3) (1) Department of Civil Engineering, Queen s University, Kingston, Ontario, Canada (2) Department of Environmental Science and Engineering, Fudan University, Shanghai, P.R. China (3) Utilities Kingston, Kingston, Ontario, Canada Abstract The City of Kingston (through Utilities Kingston, the asset management company responsible for utilities operations) has recently completed a significant upgrade at one of its two wastewater treatment facilities (Ravensview Water Pollution Control Plant, Ravensview ). This project was the largest infrastructure project ever undertaken in Kingston, and it was planned and executed with a major focus on public participation throughout, and with a view toward creating something more than just another sewage treatment plant. This paper provides details about the biological treatment component selection process for Ravensview (a biological aerated filter, BAF), including information from lab-scale and pilot-scale testing and full-scale operation, as well as information about the current operation of Ravensview in support of its new role in the creation of three important products, namely clean water, clean biosolids and green energy. In addition to the technical details, this paper includes an important focus on the societal benefits being realized and being planned for at Ravensview, in keeping with the overall goal of the upgrade. The projects and activities around these benefits are facilitating the role of this wastewater treatment facility in its larger capacity of an environmental centre that will provide continuing public education to foster a stewardship attitude among all citizens of Kingston, and serve as a template for other communities that are now facing federally-mandated requirements for improved wastewater treatment in their locations. Keywords: advanced wastewater treatment, biological aerated filtration, source water protection, integrated wastewater management, public education, water stewardship 865

2 1. INTRODUCTION 1.1 The City of Kingston The City of Kingston, Ontario, is one of the older cities in Canada, and briefly served as Canada s capital in the mid 1800 s. The City is situated at the eastern end of Lake Ontario (the last of the Great Lakes in the east), as this lake joins the St. Lawrence River with water flowing eastward to the Atlantic Ocean. Given this setting, it is not surprising to hear Kingston referred to as Canada s freshwater sailing capital, and water based activities are an important part of the Kingston economy, both past and present (e.g. sailing, swimming, recreational fishing, tourism, transportation and history). These water resources also serve as the source of drinking water for the City (intake from Lake Ontario), and as the receiver of treated wastewaters (discharged to both the Lake and the St. Lawrence River from the two wastewater treatment plants in the City). It is again not surprising to learn that the protection and preservation of these resources, in turn to protect and enhance the aquatic ecosystem, is an important mandate of the City, and part of the overall goal of Kingston to be Canada s most sustainable city. The challenge of realizing this goal lies in the age and historic design of Kingston, with combined sewers (conveying dry weather wastewater, and wet weather wastewater mixed with stormwater runoff) being a significant ongoing source of concern for the City. The age and performance of the older wastewater treatment plant (Ravensview) has also been of concern recently (despite the fact that this plant has normally functioned within the compliance requirements set by the provincial Ministry of Environment, MOE), and this plant has therefore been the focus of the largest infrastructure upgrade in the City s history over the past 5 years. This paper presents an overview of this important project, from both the technological perspective as well as from the perspective of wastewater management fitting into the larger role of water stewardship for Kingston. 1.2 Kingston and Water Stewardship A recent survey of Canadians living in urban centres across the country found that the majority of those surveyed (80%) were worried about the water quality at their local beaches and swimming holes [1]. It was also found that in certain parts of the country with rudimentary or no wastewater treatment, this fear was based mainly on the perception of raw sewage discharge directly into these water resources; elsewhere a similar fear about water quality was found, but the reasons for this fear were unknown. Interestingly, participants from areas with high level wastewater treatment were significantly less worried about water quality (but were still concerned nonetheless). It might be concluded from this survey that the presence of advanced wastewater treatment is only one component of successfully creating a stewardship attitude among urban citizens; the other important component must be a public education and awareness program that allows residents to understand the value and limitations of integrated wastewater management for water resource protection (to create an informed 866

3 and engaged citizenry). The Ravensview upgrade is therefore seen as an excellent model for this multi-faceted approach to wastewater engineering, as is described in this paper. As noted, this upgrade project was the largest infrastructure project ever undertaken in Kingston, and it was planned and executed with a major focus on public participation throughout, and with a view toward creating something more than just another sewage treatment plant. Interestingly, this project was conceived in recognition of the importance of protecting local source waters, and before programs like the provincial source water protection activities (as an outgrowth of the 2005 Ontario Clean Water Act; see for local details) or the current federal focus on a national standard for wastewater effluent (through the Canadian Council of Ministers of the Environment, CCME). It is notable that the CCME initiative has now identified treatment plants across the country that will need to upgrade over the short- (within 10 years) or longer-terms (up to 30 years); given this, the current state of the Ravensview facility means that Kingston is already exceeding current (and future) expectations and requirements of treatment efficiency, and is therefore affording an enhanced level of source water stewardship that can serve as a model for other jurisdictions. 2. THE RAVENSVIEW UPGRADE PROJECT 2.1 Background Ravensview was originally constructed in 1957, and upgraded/expanded in 1974 and 1994 respectively. Before the current project, the rated treatment capacity was 72,800 m 3 /d (average daily), with a peak hourly flow of 152,500 m 3 /d. The plant was a chemically assisted primary treatment facility serving the downtown and Kingston east areas (Figure 1); solids processing included anaerobic stabilization, solids dewatering and off-site land spreading. Typical effluent quality criteria (as per MOE) were 25/25/1.0/0.04 BOD 5 /SS/TP/Total residual chlorine (in mg/l, generally as annual average concentrations). For the period 1999 to 2003, the plant performance was summarized as follows [2]: effluent suspended solids concentration consistently below compliance limit (with about 89% SS removal); effluent BOD 5 concentration highly dependant on extraneous flows from combined sewer system, with monthly average and annual average values variable (with 60-70% removal efficiencies, as a function of particulate matter removal in the clarifiers); effluent TP removal efficiencies were proportional to the amount of metal salts added during the treatment process (as ferric chloride), with effluent values typically below the compliance limit (and 65-75% removal efficiency) 867

4 Figure 1: Location of Kingston and Ravensview (image from mapquest.ca) 2.2 Need for upgrade On-going economic development and urban growth in the serviced Kingston area in the 5 year period prior to 2004 was rapidly consuming the existing hydraulic capacity of Ravensview, and at times during this period the average daily flow capacity was exceeded. An additional driver for change was the on-going program in collection system upgrade and elimination of extraneous flows (as stormwater runoff), resulting in a stronger influent wastewater loading; as a result, the plant was also approaching the provincially mandated compliance limits noted above (particularly for the soluble constituents). In conjunction with this, it was recognized early on that a more reliable process for the removal of soluble organics and nutrients would be required in the near future (e.g. installation of a secondary or biological treatment component), which would ensure that the plant was achieving its principal goal of source water protection in the St. Lawrence River over the longer term. The need for a better treatment system, to provide additional hydraulic capacity for urban growth and significantly improved treatment performance for both the liquid and solids streams, was foreseen by the City of Kingston long before this became a requirement in the province and the country (as per CCME in 2009), and represents an excellent example of the city s pro-activity in water stewardship for the region. To facilitate the selection of an appropriate treatment technology, and in accordance with regulatory requirements, Utilities Kingston (through J.L. Richards & Associates Ltd., and XCG Consultants Ltd.) undertook a Class Environmental Assessment update which investigated various upgrade options at the plant to meet MOE requirements (Policy F-5) and to service the projected long-term growth in the area. One of the recommendations from this study was biological aerated filtration (BAF) as the preferred secondary treatment process, along with a hydraulic expansion of Ravensview to 95,000 m 3 /d average daily flow. While the BAF process had been investigated and implemented in Europe (see review in [3]), in Canada there were only three BAF units in operation (with 2 other facilities in the design phase). 868

5 Given this lack of BAF design and operational experience in Canada, and the fact that this BAF facility would be the largest such facility in Canada once implemented, it was deemed very important that a comprehensive lab and pilot testing program precede the actual BAF design, to ensure appropriate local data on system performance were available to the design team. It was also reasoned that this unique BAF application had the potential to serve as a template for other communities, hence the importance of getting it right before implementation. Finally, the design team recognized that, by implementing the BAF process at Ravensview (as the largest infrastructure project in Kingston history), Kingston had a chance to be a leader in innovation in water stewardship, through the highlighting of the critical importance of wastewater management in Canada. This again can be seen as an example of the foresight of this project by the City of Kingston and Utilities Kingston, since the discussion about the state of wastewater management in Canada (and the need for improvement) is currently becoming more commonplace in the national media [4]. 2.3 Research and testing program for system selection The testing program consisted of both pilot testing on site, and laboratory testing at Queen s University. The pilot testing was conducted specifically to assess the applicability of two different BAF technologies (Biofor supplied by Degrémont Ltd., and Biostyr supplied by John Meunier Inc.) for treating existing raw sewage to meet the target effluent requirement for the upgraded facility (including seasonal effects on operation); this side-by-side real time testing also allowed for a comprehensive comparison between the different BAF technologies. Due to the relatively low concentration of the raw sewage at Ravensview, as well as some operational constraints during pilot testing, a laboratory scale research program was also conducted in the Department of Civil Engineering, Queen s University. In this phase a scaled Biostyr system was constructed to investigate in detail the treatment performance and mechanisms of the BAF process, using synthetic wastewater. Specific research objectives here included investigation of the physical properties of the filtration medium, investigation of the BAF performance for high strength wastewater treatment (robustness testing), examination of important operational parameters (e.g. organic and hydraulic loading, aeration and backwash regime) on overall performance, and a preliminary kinetics study to model substrate removal in the BAF reactor. 869

6 Figure 2: Pilot testing BAF Units (L -Biofor ; R - Biostyr ) Figure 2 illustrates the physical set up of the two BAF systems on site (housed in a temporary building to allow for environmental control). Table 1 summarizes the pilot testing operational conditions (specifically the hydraulic loading rates for the 2 systems, for a variety of operational conditions, i.e. average daily flow, peak daily flow, etc.). In parallel with the pilot testing activities, the laboratory testing was run over a shortened time period, and Figure 3 illustrates the laboratory BAF column setup, with Table 2 summarizing the investigated parameters in this phase of the work. 1050mm In. Dia:100mm 3120mm Backwash Pump Treated wastewater Mesh (Screen) and gasket 1070mm 900 (Media height) Biomass sampling port Wastewater sampling tap Air compressor Backwash Solids Disposal Feeding Pump Synthetic wastewater Figure 3: Laboratory BAF testing unit 870

7 Table 1: Pilot testing operational conditions Parameter Full-scale design flow (m 3 /d) Peak flow factor Equivalent flow to Biofor pilot (m 3 /h) Equivalent flow to Biostyr pilot (m 3 /h) Average flow 95, Maximum flow 167, Peak Hour flow 192, Table 2: Pilot testing operational conditions Hydraulic loading (m 3 /m 2.h) Flow rate (L/h) Process air rate (L/h) Ratio of process air to water flow Backwash rate Water rinse (L/m 2.s) Air scour (L/m 2.s) As noted previously this was a comprehensive evaluation of the BAF process at the field and laboratory scales, which allowed for a robust data set to be created to help with system selection (Biofor or Biostyr ), and allowed the Ravensview operators to work with the system before full implementation. As a result of this evaluation, the Biostyr BAF process was chosen for full design, for reasons of both process effectiveness and operational simplicity (specifically for ammonium nitrogen removal and excess biomass generation). Figure 4 summarizes typical pilot scale operating results for both systems, and Table 3 provides a parameter by parameter comparison of Biofor and Biostyr performance at the pilot scale level. 871

8 Effluent Concentration (mg/l) BOD 5, TSS Design Objective (15mg/L) Biostyr Biofor TSS BOD 5 TKN TN TP Overall Performance of Two BAF Systems Figure 4: Summarized pilot-scale BAF performance Table 3: Pilot testing results summary (average % removal) System BOD 5 TSS COD TN NH 3 -N TKN Biostyr Biofor Implementation of system upgrade at Ravensview Once the BAF process selection was made, the 3 year renovation of the Ravensview treatment plant began. When completed (including the one-year proof of performance period), the plant was officially opened on 09 October 2009 (see Figure 5 for construction photos). From the beginning of this project, it set excellent benchmarks for infrastructure renewal, in terms of both environmental and fiscal responsibility. The overall cost of the project came in at approximately CAN $13,000,000 less than budgeted, and the project was completed ahead of schedule, thanks in large part to the attention paid to the concept of team-building among the contractors, administrators and the City during construction. Many have commented that this project, while extremely complex, was also the best administered in their experience. The success of this project can also be seen in the early performance data for average effluent concentrations: cbod 5 8.7/25.0 mg/l; suspended solids 3.7/25.0; phosphorus 0.48/1.0 (achieved/moe compliance level). 872

9 Figure 5: BAF construction (top L blasting limestone; top R BAF basins; bottom hydraulic testing of BAF basins) Another component worth noting during the upgrade was the involvement and engagement of the citizens of Kingston, with a Public Liaison Committee (PLC) and a Construction Liaison Committee (CLC) struck at appropriate times during the project. These committees were very active in helping with the regular newsletter distributed across the City, ensuring that questions and concerns were addressed in a very timely manner, and they were also active in the planning and execution of all aspects of the project. Many of the committee members live in close proximity to the treatment plant, and were therefore the residents to be most impacted by the construction project; the general consensus among these members, however, was also that this project had very little impact on their daily lives, and the completed project had actually improved other aspects of the area (i.e. walking and cycling trails, wildlife corridors and natural landscaping). These committees helped to create a significant educational identity for Ravensview (as did the project website and real time web cam), which allowed the public at large to understand exactly what was happening, why it was happening, and why it was important from the perspective of source water protection in the Kingston region (in essence helping to generate a water stewardship mindset among the residents of Kingston). 3. RAVENSVIEW AS AN ENVIRONMENTAL CENTRE One of the anticipated outcomes of the Ravensview upgrade project for Utilities Kingston and the City of Kingston was the creation of an environmental centre, with wastewater management as only one important aspect of water stewardship, and with integration of other environmental aspects of the urban landscape into this site [5]. It is commonly stated that Ravensview directly produces three important products: clean water, high quality residual solids for agricultural use and clean energy from the solids stabilization process (which was also upgraded during the project). The entire upgrade project has demonstrated a high level of sustainability principles, starting with the selection of the BAF process (to reduce the overall footprint of the biological treatment system and thus minimize site disturbance), and continuing with reuse of most of the blasted rock on site and application for LEED certification for certain aspects of the upgrade (if successful, this would be one of the first such certifications, which would help raise the profile of wastewater servicing). 873

10 Ravensview will also now serve as a first-class facility for Queen s University researchers. There are already a number of projects on-going at Ravensview (e.g. integration of organic solid waste into the biosolids stabilization process for enhanced biogas generation; isolation of hydrogen from the biogas for use in solid oxide fuel cells), with other research project ideas in discussion including use of the high quality effluent for non-potable urban water uses like landscape irrigation, and investigation of the presence and risk posed by pharmaceuticals and personal care products in wastewater collection systems (with a longer term view to the mitigation measures that might be required by city officials). From these projects, a clearer idea is anticipated of the role of wastewater processing in the creation of sustainable, water smart cities of the future, where we can break away from the old design paradigm of excessive water use to generate flushing flows for wastewater collection systems, and where we can identify and recover materials of value in these formerly undervalued flows (e.g. phosphorus capture and recovery; green energy generation, etc.). In this light, the Ravensview upgrade has allowed this discussion to begin in earnest, and it is anticipated that this facility will continue to engage the citizens of Kingston, and serve as a template for the way forward for other Canadian (and international) cities wrestling with similar concerns. REFERENCES [1] Zimonjic, P. Poll: Albertans least worried about water quality, The Toronto Sun, April 4 (2010). [2] J.L. Richards and XCG Consultants Ltd. Technical Memorandum Biological Aerated Filter Technology Pilot Testing Program at the Ravensview WPCP, City of Kingston, Utilities Kingston (2004). [3] Tan, H. An Evaluation of Biological Aerated Filtration for Wastewater Treatment through Pilot and Laboratory Scale Experiments, M.Sc.(Eng.) thesis, Department of Civil Engineering, Queen s University (2007). [4] Zimonjic, P. and Burnett, T. Canada s dirty little secret, The Kingston Whig Standard, May 29 (2010). [5] Anderson, B.C. Sustainable infrastructure: Ravensview sewage treatment plant upgrade, in The Story of Brownfields Development and Smart Growth in Kingston, Ontario: From Contamination to Revitalization, Welbourn, P., Cleghorn, H., Davis, J., Rose, S. (eds)., Classroom Complete Press (2009), 325p. 874

Pollution Control in the City of Windsor Wastewater & CSO Management 2013 Status & Update

Pollution Control in the City of Windsor Wastewater & CSO Management 2013 Status & Update Pollution Control in the City of Windsor Wastewater & CSO Management 2013 Status & Update The 7 th Biennial Meeting of the Lake Erie Millennium Network Status of Lake Erie Management Needs & Research Questions

More information

International Joint Commission Water & Wastewater Treatment Best Management Practices Forum Monday, March 26, 2012 Wayne State University, Detroit MI

International Joint Commission Water & Wastewater Treatment Best Management Practices Forum Monday, March 26, 2012 Wayne State University, Detroit MI STARTUP AND OPERATION OF A BIOLOGICAL AERATED FILTER (BAF) FOR SIMULTANEOUS BOD REMOVAL AND NITRIFICATION AT THE LOU ROMANO WATER RECLAMATION PLANT WINDSOR ONTARIO CANADA International Joint Commission

More information

The Municipality of North Grenville

The Municipality of North Grenville A solution is required to increase the peak flow capacity of the Kemptville WPCP, a conventional activated sludge process, within a small footprint while maintaining good effluent quality. Location: Kemptville

More information

BEING GOOD STEWARDS: IMPROVING EFFLUENT QUALITY ON A BARRIER ISLAND. 1.0 Executive Summary

BEING GOOD STEWARDS: IMPROVING EFFLUENT QUALITY ON A BARRIER ISLAND. 1.0 Executive Summary BEING GOOD STEWARDS: IMPROVING EFFLUENT QUALITY ON A BARRIER ISLAND Brett T. Messner, PE, Tetra Tech, Inc., 201 E Pine St, Suite 1000, Orlando, FL 32801 Brett.Messner@tetratech.com, Ph: 239-851-1225 Fred

More information

Regional Municipality of Halton Skyway Wastewater Treatment Plant Expansion Municipal Class Environmental Assessment Study

Regional Municipality of Halton Skyway Wastewater Treatment Plant Expansion Municipal Class Environmental Assessment Study Welcome to the Regional Municipality of Halton Skyway Wastewater Treatment Plant Expansion Municipal Class Environmental Assessment Study September 23, 2009 Please Sign In and take an Information Brief

More information

Determination of Treatment Requirements for Municipal and Private Sewage Treatment Works Discharging to Surface Waters

Determination of Treatment Requirements for Municipal and Private Sewage Treatment Works Discharging to Surface Waters PROCEDURE F-5-1 (formerly referenced by 08-01) Determination of Treatment Requirements for Municipal and Private Sewage Treatment Works Discharging to Surface Waters PROCEDURE F-5-1 DETERMINATION OF TREATMENT

More information

2017 Annual Performance Report

2017 Annual Performance Report Newcastle Water Pollution Control Plant The Regional Municipality of Durham Newcastle Water Pollution Control Plant Environmental Compliance Approval (ECA): 3-2189-87-946 Dated July 26, 1994 Amendments:

More information

Duffin Creek Water Pollution Control Plant Technical Information

Duffin Creek Water Pollution Control Plant Technical Information Duffin Creek Water Pollution Control Plant Technical Information Plant History The Duffin Creek Water Pollution Control Plant (WPCP) is located on the northern shore of Lake Ontario in the City of Pickering

More information

Post-Aerobic Digester with Bioaugmentation Pilot Study City of Meridian, ID WWTP PNCWA 2010

Post-Aerobic Digester with Bioaugmentation Pilot Study City of Meridian, ID WWTP PNCWA 2010 Post-Aerobic Digester with Bioaugmentation Pilot Study City of Meridian, ID WWTP by: William Leaf Adrienne Menniti Bruce Johnson CH2M HILL, Inc. Clint Dolsby Tracy Crane City of Meridian October 26, 21

More information

EPA Waste Water Discharge Licence Application

EPA Waste Water Discharge Licence Application Duleek Waste Water Treatment Works EPA Waste Water Discharge Licence Application ARTICLE 16 COMPLIANCE REQUIREMENTS Meath County Council EPA Document Ref: D0133-01 Section A: Non-Technical Summary Update

More information

2017 Performance Report for Bobcaygeon Waste Water Treatment Facility

2017 Performance Report for Bobcaygeon Waste Water Treatment Facility 2017 Performance Report for Bobcaygeon Waste Water Treatment Facility Amended Environmental Certificate of Approval (ECA) #3028-AEUKDQ Section 11(4) requires the Performance Reports to contain the following:

More information

Mid-Halton Wastewater (Sewage) Treatment Plant Expansion And Effluent Sewer Public Information Centre # 1 May 14, 2009

Mid-Halton Wastewater (Sewage) Treatment Plant Expansion And Effluent Sewer Public Information Centre # 1 May 14, 2009 INFORMATION BRIEF MID-HALTON WASTEWATER (SEWAGE) TREATMENT PLANT EXPANSION AND EFFLUENT SEWER SCHEDULE C CLASS ENVIRONMENTAL ASSESSMENT PUBLIC INFORMATION CENTRE (PIC) # 1 1 Municipal Class Environmental

More information

Promote fiscally responsible asset management of existing and proposed new infrastructure.

Promote fiscally responsible asset management of existing and proposed new infrastructure. 10.0 Infrastructure Goals Promote fiscally responsible asset management of existing and proposed new infrastructure. Promote all sources of water as a valuable resource through the conservation of water,

More information

ENGINEERED WETLAND TECHNOLOGY TO ADVANCE STORMWATER QUALITY TREATMENT. Sheldon Smith March 28, Photo Optional

ENGINEERED WETLAND TECHNOLOGY TO ADVANCE STORMWATER QUALITY TREATMENT. Sheldon Smith March 28, Photo Optional ENGINEERED WETLAND TECHNOLOGY TO ADVANCE STORMWATER QUALITY TREATMENT Sheldon Smith March 28, 2012 Photo Optional TWO BASIC TYPES OF CONSTRUCTED WETLANDS Stormwater (SW) Wetlands Treatment Wetlands A Stormwater

More information

Startup and Performance of the World s first Large Scale Primary Dissolved Air Floatation Clarifier ABSTRACT KEYWORDS INTRODUCTION

Startup and Performance of the World s first Large Scale Primary Dissolved Air Floatation Clarifier ABSTRACT KEYWORDS INTRODUCTION Startup and Performance of the World s first Large Scale Primary Dissolved Air Floatation Clarifier Bruce R. Johnson 1 *, Jennifer Phillips 2, Tim Bauer 3, Greg Smith 4, George Smith 5, John Sherlock 6

More information

APPENDIX C. Public Consultation Centre (PCC) Displays. Appendix C1 PCC#1 Appendix C2 PCC#2 Appendix C3 PCC#3

APPENDIX C. Public Consultation Centre (PCC) Displays. Appendix C1 PCC#1 Appendix C2 PCC#2 Appendix C3 PCC#3 APPENDIX C Public Consultation Centre (PCC) Displays Appendix C1 PCC#1 Appendix C2 PCC#2 Appendix C3 PCC#3 Appendix C1 PCC#1 Appendix C2 PCC#2 Township of Red Rock Class Environmental

More information

by M k h GROVER Degremont

by M k h GROVER Degremont Innovative Technologies for Urban Waste Water Treatment by M k h GROVER Mukesh Degremont 4th March2013 Sewage a complex waste water URBAN WASTE WATER - SEWAGE Source of Foul odour Infectious Diseases Surface

More information

The Don River and Central Waterfront are among the most degraded waterways in the City of Toronto.

The Don River and Central Waterfront are among the most degraded waterways in the City of Toronto. This document was put together following the fourth round of public consultation for the Class Environmental Assessment study for this Project. In June 2011, the Project Team consulted with stakeholders

More information

SEWAGE SYSTEM SOLUTIONS Current Issues in Ontario & Case Studies of Innovative Approaches to Remedy Failing Systems

SEWAGE SYSTEM SOLUTIONS Current Issues in Ontario & Case Studies of Innovative Approaches to Remedy Failing Systems SEWAGE SYSTEM SOLUTIONS Current Issues in Ontario & Case Studies of Innovative Approaches to Remedy Failing Systems Marie-Christine Bélanger Director Ontario Onsite Wastewater Association Rick Esselment

More information

CANADA-WIDE APPROACH FOR THE MANAGEMENT OF WASTEWATER BIOSOLIDS. October 11, 2012 PN 1477

CANADA-WIDE APPROACH FOR THE MANAGEMENT OF WASTEWATER BIOSOLIDS. October 11, 2012 PN 1477 CANADA-WIDE APPROACH FOR THE MANAGEMENT OF WASTEWATER BIOSOLIDS October 11, 2012 PN 1477 Canadian Council of Ministers of the Environment, 2012 Table of Contents 1. Context... 1 2. Policy Statement and

More information

Wastewater Treatment Processes

Wastewater Treatment Processes Wastewater Treatment Processes (Sep 27 th and 28 th, 2016) by Dr. Arun Kumar (arunku@civil.iitd.ac.in) Objective: To learn about processes used in tertiary treatment Courtesy: Dr. Irene Xagoraraki, MSU,

More information

WEAO STUDENT DESIGN COMPETITION 2019 PROJECT STATEMENT

WEAO STUDENT DESIGN COMPETITION 2019 PROJECT STATEMENT Water Environment Association of Ontario Young Professionals Committee and Student Design Competition Sub-Committee and the Ontario Ministry of the Environment and Climate Change in Collaboration with

More information

Role of Entrant s Firm. »» Final Design»» Completion of Funding. »» Engineering Services During Applications. »» Plant Startup and Filtration

Role of Entrant s Firm. »» Final Design»» Completion of Funding. »» Engineering Services During Applications. »» Plant Startup and Filtration ROLE OF OTHERS For the design focus of the project, key partners included:»» Mortenson Construction, Contractor»» Jacobs, Contract Plant Operator»» Portland Engineering and Controls, I&C The City of The

More information

WWETCO FlexFilter and Bio-FlexFilter

WWETCO FlexFilter and Bio-FlexFilter Innovative Filter Technology Tool for Reducing Energy, Expanding Capacity, Wet Weather Management and Nutrient Control WWETCO WWETCO FlexFilter and Bio-FlexFilter AGENDA WWETCO FlexFilter & Bio-FlexFilter

More information

RE: Annual Report 2016 Wardsville Wastewater Treatment Plant and Collection System

RE: Annual Report 2016 Wardsville Wastewater Treatment Plant and Collection System 14 th, 217 Tom Clubb 3232 White Oak Road, 3 rd Floor London ON N6E 1L8 Attention: Mr. Clubb RE: Annual Report 216 Wardsville Wastewater Treatment Plant and Collection System The Ontario Clean Water Agency

More information

Chapter 6 Objective: Protect and Enhance the Environment

Chapter 6 Objective: Protect and Enhance the Environment Chapter 6 Objective: Protect and Enhance the Environment 49 Irish Water Water Services Strategic Plan Our Strategic Aims Ensure that Irish Water services are delivered in a sustainable manner which contributes

More information

O R A N G E C I T Y S INTEGRAT E D W AT E R R E S O U R C E S M A N A G E M E N T & R E S I L I E N C Y P L A N

O R A N G E C I T Y S INTEGRAT E D W AT E R R E S O U R C E S M A N A G E M E N T & R E S I L I E N C Y P L A N O R A N G E C I T Y S INTEGRAT E D W AT E R R E S O U R C E S M A N A G E M E N T & R E S I L I E N C Y P L A N Cooperation is Key Cooperation among Volusia County and Cities is critical to solve our water

More information

City of Portsmouth Wastewater Division. Wastewater Facilities and Programs. City Council Briefing and Public Input Session

City of Portsmouth Wastewater Division. Wastewater Facilities and Programs. City Council Briefing and Public Input Session City of Portsmouth Wastewater Division Wastewater Facilities and Programs City Council Briefing and Public Input Session Briefing #2 June 11, 2012 November 8, 2011 Topics for Discussion Introduction Regulatory

More information

Policy Review of Municipal Stormwater Management in the Light of Climate Change Summary Report

Policy Review of Municipal Stormwater Management in the Light of Climate Change Summary Report Policy Review of Municipal Stormwater Management in the Light of Climate Change Summary Report Executive Summary In response to an Application for Review submitted under the Environmental Bill of Rights,

More information

Environment Plan Sydney Water s objectives, targets and actions to protect the environment and enhance the liveability of our communities.

Environment Plan Sydney Water s objectives, targets and actions to protect the environment and enhance the liveability of our communities. Environment Plan 18 Sydney Water s objectives, targets and actions to protect the environment and enhance the liveability of our communities. Environment Plan 18 Introduction Sydney Water s vision is to

More information

OPERATIONAL CHALLENGES AT THE KOORLONG WASTEWATER TREATMENT PLANT. Derek de Waal Kevin Murphy

OPERATIONAL CHALLENGES AT THE KOORLONG WASTEWATER TREATMENT PLANT. Derek de Waal Kevin Murphy OPERATIONAL CHALLENGES AT THE KOORLONG WASTEWATER TREATMENT PLANT Paper Presented by : Derek de Waal Kevin Murphy Authors: Derek de Waal, Operations Manager, Gutteridge Haskins & Davey Pty Ltd Kevin Murphy,

More information

Watertown Wastewater Facility Plan. August 11, 2015

Watertown Wastewater Facility Plan. August 11, 2015 Watertown Wastewater Facility Plan August 11, 2015 Watertown Wastewater Wastewater Treatment Facility History Comprehensive Planning Wastewater Concerns Capacity Condition Permitting Requirements Watertown

More information

Dealing with Unexpected Wastewater Treatment Plant Disruptions. February 16, 2017

Dealing with Unexpected Wastewater Treatment Plant Disruptions. February 16, 2017 Dealing with Unexpected Wastewater Treatment Plant Disruptions February 16, 2017 Location Map WPCP History Original WPCP constructed on this site in 1928 consisting of primary treatment and chlorination;

More information

WINNIPEG SEWAGE TREATMENT PROGRAM --- SEWPCC --- Process Selection Report presentation

WINNIPEG SEWAGE TREATMENT PROGRAM --- SEWPCC --- Process Selection Report presentation WINNIPEG SEWAGE TREATMENT PROGRAM --- SEWPCC --- Process Selection Report presentation January 24th 2011 - Winnipeg Purpose of the meeting 2 immediate purposes : Explain the recommandation of the PSR to

More information

Watershed Overview of Wastewater Treatment Plant Performance

Watershed Overview of Wastewater Treatment Plant Performance Watershed Overview of Wastewater Treatment Plant Performance Report prepared by: Grand River Conservation Authority 400 Clyde Road Cambridge ON N1R 5W6 May 2014 Table of Contents Acronyms and Abbreviations...ii

More information

Copies: Mark Hildebrand (NCA) ARCADIS Project No.: April 10, Task A 3100

Copies: Mark Hildebrand (NCA) ARCADIS Project No.: April 10, Task A 3100 MEMO To: Jeff Pelz (West Yost) Kathryn Gies (West Yost) Copies: Mark Hildebrand (NCA) ARCADIS U.S., Inc. 200 Harvard Mills Square Suite 430 Wakefield Massachusetts 01880 Tel 781 224 4488 Fax 781 224 3033

More information

Performance Evaluation of the Moores Creek Advanced Water Resource Recovery Facility

Performance Evaluation of the Moores Creek Advanced Water Resource Recovery Facility Performance Evaluation of the Moores Creek Advanced Water Resource Recovery Facility Richard W. Gullick, Ph.D. Director of Operations Timothy Castillo Wastewater Manager Presented to the Albemarle County

More information

Dundalk Wastewater Treatment Plant

Dundalk Wastewater Treatment Plant Township of Southgate Dundalk Wastewater Treatment Plant 2016 Annual Report Jim Ellis Public Works Manager Dundalk Wastewater Treatment Plant 2016 Annual Report Table of Contents Wastewater Treatment Plant

More information

WEFTEC.06. **Cobb County Water System, Marietta, Georgia

WEFTEC.06. **Cobb County Water System, Marietta, Georgia CHEMICALLY ENHANCED PRIMARY TREATMENT FOR A LARGE WATER RECLAMATION FACILITY ON A CONSTRICTED SITE - CONSIDERATIONS FOR DESIGN, START-UP, AND OPERATION ABSTRACT Jeffrey A. Mills, P.E., BCEE,* Roderick

More information

A Battle to Be the Best: A Comparison of Two Powerful Sidestream Treatment Technologies: Post Aerobic Digestion and Anammox

A Battle to Be the Best: A Comparison of Two Powerful Sidestream Treatment Technologies: Post Aerobic Digestion and Anammox A Battle to Be the Best: A Comparison of Two Powerful Treatment Technologies: Post Aerobic Digestion and Anammox David Oerke/CH2M Tom Johnson/CH2M Bruce Johnson/CH2M Heidi Bauer/CH2M Steve Graziano/CH2M

More information

VILLAGE OF ALGONQUIN 2014 WASTEWATER FACILITY PLAN UPDATE EXECUTIVE SUMMARY

VILLAGE OF ALGONQUIN 2014 WASTEWATER FACILITY PLAN UPDATE EXECUTIVE SUMMARY EXECUTIVE SUMMARY EXECUTIVE SUMMARY INTRODUCTION AND BACKGROUND The Village of Algonquin, located along the Fox River in McHenry County, provides wastewater collection and treatment services to the entire

More information

BIO-BATCH TM. Sequencing Batch Reactor (SBR) Water & Wastewater Treatment

BIO-BATCH TM. Sequencing Batch Reactor (SBR) Water & Wastewater Treatment BIO-BATCH Sequencing Batch Reactor (SBR) Napier-Reid s Bio-Batch SBR is an effective aerobic biological system to remove pollutants i.e. BOD, COD, Suspended Solids, Nitrogen and Phosphorous from municipal

More information

Efficient Design Configurations for Biological Nutrient Removal

Efficient Design Configurations for Biological Nutrient Removal Efficient Design Configurations for Biological Nutrient Removal A Case Study: Upper Blackstone Water Pollution Abatement District Jane E. Madden, P.E., BCEE August 30, 2017 UBWPAD Wastewater Treatment

More information

Chapter 2: Description of Treatment Facilities

Chapter 2: Description of Treatment Facilities 2020 Facilities Plan Treatment Report 2.1 Introduction Chapter 2: Description of Treatment Facilities This chapter defines the Milwaukee Metropolitan Sewerage District (MMSD) service area. It also describes

More information

Upgrading Lagoons to Remove Ammonia, Nitrogen, and Phosphorus *nutrient removal in cold-climate lagoon systems

Upgrading Lagoons to Remove Ammonia, Nitrogen, and Phosphorus *nutrient removal in cold-climate lagoon systems Upgrading Lagoons to Remove Ammonia, Nitrogen, and Phosphorus *nutrient removal in cold-climate lagoon systems October 7, 2015 3:15 4:00pm Session M Room Tamboti / Aloes-wood Treatment Processes Aerated

More information

EGANVILLE SEWAGE SYSTEM 2013 PERFORMANCE REPORT

EGANVILLE SEWAGE SYSTEM 2013 PERFORMANCE REPORT EGANVILLE SEWAGE SYSTEM 2013 PERFORMANCE REPORT Township of Bonnechere Valley Water and Sewage Department January 2014 Table of Contents Executive Summary... 3 Introduction... 4 Report Availability...

More information

Preparing for Nutrient Removal at Your Treatment Plant

Preparing for Nutrient Removal at Your Treatment Plant Summer Seminar Emerging Issues in the Water/Wastewater Industry Preparing for Nutrient Removal at Your Treatment Plant Rajendra P. Bhattarai, P.E., BCEE Austin Water Utility Ana J. Peña-Tijerina, Ph.D.,

More information

Baltimore City Department of Public Works

Baltimore City Department of Public Works Baltimore City Department of Public Works Back River WWTP Process and Construction Overview Michael F. Gallagher, Chief Wastewater Facilities Division Wastewater Treatment Chesapeake Bay Restoration Water

More information

Membrane Bio-Reactors (MBRs) The Future of Wastewater Technology, Science and Economy Aspects

Membrane Bio-Reactors (MBRs) The Future of Wastewater Technology, Science and Economy Aspects Membrane Bio-Reactors (MBRs) The Future of Wastewater Technology, Science and Economy Aspects Glen T. Daigger, Ph.D., P.E., DEE, NAE Senior Vice President and Chief Technology Officer CH2M HILL Presented

More information

W O C H H O L Z R E G I O N A L W A T E R R E C L A M A T I O N F A C I L I T Y O V E R V I E W

W O C H H O L Z R E G I O N A L W A T E R R E C L A M A T I O N F A C I L I T Y O V E R V I E W Facility Overview The recently upgraded and expanded Henry N. Wochholz Regional Water Reclamation Facility (WRWRF) treats domestic wastewater generated from the Yucaipa-Calimesa service area. The WRWRF

More information

Presentation Outline

Presentation Outline Presentation Outline Nitrification/denitrification refresher Treatment technologies available for nitrification and BNR/ENR What is the problem? BNR/ENR VPDES permitting Causes of reduced BNR performance

More information

Characteristics and performance of small and medium wastewater treatment plants in Greece

Characteristics and performance of small and medium wastewater treatment plants in Greece Characteristics and performance of small and medium wastewater treatment plants in Greece Evina Gavalakis, Civil-Environmental Engineer- PhD EMVIS SA Polina Poulou, Chemical Engineer- MSc Special Secretariat

More information

Review of on-site and communal water and sanitation systems for remote communities

Review of on-site and communal water and sanitation systems for remote communities Environmental Economics and Investment Assessment II 275 Review of on-site and communal water and sanitation systems for remote communities A. Perks & T. Johnson R.V. Anderson Associates Limited, Ottawa,

More information

Enhanced Nitrogen Removal Using Upflow Biological Filtration

Enhanced Nitrogen Removal Using Upflow Biological Filtration Enhanced Nitrogen Removal Using Upflow Biological Filtration November 30, 2005 B. Stitt, G. Welch Presentation Outline Background Need for Project CT General Permit Evaluation of Alternatives Project Delivery

More information

PUBLIC INFRASTRUCTURE AND UTILTIES

PUBLIC INFRASTRUCTURE AND UTILTIES PUBLIC INFRASTRUCTURE AND UTILTIES Des Moines works to keep our built environment functional and safe for all residents and businesses. The City provides basic infrastructure and public services to all

More information

Alexandria Sewage Lagoon Treatment Facility Municipal Class C Environmental Assessment Public Information Centre #2 Welcome!

Alexandria Sewage Lagoon Treatment Facility Municipal Class C Environmental Assessment Public Information Centre #2 Welcome! Alexandria Sewage Lagoon Treatment Facility Municipal Class C Environmental Assessment Public Information Centre #2 Welcome! Municipal Class Environmental Assessment Status We are Here Study Overview The

More information

MUNICIPALITY OF WEST ELGIN RODNEY WASTEWATER TREATMENT PLANT

MUNICIPALITY OF WEST ELGIN RODNEY WASTEWATER TREATMENT PLANT MUNICIPALITY OF WEST ELGIN RODNEY WASTEWATER TREATMENT PLANT 214 ANNUAL REPORT uary 1 to ember 31, 214 Environmental Compliance Approval # 3-871-88-949 Prepared by: Table of Contents Section 1: Overview...

More information

Presented By: Kevin Bossy. The Supplier Perspective: Accelerating the Adoption of Innovative Solutions

Presented By: Kevin Bossy. The Supplier Perspective: Accelerating the Adoption of Innovative Solutions Presented By: Kevin Bossy The Supplier Perspective: Accelerating the Adoption of Innovative Solutions September 16, 2015 Bishop Water specializes in sludge and slurry management for municipalities and

More information

INNOVATIVE TECHNOLOGY TO IMPLEMENT A REUSE WATER PROGRAM. Stefan Haecker*, John Healy** 9311 College Parkway, Suite 1 Fort Myers Florida 33919

INNOVATIVE TECHNOLOGY TO IMPLEMENT A REUSE WATER PROGRAM. Stefan Haecker*, John Healy** 9311 College Parkway, Suite 1 Fort Myers Florida 33919 INNOVATIVE TECHNOLOGY TO IMPLEMENT A REUSE WATER PROGRAM Stefan Haecker*, John Healy** 9311 College Parkway, Suite 1 Fort Myers Florida 33919 ABSTRACT *CDM, **Piton Environmental, LLC The city of Fort

More information

City of Elk River Wastewater Treatment Facility Improvements. Achieving Wastewater Treatment Goals

City of Elk River Wastewater Treatment Facility Improvements. Achieving Wastewater Treatment Goals City of Elk River Wastewater Treatment Facility Improvements Achieving Wastewater Treatment Goals By Tejpal Bala, P.E. Bolton & Menk, Inc. The City of Elk River received a new NPDES permit and the existing

More information

Dundalk Wastewater Treatment Plant

Dundalk Wastewater Treatment Plant Township of Southgate Dundalk Wastewater Treatment Plant 2017 Annual Report Staff Report PW2018-010 - Dundalk Wastewater Treatment Plant 2017 Annual Report Moved by Councillor Pallister, Seconded by Councillor

More information

CLEARAS WATER RECOVERY S ABNR SOLUTION PROVIDES WASTE- WATER FACILITIES WITH COST RECOVERY OPPORTUNITY WHEN ADDRESSING NUTRIENT DISCHARGE REQUIREMENTS

CLEARAS WATER RECOVERY S ABNR SOLUTION PROVIDES WASTE- WATER FACILITIES WITH COST RECOVERY OPPORTUNITY WHEN ADDRESSING NUTRIENT DISCHARGE REQUIREMENTS Wastewatcher Article May 29, 2018 CLEARAS WATER RECOVERY S ABNR SOLUTION PROVIDES WASTE- WATER FACILITIES WITH COST RECOVERY OPPORTUNITY WHEN ADDRESSING NUTRIENT DISCHARGE REQUIREMENTS Tightening nutrient

More information

AMPC Wastewater Management Fact Sheet Series Page 1

AMPC Wastewater Management Fact Sheet Series Page 1 Nitrogen removal Nitrogen present in meat processing wastewater are termed a nutrient, since they are essential elements for life. They largely derive from proteins dissolved into wastewater from meat

More information

AMPC Wastewater Management Fact Sheet Series Page 1

AMPC Wastewater Management Fact Sheet Series Page 1 Nitrogen removal Nitrogen present in meat processing wastewater are termed a nutrient, since they are essential elements for life. They largely derive from proteins dissolved into wastewater from meat

More information

Rabea-Luisa, Schubert Kompetenzzentrum Wasser Berlin 16/05/2018, POWERSTEP Conference, Munich

Rabea-Luisa, Schubert Kompetenzzentrum Wasser Berlin 16/05/2018, POWERSTEP Conference, Munich YOUR FLUSH, OUR ENERGY FULL SCALE DEMONSTRATION OF ENERGY POSITIVE SEWAGE TREATMENT PLANT CONCEPTS TOWARDS MARKET PENETRATION Rabea-Luisa, Schubert Kompetenzzentrum Wasser Berlin 16/05/2018, POWERSTEP

More information

2014 Watershed Overview of Wastewater Treatment Plant Performance

2014 Watershed Overview of Wastewater Treatment Plant Performance 2014 Watershed Overview of Wastewater Treatment Plant Performance Photo: Dundalk Lagoon Date: February 2016 Report prepared by: Kelly Hagan and Mark Anderson Grand River Conservation Authority 400 Clyde

More information

Case Study: City of Brantford. Controlling Industrial Discharges to Improve Plant Performance

Case Study: City of Brantford. Controlling Industrial Discharges to Improve Plant Performance Case Study: City of Brantford Controlling Industrial Discharges to Improve Plant Performance Tim Howarth City of Brantford, Gerry Wheeler Global Facilitation Inc., Dave Chapman CPO Inc. Introduction: In

More information

Wastewater Treatment Works... The Basics

Wastewater Treatment Works... The Basics United States EPA 833-F-98-002 Environmental Protection May 1998 Agency Office of Water (4204) Wastewater Treatment Works... The Basics O ne of the most common forms of pollution control in the United

More information

Sechelt began their LWMP process in 1997, one year before Powell River, and completed it in 2011.

Sechelt began their LWMP process in 1997, one year before Powell River, and completed it in 2011. SECHELT WATER RESOURCE CENTRE March 19, 2015 Councillor Karen Skadsheim I visited the plant with Sechelt Councillors, Alice Lutes and Darren Inkster. The tour was led by Project Co-ordinator Paul Nash

More information

/ Marley MARPAK Modular Biomedia /

/ Marley MARPAK Modular Biomedia / / Marley MARPAK Modular Biomedia / The Marley MARPAK Difference SPX Cooling Technologies is a world leader in the design, manufacturing and construction of cooling products. The design and production of

More information

COLD WEATHER NITRIFICATION OF LAGOON EFFLUENT USING A MOVING BED BIOFILM REACTOR (MBBR) TREATMENT PROCESS

COLD WEATHER NITRIFICATION OF LAGOON EFFLUENT USING A MOVING BED BIOFILM REACTOR (MBBR) TREATMENT PROCESS ABSTRACT COLD WEATHER NITRIFICATION OF LAGOON EFFLUENT USING A MOVING BED BIOFILM REACTOR (MBBR) TREATMENT PROCESS Mr. Flemming G. Wessman 1 and Mr. Chandler H. Johnson 1 AnoxKaldnes, Inc., 58 Weybosset

More information

PORT SEVERN WASTEWATER TREATMENT 2016 SUMMARY REPORT

PORT SEVERN WASTEWATER TREATMENT 2016 SUMMARY REPORT PORT SEVERN WASTEWATER TREATMENT 2016 SUMMARY REPORT ENVIRONMENTAL COMPLIANCE APPROVAL: #3-0429-96-006 INTRODUCTION The Lone Pine Road Water Pollution Control Plant in Port Severn was a design / build

More information

AquaPASS. Aqua MixAir System. Phase Separator. System Features and Advantages. Anaerobic. Staged Aeration. Pre-Anoxic.

AquaPASS. Aqua MixAir System. Phase Separator. System Features and Advantages. Anaerobic. Staged Aeration. Pre-Anoxic. PHASED ACTIVATED SLUDGE SYSTEM PHASED ACTIVATED SLUDGE SYSTEM Aqua-Aerobic Systems has led the industry in time-managed, biological technology since 1984. In 2004, Aqua-Aerobic applied its expertise in

More information

Optimization of BNR from Wastewater Using SBR and A 2 O Processes. Guo, Lei (Eric)

Optimization of BNR from Wastewater Using SBR and A 2 O Processes. Guo, Lei (Eric) Optimization of BNR from Wastewater Using SBR and A 2 O Processes by Guo, Lei (Eric) A thesis submitted for partial fulfillment of the requirements for the degree of Master of Science in Civil Engineering

More information

Introduction. Background. Case Study: The Role of Optimization in Plant Re-rating Prepared by D.T. Chapman, CPO Inc.

Introduction. Background. Case Study: The Role of Optimization in Plant Re-rating Prepared by D.T. Chapman, CPO Inc. Prepared by D.T. Chapman, CPO Inc. Introduction The Grand River Conservation Authority (GRCA) initiated a program in 2010 to optimize wastewater treatment plants (WWTPs) in the watershed to improve water

More information

Additional Information Requirements for Wastewater Treatment Projects

Additional Information Requirements for Wastewater Treatment Projects Version 04-11-25 Page 1 of 6 Additional Information Requirements for Wastewater Treatment Projects Pursuant to Section 5(2) of the Environmental Impact Assessment Regulation of the Clean Environment Act,

More information

Novel Memthane Anaerobic MBR realizing sustainable ambitions. Frankfurt; June 19, 2012; 11:30 Jan Pereboom and Jeroen van der Lubbe

Novel Memthane Anaerobic MBR realizing sustainable ambitions. Frankfurt; June 19, 2012; 11:30 Jan Pereboom and Jeroen van der Lubbe Novel Memthane Anaerobic MBR realizing sustainable ambitions Frankfurt; June 19, 2012; 11:30 Jan Pereboom and Jeroen van der Lubbe Contents 1. Introduction 2. Drivers for AnMBR 3. Novel Memthane technology

More information

Progress Report for the Drinking Water Management Plan

Progress Report for the Drinking Water Management Plan drinking water Progress Report for the Drinking Water Management Plan quality on tap for the GVWD and Member Municipalities June 2010 Progress Report for the Drinking Water Management Plan for the GVWD

More information

A STRUVITE CONTROL AND PHOSPHORUS REMOVAL PROCESS FOR CENTRATE: FULL-SCALE TESTING. 850 Pembina Highway Winnipeg, MB

A STRUVITE CONTROL AND PHOSPHORUS REMOVAL PROCESS FOR CENTRATE: FULL-SCALE TESTING. 850 Pembina Highway Winnipeg, MB A STRUVITE CONTROL AND PHOSPHORUS REMOVAL PROCESS FOR CENTRATE: FULL-SCALE TESTING Simon Baker 1, Yoomin Lee 1, Wang Li 1 1 Earth Tech Canada Inc 850 Pembina Highway Winnipeg, MB ABSTRACT The North End

More information

Case Study. Biological Help for the Human Race. Bathurst Municipal Wastewater Treatment Works, New South Wales, Australia.

Case Study. Biological Help for the Human Race. Bathurst Municipal Wastewater Treatment Works, New South Wales, Australia. Case Study BiOWiSH Aqua Bathurst Municipal Wastewater Treatment Works, New South Wales, Australia BiOWiSH Aqua Executive Summary The main objective of the study was to quantify the cost savings of using

More information

Wastewater Treatment. Where does wastewater go when it leaves your house?

Wastewater Treatment. Where does wastewater go when it leaves your house? Wastewater Treatment Where does wastewater go when it leaves your house? Let s s take a look The process includes: Collection of wastewater Primary Treatment Secondary Treatment Solids Handling Influent

More information

Eco-efficient Solids Separation Using Salsnes Filter Technology. Jonathan Leech Trojan Technologies Nov 2013

Eco-efficient Solids Separation Using Salsnes Filter Technology. Jonathan Leech Trojan Technologies Nov 2013 Eco-efficient Solids Separation Using Salsnes Filter Technology Jonathan Leech Trojan Technologies Nov 2013 Outline Process Description Technology Overview Primary Filtration Applications Full-scale application:

More information

The following biological nutrient removal processes were evaluated in detail in the 2016 Liquid Processing Facilities Plan:

The following biological nutrient removal processes were evaluated in detail in the 2016 Liquid Processing Facilities Plan: Nitrite Shunt Pilot Project Purpose: The purpose of this project is to full scale pilot test the nitrite shunt biological nutrient removal process to confirm process design criteria, impacts to sludge

More information

Our Water is Worth It!

Our Water is Worth It! SUSTAINABLE MUNICIPAL WATER MANAGEMENT Our Water is Worth It! If this information is required in an accessible format, please contact 1-800-372-1102 ext.2029. 1 CONTENTS Page Section 2. Introduction 3.

More information

Case Study. BiOWiSH Aqua. Biological Help for the Human Race. Municipal Wastewater Bathurst Waste Water Treatment Works Australia.

Case Study. BiOWiSH Aqua. Biological Help for the Human Race. Municipal Wastewater Bathurst Waste Water Treatment Works Australia. Case Study BiOWiSH Aqua Municipal Wastewater Bathurst Waste Water Treatment Works Australia BiOWiSH Aqua Executive Summary The main objective of the validation was to quantify cost savings in using BiOWiSH.

More information

EFFICACY OF A HYBRID SUBSURFACE FLOW CONSTRUCTED WETLAND FOR THE TREATMENT OF AQUACULTURE WASTEWATER

EFFICACY OF A HYBRID SUBSURFACE FLOW CONSTRUCTED WETLAND FOR THE TREATMENT OF AQUACULTURE WASTEWATER EFFICACY OF A HYBRID SUBSURFACE FLOW CONSTRUCTED WETLAND FOR THE TREATMENT OF AQUACULTURE WASTEWATER A. Snow, B.C. Anderson, B. Wootton and A. Hellebust 44 th Central Canadian Symposium on Water Quality

More information

PHYSICAL INTEGRITY: IMPACT OF URBAN AREAS ON GREAT LAKES WATER QUALITY

PHYSICAL INTEGRITY: IMPACT OF URBAN AREAS ON GREAT LAKES WATER QUALITY Chapter One PHYSICAL INTEGRITY: IMPACT OF URBAN AREAS ON GREAT LAKES WATER QUALITY Introduction The need to plan and manage urban growth and mitigate its impact on the natural environment, particularly

More information

WASTEWATER TREATMENT. Nelson Environmental Inc. Nelson Environmental Inc.

WASTEWATER TREATMENT. Nelson Environmental Inc. Nelson Environmental Inc. The OPTAER system provides reliable nutrient removal in pond based wastewater treatment plants combining cost-effective technologies and low maintenance requirements. WASTEWATER TREATMENT PrintStudioOne.com

More information

Wastewater Management in Metro Vancouver. Margaret Morales 14 March 2011 PLAN 597

Wastewater Management in Metro Vancouver. Margaret Morales 14 March 2011 PLAN 597 Wastewater Management in Metro Vancouver Margaret Morales 14 March 2011 PLAN 597 Outline Metro Vancouver an overview Wastewater Management in Metro Vancouver ILWMP What makes it Integrated? Governance

More information

WASTEWATER TREATMENT PLANT MASTER PLAN 6. BUSINESS CASE EVALUATION OF ALTERNATIVES

WASTEWATER TREATMENT PLANT MASTER PLAN 6. BUSINESS CASE EVALUATION OF ALTERNATIVES WASTEWATER TREATMENT PLANT MASTER PLAN 6. BUSINESS CASE EVALUATION OF ALTERNATIVES A range of potential ammonia limits were identified for alternatives evaluation, as discussed in Section 2.2.5. This chapter

More information

Regional District LGDE Help Manual

Regional District LGDE Help Manual [Type text] Regional District LGDE Help Manual Issued by: Local Government Infrastructure and Finance Branch December, 2016 Table of Contents 7. STATISTICS SCHEDULES... 49 7(A) SCHEDULE C1 GENERAL STATISTICS

More information

USING HYDROXYL RADICALS TO MITIGATE HYDROGEN SULPHIDE AN ODOUR CONTROL STRATEGY AT THE COURTICE WPCP

USING HYDROXYL RADICALS TO MITIGATE HYDROGEN SULPHIDE AN ODOUR CONTROL STRATEGY AT THE COURTICE WPCP USING HYDROXYL RADICALS TO MITIGATE HYDROGEN SULPHIDE AN ODOUR CONTROL STRATEGY AT THE COURTICE WPCP Ray Davis*, Andy Seeley, Regional Municipality of Durham *Regional Municipality of Durham, 100 Osborne

More information

BRACEBRIDGE WASTEWATER TREATMENT 2016 SUMMARY REPORT

BRACEBRIDGE WASTEWATER TREATMENT 2016 SUMMARY REPORT BRACEBRIDGE WASTEWATER TREATMENT 2016 SUMMARY REPORT ENVIRONMENTAL COMPLIANCE APPROVAL: 6801-7VKNAQ ENVIRONMENTAL COMPLIANCE APPROVAL: 6222-AFGSNY (Dec 16 2016) INTRODUCTION The Lagoon Lane Wastewater

More information

Sequence Batch Reactor A New Technology in Waste Water Treatment

Sequence Batch Reactor A New Technology in Waste Water Treatment Sequence Batch Reactor A New Technology in Waste Water Treatment Ashutosh Pipraiya 1, Diwan Singh 2, SK Patidar 3 1 M.Tech, Department of Civil Engineering, National Institute of Technology Kurukshetra

More information

CHEMICALLY ENHANCED PRIMARY TREATMENT AN ALTERNATE PARADIGM FOR BASIN-WIDE RIVER WATER QUALITY IMPROVEMENT

CHEMICALLY ENHANCED PRIMARY TREATMENT AN ALTERNATE PARADIGM FOR BASIN-WIDE RIVER WATER QUALITY IMPROVEMENT CHEMICALLY ENHANCED PRIMARY TREATMENT AN ALTERNATE PARADIGM FOR BASIN-WIDE RIVER WATER QUALITY IMPROVEMENT Asit Nema 1 and Dr. Vinod Tare 2 ABSTRACT In view of limited resources available for water pollution

More information

Application of the AGF (Anoxic Gas Flotation) Process

Application of the AGF (Anoxic Gas Flotation) Process Application of the AGF (Anoxic Gas Flotation) Process Dennis A. Burke Environmental Energy Company, 6007 Hill Road NE, Olympia, WA 98516 USA (E-mail: dennis@makingenergy.com http//www.makingenergy.com)

More information

Anderson Water Pollution Control Plant

Anderson Water Pollution Control Plant City of Anderson Wastewater Division Public Works Director Jeff Kiser Chief Plant Operator Plant Supervisor Operator III Operator I Phil DeBlasio Mike Hansen Tony Hinchliff Vacant Collections Supervisor

More information

Appendix 2 Screening of Keewatinoow Construction Camp Waste Water Effluent Discharge to Creek Fourteen

Appendix 2 Screening of Keewatinoow Construction Camp Waste Water Effluent Discharge to Creek Fourteen Appendix 2 Screening of Keewatinoow Construction Camp Waste Water Effluent Discharge to Creek Fourteen Prepared by: North/South Consultants Inc. July 19, 2011 Introduction The following provides a screening

More information

PHOSPHORUS RECOVERY FROM SEWAGE SLUDGE USING THE AQUACRITOX SUPERCRITICAL WATER OXIDATION PROCESS

PHOSPHORUS RECOVERY FROM SEWAGE SLUDGE USING THE AQUACRITOX SUPERCRITICAL WATER OXIDATION PROCESS 14 th European Biosolids and Organic Resources Conference and Exhibition 1 PHOSPHORUS RECOVERY FROM SEWAGE SLUDGE USING THE AQUACRITOX SUPERCRITICAL WATER OXIDATION PROCESS O Callaghan,P. 1 and O Regan,

More information

Appendix D JWPCP Background and NDN

Appendix D JWPCP Background and NDN Appendix D JWPCP Background and NDN JWPCP Background JWPCP Water Quality Primary Clarifiers HPO Reactors Final Clarifiers Unit Influent Primary Effluent Secondary Effluent BOD mg/l 460 240

More information