1 ELENA-Modena project for technical assistance to enhance energy saving in the Public Sector *** The Modena Energy Agency s experience and results
2 1) Short introductory presentation ELENA- Modena project ELENA-Modena The ELENA-Modena project provided 1.4 m for technical assistance to Municipalities with an European Investment Bank contribution; this should have led to a total amount of 54 m in energy investments on municipal property with a minimum leverage factor of 25. The project ended on August 2015 with a total amount of 27 m in energy investments, 0.9 m spent for technical assistance and a leverage factor of 33,28%. 2
3 1) Short introductory presentation ELENA- Modena project ELENA-Modena Concerning the original total amount of the investment costs (54 M ), this evaluation was developed in 2009 / 2010, especially for the PV investments, in a different situation of the market (the PV prices are decreased about 75% from the evaluation to the real application). Investments reduction (suspended/deleted) after the 2012 earthquake. 3
4 1) Short introductory presentation ELENA- Modena project ELENA-Modena As shown in the next slides, the project has supported several investments, renewable energy, public lightning and in energy saving for buildings; several performance contracts for buildings were developed by AESS before Elena s start. Energy performance contract (EPC) duration ranges from 7 to 20 years; AESS started its work on EPCs 13 years ago; now, as well, it s was very interesting for us to perform in some cases, these kinds of project for the second time! 4
5 1) Short introductory presentation ELENA- Modena project The Italian context Italian Local Administrations are generally in a condition of financial stress, due to the limitations imposed by the so-called Stability Pact. Similarly, the capacity of investment is limited by the formula: (net current cost balance) (cash flow of the year for investments) 0 As a consequence there is no option for investing internal cash (all available cash flow is used for emergency investments ), nor with loans (there is no anyway room for payment of works in the year), even if the Municipality has money from the yearly profit and loss balance. The only solution is EPC. The internal personnel is not skilled in EPC. 5
6 1) Short introductory presentation ELENA- Modena project ELENA- Modena approach The Municipalities need technical assistance to draft an EPC and usually lack money to purchase it at market costs. The Province acts as collector of requests of investments from the Municipalities signatories of the Covenant of Mayors. The provincial Energy Agency AESS undersigned the ELENA agreement with EIB and created a Supporting Unit for the supply of technical assistance. Procurement procedures are EPC, leasing, a few direct investments, some mixed solutions. The procuring agents are the single Municipalities or clusters of them. 6
7 1) Short introductory presentation ELENA- Modena project Procedure for assigning tasks to technical and legal consultants ent/article/88-bandi/327- avviso-pubblico-per-laselezione-di-tecnici-inmateria-di-efficienzaenergetica.html AESS proceeded to select a list of qualified technical and legal consultants call was published on website. On the base of the received CV, technical and legal consultants showing an adequate experience in the specific fields were selected and inserted in a public short list, published available on the website. [A3 Interim Report] 7
8 1) Short introductory presentation ELENA- Modena project Replication of project in Italy Now we focus on the peculiar characteristics of ELENA Modena project: We decided from the start to keep free the ESCo's choice to use EIB financial help (using other banks with the help of public revolving funds, regionals and national); We customized the first three EPC tender schemes adapting them to the specific contest of the market and local conditions (preparing many call for tenders and not only two or three big). We didn't use the whole EIB financing at the start of the project, but before every project decreasing the risk in case of desert call. 8
9 1) Short introductory presentation ELENA- Modena project Replication of project in Italy We researched the critical size of the projects (not too small but not too big) in order to enlarge the ESCo's participation, fractionate the risks in case of desert call and decreasing the risks of legal appeals after the signing of the contract. This approach is very expensive and it was possible only thanks to the whole AESS staff that worked supporting with his experience the project managers. In the ELENA's project these "external" costs are not eligible, but for us has determined the success of our project, despite the difficulties due to the economic crisis and due to force majeure problems. 9
10 1) Short introductory presentation ELENA- Modena project Way forward The Elena's Project represent for AESS and the Modena Province a great opportunity to give "the legs" to the Covenant of Mayors realizing concretely the items of Sustainable Energy Action Plans. We will try to continue using the ELENA's model in two different ways: Direct insertion in the call for tenders of the preparing costs, paid by the ESCo after the signing of the contract (in that case all the risks are allocated to the advisor); we are applying this model outside the Modena Province in EPC contracts and for renewable energy plants. Financing of the preparing costs of the call for tenders by banks, covered by an insurance (at the moment we are talking with many stakeholders in order to built a pilot case with the help of public revolving funds). 10
11 2) Project progress and its implementation General overview Some Statistics PARTICIPATION: Local GOVs in Modena province: 47 Local GOVs in Modena joining ELENA facility: 24 ELENA breakdown for sectors: 11
12 2) Project progress and its implementation General overview Some Statistics PARTICIPATION: Investments suspended/deleted after the 2012 earthquake: In additional to earthquake some Municipalities in North Modena were affected by flooding in January 19,
13 2) Project progress and its implementation Tenders & investment already implemented Summary of some benchmarks included in the ELENA contract Investment programme for sector ( ): original WP achieved results BUILDINGS ,27 PV ROOFS ,01 STREET LIGHTING , ,77 (51% of the target) Investment programme for typology ( ): original WP achieved results Energy efficiency ,09 RES in buildings , ,77 Energy saved or RES generated (MWh): original WP achieved results BUILDINGS ,05 PV ROOFS ,23 STREET LIGHTING , ,32 (74% of the target) Avoided CO 2 (ton): original WP achieved results BUILDINGS ,03 PV ROOFS ,12 STREET LIGHTING , ,60 (84% of the target) 13
14 2) Project progress and its implementation General overview Some Statistics Implementation plan IP identification Name of IP Sep.2011 Oct-2011 Nov.2011 Dec.2011 Jan.2012 Feb.2012 Mar.2012 Apr.2012 May 2012 June 2012 July 2012 Aug.2012 Sept.2012 Oct.2012 Nov.2012 Dec.2012 Jan.2013 Feb.2013 Mar.2013 Apr.2013 May 2013 June 2013 July 2013 Aug.2013 Sept.2013 Oct.2013 Nov.2013 Dec.2013 Jan.2014 Feb.2014 Mar.2014 Apr.2014 May 2014 June 2014 July 2014 Aug.2014 Sept.2014 Oct.2014 Nov.2014 Dec.2014 Jan.2015 Feb.2015 Mar.2015 Apr.2015 Majy2015 June 2015 B.01 Castelfranco Emilia B.05.1 Polinago B.04.1 ACER: Albareto B.06 Lama Mocogno B.04.4 ACER: Baggiovara B.02 Soliera B.07 Province of Modena B.10 Carpi B.24 Campogalliano B.03 Castelnuovo Rangone B.04.2 ACER: San Damaso B.04.3 ACER: Modena B.14 Fiumalbo B.18 Modena B.22 Riolunato PV.08 Fanano PV.02 Fiumalbo PV.05 Soliera PV.11 Modena PV.18 Modena PV.09 Modena PV.14 Finale Emilia PV.16 Nonantola PV.17 Ravarino PV.01 Vignola PV.04 Medolla PV.12 Campogalliano PV.13 Castelnuovo Rangone PV.03 Castelfranco Emilia PV.06 Province of Modena PV.07 San Prospero PV.19 Riolunato SL.02 Vignola SL.01 Lama Mocogno SL.03 Riolunato SL.04 Fiumalbo B.05.1 Polinago SL.05 Pavullo n/f SL.07 Castelvetro di Modena SL.09 Sassuolo SL.10 Castelnuovo Rangone SL.06 San Possidonio_Area Nord SL.17 Mirandola_Area Nord SL.18 Concordia_Area Nord SL.20 Carpi SL.13 Fanano EARTHQUAKE EARTHQUAKE EARTHQUAKE EARTHQUAKE EARTHQUAKE
15 2) Project progress and its implementation Tenders & investment already implemented Summary of some benchmarks included in the ELENA contract Estimated annual final energy saved for EE projects, production by RES & EE+RES [MWh] 15
16 2) Project progress and its implementation General overview Energy Saving approach in calls for tenders 1. Compliance with national laws 2. Technology compliance 3. Energy retrofitting 16
17 2) Project progress and its implementation General overview Technological measures (on buildings and systems) Reduction of the solar radiation on windows through shielding or solar films; Replacement of heating and Domestic Hot Water (DHW) systems with high energy efficiency systems/condensing boilers; Installation of thermostatic radiator valves; Remote sensed control and adjustment of the heating system; Improvement of energy efficiency on existing appliances (heat recovery, etc.); Street lighting renewal/upgrade; Building automation systems (time, light, occupancy devices) in common spaces; Installation of PV, solar-thermal, geothermal, biomass systems, hydropower systems, etc. 17
18 2) Project progress and its implementation General overview Main goals Identify one only organization in charge of management, maintenance and/or energy supply for systems; Keep systems working; Comply with obligations in planned maintenance activities; Energy saving through energy efficiency measures; Reduce the sources of light pollution; Bring up to code and compliant with regulations (safety and efficiency). 18
19 2) Project progress and its implementation Tenders & investment already implemented TOTAL BUILDINGS: (about) BUILDINGS original WP 180 = 50 MWt, of which: - 2,5 MWt from biomass boiler; - 1,9 MWt from geothermal heat pump system; mq from Solar Thermal system; - external insulation. achieved results 361 MWt with: buildings with renovation heating system; kw from biomass boiler; mq of Solar Thermal; mq from external insulation; - 94 kw from micro hydropower station; 19
20 2) Project progress and its implementation Tenders & investment already implemented PV ROOFS TOTAL SOLAR PV ROOFS: (about) original WP 170 with an average power of 33 kwp (tot. 5.5 MWp) achieved results 5.0 MWp 20
21 2) Project progress and its implementation Tenders & investment already implemented STREET LIGHTING TOTAL LIGHT SPOTS: (about) original WP achieved results
22 Ing. Piergabriele Andreoli Tel.: Bruxelles, 13/10/
Energy efficiency for hospitals: EPC and revolving fund Piergabriele Andreoli MARTE Project Partner AESS_Modena
Energy efficiency for hospitals: EPC and revolving fund Piergabriele Andreoli MARTE Project Partner AESS_Modena Workshop: Regional/Local Energy Agencies & Energy Departments of Regional Authorities: their
More informationTASK 3.1. Project Infinite Solutions. INnovative FINancIng for Local SusTainable Energy Solutions. Local Study and Action Plan.
Project Infinite Solutions INnovative FINancIng for Local SusTainable Energy Solutions Grant agreement no.: IEE/13/392.SI2.675530 TASK 3.1 Local Study and Action Plan Date: June 2015 COMUNE DI UDINE MUNICIPALITY
More informationAnnex I : Description of the Project Development Services and the planned Investment Programme
: Description of the Project Development Services and the planned Investment Programme Location of the Project Development Services Province of Bergamo, Italy. 1. Location Main purposes of the Project
More informationSOLCER HOUSE ENERGY POSITIVE - LOW CARBON - LOW COST
SOLCER HOUSE ENERGY POSITIVE - LOW CARBON - LOW COST BACKGROUND The Welsh School of Architecture has designed and built Wales first low cost energy positive house. The Solcer House is capable of exporting
More informationResults of California s Renewable Energy Program and Agricultural Biomass to Energy Program (SB704)
2 nd Annual California Biomass Collaborative Forum Results of California s Renewable Energy Program and Agricultural Biomass to Energy Program (SB704) Tony Gonçalves Program Lead Existing Renewable Facilities
More informationStrategies for energy efficiency improvement in residential and office buildings: their role at building and country scale
The Future Role of Energy Storage in South Eastern Europe Enlargement and Integration Action Workshop Strategies for energy efficiency improvement in residential and office buildings: their role at building
More informationInnovative Solar thermal systems for heating and cooling
Innovative Solar thermal systems for heating and cooling Warsaw 18 th June 2009 Panagiotis Tsekouras PhD Candidate Mechanical Engineer CRES - Solar Thermal Dept. Overview The HIGH COMBI project SC+ Symbolism
More informationCERNUSCO SUL NAVIGLIO Province of Milan
CERNUSCO SUL NAVIGLIO Province of Milan Population: 32.500 inhabitants Total Area: 13,33 sq km Urbanized Area: 7,60 sq km PAES Joined in Mayors Convenant : May 20th, 2009 SEAP approved: november 23th,
More informationIntroduction of Regional Energy Concepts (CEP-REC)
Introduction of Regional Energy Concepts (CEP-REC) Award cometition and selected projects in the regional energy concept of the Province of Torino Silvio de Nigris, Province of Turin the CENTRAL EUROPE
More informationCombined Heat and Power & District Heating Networks. For the East Midlands
Combined Heat and Power & District Heating Networks For the East Midlands Introduction to Combined Heat and Power The Basics Systems produce heat & electricity Production of electricity at the point of
More informationProspects of Solar Thermal and Heat Storage in DHC
Prospects of Solar Thermal and Heat Storage in DHC Presentation in Brussels, 02.06.2010, Euroheat and Power + COGEN Europe Dipl.-Ing. Dirk Mangold Steinbeis Research Institute for Solar and Sustainable
More informationProcuring and Financing Energy Efficiency. September 20, 2011
Procuring and Financing Energy Efficiency September 20, 2011 Oro Valley, Arizona Located just a few miles north of Tucson, Arizona Incorporated in 1974 with 1,500 residents Over 41,000 residents today
More information2013 Best Practice Selection
2013 Best Practice Selection Covenant Signatories Buildings, equipments, facilities Sustainable Järva Refurbishment Project STOCKHOLM (SE) - Optimisation of heating and ventilation systems, - Conversion
More informationScottish Court Service. Carbon Trust Standard Case Study
Scottish Court Service Carbon Trust Standard Case Study Scottish Court Service Key Facts and Figures 49 Sheriff Courts 4 High Courts Asset Book Value 375M 81% Estate is Listed Annual Estate Budget 26M
More informationMicrogeneration Installation Standard : MCS 024 SOLAR DOMESTIC HOT WATER ENERGY CALCULATION. to be used in conjunction with MIS 3001:
Microgeneration Installation Standard : MCS 024 SOLAR DOMESTIC HOT WATER ENERGY CALCULATION to be used in conjunction with MIS 3001: REQUIREMENTS FOR CONTRACTORS UNDERTAKING THE SUPPLY, DESIGN, INSTALLATION,
More informationZAGREB ENERGY EFFICIENT CITY. Refurbishment of public buildings and modernization of public lighting
Refurbishment of public buildings and modernization of public lighting Contract N : IEE/12/816.SI2.645701, Duration: 1 April 2013 30 March 2017 Energy Efficiency Finance Market Place 19 January 2017 WHY
More informationNext Generation District Heating
Next Generation District Heating FVB: Ulrika Ottosson, Heimo Zinko Lund University: Janusz Wollerstrand, Patrick Lauenburg, Marek Brand (DTU) a project The Swedish District Heating Association s R&D programme
More informationFeasibility Study. Solar plant with district heating net (Austria)
Feasibility Study Solar plant with district heating net (Austria) Elaborated by DI Horst Strießnig DI Philip Ohnewein Graz, October 2006 nahwaerme.at Energiecontracting GmbH & Co KG Herrgottwiesgasse 188
More informationVerified net Zero Energy Building with air source heat pumps for SME
Verified net Zero Energy Building with air source heat pumps for SME Field measurements were conducted on a net zero energy building designed for small to medium enterprises (SMEs). Energy flow and comfort
More informationUnderstanding the Energy Performance Contracting (EPC) model and process
Understanding the Energy Performance Contracting (EPC) model and process Professor Theocharis Tsoutsos Director, Renewable and Sustainable Energy Systems Lab School of Environmental Engineering Technical
More informationPeter Randall Solar Kingdom Ltd
Peter Randall Solar Kingdom Ltd How is Solar Doing? How is Solar Doing? Now an Established Industry How is Solar Doing? Now an Established Industry UK a Major Market Estimated Total installed capacity
More informationMicrogeneration Installation Standard : MCS 024 SOLAR DOMESTIC HOT WATER ENERGY CALCULATION. to be used in conjunction with MIS 3001:
Microgeneration Installation Standard : MCS 024 SOLAR DOMESTIC HOT WATER ENERGY CALCULATION to be used in conjunction with MIS 3001: REQUIREMENTS FOR CONTRACTORS UNDERTAKING THE SUPPLY, DESIGN, INSTALLATION,
More informationAngelica Salomon-Dealino & Dilip Limaye International Institute for Energy Conservation. Asian Development Bank, 19 June 2015
Angelica Salomon-Dealino & Dilip Limaye International Institute for Energy Conservation Asian Development Bank, 19 June 2015 Presentation Outline DSM Delivery Models, types and approaches Applicable Financing
More informationClean Energy Extension
Clean Energy Extension ag.umass.edu/energy The Clean Energy Extension is an Affiliate of the UMass Amherst Center for Agriculture, Food and the Environment 209 Agricultural Engineering Building University
More informationThe Intelligent Energy Europe Programme: Call for Proposals 2012
The Intelligent Energy Europe Programme: Call for Proposals 2012 Emilio FONT DE MORA Project Officer Executive Agency for Competitiveness and Innovation Renewable Energy Unit Sofia, 28 February 2012 The
More informationCOMPANY PROFILE 2016
COMPANY PROFILE 2016 takasolutions upgrades buildings to reduce the energy, water and costs at no expense to the owner while sharing the savings. TARGET CLIENTS THE CONCEPT Clients and buildings that are
More informationAchieving a cost optimal balance between heat supply efficiency and moderation of demand
Achieving a cost optimal balance between heat supply efficiency and moderation of demand Dr. Christian Friebe Thüga Aktiengesellschaft COGEN Europe, 25th of February 560 cities and towns, 100 companies
More informationZero Net Energy Buildings February 12, 2014 Beth Brummitt, CEM, CEA, LEED AP. Your guide for improving the performance and value of buildings
Zero Net Energy Buildings February 12, 2014 Beth Brummitt, CEM, CEA, LEED AP Your guide for improving the performance and value of buildings 1 Courtesy of Bill Reed, Integrative Design Collaborative, www.integrativedesign.net
More informationImp ementation Case:
ZEMedS: Implementation Implementation Case: IPSSART Varnelli, Cingoli, Italy General data 3 Name of the School Type of school IPSSART Cingoli High School High School Number of students Owner 724 public
More informationPublic Building Renovation through Energy Performance Contracting (EPC)
Public Building Renovation through Energy Performance Contracting (EPC) Rüdiger Lohse Brussels, March, 2017 Intention of this presentation What is Energy Performance Contracting? Demonstrate KEA s role
More informationDeep Energy Retrofit of a HighRise MURB
Deep Energy Retrofit of a HighRise MURB COLIN SHANE M.Eng., P.Eng. RDH BUILDING SCIENCES INC. SAN FRANCISCO, CA AIA Credits National Institute of Building Sciences Provider #G168 Credit(s) earned on completion
More informationImp ementation Case:
ZEMedS: Implementation Implementation Case: IPCT Bonifazi, Recanati, Italy General data 3 Name of the School Type of school IPCT Recanati High School High School Number of students Owner 277 public Location
More informationHeating & cooling (and geothermal) in the Intelligent Energy Europe & Energy Efficiency part of the Horizon 2020 programme of the EC
Heating & cooling (and geothermal) in the Intelligent Energy Europe & Energy Efficiency part of the Horizon 2020 programme of the EC Antonio Aguilo Project Advisor 5 October 2015, Brussels Intelligent
More informationTRUST EPC South benchmarking and assessment tools for energy efficiency investments
TRUST EPC South benchmarking and assessment tools for energy efficiency investments Professor Theocharis Tsoutsos Renewable and Sustainable Energy Systems Lab School of Environmental Engineering Technical
More informationNew Jersey s Clean Energy Program Report Submitted to the New Jersey Board of Public Utilities
New Jersey s Clean Energy Program Report Submitted to the New Jersey Board of Public Utilities Reporting Period: January 1, 2012 through June 30, 2013 Table of Contents I. Executive Summary 1 II. Introduction
More informationWhy Use A DES ESCO? Benefits of A DES ESCO?
Why Use A DES ESCO? High Energy Bills Old Equipment is Broken Bond Levy Passed Free Grant Money / Utility Incentive Money Going Green Reducing Carbon Footprint Desire to use specific equipment or contractor
More informationNearly zero energy building renovation, the EU-GUGLE project Javier Llorente Yoldi
Nearly zero energy building renovation, the EU-GUGLE project Javier Llorente Yoldi jllorente@cener.com In a nutshell European cities serving as Green Urban Gate towards Leadership in sustainable Energy
More informationEfficient utilization of energy sources
Efficient utilization of energy sources Perspectives for the reduction of fossil primary energy utilization in urban areas March 28 Using the energy content the most efficient way is using COMBINED HEAT
More informationSolar Photovoltaic (PV) GreenSmart Energy Performance Report
Solar Photovoltaic (PV) GreenSmart Energy Performance Report 2014-2016 A GreenSmart Energy Initiative TABLE OF CONTENTS INTRODUCTION... 1 TOTAL ELECTRICAL Production... 2 MONTHLY ELECTRICAL PRODUCTION...
More informationProposed Work Plan for Seventh Plan Development. October 2, 2014 GRAC Tom Eckman
Proposed Work Plan for Seventh Plan Development October 2, 2014 GRAC Tom Eckman Council s Analytical Process Flow Load Forecast Model Load Forecast Range (without efficiency) Regional Portfolio Model Data
More informationESCO EXPERIENCE IN JAMAICA
EU/GOJ DEVELOPING AN ENERGY SERVICES COMPANY (ESCO) INDUSTRY IN JAMAICA STAKEHOLDER CONSULTATION JULY 2ND 2013 ESCO EXPERIENCE IN JAMAICA EATON HAUGHTON, P.E. CARIBBEAN ESCO LTD. email: ehaughton@caribbeanescoltd.com
More informationEnergy Audit. Project: ENergy Efficiency and Renewables SUPporting Policies in Local level for EnergY (ENER-SUPPLY) Work Package 4
Project: ENergy Efficiency and Renewables SUPporting Policies in Local level for EnergY (ENER-SUPPLY) Work Package 4 Energy Audit Date: Country: SERBIA Partner: University of Novi Sad (UNS) Building: Health
More informationUnited Nations Economic and Social Commission for Asia and the Pacific (ESCAP) United Nations Economic Commission for Europe (UNECE)
United Nations Economic and Social Commission for Asia and the Pacific (ESCAP) United Nations Economic Commission for Europe (UNECE) Case study ALBANIA Ervin Shehaj Director of the Directory of Renewable
More informationEnergy Efficiency in Public Buildings through Energy Services The example of Germany
through Energy Services The example of Germany Michael Geissler CEO Berlin Energy Agency Odessa, 1 June 2016 Contents Berliner Energieagentur (BEA) Energy Efficiency in Public Buildings Energy Services
More informationNearly Zero Energy Building in Lecco Modern technological building compared to an ancient Villa
Nearly Zero Energy Building in Lecco Modern technological building compared to an ancient Villa Matteo BRASCA *, Oscar Luigi PAGANI **, Kanza RAUF*** * partner - AIACE S.r.l. società di ingegneria, contract
More informationFeed-in Tariff Structure Development for the Kingdom of Bahrain for PV Electricity
Feed-in Tariff Structure Development for the Kingdom of Bahrain for PV Electricity Shaker Haji *, Amal Durazi, and Yaser Al-Alawi * Dr. Shaker Haji, Associate Professor Department of Chemical Engineering,
More informationEnergy Performance Certificate
111, Greenham Road, NEWBURY, RG14 7JE Dwelling type: Semi-detached house Reference number: 0141-2891-7693-9593-5705 Date of assessment: 19 January 2017 Type of assessment: RdSAP, existing dwelling Date
More informationGOOD PRACTICE IN FINANCING THE RENOVATION OF PUBLIC AND RESIDENTAL BUILDINGS
GOOD PRACTICE IN FINANCING THE RENOVATION OF PUBLIC AND RESIDENTAL BUILDINGS CONTENT: Introduction of SEVEn 1. List of financial instruments 1. Own and banking resources 2. Subsidy schemes 3. Energy services
More informationFeasibility analyses relative to energy retrofitting of acute hospitals and community clinics
SOSTENIBILITA AMBIENTALE E PRODUZIONE EDILIZIA La ricerca scientifica sulla Produzione Edilizia nell era delle nuove sfide ambientali nel Settore delle Costruzioni Feasibility analyses relative to energy
More informationRES use in the Riga city
RES use in the Riga city Juris Golunovs, Head of Energy Efficiency Information Centre of Riga Energy Agency Empowered consumer in the energy market CONFERENCE, Riga, 21.05.2015 OBJECTIVES In order to
More informationFuture European Heat. Renewable heating comparisons
Document number Future European Heat Renewable heating comparisons Tuesday, 28 May 2013 By: Melahn Parker (Melahn.Parker@dnvkema.com) DNV KEMA Energy & Sustainability DNV KEMA serves the entire energy
More informationHeadline Sponsor. The Rocky Road to Carbon Reduction Lancaster s Carbon Management Plan
Headline Sponsor The Rocky Road to Carbon Reduction Lancaster s Carbon Management Plan Introductions Jonathan Mills Carbon, Environment & Sustainability manager Jan Bastiaans Energy Manager Session Agenda
More informationCity of Toronto Tower Renewal Program
Photo by Jesse Colin Jackson City of Toronto Tower Renewal Program CAC Presentation October 6, 2016 1 Tower Renewal A program to drive broad environmental, social, economic, and cultural change by improving
More informationWith the support of: RENOWATT. Renovate Europe October 13, 2016
With the support of: RENOWATT Renovate Europe October 13, 2016 Agenda Genesis of the project Creation of a One Stop Shop Activities of the one Stop Shop Financing the investments Tendering procedure Key
More informationSTUDY ON TESTING FEASIBILITY OF SOLAR ENERGY IN THE PALESTINIAN TERRITORIES
STUDY ON TESTING FEASIBILITY OF SOLAR ENERGY IN THE PALESTINIAN TERRITORIES FALLING WITHIN THE FRAMEWORK OF THE EXTRAORDINARY FINANCIAL ASSISTANCE OF THE CZECH REPUBLIC TO THE PALESTINIAN TERRITORIES FOLLOWING
More informationFit For The (Nearly Zero Carbon) Future? Martin Russell-Croucher MRICS CEnv
Fit For The (Nearly Zero Carbon) Future? Martin Russell-Croucher MRICS CEnv Future Focus Sustainability Energy Efficiency/ Security of Energy Supply Carbon Reduction Valuation Security of Supply Arab Spring
More information2016 ISO Flexible Capacity Needs Assessment: Study Methodology, Assumptions, and Preliminary Results
2016 ISO Flexible Capacity Needs Assessment: Study Methodology, Assumptions, and Preliminary Results Presented at the CPUC RA Workshop April 15, 2015 Clyde Loutan Senior Advisor Renewable Energy Integration
More informationEnergy Saving Public Swimming Complex In Finland
Energy Saving Public Swimming Complex In Finland Suvi Karirinne 1,a, Petri Konttinen 2,b, and Jukka Kotiniemi 3 1 Faculty of Energy and Construction, Satakunta University of Applied Science, Tiedepuisto
More informationSolar Thermal Optimization for District Hot Water through Energy Modeling
Solar Thermal Optimization for District Hot Water through Energy Modeling Joshua Morejohn, Energy Manager Priscila Castillo Cazares, JEMES CiSu UC Davis is converting their district heating system from
More informationThe use of economic instruments to renovate Europe
IEA workshop The use of economic instruments to renovate Europe Bogdan ATANASIU Buildings Performance Institute Europe Bogdan.atanasiu@bpie.eu Summary: Economic instruments to renovate Europe - Main barriers
More informationPassive Strategies and Low-Carbon Technologies: Evaluating the Energy Performance and Thermal Comfort of a Passive House Design
Proceedings of the 2 nd ICAUD International Conference in Architecture and Urban Design Epoka University, Tirana, Albania, 8- May 14 Paper No. 128 Passive Strategies and Low-Carbon Technologies: Evaluating
More informationEnergy Audit of two Apartment Buildings in Cagliari using Energy Simulation
Energy Audit of two Apartment Buildings in Cagliari using Energy Simulation Graduation Thesis by Carla Vargiu and Luisa Zedda, Master in Green Building and Energy Efficiency This thesis focuses on the
More informationEnergy Audit. Project: ENergy Efficiency and Renewables SUPporting Policies in Local level for EnergY (ENER-SUPPLY) Work Package 4
Project: ENergy Efficiency and Renewables SUPporting Policies in Local level for EnergY (ENER-SUPPLY) Work Package 4 Energy Audit Date: Country: SERBIA Partner: University of Novi Sad (UNS) Building: Pre-school
More informationUpgrading the energy performance of residential buildings in Cyprus
Upgrading the energy performance of residential buildings in Cyprus Energy Services, Barriers & Opportunities Gazzada Schianno, Varese, Italy 18-19 October 2017 Savvas Vlachos / Director Member of Cyprus
More informationTasks of the planner
Players in the planning process of a solar system Architect Subsidy donor Consultation, supervision User Client Planner Information, orders Consultation, planning, supervision Installer Offer, installation,
More informationThe Future of Electricity: A Market with Costs of Zero? Marginal
The Future of Electricity: A Market with Costs of Zero? Marginal Richard Green, IAEE European Conference, 217 1 Supply /MWh Marginal Cost Nuclear CCGT OCGT GW 2 Demand and Supply Prices reflect Marginal
More informationD.3.5 Report on best practice implementation of bankable energy actions
D.3.5 Report on best practice implementation of bankable energy actions Best practice title 1 Building energy efficiency and refurbishment by Energy Performance Contracting in municipal buildings EPC coaching
More informationThe Sustainable Development Fund in 2011
Pennsylvania Sustainable Energy Board Annual Meeting December 7, 20111 The Sustainable Development Fund in 2011 Roger E. Clark The Reinvestment Fund The Reinvestment Fund (TRF) Private, nonprofit community
More informationNew developments in the Covenant of Mayors initiative
New developments in the Covenant of Mayors initiative Granada 12 April 2018 Evolution of the initiative Priority action in the EU Action Plan for Energy Efficiency Launch of the Covenant of Mayors Launch
More informationFuture tree planting on the two acre lot will offset remaining lifetime carbon emissions.
Luxury Net-Zero Home by Rockwood Custom Homes 47 Grandview Place, Calgary AB T3Z A8 by Grant Bremner A Net-Zero Emissions (NZE) home is carbon neutral where carbon credits fully offset emissions. An NZE
More informationProject Report: SunMaxx Commercial Case Studies
Project Report: 7 x ThermoPower-VHP30 Total Gross Surface Area: 369.25 sq.ft Azimuth: 10 Incl.: 37 1200 gal/day 120 F Gas Boiler - 9 150 kbtu/hr StorMaxx NP Vol:1500 gal Existing Hot Water Heater Vol:600
More informationState of play of energy efficiency financing in Italy
State of play of energy efficiency financing in Italy Alessandro Federici ENEA, Italy s National Agency for Energy Efficiency Financing Energy Efficiency in Italy and Malta Malta, 22 November 2018 Italy
More informationImp ementation Case:
ZEMedS: Implementation Implementation Case: ITIS Merloni, Fabriano, Italy General data 3 Name of the School Type of school ITIS MERLONI High School High School Number of students Owner 398 public Location
More informationImp ementation Case:
ZEMedS: Implementation Implementation Case: IIS Vanvitelli Angelini, Ancona, Italy General data IIS Vanvitelli Angelini High School, Municipality of Ancona (AN), Italy 3 Name of the School Type of school
More informationDept. of Industrial Engineering, University of Salerno, Italy,
SustAinabLe EneRgy NOw Salerno, Italy Vincenzo Marano Dept. of Industrial Engineering, University of Salerno, Italy, vmarano@unisa.it Gianfranco Rizzo Dept. of Industrial Engineering, University of Salerno,
More informationProject Report: SunMaxx Commercial Case Studies
Project Report: 5 x ThermoPower-VHP30 Total Gross Surface Area: 263.75 sq.ft Azimuth: 10 Incl.: 37 900 gal/day 120 F Gas Boiler - 9 100 kbtu/hr StorMaxx NP Vol:1200 gal Existing Hot Water Heater Vol:400
More informationRenewable Energy in Albania
Renewable Energy in Albania National Agency of Natural Resources Artan Leskoviku,Head of RES Workshop: Renewable Energy UNDA project conclusions and way forward 13-14 December 2017, Lancaster Plaza Hotel,
More informationProject Report: SunMaxx Commercial Case Studies
Project Report: 14 x ThermoPower-VHP30 Total Gross Surface Area: 738.50 sq.ft Azimuth: 10 Incl.: 37 2100 gal/day 130 F Gas Boiler - 9 150 kbtu/hr StorMaxx NP Vol:2500 gal Existing Hot Water Heater Vol:1000
More informationAllstream Centre Energy Performance Report
Allstream Centre Energy Performance Report 2012 2014 TABLE OF CONTENTS INTRODUCTION... 1 ELECTRICAL CONSUMPTION... 2 ELECTRICAL ENERGY DISTRIBUTION... 3 BUILDING POWER AND SYSTEMS... 4 FACTORS CONTRIBUTING
More informationRenewables. Vacuum Tube Solar Systems. Solar Energy to the Power of
Renewables Vacuum Tube Solar Systems Solar Energy to the Power of FREE HOT WATER FROM DAWN TO DUSK AND THROUGHOUT THE YEAR WITH Thermomax advanced vacuum tube solar systems provide hot water in all seasons.
More informationEnergy Performance Certificate
Energy Performance Certificate 29, Fieldhead Gardens BOURNE END SL8 5RN Dwelling type: Mid terrace house Date of assessment: 15 Oct 2010 Date of certificate: 15 Oct 2010 Reference number: 8770 6720 8309
More informationEmissions Trading in China Progress on the Path towards a Unified National System
Emissions Trading in China PRESENTED BY Chen Zhibin SinoCarbon Feb. 2016 Bottom - Up ETS in China 1 Led by NDRC (National Reform and Development commission) One registry system ETS Development in China
More informationSOLARPVSYSTEM INFORMATIONPACK FIT PROGRAM
SOLARPVSYSTEM INFORMATIONPACK FIT PROGRAM (Thailand, July 2013) The Thai government has recently introduced a generous subsidy scheme involving Feed in Tariffs. This means that you get paid a premium rate
More informationEIB support to Energy Efficiency
EIB support to Energy Efficiency Louise White Energy Efficiency Division Projects Directorate EUROPEAN INVESTMENT BANK Brussels, 26 Sept 2017 26/09/2017 1 Fossil Fuels 5% Gas Networks 14% Electricity networks
More informationAdministration Division Public Works Department Anchorage: Performance. Value. Results.
Administration Division Anchorage: Performance. Value. Results. Mission Provide administrative, budgetary, fiscal, and personnel support to ensure departmental compliance with Municipal policies and procedures,
More informationThe Future of Electricity: A Market with Costs of Zero? Marginal
The Future of Electricity: A Market with Costs of Zero? Marginal Imperial College Business School Richard Green, IAEE European Conference, 217 1 Running your mouse over the bubble in the top left corner
More informationNew developed solar thermal systems for heating and cooling Budapest, 16 th April 2009 Tsekouras Panagiotis Mech. Engineer NTUA Centre for Renewable
New developed solar thermal systems for heating and cooling Budapest, 16 th April 2009 Tsekouras Panagiotis Mech. Engineer NTUA Centre for Renewable Energy Sources Solar Thermal Dept. Overview Solar Thermal
More informationEnergy Savings Performance Contracting What is Performance Contracting? How Does It Work? How Are Savings Calculated?
Energy Savings Performance Contracting What is Performance Contracting? How Does It Work? How Are Savings Calculated? ABMA Annual Meeting January 15, 2011 About the Energy Services Coalition Public-private
More informationEnergy development in Riga
RIGA ENERGY DAYS 2012 Energy development in Riga Dr.sc.ing. Maija Rubina, director Riga Energy Agency Meeting with Kosovo delegation in Riga, 12.10.2012. 12.10.2012 1 Riga Energy Agency - REA REA non profit
More informationThe EU-GUGLE project 4/26/2016. Nearly zero energy building renovation, the EU-GUGLE project
Nearly zero energy building renovation, the EU-GUGLE project Florencio Manteca National Renewable Energy Centre of Spain - CENER Conference on Sustainable Renovation Models 22nd April 2016, Aachen, Germany
More informationA 92 plus B C D E F 21-38
Energy Performance Certificate Northern Ireland 21, Cypress Drive Date of assessment: 19 November 2010 COLERAINE Date of certificate: 09 January 2011 BT52 2AF Reference number: 9893-3716-6629-3190-3903
More informationINTEROFFICE MEMORANDUM
INTEROFFICE MEMORANDUM DATE: October 23, 29 TO: Boise Public Works Commission FROM: Matt Hightree, Civil Engineer SUBJECT: Energy Consumption at Major Facilities Managed by Public Works This memo is presented
More informationEnergy Performance Certificate
Energy Performance Certificate 16, Beaumont Street BISHOP AUCKLAND DL14 6BJ Dwelling type: Mid terrace house Date of assessment: 25 Mar 2011 Date of certificate: 16 Apr 2011 Reference number: 8308 8858
More informationUTILITIES REPORT PERIOD AUGUST 2007 TO JULY University of Aberdeen
UTILITIES REPORT PERIOD AUGUST 2007 TO JULY 2008 University of Aberdeen Contents 1 Executive Summary...3 2 Energy as Supplied Summary...3 3 Carbon Dioxide Emissions Actual for 2007/2008...4 4 Carbon Dioxide
More informationFindings through Nov. 2016
BUILDING ENERGY SAVING ORDINANCE (BESO) DECEMBER 7, 2016 Findings through Nov. 2016 BESO Basics Update to RECO/CECO requiring tailored energy assessment at time of sale or periodically, based on building
More informationThe Green Deal and Energy Company Obligation (ECO): Frequently Asked Questions
The Green Deal and Energy Company Obligation (ECO): Frequently Asked Questions This document should help answer key questions you may have about the Green Deal and the Energy Company Obligation. Some of
More informationWorkshop on the Polices and Schemes for Financing Energy Efficiency in Buildings Belgrade, June, 2013
Workshop on the Polices and Schemes for Financing Energy Efficiency in Buildings Belgrade, 18-19 June, 2013 CURRENT STATUS AND PERSPECTIVES OF ESCO MARKET IN UKRAINE: MODEL and mechanisms FOR FINANCING
More informationMexico Clean Technology Fund Investment Plan revision. CTF TFC Meeting, Washington DC May 2, 2013
Mexico Clean Technology Fund Investment Plan revision CTF TFC Meeting, Washington DC May 2, 2013 Content 1. The CTF in Mexico 2. Project Status 3. Revision of the Investment Plan for Mexico 4. Mexico Investment
More informationBuildings sector: Energy Productivity in the GCC. Kankana Dubey KAPSARC
Buildings sector: Energy Productivity in the GCC Kankana Dubey KAPSARC 7 th International Forum on energy for Sustainable Development in Baku, 18 October 2016 1980 1981 1982 1983 1984 1985 1986 1987 1988
More informationGeothermal Hot Water Supply of Saburtalo District in Tbilisi, Georgia
Geothermal Hot Water Supply of Saburtalo District in Tbilisi, Georgia 1. Project brief The project proposal Geothermal hot water supply of Saburtalo district in Tbilisi, Georgia has been developed in order