Analysis of Three Recent Blackouts

Size: px
Start display at page:

Download "Analysis of Three Recent Blackouts"

Transcription

1 Analysis of Three Recent Blackouts San Diego Gas & Electric -09/08/2011 Indian Northern Grid 07/30/2012 Indian Northern & Eastern Grids 07/31/2012 Bharat Bhargava Advanced Power System Technologies, Inc. 359 Amberwood Drive Walnut, CA Copyright 2016 Advanced Power System Technologies, Inc. All Rights Reserved 1

2 Presentation Outline / Objectives Objectives: Review the three recent blackouts San Diego / Baja California September 8, 2011 Indian Northern region July 30, 2012 Indian Northern/Eastern/Northeastern regions July 31, 2012 Outline basic causes and common factors in these blackouts What can we learn from them to improve system performance and avoid/prevent blackouts What new tools and technologies are available that can help operators to avoid blackouts in future 2

3 FACTS Power transfer economics and system reliability are competing goals. Systems are designed considering the worst loading condition scenarios and for loss of one element. Systems are well planned and designed as they withstand outage of one element Most disturbances occur, not for loss of one element, but multiple contingencies occurring over an extended time period Very often, the line loadings and margins are not adjusted when line outages occur outside one s control area resulting in lack of wide area situational awareness. Tools are needed to monitor Wide Area stresses and for keeping an eye and awareness of other systems as well 3

4 New Tools can Increase Transmission Capacity and Reliability New Tools are available and can help in Monitoring wide-area system stresses Establish wide area system stress limits Increasing loading if margin is there Reducing loading if the safe limits are exceeded Comparing stress level with bench marked cases and ensuring adequate margin for dynamic loading/stresses on the system Monitoring slowly growing oscillations and their damping One of the major cause of wide spread outages Monitoring voltage levels and support at all critical locations. Voltage support is critical for safe system operations Event reconstruction, validation and analysis of mitigation alternatives 4

5 San Diego Gas & Electric System Blackout on September 8,

6 San Diego - WECC Disturbance September 8, 2011 San Diego system was importing power on two major import paths Hassyampa N. Gila- Imperial Valley Miguel 500 kv South of SONGS Five 230 kv lines (Path 44) Power also flows thru the underlying 220/115/92 kv system from Devers bus to IID and Western Administration Lower Colorado SDG & E had established individual path ratings Hassyampa N. Gila 2200 MW Path 44 south of SONGS 1800 MW SDG & E monitors these thru the EMS / SCADA system The (N-1) criterion requires that other system components should not overload for loss of a line/component 6

7 San Diego - WECC Disturbance September 8, 2011 Sequence of Events - 1 Heavily loaded system and stressed system conditions with hot weather (115 degrees in IID) Safe operation and (N-1) criteria requires that loss of a path should not result in exceeding the normal rating of other paths. RTCA are generally employed to ensure that the system is operating with in safe operating region The Hassyampa N. Gila line tripped at 15:26 hrs while carrying 1394 MW load due to an operational error Loss of this line resulted in increased power flow on Path 44 from 1302 MW to 2386 MW which exceeded the path 44 rating of 2200 MW. This indicates that SDGE was operating beyond the safe operational limit 7

8 San Diego - WECC Disturbance September 8, 2011 Sequence of Events - 2 IID flows also increased from 90 MW to 240 MW and resulted in overloading the IID transformers which tripped and increased power flow on path 44 to 2600 MW Increased Loading on path 44 may have also resulted in low voltages in CFE area and tripping of generating units in CFE system Loss of these units increased the loading on path 44 above 3200 MW (15:32:385) Path 44 has relay settings at SCE end to isolate SDGE & CFE system if the current exceeds 8000 amps or 3186 MVA Power flows on Path 44 continued to stay above 3200 MW and resulted in relay separation at SONGS. Simulations of the disturbance showed that the angle difference across the breaker at N. Gila exceeded the sync-check relay setting and may have prevented the line re-closure 8

9 San Diego - WECC Disturbance September 8, Impacts Amount of Load lost 7835 MW Areas impacted San Diego 4293 MW (1.4 million customers) CFE 2150 MW (1.1 million customers ) IID 929 MW (146,000 customers) APS 389 MW (70,000 customers) WALC 74 MW ( 5 customers + APS customers) Southern California 450 MW Total customers Impacted 2.7 million Estimated cost $ 6 Billion Time to restore power hours 9

10 San Diego - WECC Disturbance - September 8, 2011 Review of the NERC/FERC report - 1 Actions that could have helped Conducting Real Time Contingency Analysis (RTCA) Monitoring angle difference across open breakers Wide Area system monitoring and Situational Awareness Monitoring / alarming on power flow on Path 44 and angle difference between SONGS and Miguel Nomogram display of Path flows two major import paths Monitoring voltage sensitivity and angle sensitivity at appropriate locations SDG&E has 6 PMUs that could have been used for wide area visibility 10

11 Power flow on path 44 after Hassyampa N. Gila line (from FERC/NERC Report) 11

12 San Diego Path Ratings and Loading before the - WECC Disturbance on September 8, 2011 Major Paths into the Blackout Area Path Ratings Path Loadings in MW Percent loading 500 kv H-NG (Part of Corridor 1 into blackout area) 1,800 MW(31) 1,397 MW 78% Path 44 (Corridor 2 into blackout area) 2,200 MW (32 ) 1,302 MW 59% 230 kv S Line (Part of Corridor 3 into blackout area) 239 MW 90 MW 38% SDG&E Import SOL 2,850 MW 2,539 MW 89% SDG&E to CFE Path MW S-N; 241 MW N-S 60% 408 MW N-S Note: 1. Normal system rating 2200 MW 2. Emergency (30 minute ) ratings - not known 3. Trip setting at 8000 Amps (3200 MW) at 145 % 12

13 Power flows to SDG&E, CFE and IID before the N.Gila-Hassyampa line trip SCE 1302 MW Path 44 (2200 MW) Relay operation set at 3186 MW SONGS SDGE CFE IID 1800 MW (30 deg.) Devers busses 90 MW (239 MW) N.Gila 1397 MW (20 deg. ) (1800 MW) APS/SRP 13

14 San Diego Path Ratings and Loading after the N.Gila- Hassyampa line trip Major Paths into the Blackout Area Path Ratings Path Loadings in MW and % rating 500 kv H-NG (Part of Corridor 1 into blackout area) 1,800 MW 0 MW 0 % Path 44 (Corridor 2 into blackout area) 2,200 MW 2362 MW 107 % 230 kv S Line (Part of Corridor 3 into blackout area) 239 MW 189 MW 38% SDG&E Import SOL 2,850 MW 2,539 MW 89% SDG&E to CFE Path MW S-N; 241 MW N-S 60% 408 MW N-S Note: 1. Normal system rating MW 2. Emergency (30 minute ) ratings - not known 3. Trip setting at 8000 Amps (3200 MW) at 145 % 14

15 Power flows to SDG&E, CFE and IID after the N.Gila-Hassyampa line trip SCE 2000 MW (30 deg.) 2386 MW Path 44 (2200 MW) Relay operation set at 3186 MW SONGS SDGE CFE IID Devers busses 184 MW (239 MW) N.Gila MW (20 deg. ) (1800 MW) APS/SRP 15

16 Power flows /Current on Path Trip level setting 3 After line trip Path 44 Current 2 Normal Rating 1 Before line trip Reference: FERC / NERC Report 16

17 PV Curve for North Gila Bus (Source: NERC/FERC Arizona Outage Report 17

18 Indian Grid Blackouts on July 30/31, 2012 Reference : REPORT OF THE ENQUIRY COMMITTEE ON GRID DISTURBANCE IN NORTHERN REGION ON 30th July 2012 AND IN NORTHERN, EASTERN & NORTH-EASTERN REGION ON 31st JULY 2012 Issued on 16th AUGUST 2012 NEW DELHI 18

19 North Indian Blackout July 30, 2012 Disturbance occurred at 02:33:00 on July 30, 2012 High loading in Northern Region load of MW Generation of MW Imports of 5836 MW mostly from the Western Region Several 400 kv lines out of service because of Planned outages (10) Unscheduled outages (5) Voltage control (6) Western Northern grid connected on Bina-Gwalior-Agra 400 kv line line loaded to 1355 MW (2.2 SIL) Three 230 kv lines 19

20 North Indian Blackout July 30, 2012 Amount of Load lost 38,200 MW (Estimated) Areas impacted Northern region People Impacted million Estimated cost $ 6 Billion Time to restore power hours Ties lost A & B NR separated from WR and ER Separation initiated by tripping of Bina-Agra circuit on Zone 3 20

21 Generation, Imports/Exports in Indian Regional Grids before Blackout Northern Region MW MW A Western Region MW MW C B 535 MW Eastern Region MW MW North Eastern Region 1367 MW - 53 MW Total Load : NW 21

22 Northern India Grid and Regional Interconnections Effected Area Northern Region July 30, 2012 Source: Indian Blackout Investigation Report dated August 16,

23 Indian Regional Blackout July 30, 2012 Frequency Profile in Northern Region 23

24 North Indian Blackout July 30, 2012 Increased loading on Bina-Gwalior-Agra caused tripping of this line on Zone 3 Tripping of Bina-Gwalior-Agra line resulted in tripping all 230 kv WR-NR lines separating WR and NR Separation of WR-NR resulted in tripping of all Ties between ER and NR NR left with a deficit of 5686 MW ( 18 % generation deficiency in NR Resulted in rapid frequency decline and NR blackout Power restored in hours 24

25 Power Flows in Indian Regional Grids at the time of Blackout 5686 MW Northern Region MW MW A Western Region C B Eastern Region MW 53 MW North Eastern Region 1367 MW MW 535 MW Total Load :79,479 MW Load Lost: 38,000 MW Ties Lost: A and B 25

26 North/ Eastern Indian Blackout July 31, 2012 Occurred in after-noon about 1:20 Hours, shortly after the first one, while the system was still being put together Amount of Load lost MW Areas impacted Northern region Eastern Region North Eastern region People Impacted million Estimated cost $ 10 Billion (Estimated) Time to restore power hours (Estimated) Ties lost A & C separating NR, ER and NER regions from WR 26

27 North/ Eastern Indian Blackout July 31, 2012 Increased loading on Bina-Gwalior-Agra again caused tripping of this line on Zone 3, the other line was out of service Tripping of Bina-Gwalior-Agra line resulted in tripping all 230 kv WR-NR lines separating WR and NR Separation of WR-NR resulted in tripping of all Ties between ER and NR NR left with a deficit of 5686 MW ( 18 % generation deficiency in NR Resulted in rapid frequency decline and NR blackout Power restored in hours 27

28 Northern India Blackout Effected Areas July 31,

29 Generation, Imports/Exports in Indian Regional Grids before Blackout Northern Region MW +4016MW A Western Region MW MW C B Eastern Region MW MW 212 MW North Eastern Region 1014 MW +212 Total Load : NW 29

30 Generation, Imports/Exports in Indian Regional Grids before Blackout Northern Region MW +4016MW A Western Region MW MW C B Eastern Region MW MW 212 MW North Eastern Region 1014 MW +212 Total Load : NW Load Lost : MW 30

31 Indian Regional Blackout July 31, 2012 Frequency Profile in Northern Region 31

32 Indian Blackout Investigation Report Very comprehensive Investigation report details all sequence of events, system configurations All facts and figures are provided making it easy to review and comment Suggests steps that may be taken to improve situation and prevent future blackouts Original reports blamed the states of withdrawing too much power, but indicates that the system had several lines out resulting in reduced inter-region transfer capability Simulations may be improved for better analysis 32

33 Requirements for the Stability of the Grid Grid should be able to Withstand loss of ties and maintain frequency within the acceptable band Not more than 5 % imports and/or adequate UFLS Grid should be able to maintain acceptable voltages at all locations adequate voltage support and control capability Grids operate across wide area and often with angle separation of greater than 90 degrees WECC (US) operates with angle separation of degrees Eastern Interconnection operates with angle separation of greater than 200 degrees Appropriate voltage support at intermediate (every 30 degrees of angle separation) locations is very important 33

34 Steps Suggested to avoid Blackouts Better Wide Area Visualization Internal External at least adjoining areas Grid should be able to ES and EMS in operation Establishing Limits on power flows Use of RTCA Use of Synchronized Phasor Measurement technology Angle measurements and other metrics Withstand loss of ties and maintain frequency within the acceptable band 34

35 Common causes between the SDG&E and Indian Blackouts - 1 Both Systems have two major inter-connections Hassyampa-NG & SCE SONGS Path 44 WR and ER Safe operation requires that loss of one interconnection should not result in exceeding the rating of the other path Readjustment necessary after loss of one tie Both systems were clearly operating beyond safe limits No SOL established or being monitored based on the system conditions No adjustments of loading for line outages Excessive imports compared to local area generation Load 4400 MW, imports of 2698 MW (No possibility of survival when both ties are lost ) Load of imports of 5686 loss of tie-line would result in a frequency decline of about 16 % No frequency control by UFLS 35

36 Common causes between the SDG&E and Indian Blackouts - 2 No Situational Awareness, EMS or RTCA in operation Relay setting resulting in system separation Zone 3 relay settings in India Path 44 setting at SONGS No system stress monitoring (Angle separation) No previous analysis to define safe operating regions Power flows (Path 44 ) Angle differences (Bina-Gwalior) No use of advanced technologies for real time dynamics monitoring 36

37 Thanks, for questions, please to 37

Consortium for Electric Reliability Technology Solutions (CERTS)

Consortium for Electric Reliability Technology Solutions (CERTS) Consortium for Electric Reliability Technology Solutions (CERTS) CERTS-CAISO Meeting Phasor Applications for Monitoring, Alarming & Control February 17 th, 2006 Joe Eto, Jim Dyer, Manu Parashar OUTLINE

More information

2015 Operational Practices Survey Questions

2015 Operational Practices Survey Questions 2015 Operational Practices Survey Questions This document of survey questions has been provided as a courtesy. It is not the actual survey, which will be completed electronically and only by a designated

More information

Mapping of Revised TOP and IRO Reliability Standards to Address 2011 Southwest Outage Report Recommendations

Mapping of Revised TOP and IRO Reliability Standards to Address 2011 Southwest Outage Report Recommendations Mapping of Revised TOP and IRO Reliability Standards to Address 2011 Southwest Outage Report Recommendations The following table provides a mapping of the recommendations applicable to the Reliability

More information

Platte River Power Authority. Ten-Year Transmission Plan ( )

Platte River Power Authority. Ten-Year Transmission Plan ( ) Platte River Power Authority Ten-Year Transmission Plan (2015-2024) Prepared by PRPA System Planning December 31, 2014 Table of Contents I. Executive Summary II. III. IV. Scope Assumptions Criteria V.

More information

Full Network Model Expansion Draft Final Proposal

Full Network Model Expansion Draft Final Proposal December 30, 2013 Table of Contents 1 Changes from 10/30/2013 second revised straw proposal... 4 2 Executive summary... 6 3 Introduction and purpose... 8 4 Plan for stakeholder engagement... 11 5 Scope

More information

California Independent System Operator Corporation Fifth Replacement Tariff

California Independent System Operator Corporation Fifth Replacement Tariff Table of Contents Method to Assess Available Transfer Capability... 2 L.1 Description of Terms... 2 L.1.1 Available Transfer Capability (ATC)... 2 L.1.2 Total Transfer Capability (TTC)... 2 L.1.3 Existing

More information

California Independent System Operator Corporation Fifth Replacement Tariff

California Independent System Operator Corporation Fifth Replacement Tariff Table of Contents Method to Assess Available Transfer Capability... 2 L.1 Description of Terms... 2 L.1.1 Available Transfer Capability (ATC)... 2 L.1.2 Total Transfer Capability (TTC)... 2 L.1.3 Existing

More information

Full Network Model Expansion Second Revised Straw Proposal

Full Network Model Expansion Second Revised Straw Proposal October 30, 2013 Table of Contents 1 Changes from 9/11/2013 revised straw proposal... 3 2 Executive summary... 3 3 Introduction and purpose... 5 4 Plan for stakeholder engagement... 8 5 Scope of initiative...

More information

POTOMAC ELECTRIC POWER COMPANY

POTOMAC ELECTRIC POWER COMPANY POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission

More information

2015 and 2019 Final LCR Study Results San Diego-Imperial Valley

2015 and 2019 Final LCR Study Results San Diego-Imperial Valley 2015 and 2019 Final LCR Study Results San Diego-Imperial Valley Frank Chen Senior Regional Transmission Engineer Stakeholder Web Conference April 10, 2014 ARIZONA San Diego-Imperial Valley LCR Area CHINO

More information

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017 Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA March 21, 2017 Contents 1 Background...3 2 National and Regional Criteria and Guides...4 2.1 2.1 NERC Transmission Planning Standards...4 2.2

More information

Data Visualization, Daily Operations Review and Event Analysis. Fabian Robinson PMU Program Lead PJM Interconnection NASPI Houston, TX - October 2014

Data Visualization, Daily Operations Review and Event Analysis. Fabian Robinson PMU Program Lead PJM Interconnection NASPI Houston, TX - October 2014 Data Visualization, Daily Operations Review and Event Analysis Fabian Robinson PMU Program Lead PJM Interconnection NASPI Houston, TX - October 2014 PJM as Part of the Eastern Interconnection KEY STATISTICS

More information

Seasonal Assessments and Modeling of Sub-100 kv Elements (Southwest Outage Recommendations 5, 6, 7 and NERC2) May 7, 2014

Seasonal Assessments and Modeling of Sub-100 kv Elements (Southwest Outage Recommendations 5, 6, 7 and NERC2) May 7, 2014 Seasonal Assessments and Modeling of Sub-100 kv Elements (Southwest Outage Recommendations 5, 6, 7 and NERC2) May 7, 2014 Background In April 2012, the Federal Energy Regulatory Commission (FERC) and the

More information

Toward Ensuring Reliability: Reliability Performance Metrics. A NERC Staff White Paper

Toward Ensuring Reliability: Reliability Performance Metrics. A NERC Staff White Paper Toward Ensuring Reliability: Reliability Performance Metrics A NERC Staff White Paper Table of Contents Table of Contents Table of Contents... 2 Executive Summary... 3 Metrics Objective... 5 Metrics Background...

More information

March 3, Submitted to: CAISO

March 3, Submitted to: CAISO March 3, 2016 Submitted to: CAISO (regionaltransmission@caiso.com) COMMENTS OF NEXTERA ENERGY TRANSMISSION WEST, LLC ON THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION S 2015-2016 TRANSMISSION PLANNING

More information

TTC/ATC 1.0 DEFINITIONS

TTC/ATC 1.0 DEFINITIONS TTC/ATC In this section: Definitions Total Transfer Capability (TTC) Methodology Available Transmission Transfer Capability (ATC) Calculation Counterflow ATC Release of Unused Transmission in Pre- schedule

More information

2018 & 22 Draft LCR Study Results LA Basin Area

2018 & 22 Draft LCR Study Results LA Basin Area 2018 & 22 Draft LCR Study Results LA Basin Area David Le Senior Advisor - Regional Transmission Engineer Stakeholder Meeting March 9, 2017 The study results for the 2018 LCR needs for the LA Basin and

More information

Seminar on African Electrical Interconnection. Module 8 - Interconnected Systems Operating Conditions

Seminar on African Electrical Interconnection. Module 8 - Interconnected Systems Operating Conditions Seminar on African Electrical Interconnection Module 8 - Interconnected Systems Operating Conditions Module 8 - Interconnected Systems Operating Conditions Contents 1) Technical Operating Agreements 2)

More information

Forward to the Revised Draft Transmission Plan

Forward to the Revised Draft Transmission Plan Forward to the Revised Draft 2013-2014 Transmission Plan This revised draft transmission plan reflects a number of changes from the draft plan released on February 3, 2014. To assist our stakeholders following

More information

2020 & 2024 Draft LCR Study Results for LA Basin and San Diego-Imperial Valley Areas

2020 & 2024 Draft LCR Study Results for LA Basin and San Diego-Imperial Valley Areas 2020 & 2024 Draft LCR Study Results for LA Basin and San Diego-Imperial Valley Areas David Le Senior Advisor, Regional Transmission Engineer Draft LCR Study Results Meeting March 14, 2019 LA Basin and

More information

Examples of Current Paradigm vs. Future Proposed Paradigm

Examples of Current Paradigm vs. Future Proposed Paradigm Examples of Current Paradigm vs. Future Proposed Paradigm 10/30/2013 POTF Meeting Webinar Created by Dede Subakti (CAISO), Bert Peters (APS), Vic Howell & Brett Wangen (WECC RC) Presented by Dede Subakti

More information

Jan Strack and Huang Lin March 14, 2017

Jan Strack and Huang Lin March 14, 2017 SDG&E Request for Economic Planning Study of the Renewable Energy Express Transmission Project as part of CAISO s 2017-2018 Transmission Planning Process (TPP) Jan Strack (jstrack@semprautilities.com)

More information

Generator Assessment & Roles During A Restoration

Generator Assessment & Roles During A Restoration Generator Assessment & Roles During A Restoration PJM State & Member Training Dept. PJM 2015 Objectives Students will be able to: Identify the process and requirements for operating during system restoration

More information

Updated October 2, 2014 TITLE: System Operator Transmission - Senior DEPARTMENT: System Operations

Updated October 2, 2014 TITLE: System Operator Transmission - Senior DEPARTMENT: System Operations Updated October 2, 2014 System Operator Transmission - Senior interconnected system. Maintains the Western Electricity Coordinating Council (WECC) Coordinated Outage System (COS), documents standardized

More information

BULK ELECTRIC SYSTEM PLANNING CRITERIA

BULK ELECTRIC SYSTEM PLANNING CRITERIA Part 4 Attachment Kansas City Power & Light Company BULK ELECTRIC SYSTEM PLANNING CRITERIA Harold Wyble, Manager Transmission Planning March 15, 2016 Table of Contents 1.0 Introduction... 3 2.0 KCP&L Transmission

More information

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA For Compliance with NERC Reliability Standard: TPL-001-4 1/10/2017 Version: 4.2 Table of Contents 1 Revision and Approval History... 2 1.1 Revision

More information

Power Grid Reliability - Improvements with Wide Area Monitoring, Protection and Control

Power Grid Reliability - Improvements with Wide Area Monitoring, Protection and Control Power Grid Reliability - Improvements with Wide Area Monitoring, Protection and Control Dr. Damir Novosel President, Quanta Technology LLC IEEE PES President Elect CIGRE US National Committee Board Sveučilište

More information

August 14, 2003 Blackout. Gerry Cauley Director Standards North American Electric Reliability Council

August 14, 2003 Blackout. Gerry Cauley Director Standards North American Electric Reliability Council August 14, 2003 Blackout Gerry Cauley Director Standards North American Electric Reliability Council Investigation Organization Overview Steering Group U.S Canada Task Force Investigation Team Lead Project

More information

Operating Procedure PURPOSE... 2

Operating Procedure PURPOSE... 2 No. 3100 Table of Contents PURPOSE... 2 1. RESPONSIBILITIES... 2 2. SCOPE/APPLICABILITY... 3 2.1. Background... 3 2.2. Scope/ Applicability... 3 3. PROCEDURE DETAIL... 4 3.1. Acceptable System Performance

More information

WESTERN ELECTRICITY COORDINATING COUNCIL GENERATING UNIT MODEL VALIDATION POLICY

WESTERN ELECTRICITY COORDINATING COUNCIL GENERATING UNIT MODEL VALIDATION POLICY WESTERN ELECTRICITY COORDINATING COUNCIL GENERATING UNIT MODEL VALIDATION POLICY A. Introduction A.1. Title: Generating Unit Model Validation Policy A.2. Purpose: Accurate models of generators and associated

More information

Enhancing Power Grid Reliability through Synchrophasor Measurements

Enhancing Power Grid Reliability through Synchrophasor Measurements 12-14 May'14 Workshop - Energy Cities and Control of Complex Systems,, Erice, Sicily 1 Enhancing Power Grid Reliability through Synchrophasor Measurements P. K. Agarwal, Additional General Manager Power

More information

Proceedings of the 2014 Winter Simulation Conference A. Tolk, S. Y. Diallo, I. O. Ryzhov, L. Yilmaz, S. Buckley, and J. A. Miller, eds.

Proceedings of the 2014 Winter Simulation Conference A. Tolk, S. Y. Diallo, I. O. Ryzhov, L. Yilmaz, S. Buckley, and J. A. Miller, eds. Proceedings of the 2014 Winter Simulation Conference A. Tolk, S. Y. Diallo, I. O. Ryzhov, L. Yilmaz, S. Buckley, and J. A. Miller, eds. SIMULATION OF THE SEPTEMBER 8, 2011, SAN DIEGO BLACKOUT Edgar C.

More information

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System Primary Interest Groups Balancing Authorities (BAs) Transmission Operators (TOPs) Generator Operators

More information

Approved RMWG Discussion was held. ??? John Simpson need to assign SMART rating

Approved RMWG Discussion was held. ??? John Simpson need to assign SMART rating ALR1-1 Generator Reactive Limit Metric:Voltage schedules How many times did generators encounter var limits associated with holding voltage schedule. 10 3 2 1 1 3 1 Initial pilot effort completed, reaching

More information

California Independent System Operator (CAISO) Challenges and Solutions

California Independent System Operator (CAISO) Challenges and Solutions California Independent System Operator (CAISO) Challenges and Solutions Presented by Jim Hiebert EMS Power Technology Engineer Lead California ISO by the numbers 65,225 MW of power plant capacity 50,270

More information

BPA Wind Voltage Control Requirements

BPA Wind Voltage Control Requirements BPA Wind Voltage Control Requirements PJM Conference Dmitry Kosterev Bonneville Power Administration Many of BPA Paths are Stability-Limited Cross-Cascades North Montana - Northwest Cross-Cascades South

More information

Stakeholder Comments. 2012/2013 Transmission Planning Process. Presentations from December 11 and 12 meetings

Stakeholder Comments. 2012/2013 Transmission Planning Process. Presentations from December 11 and 12 meetings Stakeholder Comments 2012/2013 Transmission Planning Process Presentations from December 11 and 12 meetings Submitted by Company Date Submitted Karen Shea Garry Chinn Rabiindra Kiran Southern California

More information

ISO Transmission Plan February 1, 2016

ISO Transmission Plan February 1, 2016 2015-2016 ISO Transmission Plan February 1, 2016 APPENDIX D: 2025 Local Capacity Technical Analysis for the Los Angeles Basin (LA Basin), Big Creek/Ventura and San Diego Local Capacity Requirement Areas

More information

2018 & 2022 Draft LCR Study Results San Diego-Imperial Valley

2018 & 2022 Draft LCR Study Results San Diego-Imperial Valley 2018 & 2022 Draft LCR Study Results San Diego-Imperial Valley Frank Chen - Regional Transmission Engineer Lead David Le - Senior Advisor Regional Transmission Engineer Stakeholder Meeting March 9, 2017

More information

Synchrophasors for Situational Awareness

Synchrophasors for Situational Awareness Synchrophasors for Situational Awareness NERC Monitoring & Situational Awareness Conference Ryan D. Quint, NERC September 29, 2015 NERC Synchronized Measurement Subcommittee (SMS) North American Synchrophasor

More information

the most promising locations for new renewables in the Imperial CREZ.

the most promising locations for new renewables in the Imperial CREZ. March 3, 2016 Imperial Irrigation District (IID) appreciates the opportunity to comment on the California Independent System Operator (CAISO) presentation during its 2/18/16 Stakeholder meeting discussing

More information

Transfer Capability Methodology. for the Near-Term. Transmission Planning Horizon

Transfer Capability Methodology. for the Near-Term. Transmission Planning Horizon Transfer Capability Methodology for the Near-Term Transmission Planning FAC-013-2 Version 2.2 June 30, 2018 Table of Contents 1 PURPOSE... 3 2 DEFINITION... 3 3 APPLICABILITY... 3 4 TRANSFER CAPABILITY

More information

Conceptual Statewide Transmission Plan Update. California ISO Regional Transmission Planning Process.

Conceptual Statewide Transmission Plan Update. California ISO Regional Transmission Planning Process. 2014-2015 Conceptual Statewide Transmission Plan Update California ISO 2015-2016 Regional ning Process August 31, 2015 Prepared by Market & Infrastructure Development California Independent System Operator

More information

California ISO. Q Report on Market Issues and Performance. August 21, Prepared by: Department of Market Monitoring

California ISO. Q Report on Market Issues and Performance. August 21, Prepared by: Department of Market Monitoring California Independent System Operator Corporation California ISO Q2 2013 Report on Market Issues and Performance August 21, 2013 Prepared by: Department of Market Monitoring Table of Contents Executive

More information

System Integrity Protection Schemes Increasing operational security and system capacity

System Integrity Protection Schemes Increasing operational security and system capacity 21, rue d Artois, F-758 PARIS C2-21 CIGRE 212 http : //www.cigre.org System Integrity Protection Schemes Increasing operational security and system capacity E. HILLBERG 1, F. TRENGEREID 2, Ø. BREIDABLIK

More information

Imperial County Transmission Consultation Current Resource Deliverability Capabilities from Imperial Valley

Imperial County Transmission Consultation Current Resource Deliverability Capabilities from Imperial Valley Imperial County Transmission Consultation Current Resource Deliverability Capabilities from Imperial Valley Technical Addendum to the July 2, 2014 Imperial County Transmission Consultation Draft Discussion

More information

Fundamentals of Transmission Operations

Fundamentals of Transmission Operations Fundamentals of Transmission Operations System Restoration PJM State & Member Training Dept. PJM 2014 10/25/2013 Objectives At the end of this module the Student will be able to: Identify the different

More information

DRAFT STUDY PLAN FOR 2018

DRAFT STUDY PLAN FOR 2018 DRAFT STUDY PLAN FOR 2018 Introduction The Ten-year transmission planning process is intended to facilitate a timely, coordinated and transparent process that fosters the development of electric infrastructure

More information

EAPP interconnection readiness workshop

EAPP interconnection readiness workshop 1 EAPP interconnection readiness workshop Self-Assessment for EAPP/IC -Compliance Rwandan-Grid Gap Analysis & Proposed mitigations GENERATION, TRANSMISSION & DISTRIBUTION 01 st October, 2018 INTRODUCTION

More information

COMMENTS OF THE STAFF OF THE CALIFORNIA PUBLIC UTILITIES COMMISSION

COMMENTS OF THE STAFF OF THE CALIFORNIA PUBLIC UTILITIES COMMISSION COMMENTS OF THE STAFF OF THE CALIFORNIA PUBLIC UTILITIES COMMISSION ON THE 2015-2016 TRANSMISSION PLANNING PROCESS PRELIMINARY RELIABILITY ASSESSMENT RESULTS FOLLOWING THE SEPTEMBER 21-22 STAKEHOLDER MEETING

More information

Frequency Response Assessment and Improvement of Three Major North American Interconnections due to High Penetrations of Photovoltaic Generation

Frequency Response Assessment and Improvement of Three Major North American Interconnections due to High Penetrations of Photovoltaic Generation Frequency Response Assessment and Improvement of Three Major North American Interconnections due to High Penetrations of Photovoltaic Generation Yilu Liu 1,2, Yong Liu 1, Shutang You 1, Yingchen Zhang

More information

Peak West-wide System Model Validation Activities

Peak West-wide System Model Validation Activities Peak West-wide System Model Validation Activities 10/24/2016 Brett Wangen Hongming Zhang Gareth Lim Purpose of This Discussion Provide West-wide System Model (WSM) overview Give insight into ongoing model

More information

2005 Integrated Electricity Plan. Provincial IEP Committee Meeting #2 Planning Criteria February 22/23, 2005

2005 Integrated Electricity Plan. Provincial IEP Committee Meeting #2 Planning Criteria February 22/23, 2005 2005 Integrated Electricity Plan Provincial IEP Committee Meeting #2 Planning Criteria February 22/23, 2005 2005 IEP Objectives Means Objectives Ends (Fundamental) Objectives Agenda Items No net imports

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014 No. Comment Submitted ISO Response Date Q&A Posted 1 Can the CAISO provide a line rating methodology (similar to a NERC FAC-008 standard) or include a requirement of using any The ISO does not provide

More information

California Grid Operations: Current Conditions and Future Needs

California Grid Operations: Current Conditions and Future Needs California Grid Operations: Current Conditions and Future Needs Jim Detmers Vice President, Operations Global Climate & Energy Project November 1, 2007 STANFORD UNIVERSITY Our objective today is identify

More information

2014 ERO Enterprise Compliance Monitoring and Enforcement Program Annual Report

2014 ERO Enterprise Compliance Monitoring and Enforcement Program Annual Report 2014 ERO Enterprise Compliance Monitoring and Enforcement Program Annual Report August 2015 NERC 2014 ERO Enterprise Annual CMEP Report August 2015 i Table of Contents Preface... iii Executive Summary...

More information

CAISO View of Smart Grid

CAISO View of Smart Grid CAISO View of Smart Grid David Hawkins Lead Renewables Power Engineer March 17, 2010 Slide 2 Slide 2 1 Generation Grid Operators View Leverage smart grid policies to: Increase demand-side participation

More information

California Independent System Operator Renewable Integration Study

California Independent System Operator Renewable Integration Study California Independent System Operator Renewable Integration Study Clyde Loutan Proposed Transmission Plan for Integration of Renewables Transmission System Analysis - Overview Joint Study between the

More information

2022 LOCAL CAPACITY TECHNICAL ANALYSIS FINAL REPORT AND STUDY RESULTS

2022 LOCAL CAPACITY TECHNICAL ANALYSIS FINAL REPORT AND STUDY RESULTS California Independent System Operator 2022 LOCAL CAPACITY TECHNICAL ANALYSIS FINAL REPORT AND STUDY RESULTS May 3, 2017 Local Capacity Technical Analysis Overview and Study Results I. Executive Summary

More information

Next Generation EMS Control Center

Next Generation EMS Control Center Next Generation EMS Control Center JST-NSF-DFG-RCN Workshop on Distributed Energy Management Systems Washington DC April 20th, 2015 Jay Giri Director, Power Systems Technology & Strategic Initiatives Redmond,

More information

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements 2. Number: PRC 006 RFC 01 3. Purpose: To establish ReliabilityFirst requirements for automatic Load shedding (UFLS) to support

More information

Proposed Resource Loss Protection Criteria

Proposed Resource Loss Protection Criteria Proposed Resource Loss Protection Criteria Background and Current Methodologies The Resource Loss Protection Criteria (RLPC) is the respective Interconnection design resource loss in MW, which is used

More information

2011 Final LCR Study Results San Diego Local Area

2011 Final LCR Study Results San Diego Local Area 2011 Final LCR Study Results San Diego Local Area Luba Kravchuk Regional Transmission Engineer Stakeholder Meeting April 15, 2010 San Diego LCR Area CHINO [SCE] SERRAN O [SCE] ORANG JOHANN E A CO. [SCE]

More information

Table of Contents. To provide a methodology for determining the System Operating Limits (SOL) for the Planning Horizon at the California ISO.

Table of Contents. To provide a methodology for determining the System Operating Limits (SOL) for the Planning Horizon at the California ISO. Table of Contents Purpose... 1 Applicable Reliability Standard(s)... 1 Applicability to California ISO... 1 SOLs and IROLs... 1 Study Methodology... 2 Supporting Information... 6 Responsibilities... 6

More information

Second Report of the Tehachapi Collaborative Study Group

Second Report of the Tehachapi Collaborative Study Group Development Plan for the Phased Expansion of Electric Power Transmission Facilities in the Tehachapi Wind Resource Area Second Report of the Tehachapi Collaborative Study Group California Public Utilities

More information

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) Background On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) The CAISO s deliverability study methodology for resource adequacy purposes was discussed extensively in the CPUC

More information

Remedial Action Scheme (RAS) Modeling Value Proposition

Remedial Action Scheme (RAS) Modeling Value Proposition Remedial Action Scheme (RAS) Modeling Value Proposition Modeling SPS and Relay Ad-hoc Task Force of the Technical Studies Subcommittee and WECC Staff Western Electricity Coordinating Council May 2, 2014

More information

Voltage Stability Criteria, Undervoltage Load Shedding Strategy, and Reactive Power Reserve Monitoring Methodology May 1998

Voltage Stability Criteria, Undervoltage Load Shedding Strategy, and Reactive Power Reserve Monitoring Methodology May 1998 Western Electricity Coordinating Council Voltage Stability Criteria, Undervoltage Load Shedding Strategy, and Reactive Power Reserve Monitoring Methodology May 1998 VOLTAGE STABILITY CRITERIA, UNDERVOLTAGE

More information

Transmission Line Availability Data Guidelines and Definitions. Gregg A. Spindler SGS Statistical Services, LLC

Transmission Line Availability Data Guidelines and Definitions. Gregg A. Spindler SGS Statistical Services, LLC Transmission Line Availability Data Guidelines and Definitions Gregg A. Spindler SGS Statistical Services, LLC 315.655.8187 info@sgsstat.com Presentation Objectives About SGS Post-August 14 2003 observations

More information

Mitigating Extraordinary Events using Wide Area Monitoring Applications

Mitigating Extraordinary Events using Wide Area Monitoring Applications 2, rue d Artois, F-75008 PARIS 53 RECIFE 20 http : //www.cigre.org Mitigating Extraordinary Events using Wide Area Monitoring Applications E. JOHANSSON, K. UHLEN, G. KJØLLE Norwegian University of Science

More information

Western Wind & Solar Integration Studies

Western Wind & Solar Integration Studies Western Wind & Solar Integration Studies Kara Clark, Greg Brinkman, NREL Nick Miller, Miaolei Shao, Slobodan Pajic, Rob D Aquila, Bruno Leonardi, GE 3/22/17 NREL is a national laboratory of the U.S. Department

More information

804 OFF-NOMINAL FREQUENCY LOAD SHEDDING AND RESTORATION

804 OFF-NOMINAL FREQUENCY LOAD SHEDDING AND RESTORATION Operating Policies and Procedures Emergency System Operations OPP 804 Issued:2008-11-13 Supersedes Interim OPP Effective:2008-05-01 804 OFF-NOMINAL FREQUENCY LOAD SHEDDING AND RESTORATION 1. Purpose To

More information

SunZia Southwest Transmission Project

SunZia Southwest Transmission Project SunZia Southwest Transmission Project WECC 2011 Annual Progress Report Submitted by SouthWestern Power Group February 25, 2011 Table of Contents I. Introduction -----------------------------------------------------------

More information

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: IFHS MH MW, firm :00:00 CS

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: IFHS MH MW, firm :00:00 CS Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #80487374, under the SaskPower Open Access Transmission Tariff (OATT). The purpose of

More information

Transmission ITP. System Restoration. PJM State & Member Training Dept. PJM /10/2018

Transmission ITP. System Restoration. PJM State & Member Training Dept. PJM /10/2018 Transmission ITP System Restoration PJM State & Member Training Dept. PJM 2018 Objectives At the end of this module the Student will be able to: Identify the different causes of some of the major blackouts

More information

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: Service Requested

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: Service Requested Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #80439788, under the SaskPower Open Access Transmission Tariff (OATT). The purpose of

More information

STATE OF THE INTERCONNECTION DIGEST

STATE OF THE INTERCONNECTION DIGEST SUMMER 217 STATE OF THE INTERCONNECTION DIGEST The State of the Interconnection is a snapshot of evolving trends in the Western Interconnection. Beginning in 217, the Western Electricity Coordinating Council

More information

San Diego Gas & Electric Company FERC Order 717 Transmission Function Employee Job Descriptions June 25, Electric Grid Operations

San Diego Gas & Electric Company FERC Order 717 Transmission Function Employee Job Descriptions June 25, Electric Grid Operations San Diego Gas & Electric Company FERC Order 717 Transmission Function Employee Job Descriptions June 25, 2018 Electric Grid Operations Associate Contracting Agent Construction Services: Supports completion

More information

Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES

Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES Effective Date: September 11, 2017 Revision History Date Version Description June 6, 1998 0.0 Initial LGEE document

More information

COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN

COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN January 11, 2018 ColumbiaGrid 8338 NE Alderwood Road, Suite 140 Portland, OR 97220 www.columbiagrid.org (503) 943-4940 8338 NE Alderwood Road, Suite

More information

Operating Procedure PURPOSE... 1

Operating Procedure PURPOSE... 1 Table of Contents PURPOSE... 1 1. RESPONSIBILITIES... 2 2. SCOPE/APPLICABILITY... 2 2.1. Background... 2 2.2. Scope/ Applicability... 2 3. PROCEDURE DETAIL... 3 3.1. Order of Steps... 3 3.2. Restricted

More information

California ISO Preparing California for a Greener and Smarter Grid

California ISO Preparing California for a Greener and Smarter Grid California ISO Preparing California for a Greener and Smarter Grid Presented by Jim McIntosh Director Operations Executive Advisor California ISO Agenda CAISO Overview Current & Future Challenges Renewables

More information

FACILITY CONNECTION REQUIREMENTS NERC TO-FAC 001-0

FACILITY CONNECTION REQUIREMENTS NERC TO-FAC 001-0 FACILITY CONNECTION REQUIREMENTS NERC TO-FAC 001-0 TABLE OF CONTENTS (NERC TO-FAC-001-0) Facility Connection Requirements Introduction Procedures for Coordinated Joint Studies...1 Procedures for Notification...1

More information

Renewable Integration at ERCOT

Renewable Integration at ERCOT Renewable Integration at ERCOT Dan Woodfin Director of System Operations ERCOT CIGRE Chile September 12, 2016 The ERCOT Region The interconnected electrical system serving most of Texas, with limited external

More information

Standards de planification du NERC

Standards de planification du NERC Demande R-3498-2002 Standards de planification du NERC PREUVE EN CHEF DE TRANSÉNERGIE Original : 2002-11-27 HQT-4, Document 2 (en liasse) NERC PLANNING STANDARDS North American Electric Reliability Council

More information

Mapping Document for FAC-010-3

Mapping Document for FAC-010-3 Mapping Document for FAC-010-3 The Project 2015 09 standard drafting team (SDT) is proposing the retirement of the NERC FAC 010 3 Reliability Standard. The SDT further proposes a new paradigm regarding

More information

SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON. Rev. 1.0

SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON. Rev. 1.0 No. RC0610 SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON Rev. 1.0 By California Independent System Operator (CAISO RC) No. RC0610 Table of Contents A. Conventions... 5 B. Introduction

More information

PREPARED DIRECT TESTIMONY OF S. ALI YARI ON BEHALF OF SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY

PREPARED DIRECT TESTIMONY OF S. ALI YARI ON BEHALF OF SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY Application No: A.1-0-01 Exhibit No.: Witness: S. Ali Yari In The Matter of the Application of San Diego Gas & Electric Company (U 0 G) and Southern California Gas Company (U 0 G) for a Certificate of

More information

Adaptive Islanding to Prevent Cascading Failures

Adaptive Islanding to Prevent Cascading Failures Adaptive Islanding to Prevent Cascading Failures Vijay Vittal Ira A. Fulton Chair Professor Arizona State University Seminar March 21, 2006 Background This seminar reports on the work done in a recently

More information

Most Severe Single Contingency (MSSC) Impacts on Alberta Balancing Authority Area Operation. Observations and Information Sharing

Most Severe Single Contingency (MSSC) Impacts on Alberta Balancing Authority Area Operation. Observations and Information Sharing Most Severe Single Contingency (MSSC) Impacts on Alberta Balancing Authority Area Operation Observations and Information Sharing Date: June, 2015 Prepared by: AESO Table of Contents Executive Summary...

More information

11. TRANSMISSION AND INTERCONNECTION FACILITIES

11. TRANSMISSION AND INTERCONNECTION FACILITIES 11. TRANSMISSION AND INTERCONNECTION FACILITIES Three transmission line corridors have been investigated in this report, but no route (or routes) has been recommended. One of the five possible configurations

More information

PID 276 Feasibility Study Report 4.4MW Distribution Inter-Connection Mermentau Substation

PID 276 Feasibility Study Report 4.4MW Distribution Inter-Connection Mermentau Substation PID 276 Feasibility Study Report 4.4MW Distribution Inter-Connection Mermentau Substation Prepared by: Entergy Services, Inc. T & D Planning 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date Description

More information

Final Manual Local Capacity Area Technical Study

Final Manual Local Capacity Area Technical Study Final Manual 2019 Local Capacity Area Technical Study December 2017 Version Prepared by: California Independent System Operator 2019 Local Capacity Area Technical Study Manual Table of Contents INTRODUCTION...

More information

Conceptual Statewide Transmission Plan Update. CAISO Regional Transmission Planning Process. October 31, 2014

Conceptual Statewide Transmission Plan Update. CAISO Regional Transmission Planning Process. October 31, 2014 2013-2014 Conceptual Statewide Transmission Plan Update CAISO 2014-2015 Regional Transmission Planning Process October 31, 2014 Prepared by Market & Infrastructure Development California Independent System

More information

NERC Reliability Functional Model

NERC Reliability Functional Model NERC Reliability Functional Model Function Definitions and Responsible Entities Version 3 Approved by Standing Committees: Operating Committee: December 6, 2006 Planning Committee: December 6, 2006 Standards

More information

Addressing System Restoration Issues for the ISO New England System. Michael I. Henderson ISO New England Inc. PES General Meeting July 2015

Addressing System Restoration Issues for the ISO New England System. Michael I. Henderson ISO New England Inc. PES General Meeting July 2015 Addressing System Restoration Issues for the ISO New England System Michael I. Henderson ISO New England Inc. PES General Meeting July 2015 Key Power System and Market Facts (2014) 6.5 million households

More information

Contingency Analysis For Eastern Regional Grid of INDIA P.Pentayya, P.Mukhopadhyay, S.Banerjee, M.K.Thakur

Contingency Analysis For Eastern Regional Grid of INDIA P.Pentayya, P.Mukhopadhyay, S.Banerjee, M.K.Thakur 16th NATIONAL POWER SYSTEMS CONFERENCE, 15th-17th DECEMBER, 2010 359 Contingency Analysis For Eastern Regional Grid of INDIA P.Pentayya, P.Mukhopadhyay, S.Banerjee, M.K.Thakur Abstract-The Eastern Regional

More information

2017 LOCAL CAPACITY TECHNICAL ANALYSIS FINAL REPORT AND STUDY RESULTS

2017 LOCAL CAPACITY TECHNICAL ANALYSIS FINAL REPORT AND STUDY RESULTS 2017 LOCAL CAPACITY TECHNICAL ANALYSIS FINAL REPORT AND STUDY RESULTS April 29, 2016 Local Capacity Technical Study Overview and Results I. Executive Summary This Report documents the results and recommendations

More information

Security Guideline for the Electricity Sector: Identifying Critical Assets

Security Guideline for the Electricity Sector: Identifying Critical Assets Note: The guideline was developed for CIP-002-1 but is also applicable to CIP- 002-2 and CIP-002-3. Security Guideline for the Electricity Sector: Identifying Critical Assets Disclaimer: This supporting

More information

Implementation Plan for IRO Reliability Coordination Facilities Prerequisite Approvals Adoption of IRO-001-2, IRO-010-0, COM-001-2

Implementation Plan for IRO Reliability Coordination Facilities Prerequisite Approvals Adoption of IRO-001-2, IRO-010-0, COM-001-2 Prerequisite Approvals Adoption of IRO-001-2, IRO-010-0, COM-001-2 Conforming Changes to Requirements in s None Coordination with revisions proposed in other standards projects The IROL SDT proposes retiring

More information