TO: Public Works Commission FROM: Robyn Mattison, Jim Pardy, and Shawn Wilson DATE: June 30, 2017 RE: Water Renewal Fund Capital Projects

Size: px
Start display at page:

Download "TO: Public Works Commission FROM: Robyn Mattison, Jim Pardy, and Shawn Wilson DATE: June 30, 2017 RE: Water Renewal Fund Capital Projects"

Transcription

1 TO: Public Works Commission FROM: Robyn Mattison, Jim Pardy, and Shawn Wilson DATE: June 30, 2017 RE: Water Renewal Fund Capital Projects MAJOR PROJECTS, INITIATIVES, CURENT ISSUES Clean Water: Major Projects Status Water Renewal Facilities Plan A team led by Brown & Caldwell is performing Water Renewal Facilities Plan updates. The last plan was developed in The planning effort is a three phase process which includes: 1. Baselining Existing Assets, Identifying Constraints, and Updating Long Term Projections 2. Developing and Evaluating Solutions to Close the Gap between the Existing Assets and the Projections 3. Prioritizing and Implementing Solutions The project team has completed Phase 1 and is proceeding with Phase 2 which will continue through Related planning work includes: A task order is underway with HDR to update the facility plan for the Twenty Mile South Biosolids Application Site (TMSBAS). HDR has completed a farm baseline that will support the Facilities Planning efforts with Phase 1. The remainder of the farm facility plan work will align with the ongoing water renewal fund facilities planning efforts. A new task order is underway with HDR to provide continued regulatory guidance throughout the NPDES permit re-application process and to support developing a water reuse permit for Lander Street potentially discharging into Farmers Union Canal. This work will be coordinated with the outcome of Phase 2 of the Water Renewal Fund Facilities Planning when long term program direction is defined. Temperature Mitigation Studies

2 Staff continues to work with IDEQ and the EPA in developing temperature mitigation strategies. West Boise WRF Phosphorus Removal The contract for the West Boise Phosphorus (P) Removal Project was completed and closed in Jan 2016 (Enhanced Biological Nutrient Removal, or EBNR). As follow-up, additional design features were added to improve performance of the fermenter mixing system, which proceeded with construction in Sept The fermenter mixing system modifications are currently underway and expected to reach completion in July Operation of the EBNR process has improved and stabilized since July EPA approved the City s request for a major NPDES permit modification to adjust the West Boise interim P limits from a seasonal average of 600 µg /L Total Phosphorus (TP) to an annual average of 2,800 µg /L TP. The resulting calculation of the combined average from May 2016 through February 2017 is currently 1,375 µg /L TP and is expected to meet the annual limit of 2,800 µg /L TP. The Operations Division has been effectively producing struvite which is a critical component to comply with the TP discharge limits. Decreased performance of the Struvite Production Facility (SPF) quickly affect facility performance and impact effluent TP discharge concentrations. A significant and innovative process modification was completed by internally combining two separate treatment processes into a single blended feed to the SPF in mid-september The blended flows improve TP recovery (as struvite) which has also improved the consistency of the final struvite in the heat treatment process (Rollomixer). The process change was also able to utilize the available ammonia in the belt filter press (BFP) filtrate and eliminate the purchase of commercial aqueous ammonia used in the phosphate-enriched filtrate (PFLT) struvite reactors. The struvite heat treatment system required to satisfy EPA s 503 regulations for pathogen reduction in biosolids has been able to nearly match the struvite production rate. Final implementation of the struvite disposition contract is being negotiated with the technology provider, Multiform Harvest, Inc. (MHI). The City released six (6) full semitrailer loads of struvite, which met the Class A criteria, to MHI in February 2017 for processing as a commercial fertilizer product. West Boise Capacity Improvements: Anaerobic Digestion and Dewatering The project focus areas are biofilter expansion to meet current needs, reviewing the sludge dewatering system and investigating limitations in anaerobic digestion capacity. Bids for a new biofilter, thickened primary sludge pumping improvements, and digester piping modifications were received in June Work is expected to be completed in the fall of Dewatering evaluations are complete resulting in rehabilitation of the existing Belt Filter Presses with new and factory refurbished belt rollers. Belt Filter rehabilitation is projected to be complete by January New digester design is delayed until upgrades and inspection of the existing digesters are complete. Current digester work includes piping modifications to allow parallel flow operation to all 3 digesters, cleaning and condition assessment of the existing digesters and optimization Page 2 of 5

3 of the existing digestion capacity. HDR will perform condition assessments of the digesters starting this summer with the final inspection completed in Spring Next phase decisions will depend on the condition of the existing digesters. Dixie Drain Phosphorus Removal The Dixie Drain Phosphorous Removal Project construction was completed in 2016 and is fully operational and meeting our compliance requirement of 25 pounds per day of phosphorus. Minor upgrades to the facility include a mechanical screen cleaning system which is currently being fabricated by the manufacturer with installation anticipated in Fall Revegetation of disturbed areas along the Dixie Drain, which will help with erosion control and temperature in the drain, will begin in October. The contractor is currently completing a list of repairs identified in the 1-year warranty walkthrough. Additional improvements to advance operations and efficiency have been identified and are underway by city staff. In June of this year, the Association of Idaho Cities (AIC) presented the City of Boise a City Achievement Award for the Dixie Drain Phosphorus Removal Facility and its role in innovation. Lander Street WRF Plant-Wide Improvements The City s current NPDES permit for Lander Street (LS) requires low effluent TP concentrations and the schedule of compliance must be completed no later than September 1, Critical projects at Lander Street to meet the TP schedule of compliance and to replace critical aging infrastructure were identified from the Facility Plan and have proceeded into conceptual design. A CIP budget was approved beginning in FY17. Work during the first 5 years is expected to include site utilities improvements, new preliminary treatment, new effluent filtration to achieve the low effluent TP limits, and Ultra-violet light (UV)disinfection improvements. Public Works Engineering defined the goal to complete construction in FY21 to allow one full year of operation before the NPDES compliance date. All Lander Street improvements are expected to cost up to $80M over the next 10 years, with up to $58M before FY22. Engineering design is contracted to a team consisting of CH2M with Brown and Caldwell. The City selected McAlvain as the Construction Manager / General Contractor (CM/GC) for pre-construction and construction phase services. The Preliminary Engineering Report will be prepared by the design team, with input from the CM/GC, this Fall with Idaho Department of Environmental Quality review and approval anticipated by the end of the calendar year. Combined Heat and Power (CHP) or Renewable Natural Gas (RNG) and Food Waste Receiving This project anticipates constructing facilities to collect food waste and brown grease for methane production. The methane gas produced will either be used by generators to create electricity or will be cleaned for direct use. A CIP budget was not authorized for FY17, nor is one requested for FY18 due to cash flow constraints in the water renewal fund. Page 3 of 5

4 Clean Water: Issues & Strategies Currently the Clean Water Section has 11 FTEs, including two control system techs that were transferred from the Operations Division. The last workload projection estimated between 13 and 18 FTEs will be required through 2018 to complete planned projects. The current strategy of hiring consulting services to make up the difference between City staff and required staff will continue. In addition to the projects discussed above, the projections include near-term future projects being driven by NPDES permit requirements: filtration at West Boise for additional P removal, and effluent temperature mitigation for both WRFs. Future project needs will be updated when the Facilities Planning plant capacity assessments are completed. In December 2013 two additional positions for a process controls engineer and a process controls programmer were approved by the City Council. Only 1 was filled, and in the summer of 2016 the other position was forfeited to gain a full-time instrument technician at LS. The controls Engineer II position was filled in July 2015, and a large amount of work, some previously unrecognized, has been identified: creating, organizing and updating wiring drawings for maintenance troubleshooting; updating control standards; establishing electrical standards; developing electrical distribution models for both WRFs that are necessary for arc flash analyses; supervising two control systems technicians; and managing or providing electrical and controls support on CIPs. The intent, with the addition of these employees and the organizational changes is to maintain and monitor the automated plant controls in a systematic manner that will reduce the incidents of controls failure or of troublesome controls being overridden, and to plan for systematic technology upgrades. Staff has requested city council approval of an additional Controls Engineer II position in FY18 to better accomplish these goals. Sewer Design: Collection System Projects Status Small Diameter Sewer Pipe Rehabilitate/Replacement Program In accordance with the small diameter pipe rehabilitation/replacement program, 45 segments were identified to be rehabilitated in To date 24 of the 45 segments have been completed. Construction is on schedule. Estimated expenditures to complete this work is $1,000,000 in which budget is available. Sewer Design: Issues & Strategies A vibrant construction climate is resulting in less contractors bidding on projects and the cost of work is rising. In addition, construction companies appear to be struggling to keep and retain laborers and equipment operators. In response to this, some companies are increasing pay and benefits in an effort to attract and retain skilled workers. This also is contributing to higher bid prices. In 2018 the Engineering Department will package the rehabilitation projects into two projects instead of three. Reasoning is staff believes the larger packaged project will create more interest among contractors. Page 4 of 5

5 Large Diameter Pipe Rehabilitation Program Three large diameter sewer pipe point repairs were completed during the spring. Projects were successful in eliminating significant infiltration found within these segments. No additional large diameter projects are scheduled for this year. Inflow and Infiltration (I/I): Issues & Strategies High river flows this spring provided an opportunity to do sanitary sewer flow monitoring in hopes of identifying inflow and infiltration sources. Several weeks of data were collected and are currently being analyzed, results of which will be used to prioritize future mainline and manhole rehabilitation projects. Page 5 of 5

TO: Public Works Commission FROM: Robyn Mattison, Jim Pardy, and Paul Zimmerman DATE: April 5, 2017 RE: Water Renewal Fund Capital Projects

TO: Public Works Commission FROM: Robyn Mattison, Jim Pardy, and Paul Zimmerman DATE: April 5, 2017 RE: Water Renewal Fund Capital Projects TO: Public Works Commission FROM: Robyn Mattison, Jim Pardy, and Paul Zimmerman DATE: April 5, 2017 RE: Water Renewal Fund Capital Projects MAJOR PROJECTS, INITIATIVES, CURENT ISSUES Clean Water: Major

More information

INTEROFFICE MEMORANDUM

INTEROFFICE MEMORANDUM INTEROFFICE MEMORANDUM Date: Dec 3, 2015 To: Boise Public Works Commission From: Paul Zimmerman, Matt Hightree, and Jim Pardy Subject: Directors Report - Sewer Goal: Develop and implement a long-term wastewater

More information

INTEROFFICE MEMORANDUM

INTEROFFICE MEMORANDUM INTEROFFICE MEMORANDUM DATE: February 3, 2011 TO: Public Works Commission FROM: Heather Mink, Support Systems Manager SUBJECT: FY 2012 and 2013 CIP and Equipment Budget Recommendations ISSUE The attached

More information

INTEROFFICE MEMORANDUM

INTEROFFICE MEMORANDUM INTEROFFICE MEMORANDUM Date: March 3, 2015 To: Boise Public Works Commission From: Anthony Perreira, P.E., Project Manager Subject: Energy Consumption at Major Facilities Managed by Public Works This report

More information

INTEROFFICE MEMORANDUM

INTEROFFICE MEMORANDUM INTEROFFICE MEMORANDUM Date: August 31, 2015 To: Boise Public Works Commission From: Anthony Perreira, P.E., Project Manager Subject: Energy Consumption at Major Facilities Managed by Public Works This

More information

A REPORT FROM THE OFFICE OF INTERNAL AUDIT

A REPORT FROM THE OFFICE OF INTERNAL AUDIT A REPORT FROM THE OFFICE OF INTERNAL AUDIT PRESENTED TO THE CITY COUNCIL CITY OF BOISE, IDAHO AUDIT / TASK: #16-11, Sewer Operations AUDIT CLIENT: Public Works REPORT DATE: December 14, 2016 AUDIT GRADE:

More information

The City of Boise s Nutrient Control Approach and the Dixie Slough Offset Project

The City of Boise s Nutrient Control Approach and the Dixie Slough Offset Project The City of Boise s Nutrient Control Approach and the Dixie Slough Offset Project 2015 Annual Oregon ACWA Conference July 24, 2015 Robbin Finch, Water Quality Manager Boise City Public Works Outline Sustainability

More information

INTEROFFICE MEMORANDUM

INTEROFFICE MEMORANDUM INTEROFFICE MEMORANDUM Date: October 1, 12014 To: Boise Public Works Commission From: Anthony Perreira, P.E., Project Manager Subject: Energy Consumption at Major Facilities Managed by Public Works This

More information

INTEROFFICE MEMORANDUM

INTEROFFICE MEMORANDUM INTEROFFICE MEMORANDUM Date: February 5, 2014 To: Boise Public Works Commission From: Anthony Perreira, P.E., Project Manager Subject: Energy Consumption at Major Facilities Managed by Public Works This

More information

Role of Entrant s Firm. »» Final Design»» Completion of Funding. »» Engineering Services During Applications. »» Plant Startup and Filtration

Role of Entrant s Firm. »» Final Design»» Completion of Funding. »» Engineering Services During Applications. »» Plant Startup and Filtration ROLE OF OTHERS For the design focus of the project, key partners included:»» Mortenson Construction, Contractor»» Jacobs, Contract Plant Operator»» Portland Engineering and Controls, I&C The City of The

More information

Pre-RFP Meeting for Integrated Wastewater Treatment Plant Master Plan (MWWTP Master Plan) Presentation to Interested Parties. September 13, 2018

Pre-RFP Meeting for Integrated Wastewater Treatment Plant Master Plan (MWWTP Master Plan) Presentation to Interested Parties. September 13, 2018 Pre-RFP Meeting for Integrated Wastewater Treatment Plant Master Plan (MWWTP Master Plan) Presentation to Interested Parties September 13, 2018 Agenda Opening remarks Eileen White, Director of Wastewater

More information

Additional information summarizing the alternatives and development of this recommendation by staff is attached.

Additional information summarizing the alternatives and development of this recommendation by staff is attached. Date: July 5, 206 To: Public Works Commission From: John Tensen Subject: Lander Street Contract Delivery Strategy Issue Public Works Commission recommendation for approval to proceed with a Construction

More information

City of Ames. Water Pollution Control. Long Range Facility Plan

City of Ames. Water Pollution Control. Long Range Facility Plan City of Ames Water Pollution Control Long Range Facility Plan Introduction Over 25 years ago, the City of Ames last completed a Wastewater Facility Plan. That Facility Plan prompted design and construction

More information

Capital Improvement Plan Update:

Capital Improvement Plan Update: Board of Supervisors Meeting Carson City Public Works Department Capital Improvement Plan Update: Wastewater Collection, Treatment and Reuse March 14, 2013 Topics of Discussion Regionalization Existing

More information

Operating Experience with Ostara Struvite Harvesting Process

Operating Experience with Ostara Struvite Harvesting Process Operating Experience with Ostara Struvite Harvesting Process Authors: Steve Reusser 1, Alan Grooms 1, Aaron Dose 1, Ahren Britton 2, Ram Prasad 2 1. Madison Metropolitan Sewerage District 2. Ostara Nutrient

More information

VILLAGE OF ALGONQUIN 2014 WASTEWATER FACILITY PLAN UPDATE EXECUTIVE SUMMARY

VILLAGE OF ALGONQUIN 2014 WASTEWATER FACILITY PLAN UPDATE EXECUTIVE SUMMARY EXECUTIVE SUMMARY EXECUTIVE SUMMARY INTRODUCTION AND BACKGROUND The Village of Algonquin, located along the Fox River in McHenry County, provides wastewater collection and treatment services to the entire

More information

Wastewater Treatment Plant Facilities Plan Update

Wastewater Treatment Plant Facilities Plan Update Newberg City Council Meeting July 16, 2007 3/24/2009 1 Last WWTP Facilities Plan dated 1985 Current WWTP dates from 1987 Various minor improvements and upgrades of the plant have occurred over the last

More information

Water / Wastewater Fund

Water / Wastewater Fund WATER/WASTEWATER FUND The Water/Wastewater Fund is used to account for the provision of water and wastewater services to residents of the City. All activities necessary to provide water/ wastewater services

More information

APPENDIX A. 1. Background. 1.1 Existing Facilities. Page 1

APPENDIX A. 1. Background. 1.1 Existing Facilities. Page 1 APPENDIX A PRELIMINARY TECHNICAL SPECIFICATIONS FOR BIOSOLIDS MANAGEMENT SERVICES JEA Buckman Residuals Management Facility 1. Background JEA is seeking biosolids management services from experienced biosolids

More information

Orange County Utilities ANNUAL BIOSOLIDS REPORT

Orange County Utilities ANNUAL BIOSOLIDS REPORT Orange County Utilities 2011 ANNUAL BIOSOLIDS REPORT Introduction Orange County Utilities (OCU) provides water, wastewater, and solid waste services to the unincorporated areas of Orange County, Florida.

More information

Post-Aerobic Digester with Bioaugmentation Pilot Study City of Meridian, ID WWTP PNCWA 2010

Post-Aerobic Digester with Bioaugmentation Pilot Study City of Meridian, ID WWTP PNCWA 2010 Post-Aerobic Digester with Bioaugmentation Pilot Study City of Meridian, ID WWTP by: William Leaf Adrienne Menniti Bruce Johnson CH2M HILL, Inc. Clint Dolsby Tracy Crane City of Meridian October 26, 21

More information

DC WATER CAPITAL IMPROVEMENT PROGRAM (CIP)

DC WATER CAPITAL IMPROVEMENT PROGRAM (CIP) DC WATER CAPITAL IMPROVEMENT PROGRAM (CIP) District of Columbia Water and Sewer Authority of Maryland Thursday, April 7, 2016 George S. Hawkins, General Manager Presented by: Liliana Maldonado, Director,

More information

AGENDA LOVELAND CITY COUNCIL STUDY SESSION TUESDAY, JULY 14, 2015 CITY COUNCIL CHAMBERS 500 EAST THIRD STREET LOVELAND, COLORADO

AGENDA LOVELAND CITY COUNCIL STUDY SESSION TUESDAY, JULY 14, 2015 CITY COUNCIL CHAMBERS 500 EAST THIRD STREET LOVELAND, COLORADO AGENDA LOVELAND CITY COUNCIL STUDY SESSION TUESDAY, JULY 14, 2015 CITY COUNCIL CHAMBERS 500 EAST THIRD STREET LOVELAND, COLORADO The City of Loveland is committed to providing an equal opportunity for

More information

The TRA CRWS Master Plan. Past, Present, & Future of CRWS. Kaylee Dusek, EIT, Garver Matt Jalbert, PE, TRA

The TRA CRWS Master Plan. Past, Present, & Future of CRWS. Kaylee Dusek, EIT, Garver Matt Jalbert, PE, TRA The TRA CRWS Master Plan Past, Present, & Future of CRWS Kaylee Dusek, EIT, Garver Matt Jalbert, PE, TRA TRA operates the largest water resource recovery facility in Texas CRWS N Dallas CRWS currently

More information

Solids Master Plan Briefing June 22, 2017

Solids Master Plan Briefing June 22, 2017 Solids Master Plan Briefing June 22, 2017 Meeting Agenda Review of Master Plan Process Status Update Technology Selection Budget & Next Steps Discussion Review of Master Plan Process Master Plan Process

More information

~~~~ WWTP Master Plan Project

~~~~ WWTP Master Plan Project ~~~~ WWTP Master Plan Project City Council - April 7, 2014 WWTP History and Issues Constructed in 1994 Aging mechanical equipment - Frequent equipment failures - Resulted in TCEQ permit violations - High

More information

City of Pocatello Water Pollution Control. Collections Systems, Operations, Maintenance, Laboratory and Pretreatment

City of Pocatello Water Pollution Control. Collections Systems, Operations, Maintenance, Laboratory and Pretreatment City of Pocatello Water Pollution Control Collections Systems, Operations, Maintenance, Laboratory and Pretreatment WPC Mission statement To collect and treat wastewater at the lowest practical cost while

More information

ES.1 Solids Master Planning Background and Goals

ES.1 Solids Master Planning Background and Goals Executive Summary The Arlington County Water Pollution Control Plant (WPCP) treats incoming wastewater flows for residents, businesses, and government agencies in the Arlington County sewer service area

More information

Lucas County Sanitary Engineer 2015 Strategic Plan

Lucas County Sanitary Engineer 2015 Strategic Plan Lucas County Sanitary Engineer 2015 Strategic Plan MISSION Defines scope of responsibilities and expectations of the desired level of service TO PROVIDE CUSTOMERS WITH HIGH QUALITY, SAFE, COST EFFECTIVE

More information

Comprehensive Biosolids and Bioenergy Planning Authors: Cameron Clark* 1, Irina Lukicheva 1, Anna James 1, Kathy Rosinski 1, Dave Parry 1

Comprehensive Biosolids and Bioenergy Planning Authors: Cameron Clark* 1, Irina Lukicheva 1, Anna James 1, Kathy Rosinski 1, Dave Parry 1 Comprehensive Biosolids and Bioenergy Planning Authors: Cameron Clark* 1, Irina Lukicheva 1, Anna James 1, Kathy Rosinski 1, Dave Parry 1 1 CH2M *Email: Cameron.Clark@ch2m.com KEYWORDS: biosolids, bioenergy,

More information

Wastewater Collection System Infrastructure Condition Update

Wastewater Collection System Infrastructure Condition Update Wastewater Collection System Infrastructure Condition Update Planning Committee May 12, 2015 Agenda Background Condition Assessment Findings Gravity Interceptors Force Mains Pump Stations Phased Capital

More information

WASSTRIP (Waste Activated Sludge. Stripping to Remove Internal. Phosphorus) complements Ostara s. Pearl nutrient recovery process in

WASSTRIP (Waste Activated Sludge. Stripping to Remove Internal. Phosphorus) complements Ostara s. Pearl nutrient recovery process in WASSTRIP (Waste Activated Sludge Stripping to Remove Internal Phosphorus) complements Ostara s Pearl nutrient recovery process in bio-p plants by releasing magnesium, potassium and phosphate before it

More information

Massachusetts Water Resources Authority Update on 2018 Water and Wastewater Master Plan

Massachusetts Water Resources Authority Update on 2018 Water and Wastewater Master Plan Massachusetts Water Resources Authority Update on 2018 Water and Wastewater Master Plan February 12, 2019 Background 33 Years of MWRA Capital Investment FY86 18 $8.3 Billion Capital Spending 70% on Wastewater

More information

Sewer Facilities 102. Hampstead Sewer Service Area. Carroll County Water & Sewer Master Plan. Current Conditions

Sewer Facilities 102. Hampstead Sewer Service Area. Carroll County Water & Sewer Master Plan. Current Conditions Sewer Facilities 102 Hampstead Sewer Service Area Current Conditions Carroll County owns and operates the public sewer system that serves both the Town of Hampstead and adjoining areas in the county. The

More information

Update on Biosolids Regulatory & Market Trends. Michael D. Moore HDR Engineering, Inc.

Update on Biosolids Regulatory & Market Trends. Michael D. Moore HDR Engineering, Inc. Update on Biosolids Regulatory & Market Trends SARBS 2011 Michael D. Moore HDR Engineering, Inc. September 13, 2011 Agenda 1. Biosolids 101 2. Regulatory Trends 3. Market Trends 4. Perception & Reality

More information

Water / Wastewater Fund

Water / Wastewater Fund WATER/WASTEWATER FUND The Water/Wastewater Fund is used to account for the provision of water and wastewater services to residents of the City. All activities necessary to provide water/ wastewater services

More information

Honorable Mayor and Members of the City Council. Contract: Andes Construction, Inc. for Sanitary Sewer Manhole Rehabilitation FY 2014 Phase 1 Project

Honorable Mayor and Members of the City Council. Contract: Andes Construction, Inc. for Sanitary Sewer Manhole Rehabilitation FY 2014 Phase 1 Project Office of the City Manager CONSENT CALENDAR October 15, 2013 To: From: Honorable Mayor and Members of the City Council Christine Daniel, City Manager Submitted by: Andrew Clough, Director, Public Works

More information

Water / Wastewater Fund

Water / Wastewater Fund WATER/WASTEWATER FUND The Water/Wastewater Fund is used to account for the provision of water and wastewater services to residents of the City. All activities necessary to provide water/ wastewater services

More information

COMMISSION MEETING. April 18, Engineering and Construction Team. Piscataway WWTP Bio-Energy Commissioners Status Briefing

COMMISSION MEETING. April 18, Engineering and Construction Team. Piscataway WWTP Bio-Energy Commissioners Status Briefing COMMISSION MEETING April 18, 2018 Engineering and Construction Team Piscataway WWTP Bio-Energy Commissioners Status Briefing Item Number: Table of Contents 1. Commission Summary P. 1-2 2. Presentation

More information

Frequently Asked Questions

Frequently Asked Questions Why is the City doing this project? The wastewater treatment plant at Post Point is designed to remove solids from our sewage so the water can be cleaned before discharging it into Bellingham Bay. Currently

More information

EGANVILLE SEWAGE SYSTEM 2013 PERFORMANCE REPORT

EGANVILLE SEWAGE SYSTEM 2013 PERFORMANCE REPORT EGANVILLE SEWAGE SYSTEM 2013 PERFORMANCE REPORT Township of Bonnechere Valley Water and Sewage Department January 2014 Table of Contents Executive Summary... 3 Introduction... 4 Report Availability...

More information

Wastewater Treatment Works and Collections System Annual Report Year 2005 General Information

Wastewater Treatment Works and Collections System Annual Report Year 2005 General Information Wastewater Treatment Works and Collections System Annual Report Year 2005 General Information Facility / System: Town of Farmville Wastewater Collection System and Treatment Facilities Responsible Entity:

More information

Study Session Wastewater Enterprise, Proposed Improvement Projects and Projected Funding Needs Update

Study Session Wastewater Enterprise, Proposed Improvement Projects and Projected Funding Needs Update Study Session Wastewater Enterprise, Proposed Improvement Projects and Projected Funding Needs Update February 24, 2015 Overview Wastewater Collection System Customer Base 16,276 SFR 1,968 MFR 1,364 COM/IND

More information

SUMMARY OF TRANSMISSION INTEGRITY MANAGEMENT PROGRAM

SUMMARY OF TRANSMISSION INTEGRITY MANAGEMENT PROGRAM Page 1 of 6 SUMMARY OF TRANSMISSION INTEGRITY MANAGEMENT PROGRAM Program Overview: The Company s Transmission Integrity Management Program ( TIMP ) was established to comply with federal TIMP regulations

More information

Chapter 2: Description of Treatment Facilities

Chapter 2: Description of Treatment Facilities 2020 Facilities Plan Treatment Report 2.1 Introduction Chapter 2: Description of Treatment Facilities This chapter defines the Milwaukee Metropolitan Sewerage District (MMSD) service area. It also describes

More information

Wisconsin Wastewater Operators Association October 4 th 7 th LaCrosse, WI

Wisconsin Wastewater Operators Association October 4 th 7 th LaCrosse, WI Wisconsin Wastewater Operators Association October 4 th 7 th LaCrosse, WI Alan L. Grooms, P.E. Process & Research Engineer Madison Metropolitan Sewerage District Why do we care about phosphorus release?

More information

Little Patuxent WRP 8 th Addition - Biosolids Processing Facilities Improvements

Little Patuxent WRP 8 th Addition - Biosolids Processing Facilities Improvements Little Patuxent WRP 8 th Addition - Biosolids Processing Facilities Improvements CMAA Presentation April 19, 2017 2014 HDR, Inc., all rights reserved. Introductions Joshua Gliptis, P.E. Howard County Bureau

More information

Nitrogen and Phosphorus Harvesting and Reuse

Nitrogen and Phosphorus Harvesting and Reuse October 19, 2017 Nitrogen and Phosphorus Harvesting and Reuse MWEA Sustainable Energy Seminar Agenda What is struvite and why recover it? Technologies for struvite recovery AirPrex piloting case studies

More information

sewers ANd storm drains Storm Drain Under Construction, 1916

sewers ANd storm drains Storm Drain Under Construction, 1916 sewers ANd storm drains Storm Drain Under Construction, 1916 A d o p t e d C A p I t A L I M p R o V e M e N t p R o G R A M F I s C A L Y e A R 2 1 9 FY 219-223 Capital Improvement Program FY 218 FY 219

More information

About the RRC. February

About the RRC. February Resource Recovery Centre (RRC) and Conveyance Pipe About the RRC Siting of the RRC Resource Recovery and Biosolids Management Odour, Noise, Traffic and Safety About the Residual Solids Pipe Spill Protection

More information

Honorable Mayor and Members of the City Council

Honorable Mayor and Members of the City Council Office of the City Manager CONSENT CALENDAR October 15, 2013 To: From: Honorable Mayor and Members of the City Council Christine Daniel, City Manager Submitted by: Andrew Clough, Director, Public Works

More information

Why THP Made Sense for TRA

Why THP Made Sense for TRA Why THP Made Sense for TRA June 16, 2016 Central Regional Wastewater System Treatment Plant (CRWS) CRWS Solids Treatment Area 2 162-mgd ADF permitted and 125- mgd average daily flows Pre-THP Solids Process:

More information

NUTRIENT TRADING AND PERMITTING

NUTRIENT TRADING AND PERMITTING COLORADO WATER QUALITY FORUM NUTRIENT TRADING AND PERMITTING Dave Akers Barbara Biggs, Roxborough Water & Sanitation District David L. Clark, HDR Engineering, Inc. (dclark@hdrinc.com) May 21, 2018 2014

More information

Defining the Benefits of Harvesting Phosphorus from Dewatering Filtrate

Defining the Benefits of Harvesting Phosphorus from Dewatering Filtrate Defining the Benefits of Harvesting Phosphorus from Dewatering Filtrate Cameron Clark, PE CDM Smith August 1, 2013 Agenda Des Moines WRA Background Plant Nutrient Balance Nutrient Issues P Removal Technology

More information

HOW TO SAVE COSTS AND IMPROVE SUSTAINABILITY WHILE REDUCING EFFLUENT NITROGEN

HOW TO SAVE COSTS AND IMPROVE SUSTAINABILITY WHILE REDUCING EFFLUENT NITROGEN HOW TO SAVE COSTS AND IMPROVE SUSTAINABILITY WHILE REDUCING EFFLUENT NITROGEN Introduction Donna Kaluzniak, CEP, Utility Director, City of Atlantic Beach, Florida John E. Collins, Jr., P.E., J. Collins

More information

WHEREAS, the Board has previously so adopted a wastewater supply system comprehensive plan, and

WHEREAS, the Board has previously so adopted a wastewater supply system comprehensive plan, and LAKEHAVEN WATER AND SEWER DISTRICT King County, Washington Resolution No. 2017-1283 A RESOLUTION of the Board of Commissioners of the Lakehaven Water and Sewer District, King County, Washington, adopting

More information

Capital Investment Plan (CIP) Quarterly Report for the period ending December 2013

Capital Investment Plan (CIP) Quarterly Report for the period ending December 2013 Report Engineering Services Group Capital Investment Plan (CIP) Quarterly Report for the period ending December 2013 Summary This report provides a summary of fiscal year accomplishments, capital expenditures

More information

INTEROFFICE MEMORANDUM

INTEROFFICE MEMORANDUM INTEROFFICE MEMORANDUM DATE: April 24, 29 TO: Boise Public Works Commission FROM: Matt Hightree, civil engineer SUBJECT: Energy Consumption at Major Facilities Managed by Public Works This report contains

More information

Sausalito-Marin City Sanitary District Strategic Plan

Sausalito-Marin City Sanitary District Strategic Plan Sausalito-Marin City Sanitary District 2013-2018 Strategic Plan 0 Governing Board of Directors Raymond G. Gergus, President William F.H. Ring, Vice President Ann Arnott Donald L. Beers Dan Rheiner 2013

More information

INTEROFFICE MEMORANDUM

INTEROFFICE MEMORANDUM INTEROFFICE MEMORANDUM DATE: October 23, 29 TO: Boise Public Works Commission FROM: Matt Hightree, Civil Engineer SUBJECT: Energy Consumption at Major Facilities Managed by Public Works This memo is presented

More information

The alternatives addressed in this EIR were selected in consideration of one or more of the following factors:

The alternatives addressed in this EIR were selected in consideration of one or more of the following factors: CHAPTER 5 Project Alternatives 5.1 Introduction The purpose of the alternatives analysis in an environmental impact report (EIR) is to describe a range of reasonable alternatives to the project that could

More information

Solids Master Plan Briefing October 27, 2016

Solids Master Plan Briefing October 27, 2016 Solids Master Plan Briefing October 27, 2016 Meeting Agenda Review of Project/Stakeholder Meeting Role Update on Master Plan: Evaluating Technologies Financial Planning/Budgeting Process Next Steps Questions

More information

Leveraging Energy Audits to Effect Cultural Changes and Long-Term Energy Savings

Leveraging Energy Audits to Effect Cultural Changes and Long-Term Energy Savings Leveraging Energy Audits to Effect Cultural Changes and Long-Term Energy Savings Rich Atoulikian, PMP, P.E. Kim Kennedy, P.E. OWEA 2012 June 2012 Outline Background Energy Consumption/Savings Opportunities

More information

TABLE OF CONTENTS. WRA09x 21 Combined Sewer Solids Separation Core Bond Funds WRA09x 22 Nutrient Removal - WRF Core Bond Funds

TABLE OF CONTENTS. WRA09x 21 Combined Sewer Solids Separation Core Bond Funds WRA09x 22 Nutrient Removal - WRF Core Bond Funds TABLE OF CONTENTS Project Descr Funding WRA072 5 Aeration Blowers - WRF R&R WRA094 19 Asset Management - WRF FY 2005,06 WRA073 6 Dewatering / Thickening System - WRF R&R WRA074 7 Digester Gas System -

More information

Honorable Mayor and Members of the City Council. Contract: Andes Construction, Inc. for Sanitary Sewer Rehabilitation Project on Woolsey Street

Honorable Mayor and Members of the City Council. Contract: Andes Construction, Inc. for Sanitary Sewer Rehabilitation Project on Woolsey Street Office of the City Manager CONSENT CALENDAR October 1, 2013 To: From: Honorable Mayor and Members of the City Council Christine Daniel, City Manager Submitted by: Andrew Clough, Director, Public Works

More information

COMMISSION MEETING. June 21, Engineering and Construction Team. Piscataway WWTP Bio-Energy Commissioners Status Briefing

COMMISSION MEETING. June 21, Engineering and Construction Team. Piscataway WWTP Bio-Energy Commissioners Status Briefing COMMISSION MEETING June 21, 2017 Engineering and Construction Team Piscataway WWTP Bio-Energy Commissioners Status Briefing Item Number: Table of Contents 1. Commission Summary P.1 2. Presentation P. 2-24

More information

Sometimes Being Faced With A Challenge Can Lead To Greater Opportunities

Sometimes Being Faced With A Challenge Can Lead To Greater Opportunities Sometimes Being Faced With A Challenge Can Lead To Greater Opportunities Making the Case for Energy Savings Performance Contracting at the Opequon Water Reclamation Facility Frederick-Winchester Service

More information

MDEQ Update Focus on Sustainability

MDEQ Update Focus on Sustainability MDEQ Update Focus on Sustainability MWEA October 18, 2018 Water Resources Division, MDEQ Detroit River Lighthouse, photo courtesy of the Friends of the Detroit River Water Resources Protect and Monitor

More information

6 WASTEWATER. 6.1 Overview. 6.2 Darvill Wastewater Works

6 WASTEWATER. 6.1 Overview. 6.2 Darvill Wastewater Works 6 WASTEWATER 6.1 Overview Umgeni Water currently owns and operates the Darvill and Ixopo Wastewater Works (WWWs). It also operates the Howick WWW for umgungundlovu District Municipality under a management

More information

Meridian s Class A Recycled Water Program

Meridian s Class A Recycled Water Program Meridian s Class A Recycled Water Program 2016 PNWS Conference - Boise May 5, 2016 Clint Dolsby, PE City of Meridian Assistant City Engineer Recycled Water Defined Highly treated wastewater effluent for

More information

Center Sanitation District

Center Sanitation District EHLS Center Sanitation District EHLS Engineering Erik Jorgensen Suzanne Givler Heath Anderson Leryn Gorlitsky Outline of Presentation Background Current and Future Conditions Decision Matrix Description

More information

BIDS WILL BE CONSIDERED NON-RESPONSIVE WITHOUT THE REQUIRED SIGNATURE ACKNOWLEDGING THE FOLLOWING:

BIDS WILL BE CONSIDERED NON-RESPONSIVE WITHOUT THE REQUIRED SIGNATURE ACKNOWLEDGING THE FOLLOWING: BID SHEET FOR CIP 17-101 CIPP LINING OF SANITARY SEWER SYSTEM Item No. 16 17 18 19 20 21 Description and Bid Unit Price Brim Style Service Line Connection Sealing System Temporary Bypass Facilities Set

More information

OWEA Annual Technical Conference and Exhibition Upgrading WRFs for Biological Nutrient Removal. June 25, 2015

OWEA Annual Technical Conference and Exhibition Upgrading WRFs for Biological Nutrient Removal. June 25, 2015 OWEA Annual Technical Conference and Exhibition Upgrading WRFs for Biological Nutrient Removal June 25, 2015 Agenda Permitting and Planning BNR Overview Case Example Innovative Approaches Proactive Participation

More information

WASTEWATER DEPARTMENT. Bentonville Wastewater Treatment Plant Facts:

WASTEWATER DEPARTMENT. Bentonville Wastewater Treatment Plant Facts: Mission: The mission of the Bentonville Wastewater Treatment Utility and staff is to protect public health and the environment through the effective treatment of wastewater. Effective wastewater treatment

More information

Total Makeover for Biosolids Handling at DC Water s Blue Plains Advanced Wastewater Treatment Plant. February 2015

Total Makeover for Biosolids Handling at DC Water s Blue Plains Advanced Wastewater Treatment Plant. February 2015 Total Makeover for Biosolids Handling at DC Water s Blue Plains Advanced Wastewater Treatment Plant February 2015 Today s Makeover Will Include Recent History of Blue Plains Solid Handling Processes Evolution

More information

SSO- WDR Compliance Workshop Electronic Reporting: Reporting Requirements & Tips. Sewer System Management Plan Chapter

SSO- WDR Compliance Workshop Electronic Reporting: Reporting Requirements & Tips. Sewer System Management Plan Chapter Chapter Contents Introduction SSMP Requirements and Suggested Content SSMP Preparation Deadlines Introduction This chapter provides a brief overview of the GWDR requirements for an SSMP and provides some

More information

Massachusetts Water Resources Authority. Water and Wastewater System. Briefing to WSCAC and WAC

Massachusetts Water Resources Authority. Water and Wastewater System. Briefing to WSCAC and WAC Massachusetts Water Resources Authority 2013 MWRA Master Plan Water and Wastewater System Briefing to WSCAC and WAC November 19, 2013 Presentation Outline Introduction Water System Wastewater System 2

More information

Engineering Department Wastewater Treatment

Engineering Department Wastewater Treatment Engineering Department Wastewater Treatment Prepared by: Rich Davidson, Director Assisted by: Mary Phelps Verle Holland Steven Tam Andy Yeung Gina De la Torre Serenity Cummings Engineering Department Wastewater

More information

AECOM Amendment 2. Thien Ng Interim Public Works Director. December 13, 2017

AECOM Amendment 2. Thien Ng Interim Public Works Director. December 13, 2017 AECOM Amendment 2 Thien Ng Interim Public Works Director December 13, 2017 AECOM Agreements to be Combined Public Works Department On-Call Engineering Services $250,000 Increase $250,000 Existing Water

More information

Masses at Massillon: IFAS for Industrial Loads and Nutrient Removal

Masses at Massillon: IFAS for Industrial Loads and Nutrient Removal OWEA Annual Conference, Sandusky, OH, Wednesday, June 24, 3:00-3:45 PM Masses at Massillon: IFAS for Industrial Loads and Nutrient Removal Kristin Waller, O Brien & Gere Kristin.Waller@obg.com #obgpresents

More information

SUBJECT: SEE BELOW DATE: June 1,2016

SUBJECT: SEE BELOW DATE: June 1,2016 SAN IPSE COUNCIL AGENDA: 06/14/16 ITEM: Memorandum CITY OF, CAPITAL OF SILICON VALLEY TO: HONORABLE MAYOR AND CITY COUNCIL FROM: Kerrie Romanow SUBJECT: SEE BELOW DATE: June 1,2016 Approved ( 2 \ SUBJECT:

More information

Project Name: Central WWTP Capacity Improvements and CSO Reduction Project. MWS Project Number: 14-SC-0153 Last Updated: 12/19/14

Project Name: Central WWTP Capacity Improvements and CSO Reduction Project. MWS Project Number: 14-SC-0153 Last Updated: 12/19/14 Project Name: Central WWTP Capacity Improvements and CSO Reduction Project MWS Project Number: 14-SC-0153 Last Updated: 12/19/14 BACKGROUND / PURPOSE Metro Water Services (MWS), in order to comply with

More information

Watertown Wastewater Facility Plan. August 11, 2015

Watertown Wastewater Facility Plan. August 11, 2015 Watertown Wastewater Facility Plan August 11, 2015 Watertown Wastewater Wastewater Treatment Facility History Comprehensive Planning Wastewater Concerns Capacity Condition Permitting Requirements Watertown

More information

City of Columbus Wet Weather Management Plan Update. Dax J. Blake, P.E. Administrator City of Columbus, Ohio Division of Sewerage and Drainage

City of Columbus Wet Weather Management Plan Update. Dax J. Blake, P.E. Administrator City of Columbus, Ohio Division of Sewerage and Drainage City of Columbus Wet Weather Management Plan Update Dax J. Blake, P.E. Administrator City of Columbus, Ohio Division of Sewerage and Drainage City of Columbus, Ohio Population served ~ 1 Million 22 satellite

More information

SEWER CITY AND BOROUGH MANAGER'S OFFICE. PUBLIC WORKS DEPARTMENT Ernie Mueller, Director WASTEWATER UTILITY SUPERINTENDENT.

SEWER CITY AND BOROUGH MANAGER'S OFFICE. PUBLIC WORKS DEPARTMENT Ernie Mueller, Director WASTEWATER UTILITY SUPERINTENDENT. MISSION STATEMENT Our mission is to enhance the health and quality of life for the City and Borough of Juneau Wastewater Utility Division s customers by providing them an effective efficient system for

More information

6.2 Umgeni Water Owned Wastewater Works

6.2 Umgeni Water Owned Wastewater Works 6. WASTEWATER 6.1 Overview Umgeni Water owns and operates the Darvill and Ixopo Wastewater Works (WWW), but manages a number of other WWW on behalf of Municipalities. Management contracts are in place

More information

Energy Optimized Resource Recovery Project Presented By: Curtis Czarnecki, P.E.

Energy Optimized Resource Recovery Project Presented By: Curtis Czarnecki, P.E. Kenosha Wastewater Treatment Plant Energy Optimized Resource Recovery Project Presented By: Curtis Czarnecki, P.E. Kenosha Water Utility March 22, 2016 WWTP Service Area Overview Population: 110,000 Service

More information

Consent Decree Semiannual Report September 30, 2011 Consent Decree No. 2:11-cv EJM

Consent Decree Semiannual Report September 30, 2011 Consent Decree No. 2:11-cv EJM Consent Decree Semiannual Report September 30, 2011 Consent Decree No. 2:11-cv-01011-EJM Prepared for: UNITED STATES ENVIRONMENTAL PROTECTION AGENCY, UNITED STATES DEPARTMENT OF JUSTICE AND IOWA DEPARTMENT

More information

CASE STUDY - A Tale of Two industries Pretreatment of Confectionary and Bakery Wastewaters

CASE STUDY - A Tale of Two industries Pretreatment of Confectionary and Bakery Wastewaters CASE STUDY - A Tale of Two industries Pretreatment of Confectionary and Bakery Wastewaters Silas W. Givens Project Engineer-Industrial Processes and James K. Cable, P.E. Department Manager--Industrial

More information

Sanitary Sewer Fees 101. November 27, 2018

Sanitary Sewer Fees 101. November 27, 2018 Sanitary Sewer Fees 101 November 27, 2018 Background The City of Sausalito owns and operates a sewer collection system conveying wastewater to the Sausalito Marin-City Sanitary District (SMCSD) for treatment

More information

2015 HDR, Inc., all rights reserved.

2015 HDR, Inc., all rights reserved. 2015 HDR, Inc., all rights reserved. Hastings Utilities Water Pollution Control Facility Improvements Brian Bakke, HDR ASCE Environmental Conference 4/6/2017 Review Existing Facilities Need for the Project

More information

Public Information Centre No. 1

Public Information Centre No. 1 Public Information Centre No. 1 City of Timmins Schedule B Class Environmental Assessment for the WHITNEY TISDALE SANITARY SYSTEM UPGRADES Welcome Please Sign In Class EA Process & Public Consultation

More information

Mayo Sewer System. Chris Phipps, P.E., Director Jia Liu, Acting Utility Administrator, Central Maintenance Victor Kibec, Senior Engineer

Mayo Sewer System. Chris Phipps, P.E., Director Jia Liu, Acting Utility Administrator, Central Maintenance Victor Kibec, Senior Engineer Mayo Sewer System Chris Phipps, P.E., Director Jia Liu, Acting Utility Administrator, Central Maintenance Victor Kibec, Senior Engineer Department of Public Works History of Mayo Service Area Geographical

More information

BRACEBRIDGE WASTEWATER TREATMENT 2016 SUMMARY REPORT

BRACEBRIDGE WASTEWATER TREATMENT 2016 SUMMARY REPORT BRACEBRIDGE WASTEWATER TREATMENT 2016 SUMMARY REPORT ENVIRONMENTAL COMPLIANCE APPROVAL: 6801-7VKNAQ ENVIRONMENTAL COMPLIANCE APPROVAL: 6222-AFGSNY (Dec 16 2016) INTRODUCTION The Lagoon Lane Wastewater

More information

Performance Evaluation of the Moores Creek Advanced Water Resource Recovery Facility

Performance Evaluation of the Moores Creek Advanced Water Resource Recovery Facility Performance Evaluation of the Moores Creek Advanced Water Resource Recovery Facility Richard W. Gullick, Ph.D. Director of Operations Timothy Castillo Wastewater Manager Presented to the Albemarle County

More information

Mill Slough Water Quality Plan Description

Mill Slough Water Quality Plan Description Mill Slough Water Quality Plan Description Introduction The City of Middleton ( City ) is engaged in a three-phase plan to significantly improve non-point source surface water quality in the Mill Slough

More information

Polishing Ponds. Biosolids Storage. Ammonia Removal. Digesters. Thickeners. Pretreatment. Final Clarifiers. Primary Clarifiers.

Polishing Ponds. Biosolids Storage. Ammonia Removal. Digesters. Thickeners. Pretreatment. Final Clarifiers. Primary Clarifiers. Wastewater Treatment Facility (2012) Polishing Ponds Biosolids Storage Ammonia Removal Digesters Thickeners Pretreatment Primary Clarifiers Activated Sludge Final Clarifiers OVERVIEW Whenever a home, business,

More information

Joint Biosolids Management Program Performance Report & Biosolids Newsletter

Joint Biosolids Management Program Performance Report & Biosolids Newsletter The City of Albany s Biosolids Quarterly www.cityofalbany.net/biosolids Joint Biosolids Management Program Performance Report & Biosolids Newsletter This is our second joint Biosolids Management Program

More information

Engineering Department

Engineering Department Engineering Department Stormwater Mission: To provide for the efficient and effective cleaning and repair of the stormwater collection system and implement the federally mandated Stormwater Pollution Prevention

More information

Rehoboth Beach Commissioners Meeting Ocean Outfall & Treatment Plant Project Update July 26, Jeff Sturdevant Principal Kelvin George Principal

Rehoboth Beach Commissioners Meeting Ocean Outfall & Treatment Plant Project Update July 26, Jeff Sturdevant Principal Kelvin George Principal Rehoboth Beach Commissioners Meeting Ocean Outfall & Treatment Plant Project Update July 26, 2017 Jeff Sturdevant Principal Kelvin George Principal Rehoboth Beach Ocean Outfall/CIP Project(s) Update Agenda

More information