CONCEPTUAL PLAN & ENVIRONMENTAL MANAGEMENT PLAN

Size: px
Start display at page:

Download "CONCEPTUAL PLAN & ENVIRONMENTAL MANAGEMENT PLAN"

Transcription

1 Promoter : CONCEPTUAL PLAN & ENVIRONMENTAL MANAGEMENT PLAN INTRODUCTION & PROJECT SUMMARY: The proposed project involves construction of Group Housing Project coming up at Khasra No. 76 to 83 83/509, 88/1, 89/2, 81/532, 90/1, 79/530, 89 /1, 80/531, 83/529, 84-85/1, 88 to 90 in Village - Durgapura, Tehsil-Sanganer, Jaipur (Rajasthan). The project is promoted by ARG Developers Private Limited. The net plot area of the project is 39, sq. m. and Gross built up area envisaged for the project is 1,48, sq.m. (> 20,000 sq. m. and < 1,50,000 sq. m.). Thus, the project requires prior Environmental Clearance under Item 8 (a) {Building & Construction projects} of Schedule- EIA Notification 2006 and subsequent amendments thereafter from the State Level Environmental Impact Assessment Authority, Rajasthan. As of now, as there is no duly constituted SEIAA (Rajasthan.), this case is to be dealt at the MoEF&CC. The proposed project will constitute of 2 blocks (Residential & commercial) with 8 towers (7 Residential +1 commercial) comprising of 569 units (2 BHK: 38 nos, 3 BHK: 456 nos. 4 BHK: 75 nos.), Commercial area comprises of offices (7 nos), showrooms (3 nos.). Table: Salient features of the project Items Details Project address Khasra Nos. 76 to 83 83/509, 88/1, 89/2, 81/532, 90/1, 79/530, 89 /1, 80/531, 83/529, 84-85/1, 88 to 90 in Village -Durgapura, Tehsil-Sanganer, Jaipur (Rajasthan). Type of project Screening category Residential Project (Building & Construction). The project is categorized under 'B-2' under item 8(a) of Schedule Gazette Notification dated Sep 14 th, 2006 and subsequent amendments there off. Total Plot area 42, sq. m. Surrendered area sq. m. Net Plot area 39, sq. m. Gross Built up area Ground coverage 1, 48, sq.m. Permissible : 40 % (15, sq. m.)

2 Promoter : Proposed : 19.10% ( sq. m.) Standard BAR Achieved BAR Green Area surrendered area 2.44 ( sq.m.) % (12, sq. m.) Softscape : sq. m. (7.7%) Hardscape (Podium) : sq. m. (24.95 %) Maximum height & number of floors Total number of Dwelling units Details are as under:- Tower No. of Floors Height (in m.) Up to Terrace Level Tower 1-7 B+ S+19 th Floor 60 m Commercial B1+B2+GF+Floor 11.3 m 569 nos. dwelling units 2 BHK : 38 nos. 3BHK 4BHK : 456 nos. : 75 nos. Parking facilities Required ECU : 954 ECUs Power requirement & source Proposed ECU Connected load Maximum demand Source : 1837 ECUs : KW : KW : JVVNL Power backup DG sets of cumulative capacity 1500 kva 500kVA 1000kVA : 1 nos. : 1 nos. Water requirement & source Sewage treatment & disposal Total Water requirement Fresh Water Recycled Water Source Sewage treatment facility STP Technology Sewage discharge : 444 KLD : 210 KLD : 234 KLD : Ground Water Supply : STP of 300 KLD Capacity : MBBR Technology : 262 KLD (drain /supplied to farmers)

3 Promoter : IDENTIFICATION OF THE PROJECT PROPONENTS: ARG Group has been established in Defining & changing lifestyle for thousands of people, ARG Group today is among the leading Realty and Infrastructure Developers of Rajasthan. The Group is known for Integrated Townships, Group Housing, Shopping Malls, Office Spaces and Infrastructure & Utility Services. Legal information: Name of the company Directors : : Mr. Atma Ram Gupta : Mrs. Shashi Gupta Registered address : E-52 Chitranjan Marg, C-scheme, Jaipur, Rajasthan. REGULATORY COMPLIANCE: The project has been duly approved for construction of Group housing Project by Jaipur Development Authority, Jaipur. Patta issued on dated Application for the abstraction of ground water from CGWA is submitted on NOC FROM Airport Authority of India has been obtained on dated LOCATION OF THE PROJECT & INFRASTRUCTURE FACILITIES: The proposed project is coming up at Khasra No. 76 to 83 83/509, 88/1, 89/2, 81/532, 90/1, 79/530, 89 /1, 80/531, 83/529, 84-85/1, 88 to 90 in Village -Durgapura, Tehsil-Sanganer, Jaipur (Rajasthan).

4 Promoter : Fig: Location Map Details of community facilities within a walking distance of 2-3 km from the building entrance: Bank/ ATM Place of Worship Bus Stop Pharmacy School Courier service Grocery store (s) Hardware shop Refueling station for automobiles (petrol pump) Medical clinic/ Hospital Stationary shop Park/ Garden

5 Promoter : Details of other infrastructural facilities (aerial distance): Nearest Railway Station : Durgapura Railway station 0.95 Km towards SW : Jaipur Railway station 6.65 Km towards N Nearest Airport : Jaipur International Airport 3.8 Km towards SSE Fig: Google map

6 Promoter : PROJECT DETAILS: The proposed project will constitute of a 2 block (Residential & commercial) with 7 towers comprising of 569 units (2 BHK: 38 nos, 3 BHK: 456 nos. 4 BHK: 75 nos.), Commercial area comprises of offices (7 nos), showrooms (3 nos.).details are as under:- S. No Particulars No of dwelling units 1. 2 BHK 38 nos BHK 456 nos BHK 75nos. Total 569 nos. Floor wise details Floors Tower 1 Tower 2 Tower 3 Tower 4 Tower 5 Tower 6 Tower 7 Total First Floor Second Floor Third Floor Fourth Floor Fifth Floor Sixth Floor Seventh Floor Eighth Floor Ninth floor Tenth floor Eleventh Floor Twelfth Floor Thirteenth Floor Fourteenth Floor Fifteenth Floor Sixteenth Floor Seventeenth Floor Eighteenth Floor Nineteenth Floor Total

7 Promoter : Particulars Tower 1 Tower 2 Tower 3 Tower 4 Tower 5 Tower 6 Tower 7 Total No of Floors 3BHK 4 BHK 2 BHK 3BHK 2 BHK 3BHK 3BHK 4 BHK 3BHK 4 BHK 3BHK 4 BHK 3BHK dwelling units 1st floor nd floor rrd floor th floor th floor th floor th floor h floor th floor h floor th floor th floor floor th floor th floor floor floor th floor th floor Total

8 Promoter : GROSS BUILT UP AREA DETAILS: Floors Gross BUA B.A.R Residential Stilt Floor Basement ST Floor / Podium Lvl ND Floor RD Floor TH Floor TH Floor TH Floor TH Floor TH Floor TH Floor TH Floor TH Floor TH Floor TH Floor TH Floor TH Floor TH Floor TH Floor TH Floor TH Floor Terrace Total (a) Commercial Basement Basement Ground Floor First Floor Terrace Total (b) Services (c) Grand Total (a-c) 1,48, sq.m. 95, sq. m.

9 Promoter : PARKING REQUIREMENT: Particulars BAR Basis Required ECU Residential sq. ECU/115 sq.m. of BAR area* 817 ECU Visitors (ECU-300) X 10 %* (112) Commercial sq. ECU/75 sq.m. of BAR area* 20 ECU Visitors 25 % of the required ECU* 5 ECU Required ECU Provided ECUs 954 ECU 1465 ECUs *Source: JDA Byelaws 2017 Required ECU : 954 ECUs Provided ECU : 1837 ECUs Details of parking: Particulars Cars Scooters Total ECUS 1 st Basement ( ECU) nd Basement (8 ECU) 28 Stilt Floor Open (303 ECU) 526 Total (637.33ECU) 1837 POWER REQUIREMENT: Power requirement for the proposed project is summarized as under: Source of supply 132 kv JVVNL GSS Electrical Load Connected load : KW Maximum demand : KW Transformer Number 2 Capacity 2500 kva: each DG Sets Number 2 Capacity 500 kva : 1no. 1000kVA :1 no.

10 Promoter : Fuel Used HSD (sulphur content: 0.05%) Fuel Consumption 80 ltr/hr & 161 ltr/hr respectively There will be power backup through DG sets of cumulative capacity of 1500 kva used in case of power cut or failure. DG set will be provided with an effective safe stack height of 66 m for proper dispersion of pollutants that will keep the emissions within the permissible limit. The fuel requirement will be about 80 ltr/hr & 161 ltr/hr respectively of HSD (as and when used). POPULATION PROJECTION: S. No Particulars No of flats Basis Population 1. 2 BHK /Flat BHK person/flat BHK person/flat Visitors - 15 % of residenti 370 Population 4. Commercial sq.m 40 sq.ft/person 1783 CRITERIA OF WATER DEMAND The daily water requirement for the proposed development will be 444 KLD (fresh water: 210 KLD and the recycled/reused water demand: 234 KLD). Criteria of water demand are given as under: Water demand calculation: S. No. Particulars Population Fresh water demand Treated water demand Total water demand 1. Residential lpcd: 160 lpcd: 52 KLD 212 KLD 2. Commercial lpcd: KLD 81 KLD 3. Staff lpcd: 3 2KLD 5 KLD 4. Visitors lpcd: 4 KLD 6 KLD 5. Landscaping & General washing 140KLD 140KLD Total 210 KLD 234 KLD 444 KLD

11 Promoter : WATER BALANCE Fresh water 210 KLD Residential 160 KLD Commercial 45 KLD Staff & Visitors 5KLD KLD Waste water S T Sludge & evaporation losses 26 KLD STP treated water 234 KLD Flushing 94 KLD Landscaping & General washing 140 KLD 94 P Capacity 300 KLD Drain 2 KLD Recycled/ reused for flushing, landscaping & general washing Daily water demand: 444 KLD {210 KLD (fresh) KLD (recycled/ reused water)} Source: Fresh Water: PHED Water Supply Treated Waste water: STP Treated Water LIGHT & ELECTRICITY DETAILS: RECOMMENDED LUX LEVELS: The recommended values of illumination (in Lux) as per the National Building Code of India (2016) are as under: S. No. S pace Illumination Level (Lux) i. Entrance ii. Lifts iii. Corridor, passageways, stairs iv. Covered car par Floor 5-20 Ramp and Corner 30 Entrance and exits v. Outdoor car park 5 20

12 Promoter : IDENTIFICATION, PREDICTION AND EVALUATION OF IMPACTS Environmental impact can be defined as any alteration of environmental conditions, adverse or beneficial, caused or induced by the action or set of actions under consideration. Various operations involved in the project have been studied in details to identify, predict and evaluate impacts on various environmental components. The identified impacts were quantified using mathematical models to a possible extent so as to estimate the future environmental scenario. AIR ENVIRONMENT Air pollution has long been recognized as a brain storming issue worldwide. The onset of technological and scientific innovations in various fields and diverse activities of human race for its elegance have put extra load on the atmosphere by way of releasing air pollutants like particulate matter (PM 10, PM 2.5 ), sulphur dioxide (SO 2 ), oxides of nitrogen (NO X ), carbon monoxide (CO), unburned hydrocarbon (HC) and other organic as well as inorganic pollutants including trace metals responsible for causing health consequences. Entry of pollutants into the atmosphere occurs in the form of gases or particles. Continuous mixing, transformation and transboundary transportation of air pollutants make air quality of a locality unpredictable. The growth of population, industry and number of vehicles and make the problem of air pollution still worse. Rapid industrialization and vehicular traffic especially in the urban areas of India is a great threat to air quality. Instrument Sensitivity: Instrument Respirable Dust Sampler (PM-10) Range and Sensitivity (Other gases) (RDS) m 3 /min ±0.02 m 3 /min 0 3 LPM ± 0.2 LPM Fine Particulate Sampler (PM 2.5) : ±0.03 DGM m 3 CONSTRUCTION PHASE: SOURCES OF POLLUTION: 1. Vehicular Exhaust:

13 Promoter : The major source of pollution in construction phase will be vehicles carrying construction material. Pollution load from the same is calculated as: Pollution Load = No. of trucks Emission Factors Deterioration Factor Due to movement of average 05 trucks short term pollution load is given in table: Parameter Emission Factor Deterioration Factor Pollution Load (g /km)* (g /km)* (g/km) CO NOx SPM SO HC * Source: CPCB Publication, Emissions from Construction equipments: The fugitive dust emission sources are: Excavation Haul road movements Construction Material Handling Finishing Emissions factors for construction equipment are given in table below: Equipment Emissions Factors (g/hr) CO VOC NO X SO X PM 10 Excavator Backhoe/ Front end loader Rubber tired crane Hydraulic Crane Concrete Vibrator Paving Equipment Roller/ Compactor *Source: SCAQMD CEQA Handbook

14 Promoter : MITIGATION MEASURES: S. No. Guidance on Practices to reduce emission 1. Water Application Water will be applied to mitigate dust generation 2. Storage Piles Storage pile activity will be conducted downwind 3. Vehicles & Equipments Enclosures/ coverings will be used for storage piles Speed of vehicles will be reduced to avoid blowing of dust Proper lubrication of vehicles and machinery will be ensured to reduce emissions Engines & exhaust systems will be properly maintained. Low sulphur diesel (HSD) will be used. 4. Material Handling & Transfer systems Idling time will be eliminated/ reduced to the minimum Mud and dirt track-out and carryout will be controlled properly. Material drop will be minimized at the transfer point and enclosure PM emissions from spills will be prevented. Material handling operations will be minimized. 5. Road Surfaces On-site vehicle restrictions will be established. Unpaved roads will be properly maintained. POST CONSTRUCTION PHASE: The emission sources are mainly due to the diesel generator set of cumulative capacity 1500 kva and vehicular emissions. SOURCES OF POLLUTION: A. DG sets: Calculation of stack height of D.G. sets DG Set of capacity 500 kva- 1 no.: The stack height of DG set is calculated as under: H = h+0.2 ( capacity of the DG set in kva) = h+0.2 x ( 500) = h+0.2 x 22.36= 4.47 m = 60 m m = m say 65 m

15 Promoter : B. DG sets: Calculation of stack height of D.G. sets DG Set of capacity 1000 kva- 1 no.: The stack height of DG set is calculated as under: H = h+0.2 ( capacity of the DG set in kva) = h+0.2 x ( 1000) = h+0.2 x 31.32= 6.3 m = 60 m m = 66.3 m say 66 m However, a safe stack height of 66 m above the roof of DG house will be provided. C. Vehicular exhausts: Parameter Emission rate per ECU (g/sec/m) NOx 1.17 x 10-6 CO 1.46 x10-5 Emission Norms for 2/3 wheeler Norms CO( g/km) HC+ NOx)(g/km) 1991Norms (only HC) 1996 Norms India stage 2000 norms Bharat stage-ii Bharat Stage-III Emission Norms for passenger cars Norms CO( g/km) HC+ NOx)(g/km) 1991Norms (only HC) 1996 Norms Norms India stage 2000 norms Bharat stage-ii Bharat Stage-III Bharat Stage-IV Source: CPCB Emission norms

16 Promoter : MANAGEMENT PLAN SOURCES Exhaust from D.G. sets of cumulative capacity 1500 kva MANAGEMENT D.G. sets will be provided with effective stack height of 66 m will be provided. Low-sulphur-content fuel (HSD - Sulphur content 0.05%) will be used. Vehicular exhausts Sufficient width of driveways to ensure smooth traffic movements. especially congestions during peak traffic hours. Provisions of fully internalized parking including the parking facilities for the visitors. Guided traffic ways within the project site. Speed humps will be installed for speed restrictions inside the project area. WATER ENVIRONMENT:- CONSTRUCTION PHASE: WATER CONSERVATION TECHNIQUES: Best construction practices will be adopted to reduce the water demand for construction activities: Use of curing water: Spraying of curing water and after liberal curing, all concrete structures will be covered with gunny bags, followed by spraying of water. Use of polymer dispersion and air entraining agents to reduce the construction water demand. Admixtures will be used to reduce water demand during construction. Discouraging the washing of vehicles and equipment on the construction site. Workers will not allow to wash their personal vehicles on site. Vehicles and equipment that regularly leave the construction site should be washed offsite. MANAGEMENT PLAN: SOURCES Generation of sewerage MANAGEMENT Temporary septic tank followed by soak-pit will be provided. Un-captured run-off The rain-water entering into the pit will be screened for the removal of from the site may heavy silt and other materials. contaminate water aquifers. ground Provisions will be made to ensure the construction vehicles stick to the access track to prevent mud & dirt being deposited on roads.

17 Promoter : Fence will be constructed around the site to trap sediments whilst allowing the water to flow through. Up slope water will be diverted with turf and due care will be taken not to mix mortar in locations that will drain into storm water system. Unsanitary conditions The civil contractor will be made responsible for site sanitation and will during rainy season. be bound by the management to adhere to healthy level of sanitation. There will be no stagnant water at site, as the runoff from the relevant areas will be systematically drained into the storm water line. There will be provision of cleaning the storm water line periodically. POST CONSTRUCTION PHASE: Daily water demand will be 444 KLD (fresh: 210 KLD + recycled: 234 KLD). The fresh water demand will be met from Ground water supply. A. WATER CONSERVATION TECHNIQUES: Following water conservation techniques have been proposed for the project: Dual plumbing system will be adopted to utilize the treated waste water for flushing (94KLD), landscaping and general washing (140 KLD). This will help in reducing the fresh water demand by 52%. Dual flushing fixtures will be used to allow different volumes of water for solid and liquid flushing which will help in conserving the water demand for flushing significantly. Water meters will be installed for the following: o Potable water consumption o Landscape water consumption o Hot water consumption through solar systems, at building level o Treated waste water consumption Landscape design & management of irrigation systems: o Native & xeriscaping plant species: Choose native plant species that need less water.

18 Promoter : o Creating Hydrozones: Grouping of plant according to their water needs to provide adequate water to all plants without over or under-watering. o Maintain Healthy Soil: Healthy soils are the basis for a water-smart landscape; they effectively cycle nutrients, minimize runoff, retain water, and absorb excess nutrients, sediments, and pollutants. o Mulching: Incorporate mulch around shrubs and garden plants to help reduce evaporation, inhibit weed growth, moderate soil temperature, and prevent erosion. Adding organic matter and aerating soil can improve its ability to hold water. o Avoid watering during the heat of the day. Water early in the morning to reduce the evaporation rate o Drought tolerant species will be selected. o Turfs will be avoided to the extent possible. o Central shut off valve will be provided o Sprinkler landscaping system will be used to conserve water B. WASTE WATER GENERATION AND TREATMENT: Approximate 262 KLD waste water will be generated which will be treated in STP of capacity 300 KLD, based on MBBR technology. Physico chemical characteristics of influent and effluent are given as: Parameters Influent (mg/ltr) Treated effluent (mg/ltr) BOD mg/l < 5 mg/l COD mg/l < 30 mg/l ph Oil & Grease < 5 mg/l TSS mg/l < 10 mg/l PROCESS DESCRIPTION: OPERATING PRINCIPLE: MBBR Technology is a combination of activated sludge process (suspended growth) and bio filter processes (attached growth). Moving Bed Biofilm Bioreactor (MBBR) process uses the whole tank volume for biomass growth. It uses simple floating media, which are carriers for attached growth of biofilms. Biofilm carrier movement is caused by the agitation of air bubbles.

19 Promoter : This compact treatment system is effective in removal of BOD as well as nitrogen and phosphorus while facilitating effective solids separation. In order to conserve water, Sewage Treatment Plant has been designed to ensure that treated effluent characteristics are well below the permissible limits of local/national pollution control norms even under varying flow conditions which are typical for such systems. This implies that the selected process shall be able to withstand the shock load situation. We propose to use MBBR treatment Technology for STP. This has the following advantages: The process has long retention time and can absorb shock load situation. The process produces a well-oxidized sludge in small quantities only, which can be removed and used as manure. PROCESS DESCRIPTION: Sewage generated from various sources after passing through an oil & grease trap will be carried through battery of manholes inter connected through soil pipes under gravity flow and will be collected in the collection cum equalization tank after passing through screen chambers near the STP. Manually cleaned bar screens will be installed in the screen chamber to screen of any large pieces. Coarse bubble aeration system will be provided to keep the sewage in homogeneous condition. From the Collection cum Equalization Tank, the waste water will be pumped via two submersible solids handling pumps (1 working + 1 standby) into adjoining aeration tank. In the aeration tank waste water will be mixed with micro-organisms in presence of dissolved oxygen. Micro-organisms will assimilate organic impurities. The mixed liquor suspended solids (MLSS) will be maintained at levels of 3,000 mg/l 4,000 mg/l. The bottom of the aeration tank will be covered with submerged air diffusers. Submerged air diffusers will provide mixing and oxygen for the needs of micro-organisms. Compressed air will be supplied through two common air blowers (1 working + 1 standby) for collection cum equalization tank, aeration tank & sludge holding tank.

20 Promoter : From the aeration tank mixed liquor will flow by gravity into adjoining clarifier tank (Secondary settling tank). The solids will settle in the clarifier tank. Sludge Recirculation pumps will pump the settled sludge from the bottom of clarifier tank to sludge holding tank and the aeration tank for maintaining desired MLSS level.overflow weir with scum baffle will be provided in the clarifiers to take treated waste water out of the clarifier. From the clarifier, treated waste water will flow via gravity into adjoining treated effluent cum filter feed tank. Treated waste water after treated effluent cum Filter Feed tank will be clear, odorless, low BOD and low suspended solids. For improving the treated waste water quality, treated waste water after Filter Feed tank will be passed through Pressure Sand Filter followed by Activated Carbon Filter for further reduction of Suspended Solids, BOD, COD, etc. so as to make it suitable for Irrigation purpose process. Water will be passed through U/F feed & backwash pump, cartridge filter, U/F membrane for further reduction of suspended solid, BOD, COD etc as to make it suitable for flushing purpose. The treated effluent will be collected/stored in the flushing permeate storage tank from where it can be used for flushing, horticulture and other requirements. DESIGN PARAMETERS FOR 300 KLD STP Of MBBR TECHNOLOGY S. No DESCRIPTION 1.0 Sewage generated 300 mᶾ /day 2.0 Sewage to be treated 300 mᶾ /day Say 300 mᶾ /day 3.0 BOD in influent 300 mg/l 4.0 Total BOD load on plant 90 kg/day 5.0 Suspended solid influent 450 mg/l 6.0 SS load on plant 135 kg/day Tertiary Treatment 7.0 Desired effluent standard Before After

21 Promoter : 8.0 BOD 300 <10 mg/l 9.0 SS 450 <10 mg/l 10.0 Usage :- Gardening, Flushing, Road Washing 11.0 Plant Design :- Operating conditions Hours of use 20 hrs Av. Hourly flow 15.0 mᶾ /hr 11.1 Equalization Tanks Total Nos Of Tank (1 Operational + 1 Emergency Use) 2 Total daily flow 300 mᶾ Operating hours 20 hrs Average flow 15.0 m3/hour Retention period 6 hrs BOD Reduction In the Tank 5% 4.50 kg/day BOD Value after 5% reduction of Initial Load kg/day Total Volume of tank required mᶾ Say 90 m3 Dimensions Length 5.2 m Breath 5 m Height 3.5 m Volume 90 m Aeration Tanks Total daily flow 300 mᶾ

22 Promoter : BOD Load kg/day Desired MLSS ( mg/l) considered 3.5 kg/m3 F/M Ratio (Food to Micro Organism considered) 0.12 M(Biomass) Total volume of tank required mᶾ Say mᶾ BOD value further 70% reduction kg/day Nos. of Tanks 2 No. Volume per tank 102 mᶾ Dimensions Length 5.5 m Width 5.3 m Height 3.5 m Air requirement for BOD (BOD Load per day/ no. of aeration 60 m3/kg of air to treat m3/hr kg of BOD Air requirement for mixing m3/hr 11.3 Secondary Tank Nos. of Tank 1 nos Total Flow Rate 300 mᶾ/day Operating Hours 20 hrs Average Flow Rate 15 m3/hr BOD to be removed kg/day BOD value after further reduction to 80% 5.13 kg/day Design overflow rate m3/m2/day Design overflow rate in m3/m2/hr 0.67 m3/m2/hr Cross sectional Area m2 Depth of the tank 3.00 m

23 Promoter : volume of the tank required m³ Say m³ Dimensions Length 4.50 Width 4.30 m Height 3.50 M 11.4 Sludge Holding Tank Nos. of Tank 1 Total Flow 300 mᶾ/day Operating hours 20 Average Flow 15 mᶾ/hr Retention time 0.5 hrs Volume of tank 7.5 mᶾ Say 7.5 mᶾ Length 2.5 m Width 2 m Water Depth 1.5 m 11.5 Clear Water Tank (CWT) Nos. of Tank 1 Total Flow Rate 300 mᶾ/day Operating hours 20.0 hr Average Flow mᶾ/hr Hydraulic retention Time 3 hr Volume Required mᶾ Say mᶾ Length 3.8 m Width 3.5 m Water Depth 3.4 m

24 Promoter : Volume mᶾ 11.6 Raw Sewerage Pump Flow mᶾ/day Operational Hours 20.0 Average Flow 15.0 mᶾ/hr Provide (1 working+1 standby) 15.0 mᶾ/hr Pump flow rate 250 LPM Head 12 m 11.7 Sludge Disposal Pump Flow mᶾ/day 40% of total flow 120 mᶾ/day Operational hours 20 Average flow 6.00 mᶾ/hr Provide (1 working + 1 standby) 6.00 mᶾ/hr Pump flow rate 100 LPM Head 12 m 11.8 Irrigation Water Lifting Pump Flow mᶾ/day Operational hours 4 Average flow mᶾ/hr Say 88 mᶾ/hr Provide (1 working + 1 standby) 88 mᶾ/hr Pump flow rate LPM Head 10 m 11.9 Filter Feed Pump Flow mᶾ/day

25 Promoter : Operational hours 6 Average flow mᶾ/hr Say mᶾ/hr Provide (1 working + 1 standby) mᶾ/hr Pump flow rate LPM Head 8 m 11.1 Dual Media filter Flow mᶾ/day Operational hours 20 hr Filtration rate mᶾ/hr Say mᶾ/hr Loading rate on filter 12 m3/m2/hr Cross sectional area 1.5 Dia of Vessel 1.3 m Height of Straight 1.8 m 11.1 Activated Carbon Filter Flow mᶾ/day Operational hours 20 hr Filtration Rate mᶾ/hr Say mᶾ/hr Loading Rate on filter m3/m2/hr Cross sectional Area 1.5 Dia of vessel m Height of Straight 1.8 m STAGE WISE BOD LOAD REDUCTION Incoming BOD: 300 mg/l Stages BOD reduction (%) BOD reduction value (mg/l) Equalization Tank 5 285

26 Promoter : Aeration/MBBR Tank Secondary Settling tank Sand Filter Activated Carbon Filter Ozone Treatment (<5) STORM WATER MANAGEMENT: Construction phase Contaminant Sources Impact Mitigation Sediment & Streets, lawns, driveways, During construction, sediment fencing or other erosion Floatables roads, construction control devices will be used to mitigate the short-term activities, adverse impacts of sedimentation. Oil & Grease Roads, driveways, parking lots etc. Oil & Grease trap will be provided to remove oil & grease, suspended matter, and ensure the quality of water. Storm water control and rain water harvesting will be done as per the standards laid down by CGWA & BIS. Following measure will be adopted for the same: Construction Sequencing: Construction sequencing (involves disturbing only part of a site at a time to prevent erosion from dormant parts) has been done at site. Grading activities and construction are completed and soils are effectively stabilized on one part of the site before grading and construction commence at another part. Compost Blankets: A compost blanket is a layer of loosely applied composted material placed on the soil in disturbed areas to reduce storm water runoff and erosion. This material fills in small rills and voids to limit channelized flow, provides a more permeable surface to facilitate storm water infiltration, and promotes re-vegetation. Post Construction Phase: a. Design: For good design of rainwater harvesting, following points are to be kept under consideration: Ideal location with good ground slope.

27 Promoter : The location has adequate subsurface permeability of the aquifer to accommodate maximum recharge of rainwater through injection well. Rate of filtration should exceed average rainfall intensity. Clogging of filtration media should be cleaned periodically. Ground water pollution does not take place. b. Baseline: The average annual rainfall (based on last 10 years rainfall data) at Sanganer station is 649 mm. Rain Fall Data (last 10 years): S. No. Year Annual Average Rainfall No. of Rainy Days Total 6, Average Source: Water Resource Department, Rajasthan c. Calculation of No. of RWH Structures: The rain water harvesting structures are calculated on the basis of peak intensity of rainfall recorded as 60 mm/hr considering 15 minutes of peak rainfall. The same has been done to avoid flooding of the area. S. No Type of Structure/ Surface Area [A] (sq. m.) Run off Coefficient [C] Intensity of rainfall (m/hour) [I] Total Recharge [Q = CIA] (m 3 /hr) 1. Roof Top Landscape 12, Paved area 18,

28 Promoter : Grand Total (1-3) 39, Total Rain Water Flow : m 3 /hr Considering 15 minutes of peak rainfall, Runoff volume : m 3 /hr Volume of each pit : 27 m 3 (3 m x 3 m x 3 m) Total no. of rain water harvesting pits required : Total run-off volume/volume of each pit : /27 : 13.7 say 14 nos. Therefore, 14 Nos. rain Water Harvesting pit of size 3 m length x 3 m width x 3 m depth with PVC slotted pipe upto minimum depth of 30 m. d. Design of Rain Water Harvesting Structure: The dimensional parameters of Desilting/Settlement chamber would be 3 m (length) x 3 m (width) x 1.30 (depth). In Desilting chamber, 0.30 m depth below outflow is kept for silt deposition. The filtration tank dimension would be 3 m (length) x 3 m (width) x 1 m (depth) with 0.15 m dia recharge well of 30 m depth depending upon the formation for recharge in aquifer through vadose zone.

29 Promoter : e. Calculation of annual recharge: S. Type of Area [A] Run off Intensity Total Recharge No Structure/ Surface (sq. m.) Coefficient of rainfall [I] [Q= CIA] [C] (m/annum) (m 3 / annum) 1. Roof Top Landscape 12, Paved area 18, Grand Total (1-3) 39, say Total Annual Recharge to Ground Water Regime of the area through rainwater harvesting structure would be m 3 / annum. SOLID WASTE MANAGEMENT: Applicable Rules: Construction & Demolition Waste Management Rules, 2016

30 Promoter : Solid Waste Management Rules, 2016 Plastic Waste Management Rules, 2016 Electronic waste Management Rules, 2016 Construction Waste: Excavation will be done to the tune of 1,36,750 MT and the soil will be reutilized within the site. About 8900 MT of the construction waste will be generated. Details of the same is given as under:- S. No. Particulars Approx. Qty, (MT) Percentage 1. Wood Dry Wall Concrete Metal Scrap Cardboard Plastics Electronic Scrap Misc.(Paint, Ceramic etc) Total Source: Seeman, 2006

31 Promoter : POST CONSTRUCTION PHASE: The solid waste generated from the project considering full occupancy will be mainly domestic waste and estimated quantity of the same will be approx 1073 kg/day. The solid waste generated will be first segregated as plastic, glass, paper, and other waste separately and disposed off as per applicable Rules. SOLID WASTE CALCULATION: Particulars Population Basis Quantity of waste generated (in kg/day) Residential kg/day* 858 Floating Population 215 Total 1073 *Source: NBC 2016 BREAK UP OF RESIDENTIAL SOLID WASTE:- Particulars Quantity (kg/day) % Percentage Biodegradable Paper Plastic/rubber Metal Glass Rags Other Inerts Total Source: Municipal Solid Waste Management Manual-Part-II, CPHEEEO, MOUD, 2016

32 Promoter : Bins Particulars Treatment Disposal Green Compostable waste Collected in green colored bins and sent to the OWC Will be sent to municipality disposal site White Dry/ recyclable waste: Black Other waste/ Domestic hazardous waste No in-situ treatment. Collected in white colored bins and sent to solid waste collection point. No in-situ treatment. Collected in Black colored bins and sent to solid waste collection point Segregated waste will be handed over to authorized waste pickers or waste collectors. Source: Municipal Solid Waste Management Manual, CPHEEEO, MOUD, 2016 ENERGY CONSERVATION CALCULATIONS: Energy conservation techniques: Total flat light load can be reduced by 40% by use of LED lamps in place of fluorescent/ incandescent lamps. Lift load can be reduced by 23% by use of VF drives. All capacitors will be provided with Harmonic Filters to avoid distortion in Voltage. Automatic Power Factor correction panel with capacitor will be used for Common Load & Fixed Capacitor for Transformer to minimize the losses. Insulation of exposed walls and roof will be done to minimize heat gains inside the building. This will help to reduce the air conditioning demand of the buildings. Emphasis will be given on low maintenance, low wattage and longer life in selection of chokes and lamps for all common area and external light fixtures. RISK & HAZARD IN CONSTRUCTION INDUSTRY: The International Labour Organization (ILO) classifies the construction industry as government and private-sector firms erecting buildings for habitation or for commercial purposes and public works such as roads, bridges, tunnels, dams or airports. In India, construction workers also clean hazardous waste sites.

33 Promoter : Health Hazards On Construction Sites Construction workers are exposed to a wide variety of health hazards on the job. Exposure differs from trade to trade, from job to job, by the day, even by the hour. Exposure to any one hazard is typically intermittent and of short duration, but is likely to reoccur. A worker may not only encounter the primary hazards of his or her own job, but may also be exposed as a bystander to hazards produced by those who work nearby or upwind. This pattern of exposure is a consequence of having many employers with jobs of relatively short duration and working alongside workers in other trades that generate other hazards. The severity of each hazard depends on the concentration and duration of exposure for that particular job. Bystander exposures can be approximated if one knows the trade of workers nearby. Hazards present for workers in particular trades are listed in table. Primary Hazards Encountered In Skilled Construction Trades Each trade is listed below with an indication of the primary hazards to which a worker in that trade might be exposed. Exposure may occur to either supervisors or to wage earners. The classifications of construction trades used here are those used in India. It includes the construction trades as classified in the Standard Occupational Classification system. This system classifies the trades by the principal skills inherent in the trade. Table: OCCUPATIONAL HAZARD S.NO. OCCUPATIONS HAZARDS 1 Brick masons Cement dermatitis, awkward postures, heavy loads 2 Stonemasons Cement dermatitis, awkward postures, heavy loads 3 Hard tile setters Vapor from bonding agents, dermatitis, awkward postures 4 Carpenters Wood dust, heavy loads, repetitive motion 5 Drywall installers Plaster dust, walking on stilts, heavy loads, awkward postures 6 Electricians Heavy metals in solder fumes, awkward posture, heavy loads 7 Electrical power installers and Heavy metals in solder fumes, heavy loads repairers 8 Painters Solvent vapours, toxic metals in pigments, paint additives 9 Plasterers Dermatitis, awkward postures 10 Plumbers Lead fumes and particles, welding fumes 11 Pipefitters Lead fumes and particles, welding fumes

34 Promoter : 12 Steamfitters Welding fumes 13 Carpet layers Knee trauma, awkward postures, glue and glue vapour 14 Soft tile installers Bonding agents 15 Concrete and terrazzo finishers Awkward postures 16 Insulation workers Synthetic fibres, awkward postures 17 Paving, surfacing and tamping Asphalt emissions, gasoline and diesel engine exhaust, heat equipment operators 18 Roofers Roofing tar, heat, working at heights 19 Sheet metal duct installers Awkward postures, heavy loads, noise 20 Structural metal installers Awkward postures, heavy loads, working at heights 21 Welders Welding emissions 22 Solderers Metal fumes, lead, cadmium 23 Drillers, earth, rock Silica dust, whole-body vibration, noise 24 Air hammer operators Noise, whole-body vibration, silica dust 25 Pile driving operators Noise, whole-body vibration 26 Hoist and winch operators Noise, lubricating oil 27 Crane and tower operators Stress, isolation 28 Excavating and loading machine operators 29 Grader, dozer and scraper Silica dust, histoplasmosis, whole-body vibration, heat stress, noise Silica dust, whole-body vibration, heat noise operators 30 Truck and tractor equipment Whole-body vibration, diesel engine exhaust operators Construction Hazards As in other jobs, hazards for construction workers are typically of three classes: 1. Chemical Hazards 2. Physical Hazards 3. Biological Hazards Evaluating Exposure Evaluating either primary or bystander exposure requires knowing the tasks being done and the composition of ingredients and by-products associated with each job or task. This knowledge

35 Promoter : usually exists somewhere (e.g., material safety data sheets, MSDSs) but may not be available at the job site. With continually evolving computer and communications technology, it is relatively easy to obtain such information and make it available. Management For Safe Construction Work Effective safety programmes have several features in common. They are manifest throughout organizations, from the highest offices of a general contractor to project managers, supervisors, union officials and workers on the job. Codes of practice are conscientiously implemented and evaluated. Costs of injury and illness are calculated and performance is measured; those that do well are rewarded, those that do not are penalized. Safety is an integral part of contracts and subcontracts. Everybody-managers, supervisors and workers-receives general, site-specific and site-relevant training. Inexperienced workers receive on-the-job training from experienced workers. In projects where such measures are implemented, injury rates are significantly lower than on otherwise comparable sites. Preventing Accidents And Injuries Entities in the industry with lower injury rates share several common characteristics: they have a clearly defined policy statement that applies throughout the organization, from top management to the project site. This policy statement refers to a specific code of practice that describes, in detail, the hazards and their control for the pertinent occupations and tasks at a site. Responsibilities are clearly assigned and standards of performance are stated. Failures to meet these standards are investigated and penalties imposed as appropriate. Meeting or exceeding standards is rewarded. An accounting system is used that shows the costs of each injury or accident and the benefits of injury prevention. Employees or their representatives are involved in establishing and administering a programme of injury prevention. Involvement often occurs in the formation of a joint labour or worker management committee. Physical examinations are performed to determine workers fitness for duty and job assignment. Hazards are identified, analysed and controlled following the classes of hazards. The entire work site is inspected on a regular basis and results are recorded. Equipment is inspected to ensure its safe operation (e.g., brakes on vehicles, alarms, guards and so on). Injury hazards include those

36 Promoter : associated with the most common types of lost-time injuries: falls from heights or at the same level, lifting or other forms of manual materials handling, risk of electrocution, risk of injury associated with either highway or off-road vehicles, trench cave-ins and others. Health hazards would include airborne particles (such as silica, asbestos, synthetic vitreous fibres, diesel particulates), gases and vapours (such as carbon monoxide, solvent vapour, engine exhaust), physical hazards (such as noise, heat, hyperbaric pressure) and others, such as stress. Preparations are made for emergency situations and emergency drills are conducted as needed. Preparations would include assignment of responsibilities, provision of first aid and immediate medical attention at the site, communication at the site and with others off the site (such as ambulances, family members, home offices and labour unions), transportation, designation of health care facilities, securing and stabilizing the environment where the emergency occurred, identifying witnesses and documenting events. As needed, emergency preparedness would also cover means of escape from an uncontrolled hazard such as fire or flood. Accidents and injuries are investigated and recorded. The purpose of reports is to identify causes that could have been controlled so that, in the future, similar occurrences can be prevented. Reports should be organized with a standardized record-keeping system to better facilitate analysis and prevention. To facilitate comparison of injury rates from one situation to another, it is useful to identify the pertinent population of workers within which an injury occurred, and their hours worked, in order to calculate an injury rate (i.e., the number of injuries per hour worked or the number of hours worked between injuries). Workers and supervisors receive training and education in safety. This education consists of teaching general principles of safety and health, is integrated into task training, is specific for each work site and covers procedures to follow in the event of an accident or injury. Education and training for workers and supervisors is an essential part of any effort to prevent injuries and disease. Training about safe work practices and procedures have been provided by some companies and trade unions. These procedures, include lockout and tagout of electrical power sources during maintenance procedures, use of lanyards while working at heights, shoring trenches, providing safe walking surfaces and so on. It is also important to provide site-specific training, covering unique features about the job site such as means of entry and exit. Training should include instruction

37 Promoter : about dangerous substances. Performance or hands-on training, demonstrating that one knows safe practices, is much better. Information about chemical, physical and other health hazards is available at the work site in the languages that workers use. If workers are to work intelligently on the job, they should have the information necessary to decide what to do in specific situations. And finally, contracts between contractors and subcontractors should include safety features. Provisions could include establishing a unified safety organization at multi-employer work sites, performance requirements and rewards and penalties. LIGHTING PROTECTION: The structures shall be protected against lightning in accordance with the requirement of IS 2309: 1989 with latest amendments. The risk factor requires provision of lightning protection and in addition considered necessary for the safety of tall buildings and human life. The lightning protection system shall comprise of a grid of horizontal air terminations and vertical finials provided at the terrace of each high rise tower at the highest point and that of the low rise buildings which are not within the protective angles of the high rise terminations. The horizontal & vertical air terminations shall be connected through a series of down earth conductors running along the sides of the building with earth tapes to the Pipe type earth electrodes / earth stations. Earth test points shall be provided. The lightning protection system shall be based on use of hot dip galvanized iron i.e. GI strip conductors and GI earth stations. OR Alternatively, controlled steamer emission system along with chemical earth pits may be employed, if client prefers so, but this system of lightning protection shall not be as per IS codes. All towers shall be protected from lightning by providing Controlled streamer emission (CSE) lightning arrestors installed at the highest point at the terrace level duly connected to GI tape/cable as per system design criteria.

38 Promoter : FIRE PROTECTION Preventing fire ignition is the first line of defense in fire safety. The second line of defense, if ignition does occur, is to manage the fire s impact and minimize the risk. The two main methods for managing the impact of a fire are Manage the People Exposed and Manage the Fire itself. The automatic fire alarm shall be provided depending on the height of the tower. It shall be as follows: Group A, sub division A-4 (Apartment Houses): Above 45m but not exceeding 60 m in height, minimum fire fighting requirement (as per NBC 2016 Part IV Table 7) will be provided in the project. S. No. Description Minimum Fire Fighting Requirement 1. Fire extinguisher Required 2. First Aid Hose reel Required 3. Wet riser Required 4. Down comer Not Required 5. Yard hydrant Required 6. Automatic sprinkler system Required 7. Manually operated electronic fire alarm system Required 8. Automatic detection & alarm system Not Required 9. Underground water tank 1,50,000 L 10. Terrace water tank 10,000L FIRE DETECTION Despite the many precautions taken, fires may breakout. Hence the project will establish measures to detect a fire and to extinguish it. Automatic fire detection has many advantages such as speed and reliability and is recommended. MANAGEMENT PLAN Since the project may face fire hazards or other emergency situations; an emergency plan is provided to caution the persons during any accidents. The fundamental approach, governing fire

39 Promoter : safety attempts to ensure that fires do not at all start in the first place and should they occur, to restrain their spread by quick detection and extinguishments. The task of accident and emergency control can be simplified and made effective if pre-planned systems and procedures are available. Without these, important matters may be overlooked at the time of an emergency. Every management must survey the total operation to identify potential for fire losses and develop an action plan to put the business back to normal with minimum loss of time. A fire protection Manual should be prepared, preferably in 3-parts. 1. The first part should outline the fire risks in terms of plant locations, equipment and facilities and indicate the ways in which risks have been minimized. 2. The second part would set out operating procedures, standards of fire protection established, and maintenances of these standards action to be taken in the event of fire by every level of management responsibility for inspection and repair. It should also include instructions for staff responsible for building services. 3. The third part should outline the training required for existing and new staff, the inspection schedules and check lists, sources of additional information and help. The Management Cell of the project shall keep ready a plan to alert and take care of residents in case there is any fire. There shall be designated an Emergency Team that shall consist of staff of maintenance department, security supervisor representative of residents from campus. ELECTRICAL HAZARDS SAFETY MEASURE PLAN A dangerous condition such that contact or equipment failure can result in Electric shock, arc-flash burn, thermal burn, or blast. Electrical hazard includes dangerous meaning able or likely to inflict injury ; there are high voltage, low current sources that are not intrinsically dangerous, and there are low-voltage, high-current sources that are not safe. A harmless static electricity shock could cause sufficient startle reaction to make a worker fall off a ladder. A hazard analysis is necessary to identify electrical hazards and determine the degree of risk. We are considering different types of measures for preventing electrical hazards which are as follows:

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 SIX MONTHLY COMPLIANCE REPORT JUNE- 2015 Group Housing Complex My woods AT Plot no. GH-04, Sector -16 C, Noida Extension, Greater Noida, U.P. Being developed by M/s Mahagun India Pvt. Ltd. A-19, Sector-63,

More information

Max. building height (m)

Max. building height (m) Environmental Management Plan (EMP) for Himalaya Falaknuma by Himalaya Developers Ahmedabad No. Particulars Details 1. Proposal for New Project 2. Type of Project and Commercial Building Construction Project

More information

FORM - I-A CHECK LIST OF ENVIRONMENTAL IMPACTS

FORM - I-A CHECK LIST OF ENVIRONMENTAL IMPACTS FORM - I-A CHECK LIST OF ENVIRONMENTAL IMPACTS 1. LAND ENVIRONMENT QUERY 1.1 Will the existing land use get significantly altered from the project that is not consistent with the surroundings? Attach Maps

More information

SEPTIC TANK CONSTRUCTION GUIDELINES

SEPTIC TANK CONSTRUCTION GUIDELINES SEPTIC TANK CONSTRUCTION GUIDELINES Septic tank for this airport will be designed/ built by the general contractor of the building facilities. At the time of the project design, availability of a septic

More information

FORD GLOBAL TECHNOLOGY AND BUSINESS CENTRE FORD MOTOR PRIVATE LIMITED

FORD GLOBAL TECHNOLOGY AND BUSINESS CENTRE FORD MOTOR PRIVATE LIMITED FORD GLOBAL TECHNOLOGY AND BUSINESS CENTRE FORD MOTOR PRIVATE LIMITED Ford Motor Private Limited- Conceptual Plan 1 Contents 1 INTRODUCTION 3 1.1 BACKGROUND 3 1.2 PROJECT LOCATION 3 1.3 PROJECT FEATURES

More information

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department 2017 [Type a quote from the document or the summary of an interesting point. You can position the text box anywhere in the document. Use the Drawing Tools tab to change the formatting of the pull quote

More information

Existing vegetation with each tree detail like species, girth, canopy etc. Contours with levels Natural features like water body, stream etc.

Existing vegetation with each tree detail like species, girth, canopy etc. Contours with levels Natural features like water body, stream etc. Project name:- Project Code :- Registration Category :- General Comments :- Drawings Feedback:- 1st feedback No Dwg Name Dwg Description Recommendation 1 Site survey plan Site plan showing following in

More information

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building...

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building... Contents 11. Construction processes and materials... 11-2 11.1 Power House... 11-2 11.2 Maintenance Building... 11-2 11.3 Fuel Treatment Building... 11-3 11.4 Roads & Paths... 11-3 11.5 Fencing... 11-3

More information

Dilipbhai D. Patel. BLOCK NO. 43, F.P. NO. 45,O.P NO. 40 T.P.S. No- 17 (PUNA), Ta: SURAT CITY, DIST: SURAT

Dilipbhai D. Patel. BLOCK NO. 43, F.P. NO. 45,O.P NO. 40 T.P.S. No- 17 (PUNA), Ta: SURAT CITY, DIST: SURAT Annexure B Land Possession letters & N.A. permission letters Annexure C Photograph of the Site Annexure D Details of Buildings Area Calculation Annexure 1 Topo Sheet Annexure 2 Soil Analysis Report Annexure

More information

CONSULTING OFFICE OF MORRIS S. FARKAS PROFESSIONAL SAFETY ENGINEER

CONSULTING OFFICE OF MORRIS S. FARKAS PROFESSIONAL SAFETY ENGINEER CONSULTING OFFICE OF MORRIS S. FARKAS PROFESSIONAL SAFETY ENGINEER EDUCATION 3835 East Thousand Oaks Boulevard, #365 Westlake Village, California 91362 Telephone: (805) 494-0444 Facsimile: (805) 494-0441

More information

F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar.

F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar. 20. Karnavati Premier Living F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar. Screening & scoping / appraisal Details of the proposed project as presented before the committee

More information

Sanitary and Environmental Engineering I (4 th Year Civil)

Sanitary and Environmental Engineering I (4 th Year Civil) Sanitary and Environmental Engineering I (4 th Year Civil) Prepared by Dr.Khaled Zaher Assistant Professor, Public Works Engineering Department, Faculty of Engineering, Cairo University Wastewater Flow

More information

Activity Aspects Impacts/ Nuisances Construction phase - Site preparation. - Generation of excavated soil, debris and construction wastes

Activity Aspects Impacts/ Nuisances Construction phase - Site preparation. - Generation of excavated soil, debris and construction wastes MINISTRY OF ENVIRONMENT AND NDU ENVIRONMENTAL GUIDELINE No. 31 Asphalt Plant Set Up Temporarily For The Purposes Of A Project By A Public Department 1.0 Purpose of guideline This environmental guideline

More information

Hind Energy & Coal Beneficiation (India) Ltd.

Hind Energy & Coal Beneficiation (India) Ltd. SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF Hind Energy & Coal Beneficiation (India) Ltd. (Change in Technology) at Hindadih Village, Masturi Tehsil Bilaspur District, Chhattisgarh Submitted to

More information

Hazardous Waste Management

Hazardous Waste Management Objectives EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Objective

More information

Excavation Safety Program

Excavation Safety Program Excavation Safety Program Excavation, Trenching & Shoring Safety I. Purpose The purpose of this policy is to establish safe operating procedures for any earthwork or underground work that is done on a

More information

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are: 4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 4.1 POTENTIAL ENVIRONMENTAL IMPACTS 4.1.1 Impacts during Construction Phase Negative or adverse impacts during the construction phase are: Land environment:

More information

OPERATION AND MAINTENANCE MANUAL FOR SEWAGE TREATMENT PLANT

OPERATION AND MAINTENANCE MANUAL FOR SEWAGE TREATMENT PLANT PROPOSED RESIDENTIAL DEVELOPMENT, CORAL SPRINGS TRELAWNY FCS #: 1124/76/C OPERATION AND MAINTENANCE MANUAL FOR SEWAGE TREATMENT PLANT PREPARED FOR Gore Developments Limited 2c Braemar Ave, Kingston 10

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service.

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service. CHAPTER3 Clark Public Utilities Commercial Electric Service Handbook Commercial Underground Services Preparing for the installation The following checklist will assist in preparing a project for the installation

More information

Estimate FOR THE SEPTIC TANK

Estimate FOR THE SEPTIC TANK Estimate FOR THE SEPTIC TANK S.NO ITEM DESCRIPTION. 1 Excavation in soil,soft & hard murum... Qty UNIT Rate Excavation for footing, machine foundation, plinth beams, wall footing, gutters,brick wall, tanks

More information

SECTION 14 - GENERAL INDUSTRIAL ZONE (M2) REGULATIONS

SECTION 14 - GENERAL INDUSTRIAL ZONE (M2) REGULATIONS SECTION 14 - GENERAL INDUSTRIAL ZONE (M2) REGULATIONS 14.1 GENERAL USE REGULATIONS 14.1.1 PERMITTED USES No land, building, or structures shall be used or erected in the General Industrial Zone (M2) unless

More information

This unofficial translation of. Ministerial Decision No 421/1998. was downloaded from METS is not the copyright owner.

This unofficial translation of. Ministerial Decision No 421/1998. was downloaded from  METS is not the copyright owner. Disclaimer This unofficial translation of Ministerial Decision No 421/1998 was downloaded from www.mets-oman.com. METS is not the copyright owner. METS is not responsible for the content of this document.

More information

GRAY WATER RECYCLING SYSTEMS

GRAY WATER RECYCLING SYSTEMS GRAY WATER RECYCLING SYSTEMS Note: Section P2601.2 of the International Residential Code requires all plumbing fixtures that receive water or waste to discharge to the sanitary drainage system of the structure.

More information

Topic: Site Formation

Topic: Site Formation Topic: Site Formation Presentation prepared by Raymond Wong February 2006 Purpose of site formation is to prepare a piece of land in order to: Accommodate building/s or other facilities which will be placed

More information

Design of Sewerage System for Jaffarpur area in Southwest New Delhi

Design of Sewerage System for Jaffarpur area in Southwest New Delhi International Journal of Civil Engineering Research. ISSN 2278-3652 Volume 5, Number 1 (2014), pp. 29-34 Research India Publications http://www.ripublication.com/ijcer.htm Design of Sewerage System for

More information

SECTION TRENCHING & BACKFILLING

SECTION TRENCHING & BACKFILLING SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications

More information

PART A : CPVC PIPES AND FITTNGS (EXTERNAL WATERSUPPLY):

PART A : CPVC PIPES AND FITTNGS (EXTERNAL WATERSUPPLY): PART A : CPVC PIPES AND FITTNGS (EXTERNAL WATERSUPPLY): 01 Providing and Fixing of CPVC pipes confirming to ASTM standard including all CPVC fittings like tees, elbows, bends, unions, coupling, reducer

More information

Stormwater Attenuation Systems Sustainable Drainage Solutions for Domestic & Commercial Applications

Stormwater Attenuation Systems Sustainable Drainage Solutions for Domestic & Commercial Applications Environmental Stormwater Attenuation Systems Sustainable Drainage Solutions for Domestic & Commercial Applications Sustainable, Reliable, Affordable Stormwater Attenuation Systems Sustainable Drainage

More information

(1) Site Suitability PURPOSE

(1) Site Suitability PURPOSE 3.3 Code for Development and Use of Rural Service Industries PURPOSE This purpose of this code is to encourage the development and use of suitable rural service industries on rural, industrial or suitable

More information

6.1 Introduction to Wastewater Issues

6.1 Introduction to Wastewater Issues Section 6: Water Pollution This Section will help you: Understand if you generate industrial wastewater; Understand where your wastewater goes; Make sure you meet requirements for floor drains; Properly

More information

HINAUTI LIMESTONE MINE Mine Lease area ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P)

HINAUTI LIMESTONE MINE Mine Lease area ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P) HINAUTI LIMESTONE MINE Mine Lease area 378.261 ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P) 2012-2013 SUBMITTED TO M.P.POLLUTION CONTROL BOARD BHOPAL (M.P.) Jaypee Sidhi Cement

More information

ROOF TOP RAIN WATER HARVESTING. Manohar Patil

ROOF TOP RAIN WATER HARVESTING. Manohar Patil ROOF TOP RAIN WATER HARVESTING Manohar Patil Why harvest rainwater To arrest ground water To beneficiate water quality in aquifers To conserve surface water runoff To reduce soil erosion What is Rainwater

More information

by M k h GROVER Degremont

by M k h GROVER Degremont Innovative Technologies for Urban Waste Water Treatment by M k h GROVER Mukesh Degremont 4th March2013 Sewage a complex waste water URBAN WASTE WATER - SEWAGE Source of Foul odour Infectious Diseases Surface

More information

The Islamic University of Gaza- Civil Engineering Department Sanitary Engineering- ECIV 4325 L5. Storm water Management

The Islamic University of Gaza- Civil Engineering Department Sanitary Engineering- ECIV 4325 L5. Storm water Management The Islamic University of Gaza- Civil Engineering Department Sanitary Engineering- ECIV 4325 L5. Storm water Management Husam Al-Najar Storm water management : Collection System Design principles The Objectives

More information

CONSTRUCTION AND DEMOLITION DEBRIS DISPOSAL SITE GUIDELINES

CONSTRUCTION AND DEMOLITION DEBRIS DISPOSAL SITE GUIDELINES Nova Scotia Environment and Labour CONSTRUCTION AND DEMOLITION DEBRIS DISPOSAL SITE GUIDELINES Approval Date: October 24, 1997 Effective Date: October 24, 1997 Approved By: Peter Underwood Version Control:

More information

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra Draft Terms of References (ToR) (Based on the model TOR given in Environmental Impact Assessment Guidance Manual for building construction projects by MoEF & CC) For PROPOSED IT PARK By M/s.Balewadi Tech

More information

FORM-1 A (only for construction projects listed under item 8 of the Schedule) CHECK LIST OF ENVIRONMENTAL IMPACTS

FORM-1 A (only for construction projects listed under item 8 of the Schedule) CHECK LIST OF ENVIRONMENTAL IMPACTS APPENDIX II (See paragraph 6) FORM-1 A (only for construction projects listed under item 8 of the Schedule) CHECK LIST OF ENVIRONMENTAL IMPACTS 1. LAND ENVIRONMENT (Attach panoramic view of the project

More information

9.3.9 Industry uses code

9.3.9 Industry uses code 9.3.9 Industry uses code 9.3.9.1 Application (1) This code applies to accepted development and assessable development identified as requiring assessment against the Industry uses code by the tables of

More information

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL 1. SCOPE 2. DESIGN 3. MATERIALS 4. CONSTRUCTION 5. METHOD OF MEASUREMENT AND PAYMENT SCOPE This Specification sets out requirements for the design,

More information

TYPICAL INSTALLATION INSTRUCTIONS

TYPICAL INSTALLATION INSTRUCTIONS TYPICAL INSTALLATION INSTRUCTIONS Environment One Grinder Pump Feature Identification 1. Grinder Pump Basin High density polyethylene (HDPE) 2. Accessway Cover Painted Steel 3. Electrical Quick Disconnect

More information

Mixed Landuse Project Madhav Menon University, Sector-17A, Yamuna Expressway, Greater Noida, UP PFR

Mixed Landuse Project Madhav Menon University, Sector-17A, Yamuna Expressway, Greater Noida, UP PFR INTRODUCTION The Mixed Land Use Project, Madhav Menon University is to be developed by M/s. India Knowledge City Foundation. The project site is located at Plot No- 3, Expressway, Greater Noida, U.P. on

More information

Module 19 : Aerobic Secondary Treatment Of Wastewater. Lecture 24 : Aerobic Secondary Treatment Of Wastewater

Module 19 : Aerobic Secondary Treatment Of Wastewater. Lecture 24 : Aerobic Secondary Treatment Of Wastewater 1 P age Module 19 : Aerobic Secondary Treatment Of Wastewater Lecture 24 : Aerobic Secondary Treatment Of Wastewater 2 P age 19.1 Activated Sludge Process Conventional biological treatment of wastewater

More information

PERFORMANCE EVALUATION OF 9 MLD SEWAGE TREATMENT PLANT AT GURGAON AND COST EFFECTIVE MEASURES IN TREATMENT PROCESS

PERFORMANCE EVALUATION OF 9 MLD SEWAGE TREATMENT PLANT AT GURGAON AND COST EFFECTIVE MEASURES IN TREATMENT PROCESS PERFORMANCE EVALUATION OF 9 MLD SEWAGE TREATMENT PLANT AT GURGAON AND COST EFFECTIVE MEASURES IN TREATMENT PROCESS Mohan Singh Negi and Vaishali Sahu Department of Civil and Environment Engineering, The

More information

Environmental Leadership Program Inspection Form Portable Asphalt Facility

Environmental Leadership Program Inspection Form Portable Asphalt Facility Environmental Leadership Program Inspection Form Portable Asphalt Facility Company Name -Name & Location of Facility: Date of Inspection: FID Number Name of Inspector: Names of Inspection Participants:

More information

The Corporation of The City of London

The Corporation of The City of London The Corporation of The City of London Legislative Health and Safety Requirements The following is a health and safety guide for those providing a tender to assist in determining legislative health and

More information

Read Only Copy Not For Distribution. Chapter 17. Private Potable Water Supply Systems 17.1 GENERAL REGULATIONS 17.2 QUANTITY OF WATER REQUIRED

Read Only Copy Not For Distribution. Chapter 17. Private Potable Water Supply Systems 17.1 GENERAL REGULATIONS 17.2 QUANTITY OF WATER REQUIRED Chapter 17 Private Potable Water Supply Systems 17.1 GENERAL REGULATIONS 17.1.1 Applicability The regulations in this chapter apply to any private potable water supply system where plumbing fixtures are

More information

Activated Sludge Treatment Extended Aeration (EA) and Sequencing Batch Reactor (SBR) Systems

Activated Sludge Treatment Extended Aeration (EA) and Sequencing Batch Reactor (SBR) Systems 1 Activated Sludge Treatment Extended Aeration (EA) and Sequencing Batch Reactor (SBR) Systems General Features KEE Process packaged and purpose-built activated sludge process systems are suitable for

More information

Urban Rainwater Harvesting Systems: Promises and Challenges

Urban Rainwater Harvesting Systems: Promises and Challenges TheWaterChannel Webinar #5 Urban Rainwater Harvesting Systems: Promises and Challenges By Vishwanath S Zenrainman@gmail.com www.ircsa.org www.rainwaterclub.org Thanks for coming. The webinar will begin

More information

DESIGNING OF MODULAR RAINWATER HARVESTING SYSTEM & STORM WATER DRAIN INSTALLATION OF LATEST DESIGN & TECHNOLOGY AT BAHRAMPUR GOVT.

DESIGNING OF MODULAR RAINWATER HARVESTING SYSTEM & STORM WATER DRAIN INSTALLATION OF LATEST DESIGN & TECHNOLOGY AT BAHRAMPUR GOVT. DESIGNING OF MODULAR RAINWATER HARVESTING SYSTEM & STORM WATER DRAIN INSTALLATION OF LATEST DESIGN & TECHNOLOGY AT BAHRAMPUR GOVT. SCHOOL By LIFE GREEN SYSTEMS LIMITED 120, FIRST FLOOR, DLF GALLERIA MALL,

More information

C. Foundation stabilization for pipe and utility structures.

C. Foundation stabilization for pipe and utility structures. PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization

More information

Sanitary Sewer Systems. Sewage Collection System. Types of Sewage 10/12/2016. General Overview

Sanitary Sewer Systems. Sewage Collection System. Types of Sewage 10/12/2016. General Overview Sanitary Sewer Systems General Overview Sewage Collection System Pipes Pumping stations Maintenance entry points manholes Types of Sewage Sanitary Domestic sewage: human wastes and washwater from public

More information

DESIGN OF SEWER SYSTEMS

DESIGN OF SEWER SYSTEMS Wastewater Engineering (MSc program) DESIGN OF SEWER SYSTEMS Prepared by Dr.Khaled Zaher Assistant Professor, Public Works Engineering Department, Faculty of Engineering, Cairo University 1. Sewer Materials

More information

HOLDING TANK PLANNING & INSTALLATION GUIDELINES

HOLDING TANK PLANNING & INSTALLATION GUIDELINES HOLDING TANK PLANNING & INSTALLATION GUIDELINES Under no circumstances is sewage from a holding tank to be discharged onto the surface of the ground or into groundwater or surface waters. TABLE OF CONTENTS

More information

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)

More information

GV 001 Equipment Bases and Enclosures General Information

GV 001 Equipment Bases and Enclosures General Information Eq u ip me n tba s e s a n d En c lo s u re s Ge n e ra lin fo rma tio n E n g in e e r :R.An th o n GV0 0 1 Ap p r o v e r :Jo s h u a Jo n e s Ap r 1 7 2 0 Ap r1 7 GV 001 Equipment Bases and Enclosures

More information

Erosion & Sedimentation Control Policy

Erosion & Sedimentation Control Policy Issue Date 10/22/2010 Page 1 of 8 Erosion & Sedimentation Control Policy Introduction: Soil erosion is the removal of soil by water, wind, ice or gravity and sediment deposition occurs when the rate of

More information

Fixed-Film Processes

Fixed-Film Processes Onsite Wastewater Treatment Systems Technology Fact Sheet 2 Fixed-Film Processes Introduction Description Fixed-film systems (FFS) are biological treatment processes that employ a medium such as rock,

More information

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2 INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS 410. 1 SCOPE... 2 410. 2 DEFINITIONS 2.1 Tunneling and Jacking... 2 2.2 Tunneling... 2 2.3 Jacking... 2 410. 3 MATERIALS 3.1 General...

More information

Jack Werner, Ph.D, Lic#255 Phone: 405/

Jack Werner, Ph.D, Lic#255 Phone: 405/ AEROBIC SEWAGE TREATMENT SYSTEM IIt s Your On-Siite System Jack Werner, Ph.D, Lic#255 Phone: 405/412-7861 www.atozinspectionsok.biz Operatiion and Maiintenance Guiide for Homeowners OKLAHOMA DEPARTMENT

More information

Phase II (BIA Phase-II),

Phase II (BIA Phase-II), PROJECT PREFEASIBILITY REPORT FOR OBTAINING PRIOR ENVIRONMENTAL CLEARENCE IN TERMS OF PROVISIONS OF EIA NOTIFICATION-2006 1.0 EXECUTIVE SUMMARY OF THE PROJECT Sr. No Description Details 1 Proposed project

More information

SECTION CAST-IN-PLACE CONCRETE

SECTION CAST-IN-PLACE CONCRETE SECTION 03300 CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.01 SECTION INCLUDES A. The Contractor shall furnish all work and materials, including cement, sand and coarse aggregate, water, admixtures, curing

More information

Section [ ] Storm Water Treatment Device

Section [ ] Storm Water Treatment Device PART 1 GENERAL Section [ ] Storm Water Treatment Device 01.01.00 Purpose The purpose of this specification is to establish generally acceptable criteria for Storm Water Treatment Devices (SWTD) that treat

More information

Quality of Rainwater From Rainwater Harvesting Systems in Sanaa. Nagib Ghaleb N. Mohammed, Civil Engineering Department, University of Bahrain

Quality of Rainwater From Rainwater Harvesting Systems in Sanaa. Nagib Ghaleb N. Mohammed, Civil Engineering Department, University of Bahrain Quality of Rainwater From Rainwater Harvesting Systems in Sanaa Nagib Ghaleb N. Mohammed, Civil Engineering Department, University of Bahrain Outlines Shortage of Water Rain water harvesting Benefits of

More information

PART 1 GENERAL REQUIREMENTS

PART 1 GENERAL REQUIREMENTS PART 1 GENERAL REQUIREMENTS Contract Closeout Plan 110 Arrow diagram for project close-out...3 Erosion Control 121 Straw bale barrier... 5 122 Silt fence... 7 123 Diversion dike... 9 124 Inlet protection...

More information

FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) PART A

FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) PART A (I) FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR 2013-14 M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) Name & Address of the Owner / Occupier of the Industry Operation or Process

More information

Boise City Public Works General Drainage Plan Review Requirements Checklist

Boise City Public Works General Drainage Plan Review Requirements Checklist Boise City Public Works General Drainage Plan Review Requirements Checklist Development Name Bldg. Permit # Drainage Reviewer Site Address Initial Review Date ODI Number Designer Company Name Treated Acres

More information

GRAY WATER SYSTEMS (Reference California Plumbing Code Chapter 16 and 16A) Revised: 6/11/14

GRAY WATER SYSTEMS (Reference California Plumbing Code Chapter 16 and 16A) Revised: 6/11/14 Planning and Building Department 525 San Anselmo Avenue Building Division San Anselmo, CA 94960 Phone: (415) 258-4616 Fax: (415) 454-4683 GRAY WATER SYSTEMS (Reference California Plumbing Code Chapter

More information

Environmental Management Plan (EMP)

Environmental Management Plan (EMP) SE DELI GS DRIFT MI E ORA GE RIVER MI ES MI I G ACTIVITIES A D PROPOSED EW I PIT SLIMES DISPOSAL Environmental Management Plan (EMP) Compiled for: Namdeb Diamond Corporation (Pty) Ltd Compiled by: Unit

More information

Section XXV Preconstruction Assessments and Damage Mitigation Procedures

Section XXV Preconstruction Assessments and Damage Mitigation Procedures Section XXV Preconstruction Assessments and Damage Mitigation Procedures A. Introduction - In recent years, HRSD has received an increasing number of complaints from residents and locality staff regarding

More information

A Design Review of Waterproofing Codes

A Design Review of Waterproofing Codes A Design Review of Waterproofing Codes Section 1807 of Chapter 18 of the International Building Code addresses waterproofing under the section title of Dampproofing and Waterproofing. The section defines

More information

Electric Service Standards

Electric Service Standards V: 1 of 6 A. Padmounted Requirements Complete requirements are contained in FPL specifications given to Customers for individual projects. Typical pad mounted transformer requirements include, but are

More information

LATRINE CONSTRUCTION SHELTER. Pour flush latrine 2. Pour flush micro septic tank 3. Initial investment, location, human resources 4.

LATRINE CONSTRUCTION SHELTER. Pour flush latrine 2. Pour flush micro septic tank 3. Initial investment, location, human resources 4. LATRINE CONSTRUCTION Pour flush latrine 2 Pour flush micro septic tank 3 Initial investment, location, human resources 4 Concrete rings 5 Box 6 Cover 7 Slab and ceramic pan 8 Ring mold 9 Structure and

More information

The Clean Water Act: Phase I

The Clean Water Act: Phase I Nearly 40 percent of all surveyed bodies of water in the U.S. do not meet the Environmental Protection Agency s (EPA s) water quality standards because of untreated polluted runoff that is often discharged

More information

WASTEWATER TREATMENT SYSTEM

WASTEWATER TREATMENT SYSTEM WASTEWATER TREATMENT SYSTEM PrintStudioOne.com Nelson Environmental Inc. The Nelson Environmental OPTAER system is an efficient pond-based wastewater treatment solution utilized in a broad spectrum of

More information

Your defined goals and objectives:

Your defined goals and objectives: About us GECO GmbH was founded in 1977 as a private owned business by Josef Schlusche ( 2005). The company headquarters are located in Ketsch near Heidelberg. HOME Our customers: Administrative building

More information

FACILITIES MANAGEMENT CONTRACTOR SAFETY PROGRAM

FACILITIES MANAGEMENT CONTRACTOR SAFETY PROGRAM FACILITIES MANAGEMENT CONTRACTOR SAFETY PROGRAM Document History Version Date Comments 0.1 Sept 1, 2015 Initial Draft 0.2 Sept 30, 2015 Internal Review 0.3 Jan 25, 2016 External Review 0.4 March 21, 2016

More information

Safety and Environmental Orientation and Practices for Contractors

Safety and Environmental Orientation and Practices for Contractors Safety and Environmental Orientation and Practices for Contractors Welcome to the University of California, Irvine. Some University facilities are unique and the practices listed here are for your safety

More information

Date Prepared: Location: Time: Approximate Temperature (degrees F): Weather Conditions: Project Name:

Date Prepared: Location: Time: Approximate Temperature (degrees F): Weather Conditions: Project Name: Appendix C Hazard Assessment and Trench Entry and Authorization Form for regularly scheduled and emergency trenching activities Date Prepared: Location: Time: Approximate Temperature (degrees F): Weather

More information

CITY OF TROY CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587

CITY OF TROY CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587 CITY OF TROY DESIGN STANDARDS AND CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587 JANUARY 2010 TABLE OF CONTENTS SECTION 1 SECTION 2 SECTION 3 SECTION 4 SECTION 5 SECTION 6 APPENDIX ROADWAY DESIGN DRAINAGE

More information

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION 820-1 SCOPE OF WORK: SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION a. Furnish all labor, materials, equipment, and incidentals required for demolition and/or removal and disposal of existing

More information

Government Gazette Staatskoerant

Government Gazette Staatskoerant Government Gazette Staatskoerant REPUBLIC OF SOUTH AFRICA REPUBLIEK VAN SUID AFRIKA Regulation Gazette Vol. 629 No. 10177 10 November November Regulasiekoerant 2017 No. 41237 PART 1 OF 3 N.B. The Government

More information

UNHSC Bioretention Soil Specification February, SOIL PREPARATION (PERFORMANCE SPECIFICATION) for Bioretention Systems

UNHSC Bioretention Soil Specification February, SOIL PREPARATION (PERFORMANCE SPECIFICATION) for Bioretention Systems SOIL PREPARATION (PERFORMANCE SPECIFICATION) for Bioretention Systems PART 1 - GENERAL 1.1 SUMMARY A. Section includes soil media for the bioretention systems and rain gardens specified according to performance

More information

Purification of Stormwater Using Sand Filter

Purification of Stormwater Using Sand Filter Journal of Water Resource and Protection, 2013, 5, 1007-1012 Published Online November 2013 (http://www.scirp.org/journal/jwarp) http://dx.doi.org/10.4236/jwarp.2013.511105 Purification of Stormwater Using

More information

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields 4.1-d SUBSURFACE INFILTRATION SYSTEM Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields BMP DESIGN APPROACH Pollutant Source Control Hydrologic Source Control Stormwater

More information

Foirgniochta. Marking Scheme Leaving Certificate Examination, Ordinary Level. Construction Studies

Foirgniochta. Marking Scheme Leaving Certificate Examination, Ordinary Level. Construction Studies 2000 Foirgniochta Marking Scheme Leaving Certificate Examination, 2000 Construction Studies Ordinary Level of site.. Adjoining. Distinct Landmarks.. site in Red.. 1: (ii) Site Boundary site. Site. Drainage

More information

FAYOUM CITY SEWAGE TREATMENT PLANT, DEVELOPMENT STAGES, CASE STUDY

FAYOUM CITY SEWAGE TREATMENT PLANT, DEVELOPMENT STAGES, CASE STUDY FAYOUM CITY SEWAGE TREATMENT PLANT, DEVELOPMENT STAGES, CASE STUDY Ahmed El-Zayat, Environmental Engineering Group, Egypt Emaill: ahmed_el_zayat@yahoo.com Introduction This case study focuses on three

More information

OPERATION OF AN STP FOR RECYCLED WATER PRODUCTION PLANT. Iain Fairbairn. Iain Fairbairn, Plant Manager, Sydney Water

OPERATION OF AN STP FOR RECYCLED WATER PRODUCTION PLANT. Iain Fairbairn. Iain Fairbairn, Plant Manager, Sydney Water Winner of the Actizyme Prize for Best Paper at the NSW Operators Conference held in October 2005 OPERATION OF AN STP FOR RECYCLED WATER PRODUCTION PLANT Paper Presented by : Iain Fairbairn Author: Iain

More information

Quantity of sewage. Dry weather flow: Domestic and industrial wastewater (Base flow) including inflow, infiltration and exfiltration

Quantity of sewage. Dry weather flow: Domestic and industrial wastewater (Base flow) including inflow, infiltration and exfiltration Quantity of sewage Quantity of sewage depends on Dry weather flow and storm water Dry weather flow: Domestic and industrial wastewater (Base flow) including inflow, infiltration and exfiltration Infiltration

More information

Section Safety Section Cleanup. None Required

Section Safety Section Cleanup. None Required January 2000 Page 1 of 6 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED SECTIONS PART 2 PRODUCTS The General Conditions of the Contract, General Requirements, and Supplemental

More information

0% 3% 5% &»W3. r^oqui)

0% 3% 5% &»W3. r^oqui) Bruhat Banglore Mahngr Palike Ofice Revnu ; -^ tha Ward Comisner,.Range Date i-c / Certifd the Departmn Banglore, vr; the Khat certifa Propety No. Stands No. Sri in the / Smrtl., name in the regist this

More information

SACHSE EROSION CONTROL GUIDELINES

SACHSE EROSION CONTROL GUIDELINES SACHSE EROSION CONTROL GUIDELINES Section I. Definitions The following words, terms, and phrases, when used in this guideline, shall have the meanings ascribed to them in this Section, except where the

More information

Complying with the Edwards Aquifer Rules Technical Guidance on Best Management Practices

Complying with the Edwards Aquifer Rules Technical Guidance on Best Management Practices RG-348 Revised July 2005 Complying with the Edwards Aquifer Rules Technical Guidance on Best Management Practices Field Operations Division printed on recycled paper TEXAS COMMISSION ON ENVIRONMENTAL QUALITY

More information

Product Catalogue. Not intended for design layouts; refer to the appropriate StormTech Design Manual for specific chamber design information.

Product Catalogue. Not intended for design layouts; refer to the appropriate StormTech Design Manual for specific chamber design information. Product Catalogue Not intended for design layouts; refer to the appropriate Design Manual for specific chamber design information. Subsurface Stomwater Management Specifications and Product Comparison

More information

GRAY WATER SYSTEMS FOR RESIDENTIAL BUILDINGS

GRAY WATER SYSTEMS FOR RESIDENTIAL BUILDINGS INFORMATION BULLETIN / PUBLIC - PLUMBING CODE REFERENCE NO.: LAMC 94.1502.0 Effective: 01-01-2017 DOCUMENT NO.: P/PC 2017-012 Revised: Previously Issued As: P/PC 20014-012 GRAY WATER SYSTEMS FOR RESIDENTIAL

More information

MUNICIPAL OFFICES 1481 EAST COLLEGE AVENUE, STATE COLLEGE, PA TELEPHONE: FAX:

MUNICIPAL OFFICES 1481 EAST COLLEGE AVENUE, STATE COLLEGE, PA TELEPHONE: FAX: MUNICIPAL OFFICES 1481 EAST COLLEGE AVENUE, STATE COLLEGE, PA 16801 TELEPHONE: 814-231-3021 FAX: 814-231-3020 Checklist for Submission of APPLICATION for DEMOLITION PERMIT To obtain a permit for demolition

More information

TRENCH SAFETY TRAINING

TRENCH SAFETY TRAINING TRENCH SAFETY TRAINING TRENCH SAFETY TRAINING TRENCHING ACCIDENTS ACCOUNT FOR MORE THAN 100 DEATHS A YEAR ON U.S. SOIL. 11 TIMES MORE WORKERS ARE INJURED 1% OF ALL CONSTRUCTION ACCIDENTS INJURY RATE FOR

More information

SACRAMENTO County New Animal Care Facility LEED Elements

SACRAMENTO County New Animal Care Facility LEED Elements Construction Activity Pollution Prevention We reduced pollution from construction activities by controlling soil erosion, waterway sedimentation, and airborne dust generation by creating an Erosion and

More information

F2. Vehicle and Heavy Equipment Repair and Maintenance

F2. Vehicle and Heavy Equipment Repair and Maintenance F2. Vehicle and Heavy Equipment Repair and Maintenance Commercial / Industrial / Institutional & Municipal Pollution Prevention Goal: Prevent or reduce the risk of discharge of pollutants to stormwater

More information

SAFE WORK METHOD STATEMENT

SAFE WORK METHOD STATEMENT SAFE WORK METHOD STATEMENT Principal Contractor: ROBERT LIVINGSTONE Project Address: 123 SYDNEY ROAD SYDNEY NSW 2000 High Risk Work Hazards and Risks Identified Control Measures Persons working at a height

More information