Tasman Mine. Site Water Management Plan. Peter Dundon & Associates. Updated Final. April Dakar Place, Pymble 2073

Size: px
Start display at page:

Download "Tasman Mine. Site Water Management Plan. Peter Dundon & Associates. Updated Final. April Dakar Place, Pymble 2073"

Transcription

1 Site Water Management Plan Updated Final April Dakar Place, Pymble 2073

2 Table of Contents 1 INTRODUCTION SITE CHARACTERISTICS AND FACILITIES CLIMATE SURFACE WATER AND DRAINAGE Regional Catchments Local Catchments Surface Water Quality SURFACE GEOLOGY AND SOILS MINE FACILITIES Water Requirements Roadworks and Drainage Diversion of Clean Runoff Hardstand Area and Portal Service Road Administration Centre and Amenities Pollution Control Dams SURFACE WATER MANAGEMENT OPERATION OF SURFACE WATER MANAGEMENT FACILITIES IMPACT ASSESSMENT CRITERIA SITE WATER BALANCE SURFACE WATER MONITORING Water Quality Monitoring Flow Monitoring DECOMMISSIONING OF SURFACE WATER FACILITIES GROUNDWATER REGIME AND MONITORING GROUNDWATER REGIME GROUNDWATER LEVELS GROUNDWATER QUALITY IMPACT ASSESSMENT CRITERIA MINE WATER INFLOW VOLUME AND QUALITY MONITORING GROUNDWATER LEVELS AND QUALITY MONITORING EROSION AND SEDIMENT CONTROL PLAN BACKGROUND EROSION AND SEDIMENT CONTROL GENERAL REQUIREMENTS General Erosion Control Sediment Control swmp report - updated final.doc ( i )

3 5.2.4 Site Clearing Stabilisation and Revegetation Monitoring and Maintenance WORK SCHEDULE Stage 1: Site Security and Entry Stage 2: Sedimentation Basin Stage 3: Access Road and Portal Service Road Stage 3a: Culvert Under the Access Road Stage 4: Hardstand Area and Facilities Stage 5: Loading Loop and Coal Stockpile Stage 6: Pollution Control Dams SURFACE AND GROUND WATER RESPONSE PLAN WATER FLOW MITIGATION MEASURES WATER QUALITY MITIGATION MEASURES RESPONSE TO UNFORESEEN IMPACTS swmp report - updated final.doc ( ii )

4 List of Appendices Appendix A Appendix B Appendix C Drawings Hydrologic and Hydraulic Design Surface Water Balance Analysis List of Tables Table 2.1: Long Term Rainfall Data for East Maitland Bowling Club... 2 Table 2.2: Long Term Evaporation Data for Cessnock and Paterson... 2 Table 2.3: Rainfall Intensity:Duration Data for the Tasman Mine Site... 2 Table 2.4: Cumulative Rainfall Depths (mm) over Consecutive Days... 3 Table 2.5: Estimated Annual Catchment Runoff (ML/year)... 4 Table 2.6: Surface Water Quality Blue Gum Creek Tributaries... 5 Table 2.7: Summary of Surface Soil Characteristics at the Site... 5 Table 2.8: Estimated Project Water Requirements... 7 Table 2.9: Design Features of Pollution Control Dams... 9 Table 3.1: Predicted Mine Water Inflows and Process Water Requirements Table 3.2: Summary of Surface Water Balance Analysis Table 4.1: Representative Water Quality Data for Fassifern Seam, Roof and Floor Aquifers Table 4.2: Groundwater Inflow Monitoring Program Table 4.3: Piezometer Monitoring Program Table 5.1: Soil and Site Physical Characteristics swmp report - updated final.doc ( iii )

5 1 INTRODUCTION This has been prepared to meet the specific requirements of Conditions 16 and of the Approval for the Tasman Mine project given by the Minister for Infrastructure and Planning on 16 March The concept plans presented in the EIS have been updated as a result of detailed design of the mine operations and site facilities undertaken since the EIS was prepared. In particular, the area occupied by the surface facilities and access road has reduced from 8 ha to less than 6 ha. In addition, as required in the Conditions, all water storage facilities have been relocated outside the creek lines. These changes have led to consequential modifications in the water management arrangements originally proposed in the EIS. In the course of preparation of this plan, Cessnock City Council and Lake Macquarie City Council were consulted, as required in the Minister s Conditions of Approval, and the concerns expressed by officers of both councils have been taken into account in preparing this document. In particular, it was apparent that both councils required a comprehensive document that described the design and operation of the water management facilities as well as covering the water monitoring and management issues identified in the Conditions of Approval. In order to provide the context in which various aspects of water management occur and to demonstrate compliance with Condition 16, this report provides an overview of the site layout and the final design of the water management facilities (Chapter 2) while Chapter 3 sets out details of the operation of the surface water management system and the surface water monitoring program to be implemented for the site in accordance with the requirements of Condition 20. This chapter also provides details of the actions required for decommissioning of the surface water management facilities. Chapter 4 provides details of the groundwater monitoring program in accordance with the requirements of Condition 21 while Chapter 5 presents the erosion and sediment control plan to be implemented during construction of site facilities. Finally, Chapter 6 provides details of a surface and groundwater response plan to mitigate any adverse impacts on flows or water quality in Blue Gum Creek or unforseen surface or groundwater impacts. In addition to providing a specific response to Conditions 16 and 19-23, this report also demonstrates the way in which the project has been designed and will be operated in compliance with other Conditions of Approval relating to surface and ground water management: It describes the facilities and operational measures designed to prevent and/or minimise the potential surface and ground water impacts of the development (Condition 12). It demonstrates that the only element of the project that could possibly obstruct floodwaters (namely the culvert under the access road) has adequate capacity to ensure that flood flows are not obstructed (Condition 14). It provides details of the surface water quality monitoring regime that meets the requirements of Condition 17. It provides details of the groundwater level and quality monitoring regime that meets the requirements of Condition swmp report - updated final.doc Page 1

6 2 SITE CHARACTERISTICS AND FACILITIES This chapter provides an overview of the site and the main characteristics that of relevance to this water management plan. Material for this section has been drawn from the EIS as well as subsequent detailed design work for the mine surface facilities and access road connecting the mine to George Booth Drive. 2.1 CLIMATE Table 2.1 summarises the long term rainfall record for the East Maitland Bowling Club which is the station closest to the site (13.3 km north-north-east) while Table 2.2 provides average monthly pan evaporation data for Cessnock and Patterson which are the nearest evaporation recording stations. Table 2.1: Long Term Rainfall Data for East Maitland Bowling Club Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Year Mean (mm) Decile Median Decile Highest Monthly Lowest Monthly Highest Recorded Daily Mean No of Rain days Table 2.2: Long Term Evaporation Data for Cessnock and Paterson Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Year Cessnock ,351 Paterson ,570 These data show that evaporation significantly exceeds the mean monthly rainfall during the summer months, and is similar to but marginally in excess of rainfall during the winter months. These data indicate that water will be required for dust suppression on about 250 days per year and that runoff into the site stormwater management system is likely to be ephemeral. Table 2.3 summaries the rainfall intensity:duration data for the site (as used in the design of the water conveyance and capture systems). Table 2.3: Rainfall Intensity:Duration Data for the Tasman Mine Site ARI Rainfall Duration (minutes) (years) A further climatic characteristic of relevance to this report is the rainfall erosivity which is used to assess the erosion hazard of the site. The RAINER program developed by the NSW Soil swmp report - updated final.doc Page 2

7 Conservation Service provides the following estimates derived from the same rainfall intensity data used to derive the values in Table 2.3. The erosivity estimates are: Average annual :10 year storm 1400 Table 2.4 (data derived from Managing Urban Stormwater: Soils and Construction ) provides details for the nearest quoted station (Newcastle) of cumulative depth of rainfall over consecutive days for a range of percentile probabilities (as required for sediment basin design). Table 2.4: Cumulative Rainfall Depths (mm) over Consecutive Days Percentile Duration (days) Probability % % % % % SURFACE WATER AND DRAINAGE Regional Catchments The Tasman Mining Lease is located in the vicinity of Mt Sugarloaf at the northern end of the Sugarloaf Range, 15 km west of Newcastle, and is situated near a regional divide between three catchments (Figure 1): Blue Gum Creek, which flows northeast and east to Hexham Swamp, via Lenaghans Flat; Slatey Creek and Burkes Creek catchments to the south and southeast, that in turn flow into Cockle Creek and thence into Lake Macquarie; and Surveyors Creek to the west, that flows to Wallis Creek and into the Hunter River east of Maitland. The Tasman Project lease area is covered with dry open eucalypt forest on the hilly slopes, with dense corridors of riparian vegetation along Blue Gum Creek and its tributaries in the gullies. The project site is traversed by a number of power transmission line easements that run from southwest to northeast. All surface facilities for the Tasman Mine will be located in the upper reaches of the Blue Gum Creek catchment. The total catchment area of Blue Gum Creek above Lenaghans Flat, is 1,775 ha, approximately 306 ha of which lies within the Mining Lease area. The surface facilities and access road will disturb a total area of 5.8 ha, of which about 3 ha has already been cleared of trees within power transmission easements. Of the area disturbed by the mine facilities, only 2.7 ha will be controlled to ensure that any surface water pollutants are retained within the site by achieving zero or negligible discharge. The area of controlled catchment (2.7 ha) represents less than 1% of the Blue Gum Creek catchment at George Booth Drive and less than 0.2% of the catchment above Lenaghans Flat swmp report - updated final.doc Page 3

8

9 2.2.2 Local Catchments The local tributary catchments in the vicinity of the proposed mine are shown on Figure 2. These tributaries are ephemeral, steep, immature, and devoid of significant deposits of alluvium. All surface facilities associated with the Tasman Mine (Drawing ) will be located on the ridge between Tributaries 3 and 4. The majority of the surface facilities, including the coal stockpile and loading facilities and the machinery maintenance facilities will drain via two pollution control dams that will only discharge to Tributary 3 in exceptional circumstances. A staff car park and the majority of the mine access road to George Booth Drive will drain to Tributary 4. Tributaries 1 and 2 will be unaffected by the mining facilities. The EIS presented an analysis of the estimated annual flow (based on rainfall:runoff modelling) in Blue Gum Creek where it crosses George Booth Drive (364 ha catchment) and at Lenaghans Flat (1,775 ha catchment). These estimates are summarised in Table 2.5. Table 2.5: Estimated Annual Catchment Runoff (ML/year) Rainfall Statistic Rainfall (mm) Blue Gum Lenaghans Flat Blue Gum George Booth Drive 10 th Percentile Mean 895 2, th Percentile ,125 1,056 This table indicates that the annual yield of surface water within Blue Gum Creek may vary from 15% to 220% from the annual average yield. This large variation in yield is due to the high variability in annual rainfall and the ephemeral nature of runoff from the catchment. It has been observed (Newcastle Coal Company, pers comm) that the tributaries of Blue Gum Creek in the vicinity of the mine are ephemeral and only exhibit measurable flow following significant rainfall events, being generally less than 1 L/min along the tributary and main creek lines for the remainder of the time Surface Water Quality Upstream of George Booth Drive, the tributaries of Blue Gum Creek receive runoff from the Mt Sugarloaf Reserve and vegetated slopes above the Tasman Mine surface infrastructure area. This flow is also supplemented by small, ephemeral groundwater discharges. The only existing disturbed areas in the catchment are the transmission line corridors running north/south through the eastern part of the Mining Lease, communication towers near the summit of Mt Sugarloaf, the paved access road to the Mt Sugarloaf Reserve and a number of four wheel drive tracks. Blue Gum Creek has been inspected on a number of occasions since 2001 for collection of surface water samples. However, because of the highly ephemeral nature of flow in Blue Gum Creek and the drought conditions, the only samples collected for analyses were collected on 5 September On all other occasions the creeks have been dry at the time of intended sampling. The results of the surface water sampling are shown in Table 2.6. The water sample analyses set out in Table 2.6 indicate that the electrical conductivity (EC) during periods of low flow is significantly greater than the ANZECC (2000) guideline trigger value of 350 µs/cm for upland rivers. The cause of the high EC is probably the significant contribution of groundwater seepage to low flows. Because of the similarity of water quality between the surface and groundwater, it appears that the base flow in the creek is derived predominantly from groundwater seepage swmp report - updated final.doc Page 4

10

11 Table 2.6: Surface Water Quality Blue Gum Creek Tributaries Analyte Blue Gum Creek Tributary 1 near Bore TAS011 Blue Gum Creek Downstream of Tributary 3 ph EC (µs/cm) 1,590 1,000 Total Dissolved Solids (mg/l) 1, Total Hardness (calculation) Sulphates (mg/l) Chlorides (mg/l) Total Alkalinity as CaCO3 (mg/l) Calcium (mg/l) Magnesium (mg/l) Sodium (mg/l) Potassium (mg/l) Iron (mg/l) SURFACE GEOLOGY AND SOILS The surface facilities are to be located on the crest of a ridge that is orientated approximately NNE. The eastern side of the ridge, which will only receive runoff from the staff car park and a section of the access road, drains to Tributary 4 of Blue Gum Creek. The majority of the site drains in a westerly direction to Tributary 3. The Soil Landscapes of the Gosford-Lake Macquarie 1: Sheet (Murphy 1993) indicates that the majority (approximately 80%) of the surface facilities are located on the Killingworth Soil Landscape Unit with the remainder on the Sugarloaf Soil Landscape Unit. Relevant characteristics of these soil landscape units, which have been taken into account in developing the Erosion and Sediment Control Plan for the construction phase (see Chapter 5), are summarised in Table 2.7. Table 2.7: Summary of Surface Soil Characteristics at the Site Characteristic Soil Landscape Unit Topsoil Sub-soil Killingworth Shallow (<250 mm) loamy sand to sandy clay loam on hill crests Up to 400 mm dispersible clay subsoil Sugarloaf Shallow (<200 mm)sandy clay Up to 750 mm clay sub-soil Permeability Moderate to slow permeability topsoil with low permeability subsoil Moderate permeability in both topsoil and sub-soil Erodibility K factor = (high) K factor (high) swmp report - updated final.doc Page 5

12 2.4 MINE FACILITIES The surface facilities that are relevant to this report are shown on Drawing (prepared by Geoff Craig & Associates) (see Appendix A) and include: A sealed access road to George Booth Drive suitable for both light vehicles and coal trucks; A hard-stand area for machinery including: Maintenance shed; An under cover bunded fuel storage and machinery wash-down bay; Bath-house, amenities and administration buildings; Potable water supply tank (80,000 L) and reticulation system; Rainwater tanks adjacent to all buildings; (2 x 5,000 L on administration and amenities buildings, 2 x 9,000 L on workshop building); Pump-out wastewater collection tanks (40,000 L); Bunding and contour drains to direct clean runoff around the works area and to direct dirty runoff into two pollution control dams; Conveyor gantry to link the mine portal with the coal stockpile area; Coal stockpile and truck loading area; Mine portal service road; Under-body spray wash system for coal trucks leaving the site; An unsealed section of access road between the under-body wash facility and the coal loading loop. Relevant hydrologic and hydraulic design details for these facilities are provided in Appendix B. All coal produced by the mine will be transported by truck to the Bloomfield coal washery for processing Water Requirements Water requirements for production related activities including dust suppression and truck underbody spray wash facility are estimated to be approximately 50 litres per tonne of coal extracted. The requirements for potable water for construction, administration employees and production employees are estimated to be approximately 100 litres, 75 litres and 200 litres per person per day respectively. The estimated water requirements for the 12 year life of the project are set out in Table 2.8. All potable water will be brought to site and stored in the on-site supply tank. Rainwater collected from roofs will be utilised for appropriate purposes such as toilet flushing. Maximum use will be made of all water derived on site from mine water inflows and from capture of runoff from the mine infrastructure area, in preference to importing water from outside sources. Based on the mine water balance discussed in Chapter 3, the mine may need to import some water to make up the shortfall from internal sources at certain stages in the project life. As necessary, makeup process water will be brought to site by road tanker from the Donaldson mine, which has an excess of water derived from mine water inflows and internal runoff swmp report - updated final.doc Page 6

13 Table 2.8: Estimated Project Water Requirements Year Potable Water Process Water Mon - Fri Sat Annual Mon - Fri Sat Annual (litres per day) (ML/y) (litres per day) (ML/y) Year 1 6, , Year 2 9,750 7, ,500 60, Year 3 15,125 11, , , Year 4 16,125 12, , , Year 5 16,125 12, , , Year 6 16,125 12, , , Year 7 16,125 12, , , Year 8 16,125 12, , , Year 9 16,125 12, , , Year 10 16,125 12, , , Year 11 16,125 12, , , Year 12 10,750 8, , Roadworks and Drainage As noted previously, the project roadworks comprise two components from which runoff is directed to different locations: 1. The sealed entry road that runs from George Booth Drive to the under-body spray facility for trucks located approximately at chainage 825 m. This section of road will drain towards Tributary 4 via roadside drains and mitred outlets (approximately 50 m spacing) that direct runoff away from the road. Trucks transporting coal from the site will have covered loads and will pass through an under-body spray wash facility before driving onto this section of road. Accordingly, the pollution potential from trucks on this section of road is considered to be similar to that on public roads and no stormwater pollution facilities are proposed for this section of road. In order to minimise scouring, the roadside drains will be provided with suitable scour protection where slopes exceed 5%. As shown on Drawing , the last 20 m of each mitre drain will be constructed as a level spreader to ensure that water is discharged over the slope as uniform sheet flow in order to minimise the risk of downstream gully formation. 2. An unsealed section of road to the west of the under-body spray facility, including the road loop around the coal stockpile and the coal loading area. This section of road, which will have a steelstone (modified slag) surface, will drain to the two pollution control dams (see Section 2.4.6). Runoff from Tributary 4 will be conveyed under the sealed access road from George Booth Drive by means of twin 1,500 mm diameter culverts which have been designed to convey flows in excess of the 100 year ARI flow from the catchment. Details of the hydrologic and hydraulic design of the culvert are provided in Appendix B Diversion of Clean Runoff Runoff from up-slope areas that are not disturbed by the mine facilities will be diverted away from the surface facilities and directed to Tributary 3 as shown on Drawing : A diversion drain along the upper edge of the batter leading down to the coal stockpile area and unsealed section of the access road. A culvert under the access road, as shown on Drawing , will convey drainage to a level spreader on the northern side of the road, swmp report - updated final.doc Page 7

14 Diversion drains along the southern side of both pollution control dams to divert runoff from the small up-slope catchments that are not part of the site facilities Hardstand Area and Portal Service Road The hardstand area of about 0.6 ha is located immediately north of the mine office as shown on Drawing The drainage divide between areas draining northward towards Tributary 3 and those draining to Tributary 4 lies along the southern edge of the portal service road (i.e. the portal service road and the hardstand areas all drain northward towards Tributary 3). Stormwater drainage and pollution control features of the hardstand area are: Roofed fuel storage and machinery wash-down shed (180 m 2 ) containing a 5,000 L fuel storage tank located in a separately bunded area. As required, the retention volume within the bund is 110% of the volume of the tank; An oil separator located on the northern side of the fuel storage and machinery wash-down area to treat all effluent from these facilities; A roofed workshop (450 m 2 ) with two 9,000 L rainwater tanks. The remaining surface of the hardstand area and portal service road will comprise compacted steelstone. The piped stormwater drainage system shown on Drawing will collect surface runoff and drain it to Pollution Control Dam A. Coal stockpile and loading facility The coal stockpile and loading facility comprises a loop road with a central island for a coal stockpile of up to 5,000 t. The stockpile is fed by an overhead conveyor from the mine. Truck loading will be by means of a front end loader. Before moving onto the sealed section of the main access road leading to George Booth Drive all loaded coal trucks pass through an under-body spray facility. All surface runoff from the unsealed section of the access road (to the west of the under-body spray facility), the coal stockpile area and the conveyor will be directed to Dirty Water Dams A and B via the stormwater drainage system shown on Drawing Administration Centre and Amenities All roof runoff from the administrative and amenities buildings will be directed into rainwater tanks (2 x 5,000 L). Water from the rainwater tanks will be used for toilet flushing and irrigation of the amenity planting. All runoff from the car park area will be directed to a first flush collection pond (16 m 3 capacity = 10 mm runoff from 1,600 m 2 car park) located in the south-east corner of the car park area. A perforated riser (as per Drawing SD 6-3 in Managing Urban Stormwater: Soils & Construction) will permit slow discharge from the pond to a level spreader for distribution across the hill slope that drains to Tributary 4. Water supply for showers, hand-basins, drinking and catering will be provided from an 80,000 L tank that will be replenished by road tanker. As noted in Section 2.4.1, the average daily water requirement at peak production levels is estimated to be about 16 kl/day. All grey wastewater from the administration and amenities buildings will be directed to Pollution Control Dam A while all effluent from toilet flushing and kitchens will be directed to the two septic storage tanks located adjacent to the administration building. These tanks will be emptied by a road tanker as required. No sewage treatment or effluent disposal will be undertaken on site swmp report - updated final.doc Page 8

15 2.4.6 Pollution Control Dams In line with the Minister s Consent, no dams will be constructed on any of the watercourses. Two pollution control dams are to be located within the Tributary 3 catchment on the hillside to the north of the mine facilities (see Drawing ). Both these dams have dual functions: A lower storage zone for the supply of water for the truck under-body spray facility and dust suppression on the unsealed sections of the haul road, portal service road and hardstand area. During years when there is anticipated to be a shortfall of mine inflow for operational purposes (see ), water may be taken from the pollution control dams for operational purposes; An upper sediment settlement zone (see capacity in Table 2.9) that has been sized, and will be operated, in accordance with the requirements of Condition 16 and the principles for the design and operation of Type F basins as set out in Chapter 6 of Managing Urban Stormwater: Soils & Construction (2004). In order to provide capacity for the capture and retention of runoff containing coal dust or fine sediment, the settlement zone has been designed to function as a Type F sedimentation basin based on a 90 th percentile 20 day storm. Details of the hydrologic design of the sedimentation zone are provided in Appendix B and are summarised in Table 2.9. Appendix B also provides details of the estimated rate of accumulation of coal dust in the dams on which the sediment storage zone has been determined to allow for annual cleanout of sediment. The table shows that both pollution control dams have a total storage capacity which significantly exceeds settlement zone requirements. Table 2.9: Design Features of Pollution Control Dams Dam A Dam B Catchment area (ha) Required settlement zone capacity (m 3 ) 1,800 1,200 Settlement zone depth (m) Sediment storage zone capacity (m 3 ) Water storage zone capacity (m 3 ) 3,900 2,600 Total dam storage capacity (m 3 ) 6,000 4,000 As required for the operation of Type F sediment basins, whenever the water level encroaches into the upper settlement zone, steps will be taken to ensure that the water level is drawn down below this zone within 20 days of the end the rainfall event. Further details of the operating procedures for drawdown of water within the pollution control dams are set out in Section 3.1 below swmp report - updated final.doc Page 9

16 3 SURFACE WATER MANAGEMENT 3.1 OPERATION OF SURFACE WATER MANAGEMENT FACILITIES The surface water management facilities on the site provide for the separate conveyance and management of three different classes of runoff: All clean runoff from untouched catchment areas and the sealed section of the access road will be discharged via stabilised outlets without receiving any treatment. Runoff from the staff car park will be directed into a first flush pond that will be cleaned out as necessary. Dirty runoff from areas likely to contain pollutants such as coal dust, oil and grease. Runoff from this controlled catchment (2.7 ha) will be directed to two pollution control dams. The two pollution control dams provide the primary means for minimising the volume and frequency of discharge from the controlled area of the site and provide an appropriate level of treatment for any necessary discharge. As noted in Section 2.4.6, the pollution control dams have an upper sediment settlement zone and a lower water storage zone. The dams will be operated in the following manner: While ever the water level in the dams is below the upper sediment settlement zone (as designated by a permanent marker), the dams will be operated as water storage dams that provide a source of water for various on-site purposes. Whenever the water level encroaches into the sediment settlement zone, the water level will be drawn down to the bottom of the settlement zone within 20 days after the end of rainfall in accordance with the operational requirements set out in Managing Urban Stormwater: Soils and Construction. The following priority order will be given to various options for achieving this drawdown: Utilise water for dust suppression on the unsealed sections of road, the coal stockpile and the hardstand area (average usage 40 m 3 /day). Once sufficient underground storage capacity has been generated following completion of sections of underground workings (expected to be from Year 2 onward), any excess water that cannot be utilised for dust suppression will be pumped underground. In the event of conditions in which insufficient water can be used for dust suppression and there is no underground storage capacity available, water in the dams will be flocculated using floc-blocks or gypsum in order to achieve a suspended solids concentration of less than 50 mg/l prior to controlled discharge to Tributary 3. Water extracted for discharge to the environment will be drawn from below the surface in order to ensure that any floating oil or grease is retained within the dams. Water balance analysis for the surface facilities (see Section 3.3) indicates that all surface runoff from the works area will be required for dust suppression and other on-site purposes. There is, therefore, very low probability that the pollution control dams would reach a level that would require treatment prior to discharge from the site. It is expected that the controlled catchment area will substantially operate as a zero discharge area swmp report - updated final.doc Page 10

17 3.2 IMPACT ASSESSMENT CRITERIA The principal surface water impact assessment criteria for the Tasman project are: Frequency and volume of discharge of treated runoff or uncontrolled overflow are key indicators of the performance of the surface water management system. Greater than expected accumulation of surface runoff in the pollution control ponds could occur as a result of wetter climate than represented in the historic record, greater percentage of runoff than anticipated from the controlled catchment area and/or reduced requirement for water for dust suppression or other purposes. If a greater than expected accumulation of surface runoff occurred in combination with greater than expected groundwater inflow to the workings, there would be reduced opportunity to store any excess surface runoff underground. Such a situation could result in more frequent controlled discharge of treated water and more frequent overflow of untreated water. While greater than expected accumulation of surface runoff could (if opportunities for underground storage of excess runoff were restricted at the same time) require greater expenditure on chemicals for treatment of accumulated surface runoff, the system would still be capable of operating within the design and operational guidelines in Managing Urban Stormwater: Soils & Construction in terms of the frequency and quality of any discharge. It should also be noted that the controlled catchment area constitutes less than 1% of the catchment of Blue Gum Creek above George Booth Drive. Accordingly, any changes in runoff from the site are unlikely to be measurable in the annual flow in Blue Gum Creek. Controlled discharge of treated runoff from the pollution control dams into Tributary 3 has the potential to lead to an extended period of flow above the natural base flow in the tributary. The rate of discharge (a maximum of 3 ML over, say, 10 days or 4 L/s) might impact on the riparian ecosystem in the immediate area of the discharge point by extending the period of saturation, but is unlikely to have any effect on downstream riparian ecosystems or users. The primary function of the pollution control dams is to retain water laden with coal dust or sediments for reuse within the site. If excess runoff needs to be discharged it will be treated so as to achieve an acceptable level of NFR (<50 mg/l). By extracting water for discharge from below the surface, the dams will provide a backup system for retention of any oil or grease that is not captured by the oil separator system within the refuelling and washbay area. However, the pollution control dams will have no effect on any elevated salinity or lowered ph derived from coal. 3.3 SITE WATER BALANCE Groundwater inflows to the mine workings have been estimated by the modelling on a year by year basis, and are summarised in which also includes the estimated process water requirements (50 L/t - which includes the underground mining process, dust suppression and the under-body spray wash facility). In order to provide an overview of the year by year water balance for the mine, Table 3.1 includes the average annual surface runoff into the surface water pollution control dams (7.1 ML/year) derived from the surface water balance analysis that is summarised in Table swmp report - updated final.doc Page 11

18 Stage of Project Table 3.1: Predicted Mine Water Inflows and Process Water Requirements Coal Productio n Groundwater Inflows to Workings Surface Runoff to Pollution Control Dams Mine Process Water Requirement s Water Supply Surplus / (Shortfall) Cumulative Surplus / (Shortfall) (t/year) ML/year ML/year ML/year ML/year ML/year Pre- Nil Mining Year 1 330, Year 2 507, Year 3 975, Year 4 975, Year 5 975,000 Negligible Year 6 975, Year 7 975, Year 8 975, Year 9 975, Year , Year , Year ,000 Negligible Post- Mining Nil The table shows that there is an estimated shortfall in process water from groundwater inflow during Years 3, 5, 6, 11 and 12. However it can be seen that the cumulative predicted water balance is positive for all years. For Year 1, water required for the mining process (including dust suppression) will be derived from a combination of groundwater inflow and surface runoff. If necessary, additional water will be brought to site by road tanker. Priority will be given to use of surface runoff for dust suppression and under-body spray wash facility in order to minimise the chance of overflow from the pollution control dams. By Year 2, it is expected that an area at a lower elevation than the rest of the mine will be worked out and will be available for use as a sump for underground storage of surplus water. There will be sufficient storage capacity in that area to accommodate any surplus groundwater inflows that occur from Year 2 onwards as well as any surplus surface runoff collected in the surface water pollution control dams. As noted earlier, the main risk of surface water discharge will occur during Years 1 and 2 prior to sufficient void space becoming available underground to permit the storage of any excess surface runoff collected in the pollution control dams. Water balance modelling for the surface water management system has been undertaken using 16 years of daily climatic data to ascertain the likely volumes of surface runoff and the ability of the mine to use the water for dust suppression. Table 3.2 summarises the results of the daily water balance analysis, details of which are set out in Appendix C swmp report - updated final.doc Page 12

19 Table 3.2: Summary of Surface Water Balance Analysis Average Rainfall Climatic Conditions 1 in 10 (Dry) Median Rainfall 1 in 10 (Wet) Rainfall (mm) ,133 Evapotranspiration (mm) 1,184 1,317 1,148 1,082 Runoff (ML) Water Demand (ML) Controlled Discharge (ML) Overflow (ML) Dams Empty (days) In the table, Water Demand is based on the assessed requirement for dust suppression on the unsealed roads and the hardstand area and takes account of those days on which sufficient rainfall occurs for there to be no requirement for dust suppression. Controlled Discharge accounts for those occasions on which water within the settlement zone cannot be fully utilised for dust suppression within 20 days of the rainfall event and therefore requires transfer to the underground workings or treatment prior to discharge to Tributary 3. Overflow relates to those occasions in which the storm runoff exceeds the capacity of the dams, resulting in uncontrolled overflow from the dams. The analysis shows that: Water demand for dust suppression is likely to exceed the available volume generated by surface runoff even in wet years. The additional water for dust suppression will be drawn from underground workings (see ) or supplied by road tanker if there is a short-term shortage; Under conditions where the pollution control dams are operated in compliance with the operating procedures for Type F dams, even in a 1 in 10 wet year, only about 0.9 ML of water would need to be discharged to the underground workings or treated (by flocculation) prior to discharge; Even in a 1 in 10 wet year there is negligible chance of uncontrolled overflow occurring. It can be seen that even during the years prior to underground water storage capacity becoming available, there is only a small risk that some water might need to be treated prior to discharge into Tributary 3. Once underground storage capacity becomes available, the controlled catchment will be able to operate as a zero discharge area. 3.4 SURFACE WATER MONITORING The primary objective of the surface water management system is to retain and use as much runoff as possible within the controlled catchment area and thereby minimise any adverse impact on water quality in the creeks. The surface water balance modelling (see above) indicates that onsite uses will utilise all surface runoff in all years except very wet years. As noted previously, once sufficient underground storage capacity becomes available, any excess surface runoff will be directed underground for storage. The surface water balance modelling indicates that until underground storage becomes available, approximately 0.9 ML would need to be treated for discharge in a 1 in 10 wet year. Such discharge would be necessary on about 10 days. Under this operating regime, there is a small chance (about 1 in 5) that pumped discharge of treated water swmp report - updated final.doc Page 13

20 would be necessary on one occasion during Years 1 and 2. The chance of an uncontrolled overflow is negligible. It can be seen, therefore, that the water management system is expected to provide a significantly higher standard of environmental protection than would be achieved by the design and operating standards set out in the Conditions of Approval (ie strict compliance with the requirements of Managing Urban Stormwater: Soils and Construction which could be expected to give rise to uncontrolled overflow several times per year) Water Quality Monitoring Given that treated discharge or overflow from the pollution control dams is likely to be a rare event, the following monitoring regime will be implemented: Monthly baseline sampling and analysis of any flow in Blue Gum Creek at George Booth Drive (downstream of the site) and near Bore TAS011 (upstream of the site on Tributary 1). These samples will be sent for analysis of the following analytes: NFR Turbidity ph Conductivity On any occasions when there is treated discharge or overflow from either of the pollution control dams, daily water samples will be collected from the discharge point and from Blue Gum Creek at George Booth Drive and sent for analysis of the same suite of analytes listed above. Monthly sampling and analysis of any flow in Tributary 4 downstream of the access road. These samples will be sent for analysis of the following analytes: NFR Turbidity Oil & Grease ph Conductivity The water quality analyses from Tributary 4 will be reviewed annually. If, after two years of monitoring, the monitoring indicates no contribution to NFR or oil & grease as a result of the development, then the monitoring may be discontinued Flow Monitoring Condition 20(c) requires that flow monitoring in Blue Gum Creek be undertaken. At George Booth Drive, Blue Gum Creek has a catchment of 364 ha of which only 2.7 ha (<1%) would be subject to controlled runoff by the pollution control dams. The relatively small area of controlled catchment is unlikely to make any measurable difference to high flows. Investigations undertaken for the EIS indicated that there are a number of seeps and springs which are considered to provide an important base flow groundwater contribution to the flow in Blue Gum Creek. However, the flow from these groundwater sources is only likely to be apparent in the creek under very low flow conditions and will not be apparent during episodic surface runoff events. (Note that during the recent drought there was frequently no flow in Blue Gum Creek at George Booth Drive either as a result of reduced flow from groundwater or increased evaporation and seepage loss in the creek system.) swmp report - updated final.doc Page 14

21 Because of the perceived importance of groundwater seeps and springs to the base flow in Blue Gum Creek and any dependent ecosystems, the flow monitoring regime will be focussed on monitoring the climatic and seasonal variability in base flow and any changes that might occur as a result of the underground mining operations. The following arrangements are proposed: Construct a small 90 o V notch weir within the constructed low flow channel immediately upstream of the culvert that conveys Blue Gum Creek under George Booth Drive. A 150 mm high V notch weir will be capable of measuring flows up to 10 L/s. This height of V notch weir will not have any significant effect on the hydraulic capacity of the culvert. For flows greater than 10 L/s, flow assessment will be dependent on a depth:discharge rating relationship for the culvert that takes account of the dimensions and hydraulic characteristics of the culvert. This analysis will provide reasonable estimates of peak discharge but, because of the width of the culvert, will not be capable of providing good estimates of the mid-low flow range (10 L/s to about 500 L/s). An ultrasonic water level sensor connected to a datalogger will provide a continuous record water level. Data from the datalogger will be down loaded every three months and interpreted to determine the flow pattern and the total flow volume. 3.5 DECOMMISSIONING OF SURFACE WATER FACILITIES The following works will be undertaken to decommission the pollution control dams, which are the main significant structures within the surface water management facilities: Pump any water remaining in the pollution control dams into the underground workings. Alternatively, if underground storage is not available, treat the water prior to discharge to Tributary 3; Backfill the dams using material from the embankments; Revegetate the area using seed from vegetation endemic to the area (see Section 5.2.5). In the event that the access road is decommissioned, erosion and sediment control techniques similar to those outlined in Chapter 5 will be employed where the road embankment is excavated and the culvert removed swmp report - updated final.doc Page 15

22 4 GROUNDWATER REGIME AND MONITORING 4.1 GROUNDWATER REGIME Aquifers in the immediate vicinity of the Tasman Project lease are limited to very minor alluvial deposits associated with existing drainage channels (eg. headwaters of Blue Gum Creek and Wallis Creek), and the deep hardrock coal measures aquifers. The alluvial aquifers in proximity to the mine lease are not exploited due to their limited storage potential. They are recharged entirely from rainfall and local runoff and tend to deplete rapidly during dry spells. Groundwater in the coal measures sediments occurs mostly within the Fassifern coal seam (and other deeper seams) as brackish to saline water stored in and flowing through limited permeability developed in cleats and joints. Groundwater also occurs in the overburden and underburden sediments, which comprise conglomerates, sandstones and siltstones offering very low intergranular porosity and permeability and limited secondary storage in joints. The identifiable aquifers within the potential zone of project impact are therefore: the Fassifern coal seam; overburden sediments in the immediate roof of the Fassifern seam; floor sediments, below the Fassifern seam; and surficial alluvium (very limited, and believed to be an ephemeral aquifer). Piezometers were installed to monitor the coal measures aquifers, viz: ODO003, TAS009a, TAS011 and TAS014a Fassifern Seam; TAS009b, TAS010, TAS012 and TAS014b Roof aquifers; and TAS013 Floor aquifer. The piezometers were monitored from July 2000 until October They were all constructed as standpipe piezometers within former coal exploration drillholes, some in very deep holes, and have proven to have a limited life. Recent inspection revealed that all the previous piezometers have become inoperative, and they are currently being replaced by a new piezometer network. 4.2 GROUNDWATER LEVELS Water level hydrographs for the above piezometers are shown in Figures 3 and 4. Piezometer locations are shown on Figure 5. The hydrographs show limited correlation with rainfall recharge, although clearly rainfall on the ground surface immediately above the project site is the recharge source for the groundwater contained within both the coal and the roof and floor aquifers. Piezometer observations indicate that groundwater levels are generally located within the Fassifern seam, or in some places slightly above the top of the seam. The Fassifern seam is therefore only partly saturated, and would behave as an unconfined aquifer. Piezometer levels measured in the overburden piezometers (TAS09a, TAS010 and TAS012) are interpreted to represent a perched aquifer (or aquifers) above the Fassifern seam swmp report - updated final.doc Page 16

23 GROUNDWATER LEVEL HYDROGRAPHS - FASSIFERN SEAM 180 ODO003 TAS009a TAS011 TAS014a 160 GROUNDWATER LEVEL (m AHD) Jan Jan Jan Jan Jan Jan Jan-06 Date

24 GROUNDWATER LEVEL HYDROGRAPHS - ROOF and FLOOR AQUIFERS TAS009b TAS010 TAS012 TAS014b TAS GROUNDWATER LEVEL (mahd) Jan Jan Jan Jan Jan Jan Jan-06 Date

25

26 4.3 GROUNDWATER QUALITY Water samples were collected approximately monthly from most bores between September 2001 and October Sampling was very difficult from the deep piezometers TAS009a and b and TAS010, and only limited sampling was carried out on those bores. Representative water quality data for the Fassifern Seam, roof and floor aquifers are summarised in Table 4.1. Table 4.1: Representative Water Quality Data for Fassifern Seam, Roof and Floor Aquifers 1 Aquifer Type Fassifern Seam Roof Aquifers Floor Aquifers Bores ODO003, TAS011 TAS014a TAS009b, TAS010, TAS012 TAS013 ph EC (µs/cm) Total Dissolved Solids (mg/l) Total Hardness as CaCO 3 (mg/l) Sulphates (mg/l) Chlorides (mg/l) Total Alkalinity as CaCO 3 (mg/l) < Calcium (mg/l) Magnesium (mg/l) Sodium (mg/l) Potassium (mg/l) Iron (mg/l) Sodium Absorption Ratio (calc) CaCO 3 Saturation Index -1.8 to to to to -0.6 Generally, the groundwater quality is potable to sub-potable in the Fassifern seam, and brackish in the roof and floor aquifers. ph is slightly acidic, however repeat sampling from TAS014a revealed a persistent low ph in the range 4-5, indicating the presence of some moderately acidic pockets within the aquifer. Ephemeral streamflow in the upper tributaries of Blue Gum Creek may be supported by groundwater baseflow. Water quality sampling on the rare occasions when these streams flowed revealed salinity in the range mg/l TDS, and ph in the range 6.1 to Data shown in table are ranges of measured values. Insufficient data have been collected for meaningful statistical analysis swmp report - updated final.doc Page 17

Urban Rainwater Harvesting Systems: Promises and Challenges

Urban Rainwater Harvesting Systems: Promises and Challenges TheWaterChannel Webinar #5 Urban Rainwater Harvesting Systems: Promises and Challenges By Vishwanath S Zenrainman@gmail.com www.ircsa.org www.rainwaterclub.org Thanks for coming. The webinar will begin

More information

APPENDIX 8. Surface Water Management

APPENDIX 8. Surface Water Management APPENDIX 8 Surface Water Management Readymix Holdings Pty Limited Surface Water Assessment Proposed Lynwood Quarry, Marulan May 2005 Surface Water Assessment Proposed Lynwood Quarry, Marulan Table of Contents

More information

Section 8: Amended Soil Mounds. 8. Amended Soil Mounds

Section 8: Amended Soil Mounds. 8. Amended Soil Mounds Section 8: Amended Soil Mounds 8. Amended Soil Mounds 8. Amended Soil Mounds 8.1 Design...95 8.2 Installation...96 8.3 Inspection...101 8.4 Operation...101 8.5 Common technical issues...105 8.6 Case study...105

More information

E. STORMWATER MANAGEMENT

E. STORMWATER MANAGEMENT E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson

More information

Pennsylvania Stormwater Best Management Practices Manual. Chapter 3. Stormwater Management Principles and Recommended Control Guidelines

Pennsylvania Stormwater Best Management Practices Manual. Chapter 3. Stormwater Management Principles and Recommended Control Guidelines Pennsylvania Stormwater Best Management Practices Manual Chapter 3 Stormwater Management Principles and Recommended Control Guidelines 363-0300-002 / December 30, 2006 Chapter 3 Stormwater Management Principles

More information

Water sensitive urban design. Developing design objectives for urban development in South East Queensland

Water sensitive urban design. Developing design objectives for urban development in South East Queensland Water sensitive urban design Developing design objectives for urban development in South East Queensland Version 2-8 November 2007 Contents Contents......... ii Executive Summary............1 1 Introduction.........1

More information

HYDROGEOLOGY OF THE HUMBOLDT RIVER BASIN, IMPACTS OF OPEN-PIT MINE DEWATERING AND PIT LAKE FORMATION

HYDROGEOLOGY OF THE HUMBOLDT RIVER BASIN, IMPACTS OF OPEN-PIT MINE DEWATERING AND PIT LAKE FORMATION HYDROGEOLOGY OF THE HUMBOLDT RIVER BASIN, IMPACTS OF OPEN-PIT MINE DEWATERING AND PIT LAKE FORMATION June, 2015 Tom Myers, Ph.D., Hydrologic Consultant, Reno NV tom_myers@charter.net Prepared for: Progressive

More information

Application for resource consent Form B Damming and diversion of water

Application for resource consent Form B Damming and diversion of water Application for resource consent Form B Damming and diversion of water Notes Resource use activities must meet all the conditions of any relevant Permitted Activity Rules in the Waikato Regional Plan or

More information

Stormwater Attenuation Systems Sustainable Drainage Solutions for Domestic & Commercial Applications

Stormwater Attenuation Systems Sustainable Drainage Solutions for Domestic & Commercial Applications Environmental Stormwater Attenuation Systems Sustainable Drainage Solutions for Domestic & Commercial Applications Sustainable, Reliable, Affordable Stormwater Attenuation Systems Sustainable Drainage

More information

Muskeg River Mine Dedicated Disposal Area (DDA) Plan for In-pit Cell 1

Muskeg River Mine Dedicated Disposal Area (DDA) Plan for In-pit Cell 1 Muskeg River Mine Dedicated Disposal Area (DDA) Plan for In-pit Cell 1 Updated: November 2010 Directive 74 Appendix C Requirement Approval: 8512D Submitted to SHELL CANADA ENERGY MRM DDA PLAN-UPDATE NOV

More information

Temporary Watercourse Crossing: Culverts

Temporary Watercourse Crossing: Culverts Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol

More information

Pahiatua Waste Water Treatment Plant Wetland Erosion and Sediment Control Plan (ESCP)

Pahiatua Waste Water Treatment Plant Wetland Erosion and Sediment Control Plan (ESCP) Tararua District Council Pahiatua Waste Water Treatment Plant Wetland Erosion and Sediment Control Plan (ESCP) NOTE: This is a draft ESCP in current preparation. Additional and updated information will

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

Cochise Hall Water Harvesting / Storm water Management - Class Project

Cochise Hall Water Harvesting / Storm water Management - Class Project 1 The modern water harvesting movement is part of a broader change, or paradigm shift, in how water is treated on sites. And that is the shift from viewing water as a problem to seeing it as a resource.

More information

Advice to decision maker on coal mining project

Advice to decision maker on coal mining project . Advice to decision maker on coal mining project IESC 2015-063: West Muswellbrook Project New Development Requesting agency The New South Wales Mining and Petroleum Gateway Panel Date of request 27 January

More information

UNIVERSITY OF OREGON NORTH CAMPUS CONDITIONAL USE PERMIT PROJECT Draft Conditional Use Permit Stormwater, Sanitary Sewer, and Water Analysis Report

UNIVERSITY OF OREGON NORTH CAMPUS CONDITIONAL USE PERMIT PROJECT Draft Conditional Use Permit Stormwater, Sanitary Sewer, and Water Analysis Report UNIVERSITY OF OREGON NORTH CAMPUS CONDITIONAL USE PERMIT PROJECT Draft Conditional Use Permit Stormwater, Sanitary Sewer, and Water Analysis Report Prepared for: Cameron McCarthy Landscape Architects LLP

More information

WATERSHED. Maitland Valley. Report Card 201

WATERSHED. Maitland Valley. Report Card 201 Maitland Valley WATERSHED Report Card 201 The Maitland Valley Conservation Authority has prepared this report card as a summary on the state of our forests, wetlands, surface water, and ground water resources.

More information

Section SNOW DISPOSAL SITE DESIGN CRITERIA

Section SNOW DISPOSAL SITE DESIGN CRITERIA Section 2.150 SNOW DISPOSAL SITE DESIGN CRITERIA 2.150 A. Introduction Snow disposal sites provide storage areas for snowfall that exceeds the storage capacity of street rights-of-way and other public

More information

Constructed Wetland Use in Nonpoint Source Control

Constructed Wetland Use in Nonpoint Source Control Constructed Wetland Use in Nonpoint Source Control Description Constructed wetlands are excavated basins with irregular perimeters and undulating bottom contours into which wetland vegetation is purposely

More information

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR GRASSED WATERWAYS. Definition. Purpose

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR GRASSED WATERWAYS. Definition. Purpose STANDARD FOR GRASSED WATERWAYS Definition A natural or constructed watercourse shaped or graded in earth materials and stabilized with suitable vegetation for the safe conveyance of runoff water. Purpose

More information

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK PROVINCE OF NEW BRUNSWICK DEPARTMENT OF ENERGY AND RESOURCE DEVELOPMENT Minerals and Petroleum Development Branch GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK Guide to the

More information

STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW

STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW SUBCHAPTER 8 STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW 7:45-8.1 Purpose and scope of review Except for those projects expressly exempted by this chapter or waived by the Commission, the Commission

More information

Taking the pain out of the treatment train: continuous simulation modelling for integrated water management

Taking the pain out of the treatment train: continuous simulation modelling for integrated water management Engineers & Consultants Taking the pain out of the treatment train: continuous simulation modelling for integrated water management Stu Farrant & Reuben Ferguson, Morphum Environmental Limited Abstract

More information

6.1 Introduction to Wastewater Issues

6.1 Introduction to Wastewater Issues Section 6: Water Pollution This Section will help you: Understand if you generate industrial wastewater; Understand where your wastewater goes; Make sure you meet requirements for floor drains; Properly

More information

Stormwater Management System Project Review

Stormwater Management System Project Review TRANSIT NEW ZEALAND SH1 AVALON DRIVE BYPASS Project Review TRANSIT NEW ZEALAND TRANSIT NEW ZEALAND SH1 AVALON DRIVE BYPASS Project Review Prepared By Emma Innocente Environmental Engineer Cedric Malaval

More information

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY WHITE BLUFF PLANT CLASS 3N LANDFILL PERMIT NO S3N-R3 AFIN:

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY WHITE BLUFF PLANT CLASS 3N LANDFILL PERMIT NO S3N-R3 AFIN: 2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY WHITE BLUFF PLANT CLASS 3N LANDFILL PERMIT NO. 0199-S3N-R3 AFIN: 35-00110 JANUARY 15, 2016 ENTERGY WHITE BLUFF PLANT CLASS 3N LANDFILL 2015 ANNUAL ENGINEERING

More information

E7. Taking, using, damming and diversion of water and drilling

E7. Taking, using, damming and diversion of water and drilling E7. Taking, using, damming and diversion of water and drilling E7.1. Introduction Taking, using, damming and diversion of surface water and groundwater provisions in this plan apply in accordance with

More information

FACTSHEET INTRODUCTION. help rebalance the water cycle, mitigate the effects of climate change and improve human health and livelihoods.

FACTSHEET INTRODUCTION. help rebalance the water cycle, mitigate the effects of climate change and improve human health and livelihoods. 1 FACTSHEET INTRODUCTION World Water Day, on 22 March every year, is about focusing attention on the importance of water. This year s theme, Nature for Water, explores nature-based solutions (NBS) to the

More information

Geoenvironmental impact assessment of a landfill for solid chemical wastes

Geoenvironmental impact assessment of a landfill for solid chemical wastes ALOJZY SZYMAŃSKI, ZBIGNIEW LECHOWICZ, KAZIMIERZ GARBULEWSKI Department of Geotechnical Engineering, Warsaw Agricultural University SGGW, Poland Geoenvironmental impact assessment of a landfill for solid

More information

PHASE I ERNEST MINE COMPLEX. The objective of the project was to develop an economically feasible, safe

PHASE I ERNEST MINE COMPLEX. The objective of the project was to develop an economically feasible, safe PHASE I ERNEST MINE COMPLEX Project Objectives The objective of the project was to develop an economically feasible, safe method of diverting all flows from the Ernest Mine Complex to a central discharge

More information

CHAPTER FIVE Runoff. Engineering Hydrology (ECIV 4323) Instructors: Dr. Yunes Mogheir Dr. Ramadan Al Khatib. Overland flow interflow

CHAPTER FIVE Runoff. Engineering Hydrology (ECIV 4323) Instructors: Dr. Yunes Mogheir Dr. Ramadan Al Khatib. Overland flow interflow Engineering Hydrology (ECIV 4323) CHAPTER FIVE Runoff Instructors: Dr. Yunes Mogheir Dr. Ramadan Al Khatib Overland flow interflow Base flow Saturated overland flow ١ ٢ 5.1 Introduction To Runoff Runoff

More information

M.L. Kavvas, Z. Q. Chen, M. Anderson, L. Liang, N. Ohara Hydrologic Research Laboratory, Civil and Environmental Engineering, UC Davis

M.L. Kavvas, Z. Q. Chen, M. Anderson, L. Liang, N. Ohara Hydrologic Research Laboratory, Civil and Environmental Engineering, UC Davis Assessment of the Restoration Activities on Water Balance and Water Quality at Last Chance Creek Watershed Using Watershed Environmental Hydrology (WEHY) Model M.L. Kavvas, Z. Q. Chen, M. Anderson, L.

More information

Chapter 2: Aquifers and groundwater

Chapter 2: Aquifers and groundwater Chapter 2: Aquifers and groundwater Groundwater movement through aquifers is driven by differences in groundwater levels or pressure and is controlled by how porous the material is that it passes through.

More information

INSTRUCTIONS FOR SUBMITTING A COMMERCIAL SEWAGE DISPOSAL PERMIT APPLICATION

INSTRUCTIONS FOR SUBMITTING A COMMERCIAL SEWAGE DISPOSAL PERMIT APPLICATION Permits will be processed only when ALL required information is provided Application MUST be accompanied by the following: Property address or road location with distance from nearest intersection. IT

More information

Our Eastern Shore Groundwater Part IV Groundwater Quality on the Eastern Shore: How safe is our groundwater and are there ways we can protect it?

Our Eastern Shore Groundwater Part IV Groundwater Quality on the Eastern Shore: How safe is our groundwater and are there ways we can protect it? Our Eastern Shore Groundwater Part IV Groundwater Quality on the Eastern Shore: How safe is our groundwater and are there ways we can protect it? Britt McMillan, Malcolm Pirnie, Inc. Mercury Venus Mars

More information

TECHNICAL GUIDANCE DOCUMENT APPENDICES

TECHNICAL GUIDANCE DOCUMENT APPENDICES XIV.4. Harvest and Use BMP Fact Sheets (HU) HU-1: Above-Ground Cisterns Cisterns are large rain barrels. While rain barrels are less than 100 gallons, cisterns range from 100 to more than 10,000 gallons

More information

Erosion & Sedimentation Control Policy

Erosion & Sedimentation Control Policy Issue Date 10/22/2010 Page 1 of 8 Erosion & Sedimentation Control Policy Introduction: Soil erosion is the removal of soil by water, wind, ice or gravity and sediment deposition occurs when the rate of

More information

This unofficial translation of. Ministerial Decision No 421/1998. was downloaded from METS is not the copyright owner.

This unofficial translation of. Ministerial Decision No 421/1998. was downloaded from  METS is not the copyright owner. Disclaimer This unofficial translation of Ministerial Decision No 421/1998 was downloaded from www.mets-oman.com. METS is not the copyright owner. METS is not responsible for the content of this document.

More information

Paraprofessional Training Session 1

Paraprofessional Training Session 1 Paraprofessional Training Session 1 Part 2: Stormwater Basics November 26, 2012 Rutgers University, Cook Campus Christopher C. Obropta, Ph.D., P.E. Extension Specialist in Water Resources Associate Professor

More information

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields

SUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields 4.1-d SUBSURFACE INFILTRATION SYSTEM Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields BMP DESIGN APPROACH Pollutant Source Control Hydrologic Source Control Stormwater

More information

Filter Tube Barriers (Instream)

Filter Tube Barriers (Instream) Filter Tube Barriers (Instream) INSTREAM PRACTICES Flow Control No Channel Flow Dry Channels Erosion Control Low Channel Flows Shallow Water Sediment Control High Channel Flows Deep Water Symbol Photo

More information

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by

More information

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS WATER RESOURCES MANAGEMENT DIVISION Water Investigations Section

More information

MODEL Stormwater Local Design Manual. City of Centerville

MODEL Stormwater Local Design Manual. City of Centerville MODEL Stormwater Local Design Manual City of Centerville Adopted December 6, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 1 2.1. DETENTION REQUIREMENTS... 1 2.1.1. Discharge

More information

THE ABATEMENT PLAN. beneficial abatement plan. For the purpose of defining the pollution potential of surface waters

THE ABATEMENT PLAN. beneficial abatement plan. For the purpose of defining the pollution potential of surface waters THE ABATEMENT PLAN GENERAL PLAN Preventing surface waters from entering deep mine workings apparently offers the most beneficial abatement plan. For the purpose of defining the pollution potential of surface

More information

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department 2017 [Type a quote from the document or the summary of an interesting point. You can position the text box anywhere in the document. Use the Drawing Tools tab to change the formatting of the pull quote

More information

Stormwater Local Design Manual For Houston County, Georgia

Stormwater Local Design Manual For Houston County, Georgia Stormwater Local Design Manual For Houston County, Georgia Adopted November 15, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 2 2.1. DETENTION REQUIREMENTS... 2 2.1.1.

More information

TORO ENERGY LAKE MAITLAND DEWATERING AND WATER BALANCE REVIEW

TORO ENERGY LAKE MAITLAND DEWATERING AND WATER BALANCE REVIEW DATE 9 June 2015 PROJECT No. TO John Baines Toro Energy Ltd CC FROM Greg Hookey, Geneviève Marchand EMAIL ghookeyr@golder.com.au TORO ENERGY LAKE MAITLAND DEWATERING AND WATER BALANCE REVIEW 1.0 INTRODUCTION

More information

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

Created by Simpo PDF Creator Pro (unregistered version)  Asst.Prof.Dr. Jaafar S. Maatooq Lect.No.9 2 nd Semester Barrages, Regulators, Dams 1 of 15 In order to harness the water potential of a river optimally, it is necessary to construct two types of hydraulic structures, as shown in Figure

More information

I/I Analysis & Water Balance Modelling. Presented by Paul Edwards

I/I Analysis & Water Balance Modelling. Presented by Paul Edwards I/I Analysis & Water Balance Modelling Presented by Paul Edwards Contents Background Wet Weather Model Calibration Inflow / Infiltration Assessment Flow Containment Options Water Balance Model 20 Year

More information

TEMPORARY SEDIMENT TRAP CODE

TEMPORARY SEDIMENT TRAP CODE ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY SEDIMENT TRAP CODE 960 Source: DEFINITION A small temporary stormwater storage structure designed to trap sediment. PURPOSE The purpose of this practice

More information

Constructed Wetland Channel T-9

Constructed Wetland Channel T-9 Description A constructed wetland channel is a conveyance BMP that is built, in part, to enhance stormwater quality. Constructed wetland channels use dense vegetation to slow down runoff and allow time

More information

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination Highway Drainage Proper drainage is a very important consideration in design of a highway. Inadequate drainage facilities can lead to premature deterioration of the highway and the development of adverse

More information

Issue paper: Aquifer Water Balance

Issue paper: Aquifer Water Balance Issue paper: Aquifer Water Balance 1. Introduction And Background 1.1. Purpose and Scope The population in Kitsap County has grown rapidly in recent years and is expected to increase substantially in the

More information

Evaluation of Void Water intercepted by Werris Creek Coal Mine Operations

Evaluation of Void Water intercepted by Werris Creek Coal Mine Operations Evaluation of Void Water intercepted by Werris Creek Coal Mine Operations Prepared for: Werris Creek Coal Pty Ltd Prepared by: Australia Pty Ltd Date: 10 April 2014 Project Number: 10 April 2014 Prepared

More information

16.0 Water Quality Management Criteria for Developed Land

16.0 Water Quality Management Criteria for Developed Land October 2003, Revised February 2005 Criteria for Developed Land Page 1 16.1 Introduction 16.0 Water Quality Management Criteria for Developed Land Stormwater quality control is an integral part of any

More information

The surface water hydrology of the site has been logically divided into six phases of monitoring, analyses, and investigation as outlined below:

The surface water hydrology of the site has been logically divided into six phases of monitoring, analyses, and investigation as outlined below: SURFACE WATER HYDROLOGY The surface water hydrology of the site has been logically divided into six phases of monitoring, analyses, and investigation as outlined below: Sample Station Locations and Descriptions

More information

Rainwater Management. Dr. Iftikhar Ahmad. College of Earth and. University of The Punjab Lahore

Rainwater Management. Dr. Iftikhar Ahmad. College of Earth and. University of The Punjab Lahore Rainwater Management in Major Cities of Punjab Dr. Iftikhar Ahmad College of Earth and Environmental Sciences. University of The Punjab Lahore Need For Rainfall Harvesting in Urban Areas of Punjab Groundwater

More information

Municipal Stormwater Ordinances Summary Table

Municipal Stormwater Ordinances Summary Table APPENDIX F Municipal Ordinances Summary Table Municipality Abington Bryn Athyn Borough Hatboro Borough Ordinance, SALDO Runoff equals pre post Erosion Sediment Control Water Quality Requirements Any which

More information

The Proposed Auckland Unitary Plan (notified 30 September 2013)

The Proposed Auckland Unitary Plan (notified 30 September 2013) ART 3 REGIONAL AND DISTRICT RULES»Chapter H: Auckland wide rules»4 Natural resources» 4.14 Stormwater management Introduction The roposed Auckland Unitary lan (notified 30 September 2013) This section

More information

Water Resources on PEI: an overview and brief discussion of challenges

Water Resources on PEI: an overview and brief discussion of challenges Water Resources on PEI: an overview and brief discussion of challenges Components: Components and links Atmospheric water Surface water (including glacial water) Groundwater Links: Precipitation (atm(

More information

Constructed Wetland Pond T-8

Constructed Wetland Pond T-8 Constructed Wetland Pond T-8 Description A constructed wetlands pond is a shallow retention pond designed to permit the growth of wetland plants such as rushes, willows, and cattails. Constructed wetlands

More information

Flood risk management and land use planning in changing climate conditions Mikko Huokuna Finnish Environment Institute, SYKE

Flood risk management and land use planning in changing climate conditions Mikko Huokuna Finnish Environment Institute, SYKE 10th International Drainage Workshop of ICID 06.-11. July 2008 Flood risk management and land use planning in changing climate conditions Mikko Huokuna Finnish Environment Institute, SYKE Background hydrological

More information

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment. POND SITE SELECTION AND CONSTRUCTION Uses, Planning, & Design David Krietemeyer Area Engineer USDA-NRCS June 20, 2008 Uses Considerations for Location of Commonly Used Terms Pond A water impoundment made

More information

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO S3N-R2 AFIN:

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO S3N-R2 AFIN: 2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO. 0200-S3N-R2 AFIN: 32-00042 JANUARY 15, 2016 ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL 2015 ANNUAL ENGINEERING

More information

Lecture 9A: Drainage Basins

Lecture 9A: Drainage Basins GEOG415 Lecture 9A: Drainage Basins 9-1 Drainage basin (watershed, catchment) -Drains surfacewater to a common outlet Drainage divide - how is it defined? Scale effects? - Represents a hydrologic cycle

More information

Construction of Dariali HEPP. Reinstatement Plan

Construction of Dariali HEPP. Reinstatement Plan Construction of Dariali HEPP Reinstatement Plan 2016 Table of Content 1. Introduction... 3 2. Site Clean-up... 4 3. Headwork Site Reinstatement... 4 4. Reinstatement Of The Pipeline Corridor.9 5. Cable

More information

Municipal Stadium Wetland

Municipal Stadium Wetland W A T E R S H E D F A C T S Total watershed area 140 mi 2 Average annual rainfall 38 in Average annual temperature 58 F Elevation Max 1321 ft Min 899 ft C. J. Brown Reservoir controls flow from 83 mi 2

More information

Chapter 21 Stormwater Management Bylaw

Chapter 21 Stormwater Management Bylaw Chapter 21 Stormwater Management Bylaw SECTION 1. PURPOSE The purpose of this Bylaw is to: implement the requirements of the National Pollutant Discharge Elimination System (NPDES) General Permit for Storm

More information

Hydrology and Water Management. Dr. Mujahid Khan, UET Peshawar

Hydrology and Water Management. Dr. Mujahid Khan, UET Peshawar Hydrology and Water Management Dr. Mujahid Khan, UET Peshawar Course Outline Hydrologic Cycle and its Processes Water Balance Approach Estimation and Analysis of Precipitation Data Infiltration and Runoff

More information

Design of Sewerage System for Jaffarpur area in Southwest New Delhi

Design of Sewerage System for Jaffarpur area in Southwest New Delhi International Journal of Civil Engineering Research. ISSN 2278-3652 Volume 5, Number 1 (2014), pp. 29-34 Research India Publications http://www.ripublication.com/ijcer.htm Design of Sewerage System for

More information

SECTION STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 402 STORM DRAINAGE DESIGN CRITERIA 400-1

SECTION STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 402 STORM DRAINAGE DESIGN CRITERIA 400-1 CITY OF THORNTON Standards and Specifications Revised: October 2012 SECTION 400 - STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 401 GENERAL PROVISIONS 400-1

More information

Best Practices for Building High-Performance Resource Roads. Road Drainage. Developed by: The Roads and Infrastructure Group

Best Practices for Building High-Performance Resource Roads. Road Drainage. Developed by: The Roads and Infrastructure Group Best Practices for Building High-Performance Resource Roads Road Drainage Developed by: The Roads and Infrastructure Group THIS GUIDE IS INTENDED FOR EQUIPMENT OPERATORS CONSTRUCTION CONTRACTORS FIELD

More information

SECTION 3 NATURAL RESOURCES

SECTION 3 NATURAL RESOURCES SECTION 3 NATURAL RESOURCES The natural environment plays a large role in planning for future development. Environmental conditions, such as topography, wetlands, floodplains, and water bodies, can often

More information

Attachment 12 Stage 1 Flood Risk Assessment (IE RP-0001)

Attachment 12 Stage 1 Flood Risk Assessment (IE RP-0001) IE0311133-22-RP-0001, Issue A 17/10/2013 Attachment 12 Stage 1 Flood Risk Assessment (IE0311133-30-RP-0001) IE0311133-22-RP-0001_A_02.DOC Flood Risk Assessment Celebrating 40 Years in Business Jazz Pharmaceuticals

More information

SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS

SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS Version 2 June 2006 1. Purpose These Guidelines are supplementary

More information

Definitions 3/16/2010. GG22A: GEOSPHERE & HYDROSPHERE Hydrology

Definitions 3/16/2010. GG22A: GEOSPHERE & HYDROSPHERE Hydrology GG22A: GEOSPHERE & HYDROSPHERE Hydrology Definitions Streamflow volume of water in a river passing a defined point over a specific time period = VxA discharge m 3 s -1 Runoff excess precipitation - precipitation

More information

Cape Town water outlook 2018

Cape Town water outlook 2018 Cape Town water outlook 2018 25 January 2018 Department of Water and Sanitation City of Cape Town Cape Town s water is part of an integrated system Cape Town gets its water from a system of dams that supply

More information

BMP 6.4.4: Infiltration Trench

BMP 6.4.4: Infiltration Trench BMP 6.4.4: Infiltration Trench An Infiltration Trench is a leaky pipe in a stone filled trench with a level bottom. An Infiltration Trench may be used as part of a larger storm sewer system, such as a

More information

Information Request 11

Information Request 11 Information Request 11 Information Request 11 11-1 Responses to Information Request 11 Response to Information Request 11a Response to Information Request 11b 11-2 11-6 Federal Review Panel Information

More information

4.6 - Hydrology and Water Quality

4.6 - Hydrology and Water Quality City of Wasco - Wasco Center Walmart Hydrology and Water Quality 4.6 - Hydrology and Water Quality 4.6.1 - Introduction This section provides an evaluation of hydrology and water quality. The analysis

More information

Standards for SWMF s. (Stormwater Management Facilities) Lacombe County s Guide to Developing Stormwater Management Facilities

Standards for SWMF s. (Stormwater Management Facilities) Lacombe County s Guide to Developing Stormwater Management Facilities Standards for SWMF s (Stormwater Management Facilities) Lacombe County s Guide to Developing Stormwater Management Facilities August 2017 PREAMBLE Development results in a great amount of impervious area,

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432 PAN 16-112, Westwood Middle School, Page 1 of 6 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: August 22, 2016 AGENDA NUMBER: 10 FILE NUMBER: 16-112 ITEM: Westwood Middle School RECOMMENDATION:

More information

GRAY WATER RECYCLING SYSTEMS

GRAY WATER RECYCLING SYSTEMS GRAY WATER RECYCLING SYSTEMS Note: Section P2601.2 of the International Residential Code requires all plumbing fixtures that receive water or waste to discharge to the sanitary drainage system of the structure.

More information

Rainwater Harvesting for Domestic Water Supply and Stormwater Mitigation

Rainwater Harvesting for Domestic Water Supply and Stormwater Mitigation Rainwater Harvesting for Domestic Water Supply and Stormwater Mitigation C Liaw 1, W Huang 2, Y Tsai 3, and, J Chen 4 1 President, Taiwan Rainwater Catchment Systems Association, Chliaw@ms41.hinet.net

More information

The City of Cocoa (City) is located in east

The City of Cocoa (City) is located in east FWRJ Reclaimed Water and Stormwater: A Perfect Pair to Meet Total Maximum Daily Load Wasteload Allocations? Danielle Honour, James Wittig, John A. Walsh, and Don Stevens Danielle Honour, P.E., D.WRE, and

More information

Implementing Stormwater Management through Split-Flow Drainage Design

Implementing Stormwater Management through Split-Flow Drainage Design Implementing Stormwater Management through Split-Flow Drainage Design Stuart Patton Echols PhD, ASLA, RLA Assistant Professor - Department of Landscape Architecture 210 Engineering Unit D Center for Watershed

More information

Boise City Public Works General Drainage Plan Review Requirements Checklist

Boise City Public Works General Drainage Plan Review Requirements Checklist Boise City Public Works General Drainage Plan Review Requirements Checklist Development Name Bldg. Permit # Drainage Reviewer Site Address Initial Review Date ODI Number Designer Company Name Treated Acres

More information

The Islamic University of Gaza- Civil Engineering Department Sanitary Engineering- ECIV 4325 L5. Storm water Management

The Islamic University of Gaza- Civil Engineering Department Sanitary Engineering- ECIV 4325 L5. Storm water Management The Islamic University of Gaza- Civil Engineering Department Sanitary Engineering- ECIV 4325 L5. Storm water Management Husam Al-Najar Storm water management : Collection System Design principles The Objectives

More information

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No Environmental Resources Management January 13, 2017 Mr. Michael Malone 145 Navarro Street San Antonio, Texas 78205 Project No. 0352436 CityCentre Four 840 West Sam Houston Parkway North, Suite 600 Houston,

More information

EXAMPLE Stormwater Management Plans w/ CSS BMP Sizing Calculator (v2.1)

EXAMPLE Stormwater Management Plans w/ CSS BMP Sizing Calculator (v2.1) 525 Golden Gate Avenue, 11th Floor San Francisco, CA 94102 EXAMPLE Stormwater Management Plans w/ CSS BMP Sizing Calculator (v2.1) The following example Stormwater Management Plans (SMPs) are provided

More information

Chapter MINERAL EXTRACTION AND MINING OPERATIONS

Chapter MINERAL EXTRACTION AND MINING OPERATIONS Chapter 17.31 MINERAL EXTRACTION AND MINING OPERATIONS Sections: 17.31.010 Purpose 17.31.020 Procedure for Extraction and Rehabilitation Requests 17.31.030 Operation and Rehabilitation Standards for all

More information

28 February 2017 ATTENTION: MR HENNIE WOOD AND MS MAGGIE VON RONGE NORTHAM BOOYSENDAL CC: AMANDA PYPER AMEC FOSTER WHEELER NOTE FOR THE RECORD

28 February 2017 ATTENTION: MR HENNIE WOOD AND MS MAGGIE VON RONGE NORTHAM BOOYSENDAL CC: AMANDA PYPER AMEC FOSTER WHEELER NOTE FOR THE RECORD Project Reference: 720.01092.00001 File Ref. 170228 Erosion & Silt Management NFTR Rev1 28 February 2017 PROJECT: Booysendal South EIA Hydrology Specialist Study CLIENT: Amec Foster Wheeler ORDER No: 2338/9149/1294

More information

E5. On-site and small scale wastewater treatment and disposal

E5. On-site and small scale wastewater treatment and disposal E5. On-site and small scale wastewater treatment and disposal E5.1. Background On-site wastewater systems are utilised for residential dwellings, commercial and industrial activities and facilities not

More information

Great Keppel Island Resort EIS

Great Keppel Island Resort EIS Great Keppel Island Resort EIS For GKI Resort Pty Ltd Water Cycle Management Report 21 October 2011 Opus International Consultants (PCA) Pty Ltd ABN 89 096 110 262 Level 1, 2 Mayneview Street, Milton,

More information

Producer Statement. Design: On-Site Effluent Disposal Systems (AS/NZS 1547:2012)

Producer Statement. Design: On-Site Effluent Disposal Systems (AS/NZS 1547:2012) Producer Statement Design: On-Site Effluent Disposal Systems (AS/NZS 1547:2012) Issued by: To: To be supplied to: Property Location:. (approved qualified design professional) (owner) Kaipara District Council...

More information

Sediment Basin. Fe= (Depends on soil type)

Sediment Basin. Fe= (Depends on soil type) 3.9 Sediment Control Description: A sediment basin is an embankment with a controlled outlet that detains stormwater runoff, resulting in the settling of suspended sediment. The basin provides treatment

More information

RUM SD PLN 0040 WATER MANAGEMENT PLAN

RUM SD PLN 0040 WATER MANAGEMENT PLAN WATER MANAGEMENT PLAN Ravensworth Underground Mine 1. COMMITMENT AND POLICY 1.1 Introduction Ravensworth Underground Mine (RUM) is located in the upper Hunter Valley of New South Wales, approximately 25

More information

Monthly Environmental Data May 2016

Monthly Environmental Data May 2016 Monthly Environmental Data May 2016 Contents 1 AIR QUALITY... 2 1.1 HIGH VOLUME AIR SAMPLERS... 2 1.2 TAPERED ELEMENT OSCILLATING MICROBALANCE SAMPLING (TEOM)... 7 1.3 DUST DEPOSITION SAMPLING... 11 2

More information

Water Management Chapter 14

Water Management Chapter 14 14 Water Management ENVIRONMENTAL ASSESSMENT Water Management Chapter 14 Water Management Summary of Key Outcomes The water requirements, wastewater production, stormwater management and flooding potential

More information