1 Case study: BAM Construct Halving Waste to Landfill BAM Construct UK was one of the first contractors to sign up to the Halving Waste to Landfill industry commitment in Since then, BAM has been working with WRAP to reduce waste to landfill and continually improve its waste management. As part of this, the company has set and achieved high waste and recycling targets, developing a new data gathering tool which has brought substantial improvements in monitoring and reporting, and embedded good practices throughout its supply chain. Company Profile Courtesy of BAM Construct. Chiswick Green BREEAM Excellent building currently underway Sustainability is important to BAM Construct s ethos, so signing up to the Halving Waste to Landfill commitment was a natural step for us. It has helped us progress our waste reduction agenda, enhancing our reporting and helping us procure for waste reduction Charlie Law, Environmental Manager Key Accomplishments and Savings 85% diversion of waste from landfill in % reduction in waste to landfill [from 2008 baseline] 13% reduction in waste arisings in 2010 [from 2008 baseline] Implementation of company-wide waste data collection system Reduced reporting time and increased accuracy Introduction of contractual requirements for contractors waste management BAM Construct UK Limited (BAM) is one of the UK s largest construction services organisations. It is part of the European Royal BAM Group, consisting of 25 companies around the world with employees totalling 28,000. BAM Construct works across England, Scotland and Wales. The company covers the education, retail, mixed use development, health, office, leisure and law order sectors, with an average annual turnover of approximately 1 billion. This case study is one of a series examining how companies are implementing the Halving Waste to Landfill Commitment and what they have achieved in terms of resource efficiency and waste reduction. Halving Waste to Landfill With a strong focus on responsible business, BAM was keen to play their part in reducing waste and the Halving Waste to Landfill Commitment provided the perfect opportunity. The company s philosophy is focused on working closely with their supply chain to consistently deliver good sustainability outcomes. The Halving Waste to Landfill Commitment sets five waste reduction steps: Setting a waste reduction target Embedding the target in corporate policies and procedures Embedding these in project and supply chain requirements Measuring performance against a corporate baseline Reporting annually on performance.

2 These steps tie in well with BAM s goals to reduce their waste arisings and waste to landfill, as well as to report annually and continually improve its performance. BAM collects data on the environmental performance of every aspect of the business. This information allows it to identify problems and good practices so these can be shared across the group. It also helps reduce the amount of waste produced and ensures the Company is reusing and recycling as much waste as possible. Combined, these measures help to meet the Halving Waste to Landfill target. Waste reduction targets BAM set a target to halve the amount of waste they sent to landfill by 2012, in line with the Halving Waste to Landfill Commitment. To help them progress towards this goal, it set year-on-year targets for reducing its waste to landfill, Diversion of waste from landfill Year Target % % % % During 2010, BAM achieved 85% waste diversion from landfill. As a result of their strong focus on waste over , BAM has been able to achieve their initial halving waste to landfill target two years ahead of schedule. waste forecast and project-specific targets and actions for waste reduction and recovery; 2. provide the SWMP to the client before starting on site and on completion of the project, reporting forecast and actual performance; 3. report the quantity of waste produced and the quantity of waste sent to landfill, in m 3 / M construction value; 4. meet or exceed 75% recovery of construction, demolition and excavation waste; and 5. increase material value derived from reused and recycled content in new build. For BAM properties a 15% recycled content target was set. Engaging the supply chain on projects It s not only important to collect data, but to make use of it once you ve got it. To make the system work requires communication, motivation and a clear vision for how to progress. Working with WRAP, BAM has developed a clear strategy and process for waste reduction. To help roll out the commitment and requirements to BAM s supply chain, BAM has used the WRAP procurement guidance. This set of template procurement documentation, developed by WRAP, BAM, and other UKCG members, provides wording and guidance to help organisations set procurement requirements for waste reduction. BAM contractually required its subcontractors, suppliers and waste contractors to play an active role in helping to improve materials resource efficiency to minimise the environmental impacts of its waste, and to ensure compliance with the Site Waste Management Plan (SWMP) Regulations. Subcontractors are required to: provide an estimate of predicted waste types and volumes to feed into waste forecast (if involved from the early stages of the project) provide details of the specific materials resource efficiency methods they will employ on the project to help reduce waste. meet or better agreed waste production levels, as Embed targets within corporate policy and processes BAM have used the WRAP core requirements, a summary of industry best practices developed by WRAP in consultation with the UKCG and other industry organisations, as a guide for setting targets and requirements in corporate policy and processes: 1. implement a Site Waste Management Plan (SWMP) from an early design stage, to include a a percentage of the final fixed product quantities, for certain packages. divert at least 80% of construction, demolition and excavation waste arising from the works from landfill via reuse, recycling or recovery (BAM have a long term target of zero non-hazardous waste to landfill). use reclaimed products and materials, and products and materials with a high recycled content, wherever feasible

3 monitor and report at least weekly on the waste arisings and the destination of the waste re-use, recycling, recovery, landfill and other, and, in the case of re-use, recycling and recovery, whether this has taken place on- or off- site. Impact on BAM s projects In 2009 BAM began building the Leeds University Earth and Environment Building. The project consisted of a 8m new build and a 11m refurbishment project. The project was designed to be a sustainable building, reflecting the ethos of the university as a leader in environmental research. Best-practice waste management, and re-using existing materials on site were key priorities for the client. As such, BAM needed to ensure the construction phase met these aspirations in a timely and costeffective manner. By implementing good practice actions, BAM was able to go beyond its 75% diversion from landfill target to achieve a diversion rate of 84%. In terms of waste production, this equated to 143m 3 / M. The waste actions BAM undertook included: Used Designing Out Waste principles to re-design basements and substructures to avoid an estimated 450m³ of waste being taken off site. Worked with suppliers to select low-waste materials (e.g. pre-cut perimeter steel), and to have suppliers store leftover materials for reuse (e.g. plasterboard). Re-use of existing screed saving an estimated 600m3 of waste. Segregated waste on site so that waste streams such as timber could be easily sent to community schemes for re-use. Using waste contractors who could deliver high recycling rates on mixed waste (which was checked by a second-party). Courtesy of BAM Construct Leeds University Earth and Environment Building Measuring performance: the importance of data As part of its waste and recycling programme, over the past couple of years BAM has developed a way of collecting waste and environment data from their projects, giving accurate, reliable data that can be easily aggregated for their waste reporting. BAM was keen to develop a centralised, online tool to help monitor environmental performance in the key areas of waste production, CO2 emissions, water use and timber sourcing. BAM also wanted to capture the increasing number of sustainability requirements now included in projects such as EPC ratings, BREEAM scores, and sustainable technologies. Working alongside the Building Research Establishment (BRE), BAM developed a system that has the capacity to deal with large volumes of data in a reliable and user-friendly way.

4 With the introduction of their online Sustainability Monitoring and Reporting Tool, BAM SMaRT, in 2010, BAM is now able to measure waste returns as a yearon-year process more efficiently, as well as at the end of each job. Data is collected for every project, and held in the central system. The online system makes it easier for the Site Manager to collect the data for their project, saving valuable time and increasing accuracy. The new system enables real-time analysis, identifying good practices early on which can be shared and adopted company-wide. Before BAMSMaRT, the information we recorded was put into individual Excel spreadsheets. It was quite a laborious process, taking at least two hours each month. Now, it s about half an hour. Laura Hatfield, BAM Site Secretary for University of Strathclyde Biomedical project and Glasgow Royal Infirmary Intensive Care unit. Reporting To help record and demonstrate good work on reducing waste to landfill, BAM report into the Halving Waste to Landfill reporting portal. This reporting portal enables construction organisations to report independently on their performance on waste, aggregate and analyse their corporate figures, and anonymously benchmark their performance against the datasets of their peers. BAM regularly report construction, demolition and excavation waste (separately) into the portal. This enables BAM to run reports to keep track of their performance against corporate targets. BAM regularly report construction, demolition and excavation waste (separately) into the portal. This enables BAM to run reports to keep track of their performance against corporate targets. Benefits Having delivered excellent diversion from landfill during construction, BAM s next focus is on preconstruction waste reduction. Now that we are consistently doing as much as we can on site, we are focusing on getting waste reduction into design, says Law. BAM Construct has already begun using the WRAP Designing out Waste guidance to help reduce waste during the design process: Design for Reuse and Recovery; Design for Off Site Construction; Design for Materials Optimisation; Design for Waste Efficient Procurement; and Design for Deconstruction and Flexibility. BAM s design company, BAM Design, have held a series of WRAP workshops to bring designers up-tospeed with the WRAP Designing Out Waste Tool and the Net Waste Tool so that project teams can make use of these free resources when delivering projects. For us, signing up to Halving Waste to Landfill has been great. We have developed a world-class system for waste and environment reporting and, with WRAP s help, have been able to set procurement requirements to get our supply chain to help us achieve our targets. Charlie Law, Environmental Manager Lessons Learnt Designing out waste in the first place is vital to resource efficiency Good data is key investing in a good reporting tool brings great returns To consistently achieve good performance on waste requires knowledge sharing across the company.

5 Next Steps Following on from their strong performance to date, BAM has great plans for the future. With a clear corporate strategy of continual year-on-year improvement, and a group-wide target of Zero nonhazardous waste to landfill by 2015, the company will continue to develop new and innovative practices. Waste reduction will continue to be a key focus area for BAM as it rolls out the Designing Out Waste and Net Waste tools to its teams. This will be linked to the company-wide knowledge sharing to ensure the principles are embedded on all projects. In addition, BAM identify the need to continually engage sub-contractors so its supply chain can help support waste reduction goals. Now that BAM has incorporated waste management requirements as standard into its procurement documentation, this will be followed up with pre-start meetings and other information sessions to ensure all suppliers are aware of the requirements. Acknowledgements WRAP would like to thank BAM Construct UK for providing time and data, and assisting in the production of this casestudy. Further material For more information, visit You can access: a range of other exemplar and cost benefit case studies; procurement guidance and model wording; the Net Waste Tool (free online tool for assessing waste arisings on construction projects); WRAP s Site Waste Management Plan Template; and guidance on Designing out Waste. Courtesy of BAM Construct: Site waste management While steps have been taken to ensure its accuracy, WRAP cannot accept responsibility or be held liable to any person for any loss or damage arising out of or in connection with this information being inaccurate, incomplete or misleading. For more detail, please refer to our Terms & Conditions on our website:

A metric for the construction sector. The Net Waste Method testing a new standard for measuring waste neutrality

A metric for the construction sector. The Net Waste Method testing a new standard for measuring waste neutrality A metric for the construction sector The Net Waste Method testing a new standard for measuring waste neutrality WRAP works in partnership to encourage and enable businesses and consumers to be more efficient

More information

Defence sector: recycling waste in construction Defence Estates Regional Prime Contract East, Babcock DynCorp

Defence sector: recycling waste in construction Defence Estates Regional Prime Contract East, Babcock DynCorp Case study Defence sector: recycling waste in construction Defence Estates Regional Prime Contract East, Babcock DynCorp By thinking Best Value, not Least Cost when reviewing the way they procure and manage

More information

Reducing construction waste saves money Bridge Learning Campus, Bristol Contractor: Skanska

Reducing construction waste saves money Bridge Learning Campus, Bristol Contractor: Skanska Exemplar case study Reducing construction waste saves money Bridge Learning Campus, Bristol Contractor: Skanska Background The Bridge Learning Campus (Bristol) ( BLC ) was used as a test bed for achieving

More information

Railways: Waste less and save money

Railways: Waste less and save money Cutting the cost of waste Halving Waste to Landfill Railways: Waste less and save money Procurement good practice for railway infrastructure construction and maintenance Introduction Buying less and throwing

More information

Best Practice Construction Waste Procurement: Office Fit-Out of 15 Canada Square, Canary Wharf

Best Practice Construction Waste Procurement: Office Fit-Out of 15 Canada Square, Canary Wharf Waste procurement case study Best Practice Construction Waste Procurement: Office Fit-Out of 15 Canada Square, Canary Wharf This case study examines how engagement between the main contractor, client and

More information

The emphasis should be on the contractor to develop the targets for waste reduction and recovery. What is good practice?

The emphasis should be on the contractor to develop the targets for waste reduction and recovery. What is good practice? Material change for a better environment Procurement guidance for construction Setting a requirement for Waste Minimisation and Management 2 Setting a requirement for Waste Minimisation and Management

More information

Assessing the costs and benefits of reducing waste in construction

Assessing the costs and benefits of reducing waste in construction Assessing the costs and benefits of reducing waste in 20 new build timber-framed houses Value Percentage of 1.36m cost Cost saving potential 21,470 1.58% Additional costs to achieve these savings TOTAL

More information

Utilities: Waste less and save money

Utilities: Waste less and save money Cutting the cost of waste Utilities: Waste less and save money Procurement good practice for utility infrastructure construction and maintenance Who should read this leaflet? utility company senior managers;

More information

The efficient use of materials in regeneration projects

The efficient use of materials in regeneration projects Linking demolition and new build a step by step guide The efficient use of materials in regeneration projects 5. Key Performance Indicators WRAP works in partnership to encourage and enable businesses

More information

A blueprint for reducing waste and cutting costs

A blueprint for reducing waste and cutting costs A blueprint for reducing waste and cutting costs An average 3-bed unit produces between 5 and 13 tonnes of construction waste. Reducing this could save 250-500 per unit. Five corporate-level actions and

More information

Assessing the costs and benefits of reducing waste in construction

Assessing the costs and benefits of reducing waste in construction Assessing the costs and benefits of reducing waste in New build concrete-framed office Value Percentage of 23m cost Cost saving potential 125,800 0.55% Additional costs to achieve these savings TOTAL POTENTIAL

More information

SMARTWaste: Overview and data Maggie Blackwell. Part of the BRE Trust

SMARTWaste: Overview and data Maggie Blackwell. Part of the BRE Trust SMARTWaste: Overview and data Maggie Blackwell Part of the BRE Trust SMARTWaste Construction tools SMARTWaste Construction tools SMARTWaste Plan: Online Site Waste Management Plan tool www.smartwaste.co.uk

More information

Resource efficiency pursued through design coordination and waste management

Resource efficiency pursued through design coordination and waste management : Edinburgh International Conference Centre Expansion and Speculative Office Space Resource efficiency pursued through design coordination and Key facts Extensive use of building information modelling

More information

Design out. Waste Workshop. A guidance document produced by Network Rail in collaboration with:

Design out. Waste Workshop. A guidance document produced by Network Rail in collaboration with: Design out Waste Workshop A guidance document produced by Network Rail in collaboration with: Guidance on Designing out Waste: How to run a Design out Waste Workshop This document provides guidance on

More information

KPI. Continuous Improvement Test (CIT) Measurement. To be measured in line with HSE guidance for calculating the Accident Incident Rate (AIR)

KPI. Continuous Improvement Test (CIT) Measurement. To be measured in line with HSE guidance for calculating the Accident Incident Rate (AIR) Summary Table Key area of Health and Safety 1.1. Reportable RIDDOR accidents in the hubco members and Tier 1 suppliers' organisations active in the hub territory (business wide AIR). where the number of

More information

UKCG Built Environment Commitment

UKCG Built Environment Commitment UKCG Built Environment Commitment The UK Contractors Group (UKCG) represents some 30 major construction contractors who collectively account for a third of UK construction industry output. The UKCG commitment

More information

McGrath works in partnership with Hackney Homes

McGrath works in partnership with Hackney Homes Case study: Achieving good practice waste recovery McGrath works in partnership with Hackney Homes Hackney Homes is using a partnering approach across the whole supply chain, to deliver the Decent Homes

More information

Costs and benefits of reducing waste in construction. Defence sector new build Woolwich single living accommodation modernisation (SLAM)

Costs and benefits of reducing waste in construction. Defence sector new build Woolwich single living accommodation modernisation (SLAM) Costs and benefits of reducing waste in construction Defence sector new build Woolwich single living accommodation modernisation (SLAM) Value Percentage of 3.2m construction cost Cost saving potential

More information

Achieving effective Waste Minimisation

Achieving effective Waste Minimisation Practical solutions for sustainable construction Achieving effective Waste Minimisation Guidance for construction clients, design teams and contractors WRAP works in partnership to encourage and enable

More information

Assessing the costs and benefits of reducing waste in construction trade packages

Assessing the costs and benefits of reducing waste in construction trade packages Assessing the costs and benefits of reducing waste in construction trade packages Dense concrete blocks and facing bricks, with mineral wool insulation batts Value Percentage of 100k spend Cost saving

More information

Minimising construction waste through project design

Minimising construction waste through project design Case Study: New South Glasgow Hospitals Minimising construction waste through project design Key facts Applying WRAP s Designing out Waste principles to the project design identified 21 areas of potential

More information

ASSET MANAGEMENT SUSTAINABILITY POLICY

ASSET MANAGEMENT SUSTAINABILITY POLICY ASSET MANAGEMENT SUSTAINABILITY POLICY SustainabILITY policy statement for development projects In our activities as developers of buildings we uphold the aims of Sustainable Development: to enhance the

More information

Halving Waste to Landfill, SEESA

Halving Waste to Landfill, SEESA SEESA is working hard to achieve its target of 90% diversion of waste to landfill by 2012 by exploring new ways of working, applying initiatives to eliminate and minimise waste, and to reuse, recycle and

More information

Construction waste collection good practice: Gloucester Quays

Construction waste collection good practice: Gloucester Quays Case Study Construction waste collection good practice: Gloucester Quays This case study examines how applying good practice, such as segregation at source, produced material streams suitable for direct

More information

ASSET MANAGEMENT SUSTAINABILITY POLICY 2016

ASSET MANAGEMENT SUSTAINABILITY POLICY 2016 ASSET MANAGEMENT SUSTAINABILITY POLICY 2016 SUSTAINABILITY POLICY STATEMENT FOR DEVELOPMENT PROJECTS In our activities as developers of buildings we uphold the aims of Sustainable Development: to enhance

More information

End of Project Report : Newtown Secondary School

End of Project Report : Newtown Secondary School Resource Management Planning: Worked Example End of Project Report : Newtown Secondary School The template for this document is available at www.wrap.org.uk/node/13707 Document Owner Project Project Reference

More information

Waste management contractors selling the benefits of your Halving Waste to Landfill Commitment to construction clients

Waste management contractors selling the benefits of your Halving Waste to Landfill Commitment to construction clients Good Practice Guide: Waste management contractors 1 Good Practice Guide Waste management contractors selling the benefits of your Halving Waste to Landfill Commitment to construction clients This short

More information

Material resource efficiency in construction

Material resource efficiency in construction Material resource efficiency in construction Supporting a circular economy Katherine Adams and Gilli Hobbs Material resource efficiency in construction Supporting a circular economy Katherine Adams and

More information

Contractor follows nine-step plan to achieve best practice in construction waste management

Contractor follows nine-step plan to achieve best practice in construction waste management : Strathclyde Fire & Rescue Training Centre Contractor follows nine-step plan to achieve best practice in Key facts Lend Lease has corporate targets to reduce construction waste, aiming to achieve

More information

Innovative waste management approach achieves exemplary recovery rates

Innovative waste management approach achieves exemplary recovery rates : University of the West of Scotland, Ayr Campus Innovative waste management approach achieves exemplary Key facts The new campus was designed to achieve a BREEAM rating of Excellent. 96% of the 1,200

More information

Designing Out Waste In the Civil Engineering Sector Athens Dioni Spiliopoulou MCIWM Bob Hudson MCIWM

Designing Out Waste In the Civil Engineering Sector Athens Dioni Spiliopoulou MCIWM Bob Hudson MCIWM Designing Out Waste In the Civil Engineering Sector Athens 2014 Dioni Spiliopoulou MCIWM Bob Hudson MCIWM Overview Arup who we are Why consider Waste Prevention Resource Efficiency How and what we do Barriers

More information

Construction Waste Measurement Guide

Construction Waste Measurement Guide Draft V6 Last updated: February 2013 Construction Waste Measurement Guide A guide to measuring and reporting waste from construction activities 1 Introduction This document provides guidance on how to

More information

Sustainability Best Practice Case Study. Reducing Waste, Reducing Cost. The UK construction industry waste challenge

Sustainability Best Practice Case Study. Reducing Waste, Reducing Cost. The UK construction industry waste challenge Sustainability Best Practice Case Study Reducing Waste, Reducing Cost With the construction industry sending 17% of its total waste produced to landfill each year and spiralling landfill costs the UK government

More information

Benefits of the WRAP SWMP Template. Birmingham, 1 April 2008

Benefits of the WRAP SWMP Template. Birmingham, 1 April 2008 Benefits of the WRAP SWMP Template Birmingham, 1 April 2008 Dehlia Farrow Associate Director Environment, Halcrow Use of WRAP SWMP Template Improve your project s waste and resource efficiency Demonstrate

More information

The efficient use of materials in regeneration projects

The efficient use of materials in regeneration projects Linking demolition and new build a step by step guide The efficient use of materials in regeneration projects 10. Demolition phase The Demolition phase section outlines the planning of the demolition activities

More information

Appendix I -1 Demolition Waste Estimates

Appendix I -1 Demolition Waste Estimates Appendix I -1 Demolition Waste Estimates Appendix I-1: Estimated demolition waste generated from the proposed JFH Demolition work Year Waste Mass (tonnes) St Elmo s Substation 2018 626 Westaway Court 2019

More information

Environmental Policy and Guide December 2010

Environmental Policy and Guide December 2010 Environmental Policy and Guide December 2010 Page 1 of 11 ENVIRONMENTAL POLICY A responsible and forward-looking approach to environmental issues is an important factor in Intu Properties plc s continuing

More information

Construction Strategy: Newtown Secondary School

Construction Strategy: Newtown Secondary School Resource Management Planning: Worked Example Construction Strategy: Newtown Secondary School The template for this document is available at www.wrap.org.uk/node/13707 Document Owner Project Project Reference

More information

Delivering higher recycled content in construction projects

Delivering higher recycled content in construction projects Construction procurement guidance Delivering higher recycled content in construction projects Client and team Contractor and team Sub-contractor and team Requirement Policy Generic options for improvement

More information

Grays Waste Management

Grays Waste Management Grays Waste Management WRAP Cymru (Waste & Resources Action Programme in Wales) works directly with the recycling industry, specifically on waste management and materials recovery, and with reprocessing

More information

Laying the foundations to double re-use

Laying the foundations to double re-use Laying the foundations to double re-use How research provided the catalyst for a new to re-use in Leicestershire, Leicester City and Rutland Three neighbouring local authorities Leicestershire County Council,

More information

Tool for measuring the recovery rates in CDEW MRFs

Tool for measuring the recovery rates in CDEW MRFs Guidance notes Tool for measuring the recovery rates in CDEW MRFs Guidance notes for the Site-Specific Waste Analysis Tool (SSWAT) to measure recovery rates of construction, demolition and excavation waste

More information

Sustainable Procurement Case Study Natural History Museum

Sustainable Procurement Case Study Natural History Museum Sustainable Procurement Case Study Natural History Museumm Embedding sustainability in procurement practices: a UK museum s persp pective This documentt is uncontrolled if printed London s Natural History

More information

Plasterboard Roadmap: Status Report July 08

Plasterboard Roadmap: Status Report July 08 Plasterboard Roadmap: Status Report July 08 1. Summary This roadmap focuses on understanding and improving the life cycle impacts of plasterboard. A number of government and industry-led measures are in

More information

Raploch: urban regeneration

Raploch: urban regeneration Construction case study Raploch: urban regeneration This case study describes how the WRAP Regeneration Guide principles have been applied to the tendering and procurement stage of the Raploch regeneration

More information

Site Waste Management Plans A guide for the construction industry and supply chain

Site Waste Management Plans A guide for the construction industry and supply chain GG899 www.envirowise.gov.uk Envirowise Advice Line: 0800 585794 Notes:...... Envirowise - sustainable practices, sustainable profits. Envirowise is a Government-funded programme dedicated to putting the

More information

Zero waste to landfill: Construction waste collection good practice

Zero waste to landfill: Construction waste collection good practice Case study Zero waste to landfill: Construction waste collection good practice Zero waste policies are a key step towards sustainable waste management. This case study examines the economic and environmental

More information

North West Site Waste Management Plan September 2011

North West Site Waste Management Plan September 2011 North West Site Waste Management Plan September 2011 Table of Contents Introduction... 1 Project Information... 1 Document Control... 4 Responsibilities... 4 Site Waste Management Plans Regulations 2008

More information

Structures concrete. Structures concrete

Structures concrete. Structures concrete This section includes summary sheets for the following technical solutions: Precast concrete rather than cast in-situ; Assemble structures on site and move into place; Recycled/secondary aggregates in

More information

Resources and Waste Management Exhibition recycles 83% of waste

Resources and Waste Management Exhibition recycles 83% of waste i2i Events and the CIWM join forces to achieve 83% recycling Resources and Waste Management Exhibition recycles 83% of waste High recycling rates and plenty of supplier engagement to minimise waste on

More information

Site Waste management Plan (SWMP)

Site Waste management Plan (SWMP) Author: M.Graney & Sons Ltd. 1. Project Title: Underpinning, Lower ground floor Extension and Refurbishment Works. 2. Location: 21 Old Church Street, London, SW3 5DL. 3. Nature of Project: The works comprise

More information

User Guide For Administrators, Project Users, and Read Only users

User Guide For Administrators, Project Users, and Read Only users User Guide For Administrators, Project Users, and Read Only users Version 4 August 2013 Page 1 of 48 V4 - Aug 2013 User Guidance Contents 1.0 What is BAM SMaRT?... 3 2.0 Getting Started (All)... 3 2.1

More information

Reducing Waste in Sainsbury s Supermarket Refits through off site fabrication

Reducing Waste in Sainsbury s Supermarket Refits through off site fabrication WAS031 Off site Construction Case Study Reducing Waste in Sainsbury s Supermarket Refits through off site fabrication Sainsbury s have made effective use of the Fit Out UK / RG s off site fabrication and

More information

Benefits of off site manufacture

Benefits of off site manufacture Case Study Benefits of off site manufacture Jocelyn Park, Somerset Jocelyn Park is a housing development owned and managed by South Somerset Homes Housing Association. There are 64 homes on site designed

More information

European Pathway to Zero Waste: embedding sustainable procurement for public sector organisations in south east England

European Pathway to Zero Waste: embedding sustainable procurement for public sector organisations in south east England Final Report : embedding sustainable procurement for public sector organisations in south east England Report on the provision of bespoke advice on embedding sustainable procurement within procurement

More information

Action Responsibility Baseline data Targets Milestones

Action Responsibility Baseline data Targets Milestones The Smith s Snackfood Company Pty Ltd and Sakata Rice Snacks Australia Pty Ltd Australian Covenant Action Plan Addendum 2016 Update Table 1: Smith s and Sakata APC Action Table Action Responsibility Baseline

More information

DEFRA Consultation on Site Waste Management Plans for the Construction Industry (April 2007)

DEFRA Consultation on Site Waste Management Plans for the Construction Industry (April 2007) DEFRA Consultation on Site Waste Management Plans for the Construction Industry (April 2007) Summary The Department for Environment, Food and Rural Affairs is consulting on proposals to make Site Waste

More information

RNLI makes waves with lifejacket recycling scheme

RNLI makes waves with lifejacket recycling scheme Resource efficiencies in facilities management RNLI makes waves with lifejacket recycling scheme The Royal National Lifeboat Institution operates a stringent environmental management system and encourages

More information

Vinyl flooring: Making take-back schemes pay back on refurbishment projects

Vinyl flooring: Making take-back schemes pay back on refurbishment projects Refurbishment Resource Efficiency Case Study: Vinyl flooring take-back schemes Vinyl flooring: Making take-back schemes pay back on refurbishment projects This case study focuses on three UK vinyl flooring

More information

Reducing and recycling plasterboard waste on a site where space is a constraint

Reducing and recycling plasterboard waste on a site where space is a constraint Plasterboard case study Reducing and recycling plasterboard waste on a site where space is a constraint This case study describes the approaches taken to design out, recover and recycle plasterboard waste

More information

Material Logistics Plan Good Practice Guidance

Material Logistics Plan Good Practice Guidance Waste Minimisation in Construction Material Logistics Plan Good Practice Guidance Guidance for Clients, Design Teams, Construction Contractors and Sub-contractors on developing and implementing an effective

More information

Engaging with suppliers on waste prevention

Engaging with suppliers on waste prevention Engaging with suppliers on waste prevention SETTING THE CONTEXT As a signatory to the Courtauld Commitment 3 (CC3), Nestlé UK are engaged in waste prevention at source. All Nestle UK sites also follow

More information

RMP Design Action Plan: Newtown Secondary School

RMP Design Action Plan: Newtown Secondary School Resource Management Planning: Worked Example RMP Design Action Plan: Newtown Secondary School The template for this document is available at www.wrap.org.uk/node/13707 Document Owner Project Project Reference

More information

Cost Assessment of Wales Environment Bill Measures on Business Waste Producers in the Construction & Demolition Sector

Cost Assessment of Wales Environment Bill Measures on Business Waste Producers in the Construction & Demolition Sector Final Report Assessment of Wales Environment Bill Measures on Business Waste Producers in the Construction & Demolition Sector Assessment of the financial implications of additional segregation / collection

More information

Pinewood Structures, established in 1981, has become one of the UK s largest suppliers of timber frame structures.

Pinewood Structures, established in 1981, has become one of the UK s largest suppliers of timber frame structures. Private Developers About Us Pinewood Structures, established in 1981, has become one of the UK s largest suppliers of timber frame structures. Operating from a 5 acre site with 46,000 sq-ft of factory

More information

For guidance on disposal of Polychlorinated Biphenyl (PCB) contaminated equipment or fluids, please refer to the Guidance Note NR/GN/ESD03.

For guidance on disposal of Polychlorinated Biphenyl (PCB) contaminated equipment or fluids, please refer to the Guidance Note NR/GN/ESD03. 1 Purpose This document provides information on how to effectively manage waste. This guidance is to support the requirements that are set out in the Level 2 Environment and Social Minimum Requirements

More information

Baselines and benchmarks 2009

Baselines and benchmarks 2009 Benchmarks and Baselines 2009 Executive Summary The aim of this work, which has been funded by the Construction Resources and Waste Platform 1, was to produce a set of benchmarks for the arsings for construction

More information

Environmental Sustainability Strategy

Environmental Sustainability Strategy shgroup.org.uk Environmental Sustainability Strategy A greener Southern Housing Group 2 Southern Housing Group: Environmental Sustainability Strategy 2017-2020 Our Environmental Sustainability Strategy

More information

Waste FY Introduction. 2. Waste. 3. Management Approach

Waste FY Introduction. 2. Waste. 3. Management Approach 1. Introduction This document forms part of our Disclosures on Management Approach (DMA) series, prepared in accordance with the Global Reporting Initiative s G4 Guidelines. The DMA series is designed

More information

New Tredegar Flood Alleviation Scheme

New Tredegar Flood Alleviation Scheme WAS042 Waste Minimisation Design Review Case Study New Tredegar Flood Alleviation Scheme Design review report for the Environment Agency flood defence project at New Tredegar, Rhymney, South Wales. Potential

More information

Procurement Services Packaging Policy.

Procurement Services Packaging Policy. Procurement Services Packaging Policy. Introduction Procurement Services is committed to improving the way it manages the environmental and sustainable development issues arising from the services it provides

More information

The content in this APC Annual Report is hereby endorsed by the Chief Executive Officer, or equivalent officer of the organisation.

The content in this APC Annual Report is hereby endorsed by the Chief Executive Officer, or equivalent officer of the organisation. Signatory Name: Smiths Snackfoods Company, The Status: Completed The content in this APC Annual Report is hereby endorsed by the Chief Executive Officer, or equivalent officer of the organisation. Industry

More information

It is entirely appropriate that I m here today at one of the world s most iconic sporting venues.

It is entirely appropriate that I m here today at one of the world s most iconic sporting venues. EPOW Events Roadmap launch 5 March 2013 Liz Goodwin Good morning, and welcome all, to Lord s Cricket Ground. It is entirely appropriate that I m here today at one of the world s most iconic sporting venues.

More information

Delivering Sustainability with Prestige: at the BMW PGA Championships

Delivering Sustainability with Prestige: at the BMW PGA Championships Delivering Sustainability with Prestige: at the BMW PGA Championships Delivering Sustainability with Prestige at the BMW PGA Tour The European Tour's flagship event attracts the elite of the world s golfers

More information

NECTAR. This work has been submitted to NECTAR, the Northampton Electronic Collection of Theses and Research. Conference or Workshop Item

NECTAR. This work has been submitted to NECTAR, the Northampton Electronic Collection of Theses and Research. Conference or Workshop Item This work has been submitted to NECTAR, the Northampton Electronic Collection of Theses and Research. Conference or Workshop Item Title: Future perfect? "Bahrain: a zero waste place?" Creator: Phillips,

More information

Construction Site Waste Management Process.

Construction Site Waste Management Process. Construction Site Waste Management Process. EMS DOCUMENT TYPE: ENVIRONMENTAL ASPECT: PURPOSE: Operational Control Document Waste Management To ensure we manage our waste in compliance with legislation

More information

Non-packaging plastics

Non-packaging plastics 00 Good Practice Guide Good Practice Guide Non-packaging plastics Environmental good practice guide for the collection of non-packaging plastics The Waste Protocols Project is a joint Environment Agency

More information

BNPB3: Plasterboard - legislation and policy drivers

BNPB3: Plasterboard - legislation and policy drivers BNPB3: Plasterboard - legislation and policy drivers Version 1.6 This Briefing Note and referenced information is a public consultation document and will be used to inform Government decisions. The information

More information

BRE SMARTWaste Breakfast Briefing 8 April 2014 Royal Academy of Engineering, London

BRE SMARTWaste Breakfast Briefing 8 April 2014 Royal Academy of Engineering, London BRE SMARTWaste Breakfast Briefing 8 April 2014 Royal Academy of Engineering, London www.smartwaste.co.uk smartwaste@bre.co.uk 01923 664471 Part of the BRE Trust Welcome from the Chair Dr. Miles Watkins

More information

Collection of carpet tiles for closed loop recycling through manufacturer take-back scheme

Collection of carpet tiles for closed loop recycling through manufacturer take-back scheme Collection of non-clothing textiles case study: Carpet tile collection Collection of carpet tiles for closed loop recycling through manufacturer take-back scheme In 2012 Desso collected over 100,000m 2

More information

National Library of Scotland Public Sector Sustainability Report

National Library of Scotland Public Sector Sustainability Report Date: June 2014 Version number: - Owner: Linda MacMillan, Capital Projects Programme Manager Approval route: Corporate Management Team Approval status: Work in progress CONTENT 1.0 Introduction... 2 1.1

More information

Sustainability Policy

Sustainability Policy Sustainability Policy For the attention of: All Produced by: Deputy Principal, Finance & Resources Approved by: Board of Governors Date of publication: December 2015 Date of review: December 2017 Our Mission

More information

Corporate Social Responsibility.

Corporate Social Responsibility. Corporate Social Responsibility www.connection.uk.com Our Mission Connection recognises the importance of integration of social and environmental responsibility into a Corporate Social Responsibility (CSR)

More information

wea.org.uk Sustainable Development Policy

wea.org.uk Sustainable Development Policy wea.org.uk Sustainable Development Policy Sustainable Development Policy March 2018 Foreword Workers Educational Association, (WEA) is committed to promoting sustainability and our own sustainable development.

More information

Meet the Berkeley Group

Meet the Berkeley Group Meet the Berkeley Group A Green Growth Platform event Delivered by the Sustainable Business Network Horsham, 12 th May 2016 Working in partnership @SustBusNetwork @UoBGreenGrowth Meet the Buyer Horsham

More information

Environmental Policy Document

Environmental Policy Document Environmental Policy Document Contents Introduction 3 Environmental Policy Statement..4 Sustainability.5 Corporate Social Responsibility...6 Environmental Materials.7 Commitment to Environmental Improvement..8

More information

Resource Recovery TIMBER Collection and Transportation

Resource Recovery TIMBER Collection and Transportation Resource Recovery TIMBER Collection and Transportation This guide provides good-practice advice to improve recovery rates for all types of waste timber from construction and demolition (C&D) sites. The

More information

The Demolition Protocol: Aggregates Resource Efficiency in Demolition and Construction. Volume 3. For Contractors

The Demolition Protocol: Aggregates Resource Efficiency in Demolition and Construction. Volume 3. For Contractors The Demolition Protocol: Aggregates Resource Efficiency in Demolition and Construction Volume 3. For Contractors 2 Extracted from the Demolition Protocol Who is this document aimed at? The Demolition Protocol

More information

Moving to Whole-Life Value: BIM-enabled Deconstruction Management (DRIM) 23 rd February 2018

Moving to Whole-Life Value: BIM-enabled Deconstruction Management (DRIM) 23 rd February 2018 Moving to Whole-Life Value: BIM-enabled Deconstruction Management (DRIM) 23 rd February 2018 Dr John Henry Looney Kris Atkins Sustainable Direction: Sustainability Consultancy Environmental Engineering

More information

Developing carbon management systems

Developing carbon management systems Developing carbon management systems More than just numbers, measuring and spreadsheets Chris Sowerby Principle Consultant 1 09/06/2010 Overview Why measure and manage carbon? What is a carbon management

More information

BREEAM - Whole Building Assessment & Certification. Alan Yates Technical Director, Sustainability

BREEAM - Whole Building Assessment & Certification. Alan Yates Technical Director, Sustainability BREEAM - Whole Building Assessment & Certification Alan Yates Technical Director, Sustainability Outline The BREEAM Family Relationship to the planning system New schemes and initiatives Future direction

More information

Environmental excellence

Environmental excellence 16 Environmental excellence Driving environmental improvements at our assets reduces operating costs, carbon emissions and the use of natural resources. This helps attract and retain occupiers, and ensures

More information

Scotland s Zero Waste Plan & the opportunities for carpet reuse and recycling

Scotland s Zero Waste Plan & the opportunities for carpet reuse and recycling Scotland s Zero Waste Plan & the opportunities for carpet reuse and recycling Carpet Recycling UK Annual Conference 19 th June 2013 Louise McGregor Head of Market Development Agenda Resource efficiency

More information

WATER: The 2009 progress report on reducing water usage on construction sites

WATER: The 2009 progress report on reducing water usage on construction sites WATER: REPORT 012 The 2009 progress report on reducing water usage on construction sites Sept 2011 Prepared by Carmen Waylen on behalf of the Strategic Forum for Construction A contribution to delivering

More information

Green Building KPIs. Fermacell PE INTERNATIONAL. from BREEAM and LEED that are relevant for selected fire protection and building board products

Green Building KPIs. Fermacell PE INTERNATIONAL. from BREEAM and LEED that are relevant for selected fire protection and building board products Fermacell Green Building KPIs from BREEAM and LEED that are relevant for selected fire and building products 31/05/2012 PE INTERNATIONAL Contact: Dr. Peter Shonfield The Portergate Ecclesall Road Sheffield

More information

Waste Management Plan Template (SC6.11)

Waste Management Plan Template (SC6.11) Appendix 1 Waste Management Plan Template (SC6.11) Waste Management Plan 1.0 Introduction Project:... Site address:... Name of applicant:... Address of applicant:... Phone:... Fax:... Email:... Reason

More information

Raising the Bar for sustainable office design

Raising the Bar for sustainable office design Raising the Bar for sustainable office design Collaborative working between owners and Occupiers BREEAM: Being Outstanding 18 th July 2013 Objectives for 7 More London 1 2 3 4 Workplace for our business

More information

12 WASTE. Introduction. Review of proposed development

12 WASTE. Introduction. Review of proposed development 12 WASTE Introduction 12.1 This chapter provides a qualitative assessment of the likely significant environmental effects of solid waste generation, associated with the construction and operation of the

More information

SUSTAINABILTY. Respect for the environment

SUSTAINABILTY. Respect for the environment SUSTAINABILTY Respect for the environment Sustainability Sustainability is at the core of Milliken s philosophy to do good for the world. We believe that a healthy enterprise and a healthy earth are vitally

More information

Resource efficient remediation

Resource efficient remediation Case study Resource efficient remediation Achieving savings through remediation and onsite reuse of contaminated material Bellway, Taylor Wimpey and Hydrock Costs and savings achieved by housing developers

More information