Contractor follows nine-step plan to achieve best practice in construction waste management

Size: px
Start display at page:

Download "Contractor follows nine-step plan to achieve best practice in construction waste management"

Transcription

1 : Strathclyde Fire & Rescue Training Centre Contractor follows nine-step plan to achieve best practice in Key facts Lend Lease has corporate targets to reduce construction waste, aiming to achieve <5.5m 3 per 100k project spend and for >94% of all waste generated to be diverted from landfill. Lend Lease implemented a nine-step (waste reduction) plan that was rolled out across both the design and construction stages of the SFR Training Centre project. Figure 1 Strathclyde Fire & Rescue Training Centre, front entrance Lend Lease, the international property and infrastructure group, is the principal contractor appointed to Strathclyde Fire & Rescue s (SFR) new Training Centre in South Lanarkshire. By applying a nine-step site waste management plan (nine-step plan) to all projects, Lend Lease is working towards achieving its ambitious corporate waste reduction and recovery targets as a signatory to the Waste and Resources Action Programme (WRAP) Halving Waste to Landfill Commitment. These targets were exceeded at the SFR Training Centre, demonstrating the benefits of a strong corporate approach to construction waste management. Project background The SFR Training Centre, in Cambuslang, South Lanarkshire (Figure 1), consists of state-of-the-art bespoke facilities designed to address the specific training needs of SFR while also being available for sharing with external stakeholders. The project includes three main zones (Figure 2): In total, less than 4% of waste generated was sent to landfill. Controlled site logistics avoided an estimated 1,522 vehicle movements between the SFR Training Centre and the waste transfer station (WTS) with an associated carbon dioxide reduction of 563kg over a one-year period. 1

2 and continuous improvement, are in place. Key aspects of the approach include: Key performance indicators (KPIs), which are set for all Lend Lease projects and are communicated to all staff and subcontractors via tender agreements, inductions and monthly performance tracking. Project performance is measured against Lend Lease s waste reduction and recovery KPI targets. Figure 2 Strathclyde Fire & Rescue Training Centre, site plan (40 acres) The Academic Building providing the administration and technical training for Fire & Rescue personnel who attend the learning and development campus. Located at the front of the campus and extending over two floors, the Academic Building incorporates lecture rooms, a bespoke incident training suite, a career development assessment centre, a 180-seat auditorium, conference rooms, IT rooms, a library and a gymnasium. Practical training facilities consisting of numerous buildings and structures fitted with liquefied petroleum gas fire simulators, set within a community environment to provide a realistic training environment. Features include: a residential area, consisting of a residential village; an industrial area, to simulate hazardous material incidents; and a transport area, to simulate transport-related emergencies. Practical facilities building the hub of the practical zone and main garage area, designed as a mock fire station. The nine-step waste reduction plan Lend Lease has developed a robust corporate approach to (Table 1). The approach ensures that targets and procedures, which encourage innovation The nine-step plan covers the entire construction process, from client engagement through to a completion review. A standardised, web-based site waste management plan database called MINIMISE, developed in conjunction with BRE SmartWaste, is used on all projects. MINIMISE is used to record and monitor data on waste as well as other key environmental metrics such as energy, water and timber. Innovation and continuous improvement are actively encouraged, including trialling new approaches to site waste management and waste data collection. The nine-step plan relates to the key intervention points in the construction process when action should be taken to prevent, reduce or recover construction waste. Each step includes a set of clearly worded tasks, which are supported by a combination of standard forms, checklists and guidance documents. The plan is owned and driven by the project team, with support and troubleshooting advice available from the Lend Lease Environmental Operations Unit. The nine steps allow Lend Lease to apply a standard approach, but in a way that responds to each project s circumstances. For example, the nine steps provide the flexibility to look at each project s design opportunities for waste prevention and to select the waste contractor that can best respond to the waste streams generated by the project. Design stage waste consideration Early consideration of waste by the design team ensured that waste was avoided where 2

3 Table 1 The nine-step waste reduction strategy (Lend Lease) Step Tools and guidance 1 Client engagement Client checklist Advise the client/design team on waste reduction and align aims with client s aspirations 2 Design team waste minimisation WRAP s Designing out Arrange workshops with the design team to Waste principles and establish responsibilities and opportunities to guidance design out waste 3 Subcontractor waste forecast Contractors to submit waste forecast before Waste forecasts analysis checklist work commences and develop waste management options 4 Waste management options Lend Lease preferred Understand how waste companies deal with contractors list each material and how successful each is at waste stream recovery material recovery objectives 5 Waste contractor procurement WRAP assisted Lend Lend Lease has a list of preferred contractors Lease with model capable of removing waste streams, ensuring procurement wording, that their removal satisfies Lend Lease s which can be found corporate targets of re-use, recycle and recover here 6 Waste training and communication Lend Lease in-house Ensure that the project team is aware of the site training with WRAP waste management plan requirements and their site-practice training responsibilities 7 Waste reporting and targets Operating procedures Collect and keep on file all waste transfer notes that form part of the and ensure that waste contractors provide a Lend Lease monthly breakdown of waste removed and environmental recovery rates achieved management system 8 Ongoing review MINIMISE database The project site waste management plan is and Lend Lease KPIs reviewed monthly to ensure accuracy and to (also monitored track progress against forecasts, with the monthly) project team implementing corrective action where necessary 9 Completion review Review the success of the plan, any deviations and lessons learned Lend Lease KPIs (also monitored monthly) possible before construction had begun. Measures included: Specification of Benchmark s Karrier Panel System (ceramic granite). This walling system is installed separately from the facade, thereby wind- and weatherproofing the building at an earlier stage, enabling internal works to begin before the completion of the façade, reducing time on site and wastage resulting from on site storage of materials. Prefabrication modules for electrical cabling. Brick work was designed to match brick coursing sizes to reduce off-cuts. Standardised metal window shutter sizes to reduce off-cuts. Waste forecasting Lend Lease adopted MINIMISE, the SmartWaste waste management tool, throughout the design stage and run-up to works commencing on site. Lend Lease was able to effectively forecast potential waste generation and in doing so identify opportunities to reduce waste before works had begun. Figure 3 shows an excerpt from the SFR s waste minimisation strategy. Table 2 demonstrates the on site waste savings achieved compared with the predicted waste arisings (2,298 tonnes) through the implementation of the nine steps. Waste management options and waste contractor procurement As part of its focus on continual improvement, Lend Lease has developed a central list of preferred waste contractors that can meet the company s ambitious targets. 3

4 Figure 3 Strathclyde Fire & Rescue MINIMISE waste minimisation strategy (Lend Lease) Table 2 Strathclyde Fire & Rescue predicted versus actual waste arisings Site waste material Predicted waste arisings (tonnes) Actual waste arisings (tonnes) Savings achieved (tonnes) Wood Scrap metals General waste Inert 3,655 1,022 2,633 Plasterboard Hard plastics Packaging Removed from site for re-use without further processing Total waste collected from site and processed 3,825 1,527 2,298 4

5 Inert 67% Re-use off site Wood 12% AW Jenkinson Woodwaste Ltd Plasterboard Metal 5.5% Plasterboard recycling unit 3% EMR Packaging/hard plastics 1.5% Trident Recycling Various 1.5% Re-use off site Yooz re-use and recycling Construction site waste Mixed waste 9.5% 5.6% Various recyclers Waste transfer station 3.9% Landfill Figure 4 Construction site waste streams Table 3 SFR waste stream destinations and re-use Waste stream Inert Wood Plasterboard Receiver organisation Foulburn Farm (Shotts) AW Jenkinson Woodwaste Ltd Returned to manufacturer Re-use Crushed off site and supplied as 6F2 material to nearby farm Chipboard manufacture or various other recycled wood products Processed to produce five agricultural and two pharmaceutical products Metal EMR Processed to produce new steel Packaging/ hard plastics Trident Recycling Plastic sold to plastic moulding and refinery industries, packaging sold back to mills to produce recycled cardboard and paper goods, polythene returned to plastics industry for recycling Various Yooz Active4All Charitable construction project Project performance Given the nature of SFR, over half of the waste produced (67%) was inert/aggregate waste. All inert waste was sorted and sent for re-use off site at a local farm under a waste management licence exemption to create an equestrian facility (Figure 4). Almost one-quarter (22%) of waste produced on site was baled and compacted, placed in bulk skips and sent directly to reprocessors for recycling. This method provides clean/sorted material which facilities the recycling process while at the same time improving the efficiency of skip loads offering a reduction in skip void space. The sorted materials included wood, metal, plasterboard and hard plastic waste. Most of these will be reprocessed to create new products (specific uses are detailed in Table 3). 5

6 Table 4 Vehicle journeys avoided through waste management strategy compared with typical practice Carbon savings Quantity Vehicle movements on and off site with traditional skip hire methods 2,100 Vehicle movements on and off site for skip exchange purposes 578 Number of journeys avoided between the waste transfer station and Strathclyde Fire & 1,522 Rescue (approx. 4.5km) Carbon reduction through reduced travel miles (kg CO 2 ) 582 Plasterboard waste was collected and stored as a discrete waste stream on site and was then easily recycled. Waste plasterboard was returned to manufacturers. This approach enabled Lend Lease to ensure that plasterboard waste was removed from the mixed-waste stream and provided reprocessors with quality materials and maximised recovery rates, an initiative very much in tune with government advice. Various re-usable building materials (1.5%), including pipes, plastic fencing, insulation, gypsum, pallets, bricks, timber, drainage channels and breeze blocks, were taken off site for re-use by Yooz Active4All, a charity constructing the first custom-built state-of-the-art sports and activity centre for both disabled and able-bodied individuals. The waste which could not be sent directly to re-use or recycling options (9.5%) was sent to a waste transfer station. Much of this waste was recovered through conventional transfer station processes, resulting in less than 4% of the construction waste overall for the period being sent to landfill. The project implemented a strict segregation policy which reduced the number of vehicle movements that would have been required if a greater amount of mixed waste had been produced for transportation to a waste transfer station. Based on an estimate of the number of journeys that would have been required if all mixed-waste skips had been taken directly to a waste transfer station, the project calculated that 1,522 vehicle journeys had been saved at SFR over the course of the project. The carbon savings were calculated based on the distance to the nearest WTS, which is 4.5km (Table 4). By reducing the number of vehicle journeys associated with waste removal, Lend Lease reduced the associated carbon impact of the project with fewer transport miles; reduced the associated cost of frequent waste removal; achieved a recycling rate far higher than typical practice; and alleviated traffic congestion both at and around the site. Waste reporting and targets All of the waste contractors on Lend Lease s preferred supplier list provided Lend Lease with material types and tonnages collected; destinations of materials for reprocessing; approximate carbon savings from reduction in vehicle movements (calculated using a Defra-approved formula); volume and tonnage of re-use on and off site; and BREEAM input data. 6

7 Table 5 BREEAM Bespoke 2008 waste credits achieved Credits available Credits awarded Credit requirements How requirements will be achieved Construction resource efficiency Construction resource efficiency Waste 1 Construction site waste management 4 4 Quantity of non-hazardous construction waste is the same as or better than good/best practice levels. For three credits, the amount of waste generated per 100m 2 must be <4.7 tonnes Diversion of resources from landfill Exemplary level: at least 90% by mass of non-hazardous construction waste is diverted from landfill Materials were selected based partly on their ability to deliver minimal wastage Materials/off-cuts were re-used on the project where possible External claddings and some internal units were prefabricated and assembled on site Diversion of resources from landfill The project achieved a recovery rate of 96% Through strict segregation the project ensured that all key waste streams were identified for diversion from landfill 96% of waste was diverted from landfill to predetermined uses Innovation Wst1 Construction site waste management 1 1 Waste diversion and re-use Where at least 80% of non-hazardous and 85% of demolition waste is diverted from landfill through either re-use/return or recovery BREEAM waste credits Lend Lease was committed to achieving all of the available waste credits under BREEAM Bespoke Five credits have been achieved as a result of the project implementing the nine-step plan (Table 5). Lessons learned Works on the SFR Training Centre demonstrated the value of effective waste management to projects and the importance of ensuring the cooperation of the whole of the supply chain in both minimising waste arisings and ensuring the maximum diversion of resources from landfill. Procurement and commercial managers are crucial in ensuring that the correct quantities of materials are procured in a way that does not create unnecessary waste. It is important for them to understand which materials are likely to generate the most waste, as this provides a focus for improving procurement and on site activities. Lend Lease recognises the importance of working with the right waste management contractor for a given project. Lend Lease strives to understand at the outset of the project the waste management requirements of its subcontractors to maximise the diversion from landfill opportunities at its facilities. Lend Lease now offers targeted training to those trades that typically generate the most waste (e.g. dry-lining) to ensure that more waste is prevented than diverted. Zero Waste Scotland Ground Floor, Moray House, Forthside Way, Stirling, FK8 1QZ. helpline@zerowastescotland.org.uk Helpline freephone While steps have been taken to ensure its accuracy, Zero Waste Scotland cannot accept responsibility or be held liable to any person for loss or damage arising out of or in connection with this information being inaccurate, incomplete or misleading. This material is copyrighted. It may be reproduced free of charge subject to the material being accurate and not used in a misleading context. The source of the material must be identified and the copyright status acknowledged. This material must not be used to endorse or used to suggest Zero Waste Scotland s endorsement of a commercial product or service. For more detail, please refer to our Terms & Conditions on our website:

Innovative waste management approach achieves exemplary recovery rates

Innovative waste management approach achieves exemplary recovery rates : University of the West of Scotland, Ayr Campus Innovative waste management approach achieves exemplary Key facts The new campus was designed to achieve a BREEAM rating of Excellent. 96% of the 1,200

More information

Resource efficiency pursued through design coordination and waste management

Resource efficiency pursued through design coordination and waste management : Edinburgh International Conference Centre Expansion and Speculative Office Space Resource efficiency pursued through design coordination and Key facts Extensive use of building information modelling

More information

Minimising construction waste through project design

Minimising construction waste through project design Case Study: New South Glasgow Hospitals Minimising construction waste through project design Key facts Applying WRAP s Designing out Waste principles to the project design identified 21 areas of potential

More information

McGrath works in partnership with Hackney Homes

McGrath works in partnership with Hackney Homes Case study: Achieving good practice waste recovery McGrath works in partnership with Hackney Homes Hackney Homes is using a partnering approach across the whole supply chain, to deliver the Decent Homes

More information

Reducing construction waste saves money Bridge Learning Campus, Bristol Contractor: Skanska

Reducing construction waste saves money Bridge Learning Campus, Bristol Contractor: Skanska Exemplar case study Reducing construction waste saves money Bridge Learning Campus, Bristol Contractor: Skanska Background The Bridge Learning Campus (Bristol) ( BLC ) was used as a test bed for achieving

More information

Zero waste to landfill: Construction waste collection good practice

Zero waste to landfill: Construction waste collection good practice Case study Zero waste to landfill: Construction waste collection good practice Zero waste policies are a key step towards sustainable waste management. This case study examines the economic and environmental

More information

Best Practice Construction Waste Procurement: Office Fit-Out of 15 Canada Square, Canary Wharf

Best Practice Construction Waste Procurement: Office Fit-Out of 15 Canada Square, Canary Wharf Waste procurement case study Best Practice Construction Waste Procurement: Office Fit-Out of 15 Canada Square, Canary Wharf This case study examines how engagement between the main contractor, client and

More information

Defence sector: recycling waste in construction Defence Estates Regional Prime Contract East, Babcock DynCorp

Defence sector: recycling waste in construction Defence Estates Regional Prime Contract East, Babcock DynCorp Case study Defence sector: recycling waste in construction Defence Estates Regional Prime Contract East, Babcock DynCorp By thinking Best Value, not Least Cost when reviewing the way they procure and manage

More information

Costs and benefits of reducing waste in construction. Defence sector new build Woolwich single living accommodation modernisation (SLAM)

Costs and benefits of reducing waste in construction. Defence sector new build Woolwich single living accommodation modernisation (SLAM) Costs and benefits of reducing waste in construction Defence sector new build Woolwich single living accommodation modernisation (SLAM) Value Percentage of 3.2m construction cost Cost saving potential

More information

SMARTWaste: Overview and data Maggie Blackwell. Part of the BRE Trust

SMARTWaste: Overview and data Maggie Blackwell. Part of the BRE Trust SMARTWaste: Overview and data Maggie Blackwell Part of the BRE Trust SMARTWaste Construction tools SMARTWaste Construction tools SMARTWaste Plan: Online Site Waste Management Plan tool www.smartwaste.co.uk

More information

Construction waste collection good practice: Gloucester Quays

Construction waste collection good practice: Gloucester Quays Case Study Construction waste collection good practice: Gloucester Quays This case study examines how applying good practice, such as segregation at source, produced material streams suitable for direct

More information

Benefits of off site manufacture

Benefits of off site manufacture Case Study Benefits of off site manufacture Jocelyn Park, Somerset Jocelyn Park is a housing development owned and managed by South Somerset Homes Housing Association. There are 64 homes on site designed

More information

Reducing Waste in Sainsbury s Supermarket Refits through off site fabrication

Reducing Waste in Sainsbury s Supermarket Refits through off site fabrication WAS031 Off site Construction Case Study Reducing Waste in Sainsbury s Supermarket Refits through off site fabrication Sainsbury s have made effective use of the Fit Out UK / RG s off site fabrication and

More information

A blueprint for reducing waste and cutting costs

A blueprint for reducing waste and cutting costs A blueprint for reducing waste and cutting costs An average 3-bed unit produces between 5 and 13 tonnes of construction waste. Reducing this could save 250-500 per unit. Five corporate-level actions and

More information

A metric for the construction sector. The Net Waste Method testing a new standard for measuring waste neutrality

A metric for the construction sector. The Net Waste Method testing a new standard for measuring waste neutrality A metric for the construction sector The Net Waste Method testing a new standard for measuring waste neutrality WRAP works in partnership to encourage and enable businesses and consumers to be more efficient

More information

Halving Waste to Landfill

Halving Waste to Landfill Case study: BAM Construct Halving Waste to Landfill BAM Construct UK was one of the first contractors to sign up to the Halving Waste to Landfill industry commitment in 2008. Since then, BAM has been working

More information

Waste management contractors selling the benefits of your Halving Waste to Landfill Commitment to construction clients

Waste management contractors selling the benefits of your Halving Waste to Landfill Commitment to construction clients Good Practice Guide: Waste management contractors 1 Good Practice Guide Waste management contractors selling the benefits of your Halving Waste to Landfill Commitment to construction clients This short

More information

The emphasis should be on the contractor to develop the targets for waste reduction and recovery. What is good practice?

The emphasis should be on the contractor to develop the targets for waste reduction and recovery. What is good practice? Material change for a better environment Procurement guidance for construction Setting a requirement for Waste Minimisation and Management 2 Setting a requirement for Waste Minimisation and Management

More information

Site Waste management Plan (SWMP)

Site Waste management Plan (SWMP) Author: M.Graney & Sons Ltd. 1. Project Title: Underpinning, Lower ground floor Extension and Refurbishment Works. 2. Location: 21 Old Church Street, London, SW3 5DL. 3. Nature of Project: The works comprise

More information

Grays Waste Management

Grays Waste Management Grays Waste Management WRAP Cymru (Waste & Resources Action Programme in Wales) works directly with the recycling industry, specifically on waste management and materials recovery, and with reprocessing

More information

Assessing the costs and benefits of reducing waste in construction trade packages

Assessing the costs and benefits of reducing waste in construction trade packages Assessing the costs and benefits of reducing waste in construction trade packages Dense concrete blocks and facing bricks, with mineral wool insulation batts Value Percentage of 100k spend Cost saving

More information

BUILDING PRODUCTS DIVISION

BUILDING PRODUCTS DIVISION BUILDING PRODUCTS DIVISION The following figures show the environmental and social performance data for the Hadley Group - Building Products Division for the period 1 st May 2017 30 st April 2018. Greenhouse

More information

Halving Waste to Landfill, SEESA

Halving Waste to Landfill, SEESA SEESA is working hard to achieve its target of 90% diversion of waste to landfill by 2012 by exploring new ways of working, applying initiatives to eliminate and minimise waste, and to reuse, recycle and

More information

Assessing the costs and benefits of reducing waste in construction

Assessing the costs and benefits of reducing waste in construction Assessing the costs and benefits of reducing waste in 20 new build timber-framed houses Value Percentage of 1.36m cost Cost saving potential 21,470 1.58% Additional costs to achieve these savings TOTAL

More information

Railways: Waste less and save money

Railways: Waste less and save money Cutting the cost of waste Halving Waste to Landfill Railways: Waste less and save money Procurement good practice for railway infrastructure construction and maintenance Introduction Buying less and throwing

More information

Construction Waste Management Plan Guidelines. A resource for Western Australian Local Government, Developers, Property Owners and Builders

Construction Waste Management Plan Guidelines. A resource for Western Australian Local Government, Developers, Property Owners and Builders Construction Waste Management Plan Guidelines A resource for Western Australian Local Government, Developers, Property Owners and Builders Contents 1 Introduction... 2 2 Project Planning... 3 3 Construction

More information

Utilities: Waste less and save money

Utilities: Waste less and save money Cutting the cost of waste Utilities: Waste less and save money Procurement good practice for utility infrastructure construction and maintenance Who should read this leaflet? utility company senior managers;

More information

Construction Waste Measurement Guide

Construction Waste Measurement Guide Draft V6 Last updated: February 2013 Construction Waste Measurement Guide A guide to measuring and reporting waste from construction activities 1 Introduction This document provides guidance on how to

More information

Tool for measuring the recovery rates in CDEW MRFs

Tool for measuring the recovery rates in CDEW MRFs Guidance notes Tool for measuring the recovery rates in CDEW MRFs Guidance notes for the Site-Specific Waste Analysis Tool (SSWAT) to measure recovery rates of construction, demolition and excavation waste

More information

Raploch: urban regeneration

Raploch: urban regeneration Construction case study Raploch: urban regeneration This case study describes how the WRAP Regeneration Guide principles have been applied to the tendering and procurement stage of the Raploch regeneration

More information

Assessing the costs and benefits of reducing waste in construction

Assessing the costs and benefits of reducing waste in construction Assessing the costs and benefits of reducing waste in New build concrete-framed office Value Percentage of 23m cost Cost saving potential 125,800 0.55% Additional costs to achieve these savings TOTAL POTENTIAL

More information

Material resource efficiency in construction

Material resource efficiency in construction Material resource efficiency in construction Supporting a circular economy Katherine Adams and Gilli Hobbs Material resource efficiency in construction Supporting a circular economy Katherine Adams and

More information

Sustainability Best Practice Case Study. Reducing Waste, Reducing Cost. The UK construction industry waste challenge

Sustainability Best Practice Case Study. Reducing Waste, Reducing Cost. The UK construction industry waste challenge Sustainability Best Practice Case Study Reducing Waste, Reducing Cost With the construction industry sending 17% of its total waste produced to landfill each year and spiralling landfill costs the UK government

More information

North West Site Waste Management Plan September 2011

North West Site Waste Management Plan September 2011 North West Site Waste Management Plan September 2011 Table of Contents Introduction... 1 Project Information... 1 Document Control... 4 Responsibilities... 4 Site Waste Management Plans Regulations 2008

More information

Non-packaging plastics

Non-packaging plastics 00 Good Practice Guide Good Practice Guide Non-packaging plastics Environmental good practice guide for the collection of non-packaging plastics The Waste Protocols Project is a joint Environment Agency

More information

The content in this APC Annual Report is hereby endorsed by the Chief Executive Officer, or equivalent officer of the organisation.

The content in this APC Annual Report is hereby endorsed by the Chief Executive Officer, or equivalent officer of the organisation. Signatory Name: Smiths Snackfoods Company, The Status: Completed The content in this APC Annual Report is hereby endorsed by the Chief Executive Officer, or equivalent officer of the organisation. Industry

More information

Delivering Sustainability with Prestige: at the BMW PGA Championships

Delivering Sustainability with Prestige: at the BMW PGA Championships Delivering Sustainability with Prestige: at the BMW PGA Championships Delivering Sustainability with Prestige at the BMW PGA Tour The European Tour's flagship event attracts the elite of the world s golfers

More information

KPI. Continuous Improvement Test (CIT) Measurement. To be measured in line with HSE guidance for calculating the Accident Incident Rate (AIR)

KPI. Continuous Improvement Test (CIT) Measurement. To be measured in line with HSE guidance for calculating the Accident Incident Rate (AIR) Summary Table Key area of Health and Safety 1.1. Reportable RIDDOR accidents in the hubco members and Tier 1 suppliers' organisations active in the hub territory (business wide AIR). where the number of

More information

The efficient use of materials in regeneration projects

The efficient use of materials in regeneration projects Linking demolition and new build a step by step guide The efficient use of materials in regeneration projects 10. Demolition phase The Demolition phase section outlines the planning of the demolition activities

More information

Striving for Zero to Landfill

Striving for Zero to Landfill Striving for Zero to Landfill www.rbwaste.co.uk WASTE SOLUTIONS An Introduction Contents 3 Introduction 4 Our Recycling Facilities 6 Materials Recovery 8 Skip Hire 9 Grab Hire 10 Waste Reporting 11 Commercial

More information

Environmental Policy and Guide December 2010

Environmental Policy and Guide December 2010 Environmental Policy and Guide December 2010 Page 1 of 11 ENVIRONMENTAL POLICY A responsible and forward-looking approach to environmental issues is an important factor in Intu Properties plc s continuing

More information

The Demolition Protocol: Aggregates Resource Efficiency in Demolition and Construction. Volume 3. For Contractors

The Demolition Protocol: Aggregates Resource Efficiency in Demolition and Construction. Volume 3. For Contractors The Demolition Protocol: Aggregates Resource Efficiency in Demolition and Construction Volume 3. For Contractors 2 Extracted from the Demolition Protocol Who is this document aimed at? The Demolition Protocol

More information

Sustainability Action Plan 2019

Sustainability Action Plan 2019 Sustainability Action Plan Sustainability Action Plan Contents 1.0 Strategic goal: Engage with our stakeholders 3 Policy goal A: Engage with advisors, suppliers, tenants and stakeholders to ensure we are

More information

For guidance on disposal of Polychlorinated Biphenyl (PCB) contaminated equipment or fluids, please refer to the Guidance Note NR/GN/ESD03.

For guidance on disposal of Polychlorinated Biphenyl (PCB) contaminated equipment or fluids, please refer to the Guidance Note NR/GN/ESD03. 1 Purpose This document provides information on how to effectively manage waste. This guidance is to support the requirements that are set out in the Level 2 Environment and Social Minimum Requirements

More information

Baselines and benchmarks 2009

Baselines and benchmarks 2009 Benchmarks and Baselines 2009 Executive Summary The aim of this work, which has been funded by the Construction Resources and Waste Platform 1, was to produce a set of benchmarks for the arsings for construction

More information

The content in this APC Annual Report is hereby endorsed by the Chief Executive Officer, or equivalent officer of the organisation.

The content in this APC Annual Report is hereby endorsed by the Chief Executive Officer, or equivalent officer of the organisation. Signatory Name: Colgate Palmolive (Australia) Pty Ltd Status: Completed The content in this APC Annual Report is hereby endorsed by the Chief Executive Officer, or equivalent officer of the organisation.

More information

Appendix I -1 Demolition Waste Estimates

Appendix I -1 Demolition Waste Estimates Appendix I -1 Demolition Waste Estimates Appendix I-1: Estimated demolition waste generated from the proposed JFH Demolition work Year Waste Mass (tonnes) St Elmo s Substation 2018 626 Westaway Court 2019

More information

Reducing and recycling plasterboard waste on a site where space is a constraint

Reducing and recycling plasterboard waste on a site where space is a constraint Plasterboard case study Reducing and recycling plasterboard waste on a site where space is a constraint This case study describes the approaches taken to design out, recover and recycle plasterboard waste

More information

Benefits of off site manufacture

Benefits of off site manufacture Case Study Benefits of off site manufacture British Land Ropemaker site, London Ropemaker is a British Land commercial building on a prominent London city site. The site has 586,000 square foot net lettable

More information

Waste sustainability in action

Waste sustainability in action Waste sustainability in action www.instantwaste.com.au WASTE MANAGEMENT SOLUTIONS. waste collection, waste PROCESSING and resource recovery. OUR DIFFERENCE. Instant Waste Management operates in the waste

More information

PLASTERBOARD SUSTAINABILITY INITIATIVE PSP (UK) 13 November 2012, European Parliament Brussels Presented by: Malcolm Waddell, WRAP UK

PLASTERBOARD SUSTAINABILITY INITIATIVE PSP (UK) 13 November 2012, European Parliament Brussels Presented by: Malcolm Waddell, WRAP UK PLASTERBOARD SUSTAINABILITY INITIATIVE PSP (UK) 13 November 2012, European Parliament Brussels Presented by: Malcolm Waddell, WRAP UK Agenda Introduction to WRAP Plasterboard Sustainability Partnership

More information

Achieving effective Waste Minimisation

Achieving effective Waste Minimisation Practical solutions for sustainable construction Achieving effective Waste Minimisation Guidance for construction clients, design teams and contractors WRAP works in partnership to encourage and enable

More information

BNPB3: Plasterboard - legislation and policy drivers

BNPB3: Plasterboard - legislation and policy drivers BNPB3: Plasterboard - legislation and policy drivers Version 1.6 This Briefing Note and referenced information is a public consultation document and will be used to inform Government decisions. The information

More information

The efficient use of materials in regeneration projects

The efficient use of materials in regeneration projects Linking demolition and new build a step by step guide The efficient use of materials in regeneration projects 5. Key Performance Indicators WRAP works in partnership to encourage and enable businesses

More information

Commercial and industrial waste in Sydney. Overview. Department of Environment, Climate Change and Water NSW

Commercial and industrial waste in Sydney. Overview. Department of Environment, Climate Change and Water NSW Commercial and industrial waste in Sydney Overview Department of Environment, Climate Change and Water NSW House Commercial deconstruction and industrial waste in Sydney Manufacturers, shops and businesses

More information

Waste FY Introduction. 2. Waste. 3. Management Approach

Waste FY Introduction. 2. Waste. 3. Management Approach 1. Introduction This document forms part of our Disclosures on Management Approach (DMA) series, prepared in accordance with the Global Reporting Initiative s G4 Guidelines. The DMA series is designed

More information

Waste Management Policy

Waste Management Policy Waste Management Policy Contents 1. Introduction 2. Policy Statement 3. Policy Objectives 4. Application 5. Organisation and Management 6. Glossary of Terms Document Control Information: Last updated on:

More information

Demolition Waste Management Plan Guidelines

Demolition Waste Management Plan Guidelines Demolition Waste Management Plan Guidelines A resource for Western Australian Local Government, Developers, Property Owners and Demolition Contractors Contents 1 Introduction... 2 2 Project Planning...

More information

Scotland s Litter Problem. Quantifying the scale and cost of litter and flytipping

Scotland s Litter Problem. Quantifying the scale and cost of litter and flytipping Scotland s Litter Problem Quantifying the scale and cost of litter and flytipping Zero Waste Scotland works with businesses, individuals, communities and local authorities to help them reduce waste, recycle

More information

Material Logistics Plan Good Practice Guidance

Material Logistics Plan Good Practice Guidance Waste Minimisation in Construction Material Logistics Plan Good Practice Guidance Guidance for Clients, Design Teams, Construction Contractors and Sub-contractors on developing and implementing an effective

More information

Barts Hospital, London

Barts Hospital, London Case Study: Material Logistics Planning Barts Hospital, London A comprehensive logistics strategy at Barts Hospital in central London successfully reduces waste, site traffic and carbon emissions. Project

More information

Benefits of the WRAP SWMP Template. Birmingham, 1 April 2008

Benefits of the WRAP SWMP Template. Birmingham, 1 April 2008 Benefits of the WRAP SWMP Template Birmingham, 1 April 2008 Dehlia Farrow Associate Director Environment, Halcrow Use of WRAP SWMP Template Improve your project s waste and resource efficiency Demonstrate

More information

Waste Management Plan

Waste Management Plan Plan Development Divisional Office Client Principal Contractor Principal Designer Lead Designer Location Description of Development Development Start Pewterspear Green Road, Warrington Manchester Neil

More information

Sustainability Action Plan

Sustainability Action Plan Sustainability Action Plan Sustainability Report 2017 Contents 1.0 Strategic goal: Environmentally sustainable reuse and management of buildings 3 Policy goal A: Comply with legal requirements 3 Policy

More information

Construction Site Waste Management Process.

Construction Site Waste Management Process. Construction Site Waste Management Process. EMS DOCUMENT TYPE: ENVIRONMENTAL ASPECT: PURPOSE: Operational Control Document Waste Management To ensure we manage our waste in compliance with legislation

More information

Procurement Services Packaging Policy.

Procurement Services Packaging Policy. Procurement Services Packaging Policy. Introduction Procurement Services is committed to improving the way it manages the environmental and sustainable development issues arising from the services it provides

More information

Sustainability and Process Benefits of Modular Construction

Sustainability and Process Benefits of Modular Construction Sustainability and Process Benefits of Modular Construction Lawson, R.M. The University of Surrey, UK, (email: m.lawson@surrey.ac.uk) Ogden, R.G. Oxford Brookes University, UK, (email: rgogden@brookes.ac.uk)

More information

Sustainability Performance Report 2nd report: 2012 performance data

Sustainability Performance Report 2nd report: 2012 performance data Sustainability Performance Report 2nd report: 2012 performance data Managing Directors Statement In 2012 Lignacite Ltd committed to a Sustainable Strategy for Masonry. This initiative has been the catalyst

More information

Reducing Food and Packaging Waste in the Egg Supply Chain

Reducing Food and Packaging Waste in the Egg Supply Chain Reducing Food and Packaging Waste in the Egg Supply Chain Packaging-related product damage across the food and drink sector in the UK represents a significant cost to the grocery industry in terms of lost

More information

Expenditure. Vehicles. Call centre cost. Marketing. Cost of reuse. Disposal

Expenditure. Vehicles. Call centre cost. Marketing. Cost of reuse. Disposal Costs Introduction The cost of running a bulky waste collection service is the difference between income and expenditure. However, any set-up and up-front costs, prior to starting the service will also

More information

Cambridgeshire County Council County Planning, Minerals and Waste

Cambridgeshire County Council County Planning, Minerals and Waste Cambridgeshire County Council County Planning, Minerals and Waste Guidance on Waste Audit and Management Strategies for submission in support of a planning application or to fulfil a requirement of a planning

More information

Environmental Policy

Environmental Policy Date: February 2012 Version: V2.1 2011 City of Glasgow CollegeCharity Number: SC0 36198 1. Key Aims The Key aims of the College s are: To minimise the use of non-renewable and environmentally-damaging

More information

Environmental KPI

Environmental KPI Environmental KPI 2013 www.marshalls.co.uk Contents Marshalls plc group of specialist businesses Statement from David Sarti COO 3 Board Responsibility 3 Environmental Policy - Key Features 3-4 Environmental

More information

FLOORING RESOURCE EFFICIENCY PLAN 1 ST BROADLOOM CARPET MAP MEETING 13 TH OCTOBER 2009

FLOORING RESOURCE EFFICIENCY PLAN 1 ST BROADLOOM CARPET MAP MEETING 13 TH OCTOBER 2009 FLOORING RESOURCE EFFICIENCY PLAN 1 ST BROADLOOM CARPET MAP MEETING 13 TH OCTOBER 2009 Key Findings of Scoping Study FLOORING: Towards a Resource Efficiency Plan Scoping Study February / March 2009 Looked

More information

Transport Plan V1.0 March 2013

Transport Plan V1.0 March 2013 Transport Plan V1.0 March 2013 Contents Page No. 1.0 Introduction 2 2.0 Aims of The Transport Plan 3 3.0 Vehicle Specification and Procurement 3 4.0 Vehicle Maintenance 5 5.0 Vehicle Replacement Cycle

More information

Design out. Waste Workshop. A guidance document produced by Network Rail in collaboration with:

Design out. Waste Workshop. A guidance document produced by Network Rail in collaboration with: Design out Waste Workshop A guidance document produced by Network Rail in collaboration with: Guidance on Designing out Waste: How to run a Design out Waste Workshop This document provides guidance on

More information

Code for Sustainable Homes November Checklist Man 3 Construction Site Impacts. Evidence Demonstrating How Criteria Will Be Met

Code for Sustainable Homes November Checklist Man 3 Construction Site Impacts. Evidence Demonstrating How Criteria Will Be Met Development Name: Specification ID: Checklist Man 3 - Construction Site Impacts a. Commitment to monitor, report and set targets for CO 2 production of energy use arising from site activities 1. Confirmation

More information

End of Project Report : Newtown Secondary School

End of Project Report : Newtown Secondary School Resource Management Planning: Worked Example End of Project Report : Newtown Secondary School The template for this document is available at www.wrap.org.uk/node/13707 Document Owner Project Project Reference

More information

Construction Strategy: Newtown Secondary School

Construction Strategy: Newtown Secondary School Resource Management Planning: Worked Example Construction Strategy: Newtown Secondary School The template for this document is available at www.wrap.org.uk/node/13707 Document Owner Project Project Reference

More information

Green Star. Construction & Demolition Waste Reporting Criteria

Green Star. Construction & Demolition Waste Reporting Criteria Green Star Construction & Demolition Waste Reporting Criteria 2 Table of Contents Table of Contents 2 Executive Summary 3 About the Green Building Council of Australia and Green Star 4 Definitions 5 Reporting

More information

There will be no significant impact from solid waste arising during the development of the proposed power plant.

There will be no significant impact from solid waste arising during the development of the proposed power plant. 11 SOLID WASTE 11.1 SUMMARY OF RESIDUAL IMPACTS There will be no significant impact from solid waste arising during the development of the proposed power plant. 11.2 INTRODUCTION This chapter considers

More information

«Improving management of construction and demolition waste»

«Improving management of construction and demolition waste» «Improving management of construction and demolition waste» What is DEMOCLES? DEMOCLES (The keys of demolition) is a 2 years collaborative project involving more than 40 French stakeholders of construction

More information

CURRENT STATE OF CONSTRUCTION WASTE IN THE CITY OF CAPE TOWN. A VAN VUUREN / 16 September 2014

CURRENT STATE OF CONSTRUCTION WASTE IN THE CITY OF CAPE TOWN. A VAN VUUREN / 16 September 2014 CURRENT STATE OF CONSTRUCTION WASTE IN THE CITY OF CAPE TOWN A VAN VUUREN / 16 September 2014 THE CAPE TOWN WE LOVE OTHER IMAGES OF OUR CITY ILLEGAL DUMPING IS A REALITY During 2013: There were more than

More information

Vinyl flooring: Making take-back schemes pay back on refurbishment projects

Vinyl flooring: Making take-back schemes pay back on refurbishment projects Refurbishment Resource Efficiency Case Study: Vinyl flooring take-back schemes Vinyl flooring: Making take-back schemes pay back on refurbishment projects This case study focuses on three UK vinyl flooring

More information

The content in this APC Annual Report is hereby endorsed by the Chief Executive Officer, or equivalent officer of the organisation.

The content in this APC Annual Report is hereby endorsed by the Chief Executive Officer, or equivalent officer of the organisation. Signatory Name: Mattel Pty Ltd Status: Completed The content in this APC Annual Report is hereby endorsed by the Chief Executive Officer, or equivalent officer of the organisation. Industry sector (please

More information

Signatory Name: Ward McKenzie Pty Ltd

Signatory Name: Ward McKenzie Pty Ltd Signatory Name: Ward McKenzie Pty Ltd The question numbers in this report refer to the numbers in the report template. t all questions are displayed in this report. Status: Complete The content in this

More information

Brighton & Sussex University Hospital

Brighton & Sussex University Hospital Brighton & Sussex University Hospital Regional Centre for Teaching, Trauma & Tertiary Care known as the 3Ts Programme Project Address: Eastern Road, Brighton BN2 5BE Principal Contractor: Laing O Rourke

More information

Cost Assessment of Wales Environment Bill Measures on Business Waste Producers in the Construction & Demolition Sector

Cost Assessment of Wales Environment Bill Measures on Business Waste Producers in the Construction & Demolition Sector Final Report Assessment of Wales Environment Bill Measures on Business Waste Producers in the Construction & Demolition Sector Assessment of the financial implications of additional segregation / collection

More information

Beauly-Denny Replacement Transmission Line Project

Beauly-Denny Replacement Transmission Line Project Beauly-Denny Replacement Transmission Line Project for the Section from Beauly-Wharry Burn July 2010 Beauly-Denny Replacement Transmission Line Project Beauly-Denny Replacement Transmission Line Project

More information

Sustainable Procurement Case Study Natural History Museum

Sustainable Procurement Case Study Natural History Museum Sustainable Procurement Case Study Natural History Museumm Embedding sustainability in procurement practices: a UK museum s persp pective This documentt is uncontrolled if printed London s Natural History

More information

Signatory Name: Visy Industries Australia Pty Ltd

Signatory Name: Visy Industries Australia Pty Ltd Signatory Name: Visy Industries Australia Pty Ltd The question numbers in this report refer to the numbers in the report template. t all questions are displayed in this report. Status: Complete The content

More information

Sustainability in Precast Concrete

Sustainability in Precast Concrete Sustainability in Precast Concrete Balbriggan (IRL) Brigg (UK) Our Policy Founded in 1985, Techrete is a leading company in the design, manufacture and supply of architectural pre-cast cladding to the

More information

The content in this APC Annual Report is hereby endorsed by the Chief Executive Officer, or equivalent officer of the organisation.

The content in this APC Annual Report is hereby endorsed by the Chief Executive Officer, or equivalent officer of the organisation. Signatory Name: Alto Manufacturing Pty Ltd Status: Completed The content in this APC Annual Report is hereby endorsed by the Chief Executive Officer, or equivalent officer of the organisation. Industry

More information

Measuring the Impact of Building Materials and the Opportunity for Wood- Based Construction. 12 October 2010 Dr Ed Suttie BRE Timber

Measuring the Impact of Building Materials and the Opportunity for Wood- Based Construction. 12 October 2010 Dr Ed Suttie BRE Timber Measuring the Impact of Building Materials and the Opportunity for Wood- Based Construction 12 October 2010 Dr Ed Suttie BRE Timber Introduction Construction industry drivers Key construction materials

More information

Resources and Waste Management Exhibition recycles 83% of waste

Resources and Waste Management Exhibition recycles 83% of waste i2i Events and the CIWM join forces to achieve 83% recycling Resources and Waste Management Exhibition recycles 83% of waste High recycling rates and plenty of supplier engagement to minimise waste on

More information

Construction Method Statement

Construction Method Statement Construction Method Statement Introduction. The project involves the construction of the new Apartment Extra Car Home for Grwp Cynefin in Pothmadog, Gwynedd, Wales. The programme and construction methodology

More information

Case Study: Barts Health NHS Trust Food Waste Collection

Case Study: Barts Health NHS Trust Food Waste Collection Case study Case Study: Barts Health NHS Trust Food Waste Collection Case study outlining food waste collection services from Barts Health NHS Trust hospital sites March 2014 Case Study: Barts Health NHS

More information

Signatory Name: Master Distributors Pty Ltd

Signatory Name: Master Distributors Pty Ltd Signatory Name: Master Distributors Pty Ltd The question numbers in this report refer to the numbers in the report template. t all questions are displayed in this report. Status: Complete The content in

More information

Patons Lane CLC Meeting

Patons Lane CLC Meeting CONTENTS 01 INSERT DIVIDER TITLE 3 02 INSERT DIVIDER TITLE 4 03 INSERT DIVIDER TITLE 5 04 INSERT DIVIDER TITLE 6 05 INSERT DIVIDER TITLE 7 06 INSERT DIVIDER TITLE 8 07 INSERT DIVIDER TITLE 9 08 INSERT

More information

Delivering higher recycled content in construction projects

Delivering higher recycled content in construction projects Construction procurement guidance Delivering higher recycled content in construction projects Client and team Contractor and team Sub-contractor and team Requirement Policy Generic options for improvement

More information