EVALUATION OF ENVIRONMENTAL MONITORING DATA GATHERED DURING ASHTABULA RIVER DREDGING, ASHTABULA RIVER, OHIO

Size: px
Start display at page:

Download "EVALUATION OF ENVIRONMENTAL MONITORING DATA GATHERED DURING ASHTABULA RIVER DREDGING, ASHTABULA RIVER, OHIO"

Transcription

1 EVALUATION OF ENVIRONMENTAL MONITORING DATA GATHERED DURING ASHTABULA RIVER DREDGING, ASHTABULA RIVER, OHIO D. Plomb 1, S. Cieniawski 2, and D. Pham 3 ABSTRACT The Ashtabula River Area of Concern (AOC) lies in extreme northeast Ohio. The sediments within the Ashtabula River AOC are contaminated with polychlorinated biphenyls (PCBs) and radionuclides. PCBs are the primary constituent of concern. Based on previous evaluations of the site and collaboration between the various stakeholder groups, a dredging and disposal remedy was selected for the contaminated sediments in the Ashtabula River between the Upper Turning Basin and the 5th Street Bridge (Figure 1). The immediate project goals were to remove as much contaminant mass as feasible given constructability and financial constraints, and to restore navigational use of the river. Long-term reductions in surficial PCB concentrations are anticipated as a result of the completed environmental dredging project and natural sedimentation of clean sediments in the project area. Between 2006 and 2007, approximately 382,000 cubic meters (500,000 cubic yards) of sediment were dredged from the AOC. A 15-centimeter (6-inch) sand cover was also placed over designated areas following the completion of dredging activities. The remedial action (RA) was conducted on behalf of the U.S. Environmental Protection Agency (USEPA) under the Great Lakes Legacy Act (GLLA). One of the key components of the RA was environmental monitoring of the Ashtabula River to ensure protection of human health and the environment during dredging operations. The environmental monitoring activities included monitoring the water quality for excessive sediment resuspension during dredging, quantifying PCB and radionuclide levels in the water column during dredging, characterizing the thickness of the remaining sediment column and surficial PCB concentrations following completion of dredging, and conducting bathymetric surveys following completion of dredging and sand cover placement. As noted, one of the environmental monitoring components was to monitor sediment conditions following removal activities to ensure that the horizontal and vertical limits of dredging were achieved and that no high levels of contamination were left exposed. Characterization of post-dredge sediment conditions was accomplished by conducting a post-dredge bathymetric survey as well as by measuring post-dredge sediment thicknesses through probing and by collecting post-dredge surface sediment samples. Using the post-dredge surface sediment data, a post-dredge surface-weighted average concentration (SWAC) was calculated to determine the average PCB concentration remaining following dredging. The PCB SWAC was calculated to be 2.4 parts per million (ppm) for the entire dredge area prior to sand placement. Following sand placement over designated areas, the PCB SWAC was reduced to 1.1 ppm for the entire dredge area. A cleanup pass was performed at approximately 20% of the post-dredge sediment sampling locations. Segregating the cleanup areas from the non-cleanup areas, a PCB SWAC was also calculated. The PCB SWAC for cleanup areas was calculated to be 0.1 ppm. The PCB SWAC for non-cleanup areas was calculated to be 3.9 ppm. These values are prior to sand cover placement. Keywords: Contaminated sediment, PCBs, radionuclides, SWAC, survey. 1 Senior Project Manager, CH2M HILL, 135 S. 84 th St., Suite 325, Milwaukee, WI, 53214, USA, T: , dplomb@ch2m.com 2 Work Assignment Manager, U.S. EPA Region 5, Great Lakes National Program Office (GLNPO), 77 W. Jackson Blvd., Chicago, IL 60604, USA, T: , cieniawski.scott@epa.gov 3 Project Scientist, CH2M HILL, 135 S. 84 th St., Suite 325, Milwaukee, WI, 53214, USA, T: , dpham@ch2m.com 329

2 0 600 Feet Legend Project Area Figure 1 - Ashtabula River RA Project Area - Ashtabula River AOC 330

3 INTRODUCTION The Ashtabula River Area of Concern (AOC) lies in extreme northeast Ohio. The sediments within the Ashtabula River AOC are contaminated with polychlorinated biphenyls (PCBs) and radionuclides. The maximum historical PCB concentration was 660 parts per million (ppm), with an average of 7.5 ppm throughout the sediment column (Ashtabula River Partnership, 2001). PCBs are the primary constituent of concern. Based on previous evaluations of the site and collaboration between the various stakeholder groups, a dredging and disposal remedy was selected for the contaminated sediments in the Ashtabula River between the Upper Turning Basin and the 5th Street Bridge (Figure 1). The project goals were to remove as much contaminant mass as feasible given constructability and financial constraints, and to restore navigational use of the river. The main components of the remedial action (RA) activities were: 1) environmental dredging of contaminated sediments from just south of the Upper Turning Basin to the 5th Street Bridge, 2) monitoring of dredging conditions during removal activities to ensure that the horizontal and vertical limits of dredging are achieved and no high levels of contamination are left exposed, and the protection of human health and the environment is ensured during the dredging process, and 3) manual placement of clean cover material over specific areas. The RA was conducted on behalf of the U.S. Environmental Protection Agency (USEPA) under the Great Lakes Legacy Act (GLLA). DREDGING AND SAND COVER ACTIVITIES Between 2006 and 2007, approximately 382,000 cubic meters (500,000 cubic yards) of sediment were dredged from the AOC. The dredged sediments were transported hydraulically through a dual-walled high-density polyethylene (HDPE) pipeline to a consolidation facility (CF) where they were passively dewatered in geotextile tubes, and the weep water returned to the Ashtabula River after being treated at the water treatment plant (WTP). The sediments containing geotextile tubes will remain in place at the CF, which is a specially constructed Toxic Substances Control Act (TSCA)-level facility. Dredging operations were completed in mid-october Following the completion of dredging, placement of clean cover material occurred over specified areas. Two areas received cover material, encompassing an area of approximately 9,160 square meters (98,600 square feet) (DMU-12 and the North slope of Jack s Marine). A 15- centimeter (6-inch) sand cover was placed over these designated areas. ENVIRONMENTAL MONITORING ACTIVITIES One of the key components of the RA was environmental monitoring of the Ashtabula River to ensure protection of human health and the environment during dredging operations. The environmental monitoring activities included monitoring the water quality for excessive sediment resuspension during dredging, quantifying PCB and radionuclide levels in the water column during dredging, characterizing the thickness of the remaining sediment column and surficial PCB concentrations following completion of dredging, and conducting bathymetric surveys following completion of dredging and sand cover placement. Monitoring of Water Quality for Turbidity/Total Suspended Solids Water quality monitoring was accomplished through turbidity monitoring as a means to monitor and control contaminant release and resuspension during dredging operations. Three locations along the river were monitored for turbidity by measuring nephelometric turbidity units (NTUs). A correlation of turbidity to total suspended solids (TSS) was developed during 2006 dredging activities to estimate TSS concentrations using the turbidity readings as a surrogate. TSS concentrations were determined using turbidity as a surrogate based on an established correlation between turbidity levels and TSS concentrations derived during the 2006 dredging season. The formula for conversion of turbidity to TSS is: TSS (mg/l) = [ * (Turbidity in NTU)] The turbidity-tss correlation equation was based on data, as presented below. 331

4 End of 2006 Turbidity-TSS Correlation y = x R 2 = TSS (mg/l) Turbidity (NTU) Turbidity monitoring was conducted continuously during dredging operations. The monitoring buoys were located at US-1 (upstream location), DS-1 (downstream location), and RM-1 (river mouth location). The US-1 location was located upstream of the site, adjacent to the ARU Campground. The DS-1 location was located approximately 213 meters (700 feet) downstream of the 2007 dredging area and moved accordingly as dredging progressed down the river. The RM-1 location was located between the 5th Street Bridge and the river mouth. At each location, turbidity was recorded typically every 15 minutes by measuring NTUs by way of a turbidity meter at one-half the water column depth at that location. Dredging operations were to be performed in such a manner as to prevent excessive sediment resuspension based on TSS concentration measurements (or NTUs). For the purposes of the Ashtabula River dredging project, excessive resuspension was defined as exceeding a TSS concentration of 50 milligrams per liter (mg/l) above a daily background (upstream) concentration within 213 meters (700 feet) of the dredge head (measured on the downstream side according to the prevailing water flow conditions) at one-half the water column depth. This 50 mg/l TSS criteria was based on a 4-hour rolling average of TSS measurements. Only periodic exceedances of the 25 mg/l TSS warning level and the 50 mg/l TSS action level were observed during dredging at brief intervals at the DS-1 (213 meters downstream) location. Exceedances were immediately relayed to the dredge crew. The reason for the exceedance(s) was investigated and corrective actions, if required, were instigated. The exceedances were summarized in the daily and weekly reports for their respective periods. Water Column Sampling Water column sampling was conducted to provide historical data relative to PCB and radionuclide concentrations in the water column before and during dredging operations. Two locations along the river were sampled on a weekly basis for PCBs, Radium-226 (Ra-226), Radium-228 (Ra-228), total uranium (U), and TSS. The water sampling locations were at (1) a fixed background location upstream of the dredging operations at onehalf the water column depth and (2) a location downstream of the project dredging area near the mouth of the Ashtabula River at one-half the water column depth. The upstream sampling location was the same location as the US-1 turbidity monitoring location. The downstream location was the same location as the RM-1 turbidity monitoring location. Radioisotope concentrations in the water column during dredging were detected at low concentrations or at concentrations similar to those detected in the water column prior to dredging operations commenced in PCBs were consistently not detected in the water column during dredging in both 2006 and

5 Post-dredge Sediment Characterization One of the environmental monitoring components was to monitor of sediment conditions following removal activities to ensure that the horizontal and vertical limits of dredging were achieved and that no high levels of contamination were left exposed. Characterization of post-dredge sediment conditions was accomplished by conducting a post-dredge bathymetric survey as well as by measuring post-dredge sediment thicknesses through probing and by collecting post-dredge surface sediment samples. Post-dredge surface sediment samples were analyzed for PCBs. PCB concentrations ranged from nondetects to 32 ppm, with an average of 2.5 ppm (Figure 2). Using the post-dredge surface sediment data, a post-dredge surfaceweighted average concentration (SWAC) was calculated to determine the average PCB concentration remaining following dredging. The PCB SWAC was calculated to be 2.4 ppm for the entire dredge area prior to sand placement. Following sand placement over designated areas, the PCB SWAC was reduced to 1.1 ppm for the entire dredge area. A cleanup pass was performed at approximately 20% of the post-dredge sediment sampling locations. Segregating the cleanup areas from the non-cleanup areas, a PCB SWAC was also calculated. The PCB SWAC for cleanup areas was calculated to be 0.1 ppm. The PCB SWAC for non-cleanup areas was calculated to be 3.9 ppm. These values are prior to sand cover placement. CONCLUSIONS Dredging of bottom sediments within the Ashtabula River was successfully conducted, reducing contaminant mass within the Ashtabula River system. Environmental monitoring of river conditions before, during, and after removal activities were conducted which ensured that the horizontal and vertical limits of dredging were achieved and no high levels of contamination were left exposed. The environmental monitoring also ensured the protection of human health and the environment during the dredging activities. REFERENCES Ashtabula River Partnership (2001). Final Comprehensive Management Plan, Ashtabula River & Harbor, Ashtabula, Ohio. Disclaimer: The contents of this paper do not constitute official U.S. EPA opinion or policy. Mention of business or products does not constitute endorsement by U.S. EPA or its employees. 333

6 0 600 Feet Legend Surface Sediment Sampling Locations Dredge Area PCB Sample Results (mg/kg) > Figure 2 - Ashtabula River Post-Dredge Sediment Verification PCB Sample Results - Ashtabula River AOC 334

CLEANUP GOAL EVALUATION AND SEDIMENT DISPOSAL FOR THE OTTAWA RIVER SEDIMENT REMEDIATION PROJECT

CLEANUP GOAL EVALUATION AND SEDIMENT DISPOSAL FOR THE OTTAWA RIVER SEDIMENT REMEDIATION PROJECT CLEANUP GOAL EVALUATION AND SEDIMENT DISPOSAL FOR THE OTTAWA RIVER SEDIMENT REMEDIATION PROJECT Jack Brunner 1, Scott Cieniawski 2, and Kristi Root 3 ABSTRACT The Ottawa River Sediment Remediation Project

More information

SECTION 2 WATER 2.1 ROUTINE WATER COLUMN MONITORING Collection Summary

SECTION 2 WATER 2.1 ROUTINE WATER COLUMN MONITORING Collection Summary SECTION 2 WATER 2.1 ROUTINE WATER COLUMN MONITORING 2.1.1 Collection Summary Routine water column sampling was performed biweekly between May and October for a total of 13 sampling rounds. Water column

More information

Conditions of Section 401 Certification for Nationwide Permits and General Conditions. General Condition 12 (Soil Erosion and Sediment Controls)

Conditions of Section 401 Certification for Nationwide Permits and General Conditions. General Condition 12 (Soil Erosion and Sediment Controls) Conditions of Section 401 Certification for Nationwide Permits and General Conditions General Condition 12 (Soil Erosion and Sediment Controls) Erosion control and sediment control BMPs described in Attachment

More information

2014 WEDA ENVIRONMENTAL EXCELLENCE AWARD NOMINATION FOR CONSIDERATION

2014 WEDA ENVIRONMENTAL EXCELLENCE AWARD NOMINATION FOR CONSIDERATION 2014 WEDA ENVIRONMENTAL EXCELLENCE AWARD NOMINATION FOR CONSIDERATION Environmental Dredging of Sheboygan River, Wisconsin A multi-stakeholder collaboration, simultaneous execution of multiple projects

More information

US Steel/Spirit Lake Sediment Cleanup Update for River Corridor Coalition

US Steel/Spirit Lake Sediment Cleanup Update for River Corridor Coalition US Steel/Spirit Lake Sediment Cleanup Update for River Corridor Coalition Erin Endsley, Project Manager Mike Bares, Technical Analyst Minnesota Pollution Control Agency August 26, 2015 Outline Site history

More information

FEASIBILITY ANALYSIS ARSENIC IMPACTED SEDIMENTS BRIGGS POND VILLAGE OF PAW PAW VAN BUREN COUNTY, MICHIGAN. Prepared for:

FEASIBILITY ANALYSIS ARSENIC IMPACTED SEDIMENTS BRIGGS POND VILLAGE OF PAW PAW VAN BUREN COUNTY, MICHIGAN. Prepared for: FEASIBILITY ANALYSIS ARSENIC IMPACTED SEDIMENTS BRIGGS POND VILLAGE OF PAW PAW VAN BUREN COUNTY, MICHIGAN Prepared for: Village of Paw Paw Department of Public Services 110 Harry Bush Blvd. Paw Paw, Michigan

More information

1-6 CORDOVA HARBOR, ALASKA (CWIS NO ) (CWIS NO ) (CWIS NO ) Condition of Improvement 30 September 2011

1-6 CORDOVA HARBOR, ALASKA (CWIS NO ) (CWIS NO ) (CWIS NO ) Condition of Improvement 30 September 2011 CORDOVA 1-6 CORDOVA HARBOR, ALASKA (CWIS NO. 87136) (CWIS NO. 87186) (CWIS NO. 87711) Condition of Improvement 30 September 2011 AUTHORIZATION: Rivers and Harbors Act, 30 August 1935 (R & H Committee

More information

Design of CAD Pits in San José Lagoon, San Juan, Puerto Rico

Design of CAD Pits in San José Lagoon, San Juan, Puerto Rico Second LACCEI International Latin American and Caribbean Conference for Engineering and Technology (LACCEI 2004) Challenges and Opportunities for Engineering Education, Research and Development 2-4 June

More information

Appendix D LPRSA RM 10.9 Removal Action and Pilot Tests - Statement of Work Page 1 of 10 APPENDIX D LOWER PASSAIC RIVER STUDY AREA RM 10.

Appendix D LPRSA RM 10.9 Removal Action and Pilot Tests - Statement of Work Page 1 of 10 APPENDIX D LOWER PASSAIC RIVER STUDY AREA RM 10. Page 1 of 10 APPENDIX D LOWER PASSAIC RIVER STUDY AREA RM 10.9 REMOVAL ACTION I. INTRODUCTION A. Purpose The purpose of this Statement of Work is to provide a framework under which the Settling Parties

More information

CHAPTER 7. San Dieguito River Flooding Adaptation

CHAPTER 7. San Dieguito River Flooding Adaptation CHAPTER 7 San Dieguito River Flooding Adaptation This chapter includes a range of adaptation measures to address vulnerabilities from flooding along the San Dieguito River, including the river valley,

More information

Introduction to Sediment Remediation. Presented to: Lower Passaic River Community Advisory Group July 14, 2011

Introduction to Sediment Remediation. Presented to: Lower Passaic River Community Advisory Group July 14, 2011 Introduction to Sediment Remediation Presented to: Lower Passaic River Community Advisory Group July 14, 2011 Overview Feasibility Considerations Conceptual Site Model Dredging / Capping Dredged Material

More information

Final Total Maximum Daily Load for the Monongahela River, Greene County PCBs and Chlordane

Final Total Maximum Daily Load for the Monongahela River, Greene County PCBs and Chlordane Final Total Maximum Daily Load for the Monongahela River, Greene County PCBs and Chlordane Point Marion Lock and Dam to Grays Landing Lock and Dam March 1, 1999 Table of Contents Introduction Background

More information

TOTAL SUSPENDED SOLIDS REMOVAL TEST OF A HIGH DENSITY POLYETHYLENE WATER QUALITY UNIT. By James T. Mailloux Dean K. White

TOTAL SUSPENDED SOLIDS REMOVAL TEST OF A HIGH DENSITY POLYETHYLENE WATER QUALITY UNIT. By James T. Mailloux Dean K. White TOTAL SUSPENDED SOLIDS REMOVAL TEST OF A HIGH DENSITY POLYETHYLENE WATER QUALITY UNIT By James T. Mailloux Dean K. White Submitted to ADVANCED DRAINAGE SYSTEMS 250-04/H1098F September 2004 TOTAL SUSPENDED

More information

SEDIMENT CHOREOGRAPHY

SEDIMENT CHOREOGRAPHY Global Reach. Local Benefit. SEDIMENT CHOREOGRAPHY 4/15/2016 Maritime and the Regional Economy The Port of Cleveland spurs job creation and helps our region compete globally by connecting local businesses

More information

Hudson River PCBs Superfund Site

Hudson River PCBs Superfund Site PCBs Superfund Site Intermediate Design Report (IDR) Community Advisory Group Meeting August 31, 2005 1 Introduction Prepared by GE pursuant to the Administrative Order on Consent for Design (RD AOC) Design

More information

Using Dredging Lessons Learned in a Large Contaminated Sediment Feasibility Study. Presented by John Laplante, Carl Stivers, and Clay Patmont

Using Dredging Lessons Learned in a Large Contaminated Sediment Feasibility Study. Presented by John Laplante, Carl Stivers, and Clay Patmont Using Dredging Lessons Learned in a Large Contaminated Sediment Feasibility Study Presented by John Laplante, Carl Stivers, and Clay Patmont October 24, 2012 Presentation Outline Engineered Barriers Best

More information

SECTION SRS PROGRAM

SECTION SRS PROGRAM SECTION 4 24 SRS PROGRAM 4.1 ROUTINE WATER COLUMN MONITORING 4.1.1 Collection Summary Routine water column monitoring was performed biweekly between April and October 24 for a total of 15 sampling rounds.

More information

August Prepared by:

August Prepared by: Case Study: Use of a Decision Support Tool: Using FIELDS and SADA to Develop Contour Maps of Contaminant Concentrations and Estimate Removal Volumes for Cleanup of Soil at the Marino Brothers Scrapyard

More information

Problem Formulation and Conceptual Model Development for Aquatic Placement

Problem Formulation and Conceptual Model Development for Aquatic Placement Problem Formulation and Conceptual Model Development for Aquatic Placement Burton Suedel, Ph.D. burton.suedel@usace.army.mil DMAM Seminar Day 1 15 Sept 2009 Objectives Overview of problem formulation Overview

More information

Prepared in Cooperation with: the Houston Galveston Area Council and the Texas Commission on Environmental Quality. By Lee Bodkin and Jeannette Oden

Prepared in Cooperation with: the Houston Galveston Area Council and the Texas Commission on Environmental Quality. By Lee Bodkin and Jeannette Oden Surrogate Relationship Development of Suspended Sediment and Total Suspended Solids Utilizing Turbidity and Streamflow Data in the West Fork San Jacinto River, near Conroe, Texas, July 2008 August 2009

More information

HANFORD SITE MIXED WASTE DISPOSAL

HANFORD SITE MIXED WASTE DISPOSAL HANFORD SITE MIXED WASTE DISPOSAL Kent M. McDonald and Dale E. McKenney Fluor Hanford Waste Management Project Todd A. Shrader, US Department of Energy Richland, Washington ABSTRACT Significant volumes

More information

Beneficial Reuse of Dredged Sediments in the Middle Harbor Slip 1 Fill

Beneficial Reuse of Dredged Sediments in the Middle Harbor Slip 1 Fill Beneficial Reuse of Dredged Sediments in the Middle Harbor Slip 1 Fill Port of Long Beach Category: Environmental Enhancement Heather Tomley Director of Environmental Planning Port of Long Beach 4801 Airport

More information

Detroit River. Area of Concern Canadian Section. Status of Beneficial Use Impairments September 2010

Detroit River. Area of Concern Canadian Section. Status of Beneficial Use Impairments September 2010 The Detroit River is a major navigation corridor of the Great Lakes, extending 51 km from Lake St. Clair to Lake Erie. Its watershed, which covers about 2000 km 2 (200 000 ha) on both sides of the international

More information

A Preliminary Assessment of Potential Impacts of Uranium Mining in Virginia on Drinking Water Sources

A Preliminary Assessment of Potential Impacts of Uranium Mining in Virginia on Drinking Water Sources A Preliminary Assessment of Potential Impacts of Uranium Mining in Virginia on Drinking Water Sources EXECUTIVE SUMMARY January 28, 2011 ES-0 Executive Summary A large uranium reserve, estimated to be

More information

Overview of Pepco Benning Facility RI/FS

Overview of Pepco Benning Facility RI/FS Overview of Pepco Benning Facility RI/FS RI/FS Background Between 1985 and 2003, there have been six documented releases of PCBs into the environment at the facility. In each case, Pepco cleaned up the

More information

ADDITIONAL INDOOR SAMPLE RESULTS LEDERLE GRADUATE RESEARCH COMPLEX UNIVERSITY OF MASSACHUSETTS AMHERST, MASSACHUSETTS

ADDITIONAL INDOOR SAMPLE RESULTS LEDERLE GRADUATE RESEARCH COMPLEX UNIVERSITY OF MASSACHUSETTS AMHERST, MASSACHUSETTS ADDITIONAL INDOOR SAMPLE RESULTS LEDERLE GRADUATE RESEARCH COMPLEX UNIVERSITY OF MASSACHUSETTS AMHERST, MASSACHUSETTS Prepared For: Kimberly Tisa PCB Coordinator, Region One United States Environmental

More information

USE OF POLYMERS IN HIGH SPEED DEWATERING OF FINE GRAINED SEDIMENTS TO REPLACE CONFINED DISPOSAL FACILITIES - A CASE STUDY

USE OF POLYMERS IN HIGH SPEED DEWATERING OF FINE GRAINED SEDIMENTS TO REPLACE CONFINED DISPOSAL FACILITIES - A CASE STUDY USE OF POLYMERS IN HIGH SPEED DEWATERING OF FINE GRAINED SEDIMENTS TO REPLACE CONFINED DISPOSAL FACILITIES - A CASE STUDY Karen C. Kabbes, PE, D.WRE. 1 and Michael Hodges 2 ABSTRACT Hydraulically dredging

More information

Appendix C. Chemical Extraction Bench-Scale Study Evaluation

Appendix C. Chemical Extraction Bench-Scale Study Evaluation Appendix C Chemical Extraction Bench-Scale Appendix C Chemical Extraction Bench-Scale Response to EPA Interim Comments on CMS Report Appendix C Chemical Extraction Bench-Scale Housatonic River Rest of

More information

In Situ Thermal NAPL Remediation at the Northeast Site Pinellas Environmental Restoration Project

In Situ Thermal NAPL Remediation at the Northeast Site Pinellas Environmental Restoration Project ABSTRACT In Situ Thermal NAPL Remediation at the Northeast Site Pinellas Environmental Restoration Project R. Juhlin, M. Butherus S.M. Stoller Corporation 2597 B ¾ Road, Grand Junction, C0 81506 USA The

More information

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY REGION BROADWAY NEW YORK, NEW YORK 10007

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY REGION BROADWAY NEW YORK, NEW YORK 10007 EXHIBIT 13 "E UNITED STATES ENVIRONMENTAL PROTECTION AGENCY REGION 2 290 BROADWAY NEW YORK, NEW YORK 10007 MEMORANDUM DATE: January 18, 2001 SUBJECT: FROM: TO: National Remedy Review Board Recommendations

More information

Section SNOW DISPOSAL SITE DESIGN CRITERIA

Section SNOW DISPOSAL SITE DESIGN CRITERIA Section 2.150 SNOW DISPOSAL SITE DESIGN CRITERIA 2.150 A. Introduction Snow disposal sites provide storage areas for snowfall that exceeds the storage capacity of street rights-of-way and other public

More information

IMMEDIATE RESPONSE ACTION STATUS REPORT LEDERLE GRADUATE RESEARCH CENTER UNIVERSITY OF MASSACHUSETTS AMHERST, MASSACHUSETTS RTN:

IMMEDIATE RESPONSE ACTION STATUS REPORT LEDERLE GRADUATE RESEARCH CENTER UNIVERSITY OF MASSACHUSETTS AMHERST, MASSACHUSETTS RTN: IMMEDIATE RESPONSE ACTION STATUS REPORT LEDERLE GRADUATE RESEARCH CENTER UNIVERSITY OF MASSACHUSETTS AMHERST, MASSACHUSETTS RTN: 1-16269 Prepared For: Brian Fitzpatrick, CHMM Environmental Management Services

More information

AN APPROACH FOR DETERMINATION OF AVERAGE RESIDUAL CONCENTRATION OF PCBs IN SOIL

AN APPROACH FOR DETERMINATION OF AVERAGE RESIDUAL CONCENTRATION OF PCBs IN SOIL AN APPROACH FOR DETERMINATION OF AVERAGE RESIDUAL CONCENTRATION OF PCBs IN SOIL Stacie A. Popp, Senior Project Leader ROY F. WESTON, INC. One Weston Way West Chester, Pennsylvania 19380 ABSTRACT A pertinent

More information

Appendix C Site Specific Soil Management Plan prepared by Millennium Environmental

Appendix C Site Specific Soil Management Plan prepared by Millennium Environmental Appendix C Site Specific Soil Management Plan prepared by Millennium Environmental PLYMOUTH, MA WAKEFIELD, MA WORCESTER, MA RINDGE, NH Site Specific Soil Management Plan Lynn, Massachusetts Submitted By:

More information

Need to Verify Model TSS Reduction Estimates

Need to Verify Model TSS Reduction Estimates Examples of Proprietary BMPs Using Settling for Treatment Modeling Manufactured Stormwater Control Practices Vortechs University of Wisconsin Madison Engineering Professional Development 1 DownStream Defender

More information

Peninsula Harbour. Area of Concern Status of Beneficial Use Impairments September 2010

Peninsula Harbour. Area of Concern Status of Beneficial Use Impairments September 2010 Peninsula Harbour Area of Concern Status of Beneficial Use Impairments September 2010 Peninsula Harbour is located on the northeastern shore of Lake Superior, at the town of Marathon, midway between Sault

More information

Grand Calumet. River Revitalized

Grand Calumet. River Revitalized The Grand Calumet River Revitalized Imagine a Grand Calumet River safe for people, fish, birds and wildlife to utilize and enjoy. With the latest clean up efforts, performed under the Great Lakes Restoration

More information

Great Lakes Perspective Sediment Choreography

Great Lakes Perspective Sediment Choreography Global Reach. Local Benefit. Great Lakes Perspective Sediment Choreography Jim White Director, Sustainable Infrastructure Program AAPA H&N 15 SEPTEMBER 2015 The Port is a partner in community development

More information

Mill Street Corridor Assessment/Cleanup Overview

Mill Street Corridor Assessment/Cleanup Overview Mill Street Corridor Assessment/Cleanup Overview Former S. Bent Mill Site Site History Overview Circa 1867 to 1992 - S. Bent Mill Company (furniture manufacturing) Circa early 1900s - expansion of the

More information

CONFINED DISPOSAL FACILITIES (CDFS): GREAT LAKES EXPERIENCE. J. Miller

CONFINED DISPOSAL FACILITIES (CDFS): GREAT LAKES EXPERIENCE. J. Miller CONFINED DISPOSAL FACILITIES (CDFS): GREAT LAKES EXPERIENCE J. Miller U.S. Army Corps of Engineers, Great Lakes & Ohio River Division, Chicago, Illinois USA Confined disposal facilities, or CDFs have been

More information

A Story of Revitalization Onondaga Lake Dredging, Capping, and Habitat Restoration Project, Syracuse, New York

A Story of Revitalization Onondaga Lake Dredging, Capping, and Habitat Restoration Project, Syracuse, New York A Story of Revitalization Onondaga Lake Dredging, Capping, and Habitat Restoration Project, Syracuse, New York Prepared for: WEDA - 2017 Environmental Dredging Excellence Award Submitted by: William Hague

More information

Closure Plan Ash Disposal Area PGE Boardman Power Plant

Closure Plan Ash Disposal Area PGE Boardman Power Plant FIRST ISSUE REVISION 0 Closure Plan Ash Disposal Area PGE Boardman Power Plant Prepared for Portland General Electric September 2015 2020 SW 4th Avenue, Suite 300 Portland, Oregon 97201 This document was

More information

GOING WITH THE FLOW: DESIGN TECHNIQUES TO IMPROVE RAW WATER QUALITY

GOING WITH THE FLOW: DESIGN TECHNIQUES TO IMPROVE RAW WATER QUALITY GOING WITH THE FLOW: DESIGN TECHNIQUES TO IMPROVE RAW WATER QUALITY ABSTRACT Porter Rivers, III, PE URS Corporation Keith Cannon, PE URS Corporation Geoff Smith, PE URS Corporation Ken Green, Eastern Band

More information

Spoil and Water. Irish Ports Association Conference Ciaran Callan Dublin Port Company. 26 th September 2008

Spoil and Water. Irish Ports Association Conference Ciaran Callan Dublin Port Company. 26 th September 2008 Spoil and Water Ciaran Callan Dublin Port Company Irish Ports Association Conference 2008 26 th September 2008 Disposal of Dredge Material: Regulation and Process of Application Requirement for disposal

More information

Cost Estimate for Removal and Disposal of Contaminated Soil

Cost Estimate for Removal and Disposal of Contaminated Soil 14432 SE Eastgate Way, Suite 100 Bellevue, WA 98007 tel: 425-519-8300 Mr. Mark Menard Sound Transit 401 South Jackson Street Seattle, Washington 98104-2820 Subject: Cost Estimate for Disposal of Contaminant-Impacted

More information

ENVIRONMENTAL SCREENING REPORT

ENVIRONMENTAL SCREENING REPORT ENVIRONMENTAL SCREENING REPORT Pursuant to the Canadian Environmental Assessment Act (CEA Act) SCREENING SUMMARY TransCanada PipeLines Limited (TransCanada) is proposing to conduct a contaminant sampling

More information

Dredging and Dredged Material Disposal Overview

Dredging and Dredged Material Disposal Overview Dredging and Dredged Material Disposal Overview Tim Welp Timothy.L.Welp@usace.army.mil 601.634.2083 The process of dredging consists of the following stages: - Excavation (loosening or dislodging) of the

More information

Module 2, Add on Lesson Turbidity Sensor. Student. 90 minutes

Module 2, Add on Lesson Turbidity Sensor. Student. 90 minutes Module 2, Add on Lesson Turbidity Sensor Student 90 minutes Purpose Construct a sensor to measure the turbidity of water Graph data and reason about curves and linear relationships Calibrate the turbidity

More information

TABLE OF CONTENTS 4. PREPARATION, COMMUNICATIONS, AND CONTROLS

TABLE OF CONTENTS 4. PREPARATION, COMMUNICATIONS, AND CONTROLS TABLE OF CONTENTS SECTION PAGE NO. 1. INTRODUCTION... 1-1 1.1 Background... 1-1 1.2 Conceptual Site Model... 1-1 1.3 Plan Organization... 1-2 1.4 Certification... 1-3 2. SAMPLE COLLECTION, ANALYSIS, AND

More information

Linde FUSRAP Site Tonawanda, New York

Linde FUSRAP Site Tonawanda, New York Linde FUSRAP Site Tonawanda, New York U.S. Army Corps of Engineers Building Strong Buffalo District February 2016 FORMERLY UTILIZED SITES REMEDIAL ACTION PROGRAM The Formerly Utilized Sites Remedial Action

More information

5.14 CONTAMINATED MATERIALS

5.14 CONTAMINATED MATERIALS 5.14 CONTAMINATED MATERIALS 5.14.1 Introduction Contaminated materials are toxic or potentially harmful substances that may be present in soil, groundwater, and building materials. Contaminated materials

More information

The following answers are provided in response to questions received.

The following answers are provided in response to questions received. CARLOS PABELLON Director of Administration COUNTY OF DANE DEPARTMENT OF ADMINISTRATION PURCHASING DIVISION Room 425 City-County Building 210 Martin Luther King Jr. Blvd. Madison, WI 53703-3345 608-266-4131

More information

Cat Island Chain Restoration, Green Bay

Cat Island Chain Restoration, Green Bay Cat Island Chain Restoration, Green Bay Victoria Harris, UW Sea Grant January 27, 2005 Southern Green Bay historically provided diverse coastal wetland habitats for fish and wildlife Expansive emergent

More information

STATE OF DELAWARE DEPARTMENT OF NATURAL RESOURCES AND ENVIRONMENTAL CONTROL- SITE INVESTIGATION AND RESTORATION BRANCH

STATE OF DELAWARE DEPARTMENT OF NATURAL RESOURCES AND ENVIRONMENTAL CONTROL- SITE INVESTIGATION AND RESTORATION BRANCH STATE OF DELAWARE DEPARTMENT OF NATURAL RESOURCES AND ENVIRONMENTAL CONTROL- SITE INVESTIGATION AND RESTORATION BRANCH PROPOSED PLAN OF REMEDIAL ACTION May 2006 Ion Power Formally South Parcel of Metachem

More information

F. Impact on the Receiving Environment

F. Impact on the Receiving Environment F. Impact on the Receiving Environment Dredging is a necessity for the port to remain commercially active. However, over the past two decades the Port of Waterford has acquired numerous reports and investigations

More information

CONTINUOUS TURBIDITY MONITORING AND REGRESSION ANALYSIS TO ESTIMATE TOTAL SUSPENDED SOLIDS AND FECAL COLIFORM BACTERIA LOADS IN REAL TIME

CONTINUOUS TURBIDITY MONITORING AND REGRESSION ANALYSIS TO ESTIMATE TOTAL SUSPENDED SOLIDS AND FECAL COLIFORM BACTERIA LOADS IN REAL TIME CONTINUOUS TURBIDITY MONITORING AND REGRESSION ANALYSIS TO ESTIMATE TOTAL SUSPENDED SOLIDS AND FECAL COLIFORM BACTERIA LOADS IN REAL TIME By Victoria G. Christensen, Andrew C. Ziegler, and Xiaodong Jian

More information

2016 Water Quality Report to Consumers

2016 Water Quality Report to Consumers 2016 Water Quality Report to Consumers Is Our Water Safe To Drink? Absolutely! Ascension Consolidated Utilities District #2 is proud of the fine drinking water it provides. This 19th annual water quality

More information

ENVIRONMENTAL MEASUREMENT. Engr. Yvonne Ligaya F. Musico

ENVIRONMENTAL MEASUREMENT. Engr. Yvonne Ligaya F. Musico ENVIRONMENTAL MEASUREMENT 1 Concentration in Environment Chemical concentration is one of the most important determinants in almost all aspects of chemical fate, transport, and treatment in both natural

More information

Cleanup of the Lower Fox River, Wisconsin Operable Units 2 5

Cleanup of the Lower Fox River, Wisconsin Operable Units 2 5 Cleanup of the Lower Fox River, Wisconsin Operable Units 2 5 3 RICHARD FEENEY, BASTIAAN LAMMERS AND GREG SMITH Cleanup of the Lower Fox River, Wisconsin Operable Units 2 5 ABSTRACT The Fox River Cleanup

More information

2016 Report on Water Quality Relative to Public Health Goals

2016 Report on Water Quality Relative to Public Health Goals 2016 Report on Water Quality Relative to Public Health Goals Prepared for: ELK GROVE WATER DISTRICT 9257 Elk Grove Blvd. Elk Grove, CA 95624 (916) 685 3556 http://www.egwd.org/ Prepared by: 9888 Kent Street

More information

Stormwater Runoff Water Quality Characteristics From Highways in Lake Tahoe, California

Stormwater Runoff Water Quality Characteristics From Highways in Lake Tahoe, California California State University, Sacramento (CSUS) University of California, Davis (UCD) California Department of Transportation (Caltrans) Stormwater Runoff Water Quality Characteristics From Highways in

More information

APPENDIX B Construction Surface Water Management Plan PLANT CITY, FLORIDA SYDNEY ROAD RECLAIMED WATER PROJECT INVITATION TO BID ITB NO.

APPENDIX B Construction Surface Water Management Plan PLANT CITY, FLORIDA SYDNEY ROAD RECLAIMED WATER PROJECT INVITATION TO BID ITB NO. APPENDIX B Construction Surface Water Management Plan PLANT CITY, FLORIDA SYDNEY ROAD RECLAIMED WATER PROJECT INVITATION TO BID ITB NO. 11-91360-001 ADVERTISED: November 5, 2010 MANDATORY PRE-BID MEETING:

More information

TECHNICAL MEMORANDUM

TECHNICAL MEMORANDUM Hope Taylor, Ph.D. Larry Walker Associates 707 4th Street, Suite 200 Davis, CA 95616 530.753.6400 hopet@lwa.com Andrew Kong Laboratory Data Consultants, Inc. (LDC) 7750 El Camino Real, Suite 2L Carlsbad,

More information

Water Chemistry. Water 101

Water Chemistry. Water 101 Water Chemistry Water 101 I. Introduction A. Water is not pure Many different kinds of chemicals dissolved in it Ions, organic chemicals, organic matter, particulate matter, and gases can all be in water

More information

Greenfield Pond B Rehabilitation

Greenfield Pond B Rehabilitation Preliminary Investigation Report Centennial, Colorado November 15, 2011 Prepared for: Liverpool Metropolitan District Prepared by: Stantec Consulting Services, Inc. Table of Contents Executive Summary...

More information

C. Foundation stabilization for pipe and utility structures.

C. Foundation stabilization for pipe and utility structures. PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization

More information

Open Trench Construction Plan Review The open trench construction plan review involves the following general investigative elements:

Open Trench Construction Plan Review The open trench construction plan review involves the following general investigative elements: TNC Fisher Slough Final Design and Permitting Subject: Inverted Siphon Construction Feasibility To: From: Jenny Baker (TNC) Dave Olson (DD3) Brian Olson (DD17) Bob Boudinot Skagit County David Cline (Tetra

More information

DEPARTMENT OF ENVIRONMENTAL PROTECTION Bureau of Water Quality Protection. Design Criteria - Wetlands Replacement/Monitoring

DEPARTMENT OF ENVIRONMENTAL PROTECTION Bureau of Water Quality Protection. Design Criteria - Wetlands Replacement/Monitoring DEPARTMENT OF ENVIRONMENTAL PROTECTION Bureau of Water Quality Protection DOCUMENT NUMBER: 363-0300-001 TITLE: Design Criteria - Wetlands Replacement/Monitoring EFFECTIVE DATE: February 11, 1997 AUTHORITY:

More information

MINNESOTA SLIP FOCUSED FEASIBILITY STUDY

MINNESOTA SLIP FOCUSED FEASIBILITY STUDY MINNESOTA SLIP FOCUSED FEASIBILITY STUDY Duluth, Minnesota MPCA Work Order # SFBW-0605 MPCA Technical Document: tdr-fg05-05 Prepared for: Minnesota Pollution Control Agency 525 South Lake Avenue Suite

More information

Less than 8 feet finished water depth. 4-Foot Cap 3-Foot Cap Foot Cap. 4 Ft

Less than 8 feet finished water depth. 4-Foot Cap 3-Foot Cap Foot Cap. 4 Ft Herbivorous Animals Consuming Plants & Sediment Piscivorous Wildlife Consuming Fish Insectivorous Wildlife Consuming Emerging Aquatic Invertebrates Burrowing Organisms Contacting Contaminated Sediment

More information

Lansing Generating Station Project No Closure Plan for Existing CCR Revision: 1 TABLE OF CONTENTS

Lansing Generating Station Project No Closure Plan for Existing CCR Revision: 1 TABLE OF CONTENTS Surface Impoundment Page No. i TABLE OF CONTENTS 1. INTRODUCTION... 1 2. PROPOSED CCR IMPOUNDMENT CLOSURE PROCEDURE... 2 3. PROPOSED COVER SYSTEM... 2 4. ESTIMATED MAXIMUM INVENTORY OF CCR... 3 5. ESTIMATED

More information

Georgia-Pacific Mill Site DTSC Cleanup Update. Special City Council Meeting February 2, 2017 Town Hall, Fort Bragg, CA

Georgia-Pacific Mill Site DTSC Cleanup Update. Special City Council Meeting February 2, 2017 Town Hall, Fort Bragg, CA 1 Georgia-Pacific Mill Site DTSC Cleanup Update Special City Council Meeting February 2, 2017 Town Hall, Fort Bragg, CA 2 Tonight s Agenda Presentation to the City Council - DTSC Background - who we are,

More information

Mass Stabilization Virgin & Contaminated Soil / Sediment

Mass Stabilization Virgin & Contaminated Soil / Sediment Mass Stabilization Virgin & Contaminated Soil / Sediment Presented at: Remediation Technologies Symposium 2013 Charles Wilk, Manager Stabilization and Remediation Applications ALLU Group Inc. What is Mass

More information

Ottumwa Generating Station Project No Closure Plan for Existing CCR Revision: 0 Surface Impoundments TABLE OF CONTENTS

Ottumwa Generating Station Project No Closure Plan for Existing CCR Revision: 0 Surface Impoundments TABLE OF CONTENTS Surface Impoundments Page No. i TABLE OF CONTENTS 1. INTRODUCTION... 1 2. PROPOSED CCR IMPOUNDMENTS CLOSURE PROCEDURE... 3 3. PROPOSED COVER SYSTEM... 4 4. ESTIMATED MAXIMUM INVENTORY OF CCR... 4 5. ESTIMATED

More information

105 CMR: DEPARTMENT OF PUBLIC HEALTH

105 CMR: DEPARTMENT OF PUBLIC HEALTH 120.882: continued 120.885: Waivers (B) The Operator shall allow the duly authorized representatives of the Department, at all reasonable times, without advance notice to enter and examine any property,

More information

Environmental Protection (NJDEP) The Louis Berger Group, Inc.

Environmental Protection (NJDEP) The Louis Berger Group, Inc. Hydraulic Modeling for Preliminary Evaluation of Potential Flooding Impacts for Various Dredging, Capping and Armoring Scenarios of The Lower Passaic River Restoration Abdulai Fofanah, PE, D.WRE, CFM Murat

More information

Transparency A Water Clarity Measure

Transparency A Water Clarity Measure Volunteer Monitoring Factsheet Series 2010 Transparency A Water Clarity Measure Why are we concerned? Water clarity is one of the most obvious measures of water quality. Water clarity can be a useful indicator

More information

REUSE OF DREDGED SEDIMENTS

REUSE OF DREDGED SEDIMENTS REUSE OF DREDGED SEDIMENTS Lake Erie Waterkeeper Conference W.W. Knight Nature Preserve, Perrysburg, Ohio Friday, March 18, 2016 John H. Hull, P.E., BCEE Hull & Associates, Inc. SEDIMENT ENTERING LAKE

More information

Water Quality Design Storms for Stormwater Hydrodynamic Separators

Water Quality Design Storms for Stormwater Hydrodynamic Separators 1651 Water Quality Design Storms for Stormwater Hydrodynamic Separators Victoria J. Fernandez-Martinez 1 and Qizhong Guo 2 1 Rutgers University, Department of Civil and Environmental Engineering, 623 Bowser

More information

ANALYSIS OF BROWNFIELD CLEANUP ALTERNATIVES (ABCA) US EPA BROWNFIELD CLEANUP GRANT PROGRAM Sibley Mill 1717 Goodrich Street Augusta, GA

ANALYSIS OF BROWNFIELD CLEANUP ALTERNATIVES (ABCA) US EPA BROWNFIELD CLEANUP GRANT PROGRAM Sibley Mill 1717 Goodrich Street Augusta, GA ANALYSIS OF BROWNFIELD CLEANUP ALTERNATIVES (ABCA) US EPA BROWNFIELD CLEANUP GRANT PROGRAM Sibley Mill 1717 Goodrich Street Augusta, GA Introduction and Background The subject site is located at 1717 Goodrich

More information

Groundwater Monitoring Requirements of the CCR Rule What s Next?

Groundwater Monitoring Requirements of the CCR Rule What s Next? 2017 World of Coal Ash (WOCA) Conference in Lexington, KY - May 9-11, 2017 http://www.flyash.info/ Groundwater Monitoring Requirements of the CCR Rule What s Next? Thomas A. Mann, PE SynTerra Corporation,

More information

Avon Lake Municipal Landfill, Lorain County Ohio Administrative Code (OAC) Rule Authorization

Avon Lake Municipal Landfill, Lorain County Ohio Administrative Code (OAC) Rule Authorization State of Ohio Environmental Protection Agency STREET ADDRESS: MAILING ADDRESS: Lazarus Government Center TELE: (614) 644-3020 FAX: (614) 644-3184 P.O. Box 1049 122 S. Front Street www.epa.state.oh.us Columbus,

More information

TARGETED DREDGING OF NEAR-SHORE DEBRIS AND SEDIMENT, UPPER TRENTON CHANNEL, DETROIT RIVER: A CASE STUDY

TARGETED DREDGING OF NEAR-SHORE DEBRIS AND SEDIMENT, UPPER TRENTON CHANNEL, DETROIT RIVER: A CASE STUDY TARGETED DREDGING OF NEAR-SHORE DEBRIS AND SEDIMENT, UPPER TRENTON CHANNEL, DETROIT RIVER: A CASE STUDY M.J. Erickson, P.E. 1, R.K. Mohan, P.E. 2, W.J. Dinicola 3, and M.R. Henderson 4 ABSTRACT Under regulatory

More information

Appendix H: Construction Impacts H-5 Dredged Materials Management Alternatives Analysis

Appendix H: Construction Impacts H-5 Dredged Materials Management Alternatives Analysis Appendix H: Construction Impacts H-5 Dredged Materials Management Alternatives Analysis Dredged Material Management Alternatives Analysis A. INTRODUCTION The Tappan Zee Hudson River Crossing Project proposes

More information

Rawal Lake Water Treatment Plant Rawalpindi, Pakistan

Rawal Lake Water Treatment Plant Rawalpindi, Pakistan Rawal Lake Water Treatment Plant Rawalpindi, Pakistan 1. Background Information Rawal Lake Water Treatment Plant is managed by the Water & Sanitation Agency (WASA) under the Rawalpindi Development Authority

More information

Management of PCBs Under the MCP

Management of PCBs Under the MCP LSPA PCB Course March 28, 2013 Management of PCBs Under the MCP Eva V. Tor, P.E. Deputy Regional Director Massachusetts Department of Environmental Protection Springfield, MA Presentation Outline 1. Laws

More information

STANDARD OPERATING PROCEDURES

STANDARD OPERATING PROCEDURES PAGE: 1 of 7 CONTENTS 1.0 SCOPE AND APPLICATION* 2.0 METHOD SUMMARY* 3.0 SAMPLE PRESERVATION, CONTAINERS, HANDLING, AND STORAGE 4.0 INTERFERENCES AND POTENTIAL PROBLEMS* 5.0 EQUIPMENT/APPARATUS* 6.0 REAGENTS

More information

Polychlorinated Biphenyl (PCB) Program

Polychlorinated Biphenyl (PCB) Program Tammie J. Hynum Chief Hazardous Waste Division of Arkansas DEQ Currently serves as the ASTSWMO HW Subcommittee Chair Polychlorinated Biphenyl (PCB) Program What is the best program to guide effective investigation

More information

A. Manufactured Treatment Device Characteristics

A. Manufactured Treatment Device Characteristics Requirements for Interim Certification of Hydrodynamic Sedimentation Devices for Total Suspended Solids Based on Laboratory Testing DRAFT April 28, 2009 The New Jersey Stormwater Management Rules at N.J.A.C.

More information

4.8. Subsurface Infiltration

4.8. Subsurface Infiltration 4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of stormwater as it infiltrates into the ground. Dry wells, infiltration

More information

Initial Closure Plan Slag Pond. Nelson Dewey Generating Station. Wisconsin Power and Light Company. Prepared for:

Initial Closure Plan Slag Pond. Nelson Dewey Generating Station. Wisconsin Power and Light Company. Prepared for: Initial Closure Plan Slag Pond Prepared for: Wisconsin Power and Light Company 11999 County Highway VV Cassville, Wisconsin 53806 Prepared by: SCS ENGINEERS 2830 Dairy Drive Madison, Wisconsin 53718-6751

More information

APPENDIX D MECHANICAL DEWATERING EVALUATION (ADDENDUM 4)

APPENDIX D MECHANICAL DEWATERING EVALUATION (ADDENDUM 4) ONONDAGA LAKE PDI: PHASE IV DATA SUMMARY REPORT APPENDIX D MECHANICAL DEWATERING EVALUATION (ADDENDUM 4) PARSONS P:\Honeywell -SYR\444540-Phase IV PDI\09 Reports\Phase IV DSR\1-11 Final\PDI IV Summary

More information

Tackling Polychlorinated Biphenyls (PCBs) & Toxins Through TMDLs

Tackling Polychlorinated Biphenyls (PCBs) & Toxins Through TMDLs Tackling Polychlorinated Biphenyls (PCBs) & Toxins Through TMDLs 2015 Virginia Water Monitoring Council Conf. Exploring Emerging Water Issues November 19, 2015 Mark Richards Virginia Department of Environmental

More information

Lake County WTP Improvements and Capacity Increase. OTCO 9 th Annual Water and Wastewater Workshop. Nick Pizzi Aqua Serv

Lake County WTP Improvements and Capacity Increase. OTCO 9 th Annual Water and Wastewater Workshop. Nick Pizzi Aqua Serv 1 Lake County WTP Improvements and Capacity Increase OTCO 9 th Annual Water and Wastewater Workshop 7.31.2013 Nick Pizzi Aqua Serv Rick Douglas Lake County Presentation Agenda Some topics we will cover:

More information

ASH MANAGEMENT PLAN. U.S. Environmental Protection Agency Region 4, Atlanta, GA. Mr. Joe Alfano, Remedial Project Manager

ASH MANAGEMENT PLAN. U.S. Environmental Protection Agency Region 4, Atlanta, GA. Mr. Joe Alfano, Remedial Project Manager ASH MANAGEMENT PLAN U.S. Environmental Protection Agency Region 4, Atlanta, GA Mr. Joe Alfano, Remedial Project Manager 404-562-8933 City of Jacksonville Environmental and Compliance Department Site Investigation

More information

Renovation of the Filters at the Soldier Canyon Filter Plant in Fort Collins, Colorado

Renovation of the Filters at the Soldier Canyon Filter Plant in Fort Collins, Colorado JUST ADD WATER Renovation of the Filters at the Soldier Canyon Filter Plant in Fort Collins, Colorado Thomas M. Getting, P.E., DEE, Filtration Product Manager John Geibel, P.E., Chief Engineer Michael

More information

This document also includes proposed permit requirements, including response actions, when excursions occur.

This document also includes proposed permit requirements, including response actions, when excursions occur. Discussion of Zone of Influence, Area of Review, and the Aquifer Exemption Boundary for Class III Injection Wells used for the In-Situ Leaching (ISL) of Uranium Introduction: The purpose of this discussion

More information

ENVIRONMENTAL DREDGING. Lower Duwamish Waterway. Enhanced Natural Recovery/Activated Carbon Pilot Study

ENVIRONMENTAL DREDGING. Lower Duwamish Waterway. Enhanced Natural Recovery/Activated Carbon Pilot Study ENVIRONMENTAL DREDGING Lower Duwamish Waterway Enhanced Natural Recovery/ March 17, 2017 Mr. Craig Vogt c/o Western Dredging Association WEDA Environmental Commission via: craig@craigvogt.com Mr. Vogt:

More information

FACT PATTERN THE RESERVATION

FACT PATTERN THE RESERVATION FACT PATTERN THE RESERVATION Great Lakes Tribal Reservation Surrounded by Big River National Forest Big River flows through Reservation and into Big Lake General Environmental Concerns Wild rice areas

More information

PCBs in Building Materials. John Gorman Jim Haklar USEPA

PCBs in Building Materials. John Gorman Jim Haklar USEPA PCBs in Building Materials John Gorman Jim Haklar USEPA PCBs in Building Materials What are PCBs Sources of PCBs in Building Materials Regulatory Requirements Levels of PCBs Found Removal & Clean-up Standards

More information