Revision and Updates to the Environmental Dredging Pilot Study Lower Passaic River Restoration Project

Size: px
Start display at page:

Download "Revision and Updates to the Environmental Dredging Pilot Study Lower Passaic River Restoration Project"

Transcription

1 Revision and Updates to the Environmental Dredging Pilot Study Lower Passaic River Restoration Project Project Delivery Team Meeting Project Delivery Team Meeting March 4, 2009

2

3

4 Outline Design and Objectives of Pilot Study Revisions and Updates Volume of Sediments Dredged Productivity Analysis Resuspension Conclusion and Next Steps

5 Design & Objectives Pilot Study designed to examine production environmental dredging One mechanical dredging system equipped with an 8-CY clamshell bucket Evaluate productivity, vertical accuracy, and Best Management Practices ces Evaluate dredge-related resuspension through a monitoring program Three target depths over Evaluate approximately 1 acre of decontamination area in 5 work days technologies og es

6 Design & Objective Date December 5 December 6 December 7 December 8 December 9 December 10 Dredging gactivity 13-foot MLW cut 11-foot MLW cut 15-foot MLW cut 15-foot MLW cut No dredging due to storm 15-foot MLW cut

7 Pilot Study was NOT intended to report on. Other dredging performance features and technologies Other remedial alternatives such as capping Clean-up passes or residuals Material handling and decontamination technology (separate reports) Cost implications for a full-scale dredging operation Quality of life issues Feasibility study will extrapolate Pilot Study data to estimate a full scale operation

8 Revision on Volume of Sediments Dredged

9 Revision on Volume of Sediments Dredged Method 1 Method 2 Sum the daily dredge volumes by evaluating daily bathymetric surveys to the pre- dredge survey Compare the river bottom elevations before and after the dredging operation by using the predredge and post- dredge surveys

10

11 Method 1 Pre-dredge Versus Post-dredge Survey 3,800 ±100 Cubic Yards

12 Method 2 Daily Survey Comparison 4,000 ±210 Cubic Yards

13 Revision on Volume of Sediments Dredged Date Malcolm Pirnie (Cubic Yards) Jay Cashman (Cubic Yards) December ± December 6 1,200 ±30 1,400 December ± December ± December ± Total Volume 4,000 ±210 4,200 * Values rounded to two significant figures

14 Revision of Productivity Analysis

15 Revision of Productivity Analysis Daily surveys were used to estimate productivity Revised work time breakdown based on ClamVision data for actual dredge time Linked cycle time (ClamVision data) to the work time analysis to separate equipment movement from dredge time

16 Revision of Productivity Analysis Evaluation decreased dredge time and increased equipment movement, which h will cause an increase in productivity. Parameter Draft Dredge Pilot Value Revised Value Average Dredging Time 6.2 hours 5.0 hours Average Working Day 11 hours 10.5 hours Work Day minus Client Standby 9.6 hours 9.2 hours

17 Revision on Productivity Analysis EQUIPMENT MOVEMENT 1.7 HOURS LOST TIME 0.9 HOURS DOWNTIME 0.1 HOURS OPERATING TIME 5 HOURS CLIENT- DIRECTED STANDBY 1.3 HOURS AVERAGE PROJECT DAY 10.5 hours SETUP 1.5 HOURS

18 Revision of Productivity Analysis Date Draft Dredge Pilot Value Revised Value December 5, CY/hr 73 CY/hr December 6, CY/hr 110 CY/hr December 7, CY/hr 100 CY/hr December 8, CY/hr 99 CY/hr December 10, CY/hr 110 CY/hr * Revised values based on USACE ERDC/EL TR Technical Guidelines for Environmental Dredging of Contaminated Sediments

19 Revision of Productivity Analysis Date Average Operating Production Rate Uptime Mathematical 24-hour December CY/hr 45 percent 2,200 CY December 7-8 and CY/hr 79 percent 2,500 CY

20 Revision of Resuspension Analysis

21 Revision of Resuspension M1 M2 100 meters 300 meters M6 M5 Solids and chemical monitoring i conducted at transects between Moorings 1-2 and Moorings 5-6. Boat-Based ased ADCP Monitoring Throughout Pilot Study Area

22 Dredging Resuspension Assessment is difficult due to Resuspension from Tidal Currents Upriver Tracks on December 5, 2005 during Ebb Tide

23 ADCP Profiles on December 7, 2005 during Ebb Tide Very Near-Field (<50 meters) Boat-Based Based Monitoring Can Detect Resuspension Depth (m m) TS S (mg/l)

24 ADCP Profiles on December 10, 2005 during Flood Tide Boat-Based Monitoring Demonstrates the Rapid Dispersion of Resuspension Plume Depth (m m) TSS S (mg/l)

25 Revision of Resuspension Analysis Date Production Average Very Near-Field Rate Release Rate Percent (kg/s) (kg/s) Resuspension December 5, % 5% December 6, % December 7, % December 8, % December 10, %

26 Revision of Resuspension Analysis Best Management Practices were evaluated to optimize dredging d operations while minimizing i i i resuspension. Optimize the cycle time between ee grabs by adjusting the depth of cut, the lift speed, and hang time Optimize the use of winching and cabling in place of tugboats for repositioning the rinse tank

27 Revision on Productivity Analysis Date December 5-6 Shakedown December 7-8 BMP Optimized Mathematical Uptime Resuspension 24-hour 45 percent 2,200 CY 5-6% 79 percent 2,500 CY 1-2%

28 Revision of Resuspension Release during dredging generally masked by background TSS due to movement of salt wedge and tidal resuspension. Dredge signal was detectable ONLY in very near-field (< 50 m) of dredging operation, despite wide variation in the background sediment load. Dredge signal not readily discernable at far-field of Pilot Study Area (300 meters away). No chemical signal due to dredging. Very near-field dredging release is less than 2% of solids removal under environmental dredging conditions with Best Management Practices.

29 Conclusions and Next Steps Pilot Study Report will be revised: 4,000 CY of sediment removed 9.2 hours for the work day (minus client standby time) 79% Uptime with Best Management Practice 1-2% Resuspension using Best Management Practice Additional supporting data will be added d into the report and provided as appendices Final Report anticipated June 2009

Introduction to Sediment Remediation. Presented to: Lower Passaic River Community Advisory Group July 14, 2011

Introduction to Sediment Remediation. Presented to: Lower Passaic River Community Advisory Group July 14, 2011 Introduction to Sediment Remediation Presented to: Lower Passaic River Community Advisory Group July 14, 2011 Overview Feasibility Considerations Conceptual Site Model Dredging / Capping Dredged Material

More information

Using Dredging Lessons Learned in a Large Contaminated Sediment Feasibility Study. Presented by John Laplante, Carl Stivers, and Clay Patmont

Using Dredging Lessons Learned in a Large Contaminated Sediment Feasibility Study. Presented by John Laplante, Carl Stivers, and Clay Patmont Using Dredging Lessons Learned in a Large Contaminated Sediment Feasibility Study Presented by John Laplante, Carl Stivers, and Clay Patmont October 24, 2012 Presentation Outline Engineered Barriers Best

More information

Appendix H: Construction Impacts H-5 Dredged Materials Management Alternatives Analysis

Appendix H: Construction Impacts H-5 Dredged Materials Management Alternatives Analysis Appendix H: Construction Impacts H-5 Dredged Materials Management Alternatives Analysis Dredged Material Management Alternatives Analysis A. INTRODUCTION The Tappan Zee Hudson River Crossing Project proposes

More information

Environmental Protection (NJDEP) The Louis Berger Group, Inc.

Environmental Protection (NJDEP) The Louis Berger Group, Inc. Hydraulic Modeling for Preliminary Evaluation of Potential Flooding Impacts for Various Dredging, Capping and Armoring Scenarios of The Lower Passaic River Restoration Abdulai Fofanah, PE, D.WRE, CFM Murat

More information

EVALUATION OF ENVIRONMENTAL MONITORING DATA GATHERED DURING ASHTABULA RIVER DREDGING, ASHTABULA RIVER, OHIO

EVALUATION OF ENVIRONMENTAL MONITORING DATA GATHERED DURING ASHTABULA RIVER DREDGING, ASHTABULA RIVER, OHIO EVALUATION OF ENVIRONMENTAL MONITORING DATA GATHERED DURING ASHTABULA RIVER DREDGING, ASHTABULA RIVER, OHIO D. Plomb 1, S. Cieniawski 2, and D. Pham 3 ABSTRACT The Ashtabula River Area of Concern (AOC)

More information

1-6 CORDOVA HARBOR, ALASKA (CWIS NO ) (CWIS NO ) (CWIS NO ) Condition of Improvement 30 September 2011

1-6 CORDOVA HARBOR, ALASKA (CWIS NO ) (CWIS NO ) (CWIS NO ) Condition of Improvement 30 September 2011 CORDOVA 1-6 CORDOVA HARBOR, ALASKA (CWIS NO. 87136) (CWIS NO. 87186) (CWIS NO. 87711) Condition of Improvement 30 September 2011 AUTHORIZATION: Rivers and Harbors Act, 30 August 1935 (R & H Committee

More information

Appendix 6: Physical Oceanography. (Envirosphere 2009b)

Appendix 6: Physical Oceanography. (Envirosphere 2009b) Appendix 6: Physical Oceanography (Envirosphere 2009b) Oceanographic Survey, Oceanographic Measurements Salinity, Temperature & Turbidity, Minas Passage Study Site August 2008 March 2009 Submitted to:

More information

Lower Eight Miles of the Lower Passaic River Remedial Investigation and Focused Feasibility Study Summary for Community Advisory Group

Lower Eight Miles of the Lower Passaic River Remedial Investigation and Focused Feasibility Study Summary for Community Advisory Group Lower Eight Miles of the Lower Passaic River Remedial Investigation and Focused Feasibility Study Summary for Community Advisory Group The following summary of the Remedial Investigation and Focused Feasibility

More information

SIDA/Hilton Head Dredging And Open Water Placement Monitoring Plan

SIDA/Hilton Head Dredging And Open Water Placement Monitoring Plan Prepared for: GEL Engineering, LLC Charleston, SC Prepared by: Moffatt & Nichol September 4, 2012 TABLE OF CONTENTS 1. PROJECT DESCRIPTION AND LOCATION... 1 2. PURPOSE... 9 3. DREDGE MATERIAL AND WATER

More information

Appendix D LPRSA RM 10.9 Removal Action and Pilot Tests - Statement of Work Page 1 of 10 APPENDIX D LOWER PASSAIC RIVER STUDY AREA RM 10.

Appendix D LPRSA RM 10.9 Removal Action and Pilot Tests - Statement of Work Page 1 of 10 APPENDIX D LOWER PASSAIC RIVER STUDY AREA RM 10. Page 1 of 10 APPENDIX D LOWER PASSAIC RIVER STUDY AREA RM 10.9 REMOVAL ACTION I. INTRODUCTION A. Purpose The purpose of this Statement of Work is to provide a framework under which the Settling Parties

More information

Proposed Clarification:

Proposed Clarification: Proposed Clarification: Updated Dioxin Testing Requirements for Dispersive Disposal Sites in Puget Sound Kelsey van der Elst, USACE Dave Fox, USACE Scope Included Not Included Need for dioxin testing for

More information

Conditions of Section 401 Certification for Nationwide Permits and General Conditions. General Condition 12 (Soil Erosion and Sediment Controls)

Conditions of Section 401 Certification for Nationwide Permits and General Conditions. General Condition 12 (Soil Erosion and Sediment Controls) Conditions of Section 401 Certification for Nationwide Permits and General Conditions General Condition 12 (Soil Erosion and Sediment Controls) Erosion control and sediment control BMPs described in Attachment

More information

PUBLIC NOTICE. Dredging with ten-years maintenance, return flow to the waterway and upland placement. Georgica Cove, tributary of Georgica Pond

PUBLIC NOTICE. Dredging with ten-years maintenance, return flow to the waterway and upland placement. Georgica Cove, tributary of Georgica Pond PUBLIC NOTICE US Army Corps of Engineers New York District Jacob K. Javits Federal Building New York, N.Y. 10278-0090 ATIN: Regulatory Branch In replying refer to: Public Notice Number: NAN-2016-01054-EHA

More information

A Case Study of Brownfields Redevelopment Recycling Old Contaminated Sites

A Case Study of Brownfields Redevelopment Recycling Old Contaminated Sites A Case Study of Brownfields Redevelopment Recycling Old Contaminated Sites Presented to Conference on Revitalizing Land and Restoring Communities University of Virginia Charlottesville, VA by Marwan M.

More information

Cable Mounted Dredge Pumps Cable Hanging Dredge Pumps can be deployed with a Barge or Excavator.

Cable Mounted Dredge Pumps Cable Hanging Dredge Pumps can be deployed with a Barge or Excavator. Cable Mounted Dredge Pumps Cable Hanging Dredge Pumps can be deployed with a Barge or Excavator. Cable or Boom Deployed Dredge The picture shows an EDDY Pump unloading a barge with a boom deployment (video

More information

ALTERNATIVES ANALYSIS LBC SHIP DOCK 5 PROJECT SWG HARRIS COUNTIES, TEXAS

ALTERNATIVES ANALYSIS LBC SHIP DOCK 5 PROJECT SWG HARRIS COUNTIES, TEXAS ALTERNATIVES ANALYSIS LBC SHIP DOCK 5 PROJECT SWG-2016-00832 HARRIS COUNTIES, TEXAS Prepared for: LBC Houston, LP 11666 Port Road Seabrook, Texas 77589 Prepared by: Lloyd Engineering, Inc. 6565 West Loop

More information

Hudson River Cleanup and PCBs Community Advisory Group March 22, 2012

Hudson River Cleanup and PCBs Community Advisory Group March 22, 2012 Hudson River Cleanup and PCBs Community Advisory Group March 22, 2012 Introduction The National Resource Damages Trustees (National Oceanic and Atmospheric Administration, the U.S. Department of the Interior,

More information

Definitions. Currently serviceable: Useable as is or with some maintenance, but not so Degraded as to essentially require reconstruction.

Definitions. Currently serviceable: Useable as is or with some maintenance, but not so Degraded as to essentially require reconstruction. Definitions Best management practices (BMPs): Policies, practices, procedures, or structures implemented to mitigate the adverse environmental effects on surface water quality resulting from development.

More information

J O I N T P U B L I C N O T I C E

J O I N T P U B L I C N O T I C E J O I N T P U B L I C N O T I C E CHARLESTON DISTRICT, CORPS OF ENGINEERS 69A Hagood Avenue Charleston, South Carolina 29403 and THE S.C. DEPARTMENT OF HEALTH AND ENVIRONMENTAL CONTROL Office of Ocean

More information

TARGETED DREDGING OF NEAR-SHORE DEBRIS AND SEDIMENT, UPPER TRENTON CHANNEL, DETROIT RIVER: A CASE STUDY

TARGETED DREDGING OF NEAR-SHORE DEBRIS AND SEDIMENT, UPPER TRENTON CHANNEL, DETROIT RIVER: A CASE STUDY TARGETED DREDGING OF NEAR-SHORE DEBRIS AND SEDIMENT, UPPER TRENTON CHANNEL, DETROIT RIVER: A CASE STUDY M.J. Erickson, P.E. 1, R.K. Mohan, P.E. 2, W.J. Dinicola 3, and M.R. Henderson 4 ABSTRACT Under regulatory

More information

Dredge Spoils Management for Sustainable Support of U.S. Coast Guard Missions

Dredge Spoils Management for Sustainable Support of U.S. Coast Guard Missions Dredge Spoils Management for Sustainable Support of U.S. Coast Guard Missions Erick Jackson 1, Bethany Gollin 1, Spencer Zwenger 1, Holly Moore 1, Hudson Jackson 2, and Kassim Tarhini 3 1 Ensign, United

More information

CHAPTER 7. San Dieguito River Flooding Adaptation

CHAPTER 7. San Dieguito River Flooding Adaptation CHAPTER 7 San Dieguito River Flooding Adaptation This chapter includes a range of adaptation measures to address vulnerabilities from flooding along the San Dieguito River, including the river valley,

More information

BENEFICIAL REUSE OF DREDGE MATERIAL SOUTH BAY SALT POND RESTORATION PROJECT PHASE 2

BENEFICIAL REUSE OF DREDGE MATERIAL SOUTH BAY SALT POND RESTORATION PROJECT PHASE 2 BENEFICIAL REUSE OF DREDGE MATERIAL SOUTH BAY SALT POND RESTORATION PROJECT PHASE 2 CALIFORNIA DEPARTMENT OF FISH AND WILDLIFE EDEN LANDING ECOLOGICAL RESERVE PHASE 2 HAS TWO PARTS: PROJECT UPDATE USFWS

More information

40 YEARS OF MARINE OPERATIONS & ENGINEERING IN HAWAII. Makai Research Pier, Waimanalo, Hawaii. 863 N. Nimitz Hwy, Honolulu Harbor

40 YEARS OF MARINE OPERATIONS & ENGINEERING IN HAWAII. Makai Research Pier, Waimanalo, Hawaii. 863 N. Nimitz Hwy, Honolulu Harbor 40 YEARS OF MARINE OPERATIONS & ENGINEERING IN HAWAII Makai Research Pier, Waimanalo, Hawaii 863 N. Nimitz Hwy, Honolulu Harbor Santa Cruz, California www.seaengineering.com ABOUT US Sea Engineering, Inc.

More information

LOWER PASSAIC RIVER COMMERCIAL NAVIGATION ANALYSIS. United States Army Corps of Engineers New York District. Revised: December 29, 2008

LOWER PASSAIC RIVER COMMERCIAL NAVIGATION ANALYSIS. United States Army Corps of Engineers New York District. Revised: December 29, 2008 LOWER PASSAIC RIVER COMMERCIAL NAVIGATION ANALYSIS United States Army Corps of Engineers New York District Revised: December 29, 2008 US Army Corps of Engineers LOWER PASSAIC RIVER RESTORATION PROJECT

More information

Monitoring and Data Collection

Monitoring and Data Collection Setting the Course for Improved Water Quality Monitoring and Data Collection A TMDL training program for local government leaders and other water resource managers Session 8 wq-iw3-58 Your project to date

More information

Algae Removal from a Facultative Lagoon System Using Dissolved Air Flotation. J. Patrick Pierce, P.E. Environmental Treatment Systems, Inc.

Algae Removal from a Facultative Lagoon System Using Dissolved Air Flotation. J. Patrick Pierce, P.E. Environmental Treatment Systems, Inc. Algae Removal from a Facultative Lagoon System Using Dissolved Air Flotation J. Patrick Pierce, P.E. Environmental Treatment Systems, Inc. Facultative Lagoon System Designed for 1.5 MGD Discharging 1.15-1.35

More information

Soil Survey Investigations of Freshwater Subaqueous Soils

Soil Survey Investigations of Freshwater Subaqueous Soils Soil Survey Investigations of Freshwater Subaqueous Soils Jonathan Bakken Department of Environmental Sciences University of Rhode Island Summer 2010 Workshop Overview: Introduction Statement of Research

More information

Dredging and Dredged Material Disposal Overview

Dredging and Dredged Material Disposal Overview Dredging and Dredged Material Disposal Overview Tim Welp Timothy.L.Welp@usace.army.mil 601.634.2083 The process of dredging consists of the following stages: - Excavation (loosening or dislodging) of the

More information

FACT PATTERN THE RESERVATION

FACT PATTERN THE RESERVATION FACT PATTERN THE RESERVATION Great Lakes Tribal Reservation Surrounded by Big River National Forest Big River flows through Reservation and into Big Lake General Environmental Concerns Wild rice areas

More information

Design of CAD Pits in San José Lagoon, San Juan, Puerto Rico

Design of CAD Pits in San José Lagoon, San Juan, Puerto Rico Second LACCEI International Latin American and Caribbean Conference for Engineering and Technology (LACCEI 2004) Challenges and Opportunities for Engineering Education, Research and Development 2-4 June

More information

Self-Sustaining Treatment for Active Remediation (STAR): Overview and Applications of the Technology

Self-Sustaining Treatment for Active Remediation (STAR): Overview and Applications of the Technology Self-Sustaining Treatment for Active Remediation (STAR): Overview and Applications of the Technology Shanna Thompson, P.E. Gavin Grant, Ph.D., P.Eng. In Partnership with: siremlab.com/star Overview The

More information

The Cooperative Institute for Coastal and Estuarine Environmental Technology (CICEET) Building Technologies for Tomorrow s Coasts

The Cooperative Institute for Coastal and Estuarine Environmental Technology (CICEET) Building Technologies for Tomorrow s Coasts The Cooperative Institute for Coastal and Estuarine Environmental Technology (CICEET) Building Technologies for Tomorrow s Coasts Why CICEET? Pollution and degradation of estuarine and coastal systems

More information

Navigational Channel Dredging, Beneficial Reuse and the South Bay Salt Pond Restoration (SBSP) at Eden Landing, Alameda County

Navigational Channel Dredging, Beneficial Reuse and the South Bay Salt Pond Restoration (SBSP) at Eden Landing, Alameda County Navigational Channel Dredging, Beneficial Reuse and the South Bay Salt Pond Restoration (SBSP) at Eden Landing, Alameda County PRESENTATION TO THE CALIFORNIA MARINE AFFAIRS AND NAVIGATION CONFERENCE BY

More information

Ottumwa Generating Station Project No Closure Plan for Existing CCR Revision: 0 Surface Impoundments TABLE OF CONTENTS

Ottumwa Generating Station Project No Closure Plan for Existing CCR Revision: 0 Surface Impoundments TABLE OF CONTENTS Surface Impoundments Page No. i TABLE OF CONTENTS 1. INTRODUCTION... 1 2. PROPOSED CCR IMPOUNDMENTS CLOSURE PROCEDURE... 3 3. PROPOSED COVER SYSTEM... 4 4. ESTIMATED MAXIMUM INVENTORY OF CCR... 4 5. ESTIMATED

More information

Division of Surface Water Environmental Mitigation & Special Permitting Section

Division of Surface Water Environmental Mitigation & Special Permitting Section GUIDANCE FOR SECTION 401 WATER QUALITY CERTIFICATION AND ISOLATED WETLAND PERMITS THROUGH THE COORDINATED APPLICATION PROCESS FOR SURFACE COAL MINE SITES Division of Surface Water Environmental Mitigation

More information

SPILL ESTIMATION. Not Just A Guess Anymore

SPILL ESTIMATION. Not Just A Guess Anymore SPILL ESTIMATION Not Just A Guess Anymore SPILL ESTIMATION Under current regulations accurate spill estimation has become critical to the operation and maintenance of a sanitary collection system Reporting

More information

U.S. Army Corps of Engineers Jacksonville District Sediment Quality Control/Quality Assurance Plan For Maintenance Dredging with Beach Placement

U.S. Army Corps of Engineers Jacksonville District Sediment Quality Control/Quality Assurance Plan For Maintenance Dredging with Beach Placement U.S. Army Corps of Engineers Jacksonville District Sediment Quality Control/Quality Assurance Plan For Maintenance Dredging with Beach Placement Name of Project: Maintenance Dredging AIWW Vicinity Jupiter

More information

2014 WEDA ENVIRONMENTAL EXCELLENCE AWARD NOMINATION FOR CONSIDERATION

2014 WEDA ENVIRONMENTAL EXCELLENCE AWARD NOMINATION FOR CONSIDERATION 2014 WEDA ENVIRONMENTAL EXCELLENCE AWARD NOMINATION FOR CONSIDERATION Environmental Dredging of Sheboygan River, Wisconsin A multi-stakeholder collaboration, simultaneous execution of multiple projects

More information

US Steel/Spirit Lake Sediment Cleanup Update for River Corridor Coalition

US Steel/Spirit Lake Sediment Cleanup Update for River Corridor Coalition US Steel/Spirit Lake Sediment Cleanup Update for River Corridor Coalition Erin Endsley, Project Manager Mike Bares, Technical Analyst Minnesota Pollution Control Agency August 26, 2015 Outline Site history

More information

American Creosote Works Site

American Creosote Works Site U.S. Environmental Protection Agency American Creosote Works Site Pensacola, Florida April 2017 Public meeting scheduled to discuss the proposed Cleanup Plan Wednesday April 26, 2017 at 6:00 p.m. Sanders

More information

Panama City Marina City of Panama City, Florida

Panama City Marina City of Panama City, Florida Panama City Marina City of Panama City, Florida MARINA BULKHEAD ASSESSMENT October 3, 2011 Prepared For: Prepared By: 543 Harbor Boulevard, Suite 204 Destin, Florida 32541 DRAFT - 12/19/2011 Panama City

More information

Hudson Raritan Estuary Comprehensive Restoration Plan and Feasibility Study

Hudson Raritan Estuary Comprehensive Restoration Plan and Feasibility Study Restoring America s Estuaries 5 th National Conference on Coastal and Estuarine Habitat Restoration 16 November 2010 Hudson Raritan Estuary Comprehensive Restoration Plan and Feasibility Study Lisa Baron

More information

Keeyask Generation Project Request to Release Impounded Water with TSS Concentrations Greater than 25 mg/l in Spring 2017

Keeyask Generation Project Request to Release Impounded Water with TSS Concentrations Greater than 25 mg/l in Spring 2017 Keeyask Generation Project Request to Release Impounded Water with TSS Concentrations Greater than 25 mg/l in Spring 2017 Manitoba Hydro, in its delegated authority to manage construction of the Keeyask

More information

Cat Island Chain Restoration, Green Bay

Cat Island Chain Restoration, Green Bay Cat Island Chain Restoration, Green Bay Victoria Harris, UW Sea Grant January 27, 2005 Southern Green Bay historically provided diverse coastal wetland habitats for fish and wildlife Expansive emergent

More information

AGENCY: Department of the Army; Corps of Engineers; and Texas Commission on Environmental Quality

AGENCY: Department of the Army; Corps of Engineers; and Texas Commission on Environmental Quality DEPARTMENT OF THE ARMY GALVESTON DISTRICT, CORPS OF ENGINEERS P. O. BOX 1229 GALVESTON, TEXAS 77553-1229 April 11, 2017 AGENCY: Department of the Army; Corps of Engineers; and Texas Commission on Environmental

More information

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY REGION BROADWAY NEW YORK, NEW YORK 10007

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY REGION BROADWAY NEW YORK, NEW YORK 10007 EXHIBIT 13 "E UNITED STATES ENVIRONMENTAL PROTECTION AGENCY REGION 2 290 BROADWAY NEW YORK, NEW YORK 10007 MEMORANDUM DATE: January 18, 2001 SUBJECT: FROM: TO: National Remedy Review Board Recommendations

More information

SECTION 2 WATER 2.1 ROUTINE WATER COLUMN MONITORING Collection Summary

SECTION 2 WATER 2.1 ROUTINE WATER COLUMN MONITORING Collection Summary SECTION 2 WATER 2.1 ROUTINE WATER COLUMN MONITORING 2.1.1 Collection Summary Routine water column sampling was performed biweekly between May and October for a total of 13 sampling rounds. Water column

More information

The following answers are provided in response to questions received.

The following answers are provided in response to questions received. CARLOS PABELLON Director of Administration COUNTY OF DANE DEPARTMENT OF ADMINISTRATION PURCHASING DIVISION Room 425 City-County Building 210 Martin Luther King Jr. Blvd. Madison, WI 53703-3345 608-266-4131

More information

Executive Summary. ES-1 Introduction. ES-2 Background

Executive Summary. ES-1 Introduction. ES-2 Background ES-1 Introduction The Federal Transit Administration (FTA) and the (CTDOT) are preparing a combined Environmental Assessment (EA), Section 4(f) Evaluation, and Environmental Impact Evaluation (EIE) to

More information

Randle Reef Sediment Remediation Project Hamilton, Ontario, Canada. Erin Hartman, P.Eng. Environment Canada October 25, 2012

Randle Reef Sediment Remediation Project Hamilton, Ontario, Canada. Erin Hartman, P.Eng. Environment Canada October 25, 2012 Randle Reef Sediment Remediation Project Hamilton, Ontario, Canada Erin Hartman, P.Eng. Environment Canada October 25, 2012 Hamilton Harbour Randle Reef Sediment Remediation Project Hamilton Harbour, Lake

More information

2016 Lake Worth Lagoon CAP 1135 Benthic Macroinvertebrate Study. Preliminary Results

2016 Lake Worth Lagoon CAP 1135 Benthic Macroinvertebrate Study. Preliminary Results 2016 Lake Worth Lagoon CAP 1135 Benthic Macroinvertebrate Study Preliminary Results Study Objectives Section 1135 of the Water Resources Development Act of 1986 - U.S. Army Corps of Engineers may plan,

More information

Projected Sea Level Change

Projected Sea Level Change UBCM 2011 RISING OCEANS & RAISING DIKES A LOCAL GOVERNMENT PERSPECTIVE Carrie Baron, P.Eng. Drainage & Environment Manager Projected Sea Level Change Provincial Government reports predict sea level changes

More information

T. Frank, J. Jensen, Ch. Mudersbach, B. Schubert, M. Wörner

T. Frank, J. Jensen, Ch. Mudersbach, B. Schubert, M. Wörner Research Institute for for Water and Environment University of of Siegen Protection of Nuclear Power Plants against Flooding Considerations for the Determination of a 10.000 Years Return Period Flood between

More information

Overview of Pepco Benning Facility RI/FS

Overview of Pepco Benning Facility RI/FS Overview of Pepco Benning Facility RI/FS RI/FS Background Between 1985 and 2003, there have been six documented releases of PCBs into the environment at the facility. In each case, Pepco cleaned up the

More information

Need to Verify Model TSS Reduction Estimates

Need to Verify Model TSS Reduction Estimates Examples of Proprietary BMPs Using Settling for Treatment Modeling Manufactured Stormwater Control Practices Vortechs University of Wisconsin Madison Engineering Professional Development 1 DownStream Defender

More information

ENVIRONMENTAL DREDGING. Lower Duwamish Waterway. Enhanced Natural Recovery/Activated Carbon Pilot Study

ENVIRONMENTAL DREDGING. Lower Duwamish Waterway. Enhanced Natural Recovery/Activated Carbon Pilot Study ENVIRONMENTAL DREDGING Lower Duwamish Waterway Enhanced Natural Recovery/ March 17, 2017 Mr. Craig Vogt c/o Western Dredging Association WEDA Environmental Commission via: craig@craigvogt.com Mr. Vogt:

More information

Hudson River PCBs Superfund Site

Hudson River PCBs Superfund Site PCBs Superfund Site Intermediate Design Report (IDR) Community Advisory Group Meeting August 31, 2005 1 Introduction Prepared by GE pursuant to the Administrative Order on Consent for Design (RD AOC) Design

More information

Wetlands and Sea Level Rise

Wetlands and Sea Level Rise Learning Science Through Research Wetlands and Sea Level Rise...a hands on science experience focusing on wetland h d i i f i tl d plant adaptations and the effects of sea level rise on wetlands. WETLANDS!

More information

Current Trends in Marina Planning and Design

Current Trends in Marina Planning and Design ASSOCIATION OF PACIFIC PORTS 101 st Annual Conference, July 2014 Current Trends in Marina Planning and Design, PE, LEED AP, Reid Middleton Outline Introduction Market & Demand Planning Environmental Design

More information

WEST SHORE LAKE PONTCHARTRAIN HURRICANE AND STORM DAMAGE RISK REDUCTION STUDY INTEGRATED DRAFT FEASIBILITY REPORT AND ENVIRONMENTAL IMPACT STATEMENT

WEST SHORE LAKE PONTCHARTRAIN HURRICANE AND STORM DAMAGE RISK REDUCTION STUDY INTEGRATED DRAFT FEASIBILITY REPORT AND ENVIRONMENTAL IMPACT STATEMENT WEST SHORE LAKE PONTCHARTRAIN HURRICANE AND STORM DAMAGE RISK REDUCTION STUDY INTEGRATED DRAFT FEASIBILITY REPORT AND ENVIRONMENTAL IMPACT STATEMENT PLAN FORMULATION APPENDIX E 1 Contents Introduction...

More information

Surfactant Enhanced Remediation Of Petroleum and Chlorinated Contaminated Sites. Bud Ivey Ivey International

Surfactant Enhanced Remediation Of Petroleum and Chlorinated Contaminated Sites. Bud Ivey Ivey International Surfactant Enhanced Remediation Of Petroleum and Chlorinated Contaminated Sites Bud Ivey Ivey International SMART Remediation Ottawa, ON February 16, 2017 SMART is Powered by: www.vertexenvironmental.ca

More information

Inflow Design Flood Control System Plan for Louisa Generating Station CCR Impoundment. MidAmerican Energy Company

Inflow Design Flood Control System Plan for Louisa Generating Station CCR Impoundment. MidAmerican Energy Company Control System Plan for Louisa Generating Station CCR Impoundment MidAmerican Energy Company October 10, 2016 Control System Plan for Louisa Generating Station CCR Impoundment Prepared for MidAmerican

More information

Hydrology and Flooding

Hydrology and Flooding Hydrology and Flooding Background The 1996 flood Between February 4, 1996 and February 9, 1996 the Nehalem reporting station received 28.9 inches of rain. Approximately 14 inches fell in one 48 hour period.

More information

STREAM AND BUFFER AREA PROTECTION/RESTORATION

STREAM AND BUFFER AREA PROTECTION/RESTORATION STREAM AND BUFFER AREA PROTECTION/RESTORATION AMENDMENT OPTIONS TO STRENGTHEN POLICY IN HEADWATERS AREAS DRAFT SUBSEQUENT TO THE JANUARY 25, 2007 MEETING OF THE PLANNING COMMISSION ENVIRONMENT COMMITTEE

More information

Cross-Sections DO Concentration (mg/l) High Tide 9/11/2007. Prepared by: LRP 8/10/09 Checked db by: TRK 8/10/09

Cross-Sections DO Concentration (mg/l) High Tide 9/11/2007. Prepared by: LRP 8/10/09 Checked db by: TRK 8/10/09 Prepared by: LRP 8/10/09 Checked db by: TRK 8/10/09 / SAVANNAH HARBOR REOXYGENATION DEMONSTRATION PROJECT GEORGIA PORTS AUTHORITY SAVANNAH, GEORGIA Cross-Sections DO Concentration (mg/l) High Tide 9/11/2007

More information

ENVIRONMENTAL SAMPLING

ENVIRONMENTAL SAMPLING ENVIRONMENTAL SAMPLING 1. GENERAL. Collecting and analyzing samples provides numerical data that describe a particular situation. The ASHG shall direct sampling procedures. The sampling criteria shall

More information

LONG-TERM MANAGEMENT STRATEGY FOR THE PLACEMENT OF DREDGED MATERIAL IN THE SAN FRANCISCO BAY REGION

LONG-TERM MANAGEMENT STRATEGY FOR THE PLACEMENT OF DREDGED MATERIAL IN THE SAN FRANCISCO BAY REGION LONG-TERM MANAGEMENT STRATEGY FOR THE PLACEMENT OF DREDGED MATERIAL IN THE SAN FRANCISCO BAY REGION 12-YEAR REVIEW FINAL REPORT Prepared by San Francisco Bay Conservation and Development Commission San

More information

ECSI Number: Responsible Party: Klamath County. QTime Number: Entry Date: 9/22/04 (VCP)

ECSI Number: Responsible Party: Klamath County. QTime Number: Entry Date: 9/22/04 (VCP) ECSI Number: 1213 Responsible Party: Klamath County QTime Number: 37941 Entry Date: 9/22/04 (VCP) Proposed Remedial Action Staff Report - Addendum Chiloquin Forest Products Chiloquin, Klamath County, Oregon

More information

Council of Governments

Council of Governments Metropolitan Washington Council of Governments Anne Arundel County Draft Phase II Watershed Implementation Plan January 18, 2011 Chesapeake Bay TMDL Pollutants of Concern Nitrogen Phosphorus Sediment 2

More information

SEDIMENT CHOREOGRAPHY

SEDIMENT CHOREOGRAPHY Global Reach. Local Benefit. SEDIMENT CHOREOGRAPHY 4/15/2016 Maritime and the Regional Economy The Port of Cleveland spurs job creation and helps our region compete globally by connecting local businesses

More information

Cleanup Strategies at MGP Sediment Sites A State of the Art Review. The Issues.

Cleanup Strategies at MGP Sediment Sites A State of the Art Review. The Issues. Cleanup Strategies at MGP Sediment Sites A State of the Art Review Ram Mohan, PE, PhD, Carl Stivers, and Gabe Bolin, PE Anchor Environmental, L.L.C. Michele Leone National Grid Helder Costa Haley & Aldrich

More information

Water / Fluid Treatment Technologies and the Art of Applying Technology to Address Reuse and Recycling Challenges in the Oil and Gas Field

Water / Fluid Treatment Technologies and the Art of Applying Technology to Address Reuse and Recycling Challenges in the Oil and Gas Field Water / Fluid Treatment Technologies and the Art of Applying Technology to Address Reuse and Recycling Challenges in the Oil and Gas Field Thomas Steinke Johnson Screens Global Applications Manager Fluid

More information

Discharge and Sediment Monitoring Project Regional meeting 14 January 2009 Presented by Ms. Iwona Conlan

Discharge and Sediment Monitoring Project Regional meeting 14 January 2009 Presented by Ms. Iwona Conlan Discharge and Sediment Monitoring Project 2009-2010 Draft Project Proposal Regional meeting 14 January 2009 Presented by Ms. Iwona Conlan 1 Aims for today 1. To discuss and agree on the overall monitoring

More information

Sediment Characterization Report

Sediment Characterization Report Sediment Characterization Report Old Douglas Replacement June 2007 Revised November 2007 Jennifer Lundberg, CEP, MES Senior Environmental Scientist Prepared for: Page i of i Table of Contents Introduction...

More information

Model Results Operation and Maintenance (O& M) Results Cost-Benefit Analysis Results Conclusions

Model Results Operation and Maintenance (O& M) Results Cost-Benefit Analysis Results Conclusions BMP Performance and Outline Background Model Results Operation and Maintenance (O& M) Results Results Conclusions Melissa Baker, Water Resource Technician Capitol Region Watershed District, St. Paul, MN

More information

Greenfield Pond B Rehabilitation

Greenfield Pond B Rehabilitation Preliminary Investigation Report Centennial, Colorado November 15, 2011 Prepared for: Liverpool Metropolitan District Prepared by: Stantec Consulting Services, Inc. Table of Contents Executive Summary...

More information

REVISED FEASIBILITY STUDY REPORT

REVISED FEASIBILITY STUDY REPORT REVISED FEASIBILITY STUDY REPORT Warrenton Boat Yard 101 NE Harbor Street Warrenton, OR 97146 DEQ ECSI Site #2764 Prepared for: Warrenton Boat Yard 101 NE Harbor Street Warrenton, OR 97146 Prepared by:

More information

City of Ocean City Lagoon/Back Bay Dredging Town Hall Meeting

City of Ocean City Lagoon/Back Bay Dredging Town Hall Meeting City of Ocean City Lagoon/Back Bay Dredging Town Hall Meeting Total Estimated Dredge Material required for North to South of the City 500,000 Cubic Yards of Dredge Material Includes: North to South of

More information

Addendum to Feasibility Study

Addendum to Feasibility Study Addendum to Feasibility Study Former Duluth Works and Spirit Lake Sediment Site Prepared for Great Lakes Legacy Act Partnership between United States Steel Corporation, United States, Environmental Protection

More information

Measures for Congestion at Ports. Doug McDonald U.S. Maritime Administration Office of Policy and Plans

Measures for Congestion at Ports. Doug McDonald U.S. Maritime Administration Office of Policy and Plans Measures for Congestion at Ports Doug McDonald U.S. Maritime Administration Office of Policy and Plans 1 MAP-21 (Moving Ahead for Progress in the 21 st Century Act) Directs the creation of a national freight

More information

ASSEMBLY RESOLUTION No. 153 STATE OF NEW JERSEY. 218th LEGISLATURE INTRODUCED APRIL 5, 2018

ASSEMBLY RESOLUTION No. 153 STATE OF NEW JERSEY. 218th LEGISLATURE INTRODUCED APRIL 5, 2018 ASSEMBLY RESOLUTION No. STATE OF NEW JERSEY th LEGISLATURE INTRODUCED APRIL, 0 Sponsored by: Assemblyman TIM EUSTACE District (Bergen and Passaic) Assemblyman JOHN F. MCKEON District (Essex and Morris)

More information

Conceptual Engineering Report Collier County Beaches, Florida

Conceptual Engineering Report Collier County Beaches, Florida Conceptual Engineering Report Collier County Beaches, Florida Presented to Collier County Coastal Advisory Committee October 13, 2011 Steve Keehn, PE, CPE Topics Goals Monitoring & Performance Summary

More information

Big Sarasota Pass and New Pass Inlet Management Plan 2008 Peer Review Report

Big Sarasota Pass and New Pass Inlet Management Plan 2008 Peer Review Report Table of Contents Consolidated Report on Peer Reviews... Pages 2-17 Executive Summary. Page 2 Introduction... Page 5 Physical and Environmental Data Page 5 Numerical Modeling. Page 7 Coastal Engineering.

More information

POOL 11 ISLANDS SUNFISH LAKE AND MUD LAKE OPERATION AND MAINTENANCE MANUAL

POOL 11 ISLANDS SUNFISH LAKE AND MUD LAKE OPERATION AND MAINTENANCE MANUAL MISSISSIPPI RIVER POOL 11 ISLANDS SUNFISH LAKE AND MUD LAKE GRANT COUNTY, WISCONSIN AND DUBUQUE COUNTY, IOWA U.S. ARMY CORPS OF ENGINEERS ENVIRONMENTAL MANAGEMENT PROGRAM HABITAT REHABILITATION AND ENHANCEMENT

More information

Appendix I Cost Engineering Pigs Eye Lake Ramsey County, MN Section 204 DRAFT. Draft Feasibility Study Report with Integrated Environmental Assessment

Appendix I Cost Engineering Pigs Eye Lake Ramsey County, MN Section 204 DRAFT. Draft Feasibility Study Report with Integrated Environmental Assessment Appendix I Cost Engineering Pigs Eye Lake Ramsey County, MN Section 204 Draft Feasibility Study Report with Integrated Environmental Assessment St. Paul District U.S. Army Corps of Engineers March 2018

More information

APPENDIX A ALTERNATIVES COST ANALYSIS

APPENDIX A ALTERNATIVES COST ANALYSIS APPENDIX A ALTERNATIVES COST ANALYSIS 1.0 INTRODUCTION This appendix provides the cost detail for the remedial alternatives. The limits of the alternatives are based on the sediment PRG of 13.7 mg/kg TPAHs.

More information

Hydrologic and Ecologic Impacts from the CERP Indian River Lagoon South Project

Hydrologic and Ecologic Impacts from the CERP Indian River Lagoon South Project Hydrologic and Ecologic Impacts from the CERP Indian River Lagoon South Project Dr. Gretchen Ehlinger Senior Biologist US Army Corps of Engineers Jacksonville District November 15, 2016 AWRA Conference

More information

5.0 RECOMMENDATIONS. Recommendations going forward

5.0 RECOMMENDATIONS. Recommendations going forward 5.0 RECOMMENDATIONS Recommendations going forward Overall, the 2007 ReOx demonstration project confirmed that the Speece Cone technology can effectively add DO to the harbor and reduce instream DO deficits

More information

Atlantic Coast of New York East Rockaway Inlet to Rockaway Inlet and Jamaica Bay, NY

Atlantic Coast of New York East Rockaway Inlet to Rockaway Inlet and Jamaica Bay, NY Atlantic Coast of New York East Rockaway Inlet to Rockaway Inlet and Jamaica Bay, NY Draft Reformulation Public Information October 2016 US Army Corps of Engineers Presentation Outline Project Overview

More information

GOING WITH THE FLOW: DESIGN TECHNIQUES TO IMPROVE RAW WATER QUALITY

GOING WITH THE FLOW: DESIGN TECHNIQUES TO IMPROVE RAW WATER QUALITY GOING WITH THE FLOW: DESIGN TECHNIQUES TO IMPROVE RAW WATER QUALITY ABSTRACT Porter Rivers, III, PE URS Corporation Keith Cannon, PE URS Corporation Geoff Smith, PE URS Corporation Ken Green, Eastern Band

More information

THE BENEFITS OF MECHANICAL DEWATERING: CASE STUDY OF MACHADO LAKE ECOSYSTEM REHABILTATION PROJECT IN LOS ANGELES, CALIFORNIA

THE BENEFITS OF MECHANICAL DEWATERING: CASE STUDY OF MACHADO LAKE ECOSYSTEM REHABILTATION PROJECT IN LOS ANGELES, CALIFORNIA THE BENEFITS OF MECHANICAL DEWATERING: CASE STUDY OF MACHADO LAKE ECOSYSTEM REHABILTATION PROJECT IN LOS ANGELES, CALIFORNIA Presented by: Thomas B. Amaro, VP/GM, Tim Azevedo, Chief Estimator Machado Lake

More information

Flood Hazard Assessment Report Falls Gulch, Larimer County, Colorado January 16, 2013

Flood Hazard Assessment Report Falls Gulch, Larimer County, Colorado January 16, 2013 United States Department of Agriculture Natural Resources Conservation Service Denver Federal Center Building 56, Room 2604 P.O. Box 25426 Denver, CO 80225 720-544-2818-OFFICE alton.albin@co.usda.gov Flood

More information

Dredging for Climate Change and Transport in the Netherlands

Dredging for Climate Change and Transport in the Netherlands Dredging for Climate Change and Transport in the Netherlands Dredging to survive Polite Laboyrie (Chairman of CEC and Head of Hydr&Env Eng RWS) Organisation Ministry of Transport Dredging for Climate Change

More information

Iron Mountain Mine Shasta County, California

Iron Mountain Mine Shasta County, California CASE STUDY Iron Mountain Mine Shasta County, California August 2010 Prepared by The Interstate Technology & Regulatory Council Mining Waste Team Permission is granted to refer to or quote from this publication

More information

Our Eastern Shore Groundwater Part IV Groundwater Quality on the Eastern Shore: How safe is our groundwater and are there ways we can protect it?

Our Eastern Shore Groundwater Part IV Groundwater Quality on the Eastern Shore: How safe is our groundwater and are there ways we can protect it? Our Eastern Shore Groundwater Part IV Groundwater Quality on the Eastern Shore: How safe is our groundwater and are there ways we can protect it? Britt McMillan, Malcolm Pirnie, Inc. Mercury Venus Mars

More information

CHAPTER 5 SEWAGE PUMPS AND LIFT STATIONS

CHAPTER 5 SEWAGE PUMPS AND LIFT STATIONS 15 October 1973 FM 5-163 CHAPTER 5 SEWAGE PUMPS AND LIFT STATIONS 5-1. General Pumps for lifting sanitary sewage, storm water, and plant-unit effluents are usually high-capacity, low-head types with large

More information

Metric Conversion Tables

Metric Conversion Tables Metric Conversion Tables Measurement in: From English Units: To Metric Units: Multiply By Length inch (in) millimeter (mm) 25.40 foot (ft) meter (mm) 0.3048 yard (yd) meter (mm) 0.9144 mile (mi) kilometer

More information

San Jacinto River Waste Pits Superfund Site

San Jacinto River Waste Pits Superfund Site San Jacinto River Waste Pits Superfund Site Channelview Highlands Northern Waste Pits Before Cap North Waste Pits After Cap Approximate Limit of Armored Cap Cap Construction Completed July 12, 2011 Old

More information