CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS

Size: px
Start display at page:

Download "CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS"

Transcription

1 CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS A. General description of the small scale project activity B. Application of a baseline and monitoring methodology C. Duration of the project activity / crediting period D. Environmental impacts E. Stakeholders comments Annexes Annex 1: Contact information on participants in the proposed small scale project activity Annex 2: Information regarding public funding Annex 3: Baseline information Annex 4: Monitoring Information

2 Revision history of this document Version Date Description and reason of revision Number January 2003 Initial adoption 02 8 July 2005 The Board agreed to revise the CDM SSC PDD to reflect guidance and clarifications provided by the Board since version 01 of this document. As a consequence, the guidelines for completing CDM SSC PDD have been revised accordingly to version 2. The latest version can be found at < December The Board agreed to revise the CDM project design 2006 document for small-scale activities (CDM-SSC-PDD), taking into account CDM-PDD and CDM-NM.

3 SECTION A. General description of small-scale project activity A.1 Title of the small-scale project activity: Title: Biogas recovery from wastewater treatment in PT. Umbul Mas Wisesa Palm Oil Mill Version: 01 Date: 11/08/2011 A.2. Description of the small-scale project activity: Introduction The proposed project activity is the implementation of a sequential stage of anaerobic wastewater treatment system with biogas recovery in a palm oil mill. Both, the palm oil mill as well as the wastewater treatment system with biogas recovery are Greenfield projects. The palm oil mill will be set up by PT. Umbul Mas Wisesa ( UMW ) at Labuhan Batu, North Sumatra, Indonesia. The mill is expected to be fully operational in March 2012 for producing crude palm oil ( CPO ) while discharging the raw palm oil mill effluent ( POME ). The designed production capacity of the mill will be 65 tonnes/hr of fresh fruit bunch (FFB). The discharged POME will be rich in organic content with Chemical Oxygen Demand (COD) value approximately 65,000 mg/l. The average daily discharge of POME from the palm oil mill is expected to be 780m 3 /day. Purpose of the proposed project activity Degradation of organic content in the POME results in the generation of biogas (i.e. methane) which will be emitted into the atmosphere if not recovered. The purpose of the proposed project activity is to treat the discharged POME in an anaerobic digester and to recover the biogas which would have otherwise been emitted to the atmosphere. The recovered biogas will be combusted either by use in a boiler in the palm oil mill or by flaring or by a combination of both. The use of the biogas is not part of the CDM project activity. Treatment of discharged POME in anaerobic open lagoons without biogas recovery is the most plausible baseline scenario for the proposed project activity. This will be demonstrated under section B.4 of the PDD. Therefore in the absence of the project, the methane gas from anaerobic open lagoons would have been emitted into the atmosphere resulting in GHG emissions. Proposed technology for the project activity The technology used in the project activity comprises of pre-treatment, anaerobic digester and downstream aerobic treatment system. The POME will be stabilized and cooled down. The suspended solids and emulsified oil will be removed from the POME. The pre-treated POME will then be passed on to the anaerobic digester where the COD content will be reduced. The digester will be equipped with biogas recovery system to recover the generated biogas. The sludge generated from the digestion process will be dried and used for land application under aerobic condition. The clarified POME will be treated in the downstream activities which include aerobic treatment systems. The final treated POME from the treatment plant will be of re-usable quality and will be used for land application under aerobic condition. The project activity will therefore reduce greenhouse gases (GHG) emissions through recovery of methane in the anaerobic digesters.

4 Contribution to Sustainable Development The project activity contributes to the sustainable development in four principal aspects: Environmental Sustainability 1. The project activity involves the use of anaerobic digesters with methane recovery. It thus avoids the emission of methane into the atmosphere and therefore contributes to the reduction of GHG emissions.the project activity may further utilize the recovered biogas for energy generation for captive consumption; this would reduce the emissions associated with the fossil fuel use. It will also conserve the use of natural resources used as fuel. 2. The treated wastewater discharged from the project activity will meet the standards set for the industrial wastewater, particularly for palm oil industry The project activity introduces water re-use which reduces on-site water consumption, and thus contributes to conservation of natural resources (i.e. water). 4. The project activity will not cause any disturbance to the biodiversity and the natural habitats in the surrounding area of the project. 5. The PP will ensure all requirements pertaining to this land use, i.e. permissions and approvals from the relevant agencies, will be complied with. 6. The project activity will implement best practices in issues related to health and safety, and thus it will not impose health risk for the employees or for the local community. Further, the avoidance of methane emission will reduce the unpleasant odour associated with the POME treatment in the most plausible baseline system. 7. The PP will ensure that the project activity will comply with the work safety regulations. There will be staffs transferred from the group company, who are ISO 14001, RSPO and ISCC certified. These employees are used to work in accordance with the Health and Safety Regulations at workplace. The PP will form a specific committee for health and safety issues at workplace. 8. All procedures related to efforts in preventing accidents in the project site and the actions to be taken if accidents happen are documented in a company s reference called Kebijakan Keselamatan dan Kesehatan Kerja. Economic Sustainability 1. The project activity will not reduce the income of local community. In fact, as it requires more skilful manpower in operation from diverse backgrounds (i.e. engineering, science and finance), the implementation of this project will potentially increase employment opportunities in the region. 2. Further, the PP will ensure that there are no layoff issues, to the extent possible, which will arise due to the project activity. For any such occurance, a discussion will be conducted and the PP will ensure that the national labour law is complied. 3. The project activity will not reduce the quality of any public service (e.g. health, education, energy, etc) provided for local community in any way. Social Sustainability 1. The project activity has encouraged community participation. A local stakeholder consultation has been conducted. More details of the local stakeholder comments and the responses and further actions taken by PP are provided in section E of this PDD. 2. The project activity will not cause any conflicts in the community that can affect the social integrity of the local communities. Technological Sustainability 1. The use of foreign imported technology will stimulate and promote the development and transfer of more wastewater treatment technologies into Indonesia. The technology supplier 1 MenLH Decree 51/1995, Attachment B.IV (Palm Oil Industry),

5 A.3. will ensure that the employees can operate and maintain the system at ease independently. Further, there will be technology transfer with regards to construction of the project and the use of biogas. 2. The technology is a new anaerobic reactor imported from India. It is not obsolete and neither is in trial period. Implementation of this project will encourage the use of similar technical design technology in Indonesia and thus will promote the sustainability of this technology. 3. Through the technology transfer (i.e. skills upgrading and trainings), this project activity will involve use the new technology in the treatment system and will enhance local operators knowledge and expertise. Thus, the local capability and workforce quality will be improved. Project participants: Name of the party involved ((host) indicates a host party) Private and/or public entity(ies) Project participants (as applicable) Kindly indicate if the Party involved wishes to be considered as project participant (Yes/No) Indonesia PT Umbul Mas Wisesa No Indonesia Knowledge Integration Services No (Singapore) Pte Ltd A.4. Technical description of the small-scale project activity: A.4.1. Location of the small-scale project activity: A Host Party(ies): Republic of Indonesia A Region/State/Province etc.: North Sumatra Province, Sumatra Island A City/Town/Community etc: Panai Tengah, Labuhan Batu Regency A Details of physical location, including information allowing the unique identification of this small-scale project activity : The project activity will be located at Tanjung Mulia village, Panai Tengah sub-district, 212 km South East of Medan, the capital city of North Sumatra Province. The coordinates for the CDM project activity at the palm oil mill site is approximately 2 o N and 100 o E.

6 Labuhan Batu Figure 1: Labuhan Batu, North Sumatra (Source: Wikipedia, 2011) Figure 2: Location map for Panai Tengah (Source: Google Map, 2011) A.4.2. Type and category(ies) and technology/measure of the small-scale project activity: In accordance with Appendix B of the simplified modalities and procedures for small-scale CDM project activities (SSC M&P), the proposed project activity falls under the following category 2 : Type III: Other project activity Category M: Methane recovery Baseline and monitoring methodology applied: AMS-III.H Methane recovery in wastewater treatment (version 16) Technological description The technology applied for the project activity is introduction of a sequential stage wastewater treatment system utilising an anaerobic digester system with methane recovery for treatment of POME generated from the palm oil milling operations. 2

7 The flow of raw POME from the palm oil mill will be stabilized in an equalization tank. The stabilized POME will then be cooled through a heat exchanger system. The cooled POME will then be treated in a Dissolve Air Flotation and primary clarifier system for removing the suspended solids and emulsified oil. The POME will be treated biologically to reduce the COD content in an anaerobic digester. The digester will be equipped with biogas recovery system to recover the generated biogas. The sludge generated during the digestion process will be separated from the POME in the subsequent clarifier. A portion of the sludge is then re-circulated to the digester to help maintaining adequate population of active bacteria inside the digester. The remaining of the sludge will be dried and then used for land application under aerobic condition. The clarified overflow POME from the clarifier will be further treated in the downstream activities. This includes aerobic treatment in conventional and extended aeration tanks followed by post treatment of the POME (i.e. chlorination, de-chlorination and filtration with multi grade and activated carbon). The final treated POME will be discharged to nearby plantation area under aerobic condition. The anaerobic digester used in the project activity will have the following characteristics: Capacity: 8,495 m 3 Hydraulic residence time: 11 days (=8,495m 3 / 780 m 3 /day) COD removal efficiency: 85% A.4.3 Estimated amount of emission reductions over the chosen crediting period: Years Annual estimation of emission reductions in tonnes of CO 2 equivalent (tco 2 e) , , , , , , , , , ,399 Total estimated reductions (tonnes of CO 2 e) 513,990 Total number of crediting years 10 Annual average of the estimated reductions over the crediting period (tco 2 e) 51,399 A.4.4. Public funding of the small-scale project activity: No public funding is involved for this project activity.

8 A.4.5. Confirmation that the small-scale project activity is not a debundled component of a large scale project activity: In accordance to the Appendix C of the simplified modalities and procedures for the small-scale CDM project activities, a small-scale project activity shall be deemed to be a de-bundled component of a large project activity if there is a registered small-scale CDM project activity or an application to register another small-scale CDM project activity: With the same project participants In the same project category and technology/measure Registered within the previous 2 years Whose project boundary is within 1 km of the project boundary of the proposed small-scale activity at the closest point. The project participant (PP) has reviewed the list of projects published on the UNFCCC website and based on such review it is concluded that the project activity is not a de-bundled component of a large scale project activity. SECTION B. Application of a baseline and monitoring methodology B.1. Title and reference of the approved baseline and monitoring methodology applied to the small-scale project activity: The baseline and monitoring of this project activity is based on the following approved methodology, guidelines and tools: (1) AMS-III-H (version 16): Methane recovery in wastewater treatment (2) General Guidelines to SSC CDM methodologies (version 17). (3) Tool to determine project emissions from flaring gases containing methane (EB 28, Annex 13). (4) Tool to calculate project or leakage CO 2 emissions from fossil fuel combustion (EB 41, Annex 11). B.2 Justification of the choice of the project category: The project activity involves the installation of a Greenfield anaerobic digester based wastewater treatment facility, which will be built in parallel to a completely new palm oil mill. The approved small-scale methodology AMS-III.H (version 16) is applicable to the project due to the following reasons as presented in the table below. Table 1: Justification of the choice of the project category AMS-III.H (version 16) Para. AMS-III.H Applicability Requirements No. 1 This methodology comprises measures that recover biogas from biogenic organic matter in wastewater by means of one, or a combination, of the following options: a. Substitution of aerobic wastewater or sludge treatment systems with anaerobic systems with biogas recovery and combustion; Project activity The proposed project activity implements a Greenfield anaerobic digester with biogas recovery, without sludge treatment, to an untreated wastewater stream generated from a Greenfield palm oil mill. This therefore refers to option 1 (e). b. Introduction of anaerobic sludge treatment system

9 Para. No. AMS-III.H Applicability Requirements with biogas recovery and combustion to a wastewater treatment plant without sludge treatment; c. Introduction of biogas recovery and combustion to a sludge treatment system; d. Introduction of biogas recovery and combustion to an anaerobic wastewater treatment system such as anaerobic reactor, lagoon, septic tank or an on-site industrial plant e. Introduction of anaerobic wastewater treatment with biogas recovery and combustion, with or without anaerobic sludge treatment, to an untreated wastewater stream; f. Introduction of a sequential stage of wastewater treatment with biogas recovery and combustion, with or without sludge treatment, to an anaerobic wastewater treatment system without biogas recovery (e.g. introduction of treatment in an anaerobic reactor with biogas recovery as a sequential treatment step for the wastewater that is presently being treated in an anaerobic lagoon without methane recovery). Project activity 2 In cases where baseline system is anaerobic lagoon the methodology is applicable if: a. The lagoons are ponds with a depth greater than two meters, without aeration. b. Ambient temperature above 15 C, at least during part of the year, on a monthly average basis; c. The minimum interval between two consecutive sludge removal events shall be 30 days. As this is a Greenfield project, the characteristic of the most plausible baseline treatment system (i.e. open anaerobic lagoons without methane recovery) will be based on available information from existing anaerobic lagoons at similar industrial facilities in Indonesia. The information referred is from selected three (3) CDM projects, which are registered, that have implemented biogas recovery measure to their existing POME treatment system (i.e. open anaerobic lagoons without methane recovery) in the projects. The details of the projects are provided in Annex 3 of this PDD. In absence of the project activity, the wastewater would have been treated in series of anaerobic lagoons without methane recovery. The average depth of three (3) aboveidentified registered CDM projects (i.e. with open anaerobic lagoons as baseline units), from which the

10 Para. No. AMS-III.H Applicability Requirements Project activity baseline COD removal efficiency for this project activity is referred (i.e. 85%), is 6 meters 3. The ambient temperature in Labuhan Batu is estimated using the average temperature of the nearest major city (i.e. Medan). The average annual temperature in this area is 26.2 o C 4. Taking into the consideration of the required manpower to conduct desludging, the typical interval between two consecutive sludge removal events would be more than 30 days. Further, as per the publication Pipeline 5 the lagoons are able to properly function without sludge removal for up to 5 to 10 years. 3 The list of projects from which this value was taken is provided in Annex 3 of this PDD National Small Flows Claringhouse (1997). Lagoons Need Propoer Operation, Maintenance. PIPELINE Spring 1997; Vol. 8, No. 2.

11 Para. AMS-III.H Applicability Requirements No. 3 The recovered biogas from the above measures may also be utilised for the following applications instead of combustion/flaring: a. Thermal or mechanical, electrical energy generation directly; Project activity The recovered biogas will be combusted either by use in a boiler for energy generation or by flaring or by a combination of both. b. Thermal or mechanical, electrical energy generation after bottling of upgraded biogas; or c. Thermal or mechanical, electrical energy generation after upgrading and distribution, in this case additional guidance provided in Annex 1 shall be followed: i. Upgrading and injection of biogas into a natural gas distribution grid with no significant transmission constraints; ii. Upgrading and transportation of biogas via a dedicated piped network to a group of end users; or iii. Upgrading and transportation of biogas (e.g. by trucks) to distribution points for end users. d. Hydrogen production. e. Use as fuel in transportation applications after upgrading. 4 If the recovered biogas is used for project activities covered under paragraph 3(a), that component of the project activity can use a corresponding methodology under type I Paragraphs 5 11 are not applicable. 12 New facilities (Greenfield projects) and project activities involving a change of equipment resulting in a capacity addition of the wastewater or sludge treatment system compared to the designed capacity of the baseline treatment system are only eligible to apply this methodology if they comply with the relevant requirements in the General guidelines to SSC CDM methodologies. In addition the requirements for demonstrating the remaining lifetime of the equipment replaced, as described in the general guidelines shall be followed. Even though some of the generated biogas from the project activity might potentially be used for electricity generation in biogas engine, the PP will not claim any emission reductions generated from it. This project activity is a Greenfield project which complies with the General guidelines to SSC CDM methodologies. The determination of plausible baseline scenario is presented in section B.4. There will be no equipment replaced; therefore, provisions pertaining to remaining lifetime of the equipment are not relevant to the project activity.

12 Para. AMS-III.H Applicability Requirements No. 13 The location of the wastewater treatment plant as well as the source generating the wastewater shall be uniquely defined and described in the PDD. 14 Measures are limited to those that result in aggregate emissions reductions of less than or equal to 60,000 tco 2 e annually from all Type III components of the project activity. Project activity The location of the wastewater treatment plant will be adjacent to the source of wastewater generation (i.e. the palm oil mill). The location is defined under section A.4.1. The project activity is expected to generate annual average emission reductions of 51,399 tco 2 e during the crediting period (refer to Section A.4.3 above) B.3. Description of the project boundary: The project boundary is delineated in Figure 3. COD = 65,000 mg/l Q = 780 m 3 /day Figure 3: Delineation of Project Activity The most plausible baseline scenario identified is open anaerobic lagoons which result in baseline methane emissions from wastewater treatment. The baseline scenario is delineated in the figure below.

13 Figure 4: Delineation of Baseline Scenario Table 2: Possible Greenhouse gas produced in the baseline and project activity Baseline Source Gas Inclusion Justification Emissions from the CO 2 No CO 2 emission is not baseline wastewater accounted because this is treatment system. generated from the decomposition of organic matter.. CH 4 Yes CH 4 is the major component in the biogas produced during anaerobic wastewater treatment Emissions from the baseline sludge treatment system. Emissions on account of electricity or fossil fuel used Emissions from the discharge of the effluent into river/lake/sea N 2 O No Excluded for simplification. CO 2 No There is no baseline sludge CH 4 No treatment system which will N 2 O No be affected by the project activity. CO 2 No Baseline emissions from CH 4 No electricity or fossil fuel N 2 O No consumption will not be accounted for because there will be negligible electricity consumption in the baseline scenario. CO 2 No The treated water is used for CH 4 No land application under aerobic N 2 O No condition and there will be no discharge to any river/lake/sea.

14 Project activity Source Gas Inclusion Justification Emissions from electricity CO 2 No The electricity source is from or fuel consumption in the biomass and/or biogas based project activity captive power plant in the palm oil mill. For ex-ante estimation, this emission is assumed zero. Emissions from wastewater treatment system affected by the project activity and not equipped with biogas recovery Emissions from sludge treatment system affected by the project activity and not equipped with biogas recovery Emissions from the discharge of the effluent into river/lake/sea Emissions from biogas release in capture system Emissions due to incomplete flaring of biogas However, for ex-post estimation, this emission will be included in the case when back-up generator is used. CH 4 No Excluded for simplification. N 2 O No Excluded for simplification. CO 2 No There is no component of the CH 4 No wastewater treatment system N 2 O No affected by the project activity which is not equipped with biogas recovery system. CO 2 No There is no provision for CH 4 No sludge treatment system in the N 2 O No project activity. CO 2 No The wastewater will be used CH 4 No for land application under N 2 O No aerobic condition and will not be discharged to any river/lake/sea. CO 2 No CO 2 emission from biogas release is not accounted. CH 4 Yes CH 4 is the major component in any fugitive biogas not captured by the capture system. N 2 O No Excluded for simplification. CO 2 No It is assumed that CO 2 emissions from recovered biogas do not lead to changes of carbon pools in the LULUCF sector. CH 4 Yes Emission source due to incomplete flaring of biogas. For ex-ante estimation, this emission is assumed zero since flaring system will operate only in emergency (i.e. during maintenance or shutdown of the boiler). However, for ex-post estimation, this emission will be accounted whenever

15 Source Gas Inclusion Justification flaring system is used. N 2 O No Excluded for simplification. Emissions from biomass stored under anaerobic conditions CO 2 No No biomass will be stored CH 4 No under anaerobic conditions in N 2 O No the project activity. B.4. Description of baseline and its development: In accordance with General Guidelines to SSC CDM methodologies (Version 17), the PP has used the following steps for identifying the most plausible baseline scenario for the proposed Greenfield project activity. Step 1: Identification of alternative scenarios In this step, various alternatives available to the PP that deliver comparable level of service including the proposed project activity undertaken without being registered as a CDM project activity are identified. The comparable level of service here is defined as 85% COD removal efficiency as per specification of the technology (i.e. anaerobic digester in the CDM project activity). Alternative 1 Table 3: Alternative Scenarios for Baseline Identification No Alternative Comparability Check Installation of open anaerobic lagoons for wastewater treatment without methane recovery The use of anaerobic lagoons for treating POME has been adopted in most of the palm oil mills and can generally achieve COD removal efficiency of more than 85%. Alternative 2 Alternative 3 Alternative 4 Alternative 5 Alternative 6 Installation of anaerobic lagoons with sealed covers for wastewater treatment Use of series of aerobic lagoons for wastewater treatment Use of aerobic wastewater treatment using activated sludge Anaerobic digester without methane recovery Anaerobic digester with methane recovery but not registered as CDM project The use of anaerobic lagoons with sealed covers has been implemented previously in the region and, similar to Scenario 1, can achieve COD removal efficiency of more than 85%. This option is not a feasible alternative for POME s organic-loading is too high for direct aerobic treatment 6. Under optimal controlled conditions, the activated sludge system is able to achieve COD removal efficiency of 89% 7. The anaerobic digester tanks can generally achieve COD removal efficiency of 83-95% 8. Similar to Alternative 5, the anaerobic digester tanks can generally achieve COD removal efficiency of 83-95%. 6 Schuchardt F. et al. (2007). Effect of new palm oil processes on the EFB and POME utilisation. Proceedings of Chemistry and Technology Conference PIPOC, pg Wu T.Y., Mohammad A.W. (2010) Pollution control technologies for the treatment of palm oil mill effluent (POME) through end-of-pipe processes, Journal of Environment Management, Table 6, pg Wu T.Y., Mohammad A.W. (2010) Pollution control technologies for the treatment of palm oil mill effluent (POME) through end-of-pipe processes, Journal of Environment Management, Table 7, pg 1474.

16 Through evaluation of the possible alternatives in this step, it is shown that the use of aerobic treatment alone (i.e. series of aerobic ponds) is not feasible due to high organic load content of POME. Therefore, Alternative 3 is eliminated. Alternatives 1, 2, 4, 5 and 6 are further analysed in Step 2. Step 2: Elimination of alternatives which are non-compliant to applicable laws and regulations Alternatives 1, 2, 4, 5 and 6 are in compliance with current laws and regulations in Indonesia. The discharge of industrial wastewater in Indonesia is regulated by the Ministry of Environment under MenLH Decree 51/1995, Attachment B.IV (Palm Oil Industry) 9. According to this regulation, the COD of wastewater shall not exceed 350 mg/l and the 5-day BOD (BOD 5 ) shall not exceed 100 mg/l (refer to Table 4). There is no other regulatory requirement for the implementation of a specific wastewater treatment technology, such as an anaerobic digester or aerobic treatment system, at palm oil mills. Table 4: Effluent Discharge Standard for Palm Oil Industry 10 Parameter Maximum Permitted Level (mg/l) BOD COD 350 TSS 250 Oil and Fat 25 ph The remaining alternatives, with alternative 1, 2, 5, and 6 coupled with the downstream aerobic treatment system, are able to meet the regulated standard and hence are not excluded in this step. Step 3: Elimination of alternatives that face prohibitive barriers In this step, all the remaining alternatives will be assessed against one or more of the following barriers: investment barrier, technological barrier, and other barrier. A summary of the barrier analysis using investment, technological and other barrier is presented in Table 5 below. 9 MenLH Decree 51/1995, Attachment B.IV (Palm Oil Industry), 10 MenLH Decree 51/1995, Attachment B.IV (Palm Oil Industry),

17 Table 5: Summary of Barrier Analysis in POME Treatment Barrier Investment Barrier Alternative 1 - Installation of open anaerobic lagoons for wastewater treatment without methane recovery Construction of anaerobic open lagoons requires low capital cost. Likewise, the operation and maintenance cost are low as the energy required for operation is minimal 11. Anaerobic treatment in open lagoons will be regarded as the most financially viable. Alternative 2 - Installation of anaerobic lagoons with sealed covers for wastewater treatment Additional cost needs to be incurred by the project owner to cover the lagoons. The operational cost of operating covered lagoons will be much higher compared to operating open lagoons. In addition, several projects in relation to methane recovery from covered lagoons have been registered as CDM projects in the country thus demonstrating that this alternative already faces significant barriers compared to the most prevalent practice of treating wastewater in anaerobic open lagoons. Alternative 4- Use of aerobic wastewater treatment using activated sludge Operation of aerobic digester (i.e. activated sludge system) will not generate any revenue to the company. It involves higher capital cost and operational cost compared to the conventional anaerobic lagoon system. The aeration system in the aerobic digestion is very energy intensive. Lack of incentive together with the financial costs incurred is a prohibitive barrier for this option. Therefore, it will be unlikely for the project owner to select this alternative. Alternative 5 - Anaerobic digester without methane recovery Operation of anaerobic digester will not generate any revenue to the company. It involves higher capital cost and operational cost compared to the conventional anaerobic lagoon system. Lack of incentive together with the financial costs incurred is a prohibitive barrier for this alternative. Therefore, it will be unlikely for the project owner to select this alternative. Alternative 6 - Anaerobic digester with methane recovery but not registered as CDM project The investment barriers applicable to Alternative 5 (i.e. anaerobic digester without methane recovery) will be also applicable here. In addition, installation of methane recovery will further increase the cost. Due to high initial cash outlay, it is unlikely that the project owner will select this option. 11 Wu T.Y., Mohammad A.W. (2010) Pollution control technologies for the treatment of palm oil mill effluent (POME) through end of pipe process, Journal of Environmental Management, No 91, pg

18 Barrier Technological Barrier Alternative 1 - Installation of open anaerobic lagoons for wastewater treatment without methane recovery The ponding system technology is reliable and stable 12. Therefore, it is easier to manage and involves lower risks compared to the project activity. It does not face prohibitive technical barriers. It is observed that has the capacity to tolerate wider range of Organic Loading Rate (OLR) 13. Alternative 2 - Installation of anaerobic lagoons with sealed covers for wastewater treatment The installation of cover on anaerobic lagoons will carry potential technological difficulties. The PP runs the risk whether the cover has been implemented effectively and whether any potential biogas leakages are occurring. The biogas collecting cover system is subject to wear and tear due to: - Chemical corrosion (due to H 2 S presence in the biogas); - Mechanical fatigue (the cover expands and contracts continuously); - UV light aggression Alternative 4- Use of aerobic wastewater treatment using activated sludge Many problems can develop in activated sludge operation that adversely affects the effluent quality with origins in engineering, hydraulic and microbiological components of the process. The various microbiological problems that can occur in activated sludge operation include nonsettle able growth, pin floc problem, zoogloeal bulking and foaming, polysaccharide bulking and foaming 14. In addition, in order to operate under optimum condition, the dissolved oxygen (DO) level in Alternative 5 - Anaerobic digester without methane recovery The organic content of POME will be digested anaerobically by the microorganisms inside the digester. The process is a series of complex biological process such as hydrolysis, acidogenesis, acetogenesis, and methanogenesis, producing biogas by the end of the process 15. Each step involves a specific type of bacteria, of which growth and activity are affected by different variables (e.g. temperature, ph, retention time, etc). Particularly, the growth and activity of bacteria involved in methanogenesis process is affected by the organic loading rate and hydraulic retention time which varies Alternative 6 - Anaerobic digester with methane recovery but not registered as CDM project All the discussion of technological barriers under Alternative 5 (i.e. anaerobic digester without methane recovery) will be as well applicable here. Addition of methane recovery will increase the need of operation and maintenance procedures for the plant. There will be additional manpower required to operate and maintain the system as compared to the anaerobic lagoons. This team will need to be equipped with the necessary skills and expertise to ensure smooth operation. 12 Wu T.Y., Mohammad A.W. (2010) Pollution control technologies for the treatment of palm oil mill effluent (POME) through end of pipe process, Journal of Environmental Management, No 91, pg Poh P.E., Chong M.F. (2009) Development of anaerobic digestion methods for palm oil mill effluent (POME) treatment, Bioresource Technology 100, pg Activated Sludge Microbiology Problems and Their Control, page Information Sheet on Anaerobic Digestion, pg 4.

19 Barrier Alternative 1 - Installation of open anaerobic lagoons for wastewater treatment without methane recovery Alternative 2 - Installation of anaerobic lagoons with sealed covers for wastewater treatment - Other extreme weather conditions (e.g. high temperature, lightning, monsoon damage etc.); - Excessive pressure or stress (e.g. during peak production periods); and - Accidental damage and risk from fire / explosion. Alternative 4- Use of aerobic wastewater treatment using activated sludge the aerobic activated sludge system has to be maintained continuously. Therefore higher level of expertise will be called upon by the project owner to operate these systems in an efficient manner. Alternative 5 - Anaerobic digester without methane recovery daily subject to the chemical properties of POME and the volume discharged to the treatment system 16. Due to the complex association of different types of bacteria, digesters have a higher risk of breakdown and may be difficult to control 17. Often, problems are difficult to diagnose as there are several parameters involved. Readjusting the equilibrium of these parameters could take significant time. Thus, it requires a high level of expertise to operate the digester effectively and also constant monitoring will be required to ensure the balance of the system. Alternative 6 - Anaerobic digester with methane recovery but not registered as CDM project In addition, there will be also a need for precautionary measures for handling biogas (i.e. methane). The biogas is highly explosive and flammable, therefore, gas storage and piping system must be constructed in strict accordance to best engineering practice in order to avoid leakages. Hydrogen sulphide (H 2 S) gas which is present in the biogas imposes some risks as this H 2 S gas could accumulate in bottom tanks and is harmful in high concentration Yacob S. et al. (2006). Baseline study of methane emissions from anaerobic ponds of palm oil mill treatment, Science of the Total Environment, No. 366, pg Information Sheet on Anaerobic Digestion, pg Section Safety Anaerobic Digesters,

20 Barrier Other barrier: Lack of prevailing regulatory requirement Summary of barrier analysis Alternative 1 - Installation of open anaerobic lagoons for wastewater treatment without methane recovery Alternative 2 - Installation of anaerobic lagoons with sealed covers for wastewater treatment Alternative 4- Use of aerobic wastewater treatment using activated sludge Alternative 5 - Anaerobic digester without methane recovery Alternative 6 - Anaerobic digester with methane recovery but not registered as CDM project In Indonesia, the quality of the wastewater discharged from palm oil mill is regulated by the Decree of Ministry of Environment 51/1995. This regulates the maximum allowable concentration of COD and BOD in the discharged effluent. However, there is no regulation on how to treat the effluent. Therefore, it is most unlikely that the project owner will invest in technologies which entail higher investments and/or technical barriers. The following technologies have been predominantly used in the region (i.e. Indonesia) is Alternative 1, which is installation of anaerobic lagoons for wastewater treatment 19. This alternative is the most plausible baseline scenario as the investment and technological barriers faced are minimal. The capital cost and the operational cost incurred for implementing and operating covered lagoons is higher compared to open lagoons. Lack of incentive with high capital cost and high level of anticipated technological risks prohibit project owner to select this alternative. This scenario is not a plausible scenario for the PP. Lack of incentive with high capital cost and high level of anticipated technological risks prohibit project owner to select this alternative. This scenario is not a plausible scenario for the PP. This scenario is not a plausible scenario for the PP due to lack of incentive and high level of anticipated technological risks. In addition, the absence of policy encouraging methane recovery technology will prevent project owner from selecting this alternative. 19 The list of project activities (registered or under validation) in the region with the information of their baseline POME treatment technology is provided in Annex 3 of this PDD.

21 This step has shown that Alternative 1 needs the least investment and faces minimum technological barriers in comparison with the others. On the other hand, Alternatives 2, 4, 5 and 6 face prohibitive barriers due to higher capital and operational cost requirement as well as technological risks introduced. The outcome of this step is elimination of Alternatives 2, 4, 5 and 6. Only Alternative 1 remains. Step 4: Comparison of baseline emission of remaining alternatives The plausible baseline is, therefore, Installation of open anaerobic lagoons for wastewater treatment without methane recovery. B.5. Description of how the anthropogenic emissions of GHG by sources are reduced below those that would have occurred in the absence of the registered small-scale CDM project activity: Table 6: CDM consideration for Project Implementation Date Activities 9 February 2011 The Board of Directors decided to install anaerobic digester with biogas recovery after due consideration of CDM revenue potentials from the project activity. 10 February 2011 Signing of the main equipment/contractor contract to implement the project activity. 21 February 2011 Prior consideration submitted to the UNFCCC and the host country DNA. 5 May 2011 Conducting local stakeholders meeting. Demonstration of additionality The additionality of this project activity is demonstrated through the following barrier analyses. Investment barrier As demonstrated in Section B.4. of this PDD, the most plausible baseline scenario in the absence of this project activity would have been the implementation of a series of open anaerobic lagoons without methane recovery. Operation of open lagoons is the most economical as it requires minimum human intervention and energy consumption for their operations 20 and is the most prevalent method for treating wastewater in palm oil mills in Indonesia. On the other hand, in the project scenario, substantial capital investment will be incurred in the construction of new anaerobic digester (i.e. project activity) system with biogas recovery. Both the baseline scenario (i.e. open anaerobic lagoons without methane recovery) and project activity (i.e. anaerobic digester system with biogas recovery) do not generate any revenues to meet operational expenses. However, the baseline scenario is cheaper than the project activity. Hence, as compared to the 20 Wu T.Y., Mohammad A.W. (2010) Pollution control technologies for the treatment of palm oil mill effluent (POME) through end-of-pipe processes, Journal of Environment Management, Table 6, pg

22 baseline scenario, the project activity faces significantly large financial barrier as it involves higher capital and operational costs. Without CERs revenues, in the absence of the CDM project activity, there is no incentive for the PP to invest in such capital intensive project. The PP would have implemented the most financially viable technology, which is the series of open anaerobic lagoons without methane recovery. The registration of the project activity as a CDM project will provide the PP with additional revenue from sales of CERs which will alleviate the financial burden of the project and therefore, the PP will be more willing to invest in such project. Technological barrier It is expected that the PP will also face several technological barriers in the implementation and operation of the proposed reactor system. i. Performance risk Operation of anaerobic reactor requires high level of maintenance and its performance carries some risks. The performance of anaerobic digester is sensitive as it is a complex biological process involving different types of bacteria 21. The growth and activity of these bacteria are affected by different variables (e.g. temperature, ph-value, retention time, COD load of wastewater etc). Based on the study Baseline study of methane emissions from anaerobic ponds of palm oil mill treatment 22 it is shown that daily variation in chemical properties and discharged volume of POME will affect the methanogenesis process. Several control loops are required to keep the digester parameters within appropriate levels. All the parameters have to be balanced to provide best conditions for the bacteria. Improper operation of the digester or incorrect application of chemical substances would harm the microorganisms and lead to the collapse of the reactor system. Poor performance of the digester adversely affects the quantity and the methane content of the biogas which may eventually impact the quantity of emission reductions that may be generated from the project. In addition, there will be also a need for precautionary measures for handling biogas (i.e. methane) which is highly explosive and flammable. Gas storage and piping system must be constructed in accordance with standard engineering practice in order to avoid leakages. There is also a risk from hydrogen sulphide (H 2 S) gas which is present in the biogas. This H 2 S gas could accumulate in bottom tanks and is harmful in high concentration 23. In order to ensure smooth operation while preventing undue safety hazards, well trained and technically skilled manpower is required. In contrast, the risks associated in the open lagoons are considered very low due to simplicity and robustness of their operation principles. Operation and maintenance required is minimal given that the system is not automated. ii. Need for more manpower Unlike the anaerobic lagoons, the project system (i.e. anaerobic digester with methane recovery) requires higher level of maintenance in the operation of the reactor. There will be a need for more 21 Information Sheet on Anaerobic Digestion Yacob, S. et al. (2006). Baseline study of methane emissions from anaerobic ponds of palm oil mill treatment, Science of the Total Environment, No. 366, pg Section Safety Anaerobic Digesters, 22

23 technicians in the operation of proposed project activity (as compared to the most plausible baseline scenario (i.e. anaerobic lagoons). Furthermore, the staffs have to be trained to be qualified to ensure an appropriate handling of the anaerobic treatment system to manage the complicated biological, hydraulic processes and the precautionary measures for handling biogas. This team of staffs need to be able to provide timely assistance in the case of breakdown/unstable operations etc. Since the proposed reactor is not one of the most common wastewater treatment technologies in the region and the local operators are more used to the operation of conventional anaerobic open ponds system, the PP will face some barriers in the implementation of the project activity. Other barrier: Lack of prevailing regulatory requirement In Indonesia, the quality of POME discharged from palm oil mill is regulated by the Decree of Ministry of Environment 51/1995. It regulates the allowable concentration of pollutants both organic and nonorganic in the discharged wastewater from palm oil industry. Even though the quality of discharged wastewater from palm oil mill is regulated, there is no specific regulation on the technology to be used for wastewater treatment and for recovery of methane from the wastewater system. Therefore, it is most unlikely that the palm oil mill owners in the region will make large investments to implement technologies with methane recovery. Instead, using open lagoons with no methane recovery serves as an easier and lower cost option for them 24. However, such an alternative will result in higher GHG emissions into the environment. How CDM revenue alleviate the barriers to the project implementation The approval and registration of the project activity will alleviate the above three identified barriers and enable the project activity to be undertaken and contribute to emission reductions. CER revenues will provide the necessary financial incentive to the PP to implement such high-investment project activity and move away from the easier alternatives such as open lagoons system. The CDM revenue will provide a source of income for the project owner which will recover the capital cost for the project technology as well as the operation and maintenance cost. The expected additional CERs revenue will also mitigate the risk associated with the technological difficulties in the implementation of the project. Furthermore, the CERs revenue will help the PP in seeking and training the required manpower. B.6. Emission reductions: B.6.1. Explanation of methodological choices: Baseline emission As explained in Section B.4, the most plausible baseline scenario for the project is anaerobic lagoons without methane recovery. As per Paragraph 18 of AMS-III.H (Version 16), baseline emissions are calculated as follows: 24 Expanded Market Study for Indonesia Sustainable Energy Finance, Renewable Energy Opportunities in Palm Oil Mills in Kalimantan and Sumatra, IFC. ded+market+study+for+sustainable+energy+finance.pdf 23

24 BE y = {BE power,y + BE ww,treatment,y + BE s,treatment,y + BE ww,discharge,y + BE s,final,y } Table 7: Summary of Baseline Emissions No. Emissions Description Remarks 1 BE power,y Emissions on account of electricity or fossil fuel used 2 BE ww,treatment,y Methane emissions from baseline wastewater treatment systems Not applicable. Baseline emissions from electricity consumption will not be accounted for project because there is negligible electricity consumption in the baseline scenario. Applicable. Methane is the major component in the biogas produced during anaerobic wastewater treatment. 3 BE s,treatment,y Methane emissions from baseline sludge treatment system. Not applicable. There is no baseline sludge treatment systems affected by the project activity. 4 BE ww,discharge,y Methane emissions on account of inefficiencies in the baseline wastewater treatment systems and presence of biodegradable organic carbon in untreated wastewater discharged to sea / river / lake 5 BE s,final,y Methane emissions from the decay of the final sludge generated by baseline treatment system Not applicable. Treated wastewater is put to land application under aerobic conditions and there is no discharge to the river/lake/sea. Not applicable. Under the most plausible baseline scenario, sludge is used for land application under aerobic condition. Therefore, the baseline emission is simplified as follow: BE y = BE ww,treatment,y BE ww,treatment,y = (Q ww,i,y * COD untreated,i,y * η COD,BL,I * MCF ww,treatment,bl,i ) * B o,ww * UF BL * GWP CH4 Where: Q ww,i,y Volume of wastewater treated in baseline wastewater treatment system i in year y which is affected by the project activity (m 3 /year) COD untreated,i,y Chemical Oxygen Demand of the wastewater inflow to the baseline treatment system i in year y (tonnes/m 3 ) η COD,BL,i COD removal efficiency of the baseline treatment system i, determined as per the paragraphs 26, 27 or 28 of AMS-III.H version 16 MCF ww,treatment,bl,i Methane correction factor for the baseline wastewater treatment system i (MCF value is obtained from Table III.H.1 in AMS-III.H version 16) Methane producing capacity of the wastewater (kg CH 4 /kg COD) B o,ww 24

ID08-WWP-10, METHANE RECOVERY IN WASTEWATER TREATMENT WEST SUMATERA, INDONESIA

ID08-WWP-10, METHANE RECOVERY IN WASTEWATER TREATMENT WEST SUMATERA, INDONESIA ID08-WWP-10, METHANE RECOVERY IN WASTEWATER TREATMENT WEST SUMATERA, INDONESIA UNFCCC Clean Development Mechanism Simplified Project Design Document for Small Scale Projects DOCUMENT ID: ID08-WWP-10 VER

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS.

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS. CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS A. General description of the small scale project activity B. Application

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS A. General description of the small scale project activity B. Application

More information

Annex 27 GENERAL GUIDELINES FOR SSC CDM METHODOLOGIES. (Version 19.0) CONTENTS

Annex 27 GENERAL GUIDELINES FOR SSC CDM METHODOLOGIES. (Version 19.0) CONTENTS Page 1 GENERAL GUIDELINES FOR SSC CDM METHODOLOGIES (Version 19.0) CONTENTS Paragraphs I. Introduction... 1 3 2 A. Background... 1 2 2 B. Objectives... 3 2 II. Scope and applicability... 4 5 2 III. Terms

More information

Large-scale Consolidated Methodology Waste energy recovery

Large-scale Consolidated Methodology Waste energy recovery CLEAN DEVELOPMENT MECHANISM ACM0012 Large-scale Consolidated Methodology Waste energy recovery TABLE OF CONTENTS Page 1. INTRODUCTION... 4 2. SCOPE, APPLICABILITY, AND ENTRY INTO FORCE... 4 2.1. Scope...

More information

POME Treatment Co-benefits CDM, Malaysia Summary of the Study March, 2008 Pacific Consultants

POME Treatment Co-benefits CDM, Malaysia Summary of the Study March, 2008 Pacific Consultants POME Treatment Co-benefits CDM, Malaysia Summary of the Study March, 2008 Pacific Consultants 1. Project Information 1-1 Background Information Current feasibility study aims at the evaluation of feasibility

More information

CDM Module 1. Introduction to Programmatic CDM (PoA) Lesson 2. How does the Programmatic CDM Work? Select Next to begin. Menu November 2011.

CDM Module 1. Introduction to Programmatic CDM (PoA) Lesson 2. How does the Programmatic CDM Work? Select Next to begin. Menu November 2011. CDM Module 1 Introduction to Programmatic CDM (PoA) Lesson 2 How does the Programmatic CDM Work? November 2011 Select Next to begin Next> Lesson Partners and Collaborators How does the Programmatic CDM

More information

GUIDELINES FOR COMPLETING THE FORM FOR SUBMISSION OF BUNDLED SMALL-SCALE CDM PROJECT ACTIVITIES (F-CDM-SSC-BUNDLE) (Version 01) CONTENTS

GUIDELINES FOR COMPLETING THE FORM FOR SUBMISSION OF BUNDLED SMALL-SCALE CDM PROJECT ACTIVITIES (F-CDM-SSC-BUNDLE) (Version 01) CONTENTS GUIDELINES FOR COMPLETING THE FORM FOR SUBMISSION OF BUNDLED SMALL-SCALE CDM PROJECT ACTIVITIES (F-CDM-SSC-BUNDLE) (Version 01) CONTENTS I. Information note on bundling of Small-Scale project activities

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS A. General description of the small scale project activity B. Application

More information

VALIDATION REPORT. Univanich TOPI Biogas Project. Univanich Palm Oil Public Company Limited.

VALIDATION REPORT. Univanich TOPI Biogas Project. Univanich Palm Oil Public Company Limited. UK AR6 CDM Small Scale Validation Report Issue 1 Small Scale (VVM Version 1) VALIDATION REPORT Univanich Palm Oil Public Company Limited. Univanich TOPI Biogas Project SGS Climate Change Programme SGS

More information

CLEAN DEVELOPMENT MECHANISM SMALL-SCALE PROGRAMME OF ACTIVITIES DESIGN DOCUMENT FORM (CDM-SSC-PoA-DD) Version 01 CONTENTS

CLEAN DEVELOPMENT MECHANISM SMALL-SCALE PROGRAMME OF ACTIVITIES DESIGN DOCUMENT FORM (CDM-SSC-PoA-DD) Version 01 CONTENTS CDM Executive Board page 1 CLEAN DEVELOPMENT MECHANISM SMALL-SCALE PROGRAMME OF ACTIVITIES DESIGN DOCUMENT FORM (CDM-SSC-PoA-DD) Version 01 CONTENTS A. General description of small-scale programme of activities

More information

PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03

PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) - Version 03 CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS A. General description of the small scale project activity B. Application

More information

UNIVANICH LAMTHAP POME BIOGAS PROJECT THAILAND

UNIVANICH LAMTHAP POME BIOGAS PROJECT THAILAND UNIVANICH LAMTHAP POME BIOGAS PROJECT THAILAND Prepared by Carbon Bridge Pte Ltd page 1 CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS

More information

Project Idea Note (PIN)

Project Idea Note (PIN) (PIN) Description of size and quality expected of a PIN Basically a PIN will consist of approximately 5-10 pages providing indicative information on: A. Project participants B. Project description, type,

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS.

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS. CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS A. General description of the small scale project activity B. Application

More information

Martin-Luther King Strasse Bonn Germany 29th Nov 2007

Martin-Luther King Strasse Bonn Germany 29th Nov 2007 ~. BICX UNFCCC Secretariat Martin-Luther King Strasse 8 0-53153 Bonn Germany 29th Nov 2007 Aftn: CDM Executive Board Oear Members of the COM Executive Board, Re: Response to Request for Review for "Tradewinds

More information

Quantification Protocol for Aerobic Composting

Quantification Protocol for Aerobic Composting Quantification Protocol for Aerobic Composting Specified Gas Emitters Regulation Version 2.0 January 2017 Title: Quantification Protocol for Aerobic Composting Number: 2.0 Program Name: Alberta Carbon

More information

Case Study: Biogas generation from

Case Study: Biogas generation from Case Study: Biogas generation from food waste in Bangkok Outline: Introduction Overview of the PoA Schools show case Introduction >> Current situation Bangkok Metropolitan has more than 10 million of population

More information

Small-Scale CDM & Bundling: Criteria, Advantages & Status

Small-Scale CDM & Bundling: Criteria, Advantages & Status Small-Scale CDM & Bundling: Criteria, Advantages & Status Need for Small-Scale CDM introduced by CDM EB to encourage the development of smaller CDM projects typically would have been less attractive in

More information

Validation Report. Matrix Power Pvt. Ltd. (MPPL)

Validation Report. Matrix Power Pvt. Ltd. (MPPL) Validation Report Matrix Power Pvt. Ltd. (MPPL) Validation of the 4.5 MW Biomass (Agricultural Residues) Based Power Generation Unit of M/s Matrix Power Pvt. Ltd. (MPPL) project Report No. 6589 Revision

More information

CLEAN DEVELOPMENT MECHANISM SMALL-SCALE PROGRAM ACTIVITY DESIGN DOCUMENT FORM (CDM-SSC-CPA-DD) Version 01 CONTENTS

CLEAN DEVELOPMENT MECHANISM SMALL-SCALE PROGRAM ACTIVITY DESIGN DOCUMENT FORM (CDM-SSC-CPA-DD) Version 01 CONTENTS CDM Executive Board page 1 CLEAN DEVELOPMENT MECHANISM SMALL-SCALE PROGRAM ACTIVITY DESIGN DOCUMENT FORM (CDM-SSC-CPA-DD) Version 01 CONTENTS A. General description of CDM programme activity (CPA) B. Eligibility

More information

Waste to Energy. Biogas Production Utilizing Palm Oil Mill Effluent (POME) in Indonesia

Waste to Energy. Biogas Production Utilizing Palm Oil Mill Effluent (POME) in Indonesia Waste to Energy Biogas Production Utilizing Palm Oil Mill Effluent (POME) in Indonesia Background Sundar Bajgain Senior Advisor, SNV Palm oil mills are one of the most important agro-industries in Indonesia

More information

Validation Report. Kalpataru Energy Venture Pvt. Ltd. Validation of the Biomass Power Project at Kalpataru Energy Venture Private Limited

Validation Report. Kalpataru Energy Venture Pvt. Ltd. Validation of the Biomass Power Project at Kalpataru Energy Venture Private Limited Validation Report Kalpataru Energy Venture Pvt. Ltd. Validation of the Biomass Power Project at Kalpataru Energy Venture Private Limited Report No. 806970, Revision 01 2006, April 12 TÜV ndustrie Service

More information

Anaerobic Degradation of Organics

Anaerobic Degradation of Organics Anaerobic Degradation of Organics Nur Hidayat Anaerobic sludge treatment methane production Anaerobic wastewater treatment - Anaerobic wastewater treatment Sedimentasi floc-forming bacteria dan recycling

More information

UNOSD Expert Group Meeting Sustainable Application of Waste-to-Energy in Malaysia. Mohd Ali Hassan

UNOSD Expert Group Meeting Sustainable Application of Waste-to-Energy in Malaysia. Mohd Ali Hassan UNOSD Expert Group Meeting Sustainable Application of Waste-to-Energy in Malaysia Mohd Ali Hassan Faculty of Biotechnology and Biomolecular Sciences, Universiti Putra Malaysia 43400 UPM Serdang Selangor

More information

Analysis and Evaluation of CDM Potential of Biomethanation Sector in India

Analysis and Evaluation of CDM Potential of Biomethanation Sector in India Analysis and Evaluation of CDM Potential of Biomethanation Sector in India Srikanth Subbarao 1,* and Butchaiah Gadde 2 1 Energy Engineer, IT Power India Pvt. Ltd, # 6 & 8, Romain Rolland Street, Pondicherry

More information

Methodological tool Emissions from solid waste disposal sites

Methodological tool Emissions from solid waste disposal sites CLEAN DEVELOPMENT MECHANISM TOOL04 Methodological tool Emissions from solid waste disposal sites TABLE OF CONTENTS Page 1. INTRODUCTION... 3 1.1. Background... 3 2. SCOPE, APPLICABILITY, AND ENTRY INTO

More information

(c) Tertiary Further treatment may be used to remove more organic matter and/or disinfect the water.

(c) Tertiary Further treatment may be used to remove more organic matter and/or disinfect the water. ENERGY FROM SEWAGE Introduction - Sewage treatment, that is, the physical, chemical and biological processes used to clean industrial and domestic wastewater, has improved significantly over the past 20

More information

PART I. Programme of activities (PoA)

PART I. Programme of activities (PoA) F-CDM-PoA-DD Programme design document form for CDM programmes of activities (Version 03.0) PART I. Programme of activities (PoA) SECTION A. General description of PoA A.1. Title of the PoA A.2. Purpose

More information

Gold Standard Passport CONTENTS

Gold Standard Passport CONTENTS Gold Standard Passport CONTENTS A. Project title B. Project description C. Proof of project eligibility D. Unique Project Identification E. Outcome stakeholder consultation process F. Outcome sustainability

More information

Optimization of Anaerobic Digestion with Bio- Organic Catalyst Compositions (BOCs)

Optimization of Anaerobic Digestion with Bio- Organic Catalyst Compositions (BOCs) CASE STUDY bio-organic.com Optimization of Anaerobic Digestion with Bio- Organic Catalyst Compositions (BOCs) 14th Annual European Biosolids and Organic Resources Conference and Exhibition - November 2009

More information

Developing the complete PDD: Using Ob/Ob project as a case study

Developing the complete PDD: Using Ob/Ob project as a case study Developing the complete PDD: Using Ob/Ob project as a case study Craig Ebert Executive Vice President ICF Consulting 3rd Stakeholders Workshop Lagos, Nigeria 4 May 2006 Contents Project description Assessment

More information

The Energy and Carbon Footprint of Water Reclamation and Water Management in Greater Chicago

The Energy and Carbon Footprint of Water Reclamation and Water Management in Greater Chicago METROPOLITAN WATER RECLAMATION DISTRICT OF GREATER CHICAGO The Energy and Carbon Footprint of Water Reclamation and Water Management in Greater Chicago Joseph Kozak, PhD, PE Catherine O Connor, O PhD,

More information

Treatment of palm oil mill effluent using biological sequencing batch reactor system

Treatment of palm oil mill effluent using biological sequencing batch reactor system River Basin Management IV 511 Treatment of palm oil mill effluent using biological sequencing batch reactor system C. W. Fun, M. R. U. Haq & S. R. M. Kutty Department of Civil Engineering, Universiti Teknologi

More information

Accounting standards for methane emissions: taking stock of existing offset programs

Accounting standards for methane emissions: taking stock of existing offset programs Accounting standards for methane emissions: taking stock of existing offset programs Methane finance study group meeting Washington, DC February 7, 2013 Today s main focus Critical features for delivering

More information

CDM Guide Book for Oil & Gas Sector. Ariesta Ningrum GGFR Workshop September 19-20, 2006 Jakarta - Indonesia

CDM Guide Book for Oil & Gas Sector. Ariesta Ningrum GGFR Workshop September 19-20, 2006 Jakarta - Indonesia CDM Guide Book for Oil & Gas Sector Ariesta Ningrum GGFR Workshop September 19-20, 2006 Jakarta - Indonesia Background Context Purpose one-stop document for project developers in oil & gas sector Guide

More information

Feasibility study of wastewater treatment with anaerobic digester at starch processing plant in Tay Ninh, Vietnam. Report

Feasibility study of wastewater treatment with anaerobic digester at starch processing plant in Tay Ninh, Vietnam. Report CDM/JI Feasibility Study 2007 Feasibility study of wastewater treatment with anaerobic digester at starch processing plant in Tay Ninh, Vietnam Report Toshiba Corporation March 2008 1. Fundamental subjects

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS page 1 CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS A. General description of project activity B. Application of a baseline and

More information

PROGRAMME OF ACTIVITIES (POA) REQUEST FOR REGISTRATION - INFORMATION AND REPORTING CHECK CHECKLIST

PROGRAMME OF ACTIVITIES (POA) REQUEST FOR REGISTRATION - INFORMATION AND REPORTING CHECK CHECKLIST PROGRAMME OF ACTIVITIES (POA) REQUEST FOR REGISTRATION - INFORMATION AND REPORTING CHECK CHECKLIST PCP : Clean development mechanism project cycle procedure (version 02.0), EB 66, annex 64, 2 March 2012.

More information

Preliminary Assessment of the Opportunity for Methane Recovery from Wastewater at the Frigosinú SA Slaughterhouse, Monteria, Cordoba, Colombia

Preliminary Assessment of the Opportunity for Methane Recovery from Wastewater at the Frigosinú SA Slaughterhouse, Monteria, Cordoba, Colombia Preliminary Assessment of the Opportunity for Methane Recovery from Wastewater at the Frigosinú SA Slaughterhouse, Monteria, Cordoba, Colombia Prepared for: U.S. EPA Methane to Markets Program Prepared

More information

Overview of the CDM in the agriculture sector

Overview of the CDM in the agriculture sector Overview of the CDM in the agriculture sector Grant A. Kirkman Team Leader CDM Methodologies Methane to Markets 30 October 1 November 2007 Beijing China United Nations Framework Convention on Climate Change

More information

ACM0001 Flaring or use of landfill gas

ACM0001 Flaring or use of landfill gas ACM0001 ACM0001 Flaring or use of landfill gas Women and children Capture of landfill gas (LFG) and its flaring and/or use to produce energy and/or use to supply consumers through natural gas distribution

More information

A. General description of the small-scale project activity. C. Duration of the project activity / Crediting period

A. General description of the small-scale project activity. C. Duration of the project activity / Crediting period CDM Executive Board page 1 CLEAN DEVELOPMENT MECHANISM SIMPLIFIED PROJECT DESIGN DOCUMENT FOR SMALL-SCALE PROJECT ACTIVITIES (SSC-CDM-PDD) Version 02 CONTENTS A. General description of the small-scale

More information

A CASE STUDY: ASJA S BELO HORIZONTE CDM PROJECT BRAZIL / KYOTO PROTOCOL

A CASE STUDY: ASJA S BELO HORIZONTE CDM PROJECT BRAZIL / KYOTO PROTOCOL Fordham University School of Law February 22nd, 2010 A CASE STUDY: ASJA S BELO HORIZONTE CDM PROJECT BRAZIL / KYOTO PROTOCOL Agostino Re Rebaudengo President arr@asja.biz INDEX KYOTO PROTOCOL AND EMISSION

More information

Journey Started-Joint Research Collaboration ( Jan 2004-Dec 2006) FPI-UPM-KIT of Japan

Journey Started-Joint Research Collaboration ( Jan 2004-Dec 2006) FPI-UPM-KIT of Japan Journey Started-Joint Research Collaboration ( Jan 2004-Dec 2006) FPI-UPM-KIT of Japan - Scopes of R&D i. Study on biogas production from POME Anaerobic treatment ii. Study on potential downstream of palm

More information

Barriers, Opportunities & Challenges faced by a private sector developer in CDM & JCM schemes

Barriers, Opportunities & Challenges faced by a private sector developer in CDM & JCM schemes For Low CAR Net 6 th Annual Meeting Barriers, Opportunities & Challenges faced by a private sector developer in CDM & JCM schemes Joseph WC Hwang M.Sc., PT Gikoko Kogyo Indonesia 2014 November 1 st Bangkok

More information

final report Water quality improvement strategy for a processing site

final report Water quality improvement strategy for a processing site final report Project title: Water Quality Improvement Strategy Project code: P.PSH.0449 Prepared by: GHD Date published: July 2010 PUBLISHED BY Meat & Livestock Australia Limited Locked Bag 991 NORTH SYDNEY

More information

REVISED ANNEX C GUIDANCE ON PROJECT TYPE ELIGIBILITY

REVISED ANNEX C GUIDANCE ON PROJECT TYPE ELIGIBILITY REVISED ANNEX C GUIDANCE ON PROJECT TYPE ELIGIBILITY Project activities are eligible under Gold Standard as long as they belong to the three categories defined below. Furthermore, specific eligibility

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS. Annexes

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS. Annexes page 1 CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS A. General description of project activity B. Application of a baseline and

More information

CDM Programme of Activities Call for Public Inputs

CDM Programme of Activities Call for Public Inputs CDM Programme of Activities Call for Public Inputs Pty Ltd August, 2008 2 Programmatic CDM The opportunity Cool nrg International welcomes the opportunity to provide input into the call for public comments

More information

Monali Ranade. Financial & Technical solutions for Sustainable cities June 9, 2010

Monali Ranade. Financial & Technical solutions for Sustainable cities June 9, 2010 Monali Ranade Financial & Technical solutions for Sustainable cities June 9, 2010 Role of cities is evolving and responsibilities increasing Municipal government agenda expands as city grows Municipal

More information

ENHANCING THE PERFORMANCE OF OXIDATION DITCHES. Larry W. Moore, Ph.D., P.E., DEE Professor of Environmental Engineering The University of Memphis

ENHANCING THE PERFORMANCE OF OXIDATION DITCHES. Larry W. Moore, Ph.D., P.E., DEE Professor of Environmental Engineering The University of Memphis ENHANCING THE PERFORMANCE OF OXIDATION DITCHES Larry W. Moore, Ph.D., P.E., DEE Professor of Environmental Engineering The University of Memphis ABSTRACT Oxidation ditches are very popular wastewater treatment

More information

Yes, is attached. Yes, is attached.

Yes, is attached. Yes, is attached. CDM: Form for submission of requests for revisions of approved methodologies to the Methodologies Panel (version 01) (To be used by project participants, through the DOE/AE, for requesting revisions of

More information

Piggery Digester Systems

Piggery Digester Systems World Leading Technology From New Zealand Odour Reduction Green Energy Improved Effluent Quality Carbon Credits Waste Solutions Ltd. Business Support Division 1st Floor, John Wickliffe House 265-269 Princes

More information

The Project Design Document

The Project Design Document Downloaded from orbit.dtu.dk on: Feb 11, 2018 The Project Design Document Olsen, Karen Holm Publication date: 2012 Link back to DTU Orbit Citation (APA): Olsen, K. H. (2012). The Project Design Document

More information

I. SOURCE AND APPLICABILITY Sources This consolidated methodology is based on elements from the following methodologies:

I. SOURCE AND APPLICABILITY Sources This consolidated methodology is based on elements from the following methodologies: Draft revision to the approved consolidated baseline and monitoring methodolog ACM0006 Consolidated methodolog for electricit generation from biomass residues in power and heat plants I. SOURCE AND APPLICABILITY

More information

Economic Models for Environmental Sustainability Anaerobic Digesters and a Complimentary Energy Decision Support Tool.

Economic Models for Environmental Sustainability Anaerobic Digesters and a Complimentary Energy Decision Support Tool. Economic Models for Environmental Sustainability Anaerobic Digesters and a Complimentary Energy Decision Support Tool By: Rob Anderson Anaerobic Digestion Anaerobic digestion uses anaerobic bacteria to

More information

Organica is a registered trademark of the Keter Group Energy Division.

Organica is a registered trademark of the Keter Group Energy Division. Organica is a registered trademark of the Keter Group Energy Division. Every Day is Earth Day. 04 05 Without energy there is no life... but today s growing use of energy represents the greatest threat

More information

VALIDATION REPORT. Ratchaburi Farms Biogas Project at SPM Farm in Thailand REPORT NO REVISION NO. 01

VALIDATION REPORT. Ratchaburi Farms Biogas Project at SPM Farm in Thailand REPORT NO REVISION NO. 01 VALIDATION REPORT Ratchaburi Farms Biogas Project at SPM Farm in Thailand REPORT NO. 2007-2047 REVISION NO. 01 VALIDATION REPORT Date of first issue: Project No.: 13 December 2007 44410160 Approved by:

More information

Biogas Asia Pacific 2014

Biogas Asia Pacific 2014 Biogas Asia Pacific 2014 Evolving Into ASEAN Biogas Market - A story by A Bionexus Status Renewable Energy Company Jesse Wong 2 4 June 2014, JW Marriot Hotel, Kuala Lumpur KONZEN CLEAN ENERGY SDN BHD Introduction

More information

Clean Development Mechanism (CDM) Registration for the Gianyar Waste Recovery Project

Clean Development Mechanism (CDM) Registration for the Gianyar Waste Recovery Project Yayasan Pemilahan Sampah Temesi September 17, 2009 Clean Development Mechanism (CDM) Registration for the Gianyar Waste Recovery Project Content: 1. The Clean Development Mechanisms (CDM) Page 2 1.1 CDM

More information

III.P. Recovery and utilization of waste gas in refinery facilities

III.P. Recovery and utilization of waste gas in refinery facilities TYPE III - OTHER PROJECT ACTIVITIES Project participants shall take into account the general guidance to the methodologies, information on additionality, abbreviations and general guidance on leakage provided

More information

Improving Septic Tank Performance by Enhancing Anaerobic Digestion NOWRA Onsite Wastewater Mega-Conference

Improving Septic Tank Performance by Enhancing Anaerobic Digestion NOWRA Onsite Wastewater Mega-Conference Improving Septic Tank Performance by Enhancing Anaerobic Digestion NOWRA Onsite Wastewater Mega-Conference Christopher Jowett October 23, 2017 Outline Anaerobic 101 Important factors influencing treatment

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS A. General description of the small scale project activity B. Application

More information

PROGRAMME OF ACTIVITIES DESIGN DOCUMENT FORM FOR SSC A/R (CDM-PoA-DD-SSC-AR) - Version 01. CDM Executive Board Page 1

PROGRAMME OF ACTIVITIES DESIGN DOCUMENT FORM FOR SSC A/R (CDM-PoA-DD-SSC-AR) - Version 01. CDM Executive Board Page 1 Page 1 CLEAN DEVELOPMENT MECHANISM PROGRAMME OF ACTIVITIES DESIGN DOCUMENT FORM FOR SMALL-SCALE AFFORESTATION AND REFORESTATION PROJECT ACTIVITIES (CDM-PoA-DD-SSC-AR) (Version 01) CONTENTS A. General description

More information

01 Name of Project Gorai Landfill closure and Gas Capture Project, Mumbai, India 02 Location of Project (Village/District/St ate)

01 Name of Project Gorai Landfill closure and Gas Capture Project, Mumbai, India 02 Location of Project (Village/District/St ate) 01 Name of Project Gorai Landfill closure and Gas Capture Project, Mumbai, India 02 Location of Project (Village/District/St ate) The project is located at the existing Gorai dumpsite in the western suburbs

More information

Selecting municipal wastewater treatment technologies for greenhouse gas emissions reduction: the case of Mexico for year 2030

Selecting municipal wastewater treatment technologies for greenhouse gas emissions reduction: the case of Mexico for year 2030 Selecting municipal wastewater treatment technologies for greenhouse gas emissions reduction: the case of Mexico for year 2030 Adalberto Noyola Instituto de Ingeniería, Universidad Nacional Autónoma de

More information

UASB TECHNOLOGY EXPECTATIONS AND REALITY

UASB TECHNOLOGY EXPECTATIONS AND REALITY UASB TECHNOLOGY EXPECTATIONS AND REALITY Dr. Vinod Tare 1 and Asit Nema 2 INTRODUCTION Upflow Anaerobic Sludge Blanket (UASB) technology was introduced in India in late eighties during the Ganga Action

More information

REALIZING RENEWABLE ENERGY POTENTIAL

REALIZING RENEWABLE ENERGY POTENTIAL REALIZING RENEWABLE ENERGY POTENTIAL BY Patrick Hirl, PE Renewable natural gas (RNG) is a universal fuel that enhances energy supply diversity; uses municipal, agricultural and commercial organic waste;

More information

CDM Validation Report

CDM Validation Report Swiss Association for Quality and M a n a g e m e n t S y s t e m s ( SQ S ) B e r n s t r a s s e 1 0 3 P. O. B o x 6 8 6 C H - 3 0 5 2 Z o l l i k o f e n T e l. + 4 1 3 1 9 1 0 3 5 3 5 F a x. + 4 1

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-SSC-PDD) Version 03 - in effect as of: 22 December 2006 CONTENTS A. General description of the small scale project activity B. Application

More information

Covered Anaerobic Ponds for Anaerobic Digestion and Biogas Capture: Piggeries

Covered Anaerobic Ponds for Anaerobic Digestion and Biogas Capture: Piggeries Covered Anaerobic Ponds for Anaerobic Digestion and Biogas Capture: Piggeries INTRODUCTION Anaerobic ponds have been traditionally used in New Zealand to treat piggery, dairy farm, meatworks and other

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 02 - in effect as of: 1 July 2004) CONTENTS

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 02 - in effect as of: 1 July 2004) CONTENTS CDM Executive Board page 1 CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 02 - in effect as of: 1 July 2004) CONTENTS A. General description of project activity B. Application

More information

Doña Juana Landfill Gas-to-Energy Project

Doña Juana Landfill Gas-to-Energy Project page 1 PROJECT DESIGN DOCUMENT Doña Juana Landfill Gas-to-Energy Project CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT Version 0 - February 2008 page 2 CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN

More information

JOINT IMPLEMENTATION PROJECT DESIGN DOCUMENT FORM - Version 01

JOINT IMPLEMENTATION PROJECT DESIGN DOCUMENT FORM - Version 01 Joint Implementation Supervisory Committee page 1 JOINT IMPLEMENTATION PROJECT DESIGN DOCUMENT FORM Version 01 in effect as of 15 June 2006 CONTENTS A. General the project B. Baseline C. Duration of the

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS page 1 CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS A. General description of project activity B. Application of a baseline and

More information

ABSTRACT METHOD LIST OF ABREVIATION RSPO

ABSTRACT METHOD LIST OF ABREVIATION RSPO CONTENTS ABSTRACT...3 METHOD...3 LIST OF ABREVIATION...3 2016 KEY FIGURES - SIAT GROUP...4 RESULTS SIAT...5 RESULTS GOPDC...9 RESULTS - PRESCO...12 RESULTS - SNL...15 MONITORING AND MITIGATION...18 USE

More information

VIRIDOR WASTE MANAGEMENT ARDLEY EFW PLANT EP APPLICATION - NON TECHNICAL SUMMARY

VIRIDOR WASTE MANAGEMENT ARDLEY EFW PLANT EP APPLICATION - NON TECHNICAL SUMMARY VIRIDOR WASTE MANAGEMENT ARDLEY EFW PLANT EP APPLICATION - NON TECHNICAL SUMMARY S1014-0340-0008MPW NTS Rev1.doc Print Date 19 February 2009 ISSUE NUMBER 1 DATE 19/02/09 AUTHOR CHECKED MPW SMO Title Page

More information

CDM Training Program Final Examination

CDM Training Program Final Examination CDM Training Program Final Examination 15 July 2011 Prepared by: JICA Expert Team Name: Organization: TOTAL SCORE: /100 Renewable energy /20 Waste handling /20 Energy Efficiency & Fuel switch /20 Forest

More information

Development of JCM Projects toward a Sustainable Low-Carbon Society in Indonesia Tjandra Setiadi, Ph.D. Centre for Environmental Studies, ITB,

Development of JCM Projects toward a Sustainable Low-Carbon Society in Indonesia Tjandra Setiadi, Ph.D. Centre for Environmental Studies, ITB, Development of JCM Projects toward a Sustainable Low-Carbon Society in Indonesia Tjandra Setiadi, Ph.D. Centre for Environmental Studies, ITB, Bandung, Indonesia Da Nang, Vietnam, 14-15 January 2016 Content

More information

CDM Feasibility Study on Ventilation Air Methane Power Generation Project at Dafosi Coal Mine in China

CDM Feasibility Study on Ventilation Air Methane Power Generation Project at Dafosi Coal Mine in China Title of Feasibility Study: CDM Feasibility Study on Ventilation Air Methane Power Generation Project at Dafosi Coal Mine in China Main Implementing Entity: PEAR Carbon Offset Initiative, Ltd. 1. Implementation

More information

III.X Energy Efficiency and HFC-134a Recovery in Residential Refrigerators

III.X Energy Efficiency and HFC-134a Recovery in Residential Refrigerators III.X Energy Efficiency and HFC-134a Recovery in Residential Refrigerators Applicability Demand side activities (end users but not for manufacture) Replacement of functional units (with efficient units

More information

SUSTAINABLE BIOPLASTICS INDUSTRY FROM RENEWABLE RESOURCES IN MALAYSIA

SUSTAINABLE BIOPLASTICS INDUSTRY FROM RENEWABLE RESOURCES IN MALAYSIA SUSTAINABLE BIOPLASTICS INDUSTRY FROM RENEWABLE RESOURCES IN MALAYSIA Professor Mohd Ali Hassan University Putra Malaysia Professor Yoshihito Shirai Kyushu Institute of Technology Presentation Outline

More information

FELDA PALM INDUSTRIES SDN. BHD

FELDA PALM INDUSTRIES SDN. BHD FELDA PALM INDUSTRIES SDN. BHD Development of Biogas Projects in Felda Global Ventures Reflections & Way Forward and Opportunities for Value Creation in Palm Oil Based Biogas Biogas Asia Pacific Forum

More information

Draft Small-scale Methodology AMS-III.AV: Low greenhouse gas emitting safe drinking water production systems

Draft Small-scale Methodology AMS-III.AV: Low greenhouse gas emitting safe drinking water production systems CLEAN DEVELOPMENT MECHANISM CDM-SSCWG40-A04 Draft Small-scale Methodology AMS-III.AV: Low greenhouse gas emitting safe drinking water production Sectoral scope(s): 03 COVER NOTE 1. Procedural background

More information

Energy Optimized Resource Recovery Project Presented By: Curtis Czarnecki, P.E.

Energy Optimized Resource Recovery Project Presented By: Curtis Czarnecki, P.E. Kenosha Wastewater Treatment Plant Energy Optimized Resource Recovery Project Presented By: Curtis Czarnecki, P.E. Kenosha Water Utility March 22, 2016 WWTP Service Area Overview Population: 110,000 Service

More information

Biomass and Energy A Perspective from Municipal Solid Waste (MSW)

Biomass and Energy A Perspective from Municipal Solid Waste (MSW) Biomass and Energy A Perspective from Municipal Solid Waste (MSW) Agamuthu P. and Fauziah S.H. Institute of Biological Sciences, Faculty of Science, University of Malaya, 50603 Kuala Lumpur, Malaysia.

More information

JCM Project Design Document Form

JCM Project Design Document Form JCM Project Design Document Form A. Project description A.1. Title of the JCM project Energy saving by optimum operation at an oil refinery A.2. General description of project and applied technologies

More information

Climate Financing CDM and NAMA in Rwanda

Climate Financing CDM and NAMA in Rwanda Climate Financing CDM and NAMA in Rwanda Kigali, 7th October 2014 Faustin MUNYAZIKWIYE Director of Climate Change and International Obligations Dpt / REMA Outlines Introduction to Climate Change Mapping

More information

ANAEROBIC TREATMENT OF PAPER MILL WASTEWATER

ANAEROBIC TREATMENT OF PAPER MILL WASTEWATER ANAEROBIC TREATMENT OF PAPER MILL WASTEWATER M. Eeckhaut 1, J.P. Ombregt 1, B. Vanderhaegen 2, M. Bambridge 3, A. Ginnis 4 Abstract In this paper the performance of an anaerobic wastewater treatment plant

More information

UNFCCC/CCNUCC DRAFT STANDARD FOR THE DEVELOPMENT OF ELIGIBILITY CRITERIA FOR THE INCLUSION OF A PROJECT ACTIVITY AS A CPA UNDER THE POA. I.

UNFCCC/CCNUCC DRAFT STANDARD FOR THE DEVELOPMENT OF ELIGIBILITY CRITERIA FOR THE INCLUSION OF A PROJECT ACTIVITY AS A CPA UNDER THE POA. I. Page 1 STANDARD FOR THE DEVELOPMENT OF ELIGIBILITY CRITERIA FOR THE INCLUSION OF A PROJECT ACTIVITY AS A CPA UNDER THE POA I. Background 1. In decision 3/CMP.1 paragraph 4, Parties requested the clean

More information

Methodological tool Tool to calculate the emission factor for an electricity system

Methodological tool Tool to calculate the emission factor for an electricity system CLEAN DEVELOPMENT MECHANISM TOOL07 Methodological tool Tool to calculate the emission factor for an electricity system TABLE OF CONTENTS Page 1. INTRODUCTION... 4 2. SCOPE, APPLICABILITY, AND ENTRY INTO

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS page 1 CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS A. General description of project activity B. Application of a baseline and

More information

Project Design Document

Project Design Document Project Design Document CDM PROJECT ACTIVITY LANDFILL GAS RECOVERY IN INDONESIA JUNE 2007 FINAL VERSION EXECUTIVE SUMMARY The objective of the Project is to collect and utilize, where economically possible,

More information

CLEAN DEVELOPMENT MECHANISM SMALL-SCALE PROGRAM ACTIVITY DESIGN DOCUMENT FORM (CDM-SSC-CPA-DD) Version 01 CONTENTS

CLEAN DEVELOPMENT MECHANISM SMALL-SCALE PROGRAM ACTIVITY DESIGN DOCUMENT FORM (CDM-SSC-CPA-DD) Version 01 CONTENTS CDM Executive Board page 1 CLEAN DEVELOPMENT MECHANISM SMALL-SCALE PROGRAM ACTIVITY DESIGN DOCUMENT FORM (CDM-SSC-CPA-DD) Version 01 CONTENTS A. General description of CDM programme activity (CPA) B. Eligibility

More information

Energy Saving by High-efficiency Centrifugal Chiller

Energy Saving by High-efficiency Centrifugal Chiller MOEJ/GEC JCM Project Planning Study (PS) 2013 Final Report Energy Saving by High-efficiency Centrifugal Chiller (implemented by Nippon Koei Co., Ltd. and Ebara Refrigeration Equipment and Systems Co. Ltd.)

More information

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 02 - in effect as of: 1 July 2004) CONTENTS

CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 02 - in effect as of: 1 July 2004) CONTENTS CDM Executive Board page 1 CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 02 - in effect as of: 1 July 2004) CONTENTS A. General description of project activity B. Application

More information

Dealing with Unexpected Wastewater Treatment Plant Disruptions. February 16, 2017

Dealing with Unexpected Wastewater Treatment Plant Disruptions. February 16, 2017 Dealing with Unexpected Wastewater Treatment Plant Disruptions February 16, 2017 Location Map WPCP History Original WPCP constructed on this site in 1928 consisting of primary treatment and chlorination;

More information

VALIDATION REPORT. Quezon City Controlled Disposal Facility Biogas Emission Reduction Project in Philippines REPORT NO REVISION NO.

VALIDATION REPORT. Quezon City Controlled Disposal Facility Biogas Emission Reduction Project in Philippines REPORT NO REVISION NO. Quezon City Controlled Disposal Facility Biogas Emission Reduction Project in Philippines REPORT NO. 2007-1142 REVISION NO. 02 Date of first issue: Project No.: 2007-07-09 44410005-08 Approved by: Organisational

More information

The Impact of Elevated Leachate Levels on LFG Generation and Recovery at MSW Landfills in Asia

The Impact of Elevated Leachate Levels on LFG Generation and Recovery at MSW Landfills in Asia The Impact of Elevated Leachate Levels on LFG Generation and Recovery at MSW Landfills in Asia Methane to Markets Partnership Expo New Delhi, India 2-55 March 2010 Bryce Lloyd Organic Waste Technologies

More information