1 Community Participation and Review Committee Regulatory changes and what that means for regulation of the Orica Botany Transformation Projects 8 November 2011 Greg Sullivan NSW Environment Protection Authority 1
2 Proposed regulatory changes We are developing a modern, independent EPA making sure that public health and safety is a focus while we protect the broader environment! Photo source: Fairfax Media 2
3 Focus for EPA regulation of Orica: 1. Continue investigation into mercury vapour incident on 27 September Ensure mercury contamination is safely addressed 3. Finalise remediation of the Car Park Waste 4. Ensure ongoing clean-up of the groundwater 5. Input to the ongoing management of the HCB waste 3
4 Discussion and community views 4
5 OEH Update on HCB Matters Community Participation and Review Committee 8 November 2011 James Goodwin Sydney Industry 1
6 Overview of Presentation Carpark Waste Remediation Project - Timeline - Commercial Operations - Annual Return - Site inspections - Next steps 2
7 Timeline since last meeting 18/8/11 Initial Pre-Test results received Proof of Performance Tests 23 to 27 August 16/9/11 Licence variation issued to include additional requirements Mid-September 13 October Develop licence conditions for commercial operations 20/10/11 Licence variation to reflect updated Liner Management Plan 8 Nov August September October November 9 August 23/8/11 OEH provides formal comments on Proof of Performance Test Plan 13/9/11 Draft Proof of Performance Test results received for all three tests 30/9/11 Final report on baseline Mercury Control Trials received 14/10/11 Licence variation issued to permit commercial operations 3
8 Commercial Operations Stringent conditions imposed, including - maximum feed rate of 27 tonnes per hour - minimum exit gas temperature from Primary Treatment Unit of 445 degrees Celsius - mercury limit of 0.2 milligrams per cubic metre - monitoring requirements for contaminated feed soil - reporting of excursions above plant parameters 4
9 Annual Return Three non-compliances reported 1. Not measuring flow at Thermal Oxidiser 2. Two Carbon Monoxide data points outside range 3. Residence time on start-up less than 2 seconds - Licence amended for (1) - (2) and (3) instrumentation issues 5
10 Site inspections One announced (21 September) and one unannounced (7 November) Building on previous six inspections 6
11 Next Steps - Pro-active and re-active regulation of commercial operations - Licence variation if planning approval granted for treatment of other materials 7
12 Questions? 8
13 CPWE PROJECT UPDATE CPRC Meeting 8 November 2011 Joshua Van Der Heiden
14 CPWE PROJECT UPDATE CPoP program is now complete and OEH has approved full scale treatment operations In addition to the Continuous Emissions Monitoring System there have been eight full suite stack tests undertaken on the DTD plant and all results are well within OEH limits Excavated, transported and stockpiled 33,500m3 from the Excavation Soil Building to the Feed Soil Building and treated 52,200 tonnes in the DTD By the end of this week we will have completed excavation of approximately 2/3rds of the projected volume Excavation of Stage 1 will be complete this week with excavation of Stage 2 (remaining 1/3 of the CPWE) commencing in mid December Thermal Treatment likely to be complete in March 2012 Project demobilisation likely to be complete in May 2012
15 CPWE PROJECT UPDATE Environmental Monitoring Update Dust Continuous logging, attended monitoring and dust deposition gauges Over half a million measurements taken in the three month period 5 exceedances against the EPA goals detected: Three at Hensley Athletics Field not attributable to the CPWE project due to heavy fog, lawn mowing on Hensley and smog Two on the CPWE project (dust deposition gauges) due to inappropriate siting of the equipment (inside the active treated soil stockpile area and far from the site boundary) Noise No noise impact detected from CPWE activities
16 EXCAVATION SOIL BUILDING LOOKING WEST
17 EXCAVATION SOIL BUILDING LOOKING EAST
18 CPWE Remediation Project Independent Expert Panel Update Peter O Dea 8 November 2011
19 CPWE Remediation Project Independent Expert Panel Update IEP Members: Dr John McCracken engineering Dr Chris Clunies-Ross air emissions Dr Peter Nadebaum environment Prof Brian Priestly health Current Task: Review and comment on Commissioning and Proof of Performance (CPoP) Trials 8 November 2011
20 IEP Involvement throughout CPoP Process IEP, OEH, Orica and Thiess Workshop - November 2010 Reports on Clean Soil Shakedown, Contaminated Soil Shakedown & Mercury Control Trials IEP, OEH, Orica and Thiess Workshop - July 2011 IEP members provided reports to the CPRC in July endorsed 400 o C as minimum soil treatment temperature - agreed no additional mercury control trials were necessary - outstanding query about mass balance & request for fugitive emission data Since the August CPRC meeting, Orica has provided the following to the IEP: - Mercury Ambient Air Monitoring data (checking fugitive emissions) - Pre-Test and PoP Trial reports - Final Mercury Controls Report (finalising mass balance) - OEH Licence Amendments 8 November 2011
21 IEP Feedback since August Meeting Dr Clunies-Ross (who also conducted sampling) - no comments or concerns Prof Priestly - no comments or concerns Dr Nadebaum - queried a high mercury reading during the ambient monitoring Orica explained to his satisfaction that the sample was from inside the process equipment, not in the open air. No further comments Dr McCracken said the achieved DTD destruction efficiency represents an acceptable and best practice environmental outcome and had 5 requests for information or comment 8 November 2011
22 Dr McCracken Requests 1. Treated soil data for contaminants other than HCB, HCBD and Mercury provided summary (details had been given to OEH and Site Auditor) 2. Commentary on effect of ambient wind conditions on fugitive emissions. advised that DTD has instruments to prevent positive pressure which might cause fugitive emissions 3. Evidence that DTD pressure instruments had been calibrated provided commissioning records 4. Additional ambient air monitoring for mercury, not on a windy day tests will be repeated 1. Comments on why scrubber water discharges are not completely consumed in the pugmill and on what happens to mercury and other contaminants normally all goes to pugmill, occasionally some goes to Water Treatment Plant, where mercury (30 ppb) and other contaminant limits have always been met 8 November 2011
23 Update on Other Soils to DTD The prospect of processing other contaminated soils from the BIP, Pacific National (now called Asciano) and Southlands in the DTD was first discussed with the CPRC at the November 2006 meeting. Status: - The DoPI has approved processing of 1,000 t (600 m 3 ) of soil and concrete from the HCB stores - Orica has sought approval to process 160 m 3 of soil from the Asciano embankment - Orica has sought approval to process 1,200 m 3 of soil from Southlands Material has to be processed to the requirements of the Environment Protection Licence: Maximum 27 tonnes/hour Maximum 4,000 mg/kg HCB + HCBD in feed to DTD Compliance with Clean Air Regulations Specified Sample Frequency, etc. 8 November 2011
Villawood Soil Remediation Project Community Meeting 28 May 2014
Villawood Soil Remediation Project Community Meeting 28 May 2014 Item Presenter Time 1 Welcome, apologies, introduction Chair, Gwenda Lister (Orica) 6.30 pm 2 Update on actions since last meeting Gwenda
More informationMcCRACKEN CONSULTING SERVICES 20 Christina Place KAREELA NSW 2232 AUSTRALIA
SUJELI PTY LTD trading as: ACN 002 901 368 ABN 48 002 901 368 ENVIRONMENT SAFETY & RISK CONSULTANTS McCRACKEN CONSULTING SERVICES 20 Christina Place KAREELA NSW 2232 AUSTRALIA Telephone: +61-(0)-2-9528-2870
More informationBotany Groundwater Cleanup Project Progress Update
Botany Groundwater Cleanup Project Progress Update B Dewhurst & L Archer (Orica) 18/03/2014 Progress Since Last CLC Meeting Groundwater containment was achieved at all three containment lines (SCA, PCA
More informationSection 75J of the Environmental Planning and Assessment Act 1979
Project Approval Section 75J of the Environmental Planning and Assessment Act 1979 I, the Minister for Planning, approve the project referred to in Schedule 1, subject to the conditions in Schedule 2.
More informationKurnell Refinery Conversion Project
Kurnell Refinery Conversion Project Contamination Management Plan CALTEX REFINERIES (NSW) PTY LTD January 2014 Page 1 1 INTRODUCTION Caltex propose to convert the petroleum refinery in Kurnell (the Site
More informationSoil Treatment Facility Design and Operation for Bioremediation of Hydrocarbon Contaminated Soil. Version 1.0
PROTOCOL 15 FOR CONTAMINATED SITES Soil Treatment Facility Design and Operation for Bioremediation of Hydrocarbon Contaminated Soil Version 1.0 Prepared pursuant to Section 64 of the Environmental Management
More informationSydney Port Botany Terminal 3 Project Out of Hours Works Protocol
1/11 Terms and Definitions The following terms, abbreviations and definitions are used in this plan: Terms Explanation SPBT3 Sydney Port Botany Terminal 3 CEMP EM EPA ERAP OEH PAH OOHWP EIS MCoA Distribution
More informationReviewing Contaminated Site Assessment Reports. What the NEPM means for you
Reviewing Contaminated Site Assessment Reports What the NEPM means for you Legislative Framework EPAA (1979) EPAA Regulation (2000) State Environmental Planning Policy 55 POEO Act(1997) POEO Regulations
More informationQuestions and Answers on Orica s HCB Waste Destruction Program
Questions and Answers on Orica s HCB Waste Destruction Program Background 1 What is HCB? HCB (hexachlorobenzene) is a crystalline solid waste by-product. Internationally, it is known and classified as
More informationMayo Renewable Power Killala Construction Works Monthly Environmental Report 010 April 2016
Mayo Renewable Power Killala Construction Works Monthly Environmental Report 010 April 2016 Executive Summary John Sisk & Son (Holdings) Ltd. commissioned NVM Ltd. to monitor and report on Noise, Dust
More informationEnvironmental Guideline for Saskatchewan Asphalt Plants
Environmental Guideline for Saskatchewan Asphalt Plants Ministry of Environment July 2015 saskatchewan.ca/environment For enquiries or reporting, please contact: Government of Saskatchewan Environmental
More informationAir Quality Impact Assessment for a Groundwater Treatment Plant Proposed by Orica Australia Ltd., Botany. URS Australia Pty. Ltd.
Air Quality Impact Assessment for a Groundwater Treatment Plant Proposed by Orica Australia Ltd., Botany URS Australia Pty. Ltd. Job No 1857 5 Nov 2004 Air Quality Impact Assessment for Orica s Proposed
More informationKurnell Refinery Conversion Project
Kurnell Refinery Conversion Project Air Quality Management Plan CALTEX REFINERIES (NSW) PTY LTD January 2014 Page 1 1 INTRODUCTION Caltex propose to convert the petroleum refinery in Kurnell (the Site
More informationEnvironment Protection Licence
Licence Details Number: Anniversary Date: 20593 20-December Licensee HI-QUALITY QUARRY (NSW) PTY LTD PO BOX 42 KEMPS CREEK NSW 2171 Premises HI QUALITY KEMPS CREEK CENTRAL 1503-1519 ELIZABETH DRIVE KEMPS
More informationItem Discussion Action By
MEETING NOTES (APPROVED 13/03/2014) Thursday, 12 December 2013 at 6:30pm Lucas Heights RRP New Illawarra Rd, Lucas Heights Chair Gareth Jones Note Taker Gareth Jones ATTENDEES SITA Australia (AK) Sydney
More information10.0 AIR QUALITY AND CLIMATIC FACTORS
.0 AIR QUALITY AND CLIMATIC FACTORS.1 ASSESSMENT METHODOLOGY.1.1 General Section 39 (2) (b) (ii) of the Transport (Railway Infrastructure) Act 2001, requires that proposed developments are examined in
More informationANNUAL ENVIRONMENTAL MANAGEMENT REPORT
ORICA KOORAGANG ISLAND ANNUAL ENVIRONMENTAL MANAGEMENT REPORT DECEMBER 2013 Revision Date Description Author Approver 0 14/12/2013 2013 Annual Environmental Report A Taylor S Woodroffe Annual Environmental
More informationBusiness Case NWP National Water Training Package Review and Development. Water Industry Reference Committee
Business Case NWP National Water Training Package Review and Development Water Industry Reference Committee Date: 22 nd December 2016 NWP National Water Training Package Review Business Case 1 Executive
More informationFACILITY PROFILE. New Brunswick Power Corporation for the Belledune Thermal Generating Station
FACILITY PROFILE New Brunswick Power Corporation for the Belledune Thermal Generating Station Prepared by: Industrial Processes Section, Impact Management Branch Department of Environment and Local Government
More informationContent Copy Of Original
Content Copy Of Original Ministry of the Environment Ministère de l Environnement ENVIRONMENTAL COMPLIANCE APPROVAL NUMBER 4495-9FUQDY Issue Date: February 5, 2014 Holcim (Canada) Inc. 2300 Steeles Ave
More informationLoy Yang B Environment Improvement Plan
Loy Yang B Environment Improvement Plan 2017 Table of Contents 1 Endorsement 1 2 Environment Policy 2 3 Operating Arrangements 3 4 Site Management and Business Systems 4 5 Environmental Impacts and Risks
More informationOutcomes Summary: Consultation on noise barrier options near Glamis Street, Armitree Street, and Rosebank Avenue, Kingsgrove January 2017
Outcomes Summary: Consultation on noise barrier options near Glamis Street, Armitree Street, and Rosebank Avenue, Kingsgrove January 2017 Overview In response to public submissions made during the Environmental
More informationRegister of Contaminated Land Consent Conditions
Regional Contaminated Land Capacity Building Program Register of Contaminated Land Consent Conditions AUGUST 2017 Regional Contaminated Land Capacity Building Program This publication was produced by the
More informationRemediation of 2 Christina Road Villawood, NSW Environmental Assessment February 2011
Remediation of 2 Christina Road Villawood, NSW Environmental Assessment February 2011 Prepared for: Orica Australia Pty Ltd Report by: Thiess Services Pty Ltd ABN: 69 010 725 247 88 Phillip Street Parramatta
More informationManitoba lot Conservation
Manitoba lot Conservation Climate Change and Environmental Protection Division Environmental Assessment and Licensing Branch 123 Main Street, Suite 160, Winnipeg, Manitoba R3C 1A5 T 204 945-7100 F 204
More informationMonthly Environmental Monitoring Report
\ Monthly Environmental Monitoring Report Name of Operation Name of Licensee Environmental Protection Licence Reporting Period start date Reporting Period end date Version Author Approver Moolarben Coal
More informationKurnell Refinery Conversion Project
Kurnell Refinery Conversion Project Waste Management Plan CALTEX REFINERIES (NSW) PTY LTD January 2014 Page 1 1 INTRODUCTION Caltex propose to convert the petroleum refinery in Kurnell (the Site ) to a
More informationCURRENT STATE OF CONSTRUCTION WASTE IN THE CITY OF CAPE TOWN. A VAN VUUREN / 16 September 2014
CURRENT STATE OF CONSTRUCTION WASTE IN THE CITY OF CAPE TOWN A VAN VUUREN / 16 September 2014 THE CAPE TOWN WE LOVE OTHER IMAGES OF OUR CITY ILLEGAL DUMPING IS A REALITY During 2013: There were more than
More informationJames Cook University. Internal Audit Protocol
James Cook University Internal Audit Protocol Table of Contents A. Introduction 2 B. Management Consultation during the Annual Internal Audit Planning Process 2 C. Support Provided to QAO/External Auditor
More informationThermal Desorption of Hydrocarbon Contaminated Soil How to Successfully Use this Technology. By Cal Faminow, CTech
Thermal Desorption of Hydrocarbon Contaminated Soil How to Successfully Use this Technology By Cal Faminow, CTech Presentation Outline 1. Introduction 2. Site Summary 3. Assessment 4. Remedial Options
More informationAGL UPSTREAM INVESTMENTS PTY LTD ROSALIND PARK GAS PLANT Monthly Continuous Air Monitoring Report
AGL UPSTREAM INVESTMENTS PTY LTD ROSALIND PARK GAS PLANT Monthly Continuous Air Monitoring Report Reporting Period: February 2018 AGL Upstream Investments Pty Ltd ABN 58 115 063 744 Locked Bag 1837, St
More informationYou have applied in accordance with Section 9 of the Environmental Protection Act for approval of:
Ministry of the Environment Ministère de l Environnement CERTIFICATE OF APPROVAL AIR NUMBER 7970-7QNRDJ Issue Date: April 2, 2009 William Day Construction Limited 2500 Elm Street, P.O. Box 700 Copper Cliff,
More informationClogrennane Lime Ltd. Toonagh Lime Works AER Licence # P
Clogrennane Lime Ltd Toonagh Lime Works AER 2010 Licence # P0 771-01 Section 1 Overview. 3 1.0 Introduction 1.1 Description of Activities 1.2 Responsibility for Environmental Management 1.3 Environmental
More informationMonthly Environmental Data May 2016
Monthly Environmental Data May 2016 Contents 1 AIR QUALITY... 2 1.1 HIGH VOLUME AIR SAMPLERS... 2 1.2 TAPERED ELEMENT OSCILLATING MICROBALANCE SAMPLING (TEOM)... 7 1.3 DUST DEPOSITION SAMPLING... 11 2
More information2.0 Description of Existing Mine Operations
2.0 2.1 Mine History Austar Coal Mine is an amalgamation of several older mines and operates within a number of mining leases under 12 separate development consents issued by Cessnock City Council between
More informationEPA Inquiry: Submission on behalf of Paper Australia Pty Ltd
Our reference AGPAPE16499-9101755/01 567 Collins Street, Melbourne VIC 3000 GPO Box 9925 Melbourne VIC Tel +61 396723000 Fax +61 396723010 www.corrs.com.au CORRS CHAMBERS WESTGARTH lawyers Sydney Melbourne
More informationWILPINJONG COAL PTY LTD. Environment Protection Licence (EPL) 12425
WILPINJONG COAL PTY LTD Environment Protection Licence (EPL) 12425 Link to Environment Protection Licence EPL12425 LICENCE MONITORING DATA MONTHLY SUMMARY REPORT for 1 June 2017 to 30 June 2017 Air Monitoring
More informationWILPINJONG COAL PTY LTD. Environment Protection Licence (EPL) 12425
WILPINJONG COAL PTY LTD Environment Protection Licence (EPL) 12425 Link to Environment Protection Licence EPL12425 LICENCE MONITORING DATA MONTHLY SUMMARY REPORT for 1 August 2017 to 31 August 2017 Air
More informationDraft Protocol for managing asbestos during resource recovery of construction and demolition waste.
Draft Protocol for managing asbestos during resource recovery of construction and demolition waste www.epa.nsw.gov.au 2014 State of NSW and Environment Protection Authority The State of NSW and Environment
More informationMONTHLY ENVIRONMENTAL MONITORING REPORT PORT BOTANY REDEVELOPMENT PATRICK STEVEDORES
MONTHLY ENVIRONMENTAL MONITORING REPORT PORT BOTANY REDEVELOPMENT PATRICK STEVEDORES DECEMBER 2013 www.mcconnelldowell.com MCCONNELL DOWELL CORPORATION PAGE 1 OF 13 McConnell Dowell Constructors (Aust.)
More informationA T Adams Consulting. West Belconnen Project Environment protection matters Summary report. report prepared for: Riverview Group
A T Adams Consulting West Belconnen Project Environment protection matters Summary report report prepared for: Riverview Group 9 April 2015 TABLE OF CONTENTS 1.0 -------- Introduction 2 1.1. ------- This
More informationNEW YORK STATE DEPARTMENT OF ENVIRONMENTAL CONSERVATION REGION 1 50 CIRCLE ROAD STONY BROOK, NY 11790
NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL CONSERVATION REGION 1 50 CIRCLE ROAD STONY BROOK, NY 11790 Summary of Responses to Comments on Draft Material Removal Work Plan For Roberto Clemente Town Park,
More informationASH MANAGEMENT PLAN. U.S. Environmental Protection Agency Region 4, Atlanta, GA. Mr. Joe Alfano, Remedial Project Manager
ASH MANAGEMENT PLAN U.S. Environmental Protection Agency Region 4, Atlanta, GA Mr. Joe Alfano, Remedial Project Manager 404-562-8933 City of Jacksonville Environmental and Compliance Department Site Investigation
More informationContent Copy Of Original
Content Copy Of Original ModulR TS Inc. 21 Scott Avenue Paris, Ontario N3L 3R1 Site Location: 21 Scott Avenue Brant County Ministry of the Environment and Climate Change Ministère de l Environnement et
More informationWhat does it mean for you?
The Medium Combustion Plant Directive (MCPD) What does it mean for you? INTRODUCTION TO THE MCPD IMPROVING AIR QUALITY In 2015 the UK government announced plans to introduce the Medium Combustion Plant
More informationFor personal use only
13 APRIL 2018 AUTHIER PROJECT PRESENTATION TO KEY STAKEHOLDERS & PERMITTING UPDATE Sayona Mining Limited (ASX: SYA) ("Sayona" or the "Company") is pleased to announce that the Company held information
More informationAmbient Air Quality Monitoring Baseline Report, Kirby Misperton A Wellsite, KM8 Production Well
Ambient Air Quality Monitoring Baseline Report, Kirby Misperton A Wellsite, KM8 Production Well. Prepared for: Third Energy UK Gas Ltd. Document Control Page Client Third Energy UK Gas Ltd. Document Title
More informationFAQ: Onshore Gas Exploratory Development at Pontrhydyfen
FAQ: Onshore Gas Exploratory Development at Pontrhydyfen Frequently Asked Questions: proposed onshore gas exploratory borehole development in Pontrhydyfen The information in this document is intended to
More informationAppendix 1. In this appendix underlining indicates new text and striking through indicates deleted text. The DFSA Rulebook. General Module (GEN)
Appendix 1 In this appendix underlining indicates new text and striking through indicates deleted text. The DFSA Rulebook General Module (GEN) 1 INTRODUCTION Application 1.1.1 This module (GEN) applies
More informationEnvironment Protection Licence
Licence Details Number: Anniversary Date: 767 01-January Licensee METROPOLITAN COLLIERIES PTY. LTD. PO BOX 402 HELENSBURGH NSW 2508 Premises METROPOLITAN COLLIERY PARKES STREET HELENSBURGH NSW 2508 Scheduled
More informationRULES OF TENNESSEE DEPARTMENT OF ENVIRONMENT AND CONSERVATION DIVISION OF AIR POLLUTION CONTROL CHAPTER VISIBLE EMISSION REGULATIONS
RULES OF TENNESSEE DEPARTMENT OF ENVIRONMENT AND CONSERVATION DIVISION OF AIR POLLUTION CONTROL CHAPTER 1200-03-05 VISIBLE EMISSION REGULATIONS TABLE OF CONTENTS 1200-03-05-.01 General Standards 1200-03-05-.08
More informationSECTION 7: CLIMATE AND AIR QUALITY
SECTION 7: CLIMATE AND AIR QUALITY 7.1 INTRODUCTION This study considers the potential impacts of emissions to atmosphere on air quality including, airborne pollutants and dust emissions during operation
More informationEnvironment Protection Licence
Licence Details Number: Anniversary Date: 20850 24-November Licensee MACH ENERGY AUSTRALIA PTY LTD LEVEL 2, 179 GREY STREET SOUTH BANK QLD 4101 Premises MOUNT PLEASANT OPERATION 1100 WYBONG ROAD MUSWELLBROOK
More informationCentennial Ivanhoe No2 Colliery. Environmental Monitoring Data
Centennial Ivanhoe No2 Colliery Environmental Monitoring Data October 2012 TABLE OF CONTENTS 1. INTRODUCTION... 1 2. RAINFALL... 2 3. AIR QUALITY MONITORING... 2 3.1 Depositional Dust... 2 4. SURFACE WATER
More informationSPECIAL CONDITIONS GENERAL PERMIT NUMBER WMGR089
SPECIAL CONDITIONS GENERAL PERMIT NUMBER WMGR089 1. The approval herein granted is limited to beneficial use of lime kiln dust (LKD) as a soil amendment, for stabilization/solidification of soils and sludges,
More informationEnvironmental Management Programme (EMP)
Appendix D Environmental Management Programme (EMP) Please note that although Construction and Operational Phase measures are included in this EMP they are relevant to the issued Waste Management Licence
More informationENVIRONMENTAL SCREENING REPORT
ENVIRONMENTAL SCREENING REPORT Pursuant to the Canadian Environmental Assessment Act (CEA Act) SCREENING SUMMARY TransCanada PipeLines Limited (TransCanada) is proposing to conduct a contaminant sampling
More informationI-ROX. Chemical Reduction-Oxidation (REDOX) Technology
I-ROX Chemical Reduction-Oxidation (REDOX) Technology 1.0 TECHNOLOGY OVERVIEW The I-ROX remediation products and application technology represent a new innovative tool for in-situ and ex-situ remediation
More informationTo reduce the consumption of energy and the emission of greenhouse gases associated with Transit Systems NSW s activities.
Transit Systems NSW Environmental Management Plan GOAL 1: REDUCE THE GREENHOUSE IMPACT OF ENERGY USE To reduce the consumption of energy and the emission of greenhouse gases associated with Transit Systems
More informationCONSTRUCTION AND DEMOLITION DEBRIS DISPOSAL SITE GUIDELINES
Nova Scotia Environment and Labour CONSTRUCTION AND DEMOLITION DEBRIS DISPOSAL SITE GUIDELINES Approval Date: October 24, 1997 Effective Date: October 24, 1997 Approved By: Peter Underwood Version Control:
More informationNovember Contaminated Land Assessment in NSW
November 2015 Contaminated Land Assessment in NSW Contaminated Site Assessment and Management Process Prompts for assessing site contamination: Acquisition or divestment of property Site rezoning or DA
More informationJanuary 2008 No. 700
January 2008 No. 700 INDEX FOR SPECIFICATIONS FOR GRANULAR BASE COURSE Page 700. 1 SCOPE...1 1.1 Pre-Construction Meeting...1 1.2 Mobilization of Equipment...1 700. 3 MATERIALS 3.1 Granular Base Course
More informationCONSTRUCTION SPECIFICATION FOR BORROW
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.MUNI 212 NOVEMBER 2013 CONSTRUCTION SPECIFICATION FOR BORROW TABLE OF CONTENTS 212.01 SCOPE 212.02 REFERENCES 212.03 DEFINITIONS 212.04 DESIGN AND
More informationPOLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PUBLIC)
Environmental Management System Integra Coal Operations Pty Ltd POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PUBLIC) 2012 Doc No: Doc Owner: EMP_2014-2 Environmental Advisor Integra Coal Operations Approval:
More informationEXHIBIT LIST No Exhibit Name Page 1 P3 Control of Environment Impacts Presentation.pdf (P3) 2-34
Reference No: HOC/10001 Petitioner: Phase 2a Teach-ins Published to Collaboration Area: Friday 23-Mar-2018 EXHIBIT LIST Page 1 of 34 No Exhibit Name Page 1 P3 Control of Environment Impacts Presentation.pdf
More informationUpdate of Saskatchewan Upstream Oil & Gas Industry Regulations
Update of Saskatchewan Upstream Oil & Gas Industry Regulations Ministry of the Economy SESSA March 19, 2012 Directive S-10 DirectiveS S 10 10provides enforceable regulatory requirements for reducing flaring
More informationEnvironment Protection Licence
Licence Details Number: Anniversary Date: 12425 08-February Licensee WILPINJONG COAL PTY LTD LOCKED BAG 2005 MUDGEE NSW 2850 Premises WILPINJONG COAL MINE 1434 ULAN-WOLLAR ROAD WILPINJONG NSW 2850 Scheduled
More informationConstruction Environment Management Plan
Construction Environment Management Plan Guidance Material July 2013 ABSTRACT This CEMP guidance material has been prepared by MAC to assist the identification and management of environmental risks associated
More information4.05. Groundwater Program. Chapter 4 Section. Background. Follow-up to VFM Section 3.05, 2004 Annual Report. Ministry of the Environment
Chapter 4 Section 4.05 Ministry of the Environment Groundwater Program Follow-up to VFM Section 3.05, 2004 Annual Report Chapter 4 Follow-up Section 4.05 Background Groundwater is defined as water located
More informationExcerpt of Thermal Power Guidelines for New Plants
Excerpt of Thermal Power Guidelines for New Plants The following is an excerpt of the Thermal Power guidelines for New Plants, a complete version of which is found in the Pollution Prevention and Abatement
More informationPacific Highway Upgrade Frederickton to Eungai ENVIRONMENTAL MONITORING DATA EPL 20318
Pacific Highway Upgrade Frederickton to Eungai ENVIRONMENTAL MONITORING DATA EPL 20318 May 2014 1 INTRODUCTION The publishing of data refers to the compliance of the Frederickton to Eungai Project (the
More informationTHE ACOUSTIC GROUP PTY LTD CONSULTING ACOUSTICAL & VIBRATION ENGINEERS
THE ACOUSTIC GROUP PTY LTD CONSULTING ACOUSTICAL & VIBRATION ENGINEERS ACOUSTIC ASSESSMENT PROPOSED GROUNDWATER CLEANUP PROJECT 34.4372.R3:NSC Prepared for: Orica Australia 16-20 Beauchamp Road MATRAVILLE
More informationI. Site Name and Location
HALEY & ALDRICH, INC. 6500 Rockside Road Suite 200 Cleveland, OH 44131 216.739.0555 MEMORANDUM File No. 41938-009 SUBJECT: CCR Fugitive Dust Control Plan - Initial Jeffrey Energy Center St. Marys, Kansas
More informationAPPENDIX 11. Bushfire Threat Assessment
APPENDIX 11 Bushfire Threat Assessment Orica Mining Services Lot 2 DP 809377 George Booth Drive, Richmond Vale, NSW, 2327 Proposed Ammonium Nitrate Emulsion Production Facility Bushfire Threat Assessment
More informationSCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS
SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS Version 2 June 2006 1. Purpose These Guidelines are supplementary
More informationI. Site Name and Location
HALEY & ALDRICH, INC. 6500 Rockside Road Suite 200 Cleveland, OH 44131 216.739.0555 MEMORANDUM 17 April 2017 File No. 129778 005 SUBJECT: CCR Fugitive Dust Control Plan Revision #1 Jeffrey Energy Center
More informationASSET CREATION DEVELOPER PROCESS INSTRUCTIONS TO DESIGNERS - MAJOR WORKS
ASSET CREATION DEVELOPER PROCESS INSTRUCTIONS TO DESIGNERS - MAJOR WORKS INSTRUCTIONS TO DESIGNERS CONTENTS 1. INTRODUCTION 3 2. ROLE OF THE WATER SERVICING COORDINATOR 3 3. ROLE OF THE DESIGNER 3 4. DESIGN
More informationPORT OF PORT HEDLAND - BULK PRODUCT MANAGEMENT PROCEDURE
TABLE OF CONTENTS 1. PURPOSE... 2 2. SCOPE... 2 3. RESPONSIBILITIES... 2 4. SPECIFICATION OF BULK MINERAL PRODUCTS... 3 4.1 PROVISION OF ONGOING INFORMATION...4 4.2 SAMPLING...5 4.3 PRODUCT DEM AND MOISTURE
More informationWASTE ACCEPTANCE CRITERIA AND DEVELOPMENT OF SOIL TRIGGER VALUES FOR EPA-LICENSED SOIL RECOVERY FACILITIES
WASTE ACCEPTANCE CRITERIA AND DEVELOPMENT OF SOIL TRIGGER VALUES FOR EPA-LICENSED SOIL RECOVERY FACILITIES 1. Introduction This guidance document applies to soil recovery facilities which exceed the operational
More informationAudit Committee Charter
Audit Committee Charter 1. Background The Audit Committee is a Committee of the Board of Directors ( Board ) of Syrah Resources Limited (ACN 125 242 284) ( Syrah or the Company ) that was established under
More informationENVIRONMENTAL GUIDELINES FOR PREPARATION OF AN ENVIRONMENT MANAGEMENT PLAN. Environment Protection Authority, ACT May 2009
ENVIRONMENTAL GUIDELINES FOR PREPARATION OF AN ENVIRONMENT MANAGEMENT PLAN Environment Protection Authority, ACT May 2009 ISBN-13: 978-0-642-60494-1 ISBN-10: 0-642-60494-0 Australian Capital Territory,
More informationCONSTRUCTION SPECIFICATION FOR BORROW
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 212 NOVEMBER 2008 CONSTRUCTION SPECIFICATION FOR BORROW TABLE OF CONTENTS 212.01 SCOPE 212.02 REFERENCES 212.03 DEFINITIONS 212.04 DESIGN AND SUBMISSION
More informationReport on the Community Consultation Committee Process
Report on the Community Consultation Committee Process Bodangora Wind Farm Wellington NSW Report prepared by Committee Chair Grahame Collier Report on the Community Consultation Committee Process Bodangora
More informationAsbestos in Grounds, Asbestos Management Plan, Sydney Secondary College Balmain Campus, Balmain, NSW 2041
Asbestos in Grounds, Asbestos Management Plan, Sydney Secondary College Balmain Campus, Balmain, NSW 2041 March 2014 NSW Public Works Parsons Brinckerhoff Australia Pty Limited ABN 80 078 004 798 Level
More informationAppendix B. Commitments made in the Approved Terms of Reference
Appendix B Commitments made in the Approved Terms of Reference Approved Terms of Reference Requirements and How They Were in the 1. The study area considered for the new landfill footprint at the West
More informationConstruction Management Plan (CMP) 227 Princess Highway, Dandenong
Construction Management Plan (CMP) 227 Princess Highway, Dandenong - Construction Management Plan (CMP) June 2017 S2966 CMP.D2 PREPARED BY: Sustainable Development Consultants 2nd Floor, 555 Riversdale
More informationWhat is the Port Granby Project?
What is the Port Granby Project? The Port Granby Project is a federal initiative for the cleanup and safe long-term management of historic low-level radioactive waste situated in the southeast corner of
More informationProject & Environmental Review. Guidelines Air Emission Management Plan. July 2015
Project & Environmental Review Guidelines Air Emission Management Plan July 2015 TABLE OF CONTENTS 1. Introduction... 3 2. Overview... 3 3. Principles/Objectives... 3 3.1 Management Plan Components...
More informationGENERAL SPECIFICATION FOR THE MANAGEMENT OF EXCESS MATERIALS
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 180 NOVEMBER 2005 GENERAL SPECIFICATION FOR THE MANAGEMENT OF EXCESS MATERIALS TABLE OF CONTENTS 180.01 SCOPE 180.02 REFERENCES 180.03 DEFINITIONS
More informationCode of Practice for Concrete Producing Plants
Code of Practice for Concrete Producing Plants Effective September 30, 1996 Made under the Environmental Protection and Enhancement Act, RSA 2000, ce-12 Published by Alberta Queen s Printer Queen s Printer
More informationContent Copy Of Original
Content Copy Of Original Ministry of the Environment Ministère de l Environnement AMENDED ENVIRONMENTAL COMPLIANCE APPROVAL NUMBER 0091-9JEN2B Issue Date: July 7, 2014 Johnson & Johnson Inc. 890 Woodlawn
More informationSTRATFORD MINING COMPLEX Air Quality and Greenhouse Gas Management Plan
STRATFORD MINING COMPLEX Air Quality and Greenhouse Gas Management Plan STRATFORD MINING COMPLEX AIR QUALITY AND GREENHOUSE GAS MANAGEMENT PLAN Revision Status Register Section/Page/ Annexure Revision
More informationCountry Bridge Solutions
Country Bridge Solutions David K. Andrews, Senior Project Development Manager, Freight and Regional Program Office Roads and Maritime Services, NSW, Australia Adj Prof Wije Ariyaratne, Principal Engineer
More informationThe Hon Pru Goward MP Minister for Planning SCHEDULE I. sst Roads and Maritime Services. Land in the suburbs of Hornsby, North Wahroonga,
I nfrastructu re approval Section 1152;8 of the Environmental Planning & Assessment Act 1979 I grant approval to the State significant infrastructure application referred to in schedule 1, subject to the
More informationREPORT SURAT GAS PROJECT SUPPLEMENTARY AIR QUALITY ASSESSMENT. Coffey Environments
REPORT SURAT GAS PROJECT SUPPLEMENTARY AIR QUALITY ASSESSMENT Coffey Environments Job No: 3568D 7 June 2013 PROJECT TITLE: Surat Gas Project Supplementary Air Quality Assessment JOB NUMBER: 3568D PREPARED
More informationGUIDANCE NOTE ON THE BEST PRACTICABLE MEANS FOR
GUIDANCE NOTE ON THE BEST PRACTICABLE MEANS FOR INCINERATORS (MUNICIPAL WASTE INCINERATION) BPM 12/1 (08) Environmental Protection Department Air Policy Group February 2008 1. INTRODUCTION 1.1 This Note
More informationPOLLUTION INCIDENT RESPONSE MANAGEMENT PLAN. Bargo/Buxton Wastewater Scheme
POLLUTION INCIDENT RESPONSE FOR Bargo/Buxton Wastewater Scheme Rev Date Revision Prepared Approved A 16 December 2013 Draft L O Hare B 25 January 2013 Draft L O Hare C 10 April 2013 Draft A.White D 24
More informationFor personal use only
BALAMA PROJECT UPDATE AS AT MID MARCH 2017 BALAMA GRAPHITE PROJECT (100%) OPERATIONS UPDATE Commissioning remains on schedule for Q2 2017 Capital budget remains unchanged at US$193 million (plus US$7 million
More informationIncident Reporting Requirements
Incident Reporting Requirements Directive PNG014 December 2016 Version 2.0 Governing Legislation: Acts: The Oil and Gas Conservation Act The Pipelines Act, 1998 Regulations: The Oil and Gas Conservation
More information